ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& PAPER 263 2.6. Modeling and Dynamic Performance Aspects of Integrating HVDC into the AC Power System Analysis of the AC Polish Power System Impact on the HVDC SwePol Link Operation M. Przygrodzki, P. Rzepka, M. Szablicki, W. Lubicki Poland Lund%Symposium%27/28%May,%2015% HVDC CONNECTION SWEDEN-POLAND The HVDC SwePol Link connection between Poland and Sweden was establish in 2000 year. It consists of the following elements: • AC 400 kV overhead line with length equal to 0,2 km, between the Karlshamn substation and Starno converters, • HVDC 450 kV cable line which comprises: – 2-kilometer on-shore cable section on the Swedish side, – 241-kilometer section of the submarine cable, – 12-kilometer on-shore cable section on the Polish side • MVDC 24 kV return cable line which analogously consists of: – 2-kilometer on-shore cable section (in fact two cables connected in parallel) on the Swedish side, – 241-kilometer off-shore cable section (two cables in parallel), – 12-kilometer on-shore cable (single cable) on the Polish side, • Converter station and the AC 400/110 kV Wierzbięcino Slupsk station Lund%Symposium%27/28%May,%2015% 2% ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& COMMUTATION FAILURE • • • The thyristor is turn on with the firing angle (α) and turns off when the external voltage enforce zero with its anode current. The process of this switching is known as a commutation. The duration of the commutation is determined by the commutation/overlap angle µ. The angle is proportional to the transmitted current. The effectiveness of reverse polarity must be maintained for a certain period of time referred to as a voltage-time area measured by the duration of the extinction angle γ. Insufficient voltage-time area is resulting in commutation failure. In this case no blocking thyristor causes that conduct thyristors in the same branch of the bridge - the effect of short circuit. commutation kąt komutacji angle obszar czasowo voltage-time napięciowyarea α µ γ zapłon firing iS iR Lund%Symposium%27/28%May,%2015% prądy zaworu thyristor current 3% THE STATISTIC OF COMMUTATION FAILURE Commutation failure have occurred 204 times during over than 13 years of HVDC Link operation (till end of may 2013) Lund%Symposium%27/28%May,%2015% 4% ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& THE STATISTIC OF COMMUTATION FAILURE The monthly number of identified commutation failures estimated from the beginning of HVDC Link operation to the end of year 2013 57 60 50 40 30 21 23 21 19 20 12 10 7 19 9 8 7 1 0 Lund%Symposium%27/28%May,%2015% 5% THE STATISTIC OF COMMUTATION FAILURE The yearly correlation coefficient was equal to 0.57 which confirms the strong dependence between variables (import duration and number of CF). The monthly number of identified commutation failures accompanying imports of energy to Poland. 60% 70,0%% 50% 60,0%% 50,0%% 40% 40,0%% 30% 30,0%% 20% 20,0%% 10% 10,0%% 0% 0,0%% Number%of%CF% Percentage%of%energy%import% Lund%Symposium%27/28%May,%2015% 6% The average number of failures in the observed period of time is 0,39 CF/100 h. This means that a single failure falls on 256 importing hours which is an equivalent of 10.7 days of energy import. The year 2010 was identified as the worst year in terms of failures frequency per 100 hours of import. Frequency index is 1.3 and it is a result of 31 commutation failures related with 2 392 importing hours. • 1,40 1,20 1,00 0,80 0,60 0,40 0,20 0,00 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Lund%Symposium%27/28%May,%2015% 7% THE AC NETWORK ENVIRONMENT 0 6 P303 E 19 B P4 1 P47 7 P4 N4 01 N40 A 6 P4 6003 P30 P3 D 04 3A 9 Kiełpino N0 6B Olsztyn Mątki Swarożyn Zajączkowo C Kobylnica Szczecinek A1 Dunowo T2 T1 P632 Jeżyce 218 XSD Morzyczyn P633 FW Darłowo A1 A2 Żydowo Piła Krzewina Lund%Symposium%27/28%May,%2015% Jasiniec Grudziądz 8% 03 Bystra P303F 03 P3 Gdańsk Błonia 11 Dębnica Kaszubska T2 T1 4 P4 Gałęźnia Mała B T2 N002 XYZ P010 8 P304 A2 17 P30 4C 9 P00 Białogard 2 P6 P316 Bytów Obłęże Żydowo Dygowo P3 Miastko P017 Karścino P310 P320 P304E 3 P6 P6 3 P313 Tychowo Słupsk Szczecińska P315 P314 6601 P601 Tymień Sianów Koszalin Południe P608 P629 Ostrowite T1 Żarnowiec 2 Koszalin Przemysłowa P611 B 05 Koszalin Strefa Koszalin Północ Słupsk Hubalczyków 07 6001 5A Koszalin Morska P617 P3 Słupsk Poznańska P304A 0 P6 07 Sławno A1 A3 Gdańsk 1 P303 P616 P6 P6 Dunowo Ustronie Morskie 09 Słupsk Grunwaldzka P301 P612 P6 2A 2B Kanin P409 P311 Słupsk 08 P0 Rumia Darżyno P302 0 P3 01 N0 Chylonia 44 P4 1 4A Reda P4 3 2 P0 Darłowo A1 Słupsk P3 1 Boże Pole 0 N4 K 2 P31 IN -L 4B 07 P307B DC 2 P0 Pieńkowo P0 Lębork Krzywoustego Ustka Władysławowo P Wejherowo 463 7 SZWECJA 10 1 P4 Lębork Nowy Świat Gnieżdzewo Łebcz Gnieżdzewo P4 Żarnowiec P319 N004 7 Opalino Wojciechowo Wicko 9 P419A P46 P022B C P022 41 ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& • 5 P30 ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& THE STATISTIC OF COMMUTATION FAILURE ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& THE CASE STUDY It is has become important to discover mechanism of causes and sequence of events implying commutation failures. Transmission and distribution grid structure changes, HVDC Link parameters changes as well as connection of new wind farms should be included when defining a set of analyzed events. Accordingly, in process of selection events the following criteria were included: • phenomenon occurrence on the Polish side of the HVDC SwePol Link (registered by the recorders), • events should occur during inverter operation mode of the HVDC SwePol Link (power import from Sweden), • excluded events are these one resulting from functional disruption of HVDC Link internal structure (switch failures, control system failures, etc.), • commutation failures and associated possible outages should results from random events (within grid) and should not be the result of control system failures (eg. transmission direction change, LLD – Last Line Disconnect), • in the area of interest are commutation failures associated with transmission network disturbances (automatic reclosing cycle operation, low level of short circuit power, voltage reduction). Lund%Symposium%27/28%May,%2015% 9% THE EVENT 26 JULY 2012, HOUR 13:52:28 The HVDC Swe-Pol Link worked in the import mode with the load of 600 MW. The reason for the existing problems of commutation was close to ground fault located at the L1 phase 400 kV line Dunowo - Morzyczyn. As a result, it occurred on both sides off the line in the automatic reclosing cycle. Switchgear breakdown in TR1 bus of 400 kV Żarnowiec substation 11:16 12:29 12:34 13:30 60 MW HVDC SwePol Link import decrease Commutation failure in HVDC SwePol Link 13:52 14:21 20:55 Dunowo-Morzyczyn 400 kV line disconnection in open-close-open cycle of automatic reclosing Disturbance in CHP Bydgoszcz Lund%Symposium%27/28%May,%2015% 10% Voltages and currents measured on the DC-LINK Slupsk substation 4 400 L1 L2 L3 300 100 1 i![kA] 2 0 0 -1 -100 -2 -200 -3 -300 -400 L1 L2 L3 3 200 -4 13:52:28.598 +0,5 s +1 s 13:52:28.598 +0,5 s +1 s t![s] t![s] Lund%Symposium%27/28%May,%2015% 11% Uh/U1hL3$[%] Uh/U1hL2$[%] Uh/U1hL1$[%] THE EVENT 26 JULY 2012, HOUR 13:52:28 2.5 0.5 13:00 2.5 Ih/I1hL1$[%] 13:20 13:40 14:00 14:20 13:20 13:40 14:00 14:20 13:20 13:40 14:00 14:20 13:20 13:40 14:00 14:20 13:20 13:40 14:00 14:20 13:40 14:00 14:20 1.5 The content of voltage (U) and current (I) harmonic (10-minutes) registered at the DC-LINK Slupsk substation 0.5 13:00 2.5 1.5 0.5 3.5 2.5 1.5 0.5 13:00 4.5 Ih/I1hL2$[%] zdarzenia 1.5 13:00 4.5 3.5 2.5 1.5 0.5 13:00 4.5 Ih/I1hL3![%] u![kV] ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& THE EVENT 26 JULY 2012, HOUR 13:52:28 3.5 2.5 1.5 0.5 13:00 13:20 t![h] 3h 5h 7h 9h 11h 13h Lund%Symposium%27/28%May,%2015% 12% THE EVENT 26 JULY 2012, HOUR 13:52:28 DL DN 0 U![kV] -100 -200 -300 -400 -500 13:52:28.598 +0,5 s +1 s t![s] 8 DL DNC I![kA] 6 4 2 13:52:28.598 +0,5 s +1 s t![s] 160 α γ µ 120 80 40 0 13:52:28.598 +0,5 s t![s] ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& Time duration curves of selected HVDC Link parameters during commutation failure: • voltage (UDL) and current (IDL) of the main cable, • voltage (UDN) and current (IDNC) of return cable, • thyristor firing angle (α), extinction angle (γ) and commutation/overlap angle (µ) 0 α ,!γ,!µ![o] ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& 100 +1 s Lund%Symposium%27/28%May,%2015% 13% SUMMARY • • The Slupsk station was built as a line-commutated converter. Thus, the direct cause of commutation failures (including elimination of incorrect control system behavior) is an voltage distortion at the output side of the inventor, resulting in a reduction of voltage-time area of commutation process. The primary cause of voltage distortion and thus commutation problems are switching operations – in particular – short circuit faults and automatic reclosing operations. This thesis is confirmed by the results of the retrospective analysis. HVDC SwePol Link malfunction was caused mainly by asymmetrical transient (eliminated in automatic reclosing cycle) or solid short-circuit faults located in transmission or 110 kV network. For cases of single-phase voltage reduction in Slupsk substation it occured problems at HVDC connection work. It was a multiple commutation failures. The occurrence of multiple commutation failures much more negative impact on the stability of the whole network system than the individual commutation failure. Lund%Symposium%27/28%May,%2015% 14% ACROSS&BORDERS&*&HVDC&SYSTEMS&AND&MARKET&INTEGRATION& SUMMARY • • On the basis of the results of tests carried out for the analysis of single and multiparameter network system with a HVDC Swe-Pol Link it has been found that the occurrence of commutation failures dynamic switching accompanied by large changes in the electrical parameters in both the AC part of the Swe-Pol Link or in DC part. The results determine that the stability of working conditions through during switching operations, faults and reclosing cycles is determined by, among others, short-circuit power level, the value of voltage and phase angle in the inverter station, the level of power transmission and the control of the rectifier and inverter link. A special aspect for the stability of HVDC SwePol Link is voltage on the substation (including its amplitude and angle). The converter station location on the Polish side does not guarantee a stable network parameters during - even distant – disturbances in the transmission and 110 kV network. In particular this applies to the northwestern part of Polish Power System. Therefore there is a need for research to indicate a network investments (including the optimal development process) which could reduce the likelihood of short circuit faults. Lund%Symposium%27/28%May,%2015% 15%