GRID – the cost of time Wind Energy Engineering and Development & Operations Firm Founded 1995 Over 200 staff Operate in 9 countries Advised on over 100 projects (>16 GW of projects) Developed 39 projects (>1,100 MW) Constructed 57 projects (>900 MW) Operate 14 projects (>200 MW) Focus on Engineering Project Management & Operations Built first project in Ireland in 1998 – Crockahenny, Co. Donegal (5 MW) Opened office in Dublin in 2002 Since 1998 have project managed 25% of total installed capacity 30 Projects completed >250 MW of installed capacity operating Offices in Malahide, Co. Dublin and Listowel Co. Kerry 25 professional staff in Ireland Electrical, Civil, Mechanical Engineers Stages of Grid Connection Programme Drivers Consequences of Delay - Case Study Notification of Delay Possible Improvements Connection Application Connection Methodology Connection Offer Connection Design Consenting Procurement Construction Commissioning and Energisation Connection Application Connection Methodology Connection Offer Timeframes governed by: Group processing Sub-group negotiations Offer modifications Connection Design Consenting Timeframes governed by: Non-contestable asset design Contestable shared asset design Underground / overhead? Landowner consent Planning consent Road opening licence procurement Procurement Timeframes governed by: Non-contestable Capital approval process (ESB Networks) Procurement process (e.g. OJEC) Long lead items (transformers, substation control systems, HV equipment) Contestable Functional specification Contractor selection Long lead items Construction Timeframes governed by: Non-contestable Mobilisation of ESB contractors Availability of ESB resources Contestable Mobilisation of contestable works contractor Contestable works contractor project management Detailed design approval by Eirgird Commissioning Timeframes governed by: Project communication on ESB technical requirements Availability of ESB commissioners Possibility of switch-out (time of year) Quality of contestable works contractors works ~30 MW wind farm Financial close August 2005 WTGs delivery dates February 2006 Original energisation date agreed at financial close March 2006 Delay in ordering of long lead time equipment Actual energisation date July 2006 Additional construction Insurance Project management Costs Temporary generation Costs Acceleration payment to part supplier Legal fees due to default Maintenance Costs for WTGs Interest on payments to WTG supplier Additional Interest during construction TOTAL €20k €40k €32k €50k €80k €100k €250k €325k €847k Other factors Lost revenue of ~€1.6 million Total losses ~€2.5 million Material damage to the WTGs due to moisture (electronic components) Potential deemed take-over of the WTGs A lot of stress for the developer…. Even more stress of the project manager! The earlier you know about a delay the less it will cost Offer Design / Consenting Financial Close Shipment of wind turbines Commissioning and Energisation Things on the way: Contestability at distribution More commercial connection contracts for DSO/TSO Tighter wayleaving process for landowners Other suggestions Better availability of commissioners Better access to designers Clearer reporting on progress Public awareness on the need for infrastructure Public awareness on overhead line Vs cable More responsible local politicians