APS Construction Update

Summer 2015

Construction Update Summary

APS spends up to $300 million dollars per year on;

(a) New construction

(b) Renovations

(c) Repairs & Deferred Maintenance

(d) Instructional Technology hardware and infrastructure

Since 2009, the APS Capital Master Plan has added:

Three (3) new high schools

One (1) new middle school

Five (5) new elementary schools

One (1) new alternative school

Six (6) complete rebuilds of old schools

Seven (7) of the new schools were built on the west side of the city where

Albuquerque has experienced the most growth.

The new George I. Sanchez PreK-8 school under constructed will open in

August 2015. This new school shall alleviate continued student growth within the southwest quadrant of the District.

2

Construction Update

The New CMP (2017/22) will continue to focus is on:

1. Energy Efficiency -New Construction Design continues to focus on energy efficiency a) The current District heating and cooling utility bill is $50K a day

2. Mitigation of Portables – replacement of portables with efficient , state of the art construction

3. Early Childhood Development Centers – to provide comprehensive early childhood education to students in the Albuquerque Public Schools

4. Special Education Intensive Support Hubs – to consolidate programs into one state of the art facility, with expert teams that will better and more efficiently serve the highest need Special Education students.

5. Renewal - A focus to renew the older schools

6. Innovative Schools – a move towards technology as a vehicle to provide cutting edge, 21 st Century instruction

3

Projects under Construction/Bidding in 2015

1.

2.

3.

4.

Aztec Complex-Special Education and Autism Center

Preliminary Scope: District Intensive Support, Diagnostic, and Evaluation Center for Special

Needs

.

Total Project Budget – $ 7,600,000 Phase I

Ernie Pyle MS – under construction

Preliminary Scope: Classroom Addition; Renovation of the 300 wing into an Art Complex; Misc

HVAC work throughout the school

Total Project Budget: $10,208,226

Marie Hughes ES

Preliminary Scope: New Construction of 2 story Classroom Block, Demolish existing old classroom blocks, Portable removal, loop road/bus Drop-Off/Parking construction and New

Field/Playground construction

Total Project Budget: $21,912,667

Mountain View ES

Preliminary Scope: Total re-build of the school except for the existing kindergarten

Total Project Budget: $21,173,547

4

5.

6.

7.

8.

9.

Projects under Construction/Bidding in 2015

Reginald Chavez ES – under construction

Preliminary Scope: Kinder Addition and Replacement of Classroom Buildings

Total Project Budget – $7,415,261

Rio Grande High School – under construction

Preliminary Scope: Restructuring of the campus and the construction of 9 th and 10 th grade academies.

Total Project Budget: $25,255,234

Valley High School

Preliminary Scope: Raze Building “S” and Construct new classroom in its place.

Total Project Budget: $7,194,644

West Mesa High School

Preliminary Scope: Replace Classroom Wing “M”

Total Project Budget: $ 18,782,829

Atrisco ES – under construction

Preliminary Scope: Re-roofing and Classroom Replacement

Total Project Budget: $9,854,543

5

Projects under Construction/Bidding in 2015

10. Jackson Middle School

Preliminary Scope: New Kitchen/Cafeteria/Drama Building & Old Wing Replacement and

Renovation

Total Project Budget: $12,335,939

11. Jefferson MS

Preliminary Scope: Music Classroom Addition and Renovation

Total Project Budget: $2,218,695

6

Projects in Design to be considered for in Construction 2016

1.

2.

3.

4.

Albuquerque HS Commons/Café/Music Classrooms

Preliminary Scope: Expand Kitchen, Cafeteria, and Commons

Total Project Budget: $12,003,216

Family School West Side

Preliminary Scope: Construction of new school to accommodate K-8 students

Total Project Budget: $10,371,667

Special Education Intensive Support Hub (ISP) # 1

Preliminary Scope: ISP facility Hub prototype to handle up to 30 special needs students ages

Pre-K to 22 years

Total Project Budget – $8,027,082

Special Education Intensive Support Hub (ISP) # 2:

Preliminary Scope: ISP facility Hub prototype to handle up to 30 special needs students ages

PreK- to 22 years

Total Project Budget – $8,027,082

7

Projects in Design to be considered for in Construction 2016

5.

6.

7.

8.

9.

Desert Willow-Phase 2

Preliminary Scope: Expansion of K-8 school including a 7 classroom block, lecture hall, multipurpose space and ancillary support spaces

Total Project Budget – $3,533,720

Navajo ES Kindergarten Addition

Preliminary scope: New Kindergarten building and ancillary facilities

Total Project Budget – $7,038,000

Barcelona ES Kitchen/Café/Admin

Preliminary Scope: Cafeteria Expansion, Kitchen and Administration Modifications

Total Project Budget – $3,733,735

Madison MS

Preliminary Scope: Gymnasium/locker room Renovation

Total Project Budget: $2,814,676

Early Childhood Facility Prototype

Preliminary Scope: To design and construct an early childhood facility that will combine pre-k education and day care services. To be replicated on up to ten sites over the next 4 years. This is the first one.

Total Project Budget – $13,423,482

8

10.

11.

12.

13.

Projects in Design to be considered for in Construction 2016

Montgomery Complex Professional Development/Meeting Facility

Preliminary Scope: District training facility for teachers, staff with appropriate IT labs and meeting spaces for up to 500.

Total Project Budget – $ 12,091,178

Highland HS new Classroom Block & PE/Gym Addition

Preliminary Scope: Highland HS new Classroom Block, Gym Remodel and Renovations

Total Project Budget – $19,486,012

La Cueva HS new ISP Classroom Block & PE/Gym Addition

Preliminary Scope: Addition of ISP classroom block, ancillary spaces and PE/Gym Addition

Total Project Budget – $10,930,658

Manzano HS new PE/Gym Addition

Preliminary Scope: New Athletics complex and demolition of existing gym facilities

Total Project Budget – $21,911,976

9

George Sanchez PreK-8th Grade

Address: 4050 118th Street SW 87121

Square Footage: 245,437

Project Description: New K-8 school serving

1,350 students.

Budget: $48.6 million

Project Status: 68% construction complete

Date of Completion: July 2015

Architect: Jon Anderson Architects

General Contractor: Bradbury Stamm

10

Adobe

Acres

Elementary School

Address: 1724 Camino Del Valle SW

Year School First Opened: 1964

Project Scope: One renovated and one new building (with a total of 21,963 sq. ft.), that include:

New Building with 7 Kindergarten class rooms, 1 Art/Music multipurpose room/space square feet

New Artificial Turf Playground and

Fenced Kindergarten Tot-lot

Renovated/expanded Kitchen/Cafeteria with bathrooms and Storage

Date of Completion: Feb 2014

Budget: $5 million

Architect: RMKM

Contractor: T.A Cole & Sons

11

Chaparral Elementary School

Address: 6325 Milne RD NW

Project Scope: New Classroom wing, Kitchen

Cafeteria, & Site/Field and traffic improvements

• 21 Classroom wing addition

7 Kindergarten classrooms

1 kindergarten level D Classroom

1 Special education classroom

5 Intensive support Classrooms

1 Occupational / Physical therapy

5 regular education classrooms

1 fine arts classroom.

• Site/traffic improvements

New Play field

New Playground

New Parent & Bus pick up drop off plus roadway construction

• Kitchen Cafeteria Addition/renovation

• existing cafeteria and kitchen was enlarged additional storage was added

Budget: $15.9 Million

Project Status: Construction 95% complete; Kitchen

Cafeteria, field, and infrastructure currently in use

Estimated Date of Completion: December 2014

Architect: Cherry / See/ Reames

General Contractor: Shumate Contractors Inc.

12

Sandia HS Science Classroom Block/Library

Address: 7801 Candelaria NE, Albuq, NM 87110

Year School First Opened: 1958

Project: Two new buildings (with a total of 75,350 sq. ft.), that include:

A. New Science and Math Academy (57,592 square feet, three stories)

B. New Library - 17,758 square feet, two storiesthe new Library Building includes computer labs, small group study rooms, and a graphic arts production studio.

C. New Softball Field-provides a new natural sod field with greatly improved dugouts, practice cages, concessions, and storage facilities.

Project Status: Completed May 2014

Budget: $ 21,106,354

Architect: Mahlman Studio

General Contractor: HB Construction

13

Dolores Gonzales ES Classroom Block

Address: 900 Atlantic St SW

Year School First Opened: 1975

Project Scope:

 New 21 Classroom Block to include and Art/Music and 4 Kindergarten Classrooms

 Cafeteria expansion

 Restroom remodel

 New Playground

Project Status: Under construction

Est. Date of Completion: Phase I – December 2014 complete

Phase II – June 2015

Total Budget: $7.9 million

Architect: Westwork Architects

General Contractor: Shumate Constructors Inc.

14

Food Services Central Kitchen and Storage

Address: 800 Louisiana Blvd. NE

Square Footage : 100,000

Project : Renovation of a 100,000 square foot facility into a food processing facility/commercial kitchen/warehouse for APS

Food services

Project Status: Complete

Est. Date of Completion : December 2014

Budget : $14.2 million

Architect : Studio SW Architects

Contractor : Gerald A. Martin, LTD

15

eCademy/New Futures Cafeteria/Commons

Address: 5300 Cutler Ave NE

Year School First Opened: 1915 (old

AHS Site)

Project Scope:

 Cafeteria/Commons eCademy &

New-futures

 Site development

 Infrastructure

Date of Completion: March 2014

Budget: $3.8 million

Architect: Gregory Hicks

General Contractor: Anchor Built

16

Wilson Middle School

Address: 1138 Cardenas Dr SE

Year School First Opened: 1953

Project Scope: Entire Renovations to the 1953 2-story building including the cafeteria, administration, classrooms, kitchen, library, and other incidental spaces

Project Status: Under construction

Est. Date of Completion: March 2015

Budget: $10.6 million

Architect: Huitt-Zollars

General Contractor: HB Construction

17

Montezuma Turf

Address: 1616 Richmond NE

Year School First Opened

:

1953

Project Scope: Montezuma Elementary School

Community Turf Field consists of approximately

24,000 square feet of an artificial turf field bordered by a concrete walking path, low water use landscaping and trees. The following components were installed: Artificial turf field;

Concrete walking path; Low water use landscaping and trees; Pre-engineered steel shade structure;

Concrete plaza Infrastructure including electrical, parking and landscape; Picnic table; Seating; Trash receptacles and Fencing

Project Status: Complete

Date of Completion: August 2014

Budget: $ 360,000

General Contractor

:

Westwind Landscape

18

Inez Elementary School

Address : 1700 Pennsylvania Street NE

Albuquerque, NM 87110

Year School First Opened: 1952

Project Scope:

Kitchen/Cafeteria Renovation

New Fine Arts Classroom

Site Work – Parking/Drop-off improvements, landscaping, playground upgrades, erosion control

Date of Completion: July 2013

Project Status: 2 nd year warranty inspection

Budget: $4.15 million

Architect: NCA Architects

General Contractor: T.A. Cole & Sons General

Contractors, Inc.

19

RFK Charter High School

Address: 4300 Blake Rd SW

Year School First Opened: 2001

Project Scope:

 Multi Purpose Facility

Multi media center

Physical educational

Gymnasium/Community space combo

 Full Auto Body Shop

Project Status: Under construction

Date of Completion: May2015

Budget: $6.4 million

Architect: DWL Architects

General Contractor: Anchor Built

20

McKinley Middle School

Address: 4500 Comanche NE

Year School First Opened: 1956

Project Scope:

Classroom block Addition

Drainage/Infrastructure

Project Status: Construction nearly complete

Date of Completion: Aug 2015

Budget: $ 6,196,182

Architect: NCA

Contractor: Shumate Constructors

21

Eldorado High School

Address: 11300 Montgomery Blvd NE

Year School First Opened: 1970-71

Project Scope:

Renovation of:

Math

Humanities

Fine Arts

Project Status: Under Construction

Est. Date of Completion: July 2015

Total Budget: $4.4 million

Architect: Van H. Gilbert Architects

General Contractor: ESA Construction Inc.

22

Del Norte High School

Address: 5323 Montgomery Blvd NE

Year school First Opened: 1964-65

Project Scope: a) Phase 4 Industrial Fine Arts Building - complete b) Phase 5 Cafeteria demolition and roof

Project Status: Cafeteria under Construction

Est. Date of Completion: (phase 5) September 2015

Budget: $11.5 million

Architect: Dekker/ Perich/Sabatini

General Contractor: T.A Cole & Sons (phase 4)

ESA Construction (phase 5)

23

Monte Vista Elementary School

Address: 3211 Monte Vista

Blvd. NE

Albuquerque, NM 87106

Year School First Opened: 1931

Project Scope:

New Roof

Restroom Refurbishment

Date of Completion: January

2014

Project Status: 2 nd Year Roofing

Warranty

Budget: $1.45 million

Architect: Westwork

General Contractor: Janstar

Builders, Inc.

24

Sandia Base Elementary School

Address: 21001 Wyoming SE

KAFB East

Year School First Opened: 1950

Square Footage: 51,552

Project Scope: Cafeteria/Kitchen

Addition & Remodel

Project Status: complete

Date of Completion: August 2014

Budget: $1,659,750

Architect: DWL Architects

General Contractor: Weil

Construction, Inc

25

Montessori of the Rio Grande Charter School

Address: 1650 Gabaldon Drive NW

Project Scope: New Classroom Block

Date of Completion: July 2013

Project Status: 2 nd Year Roofing

Warranty

Budget: $3.58 million

Architect: G. Don Dudley

General Contractor: Famco, Inc.

26

Rio Grande High School

Address: 2300 Arenal Rd SW

Year School First Opened: 1959

Project: 9th and 10th grade academies new classroom block; new permanent bus lane; new courtyards and patio, addition of site lighting for security; completion of fire lane loop; new tennis courts; addition of artificial turn for football and baseball fields; landscaping and fencing upgrades

New Project SF: 92,165

Project Status: Under construction

Groundbreaking: Spring/Summer 2015

Est. Date of Completion: Summer 2016

Budget: $25 million

Architect: Van H. Gilbert Architects

General Contractor: HB Construction

27

Marie Hughes Elementary School

Address: 5701 Mojave NW

Year School First Opened: 1981

Project Scope: School replacement

Phase I: Demolition Play Areas and New

Construction of 2 story Classroom

Block

Phase 2: Demolish existing old classroom blocks, Portable removal, loop road/bus Drop-Off/Parking construction and New Field/Playground construction

Status: Under design

Ground breaking: Fall 2015

Est. Date of Completion: Spring 2017

Budget: $21.9 million

Architect: G. Don Dudley

General Contractor: TBD

28

Highland High School Rebuild

Address: 4700 Coal Avenue SE 87108

Year School First Opened: 1949

Project: Highland HS new Classroom Block,

Gym upgrade and PAC

Project Status: Under Design

Est. Groundbreaking: Phase I Summer 2016

Est. Date of Completion: Phase I

December 2017

Budget: $14.79 million

Architect: SMPC

General Contractor: TBD

29

Albuquerque High School Commons

Address: 800 Odelia Road NE 87102

Year School First Opened : 1916

Project: Commons/Cafeteria/Classroom

Renovation and Addition/ Music Classrooms

Project Status: Design Complete

Est. Groundbreaking: Summer 2016

Est. Date of Completion: Dec. 2017

Budget: $14,155,777

Architect: Jon Anderson

General Contractor: TBD

30

La Cueva HS ISP/GYM

Address: 7801 Wilshire NE 87122

Year School First Opened: 1986

Project Scope: The project consists of 3 distinct parts:

Part I : Addition of an ISP facility to serve special education programs

Part II : Addition of a weight room

Part III : Renovation of the existing weight room

Project Status: Design complete

Est. Date of Groundbreaking: Summer 2015

Est. Date of Completion: Spring 2016

Budget: $10,149,891

Architect: RMKM

General Contractor: TBD

31

West Mesa High School

Address: 6701 Fortuna Road NW

Year School First Opened: 1967

Project Scope : Classroom Building “M”

Replacement. 2 phases for a total of 28 new classrooms.

Phase 1 - a three story classroom building with 17 classrooms.

Phase 2 - a two story classroom building with 11 classrooms, situated just north of the three story building.

Project Status: Begin Construction

Estimated Date of Completion

(Phase 1) : Spring 2017

Total Project Cost: $ 18.8 million

Architects: Mahlman Studio

General Contractor: Thomson

Construction

32

The Career Enrichment Center (CEC) and Early College

Academy (ECA)

Address: 807 Mountain Road NE

Albuquerque, NM 87102

Project Square Footage: 20,230

Project Scope:

 2 Science Labs

 EMT lab

 2 language Classrooms

 2 Multi Purpose Classrooms

 Food Prep Teaching Space

 Multi Purpose PE/Functions space

 Electrical Transformer

 Flatwork/sidewalks/ADA

 Recycling/Garbage Receptacle area

Project Status: Under construction

Est. Completion Date: Spring 2016

Total Budget: $5.5million

Architect: Lee Gamelsky Architects

General Contractor: Well Construction, Inc.

33

Manzano HS Rebuild

Address: 12200 Lomas Blvd. NE 87112

Year School First Opened

:

1961

Project Scope: Preliminary Scope is

Physical Education wing Additions and

Renovations.

Project Status: 50% Construction

Documents

Est. Groundbreaking: Phase I Spring

2016

Est. Date of Completion: Phase I July

2017

Budget: $14,844,920

Architect: Studio SW

General Contractor: TBD

34

MacArthur Elementary School

Address: 1100 MacArthur Rd NW

Year School First Opened: 1948

Project Scope: 12,373 Square foot addition/renovation

• Kindergarten Classrooms & Play Lot

• Cafeteria Addition / Kitchen Upgrades

• Improve Site Lighting for Security

• Install Security Fencing

• Site Improvements

Budget: $4,309,277

Project Status: Under construction

Est. Date of Completion : Fall 2015

Architect: Wright & Hammer

General Contractor: Anchorbilt

35

Mountain View ES Rebuild

Address: 5317 Second St. SW 87105

Year School First Opened

:

1952

Project Scope:

Total re-build of the school except for the existing kindergarten

New facilities will include 25 classrooms, library, health office, parent center, cafeteria/kitchen, mini-gym, administration area, and related support spaces.

Project Status: Out to Bid

Est. Groundbreaking: September 2015

Est. Date of Completion: July 2017

Budget: $21,173,546

Architect: Gregory Hicks

General Contractor: TBD

36

Valley HS Rebuild

Address:

1505 Candelaria NW 87107

Year School First Opened

: 1954

Project Scope: The master plan requires building " S " be razed and to construct a new classroom addition consisting of a new

Crime, Law, & Protection Classroom building.

Project Status:

95% construction documents complete

Est. Groundbreaking:

Phase I Fall 2015

Est. Date of Completion: Phase I Fall 2016

Budget: $7,194,644

Architect: Huitt Zollars

General Contractor: TBD

37

Reginald Chavez ES

Address: 2700 Mountain Road NW 87104

Year School First Opened: 1955

Project Scope: 25,454 square foot addition

New 10 classroom block and library, including new kindergarten classrooms

Project Status: Under construction

Est. Date of Completion: Spring 2016

Budget: $ 7.4 million

Architect: Cherry/See/Reames

General Contractor: T.A. Cole & Sons

38

Collet Park Elementary School

Address: 2100 Morris NE

Year School First Opened: 1961

Project Scope: 19,249 square foot addition/renovation

 Kindergarten Classroom block

 Administration expansion

Project Status: Under Construction

Est. Date of Completion: Feb 2016

Budget: $6.1 million

Architect: Vigil & Associates

General Contractor: T.A Cole & Sons

39

Comanche Elementary School

Address: 3505 Pennsylvania NE 87110

Project Square Footage: 13,976 square feet

Project Scope:

Kindergarten Addition

5 Kindergarten Classrooms

Administration Renovation

Fine Arts Addition

1 Music/Fine Arts classroom

Relocation & Upgrade of existing utilities

New Fire suppression sprinkler system

Increased site work

Project Status: Under construction

Total Project Budget: $5.3 Million

Est. Date of Completion: Dec. 2015

Architect: PA Architects

General Contractor: T.A. Cole

40

Wherry Elementary School

Address: 25000 E Kirtland AFB

Year School First Opened: 1952

Project Scope: New school construction and renovation

Project Status: Begin Construction

Est. Date of Completion: Dec 2016

Budget: $16.25 million

Architect: Fanning Bard Tatum

General Contractor: McCarthy NM

41

Atrisco Elementary School

Address: 1202 Atrisco Road SW

Year School First Opened: 1960

Project Scope:

Classroom block replacement

Kitchen & Cafeteria renovation

Project Status: Under Construction

Est. Date of Completion: August 2016

Budget: $9.85 million

Architect: Greer Stafford

General Contractor: Enterprise Builders

Corporation

42

Aztec Complex Special Education and Autism Center

Address: 2611 Eubank Blvd. NE

Project Scope: District Intensive

Support, Diagnostic, and Evaluation

Center for Special Needs.

Project Status: Construction

Documents

Est. Date of Completion:

Phase I – July 2016

Phase II – December 2016

Phase III – May 2017

Budget: $7.6 million, Phase I

Architect: Westwork

General Contractor: TBD

43

Hodgin Elementary School

Address: 3801 Morningside Drive NE

Year School First Opened: 1958

Project Scope:

Tot Lot

Kindergarten

Art/Music Rooms

Project Status: Construction

Documents

Est. Date of Completion: TBD

Budget: $2.66 million

Architect: Greg T. Hicks

General Contractor: TBD

44

Intensive Support Hub Prototype 1 (Sandia HS)

Address: 7801 Candelaria NE

Year School First Opened: 1958

Project Scope: To design and construct a Special Education

Intensive Support Facility. To be replicated on up to four site over the next 5 years.

Project Status: Design

Est. Date of Completion: February

2017

Budget: $1.54 million

Architect: Vigil & Associates

Architectural Group

General Contractor: TBD

45

Jackson Middle School

Address: 10600 Indian School Rd. NE

Year School First Opened: 1958

Project Scope:

Phase I - New

Kitchen/Cafeteria/Drama building

Phase II – 7 classrooms, administration, parent room

Project Status: Design

Est. Date of Completion: February

2017

Budget: $12.33 million

Architect: NCA

General Contractor: TBD

46

Jefferson

Middle School

Address: 715 Girard Blvd NE

Year School First Opened: 1938

Project Scope: Music

Classroom Addition &

Renovation

Project Status: Design

Est. Date of Completion: April

2016

Budget: $2.21 million

Architect: Dekker Perich

Sabatini

General Contractor: TBD

47

KANW

Address: 2020 Coal Avenue SE

Albuquerque, NM 87106

Project Scope:

Construct radio station classroom addition

Communications system upgrade

Project Status: Construction near completion

Date of Completion: May, 2015

Budget: $1.32 million

Architect: Mark Baker

General Contractor: Anchor Built, Inc.

48

Marie Hughes Elementary School

Address: 5701 Mojave NW

Year School First Opened: 1981

Project Scope: School replacement

Phase I: Demolition Play Areas and New

Construction of 2 story Classroom Block

Phase 2: Demolish existing old classroom blocks, Portable removal, loop road/bus

Drop-Off/Parking construction and New

Field/Playground construction

Status: Under design

Ground breaking: Fall 2015

Est. Date of Completion: Spring 2017

Budget: $21,912,667

Architect: G. Don Dudley

General Contractor: TBD

49

Onate Elementary School

Address: 12415 Brentwood Hills NE

Year School First Opened: 1973

Project Scope: Classroom addition & remodel

Phase I: Kindergarten classroom addition, 9,730 square ft.

Phase 2: Classroom, Kitchen/Cafeteria Addition

& Remodel, 14,214 square ft.

Status: Under design

Ground breaking: Fall 2015

Est. Date of Completion:

Phase 1 - Spring 2016

Phase 2 - TBD

Budget:

Phase 1 – $ 4.42 million

Phase 2 – $ 5.49 million

Architect: Phase 1 & 2 - Studio Southwest

General Contractor:

Phase 1 - Brycon Corporation

Phase 2 - TBD

50

Ernie Pyle Middle School

Address: 1820 Valdora Rd SW

Year School First Opened: 1951

Project Scope: Classroom Addition and

Renovation of the 300 wing into an Art

Complex. HVAC updates.

Status: Under Construction

Ground breaking: January 2015

Est. Date of Completion: Fall of 2015

Budget: $ 10,208,226 million

Architect: Baker Architecture & Design

General Contractor: Thompson Construction

51