ELECTRICAL SAFETY INSPECTION REPORT ABLOOM DESIGN LTD. 37, South Shastapur, Upazila Road, Fatullah, Narayangonj. Factory List: 1. Abloom Design Ltd. Inspected by: Younten Jamtsho & Pemba Report Generated by: Pemba Inspected on July 19th 2014 SUMMARY Abloom Design Ltd., factory was constructed in the year 2005 to 2008 and started production in 2008. The eight storied building was constructed as an industrial structure with total floor area of 2233.6 sqm and 28.8m tall. There are no separate sheds other than the main buildings. There were 550 workers in the factory during the inspection. The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd. (WEC). The purpose of the survey was to identify significant electrical safety issues and to provide recommendations for remediation based on applicable standards specified by the Accord. The scope of this initial electrical safety inspection was limited to the review and identification of major electrical safety issues. The inspection did not include identification of minor deficiencies, which will be further addressed as part of follow-up inspections. Table below summarizes the major electrical safety issues identified during the inspection. Recommendations have been provided to address each issue. An implementation schedule shall be developed by the factory to remediate each of the findings. The specific timing of improvements, including any requested extensions due to design / installation constraints, shall be submitted to the Accord for approval. Abloom Design Ltd. Page 2 of 6 FINDINGS AND RECOMMENDATIONS FINDING NO: E- 1 CATEGORY: TRANSORMER FINDING: Oil cup below transformer breather is empty. RECOMMENDATION: Breather oil cup must be filled with transformer oil to required level as instructed by the manufacturer. PRIORITY: P2 REMEDIATION TIMEFRAME: 3 WEEKS Transformer breather FINDING NO: E- 2 CATEGORY: DISTRIBUTION & LT PANELS FINDING: Phase barrier/separators phases are not installed. between different RECOMMENDATION: Phase barriers between different phases supplied by the breaker manufacturer must be installed to avoid arc flashing. PRIORITY: P3 MDB installed in ground floor. REMEDIATION TIMEFRAME: 5 WEEKS Abloom Design Ltd. Page 3 of 6 FINDING NO: E- 3 CATEGORY: CABLE & CABLE SUPPORTS FINDING: Excess cables are crowded and not supported inside the panel. RECOMMENDATION: Use PVC slotted duct inside the panel to support and latch the cables. Use cable tray/ladder to support the cable outside the panel. Use industrial graded flexible pipes instead of using normal flexible pipes if required. Panel which was installed in transformer room. PRIORITY: P3 REMEDIATION TIMEFRAME: 5 WEEKS FINDING NO: E- 4 CATEGORY: DISTRIBUTION & LT PANELS FINDING: Cable entry and exit hole is not sealed and cable gland is not used for cable entry and exit. RECOMMENDATION: Make circular hole at the base plate/top plate of panels and provide cable gland according to the respective cable size for cable entry and exit so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. PRIORITY: P3 REMEDIATION TIMEFRAME: 5 WEEKS Abloom Design Ltd. Page 4 of 6 Change over switch in generator room. FINDING NO: E- 5 CATEGORY: WIRINGS FINDING: End cover of aluminum channel is missing. RECOMMENDATION: Aluminum channel should be sealed properly with PVC cover (may the cover provided by manufacturer) and it should be vermin proof. PRIORITY: P3 Aluminum channel use as cable duct in production floor. REMEDIATION TIMEFRAME: 5 WEEKS FINDING NO: E- 6 CATEGORY: SWITCH BOARD & PANELS FINDING: Panel doors not connected with earth bond. RECOMMENDATION: Provide earth connection for body and doors of metallic distribution boards using green cables preferably braid so that the metallic door remains at zero potential all the time. PRIORITY: P3 Distribution panel in production floor REMEDIATION TIMEFRAME: 5 WEEKS FINDING NO: E- 7 CATEGORY: SWITCH BOARD & PANELS FINDING: Panel base plates removed to allow cable entry. RECOMMENDATION: Install the base-plate/top-plate (metal) with the provision of gland fixation for cable-entry. PRIORITY: P3 MDB which was installed in transformer room. REMEDIATION TIMEFRAME: 5 WEEKS Abloom Design Ltd. Page 5 of 6 FINDING NO: E- 8 CATEGORY: SWITCH BOARD & PANELS FINDING: Multiple cables terminating to MCCB terminal in panel. RECOMMENDATION: Multiple cable shall not be terminated into single terminal of MCCB which may induce loose connection and overheat PRIORITY: P3 SDB in production floor. REMEDIATION TIMEFRAME: 5 WEEKS Abloom Design Ltd. Page 6 of 6