SUMMARY OF ESTIMATED COST Construction Supervision Consultancy Service Subproject: Cau Dua Pumping Station (See Annex1 for detail) No. Content of Costs Cost Summary (1000 VND) 1 Experts' Costs 512.100 2 Management Fees 256.050 3 Other Expenses 107.500 4 Income Before Tax 52.539 5 Value Added Tax 92.819 6 Contigencies 102.101 Total 1.123.109 Rounded 1.123.000 (In words One billion, one hundred tweenty three million VND only)./. International experts National experts Maximum budget Expenses Provisional sums Contingency amount 0 person-months 68 person-months 1.123.000.000 902.757.900 118.250.000 102.100.790 VND VND VND VND Annex 1: COST ESTIMATION OF CONSTRUCTION SUPERVISION CONSULTING SERVICE Subproject: Cau Dua Pumping Station 1. Basic for Preperation of Cost Estimation - Decree No. 205/2004/NĐ-CP dated 24/12/2004 of Prime Minister regulating on wage level and tables, and allowances for state-own enterprises; - Circular No. 18/2010/TT-BLĐTBXH regulating on wages of domestic consulting experts for consultance package and for applying time-based contract belonging projects funded by state budget issued by Ministry of Labour, Invalid and Society - Based on Decision No. 395/QĐ-BNN-HTQTdated 11/02/2010 of Ministry of Argicultural and Rural Development regarding approval for Investment Project "the Strengthening Water Management and Irrigations Systems Rehabilitation Projects" funded by ADB and AFD; - Decision No. 1402/QĐ-BNN-TCTL dated 14/6/2012 of Ministry of Argicultural and Rural Development regarding approval for Investment SubProject of Cau Dua Pumping Station under project of the Strengthening Water Management and Irrigations Systems Rehabilitation Projects; - Based on Circular No. 97/TT-BTC dated 06/7/2010 regarding regulation of allowance standards, cost standards for orgnization of workshops on government agancies and public-work enterprise; - Based on Decision No. 957/QĐ-BXD dated 29/09/2009 regarding anouncement of management fee rates for project management and project construction consultancies; 2. Cost Estimation NO. I 1 2 3 Nội dung công việc 5 Experts' Cost Team leader Resident engineers (2x10x2) Quantity surveyor Geological engineer (optional required) Mechanical-electrical engineer II Management Fees III Other Expenses Printing, documentation, communication, stationary... (3 years) 4 1 2 Transportation (car rental) 3 Allowance of experts for field 4 Accommodation of experts for field IV Income Before Tax V Value with VAT tax 10% VI Contigencies VII Total Unit Quan tity Rate (1000 Đ) man-month man-month man-month 9 40 9 9.700 7.200 7.200 Amount (1000 Đ) 512.100 87.300 288.000 64.800 man-month 6 7.200 43.200 man-month 4 7.200 28.800 50% *(I) 256.050 See Annex 2 Calculation of unit wage for detail 957/QĐ-BXD 107.500 year 3 10.000 day 32 1.500 night 80 150 day 70 250 30.000 48.000 12.000 6%*(I+II+III) 17.500 52.539 V = 10%*(I+II+III+IV) 92.819 10%(I+II+III+IV+V) 102.101 VII = (I+II+III+IV+V+VI) Rounded NOTE 1.123.109 1.123.000 (In words One billion, one hundred tweenty three million VND only)./. Payment will be based on actual invoices Payment will be based on actual invoices Circular 97/2010/TT-BTC dated 06/7/2010 957/ QĐ-BXD