OCCIDENTAL MINDORO ELECTRIC COOPERATIVE, INC. San Jose, Occidental Mindoro BUSINESS PLAN 2009 TO 2014 THE OMECO MANAGEMENT TEAM Table of Contents Title Page Table of Contents I. Background II. Proposed Projects 18 III. Five-Year Historical Planning Data 22 IV. Technical Analysis 24 V. Financial and Economic Analysis 26 VI. Conceptual Engineering Design 29 VII. Project Cost Estimates 43 VIII. Project Financing Plan 44 IX. Implementation Plan 46 X. Risks/Threats 47 XI. Conclusion/Recommendation 11 Annexes 1 I. Background A) The Cooperative Occidental Mindoro Electric Cooperative, Inc. is a non-stock and non-profit electric service distribution cooperative. It is duly organized under Presidential Decree No. 269, as amended and incorporated on March 25, 1974. i. Vision and Mission OMECO envisions a fully energized Occidental Mindoro, through a self-reliant electric cooperative, where the people in rural areas as well as those in urban communities enjoy reliable and sustainable electric services provided for and by the concerned member-consumers and competent, honest and enthusiastic officers and employees. It will continue to strive for the Total Electrification of its coverage area to help promote the sustainable economic development in the entire province through the genuine cooperative efforts of its stakeholders under the principles of Absolute Honesty, Maximum Efficiency and Total Solidarity. ii. Registration OMECO is registered with the National Electrification Administration on March 25, 1974, and is granted its franchise on an area coverage basis by National Electrification Commission under Franchise Registration Number 54 dated February 13, 1980 and valid until February 13, 2030. It is registered with the Securities and Exchange Commission on _____ and is authorized by the Bureau of Internal Revenue with Certificate of Registration no. OCN 1RC000292326 dated September 14, 1997. B) Operational Milestones OMECO, after 34 years of dedicated service to its member-consumers has gained invaluable lessons through its struggles from initial uncertainty to the peak of its operational efficiency. The hard-earned skills from these experiences will enable the cooperative to attain the flexibility to withstand the current problems besetting its stability. i. The Start-Up Managers and key officers from the National Electrification Administration officials stirred the cooperative during its organization and early years of operation after OMECO was awarded the franchise in the towns of San Jose, Magsaysay, Rizal and Calintaan. This phase involved massive erection and construction of facilities and simultaneous capacitating of human resources. On May 7, 1974, OMECO bought-out the private San Jose Electric System. The operation of the plant in the commercial districts of San Jose did not last long because of machine failure. It was only in December 15, 1976 when the town was re-energized using OMECO’s power plant and upgraded distribution system. The demand was much below the break-even point of operation. The revenues could not sustain the cost of operation but OMECO held-on and accelerated the load additions and expansion to the coverage area. 1 ii. Through the Years While expanding its services in San Jose, the construction of lines going to the neighboring towns went under-way. Eventually the town centers in Magsaysay (March 14, 1977), Calintaan (June 28, 1977) and Rizal (November 28, 1977) were commercially electrified for the first time. The success in infrastructure development led to the integration of the towns of Mamburao, Sablayan, Sta. Cruz, Abra de Ilog and Paluan in August 8, 1979. The second wave of distribution development was launched for the northern municipalities of Occidental Mindoro. Subsequently, OMECO’s power plant in Mamburao commenced its commercial operation in March 1, 1980 serving only the poblacion. From there, the lines to Sta. Cruz, and Abra de Ilog were constructed. In November 1980, OMECO acquired the assets of Sablayan Electric Company and took over the electrification in the center of Sablayan. The local plant was later scrapped after the town’s distribution system was upgraded and tied to the South Grid from San Jose. The massive expenditures in the infrastructure affected the finances of OMECO. It continued operating below the break-even levels. The burden was also aggravated by the inadequate institutional development, as manifested among others by poor collection efficiency and high systems loss. Load additions took the toll on the power plants that were only refurbished when initially acquired for OMECO. Maintenance expenses bloated beyond endurance until the cooperative finally succumbed to great losses in early 80’s. The turn-around of OMECO started in December 23, 1983 through the militaristic leadership of the late Col. Zoilo M. Perez, Ret. Funds for fuel and engine rehabilitation borrowed from private citizens, the strict implementation of collection/disconnection policies reinforced with hard disciplinary measures on human resources and extreme cost consciousness powered the cooperative through the very stiff climb uphill. Steady efforts on institutional development also proved worthwhile. The demand leaped as aftermath of the National Power Corporation’s take-over of the cooperative’s power plants in June 6, 1988 where tariff rate was lowered from P 4.75 to P 2.50 per kWh. The sudden load growth ate up the supply capacity in early 90’s and paved the way for the Island Power Corporation, a private generating company, to enter the picture with an exclusivity contract for 25 years. From a virtually dead electric cooperative in 1983, OMECO gradually became a Class-A+ cooperative and maintained that status long after GM Perez retired because of old age in 1996. The momentum propelled the cooperative under the management of GM Alex C. Labrador to greater heights until the hurdles of the changing environment in the Power Sector became much of a problem. The main power generator, the Island Power Corporation was the first to suffer, until it finally ceased operation in 2006 leaving OMECO to the missionary mandate of the NPC-SPUG. It was very unfortunate that the power development from NPC-SPUG was delayed, forcing OMECO to shoulder the rental of generators from a private company. This, among others influenced the eventual decline in the operational performance of OMECO. 2 The preparedness for the EPIRA environment proved futile as revenues diminished as a result of non-responsive rates approved by the Energy Regulatory Commission, and too much subsidy to system losses above the prescribed system loss cap. Plans to adjust came in too late when the cooperative is already operating through deficit spending. iii. Awards and Recognition OMECO’s performance during the past year earned the cooperative the following awards and recognition: a) Best in Collection Efficiency/Performance Award – given by NEA in 1988 through 2006 b) Exemplary Payor Award – given by NEA in 1995 through 2001 c) Outstanding Electric Cooperative (Large Category) – given by NEA in 2002 d) Top Revenue District Taxpayer (Non-individual Category) – given by Bureau of Internal Revenue District of Occidental Mindoro in 2006 e) Model Taxpayer – given by Bureau of Internal Revenue District of Occidental Mindoro in 2006 iv. Classification From a Category D Small Cooperative in early 80s OMECO rose to become Category A+ Medium Sized Electric Cooperative in mid 90s, a Category A Large Cooperative in late 90s to 2001 through 2004. It was rated Category B in 2005 & 2006. Difficulties in operation earned the Cooperative the Category Rating C in 2007 and 2008. C) The Franchise Area i. The Coverage Area Occidental Mindoro is one of the two provinces comprising Mindoro group of islands. It is located south of Batangas and north of Visayas.The eastern portion of the province is bounded by Oriental Mindoro and the western portion by the Apo East Pass. On the north, it is bounded by Calavite Passage and the Verde Island Passage and on the south by the Mindoro Strait. The Southernmost tip of the province lies in the area of the Sibuyan Sea. The province has eleven (11) municipalities. Mamburao of the northern portion of the province is the capital while the southern town of San Jose is the most highly urbanizes trade center, followed the central municipality of Sablayan. Looc and Lubang are island municipalities located in the Lubang Island Group north of the province, belong to Lubang Electric Cooperative but managed by OMECO. Table 1 Land Area Broken-Down by Municipality Province of Occidental Mindoro No. of Land Area Barangays (sq km) Municipality Abra de Ilog 9 533.70 Calintaan 7 382.50 Looc 9 132.30 113.10 Lubang 16 Magsaysay 12 296.75 15 297.60 Mamburao Paluan 12 564.50 Rizal 11 242.50 Sablayan 22 2,188.80 446.70 San Jose 38 Sta. Cruz 11 681.40 Total 162 5,879.85 Occidental Mindoro has a total land area of 5,879.85 sq km. Taking out Looc and Lubang, OMECO’s coverage area then is 5,634.35 sq km in nine (9) municipalities consisting of 137 3 barangays. The largest municipality is the highly productive agricultural town of Sablayan with 2,188.80 sq km, the second largest in the Philippines. Table 1 in the preceding page shows the breakdown of the province’s land area. The distribution service in Paluan is undertaken by the local government with the lines borrowed from OMECO and supply provided by the NPC-SPUG. The present Occidental Mindoro is an agricultural area devoted to the production of food. Its economic base is rice production (Oryza sativa culture), a Philippine staple crop. It is the leading activity and source of seasonal employment in the province, participated in by almost 80 per cent of the population, including children. Wet land or lowland rice is a rainy season crop, being heavily dependent on water, and therefore produced from July (planting season) to October (harvest season). Tobacco, onions, garlic and vegetables are rather grown during the dry season (November to May) since they are not water-intensive crops, and require longer photoperiodicity. Rice, corn, onions, garlic, salt, fish (both wild water and cultured) are some of the relatively significant surpluses produced in the province in exportable quantities. Mangoes, cashew nuts, cooking bananas (saba) and some other fruits grown in upland orchards are among the other exports of Occidental Mindoro that have traditionally contributed to its income. Peanuts are also comfortably grown in some parts of the province, as well as cassava, sweet potatoes, ginger and other minor cultivars. Forest resources include timber and minerals, among them gold, copper, silver, chrome, and non-metallic minerals such as lime for making cement, and greenstones for ornaments. Timber groups include many species of hardwoods, such as mahogany, and other types of trees in high demand for durability. Commercial and aquaculture fish production is also a major contributor to the provincial economy. Aqua farming of tiger prawns, tilapia and even milk fish is a growing industry in the province. There are no large industries in the province. The government is the biggest employer, absorbing most of the off-farm labor force. The local electric cooperative, Occidental Mindoro Electric Cooperative (OMECO), is the biggest employer in the private sector, with 174 regular employees. The rest of the population is engaged in private trades. There are many multi-faceted problems in Occidental Mindoro's economy. In rice farming, the biggest confronting the producers are the high cost of production. This is attributed mainly to the spiraling prices of farm inputs. A study concludes that from 1997 to 2003, the cost of production rose by 47 per cent, while the income derived from marketing rice has maintained 1997 levels. There are also confused reports that the average production rate has declined due to the reduced application of necessary farm chemicals. In street language, this means that the farmers simply cut the amount of inputs because they cannot afford the high capital requirements of following all the recommended inputs in the farming calendar. Another structural problem is the inadequacy of irrigation. Most of the river systems in the province no longer have the demanded volume of water to make irrigation feasible. This is attributed to the greatly deforested watersheds. The status of road networks is another major problem that affects the economy. While the development of the major ports is expected in this decade, three domestic airlines are serving the south through the San Jose Airport and access to the northern parts is afforded through roll-on/roll-off vessels plying the Batangas-Abra de Ilog route. 4 Official NSO figures reported that for October 2000, the province registered a labor participation rate of 71.5% and 86.6% employment rate. Unemployment was registered at 13.2% while the under employment registered 22.2%. The NSO QuickStat November 2002 release reported that for CY 2000, the province registered an Annual Average Family Income of P 100,607, an Annual Average Family Expenditures of P 83,353 , an Annual Averaged Family Savings of P 17,254, an Annual Average per Capita Income of P 23,553 and an Annual Average per Capita Expenditure of P 18,606. ii. Status of Energization Of the 137 barangays in the coverage area, 118 are energized through the OMECO grids while 17 where energized off-grid either with stand-alone community gensets or NRE’s provided by the Department of Energy. 99% of all the barangays are energized. Table 2 below shows the Status of Energization as of October 31, 2008. Tab le 2 Status of Enegization As of October 31, 2008 Municipality Abra de Ilog Calintaan Magsaysay Mamburao Paluan Rizal Sablayan San Jose Sta. Cruz Total Coverage 9 7 12 15 12 11 22 38 11 137 Barangays Energized 9 7 12 15 10 11 22 38 11 135 % 100% 100% 100% 100% 83% 100% 100% 100% 100% 99% iii. District T ab le 3 District R epre se ntation s Co verag e S an Jo se (Ha lf) S an Jo se (Ha lf) M ag sa ysa y Rizal Ca linta an S ab laya n M am bu rao A bra de Ilo g (P aluan ) S ta. Cruz D istrict I II II I IV V VI V II The Member-Consumers of OMECO are represented in seven (7) districts as shown in Table 3. The subdivision scheme considers the balance in the numbers of represented memberconsumers and geography and demography. iv. SPUG Area There is currently no SPUG Distribution Area in OMECO’s franchise, although the whole coverage area is under NPC-SPUG’s Supply. D) Facilities i. Major Offices 5 OMECO places itself near the hearts of its member-consumers. Its major offices and/or service centers are strategically located in major population centers. Table 4 below shows the location of major offices. Table 4 Locations of Major Offices Main Office Sablayan Area Office MAPSA Area Office Pag-asa Service Center Address M. H. del Pilar St. San Jose, Occidental Mindoro Brgy. Buenavista, Poblacion Sabla yan, Occidental Mindoro Airport Road, Brgy. Payompon Mamburao, Occidenal Mindoro National Highway, Brgy Pag-asa Sablayan Occidental Mindoro Phone (043) 491- 1021 (043) 491- 1364 (043) 491- 1981 (043) 711-1806 (043) 711- 1009 In addition, OMECO maintains maintenance quarters in most municipalities where periodic transactions, such as payment of bills, as well as service requests are handled. ii. Substation Facilities The cooperative owns a single substation unit located in Pag-asa, Sablayan. It is rated 5 MW and draws power from the TransCo 69 kV Mindoro Grid. Installed and commissioned in 2004, it has metal structures, SF6 high-side breaker and low-side breaker fitted with Vacuum Fault Interrupters. The substation is dedicated to supply the Sablayan circuits and portion of Sta. Cruz. NPC-SPUG maintains a substation in Mamburao for the OMECO MAPSA Grid or North Grid. It is rated 10 MW but the allocation is only for 2.5 MW from the TransCo/ NPC-SPUG ancillary plant. NPC-SPUG also provides OMECO with a 5 MW substation that serve as tie to the Distribution System from their almost abandoned plant, PLDPP in Brgy. Central, San Jose. The extent of the supply is better discussed later under Sources of Power Supply. iii. Distribution Lines Table 5 on the right describes the coverage of the sparesely loaded distribution system in lineal kilometers. While most of the wooden poles used, 80% of them, are exceeding their rated life expectancy, the circuits are well maintained. Ta ble 5 Distribu tio n N etw ork (Line al Km s) Typ e 69 kV Tran sm ission 3 Ph ase 13. 2/7 .62 kV 2 Ph ase 13. 2/7 .62 kV 1 Ph ase 13. 2/7 .62 kV S econ da ry U nd er-bu ilt S ep arate S econ da ry Tota l K ms. 0.4 0 28 6.7 0 6 5.9 9 21 3.3 8 29 9.2 1 8 2.8 7 94 8.5 4 Most of the distribution transformers have laminated silicon-steel cores and have to be replaced by more efficient amorphous core units in order to achieve significant reduction in systems loss. The distribution lines spanned 948.54 kms to serve the whole coverage area. The nominal primary voltage is 13.2/7.62 kV and the utilization voltage is 0/240 V – nominal. 6 iv. System Map System Operating Map Occidental Mindoro Electric Cooperative, Inc. 7 E) Consumer Profile i. Categories by Type Type of services and the tariff are categorized by occupancy and/or utilization. They are: a) Residential – for domestic dwellings b) Commercial – for establishments engaged in businesses and/or trade c) Industrial – for manufacturing sector, where raw materials are processed into finished products d) Large Loads – for utilization other than residential use, with at least 100 kva demand e) Public Buildings – for establishments owned by the government, or where non-profit services or functions to/of general public are delivered/held f) Street Lights ii. Composition Table 6 Number of Customers by Type for the Month of October 31, 2008 Residential Commercial Industrial Large Load Public Building Street Lights Total Connections 43,122 2,852 45 18 990 105 47,132 Table 6 shows the degree of service connections for the month of October 2008. % 91.49% 6.05% 0.10% 0.04% 2.10% 0.22% 100.00% Residential type of customers dominates the number at 91.49%. Commercial customers rank second at 6.05% followed by Public Buildings at 2.10%. Industrial, Large Load and Street Lights customers are insignificant in number. In the arena of energy consumption, Residential type of customers is still dominant at 53% share followed by Commercial sales at 19%. Large Load comes third at 14% while Public Buildings and Industrial Loads have 7% and 6% shares, respectively. Chart 1 Energy Sales By Type (kWh) As of October31, 2008 Revenue By Type (P ,000.00) As of October31, 2008 Street Lights 248,190 1% Public Building 2,515,312 7% Large Load 37,951 13% Large Load 5,317,699 14% Industrial 2,081,545 6% Street Lights 2,256 1% Public Building 19,100 6% Commercial 7,123,832 19% Residential 20,207,285 53% Industrial 15,181 5% Commercial 55,893 19% Residential 169,595 56% In terms of revenue generation, the market shares of the categories have the same trends as in energy consumption because the difference in tariff rates across the customer types is insignificant. This is shown in Chart 1 above. iii. Demand per Type 8 Chart 2 below shows OMECO’s Demand Curve that is typical for January to October of 2008. Chart 2 12 St Lights Pub Bldg Large Loads 10 Industrial 8 Commercial 6 4 2 Residential 0 0:15 1:30 2:45 4:00 5:15 6:30 7:45 9:00 10:15 11:30 12:45 14:00 15:15 16:30 17:45 19:00 20:15 21:30 22:45 0:00 MW OMECO Demand Curve Typical, January to October 2008 TIME The cooperative has a coincident peak of 11.75 MW between 7:00 PM and 8:00 PM. The day’s peak is in the vicinity of 8 MW, expected between 9:00 AM and 4:00 PM. The seasonality of the demand is determined by the Large Load customers, consisting mainly of Rice Mills and Ice Plants. Table 7 Peak Demand (MW) Typical for the January -October, 2008 Residential Commercial Industrial Large Load Public Building Street Lights Total Coincident Non-Coincident 9.26 9.26 1.86 2.56 1.02 0.21 0.24 2.00 0.16 1.09 0.05 0.05 11.78 15.98 The system Load Factor is at 51% while the Average Demand is in the vicinity of 6 MW, typical. The major determinant of characteristic demand is the Residential type of customers. OMECO has a non-coincident peak demand roughly in the level of 16 MW and its coincident peak demand is nearing 12 MW. The peak demand data for all types of customers are shown in Table 7 on the left. Again, Residential customers’ demand is the greatest at 9.26 MW followed by Commercial users with 2.56 MW. Industrial and Large Load users have 1.02 MW and 1.09 MW non-coincident peaks, respectively. F) Sources of Power Supply As mentioned earlier, OMECO has three isolated Distribution Grids – of course with flexibility ties. These Grids have sources described in the following subsection. i. Power Plants / Sources The matrix in Table 8 shows the available power sources in OMECO in each Distribution Grid. 9 Table 8 Sources of Power by Grid ( MW) Grid North Grid Central Grid South Grid District VII V, VI, VII I, II, III, IV Source 69 kV TL MDPP 69 kV TL PB 106 PLDPP Bubog Owner TransCo NPC-SPUG TransCo NPC-SPUG NPC-SPUG IPC Rated/Allocated Dependable Remarks 4 4 10/2.5 2.5 Ancilliary Plant 2.5 2.5 10 8 0.25 Ancilliary Plant 7 0 Non-Operational The North Grid and Central Grid are more assured of supply capacity from NPCSPUG & TransCo, neglecting the reliability issues in the transmission lines, and the reliability of supply from generators participating in the Mindoro Grid. Source for the OMECO South Grid is in critical capacity level in the standpoint of peak demand and the supply capacity. PB 106 which is a power barge has technical problems with the berthing draft levels. The IPC plant in Bubog is nonoperational for almost three (3) years because of irreparable engine break-down. ii. Average Power Requirement and Growth Rate. Chart 3 on the right shows the historical energy sales, in GWH from year 2004 to 2008. It could be gleaned that the enegy sales almost flattened during the past 5 years with an averaged growth rate of 5.5% 50.00 38.21 40.00 GW H The capacity shortage in years 2005 & 2006 caused by the failure of the IPP and the problem in the mooring site of the augmenting Power Barge 106 are the major causes of this almost saturated trend. Chart__ Chart 3 Energy Sal es 42.74 30.00 35.81 39.71 44.32 20.00 10.00 0.00 2004 2005 2006 2007 2008 Year G) Status of Operations i. Technical Performance 1) Energization Level In terms of barangay electrification, 135 of the 137 barangays in the franchise area are energized, corresponding to 98.54% electrification rate. The household electrification level as of October 31, 2008 is at 49% with 42,895 energized residential customers compared to 87,990 estimated number of households in year 2007 census, i.e. assuming a single connection per household. 2) Reclassification (Size) OMECO is grouped among the Large electric cooperative in year 2007 and 2008. It is categorized as Class C based upon the 2007 performance evaluation. The coop has yet to improve in the areas of system loss, payment to power suppliers and control of cash advance to its officers and employees. 10 3) Payment Status to Power Suppliers Based upon the Statement of Accounts from the National Power Corporation, OMECO has an outstanding accounts payable amounting to P 269,003,866.66 as of September 30, 2008. The indebtedness includes unsettled Power Billing, E-Vat component, interests and surcharges. On August 2008, the NPC approved the restructuring of accounts amounting to P102,024,283.58 and charged the interest of P32,517,464.10 through the period of 5 years. Negotiation for the condonation of previous interest charges amounting to P11 M is under way with NPC-SPUG though. 4) Loan Repayments OMECO remains current in its loan repayments to the National Electrification Administration. In 2001 when the condonation of electrification loan was announced under EPIRA, it religiously continued paying NEA until the final condonation was approved in 2004. Table 9 below shows the Historical loan repayments to NEA. Table 9 Historical Loan Repayments P Million Year Principal Payments 4.119 2004 2005 4.483 2006 4.416 2007 2.584 2008 2.929 Interest Payments 3.568 3.849 4.435 4.239 3.941 5) Customer Consumption The following Chart 4 illustrates the comparative GWh sales per type of customer for the years 2004 through 2008, and Table 10 provides the averaged growth rate for the respective classes. Revenue comes predominantly from the residential customers at 24 GWh in 2008 with an averaged growth of 2.80%. Commercial customers follow with 8 GWh at 7.90%. Chart 4 C hart__ Historical G W h Sale s 25.00 Residential Commercial Industrial Large Load Public Building Street Lights GW h 20.00 15.00 10.00 5.00 2004 2005 2006 2007 2008 Year The Large Load class follows at 7.5 GWh and 10.10% growth. Both Public Building Customers and Industrial Classes are trailing near 3.5GWh but the growth rate for Industrial class is 7.60% while it is 13.30% for the Public Buildings. Sales and growth from the Street Lighting is quite low. Table __ in the following page shows the averaged growth rates in energy sales per customer type. 11 Table 11 below shows the extent of use per customer per month. Use dilution could be observed in the Residential, Large Load and Street Light categories, owing to the diminishing degree of use of new additions to each category. The Table 12 describes the rate of such use. Residential Customers tend to consume less through the years by 5.5%. Large Load Sales per month per customers is decreasing by 6.1%. Street Lights per customer use also decreases by 4.6%. Industrial Customers’ use increases by 2.5%, Public Building by 3.3% and Industrial by 5.1%. Tab le 11 Av eraged kWh per M onth per C ustomer 2004 to 2008 2004 57 213 3,649 41,443 219 47 R eside ntial C omme rcial Industr ial Large Load Public Building Street Lights 2005 52 216 3,706 26,861 213 35 Table 10 Averaged Growth Rate GWh Sales 2004 to 2008* Tab le 12 Grow th R ate, kWh/mo/cust * 2004 to 2008 2006 52 225 4,020 28,443 254 37 % 2.80 7.90 7.60 10.10 12.30 0.60 5.50 Residential Commercial Industrial Large Load Public Building Street Lights Total 2007 47 238 4,306 38,469 243 39 2008 46 235 4,458 32,235 250 39 * % R esidential C ommercial Industrial Large Load Public Building Street Lights -5.5 2.5 5.1 -6.1 3.3 -4.6 6) Power Factor T able 13 Table 13 on the left shows the System Averaged Power Factor through the years 2004 – 2008. The fair figures were the result of the restrictions from the supply plants. System Averaged Power Factor 2004 to 2008 * Year 2004 2005 2006 2007 2008 % 90.88 92.50 91.34 92.66 95.28 The generating plants allegedly becomes unstable at higher power factors, hence to prevent trippings, capacitors are disconnected from the line. 7) System Loss Chart 5 Historical System Loss 12,500 7,009 8,652 9,934 9,008 8,872 MWH 10,000 20.00% 7,500 5,000 25.00% 16.20% 18.33% 19.87% 17.28% 16.56% 15.00% 10.00% 2,500 5.00% - 0.00% 2004 2005 2006 2007 MWh % 2008 Year Chart _ on the preceding page provides the historical system loss data. The loss curve is somehow reflective of non-technical system loss as determined 12 from the distribution system loss segregation in 2006 where the technical system loss was computed ranging from 7% to 8% during the historical year 2001 to 2005. Hence, rehabilitation of the system to reduce the system losses is the priority program of OMECO. 8) Peak Demand Chart 6 Chart__ Peak Demand 12.50 12.00 12.00 12.00 20 08 11.00 20 07 10.50 11.00 20 06 11.00 20 05 The capacity shortage in years 2005 & 2006 caused by the failure of the IPP and the problem in the mooring site of the augmenting Power Barge 106 are the major causes of this almost saturated trend. 12.00 11.50 20 04 MW Chart 6 on the right shows the historical peak demand, in MW from year 2004 to October of 2008. It could be gleaned that the peak demand almost flattened during the past 5 years with an averaged growth rate of 2.2% Year 9) Contracted Demand The contracted demand with the National Power Corporation until year 2010 could cover the coincident peak load of the system. It should be revealed that the ECA with the Island Power Corporation is not reflected in the chart below. Chart 7 13 ii. Financial Performance 1) Historical Financial Highlights OMECO registered a very large net loss of P 50.86 Million in 2008 as reported by the external auditors. This result represents 14.5% excess of cost and expenses over the revenue, although it is 32.0% lower than the previous year’s corrected large net loss of P 74.76 Million. Cash operations however, resulted to reduced but still very large net loss/cash outflow of P 29.23 Million – net of depreciation. A substantial component of the large net loss is interest expense of P 16.99 Million, which include penalty for long overdue/restructured NPC power supply accounts. This negative performance brought up further the accumulated deficit by about 20.5% now at the magnitude of P 299.16 Million, from the previous years’ corrected deficit of P 248.30 Million (2007) and P173.54 Million(2006). 2) Profitability, Liquidity, Leverage, Debt Service For the past year 2008, the return on assets is -1.21% with the debt service coverage marked at 4.12:1. The leverage (Total Long Term Debt to Total Assets) is at 9.36% and the current ratio is 1.96:1. 3) Tariff: Average per Customer Type The average system rate charged to customers during the entire year 2008 is shown in Table 14 on the right. Table 14 The figures include the supply cost, distribution cost and government revenues and taxes. H) The Organization i. Board of Directors The power of the General Assembly is vested upon their elected District Representatives to the Board of Directors who has the legislative and oversight functions on the management. The present composition of the Board is as follows: Jerry Villanada – President and Chairman of the Board. He is involved in community organizing and development with Plan International, Inc., an NGO. His term will end in May 31, 2009 after two (2) consecutive terms as director following the defeat in April 2009 district elections in San Jose District II. Samuel A. Villar – Secretary. He first represented District VI (Sablayan) in 1988 and won successive terms by re-election. He is due for reelection in 2010. A BS Mechanical Engineering Graduate and a candidate in Master in Business Administration, he also earned a Diploma in Population Studies in Bombay, India. He previously worked with the Provincial Engineer’s Office as Equipment Engineer and is currently the OIC-Provincial Officer of the National Census and Statistics Office. 14 Francisco T. Servando – Vice Chairman. He is representing District VII (Mamburao, Abra de Ilog, Paluan & Sta. Cruz Area) and first appointed in 1997. His term as elected director will expire in 2010. He is also working as the Municipal Elections Officer in Sta. Cruz COMELEC office. Melito C. Pasol – Treasurer. He is a teacher by profession in District IV (Rizal) and is a graduate of BS in Agriculture with units in Education. It is his first term as director until 2010. Myrna G. Magno – Member. She is representing District III (Magsaysay) until 2011. A graduate in BS in Education, she is a businesswoman by profession. Arsenio C. Samson – Member. He is a former municipal councilor in District V (Calintaan). A third year BS Business Administration and a licensed Radio Telephone Operator, he is currently engaged in farming and business. Eliseo M. Lising, Jr. – In-coming Director (May 31, 2009). He is a past Barangay Chairman in San Jose District I and a businessman by profession. He finished Bachelor in Fine Arts. Ferdinand B. Mercene – In-coming Director (May 31, 2009). A college professor and a former municipal councilor in San Jose (District II), he finished BS in Business Administration and is a Master of Science in Information Technology after earning vocational courses in Teaching English as a Foreign Language, Computer Programming and System Analysis and Design. ii. Management Team Alex C. Labrador – General Manager (Retired: April 30, 2009) Alfred A. Dantis – Officer-In-Charge. He is a graduate of BS in Electrical Engineering at the Mapua Institute of Technology (198084) and a Registered Electrical Engineer with PRC License No. REE 001294. Hired in 1985 as a cadet engineer, he established the Transformer Rewinding Section of the Cooperative while performing as a Shift-Charge Engineer in OMECO Power Generations Department. He led in the operational and institutional rehabilitation of MAPSA Area in 1986 and Sablayan Area in 1998. He also worked as the Chief Engineer in the Technical Services Department in early 90s before was chosen the Manager of the Institutional Services Department in 1994. He performed as the OIC in Technical Services Department in concurrent capacity in late 2005 to February 2008. He is a self-learned computer programmer in MS Visual Basic and Visual FoxPro. The OMECO Management Committee Anita G. Juaño – Finance Services Department Manager Ricky A. Gonzales – Technical Services Department Manager Glen Cris C. Luna – Institutional Service Department OIC Teresita G. Casuncad – Internal Audit Department Manager Ildefonso S. Delgado, Jr. – MAPSA Area Manager Celso S. Garcia – Sablayan Area Manager 15 iii. Personnel Complement There are 180 permanent employees in the workforce including the managers and supervisors. The number is required to provide the quality service and acceptable response time to service requests from the member consumers in the entire area coverage. The workforce is distributed in the three major service centers that are geographically separated by rough roads, savanna of farmlands and rugged terrains. Table 15 describes the distribution of permanent employees in the three centers. Table 15 Distribution of Permanent Employees Per Service Center As of March 31, 2009 Office-Based Managers Supervisors Field Work Customers NonTech Tech Main Office 6 20 28 12 61 31,110 OGM 2 2 4 4 3 FSD 1 6 15 12 ISD 1 6 6 7 2 TSD 1 6 1 1 44 IAD 1 2 Sablayan 1 3 1 1 11 9,626 MAPSA 1 3 6 5 21 12,224 Total 14 46 63 30 154 52,960 % of Employees 5% 15% 21% 10% 50% Cust vs. Mon-Mgr'l Emp 1,151 841 1,765 344 181 Main Office 1,637 1,152 2,828 519 257 Sablayan 3,209 9,626 9,626 875 602 MAPSA 4,075 2,037 2,445 582 349 One manager in the OGM is detailed in LUBELCO as the deputized Officer-In-Charge. Generally there is one (1) non-managerial employee for every 181 service connections. On the average there is one (1) fieldworker for every 344 customers, however the distribution in the service centers seems to be uneven because the heavy construction teams are counted in the San Jose Main Office. Likewise, employees rendering tasks shared in the service centers are counted in the Main Office. The non-technical and technical office based employees and the four departments, in San Jose, are delivering for the three centers. A study to balance the manpower complement in the three areas, relative to customers and circuit kilometers is contemplated. Table 16 Educational Attainment of Permanent Employees As of March 31, 2009 Master's Graduate Licensed Bachelor's College Trade 180 Degree Studies Profesionals Degree Level Courses Main Office Sablayan Mamburao Total % 1 3 7 1 0.56% 3 1.67% 1 8 4.44% 44 5 8 57 31.67% 13 1 1 15 8.33% 41 8 22 71 39.44% High School Graduate 17 3 4 24 13.33% Elementary Graduate / Level 1 1 0.56% Table 16 above shows the educational attainment of the employees of OMECO, where it could be gleaned that the workforce could efficiently deliver their jobs. Employees aged 36 and above are nearing their retirement. This represents some sixty percent 60% of the regular employees. Fifteen 16 percent (15%) of the employees will retire in the next ten (10) years. The distribution of permanent employees as to their age groups is shown in Table 17 below. OGM FSD ISD TSD IAD Sablayan MAPSA Total % Table 17 Permanent Employees' Distribution by Age Group As of March 31, 2009 Below 26-30 31-35 36-40 41-45 46-50 51-55 56-60 26 1 2 3 5 1 2 1 3 4 11 4 7 5 5 2 5 3 2 2 3 8 8 10 10 7 10 1 1 1 5 3 4 4 1 7 12 8 6 1 2 3 31 39 30 32 18 22 5 1.67% 17.22% 21.67% 16.67% 17.78% 10.00% 12.22% 2.78% Similarly, some thirty-two (32) permanent employees, representing nineteen percent (19%) of the manpower, will complete their 35 years of service in the cooperative in the next ten years as shown in the following Table 18. Table 18 Permanent Employees' Distribution by Length of Service As of March 31, 2009 Below 6-10 11-15 16-20 21-25 26-30 31-35 6 OGM 1 3 4 4 2 1 FSD 4 13 2 1 2 5 7 ISD 3 8 1 4 3 2 1 TSD 8 11 14 4 5 6 5 IAD 1 1 1 Sablayan 2 5 5 3 1 1 MAPSA 2 13 6 9 3 3 Total 21 54 32 25 16 19 13 % 11.67% 30.00% 17.78% 13.89% 8.89% 10.56% 7.22% OMECO should prepare, financially and administratively, for the retirement of the employees. 17 II. The Proposed Projects A) Distribution Projects i. Projects with direct system loss reduction a) Line Rehabilitation and Meter Clustering – This project consists of correction of over-extended secondary lines and octopus service lines that would be effected through extension of primary lines, secondary and under-built lines. Clustering of KWh meters in the affected areas where non-technical loss is significant, and installation of new KWh meters are also involved. Major requirements are: 1) 2 – phase primary lines – 0.79 km 2) 1 – phase primary lines – 28.45 km 3) Insulated secondary under-built – 40.27 km 4) Insulated separate secondary – 38.48 km 5) KWh Meters – 12,907 pcs 6) Duplex wire#6 – 64,535 meters 7) Metal Cluster Boxes with Grilled Windows – 1,984 pcs. b) Transformer Load Management – The project involves correction of distribution transformer loading through load centering, split loading or replacement. Amorphous core transformers will be used in replacing unserviceable units because of their significantly low core losses. For this matter, transformers aggregating 5,099 KVA will be required. c) Capacitor Placement – 3,000 KVARs of capacitors will be needed to preserve the power factor at 95%, thereby improving the voltage and reducing the system loss in the franchise area. ii. Projects with indirect system loss reduction OMECO classifies these projects as Essential but Non-viable Rehab/Upgrading Projects because the objective is only to improve the Reliability and/or Power Quality. a) Installation of new 5 MVA substation in Mompong, Sablayan – The feeder from Pagasa substation serving the Municipality of Sablayan and the northern portion of the town of Calintaan traverses between the banks of adjacent major rivers. For almost six (6) years, OMECO is spending millions in re-routing the feeder every time it is washed away by the turbulent waters during rainy season. This new substation would cut the feeder length by half, and will be constructed in the load center of Sablayan-Calintaan and Rizal area, reducing opportunity loss in sales and providing relief to the Power Barge 109 that is severely affected by the siltation in the mooring site down south in San Jose. Pagasa Substation would serve the needs of Sta Cruz and upland areas of Sablayan while waiting for the development of mining communities in Sablayan in the next three years. b) Conversion to three (3) phase primary lines – The project aims to provide balanced loading in affected feeders and substations where extreme unbalance are experienced. c) Reconductoring of Backbone Lines to #4/0 acsr – The project aims to provide flexibility in the source substation for the backbone feeding the municipalities of Sablayan, Calintaan and Rizal, in the south and Sta Cruz far north. 18 iii. Service Expansion a) Line Expansion to Brgy Tubili, Paluan – This project calls for the construction of 4.25 kilometers 3-phase primary and 4.25 kilometers secondary underbuilt in the off-grid barangay served by the Municipality of Paluan. b) Line Expansion to Sitios – The project requires construction of 59.16 kilometers of 1-phase primary, 10.8 kilometers insulated secondary and 55.39 secondary under-built lines to benefit 1,549 households in 43 sitios from 2009-2014. iv. Other Distribution Projects a) Double Circuit Distribution Tie-Line from San Jose Switchyard to NPCMagbay Substation – This project is required to enable OMECO the use of the new 25 MVA NPC substation to be completed at Magbay by the end of 2009. The lines will use the existing right of way of the present distribution line, with the new set of 3-phase #336.4 MCM acsr as over-built tie line to the OMECO dispatch switching station. Poles will be replaced with higher ones. Eventually the exixting set of conductors will form two dedicated feeders for Murtha-Batasan and Magbay-Magsaysay-Labangan Poblacion, with flexible contingency for any outage in PB 106 in Caminawit. b) Equipment and Logistic Build-up - The project will provide improved responses to customer needs. Components of this item are line vehicles, test equipment, line tools, and web server to serve the information needs in the whole franchise. B) Other Non-Distribution Projects i. Financing for NPC Restructured Power Accounts – OMECO has to source a loan amounting to P221.932 Million in order to pay the full principal of its restructured power accounts with NPC-SPUG. It is eyeing on NEA or other institutions for lesser interest charges, ten (10) years repayment with grace period of 5 years in order to sustain its operation. ii. Information Computerization and Telecommunications Program – This project entails the improvement in the Electronic Billing System with Cashiering and Remote Tellering plus the software requirement to enable the cooperative to create its own IT unit. C) Summary of Investment Requirements Table 19 19 D) Justification of Proposed Projects i. Expansion – The project is in compliance to the mandate of 100% Energization of the Philippines. Electrification in rural areas will help spur the economic development and provide basic comforts in daily living. ii. Rehab/Upgrading of Distribution Lines – This project will contribute in the reduction of system loss and increase the reliability of electric services while improving the power quality. Reconductoring of primary lines to #4/0 acsr as well as the construction of the double-circuit tie-line will also provide flexibility in substation loading and help in alleviating the supply problems foreseen from the derating of the major source: the NPC-SPUG’s PB106 due to siltation. Clustering of KWH Meters will reduce the non-technical losses while the Transformer Load Management is intended to reduce the technical load-losses through use of efficient amorphous core transformers and prevent high maintenance costs from transformer blow-off. iii. Add-Ons – The project will enable OMECO to connect more households in a more rapid pace. This will translate to increase in revenue and increase the return-on- assets. iv. Substation – The construction of New 5MVA substation in Mompong, Sablayan will solve the perennial problem caused by the major river washing –out the feeder for Sablayan Poblacion. Historically, the interruption accumulates to a period of a month during rainy season. The location of the substation will also substantially cut the length of the feeder, thus reducing the line losses, and will help alleviate the supply problem in San Jose with the opportunity to load-shift Calintaan and Rizal. The project is principally desired to increase the reliability and prevent opportunity loss on sales. v. Logistics - The project is desired to improve the customer services. Additional line tools, test equipments and line vehicles will capacitate the area engineering strategy of OMECO. Responses to customer calls will be shortened a third of the time previously required and the web server for engineering database will enhance the pro-action of the technical staff. vi. Substation Lot, substation control house and take-off structures, materials for rewinding of transformers - The substation related items are justified in iv. Substation above. Rewinding of distribution transformers in the OMECO shop will reduce the expenses in buying transformers without sacrificing the losses. vii. General Account – The project will help reduce the non-power cost through the development of Automated Billing, Tellering and Cashiering capability with parallel focus in the development of OMECO’s ICT capability. E) Project Benefits and Impact 20 i. Tangible Benefits a) Improvement of Reliability by 20% from flexibility in load-shifting b) Annual reduction of system loss by 1% c) Maintenance of power quality to acceptable standards d) Increase in MWh sales by and Revenue by an average of 8.5% ii. Intangible Benefits a) Reduction of carbon gases from fuel lamps b) Reduction of carbon emissions from reduction of system losses c) Improvement in corporate image d) Customer’s satisfaction F) Options/Alternatives Considered There is no alternative option for this project which is proposed to relieve OMECO of recurrent relocation works in the feeder of Sablayan. A Major section of the said feeder traversed the very unpredictable Viga river range that always wash-out the electrical structures at least twice each rainy season since year 2004. The said problem cost OMECO several millions. Considering to construct a new feeder would require about 30 kms of work over steep rocky mountain range through Sablayan Penal Colony. This scheme would practically severe the system loss in the area and would proved very costly. 21 III.Five-Year Historical and Forecast Planning Data A) Electrification Level Table 20 below shows the historical and forecast planning data of OMECO. It could be gleaned that the Barangay Electrification Level is at 99% in 2008 from 89% in 2004. The household electrification level is 40% to 39% in the respective years but had risen to 48% in 2006, statistically indicating significant increase in potential households. Table 20 100% Barangay Electrification Rate is expected to come in 2009 while the Household electrification level is expected to grow from 51% in 2009 to 60% in 2014. B) Energy Requirement Table 21 below shows the energy requirement of OMECO. Table 21 22 The energy purchased by OMECO rose from 43,279 MWh in 2004 to 55,002 MWh in 2008. In 2009 it is expected to be 59,108 MWh and will rise to 84,646 MWh in 2014. C) Infrastructure Requirement It could be gleaned in Table 22 below that there is no Rehabilitation of Distribution Lines and Reactive Power Compensation projects. This is not the case. It is only reflected that way because the projects are entered in the GCP Technical and in the Line Materials for Upgrading modules that are not linked with the DDP’s physical targets. The said projects are reflected only as costs in the capital investment requirements as cost of Electrification projects. Table 22 23 IV. Technical Analysis A) Key Historical Status Data The key historical status data for OMECO is reflected below in Table 23. The averaged growth for each customer class, i.e., energy sales, number of customers and averaged monthly consumption per customer could be found in the left-most column opposite each category. Table 23 The Total Energy Sales grows by 5.5% and the Total Energy Consumption including the cooperative’s self-use and energy recovery increased by 5.4%. The Energy Losses expressed in percentage simulates an inverted parabola with the minimum in the vicinity of 16%-17% and the central peak at 20%. The Energy Purchases increased by 5.5% with the Maximum Demand flat in 11 MW -12 MW. B) Load Forecast (SALF) From Table 24 below, The Total Energy Consumption will increase from 48,645 MWh in 2009 to 105,151 MWh in 2018. Similarly Energy Purchases would be from 57,676 MWh to 118,490 MWh with the System Losses being targeted to be from 15.7% to 11.3% in the same period. Table 24 24 The Load Factor is anticipated to be flat at 51% with the Maximum Demand annually increasing from 7.6% to 9.9% from 2009 to 2018. C) Technical Project Benefits Table 25 Table 25 above shows the impact of the technical projects in terms of Energy Sales, Energy Losses and Customer Connections. The System Loss is slightly different from the previous discussion because the Internal Use of OMECO is not considered. 25 V. Financial and Economic Analysis A) Projected Financial Highlights and Ratios Table 26 gives the projected financial highlights from 2009 to 2013. It could be seen that the Total Operating Revenue would be P393.550M in 2009 eventually increasing to P581.025M in 2013. The Operating Margin is P4.859M and P90.852M, with the Net Operating Margin (P19.043M) and P40.178M in the respective years. The Non-power Cost would improve from 18% in 2009 to 13% in 2013. Table 26 Projected Financial Highlights Similarly, Table 27 below gives the projected financial performance in NEA Standard Ratios. Table 27 B) Projected Financial Statements The effect of the loan intended to pay the Power Arrearages with NPC-SPUG, at 10% interest and 10 years repayment period with 5 years grace period is shown in the summarized cash flow statement in Table 28. Table 28 26 i. Revenue The Gross Operating Revenue is projected at P393.255M in 2009 and would increase to P588.024M in 2013 as shown in Table 26. It could be seen that the Total Operating Revenue would be P393.550M in 2009 eventually increasing to P581.025M in 2013. ii. Profitability Referring to the Key Performance Indicators in Table 27, the Net Margin is projected to improve from -3.94% to 8.28%, respectively in 2009 and 2013. The Return on Assets is ranging to -6.53 and 3.65 for the respective years. iii. Liquidity The Liquidity expressed through current ratio is 1.75 in 2009, 2.15 in 2010, 2.62 in 2011, 3.19 in 2012 and 3.85 in 2013. Table 29 Financial Ratios iv. Debt Service Cover Referring to the same Table 29, the Debt Service Coverage could be seen improving from -1.06, to 1.35, 1.38, 1.51 and 1.61 from 2009 through 2013. v. Leverage Referring to Table 29 above, the Ratio of Total Long Term Debt to Total Assets expressed in percentage is 80.15, 78.83, 76.93, 73.70, and 138.70 also in 2009 through 2013. vi. Tariff It is assumed that tariff increases for Capex (Reinvestment Fund) amounting to P0.2297/KWh and Distribution Charge equivalent to P0.42/KWh will be approved by ERC in 2009. 27 C) Impact on Rate Base of the Proposed Projects The impact on rate base of the proposed projects is summarized below in Table 30. Table 30 D) Cost-Benefit Analysis The cost-benefit analysis, exclusively for the Technical Projects is shown Table 31. Table 31 It could be observed that the benefits of the projects would be realized starting in year 2010 but would eventually tend to equalize the costs in the subsequent years. E) Sensitivity Analysis i. Minimum Tariff Increase Requirements This study assumes a minimum tariff increase amounting to P0.6497/KWh, broken down as P0.2297/KWh for Capex (Reinvestment Charge) and to P0.4200/KWh for Distribution Charge. ii. Minimum System Loss Reduction The forecast targets a minimum system loss reduction of 1% annually. iii. Minimum Demand Growth Similarly, the model suggests a minimum demand growth of 7.6% 28 VI. Conceptual Engineering Design A. 5 MVA Substation Project. Technical Specifications and Drawings I. POWER TRANSFORMER 5/6.25 MVA Power Transformer, 69 KV Delta high voltage rating / 13.2 KV Wye low voltage rating, liquid filled transformer, conservator type construction; Provisions for jacking, skidding, lifting; Diagrammatic nameplate; Steel ground pads welded to base, Manhole w/ gasketed cover, De-energized tap changer, Panel-type radiators, Cooling fans for forced-air cooling by tatung, Brand New. Cooling Class No. phases Phase Sequence Taps % BIL HV BIL LV Bushing mounting Primary Bushing mounting Secondary Standard Radiators Coil type Winding temp rise Dielectric Fluid Conductor materials Impedance No-load loss Load loss tolerance Noise OA/FA Three (3) 60 Hz 2 FCAN, 2 FCBN @ 2.5 tap percent 350 KV 150 KV Cover mounted HV Cover mounted LV ANSI C57.12 Demountable Disc Circ. IIV 65 deg C avg. Fluid Mineral dielectric fluid ASTM Copper 7.50% 6.5 KW at 85 deg C 34 KW at 85 deg C w/ ANSI 65 dB II. 69 KV PRIMARY SIDE (HV) 1. SURGE ARRESTERS Type AZES Station Class, Gapless type, manufactured in accordance to ANSI/IEEE Standards C62.11. Brand New System Voltage 60 KV MCOV 48 KV System Frequency 50/60 Hz Impulse Classifying Current 10 KA High Current Withstand 100 KA Fornt-of-Wave Protective Level 179 KV 2. DISCONNECT SWITCH (ABS) Three-pole center break, for outdoor use according to VDE/IEC standards (latest edition), 72.5 KV, 6000n min. breaking strength w/o earthing switch, Brand New Type Rated voltage Rated Frequency Rated Nominal current D300-071231M/N 72.5 KV 60 Hz 1250 A 29 Rated short time current 31.5 KA Rated short circuit current 80 KA Rated duration of short circuit 3 s Rated lightning impulse withstand voltage (BIL) ..to earth between poles 325 KV ..across open switching device 375 KV Rated power frequency withstand voltage ..to earth between poles 140 KV ..across open switching device 160 KV Ambient air temperature range -40 to +50 deg C Altitude above sea level up to 1000 m Arrangement of disconnector poles side by side Phase center distance 1350 mm Permissible ice load up to 10 mm Seismic capacity up to 0.3 g Permission wind load stressing up to 900 N/m2 INSULATOR Height 770 mm Creepage distance 1820 mm Min breaking strength 6000 N Nominal tensile strength of terminals, horizontal ….. static 1000 N ….. static and dynamic 3000 N Colors of insulators brown Without joint sealing DISCONNECTOR DRIVE: Manual drive, three pole group operated Type HA30 with rocking lever Drive mounted at pole C outside Drive lowered down around 500 mm, without fixing console Protection class IP 55 Control voltage 125 V DC Anti condensation heater voltage 240 50 Hz ….. power consumption 18 W Manual drive with ant-condensation heater (continuous operation) w/o fuse Manual drive with locking coil ..detachable cable entry plate without holes ..No. of free auxiliary contacts 8NO 8 NC 1 wiping cont. GENERAL EQUIPMENT: Horizontal mounting High voltage terminal plate (AL) according to NEMA, Corresponding to enclosed dimension sheet. The main contacts are maintenance free Nameplate in English SURFACE PROTECTION Steel parts hot dip galvanized acc to DIN 50976 No top coating (for normal service conditions acc to IEC 60694 chap 2.1) All connecting parts made of A2-materials. Motor drive aluminum housing 3. POTENTIAL TRANSFORMER 30 69 KV, Voltage Transformer type UKE 82/2, 40250:115V, 0.3 WXY, dry typr resin insulated, Brand New Type UKE-82/2 Standard IEEE C57.13-1993 Ratio 120:01 Accuracy 0.3 WXY Highest system voltage 72.5 KV Power Frequency withstand volt. Primary – Ground (1min) 3 KV Power Frequency withstand volt. Secondary - Ground (1min) 3 KV Induced Voltage 140 KV Lightning Impulse withstand voltage (1.2/50uS) 350 KV Withstand voltage for operation at altitude up to 1000 m Frequency 60 Hz Dry Type insulation Yes Insulator made of porcelain color brown Arcing distance (+/-1%) 727 mm Creepage distance (+/-3.5%) 2060 mm Protected distance (+/-3.5%) -----Primary terminal made of Copper Alloy ACCESSORIES INCLUDED IN OFFER Secondary terminal box Yes Rating plate Yes Earthing connector Yes TESTS Routine test following above standards Yes SITE CONDITIONS Ambient Temperatures(min/daily average/max) Wind Velocity N/A Seismis Conditions N/A PRIMARY Voltage Factors Thermal burden -10/+30/+40 C deg 1.2 CONT 1.5 30 SEG 1 VA 4. CURRENT TRANSFORMER 69 KV, Current Transformer, 100X150X200:5, 0.3 BO.1-BO.5, dry type resin insulated, Brand New Standard Ratio Accuracy IEEE C57.13-1993 100/150/200:5 0.2 BO.1-BO.5 C100 Protection core Highest system voltage 72.5 KV eff Power frequency withstand volt. Primary – Ground (1min) 175 KV eff Lightning Impulse withstand voltage (1.2/50 uS) 350KV cr Withstand voltage for operation at altitude up to 1000 m Frequency 60 Hz Dry Type insulation YES Insulator made of Cycloaliphatic Resin Gray color YES Creepage distance (+/-3.5%) Primary terminal made of …. Diameter of terminal …. Length of terminal 1812 mm Copper Alloy 30 mm 122.5 mm 31 5. DIFFERENTIAL RELAY Transformer Differential Relay, iXP-420, Brand New Protective Functions: Two levels of over-excitation (V/Hz) protection (24) Under – and over-voltage (27/59) Fuse-fail detection (27/FF) Phase over current (5051) for each winding Residual over current for each winding (50R/51R) Ground over current with separate CT input for low side winding (50N/51N) Negative-sequence over current (50Q/51Q) for each winding Breaker fail-to-trip and fail-to-close for both breakers Sequence over voltage (59P,59Q,59N) and positive sequence under voltage (27P) Multiple-step over/under frequency elements with voltage and current supervision (81) Differential protection element (87-2) for fast response to large magnitude internal faults Adjustable 2nd and 5th harmonic restraint on the main differential element Restricted earth fault (87N) Highlights Add new functions and features using IDEA Workbench Custom Modules Selectable transformer winding configuration Multi-feeder frequency load shedding and restoration logic Selective tripping of both high and low side breakers Breaker health monitoring for both controlled breakers Trip coil monitoring (and close coil monitoring on the ideaPLUS hardware version) Virtual Teat Set event record simulator Relay Replay : The “what-if” analysis tool Interactive oscillography and Sequence of Events Recording Amps, Volts, Watts and VAR Metering Demand and Energy Metering Eight Setting groups Programmable front panel pushbuttons and targets Programmable LCD test messages 6. CIRCUIT BREAKER SF6 Circuit Breaker, 7.2 KV, Live Tank, Type GL309F1/3120, 2000 A, 25 KA, 3 pole, 125 V dc control, complete with 5 kg SF6 gas sufficient for the first filling. Brand New Rated Max. Voltage Frequency Continuous current 72.5 KV 60 Hz 2000 A Short Circuit Current Duration of short circuit Rated break time Ambient temperature range 25 KA 3s 60 ms -30 to +40 deg C 32 Altitude above sea level up to 1000 M Features of the circuit breaker: Suitable for three phase auto reclosing Creepage distance: 1815 mm Color of porcelains : brown (RAL 8016) Protection class IP 54 Phase center distance: 1050mm Six Al high voltage terminal pads, drilled according to NEMA Suitable for erection on steel supports Circuit Breaker poles will be delivered with 0.02-0.05 Mpa SF6 pressure SF6 density monitor with two-step signaling and visible temperaturecompensated pressure reading with Mpa/bar scale Overpressure relief device per pole Nameplate in English Features of the spring operating mechanism Operating voltage of auxiliary circuits: 125 Vdc Universal motor for operating mechanism: 125Vdc Alternating current circuit (heating): 230 Vac Operating range of coils: trip 70-110%,close 85-110% With mechanical operation counter not resettable Anti-pumping device Anti-condensation heater, permanently operated Two independent trip coils, one closing coil Mechanically coupled auxiliary switch with 12 NC, 12 NO and 1 wiping contact free Local mechanical and local electrical C/O operation with local/remote selector switch With motor protection by MCB Wiring 1.r mm2, stranded wire with ferrules Glanding plate Terminal strip Phoenix UK5N with 10 mm2 earthing terminal Door of housing with provisions for padlocks Surface protection: Aluminum alloy parts will not be painted Ferrous parts are hot-dip galvanized Flanges of insulators are anodized Aluminum sheets of operating mechanism with top coating (RAL 7044) 7. PRIMARY SECONDARY SIDE Design alteration shall be discussed before the implementation prior to awarding of projects III. 15 KV SECONDARY SIDE (LV) 1. OUTDOOR CIRCUIT BREAKER NOVA Oil-free, SF6 Gas Free, Maintenance Free Recloser, 3 Phase, Vacuum Axial-Magnetic Type Interrupter, Solid Dielectric (cycloalipathic epoxy) insulation, encapsulated, complete with form 6 recloser control, Brand New. Maximum Voltage Rated BIL Radio Noise Limit (uV) Power Frequency Withstand, Dry Power Frequency Withstand, Wet Rated Continuous Current Short Circuit Current, symmetrical 15.5 KV 110 KV 100@9.4 KV 50 KV 45 KV 630 A 12.5 KA 33 Making Current, Asymmetrical Peak 31.0 KA Making Current, Asymmetrical RMS 20.0 KA Form 6 control Protective Functions: Inverse/Definite Time Overcurrent 51N-P/50N-P ….. High Current Trip ….. High Current Lockout ….. Minimum Response Time ….. Time Adder ….. Time Multiplier ….. Low Set Sensitive Earth Fault 50N+ Under/Over Voltage 27/59 1 and 3 phase tripping, pick up setting w/ time delay setting ranging from 0 to 100 seconds Under/Over Frequency 81 1 and 3 phase tripping, pick up setting w/ time delay settings ranging from 0 to 100 seconds Directional Overcurrent 67N-P Sync Check 25 ….. Hot Line/Hot Bus Closing ….. Dead Line/Hot Bus Closing ….. Hot Line/Dead Bus Closing ….. Dead Line/Dead Bus Closing Note: Sync Check Parameters include the following configurable settings: ….. Voltage Angle ….. Mechanism Operating delay ….. Dead Threshold ….. Live Threshold ….. Positive Sequence Dead Threshold ….. Upper Voltage Limit ….. Lower Voltage Limit ….. Lower Frequency Limit ….. Upper Frequency Limit ….. Fail to Close Timer Reclosing & Lockout 79/86 Local Breaker Backup 50 BF Cold Load Pickup Quick fault Locator Area location and identification Four Protection Profile (normal, Alt Prof 1, Alt Prof 2, Alt Prof 3) 50+ Time Current Curves Define Curve per Operation Block Phase, Ground or Negative Sequence Trip Separate Operation to Lockout for Phase, Ground, CLPU and SEF Metering Functions: Power-Real, Reactive, Apparent, Power Factor ….. Real (KW) ….. Reactive (KVAR) ….. Apparent (KVA) ….. Power Factor Over/Under Frequency (Hz) Energy Symmetrical Components Harmonic through the 15th Total Harmonic Distortion (THD), True RMS Demand Peak Demand IDEA WORKBENCH 34 Fully Configurable I/O Allows user to become relay design engineer with use of Boolean Logic Tools and Control inputs Fully customizable protection schemes and I/O 2. DISTRIBUTION TRANSFORMER Station Service Transformer, conventional, pole type, 10 KVA, 7620/13200Y volts Primary, 120/240 volts secondary, 60 Hz, single phase, 2-HV bushing, 3-LV terminals with 2-2.5% taps below and above normal operating voltage, 95 KV BIL primary, 30 KV BIL secondary, 65 deg C temp. rise, mineral oil fluid, ISO 9001 certified, Brand New 3. FUSE CUT-OUT Fuse cut-out, Type L, 15 KV, 100 Amperes, open, distribution class, interchangeable, with NEMA crossarm bracket, Brand New 4. SURGE ARRESTER Varistar Polymer Type, 10 KV, normal duty, distribution class, MOV, complete with tin plated bronze parallel-groove connector and NEMA crossarm mounting bracket, Brand New 5. BATTERY Maintenance Free Batteries Model Nominal Voltage Nominal Capacity Dimension in mm Design Life • Dj100 2 volts/Block 100Ah @ 8 hr discharge rate L170xW72xH212 6 years under normal operating Condition Customized Battery Rack included 6. BATTERY CHARGER Automated Float Battery Charger Input Output Voltage Normal Charging Capacity 230 VAC/60 Hz/1 phase 125 VDC 20 Amps 3 KVA Features: Automatic float service charger with cut-off @ vpc and cut-in @ 2.16 vpc Utilized industrial magnetic contactor for control and overload relay for protection With direct reading DC current meter and DC voltmeter Full wave rectification for minimal ripple Fully-isolated power transformer rated at 100% duty cycle Floor mounted enclosure with cooling fan 7. SECONDARY 15 KV SIDE STRUCTURES Design alteration shall be discussed before implementation prior to awarding of project. IV. INSTALLATION WORKS (ELECTRICAL & CIVIL) INCLUDING CONNECTORS, CABLE, INSULATORS & GROUNDING • All equipment and accessories shall be delivered on site 35 • • • • • • • • • • • • Civil works, site development and perimeter & Fencing Mounting and installation of 5 MVA Transformer Mounting and installation of structures for substation equipments & accessories Mounting and installation of 69 KV livetank circuit breaker and accessories including SF^ gas filling Mounting and installation of metering & protection equipment for primary side (69 KV) Mounting and installation of metering & protection equipment for secondary side (15 KV) Installation of insulators, Wires & Cables necessary for all equipment Assembly, positioning and wiring of all equipment Installation of control cables Installation of grounding system and grounding for all equipment Basic programming & setting for all control, relays amd other electronic devices Testing and commissioning 36 37 38 39 40 B. Meter Cluster Box 41 42 VII. Project Cost Estimates Table 32 below shows the project cost estimates listed by category Table 32 43 VIII. Project Financing Plan A) Financing Requirement 1) Expansion to Barangays – to be financed through the subsidy grant from the Department of Energy 2009 P 3.757M 2) Expansion to Sitios – to be financed through Congressional Development Initiative Fund and Department of Energy as subsidy grant 2009 P 13.488M 2010 P 5.610M 2011 P 3.850M 2012 P 2.554M 2013 P 3.508M 2014 P 3.273M 3) Expansion 2009 2010 2011 2012 2013 2014 (Connections) - to be financed through Congressional Development Initiative Fund and Department of Energy as subsidy grant P 0.804M P 0.222M P 0.250M P 0.152M P 0.247M P 0.093M 4) Add-Ons - to be financed through loans from NEA-ADB 2009 P 3.510M 2010 P 3.663M 2011 P 3.976M 2012 P 4.318M 2013 P 4.694M 2014 P 5.107M 5) Rehabilitation/Upgrading of Distribution Lines – to be financed through loans from NEA-ADB 2009 P 68.728M 2010 P 47.505M 2011 P 52.755M 2012 P 36.357M 2013 P 40.216M 2014 P 16.717M 6) Substation - to be financed through loans from NEA-ADB 2009 P 18.000M 7) Substation Lot, Equipment and Related Structures, ICT - to be financed through loans from NEA-ADB and/or CIAC 2009 P 8.367M B) Sources of Funds i. CIAC CIAC includes reinvestment charges imbedded in the tariff rates (5% of Rate), and/or subsidy grants form government agencies, foreign aid, etc. 44 ii. NEA The NEA as implementor of government projects may grant funds as subsidy or loans with 9% interest rates, of varying repayment periods and sometimes with grace period for principal payments. iii. Commercial Banks Commercial banks may provide loans carrying interest rates ranging from 12% to 16% depending on the time of approval, at varying repayment periods and other special terms. 45 IX. Implementation Plan/Gantt Charts (Please turn to the Annexes) 46 X. Risks/Threats A) Technical Risk The technical risk arises from the assumptions of the sales and revenue parameters, including the supply-demand hurdles in the plan. B) Business/Industry Risk The business/industry risk arises from the regulations in the very competitive nature of the electric power industry and the non-stock, non-profit operation called for by its charter under PD 269 that mandates the total electrification in an area coverage basis. C) Credit Risk The carrying amount of the member-consumer and other receivables represent the cooperative’s maximum exposure to credit risk. No other financial assets carry a significant exposure to credit risk. OMECO has no significant concentration of credit risk with any single member-consumer on an on-going basis. It is the cooperative’s policy that all member consumers are subjected to credit verification procedures to identify accounts to be disconnected to minimize uncollected accounts. D) Liquidity Risk Liquidity risk arises from the possibility that OMECO may encounter difficulties in collecting consumer’s accounts and in raising funds to meet various commitments. Its objective is to maintain a balance between continuity of funding and flexibility through the use of loans. These limitations make the cooperative’s operation highly dependent on supplier’s credit primarily for power supply, and on government funding support for capital expenditures by way on loans, subsidy grants, etc. E) Management Risk The cooperative’s ability to secure a fully responsive tariff through the cash-flow rate methodology prescribed for all electric cooperatives and the flexibility to source out advantageous power supply contracts form the extent of the management risk in OMECO. 47 XI. Conclusion/Recommendation This study has determined that the Technical Projects being proposed are worthy to be implemented. The projects would strengthen the liquidity of operation near the third year of the forecast period. Deferred amortization payments could be gained from retained earnings of the previous years. The loans contemplated for easier restructuring of arrearages with the NPC-SPUG may help ease the financial turmoil, and the increase in revenue from larger volume of sales in the forthcoming years, in combination with the opportunity for timely approval of more responsive rates could assure OMECO of its desired financial and operational stability. It is therefore recommended to execute all the projects as planned, while paying extra focus on rate management. 48