SIGNIFICANT OPPORTUNITIES REGISTER - PAPER, PULP AND WOOD PRODUCT MANUFACTURING Company Name Public Report Year Opportunity Category Equipment type Amcor Limited 2008 Optimisation of compressed air operations. High and low pressure compressed air systems must be kept in balance to minimise blow -off from low pressure machines. This is now regularly checked as part of routine maintenance. Changes in maintenance practices Electric motors – air compressors Amcor Limited 2008 Variable Speed Drives (VSDs) to machine cooling fan motors. VSDs have been fitted to 2 motors and are currently being evaluated for performance. To date energy savings are being realised, but there have been some problems with motor bearings. This needs to be resolved before any further VSDs are installed Investment in new technologies or new configurations of technologies not used before Electric motors – variable speed drives Air pre-heat to # 4 Boiler. Preheat combustion air with waste heat from blow down via a water to air heat exchanger Amcor Limited 2008 Investment in new technologies or new configurations of technologies not used before Boiler for steam Amcor Limited 2008 Maximise low pressure steam extraction from turbine. Operator training to ensure maximum quantity of steam is put through the turbineto generate electricity. Changes in the staff operation of equipment Stationary gas turbine engines - electricity generation Amcor Limited 2008 Insulate stock tanks. Changes to processes required stock tanks to operate at higher temperature than original design. Insulation is now cost effective and so will be retrofitted. Investment in new technologies or new configurations of technologies not used before Chemical processing plant Amcor Limited 2009 Flexibles Acacia Ridge ChW Temperature Optimization. Optimize chilled water temperature of process cooling water. So far ChW temperature has been increased 3C without any effect on extrusion plant performance Improvement in process control Electric motors – HVAC and refrigeration equipment Building Supplies Group Holdings Pty Ltd 2008 Improvement in energy measurement and monitoring Other direct combustion thermal equipment Building Supplies Group Holdings Pty Ltd 2008 Improvement in process control Own use Building Supplies Group Holdings Pty Ltd 2008 Investment in the same but more efficient technologies Lighting systems Building Supplies Group Holdings Pty Ltd 2008 Investment in new technologies or new configurations of technologies not used before Own use Building Supplies Group Holdings Pty Ltd 2008 Investment in the same but more efficient technologies; Investment in new technologies or new configurations of technologies not used before Kiln Building Supplies Group Holdings Pty Ltd 2008 Building Supplies Group Holdings Pty Ltd 2009 Building Supplies Group Holdings Pty Ltd 2009 Opportunity Description Gas Minimisation: Carter Holt Harvey's site at Oberon produces Medium Density Fibreboard (MDF). Most of the site's thermal energy comes from renewable biomass, a near zero greenhouse gas emitting fuel source. In some of the many processes biomass is supplemented with natural gas. An extensive gas sub metering system has been installed at a cost of over $40,000. Sub-meter data has enabled the site to pin-point specific end users of gas and respond more effectively to variances. Since installation overall gas use indicators suggest annual savings of about 10,000 GJ per year have been achieved. By-pass of mill: Having changed the nature of its particleboard process over many years, CHH's Tumut site identified that some older equipment could be by-passed and replaced. One such item was a chipping mill. Disconnecting and by-passing that mill's input to another line is projected to deliver annual savings of more than 800 MWh. Lighting Reduction: Lighting represents a major cost for all Carter Holt Harvey facilities. Eliminating unnecessary lighting and switching lighting off when not needed provides immediate and low cost benefits. CHH's Sawmill at Myrtleford is progressively replacing older lamps with new brighter lamps. That means up to 20% of the old lighting fixtures do not need to be replaced. The site is also introducing PLC control on its lighting circuits so that non­ essential lights can be switched off when shifts end and maintenance is not needed. The lighting project is expected to save over $10,000 per year. Chipper Optimisation: Mechanical processing of timber (e.g. chipping and sawing) is a major energy user. Chipping functions in CHH's Morwell sawmill were being performed by two large chippers, each more than 150 kW. Analysis of the process led engineering and maintenance staff to determine that chipping in this area could be performed by a single chipper. A new conveyor was installed to re-direct material previously processed in chipper 2 into chipper 1. The project is expected to save over 500 MWh of electricity and over 600 tonnes of C02e. Kiln efficiency upgrade : Carter Holt Harvey uses renewable biomass to generate most of its thermal energy. There are processes that use natural gas to supplement biomass like the Tumut Sawmill which has dual fuel for heating its kilns. A recent major project around the kilns has involved replacement of heating coils and fitting of separate temperature zones. This has reduced drying times and energy consumption. The reduction has preferentially been applied to the natural gas supply as this has the greater cost and produces greenhouse gas emissions. The project has so far cut gas use in half saving an estimated 2.5 TJ and 170 tonnes of C02e per month. Motion Sensors: Oberon can be a cold place in winter. Keeping staff warm can be a challenge in an industrial work space. To minimise electricity use in the many heater units, motion detectors for heater activation were installed in the Site 1 Holtec building. Consumption monitoring of before and after installation showed a 25% reduction. Estimated annual saving of 7500 kWh over the year have been estimated for this project. Expansion to other areas is under investigation. Plate Coolers: Press platens need to be cooled before they enter a new cycle. This duty was being performed by six electric fans. These fans have been replaced by three evaporative coolers. The evaporative coolers use only 25% of the energy used by the fans saving around $1500 per year. Air Survey and Leak Detection: The site engaged the services of a specialty compressed air company to complete an ultrasonic leak detection survey. The results showed that the leak rate was not critical however capacity for improvement was identified. The site’s maintenance team has tagged and repaired the leaks. Maintaining leak rate within the “Best operating practice” range should deliver annual savings of more than $5000 per year. Investment in new technologies or Electric motors – HVAC and new configurations of refrigeration equipment technologies not used before Investment in new technologies or new configurations of technologies not used before Electric motors – fans Changes in maintenance practices Electric motors – air compressors Building Supplies Group Holdings Pty Ltd 2009 Building Supplies Group Holdings Pty Ltd 2009 D & R Henderson Pty Ltd 2008 D & R Henderson Pty Ltd 2009 D & R Henderson Pty Ltd 2009 D & R Henderson Pty Ltd 2009 Gunns Limited 2008 Gunns Limited 2008 Gunns Limited 2009 Gunns Limited 2009 Gunns Limited 2009 Gunns Limited 2009 Gunns Limited 2009 Gunns Limited 2009 Gunns Limited 2009 Lighting Upgrades: Various lighting improvements have been made at the Tumut Saw mill. These include installation of photo-cell sensors in external areas, override switches and control systems. It is estimated that these changes have saved over $20,000 per year. Investment in new technologies or new configurations of technologies not used before Lighting systems Lighting Timer: A timer system has been installed to replicate the standard operating roster. For safety reasons some lights remain on to illuminate passage ways. If lighting is required outside the normal roster period (e.g. plant maintenance) a manual override switch is available at the maintenance work shop to switch on the mill lighting. The change has reduced consumption by around 15%. Investment in new technologies or new configurations of technologies not used before Lighting systems Fitting of inverters to three large fan motors Investment in new technologies or new configurations of technologies not used before Electric motors – fans Investment in new technologies or new configurations of technologies not used before Bioenergy Investment in new technologies or new configurations of technologies not used before Electric motors – fans Improvement in energy measurement and monitoring Own use Renewable Energy Plant: Installation of 1 MWH Bio Mass (Pyrolysis) Energy Plant would reduce our electricity consumption from the grid by 29,028 GJ pa by generating part of our own on-site energy requirements. Requires 8200 tons of bio-mass pa, this can be 100% supplied from excess sander dust generated on site in the manufacturing process (currently being used to supplement our heat energy requirements for drying) By product is bio­ char, a synthesized carbon product which significantly improved crop yields (and sequesters carbon) Estimated project cost is AUD$1.5-$2.0 Million installed using new Australian Made Technology Inverters for Jet Dryer: Install inverters onto Jet Dryer. This would enable power to fans to adjust up and down based on load balancing to evaporation requirements. This would reduce our electricity consumption by approximately 2300 GJ pa. Estimates cost is AUD $70,000 installed Energy Monitoring System: Perform 'discovery' exercise for all site electrical devices and install energy monitoring software to provide recommendations to reduce consumption by installing or upgrading current technology. It is estimated this system would reduce our electricity consumption by more than 1000 GJ pa. Estimated project cost is $100,000 Lighting Upgrade: Electricity is the second largest energy source used by Gunns and is also the most costly, providing potential for significant cost savings to be recognised. At each site a considerable portion of electrical energy is used for lighting. Gunns commissioned CB&M Solutions to Investment in the same but more undertake a detailed lighting audit at all three participating sites. This was conducted by walking through and physically identifying and counting each efficient technologies individual light fitting. CB&M Solutions then provided recommendations on lighting efficiency opportunities which included refurbishment of light fittings and lamps to energy efficient types and also investigating daylight harvesting and occupancy sensors. Kiln Efficiency: At the Tarpeena mill, more than 90% of the site's energy is consumed in the Kilns area. Kilns are thermally insulated chambers in which controlled temperature regimes are produced to dry the timber. Gunns have engaged Windsor Kilns Pty Ltd to audit both Lindsay Street and Changes in management systems Tarpeena sites and provide recommendations on improving the energy efficiency of the Kilns. Windsor Kilns are a privately owned company based in New Zealand with more than 30 years experience in manufacturing drying kilns At Triabunna the air compressor accounts for an estimated 11% of the sites electricity use. An opportunity to upgrade the air compressor to a unit which would use only one third of the electricity to run in comparison to the incumbent unit was identified. Overall, the opportunity would reduce the Investment in the same but more efficient technologies sites electricity use by approximately 7%, with a payback period of less than 3 years. A mobile plant audit was undertaken at Ling Siding with the aim of identifying if there were any nonāessential forklifts or loaders which could be made redundant to reduce diesel use on site. After reviewing operations, the audit found it would be possible to remove 3 forklifts and 1 log loader from operations. This has an annual energy saving of >8800 L diesel per year. Similarly, mobile plant audits at Kalangadoo, Tarpeena and Smithton found opportunities to either downsize mobile plant when upgrading; remove some forklifts from operation; or upgrade to more fuel efficient motors to reduce diesel consumption At Hampshire, lighting use was reviewed and it was identified that standby lighting could be reduced on weekends through altering the phasing of the lighting configuration. This change is estimated to reduce standby lighting by 30%. Lighting systems Kiln Electric motors – air compressors Improvement in process control Forklifts, front end-loaders, and other machinery Improvement in process control Lighting systems The infeed and debarker operation at the Hampshire woodchip mill accounts for approximately 25% of energy used on site. An opportunity was Investment in new technologies or recognised to bypass a section of the debarker via a process change. This process change was estimated to save >10% of the sites total energy new configurations of consumption per year. technologies not used before Power factor is the relationship between what power is drawn by the user, compared to what is actually used. In simple terms, it is a measurement of how efficiently the business is using the electrical power supplied to the site. A power factor of anywhere between 0.9 and 1 ensures the business is Investment in new technologies or using its energy effectively. However a power factor of below 0.9 may mean a higher than necessary kVA demand. At Lindsay Street, Smithton and new configurations of Hampshire the power factor is below 0.9. Hence an opportunity was identified to install power factor correction to ensure the electrical energy technologies not used before supplied to the site is being used effectively. Ultimately this will reduce ‘loss’ of electricity to the site and less electricity will need to be purchased. The payback period on these units is generally 2 years. New re-conditioning chambers were installed at Lindsay Street in October 2008. This has significantly reduced heat loss experienced in the ageing Investment in the same but more chambers and resulted in reduced wood waste and electricity consumption efficient technologies A consultant from Steam Systems provided advice on a range of boiler modifications at Ling Siding to improve the efficiency of both wood waste and Investment in new technologies or electricity. Some of the modifications implemented have included: Installation of steel ducting, air nozzles and a fan controlled by a variable speed drive new configurations of to allow controlled placement delivery of air. Control over the amount of air being drawn in and distributed around the furnace has increased the steam technologies not used before; load capacity and furnace temperature by 30%. Review of storage and infeed of fuel has allowed a drier mix of fuel (wood waste) to enter the boiler to Improvement in process control improve burning efficiency. Own use IT, communications and other elctronic equipment Heat losses Boiler for steam Hyne & Son Pty Limited 2008 Hyne & Son Pty Limited 2009 Hyne & Son Pty Limited 2009 Kimberly-Clark Australia Pty Limited 2008 Kimberly-Clark Australia Pty Limited 2008 Kimberly-Clark Australia Pty Limited 2008 Norske Skog Industries Australia Limited 2008 Norske Skog Industries Australia Limited 2009 Norske Skog Industries Australia Limited 2009 Lighting Management: As part of Hyne's capital expenditure program, energy efficiency initiatives are being reviewed at the design stage of capital projects such that energy efficiency opportunities can be assessed, and where financially justifiable, are 'built' into the project. An example of this process is a "Lighting Management Opportunity" at the site where the design team identified an opportunity to reduce the lighting energy consumption Investment in research and of an industrial storage building to be built at the site. The building is utilised to store by-product prior to sale with the by-product being transferred to the development, testing and trialling building by a materials handling system. As part of the design process, the building use, use of ambient lighting, lighting levels, and lighting controls were studied. This resulted in a lighting design that utilised ambient lighting panels as part of the structural cladding, base line illumination to comply with BeA requirements, and controlled lighting for loading operations. This opportunity is calculated to reduce the energy consumption of this building by up to 37% as compared to a traditional lighting design, saving up to 45.1 GJ of energy for this building per year. This opportunity has been implemented Secondary hot oil loop flow management: Kilns and reconditioners are utilised to dry and condition the green sawn material produced at the site. Kiln drying involves the accelerated evaporation of the water from the green sawn material under controlled conditions until the moisture content reaches a desired level. To accelerate the drying process and evaporate the water in the kiln, hot air is circulated within the kiln. This air is heated by a thermal heat transfer medium which is hot oil. The hot oil is circulated between the heat plant (which produces heat energy from combusting biomass) and the Investment in research and kilns through a primary hot oil circulation system. Each kiln has its own secondary loop that takes heat energy from the primary loop. The oil is development, testing and trialling circulated in each secondary loop through the use of secondary loop circulation pumps. These pumps are powered by electrical energy. Conventionally, secondary oil loops are a constant flow loop with a bypass valve to control the oil flow through the kiln so as to maintain a set primary loop flow for safe heat plant operation. Through research and development, Hyne have developed an energy demand flow management secondary loop oil system where th Utilisation of Kiln Residual Heat:Kilns and reconditioners are utilised at the site to dry and condition the green sawn material produced. The reconditioner is utilised following the kiln drying process to equalize and condition the dry sawn material. As per the kiln, the reconditioner also utilises thermal energy. This energy is utilized to produce the equalizing/conditioning high humidity environment. As the kiln drying process is aided by a low humidity environment, conventionally the moisture is ejected to atmosphere from the kiln as part of the drying process (just like a clothes dryer). This Investment in research and moisture laden air has low grade residual energy content. Heat recovery systems are sometimes utilised in kilns for air pre-heating for low temperature development, testing and trialling drying operations but have not conventionally proven viable for ultra high temperature drying operations. Hyne investigated different ideas to improve kiln and reconditioning energy efficiency and identified an opportunity to harness and utilise the residual energy content from the moisture laden air ejected from the kiln. Through research and development trials, Hyne was able to transform this idea into an opportunity through developing a system to e The main focus in 2007 for the SA mills was to implement a more thermally efficient process for providing electricityto the SA mill complex. At the same time an analysis of the future cost of power was undertaken in light of the new emissions trading scheme and the expanded mandated renewable energy target. Two options have been identified as providing some insulation against the expected increases in electricity and gas prices expected when gas becomes the preferred energy source for new power generation in the region and the cost of carbon emissions is added to the cost of power. The two options are:­ Investment in new technologies or * For a biomass power plant to be built adjacent to the SA mill complex which will use biomass from forest waste and other fibre based wastes. The new configurations of target is to eliminate the carbon emissions resulting from the generation of electricity needed by the mills. It is also possible that some of the mill steam technologies not used before needs could be sourced from the biomass plant, resulting in an increase in on site thermal efficiency. This secondary option needs to be investigated further. In theory, this option is unlikely to reduce the thermal efficiency in generating the power needed on site by the mill complex, but its main attraction is that th This option is likely to result in lower costs than expected in the future using traditional supplies of electricity (with the various premiums for CPRS, MRET, * Should the biomass project not proceed KCA has identified that a gas fired cogeneration project could be commercially a better solution than using conv This option is likely to result in lower costs than using traditional supplies of electricity for future needs (with the various premiums for ETS, MRET, etc) but N ti ti i lthe major ith thrust t ti ofl the id f bof th th t program ti has h been focused on d the ith main th bipower supply. l t KCA ti operates b i f th d dof Notwithstanding that first year the fEEO a program continuous improvement addressing energy use. This program has resulted in a number of small energy saving projects being implemented over many years. For the period being reported on, due to a change in product mix, and some negative aspects faced by the SA Mill complex during the year, the benefits of these energy saving programs were largely offset and there was no overall increase in energy efficiency. It is expected that this continuous improvement program will provide a long term benefit, and is therefore required to remain as part of normal operations. In addition to its continuous energy improvement program, KCA also implements a triennial assessment of energy efficiency at its mills, and benchmarks performance on an international basis against all similar plants operated by Kimberly Clark Corporation. The next triennial review for KCA is to be carried out during 2009. Optimisation of heat recovery systems to reduce steam demand This project involved reviewing operation and maintenance of process heat recovery equipment to increase waste recovery and thereby reduce steam demand. Some engineering changes were required, as well as improved monitoring and cleaning of equipment. The upfront investment cost to enable optimisation was around $100,000. To date heat recovery has improved by 27TJ per annum. The goal is to continue to increase the amount of heat recovered through refinement of operating practices and cleaning frequency during 2009. This opportunity is being implemented Waste steam recovery re-boiler An opportunity has been identified to install a steam recovery reboiler on a new thermo mechanical pulping plant. The new plant is to be installed in 2009 to replace an existing chemi-mechanical pulping process. It is anticipated that the introduction of the Carbon Pollution Reduction Scheme will provide sufficient financial incentive to justify investment in additional steam recovery equipment. This will have an upfront cost of around four million dollars and provide energy savings of around 500TJ per annum, through a reduction in steam load on the existing boiler. This opportunity is under investigation. Advanced process control of thermo mechanical pulping This project involves the installation of advanced process control technology to improve process stability and product quality with lower energy consumption. Suppliers have been evaluated and a 12 month trial is to be conducted in 2009. Based on estimated savings and experiences elsewhere, energy savings of around 50TJ could be realised. If the trials prove successful, project costs of over one million dollars will be required for full installation. This opportunity is to be implemented. Lighting systems Kiln Kiln Bioenergy Changes in management systems Own use Changes in management systems Own use Improvement in process control Boiler for steam Investment in new technologies or new configurations of technologies not used before Boiler for steam Investment in research and development, testing and trialling Own use Norske Skog Industries Australia Limited 2009 PMP Limited 2008 PMP Limited 2008 PMP Limited 2008 PMP Limited 2009 PMP Limited 2009 PMP Limited 2009 Pratt Consolidated Holdings Ltd 2008 Pratt Consolidated Holdings Ltd 2008 Pratt Consolidated Holdings Ltd 2008 Pratt Consolidated Holdings Ltd 2009 Pratt Consolidated Holdings Ltd 2009 Pratt Consolidated Holdings Ltd 2009 Optimisation of heat recovery systems to reduce steam demand Update: The heat recovery system has been further optimised. Modifications to piping, revised cleaning strategies and improved performance tracking have been implemented. Heat recovery rates have improved from 1.0 to 1.2 GJ per tonne of pulp processed to 1.4 GJ per tonne (+ 15-20%). This is equivalent to an achieved improvement of ~50 TJ per year. Optimisation and performance monitoring will continue. This opportunity has been implemented. Quick Bake Ovens: The opportunity identified relates to imprinting of aluminium plates used on the pre-press activities at the Moorebank site. The proposed quick bake ovens decrease overall drying time of the plates and provide a reduction in energy associated with electricity usage used to power the drying equipment as well as water that is used in the process. The opportunity has been implemented at Moorebank. It will also be implemented at Clayton. Virtualization of Servers: The opportunity identified applies to the development servers used on site in Clayton and involves a significant server reduction through the use of virtualization software. This reduction in physical hardware is expected to translate into significant power savings as a result of reducing server hardware which runs 24 hours a day, seven days a week. The opportunity has been implemented. The opportunity has also been implemented at our IT Hub in New Zealand. Power Correction Factor Upgrades: The opportunity identified relates to improved energy efficiency resulting from an improved power factor correction and reduced network charges. Upgrades are intended to improve energy efficiency by matching the supply of energy to the power requirements of the current equipment installed. The improved efficiency is also expected to result in cost savings in the form of minimal or nil surcharges passed on to the site by energy suppliers in relation to penalties and surcharges associated with power factors that fall below the ideal range. This has been implemented at Clayton & Moorebank. Compressor Upgrades Voltage Control Meters (upgraded metering program) LED Lighting replacement of Fluorescent lighting. Paper machine 3 which is one of two machines located at the Smithfield site currently uses rotating siphons on all drying cylinders. Blow through steam (steam used to evacuate condensate from the dryer) from the first section is cascaded to cylinders 1 and 2 with any additional steam requirement made up from live steam. However as the first drying group runs at significantly higher pressures than the first two cylinders, on most grades there is excess steam available which leads to a small amount being vented to atmosphere to maintain differential pressure in the first dryer group. Following a steam optimization clinic conducted by Kadant Johnson in the US and attended by a Visy engineer, stationary siphons are now being investigated as an alternative. As stationary siphons don’t have to lift the condensate against centripetal force, significantly less blow through is required, which could eliminate the need to vent steam from the first section. Process water is cleaned by passing it through a PETAX filter before being used as a fresh water substitute on high pressure machine showers. Any shortfall in production of PETAX water is made up with fresh water and steam is then used to heat the water to minimize any thermal shock. In reviewing steam users it was found that the steam use for this system had increased since the installation of gravity strainers which are a requirement for the new effluent treatment plant currently being constructed. The increase in steam use was traced to the addition of gravity strainer shower water to the PETAX water users. An alternative line has now been installed that supplies the gravity strainer showers with gravity strainer accepts. This has had the effect of significantly reducing the fresh water make up required and as a result has also significantly reduced the steam requirement. The Kadant Vortech rotor is being investigated as an alternative for the existing rotor on the batch pulper. The manufacturer claims a 20% reduction in power consumption for the same defibering is possible or additional defibering may be achieved for the same power. Given that the pulper currently processes well in excess of its original design capacity it is likely that a compromise position of some additional defibering with a less than 20% reduction in energy consumption would be reached. Two roof heaters are employed at the Visy Paper 4 paper machine, both of which source the supply air from the boiler house and this air is heated to 75-85°C with 11 bar live steam - this occurs to maintain adequate building temperature and humidity conditions which prevent condensations within the building (severe condensation can occur due to the large amount of water evaporated in a paper mill). The amount of live steam used in the roof heaters was calculated based on the air flow and the temperature rise from the measured temperature to 75°C. During warmer months where there is lowered risk of condensation within the machine hall, a lower roof heater temperature set point could be employed. Tests were conducted to ensure that this temperature setting could be safely achieved without compromising mill building condensation levels. Subsequently, control logic was implemented to lower the set point on warmer days to reduce the steam consumption. Pocket ventilation air aims to optimise the performance of the dryer section by introducing hot dry air at points of evaporation in the paper machine drying section. Higher than required pocket air temperature operating ranges results in higher steam consumption with limited gain in drying rate. After testing, the target pocket ventilation temperature control range was reduced for particular drying sections so that drying rate was not compromised while ensuring no excessive steam usage. A feed pump to a turbo separator is controlled to maintain desired pressure and flow rate. A control valve which was used to control pressure and flow rate was replaced with a variable speed drive which was installed to reduce the speed of the electric motor and therefore pump to obtain the desired pressure. Following the installation, reduction in motor loading was observed and therefore the installation resulted in higher electric motor energy efficiency and slightly improved process control Improvement in process control Boiler for steam Investment in new technologies or new configurations of technologies not used before Oven Investment in new technologies or new configurations of technologies not used before IT, communications and other elctronic equipment Investment in new technologies or new configurations of technologies not used before IT, communications and other elctronic equipment Investment in the same but more efficient technologies Electric motors – air compressors Improvement in energy measurement and monitoring IT, communications and other elctronic equipment Investment in the same but more efficient technologies Lighting systems Investment in research and development, testing and trialling Boiler for steam Investment in new technologies or new configurations of technologies not used before Own use Investment in research and development, testing and trialling Own use Improvement in process control Boiler for steam Improvement in process control Dryer; Boiler for steam Investment in new technologies or new configurations of technologies not used before Electric motors – variable speed drives SCA Hygiene Australia Pty Ltd 2008 SCA Hygiene Australia Pty Ltd 2008 SCA Hygiene Australia Pty Ltd 2009 SCA Hygiene Australia Pty Ltd 2009 Stock Pump Variable Speed Drive Upgrade: This project involved replacing a fluid coupling type drive for a large stock pump with an electronic variable speed drive. The total cost of this project was around $450,000 and is expected to save around 2700 GJ per year of electrical energy. Initial measurements of the energy consumed indicate that this will be achievable along with other significant business savings included in the project from maintenance, waste and downtime reductions. The cost of the project included the supply and installation of a new motor and variable speed drive as well as the necessary spare parts. Drying Process Optimisation: This opportunity considers improvements to a direct gas fired drying system. It involves upgrades and modifications to ductwork, drying hoods and exhaust flows to optimize consistency of the drying process and minimize heat loss from the exhaust system and drying hoods. This project has been split into two stages with the Stage 1 - ductwork upgrades and modifications being completed at a total cost of $55,000. Investigation into Stage 2 work will continue in 2009. The estimated energy saving from the total project is in the order of 20,000 GJ per year of natural gas. Update: Vacuum Pump Optimisation: This opportunity relates to optimising the operation of multiple vacuum pumps on two key production lines. Shutting one pump was previously trialled the first production line and was not successful as product quality and output could not be maintained. Consequently shutting one of the vacuum pumps was attempted on the second production line and has been very successful. This line is now able to run at the required production output and quality standards for about 70% of the grades manufactured. The energy savings from this opportunity is approximately 2000 GJ/annum of electrical energy. Further work on the vacuum system for this line is planned for early 2010 and it is expected that similar savings will be achieved. Air Conditioning Economiser System: One of the production areas uses a large chilled water system for area cooling as well as some process equipment cooling. It was identified that significant energy savings could be made by adding an economiser mode to the system. This would be achieved by introducing outside air into the area when the external ambient temperature was favourable. This will reduce the resultant temperature due to the high internal heat load from process machinery. It is estimated that this could reduce the running time for the chiller by up to 40% resulting in energy savings of approximately 1500 GJ/annum of electrical energy. Engineering and design work for this project is presently underway and implementation is planned for mid 2010. Investment in new technologies or new configurations of technologies not used before Electric motors – variable speed drives Investment in the same but more efficiency technology; Improvement in process control Dryer Improvement in process control Electric motors – pumps Investment in new technologies or Electric motors – HVAC and new configurations of refrigeration equipment technologies not used before Compressed Air System Pressure Reduction: This opportunity identified that the plant's compressed air system runs at a higher pressure than is be required for most process equipment. Work has Electric motors – air been carried out to eliminate restrictions in compressed air pipe work that would cause pressure drops and extended trials have successfully been Improvement in process control SCA Hygiene Australia Pty Ltd 2009 conducted at reduced operating pressures. These trials identified that it is possible to operate the plant with the compressed air system pressure compressors reduced by 10%. Following a final confirmation that all process machines are able to operate at the lower plant air pressure this opportunity will be implemented on a permanent basis in the first quarter of 2010 and will save approximately 1000 GJ/annum in electrical energy. Disclaimer. The material contained in this document is general in nature. Details of energy efficiency opportunities have been sourced from corporations' Energy Efficiency Opportunities public reports and is made available on the understanding that the Commonwealth is not thereby engaged in rendering professional advice. Before relying on the material in any important matter, users should carefully evaluate its accuracy, currency, completeness and relevance for their purposes, and should obtain any appropriate professional advice relevant to their particular circumstances. Information collated in this document by the Commonwealth is done so for convenience and does not constitute endorsement of the material within corporations' public reports or any associated organisation, product or service. Corporations' complete public reports can be accessed at www.energyefficiencyopportunities.gov.au. This work is licensed under a Creative Commons Attribution 2.5 Australia licence. To the extent that copyright subsists in third party quotes and diagrams it remains with the original owner and permission may be required to reuse the material. This work should be attributed as the Energy Efficiency Opportunities Significant Opportunities Register. Inquiries regarding the licence and any use of the Energy Efficiency Opportunities Significant Opportunities Register are welcome at: Manager, Energy Efficiency Opportunities, Energy and Environment Division, Department of Resources, Energy and Tourism, Level 9, 10 Binara Street, Canberra, ACT 2601.