JHARKHAND BIJLI VITRAN NIGAM LTD CIN –U40108JH2013-SGC001702 Engineering Building, Dhurwa, Ranchi Fax # - 0651- 2400483 email. cesp.jseb@rediffmail.com e-procurement NIT No.492/PR/JBVNL/2015-16. For MANUFACTURING, TESTING & SUPPLY OF WHOLE CURRENT A.C.SINGLE PHASE TWO WIRE SMART ENERGY METER OF ACCURACY CLASS 1.0 WITH TWO WAY COMMUNICATION FACILITY SUITABLE FOR ADVANCE METERING INFRASTRUCTURE (AMI), PEAK LOAD MANAGEMENT (PLM), AND DEMAND RESPONSE (DR). Quantity: 2,00,000 (two lacs) Nos. Due date of NIT 28.01.2016 at 11.00 hrs. Date/time for download of Date/time for submission of bids documents bids From 05.01.2016 , 18 hrs. upto 23.01.2016 , 18 hrs. Price of tender document: Rs.10,000 (Ten Thousand) only. FIRM price C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 1 of 33 JHARKHAND BIJLI VITRAN NIGAM LTD CIN –U40108JH2013-SGC001702 Engineering Building, Dhurwa, Ranchi Fax # - 0651- 2400483 email. cesp.jseb@rediffmail.com e-procurement NIT No.492 /PR/JBVNL/2015-16 General Terms and Conditions for Submission of Tender for Supply of Materials 1. Online tenders are invited from reputed and experienced manufacturers only having adequate manufacturing & testing capacity, best facilities and capability only for supply of WHOLE CURRENT A.C.SINGLE PHASE TWO WIRE SMART ENERGY METER OF ACCURACY CLASS 1.0 WITH TWO WAY COMMUNICATION FACILITY SUITABLE FOR ADVANCE METERING INFRASTRUCTURE (AMI), PEAK LOAD MANAGEMENT (PLM), AND DEMAND RESPONSE (DR) as per specifications attached at Annexure ‘B’. Offers of manufacturers who have no past experience and adequate manufacturing capacity of the tendered item may not be considered valid and may be rejected. Purchase preference will be given to manufacturing unit of Jharkhand State as per Jharkhand Procurement Policy, 2014. 2. Eligibility criteriai) The bidder should be Indian meter Manufacturer only. ii) The bidder must possess bureau of Indian Standard Certification (ISI mark) for meter manufactured in India. iii) The bidder must possess valid ISO 9001:2008 certification for meter manufacturing, ISO 27001:2005 for information security management system & ISO 14001:2004 for environmental management system. iv) Bidder should have CMMI level 3. Certificate of the same shall be enclosed with the bid. v) The bidder should have valid electrical license of state of Jharkhand at the time of installation. . 2) Quantity: 2,00,000 (two lacs) Nos. (Actual Quantity may Increase or Decrease) 3) The online Tender should be submitted in the prescribed enclosed proforma only in two parts i.e. (Technical & Commercial Part) and (Price Part) in two separate folder. 4) Both parts of the tenders will be submitted upto 18.00 hrs on 23.1.2016 in the website Jharkhand tenders.gov.in and the Part – I will be opened on 28.01.2016 at 11.00 hrs. The undersigned may extend the due date of opening of Part – I with intimation to all tenderers. Price part should only be uploaded in price part-II folder only failing which offer shall be rejected. Please note that the bidder should submit the two samples meter with box with the bid. The online Price Part (Part–II) of those tenderers whose offers are found technically and commercially acceptable will be opened later on. 5. No offers/ tenders will be accepted after due date and time. The desirous tenderers can download tender documents including terms and conditions, BoQ and technical specification from website of jharkhandtenders.gov.in. Original copy for payment of tender documents Rs. 10000/- only (non-refundable) in shape of demand draft C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 2 of 33 issued by Nationalized Bank/Schedule Bank in favour of NIGAM LTD, JHARKHAND BIJLI VITRAN payable at Ranchi must be submitted upto 18.00 hrs. on 27.1.2016 in the Office of Chief Engineer (Stores & Purchase),JBVNL, Ranchi If original copy of tender fee not submitted by bidder on above mentioned due date and time then tender will not be considered. NOTE:- Tender cost / EMD sent through speed post/ courier will not be accepted. 6. Earnest money: a) Tender must be accompanied with an earnest money for Rs. 02 Crores (Rs. Two Crores) only for the offered quantity, unless exempted from such deposit, failing which the tender will be out rightly rejected. b) The earnest money should be deposited in the form of Bank Draft / Bank Guarantee of any Nationalized Bank, valid for 180 days from date of opening of tender, drawn / issued in favour of JHARKHAND BIJLI VITRAN NIGAM LTD, payable at Ranchi Engineer (Stores & Purchase),JBVNL, Ranchi in the Office of Chief The original copy of EMD not submitted by bidder on above mentioned due date and time then tender will not be considered. NOTE:- EMD sent through speed post/ courier will not be accepted. c) Original copy of the Demand Draft / Bank Guarantee must be submitted upto 18.00 hrs. on 27.01.2016. d) Earnest money deposited by firms against any other tender of the Nigam/ or of this office will not be considered as earnest money for the present tender under any circumstances. e) f) g) No earnest money will be accepted after opening of the tender. No interest on the earnest money deposited by the tenderer will be payable by the purchaser. State unit of Jharkhand must submit copy of their registration certificates of manufacturing of tendered item upto 18.00 7. hrs. on 27.01.2016. Exemption: The tenderers of following categories are exempted from deposit of earnest money subject to the conditions laid down below: a) The firm registered with DGS&D for manufacture of the item for which tenders are to be submitted and the registration certificate should remain valid at the time of submission of the tender and during contract period. The tender in such case shall be accompanied with a certified photo state copy of the valid registration certificate failing which the tender shall be rejected. The monetary limit should be more than Rs. 100 crores (Rs. One hundred Crores) as mentioned in the DGS&D certificates, failing which the exemption will not be applicable & offer will be rejected. b) The State Govt./ Govt. of India undertaking. c) Firms registered with NSIC under single point registration scheme for manufacture of the item, provided that certificate is valid on the date of tender and during the period of delivery. The monetary limit should be more than Rs. 100 crores (Rs. One hundred C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 3 of 33 Crores) as mentioned in the NSIC certificates, failing which the exemption will not be applicable & offer will be rejected. d) The earnest money will be liable to be forfeited on revocation of tender before the validity of the quotations expires or on refusal to enter into a contract after the award (LoI/PO) is made to the tenderer. e) SSI unit of Jharkhand, registered with Department of Industries, Govt of Jharkhand / Industrial Area Development Authority, Govt of Jharkhand, for tendered item, valid on the due date of tender and during the period of contract. SSI unit of Jharkhand must submit self attested or notarized valid copy of SSI registration certificate for tendered item, issued from department of Industries/ Industrial Area Development Authority, Govt of Jharkhand, failing which, they will not be considered SSI unit. The tender in such cases should be accompanied with self attested or notarized copy of the valid registration certificate, failing which tender shall be rejected. NB: Aforementioned certificate must accompany with documentary evidence for its validity on the due date of the tender, failing which tenders will be rejected. As the documents mentioned herein above must be valid during the period of supply/ delivery also. Copy of the same shall be produced at the time of submission of bill for payment. 8. Security Deposit and Contract Agreement: The successful tenderers shall have to deposit security money @ 2% of the ordered value at the time of executing the contract agreement. However, the SSI units of Jharkhand having permanent valid registration with Department of Industries /Industrial Area Development Authority (IADA) Govt. of Jharkhand for the manufacture of the item will be required to deposit security money of the ordered value as per Jharkhand Procurement Policy’2014. In no case, exemption from security money will be granted. Security money to be deposited may be adjusted from the earnest money deposited in shape of cash/ Bank Draft only, if any. The amount of security money shall be deposited with AO,JBVNL, Ranchi in cash or in shape of Bank Draft/ Bank Guarantee (of any Nationalised Bank) will be treated as a performance guarantee. The security money thus deposited will be released after completion of satisfactory supply of full ordered quantity of materials, expiry of guarantee period. Payment will be made only after depositing the security money and execution of contract agreement. The bid security may be forfeited: a) If the Bidder: i) Withdraws its bid during the period of bid validity specified by the bidder in the bid form, or b) In the case of a successful bidder, if the bidder fails: i) to sign the contract, or ii) to furnish the required performance security. 9. Annual turnover: Annual turnover of the firm for preceding three financial years must be at least Rs. Rs. 30 crores (Rs. Thirty Crores) only Certified / Attested copy of annual A/C (Balance sheet, profit & loss A/c etc) from practicing chartered Accountant or both for financial year C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 4 of 33 2012-13, 2013-14 & 2014-15 must be submitted along with the offer to establish financial credibility of the bidders. In absence of the above credentials, offer may be rejected. However, SSI units of Jharkhand are exempted from annual turnover clause. 10. Delivery: The Commencement of delivery period shall be reckoned from the date of issue of PO. The proforma of schedule of delivery (annexure-‘H’) is enclosed with the tender. Tenderers shall fill up the proforma giving a clear schedule of delivery. Early delivery may be preferred. 11. Penalty / Liquidated damage: The delivery of goods will be guaranteed under liquidated damage clause. Our usual terms of LD-clause is ¼% (quarter percent) of the value of the materials delayed per week or part thereof subject to maximum 5% (Five percent). The above item will be deemed to have been delivered only when all its component parts are also delivered in stores of JBVNL. If certain components are not delivered in time the equipment/item will be considered as delayed till such time as the missing parts are delivered. 12. Price: Rate in figures and in words must be quoted in the enclosed proforma of price part on FIRM price, subject to any statutory change in due course of time, indicating therein Ex-factory price, freight element up to destination, element of Excise duty, sales tax and other charges. The Ex-works price shall be quoted after considering benefit under CENVAT or any other scheme to be retained by the supplier. The materials are to be dispatched to various destinations in Jharkhand as may be required. The responsibility of safe delivery will rest with the supplier. If the price elements are not quoted separately as indicated above, the tender will be liable for rejection. Freight element will include loading, unloading, packing and forwarding complete. If any other taxes are levied or reduced by the Govt. the same will be added or subtracted respectively to the landed cost for evaluation of the tender. If Excise Duty, Sale Tax / VAT or Entry Tax is not quoted separately or proof of exemption of the same is not given, the relevant duty and / or tax at the maximum rate will be added to evaluate landed cost of the bidder. Arithmetical errors will be rectified on the following basis: If there is discrepancy between unit price and the total price i.e obtained by multiplying the unit price and quantity, the unit price shall prevail and total price shall be corrected. If the bidder does not accept the correction of errors, his bid will be rejected & EMD will be forfeited. If there is a discrepancy between words and figures, the amount in words shall prevail. 11) Routine Tests:- The successful bidder will have to furnish routine test report of the meters and meter boxes expected to be supplied. The tests that will be conducted on the materials shall be stated in the tender. It is pertinent to note that each unit of material (meter and meter box) shall be subjected to the tests prescribed in the relevant standard (latest edition) before supply is affected. Untested materials shall not be accepted. 12) Type-test:- The tenderer shall also submit applicable type test report of the tendered item from any NABL(ERTL/YMPL/CPRI/ERDA) accredited laboratory, failing which the tender shall be rejected out rightly. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 5 of 33 13) BIS Licence certificate:- The bidders shall have to submit copy of BIS license certificate for tendered item which should be valid on the due date of tender, failing which the tender will be rejected out rightly. 14) Calibration:- The meters shall be factory calibrated and sealed suitably before dispatch as explained in the Guarantee Technical Particulars. Guaranteed particulars:- The performance particulars as required in the specification should be sent along with the tender. Other details not specified may also be given. 15) Past experience:Bidders must have supplied at least 5 (five) lacs static energy meters with meter box, LCD display and communication Port facility within Financial Year 2012-13, 2013-14 & 2014-15. Bidders must submit detailed list of executed purchase orders along with their copies for the same item clearly indicating PO # and date with name of material and its quantity & value and also submit name and address of the ordering authority issued in at least any one of the last 3 (three) years from the due date of tender, failing which the offer may be rejected. The bidder should also submit performance certificate if any, indicating period of supply, quantity and value for the tendered item issued during the above period with the offer. On placement of order, Bidder has to supply full ordered quantity, failing which the bidder shall not be eligible to participate in forth coming tenders, for a period of at least one year from the date of issue of such purchase order. Past performance of the material supplied earlier by a bidder to erstwhile JSEB may be taken in to account while finalizing this tender. 16) Deviation from specification:- Deviation from the specifications of the NIT, if any, should be specified/stated in the offer in the deviation sheet enclosed with this BoQ. In case there is no deviation, it must be declared clearly in the deviation sheet (Annex-‘F’). 17) Income Tax and Sales Tax:Attested copy of sales tax clearance certificate up to 31.3.2015 should accompany the tender, failing which the tender may be rejected. State and Central Sales Tax registration Number of the tenderer should also be stated. Self declaration certificate with a declaration separately that nothing is due to Income Tax Department & payment of Income tax is up-to-date. 18) Drawing and Design of item:- The detailed dimensional drawing to scale will have to be furnished with the tender. Incomplete tenders, tenders not containing full details, technical particulars, dimension, literatures, test certificates, delivery period etc are liable to be rejected. 20) Terms of payment:- a) 100% payment will be made by Sr. Manager/ Accounts Officer, JBVNL,, Ranchi on submission of 5% Bank Guarantee from any Nationalised Bank of ordered value on non-judicial stamp Rs. 60/(Rupees sixty) only valid for Guarantee period as per cl-22 and on receipt of SRV duly signed by the concerned consignee after receipt of the materials in good condition along with approved routine test certificate and duly filled check list for payment from Stores & Purchase wing. b) If the Bank Guarantee of any Nationalised Bank is not furnished, payment will be made after deducting 5% of the total order value from the first or consecutive bills after receipt of the materials in good condition along with approved routine test certificate and duly filled check list for payment from Stores & Purchase wing. The deducted amount will be kept back as performance guarantee and will be released after successful completion of guarantee period. For the above modes of payment ¼ % (Quarter percent) rebate will be deducted from the exfactory price of the materials. However, Excise Duty part will be paid only after production of documentary evidence issued by Excise Department of their jurisdiction. Sales Tax will be paid on C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 6 of 33 submission of upto date income tax and sales tax deposit certificate by competent authority of respective department. The paying officer will accept the Bank Guarantee after confirmation from the concerned bank. Supplier must submit documentary evidence in support of claim for exemption from any tax or duty if any. The 5% amount / B.G. will be paid after expiry of Guarantee period. Entry Tax, if any, shall be reimbursed based on documentary evidence. 21) Bank Guarantee for repairs of equipments / materials at the supplier’s works: In case the equipment fails, within the guarantee period and the same is required to be taken back to the supplier’s factory, the same shall be covered up by suitable Bank Guarantee of any Nationalised Bank of equivalent cost of equipment for period required for replacement. Further Bank Guarantee shall be furnished by the supplier within one week’s time on hearing from the consignees. He shall not lift the damaged/rejected equipment from our store unless the approval of acceptance of Bank Guarantee is received from our Sr. Manager/ Accounts Officer, JBVNL, Ranchi. 22) Guarantee:In the event of any defect in the equipment/materials arising out of faulty design inferior quality of raw materials and bad workmanship within a period of 5 (five) year from the date of receipt of material at purchaser’s stores, the manufacturer shall guarantee to replace or repair the defect to the entire satisfaction of the purchaser free of cost. However, the manufacturer fails to do so within a reasonable time, the purchaser reserves the right to defect repair or replacement and recover charges for repair or replacement from the manufacturer. 23) Inspection:- The manufacturer should notify the purchaser well in advance (minimum 15 days) about the program for testing of complete equipment/materials as per terms of order along with necessary work test certificate so that the purchaser can send his representative to witness the test on the mutually agreed date. The purchaser reserves the right to reject either raw materials or finished product found to be not complying with the requirement of the specifications. The manufacturer shall extend all possible facilities for inspection and testing at any time during the course of manufacturer and after offering for inspection and testing of the finished product for which no extra cost shall be charged. 24) Dispatch:a) The manufacturer after receiving dispatch clearance from the respective inspection Authority/Purchaser shall deliver the equipment/materials suitably packed to stores any- where in the state of Jharkhand. The materials should be suitably packed and the consignment is to be delivered as per dispatch instruction to be communicated in due course, after inspection of materials/equipment. The manufacturer shall notify the purchaser and consignee officer about value of consignment, weight and dimension of consignment by telegram and copy will be submitted by registered post on the strength of which the consignment can be taken delivery at destination. b) Materials/equipment as per dispatch clearance shall have to be dispatched within the stipulated period of the order and inspection of further lots against the said order will be arranged after receipt of confirmation regarding physical delivery to our stores by the inspection authority. 25) Re-inspection Charge: Re-inspection charges as applicable shall be leviable in case it is found at the time of inspection at the works of the bidder that: a) The material was not ready for inspection and the inspection notice given by supplier was fictitious. b) Quantity offered for inspection is short by more than 50% from the quantity in the inspection call. c) Inspection is not arranged / not got carried out due to any reason an account of supplier. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 7 of 33 d) Material is found not conforming to provisions of Purchase order/ GTP/ relevant BIS and thus rejected by inspecting officer. Or Manufacturing defects are observed during physical/ visual inspection/ checking. Or f) Quantity of item not found as per provisions of Purchase order. 26) Packing:e) The materials/equipment shall have to be packed suitably in transportable lots as indicated in the technical specification. If the materials/equipment are found to be acceptable after inspection and testing, the same shall have to be suitably sealed by our inspecting officers. Due care shall have to be ensured during transportation to keep the packing and seal intact for acceptance by consignee stores. All necessary Assistance in this regard shall be extended by the party to the Boards inspecting team free of cost. The party shall have to replace the entire lot at their cost if any discrepancy/defect is found in the materials/equipment delivered to the consignee stores. The Board reserves the right to take any penal action what-so-ever without any further reference to the manufacturer for causing any loss to Board. 27) Minimum Quantity: The requirement mentioned in the tender notice and general conditions is tentative and is subject to increase or decrease at the time of finalization of the tender. The tenderer must quote minimum 60% of the tendered quantity. Tenders with lesser quantity will not be entertained. 29) Penalty / Liquidated damage: The delivery of goods will be guaranteed under liquidated damage clause. Our usual terms of LD-clause is ¼% (quarter percent) of the value of the materials delayed per week or part thereof subject to maximum 5% (Five percent). Tendered item will be deemed to have been delivered only when all its component parts are also delivered in stores of JBVNL. If certain components are not delivered in time the equipment/item will be considered as delayed till such time as the missing parts are delivered. 30) Validity:Validity of the tender should be for a period of at least 180 days. 31) Risk Purchase:The time of delivery or physical dispatch stipulated in the purchase order shall deemed to be the essence of the contract and if the manufacturer fails to delivery or dispatch any consignment within the period prescribed for such deliver or dispatch in the said purchase order/contract/letter of intent, the purchaser shall be entitled to purchase such consignment or if not available, the best and nearest available substitute elsewhere on the account and at the risk of the manufacturer or to cancel the contract and manufacturer shall be liable to compensate for any loss or damage which the purchaser may sustain by reason of such failure on the part of the manufacturer. 32) Acceptance of order:The purchaser will communicate acceptance of tender to the successful bidder by a letter of intent/formal order. In case of letter of intent, formal order will follow as early as possible after receipt of unequivocal acceptance of LoI/PO. The successful tenderer shall communicate the acceptance of the order so as to reach the purchaser within a week from the date of issue of the said letter of intent/Purchase order. If the acceptance of order is not received within the above period, then the earnest money against the tender is liable to be forfeited. 33. Extension Order: In the event of an order being placed on the tenderer, the tenderer requested to give his concurrence that he is willing to accept additional order on the same terms and conditions if the extension order is placed by Nigam within 12 (twelve) month from the date of acceptance/ placement of order. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 8 of 33 34) Accuracy:The accuracy of the meters shall not exceed the permissible limit of accuracy as per standards for a period of 10 (ten) years. In case any drift is noticed which is beyond the permissible limits the bidder shall recalibrate the meters for correct accuracy and if re-calibration is not possible, the meter shall be replaced by a new meter without any extra cost. 35) Tenderers are required to intimate the deviations from the guaranteed technical particulars in the enclosed deviation sheet. In case there is no deviation, it should be mentioned clearly in the deviation sheet. The tender will be liable to be rejected if submitted with blank deviation sheet. 36) Jurisdiction of Court: The civil court Ranchi shall alone have an exclusive jurisdiction to decide any difference/ dispute/ cases for and against JBVNL/ Contractors/ Suppliers arising out of or in respect of the NIT, or contract agreement, or Purchase order. 37) The Board reserves the right to cancel full or part of the awarded contract without assigning any reason of those firms which will be found defaulter for delay in supply of materials or his supply or his supply sub-standard quality of the materials. 38) The bidders should submit self-declaration Certificate, that the firm is not blacklisted from Central Govt / State Govt / Central or State Govt. undertakings/ Public Sector Undertaking etc. for the tendered item and also submit declaration Certificate that the firm is not related to any persons employed in the Board or his/her close family member/blood relations / proxies. 39) Governing Language: The Contract shall be written in English and shall be interpreted in accordance with the laws of the union of India. 40) No documents submitted by bidders after opening of the tender (Part-I) on their own shall be accepted, unless and until asked for. 41) Sample:Two nos. sample meter alongwith meter box conforming to this specification duly sealed along with the routine test certificates shall be submitted with techno-commercial bid free of cost. The above sample meter and meter box shall be tested in purchaser’s meter testing lab/ independent test lab in presence of firm’s representative & will not be returned to bidder. The sample shall be complete in all respects and no deviations shall be allowed for technical qualification. In case sample does not conform to the specifications, the financial bid of offer shall not be opened. 42) Training:- The successful bidders will provide training to employee of the Nigam at their various Laboratories spread through out the state of Jharkhand to the entire satisfaction of the purchaser. Electrical Superintending Engineer (Purchase) JBVNL, Ranchi. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 9 of 33 Details of Annexure The bidders are required to submit their bids row wise information as per GTP and other information as per enclosed annexure which is detailed below failing which, the bid shall be rejected1 Annexure A Eligibility criteria and Instruction to bidders 2 Annexure B Technical specification of 3 phase whole current smart meter with polycarbonate meter box and DCU 3 Annexure C Tender proforma for part-I (Technical and Commercial) 4 Annexure D Tender proforma for part-II (Price Bid) Annexure E Guaranteed Technical particular of meter and DCU to be 5 6 filled by bidders Annexure F Schedule of deviation from specification. The bidder shall mention clearly in case there is no deviation. 7 Annexure G Details of testing facility available with the bidder 8 Annexure H Monthly delivery schedule 9 Annexure I Self declaration certificate that the firm is not Black listed with any state utility in India 10 Annexure J Self declaration certificate that payment of CST/VAT is up-to-date 11 Annexure K C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Declaration certificate regarding blood relation Page 10 of 33 Annexure-‘A’ Eligibility criteriaThe prospective bidder must qualify all of the following requirements to be eligible to participate in the bidding. Bidders who meet following requirements will be considered as successful bidder and management has a right to disqualify those bidders who do not meet these requirements. i) The bidder should be Indian meter Manufacturer only. ii) The bidder must possess bureau of Indian Standard Certification (ISI mark) for meter manufactured in India. iii) The bidder must possess valid ISO 9001:2008 certification for meter manufacturing, ISO 27001:2005 for information security management system & ISO 14001:2004 for environmental management system. Iv) Bidder should have CMMI level 3. Certificate of the same shall be enclosed with the bid. v) The bidder should have valid electrical license of state of Jharkhand at the time of installation. vi) The bidder must have NABL accredited laboratory and in operation. Documentary evidence of the same shall be submitted alongwith the bid. Electrical Superintending Engineer (Purchase) JBVNL, Ranchi. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 11 of 33 Annexure-‘A’ Instructions to bidders 1.0 Scope:The specification covers the design, manufacturing, testing of AC whole current 1 phase Smart Energy Meter with bidirectional communication facility for measurement of energy. The meter shall be suitable for Advanced metering Infrastructure (AMI), Peak Load management (PLM) and Demand Response. The meter shall communicate with Data Concentrator Unit (DCU) or Meter Head End (MHE) over RF mesh (license free band) /PLCC/GPRS. The Smart meter shall be DLMS/COSEM/ICS compliant and shall also support open and interoperable data collection architecture. 2.0 Requirement:2,00,000 Nos (Two lacs Nos.) 3.0 The bidders are expected to provide their clause-by-clause submission for conformance or for nonconformance. The bids received without conformance statement will be rejected. 4.0 Service Guarantee:In case the equipment fails, within the guarantee period and the same is required to be taken back to the supplier’s factory, the same shall be covered up by suitable Bank Guarantee of equivalent cost of equipment for period required for replacement. Further Bank Guarantee shall be furnished by the supplier within one week’s time on hearing from the consignees. He shall not lift the damaged/rejected equipment from our store unless the approval of acceptance of Bank Guarantee is received from our Sr. Manager/AO,JBVNL, Ranchi 5.0 In case of any contradiction/confusion, the parameters considered fit in the interest of the Nigam, shall prevail. 6.0 Specification of offered meter must conform the technical specification of the NIT, failing which offer shall be rejected. 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 Tenderer has to accept the Guarantee clause, penalty clause, payment terms and security clause as per the terms and conditions of the tender otherwise tender will be considered as invalid. The offers, which are not kept valid for acceptance, for at least 180 days from the date of opening of tenders, will be rejected. Conditional/ Incomplete tenders which do not contain full details filled guaranteed technical particulars, literature type test certificates, performance report, price of all equipments, delivery period etc. will be rejected, GTP must be filled up item wise. Incomplete or mentioning ‘as per ‘IS’ shall not be acceptable. The prices are specifically asked to be submitted as FOR destination and if not so furnished, the tender shall not be considered as valid and will be rejected. Online tender, which is not submitted in the Board’s prescribed proforma shall be rejected. Any additional particulars can be furnished in the accompanying letter of Statement. Online tender received in this Office after the due date and time shall be rejected. Prices must be indicated bold in figure and Words failing which the tender may be rejected. Tenderers have to quote FIRM price only. Electrical Superintending Engineer (Purchase) JBVNL, Ranchi. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 12 of 33 ANNEXURE-‘B’ Technical Specification for 1 phase whole current Smart Meter with polycarbonate meter box and DCU C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 13 of 33 TECHNICAL SPECIFICATIONS FOR WHOLE CURRENT A.C.SINGLE PHASE TWO WIRE SMART ENERGY METER OF ACCURACY CLASS 1.0 WITH TWO WAY COMMUNICATION FACILITY SUITABLE FOR ADVANCE METERING INFRASTRUCTURE (AMI), PEAK LOAD MANAGEMENT (PLM), AND DEMAND RESPONSE (DR). 1. SCOPE The specification covers the design, manufacturing, testing of AC whole current 1 phase 2 wires Smart Energy Meter with bidirectional communication facility. The meter shall be suitable for Advanced Metering Infrastructure (AMI), Peak Load management (PLM) and Demand Response. The meter shall communicate with Data Concentrator Unit (DCU) or Meter Head End (MHE) over RF mesh (license free band) /PLCC/GPRS. The Smart meter shall be DLMS/COSEM/ICS compliant and shall also support open and interoperable data collection architecture. Basic Features of Smart Meter 2. Bidirectional Communication Load limiting switch /relay Tamper event detection, recording and reporting Power event alarm such as loss of supply, High voltage. General Standard Applicable for Meters: Unless otherwise specified elsewhere in this specification, the performance and testing of the meters shall conform to the following Indian/International Standards and all related Indian/International standards to be read with up to-date and latest amendments/revisions thereof: Sl. No. 1 Standard No. IS 13779 with latest amendments 2 CBIP- Publication 325 3. CBIP Technical report no. 111 4. IEC-62052-11 5 IS 15884 3. Title AC Static Watt-hour Meters, class 1&2 Standardization of AC Static Electrical Energy Meters Specification for common Meter Reading Instrument Electricity metering equipments (AC) - General Requirements & test conditions Part 11. metering equipments Alternating Current direct connected Static Prepayment Meters for Active Energy (Class 1and 2) Communication Feature Communication with Data Concentrator Unit (DCU)/Meter Head End - Meter shall have ability to communicate with Data Concentrator Unit (DCU) or Meter Head End (MHE) over RF mesh (license free band) /PLCC/GPRS in secure manner. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 14 of 33 4. Remote Load control facility Meter shall be fitted with a remotely settable relay and switch/contactor which will cut off the load whenever the drawl is more than limit for a continuous period of 1 minute with suitable audio/visual indication of load cut-off. 5. Applicable Standards, Climatic Conditions, Constructional Requirements, Ratings, Starting Current, Supply System, Quantities to be Measured / Monitored, Anti Tamper Features, Accuracy & Limits of Errors, Running at no Load, Test Output Device, Name Plate and Marking, Guarantee and other Features As per Annexure- 1 6. TYPE TESTS After successful design and manufacturing meter shall be type tested as per IS: 13779 (latest version) & IS 15884 (for testing of connect/disconnect feature) in a third part NABL accredited lab. 7. DESIGN Voltage circuit, sealing arrangement, terminal block, terminal cover and nameplate etc. shall be in accordance with IS-13779 (latest version). The meter shall be compact and reliable in design, easy to transport and immune to vibration and shock involved in transportation and handling. The construction of the meter shall ensure consistent performance under all conditions especially during dust storm/heavy rains/very hot weather. The insulating material used in the meter should be non-hygroscopic, non- aging and of tested quality. The terminal block and meter case shall have safety against spread of fire. They shall not be ignited by thermal overload of live parts in contact with them as per the relevant IS- 13779. Meter shall have proper fixing arrangement. 8. ELECTRONIC COMPONENTS The meter shall be manufactured from high accuracy and reliable Surface Mount Technology (SMT) components. The supplier should submit the details of source/agencies from whom purchase of various components of meters used by them. . C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 15 of 33 Annexure-1 Particulars Specification Applicable Standards Reference Voltage The meters shall comply with IS 13779 for all requirements except for those parameters which have been specifically mentioned to be otherwise in this specification. 240 V (-40% to +20%) Single Phase Current Rating 10-60A Starting Current 0.2% of Ib Accuracy Class 1.0 as per IS 13779 for Active Energy Limits of error As per IS 13779 Operating Temperature range Humidity As per IS 13779 Frequency As per IS 13779 Influence Quantities As per IS 13779 Constructional Requirements Power Consumption of meter excluding communication module/connect/ disconnect switch Current and Voltage Circuit Running at No Load As per IS 13779 Test output device As per IS 13779 Name Plate and Marking As per IS 13779 Meter Display Min 6 digit LCD Display with legends to identify parameters on meter Instantaneous-V, I , kW, Power factor Cumulative - Active Energy, Current Demand in kW and kVA Billing parameters: Previous Month’s MD in kW, kVA and kWh,. Cumulative Number of Tamper Count Signed Average Power Factor (Lead / Lag) Logging of quality of supply events like power on/off, over/under voltage Setting of Under/Over Voltage Should have Maximum Demand registers kW and kVA with integration period 15 minutes. Resets should be automonthly or through communication command. 35 days data to be recorded with 30 minutes integration period/17 days data to be recorded with 15 minutes integration period for Active Energy, Average Voltage, Average Current. In addition cumulative mid night kWh (00.00 Hrs) shall also be recorded for 45 days. Should support 4 Time of day tariff registers with As per IS 13779 As per IS 13779 As per IS 13779 As per IS 13779 Parameters to be measured Power Quality Information Maximum Demand Load Survey/Interval Data Time of Use C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 16 of 33 programmable time zones and storage of billing parameters. LED/LCD Indicators LED indicator for pulse/kWh. LED / LCD Indicator for Tamper, Disconnection, Earth leakage. Tamper/Event recording A total of last 50 events considering all tampers defined must be detected and logged as tamper events on first in first out basis along with date & time of occurrence and restoration, total tamper counts with tamper identification. Snapshot of kWh, V and I shall be recorded along with the following tamper events all of which must have date and time stamp: Meter Cover open detection - First instance Magnetic Interference Utility shall be able to select what tamper events to be communicated back to HES as and when they occur. These tamper events shall be sent as an alarm to the HES which shall store the same in its database. Alarm for power on/off, Over Voltage, Over Current, Mal functioning of relay shall be generated and communicated to the MDAS. Single Phase Meter should have two measuring elements one in phase and other in neutral path. Alarm switch / contactor Measuring Elements Anti-Tamper features Load Control As per CEA Regulations Meter shall be remotely settable to support. Relay for connection/disconnection: Phase and Neutral Disconnection on the following conditions: i) Over current ii) Load Control Limit iii) Pre-programmed Tamper conditions (Meter Cover open detection, Magnetic Interference) iv) Disconnect signal from Control Centre such as balance unavailable in case pre-paid facility is availed by consumer. Load Control limits such as maximum sanctioned load, shall be remotely programmable. The disconnection mechanism is as follows: i) It will try to re-connect the load up to 3 times, with 5 minutes interval. ii) if the consumption is still more than the programmed limits, it will lock out and wait for 30 minutes (lock out period). iii) if the consumption is still above the limit , the procedure as defined above in i) and ii) shall be repeated. The number of re-connection attempts, time interval between re-connection and lock-out period shall be programmable as per requirement. Reconnection mechanism: Reconnection shall normally be done from MDAS/HES. In case of failure of communication,/MDAS, reconnection shall be possible through HHU locally and the same shall be password protected. For reconnection mechanism a local reset button shall also be provided on the Smart Meter. Local reset button shall be C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 17 of 33 able to reconnect the load, if load is below the programmed load curtailment limit. There shall be provision for enabling and disabling the functioning of the local reset button by utility through MDAS or HHU through password protect access. Connect/Disconnect feature Programmability Communication RTC & time synchronization Battery Backup Data display facility (manual/Auto) Connect/Disconnect facility to be provided on both the wires i.e. phase and neutral simultaneously. Status of Relay i.e. Connected / Disconnected should be available on display as well as through communication. Connection and Disconnection should also be logged as events. It should be possible to program the parameters limits /values from remote through adequate security mechanism such as device network identity. Once programmed it will be possible for the programmed parameters to come into effect from a certain date & time. Meteorology under such condition must remain intact and shall not be modifiable from remote. The port for local communication and baud rate shall be as per IS 15959. In addition to this the meter will have a provision for an ‘integral modular plug in type’ OR ‘built in type’ Communication Module for NAN (Neighborhood Area Network) i.e. from Meter to Data Concentrator or directly for WAN (Wide Area Network). This Communication Module could operate on Low Power Radio / RF with Mesh/PLC. Different communication technologies shall follow relevant National or International Standard as applicable. Meter shall have RTC with 20 years calendar programmed in the memory and provision for time synchronization. The clock day/date setting and synchronization shall only be possible through password/Key code command from one of the following: a) Hand Held Unit (HHU) or Meter testing work bench and this shall need password enabling for meter; b) From remote server through suitable communication network. Meter shall be supplied with separate battery backup for RTC and for display. Data Display shall have following three modes: 1. Auto Scroll 2. Scroll with Push-button 3. High Resolution (Shall display energy values with resolution of 2 digits before decimal and 4 digits after decimal. Support HAN (Home Automation Network) The meter shall have provision of valid communication port to communicate with In Home Display device (IHDD) Guarantee Meter should be guaranteed against defects arising out of faulty design or workmanship for a period of five and a half years from the date of receipt of consignment or 5 years from the date of commissioning, whichever is earlier. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 18 of 33 Data Concentrator Unit (DCU) The DCU provides the central link between Smart Meters and MDAS, enabling continuous meter read and control. 1. Hardware & Power Supply The installation of DCU shall be suitable for clamp mounting on poles as well as rail mounting on distribution panels (Constructional feature as per TS) Power supply shall be suitable for 3phase, 3x240V phase to neutral, -40% +20%, 50 Hz AC. Power supply shall be terminated on suitable sized MCB to facilitate isolation during in-situ maintenance. DCU shall consume minimum power for its operation and it shall also have rechargeable battery with backup for 1 hour for normal meter reading and for 5 hours to push tamper event and carry out on demand reading and the network health status / connectivity continuity & check. DCU should have feature to send power outage and restoration message to server. DCU shall have built in Real time Clock with battery backup. 2. Configuration, Functionality & Interface DCU shall be able to configure the communication with underlying devices/ nodes/meters. DCU shall pull data from the field devices and push the data at configured intervals to the MDAS. It should also support the MDAS in pulling data from the DCU. The data acquisition (Push/Pull) frequency shall be programmable. DCU shall be capable to prioritize control commands. DCU shall have internal memory for storing interval data DCU shall support on demand read of individual/group of meters. DCU shall push events like tamper, power off to MDAS immediately on occurrence/receipt from field devices/meters3. Communication The DCU shall have provision for modem with SIM slot for supporting Dual-band 850/900/1800/1900 MHz GSM/GPRS module for communication over GPRS or 3G further a valid communication terminal port i.e. RJ45/RS232 for other communication option shall also be provided. DCU modem should support only dynamic IP SIM card. The DCU also shall have Wide Area Network (WAN) connectivity to the MDAS through digital cellular GPRS / 3G communication connection DCU shall periodically monitor meter reads/downstream commands and shall retry and reconnect in case of failed events/reads. During Power Interruption, on restoration of power supply DCU shall establish communication with underlying devices as well as upstream application (MDAS) automatically. The meter communication interface shall be suitable for data transfer for speed of upto 64 kbps. The retry attempts shall be configurable DCU shall keep record of o No of packet failures o Retry o Missed periodic reading o Failure to connect For each meter upto a period of 3 days and update the same to MDAS periodically. Remote Firmware Upgrade: The DCU shall support remote configuration in order to remotely add new features and functions to DCU without having to send person to field. - ESE (Purchase) JBVNL, Hq, Ranchi C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 19 of 33 Annexure – ‘C’ Tender Proforma for Part – I (Technical & Commercial) Sl.no. 1. Parameters Bidders particulars Name & Full address of the tenderer : With Tele.no…………… fax no…….. 2. Name of Materials : 3. Name of Manufacturer : 4. Quantity offered : 5. Whether the F.O.R. destination price has been quoted giving freight element : 6. Whether quoted price is FIRM : 7. Delivery period : 8. Validity of the offer (it should not be less than 180 days) : 9. Acceptance of the terms of payment : 10. Acceptance of terms of security deposit : 11. Details of deviation from the tender Specification, if any : 12. Acceptance of the technical specification of : the materials for which offer is made 13. Guaranteed performance particulars (copies of performance & Purchase order certificates should be attached) : 14. Guarantee : 15. Acceptance of penalty clause : 16. Particulars of payment made for Purchase of : BOQ and specification (Money receipt No. & date should be quoted) 17. Amount of earnest money paid with money : receipt No. & Date 18. Name of place where the materials will be manufactured and will be available for C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 20 of 33 : Page no.of tender documents inspection by the Board’s representative 19. Whether Sales Tax clearance certificate submitted 20. Sales Tax Registration No. 21. Whether proof of financial capability Submitted (Balance sheets & profit & loss A/cs to be submitted) Annual turnover in financial year- 2012-13 Annual turnover in financial year- 13-14 Annual turnover in financial year- 14-15 22. : Yes / No : Yes / No : : Rs. : Rs. : Rs. Average Rs. Details of past performance i) Whether list of past POs executed submitted : 23. List of enclosures : 24. Whether applicable type-test report submitted: i) For Meter ii) For Meter Box Yes / No Type –test report no. From NABL accredited lab. Approved by GoI 25. Acceptance for providing training :- 26 Whether bidder is accepting clause No. 33 (Extension order) of General Terms and conditions of NIT 27. Submission of Declaration Certificate as prescript in NIT: 28. i) Annex- I ii) Annex- J iii) Annex- K iv) Annex- L Remarks : Signature of tenderer with full name Designation:………………………. Seal:……………………………….. Note: Must be filled in Board’s proforma only, Otherwise offer may be liable for rejection. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 21 of 33 Annexure – ‘D’ Tender Proforma for Part – II Price Bid 1. Name & Full address of the tenderer : 2. Name of Manufacturer : 3. Name of Materials : 4. Tender notice no. with due date : 5. Quantity offered : 6. Whether quoted price is FIRM : 7. Unit Landed price Breakup (Tendered item) : a) i) ii) iii) b) Ex-factory price Ex-works price shall be quoted after considering benefit under MODVAT or any other scheme to be retained by the supplier Meter and meter box……………. DCU per lot ………………… Excise duty c) VAT / CST d) Freight (including loading, unloading at stores,: packing forwarding etc.) 8) Insurance – will be arrangement by the Board 9) i) Cost of Installation and commissioning of meter with box and supply of necessary kits per unit ii) Applicable Taxes : 10) Other charges, if any : 11) Entry tax, if applicable : 12) Discount, if any (Conditional discount will not be accepted) 13) Total unit landed price (Smart Meter with Meter Box, DCU, Installation and commissioning of meter with box and supply of necessary kits Remarks: Must be filled in Board’s proforma only, Failing which offer may be liable for rejection. Signature of tenderer with full name Designation:………………………. Seal:……………………………….. Note:- This is proforma of price part and filled up price part should not be uploaded in technical part. 14) C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 22 of 33 Annexure – ‘E-’ Guaranteed technical particular for type-tested A.C. 3 phase 4 wire smart energy meter with meter box of accuracy class-1.0 with two way communication facility suitable for advance metering infrastructure (ami), peak load management (plm) and demand response (dr) and also its installation and commissioning with supply of necessary kits. Single Phase Smart Meter S. N. 1 2 3 Manufacturer Name & address Make Type/Model no 4 Country of origin 5 Applicable Standards 6 Reference Voltage 7 Current Rating 8 Starting Current 9 Accuracy 10 Limits of error 11 12 Operating Temperature range Humidity 13 Frequency 14 Influence Quantities 15 17 18 Power Consumption of meter excluding communication module/ connect/disconnect switch Power consumption for communication Module Current and Voltage Circuit Running at No Load 19 Test output device 20 Name Plate and Marking 21 Meter Display 22 Instantaneous Parameters to be measured 23 Billing parameters to be measured 16 Particulars C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 23 of 33 Response 24 Time period for retaining billing parameters 25 Power Quality Information 26 Maximum Demand 27 Demand integration period 28 Maximum Demand reset 29 Load Survey/Interval Data 30 Time of Use 31 LED/LCD Indicators 32 Tamper/Event recording 33 Alarm switch / contactor 34 Measuring Elements 35 36 Anti-Tamper features Load Control 37 Standard for connect/disconnect relay 38 Connect/Disconnect Indication 39 Programmability 40 Communication Communication Protocol on LPR 41 42 RTC & time synchronization 43 Permissible Drift in RTC 44 Data Retention 45 46 Battery Backup Meter Housing 47 48 Data display facility (manual/Auto) Support HAN (Home Automation Network) 49 50 Guarantee Firmware Upgrade & configuration 51 Maximum size of cable which can be connected at terminal C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 24 of 33 52 Is meter is type tested as per IS 13779/IEC, is the type test report enclosed. 53 Type material use - Meter base - Meter cover -Terminal block -Terminal Cover - Screw Material size 54 Internal Diameter of terminal hole 55 56 57 Centre to centre clearance between adjacent terminals Type of register a) Nos of digits b) Size of numerals Display a) Parameters on auto display b) Parameters on Push butto c) Type of Push Button 58 Life & Type of battery of real time clock 59 60 61 62 Life of battery for display during power off condition Approximate Weight of meter Approximate size of meter Details of ports available on meter Electrical Superintending Engineer (Purchase) JBVNL, Ranchi. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 25 of 33 Data Concentrator Unit (DCU) S.N. Requirement 1.1 Hardware & Power Supply 1.1.1 Enclosure/box of DCU shall be IP55 compliant 1.1.2 The installation of DCU shall be suitable for clamp mounting on poles as well as rail mounting on distribution panels 1.1.3 Power supply shall be suitable for 3-phase, 3x240V phase to neutral, -40% +20%, 50 Hz AC. Capable of withstanding surges & voltage spikes of 6KV as per IEC 61000-4-5 standards. Power supply shall be terminated on suitable sized MCB to facilitate isolation during in-situ maintenance. DCU shall consume minimum power for its operation. It shall also have rechargeable battery with backup for 1 hour for normal meter reading and to push tamper event and carry out on demand reading and the network health status / connectivity continuity & check. DCU should have feature to send power outage and restoration message to server. 1.1.4 1.1.5 1.1.6 DCU shall have built in Real time Clock (RTC) with separate battery backup. Size and weight of DCU 1.2 Configuration, Functionality & Interface 1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 DCU shall be able to configure the communication with underlying devices/nodes/meters. DCU shall pull data from the field devices and push the data at configured intervals to the MDAS. It should also support the MDAS in pulling data from the DCU. The data acquisition (Push/Pull) frequency shall be programmable. DCU shall be capable to prioritize control commands. DCU shall support DLMS/COSEM/IS 15959 protocol for communication to MDAS. DCU shall have internal memory for storing interval data for at least 5 days. DCU shall support on demand read and ping of individual/group of meters. 1.2.6 DCU shall push events like tamper, power off to MDAS on occurrence/receipt from field devices/meters 1.2.7 DCU shall validate communication request to achieve secure communication with MDAS 1.3.1 The DCU shall have provision for modem with SIM slot for supporting Dual-band 850/900/1800/1900 MHz GSM/GPRS module for communication over GPRS or 3G further a valid communication terminal port i.e. RJ45/RS232 for other communication option shall also be provided. DCU modem should support only dynamic IP C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 26 of 33 Response S.N. 1.3.2 1.3.3 1.3.4 1.3.5 1.3.6 1.3.7 Requirement Response SIM card. DCU shall be able to communicate with meters either on RF mesh (license free band) or PLC. DCU shall support only one communication technology towards meter side. The DCU also shall have Wide Area Network (WAN) connectivity to the MDAS through digital cellular GPRS communication. DCU shall periodically monitor meter reads/downstream commands and shall retry and reconnect in case of failed events/reads. During Power Interruption, on restoration of power supply DCU shall establish communication with underlying devices as well as upstream application (MDAS) automatically. The meter communication interface shall be suitable for data transfer for speed of upto 64 kbps. The retry attempts shall be configurable 1.3.8 DCU shall keep record of o No of packet failures o Retry o Missed periodic reading o Failure to connect For each meter up to a period of 3 days and update the same to MDAS periodically 1.3.9 DCU shall be capable to handle data of minimum 50 nos of any type of smart meter(1ph/3ph). DCU shall be able to acquire and send data to MDAS for full capacity (No. of meters/field devices it is designed for) 1.3.10 Remote Firmware Upgrade: The DCU shall support remote firmware upgrades as well remote configuration in order to remotely add new features and functions to DCU without having to send person to field. Electrical Superintending Engineer (Purchase) JBVNL, Ranchi. C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 27 of 33 Annexure – ‘F ’ SCHEDULE OF DEVIATIONS FROM SPECIFICATIONS Sl. No. SPECIFICATION / CLAUSE DEVIATION FROM SPECIFICATION JUSTIFICATION FOR DEVIATION Place: Signature of tenderer Date: Stamp NOTE:- Incase of not mentioning deviations in this deviation sheet & mentioning it elsewhere in the offer except in the tender proforma for part-1 (techno commercial), will be treated as no Deviations. Signature & Seal of Tenderer C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 28 of 33 Annexure – ‘G’ DETAILS OF TESTING FACILITIES Details of testing facilities available Name of Test 1. Remarks Test on Raw Material i. ii. iii. iv. ______________________________ ______________________________ 2. Routine Tests i. ii. iii. iv. ______________________________ ______________________________ 3. Acceptance Tests i. ii. iii. iv. ______________________________ ______________________________ 4. Type-tests i. ii. iii. iv. ______________________________ ______________________________ NOTE:- Incase testing facilities are not available for certain tests, indicate in the remarks columns from which testing House (S) / Institution (S) these tests will be got carried out. Signature & Seal of Tenderer C:\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Page 29 of 33 Annexure – ‘H ’ Proforma for schedule of requirement & specified deliveries for supply of type-tested Whole current A C Three phase Four wire smart energy meter of accuracy class1.0 with two way communication facility suitable for advance metering infrastructure (AMI), PEAK load management (PLM) and demand response (DR) current rating (10-60A) and (20-80A) with meter box and also its installation & commissioning with supply of necessary kits. . DELIVERY SCHEDLUE Offered qty. Monthly delivery schedule for tender quantity NOTE : - 1st month Nil 2nd month 3rd month 4th month 5th month 6th month 7th month 30,000 Nos. 30,000 Nos. 30,000 Nos. 30,000 Nos. 30,000 Nos. 50,000 Nos. 1. Priorities of despatches will be as notified by the Purchaser at the time of pre-despatch inspection. 2. 3. Commencement of delivery period shall be reckoned from the date of the notification of Purchase Order. Bidder who have offered quantity 60% or more but less than full tender quantity then monthly delivery shall proportionally be changed accordingly. The delivery schedule may be proportionally changed (by the purchaser) as per ordered quantity also. Signature of tenderer 4. :\Users\jseb\Desktop\smart meter boq\NIT No. 492.doc Name Address Page 30 of 33 : : : Annexure- ‘I’ SELF DECLARATION CERTIFICATE on Indian Non-Judicial Stamp of Rs. 50/- or more Sri………………………….of M/s……………………………………. with head office……………….. being their authorized signatory, do hereby solemnly affirm and declare that M/s…………………………………….. has not been Black listed/ Debarred by any Organization in India/State/Central Govt. or any of its agencies for the tendered item. If this declaration is found wrong at any subsequent time and further I understand to compensate the JBVNL, for the consequences arising out of wrong declaration. Date: Name & Signature of the Tenderer & Seal Raj(S&P)\784/PR/JSEB/2008-09 Page 31 of 33 Annexure- ‘J’ SELF DECLARATION CERTIFICATE It is hereby declared that payment of Sales tax of M/s ........................................ ..........................................................is update & nothing is due with Sales tax Department. Date: Raj(S&P)\784/PR/JSEB/2008-09 Name & Signature of the Tenderer & Seal Page 32 of 33 Annexure- ‘K’ DECLARATION CERTIFICATE It is hereby declared that none of the persons employed in the Nigam or his/her close family member/blood relations / proxies are related to M/s ……………………… ………………. directly or in directly. Date: Raj(S&P)\784/PR/JSEB/2008-09 Name & Signature of the Tenderer & Seal Page 33 of 33