DETAILED PROJECT REPORT FOR PHASE-II - 2 x 660 MW SUPERCRITICAL COAL BASED POWER PLANT AT SALAYA, GUJARAT TATA CONSULTING ENGINEERS LTD. 73/1, St. MARK’S ROAD BANGLORE – 560 001 JUNE 2010 0 CONTENTS CHAPTER TITLE PAGE NO. NO. I INTRODUCTION 9 II SUMMARY 10 - Purpose 10 - Scope 10 - Recommendations 19 NEED AND JUSTIFICATION OF THE PROJECT 20 - Installed Generation Capacity 24 - Availability of power 24 - Ministry of Power’s Blueprint for Power Development 24 - Justification for the Project 24 SITE FEATURES 25 - Location of Site 25 - Accessibility to Site 25 - Availability of Land 25 - Availability of Water 26 - Coal Supply 26 - Power Evacuation 26 - Environmental Aspects 26 - Transportation of Equipment 27 - 27 III IV V Suitability of site FUEL LINKAGE and TRANSPORTATION TO SITE 1 28 CHAPTER TITLE PAGE NO. NO. VI VII - Type of Fuel 28 - Source of Fuel and Quality 28 - Annual Coal Requirement 28 - Transportation of Coal to the Site and Storage 28 - Fuel Oil System 28 PLANT LAYOUT AND CIVIL ASPECTS 30 - Plant Layout 30 - Site Topography and Grade Level 31 - Station Building 31 - Steam Generator Area and Bunker Bay 31 - Chimney 32 - Soil Profile 33 - Machine foundations 33 - Plant Roads 34 - Fencing / Compound Wall 34 - Sewage Disposal 34 - Landscaping 35 MAIN PLANT EQUIPMENT AND SYSTEMS 36 - Plant Capacity 36 - Unit Size 36 - Turbine Cycle Heat Rate 36 - Steam Generator and Accessories 37 - Steam Turbine Generator, Accessories and Cycle 39 Equipment - Plant Cycle 40 2 VIII - Bypass system 40 - Condensate Pumps 40 - Boiler Feed Pumps 41 - Low Pressure Heaters 41 - Deaerator 41 - High Pressure Heaters 41 - Gland Steam Condenser 41 - Condensate Polishing Unit 42 - Chemical Dosing System 42 - Oxygenated Treatment 42 - Fuel Oil System & Monitoring Systems 42 INSTRUMENTATION AND CONTROL SYSTEM 44 - Distributed Microprocessor Based Instrumentation and 44 Control System (IC) - Salient Features of DCS 44 - Controls Included in DCS 45 - Control Loop Grouping Philosophy 46 - Local Operation 47 - Utility Packages 47 - Operation Package 48 - Unit Control Panel/Unit Control Desk 48 - Control Room 49 - Features of IC System 50 - Annunciation System 50 - Analytical Instruments 51 - Steam & Water Supplying System 51 - Control Valves 51 - Final Control Element Actuators 51 - Field Instruments 52 3 IX X - Air Supply for Pneumatic Equipment 52 - Power Supply 52 - Testing & Calibration Instruments 53 - Cables 53 - Instrumentation Pipes /Tubes & Fittings 53 - Vibration Monitoring System 54 - Pollution System 54 - Instrumentation Earthing 54 - Master Clock 54 ELECTRICAL SYSTEMS 55 - Generator 55 - Generator Circuit Breaker 55 - Generator Bus Duct 56 - Generator Transformers 57 - Evacuation of Power 58 - 400 kV Switchyard 59 - Auxiliary Power Supply System 61 - D.C. System 68 - Emergency Power Supply 69 - Uninterruptible Power Supply System 69 - Cabling System 76 - Lighting System 77 - Safety Earthing and Lightning Protection 78 - Communication System 79 - Fire Detection/Alarm and Fire Proof Sealing System 80 - Elevators 80 - Cathodic Protection 80 PLANT WATER SYSTEMS 81 4 XI XII - General 81 - Sea Water System 81 - Plant Water Requirement 82 - Condenser Cooling Water (CW) System 83 - Auxiliary Cooling Water (ACW) System 85 - Water Treatment (WT) Plant 86 - Service and Potable Water Systems 87 - Fire Protection System 88 - Effluent Disposal System 89 COAL HANDLING SYSTEM 91 - General 91 - Design Criteria and Assumptions 91 - System Capacity 92 - System Description 92 - Salient Features of System 92 ASH HANDLING SYSTEM 95 - General 95 - Capacity and Time Cycle 95 - System Description 96 Bottom Ash Handling 96 Fly Ash Handling System 97 - Automatic Sequential Controls for ash removal system 97 - Ash disposal and ash pond area Ash disposal 98 Ash pond area 99 5 - Possible areas of ash utilisation XIII XIV 100 MISCELLANEOUS SYSTEMS - Compressed Air System 101 - Air Conditioning System 101 - Ventilation System 102 - Hydrogen Gas System 102 - Cranes and Hoists 102 - Workshop Equipment 103 - Chemical Laboratory Equipment 104 ENVIRONMENTAL PROTECTION AND WASTE 107 MANAGEMENT - Types of Pollution 108 - Air Pollution 108 - Water Pollution 114 - Noise Pollution 119 - Pollution Monitoring and Surveillance Systems 120 - Green Belt 121 - Impact of Pollution/Environmental Disturbance 121 - Environmental Clearance 121 PROJECT SCHEDULING AND IMPLEMENTATION 122 - Project Schedule 122 - Transportation/Handling of Equipment 122 - Operation and Maintenance 123 - Preliminary and Other Works 124 XVI PERMITS AND CLEARANCES 127 XVII PROJECT COST ESTIMATES 130 XV 6 LIST OF EXHIBITS EXHIBIT NO. TITLE 1 PLOT PLAN 2 HEAT BALANCE DIAGRAM AT 567/593 RH, 247 bar, 100% TG MCR, 0.1 bar (a) CONDENSER BACK PRESSURE AND 0% MAKE-UP 3 WATER BALANCE SCHEME 4 COAL HANDLING SYSTEM – FLOW DIAGRAM 5 BOTTOM ASH HANDLING SYSTEM - FLOW DIAGRAM 6 FLY ASH HANDLING SYSTEM – FLOW DIAGRAM 7 PRESSURE TYPE ASH DISPOSAL SYSTEM – FLOW DIAGRAM 8 ELECTRICAL KEY ONE LINE DIAGRAM 9 PROJECT MILESTONE SCHEDULE 10 O AND M ORGANISATION CHART 7 LIST OF APPENDICES APPENDIX NO. TITLE PAGE NO. 1 PROJECT SITE DATA 133 2 SEA WATER ANALYSIS 134 3 COAL ANALYSIS 135 4 FUEL ANALYSIS 135 5 BASIC INFORMATION FOR ENVIRONMENTAL 136 APPRAISAL 8 CHAPTER I INTRODUCTION 1 ESSAR POWER GUJARAT LTD. (EPGL) proposes to install a 2x660 MW Super critical imported coal based thermal power station as phase II nearby Nana Manda, Khajurda Dist. Devbhumi Dwarka, Gujarat. The phase II of 2x660 MW is a capacity addition along with phase I of 2X600MW. Net output from phase II of Salaya shall be 1240MW (1320-80MW (approx Aux consumption)). EPGL has already executed a PPA with GUVNL for supply of 800MW on long term 25 years basis at a tariff of Rs. 2.80 per Unit. Balance will be supplied to prospective consumers connected to STU/CTU through short/medium term or through power exchange on day ahead basis. Power Purchase agreements (PPA), which is yet to be executed. 2 The demand for electricity has been steadily increasing in the state of Gujarat due to rapid industrialization and large scale use of electricity for irrigation, domestic and commercial purposes. Based on this forecast, GUVNL has signed a longterm power purchase agreement with EPGL for 800 MW. 3 Further the prevailing power generation scenario in the state reveals that the projected demand for peak power and energy would quickly outstrip the planned generation capacity. In order to mitigate some of the problem and as a capacity building measure EPGL has decided to set up a 1320 MW (2 x 660 MW ) power generating unit as phase II nearby Nana Manda, Khajurda Village Dist. Devbhumi Dwarka, Gujarat. 4 EPGL has retained the services of TCE, Bangalore for preparing a Detailed Project Report (DPR) for the proposed 2X660 MW phase-II super critical thermal power station.. 9 CHAPTER II EXECUTIVE SUMMARY PURPOSE 1. The purpose of this report is to present the techno-economic details of the installation of 2 x 660 MW Phase II super critical imported coal based thermal power plant nearby Nana Manda & Khajurda, Dist. Devbhumi Dwarka,, Gujarat. 2. This detailed project report highlights the details of the selected site, coal supply, availability and use of water, technical features of the main plant equipment, coal and ash handling systems, water systems, electrical systems, plant instrumentation and control system, evacuation of power, environmental aspects and schedule for project implementation of the proposed thermal power project. SCOPE OF SERVICES 3 The scope of this report covers the following: a) Justifying the need for installing the power plant. b) Company’s background with details of promoter(s). c) Suitability of the site identified by EPGL for the installation of the proposed power plant based on the following considerations:i) Availability of adequate space for locating the power plant ii) Geology and topography of the site iii) Accessibility to site iv) Availability of water v) Environmental aspects vi) Convenience of power evacuation vii) Fuel linkage aspects including fuel receipt and handling arrangement 10 d) Brief description of major plant features and salient technical parameters of the following equipment and systems: i) Main power generating equipment and auxiliaries ii) Control and instrumentation system iii) Water systems including sea water and cooling water system (within plant battery limits) e) iv) Fuel storage and handling system (within plant battery limits) v) Fire protection system vi) Effluent disposal system vii) Electrical auxiliary systems vii) Power evacuation system ix) Ash handling and ash disposal system x) Civil & structural works – Design considerations. Environmental Aspects: The report will cover data to be included in the standard format given by central pollution control authorities. (Technical data relevant to this study generated by TCE as part of this assignment will be taken care of by TCE; other required data for this purpose shall be furnished by EPGL). f) Preparation of preliminary plant layout, heat and mass balance diagrams, water balance diagram, electrical one line diagram and fuel handling system scheme. g) Preparation of project implementation schedule in the form of a bar chart. h) Status of various clearances / approvals / contracts / agreements / facilities required for implementation of the power plant i) Brief note on risks indicated below perceived during the pre-construction phase, during construction and post-construction operation phase of the project along with mitigation measures. 11 i) ii) Pre-construction phase such as – Finalization of contracts Approval & permits Availability of taxes & concessions as applicable for a project of this size Availability of land Availability of water Risks during construction such as – Ability of the Company to manage the project during the construction and operation phase given the enormity of the project size. Ability of the Company to infuse the required equity (both upfront and balance along with the debt) in the project at the required time periods. iii) iv) v) Increase in project cost Delay in completion Force majeure / damage / destruction Delay in construction of evacuation facilities Post-construction operation risks such as – Fuel availability risk Fuel transportation risk Equipment performance risk Force majeure Plant generation level (less than planned) Escalation in O&M costs. Off -take risks Price risk Payment risk Other risks Political / economic risk Exchange rate fluctuation 12 j) Change in law Conclusions. NEED FOR POWER PLANT 4 Demand for electrical power in Gujarat State has been increasing due to rapid industrial growth. In spite of the steps taken by Gujarat Urja Vikas Nigam Ltd (GUVNL) to set-up new power plants, the demand for power exceeds the availability. Further, the deficit is expected to increase substantially in the subsequent years Based on this forecast, GUVNL has signed a long term power purchase agreement with EPGL for the quantum of 800 MW. The balance power shall be supplied to other prospective consumers connected to STU/CTU through short term / Medium term open access. Since power sale for major capacity is tied up, installation of Phase II super critical imported coal based thermal power plant nearby Nana Mandha, Kajurda Dist. Devbhumi Dwarka, Gujarat is justified. LOCATION 5 The proposed site is located nearby Nanda Mandha, Khajurda Dist. Devbhumi Dwarka, at about 44 km from Jamnagar city. SITE FEATURES 6 The complete land required for the project is Government Land and in name of Essar Power Gujarat Limited. The identified area consists of non-agricultural land. The ground level is at 31.5 MSL. The proposed site area belongs to seismic zone-5. Geo-technical investigation reports are available for the proposed power plant location. CLIMATOLOGICAL FEATURES 7 The normal annual rainfall is about 537.5 mm with 88% of total rainfall receiving during monsoon season from June to September. The yearly average temperature is about 33 0 C and humidity in the locality is as high as 27-96% during monsoon with a decreased humidity of 15-35% during summer season. The annual mean wind speed of the region is about 15.37 m/s with winds blowing in the east direction predominantly. These specific climatologically data pertaining to site is available, climate data related to existing (under construction) power plant site has been considered as representative of the metrological conditions of the site and mentioned above. 13 ACCESS TO SITE 8 The site is accessible by road from Jamnagar – Okha state highway no.25. The plant site is located adjacent to the Jamnagar – Okha road as shown in Exhibit-1. Nearest railway station is Jamnagar, which is at a distance of about 44 kms from site. LAND AVAILABILITY 9 A total land area of 125 hectares is been identified for the project which is adequate for the power plant including green belt, common facilities like water complex, coal stock yard, conveyor other O&M and administrative facilities. The complete land required for the project is Government Land and in name of Essar Power Gujarat Limited. The same facility being built for Phase-I (1200MW) will be utilized to meet the requirement of Phase-II (1320MW). FUEL REQUIREMENT 10 Imported design coal having an calorific value of 4900 kCal/kg would be used as the main load carrying fuel. The annual coal requirement for 2x660 MW units is estimated to be about 4.5 million tones considering a plant availability factor of 85%. The secondary fuel would be HFO as per IS 1593 and the start-up fuel would be LDO as per IS 1460, 1995. The monthly requirement of HFO would be about 1071 cu.m. MAIN PLANT EQUIPMENT 11 For the 660 MW unit, the rated inlet steam conditions for steam turbine would be 247 bar (a) steam pressure at 567C and the reheat steam temperature would be 5930C. The steam turbine would be a multi cylinders tandem - compound machine, driving a turbogenerator at 3000 rpm to generate 660 MW output at 0.85 power factor at the generator terminals. The MCR evaporation of the steam generator would be superheated steam at about 250.7 bar (a) pressure and 569C temperature and steam temperature at reheater outlet would be 594C. The steam generators would be designed as semi- outdoor equipment while the turbine generator sets with all auxiliary and feed cycle equipment 14 would be located indoors. The parameters indicated above are preliminary and subject to confirmation by the selected main equipment suppliers. COAL HANDLING SYSTEM 12 It is envisaged that coal for this project would be imported would be (Approx) 4900 k Cal / kg of calorific value. The annual requirement of coal for the power plant would be about 4.5 million tones. The coal handling system envisaged would be capable of handling coal from plant junction tower J NT-2 to SG bunkers at rated capacity 1000TPH (1W+1S). . ASH HANDLING SYSTEM 13 The ash content in coal would be about 24 %. Hence 2,13,730 tons of bottom ash and 8,54,919 tons of fly ash would be generated annually per unit when the plant is operating with a PLF of 85%. Bottom ash would be collected in a dry type bottom ash hopper. This bottom ash shall the conveyed to bottom ash silos using scraper chain conveyors passing through clinker grinder and set of belt conveyors. The fly ash handling system would be designed to collect fly ash in dry form in silo using pressure type pneumatic system. The fly ash collected in the storage silo would be unloaded into the trucks either in conditioned form or in dry form, if required for utilization or conveyed in high concentrated slurry form to disposal area. Alternatively provision would be given to dispose BA and unused FA through High Concentrated Surry disposal (HCSD) system. FUEL OIL 14 Both fuel oil (HFO) and Light diesel oil would be required at site by road tankers from ESSAR refinery depots close to the Power plant. 15 WATER AVAILABILITY 15 The source of consumptive water for the thermal power plant would be Arabian sea, which is at a distance of 15 km from site. The total requirement of sea water make for each (i.e. one unit of 660MW) is around 1 6 5 0 9 0 m3/day. For both of 2X660MW unit water makeup is around 330180 m3/day. Sea water is proposed to be pumped from the existing sea water intake pump house to the cooling tower forebay for makeup of closed loop circulation system. 15.1 For the condenser cooling, closed circuit re-circulation system with seawater make-up using induced draught cooling towers has been proposed. The makeup water for the condenser cooling would be drawn from the sea by pumps and discharged into the common CW forebay. From the CW pump house the cooling water would be pumped to the condenser through individual MS conduits. The discharge would be led partially to the cooling tower basin through similar MS conduits with suitable lining or GRP pipes and balance back to sea. 1.3 COC shall be maintained and the discharge to the sea shall have less than 5 deg C differential temperature. 15.2 Fresh water required for other services viz. DM plant, fire protection system, cooling water make up for air-conditioning & ventilation system and plant potable water system, service water, auxiliary cooling (bearing cooling) etc. would be supplied from Desalinated plant. 15.3 Feed cycle makeup and cooling water for steam generator and turbine generator auxiliaries would be met from the DM plant. POWER EVACUATION 16 The power would be evacuated on 400 kV double circuit twin/triple moose conductors. Out of 1320 MW, 800 MW shall be supplied to GETCO, for which GETCO shall construct the line from power plant bus bar i.e battery limit of EPGL for power evacuation, to one of their nearest 400kV Substation. For balance power EPGL will take 16 Open Access (OA) for requisite amount of power from GETCO, alternatively a separate transmission line will be constructed to evacuate the balance equivalent amount of power, which shall connect to nearest PGCIL Substation. The proposed scheme for power evacuation is presented in the single line diagram Exhibit – 08. ENVIRONMENTAL ASPECTS 17 The power plant is proposed to use imported coal. One (1) Bi flue chimney for phase II is proposed with a height of 275 m high RCC chimney (stack). This Bi Flue Chimney will be common for both the steam generator units to meet the requirements of the environmental regulations. The steam generators would be provided with low NOx burners and hence the emission of oxides of Nitrogen from the steam generator would be as per environmental regulations. EPGL shall initiate the application for necessary Chimney clearance to be obtained from Ministry of Defence in similar manner as done for Phase-1 project. The steam generators would be provided with electrostatic precipitators to limit the particulate matter in the flue gas within 30 mg/Nm3 .This is also within the stipulations of Central Pollution Control Board /State Pollution Control Board. Environmental clearance for the proposed project needs to be obtained from MOEF and from State Pollution Control Board. Rapid environmental impact assessment (REIA) and comprehensive environmental impact assessment (CEIA) studies have to be completed and report submitted to MOEF and also to State Pollution Control Board for Their Clearances. it is also proposed to reserve space for installing FGD in case it is required to be installed to control SO2 emission in line with environmental norms. Adequate provisions are proposed for neutralizing the effluents from the water treatment plant. Effective ash management plan for utilization of fly ash would be planned and implemented to ensure proper disposal and use of generated fly ash. The ash utilization would be progressively increased to achieve 100 %. Rain water harvesting measures would be adopted in the proposed plant for 17 conservation of rain water. Rain water would be collected from the buildings roofs would be collected in a collection tank of suitable capacity. This water would be used for gardening purposes. All necessary measures would be taken to limit the noise levels within the permissible limits in the premises and at the plant boundary. Provision has been also made for the Green belt within the premises. In view of the above measures no significant impact on environment is expected due to the installation of proposed power project. PROJECT COST AND COST OF GENERATION 18. Estimated cost of proposed 1320 MW project is Rs. 6971 Crores, including interest during construction (IDC) and financial charges. The cost per MW works out to be Rs. 5.28 (approx) Crores per MW of installed capacity. 19. LOI received from GUVNL for supply of 800 MW Power at a levelised tariff of Rs. 2.80 / kwhr for phase II. PROJECT SCHEDULE 20 Based on expected deliveries of main plant and balance of plant equipment, project implementation period is considered as 39 months for commercial operation date (COD) from zero date for the first unit and 3 months thereafter for the second unit as indicated in preliminary project milestone schedule, Exhibit- 09. 18 RECOMMENDATIONS 21 To ensure timely completion of the proposed project, it is recommended that early action on the following activities be initiated by EPGL: a) Approval of Civil Aviation Authority for installing 275 m high chimney. As explained by EPGL the same has already been initiated. b) Preparation of EIA reports for environmental clearance from state and central pollution control authorities. As explained by EPGL the same has already been initiated. c) Discussions with prospective Indian financial institutions, foreign financial institutions, external commercial borrowing agencies, Indian commercial banks and reputed main plant equipment suppliers. d) Appointment of project consultant for carrying out detail engineering. e) EPGL to identify suitable buyers for ash generated from the power plant. 19 CHAPTER – III NEED AND JUSTIFICATION FOR THE PROJECT 1. The State of Gujarat is part of the Western Region comprising the states of Chhattisgarh, Gujarat, Madhya Pradesh, Maharashtra, Goa, Dadra and Nagar Haveli and Daman & Diu. By the end of the Jan ‘2016 the installed / available generation capacity in Gujarat was 23,972 MW and the total installed capacity in Western region was 1,02,300 MW 2. DEMAND FOR ELECTRICAL POWER Rapid industrialization and increase in commercial and domestic use of electricity are the main reasons for increase in power consumption. In addition, the government policies like rural electrification, electricity to all by 2020, development of irrigation sector, minimum per capita consumption of 1000 units / year, etc are also contributing in increasing the future power demand. To meet the above requirements, the additions in the power generation capacity would have to match with the future power demands. Demand for electrical power in Gujarat State has been increasing due to rapid industrial growth. In spite of the steps taken by Gujarat Urja Vikas Nigam Ltd (GUVNL) to set-up new power plants, the demand for power exceeds the availability. 20 3. Table III.1 and III.2 presents the peak power demand and the energy requirement of Gujarat state and Western region from Year 2016-17 to 2021-22 as per National Electricity Plan of Dec ‘2013 issued by Ministry of Power, Govt of India. Table - III.1 Projected Peak Power Demand and Energy Requirement of Western Region Sl no. 1 2 3 4 5 6 Projected Peak Power Demand and Energy Requirement of Western Region Projected Peak Power Year Projected Energy requirement (MU) demand (MW) 2016-17 62015 394188 (Projected ) 2017-18 65871 417342 (Projected ) 2018-19 70383 444735 (Projected ) 2019-20 75223 474042 ( Projected ) 2020-21 80441 505534 ( Projected ) 2021-22 86054 539310 ( Projected ) Table - III.2 Projected Peak Power Demand and Energy Requirement of Gujarat Sl no. 1 2 3 4 5 6 7 Projected Peak Power Demand and Energy Requirement of Gujarat Projected Peak Projected Energy Year Power demand requirement (MU) (MW) 2015-16 17538 101479 2016-17 (Projected ) 2017-18 (Projected ) 2018-19 (Projected ) 2019-20 ( Projected ) 2020-21 ( Projected ) 2021-22 ( Projected ) 19091 108704 20486 116649 21942 124937 23503 133825 25177 143360 26973 153582 21 Table - III.3 Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Installed Power Capacity of Gujarat Installed Generation Capacity for Gujarat State till March 2015 PLANT NAME Installed Generation Capacity in Gujarat THERMAL POWER PLANTS GANDHINAGAR 870 WANAKBORI 1470 UKAI(TH) 1350 SIKKA 490 PANANDHRO 290 TORRENT POWER 400 SURAT LIGNITE 500 AKRIMOTA 250 APL 2640 Essar Vadinar 1200 OPGS 160 Sub Total ( MW ) 9620 GAS POWER PLANTS DHUVARAN GAS 219 Dhuvaran Expansion 374 UTRAN 520 GIPCL-I 145 GIPCL-II 165 TORRENT POWER GAS 100 ESSAR POWER 515 CLPIPL 655 GSEG Stage-1 156 SUGEN 1148 GPCC Pipavav 700 Sub Total ( MW ) 4697 HYDRO POWER PLANTS UKAI(HY) 300 UKAI LBCH 5 KADANA 240 PANAM 2 PVT HY. 8.6 Sub Total ( MW ) 556 Wind Power 5850 Solar Power Plants 1587 Captive Power Plant 299 Bio Mass Plant 41 Gujarat Share out of Central Sector Power 5659 plants Total ( MW ) 28308 22 Table - III.4 Power Scenario at Western Region Installed Capacity Units 2014-15 2013-14 Hydro MW 7448 7448 Gas MW 10915 10139 Thermal(Coal) MW 65807 58020 Nuclear MW 1840 1840 Total (H+G+T+N) MW 86010 77446 Diesel MW 17.48 17.48 RES MW 12795 9925 Grand Total MW 98822 87389 Net Increase Over Previous in installed Capacity Year % 13.08% 11.52% Peak Demand Max. Peak Load Catered MW 45283 42253 Increase Over Previous Year % 7.17% 3.33% Max. Unrestricted Demand MW 46490 43215 Min. Demand MW 25460 24713 Shortage (MW) MW 182 to 2481 40 to 1377 0.1 to Shortage (%) % 0.40 to 5.83% 3.2% Energy Generation & Requirement Energy Gen ( H+G+T+N) Mus 358926 320317 Increase Over Previous Year % 12.05% 10.58% Wind & Solar Energy Injection Mus 13531 9416 Increase Over Previous Year % 43.70% 1.56% Energy Gen(H+G+T+N+ wind +Solar) Energy Gen 372457 329733 ( H+G+T+N + Wind + Solar) Mus Increase Over Previous Year % 12.96% 10.30% Net Energy Availability Mus 332278 299152 Net Unrestricted Energy Req. Mus 334712 302057 Energy Shortage (%) % 0.73% 0.96% Peak Demand Met (MW) Gujarat MW 14005 12577 Madhya Pradesh MW 10050 9972 Chattishgarh MW 3770 3459 Maharastra MW 20424 18803 Goa MW 489 489 Daman & Diu MW 331 283 DNH MW 721 653 ESIL MW 621 618 23 2012-13 7448 9185 50879 1840 69352 17.48 8987 78356 18.86% 40890 7.40% 41478 25139 244 to 2422 0.65 to 6.71% 289666 4.51% 9271 27.37% 298937 5.10% 28165 301213 6.66% 12348 9692 3320 17268 418 278 652 NOTE: The peak power demand and Energy requirement for the year 2016-2017 to 2021-2022 is estimated based on the projected growth rate as per the National electricity Plan of Dec‘2013 issued by Ministry of Power. 4. INSTALLED GENERATING CAPACITY The Installed generating capacity and availability of power to the state of Gujarat from various sources for the year 2014-2015 are tabulated in Table III.3. Considering that Wind Power, Captive power, Biomass and Hydro Power generation is not stable across different seasons and time of the day, we need to rely on sustainable power from reliable sources of thermal Plants and partly on Solar plants. Considering 80% Availability of Thermal plants ( 9620 MW ) - 7690 MW Considering 80% Availability of Central Sector ( 5690 MW ) - 4530 MW Out of Gas based Power Plants of 4690 MW, Operational Load - 1400 MW. Out of 1587 MW Solar Power & PLF of 20% – Operational Load - 320 MW. 13940 MW For the Year 2015, Out of Total 13940 MW Reliable power Source in Gujarat and Peak demand of 17538 MW ( Refer Table III.2 ), deficit Power will be 20% at Peak Load demand in Gujarat not considering the Wind Power & Hydro Power generation. Already PPA is signed between GUVNL and EPGL for the 800 MW Power Evacuation from the Plant Site considering the future high Power demand in Gujarat State and Few New thermal Power Projects being commissioned from Year 2015 to 2020. 5. MINISTRY OF POWER’S BLUEPRINT FOR POWER DEVELOPMENT: The Ministry of Power, Government of India (GOI) has developed a blueprint to address the power shortage Situation in the country and strategies to overcome it in a time bound manner. Based on the demand additional generation Capacity needs to be added in the country in the 12th five year plan by 2017. To achieve the target, already steps have been taken by different electricity boards to set up new power plants 24 CHAPTER IV SITE FEATURES LOCATION OF THE SITE 1 The proposed site for 2x660 MW Super critical imported coal based thermal power station as phase II nearby Nana Manda, Khajurda, Dist Devbhumi DwarkaGujarat. ACCESSIBILITY TO SITE 2 The site proposed for 2x660MW units has the following features: (a) The proposed site is accessible by road from Jamnagar, which is on the Jamnagar – Okha state high way. (b) The land required for the power plant is under the possession of Essar Power Gujarat Ltd. (c) Sea water make up shall be drawn from the Arabian sea and fresh water required for power plant will be available from Essar Oil desalination plant. d) The coal would be transported by sea route and would be unloaded at Stock yard, and further transported through conveyors. AVAILABILITY OF LAND 3 Based on topographical survey drawing furnished by M/S EPGL, about 125 hectares of land is available for the proposed project at Salaya. This excludes about 25 hectares of land for ash disposal (considering 24% ash content and 85% PLF) which is adequate for disposal of 100% ash generated in 4 years. The site identified for the project is mainly non agricultural with barren land generally with minimum undulations. The land for corridors of coal transportation and sea water supply pipe line from Arabian Sea to plant site are not considered in the above. 25 AVAILABILITY OF WATER 4 The makeup water shall be drawn from the Arabian sea located at about 15 km from the plant boundary. Fresh water requirement of 20640 m3/day would be supplied from the desalination plant located in Essar Oil Refinery. The makeup requirement of CW system from sea water requirement for the proposed power plant is 330180 m3/day Thus adequate and reliable quantity of water is available for the proposed power plant. The analysis of sea water is presented in Appendix-2. COAL SUPPLY 5 The annual coal consumption of the power plant would be about 4 . 5 million tonnes considering an average GCV value of coal to be 4900 kCal/kg, annual plant availability factor (PLF) of 85% and plant heat rate of 2130 kcal/kWh. Coal would be mainly received from Indonesian mines through ship using cap size vessels each of capacity of 150000 lakhs tonnes. POWER EVACUATION 6 Considering the capacity of plant and that a 400kV system is already available at close proximity to the plant, power evacuation is proposed to be done at 400 kV level. For this purpose, an outdoor type 400 kV switchyard, with two main breaker schemes, has been proposed at the power station. The 400kV switchyard would be GIS considering the fact that the site is closer to sea and will consume less space. The proposed scheme for power evacuation is presented in the single line diagram Exhibit – 08. ENVIRONMENTAL ASPECTS 7 The site proposed for the power plant is situated away from the nearby major cities, isolated and environmentally non-sensitive area. Also, since necessary pollution control measures are being proposed for the power plant, it is expected to meet the requirement of environmental authorities. 26 Thus the site has all the infrastructure requirements for the proposed power plant expansion. It is therefore considered that this site is suitable for the installation of the proposed power plant. TRANSPORTATION OF EQUIPMENT 8 All power plant equipment and construction materials would be transported by rail/road/ship to the power plant site. SUITABILITY OF SITE 9 Considering adequacy of available land, availability of river water for plant requirements, coal supply arrangements /, facilities proposed, access to site, feasible power evacuation scheme and environment aspects, it is concluded that the identified site is suitable and land is more than adequate for installation of 2x660 MW units. 27 CHAPTER V FUEL LINKAGE AND TRANSPORTATION TO SITE TYPE OF FUEL 1 Imported coal would be used for load carrying. LDO would be used for light up and initial warm up of units and heavy fuel oil (HFO) for start-up and flame stabilisation at low loads. SOURCE OF COAL AND QUALITY 2 Coal for the project would be Imported, supplied from Indonesian coal fields coal having about 24 % max. of ash content and with an average gross calorific value (GCV) of about 4900 kCal / kg. The analysis of coal is given at Appendix-3. ANNUAL COAL REQUIREMENT AND COAL LINKAGE 3. The annual consumption of coal for the power plant is estimated at 4.5 million tonnes considering average GCV of Imported coal as 4900 kCal / kg with an annual plant availability factor (PLF) of 85% and total heat rate of 2130 Kcal.kWh. TRANSPORTATION OF COAL TO SITE AND STORAGE 4 Coal will be received by large cape size cargo ships (1.5 lakhs tones) and unloaded at the existing jetting of phase-I. Coal from the jetty is envisaged to power plant by closed conveyors. FUEL OIL SUPPLY 5 The fuel oil system would be designed for the use of light diesel oil (LDO) for start-u p and heavy furnace oil (HFO) for flame stabilization purpose The secondary fuel would be HFO as per IS : 1593 and LDO as per IS 1460 : 1995. 28 Based on the statistical average oil consumption of 1 ml per kWh for normal operation & 2 ml per kWh during stabilization period at a PLF of 85%, the quantity of HFO required per month is approx 1200 cu.m and LDO would be 400 cu.m respectively Oil is envisaged to be supplied from nearest Essar refinery terminal by using road tankers to the site. Approximately 7 days of oil storage is considered adequate during trial operation. 29 CHAPTER VI PLANT LAYOUT AND CIVIL ENGINEERING ASPECTS PLANT LAYOUT 1. The layout of the main plant along with all the auxiliary systems has been shown in Plot Plan (Exhibit - 1). In laying out various facilities consideration has been given to the following general principles : (a) Least disturbance to existing habitation and vegetation, if any. (b) Flexibility to have future expansion units with particular reference to the switch yard and main plant. (c) Predominant wind directions as gathered from the wind rose to minimize pollution, fire risk, etc. 2. (d) Power evacuation corridor for connection to state grid (e) Sea water intake pump house (f) Approach road to the power plant from the main highway (g) Availability of adequate space for fabrication / construction equipment. (h) Availability of adequate space for labour colony during construction stage. All facilities of the plant are laid out in close proximity to each other to the extent practicable so as to minimize the extent of land required. The layout also facilitates communication of men and movement of materials between the various facilities both during initial construction and also during subsequent operation and maintenance. 3. Besides taking into consideration the above aspects, the Plot Plan is made to permit coal receipt by conveyors from jetty. Fuel oil would be received by road tankers. 30 CIVIL ENGINEERING ASPECTS Site Topography and Grade Level 4. Site terrain is almost flat without significant undulations. The main plant, auxiliary buildings and coal stockyard etc. would be located at suitably higher level of than the general grade level. Station Building: General Arrangement 5. The steam turbine generator and auxiliary equipment would be located in the main bay of the building having 29.0m span. Each unit is accommodated in a length of 10.0m x 9 bays. Total length of station building for both the units would be 220 m which includes two unloading / maintenance bays each of 10.0 m wide at the end of the station building. The heaters are accommodated in the auxiliary bay (Heater bay) having a span of 10.0 m. The control room / electrical building is located on the side of the station building to accommodate switch gear, electronic panels and control room in a space of 50.0 m x 41.50 m. 6. The turbine - generator bay would be serviced by three floors - ground floor at 0.0 M level, mezzanine floor at +6.9 M level and operating floor at +13.7 M level. Localized O&M platforms at required levels would be provided. The Deaerator would be located at EL+ 26.00 M in the BC bay (heater bay). Road access would be provided to the unloading and maintenance bays for unloading TG components and auxiliary equipment. 7. The superstructure would be of structural steel framing with RCC floor slabs. The roof of the TG bay would consist of sandwiched panels (with insulating material). The turbine generator pedestal would be reinforced concrete and would be isolated from the building foundations and super structure. All structures would be designed to cater to applicable wind/seismic forces in the area as per relevant Indian Standards. Steam Generator Area and Mill Bay 8. The mill bay would be of structural steel-framed construction, supporting the steel bunkers. The 14 m wide bay would have mill maintenance platform at ground level and 31 floors for the feeders and for the bunker feeding conveyors provided with trippers. The bunker bay would be located at the front side between the furnace in the steam generator area and the T-G building. Concrete paving would be provided in the steam generator area with necessary drains and trenches. Pipes and cables in this area would, in general, be routed on overhead pipe / cable racks. Chimney 9. One (1) Bi-flue chimney with common wind shield for the two units has been envisaged for the proposed thermal power plant. The total height of reinforced concrete chimney is 275 mtr, and Diameter of flue can is 7.6 mtr. This would meet the requirement of Indian Emission Regulation. The chimney windshield shall be of RCC slip form construction. Miscellaneous Buildings 10. Table - VI.1 below indicates list of major buildings / structures planned in the power plant and type of construction : Table -VI.1 Major Buildings / Structures Sl. No. 1. Building / Structure ESP control room 2. Air washer rooms 3. Ware house and Workshop 4. D.G house Remarks / Type of Construction Ground plus three floor; common for two units. Structural steel construction with brick walls. Floors and roof would be of RCC. Two per unit; Each having ground plus one floor. Structural steel construction with brick walls. Floors and roof would be of RCC. Structural steel columns with bricks for side cladding. Pre-coated galvalume sheet supported on structural steel would be provided for roof. Structural steel construction with pre- coated galvalume sheet for roof. Sides are kept open. 32 5. 6. 7. 8. 9. 10. 11. 12. Hydrogen cylinder shed CW pump house & MCC room Clarified water pump house D.M Plant Coal handling switch gear cum control room Switch yard control room DM plant control room cum switch gear room Ash handling compressor room + MCC room Structural steel construction with pre- coated galvalume sheet for roof with 1.8 m high brick dwarf walls for the sides. Structural steel construction with brick walls Structural steel construction with brick walls. Structural steel columns with pre-coated galvalume sheets for roof. Roof is supported on structural steel trusses. Sides are kept open. Structural steel construction with brick walls Structural steel construction with brick walls Concrete construction with brick walls Compressors would be provided with metallic containers and covered shed would be provided for protection. 13. Admin Building Concrete construction with brick walls 14. Canteen Building Concrete construction with brick walls 15. Service Building 16. Fire Station Building 17 Car / Scooter parking Structural steel construction with brick walls. Floors and roof would be of RCC. Structural steel construction with pre- coated galvalume sheet for roof. Sides are kept open. Fire office space would be of concrete construction with Brick walls Structural steel construction with pre- coated galvalume sheet for roof. Sides are kept open. Soil Profile and Foundations 11. Details would be furnished after the detailed geo-technical investigation of the proposed area is carried out. However the net safe bearing capacity of 40 t/m2 at 3.0 m below the existing ground level is considered for the purpose of this report. Machine Foundations 33 12. All equipment would be supported on conventional block / framed type RC foundations and would be separated from the building foundations and superstructure. All variable speed machines would be supported on vibration isolation system with springs and viscous dampers. Roads, Drains & Boundary Wall 13. The roads would initially be of water-bound macadam type with shoulders on either side of carriage width. After major construction activities are completed, these would be surfaced with bituminous carpet. All major roads would be 7.0 m wide and other approach roads would be 4.0 m wide. Storm water drains would be provided on either side of the roads. The storm water drains would be of RCC construction. The storm water drains would be connected to the nearest water body or would be treated suitably and reused for gardening and other purposes. The power plant boundary wall of 3.0 m height with anti-climbing device would be constructed from locally available stones. Design Basis 14. Dead and live loads would be considered as per relevant IS codes and standard engineering practices. The basic wind speed of 50 m / s is considered for design of buildings / structures as per IS : 875 : Part III. The power plant is located in Seismic Zone V as per IS : 1893 and seismic forces would be considered accordingly for the structures / buildings. All designs would be carried out in SI units and would be as per relevant IS codes. Sewage Disposal 15. Sewage from various buildings would be lead to STP located close to the buildings by means of CI pipes laid underground. The treated water will be used for green belt. 34 Landscaping 16. The various services / utility areas within the plant would be suitably graded to different elevations. Natural features of the plant site would be retained as far as possible to integrate with the buildings to form a harmonious / pleasant environment. Areas in front of various buildings and the entrance of power plant would be landscaped with ground cover, plants, trees based on factors like climate, adaptability etc. The green belt would consist of native perennial green and fast growing trees. Trees would also be planted around the coal stock pile area and ash disposal area to minimize the dust pollution. 35 CHAPTER VII MAIN PLANT EQUIPMENT AND SYSTEMS PLANT CAPACITY 1 EPGL have awarded for installation of 1320 MW (2x660 MW) coal based thermal power project nearby Nana Manda, Khajurda Devbhumi Dwarka Dist, Gujarat. UNIT SIZE 2 Two (2) units each of 660 MW have been considered for the project. This is based on request for proposal (RFP) document requirement. TURBINE CYCLE HEAT RATE 3 The generally adopted supercritical pressure (turbine throttle pressure) is about 247 bar (a). For the purposes of the present DPR, following options of throttle steam and reheat steam parameters for the 660 MW units have been considered to prepare heat balances and to compute turbine cycle heat rates using the software STpro: a) 4 247 bar (a), 567°C/593°C Based on the above as superheater/reheater steam temperatures increase for the same pressure, the turbine cycle heat rate decreases which means plant efficiency improves. 5 Leading supercritical boiler manufacturers in the world have proven experience in designing and manufacturing boilers for above mentioned which are in operation for long time. 6 The relevant turbine cycle heat balance is presented in Exhibit-2. Indicative parameters for both the options have been mentioned in Table VII.1. 36 STEAM GENERATOR AND ACCESSORIES 8 The steam generator (SG) would be once through type and would be designed for firing 100% Imported coal. The SG would be radiant, two pass design, single reheat, balanced draught and semi outdoor type. 9 The water wall would be spiral wound plain tubes with vertical tubes over the spiral water walls or vertical rifled tubes type. 10 Indicative design parameters for the steam generator for the 660MW unit would be as below. Table-VII.1 Indicative Parameters for the Steam Generator i Superheater outlet pressure ii Superheater outlet temperature iii Superheater outlet flow 1966.7 TPH iv Re-heater outlet pressure 51.51 bar(a) v Re-heater outlet temperature Feed water inlet temperature to vi 11 economizer 250.7bar(a) 569°C 594.4°C 297°C The steam generator would be corner fired or front and rear wall burners mounted type. The furnace would be appropriately sized to avoid slagging in the pendant/platen superheaters and reheaters and in the heat transfer surfaces in convection pass. 12 The coal burners would be of proven advanced design to reduce NOx production and the furnace would also be provided with over fire air ports to further reduce NOx production. 13 The SG would be provided with circulation system comprising steam separators to remove water moisture from the evaporator outlet and to recirculate water into economizer inlet, for use during startup and shut down. The SG and steam turbine generator (STG) would be designed for sliding pressure operation, which would increase turbine cycle efficiency and reduce boiler feed pump power consumption. The load range for sliding pressure operation would be from about 40% STG maximum 37 continuous rating (STG MCR) to 90% STG MCR. This modified sliding pressure operation would be employed to provide facility of temporary load increase even before the fuel handling and firing system can be loaded to support any sustained higher load. 14 The SG would consist of water cooled furnace, radiant and convection superheaters, reheaters, economizer, regenerative air heater, steam coil air preheaters. Smart soot blower system would be provided with soot blowers located at strategic locations for cleaning the slagged and fouled heat transfer surfaces during operation. 15 The SG would be provided with vertical spindle medium speed coal mills, which would be located in the boiler front or between the boiler and the ESP depending upon the manufacturer’s standard. The milling system would be designed such that one(1) mill would be standby and other mills would take care of MCR with worst coal and two(2) mill would be standby with design coal. The coal mills would be provided with dynamic classifiers to control the fineness of the ground coal thereby controlling the unburnt carbon losses. The coal mills would be provided with gravimetric coal feeders. 16 Sampling arrangement at mill outlet would be provided for the purpose of establishing the average gross calorific value of coal as well as coal fineness. The coal mills would be provided with steam blanketing system for the purpose of fire protection. 17 The SG would be designed to handle and burn HFO as secondary fuel upto about 22.5% SG MCR for start- up and for flame stabilization during low load operation or during mill change over. For unit light up and warm–up purposes, LDO system having 7.5 % SGMCR firing capability would be used with air atomization. 18 The SG would be provided with fuel oil pumps and fuel oil heating equipment along with high- energy electric arc ignitors to ignite the fuel oil guns. 19 The draught plant would comprise primary air fans, forced draught fans and induced draught fans. The primary and forced draught fans would be of axial blade pitch controlled axial type. The induced draught fans would be axial blade pitch controlled axial type or speed controlled (VFD) centrifugal type, which would reduce power consumption during power plant operation at TGMCR and part load operations. 38 20 Electrostatic precipitators (ESP) would be provided for the collection of fly ash. The ESP would be provided with microprocessor control system to optimize and for minimum electric power consumption. The ESP would be so designed that for worst coal firing with an ash content of about 25 %, an outlet dust concentration of 30 mg/Nm3 as stipulated by World bank group on pollution prevention and abatement / State/Central Pollution Control Boards, would be achieved. STEAM TURBINE GENERATOR AND ACCESSORIES AND CYCLE EQUIPMENT Steam Turbine Generator 21 The steam turbine generator (STG) would be rated for about 660 MW maximum continuous output at generator terminals, with throttle steam condition of 247bar(a) at 567°C/593°C reheat ,0.01 bar(a) condenser back pressure with 0% make up. The STG output at valve wide-open (VWO) condition would be about 693 MW, which is 5% above the maximum continuous rating of 660MW to enable increased output required during low frequency operation and drop in efficiencies over years of operation. 22 The steam turbine would be a multi cylinder, reheat extraction and condensing turbine. 23 The turbine generator would be complete with all accessories such as protection system, lube and control oil system, seal oil system, jacking oil system, seal steam system, turbine drain system, electro-hydraulic control system, automatic turbine run up system, on-line automatic turbine test system and turbine supervisory instrumentation. A continuous bypass (60 % capacity) method of lube oil purification is proposed to be adopted for purification of lubricating oil. 24 The turbine generator would also have all necessary indicating and control devices to permit the unit to be placed on turning gear, rolled, accelerated and synchronized automatically from the control room. Other accessories of the turbine generator would include an external oil purification unit with transfer pumps and oil storage tank of adequate capacity. 39 PLANT CYCLE 25 The condensing plant would comprise two condensers, one each for the two LP turbines. Vacuum pumps of 3x50% capacity would be provided to create vacuum in the condenser during start-up and to remove the non-condensable gases liberated during normal operation. 26 The regenerative cycle would consist of low pressure heaters, a variable pressure deaerator, three high pressure heaters and one gland steam condenser. 27 Under normal operating conditions, drains from the high pressure heater would be cascaded to the next lower pressure heater and finally to the deaerator. Drains from the low-pressure heaters would be cascaded successively to the next lower pressure heater and finally to the condenser hot well or pumped forward to the condensate line. Heaters would be provided with drain level controllers to maintain the drain level automatically throughout the range of operation of the heaters. The system would consist of splitrange control valves to take the drain to a lower pressure heater or to the condenser through a flash box under exigent conditions. Bypass system 28 The STG unit would be provided with a suitable HP-LP bypass system. a) To prevent a steam-generator trip in the event of a full export load throw-off and to maintain the unit in operation at base load b) To prevent a steam-generator trip following a turbine trip and enable quick restart of the turbine generator set c) To minimise warm restart duration of the unit after a trip d) To conserve condensate during start up e) To facilitate quick load changes in both directions without affecting the steam generator operation during start-ups. Condensate Pumps 40 29 The condensate from the condensate hotwell would be pumped by 3x50% capacity condensate pumps, two working and one stand by to the deaerator through the gland steam condenser, drain cooler and low-pressure heaters. The pumps would be vertical, cannister type, and multistage centrifugal pumps driven by AC motors. Boiler Feed Pumps 30 The feed water would be pumped from the deaerator to the steam generator through the high pressure heaters by means of 3 x 50% capacity boiler feed pumps i.e. two steam turbine driven and one motor driven type. The motor driven BFP would be used as standby and during start-up. The boiler feed pumps would be horizontal, multistage, centrifugal pumps of barrel type. Low Pressure Heaters 31 The low pressure (LP) heaters would be of shell and tube with stainless steel U-tubes (seamless) welded with their ends rolled in carbon steel tube sheets. The LP heaters would be provided with condensing zones and also with drain cooling zones. Deaerator 32 The deaerating feed water heater would be a direct contact, variable pressure type heater with spray-tray type or spray type of deaearation arrangement. The feed water storage tank would have a storage capacity adequate to feed the steam generator for 6 minutes when operating at SG MCR conditions. High Pressure Heaters 33 The high-pressure (HP) heaters would be of shell and tube with stainless steel U-tubes (seamless) welded with their ends rolled in carbon steel tube sheets. The HP heaters would be provided with de-superheating zones and a drain cooling zones in addition to condensing zones. Gland Steam Condenser 41 34 A surface type gland steam condenser would be used to condense the gland steam exhausted from turbine glands. The gland steam condenser would be of single-pass type with the main condensate flowing through the tubes to condense the steam. Exhausters would be provided to evacuate the air from the shell side and maintain the shell at the required negative pressure. Condensate Polishing Unit 35 In order to maintain high purity of the feed water, 2x50% capacity condensate polishing units (CPU) are envisaged in the condensate system. Chemical Dosing System 36 Ammonia dosing system would be provided to ensure chemical conditioning of the condensate/feed water for controlling the alkalinity. The ammonia solution would be injected into the condensate at the condensate extraction pump discharge. The lowpressure ammonia dosing system would comprise solution preparation-cum metering tanks with motorized agitators, two positive displacement type-dosing pumps, piping, valves, instruments and local control panel. Each dosing pump would be sized to cater to the 100 % dosing requirement of each of the 660 MW units. Oxygenated Treatment 37 To reduce iron pick up from the boiler, during normal operation of the plant, oxygenated treatment is also proposed. Under this treatment gaseous oxygen would be injected at CPU outlet and at BFP suction to maintain about 150-250ppb.Feed water pH is maintained in the range of 7.0-8.5. Fuel Oil system 42 38 The annual requirement would be about 1071 cu.m based on consumption of 2ml/kWh (CERC guidelines) of power generation and 85 % PAF. 39 HFO would be supplied by road tankers from Essar refinery terminals located at near to site. Two tanks each of capacity 4000 KL are proposed which are adequate to meet the normal requirement including peak requirements during commissioning and trial operation of units. 40 The HFO tanks would be fitted with steam heated floor coil heaters for initial heating and to supply fuel oil at the required temperature to the inlet of pumping and heating units. All HFO lines would be heat traced and insulated. 43 CHAPTER – VIII INSTRUMENTATION AND CONTROL SYSTEM 1. DISTRIBUTED MICROPROCESSOR BASED INSTRUMENTATION AND CONTROL SYSTEM (I&C) Microprocessor based distributed control system with state of the art Human Machine Interface (HMI) is proposed for the 2 x 660 MW to provide a comprehensive integrated instrumentation and control system including the functions of Data Acquisition System (DAS) to operate, control and monitor the steam generator and auxiliaries, steam turbine generator and auxiliaries and the balance of plant systems including electrical system with a hierarchically distributed structure. Distributed control system (DCS) has been envisaged for the main plant comprising of Boiler and auxiliaries, turbine and auxiliaries. PLC based control has been envisaged for Coal handling, Ash handling, DM plant, Fire detection & Alarm and Fire Fighting system (control for the sea water intake, CW system etc.. shall be included appropriately) . SCADA would be used for Switchyard controls. All PLC, SCADA & DCS shall be OPC compliant supporting open architecture for homogeneous connectivity & uniform operation by plant DCS operating station. The distributed microprocessor based system proposed is to be geographically centralized. In the geographically centralized microprocessor based system, electronic cubicles would be located in a centralised location with centralised operation from the control room. 2. SALIENT FEATURES OF DCS 2.1 The Distributed Control System (DCS) would use the state of the art technique of functional distribution of control and monitoring defining redundancy at appropriate level to reduce the risks associated with failure of any single controlling unit. The DCS shall have complete control capabilities that include closed loop control, open loop control, computation and interfacing for data acquisition, graphic displays, logging, annunciation, sequence of events recording, data storage, retrieval, performance calculations and management information system. The system shall allow for operation from the control room through operator work station (OWS) with TFT monitors. The communication from the control desk operators’ interface to the electronic hardware shall be over a high 44 speed data highway. The system will be based on open system architecture to facilitate interface with third party software. MIS will have interface with both DCS and all PLCs. 2.2 The microprocessor based system proposed is functionally distributed with electronic hardware located in a centralized location designated as Control Equipment Room (CER) and plant operation to be undertaken from the Central Control Room (CCR). 2.3 The instrumentation and control system would integrate the functions of plant monitoring, control and information systems. All equipment and processes in the unit would be controlled and monitored from Central Control Room. The Central Control Room shall house unit control desk while related power supply and system cabinets shall be mounted in Control Equipment Room. The operating stations (OWS) shall be functionally interchangeable. TFT display screen with keyboard control for OWS will be provided for operation and maintenance. Also dedicated software for Vibration Monitoring system (VMS), Flame monitoring system, Boiler tube detection System, Performance analysis of Plant & equipment, Diagnosis and optimization system is envisaged. LVS (Large Video Screen) has been envisaged for overview information & operation of the plant. 2.4 The DCS shall have adequate redundancy features. The system shall be provided with the redundancy at various levels. a) Processors, I/O bus, Data bus, Communication bus, power supply b) I/O module redundancy would be for critical open loop and all closed loop services only. However, TMR had been detailed separately. c) Triple redundant sensors would be considered only for critical services like boiler trip, turbine trip, furnace draft control, governor control, steam temperature, hot well level controls and bypass controls. Less-critical controls would be considered with dual redundant sensor. No redundancy would be considered for non-critical measurement system. 3. CONTROLS INCLUDED IN DCS A Microprocessor based DCS of modular hardware with state-of-the art HMI covering the following is envisaged: 45 a) Steam generator (SG) start-up / shutdown sequence, integral controls like burner management system, secondary air damper control, soot blowing, high pressure by-pass system and controls for boiler and auxiliaries and closed loop controls like combustion control and SH / RH steam temperature control. b) TG integral controls like Automatic Turbine Run-up System (ATRS), Turbine Protection (TP), Electro-hydraulic Turbine Controls (EHTC), Automatic Turbine Tester (ATT), Turbine Stress Evaluator, turbine supervisory system and LP & HP by-pass system and gland steam controls, Lube oil temperature control system. c) Balance of plant control includes auxiliary steam system, condensate system, feed water system, HP/LP Dosing system, cooling water system, auxiliary cooling water system and makeup water system. d) Coordinated master control. e) Generator Auxiliaries Control. f) The Furnace Safeguard and Supervisory System (FSSS) and the Turbine Protection System (TPS) is proposed to be implemented through triple modular redundant (TMR) control system conforming to SIL 3 with certification from an authorised agency. Where the DCS Vendor does not have this system in their product range, independent TMR system with integration to DCS through communication links is proposed. The DCS envisaged is independent for each unit except at Management Information System (MIS) level and at the shift charge engineers level which is common for both the units. 4. CONTROL LOOP GROUPING PHILOSOPHY The following critical loops would be implemented in separate dedicated TMR/redundant controllers of the same DCS system: a) Boiler protection and BMS in SIL 3 Certified Dual redundant or TMR (Triple modular redundant) system in line with latest NFPA guidelines. b) Turbine protection in TMR mode c) Electro-hydraulic governing control in TMR mode d) Furnace draft ( Redundant ) e) Steam temperature ( “ ) f) ( “ ) HP / LP Bypass controls g) Hot well controls. ( “ ) 46 h) Boiler start-up / shutdown sequence logic including BMS, Mills etc. ( ‘’ ) i) Turbine start-up / shutdown logic ( ‘’ ) All other loops would be grouped suitably without compromising availability requirements. The TMR systems will be preferably of the same family of the DCS, otherwise TMR systems will be interfaced with DCS through bi-directional OPC link with Ethernet based TCP-I/P Protocol. 5. LOCAL OPERATION Local push button station for stop facility shall be provided for all motorised drives except for solenoid valves. The motorised valve with integral starter will have LPB operation on the actuator itself. 6. UTILITY PACKAGES 6.1 Utility packages are proposed with dedicated stand-alone control system. Condensate Polishing unit, (if applicable) Coal handling system, ash handling system, water treatment plant, CW plant, sear water Pump House system, Effluent treatment system and fire protection system will be provided with independent Microprocessor based PLC control systems with VDU/KB based OS operation and will be located in the respective local control room (Common for 2 units). 6.2 Serial communication will be provided with the Plant DCS system in the main control room for monitoring. All the offsite unit control systems shall be networked with the main plant DCS so that the offsite plant information is available in plant DCS. 6.3 PLC-based control system will also be provided for Air conditioning and ventilation system and fire detection & alarm system. Sea water pump controls would be PLC based control having local control panel located in the sea water pump house & interfaced with DM Plant PLC to facilitate operation from DM plant operator station. Chemical dosing system would be relay based. Compressor package will be provided with integral microprocessor based control system with hardwired connection / serial link to DCS. 6.4 The control of the packages is proposed from dedicated PLC / microprocessor based systems that will be located in a control room nearer to the respective equipment. Suitable interface (hardwired and /or serial) would be provided with the plant I & C system in the main control room for status monitoring. 47 7. Operation Philosophy All equipment/system associated with main plant viz. SG, STG and their associated auxiliaries, other balance of plant systems like chemical dozing systems (HP & LP) etc. & Plant electrical system of each unit, and plant common systems like compressed air system, plant common station electrical system shall be operated / monitored from VDU/Keyboard based Operator stations (OS) mounted on central Control Desk (UCD) and from Large Video Screen displays (LVS). The Central control room shall be common for both the units & layout shall be accordingly planned. 8. UNIT CONTROL DESK The unit, functional group / drive level control and operation of all main plant equipment would be from a set of console type TFT monitors along with the keyboard / mouse. 9. The Control desk (CD) for each unit would house the following items: a) Operator work stations (TFT Monitors) for operation, control and monitoring of steam generator, turbine generator and the balance of plant. 10. b) Telephone handsets c) Annunciation windows d) Emergency push buttons for SG, TG ,HT and critical LT devices The operator can perform the following operations of main plant and balance of plant from monitors in the UCD through key boards: a) Operation of all control valves, control dampers, motor operated valves, interlocked isolating valves and dampers, non-interlocked isolating valves & dampers, motor operated bypass valves of control valves, warm-up valves, drain valves and vent valves in the steam generator, turbine generator and auxiliaries and auxiliary electrical systems. b) Operation of pumps and fans associated with the steam generator, turbine generator, feed cycle and other auxiliary systems. c) Call for plant overview, group display, individual loop display, etc. and carry out associated control operations. 11. All the monitors are supported by the following peripherals, which are located in the control room: 48 12. a) Colour Inkjet printer (Operator’s action) b) Dot matrix printers (logs and reports). c) Colour Inkjet printer (History). d) Colour Inkjet printer (Engineering station). e) Dot Matrix printer (SER). In addition to the above, monitors / peripherals would be provided for following: a) 2 no’s of Maintenance engineer's equipment (MEE): Monitor and Laser printer. If TMR is not part of the DCS, then separate ES or programming unit will be provided (1 No. MEE for each unit ) b) Historian and Plant Performance calculation monitor. Historian hardware will be 2 x 100% type.(for each Unit) c) Shift in charge Engineer's equipment (SCE) will comprise of Monitor and Laser printer (1 No common for 2 Units) d) Management information system: Monitors and printers. However, the plant operation shall be carried out only through the Operator Stations. Backup between the Operator Station shall be defined for Plant operation in case of one station failure. 13. CONTROL ROOM The control room of the unit is partitioned into different rooms to house the following equipment: a) Control Desk (CD) and printers in the main common control room. b) DCS system cabinets, Marshalling cabinets, electrical auxiliary cabinets, steam generator and turbine auxiliaries system cabinets in the electronic cubicle room. c) Cabinets in the Control Equipment Room. d) Shift Incharge Engineer’s monitor with key board and printers in Shift Incharge Engineer’s room. ( 1 no. common for 2 units ) e) Maintenance Engineer’s monitor with key board in MEE room and printers of I&C, steam generator and turbine system in auxiliary electronics room (common). f) LVS: The size will be 2x3 matrix (each 67” size) for each unit & 1 number for offsite plant unit comprising of CHP, AHP, DM plant etc (common for 2 Units). g) Electrical panel room in main control room h) Uninterrupted Power Supply System (UPS) in UPS room (separate). 49 14. FEATURES OF THE I&C SYSTEM 14.1 Smart transmitter maintenance facility A PC based dedicated smart transmitter maintenance facility, common for both units, would be provided for complete diagnostic, record keeping, calibration and configuration, event and log reports, historical data base records of all transmitters. 14.2 Computerised Maintenance Management System (CMMS) Computerised Maintenance Management System (CMMS) suitable for use with maintenance management of a modern power generation utility’s equipment and systems would be provided. It shall be common for both units and shall perform tasks such as asset and inventory management, preventive maintenance scheduling, job plan, work order generation, purchase and personnel functions, etc. 14.3 Performance analysis, diagnostics and optimisation system (PADO) The PADO system would provide critical analysis of the plant performance and guidance for optimisation on continuous on-line basis. The system shall analyse dynamically the status of the process and the equipment of the power generating units and generate operator guidance instructions for remedial actions for maintaining the process and the system / equipment in the plant to their optimum performance. 14.4 Sequence of Events Recording System Sequence of events recording system (SER) of 1 millisecond resolution with an input capacity of 512 points would be provided as an integral part of DCS to log trips, cause of trips and other important faults to diagnose the cause of plant trips. This shall also include switchyard inputs. The system will be provided with a dedicated printer located in the main control room. 14.5 Annunciation System A Stand-alone microprocessor based annunciation system (AS) would be provided with ISA sequence ring back feature. The system has the features of standard ISA sequences. A limited number of annunciation windows for critical alarms of process and electrical are proposed to be provided in the unit control desk. Alarm prioritisation is also 50 envisaged. A set of annunciation push buttons would be provided in the unit control desk. 14.6 Analytical Instruments Adequate number of analytical instruments would be provided for continuous monitoring of steam, condensate & feed water system. The analytical instruments proposed are for measurement of specific conductivity, cationic conductivity, pH, dissolved oxygen, silica and hydrazine. 14.7 Steam and Water Sampling System (SWAS) Various steam and water samples (with suitable sample coolers) would be routed to a centralised place and cooled to the required temperature before passing through the respective analytical sensors. The complete hardware associated with this sampling system and Flow cells with sensors are mounted in a sampling rack with facility for grab sampling. The analysers are located in a separate panel near the sampling rack in an air-conditioned environment. The SWAS room will be suitably located in the station building for each unit. 14.8 Control Valves All control valves shall be considered to handle 15% excess capacity over and above the maximum flow value. The control valve design shall be suitable for the required fail safe conditions of process / equipment. Anti-cavitation trim with controlled, staged pressure reduction shall be used for high pressure drop application. 14.9 Final Control Element Actuators All final control elements (control valves and control dampers) would have actuators of pneumatic / hydraulic type. The control system design shall be suitable for the required fail-safe conditions of process / equipment. All actuators would be sized so that the final control elements operate properly even when the upstream pressure exceeds 110% of maximum value. Pneumatic actuators would be provided with air failure lock and remote release, limit switches, adjustable minimum and maximum stops, load position indicators, positioners, electronic position transmitters and solenoid valves in accordance with the system requirements. 51 14.10 Boiler tube leak detection system A microprocessor based Boiler tube leak detection system (24 channel) with high grade audio electronic microphone type audio detectors, display unit, etc. would be provided to generate alarms on occurrence of tube leakage and to display the level of leakage in the form of bar charts. 14.11 Furnace flame monitoring system The flame monitoring and analysis system would provide flame condition monitoring and thermo-graphic analysis of the flame for each burner and guide the plant operation personnel regarding the nature of fault and the corrective action required. The system would comprise video cameras, signal conditioning cards, amplifiers, special cables, etc. with all necessary equipment and accessories. 14.12 Field Instruments Field transmitters, switches and temperature elements with adequate redundancy would be provided to meet the interlock/control requirements of the power plant. Local indicators are envisaged wherever indicating type transmitters are not provided to enable local operators to supervise and monitor equipment / process operation. Separate switches would be considered for unit and equipment trips and also for alarm / interlock purpose wherever transmitters are not envisaged. All transmitters shall be smart transmitters with integral indicators. Also smart transmitter maintenance facility will be provided. 14.13 Air Supply for Pneumatic Equipment Oil free, dry instrument air from instrument air header at a pressure of 6 - 8 bar (g) would be drawn for various instrument auxiliaries like positioners for control valves & control dampers, I/P converters, etc. Each of these pneumatic equipment which requires air supply at different pressures would be provided with an air-filter regulator. 14.14 Power Supply A redundant uninterrupted power supply (UPS) system would be provided at 230V AC, single phase, 50 Hz, 2 wire for power supply requirements of instrumentation and control systems viz. DCS man-machine interface equipment, analysers and instruments 52 mounted on the unit control panel. Any other voltages required including control system supply of + 24 VDC would be derived from the 230V AC UPS. Conversion from 230V AC UPS power to 24V DC power shall be done in redundant mode. 14.15 Testing and Calibration Instruments Necessary testing and calibration instruments required for the complete I&C system for commissioning & maintenance during operation of the plant shall be considered. (Common for Both Units). 14.16 Cables Individual / pair shielded and overall shielded twisted pair copper cables would be used for analog signals and overall shielded cables would be used for digital signals. All these cables shall be armoured. The inner sheath shall be PVC and the outer sheath shall be FRLS PVC. The size of the wire would be 1.5 sq.mm. 2.5 sq.mm copper control cable would be used for cabling for services like field solenoid valve to the control system. Compensating cables will be provided for connecting the thermocouple inputs to the measurement system of DCS and up to temperature transmitters for closed loop control system. The interconnecting cables between any two cabinets and between cabinets and panels would be of prefabricated type. 14.17 Instrumentation Pipes / Tubes and Fittings For remote located instruments like transmitters, tubes and fittings of appropriate material and rating would be used. Open type transmitter racks with canopy would be provided to group and mount all pressure, flow, level transmitters and temperature transmitters in the Turbine area and closed transmitter racks would be used in Boiler area. Junction boxes would be provided for termination of all field switches like pressure, temperature and level. For all pipe mounted instruments, pipes and fittings of appropriate material would be used. For all high pressure and temperature services (above 62 bar (g) or 425°C), two isolating valves of NB25 size would be used. For level and flow instruments NB25 size isolating valves would be used. For other services and measurements NB15 size valves would be used. 53 14.18 Vibration Monitoring and Analysis System (VMS) A microprocessor based vibration monitoring and analysis system along with sensors would be provided for steam turbine Generator and for all HT drives. STG vibration measurement will be part of standard Turbovisory package and shall be suitably interfaced with the centralized vibration analysis and diagnostic system. Sensors provided for vibration measurement will be proximity / velocity pick-ups/ acceleration pick-ups along with key phasor measurement. This VMS will be interfaced with Plant DCS. 14.19 Pollution Monitoring Analysers for continuous monitoring of CO, SO2, NOx, Mercury, SPM, monitoring are envisaged in the stack, to comply with the statutory requirements of respective Pollution Control Board. Oxygen measurement is envisaged in the flue gas duct for oxygen trimming in combustion control to ensure efficient combustion. Ambient Air Quality Monitoring System (AAQMS) is envisaged.. 14.20 Instrumentation Earthing Separate electronic earthing system with dedicated earth- pit would be provided for DCS equipment. 14.21 Master Clock A stand-alone master clock system common for both the units with suitable time formats is envisaged for synchronizing with the clock system of DCS, annunciation system, PLC systems of utility plants , Sequence of events Recorders, Disturbance Recorders, Tariff metering equipments, etc . The system shall receive time formats from the Remote GPS satellite through antenna. The master Clock shall also have No. of slave clocks at various locations in the Plant 54 CHAPTER – IX ELECTRICAL SYSTEMS GENERATOR 1. The key one line diagram (Exhibit - 08) describes the plant electrical system. The generator would be rated to deliver 776.5 MVA (660 MW), at 21 kV, 50 Hz, 0.85-power factor, at 3000 rpm. The generator rating shall not be a limiting factor for total power evacuation, and the rating shall be suitable for steam turbine VWO rating of 690 MW. The generator winding would be star connected and will deliver rated MVA output under +5% variation in voltage and -5 to +3% variation in frequency. 2. All generator components, rotor winding, stator core, end region flux shield structures and lead box, except the stator winding, are hydrogen cooled. The stator coils, parallel rings, main leads and terminal bushings are cooled directly with water. Hydrogen coolers would be built into the stator frame of the generators and would be sized to ensure at least 75% of the rated output when one hydrogen cooler is taken out for maintenance. 3. The generator would be provided with either brush-less or static excitation system. Suitable fast acting non-dead band type continuous acting digital type automatic voltage regulator would be provided. The AVR will have the required redundancy feature built in to ensure reliable operation. 4. The generator winding would be provided with Class – F insulation. However, temperature rise would be limited to Class – B limits. GENERATOR CIRCUIT BREAKER 5. The generat or circuit breaker will be provided in the run of the generator main connection to the generator transformer to connect or disconnect the generator during the startup or shutdown period of the plant or on generator fault conditions. One generator circuit breaker will be provided for each turbine generator complete with all accessories and a local control panel. The rated continuous current and rated voltage will be coordinated with the Insulated Phase Bus duct (IPBD) rating. The main current carrying parts will be 55 designed to withstand without damage for a period of one second, the effects of a short circuit due to a fault at either the generator transformer LV side or the generator side. 6. The generator circuit breaker with SF6 insulated poles (single pole construction) will be built on a common base frame with ganged operating mechanism and local control panel for test and maintenance operation, assembled to form a three phase unit. GENERATOR BUS DUCT 7. The terminals of the generator will be connected to the generator transformer through a Generator Circuit Breaker (GCB) using Isolated Phase Bus Duct (IPBD). Short circuit withstand capability of IPBD will be decided based on the fault level contribution from the Generator and grid transformer and rated for 1 sec. The bus duct will be natural air cooled and will run partly indoor and partly outdoor. The bus duct installation will be complete with generator line side and neutral side current transformers and line side voltage transformers, required for protection, metering and voltage regulation. Surge protection equipment consisting of lightning arrestors and surge capacitor with suitable discharge characteristics to suit the generator basic insulation level will be provided. Generator Isolated Phase Bus Duct (IPBD) Sl. No. Particulars Rating 1. Type of Bus Duct IPBD / Natural air cooled 2. Nominal Service Voltage / frequency 21 kV / 50 Hz 3. Rated voltage 24 kV 4. Continuous current rating 22,000 A Basic impulse insulation level (1.2/50 5. 6. 125 kV peak. micro-sec) Bus bar conductor material Aluminium 56 7. (a) VT & SP cubicle (b) Voltage transformer 3 kV / 110 / 21000 / 110 / 3 V/ 3 V, 3 nos., 100 VA / ph. (c) Lightning Arrestor 24 kV Metal oxide type, with nominal discharge current of 10 kA. 8. Bus bar material as per IS 5082 GENERATOR TRANSFORMERS (GT) 8. The GT will be either 3 Nos. 270 MVA, 2 winding, single-phase banks or one three phase 810 MVA rating transformer, ONAN / ONAF / OFAF cooled and will be provided with on-load tap changer having taps in steps of 1.25%. In case of single phase option, one additional limb (single phase bank) will be procured as spare for the station. The HV side neutral will be solidly earthed. Lightning arrestors will be provided near the generator transformer. The HV terminals of the transformers will be connected to the associated bays in 400 kV GIS thru busbars. 9. The rating and details of the generator transformer are as in Table–IX.1 below : Table – IX.1 Generator Transformers Sl.No Particulars Rating 1 Type of cooling ONAN / ONAF / OFAF 2 Rating 3x1 Phase 165/220/275 MVA or 3 Phase 486/648/810MVA (ONAN/ONAF/OFAF). * 3 No load voltage ratio 21 kV / 420 kV 57 Sl.No Particulars Rating 4 Vector group YNd1 5 Percentage impedance 16% * 6 Type of tap changer On Load 7 Tap range +10% in steps of 1.25%. * 8 Impulse voltage withstand (1.2/ 50 micro-sec) 1300 kV peak for 400kV and 9 125 kV peak for 21kV Terminal connection HV side Terminals on HV side bushings for 400kV GIS MV Side connection. Throat type with matching flanges for connection to IPBD. 10 Applicable standard IS 2026 / IEC 60076 Note : * - final values to be firmed up during detailed engineering. EVACUATION OF POWER 10 Considering the capacity of plant and as 400kV system is available at close proximity to the plant, power evacuation is proposed to be done at 400 kV level. Hence 400 kV Gas Insulated Substation will be installed in the plant. The start up power would be supplied to the unit and station transformers from 400 kV GIS by back charging the generator transformer. 11 The enclosed key one line diagram shows the arrangement of circuits in the 400 kV GIS. The 400 kV GIS will have the following bays: a) Two Generator Transformer Bays b) Four line bays. 12 The power generated in the power plant is proposed to be evacuated on 400 kV network through double circuit triple moose conductor from power plant to GETCO 400 kV substation which is about 140 km from the plant. For this purpose, GETCO shall have to carry out the required studies for augmentation or up gradation of the existing 400 kV network for reliable power evacuation. It is also proposed to evacuate power to CTU network through PGCIL 400 KV line to Bhachau. 58 Space shall be provided in the proposed power plant switchyard for one additional bay for future use. 400KV GIS DESIGN 13 Two main busbar -switching scheme is proposed for 400 kV GIS considering its high reliability, flexibility of operation and maintenance and keeping in view the general practice followed for 400 kV GIS System. 14 SF6 circuit breakers are proposed because of its proven performance and world wide experience. 15 The 400kV switchyard will be a Gas insulated indoor type considering the fact that the location is not highly polluted GIS communication and Protection Philosophy: 16 To ensure reliable operation of the various feeders/bays such as Generator Transformer bays, line bays etc. state of the art numerical protection will be provided with required redundancy. In order to communicate between substations both at power plant and remote grid substation either conventional PLCC or optical fibre ground wire (OPGW) would be provided in line with the practice being followed at the remote grid substation. 17 For each of the outgoing lines in 400 kV GIS, precision energy metering will be provided. The technical parameters of 400 kV switchyards are indicated in Table – IX.2 Table-IX.2 400 kV GIS Sl. No Parameters 400 kV GIS 1.0 Technical Data 1.1 Design Voltage Levels (a) Nominal Voltage 400 kV (b) Highest system voltage 420 kV (c) Basic impulse level 1425 kV peak. (d) Fault level (kA rms for 1 sec) 50 kA rms 59 Sl. No Parameters 400 kV GIS 2.0 Circuit Breakers 2.1 Type of breaker SF6 2.2 50 kA rms / 125 kA peak. 2.3 Short circuit breaking and making current Applicable standards 3.0 Isolators 3.1 Type of mounting and execution Centre break, horizontal upright 3.2 Applicable Standards IS 9921 / IEC 129 4.0 Current Transformers 4.1 Type Indoor 4.2 Accuracy class metering cores 0.2S for revenue metering 0.5 for other. 4.5 Applicable standards IS 2705 / IEC 60044-1 5.0 Voltage Transformer 5.1 Type Indoor 5.2 Revenue metering Electro Magnetic Voltage Transformers (EMVTs) 5.3 Other purpose Capacitive Voltage Transformers (CVTs) 5.5 Applicable standards IS 3156/ IEC 60044-1 6.0 Lightning Arrestor 6.1 Type Metal oxide, gap less 6.6 Applicable standards IEC – 60099 7.0 Line traps 60 IEC – 60056 Sl. No Parameters 400 kV GIS 7.2 Quantity Depending on the scheme (PhasePhase or Phase Earth) 7.3 Applicable standards IEC 60353 8.0 Coupling devices 8.1 CVT will serve this purpose. IEC 60481 AUXILIARY POWER SUPPLY SYSTEM 18 The proposed auxiliary power supply system is shown in enclosed key line diagram. The auxiliary power supply required for the various drives like Boiler Feed Pumps (BFP), ID/FD fans, CW pumps ranges from 200 KW to several Megawatts. Based on the techno-economical studies, the voltage level of 11 kV and 3.3 kV are proposed for these drives. 19 Various auxiliaries will be supplied at the following nominal voltages depending upon their ratings and functions: a) 11000 V, 10%, 50 Hz, -5 to +3%, 3 phase, 3 wire, medium resistance grounded AC supply for motors rated above 1500 kW. b) 3300 V, 10%, 50 Hz, -5 to +3%, 3 phase, 3 wire, medium resistance grounded AC supply for motors rated above 200KW and up to 1500KW. c) 415 V, 10%, 50 Hz, -5 to +3%, 3 phase, 3 wire, solidly grounded AC supply for motors rated 200 kW and below and other L.T. services. d) 230 V, 10%, 50 Hz, -5 to +3%, 1 phase AC supply for lighting, space heating of motors and panels, single phase motors, etc. e) 220 V, ungrounded DC supply for emergency power to critical loads of electrical system. f) 220 V, ungrounded DC supply for protection, control and indication. g) 110 V, 1 phase, grounded AC supply for AC control circuits. h) 24 V DC supply for instrumentation and control systems such as closed loop controls and open loop controls. 61 i) 230 V, 1 phase AC Uninterruptible Power Supply for plant instrumentation and control system. j) 415 V, 10%, 50 Hz, -5 to +3%,, 3 phase, 4 wire Diesel Generator for emergency back-up. 20 At this stage for the evaluation, auxiliary power consumption is considered as 6.5% of the unit capacity. The auxiliary loads will be segregated as unit loads and common station loads. 2 x 100% rating Unit Transformers (UTs) will cater to unit loads 100% rating station transformer (ST) will cater to station loads under normal operating conditions. The start-up power for the auxiliaries will be supplied through generator transformer, station transformer and unit transformers. Once the unit is started and the generator picks up rated speed and voltage, the unit will be synchronised with grid supply by closing generator circuit breaker. One Motor driven BFP and two turbine driven BFPs will be provided for each unit. The motor driven BFP will be used as a standby and also will run during starting of the unit. STATION TRANSFORMERS (ST) 21 Two station transformers of three – winding, three phase, 65/40/25 MVA, 21/ 11.5/34.5kV, with off circuit changer ±10% in steps of 1 . 2 5 % will provided. These STs will be connected through GCB to Generator Transformer. Each ST will be sized to cater to 100% station loads + outage of one UT. The ratings and details of the station transformers proposed are as given in Table–XIII.3. Table–IX.3 Station Transformers Sl. Particulars Station Transformers No. 1 . 2 . 3 . 4 . 5 . 6 . Type of cooling ONAN / ONAF Rating 65/40/25 MVA* No load voltage ratio 20/11.5/34.5kV Vector group Dyn11yn11 Type of tap changer Off-Circuit Tap range ± 10% in steps of 1.25% 62 7 . 8 . BIL 950 kV peak Terminal connections: 20kV Side Throat type with matching flanges for connection to IPBD. 11kV side Throat type with matching flanges for connection to SPBD. 9 Applicable standard IS 2026 . Note : * - final values to be firmed up during detailed engineering UNIT TRANSFORMERS (UT) 22 Two (2), two winding unit transformers will be provided for each unit. These will be 63/31.5/31.5 MVA rating, 21/11.5/11.5 kV, 3 phase, 50 Hz, with +10% offcircuit taps in steps of 1 . 2 5% on the HV side. The transformers will be ONAN/ONAF cooled with a vector group of Dyn11yn11, The 11kV side will be medium resistance earthed. The details of UT are indicated in Table–IX.4. Table–IX.4 Unit Transformers Particulars Sl. Unit Transformer No. 1 Type of cooling ONAN/ONAF 2 Rating 63/31.5/31.5 MVA* 3 No load voltage ratio 21kV / 11.5 / 11.5 kV 4 Vector group Dyn11yn11 5 Type of tap changer OCTC 6 Tap range +10% in steps of 1.25% * 7 Impulse withstand (1.2/50 125 kV peak for micro- sec) 21 kV and 75 kV peak for 11.5 kV 8 Power frequency withstand HV/LV 63 (rms) 70 kV for 21 kV Particulars S Unit Transformer l. N and 28 kV for 11.5 o KV (rms) . 9 Applicable Standards IS 2026 / IEC 60076 Note : * - final values to be firmed up during detailed engineering. 23 The unit transformers will supply power to the 11kV unit switchgear as shown in the enclosed key line diagram. As far as possible, the unit loads will be distributed equally on each 11kV unit switch gear so that in case of outage of any one bus, it would still be possible to operate the unit at partial load. UNIT AUXILIARY TRANSFORMERS (UAT) 24 Two (2) no.s , unit auxiliary transformers will be provided for each unit to feed 3.3kV unit auxiliary motor loads. These will be 16 MVA, 11/3.45 kV, 3 phase, 50 Hz, with +5% off-circuit taps in steps of 2.5% on the HV side. The transformers will be ONAN cooled with a vector group of Dyn1. The 3.3kV system would be medium resistance earthed. The required number of 11kV feeders from station switchgear would be provided for Coal Handling system, Ash Handling System, AC & Ventilation System & Other systems as required to the plant. AUXILIARY / SERVICE TRANSFORMERS 25 The required number of transformers will be provided depending on service / location / segregation of the loads, though the service transformers are indicated in the enclosed key one line diagram tentatively. These transformers will be rated at 2500 / 2000 / 1600 / 1000 kVA, 11kV/433V with a vector group of Dyn11 as per actual requirement. They will supply power to the 415 V auxiliaries of the unit and station loads. The neutral of these transformers will be solidly earthed. The transformers will be provided with + 5% off-circuit taps in steps of 2.5% on 64 the HV side. The service transformers may be dry type and will be finalised during detailed engineering. 11 kV SWITCHGEAR 26 The 11kV switchgear will comprise draw-out type Vacuum / SF6 circuit breakers housed in indoor, metal-enclosed cubicles and will cater to all 11kV motors, 11kV/433V transformers. The switchgear will be equipped with control, protection, interlock and metering communication features as required. Technical parameters of 11kV switchgear are given in Table-IX.5. 3.3 kV SWITCHGEAR 27 The 3.3 kV switchgear will comprise draw-out type Vacuum / SF6 circuit breakers housed in indoor, metal-enclosed cubicles and will cater to 3.3 kV motors. The switchgear will be equipped with control, protection, interlock and metering features as required. Technical parameters of 3.3 kV switchgear are given in Table-IX.5. Table-IX.5 11 kV and 3.3 kV Switch Gear S.No Particulars 11 kV Switchgear 3.3 kV Switchgear 1.0 Switch gear 1.1 Nominal system voltage 11kV, 3 Ph., 50 Hz 3.3kV, 3Ph., 50 Hz 1.2 System Neutral Earthing 1.3 Power frequency withstand /impulse withstand voltage Medium resistance earthed 28 kV rms / 75kV peak Medium resistance earthed 10 kV rms / 40kV peak 1.4 Short time rating ( 1 sec) 40kA rms /100kA peak 1.5 Applicable standards IS 3427 40kA rms / 100kA peak IS 3427 65 S.No Particulars 2.0 Circuit breaker 2.1 2.2 Type Operating duty 2.3 2.4 Rated current Rated breaking/making current Short time rating Mechanism 2.5 2.6 3.0 3.1 3.2 Contactors Type Application 4.0 4.1 HRC Fuses Type 4.2 Application 4.3 Symmetrical Breaking capacity Applicable standards 4.4 11 kV Switchgear Vacuum / SF6 0–0.3sec-CO3min-CO As required 40kA rms/100kA peak 40 kA for 1.0 sec. Motor charged spring closing 3.3 kV Switchgear Vacuum/SF6 0–0.3sec-CO3min- CO As required 40kA rms/100kA peak 40 kA for 1.0 sec. Motor charged spring closing Vacuum Motors in CH system Current limiting HRC fuses Short-circuit protection of 3.3 kV motor feeders with vacuum contactors 40 kA rms IS 9224 66 415 V SYSTEM 28 The 415V, 3 phase, 3 wire power for the 415V auxiliaries will be obtained from 11kV/433V transformers. The system will be a solidly earthed system. For maximum reliability, duplicate power supplies with auto changeover facility will be provided for the essential power and motor control centres. The 415V switchgear will be of metal enclosed design with a symmetrical short circuit rating of 50 kA for 1 sec. All power and motor control centres will be compartmentalised. The switchgear will be of single / double front execution depending on final layout and will be finalised during detailed engineering. They will be of fully draw-out design. The circuit breakers will be of air break type. Motor starting will be direct on line. All LT motors will be controlled by MPCB, electro-magnetic type contactors provided with ambient temperature compensated, time lagged, hand reset type thermal overload relays, having adjustable setting with built-in single phase preventer backed up by HRC fuses for protection against short circuits. The technical particulars of 415V switchgear are as given in Table–IX.6. Table-IX.6 415 V Switchgear Sl. Particulars Rating No . 1.0 Switchgear 1.1 Rated voltage/No. of phases/frequency 415V / 3 Ph / 50 Hz 1,2 System neutral earthing Solidly earthed 1.3 One minute power frequency withstand voltage 1.4 (a) Power circuit 2500 V (b) Control circuit 1500 V (c) Aux. Circuits connected to CTs 2000 V Maximum allowable Temperature of Bus bars 900C 67 Particulars Sl. Rating No. 1.5 Short circuit withstand of Bus bars 50 kA for 1 sec. 1.6 Dynamic rating of busbars 100 kA peak 2.0 Circuit breakers 2.1 Type 2.2 Operating duty 2.3 Rated breaking current / Making current 2.4 Short circuit withstand current 3.0 Starters 3.1 Type DOL 3.2 Continuous & Intermittent 3.3 Contactor rated duty as per IS 2959 & IS 8544 Utilisation categories as per IS 2959 4.0 Applicable standards IS 2516 Air break, motor charged spring closing mechanism 0 – 3 min – CO3 min – CO 50 kA at 415V AC & 0.25 pf / 100 kA 50 kA for 1 sec. AC 3 & AC 4 DC SYSTEM 29 DC loads will be divided into two categories ie, Unit DC loads and Station DC loads. Each category of loads will be catered by separate battery and charger system. Two (2) nos. 220V 100% rated batteries with associated float cum boost chargers will be provided for each system. Each battery will be capable of catering to 100% of power and control loads of Unit and Station systems respectively. A separate DC system will be provided for 400kV GIS. GIS DC system will have two (2) nos. 220V 100% rated batteries with associated float cum boost chargers. Separate 48V battery and chargers will be provided in the GIS control building to cater to the PLCC loads if PLCC is provided. 68 The batteries will be of stationary lead acid Plate type complete with battery racks, porcelain insulators, inter-cell and inter-tier connectors. The chargers will be of silicon rectifier type with automatic voltage control and load limiting features. EMERGENCY POWER SUPPLY 30 To enable the unit to shutdown safely during complete A.C supply failure in the station, certain important plant auxiliaries will be provided with a reliable A.C power supply through a separate source. For this purpose, one (1) 415V quick starting diesel generator set with automatic mains failure (AMF) will be provided for each unit. The tentative rating of the DG set will be 1500 kVA. 31 The diesel generator will feed a separate emergency 415V switch gear, to which all the essential loads such as the A.C emergency bearing lube oil and seal oil pumps, turning gear motor, battery chargers, emergency lights, and essential instrument power supply feeders will be connected. When the normal A.C supply is healthy, the emergency switchgear will be fed through a tie from the unit service switchgear. When the normal A.C supply fails, the DG set will start automatically and will feed the loads connected to the emergency switchgear. When the normal A.C supply is restored, these essential loads will be manually changed over to the normal power supply. UN-INTERRUPTIBLE POWER SUPPLY SYSTEM 32 230 V single phase A.C uninterruptible power supply will be provided for the Plant DCS/Instrumentation system. This power supply will be derived from parallel redundant with static bypass un-interruptible power supply system having two (2) sets of converters, inverters with a back up battery. Also a standby AC supply will be provided as a back up to the inverters, which will be switched on through static switch in case of inverter failure. GENERATOR AND GIS PROTECTION AND CONTROL 33 The details of the protections that will be provided for the various electrical equipment viz., Generators, Generator transformers (GT), Unit / Station transformers, unit / station service transformers, 400 kV switching equipment, 400 kV lines, motors, switch gear etc., are indicated below. 69 34 The selection of the protective scheme will be based mainly on reliability, sensitivity, selectivity and technical merits. All main protections will be of fast acting type in order to isolate the faulty system from the healthy system in the shortest possible time, to minimise damage to the equipment and ensure continuity of power supply, if possible. Generator Protections 35 Two multifunction numerical Generator protections operating on different principles and housed in generator relay panels (GRP) will be provided for each unit. The panels will be located in the unit control room / Relay room. The following minimum protections are proposed to be provided in the GRP and the protections will be divided into two groups; each group being 100% redundant. so that even if one group of protections is not available or under maintenance, the generator is protected by the other group. a) Generator differential protection (87G1) b) Generator stator 0 – 95% earth fault protection (64 GI) c) Generator stator earth fault (95 – 100%) protection (64G2) d) Generator back-up stator earth fault (0-95%) protection (64G3) e) Rotor earth fault protection (2 stage) (64F1 and F2) f) Generator negative phase sequence protection (46GI 46G2) g) Generator reverse power protection (32G1 32G2) h) Generator loss of excitation protection (40G1 40G2) i) Generator pole slipping protection (78G) j) Generator under frequency protection (81G1 81G2) k) Generator over-voltage protection (59G1 and G2) l) Generator backup impedance protection (21G) m) Generator stator overload protection (50GS) n) Generator VT fuse failure protection (60G) o) Dead machine protection (61B) p) Generator field over-voltage protection (59F) q) Generator, Generator Transformer and Unit Transformers over-fluxing protection (99G). 70 r) In case of static excitation, excitation transformer protection will be a part of the excitation system. Generator Transformer Protections 36 The following protections will be provided for the Generator Transformer: a) Generator transformer HV winding restricted earth fault protection (64GT) b) Generator, generator transformer and unit transformers overall differential protection (87 0A) c) Generator transformer differential protection (87GT) d) Generator transformer over-current and earth fault protections (51GT, 51NGT) e) Generator Transformer Over fluxing protection (99GT-1 99GT-2) f) Differential protection for 400kV Busbar line from GT to GIS. g) Buchholz (63), winding temperature (49 WT) and oil temperature (49 0T) protections, OLTC buchholz h) Generator transformer pressure relief protection (63PTX) i) Generator transformer fire protection trip, oil level low, cooler trouble alarms. 21kV /11.5kV Unit Transformer, 11kV /3.3kV Unit Auxiliary Transformer Protections 37 The protections that will be provided for the unit transformers/ unit auxiliary transformers: a) Differential protection (87) and short circuit protection (50) b) Back-up over current protection on HV side (51) c) Instantaneous phase overcurrent protection on HV side (50) d) Back-up over current protection on LV side (51) e) Back-up earth fault protection on LV side (51N) f) Buchholz (63), winding temperature (49 WT) and oil temperature (49 0T) protection g) Pressure relief protection (63PTX) 71 h) Fire protection trip (63 RTX) Station Transformer Protections 38 The following protections will be provided for the station transformers: a) Differential protection (87T) b) Instantaneous phase overcurrent protection on HV side (50) c) IDMT phase overcurrent protection on HV side (51) d) IDMT earth fault protection on HV side (51N) e) IDMT phase overcurrent protection on LV side (51) f) IDMT earth fault protection on LV side (51N) g) Restricted earth fault protection (64REF) h) Neutral displacement protection (64N) i) Buchholz (63 AX 63TX), winding temperature (49WT AX 49WT TX) and oil temperature (49 OAX 49 OTX) protection. j) Pressure relief protection (63 PTX) and Oil level (63 OLAX). k) Fire protection and trip (63 FRTX) 11000 V / 433V Service Transformer Protections 39 The following protections will be provided for service transformers: a) Over current protection on HV and LV sides (51) and short circuit protection (50) on HV side b) Earth fault current protection on HV and LV sides (50N 5IN). c) Buchholz (63), winding temperature (49 WT) and Oil temperature (49 0T) protections. 400 kV Line Protection 40 The 400 kV lines will have the following protections: (a) Distance protection (21-1) (b) Distance protection (21-2) and Directional inverse time phase over current with high set unit (67 / 50) 72 (c) Fuse fail relay (FFR) for each secondary of CVT (d) Directional inverse time earth fault protection (67N) (e) Under voltage relays for live – line / dead bus and dead – line / live bus closing and safe grid establishment (27-1, 27-2, 27S) (f) Fault locator (FL) (g) Fault recorder (FR) (h) Neutral impedance replica of distance relay (21NTR) (i) No voltage protection 400 kV Bus Bar Protection 41 Redundant type high-speed bus fault numerical relay is proposed for detecting the fault on 400 kV buses. The bus bar protection scheme will have detecting elements for each of the main bus and one check zone element. The main and check zone elements will be connected two different secondaries of CTs and tripping will be initiated only when respective bus element and check zone elements operate. Bus wire supervision relays to guard against faults in the CT secondary wiring and bus wire shorting relay to short CT secondary bus wires on fault are also proposed. The scheme shall be expandable to accommodate future lines. Local Breaker Back-up (50 LBB) 42 All 400 kV circuit breakers including generator transformer breaker will be provided with local breaker back-up protection. For generator transformer breaker, an additional relay will be provided to detect breaker failure for ground and phase fault in the generator circuit and other low magnitude faults also. 43 The local breaker back-up protection relay will be numerical relay. This will provide protection against stuck breaker condition for the 400 kV system. This protection will be initiated by primary fault detecting relays and time delayed to permit the breaker to trip. Circuit Breaker Protection 73 44 All the trip coils of the circuit breakers will be supervised. The following protections will also be included: a) Pole discrepancy protection b) Trip coil supervision relay for each trip coil (98L1 to L6) c) Anti pumping device for breaker closing (94). Protection of 11 kV and 3.3 kV Motors 45 All 11 kV and 3.3 kV motors will be provided with the following protections: a) Thermal overload protection b) Overload alarm protection c) Instantaneous over current protection d) Locked rotor protection e) Negative sequence protection f) Differential protection (For motor ratings of 1000 kW and above) g) Earth fault h) Bus under voltage i) Bearing temperature monitor j) Water flow monitor for CACW motors(if applicable) k) Lube oil pressure monitor l) Winding temperature monitor Protection of 415 Volt Motors 46 Motors rated below 100 kW will have bi-metallic relays for thermal overload protection and HRC fuses for short circuit protection. Motors rated 100 kW to 200 kW will be provided with motor protection relays inclusive of locked rotor protection in addition to above. Composite motor protection relay comprising of thermal overload, short circuit, locked rotor, instantaneous over load, IDMT earth fault protection, negative phase sequence protection, self diagnostic monitoring & trip circuit supervision will be provided. 74 Power Supply and Lighting Circuits 47 The power supply feeders will have properly rated HRC fuses for short-circuit protection. Lighting circuits will be protected by miniature circuit breakers. 48 400 kV GIS CONTROL SCADA (Supervisory Control And Data Acquisition) system comprising of various controls, metering, indication, annunciation, synchronising, remote control functions, mimic diagram, sequence of events recording, etc., shall be provided for GIS. The controller shall be configured with redundant CPU. The redundant CPU shall be configured to operate as hot standby. All the SCADA switches and servers shall be located in switchyard control room. All SCADA servers Front End Processor servers (if any) shall be rack mounted. One (1) no. Operator Station for SCADA (for control and monitoring of complete 400 kV GIS equipment) shall be located in Central Control Room (CCR) of power plant and one (1) no. in GIS Control Room. One (1) no. Engineering Station shall be provided in the CCR to make the SCADA configuration changes and system settings. The Engineering Station shall also be configured as Operator Station to act as standby in case of failure of the Operator Station in CCR. The location for the GIS control shall be central control room (CCR) by default. But provision shall be made available in the SCADA to control the GIS from GIS control room also. It shall not be possible to control the GIS from two locations simultaneously. The required selection shall be provided in the operator station of CCR. The SCADA system shall be based on a de-centralised concept with bay oriented distributed intelligence devices, for safety and availability reasons. The offered SCADA system shall be of latest state of art design with capability to interface with bay control units (separate for each bay). 75 Relay panels pertaining to switchyard would be located in the switchyard relay room, which would be kept locked. The communication between the numerical relays and SCADA system shall be with fibre optic cable. CABLING SYSTEM 49 Power cables would be selected based on the following minimum criteria: a) Continuous circuit current rating b) De-rating factors for ambient temperature and grouping c) Short circuit rating of the circuit (not applicable for MV/LV fuse protected feeders) 50 d) Voltage dip e) Standardisation of cable sizes to reduce inventory The following types of cables will be used: a) For 11 kV system 11kV unearthed grade, stranded aluminium conductor, cross linked polyethylene (XLPE) insulated, extruded black PVC inner sheathed, galvanized steel wire armoured for three core or aluminium wire armoured for single core or unarmoured* and overall FRLS extruded black PVC sheathed cables conforming to IS : 7098. b) For 3.3 kV system 3.3kV unearthed grade, stranded aluminium conductor, cross linked polyethylene (XLPE) insulated, extruded black PVC inner sheathed, galvanized steel wire armoured for three core or aluminium wire armoured for single core and overall FRLS extruded black PVC sheathed cables conforming to IS : 7098. (c) For medium and low voltage system Power cables of 1100V grade, stranded aluminium conductor, cross linked polyethylene (XLPE) insulated, extruded black PVC inner sheathed galvanized steel wire armoured for three cores or Aluminum wire armoured for single core and overall FRLS extruded black PVC sheathed cables conforming to IS : 7098. (d) For control applications 76 1100 V grade annealed high conductivity stranded copper conductor, PVC insulated, PVC inner sheathed armoured and FRLS extruded black PVC outer sheathed cables conforming to IS : 1554. Conductor cross section will generally be 1.5 mm2. CT, PT and switchyard control circuits will use 2.5 or 4 mm2 copper conductor cables. (e) For instrumentation applications Stranded high conductivity annealed tinned copper conductor, multicore, PVC insulated, flexible, twisted pair / triplets, individually and overall shielded (for low level analog signals) and only overall shielded for digital signals, PVC inner sheathed, steel wire armoured and overall FRLS PVC sheathed cables. Conductor cross section will be 0.5 mm2. Individual / pair shielded and overall shielded twisted pair copper cables would be used for analog signals and overall shielded cables would be used for digital signals. All these cables are armoured. Overall sheath would be FRLS quality. The size of the wire would be 0.5 mm2 FRLS, 1.5 mm2 copper control cable would be used for cabling between MCC and Control system. Compensating cables will be provided for connecting the thermocouple inputs to the control system. 51. Cables would be laid in fabricated steel ladder type or perforated type cable trays in the station and other auxiliary buildings and upper elevations of the steam generator area. Between buildings, the cables would be laid in built-up trenches. Cables to other plant areas located far off from the station building would be directly buried in soil or carried on overhead racks. LIGHTING SYSTEM 52 Suitable illumination necessary to facilitate normal operation and maintenance activities and to ensure safety of working personnel would be provided. This would be achieved by artificial lighting using normal, emergency and DC lighting. 77 53 For yard illumination, floodlights would be installed at suitable locations to provide the requisite level of illumination. Pole-mounted high-pressure sodium vapour fixtures would be used for approach roads. 54 Generally, energy efficient fluorescent fixtures would be used for indoor illumination. A combination of high pressure sodium vapour and fluorescent fixtures would be used for the turbine building. For steam generator area and pumps area, high-pressure sodium vapour lamp fixture will be provided. 55 The illumination levels at different places would be maintained as per accepted norms. The lighting system would be designed to ensure uniform illumination. 56 Power distribution from the lighting transformers would be through 415V, 3 phases, 4 wire distribution boards. A suitable number of lighting panels would be located in each area. Power to the lighting panels would be supplied from the 415V, 3 phase, 4-wire distribution. 57 About 80% of the total light fittings would be connected to the normal 240 V AC lighting supply and the balance 20% to the station emergency bus fed from the DG set in the station building and steam generator areas. 58 Installite type DC emergency lights are envisaged at strategic points in the power station viz., near entrances, staircases, control rooms, etc. These would be provided with local battery back up for 3 hours, which would be normally off when AC power is available. These would be automatically switched on when the normal / emergency AC supply fails. In critical areas like control room, the DC lighting will be fed from the station DC supply. SAFETY EARTHING AND LIGHTNING PROTECTION 59 A safety earthing system comprising buried steel conductor earthing grid would be provided for the switchyard and other outlying areas. This would be connected to the earth grids in various buildings. The buried earth grids would be further connected to earthing electrodes. The selection of earth conductor sizes would be based on the applicable fault levels. 60 Lightning protection system comprising roof conductors, vertical air termination and down-comers would be provided for all structures whose calculated risk index requires protection as per applicable standards. 78 COMMUNICATION SYSTEM 61 For effective communication in the plant, public address system, private automatic branch exchange system (EPABX) and CCTV systems will be provided: Public Address System a) This system will have paging and party channels comprising handset stations with amplifiers, transmitters, receivers, sound proof booths, and loud speakers. This system will facilitate paging, communication and also private conversation as in conventional telephone. EPABX System b) The EPABX will be a state of the art digital system capable of interfacing with ISDN network. The ISDN network or PSTN network available at the project site would be suitably interfaced and the communication facility/feature would be extended to individual extension as required. The number of extension will be decided during detailed engineering. Walkie-talkie System c) Walkie-talkie systems with necessary repeater / booster station will be provided for mobile communications. CCTV System d) Closed Circuit Television (CCTV) system shall be provided for monitoring plant facilities for fire, confirmation of calamities, and security check. The CCTV system will include required number of Pan-Tilt-Zoom (PTZ) cameras and Fixed cameras. PTZ cameras will be installed in the suitable locations of all over the plant area and fixed cameras will be installed along the fence. CCTV Monitors will be located in the various control room in the plant and CCTV control units will be located in the central control room. 79 FIRE DETECTION / ALARM AND FIRE PROOF SEALING SYSTEM 62 Addressable type multi criteria detector based fire detection and alarm system would be provided to facilitate visual and audible fire detection at the incipient stage of fire in strategically important areas of the power station. This system will comprise manual call points located at strategic locations in areas which are normally manned and automatic addressable type multi-criteria detectors located in plant areas, such as control room, switchgear room, battery rooms, etc., to detect fire at an early stage. Linear heat detectors will be provided for the cable gallery and conveyors. Infrared type amber detector will be provided for the conveyor gallery. Fireproof sealing will be provided for all cable penetrations through walls and floors to prevent spreading of fire from one area / floor to another. ELEVATORS 63 One freight-cum-passenger elevator of capacity 1360 kg and speed of 0.75 m/sec will be provided in each of the steam generator areas to serve major platforms of the steam generators. A separate 8 passenger (550kg), 1m/sec elevators will be provided for catering to the station building and electrical switchgear buildings. This elevator will have access to different floors. CATHODIC PROTECTION 64 Based on the water and soil analysis, cathodic protection will be provided for all requisite equipment. The type of cathodic protection (sacrificial or impressed current) will be finalized during detailed engineering. 80 CHAPTER – X PLANT WATER SYSTEMS 1 The scheme of water systems for the proposed 2x660 MW unit at Salaya is shown in Exhibit-03. Sea water would be used for condenser cooling, cooling of SG and TG auxiliaries and various other requirements like SG makeup, service and potable water. The water systems consist of various sub-systems listed below and discussed in the subsequent paragraphs of this chapter. 2 a) Sea water Intake system b) Condenser cooling water system c) Cooling water (CW) make up system d) Auxiliary cooling water (ACW) system e) Water treatment (WT) systems f) Service and potable water system g) Fire protection system h) Effluent disposal system i) Chemical laboratory equipment SEA WATER INTAKE SYSTEM The daily seawater requirement is estimated to be about 330180 m3/day ( for phase II). The main source of water for the plant is from the Arabian sea, which is about 15 km from the power plant site. The seawater will be pumped by 4 Nos seawater intake pumps. (3 working + 1 standby). Each of capacity 7500 m3/hr. These seawater intake pumps will be located in the offshore seawater intake pump house, which is a common facility for existing phase -I and proposed phase -II 81 3 PLANT WATER REQUIREMENT The total plant water requirement is summarized in Table –X.1 TABLE-X.1 Plant Water Requirement Sl. No Description 1 Cooling Tower Blow down 8690 208560 2 Evaporation & Drift Loss 2659 63816 3 Cooling water makeup for condenser and SG & STG auxiliaries with margin 11350 272400 4 Sea water as to desalination plant 2408 57792 5 Water requirement for coal and ash handling system HVAC makeup, Misc. requirements Total Makeup for Sea 6 water requirement x660 MW units Estimated quantity for 2x660 MW M3/hr M3/day feed for - 13758 2 82 Quality Sea Water Sea Water Desalinat ed water 330180 Sea Water 6 CONDENSER COOLING WATER (CW) SYSTEM An open type recirculation type of cooling system with cooling tower is proposed for CW system. The system will consist of two induced draught cooling tower (IDCT) for each unit, CW pumps, CW conduits (with valves, expansion joints and instruments as required) and CW treatment system. 6.1 Cooling Water (CW)Pumps 5 x 50% capacity CW pumps (2 x 50% pumps for each unit) each of capacity 42,600 m3/hr are proposed for the 2 x 660 MW units to meet the CW flow of 77400 m3/h with 10 % margin towards impeller wear. The type of pump would be mixed flow type with concrete volute, SS316L/ Duplex SS impeller/shaft. These pumps would be installed in individual chambers connected to the CW forebay. Each pump chamber would have provision for installing coarse screens and stop logs. The pumps would be located indoors in a pump house. CW chemical dosing system will be housed in a room adjoining the CW pump house. Handling of pumps would be through an EOT crane of suitable capacity. Handling facilities would also be made available for screens and stop logs. 6.2 Cooling Towers It is proposed to install two (2) induced draught cooling towers, for each unit of 660MW, each capacity 42600 m3/hr. The cooling water would be collected in a RCC basin. The cooling tower would be designed for a cooling range of 100C. The cooling tower shall be complete with basin associated supporting structure and foundation etc. 6.3 RC Channels The total CW flow of 170400 m3/hr from all the cooling tower basins is proposed to be 83 conveyed by gravity to the common CW forebay and CW pump chambers through RC rectangular open channels. The channels will be designed to accommodate maximum level fluctuations expected under transient flow conditions. 6.4 CW Forebay and sumps The total CW flow of 170400 m3/hr from all the units would be discharged from the open channel to a common forebay and CW pump chambers. The forebay will be designed to ensure equal distribution of flow to the CW pumps as well as to limit the entrance velocity at the CW pump chambers. The top level of the forebay walls will be fixed on the basis of maximum upsurge expected in the forebay, when all the CW pumps trip under normal water level condition. The sump level of the pump chamber is fixed so as to ensure adequate submergence for the CW pumps as per HIS standards. 6.5 CW Inlet and outlet conduits From the CW pump house, cooling water would be pumped to the condensers located in the station building, through mild steel conduits with internal lining. Expansion joints and motor operated butterfly valves will be provided on these conduits at CW pump discharge, as well as at condenser inlet/outlet. The hot water from each condenser to cooling tower will be conveyed through similar independent mild steel conduits. Both, cold and hot water conduits will be laid underground. 6.6 Valves and Specialities Motor operated butterfly valves would be provided at the discharge of the CW pumps and at the condenser inlet / outlet piping to facilitate isolation and control. Expansion joints are proposed in the CW pump discharge lines and condenser inlet and outlet lines to take care of any misalignment, thermal expansion etc., and also to facilitate erection and maintenance. CW pumps and their respective discharge valves would be suitably interlocked to facilitate coordinated operation. 6.7 Condensor On Load Tube Cleaning System ( COLTCS) Condenser on-load tube cleaning system (COLTCS) using sponge rubber balls would be provided to keep the condenser tubes clean by removing the scaling. 84 6.8 CW Blow Down and Make-Up Water Requirement Make up water requirement of CW system is obtained as the sum of drift and evaporation losses from the cooling tower and blow down from the CW system (by way of water drained from the hot water conduit of the CW system).Table-X.2 indicates the CW blow down / make up water requirements for the cooling water system. Table –X.2 CW System Make-up Requirement Sl. No. Item Quantity Quantity (m3/hr) (m3/day) 1 Cooling Tower (Evaporation + Drift Losses) 2659 63816 2 Condenser CW System Blow down 8690 208560 3 CW Make-up requirement (item 1 + item 2) 11350 272400 4 Concentration Ratio ‘C’ (item 3 / item 2) 1.3 1.3 The analysis of sea water (make up water) is presented in Appendix-2. The cooling water system is proposed to operate with a COC of 1.3. Suitable chemical dosing system will be provided for control of water chemistry in the CW system. Chemicals will possess anti scaling, anti corrosive and anti dispersant properties. The blow down requirements and the total make up water requirement is estimated based on same COC. Blow down water from the CW system would be led to the blow down weir tank from where the sea water would be led in to the sea by gravity. Make up water requirement of CW system would be about 11350 m3/hr. Four (4) (3 Working and 1 standby) Sea Water pumps would be provided to cater the makeup water requirements. These pumps would directly draw water from the sea. 7 AUXILIARY COOLING WATER (ACW) SYSTEM The ACW system will meet the cooling water requirements of all the auxiliary 85 equipment of the TG and SG auxiliary coolers. The total estimated cooling water (passivated DM water) requirement for the above auxiliaries for one unit of 660 MW plant is 3500 m3/hr. A closed loop system using passivated DM water is proposed for the ACW system. The DM water will be circulated through the auxiliary coolers by 3 nos (3x50%) closed loop cooling water (CCW) pumps, each of 2860 m3/hr capacity. The hot water from these auxiliaries will be cooled in the 3 x 50% capacity plate type ACW heat exchangers by the circulating water tapped from the main CW circuit and pressure boosted by ACW Booster pumps. 3 nos. of ACW Booster pumps (3x50%),each of 3300 m3/hr capacity, would be provided for each 660 MW unit. A CCW overhead tank will be provided to ensure positive suction to the CCW pumps and also serve as the source of make-up to the ACW system. Normal make-up to the CCW over head tank will be provided from the condensate extraction pump discharge. Initial fill for the tank will be provided from the boiler fill pumps discharge. 8 WATER TREATMENT (WT) PLANT 8.1 DM plant would meet the requirement of steam generator (SG) feed water make up, and ACW system make-up. DM water requirement is calculated based on SG feed water make up at 1% MCR. DM plant would consist of mixed bed (MB) units. The period between regenerations for each stream of the MB units would be 72 hours. MB units would be of mild steel construction with five (5) mm thick rubber lining internally and all associated piping / valves of the unit would be either rubber lined or SS. DM water from the mixed bed unit would be stored in DM water storage tanks. DM water transfer pumps would be used to transfer DM water up to the condensate storage tank. The condensate storage tanks would be sized to meet maximum requirement of DM water when one unit is under start-up. The MB unit would be designed to limit the silica less than 0.02 ppm. 86 8.2.5 Regeneration System 33% hydrochloric acid/98% Sulphuric acid and 48% sodium hydroxide would be used as regenerants for the purpose of regeneration of MB units. The equipment of regeneration system shall comprise bulk acid and alkali storage tanks (the tanks would be sized for storing acid and bulk alkali for regeneration requirements for both the streams of MB unit for 30 days), acid / alkali unloading pumps, 2x100 % mixed blowers, acid / alkali solution preparation cum measuring tanks and regeneration pumps, etc. Regeneration equipment for Condensate Polishing Units(CPU) would also be located in the same area of MB regeneration system. 8.2.6 Neutralising System The acidic and alkaline effluents from DM plant/CPU would be led to the neutralising pit, which would be in two (2) compartments to facilitate maintenance and cleaning. Acid or alkali would be added to the neutralising pit depending on nature of effluents from DM plant to neutralise the effluent collected in the neutralising pit. Two (2 x 100% capacity) nos. of neutralising pumps, each of 50 cu.m / hr. capacity and of SS 316 material of construction are proposed to re-circulate and dispose the neutralised effluents to the central monitoring basin (CMB). The neutralising pit would be RCC lined with acid alkali proof tiles. 8.2.7 Mode of Operation of DM Plant The complete mode of operation of DM plant and Sea water Pre treatment plant would be automatic for which a Programmable Logic Control (PLC) based system would be provided. 9 SERVICE AND POTABLE WATER SYSTEMS Service water system will supply water required for ventilation, HVAC system, coal handling system and other miscellaneous water requirements such as canteen, toilets etc. Two (2) horizontal service water pumps (1 W + 1 S) each of 25 m3/hr capacity are proposed. Service water pumps will pump water from the desalinated water storage tank to a overhead tank from where water would be led to consumer points by gravity. The desalinated water storage tank caters to the water 87 requirements of 2x660 MW units. Potable water would be made available by EOL to the Potable water tank from where the potable water would be distributed by gravity. 10 FIRE PROTECTION SYSTEM The fire protection system will be common for the entire plant. The plant is designed to provide a safe operating environment for equipment and personnel. This is achieved by laying out equipment with sufficient separation and segregation to minimize the risk from fire and explosion, and by selection of suitable equipment and materials Hazardous areas like oil, coal storage yard and cable areas are identified and suitable equipment is selected for use in such areas. A manual and automatic fire detection and alarm system is provided, with detection device selected to suit particular risks. A control system designed to provide operating and fire brigade staff with sufficient information to identify and respond correctly to any fire detected. Automatic and manual extinguishing systems will be provided to limit the consequences of fires in major items of plant and to minimize consequential reductions in generating capacity. Hydrants are provided at strategic locations. Internal hydrants (wall hydrant cabinets) are provided within building where appropriate. Combined foam water hydrant cabinets are provided where necessary near oil risks. All equipment and escape routes will be clearly marked in the plant. The Fire protection system shall consist of the following a) Hydrant system covering all areas of the plant. b) High velocity water spray system for the protection of generator transformers and turbine lube oil tanks, Lube oil system equipment, unit auxiliary transformers inside the steam turbine building. c) Automatic deluge (medium velocity water spray) system for the protection of cable vaults/ cable galleries and coal conveyors. d) Portable extinguishers and hand appliances for extinguishing small fires in different areas of the plant. e) Mobile fire tender The fire protection system will be designed to confirm generally to the rules and 88 regulations of the TAC/LPA. Four (4) hydrant pumps cum spray pumps(2 motordriven + 2 Diesel engine driven) of horizontal, centrifugal type, of 273 m3/hr capacity will be provided. Two (2) jockey pump (motor-driven) of horizontal, centrifugal type, of 25 m3/hr capacity will be provided to keep the system pressurized. The diesel engine provided will be utilized in case of power failure to the main motor driven pumps. Hence even during emergency conditions also the fire water pumps can be switched on to meet any adverse effects. All the above pumps will be located in the desalinated water pump house. Starting of the pumps will be automatic and stopping of the pumps is manual. The desalinated water storage tank will have a dead storage of 3000 m3 of water for the fire protection system, in line with the regulations stipulated by TAC/LPA. The emergency fire water line would be tap off from the seawater intake pumps and connected to the desalinated water storage tank. Portable extinguishers will be provided in all the buildings of plant premises. Portable trolley mounted CO2 extinguisher of capacity 22.5 kg will be provided for control room 11 EFFLUENT DISPOSAL SYSTEM The liquid effluents will be collected and treated/recycled generally as per the following: a) The waste effluents from the DM plant and CPU regeneration waste will be collected in neutralizing pit and neutralized before pumping it to the Central Monitoring Basin(CMB). b) The oil water separator will collect water from the areas where there are possibilities of contamination by oil (transformer yard and fuel oil storage area) and the drains from such areas will be connected to an oil separator. From the oil separator the clear waste water will be led to the Central Monitoring Basin, while the oily waste sludge will be collected separately and disposed off. Other plant drains can also be led into the CMB. c) All the effluents collected in the Central Monitoring Basin(CMB) will be mixed and diluted. A portion of the water from the CMB would be pumped to be utilized for the ash disposal system. The balance quantity of water from the CMB would be utilized for gardening, 89 CHEMICAL LABORATORY EQUIPMENT 12 A suitable chemical laboratory shall be provided in the power plant to enable testing of coal, fuel oil, water, flue gas, etc. as required for normal operation of the power plant. The equipment to be provided shall be decided during the contract stage. In addition to equipment, the laboratory shall also be equipped with necessary laboratory glassware, reagent chemicals and laboratory furniture, as may be required. Metrological data recording facility would also be provided. 90 CHAPTER –XI COAL HANDLING SYSTEM GENERAL 1 This chapter covers the provisions for the coal handling system for the proposed 2x660 MW supercritical thermal power plant. It covers proposed & existing facilities for receipt of coal by ships, stacking near the power plant area, reclaiming from stockpile, crushing and conveying coal upto the steam generator bunkers. Flow diagram proposed is enclosed as Exhibit-4. DESIGN CRITERIA AND ASSUMPTIONS 2 The design criteria for coal transportation from berth conveyor, stacking, reclaiming, and conveying is based on the following functional requirements and assumptions: a) Coal handling system would be designed for the proposed 2 x 660 MW units only. b) Coal handling system has been designed based on TGMCR worst coal requirement of 300 TPH having a calorific value of 4900 kCal / kg. c) The plant load factor would be considered as 85%. d) The maximum lump size of the coal expected to be received at power plant would be around (-) 50mm. Hence crushing of coal not considered. e) In the existing facility, coal received from the berth is conveyed at the rate of 5000 TPH to stockyard and then reclaimed from stockyard at the rate of 1850TPH and conveyed by closed belt conveyors to the plant junction tower (JNT-2). Further from the JNT-2, one additional stream of belt conveyor of capacity 1000 TPH will be conveyed to phase-II and one stream of existing two conveyors of phase-I will be used as a standby for phase-II as well for phase-I f) A coal stockyard for stacking of coal required for a minimum period 30 days for 2 units existing unit (2x 600MW) and proposed unit (2 x 660MW) has been considered. g) Coal handling system would be designed based on 24 hours of operation per day. 91 3 3.1 SYSTEM CAPACITY The maximum daily requirement of coal for two units of phase II would be about 14391 tones. Coal would be conveyed to SG bunkers at the rate of 1000TPH rated capacity (1W+1S). 4 4.1 SYSTEM DESCRIPTION The system description furnished below is to be read with reference to exhibit no 1 and 5 (Plot plan and coal handling flow diagram). 5.0 SALIENT FEATURES OF THE SYSTEM The following are the salient features of the coal handling system: 5.1 Belt Conveyors All conveyors would be provided with Nylon-Nylon belting with fire retardant (FR) grade covers of 5mm thickness at top and 3 mm thickness at bottom. The belt width of BCN1A/1B will be 1200 mm. Troughing angle will be 350. The belt speed would be about 2.63m/s. 5.2 Conveyor Galleries All above-ground conveyors would be provided with enclosed galleries with colour coated sheeting on side and top. Seal plates at required locations like road crossings and above buildings would be provided. 5.3 Junction Towers All junction towers would be of structural steel with chequered plate covered / RCC floors. Side cladding and roof would be provided with colour coated sheets. 5.4 Feeding of Coal to Bunkers and Bunker Ventilation System Coal would be fed to the bunkers from conveyors through motorized travelling trippers. The coalbunkers would be of circular type and the openings on the top would be covered with bunker sealing belt to avoid dust nuisance. The bunkers would be adequately ventilated to keep the bunkers free from accumulation of volatile gases, thereby eliminating fire hazard and also avoiding dust nuisance in the tripper floor. The dustladen air would be passed through bag filters before being let out to the atmosphere. 92 5.5 Metering of Coal Adequate number of electronic belt scales would be provided on conveyors at appropriate places to monitor the quantity of coal received at the plant, quantity of coal available in the stock pile and quantity of coal consumed by the steam generator. 5.6 Tramp Iron Detection and Removal Tramp iron and other magnetic materials would be removed by means of in-line magnetic separators provided above the head pulleys of conveyors leading to the crusher house and conveyor before the coal bunkers. Metal detectors would be provided on other conveyors at appropriate locations to detect non-magnetic metal pieces and heavy iron pieces that may be present in the coal being conveyed. 5.7 Dust Control Plain water spray dust suppression system would be provided for all transfer points in the junction towers. Plain water type dust suppression system would be provided all around the stockpile to suppress the dust generated and to keep dust nuisance to the minimum. The bunker ventilation system would be provided with bag filters to trap the dust generated while loading coal into bunkers and to vent out dust free gases/air. 5.8 Fire Protection Fire hydrants would be provided at all tunnel entry points, junction towers, and bunker gallery and along the overhead conveyors. Fire hydrants would also be placed along the periphery of the coal stockpile for fire fighting. 5.9 Coal Yard Drainage Drainage channels would be constructed to take all the effluent from the coal stock yard, which would be ultimately led to a coal pile run-off pit. The coal pile run off pit will have two compartments. The coal particles will settle down in the first compartment and relatively clean water will over flow to the second compartment. A sump pump would be provided to pump the water to the plant drains. 5.10 Controls Operation of the complete coal handling system, except traveling trippers over SG bunkers would be monitored from the coal handling control room. Traveling trippers would be controlled locally. The control and protection system would be microprocessor based with redundant CPU and colour monitor. Telemetered integrated readings would 93 be provided for accounting of coal consumed by the SG units. Also, annunciation would be provided in the Unit control room to indicate low level of each bunker. 94 CHAPTER-XII ASH HANDLING SYSTEM 1 GENERAL 1.1 This chapter covers the design criteria and salient features of the ash handling system for the proposed 2x660MW supercritical thermal power plant. The following data has been considered for the design of ash handling system: a) Hourly coal firing rate at 100 %MCR condition per unit for worst coal : 300 T b) Ash content : 25 c) Distribution of total ash produced as - Bottom ash : 20 % - Fly ash(evacuation design) : 90 % - Fly ash (disposal design) : 80% of ash in storage area : 1.3 m3 e) PLF : 85% f) The system proposed for bottom ash removal would be dry type. Fly ash removal d) Volume occupied by one tonne system would be two stage pneumatic conveying system. Disposal of ash would be in high concentrated slurry form. g) The water required for high concentrated slurry formation would be met from CW blow down. However, service water would be used for fly ash dust conditioners, jacket cooling of air compressors and silo / ESP aeration blowers cooling etc. 2 CAPACITY AND TIME CYCLE 2.1 The scraper chain system will operate continuously to evacuate bottom ash generated on combustion of coal. The capacity of bottom ash removal and will be 20 TPH for each unit. The system bottom ash generated is only about 12.19 TPH. Bottom ash silo has been considered of 750 tones common for both units total bottom ash generation. 95 2.3 Fly ash formed in a shift of eight (8) hours would be evacuated from the fly ash hoppers of the steam generator unit up to ash storage silo in 4 hours by two stage pneumatic conveying system with a system capacity of about 150 TPH per unit. However FA would be evacuated continuously under normal conditions. It is proposed to provide two (2) fly ash silos each of 3000 tones capacity common for both units with One (1) intermediate storage silo of 3000 tones. Details of these silos would be worked up during detail engineering stage. 2.4 Unutilized fly ash and bottom ash would be disposed into ash disposal area by HCSD pumps. Fly ash and bottom ash collected from the respective bottom ash and fly ash silos would be disposed in to ash disposal area. In a shift, FA & BA disposal from both the units would be carried out simultaneously. 3 SYSTEM DESCRIPTION 3.1 The ash handling system would include complete bottom ash (BA) evacuation system, fly ash (FA) evacuation system, fly ash storage silos, BA&FA disposal systems up to the ash pond. The ash handling system shall be as per the system description and flow diagrams enclosed. Ash formed due to combustion of coal in the pulverised fuel steam generator (SG) would be collected as bottom ash in the bottom ash hopper and as fly ash in the fly ash hoppers. The fly ash would be collected in the economiser hoppers, air-preheater hoppers and electrostatic precipitator (ESP) hoppers provided along the flue gas path. 3.1.1 Bottom Ash (BA) Handling (Refer Exhibit - 5) 3.1.1.1Bottom ash (BA) hopper would be provided below furnace with four hour storage capacity. The bottom ash collected in the BA hopper would be evacuated using scraper chain conveyor (one working + one standby). The bottom ash discharged into the water trough of the scraper chain conveyor would be crushed in a clinker grinder (one working + one stand by) the crushed bottom ash from the clinker grinder would be conveyed to the bottom ash silo by a series of belt conveyors . 96 3.1.2 Fly Ash Handling (Refer Exhibit - 6) 3.1.2.1 The fly ash handling system would be designed to collect fly ash in dry form in silo using two stage pneumatic conveying system. FA from ESP hoppers of each unit, FA would be conveyed up-to intermediate storage silo by first stage pneumatic conveying system. Hoppers in each field would be connected to common conveying line and fly ash removal from all hoppers in that field would be done one after the other. The clearance from any hopper would continue cycle after cycle till the level in the hoppers reaches low level. The removal of fly ash from any particular hopper would be initiated whenever the level in the hopper reaches predetermined level. Therefore, the removal and transfer of the fly ash to the intermediate storage silo would be done in cyclic manner on a continuous basis. Generally, the fly ash conveying system would operate continuously but with time gaps between cycles. The fly ash removal system would be designed on a continuous basis with 15 cycles of operation per hour, and during emergency with 20 cycles of operation per hour. The level probe would be provided in each hopper in such a way that the ash collected in the hopper would be equal to the volume of the ash transmitter vessel. There would be one (1) manually operated isolation valve (knife gate type) below each fly ash hopper which would be used during maintenance of the ash transmitter vessel. FA from intermediate storage silo would be conveyed by second stage pneumatic conveying system up-to the FA silos. The fly ash collected in the storage silos would be unloaded into the trucks either in conditioned form or in dry form, if required for utilization or conveyed in high concentrated slurry form into disposal area. 4 AUTOMATIC SEQUENTIAL CONTROLS FOR ASH REMOVAL SYSTEM 4.1 To automatically control all the compressors, pumps, valves, etc., in the fly ash handling system, a centralized control panel with microprocessor based PLC would be provided in the control room for the ash handling system. The PLC system would 97 provide for continuous cyclic operation of fly ash evacuation system. The opening and closing of the valves below fly ash hoppers would be controlled with the help of level switches provided on the transmitter vessel / fly ash hoppers in various streams. The hopper from which fly ash is being removed would be indicated on the monitor or mimic panel. The equipment and valves in the bottom ash handling system would be controlled automatically through a separate PLC system provided in boiler area. The status of operation of bottom ash handling system would be available on the monitor or mimic panel in ash handling system control room. Silo unloading system would be controlled from the local control panel located at silo unloading floor. 5 ASH DISPOSAL AREA 5.1 The BA and unutilized FA in high concentrated slurry form from both the units would be pumped to ash disposal area / ash pond by HCSD pumps. About 25 hectares is identified for ash disposal. The ash disposal area would be lined with geo-membrane material to avoid percolation of water into earth’s surface. 98 6 ASH POND AREA ESTIMATION The ash pond area is estimated as given below based on the following inputs and assumptions. 1 Coal firing rate : 300 TPH 2 Ash content : 25 % 3 Percentage of Fly Ash : 80% 4 Percentage of Bottom Ash : 20% 5 Area of ash pond : 25 hectares 6 Height of ash bund : 4m initial height. Subsequent increase of 4m in three phases upto ultimate height of 20 m. 7 V lume occupied by one tonne of ash in storage area : 1.3 cu.m 8 Total ash generated per hour per : unit 60.99 T 9 BA ash generated per hour per : unit 12.19 T Fly ash generated per hour per : unit 48.79 T 10 BA ash generated per year for proposed phase-II units (with PLF 85%) : 2,13,730 T 11 : 8,54,919 T 12 FA ash generated per year for proposed phase-II (with PLF 85%) The area available for ash disposal can accommodate 100% Bottom Ash generated by 2 units in 4years, and 100% Fly Ash generated by 2 units in 1 years. 99 7 7.1 POSSIBLE AREAS OF ASH UTILISATION The environmental regulations are becoming stringent on the ash disposal aspect. The present regulation stipulate for atleast 50%, 75% and 100% fly ash utilization in 1year, 2year and 3year respectively from date of commissioning. Hence it is necessary to find out the areas where ash can be utilized without harming the environment. Presently the ash based products are at developmental stage and need to be made more environmental friendly. Some of the areas of ash uses include: a) Brick/ Block/ Tiles manufacturing b) Cement manufacturing c) Roads and embankment construction d) Structural fill for reclaiming low lying areas e) Mines fill f) Agriculture, Forestry and Waste land development g) Part replacement of cement in mortar and concrete h) Hydraulic structure (Roller compacted concrete) i) Ash dyke raising j) Building components – Mortar, Concrete, concrete hollow blocks, aerated concrete blocks etc. k) Other medium & high value added products (Ceramic tiles, wood, paints) pavement blocks, light weight aggregate, extraction of alumina, cenospheres etc. 100 CHAPTER XIII MISCELLANEOUS SYSTEMS COMPRESSED AIR SYSTEM 1 Three centrifugal compressors (one working for each unit and one common stand by), each having suitable capacity to cater to the plant at a discharge pressure of 9.97 kg / cm2 (g) would be provided for 2x660 MW units. The centrifugal compressors proposed would meet the instrument and service air requirements of the plant. The requirement of the compressed air for the fly ash conveying and coal handling system would be met through separate dedicated compressors. 2 The compressed air system would include accessories such as moisture separators and air receivers. The discharge lines of all the three compressors would be branched. Two air driers (one operating and the other stand by) for each unit of suitable capacity would be provided. AIR CONDITIONING SYSTEM 3 It is proposed to air-condition the unit control room, electronic cubicle room, shift charge engineer’s room, printer room, maintenance engineer’s room, UPS room, ESP control room, static excitation cubicle room, analyser panel room, coal handling control room, DM plant control room and switchyard control room. Inside design conditions of 24.5 1.50C dry bulb temperature and relative humidity not exceeding 60% would be maintained in all air-conditioned areas. 4 Two independent centralised chilled water systems are envisaged for air-conditioning the unit control room / electronic cubicle rooms and ESP control rooms. Each centralised system would consist of three (two working and one standby) water chilling units. The system also consists of chilled water pumps, condenser cooling water pumps, induced draught FRP cooling towers, adequate number of air handling units for circulating the conditioned air through air distribution system to the room. 101 5 For air conditioning of all other rooms, packaged air conditioners or room air conditioners of suitable capacity would be provided. VENTILATION SYSTEM 6 For the ventilation of the station building, evaporative cooling system (Air washer type) is envisaged. This system consists of air washers, supply air fans, air washer circulating water pumps, centrifugal fans and air distribution system for distributing the supply air inside the station building. The exhaust of hot air out of the station building would be achieved by provision of roof extractors and wall mounted exhaust fans. 7 For ventilation of other buildings, supply air fans or louvers, exhaust air fans, roof extractors or a suitable combination of these complete with louvers, filters, ducting grilles would be provided. HYDROGEN GAS SYSTEM 8 Hydrogen gas with a purity of 99.9% (by volume) is required for cooling of the generators. It would be required for the initial filling and continuous make-up during normal operation for maintaining the required purity in the generator. The normal hydrogen gas requirement for two units is about 50 Nm3 / day. This requirement would be met by procuring the hydrogen gas cylinders from external sources CRANES AND HOISTS Station Building EOT Cranes 9 One overhead, cabin operated electric overhead travelling (EOT) crane of 115/25 ton capacity, Class M5, spanning 29 m in AB bay for TG building would be installed in the turbine hall for handling various equipment, except generator stator, during erection and maintenance. The generator stator would be erected by employing temporary erection facilities such as derrick / hydraulic jacks, or strand jack arrangement. Miscellaneous Lifting Tackles / Hoists 102 10 For equipment, which weighs above one ton, electrically operated type of hoists and trolleys would be provided. For equipment weighing less than one ton, manually operated hoists and trolleys would be provided. 11 The areas / equipment for which the lifting tackles are proposed to be provided are in warehouse, all equipment in the station building which are not accessible to station building EOT crane, steam generator area (all fans, gear boxes, mill components, etc.), DM plant (to load the chemicals in to the tanks), coal handling junction towers and ash water pump house , HCSD pump house, cooling tower area, ESPs, sea water/clarified water pump houses, fuel oil pump house, etc. WORKSHOP EQUIPMENT 12 The power plant would be equipped with a work shop capable of catering to the routine maintenance requirements of the plant. Considering the type of jobs likely to be carried out at the workshop, all or some of the following equipment are proposed to be provided. The availability of the maintenance facilities in the vicinity of the site may be taken into consideration while finalising on this aspect. a) Machine Shop Equipment i) ii) One general purpose lathe iii) One shaping machine iv) One universal milling machine v) One radial drilling machine vi) One bench drilling machine vii) One portable hand drill gun viii) One surface grinding machine ix) One double-ended pedestal grinder x) One flexible shaft grinder xi) One power driven hacksaw One set of balancing equipment 103 xii) Work benches, hand lamp sets (with transformer), hydraulic jacks, general tools, surface plates and measuring tools. b) Welding Equipment i) One AC transformer welding set ii) One rectifier welding set iii) Two oxy-acetylene gas cutting and welding sets iv) One electrode drying oven v) Welding tables, soldering irons, welding masks, etc. CHEMICAL LABORATORY EQUIPMENT 13 A chemical laboratory as per the requirement would be provided in the power plant to enable testing of fuel, water, flue gas, etc. for normal operation of the power plant and as stipulated by MOEF and GSCB. 14 Chemical laboratory would be equipped with all or some of the following equipment. In addition to these equipment, the laboratory would also be equipped with necessary laboratory glassware, reagent chemicals and laboratory furniture. A portion of the chemical laboratory housing equipment such as the spectrophotometer would be airconditioned. Necessary meteorological and environmental equipment would also be provided. Conductivity meter Alfoc test kit for oxygen pH meter Turbidity meter Spectrophotometer Jar test apparatus (laboratory flocculator) Muffle furnace Vacuum oven Ordinary oven 104 Bomb calorimeter Sieve shaker Sieves, cover receiver Mechanical jaw crushers Grinder Jar ball mill Electric oven for coal analysis Hard grove grindability tester Apparatus for oxidation stability test Coal analyser for proximate analysis Redwood viscometer Appa atus for water in oil by Dean and Stack method Interfacial tension apparatus Pensky-Martens flash point apparatus Three-bulb orsat Explosimeter (Combustible gas analyser) Ultimate analysis apparatus hydrometer. Hydrogen purity test apparatus Magnetic stirrer Balance (chainomatic) with weight box Atomic absorption spectrophotometer Triple beam balance Single pan balance Water bath Gas heating assembly Hot plate Distilling still Vacuum pump 105 Heating mantle Kipp’s apparatus Flame photometer Lovibond comparator Hot plate-cum-magnetic stirrer Laboratory centrifuge Potentiometric titration apparatus Atomic absorption spectrophotometer (AAS) Gas chromatograph with data processor (GS) Noise level meter Wind anemometer and wind vane Dial type barometer Stack monitoring kit Hygrometer Dry wet bulb thermometer Dew point tester BOD incubator COD incubator. 106 CHAPTER XIV ENVIRONMENTAL PROTECTION AND WASTE MANAGEMENT TYPES OF POLLUTION 1 The technical details and emission parameters mentioned in this chapter refer to proposed 2 x 660 MW Phase II super critical imported coal based thermal power plant near by Nana Manda & Khajurda, Dist Devbhumi Dwarka, Gujarat. This chapter details out the following environmental impact aspects: a) Air pollution b) Water pollution c) Noise pollution d) Sewage disposal. AIR POLLUTION 2 The air polluting emittants from the power plant are as follows: a) Dust particulates in flue gas, from chimney b) Sulphur dioxide (SO2) in flue gas c) Nitrogen oxides (NOx) in flue gas d) Mercury (Hg) e ) Coal dust particles while handling of coal f ) Dust in the ash disposal area. REGULATIONS FOR LIMITING AIR POLLUTION INDIAN STANDARDS 3 As per notification by Ministry of Environment and Forests dated 19 May 1993, the emission limits are as follows: a) b) Suspended particulate matter (SPM) emission (dust particulate from fly ash) : < 30 mg/Nm3 Sulphur di-oxide * <100 mg/Nm3 : 107 c) Nitrogen oxides : < 100 mg/Nm3 d) e) Mercury (Hg) Coal dust particles during : < 0.03 mg/Nm3 : Not specified : Not specified Storage/handling of coal f) Dust in the ash disposal area Note : *Sulphur di-oxide emission would be controlled by specifying minimum stack height limit which is as follows : Power Generating Capacity Minimum Stack Height 500 MW and more 275 m 200 MW and above to less than 500 MW 220 m Less than 200 MW H = 14 (Q) 0.3 Where H = stack height in M Q = SO2 emission rate in kg / hr 4 As per notification by Central Pollution Control Board dated 16 Nov 2009, for the ambient air quality, the permitted limits of ground level concentrations of pollutants considering Industrial, Residential, Sensitive areas is furnished in Table- XIV.1 below : Table –XIV.1 Pollutant National Ambient Air Quality Standards Concentration in Ambient Air Time Weighted Average Annual Average* Sulphur Dioxide (SO2) Oxides of Nitrogen as NO2 Particulate matter (size less than 10um) or PM10 ug/m3 Particulate matter (size less than 2.5um) or PM2.5 ug/m3 g/m3 Industrial Residential, Rural Other areas Area 50 Sensitive Area 20 24 hrs** Annual Average* 80 24 hrs** Annual Average* 80 60 80 60 24 hrs** 100 100 Annual Average* 40 40 24 hrs** 60 60 108 40 80 30 Table – XIV.1 Pollutant National Ambient Air Quality Standards Concentration in Ambient Air Time Weighted g/m3 Average 8 hours** 100 100 1 hours** 180 180 Annual Average* 0.50 0.50 24 hrs** 1.0 1.0 8 hours** 02 02 1 hours** 04 04 Annual Average* 100 100 24 hrs** 400 400 Benzene (C4H6) ug/m3 Annual Average* 05 05 Benzo (a) pyrene (BaP) Particulate phase only ng/m3 Annual Average* 01 01 Arsenic (As) ng/m3 Annual Average* 06 06 Nickle (Ni) ng/m3 Annual Average* 20 20 Ozon (03) ug/m3 Lead ug/m3 Carbon Monoxide mg/m3 Ammonia ug/m3 * ** Annual arithmetic mean of minimum 104 measurements in a year taken twice a week – 24 hours at uniform interval. 24 hourly / 8 hourly values should be met 98% of the time in a year. However, 2% of the time, it may exceed but not on the consecutive days. 109 Notes: 1. National Ambient Air Quality Standard: The levels of air quality necessary with an adequate margin of safety to protect the public health, vegetation and property. 2. Whenever and wherever two consecutive values exceed the limit specified above for the respective category, it would be considered adequate reason to institute regular / continuous monitoring and further investigations. Dust Particulates from Fly Ash in Flue Gas 5 As per the above norms the particulate matter (PM) emission applicable to this project would be 30 mg / Nm3. But considering prevailing international trend of limiting the PM emission to 30 mg / Nm3 as per the stipulation by the World bank group on pollution prevention and abatement (July 1998), the electrostatic precipitators (ESP) for the project would be designed to limit the emission level of PM to be within 30mg / Nm3 . Sulphur Dioxide (SO2) in Flue Gas 6 As per the above norms, the minimum stack height shall be 275m. A common twin flue Stack for two units has been proposed for effective dispersal of SO2. Space for FGD is also proposed to be considered and can be installed if required for SOx Control. Nitrogen Oxides (NOx) in Flue Gas 7 The steam generators would be fitted with low NOx burners. To reduce NOx emissions, over-fire air system would also be installed in the furnace. The NOx ground level concentrations (GLC) would be checked during preparation of EIA report for the project. 110 8 Emissions CO2 , SO2 and NOX Emission 8.1 Since supercritical units have been considered for the proposed project the CO2 , SO2 and NOX emission would be about 6-7 % less compared to sub critical unit of 660MW. The quantitative description for CO2 emission is given below. The SO2 and NOX emission will be in similar line. CO2 Emission 8.1.1 The pressure and temperature at the inlet of the steam turbine for 660 MWe supercritical unit would be 247 bar (a) and 567 oC / 594.3 oC reheat, whereas the same for a sub critical 660 MW unit would be typically 166.7 bar (a) / 537 oC/ 537 oC. Due to the high initial pressure and temperature conditions, the gross station heat rate (estimated at 0 % make up and condenser pressure 0.093 bar (a)) for a 660 MW super critical unit would be lower, i.e.2130 kcal/kWh compared to the 2444.20 kcal/kWh for the sub critical unit. Therefore the coal consumption rate at MCR conditions would be lower for a super critical unit. The details of the coal firing rates and CO2 productions are furnished in the enclosed Table-XIV.2. Since the coal firing rate for the sub critical 660 MW unit would be high, the CO2 emissions would also be higher ( i.e about 6.66 % ) compared to a super critical unit of the same capacity. 111 Table-XIV.2 660 MW TPS - CO2 Emission for Super Critical and Subcritical Unit 660 MW Super Critical unit Sl.No. Para Gross stationmeter heat rate at TG MCR, kcal/kWh Coal Firing rate ( GCV 4900 kcal/kg), kg/hr CO2 emission , kg/ kg of fuel CO2 emission tonnes/ MWh CO2 emission, million tonnes/year variation in CO2 Percentage emission 1 2 3 4 5 6 8.2 660 MW Sub Critical unit 2130 2444.20 299808 1.9481 0.8468 8.46 358673 1.9481 0.9717 9.71 Base ( + ) 18.24 Stack Emission (Preliminary) : One twin flue stack for two 660 MW units a) Number of stacks b) Number of flues per stack : Two flues in one bi-flue stack for (Unit 1 and 2) of 660 MW c) Physical stack height (m) : 275 m d) Plume diameter at exit (m) : 7.6 m (flue exit diameter) approx e) Flue gas exit velocity (m/s) : 22 m/sec approx f) Flue gas exit temp (°C) : > 125 (at stack outlet) approx 3 g) Flue gas density (kg/NM ) h) Emission rate per flue of : 1.114 approx i) SPM (mg/Nm3) : ii) SO2 (kg/h) : 321 per each stack approx iii) NOx (kg/h) 30 322 112 COAL DUST PARTICLES DUE TO HANDLING OF COAL 9 Coal dust would be generated generally at the conveyor transfer points, coal unloading area and coal stockpile area. Hence, coal transfer points and coal stockyard would be provided with dust suppression / dust extraction facilities. Further, in order to arrest the coal dust generation, all conveyors would be provided with enclosed galleries. The bottom portion of all the conveyor galleries would be provided with seal plates with in the power plant area and at road crossing. 10 Dust collection system would also be provided in coal bunkers to evacuate dust and hazardous gases like methane from the coal bunkers. Collected dust would be returned to either the associated belt conveyor or to the coal bunker. FLY ASH DUST PARTICLES FROM ASH SILOS AND ASH DISPOSAL AREA 11 Two fly ash storage silos, one for each unit are proposed to be provided, two intermediate fly ash silo common for both units to be provided. Fly ash evacuated from the ESP collecting hoppers would be transported in closed pipelines by pneumatic means. At the time of unloading fly ash in to the silos, some ash laden air would get vented out. However, In order to restrict the fly ash dust particles to the limit, a vent filter would be installed on top of each of the fly ash silos at the vents. 113 12 The following pollution control measures would be installed for ash disposal: a) Maximum utilization of fly ash in dry form is envisaged. Closed trucks and containers would be used for this purpose, as far as possible. Provision would be made to dispose the unutilized fly ash through HCSD system. b) To reduce the dust nuisance while unloading the ash into the open trucks from fly ash silos, the fly ash would be conditioned with water spray c) Water sprinkling system would be provided in the ash disposal area to restrain flying of fine ash due to wind d) The ash disposal area would be lined with impervious lining to prevent seepage of rain water from the disposal area in to the ground and pollute ground water. WATER POLLUTION 13 The water pollutants applicable for this plant are: a) Cooling tower blow down water b) Water treatment plant effluent c) Effluent from ash disposal area d) Effluent from coal pile area run off e) Air pre-heater wash water effluent f) Plant wash down water 114 g) Floor and equipment drainage effluent h) Rain water drainage i) Sewage from various buildings in the plant. REGULATIONS FOR LIMITING WATER POLLUTION: INDIAN STANDARDS 14 Environmental (Protection) Rules 1986 issued by Ministry of Environment and Forests Schedule-I, stipulates the following limits for effluent disposal: a) Ash pond effluent: i) pH : 6.5 to 8.5 ii) Suspended solids : < 100 mg/l iii) Oil and grease : < 10 mg/l b) Effluent from WT plant c) Steam generator blow down: d) : Not Specified i) Suspended solids : < 100 mg / l ii) Oil and grease : < 20 mg / l iii) Copper (total) : < 1.0 mg / l iv) Iron (total) : < 1.0 mg / l. Cooling tower blow down: a) Free available chlorine : < 0.5 mg/l b) Zinc : < 1.0 mg/l c) Chromium (total) : < 0.2 mg/l d) Phosphate : < 5.0 mg/l. 115 15 As per the notification issued by the Ministry of Environment and Forests dated 19 May 1993, the Schedule-VI specifies the quality of effluent permitted to be discharged. The qualities of effluents have been specified under the following categories: a) Inland surface water b) Public sewage c) Land for irrigation d) Marine coastal areas. 16 For the proposed power plant, the category to be considered would be under inland surface waters. The major effluent limits under category are: a) Suspended solids : 100 mg / l (max). b) pH : 5.5 to 9.0 c) Temperature : Shall not exceed 10oC above the receiving water temperature. : d) Oil and grease 17 10 mg / l. The quantity of effluents would confirm to the limits indicated above and also those limits prescribed by Gujarat State Pollution Control Board (GSPCB). REUSE OF PLANT EFFLUENTS 18 Following measures are proposed for reusing plant effluents: 116 a) Cooling Tower Blow Down The cooling tower blow down does not require treatment but relies on minimizing the level of pollutants by operating at reduced cycles of concentration to prevent the buildup of contaminants and through proper selection of treatment chemicals which do not introduce additional pollutants such as zinc and chromium. b) Water Treatment Plant Effluents The effluent from the regeneration of the cat-ion resin units in the water treatment plant (DM Plant) is generally acidic in nature and from the anion resin units are alkaline in nature. The combined waste water from the DM plant would be neutralized in a neutralizing pit. The neutralized effluent is expected to have suspended solids less than 5 ppm and pH in the range of 6.5 to 8.5. This would be led to the guard pond. c) Coal Pile Area Run- Off The coal pile area runoff water during monsoon season would be led to a separate pond. Coal particles would settle down in the pond and clear water would be allowed to flow into the ash pond. d) Effluent from Bottom Ash Handling System The drain and overflow water from the bottom ash handling system would be collected at the bottom ash sump where the ash would settle down and clarified ash water overflows to clear well section of the basin. This clear water would be sent to the ash water sump. e) Plant Wash Down Water 117 In the power plant, some specific locations require washing to maintain good plant house keeping and prevent build up of dirt and waste material. The waste water would be led to the guard pond. f) Floor and Equipment Drainage System Effluent i) Means would be provided for collecting and draining water from floors in process areas of the plant and collecting and disposing of water and other liquids from process equipment, discharged fire protection water and oil storage tanks. ii) In the turbine building, the ground floor slabs would be sloped to drain out floor drains. The equipment drains are piped directly to the drain system. Drains are collected and directed to sumps outside the buildings from where it would be pumped to the guard pond through a oil water separator. RAIN (STORM) WATER DRAINAGE 19 The rain (storm) water removed from the building roofs would be collected to a rain water collection tank. The rain water which falls on the yard area grade level surfaces would be directed through the open ditches and culverts to the storm drainage. All ditches would be concrete lined and located along the roads. All drainage ditches would be located to provide the shortest practical drainage path while providing efficient drainage for the yard. Grade level would be contoured such that storm water run off is directed on the ground by sheet flow, to well defined drainage paths leading to the ditches. SEWAGE FROM VARIOUS BUILDINGS IN THE PLANT 20 Sewage from various buildings will be by sewers connecting to the nearest manholes. The concentrated sewage will be led to a sewage treatment plant. A network of sewers with manholes located at all junctions and at a spacing of 50 m will be provided to cover all the buildings in the project. MONITORING OF GROUND WATER 118 21 Four bore-wells would be identified inside / outside the plant premises to monitor the ground water quality as per IS: 10500 (1991). NOISE POLLUTION 22 The source of noise in the proposed power plant are: - Steam turbine generator - Other rotating equipment - Combustion induced noises - Flow nduced noises - Steam safety valves REGULATIONS FOR LIMITING NOISE POLLUTION: INDIAN STANDARDS 23 As per the Environmental (Protection) Rules 1986 as well as MSPCB, the limits in the noise levels are: Industrial area 24 : 75 dB (A) in day time (6 AM to 9 PM) : 70 dB (A) in night time (9 PM to 6 AM) The Occupational Safety and Health Administration Standards (OSHA), USA indicate the following permissible noise. ---------------------------------------------------------------Duration per Day (Hours) Sound Level (dBA) ---------------------------------------------------------------8 90 6 92 4 95 3 97 2 100 1.5 102 1 105 0.5 110 0.25 115 119 25 All the equipment in the power plant would be designed / operated to have the noise level not exceeding 85 - 90 db (A) measured at a distance of 1.5 m from the equipment. Also, all the measures would be taken to limit the noise levels at the plant boundary within the stipulated limits. POLLUTION MONITORING AND SURVELLIANCE SYSTEMS 26 The emission and gas monitoring systems installed in this Project consist of the following: a) Flue Gas O2 and CO Monitoring: These would be measured at the economizer outlet. In addition, O2 would be monitored at the air pre heater outlet. For this purpose, CO and O2 monitor probes and analyzers would be installed separately. b) Stack emissions: Flue gas exiting into the atmosphere would be monitored for CO2, NOx, SO2 and Opacity. Stack emission readings would be sent to the DCS for monitoring. For this purpose, dilution probes, associated gas analyzers and support equipment, sample lines and Opacity sensor / transmitters would be installed. The Opacity sensors would be equipped with a blower to protect the optics from coating by flue gas particles. The system operation would be continuous. Stack gas analysis for SO2, CO2 and NOx would be performed by extracting a gas sample from the flowing stream in the stack, filtering to remove particulate droplets, diluting with scrubbed instrument air and conveying the sample to the analyzers. One sampling system per unit would be provided. Air Monitoring 27 Air Monitoring Stations (AMS) would be set up to monitor the air quality in the neighboring villages. The parameters being monitored are suspended particulate matter 120 (SPM), respirable particulate matter (RPM), Sulphur di-oxide (SO2), Nitrogen Oxide (NOx), Carbon monoxide (CO) and Hydro carbons (HC). The air quality monitoring would be carried out continuously including the times during which power plant boiler firing with 100% coal as test firing is done. GREEN BELT 28 In the proposed power plant, for raising plantation adequate saplings would be planted inside the power plant. IMPACT OF POLLUTION/ENVIRONMENTAL DISTURBANCE 29 Since all necessary pollution control measures to maintain the emission levels of dust particles, sulphur dioxide and nitrogen oxides within the permissible limits would be taken and n cessary treatment of effluents would be carried out, there would be no adverse impact on either air or water quality in and around the power station site on account of installation of the proposed plant. ENVIRONMENTAL CLEARANCE 30 Appendix - 6 gives the environmental appraisal for the proposed power plant in the format required by the National Committee on Environmental Planning and Coordination. 121 CHAPTER XV PROJECT SCHEDULING AND IMPLEMENTATION PROJECT SCHEDULE 1 The project milestone schedule is presented in Exhibit-09. It is envisaged to put the first unit into commercial operation in 39 months, reckoned from the date of award of boiler and turbine generator (BTG) contract for the project. The second unit would be put into commercial operation 3 months thereafter. The synchronization of each unit would be three months ahead of their commercial operation date (COD).The time between synchronization and COD would be utilized for the following activities. a) Trial operation of steam generator (SG) and turbine generator (TG) including submission of report upon successful completion 4 Weeks. Trial operation would include. i) Trial operation of the unit for 72 hours at full load on auto mode ii) Operation of the unit at various load regimes for sufficient duration on auto b) Stable operation of unit and notice for performance guarantee (PG) test for SG and TG – 2 Weeks c) Performance guarantee test including shutdown for removal of instruments and unit characteristics tests inclusive of VWO test, house load operation test, ramp rate test, demonstration of cold, warm and hot start-up times – 2 Weeks d) PG test for balance of plant systems like WT plant, water clarification plant, cooling towers, coal handling etc. – 2 Weeks e) Review/approval of PG tests and take over for commercial operation – 2 Weeks HANDLING OF EQUIPMENT 2 The following mode of handling heavy equipment at site is envisaged for at the erection stage: 122 a) All steam generators parts would be brought to the SG area and hoisted to the erection points using tower crane and other types of lifting devices b) The generator stator would be unloaded from the carriers by means of hydraulic jacks or mobile cranes in the maintenance bay of the station building. At the time of erection, the stator would be placed on the TG pedestal using the hydraulic jacks or mobile cranes c) All equipment in the station building, except the generator stator, would be erected using one (1) no 115/25 ton E.O.T. crane installed in the station building. The transport carriers would be brought into the maintenance bay of the station building to facilitate handling by the E.O.T. cranes d) The generator transformer would be jacked up and unloaded on the railway track provided for transformers close to the foundations and moved to the position by means of the bi-directional rollers provided. Smaller transformers would be skidded into position using winches. O&M PERSONNEL 3 To ensure adequate technical competence in operation and maintenance of the power station, the following measures would be taken: a) Personnel identified for O&M functions would comprise having the required background and a cadre of engineers experience in commissioning, operation and plant maintenance functions for a coal fired thermal power plant of similar capacity b) These O&M personnel would be recruited at an early stage and would be given adequate training at the manufacturer's works, at site, at other similar power stations and/or in training simulators so as to familiarise them with the necessary O&M functions relating to plant and equipment specific to this project. 123 PRELIMINARY AND OTHER WORKS 4 To ensure timely project execution within the cost envisaged, several project developmental activities are to be completed before the date of award of BTG contract. However, apart from obtaining necessary approvals and clearances, some of the important site-related works such as site enabling works viz. temporary site office, storage sheds, construction water and power supply would be taken up and completed early. RISKS PERCEIVED DURING PROJECT PHASES 5 The risks perceived during various phases of project, primarily would be in brief as below: a) Pre-construction phase The primary aspects which need attention during pre-construction phase would be related to: i) Availability of land: Adequate land is identified for installation of this project which is well connected by road and railways. Serious impact on land availability for commencement of project activities and hence on project scheduling. ii) Availability of fuel: The supply of 5.5 million Tons of imported coal for both the projects of 2x660 MW Phase-II coal would affect the plant operation. iii) Availability of water: Implementation of water supply scheme needs to be taken up early so as to ensure availability of water for project on schedule. 124 iv) Approvals and permits: The suitable actions needs to taken-up with various agencies to obtain the statutory / non- statutory clearances. Non availability of any clearances would affect the smooth functioning of project execution. The list of permits and clearances generally required to be obtained is furnished in Chapter- XVI. v) Finalization of contracts: Well documented contracts with reputed suppliers/contractors along with well defined technical/commercial terms and conditions and involvement of reputed technical consultant need to be firmed up. Loosely documented contracts would cause cost and time over run of the project b) Construction phase i) Financial strength of project developer: Sound financial strength of project developer is essential to infuse required equity part of project cost at right time so as to obtain smooth flowing of debt portion from lenders. Inability of this, would lead to fund crunch causing payment ii) default to in project Delay contractors thereby completion and affecting increase project in schedules. project cost: This could happen due to improper selection of contractors/equipment suppliers. While selecting the contractors/equipment suppliers, at- most care needs to be taken to evaluate their financial as well as technical capabilities and heavy penalties to be enforced in case of dilution of contractual conditions. Services of reputed technical consultant need to be employed for monitoring the technical iii) qualities, Delay in cost over-run construction and of timely power completion evacuation of project. facilities: Creation of power evacuation facilities generally need more time considering its nature of execution. Inadequate planning would lead to delay in availability of evacuation facility. This would delay the operation phase of project causing loss of revenue. 125 c) Post i) construction operation availability Fuel and phase transportation: Inadequate availability of fuel and/or inadequate fuel transportation facilities would lead to adverse effect on functioning of plant causing revenue loss. Hence, proper agreements related to supply and transportation of fuel need to rightly placed ii) and monitor Equipment closely. performance: Proper selection of equipment/systems during contracting stage and operation & maintenance of the same as per manufacturer’s recommendation s is very essential. Dilution of this would lead to deterioration of the equipment performance causing loss of power generation. Hence, operation and maintenance of the plant to be carried out with well equipped and by well qualified iii) O& Escalation staff. M in O&M cost: This can happen in case of improper selection of spares, non adherence to manufacturer’s recommendations and unskilled O&M personnel. Proper attention needs to be given to these aspects to keep the plant in sound condition. d) General Other risks involve would be political, economical, change in law, revenue collection etc. which would be addressed suitably. 126 CHAPTER - XVI PROJECT APPROVALS AND PERMISSIONS CHECK LIST FOR PERMITS, CLEARANCES AND LICENSES FOR POWER PROJECTS SL. NO. CLEARANCES AUTHORITY 1.1 Environmental clearance Ministry of Environmental Forest, Government of India 1.2 No objection for tallest structure Airport Authority of India, Delhi. 1.3 Registration of Company Companies Act, 1950) Registrar of Companies 1.4 Rehabilitation & resettlement of displaced families by land acquisition MoEF, Government of State 1.5 Import licenses & formalities Controller of Imports & Exports 1.6 Foreign investment approval Reserve Bank of India (RBI) 1.7 Final financial package CEA 1.8 External borrowings Reserve Bank of India, Ministry of Finance, Government of India, Income Tax Authorities. 2.0 NON-STATUTORY CLEARANCES 2.1 Land availability Government of State / Private Land 2.2 Fuel linkage and approval of fuel supply agreement Department of Petroleum and Natural Gas 2.3 Transportation of Fuel Department of Petroleum and Natural Gas, Ministry of Railways, Shipping and Surface Transport (Indian 127 New SL. NO. CLEARANCES AUTHORITY 2.4 Approval of Contractor, O&M Reserve Bank of India Contractor and other financial and legal advisors, including payment of their fees, services, etc., in foreign currency. 2.5 Real Estate, Rights & right to access and use of Site, including Right of Way for all corridors to the Facility 3.0 OTHER CLEARANCES/ APPROVALS 3.1 Approval as per Explosives Act and Chief Controller of Explosives Rules 3.2 Approval as Regulation 3.3 Approval as per Indian Electricity Act Electrical Inspectorate and Rules for Electrical Installation 3.4 Approval as per Indian Petroleum Act Chief Controller of Explosives and Petroleum Rules for storage and transport of Petroleum Products 3.5 Approval as per gas cylinder rules and Chief Controller of Explosives handling and transport of compressed gases 3.6 Approval of weigh bridge and weigh Inspector scales Measure 3.7 Allocation of Liquid Petroleum Gas per Indian Government of State Concerned Authorities Relevant Village Panchayat / / Boiler Chief Inspectorate of Boilers 128 of Weights and Director of Industries, Government of State SL. NO. 3.8 CLEARANCES AUTHORITY (a) Collection, storage and disposal of waste (b) Site clearances, safe report and safety audit SPCB 3.9 Approval Scheme of Fire Protection 3.10 Confirmation of Collector / Directorate of Town and Planning for the use of the site for the construction and operation of the Power Station and Fuel Facility 3.11 Consent of relevant Panchayat for the development of Project Site and the Township site 3.12 Approval of Chief Inspector of Factories of the proposed design and construction of power station and fuel facility (a) (b) Fire Brigade Tariff Advisory Committee Directorate Planning of State of Town and Government of Directorate of Town and Planning of Government of State Chief Inspector of Factories of Government of State SEB 3.13 Allocation / approval of electric supply for construction power and Contractor’s township in colony area SEB 3.14 Allocation for Owner’s township 3.39 of electric supply Approvals / clearances for labour / Concerned Authorities man power like License from labour commissioner for Construction labour, Registration of workers or exemption to be claimed if group insurance taken for some, etc 129 CHAPTER – XVII PROJECT COST ESTIMATES 1. PROJECT COST The total project cost including IDC is estimated at Rs. 6 9 7 1 Crores (about Rs. 5.28 Crores / MW) for the 1320 MW capacity. This cost is at par with industry standard. The Project Cost Break-up is given as under: Total Cost Description Land, Site Development including water storage EPC contracts Customs Duty @ 25%/ Excise Duty @ 12.5% Total Hard Cost Preliminary and Pre‐operative expenses 4870 933 5803 200 Margin Money for working capital IDC & Financing Costs Contingencies @ 5% of Hard Costs Project insurance Total Project Cost 204 648 94 22 6971 PRE-OPERATIVE AND PRELIMINARY EXPENSES Preliminary 10 crs Insurance 15 crs Admin & Personal Cost 60 crs Start up & Other Expense 60 crs MFA 20 crs PMC 35 crs 130 2. INTEREST DURING CONSTRUCTION PERIOD Interest on loan during construction (IDC), which is part of the project cost has been calculated based on debt-equity ratio of 75: 25 and weighted average interest rate. 3. TARIFF Power Purchase Agreement for 800 MW is to be signed with GUVNL for a period of 25 years. The cost per kWh based on standard evaluation criteria works out to Rs. 2.80 (levellised) and Balance power will be on Merchant sale. 4. ASSUMPTIONS CONSIDERED IN FINANCIAL PROJECTIONS The two-part tariff model as per the guidelines of Government of India has been adopted to calculate the cost of generation : Debt – equity ratio : 75 : 25 Cost of coal as received at site : USD 50.00 per ton Cost of fuel oil as received at site : Rs.17,000 / KL Interest rate on domestic debt : 11.5% per annum construction & 11.5% operations. Depreciation : Depreciation at 5.28 Straight line Method. Operation and maintenance charges : 18.38 Lacs/MW escalated at 4% p.a. Gross heat rate : 2130 Kcal/ kWh Gross calorific value of coal : 4900 k Cal / kg Repayment period for loans : Moratorium of 1 year from COD and thereafter repayment in 40 equal quarterly instalments. during during % Details of working capital (a) Margin money : 25 % of total working capital (b) Interest rate on balance of working capital : 11 % per annum 131 on Auxiliary power consumption: Conservatively considered 6.5% 5. FIXED CHARGES The items of cost forming a part of the fixed charge component are : a) Operation and maintenance charges b) Interest on loan becoming due during the year c) Interest on working capital d) Deprecia ion/Repayment e) Return on equity f) Income Tax. 6. VARIABLE CHARGES The variable charge component of the tariff includes the cost of primary fuel which is imported coal and secondary fuel which is fuel oil. Based on government of India norms, the following are considered while computing the annual running cost for periods beyond the initial stabilisation period: (a) Annual cost of fuel oil (b) Annual cost of coal. (c) Annual cost of water 132 APPENDIX - 1 PROJECT SITE DATA 1. Location of the plant Nearby Nana Manda Khajurda Village, Dist Devbhumi Dwarka ,Gujarat. 2. Elevation above mean sea level 31.5m 3. Climatic conditions 3.1 Temperatures : Monthly basis Highest Temperature Recorded Minimum Temperature Recorded Average Ambient Temperature Wet buld Temperature 48 deg.C 5 deg.C 34 deg.C 28 deg.C 3.2 Relative humidity Varies between 27% and 96% 3.3 Annual average rain fall Annual average rainfall is about 535.7 mm (most of which occurs during the monsoon season from June to September) 3.4 Wind speed - Maximum - Aveg. Wind speed 50 m / s. 15.37 m/s Seismic data (as per IS : 1893) Zone V 4. 133 APPENDIX - 2 SEA WATER ANALYSIS Sr.No Test Parameters Unit Result 1 Color APHA 5 2 Oil & Grease ppm ND 3 BOD ppm <5 4 COD ppm 32 5 Suspended Solid ppm 6 Turbidity NTU 10 < 16.1 7 Calcium Hardness as CaCO3 ppm 1011 8 Magnesium Hardness as CaCO3 ppm 6714 9 Chloride as Cl ppm 23716 10 Sulphate as SO4 ppm 3450 11 Sulphide as S ppm ND 12 M-Alkalinity as CaCo3 ppm 126 13 P-Alkalinity as CaCo3 ppm 6.0 14 Nitrate as NO3 ppm 3.5 15 Nitrite as NO2 ppm 50 16 Silica as SiO2-Dissolved ppm 1.43 17 Iron as Fe-Dissolved ppm 0.5 18 Iron as Fe-Suspended ppm ND 19 Total Dissolved Solids ppm 37542 20 Conductivity at 25°C µ-mho/cm 56034 21 pH at 25°C 22 Dissolved Oxygen as O2 8.1 ppm 134 7.0 APPENDIX - 3 ANALYSIS OF IMPORTED COAL Proximate analysis Worst Design Best TOTAL MOISTURE 39 11.5 5 ASH 3 24 24 VOLATILE MATTER 30 25.6 19.2 FIXED CARBON 29 38.9 51.8 4000 4922 6060 GCV (ARB) APPENDIX - 4 ANALYSIS OF FUEL OIL Unit Sl. No. Particulars 1. Flash point Deg. C min. 66 2. Viscosity @ 150C Maxi. Cst 180 3. Power point 0 21 4. Ash content by weight % max. 01 5. Free Water content by volume % max. 1.0 6. Sediments by weight % max. 0.25 7. Total sulphur by weight % max. 4.0 8. Calcium PPM 30.5 9. Sodium PPM 10 10. Lead content PPM 0.2 11. Vanadium PPM 40.50 12. Carbon residence (Rams bottom) % wt 7.74 13. Approximate gross calorific value Kcal/kg 14. SP gravity at 150C Max. C Furnace Grade MV2 : 1593) 10,000 0.933 135 Oil (IS APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT 1.Name /Title of the project : 2 x 660 MW, Imported coal based thermal power plant at Nana Manda & Khajurda, Gujarat. 2.Name and address of the project : Mr. Ramesh kumar proponent Essar Power Gujarat Limited (EPGL) 44th KM Jamnagar-Okha Highway, Village Kajurad, Dist Devbhumi Dwarka. 3.Site where proposed plant would be located (Site map, Land : Nana Manda & Khajurda, Dist Devbhumi Dwarka, Gujarat layout plan to include 25 km radius zone around the site ) 4.Capacity of the project under : 2x660 MW supercritical consideration 5. Whether alternative sites were : No, since this site was found most suitable explored? If so, give details for each site (Maps to be enclosed) 6.Land use pattern of the land : Mostly non agricultural land, some land occupied by salt pans, balance low productive agriculture land. 7. Cost of land : Covered under project cost 8.Govt. land / private land/ others : 100 % Government land. 9. Topographical features, : Generally flat drawing towards north (Refer demographic profile and Chapter - VI of the Report) physiography. 10.Nature of soil : Sandy, Murram 136 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT 11.Distance from the nearest : 11 km from Khambhalia town town/city/major human settlement 12. Population to be displaced : None 13. Distance from water source : 15 Kms 14. Area of forest land, if involved : Nil 15.Distance of forests from the site : NA 16. Give basis for selection of site : i) The land is barren and is not inhabited ii) The site is 500 m from State Highway. Nearest railway station is about 11 km from site. iii) Availability of adequate land iv) Availability of adequate quantity of sea water from arbian sea : Yes, operational 2 x 600 MW as Phase- I 17.Is this an extension? If so indicate capacity of the existing plant 18. What is the ultimate capacity? 19. Name and address of the consultant, if any : 2x660 MW : Tata Consulting Engineers Ltd. St. Mark’s Road, Banglore - 560001 137 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT GENERAL ENVIRONMENTAL INFORMATION 20. Details of major industries, : Within 10Km area- There are a number of stone thermal power plants, mines, crusher, one ceramic making plant and other quarries etc. Existing within small mills. Ship building activity takes place at a radius of 25 km of your nearby Salaya port (minor port). plant Within 25km area- Refinery of Essar oil and Reliance refinery. 21. What is the total human population of 25 km of the : There are 21 villages in 10km area of the site. The total population is approximately 88934. plant site indicate the pattern of population dispersal. 22. Give a broad description of the site. Attach map : Refer Exhibit-1. The site is approachable from Khambhalia state highway. showing topographical features 23.Nature of soil : Refer Chapter VI 24.Area of the land proposed to : Already in possession of total land of 330 Ha be acquired (Attach layout plan) 138 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT Area required for plant : For Phase- II (BTG & BOP) 125 hectares Green belt : as per MOEF norms Ash disposal Colony (indicate separately for departmental staff, contractors (if any) iv) Transmission corridors and power evacuation system v) Approach road, railway bridges etc. : Existing ash pond 25 hectares : Not envisaged. Existing Essar oil refinery colony would be used By 400kV switchyard. Evacuating to 400kV : GETCO / PGCIL substation. : Jamnagar –Okha state highway, Widening and strengthening of existing village roads & bridges. No railway network 25.Present use of land : Not Applicable 26.Area proposed to be built-up : Refer Exhibit –I or developed 27.Specify site characteristics : Coastal River basin/estuarine/ coastal/others 139 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT 28.Is the site situated in the : No forest area? Give following details:i) Area : Not applicable ii)Type of forests : Not applicable iii) If site is situated nearer to : Not applicable the forests? Give the distance from the site iv) Give a description of the : flora within 10 km of your plant site under the following heads:a) Crops b) Forest c) Grassland d) Endangered species Maize, Bajra and wheat are the main crops Not Applicable Community level grassland are present. Mangroves along the coast line on muddy patches of land e) Other (Specify) v) Give a general description of : The national park exists within 25km of site. the fauna, especially wildlife, endangered species, etc., within a radius of 25 km 140 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT vi) Give details of the following : features, if they exist, with-in a radius of 25 km of the proposed site? Yes Marine Sanctuary / Marine national Park i) Fisheries ii) Sanctuary / natural park / Biosphere rese ves None iii) Lakes / ponds / reservoir Small streams/nalla are present Yes iv) Stream / river v) Estuary / sea None vi) Hill / mountains vii) Historic / cultural /tourist / archaeological/scenic sites / None defense installations 29.Human Settlement Total number of : Refer Exhibit-10 persons proposed to be employed. i ) During construction 3000 (peak construction) ii) During operation 400 Plant personal 30.Do you propose to build a : Existing colony of Essar. Refinery at Vadinar township / housing quarters would be used to accommodate power plant for your personnel also. employees/contractor's workers? 31.Area required for above : Not applicable 141 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT 32.Population to be : During detail engg accommodated 33. Distance and direction of Within a radius of 25km from plant township from plant site Service provided in township. Daily consumption of water : 150lt /person/day Power system : 1KW/person /day Sewage treatment : The sewage (120lt/person/day) will be treated in STP Drainage : The treated water will be used for green belt. Any other : Market, school, bank, post office, police station, telephone, transport, hospital recreation halls 34.Number of persons to be : displaced along with details of their occupation and income i) Number of persons who do : not own property, but, derive their sustenance from the No rehabilitation and resettlement is envisaged land to be acquired ii) Details of rehabilitation plan : for the oustees iii) Site where they would be resettled : 142 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT iv) Compensation to be paid : v) Authority responsible for their : resettlement FUEL 35 .Has fuel linkage been established. i)Type, and : For coal characteristics refer Appendix – 3. quantity characteristics of fuel used ii) Has the linkage been : Established established? iii)Name of Mine/Block : Imported coal iv) Is it a working mine or : working yet to be opened? v) Is the mine situated in the : Not applicable. forest area? vi)Please furnish a fuel analysis : Refer Appendix - 3 report from a recognized laboratory (Details to include percentage contents of C, H, N, S and Oxygen (if any) and gross calorific value) vii) Indicate the type of fuel : Pulverized coal firing firing to be adopted 143 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT viii) Air to fuel ratio to be : During detail engineering stage specified WATER 36.Water use and liquid wastes (provide a detailed : Refer Exhibit- 3 water balance diagram) 37. What is the source of : Arabian sea water (Gulf of kutch) Water? Would it be adequate for the future use? Do you propose any measures to augment the water supply and how it affects other users 38.Lean season flow : During detail engineering stage 39.Give details of the receiving : Arabian sea water (Gulf of kutch) water body 40.Average daily approx. quantity of Water required for i) Cooling tower blow-down : Refer Exhibit- 3 ii) Evaporation and drift loss : ii) Cooling tower makeup(i+ii) : Total daily water requirement : 144 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT 41.What type of cooling system : Open cooling system with natural draught cooling towers is proposed once through/closed Give temperature difference : Temperature rise across condenser is 10C between inlet and outlet Annual temperature profile : Normal raw of the receiving water water temperature variation is expected. 42.Quantity and expected : characteristics of the waste water discharged per day from the plant i) Cooling : Not applicable ii ) Cooling Tower Blow-down : 8690 m3/hr iii) Process : 1548 m3/hr iv) Others : v) Total : 43.Type treatment of waste proposed 10238 m3/hr water : The effluent from DM plant and plant drains led to to adopted for each stream be guard pond, which would be used for plant washing, gardening and miscellaneous services The CW blow down would be returned back in to the sea 44.Applicable standards : MOEF / CPCB/ GSPCB regulations regulations for the Effluents 145 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT 45.Point of final discharge land : Sea. / sewer / river / lake /bay / estuary / sea 46.Mode Open of final channel / discharge : Mode of final discharge is through pipeline with pipeline / diffuser arrangement covered drains 47.If the liquid effluents are : Not applicable finally discharged to river/pond/lake, the impact on the quality of Water at the nearest human settlement should be mentioned 48.Details of the reuse of : Cooling tower will be installed. waste water AIR EMISSIONS 49.Please furnish for your : Refer Chapter XIV location 50.Wind rose i)Mean, maximum : Refer plot plan and : minimum temperature for every month of the year ii)Mean wind speed : iii)Humidity : iv)Mean cloud cover : Refer project details 146 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT v)Percentage(frequency) : occurrence of inversions and heights vi)Please specify the following: : vii)Number of stacks : One Twin flue stack for two units viii)Number of flues in each : Two stack ix)Inter-stack distance : - x)Stack height : 275m xi)Internal diameter of : 7.6 m (Approx.) each flue at the top xii)Gas velocity : 20 – 25 m / sec approx. (at exit) Flue gas characteristics : i) Volume (through each stack) : During detail engineering ii) Temperature : During detail engineering iii) Density : 1.286 kg/Nm3 Size distribution of : During detail engineering particulates v) Gas composition (by Vol. ) : Typical CO2 : 13.7% O2 : 9.2 % SO2 : 0.01 % 147 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT N2 H2O : 74.5 % : 2.6 % vi)Heat emission rate of gases : During detail engineering from each stack : SO2 : During detail engineering. Particulates < 30 mg / Nm³ per boiler with worst each coal firing and ash content of 24% vii)Emission rate of SO2, NOx and particulates stack in milligm/ m3 from . viii)Back ground pollution levels of SO2, NOx and particulates microgram/m3 : SO2 – Less than 80.0 NOx -Less than 80.0 (within 10km area) 148 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT a) What kind of stack emission : Flue Gas Monitoring: These are measured at the monitoring is proposed economizer outlet. For this purpose, O2 CO monitor probes analyzers are installed separately Stack emissions: Flue gas exiting into the atmosphere is monitored for CO2, NOx, SO2 and opacity. Stack emission readings are sent to the DCS for monitoring. For this purpose, dilution probes, associated gas analyzers support equipment, sample lines and opacity sensor/ transmitters are installed. The opacity sensors equipped with a blower to protect the optics from coating by flue gas particles. The system operation is continuous. Stack gas analysis for SO2 , CO2 and NOx is performed by extracting a gas sample from the flowing stream in the stack, filtering to remove particulate droplets, diluting with scrubbed instrument air and conveying the sample to the analyzers b) What equipment is proposed : Same as above to be acquired or used for this purpose c)Give pollution details control of the air : High Efficiency electrostatic precipitator to limit equipment proposed to be installed particulate emission to 30mg / Nm 3 at ESP outlet with worst coal firing and ash content of 24% 149 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT d)Give details organization of the : There would be an experienced and qualified chief set-up for chemist in charge of analytical measurements and maintenance of pollution control equipment and level expertise pollution control of and authority of person in charge e)Emission rate of particulates and sulphur dioxide to released when : SPM- < 30 mg/Nm3 be SO2 and NOx will be dispersed through 275m control tall stack. equipment is : f)Functioning normally SO2 : Particulates : With worst coal firing and ash content of 24% Wet type FGD (limestone based) is proposed. < 30 mg / Nm3 (with all fields of ESP in operation). g) Not functioning SO2 : Not applicable as the plant would be shut down Particulates : - h)What special procedure do : Adequate design margins and standby capacity you propose to lay down for the are provided air pollution control during the precipitators to forestall such problems period when emission exceeds prescribed limits for any reason including malfunction of pollution control equipment? 150 for proposed electrostatic APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT 51.Other types of pollution : Water sprinkling measures to reduce fugitive dust emissions a)Details of measures to control : All equipment would be designed / operated to noise have a total noise level not exceeding 85 to 90 dB (A) measured at a distance of 1.5 m b)Details regarding prevention and control of fire and explosion hazards : All equipment vulnerable to explosion or fire would be designed to relevant IS codes statutory regulations. Suitable fire protection system comprising hydrants and spray systems are provided for fire protection TRANSPORTATION OF FUEL: 52. Proposed mode of transport : Imported coal / of coal/ oil/ gas. Essar refinery near to site. i)By sea : Coal ii)By Road : Fuel oil iii)By Pipe / Rope ways : Nil iv)By Rail/Road : Coal v) By Others : Nil 151 Oil from APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT Coal and Ash Handling: 53. What procedure would be : Coal would be received by ships, transported from adopted for coal handling at the the jetty to plant site through closed conveyors to plant site? the stock pile. Coal within the plant from stockpile yard to coal bunkers would be transported through series of belt conveyors and traveling trippers. i)Give details suppression equipment of dust : Dust extraction system at all coal transfer points, / collection bunker ventilation system for coal bunkers would for reducing be provided and dust suppression system in the pollution from coal fines and stock yard is provided. other fugitive emissions from coal handling (conveyor transfer points, storage, Bunker filling etc.) Ii) How do you propose to : Not applicable prevent /treat the run-off from the coal storage/ handling area ? iii) What quantity of fly ash And : Total ash expected: 1464 t/day per unit ( with 24% bottom ash would be produced ash content) per day Fly ash: 1171 t / day per unit Bottom ash: 152 2 9 3 t / day per unit APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT iv) Indicate the method of : Fly ash: Fly ash collected in various hoppers collection, transportation and would be pneumatically (pressure) conveyed to disposal of the ash the silos. From silos it would be either conveyed to the disposal area in the form of high concentrated slurry or collected in dry form for commercial use Bottom ash : would be disposed off in dry / wet form Provision has been kept to dispose off the Ash generated in high concentrated slurry form v) What efforts have been : Arrangements would be made with private made or you wish to make entrepreneurs for utilizing fly ash for commercial towards utilization of fly ash for purposes Bricks /cement/ road construction/land fill/soil stabilization/ other forms of disposal or use vi) What precautions are : As high concentrated slurry disposal is envisaged proposed to be taken to prevent ,ash disposal pond would be completely lined with pollution of water source and impervious liner to prevent ground water pollution. ground water from solid waste disposal, especially with regard to coal particles and ash slurry? 153 APPENDIX - 5 BASIC INFORMATION FOR ENVIRONMENTAL APPRAISAL GENERAL INFORMATION ABOUT THE PROJECT vii) What land area is available : Around 25 hectares of land has been identified for for ash disposal? Would it be ash disposal which is adequate for the expected sufficient for the expected life of plant life in the existing facitilty. the plant ? 154 54.0 CONSTRUCTION MATERIALS i) Indicate source of supply of : Construction materials would be available with in stones and location of quarries in the site map with radius of 50 km. the alignment of the roads to the projects site and its distance from the site ii) Source of supply of sand and : Local available services within 50kms its distance from the site iii) If new roads are built : Widening & strengthening of existing village roads whether their alignment is outside the plant through agriculture land /forest/ grazing land/human settlement/fallow land iv) Mode of transportation of : All power plant equipment and construction heavy equipment, cement steel materials would be transported by Sea/ road to i.e. by road or rail or sea the power plant site v)Name of the nearest rail head : The nearest Railway station (Khambhalia) is where they would be off loaded located at a distance of 20 Km from the proposed and its distance from the site site vi)If a new road is to be built : Not required from the rail head, the details of land to be acquired should be given OCCUPATIONAL SAFETY AND HEALTH 55.Health status of workers : In coal handling areas suitable dust control especially those engaged in the /collection equipment are provided to ensure a coal handling, ash collection clean and healthy environment. No problems are and ash disposal area envisaged in ash disposal area where slurry disposal has been envisaged 155 56.Whether any adverse health effect due to noise : Noise level would be limited to 85-90 dB (A) in were these areas and hence no adverse health observed among the workers engaged in compressor the turbine, room, crushing problems anticipated mills etc 57.If the plant is new, precau- : Adequate measures would be taken as required. tionary measures proposed to be taken for safety and health protection of workers may be mentioned ENVIRONMENTAL MANAGEMENT 58.Give details organizational of : Qualified Engineer would be given responsibility of set-up you have for propose to pollution monitoring the pollution monitoring and control. and control ? 59.What is the expertise of the level of : Qualified engineers would be job person in charge of pollution control ? 60.Briefly outline the proposed : environmental monitoring programme, mention No. of observation sites and frequency of observations addressing to the following parameters: i)Air : Refer Chapter – XIV ii)Water : Refer Chapter – XIV iii)Ground water : Refer Chapter – XIV iv)Stack Monitoring : Refer Chapter – XIV 156 employed for the v) Have you been asked by the : Refer Chapter – XIV Central State Pollution Control Boards to take any special Environmental control measures and how do you Propose to carry out these obligations? vi) Raising of green belt(Area : The area may be indicated in a map) allocated for the Green belt would be developed in and around 250-300 acres of the power plant DETAILS OF EXISTING UNITS 61.If it is an extension, Please : Phase-I of 2 x 600MW (Under operation) furnish the following details in respect of the existing units: Existin g units and their capacity 2 x 600 MW Efficien cy of ESP in % 99.8 Fuel consumpti on(coal/oil /gas)tonne s/day Sulphur content in % 11568 0.01 62. Have there been public : No complaints or questions in the Parliament or State assembly regarding the environment problems posed by the existing Units. If so, give details 157 Stack height in m 275 Heat emission rate in kcal/hr from stack NA Particulates SO2 NOx NA NA 63.Have there been any : Nil representation / protests from the Public/voluntary organizations against the setting up of the new units/plant at the Proposed locations if so, give details 64.Economics of Pollution : Control Excluded from the scope of this report. During detail engg 65.What is the total project cost : During detail engg 66.Indicate costs of pollution : During detail engg ? control under the following heads Capital / Recurring (annual) : Included above Air : Included above Fly ash control : Included above Sulphur dioxide control : Included above Oxides of Nitrogen control : Included above 158 PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT AEGIS LTD - ESSAR ENGINEERING SERVICES DIV., HAZIRA 750 750 3000T 3000T 3000T 3000T