Landfill Start-Up, Shutdown, and Malfunction Plan Startup, Shutdown, and Malfunction Plan for the Landfill Gas Collection and Control System City of Midland Landfill Midland, Michigan Prepared for City of Midland Landfill 4311 East Ashman Road Midland, Michigan 48642 July 2010 Rev 02 – June 2011 Prepared by CTI and Associates, Inc. 51331 W. Pontiac Trail Wixom, Michigan 48393 CITY OF MIDLAND LANDFILL LANDFILL GAS COLLECTION AND CONTROL SYSTEM STARTUP, SHUTDOWN, AND MALFUNCTION PLAN TABLE OF CONTENTS 1.0 INTRODUCTION ................................................................................................ 1-1 1.1 Background ........................................................................................................ 1-1 1.2 Definitions........................................................................................................... 1-1 1.3 Excluded Components ....................................................................................... 1-2 1.4 Included Components ........................................................................................ 1-2 1.5 Regulatory Contacts ........................................................................................... 1-3 1.6 Owner/Engineering Contacts ............................................................................. 1-3 2.0 SSM SCENARIOS ............................................................................................. 2-1 2.1 Collection System............................................................................................... 2-1 2.2 Control System – Open Flare ............................................................................. 2-2 2.3 Control System – Compressor System .............................................................. 2-4 3.0 STANDARD OPERATING PROCEDURES ...................................................... 3-1 3.1 Control System Startup – Compressor System .................................................. 3-1 3.2 Control System Shutdown – Compressor System ............................................. 3-1 3.3 Control System Startup – Flare System ............................................................. 3-2 3.4 Control System Shutdown – Flare System ......................................................... 3-2 4.0 MODIFICATIONS, RECORDKEEPING, AND REPORTING ............................. 4-1 4.1 Modifications ...................................................................................................... 4-1 4.2 Recordkeeping ................................................................................................... 4-1 4.3 Reporting ............................................................................................................ 4-2 Pn-CML SSM Rev 02 - Final.docx i CITY OF MIDLAND LANDFILL LANDFILL GAS COLLECTION AND CONTROL SYSTEM STARTUP, SHUTDOWN, AND MALFUNCTION PLAN APPENDICES APPENDIX A: SSM Recordkeeping Forms, including Completed Forms APPENDIX B: Summary of SSM Plan Revisions Pn-CML SSM Rev 02 - Final.docx ii CITY OF MIDLAND LANDFILL LANDFILL GAS COLLECTION AND CONTROL SYSTEM STARTUP, SHUTDOWN, AND MALFUNCTION PLAN 1.0 INTRODUCTION 1.1 Background This Startup, Shutdown, and Malfunction (SSM) Plan was prepared to satisfy the requirements of the National Emissions Standards for Hazardous Air Pollutants (NESHAP) for municipal solid waste (MSW) landfills (40 CFR Part 63, subparts A and AAAA). The purpose of the NESHAP is to prevent excess emissions of hazardous air pollutants (HAPs) during a startup, shutdown, or malfunction event of the landfill gas collection and control system (LFGCCS) and associated monitoring equipment. This Plan was specifically prepared for the City of Midland Landfill (CML), located at 4311 East Ashman Road, Midland, Michigan. The CML is a licensed Type II MSW landfill, owned by the City of Midland, Michigan. This SSM Plan should be followed during all SSM events at CML. The Plan identifies the procedures for operating and maintaining the LFGCCS during SSM events. The Plan identifies procedures to adequately provide corrective actions to repair the malfunctioning equipment as soon as practicable and to minimize excess emissions of HAPs. Recordkeeping documents and reporting requirements are also included. 1.2 Definitions The NESHAP defines the following terms: Startup: “the setting in operation of an affected source or portion of an affected source for any purpose”. Shutdown: “the cessation of operation of an affected source or portion of an affected source for any purpose”. Malfunction: “any sudden, infrequent, and not reasonably preventable failure of air pollution control and monitoring equipment, process equipment, or a process to operate in a normal or usual manner which causes, or has the potential to cause, the emission Pn-CML SSM Rev 02 - Final.docx 1-1 City of Midland Landfill Landfill Gas System SSM Plan June 2011 limitations in an applicable standard to be exceeded. Failures that are caused in part by poor maintenance or careless operation are not malfunctions.” 1.3 Excluded Components The following items are not included in the requirements of the NESHAP or this SSM Plan: Failure of portable analyzers used to monitor landfill gas quality or conduct surface emissions monitoring (i.e., GEM, EAGLE, FID). Exceedances of parameters monitored monthly at individual landfill gas (LFG) extraction wells (temperature greater than 55 degrees Celsius, zero or positive pressure, and either nitrogen concentration greater than 20% or oxygen concentration greater than 5%). Exceedances of required quarterly monitoring of methane concentration at the landfill surface (surface emissions greater than 500 parts per million above background concentration). 1.4 Included Components The following items are included in the requirements of the NESHAP and this SSM Plan: The landfill gas collection system including, but not limited to, header piping, extraction wells, collection trenches, driplegs, condensate knockout pots, straw drain manholes, condensate/leachate pumps, and valves. The landfill gas control system including, but not limited to the open flare, blower and motor, compressors, ignition and operation equipment, continuous recording devices. The gas treatment system, such as those used to filter, dewater and, compress landfill gas for use as fuel in a gas to energy facility. Pn-CML SSM Rev 02 - Final.docx 1-2 City of Midland Landfill Landfill Gas System SSM Plan June 2011 1.5 Regulatory Contacts All reporting information related to the SSM Plan should be submitted to the Michigan Department of Natural Resources and Environment (MDNRE) at the following address: MDNRE Air Quality Division Saginaw Bay District Office 401 Ketchum Street, Suite B Bay City, Michigan 48708 Phone (989) 894-6214 (Ms. Kathleen Brewer, current Env. Specialist for CML) Fax (989) 684-9799 1.6 Owner/Engineering Contacts Owner: City of Midland, Michigan City of Midland Landfill 4311 East Ashman Road Midland, Michigan 48642 Scott O’Laughlin, Landfill Superintendent Phone: 989-839-6535 Cell Phone: 989-615-6231 Engineer: CTI and Associates, Inc. 51331 West Pontiac Trail Wixom, Michigan 48393 Phone: (248) 486-5100 Fax: (248)486-5050 Contact: Beth Benoit (248) 486-7308 or Xianda Zhao, P.E. (517) 420-7174. Pn-CML SSM Rev 02 - Final.docx 1-3 City of Midland Landfill Landfill Gas System SSM Plan June 2011 2.0 SSM SCENARIOS For SSM recordkeeping and reporting purposes, the LFGCCS has been divided into two main components; the collection system (including wells, piping, valves, and driplegs), and the control system (including the skid mounted flare system, the mechanical dripleg and pumping station, and the compressor and chiller/reheater system). Likely malfunctions for each of these main components are listed below along with immediate and corrective actions to be taken. For each SSM event, an SSM Recordkeeping Form, included in Appendix A, must be completed. The person completing the Form will refer to the list below to identify the component affected, the likely malfunction, the immediate action, and the recommended corrective action. 2.1 Collection System Likely Malfunction Immediate Action Corrective Action No/low flow due to pinched/damaged/settled piping/frozen piping Open or close control valves to allow continued flow to the control system and to prevent unnecessary air intrusion. Determine location of damage/settling. Repair piping by replacing damaged pipe, regrading settled areas, or thawing/covering frozen pipe. Failure of control valves If LFG is leaking to atmosphere or causing air intrusion, close/open surrounding valves and/or wellheads. Isolate affected area and replace valve. Failure of an extraction well due to: frozen or broken flexhose, fire, high water level If LFG is leaking to atmosphere or causing air intrusion, close/open surrounding valves and/or wellheads or temporarily cap wellhead. Replace/repair flexhose, isolate well/remove vacuum to control fire, pump extraction well or surrounding leachate collection system. If required, replace extraction well. Failure of a condensate drainage feature (dripleg/knockout/straw drain manhole) Isolate drainage feature by closing surrounding valves to prevent air intrusion. Refill dripleg/straw with water, cleanout blockage, or if necessary excavate area and check for damage. Collection system expansion Isolate header line affected by the expansion by closing surrounding valves to prevent air intrusion. Complete expansion of the LGCCS using best available engineering practices. Pn-CML SSM Rev 02 - Final.docx 2-1 City of Midland Landfill Landfill Gas System SSM Plan June 2011 2.2 Control System – Open Flare Likely Malfunction Immediate Action Corrective Action Wind/storm blowing out flame If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Follow SOP for flare startup. High water level in the condensate knockout If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Pump condensate from knockout into either lift station or nearby leachate manhole. Investigate blockage, repair, and restore drainage. High water level in the lift station due to blockage, damaged and/or frozen piping If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Pump condensate from mechanical lift station into nearby leachate manhole. Investigate blockage, repair, and restore drainage. Failure/malfunction of the lift station pump If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Repair pump or use temporary pump to remove condensate. Not able to restart due to ambient temperature, frozen pilot If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Use override function to initiate startup at lower temperature. Thaw the pilot. Failure of blower, including bearings, belts, fan wheel, etc. If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Repair blower using appropriate replacement parts. Failure of motor If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Repair motor using appropriate replacement parts. Failure of compressor, airlines, fittings, actuators, solenoids If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. If actuator fails, close the flare inlet valve. Repair the failed component using appropriate methods/replacement parts. Too much oxygen in the gas or If shutdown occurs, system lack of LFG flow to the flare automatically closes actuator valve to prevent LFG venting. Identify cause of oxygen or blockage of flow and repair according to SSM Plan. If oxygen level is due to extraction wells that are out of compliance, adjust wellfield to compensate. Pn-CML SSM Rev 02 - Final.docx 2-2 City of Midland Landfill Landfill Gas System SSM Plan June 2011 Likely Malfunction Immediate Action Corrective Action Loss of electricity If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Either utilize back-up generator or monitor surface emissions until electrical supply is restored to demonstrate compliance with air emissions standards. Failure of the flow and temperature recorder and/or meter – memory card malfunction, electrical malfunction If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Manually verify ongoing operation of the control device. Replace affected component; memory card, recorder, meter. Repair electrical supply as necessary. Not able to restart due to lack of pilot fuel (propane) If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Switch to existing backup fuel supply and replenish primary supply. Failure of the thermocouple If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Replace thermocouple with onsite backup unit. Failure of the flame arrestor (clogging, freezing, etc.) If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Clean flame arrestor or replace if necessary. Failure of the knockout pot, including plugging of the filter, high water level, etc. If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Clean the filter, remove collected water. Shutdown of flare due to high water levels in flare stack If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Empty flare stack drain(s). Accidental pressing of emergency STOP button If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Follow SOP for flare startup. Routine Maintenance If shutdown occurs, system automatically closes actuator valve to prevent LFG venting. Follow SOP for flare startup. Pn-CML SSM Rev 02 - Final.docx 2-3 City of Midland Landfill Landfill Gas System SSM Plan June 2011 2.3 Control System – Compressor System The following malfunctions refer to pre-programmed trips in a single compressor. Likely Malfunction Immediate Action Corrective Action Compressor oil temp/pres out of spec Compressor automatically shuts down; valve to the pipeline will automatically close. Repair/replace damaged/malfunctioning parts. Gas suction/temp/pres out of spec Compressor automatically shuts down; valve to the pipeline will automatically close. Repair/replace damaged/malfunctioning parts. Motor overheat/overload Compressor automatically shuts down; valve to the pipeline will automatically close. Repair/replace damaged/malfunctioning parts. Chiller high level Compressor automatically shuts down; valve to the pipeline will automatically close. Determine cause of high level in chiller and address. LEL level reached in compressor building Compressor automatically shuts down; valve to the pipeline will automatically close. Ventilate building and correct cause of high gas level. Pn-CML SSM Rev 02 - Final.docx 2-4 City of Midland Landfill Landfill Gas System SSM Plan June 2011 3.0 STANDARD OPERATING PROCEDURES Following are standard operating procedures (SOP) for startup and shutdown events of the control systems (both compressors and open flare). These SOPs must be followed during every startup and shutdown event. 3.1 Control System Startup – Compressor System 1. Check for unsafe conditions in the surrounding area, i.e. exposed fan belts, leaking LFG or propane gas, etc. 2. Turn off flare blowers. 3. Turn on compressor at building. 4. Start chiller/reheater system. 5. Start flare in “manual operation” until block valve connecting FCV-3300 opens. 6. Open FCV-3300 to minimum required for predetermined minimum LFG flow to flare. 7. Open FCV-3100 to pressurize pipeline. 8. Turn on ONE compressor with VFD = 50% with slide valves in open position. 9. If VFD exceeds 80%, turn on second compressor. 3.2 Control System Shutdown – Compressor System 1. Check for unsafe conditions in the surrounding are, i.e. exposed fan belts, leaking LFG or propane gas, etc. 2. Shutdown the control system by any of the following: press the emergency stop button; turn off the electrical supply using the main electric panel switch. 3. Ensure that FCV-3100 is CLOSED and that FCV-3300 is OPEN. 4. Perform “Control System Startup – Flare System” if flare is not operating at time of compressor shutdown. Pn-CML SSM Rev 02 - Final.docx 3-1 City of Midland Landfill Landfill Gas System SSM Plan June 2011 5. Verify that the system is properly shutdown (check flow rate, temperature, pressure). 3.3 Control System Startup – Flare System 10. Check for unsafe conditions in the surrounding area, i.e. exposed fan belts, leaking LFG or propane gas, etc. 11. Check that the valves are open and in proper operating position. 12. Reset the emergency stop button if necessary. 13. Check the fuel supply for the spark ignition (propane gas) 14. Check for adequate electrical supply to the control system. Reset circuit breakers or other controls if necessary. 15. Start the control system by turning the “flare power” dial “on” and pressing the “start” button. 16. Verify that the system is operating properly (check flow rate, temperature, and pressure). 3.4 Control System Shutdown – Flare System 6. Check for unsafe conditions in the surrounding are, i.e. exposed fan belts, leaking LFG or propane gas, etc. 7. Shutdown the control system by any of the following: press the emergency stop button; turn the “Flare Power” knob to off, turn off the electrical supply using the main electric panel switch. In an emergency where access to the flare system area is blocked, the LFG header pipe valves near Cell 14 and near Cells 1 – 8 can be closed, thereby stopping LFG flow to the flare. 8. Check that the actuator valve on the flare skid is in the “closed” position 9. Verify that the system is properly shutdown (check flow rate, temperature, pressure). Pn-CML SSM Rev 02 - Final.docx 3-2 City of Midland Landfill Landfill Gas System SSM Plan June 2011 4.0 MODIFICATIONS, RECORDKEEPING, AND REPORTING 4.1 Modifications The SSM Plan must be periodically modified to reflect changes in the landfill equipment, operations, or procedures. The Plan should be modified if any of the following are true: SSM Plan does not address an SSM event that has occurred. SSM Plan fails to provide for the operation of the air pollution control and monitoring equipment during an SSM event in a manner consistent with safety and good air pollution control practices to minimize emissions. SSM Plan does not provide adequate procedures for correcting the malfunctioning process and/or monitoring equipment as quickly as practicable. SSM Plan includes an event that does not meet the definition of an SSM event. SSM Plan does not address or adequately address a malfunction event. If this is true, the SSM Plan must be revised within 45 days after the event to include detailed procedures for operating and maintaining the LFGCCS during similar malfunctions. The revised Plan should include a corrective action program for similar malfunctions. Each revision or modification of the SSM Plan must be reported in the semi-annual SSM report (detailed below). Revisions or modifications to the Plan do not constitute Title V air permit revisions. Previous versions of the SSM Plan should be available for inspection by the US EPA or the MDEQ for five (5) years after the revisions are made. In order to track revisions or modifications to the plan, a summary table of revisions is included in Appendix B. 4.2 Recordkeeping The SSM Plan should be kept as a record of all SSM events and made available to the US EPA or MDEQ as requested. An SSM Report Form containing the required recordkeeping information is included in Appendix A. If an SSM event occurs, the form should be filled out completely and placed in Appendix A of this Plan. Pn-CML SSM Rev 02 - Final.docx 4-1 City of Midland Landfill Landfill Gas System SSM Plan June 2011 4.3 Reporting 4.3.1 Immediate SSM Reports If the actions taken during an SSM event were not consistent with this SSM Plan and the CML exceeded the applicable emission limitation in the landfill NESHAP, the CML must report the actions by telephone or fax within two (2) working days after commencing actions inconsistent with the Plan. Also, a letter must be sent within seven (7) working days after the end of the SSM event. The letter should include the following information: Name, title, and certifying signature of the owner or operator or other responsible official. Explanation of the circumstances of the event. The reasons the CML did not follow this SSM Plan. A description of all excess emissions and/or parameter monitoring exceedances believed to have occurred during the SSM event. 4.3.2 Semi-Annual Reports If an SSM event occurs during a semiannual reporting period (January 1 through June 30 and July 1 through December 31), the CML must submit a semi-annual report containing the following information: Name, title, and certifying signature of the owner or operator or other responsible official. Statement that the actions taken during the SSM event were consistent with the SSM Plan (if that is true). Identification of any instance where any action taken during an SSM event (including actions taken to correct a malfunction) is not consistent with the SSM Plan, but the Site did not exceed any applicable emission limitation in the NESHAP. Pn-CML SSM Rev 02 - Final.docx 4-2 City of Midland Landfill Landfill Gas System SSM Plan June 2011 The number, duration, and brief description of each SSM event which caused, or may have caused, an applicable emission limit to be exceeded. If the SSM Plan was revised during the semi-annual reporting period to reflect changes to the MSW landfill operations or procedures, the CML must report each revision to the SSM Plan in the semi-annual report. The semi-annual SSM report may be combined with the NSPS report. The NSPS report was previously required annually. However, the NESHAP now requires the NSPS report to be submitted semi-annually. Pn-CML SSM Rev 02 - Final.docx 4-3 APPENDIX A CITY OF MIDLAND LANDFILL SSM Recordkeeping Forms Pn-CML SSM Rev 02 - Final.docx City of Midland Landfill SSM Recordkeeping Form Name of Person Completing Form: Signature: Type of Event (Check One): Date(s) Form Completed: Startup Shutdown Malfunction Starting Date/Time of Event: Ending Date/Time of Event: Event Duration: Was SSM Plan Followed (Check One)? Yes No If the SSM Plan and SOPs were not followed, initiate reporting procedures listed in SSM Plan. System Affected (Check One): Collection System Open Flare Likely Malfunction (Refer to Section 2.0): Standard Corrective Action Procedures/Information Needed 1. List of new equipment required for repair (i.e. blower belts, bearings, valves, etc): 2. Was the repair completed? 3. Was a third party needed to diagnose the malfunction or to perform the repair? Contact name: 4. Name of person/company that performed repair: 5. If the LFGCCS was shutdown, who completed the startup procedure? Q:\Projects\Municipal\City Of Midland\Midland Landfill\Air Compliance\SSM\SSM Recordkeeping Form Template.doc Date/Time Completed APPENDIX B CITY OF MIDLAND LANDFILL Summary of SSM Plan Revisions Pn-CML SSM Rev 02 - Final.docx APPENDIX B Summary of SSM Plan Revisions Date of Revision Page Number(s) Revised Reason for Revision Alex Bade, EIT 2/28/2011 All Updated to include landfill gas treatment system. Beth Benoit 6/6/2011 2–4 Updated Table Name and Signature of Person Revising Plan Pn-CML SSM Rev 02 - Final.docx LFGTE Facility Malfunction Abatement/Preventative Maintenance Plan CITY OF MIDLAND GAS TO ENERGY GENERATION FACILITY MALFUNCTION ABATEMENT & PREVENTATIVE MAINTENANCE PLAN PERMIT TO INSTALL NUMBER 45-10A Prepared for City of Midland Utilities Department 333 West Ellsworth Street Midland, Michigan 48640 January 1, 2011 (revised February 9, 2011) Prepared by CTI and Associates, Inc. 51331 W. Pontiac Trail Wixom, Michigan 48393 248.486.5100 248.486.5050 FAX CITY OF MIDLAND GAS TO ENERGY GENERATION FACILITY MALFUNCTION ABATEMENT & PREVENTATIVE MAINTENANCE PLAN TABLE OF CONTENT 1. BACKGROUND ............................................................................................................................. 1 2. GENERAL INFORMATION .......................................................................................................... 3 2.1 RELATED DOCUMENTS ............................................................................................................... 3 2.2 EMERGENCY CONTACT – 24 HOURS .......................................................................................... 3 2.3 RESPONSIBLE PERSONNEL ......................................................................................................... 3 3. AFFECTED EQUIPMENT ............................................................................................................. 4 4. MALFUNCTION ABATEMENT AND PREVENTATIVE MAINTENANCE PLAN................. 5 4.1 DESCRIPTION OF EQUIPMENT ..................................................................................................... 5 4.2 EQUIPMENT INSPECTION ............................................................................................................ 5 4.3 REPLACEMENT PARTS ................................................................................................................ 7 4.4 CORRECTIVE PROCEDURES ........................................................................................................ 7 5. IMPLEMENTATION OF AND UPDATE TO PLAN.................................................................... 8 5.1 IMPLEMENTATION OF PLAN ....................................................................................................... 8 5.2 UPDATE TO THE PLAN ................................................................................................................ 8 5.3 REVISION HISTORY .................................................................................................................... 8 i SECTION 1 1. BACKGROUND This Malfunction Abatement and Preventative Maintenance Plan (Plan) was prepared in accordance with Condition III.2 of Permit Number 45-10A for the City of Midland, Waste Water Treatment Plant. The condition reads as follows: At least 60 days prior to start-up of any engine in FGICENGINES, the permittee shall submit to the AQD District Supervisor, for review and approval, a malfunction abatement/preventative maintenance plan for FGICENGINES. After approval of the malfunction abatement/preventative maintenance plan by the AQD District Supervisor, the permittee shall not operate FGICENGINES unless the malfunction abatement/preventative maintenance plan, or an alternate plan approved by the AQD District Supervisor, is implemented and maintained. The plan shall incorporate procedures recommended by the equipment manufacturer as well as incorporating standard industry practices. At a minimum the plan shall include: a. Identification of the equipment and, if applicable, air-cleaning device, and the supervisory personnel responsible for overseeing the inspection, maintenance, and repair. b. Description of the items or conditions to be inspected and frequency of the inspections or repairs. c. Identification of the equipment and, if applicable, air-cleaning device, operating parameters that shall be monitored to detect a malfunction or failure, the normal operating range of these parameters and a description of the method of monitoring or surveillance procedures. d. Identification of the major replacement parts that shall be maintained in inventory for quick replacement. e. A description of the corrective procedures or operational changes that shall be taken in the event of a malfunction or failure to achieve compliance with the applicable emission limits. If the plan fails to address or inadequately addresses an event that meets the characteristics of a malfunction at the time the plan is initially developed, the owner or operator shall revise the plan within 45 days after such an event occurs and submit the revised plan for approval to the AQD District Supervisor. Should the AQD determine the malfunction abatement/preventative maintenance plan to be inadequate, the AQD District Supervisor may request modification of the plan to address those inadequacies. (R 336.1702(a), R 336.1910, R 336.1911, R 336.1912, R 336.2803, R 336.2804, 40 CFR 52.21(c) and (d)) Rev.01, February 9, 2011 Page 1 SECTION 1 This Plan has been developed to satisfy the above requirements. As such, it provides procedures and elements of inspection, inspection frequencies, back up equipment inventories and general information used to prevent, detect, and correct malfunctions. It is important to note that the regulations anticipated that periodic shutdown of the each individual control equipment at a landfill is anticipated. Since periodic malfunctions, unforeseen circumstances or short duration maintenance activities are anticipated by the regulations, City of Midland believes they have implemented a program consistent with these requirements. City of Midland understands that AQD expects the City of Midland to address any temporary break down of a control device or devices. While a plan has been written suggesting parts lists, inspections, inspection frequencies, etc. to comply with the above paragraph it is anticipated the short duration shutdown events will continue to occur which are beyond City of Midland’s control. Rev.01, February 9, 2011 Page 2 SECTION 3 2. GENERAL INFORMATION 2.1 RELATED DOCUMENTS The following documents will be available for reference at the City of Midland Gas to Energy Generating Facility: • Start-up, Commissioning, and Training Plan for the City of Midland Integrated Utility Improvement Project – Landfill Gas to Energy Project, prepared by Green Companies, Inc., dated November 19, 2010. • Control Strategy for the City of Midland Integrated Utility Improvement Project – Landfill Gas to Energy Project, prepared by Green Companies, Inc., dated December 10, 2010. • Preventative Maintenance Plan for the City of Midland Integrated Utility Improvement Project – Landfill Gas to Energy Project, prepared by Green Companies, Inc., dated December 30, 2010. • Startup, Shutdown, and Malfunction Plan for the Landfill Gas Collection and Control System at the City of Midland Landfill, prepared by CTI and Associates, Inc., dated July 2010. 2.2 EMERGENCY CONTACT – 24 HOURS The Waste Water Treatment Plant (WWTP) is operated 24 hours a day. The Gas to Energy Generating Facility is monitored continuously through the WWTP SCADA system and alarms are communicated through the existing Wonderware software. When an alarm is activated or attention is required the WWTP Operator will follow a protocol to notify the appropriate on-call individual. 2.3 RESPONSIBLE PERSONNEL All supervisory personnel responsible for overseeing the inspection, maintenance, and repair of the engine plant are listed below: Name Title Phone Number Kevin Babinski Wastewater/GTE Superintendent 989-837-3502 Scott O’Laughlin Landfill Superintendent (GCCS) 989-839-6535 Steve Smith Wastewater/GTE Operations Supervisor 989-615-8304 Jim Ives Elec/Mech 2 (GTE/GCCS Operations) 989-839-9577 Rev.01, February 9, 2011 Page 3 SECTION 3 3. AFFECTED EQUIPMENT The City of Midland plans to operate two internal combustion engines that are covered by this Plan. The engines are used for combusting treated landfill gas and wastewater treatment plant (WWTP) digester gas to produce electricity. These engines are identified as Emission Units EUICEENGINE 1 and EUICEENGINE2 in Permit No. 45-10A issued by the Michigan Department of Natural Resources and Environment Air Quality Division. Rev.01, February 9, 2011 Page 4 SECTION 4 4. MALFUNCTION ABATEMENT AND PREVENTATIVE MAINTENANCE PLAN The following section of this Plan contains prevention of malfunctions, detection of malfunctions, and correction of malfunctions for each of the engines. 4.1 DESCRIPTION OF EQUIPMENT The City of Midland has plans to operate two internal combustion engines (both Caterpillar G3520C) for combusting treated landfill gas and WWTP digester gas to produce electricity. These engines are identified as Emission Units EUICEENGINE1 and EUICEENGINE2 in Permit No. 45-10A. In addition to these engines, the facility includes an engine heat recovery system, engine cooling system, and electrical generation equipment. 4.2 EQUIPMENT INSPECTION Table 1 shows the Engine Plant items or conditions that are inspected, the frequency of the inspections, the procedures followed to aid in the prevention of a malfunctions, monitoring parameters that are used to detect and aid in the prevention of a malfunction or equipment failure, the normal range of these parameters, and recording/ retaining of the monitoring records. Table 1 List of Engine Plant Prevention/Detection Items Item or Conditions to Be Inspected Frequency of Inspection /Monitoring Engine Air Cleaner Element Engine Oil *Performance based Assessment *Performance based Assessment Engine Oil Sample Establish Baseline for each Engine (Performance/Oil sample) Weekly Weekly Engine Oil Level Engine Oil Temperature Oil Filter Differential Pressure Engine Oil Filter Fuel Metering Valve Rev.01, February 9, 2011 Weekly Procedures to be Followed to Aid in the Prevention of Malfunctions Check Sensor (difference in pressure) Replace when necessary Establish baseline, use oil chemistry and performance as a guide (Change when necessary) Once baseline is established verify frequency with oil chemistry sampling results Check float & Secondary auto-fill Check Temperature gauge Establish Baseline for Check Electronic Technician (ET) Software Check pressure differential change Each engine (Performance Engine oil filter as needed Performance based assessment Check Codes, Clean Sensor Page 5 SECTION 4 Item or Conditions to Be Inspected Frequency of Inspection /Monitoring Throttle Control Valve (Check Elec. Valves) Cooling System Coolant Level Cooling System Coolant Temperature Cooling System Coolant Pressure Differential Pressure Crankcase Vent Generator Load Walk-Around Inspection Performance based Assessment Battery Electrolyte Level Belts (Radiator) Engine Valve Radiator *Every 6 months of service Water Pump Performance based assessment Generator *Performance based Assessment (assess at Approximately 8,000 hours Of use) Performance based assessment Ignition System Spark Plugs Turbocharger Overhaul – Top End Overhaul – In-Frame Overhaul - Major Procedures to be Followed to Aid in the Prevention of Malfunctions Check ET Software Weekly Check Sight glass for level and Color Weekly Check ET Software Weekly Check ET Software Weekly Check Pressure, Control vacuum (walk around) Check load conditions (Kilowatts) Check for any unusual conditions, Leaks, broken gauges, pinched Wire/Tubing etc. Check battery electrolyte level Weekly Weekly *Every 12 months Performance based assessment Performance based assessment *Performance based Assessment (assess at Approximately 8,000 hours Of use) *Performance based Assessment (assess at Approximately 50,000 hours Of use) Performance based assessment *Performance based Assessment (assess at Approximately 100,000 hours of use) Inspect/Adjust/Replace Adjust as needed Check inlet & outlet temps, clean/ Wash exterior surfaces as needed Inspect for leaks during walkAround inspection Visually inspect system for lose wires/fittings, vibration damage etc. Inspect/Replace Establish baseline to use as a guide (change when necessary) Overhaul Overhaul Overhaul *Engine performance supersedes frequency of maintenance activities. Approximately values used in this table should only be used as a guideline in evaluation of each parameter to be inspected, maintained and replaced. Rev.01, February 9, 2011 Page 6 SECTION 4 4.3 REPLACEMENT PARTS To facilitate quick replacement, the spare or replacement parts necessary for proper engine operation and routine maintenance will be located on site at the generation facility, the compressor facility, or at WWTP central maintenance area (major components or specialty parts will be ordered as needed). Inventory may vary from time to time. 4.4 CORRECTIVE PROCEDURES The corrective procedures or operational changes shall be undertaken in the event of a malfunction or failure of the generation facility. City of Midland will expeditiously implement the appropriate procedures to correct the event. Repair records will be maintained in an operations log. Rev.01, February 9, 2011 Page 7 SECTION 5 5. IMPLEMENTATION OF AND UPDATE TO PLAN 5.1 IMPLEMENTATION OF PLAN If the plan fails to address or inadequately addresses an event that meets the characteristics of a malfunction at the time the plan is initially developed, the owner or operator shall revised the plan within 45 days after such an event occurs and submit the revised plan for approval to the AQD District Supervisor. Should the AQD determine the malfunction abatement/preventative maintenance plan to be inadequate, the AQD District Supervisor may request modification of the plan to address those inadequacies. 5.2 UPDATE TO THE PLAN This plan will be updated within 60 days of replacing or expanding the components of the Engine Plant with components not described herein. If no components of the Engine Plant are replaced or expanded with components described herein, the Plan will be updated at least once every 5 years or as needed. 5.3 REVISION HISTORY Date Rev Description 01/01/11 00 Issue Document 02/09/11 01 Revise Section 2 to clarify the 24 Hour Emergency Notification Process. Rev.01, February 9, 2011 Page 8 " Il. PM2.5,PRIMRY LB Generic 1.7 ,o 502 LB Generic it.1l II' vae 1..6 Gooeric 5.6 i'l 11) 1I'" ~ o z "- 1'1 III r1/1 "-(I) C'I o <'I !II N o IU D "j r lv ~ II. o o IIVASTEGAS MMCF lANDFILL GAS MMCF WASTE GAS MMCF