Item No. 19 S/I/C Period: 4 months Technical Specifications for Supply, Installation, Commissioning & Testing of 1000 KVA Transformer and allied accessories at Ajmer Dairy Plant. Supply, Installation, Commissioning & Testing of 1000 KVA Transformer and its allied accessories i.e. RMU, ACB, HT Cable, LT Cable etc. same are to be placed in existing electrical circuit of Ajmer dairy. The existing system consist of 2 Nos. of transformers of 500 KVA each and having OCB of Jyoti make at incoming of each transformer. Both the transformers are capable of working independently and in parallel whenever required to cater the existing plant load. Now the new system i.e. 1000 KVA transformer is to be placed in existing HT circuit by placement of RMU (Ring Main Unit) at extension of existing system & out put of 1000 KVA transformer shall be connected to 1600 Amp. ACB placed at LT panel.. The 1000 KVA transformer will work independently & 500 KVA transformers can be loaded individually or in parallel. The system should ensure perfect safety inter looking between OCBs of 500 KVA transformers and RMU (Ring Main Unit) of 1000 KVA transformer. The detail specifications of items required for successful placement of 1000 KVA transformer in existing circuit are detail below :Part A S. Description No. 1 Supply, Installation, Testing & Commisioning of 11 KV Ring Main Unit as per following Specifications : 11 KV, 630 A, indoor type , floor mounted with copper Bus bar s, RMU should consist of 1 No. 630 A On-load isolator module as incoming & 1 No. 400 A manually operated T-off Vacuum Circuit Breaker modules as outgoings. All live parts, bus bars, isolators & VCBs of RMU should be enclosed in sealed for life welded single stainless steel tank having IP67 degree of protection filled with SF6 gas as insulation. RMU should be having following accessories such as ring core CTs, self powered microprocessor based numerical protection relays for O/C, S/C and E/F protections. Cable supports, front cable terminations, mechanical indications for breaker On/Off/trip/Spring charges, air insulated Bus PT panel, Manometer for SF6 gas Pressure indications inside the enclosure Qty. Unit Rate (Rs.) Supply Installation One set H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 1 Total (Rs.) with preassure healthy marking as per IEC: 265, 129, 694, 529, 801,56, consisting of following items: Incoming: On-Load Isolator (Incomer) should consist of following accessories. 11 KV, 630 A On-Load isolator module for isolating the incoming supply along with series integral earth switch. 3 Nos. Ring core CTs designed for 11 KV 80/1 A, 2.5 VA, Accuracy class 1.0 Metering purpose. 1 No. Digital Multifunction Energy Analyser with all the power and Load parameters as standard functions. Suitable Cable bushings for front cable terminations. Arc Proof cable covers with self interlocking mechanism between doors, earth switch isolator. Mechnical Indication for isolator ON, OFF, Earth. Outgoing: 1 Nos. T-off VCB should consist of following : 400 A manually operated T-off Vaccum Cicuit Breaker modulesfor making and breaking of fault current alog with off- load isolator in series for isolation purpose & integral earth switch. 3 Nos. Ring core Cts designed for 11 KV 80/1 A, 2.5 VA, Accuracy class 5P10 for protection. Self powered microprocessor based protection relays for 2 O/C, and E/F. Suitable Cable bushings for front cable terminations. Arc Proof cable covers with self interlocking mechanism between doors, earth switch isolator. Mechnical Indication for isolator ON, OFF, Earth. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 2 2 3 Nos.Potential Transformer of the ration 11KV 3/ 110 V 3 , 50 VA, Class 1.0 with HT fuses on primary side and MCB on secondary side. CFL for illumination. Space Haeter with Thermostat. Supply, Installation, testing & commissioning of available 1000 KVA copper-wound, 3 – phase, 50 Hz oil immersed, naturally cooled, out door type Power Transformer having a vector configuration DY11 with plus/minus 5% tapping taken out in tap changing switch, HT winding connection in Delta and LT winding connection in Star and neutral brought out and connected to a separate terminal with outdoor open porcelain bushing and complete with first charge of requisite transformer oil, with following being available :- Fitting and Accessories - Oil conservator tank with drain plug and filling cap. - silicla gel dehydration breather charged with silica gel - oil level gauge - oil drain valve - thermometer pocket with thermometer - earthing terminal - lifting lugs - four bidirectional roller wheels - air release valve - explosion vent Parallel operation of transformers:- - - - Transformers offered for the same vector group DY 11, rating and voltage ratio should be capable of operating in parallel satisfactorily. It shall be installed and commissioned as per IS 10028-1981 or latest. Other item- Fire bucket 3 nos capacity 20 ltrs, Fire extinguishers CCL type 5 Kg-2 no, Shock treatment chart 5 n0, Danger plate-5 Nos. The detail specification of 1000 H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 3 KVA transformer are detailed at Annexure – F. - Further the tenderer is advised to submit the foundation drawings of transformer and get it approved. 3. 4. 5. Providing and laying underground cable IS:1554 and approved make suitable for working voltage upto and including 11 KV in aluminium conductor XLPE armoured including excavation of 30cm x 75cm size trench as per IS:1225, 25cm thick under the layer of sand, IInd class brick covering refill earth in the removing portion making necessary connection including testing etc. as required. The size of the cable should be 3 x 95 sq.mm make ICL/ Gloster/ CCI/ Torrent. Supplying and making of Indoor / outdoor cable jointing for 11 KV XLPE cable of heat shrinkable type termination kit including preparation of cable ends. Make M Seal/Denson. (This item will include all requisite hardwares lugs etc.) a) Indoor type .. .. .. .. .. b) Outdoor type .. .. .. .. .. Supply, Installation and Commissioning of advance maintenance free chemical gel earth single pole earthing system of 2 mtrs. Length and 80mm dia 2mm thick electrolytic grade copper tube duly filled with conducting natural mineral with permanent sealing at both ends with lead terminals at the top along 1 set of Part – I 5Kg. mixture of calcium carbonate, tetra sodium Hexcyno Ferrate, Sdium sulphate. Part – II 5Kg. Copper sulphate. 30 Mtr. 3 Nos. 2 Nos. Earthing for Transformer 4 HT Panel 2 LT Panel 1 Total 7 Nos. 7 Nos. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 4 6. Supply and erection of cubical panel fabricated from CRCA sheet 14/16 SWG dust and vermin proof together with degreasing and applying two coats of red oxide and two coats of stove enameled light grey paint. The panel includes all required hardwares moulded insulators and proper rating of copper busbars having provision as follows:INCOMING : MAIN LT PANEL - ACB 1600 A Micro Processor Controls L&T / Siemens / MG make. 1 No. - voltmeter 0-500 V 96 x 96mm. - ammeter 0-500/5 A 96 x 96mm. 1 No. - LT crnt transf. 500/5 A. - Voltage selector switch. 1 No. - Ammeter selector switch. 3 Nos. - LED base indicating lamps 1 No. RYB with holders. 1 No. - Control fuses and fuse bases with tops. 3 Nos. 7. Supply, Installation & Commissioning of 1600 Amp. TPN 415 Volts, Aluminum Bus Duct, Air insulated housed in enclosures fabricated with 14 / 16 SWG GI sheet and duly powder coated. The housing shall be designed for complete dust and vermin proof with IP - 54 level protections. Busbar 3 run for phase bus one run for neutral and one run for earth bus. Note : Tenderer should quote unit rate for supply & laying of bus duct between transformer and LT Panel. System should be CPRI approved. 30 Mtr. * Please refer Part – D also. Total of Part ‘A’ The tenderer is required to take necessary approvals from the concerned Inspectorate of Electrical, Ajmer. The supplier or erector should submit ‘A’ Class contractor Certificate. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 5 Part - B TECHNICAL SPECIFICATIONS OF MOTOR CONTROL CENTRES (SHEET STEEL) 1.0 Motor Control Centre (sheet steel) 1.1 Functional requirement : To receive, control and distribute electrical power at 440V 50Hz. AC on a sheet steel housing. 1.2 Design requirement and scope of supply : 1.2.1 Statutory requirement : Motor Control Centre is to be manufactured / assembled as per the latest ISI specifications, Indian Electricity rules, including special requirements of Rajasthan State Electrical Inspectorates. 1.3 Housing details : 1.3.1 The switchboard shall be fabricated out of 16SWG sheet steel and shall consist of free standing front openable panels arranged to from a continuous line up of uniform height. Cold rolled sheets shall be used for doors and front covers. Front doors shall be hinged type and bus bars, bars and cables alloys covers shall be bolted type. Suitable M.S. channel base frame should be provided. Switch Board shall be extensible at both the ends by addition of vertical sections. Ends of the bus bars shall be suitably drilled for this purpose. The Switch board shall be totally enclosed, dust, weather and vermin proof. Gaskets of durable material shall be provided for doors and other openings. Suitable hooks shall be provided for lifting the boards. These hooks when removed, shall not leave any opening in the board. All hardware shall be corrosion resistant. All joints and connections shall be made by galvanized zinc passivated or cadmium plated high tensile strength steel bolts, units and washers secured against loosening. The switch board shall be in cubical design (each feeder components are housed in individual cubical). Suitable cable and bus bar alleys shall be provided. All components of the switch board should be approachable from front. The maximum and minimum operating handle / push button height of any feeder shall not be more than 1800 mm or less than 400 mm with reference to panel bottom. Supporting arrangement for dressing of power and control cables in cable alleys shall also be provided. 1.3.2 1.3.3 1.3.4 1.3.5 H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 6 1.3.6 Painting : All metal surfaces shall be thoroughly cleaned and degreased to remove all scales, rust, grease and dirt. Fabricated structures shall be pickled and treated to remove any trace of acid. The under surface shall be prepared by applying a coat of phosphate paint and a coat of yellow zinc chromate primer. The under surface shall be made free from all imperfections before undertaking the final coat. After preparation of the under surface, the panel shall be spray painted with final two coats of approved paint. Supplier shall obtain details of approved paint from the purchaser before final painting. The finished panels shall be dried in stoving ovens in dust free atmosphere. Panel finish shall be free from imperfections like pin holes, orange peals, fun-off paint etc. All unpainted steel parts shall be cadmium plated or suitably treated to prevent rust, corrosion etc. 1.3.7 Name Plates : Name plates for all incoming and out coming feeders shall be provided on doors of each compartment. Name plates shall be fixed by counter sunk screws only and not by adhesives. Special danger plates shall be provided as per requirement. 1.4 Busbar sizing, connecting and supports : 1.4.1 The busbar shall be made from high conductivity electrolytic aluminium. The busbars and supports shall be capable of withstanding the rated and short circuit current, stated in the feeder details. Minimum size of main power busbars shall be 200 Amps. rating. Maximum current density permissible for aluminium busbars shall be 8.2 Amps/mm². An earthing busbar of minimum 150 mm² section aluminium shall be provided outside panel at bottom throughout the length of the panel. The busbars shall be provided with PVC/heat shrinkable insulating sleeve. Supports for busbars shall be made of suitable size hyleum sheets/epoxy compound blocks and these should be adequate in number so as to avoid any sag in the busbars. Minimum clearance between phase to phase shall be 32 mm and between phase to neutral / earth shall be 26 mm. 1.4.2 1.4.3 1.5 Power Connections : 1.5.1 For power inter-connections within the panel board : Copper conductor PVC insulated cables of adequate cross section shall be used. For current rating above 63 Amps. aluminium busbar strips of adequate rating shall be used. Minimum size of copper conductor to be used shall be 2.5 mm². Cables lugs/sockets of suitable size and type shall be used for all interconnections. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 7 1.5.2 1.5.3 1.5.4 1.5.5 1.5.6 For all aluminium to copper connections, suitable bimetallic material (“CUP-al” washers) shall be used. For each outgoing motor (upto 60 HP) feeder, suitable size terminal blocks (min. 3 ways) shall be provided in its cubical and wiring upto these from contactors shall be done by panel supplier. All the terminal blocks shall be suitable for aluminium conductor cable. For incoming and outgoing feeders of the MCC aluminium conductor cable will be used and hence the panel is to be designed for receiving these and wherever required cable boxes shall be provided in panel by supplier. Removable gland plates shall be provided on top/bottom of panel for cable entries. To prevent accidental contacts, all interconnecting cables/busbars and all terminals also shall be shrouded. Standard colour code of red, yellow and blue for phases and black for Neutral to be followed for all busbars / conductors. 1.6 Auxiliary wiring and Terminals : 1.6.1 Wiring for all controls, protection, metering, signaling etc. inside the switch board shall be done with 650 volts PVC insulated copper conductors. Minimum size of those conductors shall be 1.5 mm². Control wiring to component fixed on doors shall be flexible type. The complete panel would be sub-divided into different sections by purchaser and each section shall have its own control circuit with fuse and indication. Terminal block (Minimum 3 – ways) for control wiring shall be provided for each outgoing Motor feeder in its cubical. 10% spare terminals shall always be available in each terminal block. Control wiring upto these terminal blocks shall be done by supplier. All control wiring should be provided with necessary cable / sockets / lugs at both ends. Conductor shall be terminated using compress on type lugs. Each termination shall be identified at both the ends by PVC ferrules. The identification termination numbers should match with those on drawings. Control wiring for motor feeders should be such that the “green” light of motor feeder is “NO” only when control as well as power circuit of feeder is “NO”. 1.6.2 1.6.3 1.6.4 1.6.5 1.7 Switchgears : 1.7.1 Air Circuit Breaker : The technical specifications given subsequently. 1.7.2 Moulded case circuit breakers (MCCBs) : MCCBs shall be provided with interlocking system suitably. 1.7.3 MCB: 4 poles MCB of suitable rating for all electrical loads shall be provided. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 8 1.7.4 The rating of the power contractors shall be as required depending upon the feeder rating indicated in the specifications and as per the table given below. Contractor coils shall be suitable for 230 / 440 Volts, 50Hz. Unless otherwise specified. All contractors shall be supplied with minimum 2 NO + 2 NC auxiliary contacts. Additional contacts if required for inter-licking etc. shall also provide. 1.7.5 Protective devices : Electronic relays shall be provided for all motor feeders. The relays shall be adjustable and self reset type. There should be SPP (single phase prevention) built up in the relay. Any other relays, if required for motor feeders shall be specified in the feeder details. 1.7.6 Timers : The timers shall be electronic type, suitable for 240V 50Hz. supply. 1.7.7 Push Buttons (PBs) : push buttons shall be luminous type with 22mm hole size. Push buttons shall be with contact elements, shall be generally mounted on openable covers. Colours shall be as follows : Stop / open / emergency Start / close - Red Green It should have minimum 1 NO + 1 NC contacts. Push buttons with built-in indication lamps shall also be accepted in with case separate indication lamps are not required. 1.7.8 Indication Lamps : Indication lamps shall be LED type with 22 mm hole size. Colours shall be as under:Phase : Red, yellow and blue Open/Stop/Emergency : Red Close/Start : Green/Black Bulbs shall be suitable for 250 volts AC supply. 1.7.9 Current Transformers (CTs) : CTs shall be cast resin insulated type. Primary and secondary terminals shall be marked individually. CTs shall preferably be mounted on stationary parts. CT rating and rations shall be as per feeder ratings. These shall be capable of withstanding momentary short circuit and symmetrical short circuit current for 1 H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 9 second. Neutral side of CTs shall be earthed. Protection on CTs shall be low reactance, accuracy should be class I VA burden. The CTs shall be of ALPHA make. 1.7.10 Measuring Instruments : These shall be of square pattern having approximate dimensions 96mm x 96mm, flush mounting type. Necessary auxiliary instruments like CTs PTs etc. are also included in the scope of supply. The voltmeter shall be of 0-500 V range with VSS. The ampere meter shall be 800/5 A range with ASS. The voltmeter and Ampere meter shall be of AEI / IMP make and the voltage selector switches shall be of Sulzer / Kaycee make All AC meters shall be moving iron type having class 1.0 accuracy. Ammeters for motor feeders shall have a non liner compressed scale at the end to indicate starting current. Voltmeter shall be suitable for direct line connection. Voltmeter shall be connected through fuses only Energy meters shall be suitable to measure unbalanced loads of 3 phases, 4 wire systems. 2.0 3.0 Special requirements : D.G. set change over switch : There is a requirement of 1 No. change over switch. There will be change over switch so that operation of DG set 250 KVA is possible when there is no power & also to isolate State Electricity Board power supply when there is necessity to operate the DG set. 4.0 Incomer : a) b) 4.1 For incoming feeders upto and 800 A rating provide MCCBs with 40 KA breaking capacity with overload / short circuit and earth fault protection. For all incoming feeders provide CT operated ammeter with rotary selector switch; voltmeter with selector switch and 3 Nos. indicating lamps with red lines. Outgoing feeders : a) Motor feeders of rating of 10 HP or above shall be provided with suitable automatic star-delta starters along with electronic protected relay, timer, triple pole switch fuse unit/MCCB and ammeter. All motor feeders upto 60 HP shall be provided with MCB and above 60 HP MCCBs with a minimum breaking capacity of 40 KA shall be provided. For feeders below 15 HP rating provide direct reading ammeter and for feeders of 15 HP and above H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 10 b) c) d) e) f) g) rating provide CT operated ammeters. All the power contractors of star-delta starters shall have same current rating. Feeders for star-delta starters will be provided with specified current rating in the distribution boards. Motor feeders of rating less than 10 HP will be provided with suitable direct on line starters along with thermal overload relays with single phase preventing and MCBs as per requirement. The motor feeders wired for remote control will be provided with only an OFF push buttons the distribution board whereas for the feeders wired for local control from the board, both ON and OFF push buttons along-with green indicating lamp for ON will be provided on the distribution board. Suitable cable glands provision will be provided for each of the incoming and outgoing feeders. The components to be used will be of either L&T/ Siemens / Bhartiya Cutler Hammer / C&S / GE make. Tenderer should specify the make offered. The following selection table shall be followed for starters of motor feeders unless otherwise specified: S. No. 415 V Motor H.P. Contractor Rating Amps. 16 MCB / MCCB Rating / Amps. 1 0 to 10.0 HP 2 15 HP 32 63 -do- 3 20 to 25 HP 63 63 -do- 4 30 HP 63 100 -do- 5 40 to 50 HP 100 100 -do- 6 60 HP 100 100 -do- 7 75 HP 150 150 / 175MCCB 8 100 HP to 150 HP 150 25 Switch 225 MCCB Starters / S.F. units of higher ratings should be preferably located at the bottom portion of MCC. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 11 Part – C Technical specifications of Air Circuit Breaker 4 pole 1600 Amp. Quantity Required : - 1 No. The air circuit breaker shall be 4 pole manually operated draw out type with microprocessor based protection release for overload, short circuit. & earth fault protection. The design shall be quick make and quick break type with slow closing facility for ease in maintenance. The total break time should be less than 30m sec including arcing time of 10m sec. The release shall be R.M.S. sensing type requiring no external supply for its basic function of tripping against fault. The release should diagnose the different fault i.e. there shall be inbuilt LED’s in protection release for over current, short circuit & earth fault. The release shall have provision for function blocking. The ACB shall be provided with under voltage protection. The setting of over load in release shall be 40% to 100%. The setting of short circuit shall be minimum 2 to 10 times. The ACB shall have Ics = Icw for 1 Sec. for short circuit breaking capacity of not less than 50 KA rms at 415 Volts 50HzAC. The overload current setting may be 40% to 100% of maximum rated value. The ACB neutral pole shall make earlier & break later than main pole. • Overload (phase) current setting 0.4 to 1.0. • Neutral fault current setting 0.5 to 1.0. • Earth fault current setting 0.1 to 0.6. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 12 Part – D Necessary Cables, Cable Trays etc. All necessary cables for connecting HT side to the primary of the transformer and LT side of the transformer to the main panel on LT side, main panel to distribution panels, from various panel boards to various equipments falls in the scope of the work. The quantities mentioned for cables & cable trays in this tender document are indicative only and may vary as per site conditions. The tenderers are required to quote for the quantities mentioned for various items in this section based on which the financial comparative statement shall be drawn but they should also quote the unit rate price (F.O.R. site) for each item separately also in order to make Ajmer Milk Union release payment for bills of the firm for the actual quantities of items supplied, installed, tested and commissioned as per site conditions. For connecting various equipments following cables and related shall be required :1100 KV GRADE, 3.5 C ARMOURED ALUMINUM CONDUCTOR, PVC INSULATED LT CABLE / BUSDUCT SELECTION CHART AS PER THE FEEDER DETAILS AT 8 VOLTS DROP. S. NO. FEEDER TYPE FEEDER RATING 1. 1000 KVA 1600 A TRANSFORM ER TO MAIN ACB 1600 Amp. Total CABLE SIZE Aluminum Bus Duct,1600 Amp. TPN 415 Volts, LENGTH OF CABLE (in Mtrs.) 30 Unit Rate TOTAL AMT. (in Rs.) The cables of Gloster / Hawell or equivalent make (equivalent make subjected to approval of purchaser) need be supplied. All necessary lugs of Dowell make for the various cables with due crimping shall have to be supplied and installed. Necessary loops for cables shall have to be provided wherever necessary. The unit rates for the cables of all sizes mentioned in the tender document also need be quoted. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 13 Part – E Technical Specifications for Busbar Duct System for connecting 1000 KVA transformer with LT panel ACB of 1600 Amp. at Ajmer Dairy Plant. Supply, Installation & Commissioning of 1600 Amp. TPN 415 Volts, Aluminum Bus Duct, Air insulated housed in enclosures fabricated with 14 / 16 SWG GI sheet and duly powder coated. The housing shall be designed for complete dust and vermin proof with IP - 54 level protection. Busbar 3 run for phase bus one run for neutral and one run for earth bus. ¾ Current Rating : 1600 Amp. ¾ System Voltage : Upto 600 to 1000 Volt. ¾ Conductor material : High conductivity Aluminum. ¾ Ingress Protection of IP54. ¾ Halogen free, fire retardant Class – H – Epoxy insulation. ¾ High temperature with stand capability of 55 degree over 50 degree Celsius as normal operating temperature, single Bolt bridge joint system incorporates 5mm thermal expansion provision. ¾ Design and construction for lower mV drops, higher efficiency distribution system. ¾ Short circuit ratings (up to 100 kA). System should consist of component such as straight length / End flange, End Feed Unit Tap of units, Bends, Fixing clips etc. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 14 Part - F TECHNICAL SPECIFICATIONS FOR 1000 KVA TRANSFORMER Supply period – 3 months. Supply of 1000 KVA Cooper wound 3 Phase 50 Cycles, oil immersed, naturally cooled, Core type, outdoor type with HV outdoor & cable box on LV side power transformer with stepping down provision from 11 KV to 440 V, having a vector configuration DY 11 with plus/minus 5% tapping taken out in tap changing switch (with provision of 5 steps), HT winding connection in Delta and LT winding connection in Star and neutral brought out and connected to a separate terminal with outdoor open porcelain bushing and complete - With first charge of requisite transformer oil. - - Fitting and accessories (as detailed on next page) - Oil conservator tank with drain plug and filling cap. - Silica gel dehydrating breather charged with silica gel. - Oil level gauge. - Oil drain valve. - Thermometer pocket with thermometer. - Earthing terminal. - Lifting lugs. - Four bidirectional roller wheels. - Air release valve. 1 Set Explosion vent. The transformer should conform to the IS specifications. The winding temperature rise – 55 deg C above ambient, oil temp. rise – 50 deg. C above ambient, impedance – 5.5% or above, permissible no load losses - 1.35 KW (max.), permissible on load losses – 9.75 KW (max.). The quality of oil should be good conforming to IS : 335 and the oil should be of SAVITA/APAR make or equivalent make (equivalent make subjected to purchaser approval). Reference standard IS:2026-1977 Compliance & above mentioned specifications. The winding temperature indicator with alarm & tip contacts should be of Thermal make (mercury type). The number of earthings (independent) should be four. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 15 Standard Fittings & Accessories S. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. Particulars Rating & Diagrams Plate Earthing Terminals Lifting Lugs of Transformer Lifting Lugs of Top Cover Drain Valve with Plug Filter Valve with Plug Conservator Tank Oil level gauge Oil Filling hole with Plug Air Release Plug Thermometer pocket Silica gel breather with oil seal Explosion Vent Off. Ckt. Tap Changer Switch Handle & Position indicator L.V. Terminal Box with Extended Copper Flats/suitable Bus palm Neutral brought out terminal for earthing externally Bi-Directional rollers Oil temp indicator 6” with alarm & trip contacts Double Float Buckholz relay with alarm and trip contacts Inspection cover Marshalling Box with complete wiring Magnetic oil level gauge with low 1 No. Jacking Pads Winding temp. indicator with alarm trip contacts Prismatic oil level gauge. HV Cable Box, Long pin bushings, suitable for connecting on primary side 11 KV grade XLPE Cable entry. Quantity 1 No. 5 Nos. 2 Nos. 2 Nos. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 1 No. 4 Nos. 1 No. 1 No. 1 No. 1 No. 1 No. 4 Nos. 1 No. 1 No. 1 Set Note : Further the tenderer is advised to submit 3 sets of the foundation drawings of transformer and get it approved. The supplier will also have to submit test certificates of transformer and oil. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 16 Important Note : The tenderer is advised to visit to site so as to apprise himself of actual site condition and quantum of work involved. Special notes : This is a turn key project. The quantities of various items listed are tentative only and may vary on either side during execution. The final quantities of these would be as per site conditions. Cost of installation for any addition or deletion in quantities will be calculated based on the unit prices indicated. All necessary material which may be required for the successful completion of the project falls in the scope of the work. If any extra quantities of quoted items are needed then the tenderer shall supply those at the quoted unit price. If any extra item(s), not included in the tender but required for successful completion of the work, the same will be either supplied by the RCDF / Ajmer Milk Union and erected by the tenderer or supplied and erected both by the tenderer at mutually agreed rates considering purchase price, taxes and handling charges etc. Necessary ESI / PF deductions, wherever applicable shall be borne by the tenderer. The requisite approval form Chief Electrical Inspectorate, Government of Rajasthan must be obtained by the tenderer and the actual payment shall be reimbursed by RCDF / Ajmer Milk Union against production of original documents. The tenderers are required to give the price bid for all items section-wise in the same faction as of Part – A showing the F.O.R. unit rate for supply as well F.O.R. unit rate installation, testing & commissioning as well the total cost. In addition to the standards mentioned, all works shall also conform to the requirements of the following for which necessary certifications of the concerned departments are to be obtained and submitted to the concerned Milk Union / RCDF :a) Indian Electricity Act and rules framed thereunder. b) Fire insurance regulations. c) Regulations laid down by the Chief Electrical Inspector of the State / State Electricity Board. d) Regulations laid down by the Pollution Control Board. e) Regulations laid down by the Factory Inspector of the State. f) Any other regulations laid down by the local authorities. g) Installation operating manuals of original manufacturers of equipment. H:\SARAS\Tender Form\NIT XXXI Tech. specifications\Transfomer 1000 KVA Ajmer (Item No.19).doc 17