Tempory power supplies

advertisement
WiringFeature #46
Temporary
electrical systems
DAVE ROBERTS, PIC LIBRARY
A forthcoming IET guidebook addresses
the challenges of providing temporary
power systems for live events.
By James Eade
Temporary electrical systems are
more common than you might think.
Over Christmas you probably admired
a lighting display in your local town,
visited an outdoor Christmas market
or perhaps even had a go on one of the
many temporary ice rinks that appeared
in shopping malls around the country.
As we head into the summer, the
annual round of agricultural shows,
festivals and village fêtes will soon
be upon us. Less seasonal examples
of temporary power usage include
theatre shows, corporate sales or
marketing events, film, television,
broadcasts and exhibitions.
18 | SPRING 2013 | IET wiring matters | www.theiet.org/wm
The scale of temporary systems varies
considerably. Many are small, running
from generators under 10kVA; larger
events may have multiple synchronised
generators delivering capacities
measured in MVA. The London
Olympics saw the deployment of around
220MVA of temporary generation
– equivalent to over 20 per cent of the
UK’s oil-fired generating capacity. Sky,
one of the UK’s largest broadcasters,
deploys around 100 live outside
broadcasts (OBs) for sporting events
each month, along with around 50 news
OBs every day. Not every OB needs a
temporary supply, but the majority do.
This is a very sizeable business. The
entertainment industry is worth
approximately £15bn to the UK
economy per annum, of which £1bn
comes directly from staging live music
events. When you add in all the other
agencies with a need for temporary
supplies, including the armed services,
construction, rail and power industries it
will be clear just how big the temporary
power business really is.
Hardware
The entertainment side of the industry
has changed considerably since
the 1960s and 1970s, when it was a
Fig 1: Example of electrical environments
Zone 1
fledgling business. But, although the
industry is now a much larger and more
mature, the basic objectives remain
the same: the rapid deployment of
sufficient power to where it’s needed.
In response to this goal, the industry
has developed customised, ruggedised
distribution units that can be quickly
plugged together using cable and
connector assemblies. However, while
this ‘plug ‘n’ play’ approach using
stock equipment offers real gains
from a logistical perspective, and also
has some safety benefits, too many
installers have lost sight of the need to
design and verify systems to ensure
Zone 2
that protection against the risks of
electric shock and fire is maintained
in the haste to get systems assembled
and operational. For example, it’s all
too easy to fall into the trap of thinking
that a 63A cable and connector
assembly can safely deliver 63A to
a connected load, with scant regard
to its length or the characteristics of
the supply to which it is connected.
The typical time pressures of an
event give rise to unique challenges.
A band on tour could well have two or
three 400A three-phase distribution
systems, which, along with all the
mains distribution, lighting, sound,
video and other equipment, has to
be unloaded from trucks, rigged
and ready for the show within 3648 hours. After the final encore,
everything will then be dismantled,
packed and on the road to the next
venue in an even shorter timescale.
With thousands of gig-goers
arriving at the door to see an event,
no one is interested in delay notices,
extras or similar constructionindustry-related issues. In response
to this very demanding operating
environment, the events industry has
developed its own unique culture,
along with the equipment and
working practices that enable it to
stage the same event reliably, time
after time, in venues hundreds and
sometimes thousands of miles apart.
BS 7909
While protection is one area that is
prone to being overlooked when
assembling temporary power
systems, it’s increasingly necessary
to address the relatively new issues
of power quality and EMC. In the
past most loads were linear in nature,
typified by tungsten lighting and
amplifiers with linear supplies.
Today however, nearly everything is
driven by a switched-mode power
supply if it isn’t already connected to
a dimmer or variable-speed motor
drive, giving rise to problems with
Zone 3
Zone 4
harmonics, power factor, voltage
quality and high leakage currents.
The industry has also had to respond
to environmental pressures. Recent
research by the environmental group
Green Festival Alliance shows that in
2011 UK festivals generated enough
electricity to power 12,000 homes for a
year, consuming 12 million litres of
diesel and releasing 31,600t of CO2 into
the atmosphere in the process. Not
surprisingly, there have been attempts
to introduce green energy to events,
ranging from solar power to biodiesel
and hydrogen fuel cells. However,
integrating renewable energy sources
into temporary power distribution
systems demands careful planning.
In response to these and other similar
factors, BS 7909:2011 ‘Code of practice
for temporary electrical systems for
entertainment and related purposes’
was extensively revised and rewritten in
2008, and further updated in 2011 to
reflect the changes in Amendment 1 of
BS 7671:2008. As a code of practice,
BS 7909 aims to provide guidance on
the practical considerations for
designing, deploying and managing a
temporary system. But it still requires
the reader to actually design a safe
system in accordance with the
fundamental principles of BS 7671.
BS 7909 or BS 7671?
The question of which standard to apply,
and when, often arises. BS 7909 was
largely written with the entertainment
industry, including broadcast, film,
theatre, outdoor events and touring
in mind, and the terminology often
reflects that fact. However, BS 7909 also
represents a set of recommendations
for the safe use and deployment of
temporary electrical systems of any
size or scope that use distribution
equipment designed for the purpose –
e.g. cables with plugs and sockets fitted,
purpose-built portable distribution
equipment and so on. As such, the
scope of BS 7909 is wide; it gives
recommendations for the management, >
www.theiet.org/wm | IET wiring matters | SPRING 2013 | 19
KEY POINT
HOW LONG IS
‘TEMPORARY’?
Skid-mounted distribution
unit with 400A three-phase
in and through connections
and a selection of 125A,
63A, 32A single and
three-phase socket-outlets
< design, setting-up and operation of
temporary electrical systems for both
entertainment and related industries,
which include any events or activities
using temporary electrical systems.
A note in the scope refers to the fact
that equipment used to form a
temporary electrical system should be
supplied as pre-assembled units that
have been tested and are known to be
safe and suitable for use. It doesn’t
prohibit the manufacture on site of
simple units that might be necessary,
but it does consider this should be the
exception rather than the rule. That note
answers the question of which standard
to apply. If a system plugs together
without recourse to using tools to make
terminations, then it falls within the
scope of BS 7909. However, if a system
(whether temporary or not) needs
building, with wiring accessories having
to be fitted, cables terminated and so
on, then BS 7671 alone applies. It should
be remembered that BS 7909 does
require systems to be designed in
accordance with BS 7671, but it does
make provision for simplified testing
based on the specific recommendations
for equipment being followed.
Further guidance on the symbiotic
relationship between the two standards,
and how to interpret the relevant
regulations of BS 7671 and BS 7909 in
order to achieve a safe temporary
system, is given in the IET’s new
guidebook, ‘Temporary Power Systems
20 | SPRING 2013 | IET WIRING MATTERS | WWW.THEIET.ORG/WM
and Infrastructure for Entertainment’ –
see panel on p22.
BS 7671 Part 7 – special locations
Some of the special locations in
BS 7671 are relevant to the temporary
power industry as a whole. Section
717 covers the electrical installations
within mobile and transportable
units, such as Portakabins, outside
broadcast trucks, catering buses and
accommodation units. It should be
noted that Section 717 is not concerned
with temporary electrical systems
that may be connected to such units
(except for the supply). Section 711 is
concerned with exhibitions shows and
stands, the scope of which is aimed at
the type of exhibition or show that may
be held within a purpose-designed
venue, such as the Ideal Home Show.
Theatrical-type shows or events are
excluded in the scope of Section 711 as
they come under the scope of BS 7909.
Often the technical intent of a section
will apply to a temporary system. For
example, in the case of an outdoor ice
rink consideration might be given to the
requirements of Section 702, or for a
festival with camping facilities Section
708 would be considered. The new IET
guidebook gives guidance on those
situations where the deployment of a
temporary system may not necessarily
need to (or be able to) follow all the
requirements given in the appropriate
Section of Part 7, but which should still
BS 7671 makes no distinction between
an electrical installation that is
permanently fixed to a building
structure and one that is not. It
defines an electrical installation as
“an assembly of associated electrical
equipment having coordinated
characteristics to fulfil a specific
purpose”. It goes on to define a
temporary electrical installation as
an “electrical installation erected for
a particular purpose and dismantled
when no longer required for that
purpose”. The key point to note is that
despite being temporary, in BS 7671
it is still referred to as an ‘installation’.
BS 7909 tries to make a distinction
between permanent installations
where equipment is permanently
bolted to the building structure and
temporary electrical distributions.
Throughout the course of the lifetime
of the temporary system it should
perform effectively and safely. A
Christmas lighting display would have
a defined period of existence whereas
a theatre show may have the planned
run extended if it proves successful at
the box office. There is no time limit
that a temporary system may stay in
existence but BS 7909 requires that the
designer takes into account all the
factors likely to affect the system for its
original planned duration, with a date
stated on the Completion Certificate at
which a further assessment should be
made to ensure the continued
adequacy of the system. So a designer
of a system used for a TV drama that is
due to run for six weeks may state a
reassessment date of eight weeks to
allow for minor overrun, but give an
indication that a proper review should
be taken of the system if it is proving
to be a popular show and the run is
being extended accordingly.
follow the technical intent – invariably
concerned with minimising the
enhanced risk of electric shock.
Design considerations
A quite different approach is required
when designing a temporary system,
compared to a fixed installation, and
the IET guidebook describes the many
areas that need considering, giving
both worked and practical examples
where necessary. For example, almost
invariably temporary systems will
be under the control of a skilled or
instructed person, which may have
implications for the design of circuit
protection, or it might be outdoors
exposed to the elements. In most cases
selection of equipment is important as it
needs to have the necessary resilience
for repeated use as well as changing
environmental factors. The use of
armoured cables is rare because they
are difficult to manhandle, not readily
reuseable and do not have Class 5
Distribution
units located
under a stage
flexible conductors. As such, mechanical
protection of less robust cables has
to be provided by other means, such
as cable traps or positioning, and
distribution connectors must be
robust and suitable for repeated use.
The electrical performance of a
temporary distribution also needs
careful planning. At an event the
installation is often equivalent to
‘clipped direct’ (reference method C)
and thermal insulation is uncommon.
Instead, designers must allow for factors
such as the warming of exposed cables
by solar radiation. Also, many
distribution units may be covered to
keep off the rain and this may require
MCBs to be de-rated if their ambient
operating temperature exceeds 40°C.
Another design factor often
overlooked is that the current-carrying
capacities and voltage drop tables in
BS 7671 often need to be corrected for
Class 5 flexible conductors depending
on the cable type. If multicore cables
are used (which are common for
lighting circuit distribution) further
correction factors should be applied
depending on the load of each circuit
in the multicore as well as the number
of circuits.
At larger events where significant
quantities of power processing
equipment such as switched-mode
supplies, dimming or motor controls are
used, consideration should also be
given to power quality and residual
currents as described earlier. Such
equipment is a common source of
harmonics, the triplens of which sum in
the neutral of three-phase distributions,
giving rise to high neutral currents –
especially, and this is not uncommon, if
the overall load is unbalanced.
The use of EMI filtering in such
equipment means high residual currents
can be expected, which has implications
for the specification of RCDs for circuit
Learn
protection and protection against
electric shock. The new IET guidebook
discusses how to correctly specify and
use the different types of RCDs based
on detection characteristics, operating
currents, delay and load, as well as the
common – and mostly erroneous –
practice of bypassing them. And if that
statement raised an eyebrow, then the
book explains it all.
Bonding and the environment
Another design consideration that
is often overlooked is the ‘electrical
environment’ – a term defined in
BS 7909 which is allied to, but not the
same as, an equipotential zone. To
understand the concept, consider a
house with an electrical installation,
as shown in Fig 1. The inside of the
house with its electrical supply is
one electrical environment, and if
correctly wired is also likely to be an
equipotential zone. The garden is a
different electrical environment as it is
at true Earth potential; not the potential
of the supply earth at the main earth >
Meet
Discuss
Network
30 APRIL - 2 MAY 2013 • EARLS COURT 2, LONDON
11th International Exhibition of Railway Equipment Systems & Services
Harness the power of interaction
Regis
Now fo ter
r free a
t
www
.railtex.
co.uk
save £
20 o
the do n
or
• The Track • Education and Training • Project Update Theatre • The Platform
• Networking • Innovation • The Yard • The Recruitment Wall
• Hundreds of exhibitors • Thousands of products • Live demonstrations
Further information:
Email: info@railtex.co.uk
Tel: +44 (0) 1727 814400
Media Partners
www.railtex.co.uk
Supporting Organisations
WWW.THEIET.ORG/WM | IET WIRING MATTERS | SPRING 2013 | 21
James Eade, the author of
‘Temporary Power Systems and
Infrastructure for Entertainment’,
has worked in the events
industry for over 20 years. He
was formerly technical editor of
the magazine Lighting&Sound
International as well as chairman
of the PLASA annual industry
innovation awards panel. He
currently provides industry
training in temporary power
systems as well as general
design and management of event
electrical services including
those for event venues.
Dimmer racks on
the side of the
stage at a music
awards ceremony
< terminal in the house (except for TT
systems of course). The area around
the street light in the road (which
has its own supply distinct from that
of the house) is another electrical
environment. A vehicle in the street
with an on-board generator encloses
another electrical environment.
BS 7671 does not specifically consider
the interconnection of fixed installations
derived from different supplies (save
for some commentary in Section 444). In
events, however, such interconnections
are common. Generators are often used
to provide additional power for a stage
system located within a building which
itself has its own supply, or at large
events (such as Glastonbury, for
example) multiple temporary
distributions, each with its own generating
plant, may reside together. More often
than not the earthing systems will end
up being interconnected, whether by
mutual connection through exposed
conductive parts (such as via lighting
equipment mounted on a truss) or
earth-referenced signal cables.
In the event of a neutral failure on a
TN-C-S building supply, for example,
the earth electrode of a generator being
used to supply power for an event
inside the building may form the
principal means of earthing through
fortuitous connections between the
temporary supply CPC and the
building’s CPC. Even if no failure is
present, the earth loops that can be
created by such interconnections will
invariably give rise to signal
degradation, resulting in humming
audio systems, jittery lights or scrolling
‘hum’ bars on video pictures. Taking
supplies from an installation in a
22 | SPRING 2013 | IET WIRING MATTERS | WWW.THEIET.ORG/WM
Example of a
‘keyed single-pole
connector’ as
defined in BS 7909
building to provide power for outdoor
events presents similar safety issues
that need to be considered.
Testing
The guidance given in BS 7909 is firmly
rooted in the principle that equipment
delivered to site has been checked
for electrical safety, and can be shown
to be safe and serviceable for use.
It requires all the pre-manufactured
cable assemblies and distribution
equipment be tested in accordance
with the IET Code of Practice for
In-Service Inspection and Testing.
The issue of testing temporary
distributions is probably the most
widely misunderstood aspect of the
application of both BS 7909 and BS 7671.
The new guidebook describes why
testing is conducted and how to
effectively and quickly test a temporary
distribution. It also recommends testing
intervals for portable equipment and
items such as mobile and transportable
units. In short, the book contains all you
need to know to ensure a rigorous
approach to testing within the timescale
of a typical live event. *
FACT FILE
ABOUT THE BOOK
The IET publication ‘Temporary
Power Systems and Infrastructure for
Entertainment’ deals with the correct
application of the principles of BS
7671 and the application of BS 7909 to
a temporary event. It is written in an
accessible manner to assist readers
with a range of skills and the wealth
of information contained within its
covers will be invaluable to students,
technicians as well as practising
electrical engineers. Its detailed
chapters cover key topics including:
■ The relevant legislation, standards
and industry guidance that apply to
temporary events, including those
relevant to permanent venues that
may host temporary events such
as exhibition halls or theatres.
■ Earthing arrangements including
guidance on the identification
and treatment of extraneousconductive-parts, supplementary
bonding and protection methods.
■ Design principles and
requirements including assessment,
protective devices (especially
the correct use of RCDs), load
balancing, the effects of neutral
loss, cable calculations, designing
for power factor and harmonics,
uninterruptible power supplies,
emergency lighting and more.
■ Equipment provision and testing,
including the supply of mobile
and transportable units and
correct specification of cable and
connectors. It covers the relevant
test requirements for portable
equipment, suggests time intervals
for the testing of equipment and
explains the requirements of BS 7909
in respect of equipment supply.
■ The testing requirements of BS
7909 and how to achieve results in
a timely manner on-site or when
changing location. The potential
hazards and problems associated
with testing equipment such as
dimmers, UPSs and RCDs as well
as the additional requirements for
special locations as defined in Part
7 of BS 7671 are considered.
■ Guidance on generators, street
furniture and other supplies
including operational considerations,
methods of Earthing including
earth electrode calculations,
generator/supply interconnection
and generator housekeeping.
■ Operational considerations
including bypassing RCDs, safe
working practices (including
live working), protection of the
temporary electrical distribution,
emergency procedures and the
relevant requirements of BS 7909.
■ Requirements for venues
including provision of appropriate
supplies and the requirements of
BS 7909 with regard to exchange
of information between visiting
events and venue management.
Download