M/s ANSALDO STS Firm's letter No. M0526/Metro-Kol/TPWS/002 dated 20.05.10 & 003 dated 22.5.10 Sl # Clause# Description Firm's Remark Railway Response 1 Tender Notice Completion period of project. 12 months from the date of award of contract This period is practically impossible as the type of trains and their associated control systems are different from the types we have been dealing with SR and IRPMU contracts. We need to measure the train dynamics in sort of survey and trials runs before proceeding the design. This process itself may take 3 to 4 months and the proto trials shall be other critical process which would take another 3 months. Therefore, we request Metro Railway to extend the completion period of contract to 24 month instead of 12 months. Issue discussed during the meeting. Metro railway is committed to meet the target set for the completion of the project.The completion period is not proposed to be extended. 2 SCC 26 We understand that RDSO/SPN/183/2004 version 0 Amendment 2 is the latest.We request your confirmation in this regard. The latest RDSO spec upto the date of opening of the tender will be applicable. 3 RDSO specification RDSO/SPN/183/2004 version 0 Amendment 2 with latest amendments. SCC 26(b) Train stopping for 1 minute to pass the Red Signal Whether the signal shall be Manual or Auto Signal? Under In all cases, driver has to stop for 1 min at Red signal what condition this feature is needed like On-sight mode as per G & SR. If the driver starts after stopping the or signal failure (paper clearance etc). Kindly clarify train, the TPWS system need not intervene and only record the duration of stoppage. Details required about track and train profile Index plan showing the gradient will be handed over to successful tenderer on demand after issue of LOA. Anything else required has to be clearly asked. 4 SCC 26(c Track and Train profile & d) 5 SCC 26(e) TPWS must be upgradable to The future architecturre for the CBTC-TPWS interface and The purpose is to upgrade the system to cab signalling communication based train inputs required to/from TPWS shall be required to confirm (ERTMS/ETCS level 2 or equivalent) at a future date control system this using Railway's GSM-R network (to be installed shortly). The inputs required to/from TPWS will depend on the type of system being offered through this tender. SCC 26(g) ELRS/SPEC/SI/0015 test for copy of latest version of ELRS/SPEC/SI/0015 requested This is RDSO electrical directorate specification and reliability of electronics used can be purchased from RDSO electrical directorate. in rolling stock 6 S&T/Works/4-2010 1 7 8 9 Train to be stopped in platform irrespective of signal aspect.The tolerance for stopping trains should be ?5 meters SCC When signal is green and on 26(h)(viii) board TPWS equipment passes over balise, it will be informed to the driver by audio visual indication and this indication will be available to the driver for 5 seconds SCC When signal displays yellow 26(h)(xi) and onboard equipment passes over the respective balise, the yellow lamp on the panel is lit steady. The driver must acknowledge this within 10 seconds.Failing which emergency brakes are applied to halt the train. After the driver acknowledges, the TPWS system will permit the train to go upto the normal braking distance fromt he next signal with maximum permissible speed subject to permanent speed restrictions at that stretch. Thereafter if the driver fails to regulate speed as per braking curve the system will apply brake and bring the speed to 15Kmph. SCC 26(h)(iv) This is not an ATP function.The requirement to be reviewed. Movement authority will be given upto the end of the platform irrespective of the aspect of the signal Why there is "?" mark? Read within 5 instead of ? 5 These requirements are under study and if any clarifications needed, kindly clarify Discussed during meeting. These are part of functional requirement specifications for the metro railway, kolkata. No change is proposed. Discussed during meeting. These are part of functional requirement specifications for the metro railway, kolkata. No change is proposed. S&T/Works/4-2010 2 10 26(h)(x) TPWS shall permit to release its brake application if speed of the train is 15Kmph. Driver then can drive the train to stop point without unnecessary emergency brake being initiated, except when the driver tries to pass the signal displaying red or no aspect without stopping or without acknowledging the danger aspect, when the system will apply emergency brake and bring the train to halt. 11 SCC Ready for operation lamp 26(h)(xiia) shall extinguish when fault is detected by the TPWS and immediately "TPWS faulty" lamp should be lit and horn shall sound to attract the attention of the driver. The system will restrict the speed of the train to 30 Kmph(safe mode) Discussed during meeting. These are part of functional requirement specifications for the metro railway, kolkata. No change is proposed. In case of system failure of TPWS on board equipment, system will apply Emergency brake and bring the train to standstill. Thereafter the driver has to isolate the system in order to release the Emergency Brake.In case of Track side failure of the TPWS system, the on board system of TPWS will apply the brake and then the train may proceed with restricted speed. S&T/Works/4-2010 3 Suggestion for applying emergency brake in case of failure of on Board equipments is acceptable . In case of track side failure the On Board system will act as per information given by last working switchable balise till it passes over another working switchable balise as per Para 26(h) (XII)(b). 12 SCC 26(l) Cross acceptance of TPWS 13 SCC 26(m) This will be governed by the prevailing guidelines of RDSO for Cross Accpetance and as mentioned in RDSO/SPN/13/2010. Clause 9.9 Kindly clarify In case of discrepency FRS of Metro Railway is required. between FRS as mentioned in RDSO specification & FRS of Metro Railway. FRS (Functional Requirement Specification) of Metro Railway will prevail The criteria for cross acceptance has already been given in detail under Para 26(l). RDSO/SPN/183/2010 is not yet authenticated . This can become applicable if it is authenticated before or on the date of tender opening .During discussion it is agreed that the tenderers will submit valid safety certificates alongwith the bid. The detailed docuements (safety case etc as stipulated in the cross acceptnce criteria), will be submitted immediately subsequent to the issue of letter of intent to the successful bidder. FRS of Metro Rly is given at Para 26(h). S&T/Works/4-2010 4 M/s Invensys Rail Firm's letter No. IRSI/Metro Railway/ETCS/0133 dated 21.05.2010. Sl # Clause# Firm's Question Railway Response 1 Is the Doppler radar need to be considered as part of onboard system for Kolkata Metro? 2 Clarity is required whether a fixed balise and switchable balise to be considered for all signal? The specific equipment/instrument used for deriving the requirement as specified in the tender, should meet the criteria for cross acceptance. One switchable balise per signal is definitely required. Metro Railway has uni-directional movement of trains. As such the requirement of fixed balises have to be worked out in this context by the tenderer. Description 3 SCC 31 The power supply provided by railways will be 110 Volt AC or 230 Volt AC for the track side equipments. The power supply provided by Metro Railway will be 110 Volt AC by stepping down 230 Volt AC. 4 SCC 26(h)I Please clarify whether the on-board equipment need to transmit the data between onboard and wayside station? 5 SCC 26(h)I Clarification required for Item: Distance recorder- Is this the speed sensor? Recording Unit - Is this the in built event logger on the vital computer on board " It shall be capable of transmitting data request and data to wayside station" - the quoted line is to be deleted. Distance recorder to be read as speed and distance measurement unit and anything else required for the purpose. The answer of second query is 'yes' , the recording unit is in built event logger. S&T/Works/4-2010 5 6 SCC 26(h) Ready for Operation' lamp XII shall extinguish when fault is detected by the TPWS and immediately "TPWS faulty" lamp shall be lit and horn shall sound to attract the attention of the driver. The system will restrict the speed of the train to 30 Kmph. When the system has failed, the system cannot control the train. The safer operation would be to apply emergency brake and stop the train. The driver needs to isolate the system to release the emergency brake and move the train. The suggestion of application of Emergency brake in case of On Board system failure, is acceptable. 7 SCC 31 Additional information suggested in the column of 'Supply of the materials by the railways' - brake, acceleration, wheel dia, space in cab etc The information required will be made available to the successful bidder after issue of LOA. Before that the tenderer can conduct survey as per Para 14 of SCC. 8 SCC 31 Signalling cable will be provided from where to where the firm assumed between signal aspect checking contact location to LEU location Please suggest it is essential to propose SDMI or else we can propose the standard DMI instead SDMI? Signalling cable as required by the tenderer will be supplied by the railway. The cost will be loaded against the offer. The tenderers can quote with deviation . However they need to specify the additional cost involved(in commercial bid i.e. packet II) in case no deviation is quoted. Tenderers can quote with deviations as per the configuration available, it will be evaluated on merit basis Suggestion seems to be acceptable.To be added with suitably rewording as clause 3.1.5 in the tender notice. 9 10 11 Signalling cable will be provided by the railways Requested to change "LEU shall be capable of 8 signal inputs instead of 10 signal inputs" Tender Notice The clause no. 3.1.4 of tender notice should be modified accordingly "Non Indian Firm quoting through their Indian Representative who is direct subsidiary/sister concern (having common parent) should meet the eligibility criteria as laid down in para 3.1.2 & 3.1.3" S&T/Works/4-2010 6 M/s Thales Sl # Clause# Firm's letter No. Nil dated 24.05.2010. Description Firm's Remark Railway Response The purpose is to upgrade the system to cab signalling (ERTMS/ETCS level 2 or equivalent) at a future date using Railway's GSM-R network (to be installed shortly). The inputs required to/from TPWS will depend on the type of system being offered through this tender. it means that it should either be balise or any other thing as required by the system to take the signal aspect and other information " It shall be capable of transmitting data request and data to wayside station" - the quoted line is proposed to be deleted. The simplified MMI will be exact equivalent of MMI conforming to UIC/UNISIG specification or equivalent except that instead of touch screen, it will have high glow LED indication with robust push buttons for operation. The clause is reworded as "Application software of the data preparation tool shall have user-friendly interface and shall be able to generate station/section specific application data to carry out future modifications" 1 SCC 26(e) What is ment by 'Communication based train control system through GSM-R' 2 SCC 26(h) Functional Requirement Specification what is meant by 'other sources' A system according to TPWS specification cannot sent information from the on-board to the wayside system. Please specify in detail this request. The specs of Simplified MMI is unclear. Please specify in more details. What exactly is meant by application software. Please specify in more detail 3 SCC 26(k) Please specify - train headway Please specify - the existing braking power of trains. 4 SCC 26(I) p 80 Please indicate how these checksums are calculated and provide the quoted standard RDSO/SPN/144 S&T/Works/4-2010 7 3 min. headway should be practically acheivable. Obviously the design headway should be less than 3 min. the worst braking distance from 90Kmph to 0 Kmph is 300 mtr. The clause is reworded as " Software checksum of EPROM(s)/any other software storage device shall be provided as per RDSO/SPN/144." M/s Siemens Sl # Clause# 1 Firm's letter No. Nil dated 24.05.2010. Description Firm's Remark Railway Response Please provide additional information regarding operation on Metro Railway network, especially in terms of: timetable and operational headway, signaling scheme, especially the signaling sequence 2 3 mixture of traffic (freight trains, metro trains, interregional trains etc.) Please provide additional information concerning the vehicles to be equipped: Train type (manufacturer, date of manufacture) Braking system (specification, blueprints) Installation conditions on vehicles, especially in Cab (photos, measurements or blueprints) number of non-powered axles available (for installation of tachogenerators) number of non-braked axles (for installation of tachogenerators) temperature on Cabs (air conditioning available?) A “simplified MMI” is requested [Packet I, p.77, II]. Please provide additional information about the desired properties and functions. S&T/Works/4-2010 8 The train service is available from 6.30am to 10.30pm on headway basis. The proposed operational headway is 3 minutes. Obviously the design headway has to be better than that. Drawing requested is already attached with the tender document. Only metro train (8 coach multiple unit) runs. The firm's representative was adviced to have a survey of the Metro railway system, to have a better understanding of the items asked for. The simplified MMI will be exact equivalent of MMI conforming to UIC/UNISIG specification or equivalent except that instead of touch screen, it will have high glow LED indication with robust push buttons for operation. 4 Interoperability between trackside and onboard No specific standard is proposed. Any standard which equipment is requested [Packet I, p.76, (a)]. In order to is widely prevalent elsewhere in the world and as per fulfill this requirement, not only the hardware but also the requirement of Metro Railway, will be acceptable. engineered software and data (onboard and trackside) needs to be interoperable. Please specify the corresponding interoperability standards which need to be adhered to (e.g. a specific UNISIG version). 5 The system shall comply with the “RDSO Specification The latest RDSO specification can be purchased from No. RDSO/SPN/183/2004 Ver 0 Amendment 2 for TPWS” the Signalling directorate of RDSO. [Packet I, p.75, 26)]. Please provide this specification. 6 Please provide additional information about the signals to be equipped: Type (manufacturer) Lamp types (LED / filament, voltage for day and night) Only in the tunnel, SL21 type double filament bulbs are used, all other signals are fitted with LED signals.Same voltage for day and night. Climate requirement as per RDSO specification RDSO/SPN/183/2004 ver 0 amendment 2 (or latest). There is no cases of water logging in Metro Railway. 7 Please provide additional information concerning the climate conditions, especially: temperature (maximum, minimum) humidity height of water to be expected during monsoon period M/s Larsen & Toubro Limited Firm's mail copy dated 24.05.2010. Sl # Clause# Firm's Remark Railway Response 1 Interoperability between Japanese manufacturer shall be eligible Already covered under item no. 4 of M/s Siemens questionaire above. 2 As per BOQ item No. A1, A1a), A2(page 8 of packet II), A2, A3 instead of RDSO specification No. "RDSO/SPN/183/2004 ver 0 with amendment 2(or latest)" please mention as "RDSO/SPN/183/2004 ver 0 with amendment 2(or latest) or equivelent Metro Railway intends to install a system as per RDSO specification. However tenderer are advised to quote their system with minor deviation which will be evaluated as per requirement of Metro Railway. Description S&T/Works/4-2010 9 3 4 5 IN BOQ item A1, a) "Equipment with MMI conforming to UIC/UNISIG specification." Instead of that please mention "Equipment with MMI conforming to UIC/UNISIG specification or equivalent." In item no. A2 of the system description "Mainly consist of LEU". In kyosan system LEU is not required hence amend suitably. This is one of the merit of the Kyosan System. Since Kyosan is not RDSO approved vender the feasibility of getting material inspected by RDSO may relook in that case it can be inspected by KM Rly engineer's S&T/Works/4-2010 10 agreed Tenderers can quote with deviations as per the configuration available. It will be evaluated as per requirements of Metro Railway. On date, there is no approved list of venders for supply of TPWS system. The inspection will be arranged through RDSO/Metro Railway Kolkata.