Product Line Component All HK Arc Chutes Foreign material found - 2 metal plates wedged in arc horn. All HK Arc Chutes "Sand" found in arc chutes. All HK Arc Chutes All HK Arc Chutes All HK Arc Chutes Evaluation of cracks in ABB HK Arc Chutes. ABB recommends NOT shipping arc chutes while mounted on breakers. ABB offers refurbishment of arc chutes in some cases. All HK Arc Chutes Arc Chute Jump Gap Cracks/Repairs - Arc chute issues with jump gap cracks, epoxy repairs, etc. What are other plants using as acceptance criteria when finding damage to arc chutes? Do any plants have any testing or inspection criteria. David answered some with gaps…Vogtle still finding cracks. All HK Arc Chutes Is ABB going to develop field repair procedure? All HK Arc Chutes What is the Status on repairing Arc chutes? All HK Arc Chutes There is a long lead time for HK arc chutes – They are also expensive. Can you justify repairs? Issue All HK Aux Switch SWGR Aux Switch L2 Aux Switches binding due to excessive NO-OX grease used by supplier. Perry Presentation - L2 Aux Switch (TOC) found out of adjustment resulted in breaker failure. All HK Aux Switch Aux Switch refurbishment technique All HK Aux Switch L-2 Switch Maintenance All HK Aux Switch L-2 Switch Failures Aux Switch OE16527 - Loose Linkage in 4KV Breakers Results in Failure of Auxiliary Contacts at Oconee (L2 Aux Switch) Aux Switch OE 16739 - Breaker Cell Switch Failure Caused Essential Cooling Water Pump Trip Event (L2 Aux Switch) All HK All HK All HK Aux Switch All HK Aux Switch OE17451 - Reverse Power Trip of Diesel Generator Because of a Misaligned Breaker Auxiliary Switch Breaker Auxiliary Switches Missing Internal Spacers. The missing spacers could allow the contacts to slide on the shaft to a point where the electrical contacts would not make connection or prevent the switch from rotating. All HK Aux Switch ABB Refurbishment Review SWGR Aux Switch Refurbishing & Replacing Cubicle Mounted Aux Switches (Jim Allgood) SWGR Aux Switch Adjustment travel on L2 switches…can ABB provide guidance on adjustment & switch setup? All HK Chair Moldings All HK Chair Moldings Evaluation criteria for hair-line cracks. Chair Moldings Prior to 1970 (may have) different mounting location for the puffer nozzle. All HK Charging Motor Brush Length Spec on Spring Charging Motor All HK Charging Motor OE 16879 - The Spring Charging Motor on a 4.16KV Breaker Overheated All HK Charging Motor Charging Spring Motor Failed to Operate due to excessive brush wear and charring. All HK Charging Motor Obsolescence of older Lamb / Ametek motors. All HK Charging Motor What type of grease should be used in Ametek Charging Motors. All HK Charging Motor 15HK Closing Spring All HK Closing Spring All HK Coil - Trip & Close All HK Coil - Y Trip and Close Coils Oconee has reported a potential problem with varnish buildup on the inside of the bobbin of the Y coil in their control devices. All HK Contact Springs Stationary contact assembly block spring relaxation Overhaul Maintenance of Spring Charging Motor OE20142 (Perry) Breaker Identified with Incorrect Closing Spring Combination Combination found was "Gray-Red-Gray" which documentation does not support Color & type of closing springs…can ABB give a chart? All HK Contacts Have seen cracked moving arcing contacts on HK breakers in the past couple of years, maybe 1 in 10 breakers. Has anyone else in the industry seen this type of event? All HK Control Circuit OE16764 - ABB 5HK and 15HK Series Breaker Blocking Diode Failures All HK Control Device Use of "BBs" versus "Slugs" for control device contacts. 5HK Trucks Control Device Adjustment criteria 15HK Trucks Control Device Adjustment criteria All HK Control Device Broken contact carrier. Control Device ABB January 2001 10CFR21 issued - Moving contact tip (spring seat) failure @ Seqouyah and Catawba. During manufacturing, the contacts were overformed which made them thin. Only three known cases All HK Control Device Should Control Device Springs be replaced during Control Device refurbishment? All HK Control Device Silver plating on Aux contacts is wearing off. How critical is silver plating on contacts? All HK Control Device OE16387 - Breaker Problem Caused Component Cooling Pump Manual Start All HK Control Device All HK Control Device All HK OE18438 - 4KV Breaker Control Device Contact Carrier Manufactured with Excess Molding Material Containment Spray Pump Breaker Failed to Close Using the Control Room Control Switch during Surveillance Testing due to improper adjustment of the auxiliary contact device. A contributing cause was inadequate instruction in both the vendor technical manual and the preventative maintenance procedure. All HK 7.5HK 5HK350 Control Device ABB Metal Clad Circuit Breaker Contact Forming Concern (Contacts Improperly Formed) Control Device Failure on Control Device that was rebuilt. 7.5HK has two gaps…overtravel & stop lever. Gaps were within specs. Control Device 15HK Control Device All HK Control Device 7.5HK Control Device SWGR CTs SWGR Cubicles All HK Drawings 15HK Drawings All HK Hold Pawls All HK Inspection - NRC OE18438 Breaker Failure to Close Due to Control Device Contact Carrier Manufactured with Excess Molding Material OE19937 Swgr Cubicle Interference Prevented Bkr from Operating Closing springs did not recharge after last breaker operation due to impact of closing springs' link arm with swgr interference bracket on the floor of the cubicle ABB Refurbishment Review (Hope Creek) 7.5HK Breaker Failed to Close due to Control Device Failure Retaining spring for "LSa" detached due to inadequate height of spring retainer and spring with BB may have contributed. CT liquification. Isolation between adjacent cubicles to prevent ionized gas transfer (ref SONGS 2001 failure) Revision of HK Exploded View Drawings 15HK Contact, Truck, Jackshaft, Op Mech Exploded View Drawings OE18435 - 4KV Breaker Spring Charging Failure What findings resulted from the 1998 NRC breaker "pilot inspections"? a) If cracks are found in the bus bars ceramics what could be the cause? b) What criteria is used by ABB to determine acceptability? If the megger readings are acceptable, do cracks pose any negative impact on the integrity of the bus bars ? SWGR Insulators All HK Interference Angle All HK Interference Angle OE19076 (Sequoyah) 1E Breaker Installed in N1E Application What is the proper location of the Interference Angle (i.e. rejection bracket) for all HK models? 5HK Trucks J-Hooks Seabrook & Perry discovered 5 “J” hooks with partthrough wall cracks on the inner radius of the bend and 1 fractured during breaker retest after refurbishment All HK Latch Spring All HK Latch Spring SWGR Lead Assembly North Anna Issues (OE 15980 - 4/2003) SWGR Lead Assembly Issues identified at Surry (5/2003) OE 17213 - Auxiliary Feedwater Pump Breaker Failed to Close Because of a Weak Latch Spring OE17906 - 4 kV ABB HK Breaker Charging Spring Cycling SWGR Lead Assembly Lead Bushing inspections during SWGR PM. All HK All HK Lubrication Lubrication All HK All HK Lubrication Lubrication What mechanical lubricants are approved? What electrical lubricants are approved? What amount of NO-OX should be applied to breakers? Do heaters in the cubicle degrade grease? All HK Lubrication 1) Mobil28 is being used & timing is too short. Can ABB provide timing spec for M28 2) Can we increase bridge pivot pressure? 3) Can overtightening cause galling? All HK Lubrication OE 17796 - Condensate Pump Slow Breaker Opening Due to Hardened Grease 5HK MOC Actuator Assembly parts upgraded and need to be replaced if you replace your lower frame / truck assembly and it be of the old style (ABB provided a picture of old & new style assembly) All HK MOC Linkages All HK MOC Linkages All HK MOC Linkages Notes from discussion on MOC Linkages Diesel Output Breaker Failed to Open due to Misaligned mechanism operated control switch. A design weakness of the MOC linkage attachment can result in the locking nut falling out such that the breaker control logic is disrupted. Seabrook MOC alignment failure & failure analysis report (OE24048). All HK Operating Mechanism Spurious Closure of Breaker All HK OE 17374 - Inside Recirculation Spray Pump Circuit Breaker Failed to Close Due To Mechanical Operating Mechanism Binding All HK Circuit breaker failed to close while attempting to start a Safety Injection pump. The cause of the breaker's trip free condition was interference between the pin in the third toggle assembly and the wall of the mechanism or the side of the charging cam. This interference occurred due to the use of undersized washers found on the shaft of the crank assembly. The wear caused by the rubbing of the end of the pin on the cam and the side sheet caused increased friction as the surface became rough which eventually caused the trip Operating Mechanism latch to bind and caused the breaker to fail to close. ABB supplied HK Swgr Shutter / MOC /TOC part numbers and recommended maintenace frequency. SWGR Parts All HK Parts Kit - Breakers Incorrect Parts Identified in Vendor-supplied Breaker Refurbishment Kit All HK Parts Kit - Breakers Some parts are impregnated with Anderol. All HK Parts Kit - Breakers What refurb parts kits are offered by ABB? All HK Pin - 3rd Toggle All HK Pin - Close Latch All HK All HK Pin - Shutter Roller Pin - Shutter Roller 3rd toggle pin cracks & fractures. Older style pins used cotter pins on both sides which could cause close latch return to hang up on manual close lever. Cannot Remove Breaker from Cubicle due to shutter kick pin grabbing wireway. SONGs shutter kit pin event. Loss of 1E Bus. SWGR PM - Ductoring SWGR PM - Grounding All HK PM - Inspection All HK All HK PM - Inspection PM - Inspection What is the ABB and/or Industry maximum DLRO reading for bus connections ? Based on Surry experience, connections were mostly between 3 or 4 micro-ohms, generally less than 6 micro-ohms. What means or device do other plants use to ground the bus? What is the ABB recommended inspection frequency? What is the EPRI-NMAC CBUG concensus inspection frequency? What are the recommended inspection tasks? All HK PM - Inspection Indications of lubrication problems Is there a more effective cleaner (solvent) other than isopropyl alcohol that can be used to clean bus stabs & silver plated bus connections without damaging the silver plating surface? ABB Bus Connection Torque Values SWGR SWGR PM - Inspection PM - Inspection SWGR PM - Inspection All HK PM - Inspection SWGR PM - Meggering All HK PM - Receipt All HK PM - Receipt All HK PM - Refurbishment All HK PM - Refurbishment All HK PM - Refurbishment Shipping Damage During receipt inspection of a refurbished safetyrelated breaker it was identified that the U-channel that operates the auxiliary switch on the breaker was installed incorrectly. What is the ABB recommended refurbishment frequency? What is the EPRI-NMAC CBUG concensus refurbishment frequency? (1) In case of Plant refurbishment (after about 30 years life), shall the breakers be refurbished or replaced? What is recommendation from OEM and what is industry practice? How many plants have (a) replaced or (b) refurbished breakers during Plant refurbishment? What is preferred breaker type (e.g. vacuum or air?) (2) What is maintenance / refurbishment frequency observed by industry these days? All HK PM - Refurbishment What do people do for cleaning secondary disconnects on either k-Line or Hk. ABB MV Swgr & Bus Maintenance (John Layne) Can get slow close in spec with go-no-go at minimum..then difficulty getting in spec with fast close. What is the ABB and/or Industry minimum acceptable megger reading for 5HK switchgear bus? All HK All HK PM - Refurbishment PM - Storage All HK PM - Testing Breaker refurbishment interval - MV HK breakers, what are some peoples experiences from 10y-15y? Catawba is now back to 10 years. Storage requirement for breakers – not installed. Reduced Voltage Testing Presentation (Beaver Valley) All HK PM - Testing Is reduced (minimum) voltage testing required? All HK PM - Testing What values should be used for reduced voltage testing? SWGR PM - Thermography All HK Post Maint Testing MISC MISC MISC MISC MISC SWGR Presentation Presentation Presentation Presentation Presentation Primary Disconnect All HK Primary Disconnect In the past ABB stated (including tech bulletin) that thermography can be performed to determine the conditions of connections and switchgear equipment. But industry experience indicates that thermography alone is not adequate. Most of the switchgear components cannot be monitored through thermography. Does ABB have a recommended method on modifying switchgear cabinets or other means to monitor bus connections while equipment is energized ? INPO Inspection Issue concerning breaker & relay PMT Safety Presentation - Woodbury Substation Accident PSEG Breaker Program INPO Safety Presentation - Ken Sweet AVO Arc Flash Presentation - John Lane NMAC SOER 98-2 Refresher Presentation Songs Presentation- Cubicle misalignment SONGS Presentation - 2001 failure of 3000A feeder breaker. Primary disconnect condition & traveling ionized gas issues. All HK Primary Disconnect Prairie Island Presentation - 2001 Failure & Fire All HK Primary Disconnect Primary Disconnect maintenance. All HK Primary Disconnect Primary Disconnect / over-heating inspection. All HK Primary Disconnect HK Primary Stab Maintenance CD-ROM All HK Primary Disconnect Primary Disconnect ABB Breaker tulip springs dislodged due to shutter binding Questions 1) Issues pertaining to arcing & sputtering of breaker / cubicle connections 2) Information on Primary stab design changes 3) Size/rating of breakers found with these problems All HK All HK All HK Primary Disconnect Questions (cont. from above) Primary Disconnect Prairie Island 4kV Swgr Fire Catastrophic failure in breaker cubicle (apparent cause failure of PDA, though specific cause hard to determine due to damage). Subsequent investigation at other breaker cubicles led to the determination that baked No-ox on the bus stabs create high-resistance connect that led to the failure. 5HK Primary Disconnect All HK Primary Disconnect All HK Puffer Piston All HK Push Rods 5HK Racking Mech All HK All HK Ratchet Plate Ratchet Plate OE19227 Overheating of Breaker PDAs Causes: • Slight misalignment of breaker stab • Dried deposits of No-ox on rosette contact surface • Non-silver plated copper rosette fingers ABB Refurbishment Review Aging Failure of Puffer Piston on ABB Type HK Breaker. The puffer piston shaft had failed due to age related embrittlement and fatigue. Limerick identified hair line cracks on rush rod baffles (all 3 phases). OE20459 (Seabrook) Emergency Bus Reserve Transformer Breaker Failed to Close Bkr mechanical interlock failed to go into the proper position when racked in, preventing bkr closure. Condition due to inadequate procedure guidance & lack of individual knowledge related to positive latch engagement during racking. Teeth on ratchet plate breaking off…not cause, symptom. Charging motor will run continuously. Is a higher control voltage (131 - 135 vdc) a contributor? Mispunched Rachet Plate (Fermi) All HK Ratchet Plate MISC Retrofit OE18435 Breaker Spring Charging Failure Sequoyah MV Vacuum Breaker Retrofit Experience (Presentation) All HK Retrofit Has anyone replaced their breakers (HK) with a Vacuum? All HK Retrofit OE18006 Breaker Failed to Trip Electrically All HK Retrofit All HK Retrofit Lessons Learned on Med. Volt. Replacements Presentation - DC Cook Vacuum Replacement Experience & OE SWGR Male Secondary Disconnect inspection (cubicle Secondary Disconnect mounted). 1995 BVPS failure resulted in 10CFR21. All HK HK Breaker Secondary Disconnect Connection Problems after racking the Breaker into the Cubicle. Has anyone else experienced this Secondary Disconnect Issue? 5HK250 All HK SWGR All HK SWGR Secondary Disconnect OE18906 Breaker Failure to Operate in Test Secondary Disconnect Secondary Disconnects Maintenance Loss of silver plating on Swgr (male) Secondary Disconnect causes 1E breaker failure. Secondary Disconnect (Hope Creek) OE 16633 - ABB HK-Style Breaker Spring Clip Shutter Roller Retainer Loosening Swgr shutters becoming detached from shutter lift mechanism. Shutters Shutter nylon hardware fractures & failures. ABB recommended maintenance and parts list. SWGR SWGR Shutters Shutters All HK All HK Silver Plating Silver Plating Inspection acceptance criteria. TVA Questionaire on Silver Plating All HK Silver Plating Are any plants doing silver plating? All HK Silver Plating a) What thickness of silver should be applied to the primary disconnect? b) Are the requirements for silver plating the same for both the breaker Primary Disconnect and Swgr Lead Bushing? All HK Silver Plating Silver Plating of Parts All HK Spring - Tension PART 21 NOTIFICATION - DEFECTIVE HK AND K-LINE CIRCUIT BREAKER TENSION SPRINGS Spring - Tension This is more of an FYI for the group: KLine – Had two failures back to back. Compressors Broken tension spring. Similar to Part 21 this year (3-16-2009). Part 21: Look at replacing around 1500 cycles? This one failed at about 700 cycles. These breakers were used as starters (on compressors)Part number: 716539A00. All HK All HK Spring Discharge Lever Spring Discharge Lever Damaged All HK Spring Guide All HK Spring Guide 15HK Trucks All HK All HK Spring Guide Survey Survey All HK Trip Latch All HK Trip Roller All HK Troubleshooting Found with cracked welds - is ABB intending to improve the quality of the weld? Is stress coming from slow close bracket as cracked weld is closest to slow close bracket tab Limerick found broken tack-welds on the closing spring guides. Inner Spring Tube (p/n 193309-K01) has black Alkyd resin coating. It has been determined that lubricant (Anderol, MG28) removes the resin coating & causes additional friction which can lead to closing speed changes, which negatively affects the breaker operation and/or can lead to a failure to fully close the breaker. Duke Overhaul Breaker Survey Who utilizes high speed video equipment Trip Latches with riveted pins. Trip Roller denting after few operations (i.e. "soft rollers") Troubleshooting - Paul Zamarripa - Prairie Island. NSR 5HK250 having problems with breaker not operating properly. Verified close circuitry. Testing cannot determine problem. Any suggestions on what to look for? Testing? Failure of breaker to operate from control switch. Cubicle issue. 2nd breaker tried in same cubicle with same results. Resolution ABB believes this fell into arc chute before / during mfg. Due to age of arc chute, no telling how this happened. Contact ABB-Florence (HK Product Engr) for CCRP generation. Arc Chute manufacturer process defect. See referenced EPRI Document Damage is likely to occur. If you value your arc chutes, don't ship them. Discussion on types that can and can't be repaired not included in Powerpoint presentation. ABB has document prepared by Ward Laubauch of KEMA. Sharkey’s observation is that we are not really looking at this. Ron F. says most people will find cracks if they look. ABB working on internal procedure that is not complete…was working on procedure for TVA…work in progress. EPRI perspective is that we were going to validate this procedure developed by KEMA to determine set of acceptance criteria. Needs to be two phase effort. Phase one is evaluation which is complete (2002)…issue is still open…is there still interest to proceed…do we need to move forward with phase two of testing and validation? ABB can repair arc chutes…however, older arc chutes that have the outer moldings that are glued together can only have the bundle replaced. ABB will repair some arc chutes in Florence, others have to be returned to original manufacturer. KEMA evaluation will be distributed with meeting minutes. 5HK250 and 7.5HK500 were two types of arc chutes we were going to test. David Hatfield: There is a procedure that he has developed for ABB, but has not been issued to industry…see KEMA eval comments. Sharkey says EPRI might fund this if we show interest or a need in this item (ABB will not fund this)…warns to be prepared for test results…findings might raise concerns with arc chutes in service. Testing is destructive testing of arc chutes and will require damaging several arc chutes to validate results. Note: report is now available on EPRI NMAC CBUG website. ABB can not repair or refurbish Arc chutes. Piedmont Dielectric is the current manufacturer of the arc chute. New arc chutes are available from ABB. Q: Are certain areas of arc chutes more prone to cracking? Yes, the jump gap is most susceptible to cracking (it also contains asbestos). Don’t lay arc chutes on their sides. Q: Additional question on arc chutes Where do you test the arc chute. See picture. Both sides of the Blow out coil Build up stock of arc chutes. 7 plants leave their arc chutes at their switchgear. Don’t’ store arc chutes on their side – it limits damage from using them as a table/bench. Must remove old NO-OX-ID grease during maintenance / refurb and replace with new grease. ABB recommends that the L2 switch is replaced after 8000 operations (if rotated contacts at 4000) or 10 years FYI *Document each contact configuration (e.g. - A,B,A,B). *Totally disassemble entire auxiliary switch. *Remove old NoOx-ID grease that is found. *No-Ox-Id lubricant has been found along the stationary connection (rear) that can cause failure (open circuit) due to cohesion. *Inspect silver plating, replace any piece that is missing silver plating. *During assembly, place No-Ox-Id lubricant only at pivot area (lower area, can not be seen unless disassembled). *Do not lubricated the mating/wiping surfaces. Paul Zamarripa - Prairie Island. Maintenance recommendations for L2 switch on truck? Are any plants replacing L2 switch during PM, overhaul or as corrective action for problem history? ABB pretty much covered this information. Survey says: 18 plants now present Breaker switch: 11 during breaker overhaul Cubicle switch: 4 (STP does when overhauling breaker…replaces L2 switch without de-energizing switchgear). McGuire is going to do the same. Both plants state it takes approximately 6-8 hours to replace the switch + time to make any necessary adjustments to linkages. ABB asked if it would make the process easier if they provided the switch on the mounting plate…both plants indicated it would not. Allen Dickard - Catawba. Survey of plants with L2 switch failures over past two years (approximately): # Plants being surveyed: • Which were actual failures of the L2 auxiliary switch? David Hatfield knows of 6 switch failures. • Which failures were related to linkage and/or breaker switch actuator? David knows of 4 failures related to linkage, which were also switch related. STP did an analysis of switch failures and root cause of failures was attributed to hardened lubricant (NO-Ox-ID). Abstract: While investigating an unexpected alarm that occurred during performance of an outage electrical test, it was discovered that the alarm was being initiated by an L2 auxiliary switch contact. Investigation of the switch revealed that the linkage had become loose from the actuating rod of the breaker. This was due to a retaining nut that had come off of the linkage connection point. Cell switch contact to the MOV did not close during the pump start and the pump tripped as designed. The apparent cause was an excessive amount of corrosion inhibitor (NO-OX-ID grease) applied during manufacture of the switch that had aged and behaved as an insulator. There was no formal maintenance requirement to remove the old grease, and this material resulted in degraded performance of this specific switch. The cause of the failure was that an L2 auxiliary switch on the ABB 5HK250 1200 amp incoming breaker did not correctly change state when the breaker was closed. This occurred due to failure to check for proper auxiliary switch alignment in relation to breaker open/closed status prior to placing the breaker in service. The apparent cause is a supplier problem. There were no breakdowns in the Perry procurement process or its implementation. The specific supplier cause may be determined as the result of ABB’s initiation of CAR #200700073 to have a Part 21 investigation performed. This seems to be a manufacturing issue. • Document each contact config (e.g. - A/B, fast B, etc.) • Totally dis-assemble entire aux switch • Remove old No-ox grease (No-ox lubricant has been found along the stationary connection (rear) that can cause failure (open circuit) due to cohesion • Inspect silver plating & replace any piece missing silver plating • During re-assembly, place No-ox only at pivot area (lower area, can not be seen unless dis-assembled • ABB can provide switches without No-ox - contact ABB for new part number FYI ABB: There are 4 types of crank arms and different setting adjustments on links. There are multiple holes on link arms - need to mark which link arm hole is connected when breaker is disassembled prior to refurb. Might look to see if link is bent. Plate that the switch is mounted to is two separate plates...3 bolts, but cannot adjust plate (though there may be some play). There is a new style plate that can be purchased that will allow for some adjustment. EPRI test results on McGuire moldings available. Cracks can be a result of leaning breakers on side or rear. ABB letter Issued to EPRI with TD-9608 and TD-9609 which give guidelines for Chair Molding acceptance criteria If chair molding is replaced then a new nozzle and tube may be required. Glenn Gorniak - Limerick. Is there a specification for the minimum brush length on the spring charging motor? • Lamb/Ametek • Ryobi • Black and Decker Action Item: ABB will provide this information, including part numbers for Lamb/Ametek and Ryobi brushes and cap holders. John Layne will need to confirm that these parts are still available through ABB. Misrouting the wiring harness during overhaul of the circuit breaker by a vendor. During the breaker overhaul the control devices are removed and replaced. The wiring harness for the control device was inappropriately routed under the control device instead of over the top of the device. ABB (Gene Langlois) warned that there is some risk of doing more damage than good when you are doing maintenance. ABB: You can take a static resistance. There are several different types of motors. Anything below 50 ohms is acceptable. Can megger and spin to look for dead spots. New breakers supplied with Ryobi motors. ABB can refurbish the older Lamb/Ametek motors but not the Black & Decker motors. Motor change outs to Ryobi requires additional qualification (and additional parts) and not recommended at this time. Bruce Renton of ABB. ABB motors had Beacon Exxon grease. During refurbishment, all Beacon grease should be removed and replaced with Anderol. Lonnie Little - STPEGS. What kind of maintenance is being performed on the spring charging motor during breaker overhaul? Has had some problems and is considering replacing motors during overhaul. Wants to know if any other plants are replacing motors. ABB replaces SONGS, Progress Energy, PPL motors during overhauls if motors do not pass receipt inspection. Salem performs inspection of brushes and continuity check of motor rotor on K-Lines (<10 ohms 125vdc motors while rotating gears). NOTE: ABB’s recommendation is 34.5,,,see K-Line notes. See OE Color code is important. ABB has AI to provide information. Have any plants experienced problems with broken retaining posts on trip and close coils? DC ground on breaker traced to this. FYI to look for during refurbishment. North Anna has seen this issue. Gene Langlois says coil should not be able to turn inside casing. Gentille has seen this problem. ABB inspected several coils and it appears while there is some varnish buildup on the inside of the bobbin we have not been able to reproduce this mode of failure. Main contact springs wearing out…if breaker has been closed for lengthy period…ABB is recommending that these springs be replaced. ABB: Common to see indentations, and wear on these parts. Brunswick – Have received some contacts from Florence that are cracked in the center of the contact tip. Turkey point – When would you expect to see contact wear/damage. ABB: The higher the MVA rating the more wear you will experience. Has anyone seen failures were the crack starts? Yes but not in the nuclear world. 75% tungsten – 25% silver. Blocking diode in the close control monitoring circuit had failed. The failed diode created an electrical path that kept the anti-pump relay energized which prevented the closing coil from being energized during an automatic actuation. The cause of the blocking diode failure were manufacturing defects in the die extending from the cathode to the anode that resulted in high electrical leakage. Use the newer design "slugs". Redesign due to BBs falling out of place. Part numbers are: (5) Spring 712895A00 (5) Slug (solid washer) 650362F00 See ABB referenced IB See ABB referenced IB Attributed to improper control device adjustment, quick/repetative or extreme cycling. BBC and Gould decals on the side of control devices were blue in color and all are suspected bad. ABB is red decal and is not affected by 1/01 10CFR21. The 10CFR21 recommends to replace the control the device. If the customers feels that they are qualified enough to simply replace the contacts then the springs and BB should be replaced with the round slug and new type springs. ABB David Hatfield: All the springs are required to be replaced and only a tiny dab of no-ox grease should be applied at the pivot point (no grease on the contact). ABB: Zero tolerance on loss of silver plating. Reference L2 IB for maintenance recommendations. During refurbishment L2 is completely disassembled. Plants measuring resistance of contacts during PM – majority of plants take resistance measurements and do not replace the auxiliary switch contacts when copper is showing if the contact resistance is less than 1 ohm. Note: Dave Hatfield commented that single contacts can be swapped around with good ones that are not being used in the circuit. The cause of breaker 1ETB6 failing to close was a failure of limit switch 2 (LS2, contact 10 - 11), to make in the breaker close circuit in the control device. There are two causes for the contact failure. One cause was most likely improper assembly of the breaker's control device. The assembly problem left the control device internals in a bind and caused an intermittent open contact in the breaker's control device disabling the close circuit on the breaker. This cause is not definite as the failure cannot be intentionally repeated either by site persons or the equipment manufacturer. The second cause was a weak lever arm return spring on the control device. This spring was also found to be longer than the manufacturer's specifications. These spring problems would result in less than adequate force on the lever arm and would exacerbate any additional resistance to movement created by an improper assembly. Discussions with the vendor concerning the springs and spring specifications are still in progress. Excess molding material ("flash") on the carrier assembly resulted in this breaker failing to close. Revise the 5HK250 and 5HK350 preventative maintenance procedure to include auxiliary contact device adjustments and visual verification of operation. This information has been shared with the manufacturer. At this time no response has been received in relation to this issue. ABB: Are you using latest copy of IB (Last addendum, May 2001??, had to do with C/D gap measurements). New IB has overtravel dimension. Need to document overtravel with feeler gauges before removing C/D when damaged which will allow ebb to evaluate this specification. ABB cannot assess failure w/o knowing as found results. • Extra material causes Yb contact to hang open • This has been seen recently on a K-Line • Two event reported to ABB in 2004 - 2005 • ABB entered a CCRP and is reviewing the issue • Bkr did not charge after closing in cubicle but did operate outside of cube • Op mech did not fully travel (after closure) resulting in the timing lever to travel improperly, which caused the control device not to operate the limit switch properly • Material removed from interference plate corrected problem • ABB made a new swgr interference plate mounting bracket • Inspect contact carrier for excess molding which can cause moving contacts to hang up • Moving spring (p/n 702338D00) & BB (p/n 703956A00) need to be replaced with new spring (p/n 712895A00) and solid washer (slug) (p/n 650362F00) See OE (number unknown at time) Hope Creek Date 050422 All CT’s should be inspected. ABB issued Part 21 on liquifaction of CT’s on April 17, 1989. SONGS: The switchgear is not designed to be air tight. There is a bus bar that goes from cubicle to cubicle. The intent is to simply minimize the transfer of any ionized gases by eliminating unnecessary or excessive holes. ABB: Simply minimize the openings – No effort should be made to create an air-tight junction. Kevin Mullen - Seabrook. Action Item to Sharkey: New HK exploded view drawings have been provided to Jim Sharkey and need to be incorporated on webpage. FYI The breakers hold pawls pins were bound in the carrier causing the holding pawls to not engage quickly enough. The pawls were catching only a fraction of the ratchet plate's tooth, which caused it to wear prematurely. The affected breaker was repaired. All pawls, pins, the carrier and the ratchet plate were replaced. See 1998 HK CBUG Meeting Notes a) Age and heat can cause cracking. b) If heat has caused cracks then the insulation should be replaced. Hi-Pot testing (best) can be performed per the IB to check insulation strength if cracks are found. This is Go/No-Go testing, must maintain value for approx.. one minute. Only NETA has megger maintenance testing criteria for megaohm values per voltage class. Doble testing can be used also. See OE ABB Dwgs available (Reference ITE Spec TD-6931 for 5HK and ITE Sheet L8535 for 7.5HK & 15HK) FYI - Seabrook and Perry simply want to make the users aware of this issue. Plants may wish to inspect for this whenever convenient. Both ABB and Grand Eagle has seen this problem. Part number is 00RM44772002 (ABB Part Numbers 191638A00 (LH) and 191638B00 (RH). Increased mechanical resistance of the breaker mechanism caused by a random build up of tolerances from wear and case distortion which our existing overhaul program did not identify, coupled with a significant reduction in latch spring rotational torque capability (6 turn spring). The stronger 5-turn spring was able to overcome the higher resistance, while the 6-turn spring could not. The cause for this event is still under investigation, however, The initial cause appears to be the charging latch spring tension. Gene Langlois reported as found conditions: ● Upper & lower 3000 leads found overheated & missing >50% silver plating (removed, replated, re-installed) ● Bus bar insulation overheated & cracking (removed, insulation removed & replaced, replated then re-installed) ● Bus bar boots dried from overheating (replaced) ● Ckt Bkr PDAs overheated & missing silver plating (removed, replated, reinstalled) ● Ckt Bkr upper/lower lead assemblies overheated & silver plating discolored (removed, replated, refurbished, re-installed) ● Shutters replaced Gene Langlois reported as found conditions: ● Upper & lower 1200 leads found to have sputtering connections & missing silver plating - not overheated (removed, replated and then new parts were purchased & installed - See new part design discussion by John Layne) ● Bus bar insulation was fine but cracked in some cases - not removed ● Bus bar boots were NOT overheated but replaced ● 3000 amp ckt bkr PDAs were oxidized slightly but NOT overheated (removed, replated (refurbished) & re-installed) - New style have different springs (dimension & color) ● Ckt bkr upper & lower lead assemblies oxidized slightly & silver plating discolored (removed, replated, refurbished, re-installed) ● Shutters replaced - Had to be re-positioned & Gene & Curtis to discuss. • Users need to inspect the silver plating of primary lead bushing in switchgear during de-energization of bus to check for conditions listed below: • Missing Plating • Hardened NO-OX-ID Lubricant • Burned area (sputtering). • Corrosion • Switchgear lead bushings (stab) should have silver plating intact. If the stabs are found to have missing plating then if possible, they should be replaced or re-plated. • Lead bushing stabs that are missing 50% or less plating at the penetration point (1”), does not have gouges, nicks or sputtering connections, and can not be replaced at that time, can be re-used if coated with NO-OX-ID. • Switchgear Primary Lead Bushing Stab Burnt Anderol 757 (obsolete), CGC-757-2 (Anderol replacement), Mobilgrease 28 NO-OX-ID ABB: Thin film per the IB. Answer: YES 1) Mobil28 is speeding breaker…tightening bridge pivot affects speed with M28. ABB is not changing timing spec. Recommends adjusting breakers to conform to timing specs. 2) Unofficially yes. Should have bridge pivot moving freely. 3) Not with enough lubrication. ABB will evaluate changing bridge pivot spec. IB for HK has not been updated to allow use of M28. Dial bridge pivot in to get speed. If too fast on closing but ok on trip can adjust springs. CAUTION Bridge pivot will loosen over time...if too tight & tears silver plate condition will worsen. Use force gauge when adjusting. Speed is adjustable by opening springs...second by bridge pivot. The breaker operating mechanism was disassembled. Several needle bearings had hardened grease. This circuit breaker had not been overhauled since initial installation. The cause of the slow operation of the circuit breaker was due to not overhauling the breaker within the time period recommended by the manufacturer. This is a well documented industry problem (See SOER 98-02) New style part numbers: 1. Bolt (p/n 54390C04) 2. Flatwasher (p/n 54500H00) 3. Bushing (p/n 165322A00) 4. Nut (p/n 54400H00) 5. MOC actuator link assembly (p/n 187920K02) • Need to check your dimension on the linkages • Check the rotation – Need 90 degree rotation. • You could have “wiring issues”. • ABB has built some aux switches dry (without grease) and are doing some endurance testing. They have asked customers (Turkey Point) with dry switches. • ABB will accept a PO that requires L-2 switches to be dry. ABB will disassemble tswitch, clean out the grease, and rebuild the switch. • STP now uses dry switches. • It is not possible to buy individual switch parts. If a bad part is found, you must discard or cannibalize for parts. • See ABB presentation for more information. • To clean, STP uses alcohol and citrus cleaner. The failed linkage connection was adjusted, reattached, and tightened. Visual inspections were performed on all 62 of the Class 1E ABB 4 kV breakers at SONGS to confirm that the MOC linkage lock nuts were properly in place. Periodic preventive maintenance inspections have been initiated for all ABB 4 kV breakers. A design change to the linkage connection is being considered. Station incorporated step in procedure to check the tightness of lock nuts. See document Dave Watkins - Perry. Had breaker that closed on its own. BV had breaker do the same. Perry has ruled out any similarities between BV failure and their breaker failure. Group feedback? Only happens when going from zero energy state….only happens on initial closure, then breaker will operate normally. Hatfield: manual firing lever over-travel when installing breaker in cubicle resets due to shock when breaker trips free. Has also seen issues when installing front plate jamming manual close lever. Also links on manual firing lever (old style with cotter pins vs. new design) might contribute to problem. Mechanical binding due to interference between the moving parts of the breaker 24J-4 operating mechanism. A spare breaker was refurbished with a retrofit upgrade repair kit and installed as breaker 24J-4. The retrofit upgrade repair kit improves the design by reducing the inherent gaps in the operating mechanism. Replaced the subject breaker with a spare breaker and completed satisfactory testing. The removed breaker was overhauled (refurbished) which included replacing the Operated Mechanism with a rebuilt mechanism. Other similar breakers were reviewed and verified to be functional. FYI During implementation of a plant 4160 volt breaker refurbishment program, an incorrect part was received in a 4160V breaker refurbishment kit. ABB recomends to thoroughly clean all parts (new and used) to remove any Anderol prior to adding Mobilgrease 28. Per ABB, the lead time is 2-4 weeks on standardized overhaul parts kits. Custom kits can be developed for a specific utility/plant. Large numbers of kits may take longer to produce Requires close inspection (including dye penetrant testing) and condition based replacement. New style pins (part # 148115A00) have head on one side. Kevin Mullen - Seabrook. Plant has a 5HK breaker that cannot be physically removed from the cubicle due to shutter kick pin grabbing wireway. Possibility of cubicle shifting. Any other plants with similar issues of cubicles shifting / settling? Any ideas of how to remove with bus energized. Hatfield: Possible to wear PPE, use insulated pole/stick (fiberglass) to wedge wireway enough to remove breaker. Presentation Field experiences has found that 10 micro ohm or less is acceptable. The higher the current rating, the lower the values will be found consistently. Grounding trucks, grounding breakers, grounding cables/clamps. 1 to 5 years (environment dependant) Not to exceed 6 years. See reference document Section 4 Ensure proper maintenance program to look for & correct: ● Bkr PDAs (lubrication baked on; Unable to rotate PDA; Springs have lost tension and are discolored; Pitting caused by arcing; Discoloration of molding around assembly) ● Overheating of contact structures such that No-ox liquified in upper/lower contacts and ran onto molding & bkr frame ● Similar issue where lubrication will drip onto contacts causing arcing and contacts to not reset properly ● Swgr stabs (hardened lubrication, loss of silver plating, greenish substance, overheating, AVOID use of abrasive material that will damage silver plated surfaces) ● Swgr Bus (hardened lubrication, damage to insulation material, boots cracked & brittle, bus bar damage) ● Visual damage to bkr Arc Chutes Citrus cleaners can be used (do not dilute) as long as residue is a removed immediately with alcohol. Must Hi-Pot test if citrus is used. ABB provided torque values FYI Fast close is final test for as-left…slow close is only for initial setup. Only NETA has megger maintenance and acceptance criteria values. Mike Jasurda - SONGS. Problems with shipping damage other plants are experiencing? No others responded that they have seen any damage. ABB states some of the problem might be with the carrier used for shipment. ABB does have a preferred vendor that they recommend. SONGS contract specifies use of one of their contract carriers. Hatfield recommends using Emery Freight. The U-Channel was removed and installed correctly to ensure the auxiliary switch would operate correctly. The current vendor guidance was obtained for determining breaker health and the maintenance procedures were revised to the latest test methods. 10 years. 8 to 12 years. The Vendor Recommend 10 Years and EPRI recommends 10-15 Years for refurbishment. Should we refurbish or replace? It depends on many factors that need to be considered. Follow up: Is a breaker life dictated by end of cycle life or a time based replacement? Yes – 10000 operations is the EOL for that breaker, even if it has not reached 10 years. Additional factors apply. Scotchbrite and alcohol. Silverpolish. SS Fine tootbrush, alchohol and rag. Found anderol only lasts 10-12 years in their environment. For the ABB breakers the users group found that the testing done in labs and industry experience found that the life of anderol is about 12 years. Made the guidance document say that the max frequency is 12 years and the OEM recommends about 10 years. ABB is using cgc77 in leu of anderol grease which is no longer made. SOER 98-02 provides the basis for pre-installation testing FYI The NRC (David Skeen) currently views this as a trendable item and stated that, although it is not required, the trending of reduced voltage test data is “a good idea”. Plants need to take into consideration control circuit voltage drops and battery voltage after 4 hour station blackout periods (if applicable), or whatever is the worst-case expected voltage for each particular breaker. ABB: Do not modify switchgear to perform Thermogaphy. Check with thermography experts to see if a “digitizer” type can be found that looks beyond steel panels. FYI FYI FYI FYI FYI FYI FYI - Breaker Primary Disconnect & Swgr Lead Bushing misalignment. FYI - Silver plating of primary disconnects and primary lead bushing in switchgear (i.e Corroded, Missing Plating, Hardened NO-OX-ID Lubricant) FYI ABB recommends replacing or silver plating all primary disconnects and replacing garner springs during refurbishment of all breakers. Users need to discontinue polishing (Roysen) the primary disconnects while completely assembled. Causes degradation of the garner spring finish which leads to rusting. Users need to inspect the lead bushings during de-energization of bus to check for these conditions. • Sputtering connections, arcing contacts, or pitting • Difficulty in removing and/or rotating the tulip • Dripping or hardening of NO-OX lubricant • Appearance of silver – Not varnished • Discoloration on leads (rainbow effect) or contacts • Whiteness or discoloration of chair molding • Lack of silverplating • Cracked insulation on bus bars • Cracked boots • Arc chute insulation materials flaking • Broken springs on tulips Jim Sharkey – EPRI. HK primary stab and disconnect maintenance (breaker and switchgear) Action Item: Sharkey add info from CD. Action Item: Dave Davis will send out survey of what maintenance plants are performing with regard to primary stab/primary disconnect maintenance. Inspection revealed that the switchgear cubicle shutter cover assembly malfunctioned which caused tulip rubbing that forced the springs to be dislodged. There was no failure or loss of breaker function. Answers 1) Four factors identified • Over time No-ox becomes hard when heated & become an insulator. Current through connection with hardened burnt No-ox causes No-ox to burn away causing sputter. • Old breaker Primary Disconnect springs lessens connection point pressure • Silver loss causing oxidation which increases connection resistance • Improper alignment causing higher connection resistance 2) ABB Inc - Swgr Systems in Lake Mary, FL changed design in 4-18-02: • The 5HK250 & 350, 1200 & 2000 amp primary stabs. Example p/n is #838964A00 & #838964B00 (1200 amp model) and #838965A00 and #838965B00 (2000 amp) • Parts went from a four piece fabricated design to a one piece caste design • New caste design eliminates significance labor (no fab assembly, just silver plating) which allows for quicker turnaround time & less quality problems caused during fabrication • Part is easier to install & remove as new design has a threaded barrel & machined contact surface instead of an inserted nut. The inserted nut has been found to slip when installing or removing which can aggravate the installation / removal. The machined surface gives more contact area for the bus connection along with elevating any problems of loose nut. 3) 5HK250 & 350, 1200 & 2000 amp primary stabs. Example p/n is #83896A01 & #83896A02 (1200 amp model). Age, heat & maintenance (lack there of) are the primary factors in failures Corrective Actions: ● Inspect circuit bkrs prior to connecting to bus ● Stopped use of abrasives such as scotch brite for cleaning terminal connections as detrimental to silver plating ● Use of ground & test truck for measuring good PDA connection to bus. Practice had been taking resistance measurement cube-to-cube / stab-tostab (typical 40 micro-ohm), but through use of test truck to measure through PDA, was finding high resistance connections (typical 1,111 micro-ohm). ● Alternate method used for measuring ckt bkr contact resistance to include PDA ● Explicitly call out inspection & cleaning of bus stabs in procedures ● Heightened awareness of condition of silver plated connection surfaces CONCERN: During investigation 2 bkrs were inspected SAT (PDAs) installed and 3 months later found all 6 PDAs on each bkr with significant overheating damage. Thermography performed during the 3 months did not indicate a hazard (perhaps due to thermography only being at single points in time). ABB: • Bkr only 6 yrs old; PDAs were replaced & swgr stabs checked for alignment From OE: • Installed upgraded design of breaker stab & rosette parts inspected for silver-plating • Procedures revised to address removal of no-ox grease on rosette contact surfaces • Users need to inspect the silver plating of the PDAs on the breakers more closely to check for conditions listed below: -- Corrosion -- Missing plating -- Hardened No-ox -- Burned area (sputtering) • Bkr PDAs should have the garter springs replaced & the finger contacts should be 100% silver plated • No gouges, nicks or sputtering connections shall be present on PDA • Any 5HK350-1200 used in a 60kA fault duty application needs to have 2000 PDAs installed • 3000 amp bkrs get new style garter springs which in some cases changes the finger assemblies All of the station 4 KV breakers are to be replaced with vacuum breakers that do not have or need puffer assemblies. FYI See OE ABB recommendation to replace with ratchet plate with 2 skipped tooth. Cause is slow moving ratchet pawl…grease in wrong location applied inappropriately…spring is probably weak. Breakers are designed for 140vdc so this is not a contributor. ABB Dwg Sheet 191745 • Last year discussed a 1979 CB with original hold pawls pins that were thought to be binding in the carrier causing the holding pawls to not engage quickly enough • The pawls were catching only a fraction of the single missing tooth ratchet plate's tooth, which caused premature wear. Broke one tooth. • ABB has revised pawls & ratchet plate • ABB has issued a preliminary report that indicates the following possible causes: -- Weak ratchet pawl spring -- Dragging of the pawl due to spiral pin & lubricant placement -- Heat treat of ratchet plate has irregular values such that teeth are not as hard as plate itself • ABB recommends to replace pawls & ratchet plate if problem found. DO NOT lubricate on the side of the ratchet pawl. FYI McGuire has purchased some 5VHKX breakers but has not yet installed. SONGS also have breaker replacements. • 5VHK-R250 utilizing the K-Line type mech • Roll-in-Replacement (RIR) for 4.16AMH250 designed by ABB services Inc & qualified by CE Nuclear (now Westinghouse - BNFL) • ABB has decided not to ever supply a 5VHK-R250 or 5VHK-X250 to Nuclear Industry • ABB will supply 5VHK-X350 for any 250 MVA RIR, which uses the K3000 Op Mech Paul Battish - SONGS. Survey of plants with medium voltage vacuum breaker conversions. Lessons learned. OE. Paul believes replacement cost of new HK breaker is equal to roll-in vacuum replacement breaker. Sharkey recommends reviewing EPRI document: “Considerations for Replacement of ….” Rick Sparks has some industry experience to share and did presentation during Siemens-Wyle meeting. TVA had significant issues related to MOC/Cubicle interface (now resolved). ABB reports the VHK does have any reported MOC/cubicle interface problems. McGuire has installed 8 with no problems. FYI FYI SONGS bumps their loads after they roll in a breaker. Occasionally find the issue on their breakers. Surry sees the issue also. Fermi also has seen some of the same problems, and their operators rack the breaker in and out 4-5 times to clean up the (wipe) contacts. They seem to have good reliability. • Secondary Disconnect was not making good contact • Swgr & Bkr side secondary disconnects have been found oxidized and not able to make good connection • Inspections of swgr & bkr sec disc need to be performed to prevent such failures • Clean silver plated copper connection gently with scotchbrite should be done if oxidation is found. CAUTION - these may be energized. • These was an ABB Part 21 (8/1995) for swgr sec disc - cracking of the dielectric material. Paul Zamarripa - Prairie Island. What maintenance performed on secondary disconnects in cubicle and frequency. Note: there is an old part 21 issue (SONGS August 1995). Has had loss of indication (lights) attributed to secondary disconnect. Most plants replaced secondary disconnect assemblies…several plants did find faulty contact fingers. Alignment issues should not occur due to play in secondary contact assembly on breaker. Keith Smith…have you tried bluing to verify contact? Discussion of mounting washers used as spacers. John Layne: TP/OP contacts…make sure screw is tight on phenolic. Paul Battish had similar problem and had to install addition washers on assembly to realign due to settling of switchgear. Keith Smith also cleans contacts with scotch brite during switchgear maintenance. Ron Ferrie cautions to not remove silver plating. Mark McClelland…what is ABB doing to female secondary disconnects during refurb? ABB does not disassembly disconnect…clean faces where they interact with male part with alcohol. Is there No-OX on secondary disconnects? Hatfield says no….these Frequency: Switchgear inspections TXU 3 yrs. STP 5 years. McGuire 5 year FYI During inspection of a 5HK breaker, the spring clip that holds the shutter roller on the breaker was found missing. The roller was still attached to the breaker and did not pose any problem with the operation of the breaker. However, the missing spring clip could have allowed the roller to come off. If this had occurred, the breaker could not be racked onto the bus due to the interference caused by the shutter not being raised high enough. Excessive wear identified on lift rods. Apply light film of mechanical lubricant on lift rod. Perform routine inspections. Shutter nylon hardware becomes brittle with age. Requires inspection and condition based replacement. FYI ABB: Zero tolerance on loss of silver plating. Replace part if any silver plating missing, especially critical at pivot/mating surfaces. FYI Three plants send off to third party for re-plating. None do their own replating. NLI will do it if you tell them the thickness (NLI will replate safety related), Excel Energy Service Company, and Non-Safety: Rockwell commons in Cedar Rapids – They can do anything, but don’t have an Appendix B program. a) Plating thickness on switchgear ranges from 0.00001 - 0.00005 (pre 1978) and 0.000025 - 0.00005 (1978 - now) depending on application. b) Yes for Disconnect & Bushing plating thickness. Lonnie Little - STPEGS. What parts can ABB not re-silver plate? ABB can re-plate any part that has been previously re-plated. During the cleaning process parts may be identified as having damage which will require replacement. Breaker HK lower terminal has a pressed on part, if corrosion is present, ABB recommends not re-plating. David Hatfield did say ABB will re-plate bulk shipments and provide volume discounts. NOTE: ABB will re-plate silver products from any breaker (safety related or not. (Medium Voltage) and K-Line (Low voltage) circuit breakers. In the HK breaker, the spring is used on the racking mechanism to position the racking mechanism interlocking latch. Circuit breakers and spare parts procured from ABB between 04/23/2008 and 02/27/2009 may have suspect springs installed. Initial report of the nonconformance was generated on 02/11/2009 (NCR #68999JL) Given the large number of applications for the affected circuit breakers, ABB (Medium Voltage Service) cannot determine if the potential for a substantial safety hazard exists at any licensee's facility if a similar failure of the tension spring occurs. Licensees are requested to evaluate the history of inspections, maintenance practices, and circuit breaker operating cycles for K-Line breakers, and racking cycles for HK breakers to determine if the circuit breaker spring should be replaced immediately or at the next convenient maintenance opportunity. ABB recommends that any suspect spring with greater than 1,400 operating cycles be replaced as soon as possible. This issue was bounded by specific dates set forth in the Part 21. This is the same spring on the HK Racking mechanism. Gene Langlois – Waukesha (for North Anna). Spring discharge lever in floor of cubicle damaged coupled with settling of floor caused springs to discharge and breaker closing when racked to the disconnect position. FYI during cubicle inspections. Visually inspect strike plate on cubicle floor. ABB modified this part & has not seen any fail but some split open. ABB is not going to do anything to upgrade this part…will continue to find cracked welds and will have to replace these parts. Cracked welds will not cause breaker to fail, however parts will continue to be rejected. ABB has AI to provide applicability for Roundtable notes. Group has AI to begin documenting all of these failed parts and begin submitting info to ABB. FYI - The consensus was that, during overhaul, this should be inspected. ABB recommends that if found, replace. Do not add Anderol 757 or MG28 to the outside (exterior) of this Inner Spring Tube during assembly. If found to have lubricant, then it will need to be removed (part replaced if coating is missing). FYI Waterford, TMI, TVA, and PSEG If rivet can be moved by hand, the entire latch should be replaced per ABB. If not loose, no need to replace. New Trip Latches have welded reset spring return pin. Part 21 issued on 12-2-99 to inspect and replace. Bad batches from back to 1995 due to improper material and/or not heat treated. Mark McClelland: HK problem with failing to close…assumed hand switch…operator issue possibly. Traced problem to L2 switch in another cubicle. Spring clip had come off. Suggests PI might have permissive circuitry problem. PI has verified signal to secondary disconnect. Intermittent problem. References 2005 CBUG Meeting Notes HK Roundtable Issues 1998 HK CBUG Meeting Notes 2000 HK CBUG Powerpoint EPRI "Evaluation of Cracks in ABB HK Arc Chutes" Rev 0 dated 11/13/02. 2001 ABB T&D Discussion Items HK 2001 ABB T&D Discussion Items HK 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable EPRI "Evaluation of Cracks in ABB HK Arc Chutes" Rev 0 dated 11/13/02. 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable EPRI "Evaluation of Cracks in ABB HK Arc Chutes" Rev 0 dated 11/13/02. 2008 CBUG ABB HK Roundtable Notes 2009 CBUG ABB HK Roundtable Notes 2002 ABB Discussion Items HK 2003 CBUG Powerpoint Presentation 2003 CBUG Meeting Notes 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2004 CBUG Meeting Notes, OE 16527 2004 CBUG Meeting Notes, OE 16739 2004 CBUG Meeting Notes, OE 17451 2008 CBUG HK Meeting Notes OE 25399 - Perry - 8/2007 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2006 CBUG Powerpoint Presentation 2007 CBUG Powerpoint Presentation (Modified 2007 by D. Hatfield) 2005 CBUG Meeting Notes HK Roundtable Issues 2001 ABB T&D Discussion Items HK 2001 ABB T&D Discussion Items HK 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2004 CBUG Meeting Notes, OE 16879 2008 CBUG HK Meeting Notes OE 24754 - Prairie Island - 4/2007 OE 25640 (Update to OE 24754) 2000 HK CBUG Powerpoint 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2005 CBUG Meeting Notes Remaining HK Breaker OE NOT Previously Addressed in the ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers 2005 CBUG Meeting Notes HK Roundtable Issues 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2001 ABB T&D Discussion Items HK 2005 CBUG Meeting Notes HK Roundtable Issues 2008 CBUG ABB HK Roundtable Notes 2004 CBUG Meeting Notes, OE 16764 2001 ABB T&D Discussion Items HK 2009 CBUG Handout (reissued) ABB IB 6.2.1.7B Supplement (5/31/00) 2009 CBUG Handout (reissued) ABB IB 6.2.1.7B Supplement (5/31/00) 2000 HK CBUG Powerpoint 2001 ABB T&D Discussion Items HK 2003 CBUG Meeting Notes 2003 CBUG Meeting Notes 2004 CBUG Meeting Notes, OE 16387 2004 CBUG Meeting Notes, OE 18438 2008 CBUG HK Meeting Notes OE 25535 - Prairie Island - 8/2007 2008 CBUG HK Meeting Notes OE 25990 - McGuire - 11/2007 2005 CBUG Meeting Notes HK Roundtable Issues 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2005 CBUG Meeting Notes Remaining HK Breaker OE NOT Previously Addressed in the ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers 1999 HK CBUG Meeting Notes 2002 CBUG Meeting Notes 2003 NMAC "No Intentional Opening" Powerpoint Presentation 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2009 CBUG Handout 2004 CBUG Meeting Notes, OE 18435 1998 HK CBUG Meeting Notes 2003 CBUG Meeting Notes 2005 CBUG Meeting Notes Remaining HK Breaker OE NOT Previously Addressed in the ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers 1999 HK CBUG Issue Notes 2001 CBUG Meeting Notes 2004 CBUG Meeting Notes, OE 17213 2004 CBUG Meeting Notes, OE 17906 2005 CBUG Info collected on HK Primary Stabs Powerpoint - ABB (CBTS) Action / Discussion Items for Type HK Switchgear Maintenance (Part of Powerpoint) 2005 CBUG Info collected on HK Primary Stabs Powerpoint - ABB (CBTS) Action / Discussion Items for Type HK Switchgear Maintenance (Part of Powerpoint) 2003 CBUG Meeting Notes EPRI TR-109642 EPRI 1003087 (Mobil28 Evaluation) EPRI TR-109642 2003 CBUG Meeting Notes 2008 CBUG ABB HK Roundtable Notes 2005 CBUG Meeting Notes HK Roundtable Issues 2004 CBUG Meeting Notes, OE 17796 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2008 CBUG HK Meeting Notes OE 25341 - San Onofre - 7/2007 2007 CBUG Meeting Notes OE24048 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2004 CBUG Meeting Notes, OE 17374 2009 CBUG HK Meeting Notes OE 28777 - Comanche Peak - 3/2009 2006 CBUG Presentation 2009 CBUG HK Meeting Notes OE27451 - Vogtle - 8/2008 2001 CBUG Meeting Notes 2002 CBUG Meeting Notes 1998 HK CBUG Meeting Notes 2001 ABB T&D Discussion Items HK 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2009 CBUG Handout (reissued) 2003 CBUG Meeting Notes 2003 CBUG Meeting Notes ABB MS 3.2.1.9-1 EPRI TR-109642 EPRI TR-109642 EPRI TR-109642 2005 CBUG Info collected on HK Primary Stabs Powerpoint - Waukesha (Gene Langlois) 2005 CBUG Info collected on HK Primary Stabs Powerpoint - ABB (CBTS) Action / Discussion Items for Type HK Switchgear Maintenance (Part of Powerpoint) 2007 CBUG Meeting Notes 2006 CBUG Powerpoint Presentation 2005 CBUG Meeting Notes HK Roundtable Issues 2003 CBUG Meeting Notes 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2008 CBUG HK Meeting Notes OE 26649 - Sequoyah - 3/2008 ABB MS 3.2.1.9-1 EPRI NP-7410-V2P1 Sec 4.0 2008 CBUG ABB HK Roundtable Notes 2009 CBUG ABB HK Roundtable Notes 2009 CBUG ABB HK Roundtable Notes 2008 CBUG ABB HK Roundtable Notes 2009 CBUG Handout (reissued) 1998 HK CBUG Meeting Notes 1998 HK CBUG Meeting Notes EPRI TR-112814 (Reduced Cnl Voltage Testing) 2003 CBUG Meeting Notes 2006 CBUG Powerpoint Presentation 2003 CBUG Powerpoint Presentation 2003 CBUG Powerpoint Presentation 2003 CBUG Powerpoint Presentation 2003 CBUG Powerpoint Presentation 2003 CBUG Powerpoint Presentation 2002 CBUG Powerpoint 2002 ABB Discussion Items HK 2005 CBUG Powerpoint & Failure Analysis Presentation 2002 ABB Discussion Items HK 2003 CBUG Meeting Notes OE 15980 - North Anna - 4/2003 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2009 CBUG HK Meeting Notes OE 28125 - Perry - 12/2008 2005 CBUG Info collected on HK Primary Stabs ABB (Hatfield) response to EPRI email request (07/01/03) for information (Sharkey) on HK Primary Stab Maintenance 2005 CBUG Info collected on HK Primary Stabs ABB (Hatfield) response to EPRI email request (07/01/03) for information (Sharkey) on HK Primary Stab Maintenance (cont.) 2005 CBUG Info collected on HK Primary Stabs Paper on Prairie Island Nuclear Generating Plant 4kV Switchgear Events Following the 3 August 2001 Bus Fire 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2009 CBUG HK Meeting Notes OE 28220 - San Onofre - 11/2008 2002 CBUG Meeting Notes 2005 CBUG Meeting Notes Remaining HK Breaker OE NOT Previously Addressed in the ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers 2005 CBUG Meeting Notes HK Roundtable Issues 2007 CBUG Handout 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) ALSO DISCUSSED IN 2005 HK ROUNDTABLE 2003 CBUG Powerpoint Presentation 2008 CBUG ABB HK Roundtable Notes 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2007 CBUG Powerpoint Presentation OE22305 OE22346 2002 CBUG Meeting Notes 2008 CBUG ABB HK Roundtable Notes 2005 CBUG Meeting Notes ABB Presentation: EPRI Action / Discussion Items HK Circuit Breakers (cont.) 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2006 CBUG Presentation of failure report 2004 CBUG Meeting Notes, OE 16633 1998 HK CBUG Meeting Notes 2001 ABB T&D Discussion Items HK 1998 HK CBUG Meeting Notes 2002 ABB HK S-G Part Rplcmnt Speadsheet 2003 CBUG Meeting Notes 2003 CBUG Document 2003 CBUG Meeting Notes 2003 CBUG Meeting Notes 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2009 CBUG HK Meeting Notes 03/11/2009 (NCR #68999JL) 2009 CBUG ABB HK Roundtable Notes 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable 2005 CBUG Meeting Notes HK Roundtable Issues 2001 CBUG Meeting Notes 2005 CBUG Meeting Notes ABB Product & Service Information Bulletin Notice 2005-2-0002 2002 Duke Breaker Survey Spreadsheet 2003 CBUG Round Table 1999 HK CBUG Meeting Notes 2001 ABB T&D Discussion Items HK 1999 HK CBUG Meeting Notes 2000 HK CBUG Powerpoint 2004 CBUG Meeting Notes, Notes from HK Utility Roundtable