Presentation

advertisement
Grounding and Bonding in
Communications Systems
David Brender, P.E.
Copper Development Association Inc.
david.brender@copperalliance.us
Ennes Workshop
Sacramento, February 23, 2013
©MMXIII
This talk concentrates on:
Interconnection of equipment
Connection to earth
Physics is physics everywhere
1
Grounding and Bonding
Grounding and bonding are fundamental
components of power quality and reliability, and
should be robust before you do anything else
Grounding
Grounding is the intentional connection of the
electrical system to the “earth” or a body that
serves in place of the earth
2
Bonding
Bonding is the intentional interconnection of
normally non-current-carrying parts of electrical
equipment to prevent shock and voltage
differences in the event of a fault
The terms “grounding” and “bonding” are
sometimes used incorrectly and often
interchanged.
Orange County, FL 911 system
Retrofit of existing sites
3
Orange County, FL 911
11 transmitter sites
Orange County, FL 911
Headquarters
Apopka, FL
• Source: Power & System
Innovations, Inc., Orlando
4
Orange County 911 - Apopka
280 foot tower
3 sets of 5 guys
g y
Orange County 911 - Apopka
$100 K/yr. damage at
Apopka alone
5
Orange County 911 System
$1-2 million equipment losses system-wide
/year
Step 1
Staff was not expert in power quality,
called
ll d in
i knowledgeable
k
l d
bl professional
f
i
l
6
3 Independent grounds
un-maintained
elec svc gnd
No connection
guys
60 Ω
coax
firewall
tower
threaded rod
Refitted site
Everything bonded together
7
Throughout The System
Ungrounded equipment cabinets
Facility ground at Apopka
Main electrode was all-thread rod
8
Old Apopka ground rod
Measured 550 ohms
Apopka Tower Grounding
Retrofits:
p (60
( ft))
Deep
electrode
supplements tower
9
Coax Shields
Coax shield bonded to bus,
to electrode system
y
Proper coax shield grounds:
10
New bus on tower
For coax grounds then 4/0 to electrode
Outside Firewall
Only ONE Cu strip connected to electrode
11
Outside Firewall
Strip bonded together and to ring with 4/0
At all Equipment Cabinets
Bond equipment properly
12
Separate Bonding
All equipment bonds brought to buses
Buses tied to halo rings
g
Reedy Creek
Remote repeater
y World
near Disney
13
Reedy Creek
More real estate to work with
Reedy Creek
Grounding layout: double rings plus
deep electrodes
14
Orange County 911 – Reedy Creek
Each rod was
di
driven
deep
d
enough to achieve
< 5 ohms
independently
Orange County 911 – Reedy Creek
Wide, sweeping turns
15
Orange County 911 – Reedy Creek
Replacing connections like this
Orange County 911 – Reedy Creek
Note lock washer, double nuts
16
OC 911
SPD’s on
main service
entrance
OC Experience
• Thousands of events recorded
• One strike witnessed
• NO Downtime! No equipment damage.
17
Major lessons from OC 911
3 different contractors
electrical
•radio room
•tower
No one party had
•responsibility
Major lessons from OC 911
Political control (low bid)
No maintenance
Minimal design
18
Power Quality is CostCost-effective
OC 911:
<$100,000
,
cured $1 million damages
g
6-mos. to 1 year paybacks common
KPTM--TV
KPTM
4800 kW station
Studios in Omaha,, NE
19
KPTM--TV
KPTM
Two 300 ft. towers adjacent to studio
Lightning strikes damaged $1,000’s of
equipment, took station off the air.
KPTM--TV
KPTM
Installed 2 electrodes at 125 foot deep
3-ohm
3
ohm resistance
20
KPTM--TV
KPTM
Inspection well to test resistances
KPTM--TV
KPTM
Satellite dishes were not bonded to studio
21
KPTM--TV
KPTM
Re-bonded all interior and exterior equipment:
Equipment racks
Satellite dishes
Towers
New ground bus
•No damage
•No downtime
after retrofit
Sumter County 911
2004 lightning strike
t k outt entire
took
ti ffacility
ilit
22
Tower had separate grounding
121 foot tower erected in 2007
Separate
p
ground
g
independent
p
from building
g
230 ohms to ground
Building had single galvanized rod
230 ohms
23
Independent grounds
2 emergency generators each had
independent ground
Hose clamp connection
Steel was not grounded
2 transformers were grounded to
building steel, but steel was not
bonded to ground electrode
24
Sumter County 911
Complete renovation of bonding and grounding
•
Removed daisy-chained
y
grounds
g
•
Ground system supplemented and tied
together
•
Building steel bonded to electrode
KKIT - FM
Angel
g Fire,, NM
25
Actual Tower grounding
Proper connection methods?
•KKIT-FM
Actual Connection to ground rod
Proper connection methods?
•KKIT-FM
26
Actual Water pipe bonding
Corrosion and connection errors.
•KKIT-FM
Think of “current divider”
Energy
High R
Low R
27
KPTH - KMEG
1988 ft. tower
Near S. Sioux City, NE
Ufer ground after lightning
28
At tower base
2- 8 ft. ground rods
190 Ω
Ice bridge
#2 AWG connected to same rods
29
Guy wires
Note double U-bolts
Connectors not listed
90° angles
Vibration
Guy grounding
Note right angles
30
Guy grounding
New “listed” tin-plated silicon-bronze
connectors
Parallel to guy wires
Guy grounding
3-80 ft. deep SS rods
250 kcmil to ring
31
Ice bridge
Note rust
Strap has lower impedance
32
Result
One ground system
33
Recommended Practice
Correct corrosion issues
Recommended Practice
Use bolt-in CB’s,
p
not snap-in
34
Inadequate Tower Grounding
Is Ufer EGC actually
bonded to rebar?
Ground wire outside conduit
Proper wiring methods?
35
Separate Neutral and Ground
Improper N-G bonds
Interior Grounding
Look for paint or other insulation
36
After commissioning
Check resistance to earth annually
Under 5 ohms is desirable
Rules
“Radial” bonding
( d
(no
daisy-chains)
i
h i )
37
Interior Grounding
There should be ONE central point connecting
the neutral to the ONE exterior grounding
electrode
e
ect ode syste
system
 Source: Dranetz Field Handbook
Rules
Earth is not a current path, i.e.:
no independent ground paths
38
Rules
No separate grounds – one
grounding system
Desired Grounding
39
Rules
Equipment should be protected
b SPDs
by
SPD
SPD Sizes
Type C
•
150 kA
/mode
Type B
Type A
75 kA
25 kA /mode
40
Takeaways
1. Exceed the Code, but don’t violate the Code!
((Code minimum is one step
p above “illegal”)
g )
2. You don’t get what you expect,
you only get what you inspect.
3. Have a written plan and procedures.
Insist contractors follow it.
3. Get the grounding and bonding right before anything
else. Most lightning and transient problems can be
cured at minimal cost.
FREE PUBLICATIONS or SEMINARS
Visit www.copper.org
• Case histories
• White papers
• Recommendations
• DVDs and CD-ROMs
• All free
• No commercials
• Very informative
41
WE NEED CASE HISTORIES
Highlight good practice or
corrections
No cost to you
We write
You get full editing rights
Please contact me to discuss.
Contact Information
Web site: www.copper.org
david.brender@copperalliance.us
212-251-7206 office
917-297-5738 cell
42
Download