07 71 23 – ROOF SPECIALTIES AND ACCESSORIES PART 1 GENERAL 1.01 A. SECTION INCLUDES (ALTERNATE PROPOSAL ONLY): Provide all Labor, Materials, and Equipment to replace existing roof scuppers, gutters, downspouts, and associated hangers & accessories, if any and as necessary, in order to replace the ACM siding and soffit systems required to be replaced under the Alternate Price Proposal scope of work. Work of this Section includes contractor compliance with all applicable requirements of the following sections of the project specifications: 1) Division 01; 2) Section 02 41 00 – DEMOLITION; 3) 07 71 23 – ROOF SPECIALTIES AND ACCESSORIES 4) 26 00 00 - BASIC ELECTRICAL WORK (if any) 1.02 LOCATIONS OF WORK: Furnish and install new scuppers, gutters, downspouts and accessories on the Hangar Building, in the same locations as existing scuppers, gutters and downspouts. 1.03 RELATED SECTIONS: A. SECTION 02 41 00 – DEMOLITION: Removal of the existing gutters, downspouts, and accessories on three buildings. B. SECTION 07 60 10 – HANGAR BUILDING ACM SIDING AND SOFFIT REPLACEMENT. 1.04 A. APPLICABLE PUBLICATIONS: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. American Society of Testing and Materials (ASTM) A167-99(2009) 5695607 - ALTERNATE Stainless and Heat-Resisting Specification Section 07 71 23,Page 1 Chromium-Nickel Steel Plate, Sheet, and Strips B. B209/209M-14 Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate B221/221M-14 Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes C920-14a Standard Specification for Elastomeric Joint Sealant SHEET METAL AND AIR CONDITIONING CONTRACTORS’ NATIONAL ASSOCIATION (SMACNA): 1120-12, 7th Ed. 1.05 Architectural Sheet Metal Manual SUBMITTALS: Submit the following in accordance with Section 01 33 00: A. CATALOG CUTS: Provide manufacturer’s catalog cuts describing manufactured components used to construct the new scuppers, gutter and downspout system, including accessories. Submit installation instructions. B. SHOP DRAWINGS: Provide detailed shop drawings showing design of proposed scuppers, gutter and downspout system. At a minimum, show the following dimensioned and labeled drawings: 1) Plan, section, and detail drawings of typical arrangements. Show all gutter and downspout locations. a) Locate new gutters and downspouts in the same locations as existing gutters and downspouts. 2) Plan, section, and detail drawings at each unique condition, including but not limited to: splices, transitions, attachments, etc. 3) Relative elevations and all new and existing conditions affecting the designs and installation. 5695607 - ALTERNATE Specification Section 07 71 23,Page 2 PART 2 PRODUCTS 2.01 GENERAL REQUIREMENTS: A. Gutters, downspouts, leaf guards and other accessories shall be manufactured by the same company. B. All materials used installation shall install dissimilar that would lead to C. SERVICE CONDITIONS: All materials and designs used on this project, and/or contractor furnished, shall safely accommodate load combinations and design parameters as required by ASCE 7 and the service conditions and Use Classification indicated in subpart 1.17 of Section 01 10 00. D. COORDINATION WITH OTHER TRADES: Coordinate design and installation details, interface details, specifications, new product colors, and construction installation sequencing with installers of related Sections. E. COLORS OF SCUPPERS, GUTTERS AND DOWNSPOUTS: Colors shall match as close possible to items being replaced. 2.02 A. 2.03 A. in the manufacture and be chemically compatible. Do not metals in contact with each other accelerated corrosion. ROOF GUTTERS (If Any): Match existing in size, profile, and other attributes; except that a U.V. Protected Kynar 500 factory finish shall be provided. In addition to requirements of subpart 2.01C of this Section, roof gutter systems (including attachment and supports) shall support a vertical load of at least 50 plf. DOWNSPOUTS (If Any): Match existing in size, profile, and other attributes; except that a U.V. Protected Kynar 500 factory finish shall be provided. GUTTER WALL STRAPS AND FASTENERS (If Any): Of sufficient size and thickness to safely anchor and support downspouts in accordance with ASCE 7; but in no case less than 22 gage x 1.5 inches wide. Color and finish to match new downspouts. 5695607 - ALTERNATE Specification Section 07 71 23,Page 3 2.04 GUTTER LEAF GUARDS (If Any): Heavy Commercial Grade, Manufactured specifically for use with the gutter size, material, and profile furnished. Leaf Guards furnished shall be low profile, removable, and feature clip-on or hidden fasteners. Leaf Guard fastening system shall be sufficient to secure Leaf Guards under expected coastline wind loads in accordance with ASCE 7. Leaf Guard color to be selected by Contracting Officer from manufacturer’s standard color selection, to match new gutters. 2.05 ACCESSORIES (If Any): Include all accessories for a complete installation, including but not limited to: hangers, support straps, spacers, end caps, outlet tubes, downspout strainers, fasteners, anchors, and aesthetic downspout transition pieces for attachment to underdrain pipes where applicable. A. Screws, rivots, straps, and accessories shall be weather protected and factory finished, with color to match new gutters and downspouts respectively. PART 3 EXECUTION 3.01 SCUPPERS, ROOF GUTTERS, DOWNSPOUTS, AND ACCESSORIES: A. Install scuppers, gutters and downspouts in accordance with manufacturer’s published instructions and the reviewed shop drawings. Only use fasteners and clips specifically recommended for use with the manufactured products being installed on this project. B. Without exception, install new scuppers, gutters, and downspouts in the same locations that existing scuppers, gutters and downspouts are located. C. Secure new manufactured products and accessories adequately to the building in order to safely resist the loadings and service conditions specified in subpart 1.17 of Section 01 10 00. D. Install new downspouts plumb and with reveal to building corners and other building lines. E. Install new gutters and downspouts in straight lines for a professional installation appearance. 5695607 - ALTERNATE constant vertical Specification Section 07 71 23,Page 4 F. Where applicable, connect new downspouts to existing under drain riser pipes using factory finished fittings, manufactured specifically for that purpose, and of the same color as the downspout. END OF SECTION 5695607 - ALTERNATE Specification Section 07 71 23,Page 5