KOMFORT W O R K S P A C E Orbis single glazed - a mullion free crystal clear dry vertical jointed system with square aluminium sections ORBIS Single Glazed Method of Build Komfort Installation Love the space you’re in. June 2012 KOMFORT WORKSPACE Index Section Page No. Contractor / Komfort Installation Responsibilities 1-3 2 Health and Safety 4 3 Tools 5 4 Orbis Exploded Isometric Drawing 6 5 Component Identification 7 6 Pre Build Storage 8 7 Setting Out 9 7 Solid Partition 10 7 Wall Abutment Installation 11 8 Head Channel Installation 12 9 - 10 Base Channel Installation 13 10 - 11 Top Pivot and Fixing Plate Assembly 14 12 15 13 16 14 17 15 18 16 19 17 Straight Crystal Glass to Glass Dry Joints 20 18 90 deg Crystal Glass to Glass Dry Joints 21 19 135 deg Crystal Glass to Glass Dry Joints 22 19 - 20 3 Way Crystal Glass to Glass Dry Joints 23 20 - 21 Head Channel Wedge Seal Installation 24 21 Glass Door Installation 25 22 Timber Door / Timber Door and Overpanel Installation 26 22 Final Inspection and Cleaning 27 22 Personel Notes - 23 for full height glass doors Door Stop and Head Channel Insert Installation for full height glass doors Door Frame Installation for standard height glass and timber doors with glass overpanel Door Frame Installation for full height glass and timber doors Door Frame Cast Lockbox for timber doors Door Frame Striker Plate and Backbox for glass doors ORBIS Single Glazed METHOD OF BUILD page 1 of 23 KOMFORT WORKSPACE 1.0 The Contractor 1.1 Is responsible for the installation of all the solid elevations including all wall abutment finished openings, adaptor posts ensuring that they are plumb to allow the Orbis Head and Base sections to be installed. 1.2 Is responsible to ensure that there are no hidden hazards such as electrical cables and pipes within the abutment areas that the Orbis partitioning system is to be installed. 1.3 Must ensure that the ceiling, floor and all abutment walls are ready for the installation of Orbis 1.4 Due to the handling of glass that the area is free from other trades. 1.5 A clear path, void of obstacles and other trades is made available to allow the unloading and movement of the glass onto the site and through to the build location. 1.6 A defined temporary safe storage area is allocated that will enable all materials and the glass to be stored as detailed in section 4. 2.0 Komfort Surveyor / Installation Team 2.1 The Komfort glass surveyor will attend site and carry out a full survey against the plans supplied by the contractor for the delivery of all materials and installation of the Orbis partitioning system. Any extras to order or alterations after the Komfort surveyor has completed his survey will be subject to a separate quotation, order and installation date. 2.2 The Komfort installation team will attend site and install all Orbis head, base and wall abutment and adapt were required a wall abutment to overcome a existing skirting etc using a 38mm square timber section finished white (excluding adaptor posts as detailed in section 1.1) the glass panels, door frames, glass doors, lock sets and overhead closers. 2.3 Elements that are required to be silicon jointed will be allowed a minimum 48 hours to cure before additional works. 2.4 Manifestation will be applied, should this service be required. 2.5 If manifestation is not being applied, the finished installation will be left with a safety marking applied using tape on each panel to indicate that the glass has been installed. 3.0 The Komfort Contractor 3.1 Will be responsible for the fitting of any timber doors and their furniture after the Komfort glazier has completed his work. 3.2 The Komfort contractor will also be responsible for the cleaning away of any materials not used. 3.3 Komfort contractor complete sign off and acceptance documentation. ORBIS Single Glazed METHOD OF BUILD page 2 of 23 KOMFORT WORKSPACE 4.0 Health and Safety 4.1 Safety is very important therefore site working conditions should be fully observed at all times. 4.2 The use of PPE is essential to avoid injury. 4.3 Many Partitioning products are supplied in their finished state and, in addition to careful handling should be stored in a clean and dry location, protected from accidental damage and inclement weather. 4.4 Pre-finished metal and doors are supplied with suitable protection. They should always be stored under cover, stacked vertically or horizontally on raised support structures. Care should be taken during handling and storing on site to avoid damage and distortion. Lengths of aluminium, steel, plastic or timber components should be laid flat. 4.5 When storing glass on site particular attention should be paid to the following: a) Glass should be stored on its edge on raised support structures; whether it is the short or long edges will be depend on size, substance and availability of space, etc. b) The angle of inclination or lean of the glass should be from three to six degrees from the vertical on static racks with sufficient lateral support to prevent bowing. An angle greater than six degrees will tend to put additional load on the back of the sheets and may cause breakage. c) Glass should be stored in clean, dry and well-ventilated conditions, out of direct sunlight and away from sources of heat. If moisture or condensation is apparent between panes of stacked glass, the panes should be separated immediately and dried thoroughly: otherwise they may stick together or be stained permanently. d) Glass should not be stored in contact with any substance that is harder than itself, eg concrete, stone or ferrous metals. To minimise further the risk of damage or breakage, all support structures should be clad with timber, felt or other relatively soft materials. 4.6 All materials and components should be stored in accordance with the recommendations of the manufacturer or supplier. ORBIS Single Glazed METHOD OF BUILD page 3 of 23 KOMFORT WORKSPACE 5.0 Recommended Tools Listed below is a check list of tools, which are required in the fitting of this partitioning system, but does not include tools required by contractor for installation of a timber door or timber door and overpanel =Chalk Line and or Laser =Claw Hammer =Combination Set Square =Cordless Screw Driver =Driver Extension Piece =Cordless Hammer Drill =No.1 Pozi Screw Driver =No. 2 Pozi Screw Driver =Pencil =Pliers =Plumb Line or Lasar =Pozi Driver Bits =Rubber Mallet =Selection of Files =Selection of High Speed Drills =Set of Allen Keys =Stanley Knife and Blades =SDS 5.5 Masonry Hammer Drill Bit =Spirit Level =Tape Measure =Tin Snips =110 volt Chop Saw (with blades to cut aluminium) =110 volt extension lead * =110 volt Transformer * =110 volt Power Hammer Drill * other equipment =Approved step ladders, trestles or staging =Hoover =Glass Cleaning Materials * Power tools require if Cordless Hammer Drill is not available ORBIS Single Glazed METHOD OF BUILD page 4 of 23 KOMFORT WORKSPACE 6.0 ORBIS single glazed partitioning system Exploded Isometric Note: The following glass to glass joint options are available but not shown 90 degree Joint - 135 degree Joint 3 Way Joint - Silicon Joint 02 l l 01 14 04 l l l 14 l 08 l 05 l 08 l 02 l l l 01 l 03 07 06 l 14 l 09 03 l l 12 07 l 12 11 l l Head / abutment channel - SJ66 Abutment seal - 342 PVCu glazing channel - SJ36 Straight jointing cleat - SJ.JC1 PETg straight glazing joint - SJ90 Aluminium door frame - SJ65 Door frame seal - PSQ21 ORBIS Single Glazed METHOD OF BUILD l l 06 13 Crystal clear dry jointed system with square aluminium sections 01 02 03 04 05 06 07 l 10 08 09 10 11 12 13 14 10mm / 12mm toughened safety glass 10mm / 12mm toughened safety glass door Base channel - SJ2 Base channel leg - SJ3 Glazing bead - SJ11 / SJ12 Glass packer Glass glazing gasket - SJ73 / SJ74 page 5 of 23 KOMFORT WORKSPACE 7.0 Component Identification Aluminium Vertical & Horizontal Sections PROFILE CODE SJ66 SJ2 SJ3 DESCRIPTION Glazing Sections PROFILE Head Channel CODE SJ65 SJ67 DESCRIPTION SJ11 4mm dia Base Channel Gasket SJ12 5mm dia Base Channel Gasket SJ36 Door Frame Glazing Channel SJ73 10mm Glass Glazing Gasket SJ74 12mm Glass Glazing Gasket Base Channel Base Channel Leg Door Frame Components PROFILE CODE DESCRIPTION Door Frame Door Frame Base Bracket SJ68 Cast Lockbox Fixing Bracket SJ64 Head Channel Insert use with frameless full height glass doors SJ90/10 10mm Glass Straight Joint SJ90/12 12mm Glass Straight Joint SJ91/10 10mm Glass 90o Corner Joint SJ91/12 12mm Glass 90o Corner Joint SJ92/10 10mm Glass 135o Corner Joint SJ92/12 12mm Glass 135o Corner Joint SJ93/10 10mm Glass 3 Way Corner Joint SJ93/12 12mm Glass 3 Way Corner Joint Miscellaneous Items PROFILE CODE DESCRIPTION Top Pivot & Fixing Plate Kit 586LRG 812L PSQ21 Cast Lockbox / Striker use with timber doors Door Frame Cleat LMSJ22PK 342 SJORDS ORBIS Single Glazed includes ADGS - striker plate. ADGSBB - backbox ADG/S - screws Door Stop use with frameless full height glass doors METHOD OF BUILD Head Channel Abutment Foam SJ.JC1 Straight Joint Cleat for SJ66 Head Channel SJ.JC2 90 deg Joint Cleat for SJ66 Head Channel SJ.JC3 135 deg Joint Cleat for SJ66 Head Channel Door Frame Gasket GDS Striker & Back Box Kit use with glass doors SJAGD includes LMSJ 22 - pivot plate LM SJ23 - fixing plate M6 cap screws SILICONTHN Translucent Silicon Sealant For glass door furniture (ironmongery) see seperate component data sheet page 6 of 23 KOMFORT WORKSPACE 8.0 Pre Build Storage 8.1 Before commencing the building of the Orbis single glazed frame work you are requested to identify with the aid of the component identification sheet all materials detailed below that have been delivered with the aluminium sections and carefully store in a clean, dry location until they required. 8.2 Single glazed materials are; SJ11 - 4mm dia Glazing Base Channel Gasket SJ12 - 5mm dia Glazing Base Channel Gasket SJ36 - Door Frame Glazing Channel Gasket (black) SJ73 - 10mm Glass Glazing Gasket SJ74 - 12mm Glass Glazing Gasket SJ90 - Straight Dry Joint SJ91 - 90 deg Dry Joint SJ92 - 135 deg Dry Joint SJ93 - 3 Way Dry Joint PSQ21 - Door Gasket Note: Any missing or damaged materials could effect completion by the Komfort installation team and will be invoiced for all replacements. 9.0 Setting Out 9.1 Set out the partitioning run including position of all junctions and doorway centre lines on the ceiling and using a plumb line or laser mirror the setting out on the floor. Alternatively set out the run on the floor and transfer to the ceiling using the same method. 9.2 Set the position of the doorways out by using the information and dimensions given on details contained in sections 13a to 13c or on technical junction drawings available on the web site www.komfort.com. No. 26003 - for code: SJ65 aluminium frame with glass door No. 26006 - for code: SJ65 aluminium frame with timber door No. 26015 - for glass door without door frame 10.0 Solid Partiton 10.1 The contractor installs the partitions solid elevation (stud and plasterboard) as normal using the Head Channel (code: 821) for 75mm system or (code: 825) for 100mm system ensuring that along the length of the head channel abutment face has two strips of the foam seal (code: 342) installed 6mm in from each edge and that the channel is securely fixed at 600mm centres according to the systems method of build requirement. ORBIS Single Glazed METHOD OF BUILD page 7 of 23 KOMFORT WORKSPACE 11.0 Wall Abutment 11.1 The prepared opening should be a finished wall, free of any obstacles such as skirting or trunking or have been installed by the contractor with a Komfort adaptor post as detailed in section 1.1. 11.2 If Orbis is to be installed against a wall that has an existing skirting or trucking protrusion that is no greater than 38mm in depth then the (code: STD 939) White Timber Abutment section is to be used. 11.3 Should the wall abutment protrusion be greater than 38mm then the contractor must be informed that it is their responsibility to take all the appropriate action to build around what ever it is, and provide a full finished section that the Orbis system can be installed against. 342 Foam Seal l 65 50 l 11.4 The following method of installation should be undertaken when installing a Orbis wall abutment that requires the addition of the (code: STD 939) White Timber Abutment. 11.5 Measure the floor to ceiling height as close as possible to were the abutment timber is to be installed and then cut to the length required. 11.6 Hold the timber against the skirting or trucking profile and using a pencil mark the location of the area to be cut out. 11.7 To establish the shape of the cut out use either a Forge Steel Profile Gauge to provide the outline shape or carefull measurment the shape directly onto the timber abutment before carefully cutting out. 11.8 Apply 2 No. strips of (code: 342) Foam Seal to the wall abutment face 6mm in from each edge along the total length that includes the cutout profile. 600 centres Pilot Holes then at 600 centres STD 939 White Abutment Timber Existing Skirting Obstacle maximum thickness 38mm SJ66 Head / Abutment Channel or SJ2 Base Channel 11.9 To avoid splitting the abutment timber we strongly recommend pilot hole in the centre face of the timber that will be covered by (code: SJ66) alumimium Channel 50mm in from the top and the bottom than at a first and last holes, then using (code: 311) No.8 x 38mm long screw and plastic plugs (if required) screw the abutment timber to the wall. 11.10 The Orbis (code: SJ66) Head / Abutment Channel or when required (code: SJ 2) Base Channel can now be installed as after pilot hole drilling the first and last holes 65mm in from each end than at a maximum 600mm centres along the length. Orbis Single Glazed METHOD OF BUILD page 8 of 23 KOMFORT WORKSPACE 12.0 Head Channel Ceiling Tile 12.2 12.3 12.4 821 or 825 Komfire Head Channel Unwrap and check that the head channel is undamaged and trim each end or cut to length required ensuring the cut is clean and square without burrs. Establish the office face line of the proposed head channel (code: SJ66) to the office frontage and cut the head section to length as shown on detail 1. The head channel should be screw fixed to the ceiling at a maximum 600mm centres using (code: 311) No.8 x 38mm long screw. SJ66 Head Channel Face Line 12.1 Fixing batten above the ceiling tile detail.1 Prepare the (code: SJ66) head channel for the front (corridor) runs by establishing from the setting out the intersecting partitioning cross wall run location to meet the frontage glass panels and mark the centre line of the intersection to enable the notching of the head channel as shown in detail. 2 SJ66 Head Channel optional SJ4 or SJ45 Adaptor Post Plasterboard detail.2 Using the ‘V’ groove in the inside along the centre of the head channel (code: SJ66) drill the fixing clearance holes using a 4mm diameter drill at 600mm centres starting a maximum 50mm in from each end. Care must be taken not touch the open face edges of the head channel with the drill chuck and that no burrs are left that will prevent the channel from sitting flat to the abutting surface. centre line ‘V’ groove 342 Foam Seal It is recommended the holes are in line along the length of the section. 12.5 After notching and pre drilling the head channel apply along the length of the abutment face two strips of (code: 342) foam appropriately 6mm in from each edge. 12.6 If full height glass doors are to be installed then prior to fixing the head channel (code: SJ66) into position it is important to ensure that the Top Pivot (code: LMSJ22) and Fixing Plate (code: LMSJ23) assembly is inserted into the grove provided within the head channel as detailed in section 14.0 Warning: the Top Pivot Assembly cannot be installed retrospectively after installation of the head channel 12.7 Utilise according to the requirement the steel jointing cleats into the ends of the head channel. 50 max 342 Foam Seal 342 Foam Seal fixing clearance hole 50 max fixing clearance hole 50 max SJ.JC1 Straight Joint Cleat ORBIS Single Glazed METHOD OF BUILD 50 max 342 Foam Seal fixing clearance hole SJ.JC3 135 degJoint Cleat SJ.JC2 90 deg Joint Cleat page 9 of 23 KOMFORT WORKSPACE 342 Foam Seal The horizontal to vertical is a straight cut for butt joint as shown in detail.3 It is important to ensure that there are no burrs and that the first fixing position is a maximum 50mm from each end. 12.8 12.9 If required, acoustic sealant (code: 924) may be applied to the abutment face of the head channel between the foam strips. The sealant should be applied to ensure fully acoustic certificated performance. detail.3 Fix the head / abutment channel using suitable screws and rawplugs (if required) using the pre-drilled holes as detailed in section 14.3 to the ceiling or soffit. Note: a) It is important that there is a screw fixing within 50mm either side of all joints. b) Do not use drywall screws. 13.0 Base Channel 13.1 Unwrap and check that the base channel is undamaged and trim each end or cut to length required ensuring the cut is clean and square without burrs. 13.2 Plumb down from the head to establish the position of the base channel body (code: SJ2). 13.3 Establish from the specification the size of door being supplied (if on site double check by measureing, then set the position of the door frame out as follows: a) For SJ65 door frame with a glass door dimension ‘C’ is the distance between the base tracks which equals dimension ‘X’ the door width plus 72mm. SJ65 Door Frame afj=u=Z SJ2 / SJ3 Base Channel Glass Door Width see specification 32 4 4 32 afj=`=Z Overall Door Frame Width (distance between SJ2 / SJ3 base channel) b) For SJ65 door frame with a timber door dimension ‘C’ is the distance between the base tracks which equals dimension ‘X’ the door width plus 69mm. SJ65 Door Frame SJ2 / SJ3 Base Channel afj=u=Z Timber Door Width see specification 32 2.5 2.5 32 afj=`=Z Overall Door Frame Width (distance between SJ2 / SJ3 base channel) ORBIS Single Glazed METHOD OF BUILD page 10 of 23 KOMFORT WORKSPACE c) For glass door without a door frame dimension ‘C’ is the distance between the base tracks which equals dimension ‘X’ the door width plus 8mm. afj=u=Z SJ2 / SJ3 Base Channel 4 Glass Door Width see specification 4 afj=`=Z Overall Door Frame Width (distance between SJ2 / SJ3 base channel) 13.4 13.5 13.6 Prepare the base channel for the front (corridor) runs by establishing from the setting out the intersecting partitioning cross wall run location to meet the frontage glass panels and mark the centre line of the intersection to enable the notching of the base channel as shown in detail.4 25 Along the centre of each glazing pocked in the base channel (code: SJ2) drill the fixing clearance holes using 4mm diameter drill at 600mm centres starting a maximum 50mm in from each end. It is recommended the holes are in line along the length of the section. The base channel should be installed so that the removable leg will be positioned on the office side of a corridor run. 10 detail.4 drill holes between pips this face to the corridor side 13.7 If required, acoustic sealant (code: 924) may be applied between the pips on each side of the base channel. The sealant should be applied to ensure fully certificated performance. 13.8 Fix the base channel using (code: 311) No.8 x 38mm long screws and rawplugs (if required) using the pre-drilled holes as detailed in section 13.5 to the floor. Note: a) It is important that there is a screw fixing within 50mm either side of all joints. b) Do not use drywall screws. 13.9 The Komfort glazier will install the glass, the Orbis door frames, glass doors and carry out all the silicon jointing when and if required between the glass panes. 13.10 The Partitioning Contractor is responsible for the installation of all timber veneered or laminated doors. ORBIS Single Glazed METHOD OF BUILD page 11 of 23 KOMFORT WORKSPACE 14.0 Installation of Top Pivot and Fixing Plate Assembly for use with full height glass door 14.1 Loosely fix (codes: LMSJ22 & LMSJ23) Top Pivot and Fixing Plate together using the 2 No. M6 x 16 long countersunk socket head screws. Do not tighten at this stage. 14.2 Slide the Top Pivot assembly into the head track before the head track is fitted into position. M6 x 16 Countersunk socket head screw WARNING The Top Pivot assembly must be inserted into the head channel before the head channel is fitted into place. The pivot cannot be fitted once the head channel has been installed. 14.3 Fit the head track into position, ensuring that the pivot does not slide out and can slide freely and is unobstructed by the head fixings. 14.4 Once the head track is fitted, slide the Top Pivot assembly into position. The pivot pin is offset on its mounting plate. Ensure that the gap between the centre of the pivot and the edge of the glass or wall abutment is 65mm. You will need to position the top pivot assembly so that the 45mm side is closest to the glass screen edge. SJ66 Head Channel LMSJ23 Fixing Plate M6 x 16 Countersunk socket head screw 45mm LMSJ22 Top Pivot 65mm 10mm or 12mm Toughened glass LMSJ23 Fixing Plate LMSJ22 Top Pivot M6 x 16 Screw LMSJ22PK Complete Kit Supplied M6 x 16 Screw 14.5 Holding the setting out template against the pivot swing it up-ward over the glass edge. Then ensuring that the template is tight against both the pivot and the glass, and using the allen key provided tighten the outer clamping screw before removing the template. Finally tighten the inner clamping screw. 14.6 Wipe down with a clean cloth to remove any finger marks etc. 14.7 The pivot is now ready to receive the top mounted pivot fitting that has been assembled on to the glass door. ORBIS Single Glazed METHOD OF BUILD LMSJ23 Fixing Plate LMSJ22 Top Pivot Top Pivot Template postion against the pivot and swing up-wards over the glass. page 12 of 23 KOMFORT WORKSPACE 15.0 Installation of Door Stop and Head Channel Insert for use with full height glass door 15.1 The installation of both the (code: SJORDS) Door Stop and the (code: SJ64) Head Channel Insert are best carried out after the installation of the full height glass door. 15.2 Insert the door stop into the head channel and subject to the handing required positioned in one side of the joining cleat groove 5mm in from the installed glazed screen opening door side. 15.3 Using the holes in the door stop as a template carefully drill 2 No. 3mm diameter pilot holes in the head channel and secure the door stop using the 2 No. (code: 301) No. 6 x 8 long pozi pan head screws provided. SJORDS Door Stop 301 No. 6 x 8mm Pan head screw 3.5 44 SJ64 Head Channel Insert 15.4 To obtain the length of the (code; SJ64) head channel insert, measure the distance between the edge of the glass screen and the top pivot plate and deduct a maximum 2mm. 15.5 Offering the insert against the head channel, use a pencil to mark the position of the door stop. 15.6 Then using tin snips notch the head channel insert as detailed above to allow for the door stop making sure that there are no sharp or ragged edges. Complete Door Stop and Head Channel Insert Installation 15.7 Insert in notched channel into the head channel so that the gap between insert and the top pivot plate is a maximum 1.5mm 1.5 maximum gap 15.8 Wipe down with a clean cloth to remove any finger marks etc. ORBIS Single Glazed METHOD OF BUILD page 13 of 23 KOMFORT WORKSPACE 16.0 Installation of SJ65 Doorframe for use with standard height glass and timber doors with glass overpanel 16.1 The door frame to be installed is suitable for use with a glass or timber door that is to have a glass overpanel fitted above the door frame. 16.2 If the door frame is to be installed with a single glass module either or a single glass module to one side then the door frame can only be installed after the glass side panels have been fitted. 16.3 Unwrap and check that the door frame is undamaged, that it is the correct width, height, handing and a) for a glass door the door frame closing leg has been milled for installation of the (code: SJAGD) Striker Plate and Backbox as detailed in section 19. b) for a timber door the frame has been fitted with Lift Off Steel Hinges and that the closing leg has been milled for installation of the (code: 586LRG) Cast Lockbox as detailed in section 18. 16.4 After establishing the actual door height measure from the inside mitre down and cut the door frame legs to suit. A further 1mm to the height is automatically added when fitting the (code: SJ67) Door Frame Base Fixing Bracket. 16.5 Assembly the door frame head and legs using the (code: 812L) Door Frame Cleats. 16.6 Slide the base fixing bracket into the bottom of the door frame extrusion and tape in place (if required). 16.7 Once the frame is in the required position check that the distance between the underside of the door head and the finished floor level are correct. 16.8 Ensure the door frame head is level and the frame legs are plumb in both vertical plains before securing the bottom of the door frame using (code: 311) No.8 x 38mm long countersunk screws and rawplugs (if required). 812L Steel Mitre Cleat SJ65 Aluminium Door Frame 311 No. 8 x 38 long countersunk screws SJ65 Aluminium Door Frame SJ67 concealed fixing detail if door frame base bracket is first inserted into the door frame screws installed after frame has been postioned ORBIS Single Glazed METHOD OF BUILD SJ67 exposed base bracket fixed to floor allowing door frame to be installed over the bracket which is then hidden by the carpet page 14 of 23 KOMFORT WORKSPACE 812L Steel Mitre Cleat STD921 Timber Insert 17.0 Installation of SJ65 Doorframe for use with full height glass and timber doors 17.1 The door frame to be installed under the head track is suitable for use with a glass or timber full height door and will require (code: STD921) Timber Insert fitted internally between the head track and the head of the door frame 17.2 If the door frame is to be installed with a single glass module either side or a single glass module to one side then the door frame can only be installed after the glass side panels have been fitted. 17.3 Unwrap and check that the door frame is undamaged, that it is the correct width, height, handing and a) for a glass door the door frame closing leg has been milled for installation of the (code: SJAGD) Striker Plate and Backbox as detailed in section 19. SJ65 Aluminium Door Frame 26 No. 10 x 75 long countersunk screws b) for a timber door the frame has been fitted with Lift Off Steel Hinges and that the closing leg has been milled for installation of the (code: 586LRG) Cast Lockbox as detailed in section 18. equally spaced 17.4 After establishing the actual door height measure from the inside mitre down and cut the door frame legs to suit. A further 1mm to the height is automatically added when fitting the (code: SJ67) Door Frame Base Fixing Bracket. 17.5 Using a 4mm dia drill pilot hole the aluminium door frame head and timber insert (minimum 3 No.for single and 5 no. for double doors) per the above detail 17.6 Assembly the door frame head and legs using the (code: 812L) Door Frame Cleats. 17.7 Slide the base fixing bracket into the bottom of the door frame extrusion and tape in place (if required). 17.8 17.9 Once the frame is in the required position check that the distance between the underside of the door head and the finished floor level are correct. Ensure the door frame head is level and the frame legs are plumb in both vertical plains before securing the bottom of the door frame using screws installed (code: 311) No.8 x 38mm after frame has long countersunk screws been postioned and rawplugs (if required) and fix the door frame head using (code: 318) No.10 x 50mm long countersunk screws and rawplugs (if required). ORBIS Single Glazed METHOD OF BUILD 75 max from inside mitre 311 No. 8 x 38 long countersunk screws SJ65 Aluminium Door Frame SJ67 concealed fixing detail if door frame base bracket is first inserted into the door frame SJ67 exposed base bracket fixed to floor allowing door frame to be installed over the bracket which is then hidden by the carpet page 15 of 23 KOMFORT WORKSPACE 18.0 Cast Lockbox / Striker installation into SJ65 aluminium door frame for use with timber door 18.1 The door frame should have been supplied with the lockbox already installed, however if it has not and providing the frame has been machined then follow stages 18.2 to 18.9. 18.2 The (code: SJ68) Cast Lockbox Fixing Plate must be installed into the door frame and held in position by the (code 586LRG) Cast Lockbox / Striker before installation of the door frame assembly. 18.3 Offer the (code: 586LRG) Cast Lockbox in place and check that the milling detail is correct for both depth and profile. Then put carefully to one side. SJ68 Cast Lockbox Fixing Plate 18.4 Insert the (code: SJ68) Cast Lockbox Fixing Plate into the aluminium door frame and slide in position so that the top and bottom of the Fixing Plate is positioned equally behind the Cast Lockbox milling. 18.5 Place the Cast Lockbox in position and using the top and bottom holes in the box as a template drill 2 No. 2.8mm diameter holes in the Cast Lockbox Fixing Plate. 18.6 Care must be taken not touch the open face edges of the Lockbox with the drill chuck. SJ65 Aluminium Door Frame 586LRG Cast Lockbox / Striker 18.7 Without removing the Cast Lockbox check that the holes are in align and screw fix in place using (code: 301) 2 No. No.6 x 8mm pozi head screws, but do not fully tighten. 18.8 Check that the Cast Lockbox / Striker is correctly positioned within the milled profile and fully tighten the screws ensuring and that they are flat against the internal face. 18.9 The door frame striker leg can now be used to complete the door frame assembly for use with standard height timber door as detailed in section 16. or for full height timber doors or door and overpanel timber door set as detailed in section 17. 301 No. 6 x 8 long pan head screws ORBIS Single Glazed METHOD OF BUILD page 16 of 23 KOMFORT WORKSPACE 19.0 Striker Plate and Backbox installation into SJ65 aluminium door frame for use with glass door SJAGD - Kit Components 19.1 The door frame should have been supplied with the lockbox already installed, however if it has not and providing the frame has been machined then follow stages 19.2 to 19.8. 19.2 Before fitting the striker plate and backbox check that the door gaps between the door and the door frame are equal on each side of the door. 19.3 Offer the striker plate in place and check that the milling detail is correct for both depth and profile. 19.4 Using the striker plate as a template drill 2 No. 2.8mm diameter holes. 19.5 Place the backbox and striker plate in postion and insert the 2 No. No.6 x 10mm pozi flange head screw provided, but do not fully tighten. 19.6 Check that the backbox and striker plate are correctly postioned and fully tighten the screws. 19.7 Close the door so that the latch / lock engage and check that there is no door rattle. 19.8 To eliminate an rattling of the door in the frame adjust the internal tab until eliminated. 1 No. AGDS - Stainless Steel Striker Plate 1 No. AGDBB - Back Box 2 No. AGD/S - No. 6 x 10mm Pozi Flange Head Screws SJ36 Glazing Gasket SJ37 Door Seal SJ65 Door Frame AGDSBB Back Box AGDS Stainless Steel Striker Plate ADG/S No.6 x 10mm Pozi Flange Head Screw Adjustable Tab ORBIS Single Glazed METHOD OF BUILD page 17 of 23 KOMFORT WORKSPACE 20.0 Straight Crystal Dry Joint Installation (code: SJ90) 20.1 Glass panels to be smoothed (polished) and a small bevel applied to the two vertical edges during manufacture. 20.2 Before proceeding with the glass insulation check that the glass supplied is within the height limitations and that the crystal joints are correct for the glass thickness. a) 10mm thick glass to a maximum height of 2700mm. b) 12mm thick glass to a maximum height of 3000mm. 20.3 Install the first glazed panel ensuring that it has the recommended 12mm edge cover when installed into the abutment channel and that it is level and the leading edge is plumb, The leading vertical edge should then be cleaned to remove dust and grease. 20.4 Straight crystal joint glass to glass section is designed to grip as it is pushed onto the glass and therefore has no need for an adhesive tape. 20.5 Cut the (code: SJ90) Straight crystal dry joint profile to a length that will allow it to tuck into both Orbis aluminium head and base channels. Clean up the cut ends and using a soft clean cloth remove all site dirt / dust along the length of material. 20.6 Starting at the head channel slightly tuck joint section onto the head channel and at the same time over the edge of the glass, then working downwards push the section in place ensuring that it ends tucking slightly into the base section. vertical edges to be plumb 20.7 20.8 Install the next panel of glass in close proximity and careful level so the vertical edges are plumb and that the glass to glass butt joint either side of the crystal joint is parallel. ensure edge is clean Slide SJ90/10 for 10mm thick glass SJ90/12 for 12mm thick glass Both vertical edges should be cleaned to remove dust and grease before sliding the glass panel into the joint already installed on the first glass panel. 20.9 Repeat steps 20.4 to 20.8 until the glazed run is completed. 20.10 Install the base channel leg to the inside of the office area and than subject to the glass thickness install either (code: SJ11 or SJ12) Base Channel Gasket both sides of the glass. SJ2 Base Channel 10 edge cover SJ11 or SJ12 Base Channel Gasket SJ3 Base Channel Leg (best installed on the inside of the office) floor glass packer SJ11 - 4mm diameter gasket suitable for use with 12mm thick glass SJ12 - 5mm diameter gasket suitable for use with 10mm thick glass ORBIS Single Glazed METHOD OF BUILD page 18 of 23 KOMFORT WORKSPACE 21.0 90 degree Crystal Dry Joint Installation (code: SJ91) 21.1 90 degree crystal joint glass to glass section is designed to be installed between glass panels that have a flat smooth (polished) and a small bevel applied to the two vertical edges when manufactured. 21.2 Cut the (code: SJ91) 90 degree crystal dry joint profile to a length that will allow it to tuck into both Orbis aluminium head and base channels. Clean up the cut ends and using a soft clean cloth remove all site dirt / dust along the length of material. 21.3 Peel the red protective tape, approximately 150mm exposing the glue surface on the face to be bonded to the glass edge. Holding the exposed glue surface close to the glass and tucking slightly into the head channel carefully align with the glass flat edge between the bevelled edges before lightly pressing in place. 21.4 Then working downwards gradually peel away the red strip a portion at a time which will help to avoid the adhesive sticking prematurely to the glass, but at the same time allow you to align the profile in position before pressing in place. 21.5 Once the 90 degree joint has been bonded to the glass leading edge the next panel that forms the 90 degree corner can be installed in close proximity. Carefully level so the vertical edges are plumb and that the glass to glass joint each side of the crystal joint is parallel. 21.6 Both vertical edges should be cleaned to remove dust and grease before sliding the glass panel into the 90 degree joint already installed. 21.7 21.8 21.9 21.10 ensure edge is clean Slide The next stage is best carried out by two operatives, with one holding the first glass panel that has been fitted with the 90 degree joint. This will allow the second operative to slowly shuffled the glass panel onto the joint and ensure good edge contact within the 90 degree crystal joint. SJ91/10 for 10mm thick glass SJ91/12 for 12mm thick glass adhesive tape Using a spirit or lazar level check that the corner joint is plumb in both vertical plains and adjust if required. Complete the glass installation straight run as required either side of the 90 deg corner following section 20.4 to 20.9 until the run is completed. SJ2 Base Channel 10 edge cover SJ11 or SJ12 Base Channel Gasket SJ3 Base Channel Leg (best installed on the inside of the office) floor glass packer Install the base channel leg and gasket as detailed in section 20.10 22.0 135 degree Crystal Dry Joint Installation (code: SJ92) 22.1 135 degree crystal joint glass to glass section is designed to be installed between glass panels that have a flat smooth (polished) and a small bevel applied to the two vertical edges when manufactured. 22.2 Cut the (code: SJ92) 135 degree crystal dry joint profile to a length that will allow it to tuck into both Orbis aluminium head and base channels. Clean up the cut ends and using a soft clean cloth remove all site dirt / dust along the length of material. ORBIS Single Glazed METHOD OF BUILD page 19 of 23 KOMFORT WORKSPACE 22.3 Peel the red protective tape, approximately 150mm exposing the glue surface on the face to be bonded to the glass edge. Holding the exposed glue surface close to the glass and tucking slightly into the head channel carefully align with the glass flat edge between the bevelled edges before lightly pressing in place. 22.4 Then working downwards gradually peel away the red strip a portion at a time which will help to avoid the adhesive sticking prematurely to the glass, but at the same time allow you to align the profile in position before pressing in place. 22.5 Once the 135 degree joint has been bonded to the glass leading edge do not remove the outer protective tape. Install the next panel of 135 degree joint and making sure that it is level / plumb and that the glass to glass butt joint either side of the joint is parallel. 22.6 Then sliding the glass panel away from the 135 degree joint far enough that will allow you to clean the new glass panel edge and the peel away the outer joint adhesive protection tape. 22.7 The next stage is best carried out by two operatives, with one holding the first glass panel that has been fitted with the 135 degree joint. This will allow the second operative to slowly shuffled the glass panel onto the joint and ensure good edge contact within the 135 degree crystal joint. 22.8 22.9 Using a spirit or lazar level check that the corner joint is plumb and adjust if required. Complete the glass installation straight run as required either side of the 135 deg corner following section 20.4 to 20.9 until the run is completed. ensure edge is clean Slide adhesive tape SJ92/10 for 10mm thick glass SJ92/12 for 12mm thick glass SJ2 Base Channel SJ11 or SJ12 Base Channel Gasket 10 edge cover SJ3 Base Channel Leg (best installed on the inside of the office) floor glass packer 22.10 Install the base channel leg and gasket as detailed in section 20.10 23.0 3 Way Crystal Dry Joint Installation (code: SJ93) 23.1 3 Way crystal joint glass to glass section is designed to be installed between glass panels that have a flat smooth (polished) and a small bevel applied to the two vertical edges when manufactured. 23.2 Cut the (code: SJ93) 3 way junction dry joint profile to a length that will allow it to tuck into both Orbis aluminium head and base channels. Clean up the cut ends and using a soft clean cloth remove all site dirt / dust along the length of material. 23.3 We recommend that the 3 way junction section is first bonded to the glass dividing wall. 23.4 Peel the red protective tape, approximately 150mm exposing the glue surface on the face to be bonded to the glass edge. Holding the exposed glue surface close to the glass and tucking slightly into the head channel carefully align with the glass flat edge between the bevelled edges before lightly pressing in place. 23.5 Then working downwards gradually peel away the red strip a portion at a time which will help to avoid the adhesive sticking prematurely to the glass, but at the same time allow you to align the profile in position before pressing in place. ORBIS Single Glazed METHOD OF BUILD page 20 of 23 KOMFORT WORKSPACE 23.6 23.7 Once the 3 way junction joint has been bonded to the glass leading edge one of the panels that form the front of the 3 way junction can be installed in close proximity. Carefully level so the vertical edges are plumb and cleaned to remove dust and grease The next stage is best carried out by two operatives, with one holding the glass dividing panel that has been fitted with the 3 way joint. This will allow the second operative to slowly shuffled the glass panel onto the joint and ensure good edge contact within the 3 way crystal joint. SJ93/10 for 10mm thick glass SJ93/12 for 12mm thick glass glazed dividing wall adhesive tape glazed office front Slide Slide ensure edge is clean vertical edges to be plumb 23.8 The section glass panel the completes the 3 way junction can now be installed by repeating section 23.6 and 23.7. 23.9 Using a spirit or lazar level check that the 3 way joint is plumb in both vertical plains and adjust if required. 23.10 23.11 Complete the glass installation straight run as required either side of the 3 way junction following section 20.4 to 20.9 until the run is completed. SJ2 Base Channel SJ11 or SJ12 Base Channel Gasket SJ3 Base Channel Leg (best installed on the inside of the office) 10 edge cover floor glass packer Install the base channel leg as detailed in section 20.10 24.0 Head Channel Wedge Seal Installation (code: SJ73 and SJ74) 24.1 The glazing gasket is best installed by two operatives, one each side of the glazed screen. 24.2 Select the head channel wedge gaskets subject to the glass thickness install either (code: SJ73 or SJ74) Glass Glazing Gasket both sides of the glass. SJ73 - suitable for use with 10mm thick glass SJ74 - suitable for use with 12mm thick glass SJ66 Head / Abutment Channel SJ73 or SJ74 Glass Glazing Gasket 24.3 From the coil of the gasket provided reel off enough of the material to cover the length of the glazed screen and carefully lay along side the screen, 24.4 Starting in the middle of the run and working in the same direction from both sides insert the gasket until install leaving a small amount hanging loose. Do not completely install or cut to fit the first half of the run. 24.5 The second half of the run in the opposite direction should now be installed, again leaving a small amount hanging loose. 24.6 All other glazed runs should now have the gasket installed following section 24.2 to 24.5 until completed. 24.7 Return to the first glazed screen run (having given time for any seal Shrink back) and complete the installation by trimming the small loose gasket at each end to length and pushing in place. Now complete the remainder of the screen runs in the same order the gasket has been installed. ORBIS Single Glazed METHOD OF BUILD page 21 of 23 KOMFORT WORKSPACE 25.0 Glass Door Installation 25.1 Due to the complexity of the range patch pivots, patch hinges, patch locks and ‘D’ handle door furniture available the installation instruction have been produced on separate data sheets which can be found on our web site www.komfort.com or obtained by contacting our Technical Services Department. 26.0 Timber Door Installation 26.1 Timber door installation is the responsibility of the Komfort contractor. 26.2 The (code: SJ65) door frame has been supplied and fitted with (code: 582) steel left off hinges. a) 1 pair for standard height (1981mm or 2040mm) doors . b) 11/2 pair (3No.) for all other doors. 26.3 The top hinge in all applications has a longer pin therefore care must be taken when removing hinge leaf to fit to the door lipping. 26.4 To avoid splitting the door lipping we strongly recommend the use of drilling 2.8mm - 3mm diameter pilot holes before screw fixing the hinges using (code: 311) No.8 x 38mm long pozi countersunk screws. 26.5 For installation of matched veneered or laminated door overpanels refer to separate data sheets which can be found on our web site www.komfort.com or obtained by contacting our Technical Services Department. 27.0 Final Inspection and Cleaning 27.1 Before leaving the site and approaching the contractors representative to complete sign off and acceptance documentation a full inspection and of the installation must be carried to check for the following; a) b) c) d) e) f) g) h) 27.2 All metal paint work is free of any damage. There are no open door frame mitres. All top wedge seals are full installed and that there has been no shrinkage. All base channel gaskets are full installed and that there has been no shrinkage. That there is no evidence of glass grinning due to being under size. All glass installed is safety marked and that the mark is in the same location for all modules. The glass is within the requirements of BS EN ISO 12543-6 for imperfections and scratches. All door furniture is full functional and that all cover trims are installed. The glass should be full cleaned on both sides and all metal work and door furniture wiped down using approved cleaning materials. ORBIS Single Glazed METHOD OF BUILD page 22 of 23 KOMFORT WORKSPACE Personal Notes ORBIS Single Glazed METHOD OF BUILD page 23 of 23 KOMFORT WORKSPACE Orbis - single glazed ORBIS Partitioning Systems Method of Build Produced by : Komfort Workspace Ashurst Building Broadlands Business Campus Langhurstwood Road Horsham West Sussex RH12 4QP Tel - 01403 390300 e mail - komfort.com