Proceedings of Indian Geotechnical Conference December 15-17,2011, Kochi (Invited Talk-7.) NEW CHALLENGE IN D-RUNWAY CONSTRUCTION OF TOKYO HANEDA AIRPORT Yoichi Watabe, Port and Airport Research Institute, Yokosuka, Japan, watabe@ipc.pari.go.jp Takatoshi Noguchi, Kanto Regional Development Bureau, Ministry of Land, Infrastructure, Transport and Tourism, Japan ABSTRACT: Tokyo International Airport (Haneda Airport) has been developed by land reclamation. A new runway, named “D-runway,” was constructed from March 2006 to October 2010. Because some part of the D-runway is located in a river mouth, a hybrid structure consisted of piled pier and reclamation fill was adopted. To overcome the difficulties in construction on soft clay deposit, it adopted various technologies in design and construction. This paper describes about the outline of the project, ground investigation, and designing of the D-runway structure, from a view point of geotechnical engineering. INTRODUCTION Tokyo International Airport (Haneda Airport) has been developed by reclamation. The offshore expansion project started from 1984 was an epoch-making project, in which airport island was constructed from a dredged clay disposal facilities in ultra-soft state (Katayama, 1991). Recently, The fourth runway named “D-runway” has been newly constructed (Photo 1, Fig.1). The D-runway started its operation in October 2010 on schedule. This paper describes about the outline of the D-runway project, soil stratigraphy, and designing of the manmade island, from a view point of geotechnical engineering. The geological cross-section in the D-runway direction is shown in Fig.2. Soil layers are named reflecting the geological history; i.e. Y (Yurakucho layer), Na (Nanago layer), To (Tokyo layer), and Ed (Edogawa layer). Subscripts c, s, and g represent clay, sand, and gravel layers, respectively. The interface between Yuc and Ylc is almost horizontal; however, lower boundary of Ylc is slightly deeper around the south-west end of the D-runway (side of the Tamagawa River). Most part of Na layer, Nac and Nas deposited alternately. The Na layer at A-13 deposited deeper and thicker than that at others, indicating that the Nac at A-13 deposited in an eroded valley in Tokyo layer. OUTLINE OF THE D-RUNWAY PROJECT The D-runway is located 600 m offshore from the previous airport island. In the area inside the river mouth of the Tama River, a pier structure with an impediment rate of river flow less than 8% is adopted to ensure a sufficient flow rate during times of floods. Therefore, the D-runway is a hybrid structure of piled pier and reclamation fill. The length of the D-runway is 2500 m. The elevation at the offshore end of the D-runway is required to be higher than A.P. +17.1 m, which is extremely higher than ordinal manmade island. Here, elevation ±0 in A.P. corresponds to +1.134 m in T.P. STRUCTURE OF THE D-RUNWAY Reclamation Section Seawall type The reclamation section was constructed on a soft clay seabed as a high embankment whose thickness is approximately 41 m from seabed to the top. Because of C-runway 3,000m A-runway 3,000m New control tower Apron Terminal 2 Garden Terminal 1 New international area Parking New runway (D-runway) 2,500m Passenger terminal Cargo terminal Photo 1. A scene of the D-runway construction taken on 18 July 2010. 41 Fig.1. Site plan of the D-runway and previous airport facilities. Yoichi Watabe & Takatoshi Noguchi A.P. (m) -10 Å Tama River side (SW) A-9 -15 A-8 -20 N-value 0 50 0 A-10 N-value 0 50 N-value 50 Jonan Island side (NE) Æ A-12 N-value 0 50 A-11 N-value 0 50 A-13 N-value 0 50 Hc A-1 Nvalue 0 50 A-2 N-value 0 50 -25 Yuc (Ac1) Ys1 (As1) -35 -40 Ylc (Ac2) -45 Nac1 (Dc1) -50 Nas1 (Ds1) -60 -65 -70 -75 -85 Nas1 (Ds1) Nas1 (Ds1) Nac1 (Dc1) Yuc (Ac1) Yuc (Ac1) (1) -30 Ylc (Ac2) Ylc (Ac2) Nas1 (Ds1) Nac1 (Dc1) (2) Ys2 (As2) Nac1 (Dc1) Nas2 (Ds2) Nac2 (Dc2) Nas2 (Ds2) Nac2 (Dc2) Nas2 (Ds2) Nac1 (Dc1) Nac1 (Dc1) Nac1 (Dc1) Nac1 (Dc1) Nas1 (Ds1) Nas2 (Ds2) Nas2 (Ds2) Nas1 (Ds1) Tos1 (Ds3) Nac2 (Dc2) UG (ash) Tos1 (Ds3) Toc1 (Dc3) Toc3 (Dc5) Toc3 (Dc5) Nac2 (Dc2) Tos1 (Ds3) Toc1 (Dc3) Tos1 (Ds3) btg (Dg1) (3) Edc1 (Dc6) TB10䌾18 (ash) Toc1 (Dc3) Toc2 (Dc4) Tos2 (Ds4) Tog3 (Dg4) -90 Tog2 (Dg3) Tog3 (Dg4) (5) -85 Edc1 (Dc6) Eds1 (Ds6) Eds1 (Ds6) Edc1 (Dc6) Edc1 (Dc6) Eds1 (Ds6) -95 Toc1 (Dc3) Tos1 (Ds3) Toc1 (Dc3) (4) Tos3 (Ds5) Toc3 (Dc5) Tog3 (Dg4) Nac2 (Dc2) Eds1 (Ds6) -100 Fig.2. The geological cross-section in the D-runway direction in original plan. Parapet Block Wave-dissipating blocks Cover stones Sand 1 Rubble Cement treated soil (pneumatic mixing) Partition 2 Rubble Sand (counterweight) Mound Mound Replaced sand SCP 60% Partition 1 Sand (cover) SCP 60% Sand (1)-C-1 SCP 30% (1)-C-2 SD (2)-C ႇᄖ ጯ ⼔ ᴺ ✢ ⓨ ᣉ ᷼ ⸳ ↪ ⇇ Ⴚ ႇౝ (2)-S (2)-C (3)-S Fig.3. A typical cross-section of the mild slope rubble seawall (general seawall section). 30% (low replacement ratio SCP) was utilized to improve the stability as a composite ground and to accelerate the consolidation as drainages. SCP pile arrangement was 3.0 m × 3.5 m. consolidation settlement, the thickness is larger than the total of the water depth and elevation of the runway. Incremental consolidation pressure applying to the seabed surface by this reclamation reached up to approximately 550 kN/m2. This consolidation pressure, equivalent to that at the second phase island of the Kansai International Airport, is the largest in the history of the Tokyo Bay. In addition, soft clay seabed in front of the seawall was dredged and replaced by sand as counterweight. The dredged clay was cement treated and backfilled as lightweight soil. These two technologies of counterweight and cemented lightweight soil contribute to improve the stability of the seawall. A mild slope rubble seawall was adopted for the general seawall section (4144.1 m), and a gravity type caisson seawall was adopted for the approach light seawall (100.2 m) and tentative quay wall for the construction (221.0 m). Inside the Reclamation Fill Inside the reclamation fill, the soft ground was improved by sand drains (SD), to decrease residual settlement during the in-service period by accelerating the consolidation behavior. To achieve a degree of consolidation of 80% in Yuc layer (deposited up to A.P. –35 m with a coefficient of Mild slope rubble seawall The mild slope rubble seawall was utilized to the general seawall section because of flexibility for both settlement and lateral movement. A typical cross-section is shown in Fig.3. Sand compaction pile method with a replacement ratio of 42 New challenge in D-runway construction of Tokyo Haneda Airport Reclamation Pire ᯅㇱ Expansion device (Rolling leaf) Beam ᷰࠅᩴ Columns #2 Pavement and Cover soils Asphalt treated layer િ❗ⵝ⟎ ࡠࡦࠣࡈ࠲ࠗࡊ Airfoam treated soil 2 (10.0 kN/m3) ࠕࠬࡈࠔ࡞࠻ቯಣℂ Airfoam treated soil 1 (11.5 kN/m3) Cover stones *9.#2 .9.#2r (1)-H (1)-C-1 #2 #2 (1)-C-2 SCP 60% SCP 30% * % #2 Fig.4. Contours of the predicted residual settlement in 100year in-service period. #2 (2)-C-1 % シ㊂ᷙวಣℂ ǫM0㨙 ㇱ᭴ㅧ Cement treated soil 2 (14.0 kN/m3) Rubble mound ⵍⷒ⍹ SCP78% Cement treatedシ㊂ᷙวಣℂ ǫM0㨙 soil 1 (14.0 kN/m3) #2 ਛ ೨㕙ࡑ࠙ࡦ࠼ SCP 30% ᝥ⍹ #2 5%2ᡷ⦟ 5%2ᡷ⦟ 5%2ᡷ⦟ Steel pipe piles ▤ਛᷙว࿕ൻಣℂ ǫM0㨙 Sand Sand mat (1)-H ▤ਛᷙว࿕ൻಣℂ ǫM0㨙 (1)-C-1 ⼔⍾ (1)-C-2 ࠨࡦ࠼ࡑ࠶ * 5%2ᡷ⦟ % #2 (2)-C-1 % ㍑▤⍫᧼Ǿ % (3)-S #2 (3)-C-1 5 (3)-C-1 #2 5 (5) (5) #2 #2 % (3)-S #2 % % Fig.5. Cross-section of the joint structure between the reclamation and pier sections. Piled Pier Section In the piled pier section, to conduct the construction within the short period, prefabricated jacket structure was adopted. A jacket unit is composed of upper steel girder and lower steel pipe legs reinforced by truss structure, as shown in Photo 2. Its standard dimension is 63 m in length, 45 m in width, 32 m in height, and 1300 t in mass. Total 198 units of jacket were installed for the main body of the D-runway. Photo 2. A scene of installation of a jacket unit. consolidation cv of approximately 100 cm2/day) at 4 months after a staged filling, the arrangement of SDs with 400-mm diameter were set to be 2.5 m × 1.6 m. The SDs were installed up to A.P. –35.5 m to A.P. –37.5 m corresponding to the depth of Ylc layer. The SD installation was conducted after placing the 1.5-m thick sand mat drainage (hydraulic conductivity is higher than 1 × 10–4 m/s). After the SD installation, 2.5-m thick sand layer (hydraulic conductivity is higher than 1 × 10–5 m/s) was placed for SD head protection. In the assembling procedure of the jacket structure (Photo 2), six steel pipe piles were first driven to the ground, then the prefabricated jacket unit were set by inserting the pile heads into the pipe legs, and then the clearance between the pile heads and legs were grouted by mortar. After assembling the jackets, there was a clearance of 2–3 m between two adjacent jackets, and then a segment in adjusted dimensions were inserted into the clearance and welded to be an integrated body. Cross-section of the joint structure between the reclamation and pier sections is shown in Fig.5. Piled foundations of the jackets were supported by the bearing layer (deeper than A.P. –80 m), which shows N-values continuously greater than 50. Determination of final land reclamation height Incremental consolidation pressure from the reclamation fill was approximately 550 kN/m2 and 300 kN/m2 near the offshore end and near the joint section, respectively, of the Drunway. The predicted total settlement in average was 7.2 m. Contours of residual settlements calculated for in-service period of 100 years are shown in Fig.4. The predicted residual settlement along the D-runway was 0.50–0.65 m and 0.60–0.70 m near the joint section and end of the runway, respectively. The seawall sections, where significant residual settlement larger than 0.7 m was calculated, correspond to the position of late backfilling, because these section was used as either the open mouth (gateway) for ships/barges used for reclamation filling or tentative material yard. Joint Section The joint structure between the reclamation and pier sections is simply called as “joint section.” The joint section is a very important structure, which takes the roles of both the seawall of the manmade island and abutment for the joint girder. In this project, well-foundation of steel pipe piles, which has a good track record in bridge foundations and abutments, was utilized (Fig.5). The well-foundation has consecutive 24 rectangle cells consisted of two parallel steel pipe sheet piles as outer envelope and 25 orthogonal steel pipe sheet piles. Summarizing the above results on the long-term settlement, residual settlement for 100-year in-service period at the highest point (the end) of the D-runway was expected to be 0.69 m (0.73 m after completion of filling). Consequently, in consideration of the residual settlement, the filling of the Drunway at the start of in-service period was decided to be 0.70 m (slightly larger than 0.69 m) higher than the design elevation, which is required from the aviation operation. To ensure the stability of the well-foundation, which was embedded to the bearing layer, it was required to utilize lightweight backfill such as pneumatic mixing cement treated soil (Kitazume and Satoh, 2003) and air-foam treated lightweight soil (Tsuchida and Egashira ed., 2004; Watabe et al., 2004). The lightweight backfill can contribute to decrease the lateral earth pressure, consolidation settlement, and lateral 43 Yoichi Watabe & Takatoshi Noguchi period. On the other hand, the latter section, i.e. manmade island, is a so called high embankment. The elevation at the offshore end of the D-runway is required to be higher than A.P. +17.1 m, because airplanes have to overpass a large ship navigating nearby. Table 1. An example of mix proportion for the pneumatic mixing cement treated soil. W/C in weight (%) Cement per unit weight of slurry C (kg/m3) Dredged clay in front of the seawall 10.2 The soft subsoil under the mild slope rubble seawall, of which allowable deformation is relatively large, and gravity type caisson seawall, of which allowable deformation is significantly small, was improved by SCP (low replacement ratio) and CDM (block type), respectively. In addition, lightweight treated soils were backfilled The upper soft subsoil was improved by SD method to accelerate the consolidation. 85 Dreaded clay from Tokyo Navigation Channel No. 1 8.5 103 Table 2. An example of mix proportion for the air-foam treated lightweight soil. Bulk density of clay slurry Ut (g/cm3) Cement per unit weight of slurry C (kg/m3) Volumetric percentage of airfoam in mixture (%) The upper soft subsoil was improved by SD method to accelerate the consolidation, however, it was expected that the lower clayey layer, which cannot be improved because of the large depths, would cause a long-term settlement of approximately 0.70 m. Consequently, in consideration of the residual settlement, the filling of the D-runway was decided to be 0.70 m higher than the design elevation. Target Ut = 1.02 g/cm3 (Jt = 10 kN/m3) 1.196 Target Ut = 1.12 1.211 78 g/cm3 (J t = 11 47 19.6 kN/m3) 11.8 In the construction of the D-runway, not only the ground improvement technologies (SD, SCP, and CDM) but also the new developed construction materials (pneumatic mixing cement treated soil and air-foam treated lightweight soil) were utilized. In addition, observational construction with high-tech instruments for measurement was conducted. Moreover, collaboration between geotechnical and geological knowledge contributed to the interpretation of the ground condition. In the-D-runway project, various technologies accumulated through previous airport constructions were applied to ground investigation, design, construction work, as well as maintenance. soil movement. In addition, the soft deposit in front of the structure was improved by sand compaction piles with high replacement ratio, to increase the lateral resistance of the well foundation. Observational construction was conducted by monitoring the settlement and lateral movement caused by backfilling. Effect of the Lightweight Soils Cement treated lightweight soils made of dredged clay were backfilled to the seawall. Major part of those was the pneumatic mixing cement treated soil, which is appropriate to large scale construction work, as a backfill of the mild slope rubble seawall (Fig.3). In the joint section, to reduce the earth pressure applying to the well-foundation whose height is approximately 30 m from the seabed, pneumatic mixing cement treated soil and air-foam treated lightweight soil were placed at lower and upper sections, respectively (Fig.5). ACKNOWLEDGMENTS This paper was written in collaboration with Kanto Regional Development Bureau of Ministry of Land, Infrastructure, Transport and Tourism, Port and Airport Research Institute, and Joint Venture for D-runway construction in the further expansion project of Haneda Airport. Total volume of lightweight soils (pneumatic mixing cement treated soil and airfoam treated lightweight soil) used in the reclamation work of the D-runway project was approximately 5,500,000 m3, which was equivalent to approximately 15% of total reclamation soil volume of approximately 38,000,000 m3. A typical mix proportions of the pneumatic mixing cement treated soil and air-foam treated lightweight soil used in this project are shown in Tables 1 and 2, respectively. REFERENCES 1. Katayama, T. (1991), Meeting the challenge to the very soft ground –the Tokyo International Airport Offshore Expansion Project. Proc. Int. Conf. Geotech. Engrg for Coastal Development, GEO-COAST’91, 954–967. 2. Kitazume, M. and Satoh, T. (2003), Development of pneumatic flow mixing method and its application to Central Japan International Airport construction. Proc. Ground Improvement, 7(3), 139–148. 3. Tsuchida, T. and Egashira, K. (ed.) (2004), The lightweight treated soil method, A. A. Balkema 4. Watabe, Y., Itou, Y., Kang, M.-S. and Tsuchida, T. (2004), One-dimensional compression of air-foam treated lightweight geo-material in microscopic point of view. Soils and Foundations, 44(6), 53–67. SUMMARY One of the remarkable features of the D-runway is the hybrid structure consisted of piled pier and reclamation fill. The former section was adopted in the river mouth of the Tama River, to ensure a flow rate during times of flooding. This piled pier section was constructed by assembling the jackets prefabricated in a factory yard to shorten the construction 44