MISSISSIPPI STATE PORT AUTHORITY - PORT OF GULFPORT RESTORATION PROGRAM SECTION 00 91 13 ADDENDA ADDENDUM NUMBER 2 – ISSUED JULY 06, 2016 DATE: July 06, 2016 PROJECT TITLE: Marine Research Facility – Early Start Foundation Package PROJECT NUMBER: 413 OWNER: Mississippi State Port Authority ARCHITECT OF RECORD: Eley Guild Hardy Architects PA TO: Prospective Bidders This Addendum forms a part of the Contract Documents and modifies the June 1, 2016 Issued for Bid documents with amendments and additions noted below. Acknowledge receipt of this Addendum in the space provided in the Bid Form. Failure to do so may disqualify the Bidder. This Addendum consists of 1 page and 5 pages of attachments as follows: SPECIFICATION CHANGES: 1. Section 00 41 43 Bid Form: Delete the Section 00 41 43 Bid Form in its entirety and replace with the attached Section 00 41 43. Pay Item 26 05 01 was added to the Bid Form (5 pages) to capture the electrical work. END OF SPECIFICATION CHANGES FOR ADDENDUM NO. 2 END OF DOCUMENT PGRP Project No.: 413 PGRP Project Title: Marine Research Facility – Early Start Foundation Package Architect: Eley Guild Hardy Architects PA Issued – July 06, 2016 Addenda No. 2 00 91 13 - 1 MISSISSIPPI STATE PORT AUTHORITY - PORT OF GULFPORT RESTORATION PROGRAM SECTION 00 41 43 BID FORM ADDENDUM 2 – ISSUED JULY 06, 2016 (SINGLE-PRIME CONTRACT) Proposal of ________________________________ (hereinafter called "Bidder"), doing business as a __________________, (insert "a corporation," "a partnership," or "an individual” applicable; if a corporation, indicate state of incorporation) to the Mississippi State Port Authority ("hereinafter called "Port Authority" or "Authority), an agency existing under the laws of the State of Mississippi. In compliance with your Advertisement for Bids, Bidder hereby proposes to perform all Work for the Work of Improvement known as: “Marine Research Facility – Early Start Foundation Package, Project No. 413” and all appurtenant Work and materials required to complete the Work, in strict accordance with the Contract Documents, within the time set forth therein, and at the prices stated below. By submission of this Bid, each Bidder certifies, and in the case of a joint Bid, each party thereto certifies as to his/her own organizations, that this Bid has been arrived at independently, without consultation, communication or agreement as to any matter relating to this Bid with any other Bidder or with any competitor. Bidder hereby agrees to commence Work of Improvement under this Contract within 5 consecutive calendar days after the date of service of the Notice to Proceed and to fully complete the project within 242 consecutive calendar days thereafter as provided in Sections 7 and 34 of the General Conditions. Bidder acknowledges receipt of the following Addenda: (if none, so state) No.__________________ No.__________________ No.__________________ No.__________________ Date: __________________ Date: __________________ Date: __________________ Date: __________________ Attached to this Bid is a list of Subcontractors (Appendix A) as required by Section 27 of the General Conditions and Advertisement for Bid. Bidder agrees to perform all the Work described in the Contract Documents for the lump sum and unit prices as set forth in the following Bid Schedule. UNIT PRICES: For changing quantities of work from those indicated on the Drawings and contained within these Specifications, upon written inspections from the Engineer and the Mississippi State Port Authority and for determining payments on account of the contract, the following unit prices shall prevail: PGRP Project No.: 413 PGRP Project Title: Marine Research Facility – Early Start Foundation Package Architect: Eley Guild Hardy Architects PA Document Status: IFB – June 1, 2016 (Revised Addendum #2 – July 06, 2016) Bid Form – Addendum 2 00 41 43 - 1 MISSISSIPPI STATE PORT AUTHORITY - PORT OF GULFPORT RESTORATION PROGRAM DESCRIPTION Mobilization / Demobilization Selective Site Demolition Test pile and Reaction piles for Compression Test ASTM D1143 and Tension Test ASTM D3689, piles for test program 95’-0”, Thermal Integrity Profile (TIP) Test ASTM D7949-14 each test pile UNITS Lump Sum Lump Sum Each QUANTITY 1 1 2 31 63 16.02 Production pile, 18” Auger-cast Lineal Foot 15,010 31 63 16.03 Spoils removal Cubic Yards 1,020 PAY ITEM 01 20 00.01 02 41 00 31 63 16.01 31 63 16.04 01 09 00-A 01 55 00-A 01 55 00-B 02 41 00-A 02 41 00-B 02 41 00-C 02 41 00-D 02 41 00-E 02 41 00-F 26 05 01 31 25 00-A 31 25 00-B 31 25 00-C Thermal Integrity Profile (TIP) Test ASTM D7949-14 CONSTRUCTION LAYOUT MAINTENANCE OF TRAFFIC MAINTENANCE STONE REMOVAL OF PAVEMENTS (ALL TYPES, ALL DEPTHS) REMOVAL OF PIPE (8" AND UNDER) REMOVAL OF PIPE (LARGER THAN 8") REMOVAL OF FENCE REMOVAL OF DRAINAGE STRUCTURES REMOVAL OF FIRE HYDRANT & CAPPING LINE MINOR ELECTRICAL DEMOLITION Removal/storage of flood lights and poles, relocation and reconnection of panelboards, controls, and existing site lighting circuits shall be measured and paid as a lump sum. All work described in other Sections of Division 26 shall be absorbed into this Pay Item. SILT FENCE STRAW WATTLES INLET PROTECTION PGRP Project No.: 413 PGRP Project Title: Marine Research Facility – Early Start Foundation Package Architect: Eley Guild Hardy Architects PA Document Status: IFB – June 1, 2016 (Revised Addendum #2 – July 06, 2016) Each LS LS TON 15 1 1 120 SY 6500 LF 200 LF LF 400 1000 EA 4 EA LS 1 1 LF LF EA 800 100 5 UNIT COST TOTAL Bid Form – Addendum 2 00 41 43 - 2 MISSISSIPPI STATE PORT AUTHORITY - PORT OF GULFPORT RESTORATION PROGRAM 31 25 00-D 31 25 00-E 31 25 00-D 32 10 00-A 32 10 00-B 32 31 00-A 32 31 00-B 32 31 00-C 32 31 00-D 33 30 00-A 33 30 00-B 33 30 00-C 33 30 00-D 33 30 00-E 33 41 00-A 33 41 00-B 33 49 00-A 33 49 00-B CONSTRUCTION ENTRANCE FILTER SOCK TEMPORARY STOMWATER DRAIN SELECT BEDDING MATERIAL SELECT FOUNDATION MATERIAL 6' TALL TEMPORARY FENCE 4' WALK GATE 16' DOUBLE SWING GATE 8' TALL PERMANENT FENCE WITH BASE PLATE 8" SEWER MAIN (0'-10' DEEP) INSTALL 8" CLEANOUT AND CONNECT TO EXISTING SEWER MANHOLE, 4' DIA. (0'-10') 6" SEWER SERVICE CONNECT NEW SEWER TO EXISTING MANHOLE 15" RCP 24" RCP CAST-IN-PLACE CONCRETE DRAINAGE STRUCTURES CASTINGS & GRATING EA LF LS 1 450 1 CY 300 CY LF EA EA 150 700 2 1 LF 140 LF 360 LS 1 EA LF 3 10 EA LF LF 1 60 350 CY LB 10 1000 BASE BID: TOTAL AMOUNT OF BASE BID: $ (IN FIGURES) TOTAL AMOUNT OF BASE BID: (IN WORDS) Note: Bids shall include sales tax and all other applicable taxes and fees. All blanks shall be filled in. Total amount of Bid shall be the sum of the Items. Contract Award will be made based upon the pricing of this Bid Schedule and the contractor qualifications as set forth in the bid documents. In case of discrepancy between the sum of the items and Total Amount of Bid, the sum of the items shall be considered to be the Total Amount of Bid. Award will be made to only one Bidder based upon the Base Bid as applicable from this Bid Form and determination of best value. The undersigned, having read and understood the Bidding Documents and examined the Project site and adjoining areas, and being familiar with the obstacles and conditions that will affect proposed PGRP Project No.: 413 PGRP Project Title: Marine Research Facility – Early Start Foundation Package Architect: Eley Guild Hardy Architects PA Document Status: IFB – June 1, 2016 (Revised Addendum #2 – July 06, 2016) Bid Form – Addendum 2 00 41 43 - 3 MISSISSIPPI STATE PORT AUTHORITY - PORT OF GULFPORT RESTORATION PROGRAM Work, hereby offers and agrees to furnish all labor, equipment and materials and to perform all the Work required for “Marine Research Facility – Early Start Foundation Package” project at the Mississippi State Port Authority at Gulfport, Port of Gulfport, Gulfport, Mississippi in accordance with the Contract Documents and at the prices stated in the preceding Bid Schedule. Respectfully submitted, Legal Name of Bidder Address ___________________________________ Signature of Authorized Person City, State Zip Name & Title of Authorized Person Attest ________________________________________ Name & Title (SEAL--if Bid is by a corporation) Notes: If Bid is by a corporation, corporate seal is affixed in space provided immediately above. Signature is by an individual legally authorized to bind Bidder to a contract. If signature is by an agent of Bidder, the current power-of-attorney verifying agent’s authority to bind Bidder is attached. END OF DOCUMENT PGRP Project No.: 413 PGRP Project Title: Marine Research Facility – Early Start Foundation Package Architect: Eley Guild Hardy Architects PA Document Status: IFB – June 1, 2016 (Revised Addendum #2 – July 06, 2016) Bid Form – Addendum 2 00 41 43 - 4 MISSISSIPPI STATE PORT AUTHORITY - PORT OF GULFPORT RESTORATION PROGRAM THIS PAGE INTENTIONALLY LEFT BLANK PGRP Project No.: 413 PGRP Project Title: Marine Research Facility – Early Start Foundation Package Architect: Eley Guild Hardy Architects PA Document Status: IFB – June 1, 2016 (Revised Addendum #2 – July 06, 2016) Bid Form – Addendum 2 00 41 43 - 5