Lift / Pump Stations - Prime Construction Group

advertisement
“Our People make the difference with Pride, Integrity and Quality”
Project Type: Lift and Pump Station Constuction
Job #
Project Name
604
09-008 Lift Station 8 & Surface Water Pump Station Replacement
Final Contract
Owner:
City of Altamonte Springs
Scope of Work
Replacement of the existing lift station 8 and SWPS, new wet well, electrical building, generator, rehab existing LS 8 wetwell,
conversion of wetwell to SWPS, conversion of SWPS to weir box.
Job #
Project Name
Final Contract
586
090128-NT-001 Palmera Missile & Fire Control Sewer Replacement
$0
Owner:
Lockheed Martin Corporation
Scope of Work
Installation of a duplex 30 hp pump station with a 125 kW genset and 12" electromagnetic flowmeter; 10", 12", 18" gravity sewer,
16" force main, jack & bore, asphalt paving, concrete, erosion control. Removal of existing sanitary and re-use main. Special
requirements: Height restriction due to overhead high voltage power lines.
Job #
Project Name
Final Contract
578
Mill Creek Reclaimed Water Distribution Pump Station
$1,320,638
Owner:
City of Sanford
Scope of Work
The project involves installation of a prefabricated pump station (pump/electrical room, air compressor room & chemical feed
room) to include aluminum frame skid, doors, HVAC units, aluminum metal roofing system, roof hatches, FRP interior & exterior,
lighting, five vertical turbine cans, four canned vertical turbine pumps with VFDs, electrical and controls; a submerged pond water
intake screen; a pond water supply control valve station; associated yard piping, miscellaneous sitework, signage, fencing,
entrance/exit gates, sodding, landscaping, irrigation system, electrical and instrumentation systems.
Job #
Project Name
Final Contract
574
#2379 Water Conserv II Master Pump Station & Flow Equalization
$0
Owner:
City of Orlando
Scope of Work
New 3-level wet pit/dry raw sewage master pump station with five 9,975 gpm raw sewage pumps with variable frequency drives;
3.5 mg flow equalization tank, new precast concrete electrical building, new master pump station influent junction box;
modifications and rehabilitation of existing master pumping station systems and conversion to a transfer pumping station,
modifications to the existing primary clarifiers and associated site, electrical, controls, mechanical and other work.
Wednesday, November 17, 2010
Page 1 of 6
“Our People make the difference with Pride, Integrity and Quality”
Project Type: Lift and Pump Station Constuction
Job #
Project Name
Final Contract
566
Winter Park Drive North Realignment
$5,661,289
Owner:
City of Casselberry
Scope of Work
Construct approx. 1.5 miles of two lane roadway through an undeveloped ROW along with supporting drainage & utility
infrastructure. Work included excavation, embankment, stabilization, base, asphalt, reinforcing steel, lift station, mast arm
assembly, signalization, MOT, irrigation. Drainage system included approx. 11,250 lf RCP 24"-42", 32 inlets and 28 manholes;
utilities included approx 2,361 lf 8" potable water main with 14 service connections, approx 2,334 lf 8" reclaimed water main with
12 service connections and approx 4,487 lf of 6"-10" PVC sanitary sewer with 17 manholes and 25 service connections.
Job #
Project Name
Final Contract
536
Bonneville Pump Station #3221 Rehabilitation
$1,157,700
Owner:
Orange County Utilities
Scope of Work
Rehabilitation of Pump Station #3221 including remove/install 8" piping, three 58 hp pumps, electrical & control equipment.
Rehabilitation of existing wet well & manhole by installing new fiberglass liner, 1000 gal above ground storage tank, odor control
unit, flow meter assembly, 8' block privacy wall with anti graffiti coating, relocate existing utilities & connect new piping.
Job #
Project Name
Final Contract
532
Tier 8 - Orange Blossom Trail PS 3109 Improvements
$694,084
Owner:
Orange County Utilities
Scope of Work
Rehabilitate and upgrade the existing wastewater pump station. Work included installation of a ITT Flygt 30 hp submersible
pumps, manhole rehabilitation, bypassing, new chain link fence with automatic gate, electrical improvements, a Kohler diesel
engine generator, 65 kw, 60 hz 3 phase 277/480 volt with auto transfer switch, an H-120 bio filter modular skid mounted odor
control system, driveway, wet well & valve vault corrosion proof lining and coating, miscellaneous mechanical and electrical
equipment.
Job #
Project Name
Final Contract
518
Jason Dwelley Pkwy Ext, Bradshaw Rd Roadway & Drainage, 3rd St Parking &
Drainage Improvements
$9,942,165
Owner:
City of Apopka
Scope of Work
The original scope of work required the following. Jason Dwelley Parkway: Approximately 2 miles of new two lane roadway,
storm drainage, lined pond construction, sport field grading, paved parking lots, and a new reclaimed water pump station.
Bradshaw Road: Approximately 1/2 mile of roadway widening from two to three lanes, storm drainage, and pond construction.
3rd Street: Storm drainage improvements and new paved public parking areas.
Wednesday, November 17, 2010
Page 2 of 6
“Our People make the difference with Pride, Integrity and Quality”
Project Type: Lift and Pump Station Constuction
Job #
Project Name
Final Contract
515
Peppertree, Boreas Drive & Lk Underhill Hospital Pump Stations
$961,270
Owner:
Orange County Utilities
Scope of Work
Project consists of construction of two duplex wastewater pump stations in residential neighborhoods, at Peppertree and Boreas
Drive, and the rehabilitation of one duplex wastewater pump station at Lake Underhill Hospital.
Job #
Project Name
Final Contract
511
Pump Station #28 and Pump Station #112 Improvements
$572,807
Owner:
Toho Water Authority
Scope of Work
Modifications of Pump Station #28 and Pump Station #112 including precast structures, wet well and manhole coating, sanitary
sewer force main, pumps and miscellaneous piping. The stations were located in Osceola County along arterial roadways.
Job #
Project Name
Final Contract
492
Orange County Landfill Pond 2 Pump Station Improv.
$1,990,326
Owner:
Orange County Utilities
Scope of Work
Refurbish existing pumps, installation of 5500 gpm cylinder mounted pumps to include replacement of emergency generator,
valves, controls & minor structural work. Install 3000 lf 20' DIP FM to OUC property line.
Job #
Project Name
Final Contract
482
Tallwood - Laredo Stormwater Improvements
$562,747
Owner:
City of Deltona
Scope of Work
Approximately 4000 LF of HDPE storm drainage pipe of various sizes was installed through out this project to improve and
eliminate flooding conditions on several streets in a residential area. Several MES, headwalls, manholes and inlets were installed
as part of this new storm water management system. A storm water pump station was installed which out-felled to a new 1 acre
retention area. One of the storm lines was installed in a 10’ easement between two homes with out incident. Several drive way
crossings were completed and concrete drives were installed.
Job #
Project Name
Final Contract
480
Old Winter Garden Road & Professional Parkway
$6,997,105
Owner:
City of Ocoee
Scope of Work
Project required the widening of 1.262 miles of existing Old Winter Garden Rd. from a 2 lane road into a 4 lane divided roadway.
Work included utility relocations/improvements, storm pond excavation, storm drainage system installations, signalization,
fencing, landscape & irrigation, signage, and pavement markings. Relocation and improvements of Sprint Telephone facilities
located within the right-of-way of this project.
Wednesday, November 17, 2010
Page 3 of 6
“Our People make the difference with Pride, Integrity and Quality”
Project Type: Lift and Pump Station Constuction
Job #
Project Name
Final Contract
477
Reclaimed Water Booster Pumping Facility
$1,138,854
Owner:
City of Ocoee
Scope of Work
Reclaimed water booster pumping facility with electrical equipment building, wet tap connection to RWFM pipeline, paving,
landscaping, ornamental wall, VFDs for four vertical turbine pumps, controls, telemetry system.
Job #
Project Name
Final Contract
472
Cranes Roost PS Modif. & Reuse Weir Structure
$406,220
Owner:
City of Altamonte Springs
Scope of Work
Rehabilitation of storm water pump station from Cranes Roost, new 150 HP vertical turbine pumps, new controls. Also, sheet
down to existing 21" gravity sewer & pour concrete structure for reclaimed water supply enhancement.
Job #
Project Name
Final Contract
469
MoHo MH Park & Weatherly Pump Stations
$409,664
Owner:
Orange County Utilities
Scope of Work
Construction of two new wastewater duplex pump stations, gravity main and manhole. Also included are submersible pumps,
emergency bypass, wet wells, valve vaults w/ corrosion proof lining & coatings, water service, landscaping, misc mechanical &
electric
Job #
Project Name
Final Contract
464
Dubsdread Neighborhood Sewer Improvements
$2,279,659
Owner:
City of Orlando
Scope of Work
Provide labor, materials and equipment to install 7300 LF of PVC gravity sewer (to 16' depth), install one duplex lift station via
tremie method, 38 gravity sewer manholes (to 18' depth), 1200 LF of 6" Forcemain (to include directional drills), 5300 LF
residential and commercial water lines and services (2" to 6" DIP main lines), residential road restoration, open cut Edgewater
Drive, a major city thoroughfair, providing extensive MOT to include continuous business/public access, restore roadway with
black base and associated storm water system modifications.
Job #
Project Name
Final Contract
455
Rouse Rd & Berry Dease Pump Station Improve.
$1,883,803
Owner:
Orange County Utilities
Scope of Work
New VFDs and enclosure at Berry Dease pump station,. New HDPE lining, piping and pumps at Rouse Road Master Station.
Concrete restoration at Rouse Rd. Bypassing of Rouse Road Pump Station.
Wednesday, November 17, 2010
Page 4 of 6
“Our People make the difference with Pride, Integrity and Quality”
Project Type: Lift and Pump Station Constuction
Job #
Project Name
Final Contract
443
Liberty Mutual - Pump Stations A & Pine Hills
$1,885,080
Owner:
Orange County Utilities
Scope of Work
Takeover & completion of project abandoned by contractor. Work included rehabilitation of two master pump stations and
construction of one new master pump station. Also laid 30" gravity sewer in an existing neighborhood to tie in to new pump
station.
Job #
Project Name
Final Contract
439
Pine Hills Pump Station Improvements
$544,789
Owner:
Orange County Utilities
Scope of Work
Rehabilitation of three lift stations in Pine Hills to include new piping, new pumps & controls. Dismantle old stations. Sliplining of
+/- 400 LF of 8" gravity sewer & 60 LF of 10" gravity sewer.
Job #
Project Name
Final Contract
433
Tupperware Utilities Relocation
$425,000
Owner:
Tupperware Center
Scope of Work
Installation of new sewage pumping station, gravity sewer and water supply mains for Tupperware to allow for the widening of US
441 by the FDOT.
Job #
Project Name
Final Contract
427
Saxon West Extension
$560,826
Owner:
Volusia County
Scope of Work
Installation of 6", 8", 14" & 16" PVC force main (direct bury); 16" HDPE (directional drill), upgrade Regional Lift Station (SW60)
including removal of existing pumps & pipe, cleaning walls & recoating, install new pumps, electrical controls, telemetry &
Job #
Project Name
Final Contract
425
Kopsia, Lynwood, Lk Conway Est & Shenandoah PS Improve.
$768,500
Owner:
Orange County Utilities
Scope of Work
Replace existing wet pit/dry pit or above ground steel can (dry pit) pump stations w/ new submersible pump stations. Work
included valve vault, paving, fencing, & misc site work. Some sites required demolition, install/conversion of MHs, sliplining of e
Wednesday, November 17, 2010
Page 5 of 6
“Our People make the difference with Pride, Integrity and Quality”
Project Type: Lift and Pump Station Constuction
Job #
Project Name
Final Contract
415
Beverly Shores Water & Sewer Improvements
$4,019,680
Owner:
City of Orlando
Scope of Work
Installed approx 13,000 LF of gravity sewer (to 24' depth), approx 7,635 LF of water pipe, new lift station, drainage structures, 50
manholes. Work included pavement removal & restoration, concrete sidewalks & drives, sodding. Project was a complete sewer
installation project within an existing neighborhood. The site required exstensive MOT for local residences.
Job #
Project Name
Final Contract
265
Landfill Leachate Pump Station Rehabilitation
$156,721
Owner:
Orange County Utilities
Scope of Work
Installed new influent line to existing wetwell from manhole #5, removed & replaced leachate submersible pumps, electrical
controls & control panel, flow meter & recorder, added landfill gas venting system, upgraded gas valves in valve pits, installed
drain inlets & required piping, site improvement and fencing.
Wednesday, November 17, 2010
Page 6 of 6
Download