Roosevelt Hall Interior Renovation Brooklyn, New York BID SET Specifications July 28, 2010 TABLE OF CONTENTS ROOSEVELT HALL INTERIOR RENOVATION CONSTRUCTION DOCUMENTS DIVISION 1 - GENERAL REQUIREMENTS SECTION 010000 011116 012600 013000 013100 013119 013300 013524 013529 013530 013553 014000 014100 014200 014500 015100 015213 015219 015316 015423 015716 016000 016500 016600 016619 017123 017133 017329 017413 017416 017419 017423 017713 017719 017813 Contract Documents Summary of Work Modification Procedures Administration of Contracts and Project Procedures Project Coordination Project Meetings Submissions Site Safety Site Security Protection of Rights, Persons and Property Security – General Provisions Quality Requirements Regulatory Requirements Definitions and Omissions Quality Control Temporary Services Construction Field Office Temporary Toilets Sidewalk Bridge Scaffolding and Hoisting Temporary Pest Control Product Requirements Removals and Delivery Storage Materials and Equipment Field Engineering Protection of Adjacent Property Cutting and Patching Cleaning Site Maintenance Construction Waste Management and Disposal Final Cleaning Substantial Completion Contract Closeout Punch List Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 TOC-1 Table of Contents July 28, 2010 017823 017836 017839 Operation and Maintenance Data Guarantees and Warranties Project Record Documents DIVISION 4 - MASONRY SECTION 042000 Unit Masonry DIVISION 8 - OPENINGS SECTION 081113 081416 083473 087100 088000 Steel Doors and Frames Wood Doors Sound Control Door Assemblies Finish Hardware Glass and Glazing DIVISION 9 - FINISHES SECTION 092900 095113 097723 099000 Gypsum Drywall Acoustic Panel Ceilings Fabric Wrapped Acoustic Wall Panels Painting and Finishing DIVISION 23 - HEATING, VENTILATING AND AIR CONDITIONING SECTION 230500 230513 230529 230548 230553 230593 230700 230993 233113 233300 233416 233713 238216 Common Work Results for HVAC Common Motor Requirements for HVAC Equipment Hangers and Support for HVAC Equipment Vibration and Seismic Controls for HVAC Equipment Identification for HVAC Equipment Testing, Adjusting and Balancing HVAC Insulation Sequence of Operations Metal Ducts Air Duct Accessories Centrifugal HVAC Fans Diffusers, Registers and Grilles Air Coils Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 TOC-2 Table of Contents July 28, 2010 DIVISION 26 - ELECTRICAL SECTION 260500 260519 260529 260533 260548 260553 262200 262416 262726 262813 262816 262913 264313 Common Work Results for Electrical Low Voltage Electric Power Conductors and Cables Hangers & Supports for Electrical Systems Raceway & Boxes for Electrical Systems Vibration and Seismic Controls for Electrical Systems Identification for Electrical Systems Low Voltage Distribution Transformer Panelboards Wiring Devices Fuses Enclosed Switches and Circuit Breakers Enclosed Controllers Transient Voltage Suppression for Low-Voltage Electrical Power Circuits Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 TOC-3 Table of Contents July 28, 2010 DIVISION 01 GENERAL REQUIREMENTS SECTION 01 00 00 CONTRACT DOCUMENTS A. CONTRACT DOCUMENTS 1. The Contract Documents are for the renovation of Roosevelt Hall to create temporary office, practice and classroom spaces for the Music Department. Building is occupied however all spaces to be renovated will be vacant. 2. The Contract Documents include: the “Roosevelt Hall Renovation Drawings from Pfeiffer Partners Architects (PPA shown hereafter as AE), dated July 28, 2010”; "Contract Specifications"; "Instructions to Bidders and General Conditions"; the "Form of Proposal", and all amendments and addenda, all of which govern the Work of this Agreement. 3. These Contract Documents provide required specifications for Architectural, Mechanical, Electrical, and Plumbing work. Any variation, discrepancy or conflicting information found by Contractor shall be brought to the attention of Hill International, Inc. (shown hereafter as Hill or CM), acting on behalf of “The City University of New York” (CUNY), specifically CUNY Department of Design, Construction, and Management (CUNY DDCM). 4. Contractor is responsible for all items of Work included in the specifications and on the drawings. 5. Contractor shall be fully responsible for coordination between all of his/her subcontractors. a. The Specifications that follow define the Work as follows: General Construction Division 1 – General Requirements Divisions 4, 8, 9, 23, 26 6. The scope of work for each trade is listed below and described in detail in the Project specifications. All items included in Specifications are considered part of Contractor’s Project scope of Work. Any discrepancies in the Specifications shall promptly be brought to the attention of the CM. 7. Note that all provisions listed in Div. 1 General Requirements of the Specifications herein apply to Contractor and subcontractors except where noted. B. GENERAL PROVISIONS 1. Hill International, Inc. is acting as Construction Manager (CM) on behalf of CUNY DDCM with regard to the procurement and management of subcontractor(s) for this work. Throughout this document, all references to Hill and/or CM are as CUNY’s representative. Unless specified, all communication and documentation will be through Hill. Div. 01 General Requirements Page 1 of 53 2. Bidders are cautioned to read carefully the Specifications for all Work included in this Agreement. Bidders are responsible for ascertaining that the Specifications have the correct number of pages. The prospective bidder must visit the Site to ascertain the full nature and extent of the Work required. 3. Contractor's Base Bid as accepted by the CM includes the total cost to CUNY of all Work required by the Contract Documents. Prior to commencing construction Work, verify dimensions and existing conditions at the job Site. Contractor shall report to the CM any conditions which will prevent proper performance of Work. Contractor shall immediately notify the CM in writing of any discrepancies between the Contract Documents and field conditions which affect the Work. 4. Contractor and subcontractors shall take whatever precautions necessary to protect the property of CUNY and its Occupants from damage or loss arising out of their execution of this contract. Contractor shall assume responsibility for any such damage or loss caused by them and shall, at his/her own expense, repair or replace any property that becomes damaged or destroyed. Together with the CM, the CUNY DDCM Construction Project Manager shall determine whether affected property has been damaged to such an extent that it cannot be restored to its original condition and must be replaced. 5. All Work at the Site shall be done in a neat and clean manner by experienced and capable workers. Workmanship shall be of superior quality. Work will be controlled by the Hill Construction Project Manager and work that is performed improperly, poorly made construction and non-approved changes in specified materials will be rejected and satisfactory corrections shall be made at Contractor's sole cost and expense. 6. Neither the Contractors staff nor the subcontractors staff are allowed to discuss any aspects of the Project, their work, or the scheduling of work with any College Personnel, without permission of the CM; all discussions shall be directed to the CM. Any violation of this will result in the removal of the offending party from the project for the duration of the project. 7. No work shall be scheduled or performed in such a manner that New York City Building Department and Fire Department Code requirements for building occupant emergency egress are violated. 8. The Contractor, its workers and agents, shall at all times maintain their work areas in a clean and orderly manner to safeguard the College Population. Upon completion of the day’s work, the area shall be free of debris with the floor swept and the area left dust free. The Contractor is responsible for removal and proper placement of their debris within containers. If the Contractor is found to be placing debris in an unsafe manner, they will be notified to immediately correct the unsafe condition. If notification is left unheeded, the Contractor shall be back=charged for correcting the condition. 9. For the health and safety of the Contractor and all other personnel, the Contractor shall take all necessary precautions and measures to control and minimize the spread of dust and debris in the building. The Contractor shall install additional temporary enclosures or modify existing enclosures in order to limit any such debris or dust entering occupied spaces at the direction of the CM. Div. 01 General Requirements Page 2 of 53 10. The Contractor shall produce their own Site Specific Safety Program and submit it to the CM for review and acceptance. Each Site Specific Safety Program shall meet, at a minimum, the requirements of the Project Site Safety Plan adopted by the CM. The Contractor shall execute the requirements of the Site Safety Plan and address the violations noted by the Site Safety Manager. 11. Comply with applicable federal and State of New York Right-to-Know Law provisions and supply copies of the appropriate Material Safety Data Sheets (MSDS) to the CM. 12. Contractor will supply the CM with a telephone number or method to contact the supervisor for the Work in case of an emergency after work hours, including weekends and holidays. 13. Work hours shall be as established by the CM. No work may be performed at any other time without written authorization from the CM. 14. Workers are required to be dressed in accordance with OSHA and Construction Industry Standards. No sleeveless shirts, shorts, sneakers, etc. shall be worn at any time. 15. The Contractor and its workforce shall promptly arrive at the Campus at the beginning of each workday and directly proceed into the construction site area. Loitering at anytime within the other areas or other campus buildings is prohibited. 16. The Contractor and its workforce shall promptly leave the Campus at the end of the workday. 17. There shall be NO smoking in any College building or tunnel in accordance with CUNY policy and NYS Law. All smoking materials must be properly disposed. 18. No worker is permitted to fraternize with or otherwise engage the student population. Doing so shall result in the immediate removal of the worker by the Campus Security Force. 19. Anyone removed by the College Security Force will be BANNED FROM THE JOB SITE for the duration of the Project. 20. Contractor or Sub-Contractors shall possess the appropriate licenses for all the Work of their trades that require licenses by any Federal, State or Local Law or Agency having jurisdiction there of. 21. Electrical work shall be done by or under the Supervision of an electrician possessing a master electrician’s license issued by the City of New York. 22. Plumbing work shall be done by or under the supervision of a plumber possessing a master plumber’s license issued by the City of New York. 23. Welding work if required shall be done by NYC DOB Certified welder. 24. Project Coordination: It is essential that the General Contractor coordinate the work of the subcontractors of the various trades, General Construction; Mechanical (HVAC); Plumbing; and Electrical to create the least possible hardship to all parties involved. Major areas of concern include storage of materials, use of Site, access to areas of work, etc. The specification sections address most foreseeable areas of conflict but do Div. 01 General Requirements Page 3 of 53 not necessarily mention every condition requiring coordination. Contractor shall fully cooperate and coordinate the Work of this Agreement with activities of CUNY and other contractors working at the Site, at no additional cost to CUNY. 25. Prior to proceeding with any Work, obtain all necessary work permits from the NYC Department of Buildings and other public agencies which have jurisdiction. Prepare, file and submit to such agencies for their approval all required plans and applications; obtain all necessary work permits and certificates of compliance and deliver same to CUNY. These documents shall be posted as required. 26. It is Contractor’s responsibility to take field measurements and verify all dimensions and field conditions upon which the new work is in any way dependent for accurate and correct workmanship. Contractor's Base Bid, as accepted by CUNY, includes the total cost to CUNY of all the Work of all trades required by the Contract Documents. There will be no adjustments of the contract price due to field measurements and conditions differing from those specified in contract specifications. 27. The apparent silence of the contract documents regarding any detail of the specified Work or the apparent omission of a detailed description of Work to be done or materials furnished shall be regarded as meaning that only the best general practice is to be used and interpretation of these documents shall be made upon that basis. Should any conflict occur in the contract Specifications, Contractor shall be deemed to have bid on the most expensive way of doing the Work unless he/she has asked for and obtained a written decision from the CM resolving the conflict prior to the bid closing date. 28. Contractor shall start duly authorized Work and continue on a full time work program until completed. Failure to maintain a full time work schedule will be considered grounds for the denial of requests for extensions to the time for completion of the Work under the Agreement. SECTION 01 11 16 SUMMARY OF WORK PART 1 - GENERAL 1.1 A. 1.2 A. RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. SUMMARY Section Includes: 1. 2. Project information. Work covered by Contract Documents. Div. 01 General Requirements Page 4 of 53 3. 4. 5. 6. 7. 8. 1.3 A. PROJECT INFORMATION Project Identification: Roosevelt Hall Renovation 1. B. Work by Owner. Access to site. Coordination with occupants. Work restrictions. Specification and drawing conventions. Miscellaneous provisions. Project Location: 11210 Brooklyn College 2900 Bedford Ave. Brooklyn, New York Owner: The City University of New York 1. Owner's Representative: CUNY Dept. of Design, Construction & Management 555 West 57th Street, 10th Floor New York City, New York 10019 C. Architect: Pfeiffer Partners Architects, P.C.: 62 White Street, Ste. 5E, New York, New York 10013 (212) 625-3911 D. Architect's Consultants: The Architect has retained the following design professionals who have prepared designated portions of the Contract Documents: E. 1. MEP / Acoustical Engineering: Arup 155 Avenue of the Americas New York City, New York 10013 (212) 897-1411. 2. Matrix / New World Engineering, Inc.: 120 Eagle Rock Ave., Ste. 207 East Hanover, New Jersey 07936 (973) 240-1800 Construction Manager (CM): Hill International, Inc. One Penn Plaza Suite 3415 New York, NY 10119 (212) 244-3700. 1. F. Construction Manager has been engaged for this Project pursuant to a Construction Management/Build Services Agreement between the Owner and the CM. Document Control: Document Control will be provided and administered by the Construction Manager for purposes of managing communication and documents during the Project. There is no cost to the Contractor. 1. Upon award of the Agreement for General Construction, the CM will provide further information on the Document Control System that will be utilized during the Project. Document Control for managing communication and documents will be provided and administered by the CM at no cost to the Contractor. Div. 01 General Requirements Page 5 of 53 1.4 A. B. WORK COVERED BY CONTRACT DOCUMENTS The Work of Project is defined by the Contract Documents and consists of the following: 1. General Scope: The project includes renovation of limited areas within existing Roosevelt Hall on the Brooklyn College campus and includes construction of new partitions, doors and hardware. Limited electrical and mechanical work is included to provide for use of the newly configured spaces for classroom instruction. Limited remediation of asbestos and other hazardous materials will be required. 2. Demolition: Limited removal of hazardous materials will be required as described in the report attached to the specifications. Wherever possible, finishes are left in place to avoid disturbing adhesives and backing containing hazardous materials. 3. Build spaces for new Recording Studio, Choral / Opera Rehearsal, Music Rehearsal, large music classrooms, and individual and small ensemble music practice rooms. 4. Interior partitions, painting, and acoustical finishes where noted. 5. Suspended acoustical ceilings 6. New hollow metal doors and frames, hardware and acoustical seals 7. No structural work required 8. New HVAC work limited to transfer ducts, grilles and diffusers to redirect air flow 9. Salvage and reuse existing light fixtures, provide new fixtures to match where required. 10. Provide electrical outlets, switching to meet code and control new lighting. 11. Modification of fire alarm system to reflect new room layouts. 12. New signage. Type of Agreement: 1. 1.5 A. Project will be constructed under a single prime agreement. WORK BY OWNER General: Cooperate fully with Owner and CM so work may be carried out smoothly, without interfering with or delaying work under this Agreement or work by Owner. Coordinate the Work of this Agreement with work performed by Owner. Div. 01 General Requirements Page 6 of 53 B. Preceding Work: Owner will perform the following construction operations at the Project site. Those operations are scheduled to be substantially complete before work under this Agreement begins. 1. C. D. Concurrent Work: Owner will perform the following construction operations at the Project site. Those operations will be conducted simultaneously with work under this Agreement. 1. Owner will require coordination of construction to minimize disruption of ongoing use of adjacent areas of this and surrounding buildings. 2. Owner will provide IT installations for all telephone, fax, and computer / data requirements. Subsequent Work: Owner will perform the following additional work at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Agreement. 1. 1.6 Owner will deliver the area clear and free of obstructions and other stored materials.. Owner will coordinate move of program activities from other parts of the campus into the renovated areas of Roosevelt Hall. ACCESS TO SITE A. General: Contractor shall have full use of Project site, as directed by the CM, for construction operations during construction period. Contractor's use of the Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project. B. General: Contractor shall have limited use of Project site for construction operations as indicated on Construction Documents, the Agreement, and the limits and as indicated by requirements of this Section. C. Use of Site: Limited use of the Project site to work in areas within the Agreement limits as indicated in the plans and specifications. Do not disturb portions of Project site beyond areas in which the Work is indicated. 1. 2. Limits: Confine construction operations to interior portions of existing Roosevelt Hall. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to CM, Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. a. b. Schedule all deliveries through the CM; minimize use of driveways and entrances by construction operations. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. Div. 01 General Requirements Page 7 of 53 D. 1.7 A. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations. COORDINATION WITH OCCUPANTS Partial Owner Occupancy: Owner and/or CM will occupy the building and premises during entire construction period, with the exception of areas under construction. Cooperate with Owner and CM during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with CM’s and Owner's operations. Maintain existing exits unless otherwise indicated. 1. 2. B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work. 1. 2. 3. 1.8 A. Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work. On final sign-off, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work. WORK RESTRICTIONS Work Restrictions, General: Comply with restrictions on construction operations. 1. B. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from CM or Owner and authorities having jurisdiction. Provide not less than 72 hours' notice to CM of activities that will affect Owner's operations. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7 a.m. to 6 p.m., Monday through Friday, unless otherwise indicated. 1. 2. Weekend Hours: Only as approved by CM and CUNY with minimum 48 hours notice to CM. Early Morning Hours: No noise before 7:00 AM under any circumstances. Div. 01 General Requirements Page 8 of 53 3. 4. C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated: 1. 2. D. Hours for Utility Shutdowns: As coordinated with CM and not to affect student activities on campus. Hours for Core Drilling As coordinated with CM and not to affect student activities on campus. Notify Construction Manager in writing not less two (2) days in advance of proposed utility interruptions. Obtain Construction Manager's written permission before proceeding with utility interruptions. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with CM. 1. 2. Notify Construction Manager in writing not less than two (2) days in advance of proposed disruptive operations. Obtain CM’s written permission before proceeding with disruptive operations. E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet (8 m) of entrances, operable windows, or outdoor-air intakes. All smoking materials must be disposed of in appropriate trash receptacles. F. Controlled Substances: Use of tobacco products and other controlled substances is not permitted, except in designated smoking areas. G. Employee Identification: Brooklyn College will provide identification tags for Contractor personnel working on the Project site. Require personnel to use identification tags at all times. H. Employee Screening: Comply with Owner's requirements for any and all drug and background screening of Contractor personnel working on Project site. 1. 1.9 A. Maintain list of approved screened personnel with CM and Owner's representative. SPECIFICATION AND DRAWING CONVENTIONS Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows: 1. 2. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase. Specification requirements are to be performed by Contractor unless specifically stated otherwise. Div. 01 General Requirements Page 9 of 53 B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications. C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products: 1. 2. 3. 1.10 A. 1.11 Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual. MISCELLANEOUS PROVISIONS In the event that additional storage is required, permission may be obtained through proper, advance notification through the CM. Contractor may be required to provide fenced-in enclosure per requirements set forth in the General Requirements. All costs and/or expenses thereof shall be the responsibility of the Contractor. COORDINATION OF TRADES General: Contractor is responsible for coordination between all of his subcontractors. Contractor shall do the following work: Cores and other necessary penetrations in vertical or horizontal built surfaces for ducts, sleeves, pipes, conduits, and other such elements. All required insulation and/or firestopping around all ducts, pipes, conduits etc. Installation and connection of all devices and equipment. Final surface finishes upon completion of work, including but not limited to final painting of all surfaces. 1.12. ADDITIONAL SCOPE OF WORK REQUIREMENTS 1. Scaffold Design Drawing: A "Scaffold Design Drawing" as per Section BC 3314 of the 2008 New York City Building Code shall be made available to the Building Commissioner at the job Site, and submitted as specified. 2. Contractor shall provide sidewalk shed drawing and other protection for pedestrians as required by Section BC 3307 of the 2008 NYC Building Code. 3. Contractor shall provide a Noise Reduction Plan and noise reduction barriers as required by the NYC DEP and NYC Local Law 113. 4. Contractor shall submit a Final Contract Progress Schedule in the form of a critical path Div. 01 General Requirements Page 10 of 53 chart, outlining phases and critical dates involved for completion of the Work, showing the sequence in which the Work will progress. 5. As per Article 42.6 of the Agreement, Contractor shall submit a final Detailed Bid Breakdown of Contract Price outlining all material and labor costs for the Work including accurate materials list from subcontractors in a format approved by the CM. SECTION 01 26 00 MODIFICATION PROCEDURES A. RELATED SECTIONS 1. Instructions to Bidders` B. MODIFICATIONS 1. Authorization for additional or deleted Work shall be by written direction or bulletin only. C. REQUESTS FOR INFORMATION (Prior to Bid) 1. Contract Documents shall be thoroughly reviewed by all bidders prior to submitting bids and any conflicts or inadequacies of the Contract Documents should be brought immediately to the attention of the CM in writing. No adjustment of the contract price will be made due to the failure of Contractor to familiarize himself/herself with ALL Contract Documents or to request information in writing prior to the bid date. 2. Contractor shall attend the mandatory Pre-Bid meeting for further information on the Project. All questions must be sent in writing to Hill and answers will be issued to all parties in a bid addendum. 3. The form to request information is provided in Section IX, Attachment C of the Invitation to Bid. D. REQUESTS FOR INFORMATION (Subsequent to Bid) 1. Before submitting a request for information, Contractor shall review all relevant Contract Drawings and Specifications carefully, in order to avoid unnecessary delays due to unseen or unread information. This shall include all addenda, bulletins, and previously issued replies to requests for information or clarification. 2. Requests for Information (“RFI”) by Contractor subsequent to the opening of bids shall be submitted in writing to the CM. 3. All Requests for Information shall be submitted in a timely manner so as not to cause delays to the Work of any of the four contracts. 4. No orders shall be placed by Contractor unless Contractor has received approval of all necessary and required shop drawings and submittals. No compensation shall be made to Contractor for losses due to a failure on his/her part to request the information necessary to place a correct order. Div. 01 General Requirements Page 11 of 53 5. It shall be the responsibility of the Contractor to incorporate into the work the information received in a reply to an RFI.. SECTION 01 30 00 ADMINISTRATION OF CONTRACTS AND PROJECT PROCEDURES A. RELATED SECTIONS 1. 01 26 00 Modification Procedures 2. 01 31 19 Project Meetings B. ADMINISTRATION OF CONTRACTS 1. The Work shall be under the direction and supervision of Hill as a representative of CUNY’s Department of Design, Construction, and Management, Construction Division. Contractor shall notify Hill, in writing of the date the Work shall begin. Such notification to be received by Hill at least five (5) business days prior to commencement of Work. Correspondence shall be addressed to: Joseph Rhoades Hill International, Inc. One Penn Plaza, Suite 3415 New York, NY 10119 (T) 212-244-3700 josephrhoades@hillintl.com C. PROJECT PROCEDURES 1. Contractor must commence work within three (3) days after the date specified in a written Notice to Proceed from the CM and continue on a full-time work program. The Work shall be fully complete in the time set forth in the Bid Documents. 2. Each work day, Contractor and subcontractors shall sign Contractor Log upon arrival and before leaving the Project grounds and provide a list of all employees and titles and the last four digits of the SSN, and their work location for the day. At the start of each day Contractor and subcontractors shall inform the CM Construction Project Manager as to the location and scope of Work planned. Any condition which might adversely affect college occupants whether during the workday or after close of operations shall be reported to the CM Construction Project Manager promptly. 3. Conduct operations under this Agreement in such a manner as to allow, at all times during the performance of the Work, ingress and egress for the occupants and public with CUNY’s cooperation. Contractor, through the CM, shall notify and cooperate with the CUNY’s representatives to coordinate his/her work to meet this condition. Div. 01 General Requirements Page 12 of 53 4. Contractor shall be responsible to provide the CM with a two-week look ahead schedule; in addition, the Contractor will notify the CM Construction Project Manager on his/her arrival at the Project with his/her field force and/or equipment prepared to perform the work, and every day thereafter that he/she intends to perform work until this Agreement is completed. Any Work done without previous notification to the CM Construction Project Manager may be rejected. Any deviation from the two-week look ahead schedule must be approved by the CM. 5. Contractor shall be prepared to coordinate work so as to minimize disruption to the College. 6. Work shall be provided without disruption of services to any portion of the College. Where existing utilities serving the buildings are required to be shut off, notify CUNY through the CM in writing at least 7 days in advance. It shall be the responsibility of Contractor to notify and make all arrangements with the Utility Company or other authorities having jurisdiction over such utility. D. CONTRACTOR USE OF THE PREMISES 1. During the construction period Contractor shall have full use of the premises within Construction Limits shown on the Contract Drawings for construction operations. Contractor's use of the premises is limited only by Project phasing, egress, CUNY's right to perform Work, or to retain other contractors on portions of the Project. 2. Contractor may not use or disturb any portions of the Site beyond Construction Limits specified without specific written permission of CUNY DDCM. 3. Contractor shall be responsible to keep all existing entrances and exits serving occupied buildings clear with an unobstructed path to the nearest street. SECTION 01 31 00 PROJECT COORDINATION A. GENERAL 1. It shall be Contractor's responsibility to formulate a schedule of work and coordinate the work on this schedule with the subcontractors, including sequence in which the work will progress throughout this project. 2. The Contractor shall prepare a baseline schedule showing milestones and sequence of work. In addition, the contractor shall prepare update/progress schedules for review at the project meetings. These schedules will be in two parts: work completed and 2 week look ahead. 3. If through no fault of a Contractor or Sub-contractor the approved progress schedule is not adhered to, the affected Contractor shall promptly notify the CM in writing of the effects of such condition. Failure to do so shall constitute a waiver by Contractor of any and all claims for damage or delay arising therefrom. Div. 01 General Requirements Page 13 of 53 B. PRIMAVERA 1. WORK INCLUDED a. General: This Section specifies administrative and procedural requirements for the scheduling and reporting progress of the work. b. The Preliminary Construction Schedule is included in the submission requirements of the Contract under Section 01 32 13 General Requirements. (a) CPM SCHEDULE DETAIL: Contractor shall provide a schedule with sufficient detail and clarity of form; and so they shall utilize the CPM schedule to properly control, monitor and follow progress for all portions of the work. The CPM schedule shall comply with the various limits imposed by the scope of work and any contractually specified intermediate milestone dates and completion dates, including milestone inspections and sign-offs by CUNY and other agencies having jurisdiction. The degree of detail shall be to the satisfaction of the CM. This will be the baseline schedule for the project. 2. PROJECT SCHEDULES: a. At each Project Job Meeting, Contractor shall be responsible to provide the CM with a two-week look ahead schedule. In addition, the Contractor will notify the CM Construction Project Manager on his/her arrival at the Project with his/her field force and/or equipment prepared to perform the work, and every day thereafter that he/she intends to perform work until this Contract is completed. Any work done without previous notification to the CM Construction Project Manager may be rejected. Any deviation from the two-week look ahead schedule must be approved by the CM. b. At each bi-weekly update meeting, Contractor shall submit a list of each activity that was worked on in the previous period, including the date the activity started, the percentage complete as of the update, the date the activity was completed, and the status of any associated long lead items. This information will be reviewed, and corrected as necessary, at the meeting to insure that it accurately reflects the actual progress of the work. Contractor will report on areas completed, areas losing time, and areas picking up time. For any area losing time, give the amount of time lost, the reason, the resolution, and the plan for making up the lost time. An updated baseline schedule will be needed: (1) When a change or delay significantly affects specified immediate milestone dates or completion dates or the sequence of activities. (2) When Contractor elects to change any sequence of activities affecting the critical path or to significantly change the previous approved work plan. (3) When in the opinion of the CM the status of the work is such that the schedule is no longer representative for planning and evaluation of the work. Div. 01 General Requirements Page 14 of 53 Responsibility of Contractor: Contractor is advised that acceptance of the baseline schedule by the CM does not relieve Contractor of any contractual obligations for scheduling of work or construction procedures or any other requirements of the contract, and that the schedule shall not be utilized for the purpose of making claims for delay or other claims against the CM or CUNY for any reason whatsoever. Contractor is bound to the completion dates established in their Agreement with the CM. SECTION 01 31 19 PROJECT MEETINGS A. RELATED SECTIONS 1. 01 30 00 Administration of Contracts and Projection Procedures B. Pre-Construction Kick-Off Meeting: Contractor and subcontractors shall attend a kick-off job-Site meeting with the CM and attended by the stakeholders prior to commencing any work. All Contract Documents shall be reviewed at this meeting. C. Job Meetings: Separate Weekly job meeting shall be held at the job Site between the CM, Contractor and subcontractors. CM shall fix the time for the meeting in consultation with Contractor. The job meeting schedule may be changed to bi-weekly at the discretion of the CM. All requirements for the weekly meetings would apply. D. During the course of the Contract Work the Contractor and all subcontractors shall attend jobsite meetings with the CM. SECTION 01 33 00 SUBMISSIONS A. RELATED SECTIONS 1. 01 77 19 Contract Closeout B. SUBMITTAL SCHEDULE 1. Contractor shall submit a preliminary list of submittals and schedule of dates for submission as stipulated in the Contract Documents and as required for the execution of the Work. (See attached sample in paragraph I. herein.) All submissions must be transmitted to the CM in a timely manner to ensure that the AE has adequate time to review without impacting the schedule. Contractor will submit the list and schedule on hard copy and electronically, with submission numbers clearly noted. The CM will review proposed lists and schedules for acceptance and submit any revisions necessary. Time frames are to be given in consecutive calendar days, not number of working days. Such schedules shall be submitted at the Project Pre-Construction conference. 2. The following guidelines shall apply: Div. 01 General Requirements Page 15 of 53 a. Phase 1 Submissions: Long lead items, preparatory work items and other items required for the Work to start, shall be submitted within fourteen (14) days after Notice to Proceed: 1. Work permits 2. Temporary facilities/utilities drawings and permits 3. Storage area location(s) 4. Project schedules, procedures, and phasing plan 5. Scaffolding (if required): drawings, specifications and permit(s) 6. Security and Site utilization plan 7. Pest control plan 8. Preliminary coordination drawings b. Phase 2 Submissions: All technical and product data, shop drawings, samples, ongoing submittals such as monthly progress reports, progress photographs, and submission items which are not required for the Work to start, will be submitted according to the approved submittal schedule. c. Phase 3 Submissions: Items such as guarantees, warrantees, as-built drawings, reports, installation certificates, operation or maintenance manuals, quality control testing, lab reports, and permits (including all Agency approvals and sign-offs) will be accepted no later than thirty (30) days prior to the approved Project date of final completion, or as mandated by time frames set by any Agency having jurisdiction over the Project. 3. The submission schedules shall indicate dates when each item will be sent by Contractor to the CM/AE for their review and approval. 4. Contractor shall be responsible for strict adherence to approved schedules unless a written request for deviation from the schedule is made to the CM. The request shall not be valid until approved. 5. Submit all shop drawings, samples and product data from each specification section at the same time, unless otherwise noted in the approved Submissions schedule. 6. Final payment to Contractor will not be released until all approved submissions of all phases are received, checked and approved. 7. Submissions returned for corrections shall be resubmitted with the required corrections made within ten (10) consecutive calendar days, calculated from the date of receipt of the returned submission(s) by Contractor. The procedure shall be repeated as many times as required, until final submissions are obtained that require no further correction. 8. Rejected submissions shall be resubmitted with the required corrections made within ten (10) consecutive calendar days, calculated from the date of receipt of the returned submission(s) by Contractor. The procedure shall be repeated as many times as Div. 01 General Requirements Page 16 of 53 required until final submissions are obtained that require no further correction. C. DISTRIBUTION OF SUBMISSIONS 1. Distribution of all submissions shall be as indicated below. D. LOCATIONS: Manager. Submissions and/or transmittals are to be delivered to the CM Project E. DISTRIBUTION OF PRODUCT DATA, SAMPLES AND SHOP DRAWINGS 1. General Construction Submissions a. Contractors shall submit product data, samples and shop drawings to CM Project Manager. b. Product Data: a total of seven (7) copies shall be submitted. c. Samples: a total of three (3) samples shall be provided. F. SUBMISSION REQUIREMENTS, GENERAL 1. Contractor must be prepared to submit documents electronically if that method is found to be in the best interest of the Project. 2. Contractor submissions shall be accompanied with a dated transmittal letter, indicating the contract number, Facility name, and the applicable specifications section number. Submittals not accompanied by a clear transmittal will not be accepted. 3. Contractor shall be responsible for the pickup of all unacceptable or rejected submissions. 4. Contractor shall check all submittals for accuracy, completeness, dimensions, clearances, connections, accessibility, servicing, maintenance, and compliance with the Contract Documents, including changes by addenda, change orders, and coordination drawings of related trades. In addition, Contractor shall verify all field measurements and conditions. Submissions shall bear Contractor’s stamp of approval as evidence that they have been so reviewed. Contractor shall then transmit the submission(s) for review. Submissions that do not fully comply with these requirements will not be accepted. 5. Duplication or tracing of contract drawing details will not be accepted and will be rejected without comment or notations. Shop drawings prepared by a fabricator are a contract requirement and the fabricator shall be obligated to Contractor as to the accuracy of all work. All costs incurred to meet this requirement shall be borne by Contractor and shall be included in the base bid. 6. All shop drawings prepared by the fabricator shall be based on field dimensions taken by the fabricator. 7. The shop drawing(s) shall show in detail all components, finishes, fabrication and installation methods, relationship to adjoining work on shop drawing(s), sizes, Div. 01 General Requirements Page 17 of 53 dimensions, sections, gauges, connections and anchors. Include on each sheet information as to vendor's name, drawing(s) number, date drawn, revision number and revision date. Contract Drawings submitted as shop drawings WILL NOT BE ACCEPTED 8. Shop drawings, product data etc. shall be submitted either in paper form or electronically as directed by the CM. Submissions by fax shall not be accepted. 9. Acceptance of a separate item shall not be interpreted as acceptance of an assembly in which the item functions. The right is reserved by the CM to require submissions of details, shop erection, coordination or setting drawings, and of any schedules for any part of the Work, whether or not specifically mentioned in Specification Sections, where substitutions or modifications are proposed by any Contractor or where such information is essential to the proper assembly, coordination or execution of the work under the Agreement. 10. The items listed in Contractor’s submissions list do not limit Contractor’s responsibility from submitting Shop Drawings, Product Data or Samples for all equipment, accessories and operations that are to be provided under this contract. There will be no adjustment to the contract price to compensate Contractor for submissions requested which are not specifically listed. 11. All substitutions requested by Contractor shall be supported by comparison sheets for both the specified item and the proposed substitution, showing all necessary equivalent information for both. Submissions including only information on the proposed substitution will not be accepted. 12. All shop drawings shall be printed to scale, and the scale identified in the title block of the drawing. 13. All items of related equipment in a system shall be the product of one manufacturer, and shall be submitted together at one time, unless otherwise noted in the schedule. The submissions for a system shall consist of original catalog cuts accompanied by an enclosed table of contents. This table of contents shall contain a list of all equipment proposed to be used, giving the manufacturer’s name, trade name, catalog number or other positive means of identification for each item. 14. The term "w/color chart" refers to the submittal of a manufacturer's full assortment of colors available for the specified product. Submittals shall be in color. Black and white copies are not acceptable. 15. Where physical samples are required, two samples shall be submitted for each item except in the case of finishes (flooring, paint, exposed masonry, paving, etc.), in which three samples shall be submitted. 16. Deviations from the Contract Documents shall be clearly marked, indicating component and system variations, additions, deletions, revised equipment locations, construction detail variations, substitutions, and similar changes. Include a written description of the reason for the deviation, indicating headroom heights, ceiling heights, clearances, and other dimensions affected by the proposed deviations. All variations from the Contract Documents not brought to the attention of the CM in this manner shall be the sole responsibility of Contractor even when such submittal has been accepted. Div. 01 General Requirements Page 18 of 53 17. Contractor's Responsibility: The CM/AE review and acceptance shall not relieve Contractor from responsibility for error in shop drawings or for proper coordination and assembly of materials and equipment with other work; nor from the responsibility of furnishing materials and labor not indicated on the shop drawings, but required by the Contract Documents for completion of the Work. 18. Equivalent Quality of Materials: All materials and equipment which are designated in the Specifications by a number in the trade name are designated for the purpose of describing the article and fixing the standard of the quality and finish. Materials and equipment which are, in the opinion of CUNY DDCM, the equivalent to that specified, will be accepted. Contractor shall be responsible for any and all costs associated with providing any substitute material and/or equipment. 19. No Work shall be fabricated, or materials delivered to the Site, until final approval of all shop drawing(s) and other required submissions for that work has been obtained. Final approved copies of all shop drawing(s) must be completed without added corrections, notes or comments, in pencil or ink on the white prints or blueprints. At the time of submission, Contractor shall call to the attention of the CM, in writing, to any deviations from the Contract Documents contained on the Shop Drawing(s). The approval of the Drawing(s) containing deviations not specifically brought to the attention of the CM or containing errors or omissions of any sort, shall not relieve Contractor of the responsibility for executing the Work in accordance with the Contract Documents. 20. Final payment to any Contractor will not be released until all approved submissions of all phases are received, checked, and approved. 21. In submittals requiring manufacturer's literature, provide complete installation instructions for specified product and any associated miscellaneous material required to complete installation. 22. The submission of any material, or article, as the equal of the materials or articles set forth in the specifications as a standard shall be accompanied by illustrations, drawings, descriptions, catalogs, records of tests, samples and any other information for both the specified item and the potential substitute item essential for judging, the quality and the materials, finish and durability of that specified as standard, as well as information indicating satisfactory use under similar operating conditions. 23. Where contractor is submitting a commodity exactly as specified, i.e. identical manufacturer / model, and a catalog cut is not necessary for color selection or other specified purpose, Contractor may submit a letter on the company’s letterhead, signed by a principal of the company, attesting to this fact, in lieu of the catalog cut. 24. Identify each submission by the Submission Control Number assigned on the Submission List. The control number shall be clearly written on the upper right hand corner of each catalog cut, incorporated into the title block of all shop drawings, included on all transmittals, and on identifying labels affixed to all samples. Items not submitted in this format will be rejected without review. 25. In the event that all or any portion of a submission is rejected due to nonconformance with the CMs packaging and labeling requirements, or for any other reason, Contractor shall tender a new submission conforming to contract requirements within (10) ten Div. 01 General Requirements Page 19 of 53 consecutive calendar days, calculated from the submission’s rejection date. In no event shall a Contractor be permitted to tender submissions beyond the dates contained in the approved Submissions schedule without written approval of the CM. 26. Rejected submissions are to be returned to Contractors directly. 27. No work shall be fabricated, manufactured, or installed from shop drawings stamped "Revise and Resubmit" or "Rejected", and such shop drawings shall be corrected and resubmitted by the Contractor until accepted by the Architect. At least one complete set of "No Exceptions Taken and/or Make Corrections Noted" shop drawings shall be kept at the site in the Contractor's field office for reference at all times. "Revise and Resubmit" or "Rejected" shop drawings shall not be permitted at the site. 28. Submittals marked “No Exceptions Taken”: Submittals which require no corrections by the Architect will be marked "No Exceptions Taken". 29. Submittals marked "Make Corrections Noted": Submittals which require only a minor amount of correcting shall be marked "Make Corrections Noted". This mark shall mean that checking is complete and all corrections are obvious without ambiguity. Fabrication will be allowed on work marked "Make Corrections Noted" provided such action will expedite construction and noted corrections are adhered to. If fabrication is not made strictly in accordance with corrections noted, the item shall be rejected in the field, and the Contractor will be required to replace such work in accordance with corrected submittals. 30. Submittals marked "Revise and Resubmit" or "Rejected": When submittals are contrary to contract requirements or too many corrections are required, they shall be marked "Revise and Resubmit" or "Rejected". No work shall be fabricated under this mark. The Architect shall list his reasons for rejection on the submittals or in the transmittal letter accompanying their return. The submittals must be corrected and resubmitted for approval. Div. 01 General Requirements Page 20 of 53 I. SAMPLE SUBMISSION SCHEDULES SUBMISSIONS LIST Brooklyn College Roosevelt Hall Renovation Contractor Name: Address: Phone: Fax: CSI Section HILL Control No. Item Description L Div. 01 General Requirements Page 21 of 53 D S Submission Phase (I, II, or III) SECTION 01 35 29 SITE SECURITY A. GENERAL SECURITY 1. Any personnel working on this Project shall not bring or consume alcoholic beverages or controlled substances at the factory and the Site and shall not be under the influence of drugs or alcohol during operating hours. 2. Any personnel working on this Project employed by Contractor and/or Sub-contractor shall wear a Worker I.D. Badge at all times. 3. Any personnel working on this Project shall not remove scrap or salvage material or grant any third party access to do so without the permission of the CM Construction Project Manager. 4. Scrap or waste material scheduled to be removed shall be removed only during designated times and under supervision of those stated above. 5. The Contractor shall protect all property from damage, and the public against hazard or injury. 6. The Contractor shall provide and maintain fencing, footbridges, warning lights, signs, watchers, flaggers, or other personnel as required by 2008 NYC Building code, Section BC 3307, for the maintenance of the Site and adjacent areas to the extent required by law. 7. The Contractor shall maintain access to firefighting facilities at the Site at all times. 8. Contractor shall protect and be responsible for existing buildings, new construction, and areas of the facility affected by the Project. Should any portion of the Site be damaged, disturbed or otherwise affected due to work of the Contractor, Contractor shall report the conditions and circumstances to the CM Construction Project Manager and make all necessary repairs and replacements to such damaged work at his/her own expense and with new materials to match existing work in every respect, as approved by the CM Construction Project Manager. 9. Contractor shall properly and completely protect all apparatus included in this Agreement against dirt and damage. Contractor shall be held fully responsible for all damage to apparatus, regardless of ownership, until final acceptance. Any equipment furnished under the Agreement and any property of CUNY damaged or destroyed by Contractor or his/her employees shall be repaired or replaced as necessary without additional cost to CUNY. 10. Contractor shall remove all snow and ice as it accumulates on the sidewalks within the contract limit lines. 11. Contractor shall provide all necessary safety equipment, materials and personnel to protect public walks and grounds within the work areas of this contract so pedestrians, occupants and the public are protected at all times. Div. 01 General Requirements Page 22 of 53 12. Contractor is responsible for the security of the Work Site and shall provide suitable Site protection to prevent unauthorized entry onto the Site, until final acceptance by CUNY. 13. Contractor shall locate all existing utilities and service lines prior to demolition or construction. Notify the utility company or city agency affected, the CM, and CUNY DDCM at least 72 hours in advance, for any removal, relocation, or interruption in services required. Cap all existing utilities as directed. B. BARRIERS AND ENCLOSURES 1. Contractor shall adequately enclose and protect areas against the weather where the installation is incomplete at the end of the working day, and shall be responsible for any damage or inconvenience resulting from a failure to do so. Such protection shall be done to the complete satisfaction of the CM. 2. Provide temporary barricades, including noise reduction barriers, as required. Post signs for safety and provide dust controls as described in Section 01 74 13. Signage must be in place 24 hours prior to the commencement of construction activity. 3. Provide enclosures around piles of separated materials. Locate enclosures out of the way of construction traffic. Provide adequate space for pick-up and delivery and convenience to subcontractors. SECTION 013530 PROTECTION OF RIGHTS, PERSONS AND PROPERTY A. Accident Prevention 1. The Contractor shall, at all times, take every precaution against injuries to persons or damage to property and for the safety of persons on or about the Site or engaged in the performance of the Work. B. Safety Programs 1. The Contractor shall be responsible for the initiation, maintenance and supervision of safety precautions and programs in connection with the Work. 2. The Construction Manager shall provide the Contractor with copies of the safety orientation booklet. The Contractor shall provide copies of the booklet to each of its workers and to each worker of its Subcontractors prior to each worker starting Work. The Contractor shall maintain documentation that each worker received a copy of the safety orientation booklet prior to the worker starting Work. C. Protection of Work and Property 1. The Contractor shall, at all times, guard the Owner’s property from injury or loss in connection with the Work. The Contractor shall, at all times, guard and protect the Contractor’s Work, and adjacent property. The Contractor shall replace or make good any said loss or injury unless said loss or injury is caused directly by the Owner. Div. 01 General Requirements Page 23 of 53 2. The Contractor shall have full responsibility to protect and maintain all materials and supplies on or off Site in proper condition and forthwith repair, replace and make good any damage thereto until construction completion. The Contractor shall maintain an inventory of all materials and supplies for the Project that are delivered to the Site or approved for off-Site storage facilities. 3. The Contractor shall report any loss, theft, burglary, vandalism or damage of materials or installed Work to the Owner by phone and facsimile as soon as it is discovered. If vandalism, theft, or burglary is suspected as the cause of the loss, the Contractor shall notify Site security personnel and the municipal police. The Contractor shall also protect the place of loss until released from protection by the Owner or the Owner’s Representative. The Contractor shall insure that no potential evidence relating to the loss is removed from the place of loss. 4. Should the Contractor feel there is a claim for recovery under the CM builders risk insurance, a fully documented claim must be submitted to the CM within thirty (30) days of discovery. The claim must at least include the following: a. A copy of a police report (if applicable). b. A complete inventory of damaged or lost items including: (1). Description of each item. (2). Purchase date and proof of delivery of each item. (3). Supplier from whom purchased. (4). Serial number (if applicable). (5). Price of each item. (6). Total number of pieces and cost of all lost or damaged items. c. The name, address and telephone number of the person who controlled the lost or damaged items immediately before the loss or damage. d. The name, address and telephone number of the person who discovered the loss or damage. e. A written description of how the loss or damage occurred. The Owner may refuse any claim from the Contractor for loss or damage unless all of the items required in this section are provided to the Owner, and are to the satisfaction of the Owner. D. Adjoining Property 1. The Contractor shall protect all adjoining property and shall repair or replace any said property damaged or destroyed during progress of the Work. E. Risks Assumed by the Contractor Div. 01 General Requirements Page 24 of 53 1. The Contractor solely assumes the following distinct and several risks whether said risks arise from acts or omissions, whether supervisory or otherwise, of the Owner, of the Client, of the CM, of any Subcontractor, of third persons or from any other cause, including difficulties which may be encountered in the prosecution of the Work, whether said risks are within or beyond the control of the Contractor and whether said risks involve any legal duty, primary or otherwise, imposed upon the Owner, excepting only risks which arise from faulty designs as shown by the plans and specifications, unforeseen obstacles or from the negligence of the Owner or Owner’s members, officers, representatives or employees that caused the loss, damage or injuries hereinafter set forth: a. The risk of loss or damage, includes direct or indirect damage or loss, of whatever nature to the Work or to any plant, equipment, tools, materials or property furnished, used, installed or received by the Owner, the Construction Manager, the Contractor or any Subcontractor, material men or workmen performing services or furnishing materials for the Work. The Contractor shall bear said risk of loss or damage until construction completion or until completion or removal of said plant, equipment, tools, materials or property from the Site and the vicinity thereof, whichever event occurs last. In the event of said loss or damage, the Contractor immediately shall repair, replace or make good any said loss or damage. b. The risks of claims, just or unjust, by third persons against the Contractor or the Owner, the Client, and the Construction Manager on account of wrongful death, bodily injuries and property damage, direct or consequential, loss or damage of any kind whatsoever arising or alleged to arise out of or as a result of or in connection with the performance by the Contractor of the Work, whether actually caused by or resulting from the performance of the Work, or out of or in connection with the Contractor’s operations or presence at or in the vicinity of the Site. The Contractor shall bear the risk for all deaths, injuries, damages or losses sustained or alleged to have been sustained prior to the construction completion of the Work. The Contractor shall bear the risk for all deaths, injuries, damages or losses sustained or alleged to have been sustained resulting from the Contractor’s negligence or alleged negligence which is discovered, appears, or is manifested after acceptance by the Owner. c. The Contractor assumes entire responsibility and liability for any and all damage or injury of any kind or nature whatsoever, including death resulting there from, to all persons, whether employees of the Contractor or otherwise, and to all property, caused by, resulting from, arising out of, or occurring in connection with the execution of the Work. If any person shall make said claim for any damage or injury, including death resulting there from, or any alleged breach of any statutory duty or obligation on the part of the Owner, the Client, the Owner’s Representative, Construction Manager, servants and employees, the Contractor shall assume the defense and pay on behalf of the Owner, the Client, the Owner’s Representative, the Construction Manager, servants and employees, any and all loss, expense, damage or injury that the Owner, the Client, the Owner’s Representative, Construction Manager, servants and employees may sustain as the result of any claim, provided however, the Contractor shall not be obligated to indemnify the Owner, the Client, the Owner’s Representative, Construction Manager, servants and employees for their own negligence, if any. The Contractor agrees to assume, Div. 01 General Requirements Page 25 of 53 and pay on behalf of the Owner, the Client, and the Owner’s Representative, Construction Manager, servants and employees, the defense of any action at law or equity which may be brought against the Owner, the Client and the Owner’s Representative, Construction Manager, servants and employees. The assumption of defense and liability by the Contractor includes, but is not limited to the amount of any legal fees associated with defending, all costs of investigation, expert evaluation and any other costs including any judgment or interest or penalty that may be entered against the Owner, the Client, and the Owner’s Representative, Construction Manager, servants and employees, in any said action. d. The Contractor is advised that the Work required under this contract may impose certain obligations and requirements mandated by the U.S. Department of Labor Occupational Safety and Health Administration regulations, Title 29 CFR Part 1926.62 Lead Exposure in Construction, relative to the potential exposure to lead by its employees. The Contractor assumes entire responsibility and liability for complying fully in all respects with these regulations. 2. The Contractor’s obligations under this Article shall not be deemed waived, limited or discharged by the enumeration or procurement of any insurance for liability for damages. The Contractor shall notify its insurance carrier within twenty-four (24) hours after receiving a notice of loss or damage or claim from the Owner or Owner’s Client. The Contractor shall make a claim on its insurer specifically under the provisions of the contractual liability coverage and any other coverage afforded the Owner or the Client including those of being an additional insured where applicable. 3. Neither Final Acceptance of the Work nor making any payment shall release the Contractor from the Contractor’s obligations under this Article. The enumeration elsewhere in the Agreement of particular risks assumed by the Contractor or of particular claims for which the Contractor is responsible shall not be deemed to limit the effect of the provisions of this Article or to imply that the Contractor assumes or is responsible for only risks or claims of the type enumerated; and neither the enumeration in this Article nor the enumeration elsewhere in the Agreement of particular risks assumed by the Contractor of particular claims for which the Contractor is responsible shall be deemed to limit the risks which the Contractor would assume or the claims for which the Contractor would be responsible in the absence of said enumerations. Upon the conclusion of any action, proceeding or lawsuit, should a final binding determination of responsibility be made which allocates responsibility to the Owner, the Client, or the Owner’s members, officers, employees, or representatives, the Owner agrees that the obligation to indemnify and hold harmless shall not be applicable to the portion of any uninsured money judgment for which the Owner is responsible, and the Owner agrees to pay the Contractor the percentage of uninsured defense costs which the Contractor incurred based upon an apportionment of the Owner’s allocated responsibility. Div. 01 General Requirements Page 26 of 53 SECTION 01 35 24 SITE SAFETY A. RELATED SECTIONS 1. 01 41 00 Safety Requirements 2. 01 54 23 Scaffolding and Hoisting 3. 01 65 00 Removals and Delivery B. General: In addition to complying with Exhibit H of the Agreement, the Contractor shall be responsible for ensuring that all construction operations are performed in a safe and lawful manner, in full conformance with the NYC Building Code, OSHA regulations, and all other Local, State, and Federal Regulatory Agencies as well as accepted industry standards for worker and public safety. This requirement shall include, but not be limited to, Contractors’ compliance with regulations governing the use of scaffolding, sidewalk sheds, temporary shoring, barricades, Fire Department requirements for Work procedures, and sequencing which affect public or worker safety. Contractor is to submit a Site Specific Safety Work Plan at the initial progress meeting. C. Contractor shall conduct operations under this Agreement in such a manner as to allow continuous access for the occupants and public to their locations and the public spaces of the college at all times during the performance of the Work. Contractor shall conduct all operations as required to minimize disruptions of basic services within occupied buildings and to avoid inconvenience and danger to the occupier’s body. D. Any scheduled activities that will result in interruptions of basic services or utilities or may cause inconvenience to college staff and students shall be reported to the CM Construction Project Manager at least one week (seven calendar days) prior to the anticipated date. It shall be the responsibility of Contractor to notify and make all arrangements with the Utility Company or other authorities having jurisdiction whenever utility shutdowns are required. That Contractor shall provide and distribute/post notices of any service interruptions or other inconveniences to the occupants as required by the CM Construction Project Manager at least 48 hours prior to the shut down. Under no circumstances shall interruption of any service, utility, or area of the facility be allowed without prior notification by Contractor and written approval from the CM. E. Contractor shall allow unrestricted access to all areas under Contractor’s control to CUNY employees and emergency personnel in the performance of their duties. F. Contractor shall remove all snow and ice as it accumulates on all sidewalks and roads within the contract limit lines and shall keep the sidewalks and roads clear and salted at all times as necessary. G. At the start of each workday, contractor shall inform the CM as to the location and scope of Work planned. Any condition which might adversely affect the college, whether during the workday or after close of operations, shall be reported promptly to the CM, who will report it to the College Facilities. H. Contractor shall take every precaution necessary to avoid damaging any existing pipe insulation, since it may contain asbestos. When any such insulation is encountered, Contractor discovering it shall immediately notify the CM in order that samples may be taken and tested for the presence of asbestos. Should the pipe insulation be damaged resulting in asbestos being released into the surroundings, Contractor who damaged the insulation shall be held liable for the cost of all remedial work mandated by the Department of Environmental Protection regulations. Div. 01 General Requirements Page 27 of 53 I. Contractor shall have a licensed electrician on the premises during all demolition work affecting electrical wiring, outlets, or fixtures. J. Safety Precautions for Electric Circuits: Electrical circuits, the failure of which will cause a hazard to life and property, shall comply with Bulletin No. 8 of the Bureau of Gas and Electricity, dated March 5, 1963. K. Site Protection: Contractor shall be responsible for all general features of Site and worker safety, including but not limited to scaffolding, sidewalk sheds, perimeter barriers, and danger signage. L. Worker Protection: Contractor shall be responsible for enforcing all safety aspects for workers within and stemming from their scope of Work, including but not limited to prevention of loose wiring, exposed scrap material or debris, wet walking surfaces, etc. M. Contractor shall, for their own workforce, College employees and all their associated sub contractors, enforce any and all required or accepted worker safety features, including but not limited to wearing hard hats, dust masks, respirators, work gloves, safety boots, safety vests, and goggles. N. Other Safety Equipment: Provide first-aid medical kit and safety harness to be kept in the CM Site office. O. In the event of conflict between this Section and Exhibit H, Exhibit H shall control. SECTION 01 35 53 SECURITY – GENERAL PROVISIONS A. RELATED SECTIONS 1. Section 01 56 34 - Guard Service 2. Section 01 56 35 - Security Lighting B. Contractor is responsible for the security of the Work Site until final acceptance by CUNY DDCM. Contractor shall be responsible to provide suitable Site protection to prevent unauthorized entry onto the Site and shall be responsible for any loss or damage for the duration of the contract until final acceptance by CUNY DDCM. C. Contractor shall carefully protect and minimize damage to any existing Work that is to be retained. Contractor shall properly and completely protect all apparatus included in this Agreement against dirt, damage and vandalism. Any equipment furnished under the Agreement and any property of CUNY damaged or destroyed by Contractor or his/her employees shall be restored to its original condition or replaced without additional cost to CUNY. D. Contractor shall adequately enclose and protect areas against the weather where the installation is incomplete at the end of the working day, and shall be responsible for any damage or inconvenience due to his/her failure to do so. Such protection shall be done to the complete satisfaction of the CM. E. Contractor shall provide all necessary safety equipment, materials and personnel, to protect the public walks, entrances to the buildings, grounds within the work areas of this contract in order that pedestrians, College staff and students and the public be protected at all times. F. Contractor shall provide temporary barricades as required, post signs for safety, and provide dust controls. Div. 01 General Requirements Page 28 of 53 G. Contractor shall provide temporary, secure entrance doors when new entrance installation cannot be completed before the end of the working day at no additional cost to CUNY. Section 014000 QUALITY REQUIREMENTS This Section includes administrative and procedural requirements for quality assurance and quality control. RELATED sections Submittals – Section 013300. See Specification Sections for specific test and inspection requirements. DEFINITIONS Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and ensure that proposed construction complies with requirements. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with requirements. Services do not include contract enforcement activities performed by Architect. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency. DELEGATED DESIGN Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated. .1.A.1.a.1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect. SUBMITTALS Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems Div. 01 General Requirements Page 29 of 53 are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services. Schedule of Tests and Inspections: Prepare in tabular form and include the following: .1.A.1.a.2. Specification Section number and title. .1.A.1.a.3. Description of test and inspection. .1.A.1.a.4. Identification of applicable standards. .1.A.1.a.5. Identification of test and inspection methods. .1.A.1.a.6. Number of tests and inspections required. .1.A.1.a.7. Time schedule or time span for tests and inspections. .1.A.1.a.8. Entity responsible for performing tests and inspections. .1.A.1.a.9. Requirements for obtaining samples. .1.A.1.a.10. Unique characteristics of each quality-control service. Reports: Prepare and submit certified written reports that include the following: .1.A.1.a.11. Date of issue. .1.A.1.a.12. Project title and number. .1.A.1.a.13. Name, address, and telephone number of testing agency. .1.A.1.a.14. Dates and locations of samples and tests or inspections. .1.A.1.a.15. Names of individuals making tests and inspections. .1.A.1.a.16. Description of the Work and test and inspection method. .1.A.1.a.17. Identification of product and Specification Section. .1.A.1.a.18. Complete test or inspection data. .1.A.1.a.19. Test and inspection results and an interpretation of test results. .1.A.1.a.20. Ambient conditions at time of sample taking and testing and inspecting. .1.A.1.a.21. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements. .1.A.1.a.22. Name and signature of laboratory inspector. .1.A.1.a.23. Recommendations on retesting and reinspecting. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar Div. 01 General Requirements Page 30 of 53 documents, established for compliance with standards and regulations bearing on performance of the Work. QUALITY ASSURANCE Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in the State of New York and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated. .1.A.1.a.24. Requirement for specialists shall not supersede building codes and similar regulations governing the Work, nor interfere with local trade-union jurisdictional settlements and similar conventions. Testing Agency Qualifications: An agency with the experience and capability to conduct testing and inspecting indicated, as documented by ASTM E 548, and that specializes in types of tests and inspections to be performed. Preconstruction Testing: Testing agency shall perform preconstruction testing for compliance with specified requirements for performance and test methods. .1.A.1.a.25. Contractor responsibilities include the following: Provide test specimens and assemblies representative of proposed materials and construction. Provide sizes and configurations of assemblies to adequately demonstrate capability of product to comply with performance requirements. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work. Fabricate and install test assemblies using installers who will perform the same tasks for Project. Div. 01 General Requirements Page 31 of 53 When testing is complete, remove assemblies; do not reuse materials on Project. .1.A.1.a.26. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Architect with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents. part 2 EXECUTION REPAIR AND PROTECTION General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes. .1.A.1.a.27. Provide materials and comply with installation requirements specified in other Sections of these Specifications. Restore patched areas and extend restoration into adjoining areas in a manner that eliminates evidence of patching. Protect construction exposed by or for quality-control service activities. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services. SECTION 01 41 00 REGULATORY REQUIREMENTS A. GENERAL 1. All Work shall be done as hereinafter specified and in accordance with the latest rules and regulations of all regulatory and public agencies having jurisdiction in the Work of this contract. 2. Only the latest editions or revisions of reference standards, New York City Building Code, and specifications in force at the date the Work being performed shall be applicable unless otherwise specifically noted. 3. The Specifications of the American Society for Testing and Materials (ASTM), latest edition, shall apply to any and all for which the ASTM Standard has been established, unless otherwise specified. Each manufacturer or supplier of each material shall certify that their material conforms to the applicable ASTM Specification. 4. If Work under this contract requires street excavation, notify the NEW YORK CITY ONE CALL CENTER at 1-800-272-4480 prior to performing any such excavation, notification to be made at least two but no more than ten working days prior to start of excavation. 5. Contractor shall be responsible for knowing and complying with regulatory requirementsFederal, State and Local- pertaining to legal disposal of all construction and demolition waste materials. 6. All Work shall conform to the minimum accessibility standards set by New York City Local Law 58 and the Uniform Federal Accessibility Standards, 1984. Div. 01 General Requirements Page 32 of 53 B. PERMITS, APPLICATIONS AND CERTIFICATES 1. Contractor shall be responsible, at no additional cost to CUNY, for the filing of all required applications, reports and forms with all Governmental Agencies having jurisdiction. Contractor shall obtain all work permits and certificates as required according to the final Contract Drawings and Amendments, as approved by the Building Department. 2. Contractor shall obtain all required Building Department and Bureau of Electrical Control approvals and sign-offs for the Work of the Heating and Ventilation, Electrical Work and Plumbing required to obtain the required Certificates of Occupancy. Div. 01 General Requirements Page 33 of 53 Roosevelt Hall Renovation Project Brooklyn College SECTION 01 42 00 DEFINITIONS AND OMISSIONS A. DEFINITIONS Unless otherwise specified the following are definitions of terms used in these technical specifications: 1. "Addendum" and "Addenda" refer to written or graphic documents issued by CUNY prior to the start of the Agreement, which modify or interpret the Bidding Documents by addition, deletions, clarifications or corrections. Upon issuance, Addenda become part of the Contract documents. 2. "Adequate" or "sufficient" shall mean adequate or sufficient in the opinion of CUNY or its Authorized Representative. 3. “AE” means Pfeiffer Partners Architects and their subconsultants. 4. "Approved" or words of similar import shall mean approved in writing by any governmental agency having jurisdiction or CUNY or its Authorized Representative. 5. "CUNY" means The City University of New York City. 6. "Certification" refers to the submittal of any and all certified mill or laboratory test reports indicating that the material submitted complies with the requirements specified and is intended generally for the applications shown. 7. "Color chart" refers to the submittal of a manufacturer's full assortment of colors available for the specified product. Submittals shall be in color, black and white copies or reproductions are not acceptable. 8. “DDCM” means CUNY Department of Design, Construction and Management. 9. "Equal" shall mean equivalent in the opinion of CUNY or its Authorized Representative. 10. "Furnish" shall mean procure, supply, and deliver the article required for the completion of that portion of Work. 11. "Indicated" is a cross-reference to graphic representations, notes or schedules on the drawings, to other paragraphs or schedules in the specifications, and to similar means of recording requirements in Contract Documents. Where terms such as "shown", "noted", "scheduled", and "specified" are used instead of "indicated", it is for the purpose of helping the reader locate the cross-reference, and no limitation of location is intended except as may be specifically noted. 12. "Install" shall mean build-in, set, or place the article into assembly. 13. “Occupants” shall mean faculty, staff, students, and visitors of the campus. 14. "Provide" shall mean furnish and install. 15. "Remove" shall mean to extract in an orderly manner, an article or assembly, and to dispose of that item in an approved manner, off Site. Div. 01 General Requirements Page 34 of 53 Roosevelt Hall Renovation Project Brooklyn College 16. Material or equipment designated by specification number shall mean the latest revision of that Specification. 17. All equipment furnished and installed under the Agreement shall be as Specified or its Equal as approved by CUNY and be new and of the latest model or design. B. WORD OMISSIONS 1. Omissions in the sections of the Specifications following such words as "the Contractor shall," "shall be," "shall consist of," "the" etc., are intentional. Such words and phrases shall be applied where a colon occurs or by inference as is done in the case of a note on the Drawings. Wherever instructions are given in the Drawings or Specifications they are directed to Contractor unless otherwise noted. Where clarity of intent requires it, the long form is used. SECTION 01 45 00 QUALITY CONTROL A. PROJECT/SITE CONDITIONS 1. Field Measurements: Contractor shall verify that field measurements are as indicated on construction and shop drawings before confirming product orders or proceeding with Work, to minimize waste due to excessive materials. 2. Metals in contact with dissimilar metals or materials that can cause deterioration shall be separated from these materials through the use of protective coatings such as bituminous paint etc., platings, plastic shims, sleeves, gaskets or other isolators. Compatible fasteners shall be used to reduce galvanic action. B. PACKING AND SHIPPING 1. Shipping: Coordinate the schedule of product delivery to designated prepared areas to minimize Site storage time and potential damage to stored materials. 2. Packing: Arrange for the return of packing materials, such as wood pallets, where economically feasible. C. PREPARATION (see also 01 66 00) 1. Designate receiving/storage areas for incoming material to be delivered according to installation schedule. D. INSTALLATION 1. Install product(s) according to manufacturer's recommendations SECTION 01 51 00 TEMPORARY SERVICES A. GENERAL 1. All temporary services (as outlined below) shall be provided by Contractor at his/her own expense Div. 01 General Requirements Page 35 of 53 Roosevelt Hall Renovation Project Brooklyn College a. Temporary Lighting and Electrical: Owner shall provide electricity. Contractor to provide all routing necessary to bring power from building sources to work locations as necessary. No power is to be taken from individual rooms in any fashion. Contractor shall provide temporary lighting as required to maintain a minimum of 10 foot candles in the work areas. Contractor shall provide ground-fault protection for personnel on single phase 15 and 20 ampere receptacle outlets. Receptacle outlets and portable cord connectors shall have standard NEMA configuration. Make necessary arrangements and hookup location for temporary electrical services. Furnish and install all required cut off switches, panels, wiring, meters, etc and maintain until no longer required. Turn off all power at the end of each working day. Remove all temporary electric supplies and equipment when no longer required. . b. Temporary Water Temporary water will be made available for the work without charge at source or sources directed within the limits of the existing supply and usage. Contractor shall make arrangement with the CM for hookup. Contractor is responsible for maintenance and for shutting off service at the end of each working day. c. Temporary Use of Existing Permanent Elevator The Contractor will be permitted to use the freight elevator designated by the CM for transportation of workers, tools, materials, and equipment. Contractor to provide protective pads for the cab, masonite for the floors, and any other appropriate protective measures for the car and entrance doors and frames. At the end of construction, the elevator must be restored to the condition in which it was found prior to construction. d. Temporary Ventilation The Contractor shall provide and pay for ventilation of the enclosed space for workers in accordance with applicable laws. It shall also provide ventilation of the enclosed space as required to facilitate drying of plaster or taping compound, or other materials requiring ventilation in accordance with manufacturer’s directions and as required to maintain proper moisture levels within building including materials, surface and ambient air for installation and application of interior materials and equipment. Div. 01 General Requirements Page 36 of 53 Roosevelt Hall Renovation Project Brooklyn College SECTION 01 52 13 CONSTRUCTION FIELD OFFICE A. RELATED SECTIONS 1. 01 30 00 Administration of Contracts & Project Procedures 2. 01 31 00 Project Coordination 3. 01 35 29 Site Security General Contractor shall be required to provide the following within fifteen (15) days of the start of work until final acceptance of the project: A. Office build out and contents for Construction Manager: The office area will be located on the first floor as indicated on Drawing A-101.00 / Office 100 RE. For complete work see Drawings. a. The Contractor will carry an allowance of $45,000 for selective demolition, minor construction, and provision of furniture, fixtures, and equipment as follows. b. Provide three (3) private offices each a minimum of 150 sf. c. For security purposes, existing hardware will be modified and/or replaced to accommodate locking of the offices. Copies of keys will be issued to requisite CUNY and Brooklyn College representatives. d. Provide conference room / area large enough to accommodate up to 20 persons. e. Provide complete interior furnishings including five (5) desks and eight (8) chairs for the offices and reception area. Finishes must be of good quality and in good condition. f. Toilet facility. g. Toiletries, paper towels, toilet paper and soap. h. Include eight (8) wastepaper baskets and two large waste receptacles for separation of paper waste and common trash per LEED requirements. i. One (1) Plan Desk (minimum 3’ x 6’) with storage plan boxes for rolled up drawings j. One (1) Conference Table with seating for sixteen (16) k. Twenty (20) Chairs for Conference Table l. Five (5) - four drawer Filing Cabinets with capacity for legal size hanging files m. Two (2) 4 level Book Shelving for contracts, Project Manuals, and supplies. n. 8 Mailbox Slots for Contractors o. Water Cooler (5 gallon) with hot/cold ports with water delivery service for the duration of Roosevelt Interior project. p. Microwave Oven q. Coffee Machine r. Refrigerator 3’ x 4’ s. One (1) minimum 8 megapixel digital camera with 3x optical zoom, water and shock resistant, with two (2) minimum 256 mb storage card. t. Contractor will be required to clean the office once per week, which includes removal of all trash as often as needed. u. One (1) 200 GB external hard drive USB 2.0 for data backup storage. Div. 01 General Requirements Page 37 of 53 Roosevelt Hall Renovation Project Brooklyn College B. Additional Equipment for Resident Engineer The following items (See Diagram 1) are to be included and must be maintained for the Project duration through final completion. Notes: 1. Equipment shall be provided at the direction of the Construction Manager, and any equipment not provided, shall be credited back to the CUCF. 2. After completion of the Project all purchased equipment will become the property of CUNY and will remain in the Office. Office must be provided with at least 15 120v outlets (inclusive of existing outlets) in addition to all required telephone outlets (minimum 5) and necessary computer network jacks including wireless network router. Contractor is to coordinate the work and pay for all associated costs to connect and route the phones, fax, computers, and copier per the direction of Brooklyn College Facilities Management / University Engineer. No. [1] 001 Items [2] Telephones Units [3] See [4] 002 Internet Connection See [4] 003 Windows 2003 Server: 1 004 Switch: 12-Port 1 005 Network Printer 1 006 Network Copy Machine 1 007 Fax Machine 1 Description [4] Three phone lines (Separate phone numbers) for voice and one Fax dedicated phone line. Provide 5 phones as follows; One phone will have dedicated phone number/lines and the other four phones will share the other two lines. Insure that all phones are working properly. Provide repairs/maintenance as needed. Provide DSL high speed connection to the Wireless Office Network (LAN) and maintain functional through project completion. This server will be connected to six users at peak and will include all required / necessary software, licenses, (wireless) connections, etc. and is a part of this contract. It must have a minimum of a 2.8 GHz processor, Windows Server 2003 Std, Internal Tape Drive for backup with backup software, RAM capacity of 512 MB and HD capacity of 80 GB. Licenses for at least 6 users must be included. 17” Monitor, key board and optical mouse should be included. Provide training for the staff members on back-up. Include all maintenance/repair as required to provide operational network at all times. At least an Ethernet 10/100 Auto-Sensing Color Laser Printer with wireless network capability (includes access to laser printers from all work stations) 25ppm, 2400 x 600 dpi, Input paper capacity 600, Output paper capacity 500, max. paper size 11 x 17, memory 64MB. (Note: Items 009, 010, & 011 may be supplied as a single multi-function unit with wireless / network capability.) Provide a lease for the benefit of the project including all supplies and maintenance. Multi Function (MFP) – Wireless Network Printing, Scanning, Faxing, and Finishing capable. Minimum 60 ppm for black and white copies and minimum 600 dpi. Separate paper supply trays for multiple paper sizes of at least 300 sheets. The copier shall have a max media/sheet size of 11 inch x 17 inch, and finisher with stapler. Separate Fax 2920 high speed Laser fax with 33.6k Bps Super G3 Fax Div. 01 General Requirements Page 38 of 53 Roosevelt Hall Renovation Project Brooklyn College 008 X1 wall outlet connection and wiring. C. 1 Modem, 30 Page ADF, 16 MB Memory, Dual Access, 250 Sheet Input Capacity. Additional Communication Outlet for a visiting staff member Laptop (Provide The Outlet ONLY , Computer is not required) Must be ready for use by a staff member. Software License for the Server must be included. A complete set of contract documents and construction sketches shall be kept at the Site in the field office at all times, in an organized manner for the use of CM/CUNY. SECTION 01 52 19 TEMPORARY TOILETS A. The building is presently occupied and operational with available toilet facilities; the Contractor may use the existing facilities as directed by Hill. However, it will be the responsibility of the Contractor to designate and maintain these rooms. Any damage caused by the Contractor will be the sole responsibility of the Contractor to remedy. The Contractor shall provide, at the beginning of Work, and shall maintain temporary toilets, wash facilities, and potable drinking water. Comply with regulations and health codes for the type, number, location, operation, and maintenance of fixtures and facilities. SECTION 01 53 16 SIDEWALK BRIDGE A. RELATED SECTIONS 1. 01 35 33 Site Safety 2. 01 41 00 Regulatory Requirements B. Contractor shall secure permits for any sidewalk bridges and shall adhere to Local Law 33/91 requirements. Applicants for the permit must state why the bridge is required and why permit should be renewed at time of expiration. Installation shall be by licensed contractor. 1. Any sidewalk bridges shall conform to the Section BC 3307 of 2008 NYC Building Code, OSHA regulations, and to all requirements of public agencies having jurisdiction thereof. 2. Contractor shall notify the CM Construction Project Manager 48 hours prior to the erection of any sidewalk bridges, and shall coordinate his/her efforts so as not to interfere with normal activities of the Campus. 3. The Sidewalks bridge(s) shall be safe, secure, and properly maintained at all time. All necessary provisions shall be made to protect the workers and the public against any hazard or injury, and all property from damage. Contractor shall be held fully and solely liable for any harm, injury or damage resulting from faulty, damaged, or weak construction of sidewalk bridges. Div. 01 General Requirements Page 39 of 53 Roosevelt Hall Renovation Project Brooklyn College SECTION 01 54 23 SCAFFOLDING AND HOISTING A. RELATED SECTIONS 1. 01 35 33 Site Safety 2. 01 41 00 Regulatory Requirements B. SCAFFOLDING 1. If required, erect adequate scaffolding for this Work. Contractor shall make the necessary arrangements for, and obtain all permits required for his/her work, paying the costs and expenses thereof. 2. Erect and operate all scaffolding by or under the supervision of a licensed rigger. Present original rigger’s license to the CM for verification prior to installation. 3. Scaffolding shall conform to the Section BC 3314 of 2008 NYC Building Code, OSHA regulations, and to all requirements of public agencies having jurisdiction thereof. 4. Scaffolding shall be erected in such a manner as not to disturb any parts of the building under construction, or in any way affect the guarantee of the roofing, exterior cladding, or any other material and/or equipment being installed as part of the Work. 5. Contractor shall notify the CM 48 hours prior to the erection of any scaffolding, and shall coordinate his/her efforts so as not to interfere with normal activities of the campus. 6. Scaffolding shall be safe, secure, and properly maintained at all time. All necessary provisions shall be made to protect the workers and the public against any hazard or injury, and all property from damage. Contractor shall be held fully and solely liable for any harm, injury or damage resulting from faulty, damaged, or weak scaffolding. C. HOISTING AND LIFTING 1. Not applicable SECTION 01 57 16 TEMPORARY PEST CONTROL A. RODENT AND INSECT CONTROL 1. Furnish and pay for the services of a licensed exterminating company approved by Brooklyn College, from the time the Work is started until final acceptance for the purpose of control of all rodents and insects. The exterminating company shall provide all labor, material and equipment necessary to maintain complete exterminating services in the building under construction and the surrounding ground areas within the boundary lines of the Site, including all temporary toilets, field office, and storage areas. 2. Qualifications: The exterminating company must submit satisfactory evidence of at least ten (10) years experience in this class of Work, including names and addresses of at least five (5) business concerns for whom similar services have been performed by the company within the past five (5) years. The service operators must be fully uniformed when making regular scheduled or emergency service visits to the job Site. 3. Materials, chemicals and equipment used for exterminating purposes shall comply with all rules and regulations of all applicable City, State and Federal agencies, including, but not limited to, the New York State Department of Environmental Conservation, Div. 01 General Requirements Page 40 of 53 Roosevelt Hall Renovation Project Brooklyn College Bureau of Pesticides and Radiation. The exterminating company shall provide copies of all MSDS 4. At the pre-construction stage, Contractor shall thoroughly inspect the construction Site, staging areas, and contiguous areas for any signs of rodent or pest presence. If required tamper-proof bait stations for rodents shall be placed at minimum 20’ intervals around the perimeter. Traps shall be checked regularly and if active cleaned and replaced daily. 5. As part of the construction set-up, Contractor shall implement all preventive methods for pest control, including but not limited to the following: a. At eating areas for Site workers, provide rodent proof waste containers in sufficient number to accommodate all waste without overflow between collection days. b. All dumpsters shall be rodent proof and covered. At a minimum, dumpsters shall be emptied weekly and waste containers daily. c. Store all materials on racks a minimum of 18” a.f.f. 6. Inspections and treatments by service operators of the Site are to be made on a set day once each week during regular work day hours for rats, mice, roaches, water beetles and all other pests, with special attention given to the following conditions and/or areas. a. Wet areas inside and/or outside the building, including all temporary structures. b. Temporary toilet facility areas. c. Field Office. d. Wherever there is evidence of food waste and discarded food or drink containers in quantity that would cause breeding of rodents or the insects herein specified. e. Any other portion of the premises requiring such special attention. 7. Service operators shall report to the CM upon service completion of each scheduled or emergency service visit to the Site, and shall furnish the CM Construction Project Manager with a written detailed report of that area served and the conditions found in that area. 8. Contractor shall use the least toxic treatments and materials for the duration of the Project for rodent, termite, and vegetation control. All areas that receive treatment shall have signs clearly posted inside and outside the facility. If an exterminating service is engaged Contractor it shall be approved by the CM and apply methods as stated above. 9. Use only soil treatments which are not injurious to plants. 10. It will be the responsibility of Contractor to see that the entire Site conforms to the above regulations and that all subcontractors abide by the pest control requirements listed herein. Div. 01 General Requirements Page 41 of 53 Roosevelt Hall Renovation Project Brooklyn College SECTION 01 65 00 REMOVALS AND DELIVERY A. RELATED SECTIONS 1. 01 35 33 Site Safety 2. 01 54 23 Scaffolding and Hoisting 3. 01 74 13 Cleaning B. REMOVALS & DELIVERY 1. Contractor shall be responsible for removal and legal disposal of construction debris. 2. Contractor shall be responsible for the cleaning up of his/her work area, including surplus materials and the depositing of it in the containers at the completion of each shift of Work. 3. Debris resulting from construction activity will not be permitted to drop free from openings but shall be removed only by the use of materials hoist, or closed, dust-tight type rubbish chutes or other method approved by the CM. Hoists and chutes shall be so protected as to prevent damage, staining or marring of any permanent work. Rubbish dirt and other dust producing materials shall be wetted down to minimize air borne particles. 4. No debris or materials shall be passed through the finished openings of the exterior walls, without proper protection of the openings in a manner approved by the CM. 5. All materials shall be delivered to the work Site within a building by the stairs, ramps, materials hoist, or other method approved by the CM. SECTION 01 66 00 STORAGE A. GENERAL REQUIREMENTS 1. Store and handle materials in a manner that prevents loss from weather and other damage. Keep materials covered and off the ground, and store in a dry secure area. 2. Protect all materials and installations from damage by activities of other trades. 3. Materials stored on the floors of a building during construction or demolition operations shall comply with Sections 3303.4.5.1 and 3303.4.5.2 of 2008 NYC Building Code. SECTION 01 66 19 MATERIALS AND EQUIPMENT A. GENERAL REQUIREMENTS 11. Manufactured materials shall be delivered to the Project Site in their original packages and containers. Damaged or deteriorated materials shall not be used or stored on the Site. Div. 01 General Requirements Page 42 of 53 Roosevelt Hall Renovation Project Brooklyn College 12. All manufactured articles, materials and equipment shall be applied, installed, connected, erected, used, and cleaned in accordance with the manufacturer' directions unless otherwise specified. 13. Materials shall be new, best quality, free from defects and shall conform to the specification list for that item. 14. Materials shall fully comply with all applicable reference standards and municipal regulations. B. TRANSPORTATION 1. Transport materials in covered trucks to prevent contamination of product or littering of surrounding areas. 2. Driveways and parking lots may be used by Contractor only with the expressed permission of CUNY in coordination with the CM Construction Project Manager, in compliance with requirements of CUNY and municipal regulations. Any and all damage to driveways and parking lots must be repaired by Contractor at Contractor’s expense to the satisfaction of CUNY DDCM. 3. Do not drive any delivery vehicle over any un-paved or landscaped area of the Site. Any damage to landscaped areas incurred during delivery of materials ore equipment shall be repaired by Contractor at no expense to CUNY. SECTION 01 71 23 FIELD ENGINEERING A. RELATED SECTIONS 1. 01 77 19 Contract Closeout Procedures B. EXISTING PROPERTY SURVEY 1. Identification: Contractor will be responsible to identify existing control points and property line corner stakes. 2. Verify layout information shown on the Consultant’s drawings, in relation to the property survey and existing benchmarks, before proceeding to lay out the work. Locate and protect existing benchmarks and control points. Preserve permanent reference points during construction. a. Do not change or relocate benchmarks or control points without prior written approval. Promptly report lost or destroyed reference points or requirements to relocate reference points because of necessary changes in grades or locations. b. Promptly replace lost or destroyed Project control points. Base replacements on the original Survey control points. SECTION 01 71 33 PROTECTION OF ADJACENT PROPERTY A. RELATED SECTIONS 1. 01 74 16 Site Maintenance Div. 01 General Requirements Page 43 of 53 Roosevelt Hall Renovation Project Brooklyn College B. Contractor shall protect adjoining public and private property from damage during construction or demolition as per Section BC 3309 of 2008 NYC Building Code. B. Contractor shall take all precautions necessary to protect adjacent buildings, property of CUNY, its occupants at the facility and property adjacent to the work Site from damage or loss arising out of execution of this contract. Contractor shall assume responsibility for any such damage or loss caused by them and shall, at his/her own expense, repair or replace any property that becomes damaged or destroyed. The CM with the CUNY DDCM Construction Project Manager shall determine whether affected property has been damaged to such an extent that it can not be restored to its original condition and must be replaced. C. Contractor shall be responsible to protect all Site work including all existing plantings and trees within and adjacent to the work Site. Contractor shall be responsible for any damage or loss to any plantings, lawn or open areas, and trees within or adjacent to the work Site and shall, at his/her own expense, replace with same species and size any plantings and trees which in the opinion of the CM become damaged. SECTION 01 73 29 CUTTING AND PATCHING A. RELATED SECTIONS 1. 01 31 00 Project Coordination B. CUTTING 1. Contractor and their subcontractors shall execute their removals in an accurate and professional manner, with minimal damage to the adjacent finishes while observing approved dust control procedures and all governmental regulations regarding the removal and disposal of hazardous materials. 2. No cutting of beams, bearing walls or other structural parts of the building shall be done without prior approval of the CM. 3. Contractor shall be responsible for all cutting of walls, floors, ceilings, etc., necessary for installation of the Work 4. Contractor shall do all cutting necessary whether it is masonry cutting or steel cutting (burning) to free all items to be removed with minimal damage to adjacent finishes. All new work shall be fitted neatly into the existing. If removals expose poorly finished surfaces or surfaces structurally deficient for attaching new equipment or items, the exposed surface shall be structurally reinforced or refinished in an approved manner at no additional cost to CUNY. Such conditions shall be brought to the attention of the CM prior to remediation. 5. Drilling for expansion bolts, hangers and supports shall be done by Contractor subject to the conditions stated in this Section. 6. Cut construction-using methods least likely to damage elements retained or adjoining construction. Where possible review proposed procedures with original installer and comply with original installer's recommendations. C. PATCHING 1. Contractor shall patch and finish all adjacent surfaces left missing, damaged or unfinished by the normal execution of the Work that makes up this Project. Completed Div. 01 General Requirements Page 44 of 53 Roosevelt Hall Renovation Project Brooklyn College repairs shall match existing adjacent surfaces and shall include painting where necessary. 2. Contractor shall patch, repair and restore to their undamaged condition, all surfaces, materials and equipment damaged through the course of construction and transportation negligence of Contractor or his/her forces or suppliers. Completed repairs shall match existing adjacent surfaces and shall include painting where necessary. 3. All patching shall be done in a neat and careful manner, leaving the finished work free from cracks, stains and defects in a condition acceptable to the CM. Contractor shall be responsible to patch and finish all walls, floors, ceilings, and all other surfaces to match the surrounding surfaces in all areas affected by the Work of this contract. 4. Where patching occurs in a smooth painted surface, extend final paint coat over entire unbroken surface, restoring surface to a uniform color and sheen. SECTION 01 74 13 CLEANING A. RELATED SECTIONS 1. 01 74 16 Site Maintenance 2. 01 74 23 Final Cleaning B. CLEANING – General 1. Upon completion of the Work and/or at the end of each working day, each Contractor shall remove from the premises all hazardous or flammable materials and assume ownership of all debris resulting from the Work, and legally dispose of it unless otherwise specified by the CM. 2. As the Work in various areas is completed, they shall be broom cleaned and all rubbish, debris, excess materials and tools and scaffolding shall be removed. In these areas, Contractor shall thoroughly clean all surfaces, including all adjacent exterior areas. 3. Contractor shall clean all paint spots, oils, plaster and stains from floors, walls, woodwork, glass, hardware metal work and all similar items upon completion of any area of Work. 4. Dust control procedures as specified herein shall be employed throughout all Work. Wet down dust with water spray where necessary. 5. Finished surfaces, installed flooring, and equipment shall be protected with drop cloths, plastic sheeting, or other appropriate protective devices. Drop cloths and other protective devices shall be kept clean at all times. Plaster dust shall be removed daily by commercial type vacuum cleaners. 6. Plumbing fixtures, waste pipes, chases, pits, etc., shall not be used for the disposal of any waste, paints, oils or other materials. Such areas shall be kept clean of all debris and waste materials at all times. 7. Contractor shall leave the premises broom clean at end of each day. Keep dirt and debris to a minimum in the construction repair areas. SECTION 01 74 16 Div. 01 General Requirements Page 45 of 53 Roosevelt Hall Renovation Project Brooklyn College SITE MAINTENANCE A. RELATED SECTIONS 1. 01 35 33 -- Site Safety 2. 01 57 16 – Rodent and Insect Control 3. 01 71 33 -- Protection of Adjacent Property 4. 01 74 13 -- Cleaning B. MAINTENANCE OF THE SITE 1. Contractor shall provide all necessary safety equipment, materials and personnel, to protect the public walks, entrances to the buildings, grounds within the work areas of this contract in order that pedestrians, College staff and students and the public be protected at all times and shall post signs for safety as required by the NYC Building Code and all other applicable regulations or as directed by the CM. 2. Contractor shall adequately enclose and protect areas against the weather where the installation is incomplete at the end of the working day, and shall be responsible for any damage or inconvenience due to his/her failure to do so. Such protection shall be done to the complete satisfaction of the CM. 3. Contractor shall properly and completely protect all apparatus included in their Agreement against dirt and damage. Contractor shall be held fully responsible for all damage to apparatus, regardless of whether provided by him/her or belonging to CUNY, until final acceptance. Any equipment furnished under the Agreement and any property of CUNY damaged or destroyed by any Contractor or his/her employees shall be restored to its original condition or replaced without cost to CUNY. C. Contractor shall carefully protect and minimize damage to any existing Work that is to be retained. Contractor shall be responsible for providing for a secured closed dust-tight connection between existing and new construction, subject to approval by the CM. D. Contractor shall protect and be responsible for the existing buildings, facilities, on-going construction, and improvements within the areas of his/her operation under this contract. Should any portion of the area be damaged, disturbed or otherwise affected due to the Work of the Agreement, Contractor whose work was responsible shall report the conditions and circumstances to the CM and shall make all necessary repairs and replacements to such damaged work at his/her own expense and with new materials to match the existing Work in every respect, as approved by the CM. Contractor shall restore or replace to their former conditions and to the satisfaction of the CM, all existing or new construction, finishes, lawns, plantings, and other improvements that are to remain and that have been damaged as a result of his/her operation at his/her own expense. E. Where existing Site assets, such as street lights, signs, hydrants, curbs, and any utility services, public or private are to be retained, they shall be properly protected before and during construction. F. Contractor is to acquaint himself/herself with the existence and location of any surfaces or sub-surface structures and utilities within the Project area, and is warned against the use of heavy equipment over these utilities. G. Should Contractor encounter any utilities or services during the performance of the Work, he/she shall notify the Municipal Agency or Company owning or controlling services, to disconnect these services if so required. Any services cut off or interrupted by Contractor’s operation shall be restored at Contractor’s expense. Div. 01 General Requirements Page 46 of 53 Roosevelt Hall Renovation Project Brooklyn College H. Demolition and Removals shall be defined as the removal and disposal of such features as accumulated debris, overburden, trees, curbs, walls of all kinds, abandoned utilities, telephone poles and light poles, pavements and foundations and footings for same. All materials shall be properly disposed of off the Site at no additional cost to CUNY DDCM. SECTION 01 74 23 (01710) FINAL CLEANING A. Contractor shall be responsible for final cleaning upon completion of all Work. The premises shall be cleaned to a neat and perfect condition satisfactory to the CM. This work shall include washing of all windows and surfaces and mopping of all floors. B. Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to the condition expected in normal residential building cleaning and maintenance program. Comply with manufacturer's instructions when finish materials require special treatment. C. Remove labels that are not permanent labels. D. Clean transparent and reflective materials, including mirrors and glass in doors and windows. Remove glazing compound and other substances that are noticeable visionobscuring materials. Replace chipped or broken glass and other damaged transparent materials. E. Clean exposed exterior and interior hard-surfaced finishes, equipment, cabinets, shelving, etc., to a dust-free condition, free of joint compound, stains, film and similar foreign substances. Restore reflective surfaces to their original reflective condition. F. Broom clean concrete floors. Vacuum carpeted surfaces. Mechanically clean and polish resilient floor tile. Clean ceramic tile, removing grout material left from installation, dirt and grime. G. Wipe surfaces of mechanical and electrical equipment. Remove excess lubrication and other substances. Clean plumbing fixtures to a sanitary condition. Clean light fixtures and lamps. H. Clean the Site of rubbish, litter, and other foreign materials. Remove any stains, spills, or other foreign deposits from paved areas and sweep broom clean. I. Compliance: Comply with regulations of authorities having jurisdiction and safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on the Owner's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from the Site and dispose of lawfully. SECTION 01 77 13 SUBSTANTIAL COMPLETION Div. 01 General Requirements Page 47 of 53 Roosevelt Hall Renovation Project Brooklyn College A. General: This Section shall supplement the Substantial Completion requirements set forth in the Agreement. In case of conflict, the Agreement shall control. B. Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, Contractor must complete the following. List exceptions in the request. 1. In the Application for Payment that coincides with, or first follows, the date Substantial Completion is claimed, show 100 percent completion for the portion of the Work claimed as substantially complete. a. Include supporting documentation for completion as indicated in these Contract Documents and a statement showing an accounting of changes to the Contract Price. b. If 100 percent completion cannot be shown, include a list of incomplete items, the value of incomplete construction, and reasons why the Work is not complete. 2. Advise the CM of pending insurance changeover requirements. 3. Submit specific warranties, workmanship bonds, maintenance agreements, final certifications, and similar documents. 4. Submit record drawings, maintenance manuals, final Project photographs, if required, damage or settlement surveys, property surveys, and similar final record information. 5. Deliver tools, spare parts, extra stock, and similar items. 6. Make final changeover of permanent locks and transmit keys to the CM. Advise the Owner's personnel of changeover in security provisions. 7. Complete startup testing systems and instruction of the CUNY's operation and maintenance personnel. Discontinue and remove temporary facilities from the Site, along with mockups, construction tools, and similar elements. 8. Touch up and otherwise repair and restore marred, exposed finishes. 9. Complete final cleanup requirements. C. Inspection Procedures: On receipt of request for inspection, the CM and the AE will either proceed with inspection or advise Contractor of unfulfilled requirements. D. The AE will prepare the Certificate of Substantial Completion following inspection or advise Contractor of construction that must be completed or corrected before certification will be issued. E. The CM with the AE will repeat inspection when assured that the Work is substantially complete. Results of the complete inspection will form the basis of requirements for final acceptance. SECTION 01 77 19 CONTRACT CLOSEOUT A. SUMMARY 1. This Section includes administrative and procedural requirements for contract closeout, including inspection procedures. 2. Closeout requirements for specific construction activities are included in the appropriate Specification Sections. Div. 01 General Requirements Page 48 of 53 Roosevelt Hall Renovation Project Brooklyn College B. FINAL ACCEPTANCE 1. This Section shall supplement the Final Acceptance requirements set forth in the Agreement. In case of conflict, the Agreement shall control. 2. Preliminary Procedures: Before requesting final inspection for certification of final acceptance and final payment, complete the following. List exceptions in the request. a. Submit the final payment request with releases and supporting documentation not previously submitted and accepted. Include insurance certificates for products and completed operations where required. b. Submit an updated final statement, accounting for final additional changes to the Contract Sum. c. Submit a certified copy of the AE’s final inspection list of items to be completed or corrected, endorsed and dated by the CM. The certified copy shall state that each item has been completed or otherwise resolved for acceptance. d. Submit final meter readings for utilities, if applicable, a measured record of stored fuel, if applicable, and similar data as of the date of Substantial Completion or when CUNY took possession of and assumed responsibility for corresponding elements of the Work. e. Submit consent of surety to final payment. f. Submit a final liquidated damages settlement statement. g. Submit evidence of final, continuing insurance coverage complying with insurance requirements. 3. Re-inspection Procedure: The CM and the AE will re-inspect the Work upon receipt of notice that the Work, including inspection list items form earlier inspections, has been completed, except for items whose completion is delayed under circumstances acceptable to CUNY. a. Upon completion of re-inspection, the CM will prepare a certificate of final acceptance. If the Work is incomplete, the CM will advise Contractor of Work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance. b. If necessary, re-inspection will be repeated. C. COMPLETION PAYMENTS a. Upon receipt of all required items, the AE will issue a Substantial Completion Letter. b. Contractor may then request Substantial Completion Payment (the “Final Voucher”) after issuance of substantial completion letter by the AE. In such Final Voucher, Contractor shall include the substantial completion letter and all such documents and information as the CM requires as specified in this above sections. c. Contractor shall turn the Work over to CUNY in new condition, in proper repair and in full adjustment, ready for use and occupancy. d. The CM will make Final Payment only after all such obligations of Contractor which are listed in detail above are discharged; including specifically guarantees, warrantees, as built drawings, waste manifests if any and Operations and Maintenance Manuals. The CM shall not make final payment nor release remaining retainage unless all required documents are turned over to the CM Div. 01 General Requirements Page 49 of 53 Roosevelt Hall Renovation Project Brooklyn College D. e. The CM reserves the right to correct Partial Payments previously made before issuing both Substantial Completion Payment and Final Payment. f. Acceptance by Contractor, or by Contractor's agent, of Final Payment, whether such payment be made pursuant to any judgment of any court or otherwise, shall constitute and operate as a release of CUNY and CM from any and all claims of and liability to Contractor for anything done or furnished for or relating to or arising out of Agreement, and for any prior act, neglect or default on the part of CUNY or any of its officers, agents or employees excepting only a claim against its officers, agents or employees for the amounts deducted or retained in accordance with the terms and provisions of this Agreement or by law, and excepting a claim, not otherwise waived, which is contained in the Verified Statement filed pursuant to Section 11 above. g. Nothing in this Section shall be deemed to relieve Contractor of any obligation to complete the requirements of the Contract Documents. h. Nothing in this Section shall be deemed to relieve the Contractor from the obligation of giving timely notice of claim pursuant to any other provision of this Agreement. PARTIAL PAYMENTS a. Contractor may submit a requisition for a Partial Payment not more than once each month. b. Such requisitions shall be in a form approved by the CM. c. Invoices shall certify that Subcontractors, Sub-subcontractors and Vendors have been paid to date. d. The CM reserves the right to deny payment for Materials and Equipment in advance of their actual incorporation into, or use in, the Work. e. The CM will retain five percent (5%) from each invoice until Completion. SECTION 01 78 13 PUNCH LIST A. PUNCH LIST 1. Contractor shall notify the CM in writing when all Work is completed. The notification shall include a joint statement from each trade that they have closely inspected the Work and that all offices, public spaces, classrooms, storage areas, toilets and all other interior and exterior areas have been complete and/or restored in accordance with the contract, that all damaged items have been replaced or repaired as per contract requirements, and the entire building and grounds are ready for Punch List review by the CM and the AE. The CM will then review the condition of the building and grounds at that time to determine acceptability of the Work and will develop a Punch List of items requiring correction. 2. The CM will deliver the Punch List to Contractor of uncompleted and/or unsatisfactory Work. Contractor shall work expeditiously to complete all Punch List items within fifteen (15) working days after receiving the Punch List from the CM. If Contractor fail to correct Div. 01 General Requirements Page 50 of 53 Roosevelt Hall Renovation Project Brooklyn College all Punch List work within the specified fifteen (15) day period, the CM may complete the Work with its own forces and shall withhold payment to Contractor in the amount of one and one half (1-1/2) times the estimated cost of the work as determined by the CM. Such withheld monies shall be backcharged against Contractor’s next Partial Payment Requisition due and shall be deducted from the Final Payment in the form of a Credit Change Order. SECTION 01 78 23 OPERATION AND MAINTENANCE DATA A. Operations and Maintenance Manuals 1. Contractor shall submit three copies of an Operating and Maintenance Manual for all operating equipment. Manuals shall consist of plastic covered three ring binders with Project name lettered on the front. If possible, sheets shall be 8 1/2" x 11". When larger sheets must be used, they shall be neatly folded to 8 1/2" x 11" and inserted as a pullout. Each manual shall include: a. Name, address, and trade of all subcontractors, manufacturers, and suppliers who participated in the construction or furnished materials and equipment. b. Complete maintenance instruction, name, address, telephone number of installing Subcontractor and manufacturer's Local representative for each piece of operative equipment and finish material. c. Catalog data bearing the Architect's action stamp on all product data submittals. Manufacturer's advertising or promotional literature will not be acceptable. d. Manufacturer's name, model number, service manual, spare parts lists, and descriptive literature for all components. e. Preventive maintenance instructions and schedules for all major equipment. f. Instruction for starting and operating the actual system as installed. g. Field test reports. h. Copies of all guarantees and warranties issued by any manufacturer or subcontractor for material or equipment installed as part of the Work. i. Any other information necessary for proper maintenance of any operating equipment. B. Bulletins, Operating And Service Manuals 1. Submit three (3) sets of prints in the form of technical bulletins, operating and service manuals, or other printed matter as a shop drawing, having diagrams or drawings thereon of a material or equipment installed in the Work. SECTION 01 78 36 GUARANTEES AND WARRANTIES A. GUARANTEES 1. Contractor and subcontractors shall make any required or directed adjustments, repairs and replacement which are necessary because of faulty work or defective material upon 48 hours notice by the CM during construction, and by CUNY DDCM for a period set forth in the individual specifications for each trade but not less than one (1) year after Div. 01 General Requirements Page 51 of 53 Roosevelt Hall Renovation Project Brooklyn College completion of the entire job or until all permits and approvals have been received, whichever is later. In the event that any portion of the Site is taken over by CUNY prior to Final Acceptance, the guarantees for this portion only shall commence from the time of takeover. 2. Guarantee the Work to be free of all defects. Replace or repair defective materials or workmanship, and all damage to the work of other trades resulting from the replacement or repairs during guarantee periods. 3. The acceptance shall be the date of final payment of the Work or the date of a formal notice of acceptance, whichever is earlier. B. WARRANTIES 1. Provide a special Project warranty, signed by Contractor, Installer, and Manufacturer, agreeing to replace, and/or restore defective materials and workmanship of mechanical systems during the warranty period. "Defective" includes, but is not limited to, operation or system failures, but is not limited to, operation or system failures, performance below required levels, unsafe conditions, finishes, need for excessive maintenance, abnormal noise or vibration, and similar, unusual, unexpected or unsatisfactory conditions. 2. The warranty period is for twelve (12) months, starting on the date of final acceptance of the building by CUNY. SECTION 01 78 39 PROJECT RECORD DOCUMENTS A. RELATED DOCUMENTS 1. Section 01 77 13 – Substantial Completion 2. Section 01 77 19 – Contract Closeout 3. Section 01 78 23 – Operation and Maintenance Data 4. Section 01 78 36 – Guarantees and Warranties B. RECORD (AS-BUILT) DRAWINGS ( Contractor) 1. The CM at the Design/Construction kick-off meeting will furnish to Contractor and subcontractors at no cost a complete set of existing drawings pertaining to the Work to be performed under his/her Agreement. It is the responsibility of Contractor to modify the drawings to indicate all changes and corrections, if any, occurring in the Work as actually installed. Contractor is required to furnish all other drawings, such as addenda drawings and supplementary drawings, as may be necessary to indicate all Work in detail as actually completed. 2. All professional seals must be blocked out. Title box complete with Project title and Consultants names will remain. 3. Contractor shall maintain, during the progress of the Work, an accurate record of the Work as actually installed, on record drawings. These drawings shall be revised and updated as necessary on an on-going basis, and shall be made available to the CM upon request. 4. Contractor's attention is particularly directed to the necessity of keeping accurate records of all subsurface and concealed work, so that the record drawings may contain this Div. 01 General Requirements Page 52 of 53 Roosevelt Hall Renovation Project Brooklyn College information in exact detail and location. Drawings should also show all connections, valves, gates, switches, cutouts and similar operating equipment. 5. Before substantial completion payment, Contractor shall furnish to the CM three (3) complete set of record (as-built) drawings, in ink, indicating all of the work and locations as actually installed, plus one (1) electronic copy. 6. Record (As-Built) drawings shall be of the same size as the Consultant’s Drawings, with a 1/2-inch margin space on three sides and a 2-inch margin space on the left side 7. Each record drawing shall bear the legend "RECORD (AS-BUILT) DRAWING" in heavy block lettering, 1/2-inch high and shall contain the following data: RECORD (AS-BUILT) DRAWINGS Contractor’s Name Contractor’s Address Drawn by Checked by Date Date 8. Record (As-Built) Drawing Title Sheet: Contractor shall prepare a title sheet of the same size as Record (As-Built) Drawings and containing the following: a. Name of the Project and Location b. Contractor's Name. c. Record of changes: a caption description of work affected, and the date and recorded number of Change Order or other authorization of the change(s). d. List of Record (As-Built) Drawings. 9. All changes from contract drawings shall be conspicuously encircled and identified by change order number correlating to changes listed on "Title Sheet." Contractor shall show within the encircled areas the Work as actually installed. 10. Bulletins, Operating And Service Manuals - Where Contractor has submitted prints in the form of technical bulletins, operating and service manuals, or other printed matter as a shop drawing, having diagrams or drawings thereon of a material or equipment installed in the Work, he/she shall furnish three (3) sets thereof. C. Miscellaneous Record Submittals: Refer to other Specification Sections for requirements of miscellaneous record keeping and submittals in connection with actual performance of the Work. Immediately prior to the date or dates of Substantial Completion, complete miscellaneous records and place in good order. Identify miscellaneous records properly and bind or file, ready for continued use and reference. Submit for the CUNY's records. D. FLOW AND WIRING DIAGRAMS 1. Provide detailed and simplified type, one-line, color-coded flow and wiring diagrams. Provide to the CM in a frame with Plexiglas front. Mount on wall where directed by the CM. E. PERMITS, GUARANTEES, BONDS AND CERTIFICATES 1. Deliver to CM originals of all permits obtained by Contractor, including the Certificate of Occupancy, and originals of all Contractors' guarantees, warranties, bonds and Certificates of Controlled Inspections. END OF DIVISION 01 Div. 01 General Requirements Page 53 of 53 SECTION 042000 UNIT MASONRY PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. 1.3 The Work of this Section includes all labor, materials, equipment and services necessary to complete the unit masonry work as shown on the drawings and/or specified herein, including but not necessarily limited to the following: 1. Concrete block walls and partitions. 2. Metal joint reinforcing, anchors, ties, weeps, closures and related accessories for masonry. 3. Control and expansion joints in masonry, filled with joint fillers. 4. Chases, recesses, pockets and openings in masonry as required for installation of work by others. 5. Building in of items furnished by others into masonry, including access doors, door frames, anchors, sleeves and inserts, and other similar items to be embedded in masonry. 6. Grouting in of metal items built into masonry work. 7. Protection, pointing and cleaning of masonry. SUBMITTALS A. B. Submit Shop Drawings for the following: 1. Anchoring details. 2. Control and expansion joint locations and details. Submit Samples for the following: 1. Joint reinforcing, each type, width and proposed location (labeled). 2. Anchors, wedges and ties, each type, width and proposed location (labeled). 3. Joint filler, each type. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-1 Unit Masonry July 28, 2010 C. D. Submit technical and installation information for the following: 1. Mortar materials, each material and mortar type. 2. Certification of mortar mix. 3. Flashing material, descriptive literature. 4. Concrete block, joint reinforcing, anchors, ties and joint filler; submit manufacturer's technical and descriptive literature. 5. Block manufacturer shall submit certifications of compliance with ASTM C 90, C 331 and UL 618 prior to any job site delivery. Field sampling of concrete block may be tested by an Independent Testing Laboratory retained by the Owner according to the requirements of ASTM C 140. Construction Procedures (Submit the following) 1. 1.4 Procedures and materials for cleaning masonry work; including certification that cleaner will not adversely affect stone, gaskets, sealants, etc. QUALITY ASSURANCE A. Conform to the following non-cumulative tolerances (any masonry work not meeting these standards shall be re-built as directed by the Architect). 1. Variation from the plumb: a. 2. C. Minus Plus 1/8" 1/8" Variation in dimensions of masonry openings: a. b. B. 1/8" Variation in cross-sectional dimensions of columns and in thickness of walls: a. b. 3. In lines and surfaces of columns, walls and arrises: 1). In 10 feet Horizontal dimension Vertical dimension -0" + 1/16" +0" - 1/16" Work of this Section shall conform to the requirements of the following: 1. 2005 ACI 530/ASCE 5/TMS 402 Building Code Requirements for Masonry Structures. 2. 2005 ACI 530-1/ASCE 6/TMS 602 Specifications for Masonry Structures. Pre-Construction Conference: Prior to installation of masonry and associated work, Contractor shall arrange a meeting with Masonry Subcontractor, installers of related work, and other entities concerned with masonry wall performance, including the Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-2 Unit Masonry July 28, 2010 Architect and Owner. Contractor shall record discussions and agreements and furnish copy to each participant. Provide at least seventy-two (72) hours' advance notice to participants prior to convening conference. Review methods and procedures related to masonry work, including, but not limited to, the following: 1.5 1. Review masonry requirements (drawings, specifications and other Contract Documents). 2. Review required submittals, both completed and yet to be completed. 3. Review and finalize construction schedule related to masonry work and verify availability of materials, installer’s personnel, equipment and facilities needed to make progress and avoid delays. 4. Review required inspection, testing, certifying and material usage accounting procedures. 5. Review weather and forecasted weather conditions, and procedures for coping with unfavorable conditions. PRODUCT HANDLING A. General: Deliver, store, handle and protect all materials from damage, moisture, dirt and intrusion of foreign matter. Store all masonry units and mortar materials on raised platforms and under ventilated and waterproof cover. Store packaged materials in manufacturer's unopened containers, marked with manufacturer's name and product brand name. Immediately reseal containers after partial use. Remove and replace damaged materials. B. Masonry Units: Pack, deliver and store to prevent breakage, cracking, chipping, spalling or other damage. Store, protect and ventilate units at project site. C. Aggregate: Store with provisions for good drainage. D. Reinforcement and Anchors: Store and protect so that when placed, joint reinforcement and anchors will be free of soil, dirt, ice, loose rust, scale, or other coatings which would destroy or reduce bond with mortar, and will not be disfigured or bent out of shape. 1.6 CODE REQUIREMENTS A. Work of this Section shall conform to all applicable requirements of the New York City Building Code. 1. Concrete block shall comply with Reference Standard RS-10. 2. Concrete blocks shall be type approved by the Board of Standards and Appeals. a. Concrete blocks used for fireproofing shall conform to New York City Building Code requirements and shall provide ratings required by the Contract Documents. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-3 Unit Masonry July 28, 2010 3. For special inspection of masonry construction, refer to Section 014100, "Testing and Inspection." B. Fire rated masonry partitions shall have MEA number. C. Conform to New York City Local Law 17-95 for Seismic Requirements. D. Comply with New York City Section 32-05 of Chapter 32 of Title 1 of the Official Compilation of the Rules of the City of New York regarding “Impact Resistant Stair and Elevator Enclosures” when such enclosures are of masonry construction. 1.7 JOB CONDITIONS A. In cold weather, when the outside temperature is below forty (40) degrees F., conform to the requirements of "Cold Weather Masonry Construction and Protection Recommendations" publication by Brick Industry Association (BIA). No anti-freeze admixtures are permitted. B. Hot-Weather Requirements: Protect unit masonry work when temperature and humidity conditions produce excessive evaporation of water from mortar and grout. Provide artificial shade and wind breaks and use cooled materials as required. Do not apply mortar to substrates with temperatures of 100 deg. F. and above. C. Protection of Masonry: During erection, cover tops of walls, projections, and sills with waterproof sheeting at end of each day's work. Cover partially completed masonry when construction is not in progress. D. 1. Extend cover a minimum of 24" down both sides and hold cover securely in place. 2. Where one wythe of multi-wythe masonry walls is completed in advance of other wythes, secure cover a minimum of 24" down face next to unconstructed wythe and hold cover in place. Stain Prevention: Prevent grout, mortar, and soil from staining the face of masonry to be left exposed or painted. Immediately remove grout, mortar, and soil that come in contact with such masonry. 1. Protect base of walls from rain-splashed mud and mortar splatter by coverings spread on ground and over wall surface. 2. Protect sills, ledges, and projections from mortar droppings. 3. Protect surfaces of window and door frames, as well as similar products with painted and integral finishes, from mortar droppings. 4. Turn scaffold boards near the wall on edge at the end of each day to prevent rain from splashing mortar and dirt on completed masonry. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-4 Unit Masonry July 28, 2010 PART 2 PRODUCTS 2.1 MATERIALS A. Standard Concrete Block 1. Portland cement, ASTM C 150, Type 1, one source. 2. Aggregates, ASTM C 331, lightweight expanded shale, clay or slate aggregates, manufactured by the rotary kiln process equal to "Solite," "Norlite" or "Haydite." a. 3. All block shall be from one aggregate type and from one manufacturer. Concrete Masonry Units: Load bearing lightweight aggregate concrete masonry units conforming to the requirements of ASTM C 90. a. b. Block at stair and elevator enclosurees block requiring acoustic separation, and block for rated walls shall be 75% solid units. All other block may be hollow units. 4. The producer of the concrete masonry units shall furnish certification from an independent testing laboratory confirming that all 8" or larger masonry units meet all of the UL 618 requirements for two (2) hours or better (as required), referencing full scale fire test reports (ASTM E 119). All 4" and 6" units shall conform to "National Bureau of Standards" and "National Research Council" full scale fire tests. 5. Sizes and Shapes: Nominal face size 8" x 16" by thickness as indicated on drawings, with stretcher units, jamb units, header units, square corner units (at ends and corners of exposed or painted work), sash units (at control joints within masonry wall), lintel units and other special shapes and sizes required to complete the work. 6. Finish: For exposed or painted block surfaces, in addition to ASTM requirements, block shall have uniformly dense, flat, fine grain texture, with no cracks, chips, spalls, or other defects which would impair appearance. For concealed CMU, surfaces shall be free from deleterious materials that would stain plaster or corrode metal. 7. Curing: All concrete block shall be steam cured, and air dried for not less than thirty (30) days before delivery. 8. Density of concrete block shall not exceed one hundred and five (105) lbs. per cubic foot. 9. Shrinkage: Shrinkage of concrete blocks shall not exceed 0.065% when tested in accordance with ASTM C 426-99. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-5 Unit Masonry July 28, 2010 10. Water Content a. b. B. Joint Reinforcing for Masonry Walls 1. For interior block walls and partitions, provide standard reinforcing fabricated of 9 ga. side and cross rods, truss or ladder design, no ties, spaced every other block course. Provide prefabricated pieces at corners and intersections of walls or partitions. Reinforcing shall be mill galvanized conforming to ASTM A 641, Class B-1, applied after fabrication. 2. Wire used in assemblies noted above shall be cold drawn steel wire conforming to ASTM A 82. 3. Approved Joint Reinforcing Manufacturers a. b. c. d. C. Hohmann & Barnard Dur-O-Wal Heckmann Building Products National Wire Products Industries, Inc. Anchors and Ties 1. For anchoring masonry to structural steel, provide hot-dip galvanized steel anchors as listed made by Hohmann & Barnard or approved equal manufacturer noted above. Galvanizing shall conform to ASTM A 153, with zinc coating of 1.5 oz. of zinc per sq. ft. a. b. c. d. D. At the time of delivery to the job site, concrete masonry units shall have a value, in weight of contained water, of not more than thirty (30) percent of the fully saturated content for the unit tested. Ship all units from the factory, and store at the job site, with all necessary protection to prevent increase of water content from rain and other sources. No. 355 column anchors. No. 356 column anchors. No. 357 beam anchors. No. 359 F anchor straps with VWT tie. 2. For anchoring CMU interior partitions to underside of steel beams, provide hot-dip galvanized steel tube anchor equal to No. PTA-420 made by Hohmann & Barnard or approved equal. 3. For anchoring CMU interior partitions to underside of structural deck, provide 4" x 4" x 1/4" galvanized steel angles (ASTM A 36), 3'-0" long spaced 3'-0" o.c. alternately on each side of partition. Anchor partition securely to structural deck Reinforcing Bars and Rods: ASTM A 615, Grade 60. See Drawings for size. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-6 Unit Masonry July 28, 2010 E. Control and Expansion Joint Fillers 1. Vertical Installation Within Concrete Masonry Wall: Extruded high grade neoprene rubber, cross shape, for use with concrete masonry sash units, which shall provide a force fit in the grooves of the sash block, and shall have 1/2" diameter tubular ends (compressed 25% when installed in 3/8" wide joint). a. b. 2. 2.2 Provide the following sizes: 1). 2-5/8" wide control joint fillers for 4" block walls. 2). 4-5/8" wide for 6" block walls. 3). 6-5/8" wide for 8", 10" and 12" block walls. Provide backer rod and sealant joint over joint filler as per drawings. Isolation Joint Filler at Abutting Construction and at Intersecting CMU Walls: Compressible and resilient closed cell neoprene gasket with pressure sensitive adhesive backing, thickness 30% greater than thickness of joint. Acceptable joint filler shall be "Everlastic, Type NN-1" by Williams Products, Inc., or approved equal. Recess joint filler and install backer rod and sealant as per drawings and Section 079200 of these specifications. MORTAR MATERIALS A. Portland Cement: ASTM C 150, Type 1, standard color, one source. B. Hydrated Lime: ASTM C 207, Type S, as manufactured by Corsons, or approved equal. C. Sand: Clean, washed, buff colored sand, graded per ASTM C 144. D. Water: Clean, fresh and suitable for drinking. 2.3 MORTAR MIX A. Interior Masonry Construction: Provide Portland cement/lime mortar conforming to ASTM C 270, Type N, for load bearing conditions, mortar shall conform to ASTM C 270, Type M. B. Grout for Unit Masonry: Comply with ASTM C 476 for grout for use in construction of unit masonry. Use grout of consistency (fine or coarse) at time of placement which will completely fill all spaces intended to receive grout. C. Mixing 1. General: Add cement just before mixing and mix dry. Use sufficient amount of water as necessary to produce workable mix. Mix in small batches to make plastic mass. 2. Mixing: Machine mix all mortars in approved type mixer with device to accurately and uniformly control water. Add hydrated lime dry. Mix dry materials not less than two (2) minutes. Add water, then mix not less than three (3) minutes. Mix only amount of mortar that can be used before initial set. Do not Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-7 Unit Masonry July 28, 2010 use mortar which has reached its initial set or two (2) hours after initial mixing, whichever comes earlier. Mortar may not be re-tempered. Clean mixer for each batch, whenever mortar type is changed, and at end of each day's work. D. 3. Acceleration or other admixtures not permitted. 4. Mortar shall have a flow after suction of not less than seventy-five (75) percent of that immediately after mixing as determined by ASTM C 91. Admixtures 1. No air-entraining admixtures or cementitious air-entraining admixtures shall be used in the mortar. materials containing 2. No antifreeze compounds or other substances shall be used in the mortar to lower the freezing point. 3. Calcium chloride or admixtures containing calcium chloride shall not be used in mortar. PART 3 EXECUTION 3.1 SURFACE CONDITIONS A. B. 3.2 Inspection 1. Prior to all work of this Section, carefully inspect the installed work of all other trades and verify that all such work is complete to the point where this installation may properly commence. 2. Verify that masonry may be completed in accordance with all pertinent codes and regulations, the referenced standards, and the original design. 3. Do not start any work until mock-ups are approved by the Architect. Discrepancies 1. In the event of discrepancy, immediately notify the Architect in writing. 2. Do not proceed with installation in areas of discrepancy until all such discrepancies have been fully resolved. COORDINATION A. 3.3 Carefully coordinate with all other trades to ensure proper and adequate interface of the work of other trades with the work of this Section. PREPARATION A. Concrete Block: Do not wet concrete block units. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-8 Unit Masonry July 28, 2010 3.4 INSTALLATION A. B. General 1. Build walls to the full thickness shown. Build single wythe walls to the actual thickness of the masonry units, using units of nominal thickness shown. 2. Build chases and recesses as shown or required for the work of other trades. 3. Leave openings for equipment to be installed before completion of masonry work. After installation of equipment, complete masonry work to match work immediately adjacent to the opening. 4. Lay out walls in advance for accurate spacing of surface bond patterns with uniform joint widths and to properly locate openings, movement type joints, returns and off-sets. Avoid the use of less than half size units at corners, jambs and wherever possible. 5. Lay up walls plumb and true with courses level, accurately spaced and coordinated with other work. 6. Provide templates made of steel studs for plumbing of two story masonry openings. 7. Pattern Bond: Lay exposed masonry patterns as noted on drawings. If not shown, provide running bond. Lay concealed concrete block with all units in a wythe bonded by lapping not less than two (2) inches. Bond and interlock each course of each wythe at corners. Do not use units of less than four (4) inches horizontal face dimensions at corners or jambs. 8. Where possible, masonry walls and partitions shall be built after all overhead ducts, pipes and conduits are in place and tested. Masonry shall be neatly built around the items above. Walls and partitions shall be plumb, true to line and free from defects such as open cells, voids, dry joints and other similar defects. In rooms and spaces scheduled to have concrete block finish, all such surfaces including upper wall surfaces up to termination of structural ceiling in spaces without suspended ceilings, shall be made suitable for paint application. Cutting of openings in walls and partitions in place shall be done only with the approval of the Architect. Mortar Bedding and Jointing 1. Lay concrete masonry units with full mortar coverage on horizontal and vertical face shells. Bed webs in mortar in starting course on exterior walls and in all courses of piers, columns and pilasters, where solid CMU is used and where adjacent to cells or cavities to be reinforced or filled with concrete or grout. a. 2. To ensure alignment of brick and block coursing, adjust block back-up by cutting block to insure alignment of coursing or use adjustable anchorage. Lay masonry walls with 3/8" joints unless otherwise shown on drawings. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-9 Unit Masonry July 28, 2010 3. Tool exposed joints of CMU slightly concave. Concealed joints shall be struck flush. 4. Remove masonry units disturbed after laying; clean and reset in fresh mortar. Do not pound corners at jambs to fit stretcher units which have been set in position. If adjustments are required, remove units, clean off mortar and reset in fresh mortar. C. Stopping and Resuming Work: Rake back 1/2 block length in each course; do not tooth. Clean exposed surfaces of set masonry, wet units lightly (if required) and remove loose masonry units and mortar prior to laying fresh masonry. D. Built-In Work 1. As the work progresses, build in items specified under this and other Sections of these specifications. Fill in solidly with masonry around built-in items. 2. Mortar in door frames, access doors, louvers and other metal items embedded or built into masonry work solidly with mortar as the masonry units are laid up. 3. Grout under lintels, bearing plates, and steel bearing on masonry with solid bed grout. 4. Sleeves, pipes, ducts and all other items which pass through masonry walls shall be caulked with interior grade sealant, so as to be air tight and prevent air leakage. Pack voids in rated masonry walls with mineral fiber insulation. 5. Fill vertical cells of masonry units solid with grout which have anchoring, reinforcing rods, supporting or hanging devices embedded in the cell including stone anchors and window or curtain wall anchors. 6. Fill vertical cells of masonry units solid with mortar on each side of door frames to sixteen (16) inches beyond. 7. Unless otherwise noted, fill vertical cells of masonry units solid with grout which are below steel bearing plates, steel beams, and ends of lintels, to eight (8) inches beyond bearing and from floor to bearing. 8. Place wire mesh in horizontal joint below masonry unit cells to be filled with mortar, to prevent mortar from dropping into unfilled cells below. 9. Masonry indicated as being reinforced shall have all voids filled solid with grout. Grout shall be consolidated in place by vibration or other methods which insure complete filling of cells. When the least clear dimension of the grouted cell is less than two (2) inches, the maximum height of grout pour shall not exceed twelve (12) inches. When the least clear dimension is two (2) inches or more, maximum height of grout pour shall not exceed forty-eight (48) inches. When grouting is stopped for one (1) hour or longer, the grout pour shall be stopped 1-1/2" below the top of a masonry unit. Vertical bar reinforcing shall be accurately placed and held in position while being grouted, and shall be in place before grouting starts. All such reinforcing shall have a minimum clear cover of 5/8". Lap all bars a minimum of forty (40) bar diameters and provide steel spacer ties (not to exceed Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-10 Unit Masonry July 28, 2010 192 bar diameter) to secure and position all vertical steel and prevent displacement during grouting. Provide continuous horizontal reinforcement embedded in mortar joints every second course. 10. Masonry walls to be fully grouted include 8” CMU walls designated for acoustic separation, 10” CMU walls enclosing stairs and elevator shafts and any other CMU walls noted on drawings to be fully grouted. E. F. G. Cutting and Patching 1. All exposed masonry which requires cutting or fitting shall be cut accurately to size with motorized carborundum or diamond saw, producing cut edges. 2. Do not saw cut any masonry openings in face brick construction without Architect's approval and after a procedure has been reviewed and approved. 3. Holes made in exposed masonry units for attachment of handrail brackets and similar items shall be neatly drilled to proper size. 4. All masonry which requires patching in exposed work, if approved by Architect, shall be patched neatly with mortar to match appearance of masonry as closely as possible and to the Architect's satisfaction. Rake back joints and use pointing mortar to match as required. Solid Wall Construction 1. Fill the vertical longitudinal joint between wythes solidly with mortar by parging the in-place wythe and shoving units into the parging. 2. Tie wythes with continuous horizontal reinforcement embedded in mortar joints sixteen (16) inches o.c. vertically. Interior Block Partitions 1. Build to full height unless otherwise shown on drawings. At non-rated partitions fill void between CMU and structural deck with continuous neoprene filler. At fire rated partitions, fill void with mineral fiber fire stop material. Fasten to structure at top of partition using steel angles as specified herein. 2. Provide continuous horizontal joint reinforcing every other block course, except as otherwise noted. Fully embed longitudinal side rods in mortar for their entire length with a minimum cover of 5/8". Lap reinforcement a minimum of six (6) inches at ends of units. 3. Provide continuity at corners and wall intersections by use of prefabricated "L" and "T" sections. Cut and bend units as directed by manufacturer for continuity at returns, offsets, column fireproofing, pipe enclosures and other special conditions. 4. Corners a. Provide interlocking masonry unit bond in each course at corners. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-11 Unit Masonry July 28, 2010 b. 5. Intersecting and Abutting Walls a. H. 1. Provide ties and anchors as shown or specified, but not less than one metal tie, spaced not to exceed sixteen (16) inches o.c. horizontally and/or vertically. Provide additional ties within 1'-0" of all openings and spaced not more than 24" apart around perimeter of openings. 2. Anchor masonry to structure complying with the following: Provide an open space not less than 1/2" in width between masonry and structural member, unless otherwise shown. Keep open space free of mortar or other rigid materials. Control and Expansion Joints 1. Provide vertical expansion, control and isolation joints in masonry as shown. Build in related items as the masonry work progresses. 2. CMU Control Joint Spacing: If location of control joints is not shown, place vertical joints spaced not to exceed 20'-0" o.c. In addition, locate joints at points of natural weakness in the masonry work, including the following: a. b. c. d. e. f. 3.5 Unless vertical control joints are shown as part of structural frame, provide interlocking masonry bond. Provide starters and special shapes as shown on the drawings to bond these horizontal reinforcement using prefabricated "T" units at interior partitions. Ties and Anchors for Masonry Construction a. I. Provide continuity at corners with prefabricated "L" reinforcement units, in addition to masonry bonding. At structural column or joint between bay. Above control joints in the supporting structure. Above major openings at end of lintels upward and below at ends of sills downward. Place at one side of jamb for openings not less than 7'-0" wide and at both sides for openings over 6'-0" wide. At reduction of wall thickness. Where masonry abuts supporting structure. If additional joints are required, indicate same on approved shop drawings. CLEANING, PROTECTION, ADJUSTMENT A. Protection 1. The Contractor shall take adequate precautions for the protection of all surfaces against mortar spatter, and shall immediately remove any such spatter should it inadvertently occur, leaving no stain or discoloration. 2. Excess mortar shall be wiped off the masonry surfaces as the work progresses. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-12 Unit Masonry July 28, 2010 B. 3. Wood coverings shall be placed over all such masonry surfaces as are likely to be damaged during the progress of the entire project. 4. Protective measures shall be performed in a manner satisfactory to the Architect. 5. Damaged masonry units shall be replaced to satisfaction of the Architect. 6. Exterior masonry walls shall be draped with waterproof covering until copings are in place, to prevent water penetration in cavity. Clean-Up 1. C. Upon completion, all exposed masonry shall be thoroughly cleaned following recommendations of the IMI Technical Note No. 20. Before applying any cleaning agent to the entire wall, it shall be applied to a sample wall area of approximately 4' x 4' in a location approved by the Architect. No further cleaning work may proceed until the sample area has been approved by the Architect, after which time the same cleaning materials and method shall be used on the remaining wall area. If stiff brushes and water do not suffice, the surface shall be thoroughly saturated with clear water and then scrubbed with a solution of an approved detergent masonry cleaner, equal to "Vana Trol" made by ProSoCo Inc. or equal made by Diedrich or approved equal, mixed as per manufacturer's directions, followed immediately by a thorough rinsing with clear water. All lintels and other corrodible parts shall be thoroughly protected during cleaning. Pointing: Point any defective joint with mortar identical with that specified for that joint. END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 042000-13 Unit Masonry July 28, 2010 SECTION 081113 STEEL DOORS AND FRAMES PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. 1.3 Work of this Section includes all labor, materials, equipment and services necessary to complete the steel doors and frames work as shown on the drawings and/or specified herein, including, but not limited to, the following: 1. Interior hollow metal doors and frames for fire rated and unrated door openings. 2. Interior hollow metal vision panels. 3. Preparation of metal doors and frames to receive finish hardware, including reinforcements, drilling and tapping necessary. 4. Preparation of hollow metal doors to receive glazing where required. 5. Furnishing anchors for building into masonry and drywall. 6. Factory prime painting of work of this Section. 7. Doors and frames scheduled as smoke separations. RELATED SECTIONS A. Wood Doors – Section 081416. B. Finish hardware – Section 087100. C. Glass and glazing – Section 088000. D. Gypsum drywall – Section 092900. E. Painting – Section 099000. 1.4 SUBMITTALS A. Product Data: Include construction details, material descriptions, core descriptions, label compliance, compliance with standards referenced herein, sound and fire-resistance ratings, and finishes for each type of door and frame specified. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-1 Steel Doors and Frames July 28, 2010 B. Shop Drawings: Show fabrication and installation of doors and frames. Include details of each frame type, elevations of door design types, conditions at openings, details of construction, reinforcement for surface applied hardware, dimensions of profiles and hardware preparation, location and installation requirements of door and frame hardware and reinforcements, and details of joints and connections. Show anchorage and accessories. C. Door Schedule: Submit schedule of doors and frames using same reference numbers for details and openings as those on Drawings. 1. 1.5 Coordinate glazing frames and stops with glass and glazing requirements. QUALITY ASSURANCE A. Manufacturer Qualifications: A firm experienced in manufacturing custom steel doors and frames similar to those indicated for this Project and with a record of successful inservice performance, as well as sufficient production capacity to produce required units. B. Testing Agency Qualifications: An independent agency qualified according to ASTM E 329 for testing indicated, as documented according to ASTM E 548. C. Source Limitations: Obtain custom steel doors and frames through one source from a single manufacturer. D. Fire-Rated Door and Frame Assemblies: Assemblies complying with NFPA 80 that are listed and labeled by a testing and inspecting agency acceptable to authorities having jurisdiction, for fire-protection ratings indicated. 1. Test Pressure: Test according to NFPA 252 or UL 10C. After 5 minutes into the test, the neutral pressure level in furnace shall be established at 40" or less above the sill. 2. Oversize Fire-Rated Door Assemblies: For units exceeding sizes of tested assemblies, provide certification by a testing agency acceptable to authorities having jurisdiction that doors comply with standard construction requirements for tested and labeled fire-protection-rated door assemblies except for size. 3. Temperature-Rise Rating: At exit enclosures, provide doors that have a temperature-rise rating of 250 deg. F. (or greater if required by Code) maximum in 30 minutes of fire exposure. E. Fire-Rated, Borrowed-Light Frame Assemblies: Assemblies complying with NFPA 80 that are listed and labeled, by a testing and inspecting agency acceptable to authorities having jurisdiction, for fire-protection ratings indicated, based on testing according to NFPA 257 or UL 9. Label each individual glazed lite. F. Smoke-Control Door Assemblies: Comply with NFPA 105 or UL 1784. G. Fire rated assemblies must have M.E.A. approval with UL label. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-2 Steel Doors and Frames July 28, 2010 H. 1.6 Work of this Section must meet the minimum standards of ANSI 250.4 and SDI-100 (Steel Door Institute); where more stringent requirements are specified herein, such requirements shall apply. DELIVERY, STORAGE, AND HANDLING A. Deliver doors and frames palleted, wrapped, or crated to provide protection during transit and Project site storage. Do not use nonvented plastic. B. Inspect doors and frames, on delivery, for damage. Minor damage may be repaired provided refinished items match new work and are approved by Architect; otherwise, remove and replace damaged items as directed. C. Store doors and frames under cover at building site. Conform to the requirements of ANSI A 250-11-2001 for site storage unless more stringent requirements are noted herein. Place units on minimum 4-inch high wood blocking. Avoid using nonvented plastic or canvas shelters that could create a humidity chamber. If wrappers on doors become wet, remove cartons immediately. Provide minimum 1/4-inch spaces between stacked doors to permit air circulation. PART 2 PRODUCTS 2.1 FABRICATION – GENERAL A. Recycled Content of Steel Products: Provide products with average recycled content of steel products such that postconsumer recycled content plus one-half of preconsumer recycled content is not less than 25 percent. B. Fabricate hollow metal units to be rigid, neat in appearance and free from defects, warp or buckle. Accurately form metal to required sizes and profiles. Weld exposed joints continuously, grind, dress, and make smooth, flush and invisible. Metallic filler to conceal manufacturing defects is not acceptable. C. Unless otherwise indicated, provide countersunk flat Phillips or Jackson heads for exposed screws and bolts. D. Prepare hollow metal units to receive finish hardware, including cutouts, reinforcing, drilling and tapping in accordance with Finish Hardware Schedule and templates provided by hardware suppliers. Comply with applicable requirements of ANSI A115 "Specifications for Door and Frame Preparation for Hardware." E. Locate finish hardware as shown on final shop drawings in accordance with locations noted herein. 2.2 MANUFACTURERS A. Provide products manufactured by Steelcraft, Curries, Ceco Door Products, or approved equal meeting these specifications. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-3 Steel Doors and Frames July 28, 2010 2.3 FRAMES A. Materials 1. B. Frames for interior openings shall be either commercial grade cold-rolled steel conforming to ASTM A 1008/A, Type B or commercial grade hot-rolled steel conforming to ASTM A 1011/A, Commercial Steel, Type B. Metal thickness shall be not less than sixteen (16) ga. for frames in openings 4'-0" or less in width; not less than fourteen (14) ga. for frames in openings over 4'-0" in width. Design and Construction 1. All frames shall be welded units with integral trim, of the sizes and shapes shown on approved shop drawings. 2. All finished work shall be strong and rigid, neat in appearance, square, true and free of defects, warp or buckle. Molded members shall be clean cut, straight and of uniform profile throughout their lengths. 3. Jamb depths, trim, profile and backbends shall be as shown on drawings. a. Frames at drywall partitions shall be formed with double return backbends to prevent cutting into drywall surface. 4. Welded frames shall have corners mitered and reinforced and faces of welded frames shall be continuously back welded full depth and width of frame conforming to NAAMM Standard HMMA-820; face joints shall be hairline. 5. Minimum depth of stops shall be 5/8". 6. Frames for multiple or special openings shall have mullion and/or rail members which are closed tubular shapes having no visible seams or joints. All joints between faces of abutting members shall be securely welded and finished smooth. a. 7. Mullions shall have 16 ga. internal steel stiffeners welded not less than 4” o.c. Hardware Reinforcements a. Frames shall be mortised, reinforced, drilled and tapped at the factory for fully-templated mortised hardware only, in accordance with approved hardware schedule and templates provided by the hardware supplier. Where surface-mounted hardware is to be applied, frames shall have reinforcing plates. b. Minimum thickness of hardware reinforcing plates shall be as follows: 1). Hinge and pivot reinforcements - seven (7) ga., 1-1/4" x 10" minimum size. 2). Strike reinforcements - twelve (12) gauge Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-4 Steel Doors and Frames July 28, 2010 3). 4). 5). 8. Floor Anchors a. b. 9. Flush bolt reinforcements - twelve (12) gauge Closer reinforcements - twelve (12) gauge Reinforcements for surface mounted hardware - twelve (12) gauge. Provide adjustable floor anchors, providing not less than two (2) inch height adjustment. Minimum thickness of floor anchors shall be fourteen (14) gauge. Jamb Anchors a. b. Frames for installation in stud partitions shall be provided with steel anchors of suitable design, not less than eighteen (18) gauge thickness, securely welded inside each jamb as follows: 1). Frames up to 7'-6" height - four (4) anchors. 2). Frames 7'-6" to 8'-0" height - five (5) anchors. 3). Frames over 8'-0" height - five (5) anchors plus one additional for each 2'-0" or fraction thereof over 8'-0". Frames to be anchored to previously placed concrete or masonry shall be provided with minimum 3/8" concealed bolts set into expansion shields or inserts at six (6) inches from top and bottom and twenty-four (24) inches o.c. Reinforce frames at anchor locations with sixteen (16) gauge sheet steel stiffeners welded to frame at each anchor. 10. Anchors in exterior frames and in masonry walls shall be hot dip galvanized per ASTM A 153. 11. Frames for installation in masonry wall openings more than 4'-0" in width shall have an angle or channel stiffener factory welded into the head. Such stiffeners shall be not less than twelve (12) gauge steel and not longer than the opening width, and shall not be used as lintels or load bearing members. 12. Dust cover boxes (or mortar guards) of not thinner than twenty-six (26) gauge steel shall be provided at all hardware mortises on frames to be set in masonry or plaster partitions. 13. Ceiling Struts: Minimum 3/8" thick x 2" wide steel. 14. All frames shall be provided with a steel spreader temporarily attached to the feet of both jambs to serve as a brace during shipping and handling. 15. Loose glazing stops shall be of cold rolled steel, not less than twenty (20) gauge thickness, butted at corner joints and secured to the frame with countersunk cadmium-or zinc-plated screws. Interior frames may be provided with snap-on glazing stops. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-5 Steel Doors and Frames July 28, 2010 16. Except on weatherstripped frames, drill stops to receive three (3) silencers on strike jambs of single door frames and two (2) silencers on heads of double-door frames. 17. Grout frames where scheduled. Acceptable Product: Gypsolite by US Gypsum C. Finish: After fabrication, all tool marks and surface imperfections shall be removed, and exposed faces of all welded joints shall be dressed smooth. Frames shall then be chemically treated to insure maximum paint adhesion and shall be coated on all surfaces with one coat of rust-inhibitive baked-on alkyd primer standard with the manufacturer which is fully cured before shipment to a dry film thickness of 2.0 mils. 1. 2.4 Frames set in masonry walls shall be grouted in as described in Section 04800 – Unit Masonry. These frames shall have surfaces in contact with grout shop coated with epoxy coating equal to Series 27 FC Typoxy made by Tnemec or approved equal spray applied at 4 to 6 mils, passing NFPA 101, Class A for smoke and flame spread, tested per ASTM E 84. HOLLOW METAL DOORS A. B. Materials: Doors shall be made of commercial quality, level, cold rolled steel conforming to ASTM A 1008/A, Commercial Steel, Type B and free of scale, pitting or other surface defects. 1. Face sheets for interior doors shall be sixteen (16) gauge. Face sheets for exterior doors shall be not less than sixteen (16) gauge and shall have a hot dipped galvannealed coating conforming to ASTM A 924 and A 653, A-60 coating. The zinc alloy coating shall be a dull matte surface treated for paint adhesion. 2. Include mineral fiber or fiberglass core where specified, with minimum density 3.5 lb/ft3. Acceptable products: Roxul RockBoard 35. Design and Construction 1. All doors shall be custom made, of the types and sizes shown on the approved shop drawings, and shall be fully welded seamless construction with no visible seams or joints on their faces or vertical edges. Minimum door thickness shall be 1-3/4". 2. All doors shall be strong, rigid and neat in appearance, free from warpage or buckles. Corner bends shall be true and straight and of minimum radius for the gauge of metal used. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-6 Steel Doors and Frames July 28, 2010 3. Face sheets shall be stiffened by continuous vertical formed steel sections spanning the full thickness of the interior space between door faces. These stiffeners shall be not less than twenty two (22) gauge spaced not more than six (6) inches apart and securely attached to face sheets by spot welds not more than five (5) inches o.c. Spaces between stiffeners shall be sound deadened and thermal insulated the full height of the door with an inorganic non-combustible batt type material. 4. Door faces shall be joined at their vertical edges by a continuous weld extending the full height of the door. All such welds shall be ground, filled and dressed smooth to make them invisible and provide a smooth flush surface. 5. Top and bottom edges of all doors shall be closed with a continuous recessed steel channel not less than fourteen (14) gauge, extending the full width of the door and spot welded to both faces. Exterior doors shall have an additional flush closing channel at their top edges and, where required for attachment of weatherstripping, a flush closure also at their bottom edges. Openings shall be provided in the bottom closure of exterior doors to permit the escape of entrapped moisture. 6. Edge profiles shall be provided on both vertical edges of doors as follows: a. b. c. 7. Hardware Reinforcements a. b. 8. Single-acting swing doors - beveled 1/8" in two (2) inches. Double acting swing doors - rounded on 2-1/8" radius. No square edge doors permitted. Doors shall be mortised, reinforced, drilled and tapped at the factory for fully templated hardware only in accord with the approved hardware schedule and templates provided by the hardware supplier. Where surface-mounted hardware (or hardware, the interrelation of which is to be adjusted upon installation - such as top and bottom pivots, floor closers, etc.) is to be applied, doors shall have reinforcing plates. Minimum gauges for hardware reinforcing plates shall be as follows: 1). Hinge and pivot reinforcement - seven (7) gauge. 2). Reinforcement for lock face, flush bolts, concealed holders, concealed or surface mounted closers - twelve (12) gauge. 3). Reinforcements for all other surface mounted hardware - sixteen (16) gauge. Glass Moldings and Stops a. b. Where specified or scheduled, doors shall be provided with hollow metal moldings to secure glazing by others in accordance with glass opening sizes shown on drawings. Fixed moldings shall be securely welded to the door on the security side. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-7 Steel Doors and Frames July 28, 2010 c. Loose stops shall be not less than twenty (20) gauge steel, with mitered corner joints, secured to the framed opening by cadmium or zinc-coated countersunk screws spaced eight (8) inches o.c. Snap-on attachments will not be permitted. Stops shall be flush with face of door. Set glazing stops in a continuous bead of sealant. U-shaped neoprene glazing gaskets shall be continuous around perimeter forming an airtight seal. C. Finish: After fabrication, all tool marks and surface imperfections shall be dressed, filled and sanded as required to make all faces and vertical edges smooth, level and free of all irregularities. Doors shall then be chemically treated to insure maximum paint adhesion and shall be coated, on all exposed surfaces, with manufacturer's standard rust-inhibitive alkyd primer as specified for frames which shall be fully cured before shipment. D. Flatness: Doors shall maintain a flatness tolerance of 1/16" maximum, in any direction, including in a diagonal direction. 2.5 LABELED DOORS AND FRAMES A. Labeled doors and frames shall be provided for those openings requiring fire protection ratings as scheduled on drawings. Such doors and frames shall be labeled by Underwriters' Laboratories or other nationally recognized agency having a factory inspection service. B. If any door or frame specified by the Architect to be fire-rated cannot qualify for appropriate labeling because of its design, size, hardware or any other reason, the Architect shall be so advised before fabricating work on that item is started. 2.6 HARDWARE LOCATIONS A. 2.7 The location of hardware on doors and frames shall be as noted in “Recommended Locations for Architectural Hardware for Standard Steel Doors and Frames” of the Door Hardware Institute unless otherwise required by prevailing Handicap Codes. CLEARANCES A. B. Fabricate doors and frames to meet edge clearances as follows: 1. Jambs and Head: 1/8" plus or minus 1/16". 2. Meeting Edges, Pairs of Doors: 1/8" Plus or minus 1/16". 3. Bottom: 3/4", if no threshold. 4. Bottom: 3/8", at threshold. Fire rated doors shall have clearances as required by NFPA 80. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-8 Steel Doors and Frames July 28, 2010 2.8 MANUFACTURING TOLERANCES A. Manufacturing tolerance shall be maintained within the following limits: 1. Frames for Single Door or Pair of Doors a. b. c. 2. Doors a. b. c. d. e. 2.9 Width, Measured Between Rabbets at the Head 1). Nominal opening width +1/16", -1/32" Height (total length of jamb rabbet): 1). Nominal opening height + 3/64" Cross Sectional Profile Dimensions 1). Face: + 1/32" 2). Stop: + 1/32" 3). Rabbet: + 1/64" 4). Depth: + 1/32" 5). Throat: + 1/16". Frames overlapping walls to have throat dimension 1/8" greater than dimensioned wall thickness to accommodate irregularities in wall construction. Width: + 3/64" Height: + 3/64" Thickness: + 1/16" Hardware Cutout Dimensions 1). Template dimensions +0.015", -0" Hardware Location: + 1/32" PREPARATION FOR FINISH HARDWARE A. B. 2.10 A. Prepare door and frames to receive hardware: 1. Hardware supplier shall furnish hollow metal manufacturer approved hardware schedule, hardware templates, and samples of physical hardware where necessary to insure correct fitting and installation. 2. Preparation includes sinkages and cut-outs for mortise and concealed hardware. Provide reinforcements for both concealed and surface applied hardware: 1. Drill and tap mortise reinforcements at factory, using templates. 2. Install reinforcements with concealed connections designed to develop full strength of reinforcements. REJECTION Hollow metal frames or doors which are defective, have hardware cutouts of improper size or location, or which prevent proper installation of doors, hardware or work of other trades, shall be removed and replaced with new at no cost. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-9 Steel Doors and Frames July 28, 2010 PART 3 EXECUTION 3.1 INSPECTION A. Examine the areas and conditions where steel doors and frames are to be installed and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work. B. Preparation 1. Remove welded-in shipping spreaders installed at factory. 2. Prior to installation and with installation spreaders in place, adjust and securely brace standard steel door frames for squareness, alignment, twist, and plumb to the following tolerances: a. b. c. d. 3. C. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a line 90 degrees from jamb perpendicular to frame head. Alignment: Plus or minus 1/16 inch, measured at jambs on a horizontal line parallel to plane of wall. Twist: Plus or minus 1/16 inch, measured at opposite face corners of jambs on parallel lines, and perpendicular to plane of wall. Plumbness: Plus or minus 1/16 inch, measured at jambs on a perpendicular line from head to floor. Drill and tap doors and frames to receive non-templated mortised and surfacemounted door hardware. Installation 1. General: Provide doors and frames of sizes, thicknesses, and designs indicated. Install standard steel doors and frames plumb, rigid, properly aligned, and securely fastened in place; comply with Drawings and manufacturer's written instructions. 2. Set frames accurately in position; plumbed, aligned, and braced securely until permanent anchors are set. After wall construction is complete, remove temporary braces, leaving surfaces smooth and undamaged. a. b. c. d. Install frames in accordance with ANSI 250.11-20001, Recommended Erection Instructions for Steel Frames, unless more stringent requirements are specified herein. At fire-protection-rated openings, install frames according to NFPA 80. Where frames are fabricated in sections due to shipping or handling limitations, field splice at approved locations by welding face joint continuously; grind, fill, dress, and make splice smooth, flush, and invisible on exposed faces. Install frames with removable glazing stops located on secure side of opening. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-10 Steel Doors and Frames July 28, 2010 e. f. g. 3. Frames set in masonry walls shall have door silencers installed in frames before grouting. Remove temporary braces necessary for installation only after frames have been properly set and secured. Check plumb, squareness, and twist of frames as walls are constructed. Shim as necessary to comply with installation tolerances. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to floor and secure with post-installed expansion anchors. a. Floor anchors may be set with powder-actuated fasteners instead of postinstalled expansion anchors if so indicated and approved on Shop Drawings. 4. Metal-Stud Partitions: Solidly pack mineral-fiber insulation behind frames. Solidly fill with grout where indicated on the door schedule. Use Gypsolite by USG or approved equal. 5. In-Place Concrete or Masonry Construction: Secure frames in place with postinstalled expansion anchors. Countersink anchors, and fill and make smooth, flush, and invisible on exposed faces. 6. In-Place Gypsum Board Partitions: Secure frames in place with post-installed expansion anchors through floor anchors at each jamb. Countersink anchors, and fill and make smooth, flush, and invisible on exposed faces. 7. Ceiling Struts: Extend struts vertically from top of frame at each jamb to supporting construction above, unless frame is anchored to masonry or to other structural support at each jamb. Bend top of struts to provide flush contact for securing to supporting construction above. Provide adjustable wedged or bolted anchorage to frame jamb members. 8. Installation Tolerances: Adjust steel door frames for squareness, alignment, twist, and plumb to the following tolerances: a. b. c. d. 9. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a line 90 degrees from jamb perpendicular to frame head. Alignment: Plus or minus 1/16 inch, measured at jambs on a horizontal line parallel to plane of wall. Twist: Plus or minus 1/16 inch, measured at opposite face corners of jambs on parallel lines, and perpendicular to plane of wall. Plumbness: Plus or minus 1/16 inch, measured at jambs at floor. Steel Doors: Fit hollow-metal doors accurately in frames, within clearances specified below. Shim as necessary. a. Non-Fire-Rated Standard Steel Doors: 1). Jambs and Head: 1/8 inch plus or minus 1/16 inch. 2). Between Edges of Pairs of Doors: 1/8 inch plus or minus 1/16 inch. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-11 Steel Doors and Frames July 28, 2010 3). b. Between Bottom of Door and Top of Threshold: Maximum 3/8 inch. 4). Between Bottom of Door and Top of Finish Floor (No Threshold): Maximum 3/4 inch. Fire-Rated Doors: Install doors with clearances according to NFPA 80. 10. Glazing: Comply with installation requirements in Division 8 Section "Glazing" and with standard steel door and frame manufacturer's written instructions. a. D. Secure stops with countersunk flat- or oval-head machine screws spaced uniformly not more than 9 inches o.c., and not more than 2 inches o.c. from each corner. Adjustments: Check and readjust operating finish hardware items just prior to final inspection. Leave work in complete and proper operating condition. Remove and replace defective work, including doors or frames which are warped, bowed or otherwise unacceptable. END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081113-12 Steel Doors and Frames July 28, 2010 SECTION 081416 WOOD DOORS PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. 1.3 Work of this Section includes all labor, materials, equipment and services necessary to complete the wood doors as shown on the drawings and/or specified herein, including but not limited to, the following: 1. Solid core flush wood doors. 2. Fire rated flush wood doors. 3. Doors and frames scheduled as smoke separations. RELATED SECTIONS A. Hollow metal frames – Section 081113. B. Finish hardware – Section 087100. C. Glass and glazing – Section 088000. D. Field painting – Section 099000. 1.4 SUBMITTALS A. B. Product Data: Submit door manufacturer’s product data, specifications and installation instructions for each type of wood door. 1. Include details of core and edge construction and trim for openings. 2. Include factory finish specifications. 3. Include certifications to show compliance with specifications. 4. Include certification to show compliance with WDMA TM-7 test for 1 million slams. Shop Drawings: Submit shop drawings indicating location and size of each door, elevation of each kind of door, details of construction, location and extent of hardware blocking, fire ratings, requirements for finishing and other pertinent data. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081416-1 Wood Doors July 28, 2010 1. C. Submit the following 1. 1.5 Include requirements for veneer matching. Factory finishes applied to actual door face materials, approximately 8 by 10 inches for each material and finish. For each wood species and transparent finish, provide set of three samples showing typical range of color and grain to be expected in the finished work. QUALITY ASSURANCE A. Source Limitations: manufacturer. B. Quality Standard: Comply with AWI's "Architectural Woodwork Quality Standards Illustrated"; latest edition "Premium" grade. C. 1. Only manufacturers that are certified and listed by AWI to be QCP qualified are acceptable for this project. 2. Provide letter of licensing for Project indicating that doors comply with requirements of grade specified. Fire Rated Wood Doors: Doors complying with Category A, Positive Pressure or Neutral Pressure testing standards per UBC 7-2-1997 and UL 10-C (UBC 7-2-1994 and UL 10B) that are listed and labeled by a testing and inspecting agency acceptable to authorities having jurisdiction, for fire ratings indicated on Door Schedule, based on testing according to NFPA 252. 1. D. Obtain flush wood doors through one source from a single Conform to prevailing Code requirements to determine which pressure standard (Positive or Neutral) is required. The following LEED criteria are required for the products included in this Section: 1. All composite wood, engineered wood, or agrifiber products (e.g., plywood, particleboard, medium density fiberboard) shall contain no added ureaformaldehyde resins. Acceptable resins and binders include, but are not limited to, phenol formaldehyde and methyl diisocyanate (MDI). Certification of these products shall be in accordance with the Submittal Requirements. 2. Wood materials shall be "FSC Certified" products (except recycled or salvaged wood) which have been harvested in accordance with the "FSC Principles and Criteria" for well managed forests developed by the Forest Stewardship Council (FSC). 3. Engineered wood (except FSC Certified or salvaged wood) shall contain a minimum of 50% (combined) post-industrial/post-consumer recycled content (the percentage of recycled content is based on the weight of the component materials). Certification of recycled content shall be in accordance with Substantial Requirements herein. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081416-2 Wood Doors July 28, 2010 4. 1.6 Provide evidence that mill is certified for chain of custody by a FSC accredited certification body. DELIVERY, STORAGE, AND HANDLING A. Comply with requirements of referenced standard and manufacturer's written instructions. B. Package doors individually in plastic bags or cardboard cartons. C. Mark each door on top and bottom rail with opening number used on Shop Drawings. 1.7 PROJECT CONDITIONS A. 1.8 Environmental Limitations: Do not deliver or install doors until building is enclosed, wet work is complete, and HVAC system is operating and will maintain temperature and relative humidity at occupancy levels during the remainder of the construction period. WARRANTY A. Special Warranty: Manufacturer's standard form, signed by manufacturer, Installer, and Contractor, in which manufacturer agrees to repair or replace doors that are defective in materials or workmanship, have warped (bow, cup, or twist) in excess of permitted standard noted in Article 2.5 herein, or show telegraphing of core construction in face veneers. 1. Warranty shall also include installation and finishing that may be required due to repair or replacement of defective doors. 2. Warranty shall be in effect during the following period of time from date of Substantial Completion: a. Solid Core Flush Wood Doors: Life of installation. PART 2 PRODUCTS 2.1 SOLID CORE FLUSH WOOD DOORS A. Provide AWI PC-5 Premium Grade hot pressed 5-ply solid core particleboard doors, 13/4" thick, conforming to standards specified herein. Subject to meeting standards specified herein, the following manufacturers are acceptable: Marshfield Door Systems, Inc., Algoma Hardwoods Inc., or Eggers Hardwood Products Corp. 1. Core shall consist of a formed flat panel consisting of wood particles bonded together with synthetic resins or other added binder, with an average density of 30 to 32 lbs. per cubic foot. The material shall meet or exceed the requirements of ANSI A208.1, Grade 1-LD-2 covering mat formed particleboard with face screw holding of 124 lbs., modulus of rupture of minimum 700 psi and modulus of elasticity of not less than 148,000 psi. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081416-3 Wood Doors July 28, 2010 2. Core shall be capable of satisfying this WDMA TM-7 cycle slam test for 1 million slams for surface mounted hardware. Where the manufacturer's core does not meet this criteria, stiles and rails must measure a minimum of 5-1/2" and must be fabricated of hardwood. a. Surface mounted hardware must be installed with 1-1/4" screw penetrations using threaded to the head screws; coordinate with Section 087100. B. Cross Bands: Shall be 1/16" thick hardwood extending full width of door and laid with grain at right angles to face veneers. Cross bands and faces shall be laminated to the core with Type I MF or PVA glue. C. Stiles, Rails: Stile edge bands shall be a minimum of 1-3/8" solid hardwood or structural composite lumber (after trimming) laminated to the core. Stiles and rails must be securely glued to the core with no voids allowed. D. Doors with transparent finish to have center balanced, slip matched, quarter sliced, Select Maple veneer. Veneer to conform to AWI, "AA" grade veneer with 3" wide leaf. Minimum veneer thickness shall be not less than 1/50" after sanding. E. Where glass lites are noted, factory cut openings. Trim openings with solid hardwood moldings of same type of wood as face veneer. Lite openings in 20 minute rated doors shall have manufacturer's 20 minute approved hardwood system. Set glazing stops in a continuous bead of sealant. U-shaped neoprene glazing gaskets shall be continuous around perimeter forming an airtight seal. F. Doors to be field painted shall have MDO or hardboard face. 2.2 FIRE RATED WOOD DOORS ("B" LABEL) A. Provide mineral core 1-3/4” thick solid core wood doors conforming to standards specified herein, manufactured by one of the manufacturers noted above. Stile construction on both stiles shall conform to the following: 1. Stile edge screw withdrawals when tested in accordance with ASTM D 1037-78 shall exceed 650 lbs. This applies to both stiles. 2. Stile edge split resistance when tested in accordance with ASTM D 143-52 (78) Modified must exceed 950 lbs. This applies to both stiles. B. Door to have face finish as specified above in Article 2.1. C. Blocking: For surface mounted hardware only, provide composite blocking designed to maintain fire resistance of door but with improved screw-holding capability of same thickness as core and with minimum dimensions as follows: 1. 5-inch top rail blocking. 2. 5-inch bottom rail blocking. 3. 1 – 5" x 18" lock block at cylinder or mortise locksets. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081416-4 Wood Doors July 28, 2010 4. 2 – 5" x 18" lock blocks at exit devices. D. Pairs: Provide fire-rated pairs with fire-retardant stiles that are labeled and listed for kinds of applications indicated without formed-steel edges and astragals. E. Set glazing stops in a continuous bead of sealant. U-shaped neoprene glazing gaskets shall be continuous around perimeter forming an airtight seal. 2.3 SHOP FINISH A. Transparent Finish: Finish in the shop with clear satin catalyzed polyurethane finish conforming to AWI System “Catalyzed Polyurethane Transparent”. B. Opaque Finish: For doors to be field painted, shop prime on all surfaces with one coat of alkyd wood primer applied to a dry film thickness of 1.5 mils. 2.4 FABRICATION A. Prefit and premachine wood doors at the factory. B. Comply with the tolerance requirements specified herein. Machine doors for hardware requiring cutting of doors. Comply with final hardware scheduled and door frame shop drawings, and with hardware templates and other essential information required to ensure proper fit of doors and hardware. C. Take accurate field measurements of hardware mortises in metal frames to verify dimensions and alignment before proceeding with machining in the factory. D. Doors shall be factory sized to door opening so that trimming and fitting are not required in the field. E. Factory fit doors to suit frame-opening sizes indicated, with the following uniform clearances unless otherwise indicated. F. 1. Three degree bevel or bevel to suit frame sizes indicated, with 3/16" prefit in width, +0/-1/32" tolerances. Prefit top of door 1/8" + 1/16"/-0" and undercut as required by floor condition. Undercut shall not exceed 1/8" from bottom of door to top of finished floor; where threshold occurs undercut shall not exceed 1/8" from bottom of door to top of threshold. 2. Comply with requirements in NFPA 80 for fire-rated doors. Factory machine doors for hardware that is not surface applied. Locate hardware to comply with DHI-WDHS-3 unless otherwise noted. Comply with final hardware schedules, door frame Shop Drawings, DHI A115-W series standards, and hardware templates. 1. Coordinate measurements of hardware mortises in metal frames to verify dimensions and alignment before factory machining. 2. Provide concealed intumescent seals at fire-rated pairs of doors meeting the requirements of U.L. 10 C. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081416-5 Wood Doors July 28, 2010 G. 2.5 Openings: Cut and trim openings through doors to comply with applicable requirements of referenced standards for kinds of doors required. SOURCE QUALITY CONTROL A. Once installed, maximum allowable warp, bow, cut or twist in doors shall be 1/16" as measured by the 1/16 inch feeler gauge and a straight-edge extending from corner to corner of the door face at stiles, top and bottom rails and along both diagonals. PART 3 EXECUTION 3.1 INSTALLATION A. B. Wood Doors 1. Condition doors to average prevailing humidity in installation area prior to hanging. 2. Install doors in accordance with manufacturer’s instructions. 3. Fit door to frames and machine for hardware to whatever extent not previously worked at factory as required for proper fit and uniform clearance at each edge. 4. Clearances: Install doors to meet clearance requirements specified in Section 081113. 5. Fire-Rated Doors: Install in corresponding fire-rated frames in accordance with the requirements of NFPA No. 80. Provide clearances complying with the limitations of the authority having jurisdiction. Adjustments: Check and readjust operating finish hardware items just prior to final inspection. Leave work in complete and proper operating condition. Remove and replace defective work, including doors or frames which are warped, bowed or otherwise unacceptable. END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 081416-6 Wood Doors July 28, 2010 SECTION 083473 SOUND CONTROL DOOR ASSEMBLIES PART 1 GENERAL PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. Acoustical metal door systems, including doors, frames, perimeter seals, cam-lift hinges, metal thresholds and accessories to maintain door operation and the required STC ratings indicated on the Drawings. B. Perimeter seals and all other hardware for other doors (metal and wood) required are specified in Section 087100. 1.3 RELATED SECTIONS A. Sealants – Section 079200. B. Finish hardware – Section 087100. C. Glass and glazing – Section 088000. 1.4 REFERENCES A. ASTM C 423: Standard Test Method for Sound Absorption and Sound Absorption Coefficients by the Reverberation Room Method. B. ASTM E 90: Standard Test Method for Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements. C. ASTM E 336: Standard Test Method for Measurement of Airborne Sound Attenuation between Rooms in Buildings. D. ASTM E 413: Classification for Rating Sound Insulation. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 083473-1 Sound Control Door Assemblies June 25, 2010 1.5 QUALITY ASSURANCE A. B. C. Single Responsibility: Assign undivided responsibility of the sound retardant door work to a single firm specializing in this type of work. The firm and their personnel engaged in the work shall be able to demonstrate successful experience with work of comparable extent, complexity and quality to that shown and specified. Do not engage a firm unacceptable to the manufacturers of the primary materials to be used. The firm shall engage other specialist firms to perform any part of the work which he is not equipped or qualified to perform properly with his own personnel. Include the following major items of work in the scope of work for undivided responsibility: 1. Doors and frames. 2. Gasketing and sills. 3. Door hardware. 4. Glass and glazing. Qualifications: 1. Provide doors and frames manufactured by a firm specializing in the production of sound control doors. 2. Provide sound control doors for fire rated openings manufactured by a firm whose units are inspected, tested and listed by UL for single point hardware for sizes and profiles shown. Requirements of Regulatory Agencies: Comply with the label requirements of NFPA and applicable local codes. Fabricate doors and frames which comply with the requirements of NFPA Standard Number 80 for the class of door opening shown and scheduled and which have been tested and rated by a Testing Laboratory accepted by the local building authority. 1. Provide Testing Laboratory’s label on each door scheduled or required to be labeled. Include all information required by the local building authority. 2. Provide anchors for labeled frames as required by the local building authority. D. Field Measurements: Take field measurements prior to preparation of shop drawings, and prior to fabrication, where possible, to ensure proper fitting of work. However, allow for trimming and fitting wherever taking of field measurements before fabrication might delay work. E. Inserts and Anchorages: Furnish inserts and anchoring devices which must be built into other work. Coordinate delivery with other work to avoid delay. 1.6 SUBMITTALS A. Manufacturer’s Data: Submit two copies of the manufacturer’s detailed technical data for materials, fabrication, and installation. Include catalog cuts of hardware, anchors, fastenings, and accessories. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 083473-2 Sound Control Door Assemblies June 25, 2010 B. Provide illustrations and descriptions of all seals and hardware items which will be exposed on doors and frames. C. Shop Drawings: Submit shop drawings for the fabrication and erection of assemblies which are not fully described by manufacturer’s data. Show all anchorage and accessory items and finishes. 1. Submit setting drawings, templates, and instructions for installation of anchorage devices built into other work. 2. Provide installation details applicable to the construction in which the sound control doors and frames will be installed. 3. Indicate construction, sizes, thicknesses, reinforcing, anchoring, and finishes of all materials. D. Samples: Submit three (3) samples of each color and finish required. Samples will be reviewed for color, texture and surface reflectivity only. Compliance with all other requirements is the exclusive responsibility of the Contractor. E. Submit certified test reports indicating that the acoustical performance of the door meets the Sound Transmission Class (STC) performance as indicated in the door schedule. Test data shall be produced from an accredited independent acoustical laboratory which is a member of NVLAP (National Volunteer Laboratory Accreditation Program). Reports shall indicate that the test was performed on the doors and frames of the type to be supplied, in conformance with the requirements of test method ASTM E 90 and ASTM E 413. Earlier test reports will not be acceptable. The test results shall be representative of the performance of the proposed Sound Control Door assembly. F. Test reports by an independent Acoustical Engineer certifying a Field Sound Transmission Class (FSTC) or Noise Isolation Class (NIC) in conformance with the requirements of test method ASTM E 336, performance of no more than six points below the laboratory STC performance on similar installations. G. Written guarantee that door is constructed in accordance with the laboratory tested door and free of defects in material and workmanship for a period of 3 years after installation. H. Fire label as specified in the door schedule. 1.7 PERFORMANCE REQUIREMENTS A. Rated doors shall have a Sound Transmission Class (STC) rating as scheduled. B. Installed door assemblies shall meet Field Sound Transmission Class (FSTC) values no less than 3 dB points below the specified STC ratings. C. Test shall be for proposed door, frame, threshold, seals and hardware. Doors shall be fully operational at the time of the test. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 083473-3 Sound Control Door Assemblies June 25, 2010 1.8 PRODUCT HANDLING A. Upon award of contract, and before commencement of building construction, submit to the Architect any special requirements (scheduling, flatness of floor, etc.) which are necessary to assure successful installation. B. Protect door systems during transit, handling, and storage to prevent damage, soiling, and deterioration. C. Deliver frames to General Contractor with complete installation drawings and instructions for installation by the General Contractor. D. Deliver doors to project site only after the building has been closed in. Store doors in the building in a dry location and stack in accordance with the manufacturer’s instructions. E. Protect door assemblies, especially sound gaskets, from damage before, during and after their installation. PART 2 PRODUCTS 2.1 DOOR ASSEMBLIES A. General: The door assemblies shall be configured as indicated on the Contract Drawings as follows: 1. The weight of each door shall not be less than 9 psf. 2. The door hardware shall be sized to support the weight of the door and provide easy movement by one person. 3. The gasketing system shall provide an airtight seal around the entire perimeter of the door when closed. The force to compress the seal shall not exceed 29(ed.) pounds applied to the lockset. 4. Provide a mechanism, manual or powered, appropriate to the door weight and mode of operation (sliding or hinged) to release and reapply pressure on the door seals. No floor track. B. Provide all door assemblies with complete frame assemblies, including the extended frame(s), thresholds and joint covers required for split wall construction (if any). C. Provide door assemblies as scheduled, manufactured by Industrial Acoustics Company, Krieger Steel Products Co., Overly Manufacturing Co., or approved equal. D. Doors shall be 1-3/4" thick flush design of cold-rolled steel construction, 16 gauge minimum thickness. The core shall be acoustically non-coupling and shall be noncombustible. Vision panels, where indicated, shall be of glazing in accordance with the acoustically tested product, and be supplied by the door manufacturer. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 083473-4 Sound Control Door Assemblies June 25, 2010 E. Door and frames shall be factory mortised, reinforced, and fitted for heavy-duty locksets, strikes, and closers. All hardware shall be supplied by the door manufacturer as specified in the hardware schedule. F. Frames shall be formed to sizes and shapes indicated and shall have full welded unit-type construction at corners and other joints and packed with glass or mineral fiber. Frames shall be of cold-rolled steel construction. All contact edges shall be closed tight. Welds on corners and exposed surfaces shall be pressed flush and smooth. Steel frame members shall be pre-straightened, free of wind or twist. Frames shall be factory-aligned to a diagonal tolerance of +/- 1/16". G. All doors all have cam-lift action hinges, closers, and aluminum thresholds. The cam-lift shall lower the door onto the sill as the door is closed, and provide a tight positive seal with the threshold. When opening, the door shall rise fast enough t o minimize drag on the threshold. 1. Surface strap or butt hinges are not acceptable. H. The cam-lift seal shall be a full mortised neoprene door bottom and shall close the entire gag between the door and the floor. The cam-lift seal shall ensure a continuous, positive seal at the floor with minimum friction, drag and roll of the assembly on the floor. I. All hardware shall be finished as scheduled on the drawings. J. Perimeter Treatment: 1. Clearance between frame and door shall not exceed 1/8". All sills shall be of aluminum construction to insure a proper bottom seal. 2. All head and jamb seals shall be magnetic or compression stop in a fully adjustable retainer assembly. 3. The door shall be supplied with a bottom closed cell neoprene seal covered in Teflon type material and felt/neoprene compression seal at jambs and head. The seal shall be adjustable with flush Phillips head screws, to conform to job site sill conditions. Automatic drop bottoms will not be permitted. All screws shall be flush with the door leaf; no surface exposed screw heads or bolts are acceptable. 4. Where a double leaf door is specified, the astragal shall be rabbeted or beveled and contain neoprene compression and/or magnetic seals for the full height of the door. There shall be no gaps in the seals at the head and sill of the door. There shall be continuous pressure applied to the astragal to compress the seals and prevent the leaves from bowing out and disengaging the astragal seals. Double door acoustic test data shall be submitted. Single leaf test data will not be acceptable for double doors. 5. Door shall have an Underwriter’s Laboratory fire label if required (or certificate if the door exceeds the maximum opening size) as called out in the schedule of drawings. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 083473-5 Sound Control Door Assemblies June 25, 2010 PART 3 EXECUTION 3.1 INSPECTION A. 3.2 Examine the areas and conditions in which the work of this section is to be installed, including condition of substrate to which the item is to be attached. Do not proceed with work until unsatisfactory conditions have been corrected. INSTALLATION - GENERAL A. General: Comply with the recommendations of the manufacturer for secure and proper installation in accordance with final shop drawings. Install the work in locations on the drawings, with proper clearances, elevation and anchorage. Provide accessories indicated and anchors, inserts, and other items required for installation of items and attachment to adjoining construction. B. Install seals so they are in intimate contact with the entire length of the jambs and head. 3.3 INSTALLATION OF FRAMES A. Comply with provisions of SDO-105 "Recommended Erection Instructions for Steel Frames," unless otherwise indicated. B. Place all frames for acoustical doors after all walls are set and in place. Set frames accurately in position, plumbed, aligned and braced securely until permanent anchors are set. C. In masonry construction, locate 3 wall anchors per jamb at hinge and strike levels. D. At in-place concrete, masonry or steel construction, set frames and secure t o adjacent construction with machine screws and masonry anchorage devices in accordance with all approved shop drawings. E. Fill vertical cells of masonry units solid with grout where anchors are to be built-in to masonry construction. F. Grouting of frames complete with any rebar reinforcement and installation of insulation in the frame, shall be performed by the installing contractor as part of his work to insure the acoustical and structural integrity of the assembly. G. Install fire-rated frames in accordance with NFPA Std. No. 80. H. Remove spread bars only after frames have been properly set and secured. 3.4 DOOR INSTALLATION A. Fit acoustical doors accurately in frames, within clearances specified in SDI-100 and as herein specified. B. Doors must be installed plumb and aligned. C. Place fire-rated doors with clearances as specified in NFPA Std. No. 80. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 083473-6 Sound Control Door Assemblies June 25, 2010 D. 3.5 Adjust all automatic or adjustable acoustical perimeter and drop seals to insure a tight fit per manufacturer’s recommendation. ADJUST AND CLEAN A. Prime Coat Touch-Up: Immediately after erection, sand smooth any rusted or damaged areas of prime coat and apply touchup of compatible air-drying primer. B. Final Adjustments: Check and readjust operating finish hardware items and acoustical seals, leaving steel doors and frames undamaged and in complete and proper operation condition. Check for any air, light (and sound) gaps at door jambs, heads and sills, and adjust seals as necessary. C. Upon completion of the installation, put each operating component through at least 10 operating cycles. Adjust to achieve optimum operation. 3.6 FIELD SUPERVISION A. 3.7 The door manufacturer shall provide factory trained supervision personnel during installation and final adjustment of sound seals. The manufacturer shall issue a letter of compliance certifying the completion of a successful installation. FIELD TESTING A. If required, the Owner will retain the services of an independent acoustical consultant to conduct an acoustical test at any designated door locations where noise transmission is suspected of being below the set criteria. The test shall consist of a Field Sound Transmission Class (FSTC) or Noise Isolation Class (NIC) test per ASTM E 336. If such results indicate non-conformance with the established FSTC or NIC requirements, it shall be the responsibility of the Contractor and manufacturer to correct, at their expense, such deficiencies by methods that shall be approved by the Acoustical Consultant and Owner prior to incorporation. Acoustical tests shall be repeated and corrective measures devised and incorporated until the set criteria and performance standards are met. If the Acoustical Consultant or Architect determines that the materials are not as specified herein, all costs for the initial acoustical test as well as the cost of all retesting shall be borne by the Contractor and the Manufacturer. END OF SECTION Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 083473-7 Sound Control Door Assemblies June 25, 2010 SECTION 087100 FINISH HARDWARE PART 1 - GENERAL 1.01 A. 1.02 A. 1.03 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. SUMMARY The required hardware items for doors are indicated in hardware sets shown herein. Should any opening be omitted, hardware shall be provided as specified for other doors of similar locations, function, quality and design. QUALITY ASSURANCE A. Standards: All finish hardware shall conform to all the following standards: 1. Testing Laboratories: Underwriters Laboratory (UL) and or Warnock Hersey Fire Laboratories Division: All fire rated doors shall have hardware assemblies approved by one of the listed laboratories. Panic hardware UL Listed only. 2. National Fire Protection Association: NFPA 80 and NFPA 101. 3. Builders Hardware Manufacturers Association (BHMA). 4. American National Standards Institute (ANSI). 5. American Disabilities Act (ADA). B. Supplier: Finish hardware shall be furnished by those having a minimum of 5 years of builders hardware experience and shall have in their employ at least one certified Architectural Hardware Consultants (AHC) to correctly interpret the plans, detailed drawings and specifications. 1.04 SUBMITTALS A. General: Submit the following in accordance with the provisions of the general contract documents. B. Hardware Schedule: Submit three (3) copies of a vertical hardware schedule. Horizontal schedules will not be accepted. Follow Door and Hardware Institute (DHI) guide lines for scheduling. At the end of the schedule list each door number with appropriate heading number and hardware set number. Furnish initial draft of schedule at the earliest possible date, in order to facilitate the fabrication of other work. Furnish final schedule after samples, manufacturer's data sheets have been approved. C. Product Data: Submit three (3) copies of the manufacturer's data for each item of hardware. Include whatever information may be necessary to show compliance with requirements. D. Keying Schedule: A key schedule showing all key numbers and spaces to which each permits entry, shall be provided. Consult with Owner before submitting final key schedule. After final approval has been received, the schedule and the key cabinet, Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 087100 FINISH HARDWARE July 28, 2010 along with the key gathering envelopes containing keys for each lock endorsed with lock number and space designation, shall be turned over to the Owner. E. 1.05 Samples: Prior to submittal of the final hardware schedule and prior to delivery of hardware, submit one (1) sample of each exposed hardware unit. Sample will be reviewed by the Architect for design, color and texture only. Compliance with other requirements is the exclusive responsibility of the Contractor. Samples approved by the Architect shall be turned over to the Owner for attic stock. PRODUCT HANDLING A. Handle, store, distribute, protect and install in accordance with the manufacture's instructions. Deliver packaged material in original containers with seals unbroken and labels intact. Deliver assemblies completely identified and with adequate protection for storage, handling and installation. B. Provide secure lock-up for hardware delivered to the project, but not yet installed. Control the handling and installation of hardware which are not immediately replaceable, so that completion of the work will not be delayed by hardware losses; both before and after installation. 1.06 PROJECT CONDITIONS A. Coordinate hardware with other work. Tag each item or package separately, with identification related to the final hardware schedule, and include basic installation instructions in the package. Furnish hardware items of proper design for use on doors and frames of the thickness, profile, swing, security and similar requirements indicated and as necessary for proper installation and function. Deliver packaged hardware items to the proper locations for installation. B. Furnish hardware templates to each fabricator of doors, frames and other work to be factory prepared for the installation of hardware. 1.07 A. WARRANTIES The hardware manufacturers shall provide full replacement warranty as listed below. Replacement warranty shall not include any labor cost. 1. Surface Closers 10 years. 2. Exit Devices 3 years. 3. Locksets etc. 1 year 4. Balance of hardware 1 year PART 2 - PRODUCTS 2.01 MATERIALS AND FABRICATION: A. Hand of Door: The drawings show the swing or hand of each door leaf. Furnish each item of hardware for proper installation and operation of the door swing shown. B. Base Metals: Produce hardware units of the basic metal and forming method indicated, using manufacturer's standard metal alloy, composition, temper and hardness but in no case of lesser quality material. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 087100 FINISH HARDWARE July 28, 2010 C. Fasteners: Manufacture hardware to conform to published templates, generally prepared for machine screw installation. Do not provide hardware which has been prepared for self-tapping sheet metal screws. D. Screws: Furnish screws for installation, with each hardware item. Finish exposed screws to match the hardware finish. E. Tools for Maintenance: Furnish a complete set of specialized tools as needed, for the Owner continued maintenance, removal and replacement of hardware. F. Concealed Fasteners: Provide concealed fasteners for hardware units, which are exposed when the door is closed, except to the extent no standard manufacturer's units are available with concealed fasteners. Use thru bolts only where necessary to adequately fasten hardware to the door. 2.02 HINGES A. Unless otherwise noted, all hinges shall be full mortise five knuckle ball bearing type template, with non-rising loose pins. All out swinging doors shall be furnished with non-removable pins (NRP). B. All hinges for 1-3/4" thick doors shall be 4-1/2" wide in the open position. For other thickness doors hinges shall be of a width to permit unobstructed swing of the doors. C. Size and weight of hinges shall conform to the following: 1. Up to 36" 4-1/2" standard weight 2. Over 36" to 42" 5" heavy weight 3. 42" and over Zero Continuous Hinge 910DBAA D. Quantity of hinges shall be provided to conform to the following: 1. Doors up to 60" in height 2 hinges 2. Doors 60" to 90" in height 3 hinges 3. Doors 90" and over l hinge every 30" in height E. All hinges shall be the products of one manufacturer. 2.03 A. 2.04 LOCKSETS AND LATCHSETS Unless otherwise noted, all locksets and latchsets shall be heavy duty mortise type, function as specified in hardware sets. Furnish wrought steel box strikes. Furnish curved lip strikes with proper lip lengths as required. KEYS, KEYING AND CYLINDERS A. Keys: shall be nickel silver. All keys shall have visual key control and words "DO NOT DUPLICATE' embossed on one side. Furnish a quantity of keys as follows. 1. Grand Master Keys 10 2. Master Keys 10 each per group 3. Change Keys 3 each per cylinder 4. Control Keys 10 5. Construction Keys 20 B. Keying: All locks shall be construction keyed and grand master keyed to the existing Best keying system. Hardware supplier shall meet with Owner to establish keying Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 087100 FINISH HARDWARE July 28, 2010 requirements for this project. All master keys shall be hand delivered to the Owner by the manufacturer or his representative. C. 2.05 Cylinders: All cylinders shall have seven pin removable core with visual key control. DOOR CLOSING DEVICES A. All surface closers shall meet ANSI A156.4 Grade 1 requirements, barrier free. B. All closers shall be installed so that closer bodies are positioned on room side of doors to and from corridors, i.e., in-swing doors shall be regular arm. Out-swing doors shall have a parallel arm. Regular arm shall be used in connecting doors between rooms. C. Furnish all brackets, drop plates and any other necessary hardware required to insure proper installation. 2.06 FLUSH BOLTS AND COORDINATORS A. Manual Flush Bolts: Shall be Trimco W3917/3916 series furnish 3910 dustproof strikes for all bottom bolts. Top bolts shall be furnished with proper extensions to allow for easy operation. B. Self Latching Flush Bolts: Shall be Trimco 3820/3825 series furnish 3910 dustproof strikes for all bottom bolts. Furnish wear plates as required. C. Automatic Flush Bolts: Shall be Trimco 3810/3815 series furnish 3910 dustproof strikes for all bottom bolts. Furnish wear plates as required. D. Coordinators: Shall be Trimco 3094 series. Furnish all fillers, mounting brackets, carry bars and special cutouts for use with exit devices, as required. Finish shall be PC. E. All flush bolts and coordinators shall be the products of one manufacturer. 2.07 PROTECTION PLATES A. All kick plates shall be 16” high x 2”less door width x .050 thick x beveled 3 edges. B. All mop plates shall be 8” high x 2”less door width x .050 thick x beveled 3 edges. C. All armor plates shall be 34” high x 2”less door width x .050 thick x beveled 3 edges. 2.08 A. 2.09 A. OVERHEAD STOPS AND HOLDERS All overhead stops and holders for interior hollow metal doors shall be Dorma 710S series, and for interior wood doors furnish Dorma 700S series. DOOR STOPS All door stops shall be wall type Trimco 1270WV series. Where wall stops will not function properly, furnish floor stops Trimco W1211. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 087100 FINISH HARDWARE July 28, 2010 PART 3 - EXECUTION 3.01 GENERAL A. Approval: As soon as practical after award of Contract and before a hardware schedule is prepared, and before any hardware is ordered or delivered to the project, the Contractor shall submit to the Architect for his written approval, copies of sample list, listing each of the different items of builders hardware and catalog cuts of each item. B. Templates: As soon as the hardware schedule is approved the hardware supplier shall furnish to the various fabricators, required templates for fabrication purposes. Templates shall be made available not more than (10) days after receipt of the approved hardware schedule. C. Packaging and Marking: All hardware shall be shipped with proper fastenings for secure application. Each package of hardware shall be legibly marked indicating the part of the work for which it is intended. Markings shall correspond with the item numbers shown on the approved hardware schedule. Keys shall be tagged within each package set and plainly marked on the face of the envelope with the key control number, door designation and all identification as necessary. D. Delivery: Delivery shall be made to the project site to the attention of the Contractor. Where delivery of special hardware is required at any fabricator’s plant, the hardware supplier shall make such delivery. 3.02 INSTALLATION A. Mount hardware units at heights recommended in "Recommended Locations for Builders Hardware" by BHMA, unless otherwise noted or directed by the Architect. B. Install each hardware unit in compliance with the manufacturer's recommendations. 3.03 ADJUST AND CLEAN A. Adjust and check each operating item of hardware and each door to ensure proper operation or function of every unit. Lubricate moving parts with type lubrication recommended by manufacturer. Replace units that cannot be adjusted. B. Wherever hardware installation is made more than one (1) month prior to acceptance or occupancy of a space or area, return to the work during the week prior to acceptance make a final check, and adjust all hardware items in such space or area. Adjust door control devices and compensate for final operation of heating and ventilating equipment. C. Instruct Owner personnel in proper adjustment and maintenance of hardware and hardware finishes, during the final adjustment of hardware. 3.04 HARDWARE SETS A. The following is a general listing of hardware requirements and is not intended for use as a final hardware schedule. Any items of hardware required by established standards or practices, or to meet state and local codes or proper door operation shall be furnished whether or not specifically called out in the following listed groups. B. Items as specified in hardware sets are to be the products of the listed manufacturers. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 087100 FINISH HARDWARE July 28, 2010 C. Note that numbering system used coordinates with set numbers for Brooklyn College Performing Arts Center new construction to avoid confusion. HARDWARE SET # 1 Each to have: 1 1 1 3 Hinges Office Lock Door Closer w/stop Kick Plate Silencers PBB (as required) x US26D Sargent 8205 x LNE x US32D Dorma 8616IS-FC x Alum Trimco (see description) x US32D Trimco 1229A HARDWARE SET # 1B Each to have: 1 1 1 1 1 1 Hinges Office Lock Door Closer Door Stop Set Sound Seals Door Bottom Saddle PBB (see description) x US26D Sargent 8205 x LNE x US32D Dorma 8616AF-FC x Alum Trimco (see description) x US32D Zero 870A @ jambs & head Zero 367A Zero (as detailed) HARDWARE SET # 1C Each to have: 1 1 1 1 3 Hinges Office Lock Door Closer Door Stop Kick Plate Silencers PBB (as required) x US26D Sargent 8205 x LNE x US32D Dorma 8616AF-FC x Alum Trimco (see description) x US32D Trimco (see description) x US32D Trimco 1229A HARDWARE SET # 1D Each to have: 1 1 1 Set Sound Seals Door Bottom Saddle Zero 870A @ jambs & head Zero 367A Zero (as detailed) HARDWARE SET # 2 Each to have: 1 1 1 1 1 1 1 Hinges Storeroom Lock Door Closer Mounting Bracket Door Stop Set Sound Seals Door Bottom Saddle Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 PBB (see description) x US26D Sargent 8204 x LNE x US32D Dorma 8616AF-FC x Alum Zero 870SPB x Alum Trimco (see description) x US32D Zero 870A @ jambs & head Zero 369A Zero (as detailed) 087100 FINISH HARDWARE July 28, 2010 HARDWARE SET # 2D Each to have: 1 1 1 Hinges Storeroom Lock Door Closer w/stop Set Smoke Seals PBB (see description) x US26D Sargent 8204 x LNE x US32D Dorma 8616DS-FC x Alum Zero 188S-BK @ jambs & head HARDWARE SET # 3 Each to have: 1 1 1 1 1 1 Hinges Passage Set Door Closer Door Stop Set Sound Seals Door Bottom Saddle PBB (see description) x US26D Sargent 8215 x LNE x US32D Dorma 8616AF-FC x Alum Trimco (see description) x US32D Zero 870A @ jambs & head Zero 369A Zero (as detailed) HARDWARE SET # 5 Each to have: 1 1 1 1 1 1 1 Hinges Classroom Lock Door Closer Door Stop Kick Plate Set Sound Seals Door Bottom Saddle PBB (see description) x US26D Sargent 8237 x LNE x US32D Dorma 8616AF-FC x Alum Trimco (see description) x US32D Trimco (see description) x US32D Zero 870A @ jambs & head Zero 367A Zero (as detailed) HARDWARE SET # 5A Each to have: 1 1 1 1 1 1 Hinges Classroom Lock Door Closer w/stop Kick Plate Set Sound Seals Door Bottom Saddle Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 PBB (see description) x US26D Sargent 8237 x LNE x US32D Dorma 8616IS-FC x Alum Trimco (see description) x US32D Zero 870A @ jambs & head Zero 367A Zero (as detailed) 087100 FINISH HARDWARE July 28, 2010 HARDWARE SET # 5G Each to have: 1 1 1 Continuous Hinges Classroom Lock Door Closer w/stop Zero 910DBAA x US26D Sargent 8237 x LNE x US32D Dorma 8616IS-FC x Alum Note: the acoustical door manufacturer shall provide the balance of the hardware. HARDWARE SET # 8 Each to have: 2 1 1 1 1 2 2 1 Hinges Automatic Flush Bolts Classroom Lock Dummy Trim Set Coordinating Closer Set Sound Seals Door Bottom Astragal Seals Saddle PBB (see description) x US26D Trimco (see description) x US26D Sargent 8237 x LNE x US32D Sargent 8293 x LNE X US32D Dorma TS93GSR series x Alum Zero 870A @ jambs & head Zero 367A Zero 328A Zero (as detailed) HARDWARE SET # 8A Each to have: 2 1 1 1 1 6 Hinges Automatic Flush Bolts Classroom Lock Dummy Trim Set Coordinating Closer Saddle Silencers PBB (see description) x US26D Trimco (see description) x US26D Sargent 8237 x LNE x US32D Sargent 8293 x LNE X US32D Dorma TS93GSR series x Alum Zero (as detailed) Trimco 1229A HARDWARE SET # 9 Each to have: 1 1 1 1 1 1 3 Hinges Set Push & Pull Dead Lock Door Closer Door Stop Kick Plate Mop Plate Silencers PBB (see description) x US26D Trimco 1894-4B x US32D Sargent 4877 x US26D Dorma 8616AF-FC x Alum Trimco (see description) x US32D Trimco (see description) x US32D Trimco (see description) x US32D Trimco 1229A END OF SECTION 08710 Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 087100 FINISH HARDWARE July 28, 2010 SECTION 088000 GLASS AND GLAZING PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. 1.3 Work of this Section includes all labor, materials, equipment and services necessary to complete the glass and glazing as shown on the drawings and/or specified herein, including but not limited to glazing of the following: 1. Interior borrowed lites. 2. Laminated glass at observation windows at control booth. RELATED SECTIONS A. Hollow metal doors and frames – Section 081113. B. Wood doors – Section 081416. 1.4 PERFORMANCE REQUIREMENTS A. General: Provide glazing systems capable of withstanding normal thermal movement and wind and impact loads (where applicable) without failure, including loss or glass breakage attributable to the following: defective manufacture, fabrication, and installation; failure of sealants or gaskets to remain watertight and airtight; deterioration of glazing materials; or other defects in construction. B. Glass units shall be annealed, heat strengthened, fully tempered or laminated where required to meet wind load and safety glazing requirements, as shown, specified or recommended by the glass fabricator and as required by the prevailing Building Code. 1.5 SUBMITTALS A. Product Data: Submit manufacturer's printed product data, specifications, standard details, installation instructions, use limitations and recommendations for each material used. Provide certifications that materials and systems comply with specified requirements. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-1 Glass and Glazing July 28, 2010 B. 1.6 Verification Samples: Submit representative samples of each glass and glazing material that is to be exposed in completed work. Show full color ranges and finish variations expected. Provide glass samples having minimum size of 144 sq. in. and 6 in. long samples of sealants and glazing materials; all samples shall bear the name of the manufacturer, brand name, thickness, and quality. QUALITY ASSURANCE A. Source: For each glass and glazing type required for work of this Section, provide primary materials which are products of one manufacturer. Provide secondary or accessory materials which are acceptable to manufacturers of primary materials. B. Installer: A firm with a minimum of five years experience in type of work required by this Section and which is acceptable to manufacturers of primary materials; and with a successful record of in-service installations similar in size and scope to this Project. C. Glass Thickness: Glass thicknesses shown on drawings and/or specified herein are minimum thicknesses. Determine and provide size and thickness of glass products that are certified to meet or exceed performance requirements specified in this Section. D. Glazing Publications: Comply with published recommendations of glass product manufacturers and organizations below, unless more stringent requirements are indicated. E. 1.7 1. GANA Publications: GANA'S "Glazing Manual" and "Laminated Glass Design Guide". 2. SIGMA Publications: SIGMA TM-3000, "Vertical Glazing Guidelines for Sealed Insulating Glass Units". Safety Glazing Products: Comply with testing requirements in 16 CFR 1201. 1. Subject to compliance with requirements, obtain safety glazing products permanently marked with certification label of the Safety Glazing Certification Council. 2. Where glazing units, including Kind FT glass and laminated glass, are specified in Part 2 articles for glazing lites more than 9 sq. ft. in exposed surface area of one side, provide glazing products that comply with Category II materials, for lites 9 sq. ft. or less in exposed surface area of one side, provide glazing products that comply with Category I or II materials, except for hazardous locations where Category II materials are required by 16 CFR 1201 and regulations of authorities having jurisdiction. DELIVERY, STORAGE AND HANDLING A. Deliver materials and products in unopened, factory labeled packages. Store and handle in strict compliance with manufacturer's instructions and recommendations and GANA Manual. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-2 Glass and Glazing July 28, 2010 1. Protect materials from moisture, sunlight, excess heat, sparks and flame. 2. Sequence deliveries to avoid delays, but minimize on-site storage. PART 2 PRODUCTS 2.1 GLASS MATERIALS AND PRODUCTS A. Clear Float Glass: ASTM C 1036, Type I-Transparent, Flat, Class 1-Clear, Quality q3, minimum 1/4" thick. B. Clear Tempered Glass: ASTM C 1048, Condition A (Uncoated), Type I (Transparent, Flat), Class 1 (Clear), Quality q3, Kind FT, minimum 1/4" thick. Tempered glass must be certified by SGCC to meet applicable standards. Tempered glass shall also conform to the following: C. 1. Length and Width: For 2.9 mm to 6.0 mm; +/=1.6 mm. 2. Diagonal: +/- 3,0 mm. 3. Edgework: Belt seaming or diamond wheels. 1.5 mm seam of upper and lower glass edges. No sharp edges. 4. Corners: No more than 3.0 mm from square. 5. Float Glass Defects: Must meet the requirements of ASTM C 1036. The most common defects are scratches, stones gaseous bubbles and edge chips. Tables in the glass standards have limits for size/quantity of defects. 6. Tempered glass shall have a minimum surface compression of 10,000 psi. 7. Bow in Glass: Maximum allowable bow shall be on 50% of values shown in tables in ASTM C 1048. 8. Roller Waves: Maximum 0.076 mm for 6 mm. Laminated Safety Glass: Provide two glass panes of equal thickness, laminated together with a polyvinyl butyl interlayer, conform to ASTM C 1172, and as follows: 1. Interlayer Color: Clear. 2. Interlayer Material: Provide Monsanto "Saflex" or DuPont "Butacite," 0.030" thick at vertical applications, and 0.060" thick at sloped or horizontal applications. 3. Minimum thickness of 1/4". Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-3 Glass and Glazing July 28, 2010 2.2 GLAZING MATERIALS AND PRODUCTS A. General: Provide sealants and gaskets with performance characteristics suitable for applications indicated. Ensure compatibility of glazing sealants with insulated glass sealants, with laminated glass interlayers, and with any other surfaces in contact. B. General Glazing and Cap Bead Sealant: Provide sealant with maximum Shore A hardness of 50. Provide one of the following: 1. Dow Corning 795. 2. General Electric Silglaze N 2500 or Contractors SCS-1000. 3. Tremco Spectrem 2. C. Dense Elastomeric Compression Seal Gaskets: Provide molded or extruded neoprene or EPDM gaskets, Shore A hardness of 75+5 for hollow profile, and 60+5 for solid profiles, ASTM C 864. D. Cellular, Elastomeric Preformed Gaskets: Provide extruded or molded closed cell, integral-skinned neoprene, Shore A 40+5, and 20% to 35% compression, ASTM C-509; Type II. E. Preformed Glazing Tape: Provide solvent-free butyl-polyisobutylene rubber with 100% solids content complying with ASTM C1281 AAMA A 800 with integral continuous EPDM shim. Provide preformed glazing tape in extruded tape form. Provide Tremco “Polyshim II” or approved equal. F. Setting Blocks: Provide 100% silicone blocks with Shore A hardness of 80-90. Provide products certified by manufacturer to be compatible with silicone sealants. Length to be not less than 4”. Width for setting blocks to be 1/16” more than glass thickness and high enough to provide the lite recommended by glass manufacturer. When thickness of setting block exceeds 3/4” the glass manufacturer must be consulted for sizes and configuration. In a vented system, setting block shall be designed so as to not restrict the flow of water within the glazing rabbet to the weep holes. 1. Shims: For shims used with setting blocks, provide same materials, hardness, length and width as setting blocks. 2. Structural Silicone Glazing: Provide silicone setting blocks where structural silicone occurs at sills and at insulated units with silicone edge seals. G. Edge Blocks: Provide neoprene or silicone as required for compatibility with glazing sealants. Provide blocks with Shore A hardness of 55+5. H. Spacers: Elastomeric blocks or continuous extrusions with a Shore A durometer hardness required by glass manufacturer to maintain glass lites in place. I. Miscellaneous Glazing Materials: Provide sealant backer rods, primers, cleaners, and sealers of type recommended by glass and sealant manufacturers. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-4 Glass and Glazing July 28, 2010 2.3 FABRICATION OF GLASS AND OTHER GLAZING PRODUCTS A. Fabricate glass and other glazing products in sizes required to glaze openings indicated for Project, with edge and face clearances, edge and surface conditions, and bite complying with written instructions of product manufacturer and referenced glazing standard, to comply with system performance requirements. B. Clean-cut or flat-grind vertical edges of butt-glazed monolithic lites in a manner that produces square edges with slight kerfs at junctions with indoor and outdoor faces. C. Grind smooth and polish exposed glass edges. PART 3 EXECUTION 3.1 EXAMINATION A. B. 3.2 Examine framing glazing, with Installer present, for compliance with the following: 1. Manufacturing and installation tolerances, including those for size, squareness, and offsets at corners. 2. Presence and functioning of weep system. 3. Minimum required face or edge clearances. 4. Effective sealing between joints of glass-framing members. Proceed with installation only after unsatisfactory conditions have been corrected. PREPARATION A. 3.3 Clean glazing channels and other framing members receiving glass immediately before glazing. Remove coatings not firmly bonded to substrates. GLAZING, GENERAL A. Comply with combined written instructions of manufacturers of glass, sealants, gaskets, and other glazing materials, unless more stringent requirements are indicated, including those in referenced glazing publications. B. Glazing channel dimensions, as indicated on Shop Drawings, provide necessary bite on glass, minimum edge and face clearances, and adequate sealant thicknesses, with reasonable tolerances. Adjust as required by Project conditions during installation. C. Protect glass edges from damage during handling and installation. Remove damaged glass from Project site and legally dispose of off Project site. Damaged glass is glass with edge damage or other imperfections that, when installed, could weaken glass and impair performance and appearance. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-5 Glass and Glazing July 28, 2010 D. Apply primers to joint surfaces where required for adhesion of sealants, as determined by preconstruction sealant-substrate testing. E. Install setting blocks in sill rabbets, sized and located to comply with referenced glazing publications, unless otherwise required by glass manufacturer. Set blocks in thin course of compatible sealant suitable for heel bead. F. Do not exceed edge pressures stipulated by glass manufacturers for installing glass lites. G. Provide spacers for glass lites where the length plus width is larger than 50 inches as follows: 1. Locate spacers directly opposite each other on both inside and outside faces of glass. Install correct size and spacing to preserve required face clearances, unless gaskets and glazing tapes are used that have demonstrated ability to maintain required face clearances and to comply with system performance requirements. 2. Provide 1/8-inch minimum bite of spacers on glass and use thickness equal to sealant width. With glazing tape, use thickness slightly less than final compressed thickness of tape. H. Provide edge blocking where indicated or needed to prevent glass lites from moving sideways in glazing channel, as recommended in writing by glass manufacturer and according to requirements in referenced glazing publications. I. Set glass lites in each series with uniform pattern, draw, bow, and similar characteristics. J. Where wedge-shaped gaskets are driven into one side of channel to pressurize sealant or gasket on opposite side, provide adequate anchorage so gasket cannot walk out when installation is subjected to movement. K. Square cut wedge-shaped gaskets at corners and install gaskets in a manner recommended by gasket manufacturer to prevent corners from pulling away; seal corner joints and butt joints with sealant recommended by gasket manufacturer. L. Flush Glazing 1. If the butt joint in the metal framing is in the vertical direction, the glazier shall run the tape initially on the head and sill members going directly over this joint. Should the butt joint in the metal framing run horizontally, tapes must first be applied to the jambs so that it crosses over the joint. 2. Each tape section shall butt the adjoining tape and be united with a tool to eliminate any opening. 3. Do not overlap the adjoining length of tape or rubber shim as this will prevent full contact around the perimeter of glass. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-6 Glass and Glazing July 28, 2010 M. 3.4 Off-Set Glazing 1. Where the glazing legs are off-set, the difference in the rabbet width shall be compensated by employing different glazing tapes with different diameter shims. The difference in shim shall be equal to the size of the off-set. The thinner tape shall be positioned first on the glazing leg closest to the interior. The thicker tape shall be cut to the exact length of the dimension between the applied tapes, and installed on the outermost glazing leg. 2. Immediately prior to setting glass, paper backing shall be removed. Apply a toe bead of sealant 6” in each direction, from each corner. 3. Locate setting blocks in the sill member at quarter points, or if necessary to within 6” of each corner. Setting blocks must be set equal distance from center line of the glass and high enough to provide the recommended bite and edge clearances. 4. Set edge block according to glass manufacturer’s recommendations. 5. Set Glass: The glass shall be pressed firmly against the tape to achieve full contact. 6. In a vented system, apply a heel bead (air seal) of sealant around the perimeter of glass, between the sole of the I.G. unit and the base of the rabbet of the metal framing developing a positive bond to the unit and to the metal framing. The bead of the sealant shall be deep enough so that it will partially fill the channel to a depth of 1/4” between the glass edge and the base of the metal framing rabbet. 7. Interior stops shall be set, and glazing tape spline for the appropriate face clearance shall be rolled into place, compressing the glass to the shim within the glazing tape. GASKET GLAZING (DRY) A. Fabricate compression gaskets in lengths recommended by gasket manufacturer to fit openings exactly, with stretch allowance during installation. B. Insert soft compression gasket between glass and frame or fixed stop so it is securely in place with joints miter cut and bonded together at corners. C. Center glass lites in openings on setting blocks and press firmly against soft compression gasket by inserting dense compression gaskets formed and installed to lock in place against faces of removable stops. Start gasket applications at corners and work toward centers of openings. Compress gaskets to produce a weathertight seal without developing bending stresses in glass. Seal gasket joints with sealant recommended by gasket manufacturer. D. Install gaskets so they protrude past face of glazing stops. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-7 Glass and Glazing July 28, 2010 3.5 SEALANT GLAZING (WET) A. Install continuous spacers, or spacers combined with cylindrical sealant backing, between glass lites and glazing stops to maintain glass face clearances and to prevent sealant from extruding into glass channel and blocking weep systems until sealants cure. Secure spacers or spacers and backings in place and in position to control depth of installed sealant relative to edge clearance for optimum sealant performance. B. Force sealants into glazing channels to eliminate voids and to ensure complete wetting or bond of sealant to glass and channel surfaces. C. Tool exposed surfaces of sealants to provide a substantial wash away from glass. 3.6 PROTECTION AND CLEANING A. Protect exterior glass from damage immediately after installation by attaching crossed streamers to framing held away from glass. Do not apply markers to glass surface. Remove nonpermanent labels, and clean surfaces. B. Protect glass from contact with contaminating substances resulting from construction operations, including weld splatter. If, despite such protection, contaminating substances do come into contact with glass, remove them immediately as recommended by glass manufacturer. C. Examine glass surfaces adjacent to or below exterior concrete and other masonry surfaces at frequent intervals during construction, but not less than once a month, for build-up of dirt, scum, alkaline deposits, or stains; remove as recommended by glass manufacturer. D. Remove and replace glass that is broken, chipped, cracked, abraded, or damaged in any way, including natural causes, accidents, and vandalism, during construction period. END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 088000-8 Glass and Glazing July 28, 2010 SECTION 092900 GYPSUM DRYWALL PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the Contract Documents. SECTION INCLUDES A. 1.3 Work of this Section includes all labor, materials, equipment, and services necessary to complete the gypsum drywall as shown on the drawings and/or specified herein, including, but not limited to, the following: 1. Gypsum board work for partitions, ceilings, column enclosures, furring, and elsewhere where gypsum drywall work is shown on drawings. 2. Metal supports for gypsum drywall construction. 3. Acoustical insulation for gypsum drywall work. 4. Sealant for gypsum drywall work. 5. Concealed metal reinforcing for attachment of railings, toilet partitions and other items supported on drywall partitions and walls. 6. Taping and finishing of drywall joints. 7. Installing rings and frames in drywall surfaces for grilles, registers and lighting fixtures. 8. Bracing and connections. RELATED SECTIONS A. Hollow metal door frames – Section 081113. B. Painting – Section 099000. C. Rings for grilles, registers and light fixtures – Division 23 and 26. 1.4 QUALITY ASSURANCE A. The following standards, as well as other standards which may be referred to in this Section, shall apply to the work of this Section: 1. Gypsum Drywall Construction Handbook, latest edition, U.S. Gypsum Co. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-1 Gypsum Drywall July 28, 2010 2. ASTM C 645 "Standard Specification for Non-Load (Axial) Bearing Steel Studs, Runners (Track), and Rigid Furring Channels For Screw Application of Gypsum B. Allowable Tolerances: 1/32" offsets between planes of board faces, and 1/16" in 8'-0" for plumb, level, warp and bow. C. System Design Load 1. Provide drywall wall assemblies designed and tested by manufacturer to withstand a lateral load of 5 lbs. per sq. ft. for the maximum wall height required, and with deflection limited to 1/240 of partition height. 2. Provide drywall ceiling assemblies designed, fabricated and installed to have a deflection not to exceed L/360. 3. Take special care to design framing to support increased dead loads where multiple layers of wallboard or MDF are indicated to meet requirements for acoustic mass. D. Fire-Resistance Rating: Where gypsum drywall with fire resistance ratings are indicated, provide materials and installations which are identical with those of applicable assemblies tested per ASTM E 119 by fire testing laboratories, or to design designations in UL "Fire Resistance Directory" or in listing of other testing agencies acceptable to authorities having jurisdiction, and compliant with UL Test #2079; criteria for cycle movement for all field height wall sections requiring allowance for vertical deflection within framing details. E. Installer: Firm with not less than 5 years of successful experience in the installation of specified materials. 1.5 SUBMITTALS A. Samples: Each material specified herein, 12" x 12", or 12" long, or in manufacturer's container, as applicable for type of material submitted. B. Manufacturer's Literature: Submit technical and installation instructions for each drywall partition, furring and ceiling system specified herein, and for each fire-rated and sound-rated gypsum board assembly. Submit other data as required to show compliance with these specifications, including data for mold and moisture resistant joint compound. C. Test Reports: This Contractor shall submit test report, obtained by drywall manufacturer, indicating conformance of drywall assemblies to required fire ratings and sound ratings. 1.6 PRODUCT HANDLING AND PROTECTION A. Deliver, store and handle drywall work materials to prevent damage. Deliver materials in their original, unopened containers or bundles, and store where protected from moisture, damage and from exposure to the elements. Store wallboard in flat stacks. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-2 Gypsum Drywall July 28, 2010 B. 1.7 Protect wallboard from becoming wet. ENVIRONMENTAL CONDITIONS A. Provide and maintain minimum temperature of fifty-five (55) degrees F. and adequate ventilation to eliminate excessive moisture within the building in the area of the drywall work for at least twenty-four (24) hours, prior to, during and after installation of drywall work. Installation shall not start until windows are glazed and doors are installed, unless openings are temporarily closed. Space above suspended ceilings shall be vented sufficiently to prevent temperature and pressure build up. PART 2 PRODUCTS 2.1 MANUFACTURERS A. Acceptable Manufacturers for Gypsum Drywall Panels and Accessories: Materials specified below, unless noted otherwise or specified herein, are those of U.S. Gypsum Co. Equivalent materials of National Gypsum Co., Georgia Pacific and Lafarge meeting specification requirements are acceptable. B. Acceptable Manufacturers for Metal Supports of Drywall Assemblies: Unless otherwise noted, provide products manufactured by Dietrich Metal Framing, Super Steel Building Products, Marino/Ware, Super Steel Studs, Clark Western or approved equal. 2.2 METAL SUPPORTS A. Recycled Content of Steel Products: Provide products with average recycled content of steel products such that postconsumer recycled content plus one-half of preconsumer recycled content is not less than 25 percent. B. Metal Floor and Ceiling Runners 1. Channel Type: Formed from 20 U.S. Std. gauge (unless otherwise noted) galvanized steel, width to suit channel type metal studs. Use 20 ga. top runners with 1-1/4" minimum flanges. 2. Ceiling runners and head of wall connections at rated partitions shall conform to UL #2079 for cycle movement. Provide positive mechanical connection of framing to structure, allowing for vertical movement within connections. Minimum of 20 ga. galvanized steel for clips, 25 ga. galvanized steel for ceiling runners. Providing a friction free – anti-seizure movement capacity. a. b. As manufactured by the Steel Network, VertiClip or VertiTrack or equal made by Metal-Lite Inc. FireTrak (including stud clips) by FireTrak Corp. or equal made by Metal-Lite Inc. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-3 Gypsum Drywall July 28, 2010 3. C. D. E. 2.3 "J" Type: Formed from 20 U.S. Std. gauge galvanized steel, 1" x 2-1/2" or 4" wide (to suit detail). Metal Studs, Framing and Furring 1. Channel Type Studs: Channel type with holes for passage of conduit formed from minimum 18 U.S. Std. gauge (unless heavier gauge is required to meet deflection limits) galvanized steel, width as shown on drawings. 2. Furring Channels: Hat shaped, formed from galvanized steel, 25 U.S. Std. gauge. 3. Continuous 16 gauge x 8" wide steel wall plate screwed to studs as required for support of items supported on drywall partitions and walls. Suspended Ceiling and Fascia Supports 1. Main Runners: 1-1/2" steel channels, cold rolled at 0.475 lbs. per ft., rust-inhibitive paint finish. 2. Furring Members: Screw-type hat-shaped furring channels of 25 ga. zinc-coated steel; comply with ASTM C 645. 3. Hangers: Galvanized, 1" x 3/16" flat steel slats capable of supporting 5x calculated load supported. 4. Hanger Anchorages: Provide inserts, clips, bolts, screws and other devices applicable to the required method of structural anchorage for ceiling hangers. Size devices for 5x calculated load supported. 5. Furring Anchorages: 16 ga. galvanized wire ties, manufacturer's standard clips, bolts or screws as recommended by furring manufacturer. All galvanize steel members shall have coating conforming to ASTM A 653, G-60. GYPSUM WALLBOARDS A. Size: Provide in maximum lengths and widths available that will minimize joints in each area and that correspond with support system indicated. B. Gypsum Wall Board: 5/8" thick as indicated on drawings, "Sheetrock," 48" wide, in maximum lengths available to minimize end-to-end butt joints. C. Fire Rated Gypsum Wall Board: 5/8" thick as indicated on drawings, "Sheetrock Firecode C," 48" wide, in maximum lengths available to minimize end-to-end butt joints. D. Abuse Resistant Wallboard: Where indicated on drawings, "Fiberock Brand Panel VHI Abuse Resistant," by USG or “Dens armor Plus abuse Guard” by Georgia Pacific 48" wide in maximum lengths available to minimize end-to-end butt joints. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-4 Gypsum Drywall July 28, 2010 2.4 ACCESSORIES A. Acoustic Insulation: Paper-less, non-combustible, semi-rigid mineral fiber mat, 2" thick, in walls (unless otherwise indicated), 3 lb./cu. ft. maximum density; Thermafiber LLC "Thermafiber," or approved equal. B. Fasteners for Wall Board: USG Brand Screws; Type S Bugle Head for fastening wallboard to lighter gauge interior metal framing (up to 20 ga.). Type S-12 Bugle Head for fastening wallboard to heavier gauge interior metal framing (20 ga. to 12 ga.); Type S and Type S-12 Pan Head for attaching metal studs to door frames and runners; and Type G Bugle Head for fastening wallboard to wall board. Lengths specified below under "Part 3 - Execution" Articles and as recommended by drywall manufacturer. C. Laminating Adhesive: "Sheetrock Brand Joint Compound." D. Metal Trim - Corner Beads: For 90 degree External Corners - "Dur-A-Bead" No. 103, 27 U.S. Std. ga. galvanized steel, 1-1/4" x 1-1/4", for 90 degree external corners. E. Metal Trim - Edge Beads: "Sheetrock Brand Paper Faced Metal Bead and Trim." F. Metal Trim Treatment Materials and Joint Treatment Materials for Gypsum Drywall Boards: Paper tape for joint reinforcing; Setting Type (Durabond 90) or Lightweight Setting Type Joint Compound for taping and topping; and Ready Mix Compound for finishing. G. Control Joints: No. 0.093, USG. H. Acoustical Sealant: USG "Acoustical Sealant" or "Tremco Acoustical Caulking" of Tremco Mfg. Co., or approved equal. I. Neoprene Gaskets: Conform to ASTM D 1056. PART 3 EXECUTION 3.1 INSPECTION A. 3.2 Examine the areas and conditions where gypsum drywall is to be installed and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work. GENERAL INSTALLATION REQUIREMENTS A. General 1. Install drywall work in accordance with drywall manufacturer's printed instructions and as indicated on drawings and specified herein. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-5 Gypsum Drywall July 28, 2010 2. All metal framing for drywall partitions shall extend from floor to underside of structural deck above. Provide for vertical deflection with positive mechanical connections of framing members to structure. 3. Provide concealed reinforcement, 16 ga. thick by eight (8) inches wide or as detailed or as recommended by manufacturer, for attachment of railings, toilet partitions, and other items to be supported on the partitions which cannot be attached to the metal framing members. Concealed reinforcement shall span between metal studs and be attached thereto using two (2) self-tapping pan head screws at each stud. a. Back of drywall shall be scored or notched to prevent bulging out where reinforcement plate occurs. B. Fire-Rated Assemblies: Install fire-rated assemblies in accordance with requirements of authorities having jurisdiction, Underwriters' Laboratories and test results obtained and published by the drywall manufacturer, for the fire-rated drywall assembly types indicated on the drawings. C. Acoustic Assemblies: Install acoustic rated assemblies to achieve a minimum STC as noted on drawings, in accordance with test results obtained and published by the drywall manufacturer, for the drywall assembly type indicated on the drawings. D. Sealant E. 1. Install continuous acoustical sealant bead at top and bottom edges of wallboard where indicated or required for sound rating as wallboard is installed, and between metal trim edge beads and abutting construction. 2. Install acoustical sealant in 1/8" wide vertical control joints within the length of the wall or partitions, and in all other joints, specified below under "Control Joints." Install bead of acoustical sealant around electric switch and outlet boxes, piping, ducts, and around any other penetration in the wallboard; place sealant bead between penetrations and edge of wallboard. 3. Where sealant is exposed to view, protect adjacent surfaces from damage and from sealant material, and tool sealant flush with and in same plane as wallboard surface. Sealant beads shall be 1/4" to 3/8" diameter. Wall Board Application 1. Do not install wallboard panels until steel door frames are in place; coordinate work with Section 081113 – Steel Doors and Frames. 2. See drawings for all board types. Use fire-rated wallboard for fire-rated assemblies. Use water-resistant wallboard where indicated on drawings and where wallboard would be subject to moisture. Install water-resistant wallboard in full, large sheets (no scraps) to limit number of butt joints. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-6 Gypsum Drywall July 28, 2010 F. G. 3. Apply wallboard with long dimension parallel to stud framing members, and with abutting edges occurring over stud flanges. 4. Install wallboard for partitions from floor to underside of structure above and secure rigidly in place by screw attachment, unless otherwise indicated. 5. Provide "Thermafiber" safing insulation at flutes of metal deck where partitions carry up to bottom of metal deck. 6. Neatly cut wallboard to fit around outlets, switch boxes, framed openings, piping, ducts, and other items which penetrate wallboard; fill gaps with acoustic sealant. 7. Where wallboard is to be applied to curved surfaces, dampen wallboard on back side as required to obtain required curve. Finish surface shall present smooth, even curve without fluting or other imperfections. 8. Screw fasten wallboard with power-driven electric screw driver, screw heads to slightly depress surface of wallboard without cutting paper, screws not closer than 3/8" from ends and edges of wallboard. 9. Where studs are doubled-up, screw fasten wallboard to both studs in a staggered pattern. Metal Trim: Install and mechanically secure in accordance with manufacturer's instructions; and finish with three (3) coats of joint compound, feathered and finish sanded smooth with adjacent wallboard surface, in accordance with manufacturer's instructions. 1. Corner Beads: Install specified corner beads in single lengths at all external corners, unless corner lengths exceed standard stock lengths. 2. Edge Beads: Install specified edge beads in single lengths at all terminating edges of wallboard exposed to view, where edges abut dissimilar materials, where edges would be exposed to view, and elsewhere where shown on drawings. Where indicated on drawings, seal joint between metal edge bead and adjoining surface with specified gasket, 1/8" wide minimum and set back 1/8" from face of wallboard, unless other size and profile indicated on drawings. 3. Casing beads shall be set in long lengths, neatly butted at joints. Provide casing beads at juncture of board and vertical surfaces and at exposed perimeters. Control Joint Locations: Gypsum board surfaces shall be isolated with control joints where: 1. Ceiling abuts a structural element, dissimilar wall or other vertical penetration. 2. Construction changes within the plane of the partition or ceiling. 3. Shown on approved shop drawings. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-7 Gypsum Drywall July 28, 2010 H. 3.3 4. Ceiling dimensions exceed thirty (30) feet in either direction. 5. Wings of "L," "U," and "T" shaped ceiling areas are joined. 6. Expansion or control joints occur in the structural elements of the building. 7. Partition or furring abuts a structural element or dissimilar wall or ceiling. 8. Partition or furring runs exceed 30' without interruption. 9. Where control joints are required, ceiling height door frames may be used as control joints. Less than ceiling height frames shall have control joints extending to the ceiling from both corners. Joint Treatment and Spackling 1. Joints between face wallboards in the same plane, joints at internal corners of intersecting partitions and joints at internal corners of intersections between ceilings and walls or partitions shall be filled with joint compound. 2. Screw heads and other depressions shall be filled with joint compound. Joint compound shall be applied in three (3) coats, feathered and finish surface sanded smooth with adjacent wallboard surface, in accordance with manufacturer's instructions. Treatment of joints and screw heads with joint compound is also required where wallboard will be covered by finish materials which require a smooth surface, such as vinyl wall coverings. FURRED WALLS AND PARTITIONS A. Use specified metal furring channels. Run metal furring channel framing members vertically, space sixteen (16) inches o.c. maximum. Fasten furring channels to concrete or masonry surfaces with power-driven fasteners or concrete stub nails spaced sixteen (16) inches o.c. maximum through alternate wing flanges (staggered) of furring channel. Furring channels shall be shimmed as necessary to provide a plumb and level backing for wallboard. At inside of exterior walls, an asphalt felt protection strip shall be installed between each furring channel and the wall. Furring channel and splices shall be provided by nesting channels at least eight (8) inches and securely anchoring to concrete or masonry with two (2) fasteners in each wing. B. Wallboard Installation: Same as specified under Article 3.4 - "Metal Stud Partitions." 3.4 METAL STUD PARTITIONS A. Runner Installation: Use channel type. Align accurately at floor according to partition layout. Anchor runners securely sixteen (16) inches o.c. maximum with power-driven anchors to floor slab, with power-driven anchors to structural slab above. See "Stud Installation" below for runners over heads of metal door frames. Where required, carefully remove sprayed-on fireproofing to allow partition to be properly installed. B. Stud Installation Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-8 Gypsum Drywall July 28, 2010 C. 1. Use channel type, positioned vertically in runners, spaced as noted on drawings, but not more than sixteen (16) inches o.c. 2. Anchor studs to floor runners with screw fasteners. Provide snap-in or slotted hole slip joint bolt connections of studs to ceiling runners leaving space for movement. Anchor studs at partition intersections, partition corners and where partition abuts other construction to floor and ceiling runners with sheet metal screws through each stud flange and runner flange. 3. Connection at ceiling runner for non-rated partitions shall be snap-in or slotted hole slip joint bolt connection that shall allow for movement. Seal studs abutting other construction with 1/8" thick neoprene gasket continuously between stud and abutting construction. 4. Connections for fire rated partitions at ceiling runners shall conform to UL Design #2079. 5. Install metal stud horizontal bracing wherever vertical studs are cut or wallboard is cut for passage of pipes, ducts or other penetrations, and anchor horizontal bracing to vertical studs with sheet metal screws. 6. At jambs of door frames and borrowed light frames, install doubled-up studs (not back to back) from floor to underside of structural deck, and securely anchor studs to jamb anchors of frames and to runners with screws. Provide cross braces from hollow metal frames to underside of slab. 7. Over heads of door frames, install cut-to-length section of runner with flanges slit and web bent to allow flanges to overlap adjacent vertical studs, and securely anchor runner to adjacent vertical studs with sheet metal screws. Install cut-tolength vertical studs from runner (over heads of door frame) to ceiling runner sixteen (16) inches maximum o.c. and at vertical joints of wallboard, and securely anchor studs to runners with sheet metal screws. 8. At control joints, in field of partition, install double-up studs (back to back) from floor to ceiling runner, with 1/4" thick continuous compressible gasket between studs. When necessary, splice studs with eight (8) inches minimum nested laps and attach flanges together with two (2) sheet metal screws in each flange. All screws shall be self-tapping sheet metal screws. Runners and Studs at Chase Wall: As specified above for "Runners" and "Studs" and as specified herein. Chase walls shall have either a single or double row of floor and ceiling runners with metal studs sixteen (16) inches o.c. maximum and positioned vertically in the runners so that the studs are opposite each other in pairs with the flanges pointing in the same direction. Anchor all studs to runner flanges with sheet metal screws through each stud flange and runner flange following requirements of paragraph 3.4, B. Provide cross bracing between the rows of studs by attaching runner channels or studs set full width of chase attached to vertical studs with one self-tapping screw at each end. Space cross bracing not over thirty-six (36) inches o.c. vertically. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-9 Gypsum Drywall July 28, 2010 D. E. Wallboard Installation - Single Layer Application (Screw Attached) 1. Install wallboard with long dimension parallel to framing member and with abutting edge joints over web of framing member. Install wallboard with long dimension perpendicular to framing members above and below openings in drywall extending to second stud at each side of opening. Joints on opposite sides of wall shall be arranged so as to occur on different studs. 2. Boards shall be fastened securely to metal studs with screws as specified. Where a free end occurs between studs, back blocking shall be required. Center abutting ends over studs. Correct work as necessary so that faces of boards are flush, smooth, true. 3. Wallboard screws shall be applied with an electric screw gun. Screws shall be driven not less than 3/8" from ends or edges of board to provide uniform dimple not over 1/32" deep. Screws shall be spaced twelve (12) inches o.c. in the field of the board and 8" o.c. staggered along the abutting edges. 4. All ends and edges of wallboard shall occur over screwing members (studs or furring channels). Boards shall be brought into contact but shall not be forced into place. Where ends or edges abut, they shall be staggered. Joints on opposite sides of a partition shall be so arranged as to occur on different studs. 5. At locations where piping receptacles, conduit, switches, etc., penetrate drywall partitions, provide non-drying sealant and an approved sealant stop at cut board locations inside partition. Wallboard Installation - Double-Layer and Triple Layer Application 1. General: See drawings for wallboard partition types required. 2. First Layer (Screw Attached): application. 3. Second Layer (Screw Attached): Screw attach second layer, unless laminating method of attachment indicated on drawings or necessary to obtain required sound rating or fire rating. Install wallboard vertically with vertical joints offset thirtyfour (34) inches from first layer joints and staggered on opposite sides of wall. Attach wallboard with 1-5/8" screws sixteen (16) inches o.c. along vertical joints and sixteen (16) inches o.c. in the field of the wallboard. Screw through first layer into metal framing members. Install as described above for single layer F. Wallboard Installation - Laminated Application: Where laminated wallboard is indicated, use specified laminating adhesive, install wallboard vertically and maintain tolerances as specified for screw attached wallboard. G. Insulation Installation: Install where indicated on drawings. Place blanket tightly between studs. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-10 Gypsum Drywall July 28, 2010 H. Deflection of Structure Above: To allow for possible deflection of structure above partitions, provide top runners for non-rated partitions with 1-1/4" minimum flanges and do not screw studs or drywall to top runner. Where positive anchorage of studs to top runner is required, anchorage device shall be by means of slotted hole (in clip connection with screw attachment to web of steel through bushings located in slots of clips), or other anchorage device approved by Architect. I. Control Joints 3.5 1. Leave a 1/2" continuous opening between gypsum boards for insertion of surface mounted joint. 2. Back by double framing members. 3. Attach control joint to face layer with 9/16" galvanized staples six (6) inches o.c. at both flanges along entire length of joint. 4. Provide two (2) inch wide gypsum panel strip or other adequate seal behind control joint in fire rated partitions and partitions with safing insulation. DRYWALL FASCIAS AND CEILINGS A. Furnish and install inserts, hanger clips and similar devices in coordination with other work. B. Secure hangers to inserts and clips. Clamp or bolt hangers to main runners. C. Space main runners 4'-0" o.c. and space hangers 4'-0" o.c. along runners, except as otherwise shown. D. Level main runners to a tolerance of 1/4" in 12'-0", measured both lengthwise on each runner and transversely between parallel runners. E. Metal Furring Channels: Space sixteen (16) inches o.c. maximum. Attach to 1-1/2" main runner channels with furring channel clips (on alternate sides of main runner channels). Furring channels shall not be let into or come in contact with abutting masonry walls. End splices shall be provided by nesting furring channels no less than eight (8) inches and securely wire tying. At any openings that interrupt the furring channels, install additional cross reinforcing to restore lateral stability. F. Mechanical accessories, hangers, splices, runner channels and other members used in suspension system shall be of metal, zinc coated, or coated with rust inhibitive paint, of suitable design and of adequate strength to support units securely without sagging, and such as to bring unit faces to finished indicated lines and levels. 1. Provide special furring where ducts are over two (2) feet wide. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-11 Gypsum Drywall July 28, 2010 G. 3.6 Apply board with its long dimension at right angles to channels. Locate board butt joints over center of furring channels. Attach board with one (1) inch self-drilling drywall screws twelve (12) inches o.c. in field of board; eight (8) inches o.c. at butt joints located not less than 3/8" from edges. ERECTION AT COLUMN ENCLOSURES A. Metal furring supports shall be provided under work of this Section, and shall be cut to lengths as necessary for tight fit such that spacing is not more than sixteen (16) inches o.c. B. Board shall be fastened securely to supports with screws as specified. Place boards in position with minimum amount of joints. Where free ends occur between supports, back-blocking or furring shall be required. Center abutting ends over supports. Correct work as necessary so that faces of boards are flush, smooth and true. Provide clips or cross furring for attachment as required. C. All layers shall be screw attached to furring. D. When column finish called for on drawings to be in the same plane as drywall finish layer, maintain even, level plane. 3.7 FINISHING A. Taping: A thin, uniform layer of taping compound shall be applied to all joints and angles to be reinforced. Reinforcing tape shall be applied immediately, centered over the joint, seated into the compound. A skim coat shall follow immediately, but shall not function as a fill or second coat. Tape shall be properly folded and embedded in all angles to provide a true angle. B. Filling: After taping compound has hardened, topping compound shall be applied, filling the board taper flush with the surface. The fill coat shall cover the tape and feather out slightly beyond the tape. On joints with no taper, the fill coat shall cover the tape and feather out at least four (4) inches on either side of the tape. No fill coat is necessary on interior angles. C. After topping compound is set, a finishing coat of topping compound shall be spread evenly over and extending slightly beyond the fill coat on all joints and feathered to a smooth, uniform finish. Over tapered edges, the finished joint shall not protrude beyond the plane of the surface. All taped angles shall receive a finish coat to cover the tape and taping compound, and provide a true angle. Where necessary, sanding shall be done between coats and following the final application of compound to provide a smooth surface, ready for painting. D. Fastener Depressions: Taping compound shall be applied to all fastener depressions followed, when hardened by at least two (2) coats of topping compound, leaving all depressions level with the plane of the surface. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-12 Gypsum Drywall July 28, 2010 E. Finishing Beads and Trim: Taping compound shall be applied to all bead and trim and shall be feathered out from the ground to the plane of the surface. When hardened, this shall be followed by two (2) coats of topping compound each extending slightly beyond the previous coat. The finish coat shall be feathered from the ground to the plane of the surface and sanded as necessary to provide a flat, smooth surface ready for decoration. F. Level of finish for surface exposed to view shall conform to Level 4 of ASTM C 840 and GA-214 of the Gypsum Association. G. Drywall construction with defects of such character which will mar appearance of finished work, or which is otherwise defective, will be rejected and shall be removed and replaced at no expense to the Owner. 3.8 CLEANING AND ADJUSTMENT A. At the completion of installation of the work, all rubbish shall be removed from the building leaving floors broom clean. Excess material, scaffolding, tools and other equipment shall be removed from the building. B. Work shall be left in clean condition ready for painting or wall covering. All work shall be as approved by Architect. C. Cutting and Repairing: Include all cutting, fitting and repairing of the work included herein in connection with all mechanical trades and all other trades which come in conjunction with any part of the work, and leave all work complete and perfect after all trades have completed their work. 3.9 PROTECTION OF WORK A. Installer shall advise Contractor of required procedures for protecting drywall work from damage and deterioration during remainder of construction period. END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 092900-13 Gypsum Drywall July 28, 2010 SECTION 095113 ACOUSTIC PANEL CEILINGS PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. Work of this Section includes all labor, materials, equipment and services necessary to complete the acoustic panel ceilings as shown on the drawings and/or specified herein, including but not limited to, the following: 1. Interior acoustical panel ceiling units to match existing. 1.2. Exposed "T" suspension system, including hangers and inserts. 2.3. Provisions for the installation of lighting fixtures, diffusers, grilles and similar items provided under other Sections. 3.4. Cutting, drilling, scribing and fitting as required for electro-mechanical penetrations. 4.5. Perimeter and column moldings, trim and accessories for acoustical ceilings. 1.3 RELATED SECTIONS A. Drywall ceilings – Section 092900. B. Diffusers, grilles and related frames – Division 23. C. Lighting fixtures – Division 26. 1.4 QUALITY ASSURANCE A. Codes and Standards: In addition to complying with all pertinent codes and regulations, comply with all pertinent recommendations published by the Ceilings and Interior Systems Contractor’s Association. B. Qualifications of Installers 1. The suspended ceiling subcontractor shall have a record of successful installation of similar ceilings acceptable to Architect and shall be currently approved by the manufacturer of the ceiling suspension system. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 095113-1 Acoustic Panel Ceiling July 28, 2010 2. C. For the actual fabrication and installation of all components of the system, use only personnel who are thoroughly trained and experienced in the skills required and completely familiar with the requirements established for this work. The work is subject to the following standards: 1. American Society for Testing and Materials (ASTM) a. b. c. d. D. 1.5 ASTM C 423, Standard Test Method for Sound Absorption and Sound Absorption Coefficients by the Reverberation Room Method. ASTM C 635, Standard Specification for Metal Suspension Systems for Acoustical Tile and Lay-In Panel Ceilings. ASTM C 636, Standard Recommended Practice for Installation of Metal Ceiling Suspension Systems for Acoustical Tile and Lay-In Panels. ASTM E 795, Standard Practices for Mounting Test Specimens During Sound Absorption Tests. In addition to suspension system specified, provide seismic struts and seismic clips to meet seismic standards as required by prevailing Codes and Ordinances. SUBMITTALS A. Shop Drawings: Submit completely dimensioned ceiling layouts for all areas where acoustical ceilings are required, showing: 1. Any deviations from Architect’s reflected ceiling plan layouts, especially lighting fixture and dimensions. Also indicate if any light fixtures will not fit into Architect’s ceiling layout due to dimensional restrictions of field conditions. 2. Direction and spacing of suspension members and location of hangers for carrying suspension members. 3. Direction, sizes and types of acoustical units, showing suspension grid members, and starting point for each individual ceiling area. 4. Moldings at perimeter of ceiling, at columns and elsewhere as required due to penetrations or exposure at edge of ceiling tiles. 5. Location and direction of lights, air diffusers, air slots, and similar items in the ceiling plane. 6. Details of construction and installation at all conditions. 7. Materials, gauges, thickness and finishes. B. Certify that exterior application meets wind uplift requirements specified herein. C. Samples and Product Literature: manufacturer’s descriptive literature. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 Submit the following samples and related 095113-2 Acoustic Panel Ceiling July 28, 2010 1.6 1. Twelve (12) inch long sample of each components of suspension systems, including moldings. 2. Acoustical units — full size. DELIVERY, STORAGE AND HANDLING A. Deliver acoustical ceiling units to project site in original, unopened packages and store them in a fully enclosed space where they will be protected against damage from moisture, direct sunlight, surface contamination or other causes. B. Before installing acoustical ceiling units, permit them to reach room temperature and a stabilized moisture content. C. Handle acoustical ceiling units carefully to avoid chipping edges or damaging units in any way. D. Acoustical ceiling panels to be removed from packaging and stored in unoccupied ventilated areas (100% outside air supply, minimum of 1.5 air changes per hour, no recirculation) for 24-72 hours prior to installation. E. Acoustical ceiling panels shall not be stored with materials which have high sort-term emissions of VOCs or other contaminants. 1.7 PROJECT CONDITIONS A. 1.8 Do not install acoustical ceilings until wet-work in space is completed and nominally dry, work above ceilings has been completed, and ambient conditions of temperature and humidity will be continuously maintained at values near those indicated for final occupancy. COORDINATION A. 1.9 Coordinate layout and installation of acoustical ceiling units and suspension system components with other work supported by or penetrating through ceilings, including light fixtures, HVAC equipment, fire suppression system components, and partition system. EXTRA STOCK A. Extra Stock: Deliver stock of maintenance material to Owner. Furnish maintenance material matching products installed, packaged with protective covering for storage and identified with appropriate labels. 1. Acoustical Ceiling Units: Furnish quantity of full size units equal to 2.0% of amount installed. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 095113-3 Acoustic Panel Ceiling July 28, 2010 PART 2 PRODUCTS 2.1 ACOUSTICAL UNITS A. Provide ceiling tiles to match existing as closely as possible. B. Provide exposed "T" suspension system, steel, with low sheen white baked enamel finish equal to "Prelude XL," 15/16" exposed tee 2-way fire rated grid system made by Armstrong World Industries, or equal made by USG Interiors, Inc. or Chicago Metallic Corp. C. The suspension system shall support the ceiling assembly shown on the drawings and specified herein, with a maximum deflection of 1/360 of the span, in accordance with ASTM C 635. D. Hanger for suspension system shall be 1" x 3/16", galvanized steel flats or 1/4" diameter galvanized pencil rods spaced 4'-0" o.c. conforming to New York City Code requirements. E. Main carrying channels, to which suspension systems shall be fastened, shall be 1-1/2" cold rolled galvanized steel channel; spaced 4'-0" o.c., conforming to New York City Code requirements. F. Provide ceiling clips and inserts to receive hangers, type as recommended by suspension system manufacturer, sizes for pull-out resistance of not less than five (5) times the hanger design load, as indicated in ASTM C 635. G. Suspension systems shall conform to ASTM C 635, intermediate duty. H. Provide manufacturer’s standard wall moldings with off-white baked enamel finish to match suspension systems. For circular penetrations of ceilings, provide edge moldings fabricated to diameter required to fit penetration exactly. PART 3 EXECUTION 3.1 INSPECTION A. 3.2 Examine the areas where acoustic panel ceilings are to be installed and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected to permit proper installation of the layout. PREPARATION A. Coordination: Furnish layouts for inserts, clips, or other supports required to be installed by other trades for support of acoustical ceilings. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 095113-4 Acoustic Panel Ceiling July 28, 2010 B. 3.3 Measure each ceiling area and establish layout of acoustical units to balance border widths at opposite edges of each ceiling. Avoid use of less-than-half width units at borders, and comply with reflected ceiling plans. INSTALLATION A. Codes and Standards: Install materials in accordance with manufacturer’s printed instructions, and to comply with governing regulations and industry standards. B. Install suspension systems to comply with ASTM C 636, with wire hangers supported only from building structural members. Locate hangers not more than 6" from each end and spaced 4'-0" along direct-hung runner, leveling to tolerance of 1/8" in 12'-0". C. Space rod or flat iron (New York City) hangers not more than 4'-0" o.c. along main carrying channels; attach by clips or wire ties to building structure. Locate hangers not more than 6” from each end. Space main carrying channels 4'-0" o.c. Attach suspension system to carrying channels using clips or ties, leveling to a tolerance of 1/8" in 12'-0". D. Install hangers plumb and free from contact with insulation or other objects within ceiling plenum which are not part of supporting structural or ceiling suspension system. Splay hangers only where required to miss obstructions and offset resulting horizontal force by bracing, reinforcing, countersplaying or other equally effective means. E. Install edge moldings at edges of each acoustical ceiling area, and at locations where edge of acoustical units would otherwise be exposed after completion of the work. 1. Secure moldings to building construction by fastening through vertical leg. Space holes not more than 3" from each end and not more than sixteen (16) inches o.c. between end holes. Fasten tight against vertical surfaces. 2. Level moldings with ceiling suspension system, to a level tolerance of 1/8" in 12'0". F. Install acoustical units in coordination with suspension system, with edges concealed by support of suspension members. Scribe and cut panels to fit accurately at borders and at penetrations. G. Install hold-down clips in toilet areas, and in areas where required by governing regulations; space 2'-0" o.c. on all cross tees. H. Light fixtures or other ceiling apparatus shall not be supported from main beams or cross tees if their weight causes the total load to exceed the deflection capability of the ceiling suspension system. In such cases the load shall be supported by supplemental hangers furnished and installed by this Section of work. I. Where fixture or ceiling apparatus installation causes eccentric loading on runners, provide stabilizer bars to prevent rotation. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 095113-5 Acoustic Panel Ceiling July 28, 2010 3.4 ADJUST AND CLEAN A. Clean exposed surfaces of acoustical ceilings, including trim, edge molding, and suspension members; comply with manufacturer’s instructions for cleaning and touchup of minor finish damage. Remove and replace work which cannot be successfully cleaned and repaired to permanently eliminate evidence of damage. END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 095113-6 Acoustic Panel Ceiling July 28, 2010 SECTION 097723 FABRIC WRAPPED ACOUSTIC WALL PANELS PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. Work of this Section includes all labor, materials, equipment and services necessary to complete the acoustic wall panels as shown on the drawings and/or specified herein, including, but not limited to, the following: 1. 1.3 Acoustical absorption panels wrapped in selected fabric, with varying thicknesses and profiles as shown on drawings. RELATED SECTIONS A. 1.4 Gypsum wallboard – Section 092900. QUALITY ASSURANCE A. 1.5 Manufacturer Qualification: At least 5 years' experience fabricating and installing comparable work, employing skilled mechanics under competent supervision for all phases of the Work. SUBMITTALS A. Shop Drawings/Product Data 1. Base drawings on field measurements. 2. Show dimensioned wall elevations with seam and joint locations, cutout sizes and locations, anchor locations, relation to adjacent work; large scale joint and mounting details; materials type, weight/thickness, design, color; and other data necessary to fabricate and install work and coordinate work with affected trades. B. Samples: Two 12" x 12" (minimum) panels in selected finish, showing seam, edge and cutout conditions. C. Certification 1. Acoustical Performance: Certified reports of acoustical performance tests conducted and/or witnessed by a recognized, independent, testing agency. Tests shall have been done by specified methods or recognized equivalent. Sound Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 097723-1 Fabric Wrapped Acoustic Wall Panels July 28, 2010 absorption tests shall be not more than three years old. Reports on earlier tests are acceptable if it can be established to the Architect's satisfaction, that they are valid indications of compliance with Project requirements. 2. Fire Hazard: Evidence of compliance with regulatory agency and specifications requirements. D. Cleaning and Maintenance Instructions: Recommendations for Owner maintenance and cleaning. Identify cleaning/spotting products generically or by trade name. E. Manufacturer Qualifications: List comparable installations with 3-year (minimum) service histories. Describe installations and give Owner/building manager names and addresses. 1.6 REFERENCES A. ASTM C 423 Test for Sound Absorption and Sound Absorption Coefficients by the Reverberation Room Method. B. ASTM E 84 Test for Surface Burning Characteristics of Building Materials. 1.7 DELIVERY, STORAGE AND HANDLING A. 1.8 Allow materials to become acclimated to Project conditions before installation, if necessary to prevent sag and distortion during service life. PROJECT CONDITIONS A. Environmental Conditions 1. Work areas shall be at or near ambient occupancy temperature and relative humidity. 2. Painting, dust-raising activities, and work that introduces dampness shall be completed. PART 2 PRODUCTS 2.1 MANUFACTURERS A. Provide products manufactured by one of the following: 1. Wenger Corp. 2. Armstrong World Industries. 3. Celotex. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 097723-2 Fabric Wrapped Acoustic Wall Panels July 28, 2010 2.2 GENERAL A. Fabricate panels to sizes and configurations indicated; attach facing materials to cores to produce installed panels with visible surfaces fully covered and free from waves in fabric weave, wrinkles, sages, blisters, seams, adhesive or other foreign matter. 1. Fabricate back mounted panels in factory to exact sizes required to fit wall surfaces based on field measurements of completed substrates indicated to receive acoustical wall panels. 2. Where radius corners are indicated, attach facing material so there are no seams or gathering of material. B. Dimensional Tolerances of Finished Units: panels - plus or minus 1/16". C. Sound Absorption Performance: Provide acoustical wall panels with minimum noise reduction coefficients (NRC) indicated, as determined by testing per ASTM C 423 for mounting type specified under individual product requirements. D. Colors, Textures, and Patterns: As selected by Architect. 2.3 Overall height and width of BACK MOUNTED ACOUSTICAL WALL PANELS A. 2.4 Back Mounted, Edge Reinforced Acoustical Wall Panels: Manufacturer's standard panel construction consisting of facing material laminated to front, edges, and back border of molded glass fiber board core; with edges chemically hardened to reinforce panel perimeter against warpage and damaged; and complying with the following requirements: 1. Core Density: 6 - 7 lb./cu. ft. 2. Thickness and NRC: Nominal overall panel thickness of 2" and NRC of not less than 0.95 for Type A (ABPMA No. 4) mounting. 3. Facing Material: Provide Guilford of Maine Textiles FR 701, Style 2100;, color selected by the Architect. 4. Panel Size: As indicated. 5. Edge Detail: Square. ACCESSORIES A. Back Mounting Accessories: Manufacturer's standard or recommended accessories for securely mounting panels of type and size indicated to substrates provided, and complying with the following requirements: 1. Mechanically Mounted Edge Reinforced Panels: Metal panel clip and base support bracket system consisting of 2 part panel clips, with one part of each clip Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 097723-3 Fabric Wrapped Acoustic Wall Panels July 28, 2010 mechanically attached to back of panel and the other part to wall substrate, designed to support panels laterally; and base support brackets designed to support full weight of panels; with both designed to allow panel removal. PART 3 EXECUTION 3.1 INSPECTION A. 3.2 Examine the areas and conditions where acoustic wall panels are to be installed and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work. INSTALLATION A. General 1. Install acoustical wall panels in locations indicated with vertical surfaces and edges plumb, top edges level and in alignment with other panels, scribed to fit adjoining work accurately at borders and at penetrations. Comply with panel manufacturer's printed instructions for installation of panels using type of mounting accessories indicated or, if none indicated, as recommended by manufacturer. 2. Construction Tolerances a. b. Variation from Plumb and Level: Variation of Joints from Hairline: +/- 1/16". Not more than 1/16". B. Anchoring to Drywall: Anchor clips to unreinforced gypsum board with toggle or Molly anchors. Anchor clips to metal drywall framing with tapping sheet metal screws. C. Panels shall be pressed against wall and slid down engaging "Z" clips into wall brackets. D. Remove and replace panels that are damaged and are unacceptable to Architect. 3.3 ADJUSTING AND CLEANING A. Correct non-complying and damaged/defective Work. Replace work that cannot be satisfactorily repaired. B. Restretch and reinstall sagging and distorted fabric and correct other defects that occurred during normal service. C. Carefully and thoroughly clean completed work by vacuuming and/or other means. Remove soil, stains, loose threads. D. Protect work from soiling and other damage. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 097723-4 Fabric Wrapped Acoustic Wall Panels July 28, 2010 END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 097723-5 Fabric Wrapped Acoustic Wall Panels July 28, 2010 SECTION 099000 PAINTING AND FINISHING PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. 1.2 Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. SECTION INCLUDES A. 1.3 Work of this Section includes all labor, materials, equipment, and services necessary to complete the painting and finishing of the entire facility, including new and existing surfaces as shown on the drawings and/or specified herein, including, but not limited to, the following: 1. Prime painting unprimed surfaces to be painted under this Section. 2. Painting all items furnished with a prime coat of paint, including touching up of or repairing of abraded, damaged or rusted prime coats applied by others. 3. Painting all ferrous metal (except stainless steel) exposed to view. 4. Painting interior concrete block exposed to view. 5. Painting gypsum drywall exposed to view. 6. Painting surfaces above, behind or below grilles, gratings, diffusers, louvers, lighting fixtures, and the like, which are exposed to view through these items. 7. Incidental painting and touching up as required to produce proper finish for painted surfaces, including touching up of factory finished items. 8. Painting of any surface not specifically mentioned to be painted herein or on drawings, but for which painting is obviously necessary to complete the job, or work which comes within the intent of these specifications, shall be included as though specified. RELATED SECTIONS A. Shop priming is required on some, but not all of the items scheduled to be field painted. Refer to other Sections of work for complete description. B. Shop coat on machinery and equipment: Refer to the Sections under which various items of manufactured equipment with factory applied shop prime coats are furnished, including, but not necessarily limited to, the following Sections. All items of equipment furnished with prime coat finish shall be finish painted under this Section. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-1 Painting and Finishing July 28, 2010 C. 1. Heating, ventilation and air conditioning – Division 23. 2. Plumbing – Division 22. Color Coding of Mechanical Piping and Electrical Conduits – Division 23 and 26. 1. 1.4 This Color Coding consists of an adhesive tape system and is in addition to painting of piping and conduits under this Section, as specified above. MATERIALS AND EQUIPMENT NOT TO BE PAINTED A. Items of equipment furnished with complete factory finish, except for items specified to be given a finish coat under this Section. B. Factory-finished acoustical tile. C. Galvanized ferrous metals exposed to view. D. Non-ferrous metals, except for items specified and/or indicated to be painted. E. Finished hardware, excepting hardware that is factory primed. F. Surfaces not to be painted shall be left completely free of droppings and accidentally applied materials resulting from the work of this Section. 1.5 QUALITY ASSURANCE A. B. Job Mock-Up 1. In addition to the samples specified herein to be submitted for approval, apply in the field, at their final location, each type and color of approved paint materials, applied 10 feet wide, floor to ceiling of wall surfaces, before proceeding with the remainder of the work, for approval by the Architect. Paint mock-ups to include door and frame assembly. 2. These applications when approved will establish the quality and workmanship for the work of this Section. 3. Repaint individual areas which are not approved, as determined by the Architect, until approval is received. Assume at least two paint mock-ups of each color and gloss for approval. Qualification of Painters: Use only qualified journeyman painters for the mixing and application of paint on exposed surfaces. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-2 Painting and Finishing July 28, 2010 C. 1.6 Paint Coordination: Provide finish coats which are compatible with the prime paints used. Review other Sections of these specifications in which prime paints are to be provided to ensure compatibility of the total coatings system for the various substrates. Upon request from other subcontractors, furnish information on the characteristics of the finish materials proposed to be used, to ensure that compatible prime coats are used. Provide barrier coats over incompatible primers or remove and re-prime as required. Notify the Architect in writing of any anticipated problems using the coating systems as specified with substrates primed by others. SUBMITTALS A. B. C. 1.7 Materials List 1. Before any paint materials are delivered to the job site, submit to the Architect a complete list of all materials proposed to be furnished and installed under this portion of the work. 2. This shall in no way be construed as permitting substitution of materials for those specified or accepted for this work by the Architect. Samples 1. Accompanying the materials list, submit to the Architect copies of the full range of colors available in each of the proposed products. 2. Upon direction of the Architect, prepare and deliver to the Architect two (2) identical sets of Samples of each of the selected colors and glosses painted onto 81/2" x 11" x 1/4" thick material; whenever possible, the material for Samples shall be the same material as that on which the coating will be applied in the work. Manufacturer's Recommendations: In each case where material proposed is not the material specified or specifically described as an acceptable alternate in this Section of these specifications, submit for the Architect's review the current recommended method of application published by the manufacturer of the proposed material. PRODUCT HANDLING A. Deliver all paint materials to the job site in their original unopened containers with all labels intact and legible at time of use. B. Protection 1. Store only the approved materials at the job site, and store only in a suitable and designated area restricted to the storage of paint materials and related equipment. 2. Use all means necessary to ensure the safe storage and use of paint materials and the prompt and safe disposal of waste. 3. Use all means necessary to protect paint materials before, during and after application and to protect the installed work and materials of all other trades. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-3 Painting and Finishing July 28, 2010 C. 1.8 Replacements: In the event of damage, immediately make all repairs and replacements necessary. EXTRA STOCK A. 1.9 Upon completion of this portion of the Work, deliver to the Owner an extra stock of paint equaling approximately 5 percent, but not less than one gallon) of each color and gloss used and each coating material used, with all such extra stock tightly sealed in clearly labeled containers. JOB CONDITIONS A. Apply water-based paints only when the temperature of surfaces to be painted and the surrounding air temperatures are between 50 and 90 degrees F., unless otherwise permitted by the paint manufacturer's printed instructions. B. Apply solvent-thinned paints only when the temperature of surfaces to be painted and the surrounding air temperatures are between 45 and 95 degrees F. unless otherwise permitted by the paint manufacturer's printed instructions. C. Do not apply paint in snow, rain, fog or mist; or when the relative humidity exceeds 85 percent; or to damp or wet surfaces; unless otherwise permitted by the paint manufacturer's printed instructions. D. Painting may be continued during inclement weather only if the areas and surfaces to be painted are enclosed and heated within the temperature limits specified by the paint manufacturer during application and drying periods. PART 2 PRODUCTS 2.1 PAINT MANUFACTURERS A. Except as otherwise noted, provide the painting products listed for all required painting made by one of the manufacturers listed in the paint schedule (Section 2.4). These companies are Benjamin Moore, Tnemec (where noted), Wolf Gordon (where noted), IPC Paint, ICI Dulux and Sherwin Williams (S-W). Comply with number of coats and required minimum mil thicknesses as specified herein. B. Paints noted in Finish Schedule are Benjamin Moore; other manufacturers listed herein may substitute their equivalent paints with the approval of the Architect. 2.2 MATERIALS A. Provide undercoat paint produced by the same manufacturer as the finish coats. Use only thinners approved by the paint manufacturer, and use only to recommended limits. B. Colors and Glosses: All colors and glosses shall be as selected by the Architect. Certain colors will require paint manufacturer to prepare special factory mixes to match colors selected by the Architect. Color schedule (with gloss) shall be furnished by the Architect. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-4 Painting and Finishing July 28, 2010 C. Coloring Pigment: Products of or furnished by the manufacturer of the paint or enamel approved for the work. D. Driers, Putty, Spackling Compound, Patching Plaster, etc.: Best quality, of approved manufacture. E. Heat Resistant Paint: Where required, use heat resistant paint when applying paint to heating lines and equipment. 2.3 GENERAL STANDARDS A. The various surfaces shall be painted or finished as specified below in Article 2.4. However, the Architect reserves the right to change the finishes within the range of flat, semi-gloss or gloss, without additional cost to the Owner. B. All paints, varnishes, enamels, lacquers, stains and similar materials must be delivered in the original containers with the seals unbroken and label intact and with the manufacturer's instructions printed thereon. C. All painting materials shall bear identifying labels on the containers with the manufacturer's instructions printed thereon. D. Paint shall not be badly settled, caked or thickened in the container, shall be readily dispersed with a paddle to a smooth consistency and shall have excellent application properties. E. Paint shall arrive on the job color-mixed except for tinting of under-coats and possible thinning. F. All thinning and tinting materials shall be as recommended by the manufacturer for the particular material thinned or tinted. G. It shall be the responsibility of the Contractor to see that all mixed colors match the color selection made by the Architect prior to application of the coating. 2.4 SCHEDULE OF FINISHES A. High Performance Coating On Exterior Galvanized Ferrous Metals First Coat: Second Coat: B. "27 Typoxy" or "N69 Epoxoline II" by Tnemec; "Intergard 345" by International Protective Coatings; or "Carboguard 893 SG" or "Carboguard 888" by Carboline or Akzo: Devran 203 WB Epoxy Primer "V73 Endura Shield" or "1074/1075" by Tnemec; "Interthane 870UHS" or "990 UHS" by International Protective Coatings; or "Carbothane 133 LH" by Carboline or Akzo: Devethne 379H Aliphatic Vizethne High Performance Coating On Exterior Non-Galvanized Ferrous Metals Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-5 Painting and Finishing July 28, 2010 Prime Coat: Second Coat: Third Coat: C. "Tneme-Zinc 90/97" by Tnemec; "Interzinc 52" or "315" by International Protective Coatings; or "Carbozinc 859, Class B" by Carboline "27 Typoxy" or "N69 Epoxoline II" by Tnemec; "Intergard 345" by International Protective Coatings; or "Carboguard 893 SG" or "Carboguard 888" by Carboline "V73 Endura Shield" or "1074/1075" by Tnemec; “Interthane 870UHS or 990 UHS" by International Protective Coatings; or "Carbothane 133 LH" by Carboline Interior Ferrous Metal Satin Finish/Latex Primer: 1 coat Rust-O-Lastic Anti-Corrosive Primer (073-132) MAB First Coat: 1 coat AURA Matte Waterborne Interior Paint (522) BM 1 coat Enviro-Pure Latex Flat – Zero VOC (040) MAB 1 coat ULTRA-WALL latex Flat Interior Wall Paint (1230) ICI Second Coat: 1 coat AURA Matte Waterborne Interior Paint (522) BM 1 coat Enviro-Pure Latex Flat – Zero VOC (040) MAB 1 coat ULTRA-WALL latex Flat Interior Wall Paint (1230) ICI Semi-Gloss Finish/Latex Primer: 1 coat Rust-O-Lastic Anti-Corrosive Primer (073-132) MAB First Coat: 1 coat AURA Semi Gloss Waterborne Interior Paint (528) 1 coat Enviro-Pure Semi-Gloss - Zero VOC (047) Second Coat: 1 coat AURA Semi Gloss Waterborne Interior Paint (528) 1 coat Enviro-Pure Semi-Gloss - Zero VOC (047) D. BM MAB BM MAB Interior Concrete Block Flat Finish/Vinyl Acrylic Latex over Filler Block Filler: 1 coat Moorcraft Super Craft Latex Block Filler (285) 1 coat Seal-Crete Waterproofing Sealer (101) 1 coat S-W Preprite Block Filler White, B25W25 First Coat: 1 coat AURA Matte Waterborne Interior Paint (522) 1 coat Enviro-Pure Latex Flat – Zero VOC (040) 1 coat ULTRA-WALL Latex Flat Interior Wall Paint (1230) Second Coat: 1 coat AURA Matte Waterborne Interior Paint (522) 1 coat Enviro-Pure Latex Flat – Zero VOC (040) 1 coat ULTRA-WALL Latex Flat Interior Wall Paint (1230) Eggshell Finish/Vinyl Acrylic Latex over Filler Block Filler: 1 coat Moorcraft Super Craft Latex Block Filler (285) 1 coat Seal-Crete Waterproofing Sealer (101) 1 coat S-W Preprite Block Filler White, B25W25 First Coat: 1 coat AURA Eggshell Waterborne Interior Paint (524) BM 1 coat Enviro-Pure Eggshell - Zero VOC (045) MAB 1 coat CUSTOM HOME Latex Flat Eggshell Enamel (1493) Second Coat: 1 coat AURA Eggshell Waterborne Interior Paint (524) BM Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-6 BM MAB S-W BM MAB ICI BM MAB ICI BM MAB S-W ICI Painting and Finishing July 28, 2010 1 coat Enviro-Pure Eggshell - Zero VOC (045) MAB 1 coat CUSTOM HOME Latex Flat Eggshell Enamel (1493) ICI Semi-Gloss Finish/Vinyl Acrylic Latex over Filler Block Filler: 1 coat Moorcraft Super Craft Latex Block Filler (285) 1 coat Seal-Crete Waterproofing Sealer – Zero VOC (101) 1 coat S-W Preprite Block Filler White, B25W25 First Coat: 1 coat AURA Semi Gloss Waterborne Interior Paint (528) 1 coat Enviro-Pure Semi-Gloss - Zero VOC (047) 1 coat CUSTOM HOME Latex Flat Semi-Gloss Enamel (1493) ICI Second Coat: 1 coat AURA Semi Gloss Waterborne Interior Paint (528) 1 coat Enviro-Pure Semi-Gloss - Zero VOC (047) 1 coat CUSTOM HOME Latex Flat Semi-Gloss Enamel (1493) ICI E. BM MAB Interior Drywall Flat Finish/Vinyl Acrylic Latex Primer: 1 coat Pristine Eco Spec Interior Latex Primer (231) 1 coat Enviro-Pure Latex Flat – Zero VOC (040) 1 coat HARMONY Interior Latex Primer (B11W900) S-W First Coat: 1 coat AURA Matte Waterborne Interior Paint (522) 1 coat ULTRA-WALL Latex Flat Interior Wall Paint 1230) 1 coat HARMONY Interior Latex Flat (B5) Second Coat: 1 coat AURA Matte Waterborne Interior Paint (522) 1 coat ULTRA-WALL Latex Flat Interior Wall Paint 1230) 1 coat HARMONY Interior Latex Flat (B5) Eggshell Finish/Vinyl Acrylic Latex Primer: 1 coat Pristine Eco Spec Interior Latex Primer (231) 1 coat Enviro-Pure Latex Flat – Zero VOC (040) 1 coat PREP & PRIME AQUACRYLIC GRIPPER (3210) First Coat: 1 coat AURA Eggshell Waterborne Interior Paint (524) BM 1 coat HARMONY Interior Latex EG-SHEL (B9) Second Coat: 1 coat AURA Eggshell Waterborne Interior Paint (524) BM 1 coat HARMONY Interior Latex EG-SHEL (B9) F. BM MAB S-W BM MAB BM MAB BM ICI S-W BM ICI S-W BM MAB S-W S-W S-W Interior Painted Wood Doors: Eggshell Finish/Latex Primer: 1 coat Pristine Eco Spec Interior Latex Primer (231) 1 coat Seal-Crete Waterproofing Sealer - Zero VOC (101) First Coat: 1 coat AURA Semi gloss Waterborne, Interior Paint (522) 1 coat ULTRA-WALL Latex Flat Interior Wall Paint 1230) 1 coat HARMONY Interior Latex Flat (B5) Second Coat: 1 coat AURA Semi gloss Waterborne, Interior Paint (522) 1 coat ULTRA-WALL Latex Flat Interior Wall Paint 1230) Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-7 BM MAB BM ICI S-W BM ICI Painting and Finishing July 28, 2010 2.5 1 coat HARMONY Interior Latex Flat (B5) S-W Semi-Gloss Finish/Latex Primer: 1 coat Pristine Eco Spec Interior Latex Primer (231) 1 coat Seal-Crete Waterproofing Sealer - Zero VOC (101) First Coat: 1 coat AURA Semigloss Waterborne Interior Paint (528) 1 coat Enviro-Pure Semi-Gloss - Zero VOC (047) 1 coat CUSTOM HOME Latex Semi-Gloss Enamel (1497) Second Coat: 1 coat AURA Semigloss Waterborne Interior Paint (528) 1 coat Enviro-Pure Semi-Gloss - Zero VOC (047) 1 coat CUSTOM HOME Latex Semi-Gloss Enamel (1497) BM MAB BM MAB ICI BM MAB ICI EXISTING SURFACES TO BE PAINTED A. 2.6 Existing surfaces shall be painted in accordance with schedule given in Article 2.4 herein except that first or prime coat may be eliminated where existing paint is sound. Where existing paint must be removed down to base material, provide first or prime coat as specified. PIPING AND MECHANICAL EQUIPMENT EXPOSED TO VIEW A. Paint all exposed piping, conduits, ductwork and mechanical and electrical equipment. Use heat resisting paint when applied to heating lines and equipment. The Contractor is cautioned not to paint or otherwise disturb moving parts in the mechanical systems. Mask or otherwise protect all parts as required to prevent damage. B. Exposed Uncovered Ductwork, Piping, Hangers and Equipment: Latex Enamel Undercoater and one (1) coat Acrylic Latex Flat. C. Exposed Covered Piping, Duct Work and Equipment: Primer/Sealer and one (1) coat Acrylic Latex Flat. D. Panel Boards, Grilles and Exposed Surfaces of Electrical Equipment: Latex Enamel Undercoater and two (2) coats Latex Semi-Gloss. E. Equipment or Apparatus with Factory-Applied Paint: Refinish any damaged surfaces to match original finish. Do not paint over name plates and labels. F. All surfaces of insulation and all other work to be painted shall be wiped or washed clean before any painting is started. G. All conduit, boxes, distribution boxes, light and power panels, hangers, clamps, etc., are included where painting is required. H. All items of Mechanical and Electrical trades which are furnished painted under their respective Contracts shall be carefully coordinated with the work of this Section so as to leave no doubt as to what items are scheduled to be painted under this Section. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-8 Painting and Finishing July 28, 2010 PART 3 EXECUTION 3.1 INSPECTION A. 3.2 Examine the areas and conditions where painting and finishing are to be applied and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work. GENERAL WORKMANSHIP REQUIREMENTS A. Only skilled mechanics shall be employed. Application may be by brush or roller. Spray application only upon acceptance from the Architect in writing. B. The Contractor shall furnish the Architect a schedule showing when he expects to have completed the respective coats of paint for the various areas and surfaces. This schedule shall be kept current as the job progresses. C. The Contractor shall protect his work at all times, and shall protect all adjacent work and materials by suitable covering or other method during progress of his work. Upon completion of the work, he shall remove all paint and varnish spots from floors, glass and other surfaces. He shall remove from the premises all rubbish and accumulated materials of whatever nature not caused by others and shall leave his part of the work in clean, orderly and acceptable condition. D. Remove and protect hardware, accessories, device plates, lighting fixtures, and factory finished work, and similar items, or provide ample in place protection. Upon completion of each space, carefully replace all removed items by workmen skilled in the trades involved. E. Remove electrical panel box covers and doors before painting walls. Paint separately and re-install after all paint is dry. F. All materials shall be applied under adequate illumination, evenly spread and flowed on smoothly to avoid runs, sags, holidays, brush marks, air bubbles and excessive roller stipple. G. Coverage and hide shall be complete. When color, stain, dirt or undercoats show through final coat of paint, the surface shall be covered by additional coats until the paint film is of uniform finish, color, appearance and coverage, at no additional cost to the Owner. H. All coats shall be dry to manufacturer’s recommendations before applying succeeding coats. I. Do not apply paint behind frameless mirrors that use mastic for adhering to wall surface. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-9 Painting and Finishing July 28, 2010 3.3 PREPARATION OF SURFACES A. Existing Surfaces: Clean existing surfaces requiring paint or finishing, remove all loose and flaking paint or finish and sand surface smooth as required to receive new paint or finish. No “telegraphing” of lines, ridges, flakes, etc., through new surfacing is permitted. Where this occurs, Contractor shall be required to sand smooth and re-finish until surface meets with Architect’s approval. B. General C. D. 1. The Contractor shall be held wholly responsible for the finished appearance and satisfactory completion of painting work. Properly prepare all surfaces to receive paint, which includes cleaning, sanding, and touching-up of all prime coats applied under other Sections of the work. Broom clean all spaces before painting is started. All surfaces to be painted or finished shall be perfectly dry, clean and smooth. 2. Perform all preparation and cleaning procedures in strict accordance with the paint manufacturer’s instructions and as herein specified, for each particular substrate condition. 3. Clean surfaces to be painted before applying paint or surface treatments. Remove oil and grease with clean cloths and cleaning solvents prior to mechanical cleaning. Program the cleaning and painting so that dust and other contaminants from the cleaning process will not fall in wet, newly painted surfaces. Metal Surfaces 1. Weld Fluxes: Remove weld fluxes, splatters, and alkali contaminants from metal surfaces in an approved manner and leave surface ready to receive painting. 2. Bare Metal: Thoroughly clean off all foreign matter such as grease, rust, scale and dirt before priming coat is applied. Clean surfaces, where solder flux has been used, with benzene. Clean surfaces by flushing with mineral spirits. For aluminum surfaces, wipe down with an oil free solvent prior to application of any pre-treatment. 3. Shop Primed Metal: Clean off foreign matter as specified for “Bare Metal.” Prime bare, rusted, abraded and marred surfaces with approved primer after proper cleaning of surfaces. Sandpaper all rough surfaces smooth. 4. Galvanized Metal: Prepare surface as per the requirements of ASTM D 6386. 5. Metal Filler: Fill dents, cracks, hollow places, open joints and other irregularities in metal work to be painted with an approved metal filler suitable for the purpose and meeting the requirements of the related Section of work; after setting, sand to a smooth, hard finish, flush with adjoining surface. Gypsum Drywall Surfaces: Scrape off all projections and splatters, spackles all holes or depressions, including taped and spackled joints, sand smooth. Conform to standards established in Section 092900 Gypsum Drywall. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-10 Painting and Finishing July 28, 2010 E. Wood Door Surfaces: Sand to remove all roughness, loose edges, slivers, or splinters and then brush to remove dust. Wash off grease or dirt with an approved cleaner.. F. Block Masonry Surfaces: Thoroughly clean off all grit, grease, dirt mortar drippings or splatters, and other foreign matter. Remove nibs or projections from masonry surfaces. Fill cracks, holes or voids, not filled under the "Masonry" Section, with Portland cement grout, and bag surface so that it has approximately the same texture as the adjacent masonry surface. G. Testing for Moisture Content: Contractor shall test all plaster, masonry, and drywall surfaces for moisture content using a reliable electronic moisture meter. Contractor shall also test latex type fillers for moisture content before application of top coats of paint. Do not apply any paint or sealer to any surface or to latex type filler where the moisture content exceeds 7 percent as measured by the electronic moisture meter. H. Touch-Up: Prime paint all patched portions in addition to all other specified coats. 3.4 MATERIALS PREPARATION A. Mix and prepare painting materials in strict accordance with the manufacturer’s directions. B. Store materials not in actual use in tightly covered containers. Maintain containers used in storage, mixing, and application of paint in a clean condition, free of foreign materials and residue. C. Stir all materials before application to produce a mixture of uniform density, and as required during the application of the materials. Do not stir any film which may form on the surface into the material. Remove the film and, if necessary, strain the material before using. D. Tint each undercoat a lighter shade to facilitate identification of each coat where multiple coats of the same material are to be applied. Tint undercoats to match the color of the finish coat, but provide sufficient difference in shade of undercoats to distinguish each separate coat. 3.5 APPLICATION A. General 1. Apply paint by brush or roller in accordance with the manufacturer’s directions. Use brushes best suited for the type of material being applied. Use rollers of carpet, velvet back, or high pile sheep's wool as recommended by the paint manufacturer for material and texture required. 2. The number of coats and paint film thickness required is the same regardless of the application method. Do not apply succeeding coats until the previous coat has completely dried. Sand between each enamel or varnish coat application with fine sandpaper, or rub surfaces with pumice stone where required to produce an even, smooth surface in accordance with the coating manufacturer’s directions. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-11 Painting and Finishing July 28, 2010 3. Apply additional coats when undercoats, stains, or other conditions show through the final coat of paint, until the paint film is of uniform finish, color and appearance. Give special attention to insure that all surfaces, including edges, corners, crevices, welds, and exposed fasteners receive a film thickness equivalent to that of flat surfaces. 4. Paint surfaces behind movable equipment and furniture the same as similar exposed surfaces. Paint surfaces behind permanently fixed equipment or furniture with prime coat only. a. B. "Exposed surfaces" is defined as those areas visible when permanent or built-in fixtures, convector covers, covers for finned tube radiation, grilles, etc., are in place in areas scheduled to be painted. 5. Paint interior surfaces of ducts, where visible through registers or grilles, with a flat, non-specular black paint, before final installation of equipment. 6. Paint the back sides of access panels, removable or hinged covers to match the exposed surfaces. 7. Finish doors on tops, bottoms, and side edges the same as the faces, unless otherwise indicated. 8. Enamel finish applied to wood or metal shall be sanded with fine sandpaper and then cleaned between coats to produce an even surface. 9. Paste wood filler applied on open grained wood after beginning to flatten, shall be wiped across the grain of the wood, then with a circular motion, to secure a smooth, filled, clean surface with filler remaining in open grain only. After overnight dry, sand surface with the grain until smooth before applying specified coat. Scheduling Painting 1. Apply the first coat material to surfaces that have been cleaned, pre-treated or otherwise prepared for painting as soon as practicable after preparation and before subsequent surface deterioration. 2. Allow sufficient time between successive coatings to permit proper drying. Do not re-coat until paint has dried to where it feels firm, does not deform or feel sticky under moderate thumb pressure, and the application of another coat of paint does not cause lifting or loss of adhesion of the undercoat. C. Prime Coats: Re-coat primed and sealed walls and ceilings where there is evidence of suction spots or unsealed areas in first coat, to assure a finish coat with no burn-through or other defects due to insufficient sealing. D. Pigmented (Opaque) Finishes: Completely cover to provide an opaque, smooth surface of uniform finish, color, appearance and coverage. Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-12 Painting and Finishing July 28, 2010 E. 3.6 “Touching-Up” of Factory Finishes: Unless otherwise specified or shown, materials with a factory finish shall not be painted at the project site. To “touch-up,” the Contractor shall use the factory finished material manufacturer’s recommended paint materials to repair abraded, chipped, or otherwise defective surfaces. PROTECTION A. Protect work of other trades, whether to be painted or not, against damage by the painting and finishing work. Leave all such work undamaged. Correct any damages by cleaning, repairing or replacing, and repainting, as acceptable to the Architect. B. Provide "Wet Paint" signs as required to protect newly painted finishes. Remove temporary protective wrappings provided by others for protection of their work after completion of painting operations. 3.7 CLEAN UP A. During the progress of the work, remove from the site all discarded paint materials, rubbish, cans and rags at the end of each work day. B. Upon completion of painting work, clean window glass and other paint spattered surfaces. Remove spattered paint by proper methods of washing and scraping, using care not to scratch or otherwise damage finished surfaces. C. At the completion of work of other trades, touch-up and restore all damaged or defaced painted surfaces. END OF SECTION Roosevelt Hall Interior Renovation Brooklyn College Brooklyn, NY Project #6032.20 099000-13 Painting and Finishing July 28, 2010 SECTION 230500 COMMON WORK RESULTS FOR HVAC PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 1.3 Transition fittings. Dielectric fittings. Mechanical sleeve seals. Sleeves. Escutcheons. Grout. HVAC demolition. Equipment installation requirements common to equipment sections. Painting and finishing. Concrete bases. Supports and anchorages. DEFINITIONS A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels. B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms. C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations. D. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and chases. E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures. Examples include installations within unheated shelters. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 1 Common Work Results for HVAC June 30, 2010 F. The following are industry abbreviations for plastic materials: 1. G. The following are industry abbreviations for rubber materials: 1. 2. 1.4 PP: Polypropylene plastic. EPDM: Ethylene-propylene-diene terpolymer rubber. NBR: Acrylonitrile-butadiene rubber. SUBMITTALS A. Product Data: For the following: 1. 2. 3. 4. B. 1.5 Transition fittings. Dielectric fittings. Mechanical sleeve seals. Escutcheons. Welding certificates. QUALITY ASSURANCE A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel." B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications." 1. C. 1.6 Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current. Electrical Characteristics for HVAC Equipment: Equipment of higher electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements. DELIVERY, STORAGE, AND HANDLING A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture. B. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 2 Common Work Results for HVAC June 30, 2010 1.7 COORDINATION A. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of construction, to allow for HVAC installations. B. Coordinate installation of required supporting devices and set sleeves in poured-inplace concrete and other structural components as they are constructed. C. Coordinate requirements for access panels and doors for HVAC items requiring access that are concealed behind finished surfaces. Access panels and doors are specified in Division 08 Section "Access Doors and Frames." 1.8 REGULATIONS, CODES, PERMITS AND FEES A. General 1. 2. 3. 4. 5. 6. B. Inspections and Approvals 1. 2. C. The installation shall be in accordance with all relevant codes and regulations of the City and State having jurisdiction over the project location. Codes, standards and specifications applicable to this work shall be the latest editions in effect at the date of the proposal. It is not the intent of Drawings and Specifications to repeat requirements of codes except where necessary for completeness or clarity. Nothing in the Drawings or Specifications shall be construed to permit Work not conforming to applicable laws, ordinances, rules or regulations. When the Documents conflict with regulatory or code requirements the most stringent requirement shall apply. Contractor shall be responsible for all law violations caused by the work under this Division. Notify the Architect/Engineer in writing when a discrepancy occurs between code requirements and work shown on drawings and resolve the discrepancy before proceeding with work. Provide the Owner, the Construction Manager and local Inspectors access to work at all times. All controlled inspections shall be the responsibility of the Contractor. The Contractor shall coordinate all inspections and provide all support and personnel necessary for successful completion. Permits and Fees 1. 2. Make application and pay for all certificates of inspection, taxes and permits required by AHJs. Deliver to the Owner any and all certificates of inspections, permits, and approvals which may be required by AHJs. Pay all utility charges and charges from the AHJ for providing temporary and permanent water, sewer, and gas services to buildings. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 3 Common Work Results for HVAC June 30, 2010 1.9 REVIEW OF CONSTRUCTION A. Work may be reviewed at any time by Architect/Engineer. B. Advise Architect/Engineer that work is ready for review at following times: 1. 2. 3. 4. Prior to backfilling buried work. Prior to concealment of work in walls and above ceilings. When an area or section of work is ready for punchlisting by the Architect/Engineer. When all requirements of Contract have been completed. C. Do not backfill or conceal work without Architect/Engineer’s consent. D. Maintain at the job site a set of Specifications and Drawings for use by Architect/Engineer. E. Architect/Engineer's reviews will be periodic, depending upon nature of construction. Architect/Engineer is not required to perform extensive or continuous inspection, is not responsible for execution of Contract Documents by Contractor and is not responsible for construction methods, sequences, or safety precautions. 1.10 MINOR DEVIATION A. The dimensions and ratings of equipment herein specified or indicated on the Drawings are intended to establish the desired outlines and characteristics of such equipment. Minor deviations may be permitted after review by the Architect/Engineer to allow manufacturers specified to bid on their nearest standard equipment. B. Manufacturers catalog or model numbers and types mentioned in the Specifications or indicated on the drawings are intended to be used as guides and shall not be interpreted as taking precedence over specific ratings or duty called for or shown, which modify stipulations in such catalogs. In all cases, the manufacturer shall verify the duty specified with the particular characteristics of the equipment he intends to submit and shall only submit items that comply with Specification requirements. 1.11 DEFECTIVE WORK A. Defective work, whether the result of poor workmanship, use of defective materials, damage through carelessness, or other cause shall be removed within ten (10) days after written notice is given by the Architect/Engineer and the work shall be re-executed by the Contractor. B. The fact that the defects may have previously overlooked by the Architect/Engineer shall not constitute total or partial acceptance or grounds for additional payment for corrective work. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 4 Common Work Results for HVAC June 30, 2010 1.12 A. COOPERATION BETWEEN TRADES General 1. 2. 3. 4. Cooperate with all other Divisions performing work on this project as necessary to achieve a complete neatly fitted installation for each condition. Consult the Drawings and Specifications to determine nature and extent of work specified in other Divisions which adjoins or attaches to the work of this Division. Confer with other Divisions at the site to coordinate this work with theirs in view of job conditions to the end that interferences may be eliminated and that maximum head room and clearance may be obtained. In the event that interferences develop, the Architect/Engineer's decision will be final as to which Division shall relocate its work and no additional compensation will be allowed for the moving of ductwork, conduit or equipment to clear such interferences. Provide templates, information and instructions to other divisions to properly locate holes and openings to be cut or provide. For Testing and Balancing of the system, ensure full co-ordination between the Testing and Balancing subcontractor and all other Trades to achieve access to all system components including leaving wall/ceiling sections down for access. Ensure full co-ordination between controls subcontractor and Testing and Balancing subcontractor to ensure the system is commissioned in accordance with the requirements of the contract documents. B. The Contractor shall be responsible for the coordination of the mechanical ducting distribution with the lighting, conduit, cable tray and structural members. C. Electrical work for mechanical equipment. 1. 2. 3. It is the Division 23 Contractor's responsibility to ensure the Division 26 Contractor is aware of the electrical power and control requirements of all mechanical equipment. Electrical Work in this Division shall conform to requirements of Division 26. Work and equipment specified in Division 26 and to be completed by the Division 26 Contractor: a. b. c. d. e. f. g. h. Motors except motors packaged with a piece of equipment Motor control centers. Motor starters except starters packaged with a piece of equipment. Disconnect switches except disconnect switches packaged with or factory mounted to a piece of equipment. Power wiring to all equipment including from equipment disconnect switches to motors. Power wiring to all components of equipment that are not factory prewired including but not limited to solenoid valves and relays. Power wiring to all control panels. Hard wired interlocks between the BMS and all other electrical systems including but not limited to fire alarm, security and information technology systems. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 5 Common Work Results for HVAC June 30, 2010 i. j. k. 4. Conduit for the controls system wiring specified in Division 23. Wiring for the fire protection system. Smoke detectors for mounting in the Division 23 system and wiring to the smoke detectors. The smoke detectors will be mounted by the Division 23 contractor. Smoke detectors shall be located according to manufacturer’s installation requirements and locations shall be shown on the mechanical shop drawings. Work specified in this Division and to be completed by the Division 23 contractor: a. b. c. d. e. Supply of complete and accurate wiring diagrams to Division 26 for all equipment requiring electrical power wiring. Adjustable motor bases and all bolts and nuts required for installation of base and motor. Alignment and adjustment of mechanical couplings for direct-driven motorized equipment and of drive and belt tension on belt driven equipment. Field lubrication of all motors prior to operation and up to time of acceptance of equipment by the Owner. Motor terminal connection diagram as prepared by motor manufacturers. PART 2 PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where subparagraph titles below introduce lists, the following requirements apply for product selection: 1. 2.2 Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified. GROUT A. Description: ASTM C 1107, Grade B, nonshrink and nonmetallic, dry hydrauliccement grout. 1. 2. 3. Characteristics: Post-hardening, volume-adjusting, nonstaining, noncorrosive, nongaseous, and recommended for interior and exterior applications. Design Mix: 5000-psi (34.5-MPa), 28-day compressive strength. Packaging: Premixed and factory packaged. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 6 Common Work Results for HVAC June 30, 2010 PART 3 EXECUTION 3.1 HVAC DEMOLITION A. Refer to Division 01 Section "Cutting and Patching" and Division 02 Section "Selective Structure Demolition" for general demolition requirements and procedures. B. Disconnect, demolish, and remove HVAC systems, equipment, and components indicated to be removed. 1. 2. 3. 4. 5. C. 3.2 Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material. Equipment to Be Removed: Disconnect and cap services and remove equipment. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner. If pipe, insulation, or equipment to remain is damaged in appearance or is unserviceable, remove damaged or unserviceable portions and replace with new products of equal capacity and quality. EQUIPMENT INSTALLATION - COMMON REQUIREMENTS A. Install equipment to allow maximum possible headroom unless specific mounting heights are not indicated. B. Install equipment level and plumb, parallel and perpendicular to other building systems and components in exposed interior spaces, unless otherwise indicated. C. Install HVAC equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting, with minimum interference to other installations. Extend grease fittings to accessible locations. 3.3 PAINTING A. Painting of HVAC systems, equipment, and components is specified in Division 09 Sections "Interior Painting" and "Exterior Painting." B. Damage and Touchup: Repair marred and damaged factory-painted finishes with materials and procedures to match original factory finish. 3.4 ERECTION OF METAL SUPPORTS AND ANCHORAGES A. Refer to Division 05 Section "Metal Fabrications" for structural steel. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 7 Common Work Results for HVAC June 30, 2010 B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor HVAC materials and equipment. C. Field Welding: Comply with AWS D1.1. 3.5 ERECTION OF WOOD SUPPORTS AND ANCHORAGES A. Cut, fit, and place wood grounds, nailers, blocking, and anchorages to support, and anchor HVAC materials and equipment. B. Select fastener sizes that will not penetrate members if opposite side will be exposed to view or will receive finish materials. Tighten connections between members. Install fasteners without splitting wood members. C. Attach to substrates as required to support applied loads. 3.6 GROUTING A. Mix and install grout for HVAC equipment base bearing surfaces, pump and other equipment base plates, and anchors. B. Clean surfaces that will come into contact with grout. C. Provide forms as required for placement of grout. D. Avoid air entrapment during placement of grout. E. Place grout, completely filling equipment bases. F. Place grout on concrete bases and provide smooth bearing surface for equipment. G. Place grout around anchors. H. Cure placed grout. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230500- 8 Common Work Results for HVAC June 30, 2010 SECTION 230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. 1.3 Section includes general requirements for single-phase and polyphase, general-purpose, horizontal, small and medium, squirrel-cage induction motors for use on ac power systems up to 600 V and installed at equipment manufacturer's factory or shipped separately by equipment manufacturer for field installation. COORDINATION A. Coordinate features of motors, installed units, and accessory devices to be compatible with the following: 1. 2. 3. 4. Motor controllers. Torque, speed, and horsepower requirements of the load. Ratings and characteristics of supply circuit and required control sequence. Ambient and environmental conditions of installation location. PART 2 PRODUCTS 2.1 GENERAL MOTOR REQUIREMENTS A. Comply with requirements in this Section except when stricter requirements are specified in HVAC equipment schedules or Sections. B. Comply with NEMA MG 1 unless otherwise indicated. C. Comply with IEEE 841 for severe-duty motors. 2.2 MOTOR CHARACTERISTICS A. Duty: Continuous duty at ambient temperature of 40 deg C and at altitude of 3300 feet (1000 m) above sea level. B. Capacity and Torque Characteristics: Sufficient to start, accelerate, and operate connected loads at designated speeds, at installed altitude and environment, with Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230513- 1 Common Motor Requirements for HVAC Equipment June 30, 2010 indicated operating sequence, and without exceeding nameplate ratings or considering service factor. 2.3 POLYPHASE MOTORS A. Description: NEMA MG 1, Design B, medium induction motor. B. Efficiency: Premium, as defined in NEMA MG 1. C. Service Factor: 1.15. D. Multispeed Motors: Variable torque. 1. 2. For motors with 2:1 speed ratio, consequent pole, single winding. For motors with other than 2:1 speed ratio, separate winding for each speed. E. Multispeed Motors: Separate winding for each speed. F. Rotor: Random-wound, squirrel cage. G. Bearings: Double-shielded, prelubricated ball bearings suitable for radial and thrust loading. H. Temperature Rise: Match insulation rating. I. Insulation: Class F. J. Code Letter Designation: 1. 2. K. 2.4 Motors 15 HP and Larger: NEMA starting Code F or Code G. Motors Smaller than 15 HP: Manufacturer's standard starting characteristic. Enclosure Material: Cast iron for motors 7.5 hp and larger; rolled steel for motors smaller than 7.5 hp. POLYPHASE MOTORS WITH ADDITIONAL REQUIREMENTS A. Motors Used with Reduced-Voltage and Multispeed Controllers: Match wiring connection requirements for controller with required motor leads. Provide terminals in motor terminal box, suited to control method. B. Motors Used with Variable Frequency Controllers: Ratings, characteristics, and features coordinated with and approved by controller manufacturer. 1. 2. 3. Designed with critical vibration frequencies outside operating range of controller output. Temperature Rise: Matched to rating for Class B insulation. Insulation: Class H. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230513- 2 Common Motor Requirements for HVAC Equipment June 30, 2010 4. C. Source Quality Control for Field-Installed Motors: Perform the following tests on each motor according to NEMA MG 1: 1. 2. 3. 4. 2.5 Thermal Protection: Comply with NEMA MG 1 requirements for thermally protected motors. Measure winding resistance. Read no-load current and speed at rated voltage and frequency. Measure locked rotor current at rated frequency. Perform high-potential test. SINGLE-PHASE MOTORS A. Motors larger than 1/20 hp shall be one of the following, to suit starting torque and requirements of specific motor application: 1. 2. 3. Permanent-split capacitor. Split phase. Capacitor start, capacitor run. B. Multispeed Motors: Variable-torque, permanent-split-capacitor type. C. Bearings: Prelubricated, antifriction ball bearings or sleeve bearings suitable for radial and thrust loading. D. Motors 1/20 HP and Smaller: Shaded-pole type. E. Thermal Protection: Internal protection to automatically open power supply circuit to motor when winding temperature exceeds a safe value calibrated to temperature rating of motor insulation. Thermal-protection device shall automatically reset when motor temperature returns to normal range. PART 3 EXECUTION (NOT APPLICABLE) Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230513- 3 Common Motor Requirements for HVAC Equipment June 30, 2010 SECTION 230529 HANGERS AND SUPPORTS FOR HVAC EQUIPMENT PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following hangers and supports for HVAC system piping and equipment: 1. 2. 3. B. Related Sections include the following: 1. 2. 3. 4. 1.3 Metal framing systems. Fastener systems. Equipment supports. Division 05 Section "Metal Fabrications" for structural-steel shapes and plates for trapeze hangers for pipe and equipment supports. Division 21 Section "Water-Based Fire-Suppression Systems" for pipe hangers for fire-protection piping. Division 23 Section "Vibration and Seismic Controls for HVAC Equipment" for vibration isolation devices. Division 23 Section(s) "Metal Ducts" and "Nonmetal Ducts" for duct hangers and supports. DEFINITIONS A. MSS: Manufacturers Standardization Society for the Valve and Fittings Industry Inc. B. Terminology: As defined in MSS SP-90, "Guidelines on Terminology for Pipe Hangers and Supports." 1.4 PERFORMANCE REQUIREMENTS A. Design supports for multiple pipes, including pipe stands, capable of supporting combined weight of supported systems, system contents, and test water. B. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230529- 1 Hangers and Supports for HVAC Equipment June 30, 2010 1.5 SUBMITTALS A. Product Data: For the following: 1. 2. 3. B. Shop Drawings: Signed and sealed by a qualified professional engineer. Show fabrication and installation details and include calculations for the following: 1. 2. 3. 4. C. 1.6 Steel pipe hangers and supports. Thermal-hanger shield inserts. Powder-actuated fastener systems. Trapeze pipe hangers. Include Product Data for components. Metal framing systems. Include Product Data for components. Pipe stands. Include Product Data for components. Equipment supports. Welding certificates. QUALITY ASSURANCE A. Welding: Qualify procedures and personnel according to [AWS D1.1, "Structural Welding Code--Steel."] [AWS D1.3, "Structural Welding Code--Sheet Steel."] [AWS D1.4, "Structural Welding Code--Reinforcing Steel."] [ASME Boiler and Pressure Vessel Code: Section IX.] B. Welding: Qualify procedures and personnel according to the following: 1. 2. 3. 4. 5. AWS D1.1, "Structural Welding Code--Steel." AWS D1.2, "Structural Welding Code--Aluminum." AWS D1.3, "Structural Welding Code--Sheet Steel." AWS D1.4, "Structural Welding Code--Reinforcing Steel." ASME Boiler and Pressure Vessel Code: Section IX. PART 2 PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection: 1. 2. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, manufacturers specified. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers specified. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230529- 2 Hangers and Supports for HVAC Equipment June 30, 2010 2.2 METAL FRAMING SYSTEMS A. Description: MFMA-3, shop- or field-fabricated pipe-support assembly made of steel channels and other components. B. Manufacturers: 1. 2. 3. 4. 5. 6. 7. B-Line Systems, Inc.; a division of Cooper Industries. ERICO/Michigan Hanger Co.; ERISTRUT Div. GS Metals Corp. Power-Strut Div.; Tyco International, Ltd. Thomas & Betts Corporation. Tolco Inc. Unistrut Corp.; Tyco International, Ltd. C. Coatings: Manufacturer's standard finish, unless bare metal surfaces are indicated. D. Nonmetallic Coatings: Plastic coating, jacket, or liner. E. Padded Hangers: Hanger with rubber or felt isolator for support of bearing surface of piping. 2.3 FASTENER SYSTEMS A. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete with pull-out, tension, and shear capacities appropriate for supported loads and building materials where used. 1. B. Manufacturers: a. Hilti, Inc. b. ITW Ramset/Red Head. c. Masterset Fastening Systems, Inc. d. MKT Fastening, LLC. e. Powers Fasteners. Mechanical-Expansion Anchors: Insert-wedge-type zinc-coated steel, for use in hardened portland cement concrete with pull-out, tension, and shear capacities appropriate for supported loads and building materials where used. 1. Manufacturers: a. B-Line Systems, Inc.; a division of Cooper Industries. b. Empire Industries, Inc. c. Hilti, Inc. d. ITW Ramset/Red Head. e. MKT Fastening, LLC. f. Powers Fasteners. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230529- 3 Hangers and Supports for HVAC Equipment June 30, 2010 2.4 EQUIPMENT SUPPORTS A. 2.5 Description: Welded, shop- or field-fabricated equipment support made from structural-steel shapes. MISCELLANEOUS MATERIALS A. Structural Steel: ASTM A 36/A 36M, steel plates, shapes, and bars; black and galvanized. B. Grout: ASTM C 1107, factory-mixed and -packaged, dry, hydraulic-cement, nonshrink and nonmetallic grout; suitable for interior and exterior applications. 1. 2. Properties: Nonstaining, noncorrosive, and nongaseous. Design Mix: 5000-psi (34.5-MPa), 28-day compressive strength. PART 3 EXECUTION 3.1 HANGER AND SUPPORT APPLICATIONS A. Specific hanger and support requirements are specified in Sections specifying equipment. B. Comply with MSS SP-69 for pipe hanger selections and applications that are not specified in piping system Sections. C. Use hangers and supports with galvanized, metallic coatings for equipment that will not have field-applied finish. D. Use nonmetallic coatings on attachments for electrolytic protection where attachments are in direct contact with copper tubing. E. Floor support hanger devices or systems shall not be used. F. Angle iron or Unistrut type wall brackets shall not be used. G. Hanger-Rod Attachments: Unless otherwise indicated, install the following types: 1. 2. H. Steel Turnbuckles (MSS Type 13): For adjustment up to 6 inches (150 mm) for heavy loads. Malleable-Iron Sockets (MSS Type 16): For attaching hanger rods to various types of building attachments. Building Attachments: Unless otherwise indicated, install the following types: 1. Steel or Malleable Concrete Inserts (MSS Type 18): For upper attachment to suspend pipe hangers from concrete ceiling. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230529- 4 Hangers and Supports for HVAC Equipment June 30, 2010 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. I. Side-Beam Brackets (MSS Type 34): For sides of steel or wooden beams. Plate Lugs (MSS Type 57): For attaching to steel beams if flexibility at beam is required. Horizontal Travelers (MSS Type 58): For supporting piping systems subject to linear horizontal movement where headroom is limited. Spring Hangers and Supports: Unless otherwise indicated, install the following types: 1. 2. 3. J. Top-Beam C-Clamps (MSS Type 19): For use under roof installations with barjoist construction to attach to top flange of structural shape. Side-Beam or Channel Clamps (MSS Type 20): For attaching to bottom flange of beams, channels, or angles. Center-Beam Clamps (MSS Type 21): For attaching to center of bottom flange of beams. Welded Beam Attachments (MSS Type 22): For attaching to bottom of beams if loads are considerable and rod sizes are large. C-Clamps (MSS Type 23): For structural shapes. Top-Beam Clamps (MSS Type 25): For top of beams if hanger rod is required tangent to flange edge. Side-Beam Clamps (MSS Type 27): For bottom of steel I-beams. Steel-Beam Clamps with Eye Nuts (MSS Type 28): For attaching to bottom of steel I-beams for heavy loads. Linked-Steel Clamps with Eye Nuts (MSS Type 29): For attaching to bottom of steel I-beams for heavy loads, with link extensions. Malleable Beam Clamps with Extension Pieces (MSS Type 30): For attaching to structural steel. Welded-Steel Brackets: For support of pipes from below, or for suspending from above by using clip and rod. Use one of the following for indicated loads: a. Light (MSS Type 31): 750 lb (340 kg). b. Medium (MSS Type 32): 1500 lb (680 kg). c. Heavy (MSS Type 33): 3000 lb (1360 kg). Spring Cushions (MSS Type 48): For light loads if vertical movement does not exceed 1-1/4 inches (32 mm). Spring-Cushion Roll Hangers (MSS Type 49): For equipping Type 41 roll hanger with springs. Constant Supports: For critical piping stress and if necessary to avoid transfer of stress from one support to another support, critical terminal, or connected equipment. Include auxiliary stops for erection, hydrostatic test, and loadadjustment capability. These supports include the following types: a. Horizontal (MSS Type 54): Mounted horizontally. b. Vertical (MSS Type 55): Mounted vertically. c. Trapeze (MSS Type 56): Two vertical-type supports and one trapeze member. Comply with MSS SP-69 for trapeze pipe hanger selections and applications that are not specified in piping system Sections. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230529- 5 Hangers and Supports for HVAC Equipment June 30, 2010 K. Comply with MFMA-102 for metal framing system selections and applications that are not specified in piping system Sections. L. Use mechanical-expansion anchors instead of building attachments where required in concrete construction. 3.2 HANGER AND SUPPORT INSTALLATION A. Metal Framing System Installation: Arrange for grouping of parallel runs of piping and support together on field-assembled metal framing systems. B. Fastener System Installation: 1. 2. 3.3 Install powder-actuated fasteners for use in lightweight concrete or concrete slabs less than 4 inches (100 mm) thick in concrete after concrete is placed and completely cured. Use operators that are licensed by powder-actuated tool manufacturer. Install fasteners according to powder-actuated tool manufacturer's operating manual. Install mechanical-expansion anchors in concrete after concrete is placed and completely cured. Install fasteners according to manufacturer's written instructions. EQUIPMENT SUPPORTS A. Fabricate structural-steel stands to suspend equipment from structure overhead or to support equipment above floor. B. Grouting: Place grout under supports for equipment and make smooth bearing surface. C. Provide lateral bracing, to prevent swaying, for equipment supports. 3.4 METAL FABRICATIONS A. Cut, drill, and fit miscellaneous metal fabrications for trapeze pipe hangers and equipment supports. B. Fit exposed connections together to form hairline joints. Field weld connections that cannot be shop welded because of shipping size limitations. C. Field Welding: Comply with AWS D1.1 procedures for shielded metal arc welding, appearance and quality of welds, and methods used in correcting welding work, and with the following: 1. 2. 3. 4. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals. Obtain fusion without undercut or overlap. Remove welding flux immediately. Finish welds at exposed connections so no roughness shows after finishing and contours of welded surfaces match adjacent contours. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230529- 6 Hangers and Supports for HVAC Equipment June 30, 2010 3.5 ADJUSTING A. Hanger Adjustments: Adjust hangers to distribute loads equally on attachments and to achieve indicated slope of pipe. B. Trim excess length of continuous-thread hanger and support rods to 1-1/2 inches (40 mm). 3.6 PAINTING A. Touch Up: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces. 1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils (0.05 mm). B. Touch Up: Cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint on miscellaneous metal are specified in Division 09 painting Sections. C. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230529- 7 Hangers and Supports for HVAC Equipment June 30, 2010 SECTION 230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC EQUIPMENT PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. 3. 4. 5. 1.3 Restrained spring isolators. Elastomeric hangers. Spring hangers. Spring hangers with vertical-limit stops. Restraining braces and cables. DEFINITIONS A. IBC: International Building Code. B. ICC-ES: ICC-Evaluation Service. 1.4 PERFORMANCE REQUIREMENTS A. Seismic-Restraint Loading: 1. 2. Site Class as Defined in the IBC: D. Assigned Seismic Use Group Category as Defined in the IBC: II. a. b. c. 3. 4. 1.5 Component Importance Factor: 1.0. Component Response Modification Factor: 2.5. Component Amplification Factor: 1.0. Design Spectral Response Acceleration at Short Periods (0.2 Second): 0.367g. Design Spectral Response Acceleration at 1-Second Period: 0.114g. SUBMITTALS A. Product Data: For the following: 1. Include rated load, rated deflection, and overload capacity for each vibration isolation device. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 1 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 2. Illustrate and indicate style, material, strength, fastening provision, and finish for each type and size of seismic-restraint component used. a. b. 3. B. Tabulate types and sizes of seismic restraints, complete with report numbers and rated strength in tension and shear as evaluated by an agency acceptable to authorities having jurisdiction. Annotate to indicate application of each product submitted and compliance with requirements. Interlocking Snubbers: Include ratings for horizontal, vertical, and combined loads. Delegated-Design Submittal: For vibration isolation and seismic-restraint details indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 1. Design Calculations: Calculate static and dynamic loading due to equipment weight and operation, seismic forces required to select vibration isolators, seismic restraints, and for designing vibration isolation bases. a. 2. 3. 4. Coordinate design calculations with wind load calculations required for equipment mounted outdoors. Comply with requirements in other Division 22 Sections for equipment mounted outdoors. Riser Supports: Include riser diagrams and calculations showing anticipated expansion and contraction at each support point, initial and final loads on building structure, spring deflection changes, and seismic loads. Include certification that riser system has been examined for excessive stress and that none will exist. Vibration Isolation Base Details: Detail overall dimensions, including anchorages and attachments to structure and to supported equipment. Include auxiliary motor slides and rails, base weights, equipment static loads, power transmission, component misalignment, and cantilever loads. Seismic-Restraint Details: a. b. c. Design Analysis: To support selection and arrangement of seismic restraints. Include calculations of combined tensile and shear loads. Details: Indicate fabrication and arrangement. Detail attachments of restraints to the restrained items and to the structure. Show attachment locations, methods, and spacings. Identify components, list their strengths, and indicate directions and values of forces transmitted to the structure during seismic events. Indicate association with vibration isolation devices. Coordinate seismic-restraint and vibration isolation details with windrestraint details required for equipment mounted outdoors. Comply with requirements in other Division 22 Sections for equipment mounted outdoors. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 2 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 d. Preapproval and Evaluation Documentation: By an agency acceptable to authorities having jurisdiction, showing maximum ratings of restraint items and the basis for approval (tests or calculations). C. Coordination Drawings: Show coordination of seismic bracing for HVAC equipment with other systems and equipment in the vicinity, including other supports and seismic restraints. D. Welding certificates. E. Qualification Data: For professional engineer and testing agency. F. Field quality-control test reports. 1.6 QUALITY ASSURANCE A. Testing Agency Qualifications: An independent agency, with the experience and capability to conduct the testing indicated, that is a nationally recognized testing laboratory (NRTL) as defined by OSHA in 29 CFR 1910.7, and that is acceptable to authorities having jurisdiction. B. Comply with seismic-restraint requirements in the IBC unless requirements in this Section are more stringent. C. Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel." D. Seismic-restraint devices shall have horizontal and vertical load testing and analysis and shall bear anchorage preapproval OPA number from OSHPD, preapproval by ICC-ES, or preapproval by another agency acceptable to authorities having jurisdiction, showing maximum seismic-restraint ratings. Ratings based on independent testing are preferred to ratings based on calculations. If preapproved ratings are not available, submittals based on independent testing are preferred. Calculations (including combining shear and tensile loads) to support seismic-restraint designs must be signed and sealed by a qualified professional engineer. PART 2 PRODUCTS 2.1 VIBRATION ISOLATORS A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. Kinetics Noise Control. Mason Industries. Vibrex. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 3 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 B. General 1. 2. 3. C. Spring Hangers: Combination coil-spring and elastomeric-insert hanger with spring and insert in compression. 1. 2. 3. 4. 5. 6. 7. D. Provide vibration isolators in accordance with the load distribution to produce uniform minimum deflection as specified on the schedule. All static deflections stated are the minimum acceptable deflection for the vibration isolator under actual load as shown on the drawings. Isolators selected purely on the basis of rated deflection are not acceptable. Where static deflections are not specified, provide minimum 2 inches static deflection for rotating and reciprocating equipment. Where specific type of vibration isolation hardware equipment is not shown or specified, furnish isolators recommended by the isolation manufacturer compatible with equipment arrangements shown. Frame: Steel, fabricated for connection to threaded hanger rods and to allow for a maximum of 30 degrees of angular hanger-rod misalignment without binding or reducing isolation efficiency. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load. Minimum Additional Travel: 50 percent of the required deflection at rated load. Lateral Stiffness: More than 80 percent of rated vertical stiffness. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure. Elastomeric Element: Molded, oil-resistant rubber or neoprene. Steel-washerreinforced cup to support spring and bushing projecting through bottom of frame. Self-centering hanger rod cap to ensure concentricity between hanger rod and support spring coil. Flexible Duct Connections 1. 2. 3. 4. 5. Ductwork flexible connections shall be fabricated from flexible airtight-coated fabric. Connections shall be constructed from a UL listed fire retardant (25flame spread, 50 smoke developed rating) neoprene coated woven glass fiber fabric to NFPA 90A and shall withstand the temperatures and pressure involved (Ventfabrics, Durodyne or approved equal). Connectors shall include a companion flange. The connectors, between fan intake/discharge and ductwork, overall width shall not be less than 3 inches long nor more than 6 inches long. For ducts passing across building expansion joints or acoustical isolation joints the connectors overall width shall not be less than 6 inches long nor more than 10 inches long. Allow at least 1 inch slack in these connections to insure that no vibration is transmitted from fan to ductwork. Flex connector shall not be drawn into the duct/air stream. Where duct transition occurs from larger to smaller duct size at connection to the equipment, the flexible connector shall be sized and installed in the larger duct. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 4 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 6. 2.2 The fabric shall either be folded in with the metal or attached with metal collar frames at each end to prevent air leakage. SEISMIC-RESTRAINT DEVICES A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. 4. 5. 6. 7. 8. B. Amber/Booth Company, Inc. Cooper B-Line, Inc.; a division of Cooper Industries. Hilti, Inc. Kinetics Noise Control. Loos & Co.; Cableware Division. Mason Industries. TOLCO Incorporated; a brand of NIBCO INC. Unistrut; Tyco International, Ltd. General Requirements for Restraint Components: Rated strengths, features, and applications shall be as defined in reports by an agency acceptable to authorities having jurisdiction. 1. Structural Safety Factor: Allowable strength in tension, shear, and pullout force of components shall be at least four times the maximum seismic forces to which they will be subjected. C. Channel Support System: MFMA-3, shop- or field-fabricated support assembly made of slotted steel channels with accessories for attachment to braced component at one end and to building structure at the other end and other matching components and with corrosion-resistant coating; and rated in tension, compression, and torsion forces. D. Restraint Cables: ASTM A 603 galvanized-steel cables with end connections made of steel assemblies with thimbles, brackets, swivel, and bolts designed for restraining cable service; and with a minimum of two clamping bolts for cable engagement. E. Hanger Rod Stiffener: Steel tube or steel slotted-support-system sleeve with internally bolted connections to hanger rod. F. Bushing Assemblies for Wall-Mounted Equipment Anchorage: Assemblies of neoprene elements and steel sleeves designed for rigid equipment mountings, and matched to type and size of attachment devices used. G. Resilient Isolation Washers and Bushings: One-piece, molded, oil- and water-resistant neoprene, with a flat washer face. H. Mechanical Anchor Bolts: Drilled-in and stud-wedge or female-wedge type in zinccoated steel for interior applications and stainless steel for exterior applications. Select Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 5 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 anchor bolts with strength required for anchor and as tested according to ASTM E 488. Minimum length of eight times diameter. I. 2.3 Adhesive Anchor Bolts: Drilled-in and capsule anchor system containing polyvinyl or urethane methacrylate-based resin and accelerator, or injected polymer or hybrid mortar adhesive. Provide anchor bolts and hardware with zinc-coated steel for interior applications and stainless steel for exterior applications. Select anchor bolts with strength required for anchor and as tested according to ASTM E 488. FACTORY FINISHES A. Finish: Manufacturer's standard prime-coat finish ready for field painting. PART 3 EXECUTION 3.1 EXAMINATION A. Examine areas and equipment to receive vibration isolation and seismic[- and wind]control devices for compliance with requirements for installation tolerances and other conditions affecting performance. B. Examine roughing-in of reinforcement and cast-in-place anchors to verify actual locations before installation. C. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 APPLICATIONS A. Hanger Rod Stiffeners: Install hanger rod stiffeners where indicated or scheduled on Drawings to receive them and where required to prevent buckling of hanger rods due to seismic forces. B. Strength of Support and Seismic-Restraint Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static and seismic loads within specified loading limits. 3.3 VIBRATION-CONTROL AND SEISMIC-RESTRAINT DEVICE INSTALLATION A. General Requirements 1. 2. Vibration isolation manufacturer’s representative shall supervise and inspect all installed isolation hardware and generate a written punchlist for the Construction Manager, along with corrective measures required. Submit inspection report. The installation or use of vibration isolators must not cause any change in position of equipment, or ducts that result in stresses in any connections or misalignment of shafts or bearings. Equipment shall be maintained in a rigid position during installation. The load shall not be trans-ferred to the isolators until the installation is complete and in operational condition. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 6 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 3. 4. 5. 6. 7. 8. 9. 10. B. Do not install any mechanical equipment, or ducts that makes rigid contact with the "building" unless it is approved in this specification or by the Engineer. "Building" includes, but is not limited to, slabs, beams, columns, walls, partitions, ceilings, studs, ceiling framing, and suspension systems. Prior to installation, the Contractor shall bring to the Owner’s Representative's attention any conflicts between trades that will result in unavoidable rigid contact of equipment, or ducts with the build¬ing. Corrective work after installation, necessitated by unresolved conflicts before installa¬tion, shall be at the Contractor's expense. The Contractor shall obtain written instructions from the vibration isolation manufacturer as to the proper selection, installation, and adjustment of all vibration isolation devices. No equipment unit shall bear directly on vibration isolators unless its own frame is suitably rigid to span between isolators and such direct support is approved by the equipment manufacturer. This provision shall apply whether or not a base frame is called for on the schedule. In the case that a base frame is required for the unit because of the equipment manufacturer's requirements and is not specifically called for on the equipment schedule, a base frame recommended by the equipment manufac¬turer shall be provided at no additional expense. Unless otherwise indicated, there is to be a minimum operating clearance of 1" between inertia bases or steel frame bases and the floor beneath the equipment. Position isolator mounting brackets and adjust isolators so that the required clearance is maintained. The clearance space shall be cleaned thoroughly by the Contractor to ensure that no construction debris has been left to short-circuit or restrict the proper operation of the vibration isolation system. Provide a minimum of 1" clearance between the building structure (walls, floors, and ceilings) and vibration isolated supports, ducts, and equipment. Ceiling-suspended equipment shall be supported from the building structure, such as trusses, girders, beams, or joists. If necessary, provide heavy extra substructure between the building's existing heavy structure in order to support vibration-isolated equipment. Do not suspend equipment from roof decks or floors without approval. Connect vibration isolation hangers directly to, or as close as possible to, structure that is stiff. Hanger housings should be free to rotate a full 360 degrees about the rod axis without contacting any object. Any bracing or supports for mechanical ductwork, and equipment shall not bridge or reduce the effectiveness of vibration isolators. Vibration Isolated-Equipment 1. 2. 3. 4. Locations of all vibration isolation equipment shall be selected for ease of inspection and adjustment as well as for proper operation. Installation of vibration isolation equipment shall be in accordance with the manufacturer's written instructions. Unless otherwise noted, mount motors on rigid base common with equipment or supported from equipment frame. Fasten all vibration isolators to the structure, not to floor diaphragms or lightweight components. Use bolts where holes are provided in the mounting flanges; otherwise, adhere using structural adhesive. Where mounting flanges Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 7 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 5. 6. 7. 8. 9. 10. 11. 12. C. are steel, use neoprene grommets and washers under anchor bolts. Where vibrating elements are to be fastened to structural elements provide connection details for review. All vibration-isolated equipment shall be connected to the adjacent ductwork via a flexible connection positioned to avoid a direct connection between equipment and mounting surface. Do not use vibration isolation components to straighten or connect misaligned sections of ductwork. Inspect all vibration-isolated equipment, coordinate the work of all involved trades, and verify that vibration isolators are not short-circuited by drain lines, conduits, control tubing, duct connections, etc. Adjust all leveling bolts and hanger rod bolts so that the isolated equipment is level and in proper alignment with connecting ducts. Hanger rods shall be aligned and free of contact with hanger box. Align spring isolation hanger rods to clear the hanger box under all operating conditions. Level vibration isolated equipment under rated design operating conditions while maintaining the isolation criteria. Isolators shall be plumb and aligned to preclude misalignment or undesired contact during operation. Separate snubbers shall be provided for all floor-mounted equipment on opentype (un-restrained) spring mounts. Provide a minimum of four snubbers at each item of equipment. Snubbers shall not be in contact during normal equipment operation. Number, size, and method of installation shall be as recommended by the isolator supplier. Flexible Duct Connections 1. 2. 3. 4. 5. 6. 7. Flexible duct connections shall be installed at all fan unit intakes, fan unit discharges, and wherever else shown on the drawings or elsewhere specified. If used at axial flow fan discharge or intake, flexible connector shall be placed after transition ducts. Flexible duct connections shall be installed wherever ducts pass across an Acoustical Isolation Joint (AIJ) between isolated and non-isolated structures, or between independently isolated structures. The connectors, between fan intake/discharge and ductwork, overall width shall not be less than 3 inches long nor more than 6 inches long. Where duct crossing building expansion joints, the connectors overall width shall not be less than 6 inches long nor more than 10 inches long. Allow at least 1 inch slack in these connections to insure that no vibration is transmitted from fan to ductwork. Install flexible connections in ducts that cross structural expansion joints. Where duct transition occurs from larger to smaller duct size at connection to the equipment, the flexible connector shall be sized and installed in the larger duct. The fabric shall either be folded in with the metal or attached with metal collar frames at each end to prevent air leakage Sheet metal ducts or plenum openings shall be squarely aligned with the fan discharge, fan intake, or adjacent duct section prior to installation of the flexible connection so that the clear separation is not greater than 3" and equal all the way Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 8 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 8. around the perimeter. Flexible duct connections shall not be installed until this provision is met. Allow at least 1 inch slack in connections. Secure fabric connectors tightly to fans, casings and ducts as follows: a. b. D. Secure round connectors with No. 12 US gage by 1 inch wide galvanized steel draw bands. Secure bands with bolts and nuts or use companion flanges. Secure rectangular connectors with 1 inch by 1/8-inch thick flat galvanized steel bars, with screws or bolts on 8 inch centers maximum, or with sheet metal slip joints. Tightly crimp fabric into sheet metal joint and secure complete joint with sheet metal screws on 6-inch centers maximum. Services Penetrations (Mechanical, Plumbing) 1. Ductwork: Where each duct penetrates acoustical rated partitions (designated on architectural drawings) and mechanical room wall and slab, create an acoustic seal around the ducts described herein and shown on the mechanical drawings. If the gap between the duct and the structure exceeds 1 inch, pack the gap with fiberglass and cover the entire joint with an 18 gauge metal angle or 5/8 inch gypsum board cover plate. Fully bed the angle or cover plate in non-hardening acoustical sealant. If the gap between the duct and the structure is less than 1/2 inch, pack the gap with fiberglass and sealed with non-hardening acoustical sealant backed by foam rod. E. Isolation of Fractional Horsepower Equipment: Isolate all fractional horsepower fans, pumps, and equipment which are mounted on or suspended from floors that are not ongrade with neoprene-in-shear isolators as specified except where such isolators are furnished as an integral part of the machine. F. Electrical Connections to Resiliently Mounted Equipment: Make electrical connections to equipment which is supported or suspended by vibration isolators with long lengths of flexible steel conduit or flexible armored cable. Locate these flexible connections so as to prevent rigid connections between the resiliently mounted equipment and the building structure. G. Equipment Restraints: 1. 2. 3. H. Install seismic snubbers on HVAC equipment mounted on vibration isolators. Locate snubbers as close as possible to vibration isolators and bolt to equipment base and supporting structure. Install resilient bolt isolation washers on equipment anchor bolts where clearance between anchor and adjacent surface exceeds 0.125 inch. Install seismic-restraint devices using methods approved by an agency acceptable to authorities having jurisdiction providing required submittals for component. Install cables so they do not bend across edges of adjacent equipment or building structure. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 9 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 I. Install seismic-restraint devices using methods approved by an agency acceptable to authorities having jurisdiction providing required submittals for component. J. Install bushing assemblies for anchor bolts for floor-mounted equipment, arranged to provide resilient media between anchor bolt and mounting hole in concrete base. K. Install bushing assemblies for mounting bolts for wall-mounted equipment, arranged to provide resilient media where equipment or equipment-mounting channels are attached to wall. L. Attachment to Structure: If specific attachment is not indicated, anchor bracing to structure at flanges of beams, at upper truss chords of bar joists, or at concrete members. M. Drilled-in Anchors: 1. 2. 3. 4. 5. 6. 3.4 Identify position of reinforcing steel and other embedded items prior to drilling holes for anchors. Do not damage existing reinforcing or embedded items during coring or drilling. Notify the structural engineer if reinforcing steel or other embedded items are encountered during drilling. Locate and avoid prestressed tendons, electrical and telecommunications conduit, and gas lines. Do not drill holes in concrete or masonry until concrete, mortar, or grout has achieved full design strength. Wedge Anchors: Protect threads from damage during anchor installation. Heavy-duty sleeve anchors shall be installed with sleeve fully engaged in the structural element to which anchor is to be fastened. Adhesive Anchors: Clean holes to remove loose material and drilling dust prior to installation of adhesive. Place adhesive in holes proceeding from the bottom of the hole and progressing toward the surface in such a manner as to avoid introduction of air pockets in the adhesive. Set anchors to manufacturer's recommended torque, using a torque wrench. Install zinc-coated steel anchors for interior and stainless-steel anchors for exterior applications. FIELD QUALITY CONTROL A. Testing Agency: Engage a qualified testing agency to perform tests and inspections. B. Tests and Inspections: 1. 2. 3. Provide evidence of recent calibration of test equipment by a testing agency acceptable to authorities having jurisdiction. Schedule test with Owner, through Architect, before connecting anchorage device to restrained component (unless postconnection testing has been approved), and with at least seven days' advance notice. Obtain Architect's approval before transmitting test loads to structure. Provide temporary load-spreading members. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 10 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 4. 5. 6. 7. 8. 9. Test at least four of each type and size of installed anchors and fasteners selected by Architect. Test to 90 percent of rated proof load of device. Measure isolator restraint clearance. Measure isolator deflection. Verify snubber minimum clearances. If a device fails test, modify all installations of same type and retest until satisfactory results are achieved. C. Remove and replace malfunctioning units and retest as specified above. D. Prepare test and inspection reports. 3.5 ADJUSTING A. Adjust limit stops on restrained spring isolators to mount equipment at normal operating height. After equipment installation is complete, adjust limit stops so they are out of contact during normal operation. B. Adjust active height of spring isolators. C. Adjust restraints to permit free movement of equipment within normal mode of operation. 3.6 VIBRATION ISOLATOR SCHEDULE A. Equipment and Ductwork Equipment Isolator type Deflection Suspended Fans Ductwork: Isolate all ductwork within 50 feet of fans and air handlers or within the mechanical rooms, whichever is greater. Spring Hangars Spring Hangars 2” 0.25” Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230548- 11 Vibration and Seismic Controls for HVAC Equipment June 30, 2010 SECTION 230553 IDENTIFICATION FOR HVAC EQUIPMENT PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. Section Includes: 1. 2. 3. 4. 5. 6. 1.3 Equipment labels. Warning signs and labels. Duct labels. Stencils. Valve tags. Warning tags. SUBMITTALS A. Product Data: For each type of product indicated. B. Samples: For color, letter style, and graphic representation required for each identification material and device. C. Equipment Label Schedule: Include a listing of all equipment to be labeled with the proposed content for each label. D. Valve numbering scheme. 1.4 COORDINATION A. Coordinate installation of identifying devices with completion of covering and painting of surfaces where devices are to be applied. B. Coordinate installation of identifying devices with locations of access panels and doors. C. Install identifying devices before installing acoustical ceilings and similar concealment. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230553- 1 Identification for HVAC Equipment June 30, 2010 PART 2 PRODUCTS 2.1 EQUIPMENT LABELS A. Adhesive backed plastic tape: 1. 2. 3. Small labels: adhesive backed plastic tape with embossed letters in contrasting colors. Tape shall be 3/8” wide. Large labels: adhesive backed plastic tape with embossed letters in contrasting colors. Tape shall be 3/4” wide. Make: Seton Name Plate Company. B. Label Content: Include equipment's Drawing designation or unique equipment number, Drawing numbers where equipment is indicated (plans, details, and schedules), plus the Specification Section number and title where equipment is specified. C. Equipment Label Schedule: For each item of equipment to be labeled, on 8-1/2-by-11inch (A4) bond paper. Tabulate equipment identification number and identify Drawing numbers where equipment is indicated (plans, details, and schedules), plus the Specification Section number and title where equipment is specified. Equipment schedule shall be included in operation and maintenance data. 2.2 WARNING SIGNS AND LABELS A. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical engraving, 1/16 inch (1.6 mm) thick, and having predrilled holes for attachment hardware. B. Letter Color: White. C. Background Color: Red. D. Maximum Temperature: Able to withstand temperatures up to 200 deg F (93 deg C). E. Minimum Label Size: Length and width vary for required label content, but not less than 2-1/2 by 3/4 inch (64 by 19 mm). F. Minimum Letter Size: 1/4 inch (6.4 mm) for name of units if viewing distance is less than 24 inches (600 mm), 1/2 inch (13 mm) for viewing distances up to 72 inches (1830 mm), and proportionately larger lettering for greater viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal lettering. G. Fasteners: Stainless-steel rivets or self-tapping screws. H. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate. I. Label Content: Include caution and warning information, plus emergency notification instructions. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230553- 2 Identification for HVAC Equipment June 30, 2010 2.3 DUCT LABELS A. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical engraving, 1/16 inch (1.6 mm) thick, and having predrilled holes for attachment hardware. B. Maximum Temperature: Able to withstand temperatures up to 160 deg F (71 deg C). C. Minimum Label Size: Length and width vary for required label content, but not less than 2-1/2 by 3/4 inch (64 by 19 mm). D. Minimum Letter Size: 1/4 inch (6.4 mm) for name of units if viewing distance is less than 24 inches (600 mm), 1/2 inch (13 mm) for viewing distances up to 72 inches (1830 mm), and proportionately larger lettering for greater viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal lettering. E. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate. F. Duct Label Contents: Include identification of duct service using same designations or abbreviations as used on Drawings, duct size, and an arrow indicating flow direction. 1. 2. 2.4 Flow-Direction Arrows: Integral with duct system service lettering to accommodate both directions or as separate unit on each duct label to indicate flow direction. Lettering Size: At least 1-1/2 inches (38 mm) high. STENCILS A. Stencils: Prepared with letter sizes according to ASME A13.1; minimum letter height of 1-1/4 inches (32 mm) for ducts; and minimum letter height of 3/4 inch (19 mm) for access panel and door labels, equipment labels, and similar operational instructions. 1. 2. 3. 2.5 Stencil Material: Fiberboard. Stencil Paint: Exterior, gloss, acrylic enamel black unless otherwise indicated. Paint may be in pressurized spray-can form. Identification Paint: Exterior, acrylic enamel in colors according to ASME A13.1 unless otherwise indicated. WARNING TAGS A. Warning Tags: Preprinted or partially preprinted, accident-prevention tags, of plasticized card stock with matte finish suitable for writing. 1. 2. 3. 4. Size: Approximately 4 by 7 inches (100 by 178 mm). Fasteners: Reinforced grommet and wire or string. Nomenclature: Large-size primary caption such as "DANGER," "CAUTION," or "DO NOT OPERATE." Color: Yellow background with black lettering. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230553- 3 Identification for HVAC Equipment June 30, 2010 PART 3 EXECUTION 3.1 PREPARATION A. 3.2 Clean equipment surfaces of substances that could impair bond of identification devices, including dirt, oil, grease, release agents, and incompatible primers, paints, and encapsulants. EQUIPMENT LABEL INSTALLATION A. Install or permanently fasten labels on each scheduled item of mechanical equipment. B. Locate equipment labels where accessible and visible. 3.3 DUCT LABEL INSTALLATION A. Install self-adhesive duct labels with permanent adhesive on air ducts in the following color codes: 1. White lettering with green background: a. 2. White lettering with blue background: a. 3. B. 3.4 Outside Air Intake Black lettering with yellow background: a. b. c. 4. Supply Air Return Air Exhaust Air Relief Air ASME A13.1 Colors and Designs: For hazardous material exhaust. Locate labels near points where ducts enter into concealed spaces and at maximum intervals of 30 feet (9 m) in each space where ducts are exposed or concealed by removable ceiling system. WARNING-TAG INSTALLATION A. Write required message on, and attach warning tags to, equipment and other items where required. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230553- 4 Identification for HVAC Equipment June 30, 2010 SECTION 230593 TESTING, ADJUSTING, AND BALANCING PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. Provide all labor, materials, tools and equipment, man-lifts, incidentals and services to carry out the work of this section. This Section includes TAB to produce design objectives for the following: 1. Air Systems: a. b. 2. 3. 4. 5. 6. 7. 8. 1.3 Constant-volume air systems. All Miscellaneous air moving devices. HVAC equipment. Space pressurization testing and adjusting. Vibration measuring. Sound level measuring. Indoor-air quality measuring. Verifying that automatic control devices are functioning properly. Reporting results of activities and procedures specified in this Section. DEFINITIONS A. Adjust: To regulate fluid flow rate and air patterns at the terminal equipment, such as to reduce fan speed or adjust a damper. B. Balance: To proportion flows within the distribution system, including submains, branches, and terminals, according to indicated quantities. C. Barrier or Boundary: Construction, either vertical or horizontal, such as walls, floors, and ceilings that are designed and constructed to restrict the movement of airflow, smoke, odors, and other pollutants. D. Draft: A current of air, when referring to localized effect caused by one or more factors of high air velocity, low ambient temperature, or direction of airflow, whereby more heat is withdrawn from a person's skin than is normally dissipated. E. NC: Noise criteria. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 1 Testing, Adjusting, and Balancing June 25, 2010 F. Procedure: An approach to and execution of a sequence of work operations to yield repeatable results. G. RC: Room criteria. H. Report Forms: Test data sheets for recording test data in logical order. I. Smoke-Extract System: A system that uses fans to exhaust smoke from the building with make-up air by infiltration through dedicated openings or fan powered. J. Smoke-Extract Zone: A space within the building that is part of a zoned smoke-purge system. K. Static Head: The pressure due to the weight of the fluid above the point of measurement. In a closed system, static head is equal on both sides of the pump. L. Suction Head: The height of fluid surface above the centerline of the pump on the suction side. M. System Effect: A phenomenon that can create undesired or unpredicted conditions that cause reduced capacities in all or part of a system. N. System Effect Factors: Allowances used to calculate a reduction of the performance ratings of a fan when installed under conditions different from those presented when the fan was performance tested. O. TAB: Testing, adjusting, and balancing. P. Terminal: A point where the controlled medium, such as fluid or energy, enters or leaves the distribution system. Q. Test: A procedure to determine correct operation and quantitative performance of systems or equipment. R. Testing, Adjusting, and Balancing (TAB) Firm: The entity responsible for performing and reporting TAB procedures. 1.4 SUBMITTALS A. Qualification Data: Within 30 days from Contractor's Notice to Proceed, submit 6 copies of evidence that TAB firm and this Project's TAB team members meet the qualifications specified in "Quality Assurance" Article. B. Contract Documents Examination Report: Within 60 days from Contractor's Notice to Proceed, submit 6 copies of the Contract Documents review report as specified in Part 3. C. Strategies and Procedures Plan: Within 90 days from Contractor's Notice to Proceed, submit 6 copies of TAB strategies and step-by-step procedures as specified in Part 3 Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 2 Testing, Adjusting, and Balancing June 25, 2010 "Preparation". Include a complete (all design data filled in) set of report forms intended for use on this Project. Submit plan drawings of the systems keying individual devices to be balanced to the forms. D. Certified TAB Reports: Submit two copies of final reports prepared, as specified in this Section, on approved forms certified by TAB firm. Submit plan drawings of the systems keying individual devices balanced to the forms. E. Instruments: A complete list of instruments proposed to be used, organized in appropriate categories, with data sheets for each. Show: 1. 2. 3. 4. Manufacturer, model and serial number. Description and use when needed to further identify the instrument. Size or capacity range. Latest calibration date and certificates of calibration. F. Reports on “Examinations” specified in Part 3 of this Section. G. Warranties specified in this Section. 1.5 QUALITY ASSURANCE A. Qualifications: Engage a TAB firm certified by either AABC or NEBB. TAB Technicians shall have a minimum of 2 years experience and shall be certified by either the AABC or NEBB. All work shall be carried out under the supervision of the approved TAB technicians. The TAB firm shall submit certification of their current membership of either NEBB or AABC. B. TAB Conference: Meet with Owner's and Architect's representatives on approval of TAB strategies and procedures plan to develop a mutual understanding of the details. Ensure the participation of TAB team members, equipment manufacturers' authorized service representatives, HVAC controls installers, and other support personnel. Provide seven days advance notice of scheduled meeting time and location. 1. Agenda Items: Include at least the following. a. b. c. d. e. f. Submittal distribution requirements. The Contract Documents examination report. TAB plan. Work schedule and Project-site access requirements. Coordination and cooperation of trades and subcontractors. Coordination of documentation and communication flow. C. TAB Report Forms: Use standard forms from NEBB's "Procedural Standards for Testing, Adjusting, and Balancing of Environmental Systems", or similar by AABC. D. Certification of TAB Reports: Certify TAB field data reports. This certification includes the following. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 3 Testing, Adjusting, and Balancing June 25, 2010 1. 2. 3. E. Instrumentation Type, Quantity, and Accuracy: As described in NEBB's "Procedural Standards for Testing, Adjusting, and Balancing of Environmental Systems," Section II, "Required Instrumentation for NEBB Certification", or similar by AABC. 1. F. Keep an updated record of instrument calibration that indicates date of calibration and the name of party performing instrument calibration. Reference Standards: 1. 2. 3. 4. 1.6 Review field data reports to validate accuracy of data and to prepare certified TAB reports. Certify that TAB team complied with approved TAB plan and the procedures specified and referenced in this Specification. The TAB Contractor shall provide a NEBB or AABC Certificate of Conformance Certification (issued by the NEBB or AABC national office) for all work specified to confirm that the work has been carried out in accordance with the applicable NEBB or AABC Standards and Procedures, and the provisions of the NEBB or AABC Quality Assurance Conformance Certification Rules of Procedures. General mechanical systems: Comply with applicable procedures and standards of “National Standards for Field Measurements and Instrumentation, Total System Balance” by the Associated Air Balance Council (AABC). NEBB – National Environmental Balancing Bureau SMACNA – Sheet Metal and Air Conditioning Contractors National Association ASHRAE – Handbook of Fundamentals PROJECT CONDITIONS A. Partial Owner Occupancy: Owner may occupy completed areas of building before Substantial Completion. Cooperate with Owner during TAB operations to minimize conflicts with Owner's operations. B. System Readiness 1. 2. 3. 4. The building envelope must be complete. All windows, doors, insulation, internal sheet finishes (such as gypsum wall board), cladding curtain walling, etc., must be installed so that the full specified performance of the envelope is achieved. The specified system being tested and balanced must be complete. Balancing of partially completed systems will not be acceptable. Sub-systems may be tested and balanced separately. A mechanical sub-system is a fan together with its associated ductwork, terminal units, dampers, grilles and diffusers. Fans that operate together, such as ventilation supply and exhaust fans serving common area shall be tested together as a common mechanical sub system. The system must be running fault free. Pressure testing and leak testing must be satisfactorily complete. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 4 Testing, Adjusting, and Balancing June 25, 2010 1.7 COORDINATION A. Coordinate the efforts of factory-authorized service representatives for systems and equipment, HVAC controls installers, and other mechanics to operate HVAC systems and equipment to support and assist TAB activities. B. Coordinate with the Construction Manager to produce a complete schedule for the TAB work including identifying all other aspects of the construction work by other trades upon which successful completion of the TAB work depends. All such dependencies shall be identified to allow proper sequencing of the required work. This schedule shall be prepared using the same computer software as the construction manager’s schedule such that it can be added to the construction manager’s schedule. Schedule shall be kept up-to-date. The schedule shall show, as a minimum: 1. 2. 3. 4. 5. 6. 7. 8. Itemize all systems to be made operational, tested and balanced. Identify the dates that system construction, cleaning, pressure testing and pretesting will be completed.) Identify interdependencies between systems that impact the TAB work. (For example, the heating system cannot be considered complete until the associated electrical power system and controls system are complete. Each trade affected by and required for the TAB will be identified to ensure that the adequate time for their work is scheduled. Identify the beginning and end of the TAB work for each building system. All submittal dates for first, second, etc., submittals shall be clearly identified on the schedule. Required review and re-submittal dates shall also be included. Requirements for tests and inspections required by AHJ and schedule for inspections completion, submission, and approval. Include dates for training of Owner’s staff. C. Notice: Provide seven days' advance notice for each test. Include scheduled test dates and times. D. Perform TAB after leakage and pressure tests on air systems have been satisfactorily completed. E. Coordinate with the work of Section 15900 and 15901 to determine positions of all dampers and control valves in accordance with the outlined sequences of operation. F. In the event the TAB Contractor fails to coordinate with any party and costs are incurred for testing or retesting by any party as a result of this failure to coordinate, then the TAB Contractor shall be responsible for these costs. G. TAB Meetings 1. The TAB Contractor’s Project Manager shall attend regular commissioning meetings as required by the Construction Manager. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 5 Testing, Adjusting, and Balancing June 25, 2010 1.8 WARRANTY A. Special Guarantee: Provide a guarantee on NEBB forms stating that NEBB will assist in completing requirements of the Contract Documents if TAB firm fails to comply with the Contract Documents. Guarantee shall include the following provisions: 1. 2. B. During the warranty period of one year following substantial completion of TAB, seasonal testing and other deferred testing required shall be completed. The TAB firm shall coordinate this activity with the Owner and CM. 1. 2. 3. C. The certified TAB firm has tested and balanced systems according to the Contract Documents. Systems are balanced to optimum performance capabilities within design limits. Approximately six months after completion of the TAB, the TAB firm shall return to the project site for Seasonal Testing and carryout a 72-hour run test of the complete building systems as described above. All sensors, devices, etc., shall be trended for this period and presented in graphical format at a useful resolution. The TAB firm shall make any adjustments necessary to the system to ensure all systems and systems components are operating in a correct manner and that design conditions are being maintained within the building without hunting. See also paragraph 3.4.F. of this Section. In addition the TAB firm will return to the project approximately 10 months into the warranty period. During this visit(s) the TAB firm will review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal commissioning. The TAB firm will also interview facility staff and identify problems or concerns they have operating the building as originally intended. The TAB firm will make suggestions for improvements and will record these changes in the O&M manuals. Deferred Testing: any system or item that cannot be properly tested during the construction period, due to, for example, weather conditions, shall be tested and balanced as far as possible. The TAB process shall be completed when conditions are favorable. Final Acceptance 1. When all TAB work has been carried out, the building systems will be run in full automatic mode for a minimum period of 72 hours. All FMS sensors, devices, etc., shall be trend logged every minute and presented in a graphical format at a useful resolution. Final acceptance of the building systems will be contingent upon the system maintaining conditions within design tolerances without hunting for all of the 72 hours. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 6 Testing, Adjusting, and Balancing June 25, 2010 PART 2 PRODUCTS (NOT APPLICABLE) PART 3 EXECUTION 3.1 EXAMINATION A. Examine the Contract Documents, and any subsequent revisions to these, to become familiar with Project requirements and to discover conditions in systems' designs that may preclude proper TAB of systems and equipment. 1. 2. 3. Contract Documents are defined in the General and Supplementary Conditions of Contract. Verify that the necessary TAB devices, such as test ports, gage cocks, thermometer wells, flow-control devices, balancing valves and fittings, access doors and panels, manual volume dampers, are required by the Contract Documents. Verify that quantities and locations of these balancing and for efficient system and equipment operation. The lead TAB technician shall visit the job bi-weekly during construction to review the installation. Submit written report with suggestions for work to be performed or devices added to allow for proper balancing. This technician shall verify that Work, fittings, dampers, balancing devices, etc. are properly fabricated and installed as specified or shown and that proper balancing can be done. B. Examine approved submittal data of HVAC systems and equipment and use in TAB process. C. Examine Project Record Documents described in Division 1 Section "Project Record Documents" to ensure all TAB devices and final approved values are recorded. D. Examine equipment performance data including fan and pump curves. Relate performance data to Project conditions and requirements, including system effects that can create undesired or unpredicted conditions that cause reduced capacities in all or part of a system. Calculate system effect factors to reduce performance ratings of HVAC equipment when installed under conditions different from those presented when the equipment was performance tested at the factory. To calculate system effects for air systems, use tables and charts found in AMCA 201, "Fans and Systems," Sections 7 through 10; or in SMACNA's "HVAC Systems--Duct Design," Sections 5 and 6. Compare this data with the design data and installed conditions. E. Examine system and equipment installations to verify that they are complete and that testing, flushing, cleaning, and adjusting specified in individual Sections have been performed. F. Examine system and equipment test reports. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 7 Testing, Adjusting, and Balancing June 25, 2010 G. Examine HVAC system and equipment installations to verify that indicated balancing devices, such as test ports, gage cocks, thermometer wells, flow-control devices, balancing valves and fittings, and manual volume dampers, are properly installed, and that their locations are accessible and appropriate for effective balancing and for efficient system and equipment operation. Perform this inspection as often as necessary to ensure all work is inspected prior to closing-in or concealment. H. Examine systems for functional deficiencies that cannot be corrected by adjusting and balancing. I. Examine HVAC equipment to ensure that clean filters have been installed, coils, fans, dampers, plenums, ducts, etc. are clean, bearings are greased, belts are aligned and tight, and equipment with functioning controls is ready for operation. J. Examine terminal units, such as variable-air-volume boxes, to verify that they are accessible and their controls are connected and functioning. K. Examine plenum ceilings used for supply air to verify that they are airtight. Verify that pipe penetrations and other holes are sealed. L. Examine strainers for clean screens and proper perforations. M. Examine three-way valves for proper installation for their intended function of diverting or mixing fluid flows. N. Examine equipment for installation and for properly operating safety interlocks and controls. O. Examine automatic temperature system components to verify the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Dampers, valves, and other controlled devices are operated by the intended controller. Dampers and valves are in the position indicated by the controller. Integrity of valves and dampers for free and full operation and for tightness of fully closed and fully open positions. This includes all motorized dampers and valves and variable-air-volume terminals. Automatic modulating and shutoff valves, including two-way valves and threeway mixing and diverting valves, are properly connected. Thermostats and humidistats and sensors are located to avoid adverse effects of sunlight, drafts, and cold walls. Sensors are located to sense only the intended conditions. Sequence of operation for control modes is according to the Contract Documents. Controller set points are set at indicated values. Interlocked systems are operating. Changeover from heating to cooling mode occurs according to indicated values. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 8 Testing, Adjusting, and Balancing June 25, 2010 P. 3.2 Report deficiencies discovered before and during performance of TAB procedures. Observe and record system reactions to changes in conditions. Record default set points if different from indicated values. PREPARATION A. Prepare a TAB plan that includes strategies and step-by-step procedures. B. Complete system readiness checks and prepare system readiness reports. Verify the following: 1. 2. 3. 4. 5. 6. 7. 3.3 Permanent electrical power wiring is complete. Automatic temperature-control systems are operational. Equipment and duct access doors are securely closed. Balance, smoke, and fire dampers are open. Isolating and balancing valves are open and control valves are operational. Ceilings are installed in critical areas where air-pattern adjustments are required and access to balancing devices is provided. Windows and doors can be closed so indicated conditions for system operations can be met. PRELIMINARY TESTING A. The Mechanical Contractor will carry out a series of preliminary tests prior to the commencement of the TAB work of this contract. The intent of these tests is to demonstrate that the equipment operates properly in all modes. The TAB Contractor shall review these test reports and shall record from these reports any data required to carry out the work of this contract. B. The Mechanical Contractor shall, as a minimum, carry out the tests, procedures and checks recommended by the equipment manufacturer and shall use the services of equipment manufacturer representatives to ensure the successful start-up and correct operation of all systems and equipment. C. The TAB Contractor shall witness the above work and submit a deficiency report for any incomplete work that will affect the work of this Contract. D. The TAB Contractor shall review and report on the following, as a minimum: 1. 2. 3. 4. E. Installation of equipment Installation of devices Completeness of the ductwork and pipework installation Installation of access doors or other access provisions for balancing devices, fire and smoke dampers The TAB Contractor shall issue reports weekly during the Mechanical Contractors preliminary testing process. Any major deficiencies shall be reported daily. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 9 Testing, Adjusting, and Balancing June 25, 2010 F. 3.4 The TAB Contractor shall witness the Mechanical Trade Contractors ductwork leakage and pipe pressure tests. GENERAL PROCEDURES FOR TESTING AND BALANCING A. Perform testing and balancing procedures on each system according to the procedures contained in NEBB’s “Procedural Standards for Testing, Adjusting and Balancing of Environmental Systems” and this Section. B. Cut insulation, ducts, pipes and equipment cabinets for installation for test probes to the minimum extent necessary to allow adequate performance of procedures. After testing and balancing, close probe holes to prevent leakage and patch insulation with new materials identical to those removed. Restore vapor barrier and finish according to insulation Specifications for this project. C. Mark equipment and balancing device settings with paint or other suitable, permanent identification material, including damper-control positions, valve position indicators, fan-speed-controllers, and similar controls and devices, to show final settings. D. Take readings as shown, specified and as required to demonstrate that all equipment terminal devices, controls, etc. are operating in accordance with scheduled or manufacturer’s published ratings. E. Make adjustments and/or corrections to equipment, air systems necessary for proper balancing. F. Perform capacity checks of heating systems during the balancing period and again during design condition the following winter. Perform capacity checks for cooling systems during the balancing period and again during design the following summer. G. Operating tests of heating and cooling apparatus, fans, and other equipment to be of not less than four hours duration, after stabilized operating conditions have been established. Capacities to be based on temperatures and air quantities measured during such tests. H. Take and report testing and balancing measurements in inch-pound (IP) units. I. The TAB Contractor shall confirm in the reports that deficiencies identified in Mechanical Services installation have been corrected prior to the commencement of the TAB work. J. The specified systems shall be reviewed and inspected for conformance to the design documents. Testing, adjusting and balancing on each system shall be performed. The accuracy of measurements shall be in accordance with AABC or NEBB Standards. See below for tolerances on measured quantities. K. Any deficiencies in the installation or performance of a system or component shall be reported in writing to both the Mechanical Trade Contractor and Consultant. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 10 Testing, Adjusting, and Balancing June 25, 2010 L. Should the results of balancing indicate that a mechanical system does not provide the design intent performance, then the Consultant, the Mechanical Contractor and the TAB Contractor shall review the results. The Consultant shall approve any corrections that are to be made by the Mechanical Contractor. M. Should the results of balancing indicate that particular equipment does not provide the design intent performance then the Mechanical Contractor shall repair or replace the equipment. The TAB Contractor shall retest the equipment. 3.5 GENERAL PROCEDURES FOR BALANCING AIR SYSTEMS A. Prepare test reports for both fans, ducts and outlets. Obtain manufacturer’s outlet factors and recommended testing procedures. Crosscheck the summation of required outlet volumes with required fan volumes. B. Prepare schematic diagrams of systems “as-built” duct layouts for use in recording measurements. Diagram shall show all equipment components and be cross-referenced to the TAB forms and reports. C. For variable air-volume systems, develop a plan to simulate diversity, where system capacity (fans) is less than the sum of the outlet volumes. D. Determine the best locations in main and branch ducts for accurate duct airflow measurements. E. Check airflow patterns from the outside-air louvers and dampers and the return-and exhaust-air dampers, through the supply-fan discharge and mixing dampers. F. Locate start-stop and disconnect switches, electrical interlocks, and motor starters. G. Verify that motor starters are equipped with properly sized thermal protection. H. Check dampers for proper position to achieve desired airflow path and proper operation. For automatic dampers, fan speeds, etc., work with controls contractor to establish and set required positions and values to maintain design airflow for different operating conditions specified. I. Check airflow blockages and resolve. J. Check condensate drains for proper connections and proper function. K. Check for proper sealing of air-handling unit components L. Adjust air quantities to following tolerance: 1. 2. 3. 4. Each outlet of 200 cfm or less: Minus 0 to plus 10 percent of design. All other outlets: Minus 0 to plus 5 percent. Each room with multiple outlets: Minus 0 to plus 5 percent. Each floor or major zone: Minus 0 to plus 5 percent. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 11 Testing, Adjusting, and Balancing June 25, 2010 5. 6. 7. 8. Fans: Minus 0 to plus 5 percent. Temperature readings: Within ½ degree F. Equipment Pressure drops readings: 0.10 inch W.G. Space pressure readings: 0.05 inch W.G. M. Final Measurements of Air Quantity: Make final measurement of air quantity, after the air terminal has been adjusted to provide the optimum air patterns of diffusion. Adjust all diffusers and registers to eliminate drafts in all areas and result in uniform distribution. N. Verify that ductwork, dampers, grilles, registers and diffusers have been installed per design. O. Balance air handling systems at minimum outdoor air quantities. On completion of balancing procedures, retest at maximum outdoor air quantities. P. Test and record motor voltage and amperage. Compare data with nameplate limits. Q. Perform pitot tube traverse at all main and branch ducts. Compare traverse total with measured outlet total to determine actual duct leakage. R. Test and adjust minimum outdoor and relief air volumes. S. Test and record entering and leaving air conditions for each heat transfer coil and device. Simulate conditions to achieve winter or summer design patterns. T. Test and record settings of motor thermal overload devices. Adjust settings where required. U. Verify air flow measurement at all airflow monitoring stations. Coordinate positioning of dampers with the FMS Trade Contractor and the air monitoring station manufacturer. V. Verify minimum outside air flow requirements. Coordinate damper position with the FMS Trade Contractor. W. Adjust duct distribution to obtain specified air quantities. At least one zone balancing damper shall be completely open. Multi diffuser/grille branch ducts shall have at least one volume damper completely open. 3.6 PROCEDURES FOR CONSTANT-VOLUME AIR SYSTEMS A. Adjust fans to deliver total indicated airflows within the maximum allowable fan speed listed by fan manufacturer. 1. Measure fan static pressures to determine actual static pressure as follows: a. Measure outlet static pressure as far downstream from the fan as practicable and upstream from restrictions in ducts such as elbows and transitions. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 12 Testing, Adjusting, and Balancing June 25, 2010 b. c. 2. Measure static pressure across each component that makes up an air-handling unit, rooftop unit, and other air-handling and -treating equipment. a. 3. 4. 5. 6. B. Measure inlet static pressure of single-inlet fans in the inlet duct as near the fan as possible, upstream from flexible connection and downstream from duct restrictions. Measure inlet static pressure of double-inlet fans through the wall of the plenum that houses the fan. Simulate dirty filter operation and record the point at which maintenance personnel must change filters Measure static pressures entering and leaving other devices, such as sound traps, under final balanced conditions to create a complete static pressure profile for the system. Compare design data with installed conditions to determine variations in design static pressures versus actual static pressures. Compare actual system effect factors with calculated system effect factors to identify where variations occur. Recommend corrective action to align design and actual conditions. Obtain approval from Engineer for adjustment of fan speed higher or lower than indicated speed. Make required adjustments to pulley sizes, motor sizes, and electrical connections to accommodate fan-speed changes. Provide sheaves and belts for a minimum of one change per fan. Do not make fan-speed adjustments that result in motor overload. Consult equipment manufacturers about fan-speed safety factors. Modulate dampers and measure fan-motor amperage to ensure that no overload will occur. Measure amperage in full cooling, full heating, economizer, and any other operating modes to determine the maximum required brake horsepower. Adjust volume dampers for main duct, submain ducts, and branch ducts to indicated airflows within specified tolerances. 1. 2. Where sufficient space in submain and branch ducts is unavailable for Pitot-tube traverse measurements, measure airflow at terminal outlets and inlets and calculate the total airflow for that zone. Remeasure each submain and branch duct after all have been adjusted. Continue to adjust and measure to indicated airflows within specified tolerances. C. Measure terminal outlets using a direct-reading hood or outlet manufacturer's written instructions and calculating factors. D. Adjust terminal outlets and inlets for each space to indicated airflows within specified tolerances of indicated values. Make adjustments using branch duct volume dampers rather than dampers at air terminals where relevant. 1. Adjust each outlet in same room or space to within specified tolerances of indicated quantities without generating noise levels above the limitations prescribed by the Contract Documents. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 13 Testing, Adjusting, and Balancing June 25, 2010 2. 3.7 Adjust patterns of adjustable outlets for proper distribution without drafts. PROCEDURES FOR TEMPERATURE MEASUREMENTS A. 3.8 During TAB, report the need for adjustment in temperature regulation within the automatic temperature-control system. PROCEDURES FOR OUTSIDE AIR VOLUME AND SPACE PRESSURIZATION MEASUREMENT AND ADJUSTMENTS A. General 1. Outside air is introduced to the building via the air handling units for 3 functions: a. b. c. 2. Air is removed from the building by: a. b. c. 3. B. Space pressurization Exhaust system make-up air Ventilation air for occupants Exfiltration due to over pressurization Return fans in air handling systems which spill some of this return air. Miscellaneous building exhaust systems including, but not limited to, bathroom exhaust, retail exhaust, combustion air, air craft loading walkway pressurization, etc. The building shall be positively pressurized at all times. Refer to building air balance information on the drawings. Test and adjust so that space pressurization is achieved in the following operating modes: 1. 2. 3. 4. 5. 6. Unoccupied with all exhaust systems off. Unoccupied with all fixed rate, 24/7 exhaust systems operating. Unoccupied with variable run-time exhaust systems operating, in addition to the systems in paragraph (2) above. Begin with none of these variable run-time systems operating, start one at a time and ensure positive pressurization is obtained and stability maintained before starting the next. Repeat test for shutdown of these systems, one at a time. Simulate building occupancy by adjusting the CO2 measured values to test that the ventilation air quantity control is correctly operational. Ensure system air balance maintains positive building pressurization under varying values of return air CO2 levels. Test for 3 different CO2 values. Where space pressure sensors and controls are provided ensure specified differential is achieved. Refer to Sequences of Operation in Section 15900 and confirm system operation complies. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 14 Testing, Adjusting, and Balancing June 25, 2010 C. Before testing for space pressurization, observe the space to verify the integrity of the space boundaries. Verify that windows and doors are closed and applicable safing, gaskets, and sealants are installed. Report deficiencies and postpone testing until after the reported deficiencies are corrected. D. Measure, adjust, and record the pressurization of each room and each zone by adjusting the supply, return, and exhaust airflows to achieve the indicated conditions: air flow is used as the design criteria for space pressurization, except where pressure differential control is specified. E. Record indicated conditions and corresponding initial and final measurements. Report deficiencies. 3.9 PROCEDURES FOR VIBRATION MEASUREMENTS A. Use a vibration meter meeting the following criteria: 1. 2. 3. 4. 5. B. Calibrate the vibration meter before each day of testing. 1. 2. C. Solid-state circuitry with a piezoelectric accelerometer. Velocity range of 0.1 to 10 inches per second. Displacement range of 1 to 100 mils. Frequency range of at least 0 to 1000 Hz. Capable of filtering unwanted frequencies. Use a calibrator provided with the vibration meter. Follow vibration meter and calibrator manufacturer's calibration procedures. Perform vibration measurements when other building and outdoor vibration sources are at a minimum level and will not influence measurements of equipment being tested. 1. 2. Turn off equipment in the building that might interfere with testing. Clear the space of people. D. Perform vibration measurements after air balancing and equipment testing is complete. E. Clean equipment surfaces in contact with the vibration transducer. F. Position the vibration transducer according to manufacturer's written instructions and to avoid interference with the operation of the equipment being tested. G. Measure and record vibration on rotating equipment over 3 hp. H. Measure and record equipment vibration, bearing vibration, equipment base vibration, and building structure vibration. Record velocity and displacement readings in the horizontal, vertical, and axial planes. 1. Fans Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 15 Testing, Adjusting, and Balancing June 25, 2010 a. b. c. d. e. f. Fan Bearing: Drive end and opposite end. Motor Bearing: Drive end and opposite end. Equipment Casing: Top and side. Equipment Base: Top and side. Building: Floor. Ductwork: To and from equipment after flexible connections. I. For equipment with vibration isolation, take floor measurements with the vibration isolation blocked solid to the floor and with the vibration isolation floating. Calculate and report the differences. J. Inspect, measure, and record vibration isolation: 1. 2. 3. 4. 5. 3.10 Verify that vibration isolation is installed in the required locations. Verify that installation is level and plumb. Verify that isolators are properly anchored. For spring isolators, measure the compressed spring height, the spring OD, and the travel-to-solid distance. Measure the operating clearance between each inertia base and the floor or concrete base below. Verify that there is unobstructed clearance between the bottom of the inertia base and the floor. PROCEDURES FOR SOUND-LEVEL MEASUREMENTS A. Perform sound-pressure-level measurements with a sound meter complying with IEC 651, Type 1 or 2, set to an “A” weighting and “slow” meter response. B. Calibrate sound meters before each day of testing. Use a calibrator provided with the sound meter complying with ANSI S1.40 and that has NIST certification. C. Use a microphone that is suitable for the type of sound levels measured. For areas where air velocities exceed 100 fpm, use a windscreen on the microphone. D. Perform sound-level testing after air balancing and equipment testing are complete. E. Close windows and doors to the space. F. Perform measurements when the space is not occupied and when the occupant noise level from other spaces in the building and outside are at a minimum. G. Clear the space of temporary sound sources so unrelated disturbances will not be measured. Position testing personnel during measurements to achieve a direct line-ofsight between the sound source and the sound-level meter. H. Take sound measurements at a height approximately 60 inches above the floor and at least 36 inches from a wall, column, and other large surface capable of altering the measurements. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 16 Testing, Adjusting, and Balancing June 25, 2010 I. Take sound measurements in dBA and in each of the 8 unweighted octave bands in the frequency range of 63 to 8000 Hz. J. Take sound measurements with the HVAC systems off to establish the background sound levels and take sound measurements with the HVAC systems operating. 1. K. 3.11 Calculate the difference between measurements. Apply a correction factor depending on the difference and adjust measurements. Perform sound testing for each occupied space. For each space tested, select a measurement location that has the greatest sound level. When testing multiple locations for each space type, select at least one location that is near and at least one location that is remote from the predominant sound source. PROCEDURES FOR INDOOR-AIR QUALITY MEASUREMENTS A. After air balancing is complete and with HVAC systems operating at indicated conditions, perform indoor-air quality testing. B. Observe and record the following conditions for each HVAC system: 1. 2. 3. C. Make measurements at multiple locations served by the system if required to satisfy the following: 1. D. At least one test location per fan system. Measure and record the following indoor conditions for each location specified two times at two-hour intervals, and in accordance with ASHRAE 113: 1. 2. 3. 4. 5. 6. 7. 3.12 The distance between the outside-air intake and the closest exhaust fan discharge, flue termination, or vent termination. Specified filters are installed. Check for leakage around filters. Insulation in contact with the supply, return, and outside air is dry and clean. Temperature. Relative humidity. Air velocity. Concentration of carbon dioxide (ppm). Concentration of carbon monoxide (ppm). Nitrogen oxides (ppm). Formaldehyde (ppm). FACILITY MANAGEMENT SYSTEM VERIFICATION A. Verify that controllers are correctly wired, calibrated and commissioned. B. Check transmitter and controller locations and note conditions that would adversely affect control functions. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 17 Testing, Adjusting, and Balancing June 25, 2010 C. Check the operation of limiting controllers (i.e., high- and low-temperature controllers). D. Check free travel and proper operation of control devices such as damper and valve operators. E. Check the sequence of operation of control devices in all modes of operation. Note device positions and correlate with airflow measurements. Note the speed of response to input changes. F. Check the interaction of electrically operated switch transducers. G. Check the interaction of interlock and lockout systems. H. Record voltages of power supply and controller output. Determine whether the system operates on a grounded or nongrounded power supply. I. Note operation of electric actuators using spring return for proper fail-safe operations. J. Upon completion of the Building Control System completely check out and field test hardware and software to assure that the complete system performs in accordance with the approved sequences of operation. Test all equipment and control functions for proper automatic and manual activation. Test each system and zone for proper operation through its complete heating and cooling cycles. K. Include the specific tests and control functions listed below: 1. 2. 3. 4. 5. 6. 7. 8. 9. 3.13 A. 3.14 A. Full point check. Smoke extract strategy. Manual activation of each fan and smoke and fire/smoke damper. System priorities and overrides. Trouble, monitoring and annunciation capability. Power resumption response. System failure response, including emergency power operation. All user notification messages. All controls loops shall be verified as operating in a stable manner with no hunting prior to the start of the commissioning process. TOLERANCES Set HVAC system airflow rates within the tolerances specified above. REPORTING Initial Construction-Phase Report: Based on examination of the Contract Documents as specified in "Examination" Article, prepare a report on the adequacy of design for systems' balancing devices. Recommend changes and additions to systems' balancing devices to facilitate proper performance measuring and balancing. Recommend changes and additions to HVAC systems and general construction to allow access for performance measuring and balancing devices. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 18 Testing, Adjusting, and Balancing June 25, 2010 B. 3.15 Status Reports: As Work progresses, prepare reports to describe completed procedures, procedures in progress, and scheduled procedures. Include a list of deficiencies and problems found in systems being tested and balanced. Prepare a separate report for each system and each building floor for systems serving multiple floors. FINAL REPORT A. General: Typewritten, or computer printout in letter-quality font, on standard bond paper, in three-ring binder, tabulated and divided into sections by tested and balanced systems. B. Include a certification sheet in front of binder signed and sealed by the certified testing and balancing engineer. 1. C. Final Report Contents: In addition to certified field report data, include the following: 1. 2. 3. 4. 5. D. Include a list of instruments used for procedures, along with proof of calibration. Pump curves with operating points. Fan curves with operating points. Manufacturers' test data. Field test reports prepared by system and equipment installers. Other information relative to equipment performance, but do not include Shop Drawings and Product Data. General Report Data: In addition to form titles and entries, include the following data in the final report, as applicable: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Title page. Name and address of TAB firm. Project name. Project location. Architect's name and address. Engineer's name and address. Contractor's name and address. Report date. Signature of TAB firm who certifies the report. Table of Contents with the total number of pages defined for each section of the report. Number each page in the report. Summary of contents including the following: a. b. c. 12. 13. Indicated versus final performance. Notable characteristics of systems. Description of system operation sequence if it varies from the Contract Documents. Nomenclature sheets for each item of equipment. Data for terminal units, including manufacturer, type size, and fittings. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 19 Testing, Adjusting, and Balancing June 25, 2010 14. 15. Notes to explain why certain final data in the body of reports varies from indicated values. Test conditions for fans and pump performance forms including the following: a. b. c. d. e. E. System Diagrams: Include schematic layouts of air distribution systems. Present each system with single-line diagram and include the following: 1. 2. 3. 4. 5. F. Settings for outside-, return-, and exhaust-air dampers. Conditions of filters. Fan drive settings including settings and percentage of maximum pitch diameter. Settings for supply-air, static-pressure controller. Other system operating conditions that affect performance. Quantities of outside, supply, return, and exhaust airflows. Duct, outlet, and inlet sizes. Terminal units. Balancing stations. Position of balancing devices. Fan Test Reports: For supply fans, include the following: 1. Fan Data a. b. c. d. e. f. g. h. 2. System identification. Location. Make and type. Model number and size. Manufacturer's serial number. Arrangement and class. Sheave make, size in inches, and bore. Sheave dimensions, center-to-center, and amount of adjustments in inches. Motor Data a. b. c. d. e. f. g. h. i. j. k. l. m. Make and frame type and size. Horsepower and rpm. Volts, phase, and hertz. Full-load amperage and service factor. Sheave make, size in inches, and bore. Sheave dimensions, center-to-center, and amount of adjustments in inches. Number of belts, make, and size. Test Data (Indicated and Actual Values): Total airflow rate in cfm. Total system static pressure in inches wg. Fan rpm. Discharge static pressure in inches wg. Suction static pressure in inches wg. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 20 Testing, Adjusting, and Balancing June 25, 2010 G. Round and Rectangular Duct Traverse Reports: Include a diagram with a grid representing the duct cross-section and record the following: 1. Report Data a. b. c. d. e. f. g. h. i. j. k. H. System-Coil Reports: For heating coils, include the following: 1. Unit Data a. b. c. d. 2. Airflow rate in cfm. Entering-air temperature in deg F. Leaving-air temperature in deg F. Vibration Measurement Reports 1. 2. 3. 4. 5. 6. 7. J. System and air-handling unit identification. Location and zone. Room or riser served. Coil make and size. Test Data (Indicated and Actual Values) a. b. c. I. System and air-handling unit number. Location and zone. Traverse air temperature in deg F. Duct static pressure in inches wg. Duct size in inches. Duct area in sq. ft. Indicated airflow rate in cfm. Indicated velocity in fpm. Actual airflow rate in cfm. Actual average velocity in fpm. Barometric pressure in psig. Date and time of test. Vibration meter manufacturer, model number, and serial number. Equipment designation, location, equipment, speed, motor speed, and motor horsepower. Diagram of equipment showing the vibration measurement locations. Measurement readings for each measurement location. Calculate isolator efficiency using measurements taken. Description of predominant vibration source. Sound Measurement Reports: Record sound measurements on octave band and dBA test forms and on an NC or RC chart indicating the decibel level measured in each frequency band for both "background" and "HVAC system operating" readings. Record each tested location on a separate NC or RC chart. Location shall be noted and keyed to plans. Record the following on the forms: Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 21 Testing, Adjusting, and Balancing June 25, 2010 1. 2. 3. 4. 5. 6. 7. K. Indoor-Air Quality Measurement Reports for Each HVAC System: 1. 2. 3. 4. 5. 6. L. Date and time of test. Record each tested location on its own NC curve. Sound meter manufacturer, model number, and serial number. Space location within the building including floor level and room number. Diagram or color photograph of the space showing the measurement location. Time weighting of measurements, either fast or slow. Description of the measured sound: steady, transient, or tonal. Description of predominant sound source. HVAC system designation. Date and time of test. Outdoor temperature, relative humidity, wind speed, and wind direction at start of test. Room number or similar description for each location. Measurements at each location. Observed deficiencies. Instrument Calibration Reports 1. Report Data a. b. c. d. e. M. Miscellaneous Equipment Reports 1. 3.16 A. Instrument type and make. Serial number. Application. Dates of use. Dates of calibration. All air, fan, motor and controller data specified above. INSPECTIONS Initial Inspection 1. 2. After testing and balancing are complete, and the 72-hour test has been successfully completed, operate each system and randomly check measurements to verify that the system is operating according to the final test and balance readings documented in the Final Report. Advise Owner 5 days in advance of check tests. Randomly check the following for each system: a. b. c. d. Measure airflow of at least 10 percent of air outlets. Measure room temperature at each thermostat/temperature sensor. Compare the reading to the set point. Measure sound levels at 15 locations. Measure space pressure of at least 10 percent of locations. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 22 Testing, Adjusting, and Balancing June 25, 2010 e. f. B. Verify that balancing devices are marked with final balance position. Note deviations to the Contract Documents in the Final Report. Final Inspection 1. 2. 3. 4. 5. 6. 7. After initial inspection is complete and evidence by random checks verifies that testing and balancing are complete and accurately documented in the final report, request that a final inspection be made by Owner. TAB firm test and balance engineer shall conduct the inspection in the presence of Owner. Owner shall randomly select measurements documented in the final report to be rechecked. The rechecking shall be limited to 15 percent of the total measurements recorded in the TAB process. If the rechecks yield measurements that differ from the measurements documented in the final report by more than the tolerances allowed, the measurements shall be noted as “FAILED.” If the number of "FAILED" measurements is greater than 15 percent of the total measurements checked during the final inspection, the testing and balancing shall be considered incomplete and shall be rejected. Tab firm shall recheck all measurements and make adjustments. Revise the final report and balancing device settings to include all changes and resubmit the final report. Request a second final inspection. If the second final inspection also fails, Owner shall contract the services of another TAB firm to complete the testing and balancing in accordance with the Contract Documents and deduct the cost of the services from the final payment. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230593- 23 Testing, Adjusting, and Balancing June 25, 2010 SECTION 230700 HVAC INSULATION PART 1 GENERAL 1.1 DESCRIPTION A. 1.2 Provide and install complete systems of insulation for all new ductwork and equipment as shown and specified. QUALITY ASSURANCE A. Insulation materials and accessories furnished and installed hereunder shall, where required, be accompanied by manufacturers’ current submittal or data sheets showing compliance with applicable specifications listed here. B. Insulation materials and accessories shall be installed in a workmanlike manner by skilled and experienced workers who are regularly engaged in commercial insulation work. C. Insulation materials, including all weather and vapor barrier materials, closures, hangers, fitting covers and other accessories, shall be furnished and installed in strict accordance with project drawings, plans and specifications. Work not in accordance with these Specifications, damaged, or incorrectly installed shall be removed and/or repaired and replaced as directed. D. Mockups: 1. 1.3 Approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. REFERENCE STANDARDS: A. Thermal insulation materials shall meet the property requirements of one or more of the following specifications as applicable to the specific product or use: 1. American Society for Testing of Materials Specifications: a. b. c. d. ASTM C 553, "Standard Specification for Mineral Fiber Blanket Thermal Insulation for Commercial and Industrial Applications" ASTM C 612, "Standard Specification for Mineral Fiber Block and Board Thermal Insulation" ASTM C 795, "Standard Specification for Thermal Insulation for Use in Contact with Austenitic Stainless Steel" ASTM C 1136, "Standard Specification for Flexible, Low Permeance Vapor Retarders for Thermal Insulation" Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 1 HVAC Insulation June 30, 2010 e. f. g. h. ASTM C 1290, "Standard Specification for Flexible Fibrous Glass Blanket Insulation Used to Externally Insulate HVAC Ducts" ASTM G 21, "Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi" (fungi resistance section only) ASTM G 22, "Practice for Determining Resistance of Plastics to Bacteria (bacteria resistance section only) ASTM - American Society for Testing and Materials 1) 2. U. S. Coast Guard Specification: a. 3. 7. Duct Liner Application Standard. Mechanical Fastener Standard HF-1. UL - Underwriters Laboratories Inc. a. 6. ASC-A-7001C Standards for Adhesives for Duct Liner. SMACNA - Sheet Metal and Air Conditioning Contractors National Association Inc. a. b. 5. Approval #164.009, "Noncombustible Materials" ASC - Adhesive and Seal Council a. 4. 723 Tunnel Test. NAIMA - North American Insulation Manufacturer’s Association “Fibrous Glass Duct Linear Standard” Requirements of Regulatory Agencies: a. NFPA - National Fire Protection Association 1) 2) B. 90A, Air Conditioning and Ventilating Systems. 90B, Warm Air Heating and Air Conditioning Systems. Insulation systems shall include: 1. 2. 3. 1.4 E-84 Standard Test Method for Surface Burning Characteristics of Building Materials. Ductwork insulation and jacketing lining and accessories. Firestopping Accessories SUBMITTALS A. Manufacturer's Data indicating product description and installation instructions. 1. Insulation Materials. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 2 HVAC Insulation June 30, 2010 2. 3. 4. 5. Adhesives. Fastening Devices. Vapor Barriers. Jackets. B. Submit schedules of types, thickness, jacketing and accessories for application and location. C. Submit materials safety sheets for all adhesives. 1.5 DEFINITIONS A. 1.6 The term "mineral fiber" as defined by the above specifications includes fibers manufactured of glass, rock, or slag processed from a molten state, with or without binder. SYSTEM PERFORMANCE A. Insulation materials furnished and installed under this specification should meet the minimum requirements of ASHRAE 90.1-2004. However, if other factors such as condensation control or personnel protection are to be considered, the selection of the thickness of insulation should satisfy the controlling factor). B. Insulation materials furnished and installed hereunder shall meet the fire hazard requirements of any one of the following specifications: 1. 2. 3. C. 1.7 ASTM E 84 UL 723 NFPA 255 Show ratings on products, cartons, labels,etc. or verify by report from an approved independent testing laboratory. 1. 2. D. American Society for Testing of Materials Underwriters' Laboratories, Inc National Fire Protection Association Flamespread: Minimum 25 Fuel contributed and smoke developed: Maximum 50 Flame proofing treatments subject to deterioration due to moisture or humidity are not acceptable. ENVIRONMENTAL REQUIREMENTS A. 1.8 Maintain manufacturer’s recommend temperatures and conditions for tapes, adhesives, and cements. DELIVERY AND STORAGE OF MATERIALS A. All of the insulation materials and accessories covered by this specification shall be delivered to the job site and stored in a safe, dry place with appropriate labels and/or other product identification. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 3 HVAC Insulation June 30, 2010 B. The contractor shall use whatever means are necessary to protect the insulation materials and accessories before, during, and after installation. No insulation material shall be installed that has become damaged in any way. The contractor shall also use all means necessary to protect work and materials installed by other trades. C. If any insulation material has become wet because of transit or job site exposure to moisture or water, the contractor shall remove it from the job site and replace it with no increase to the Contract Sum. PART 2 PRODUCTS 2.1 ACCEPTABLE MANUFACTURERS A. Fiberglass Insulation: 1. 2. 3. B. Flexible Elastomeric Insulation: 1. 2. 3. C. The Manville Corp. Owens-Corning Fiberglas Corp. Certain-Teed The Manville Corp. Armstrong Halstead Calcium Silicate Insulation: 1. 2. 3. The Manville Corp. Owens-Corning Fiberglas Corp. Pabco. D. Styrofoam Insulation: Dow FR or FB. E. Adhesives 1. 2. 3. 4. 5. F. Benjamin Foster Insul-Coustic 3M Childers Products Co. Miracle Weld Pins: 1. 2. 3. 4. 5. Nelson Stud Welding Div. TRW Inc. Duro-Dyne Corporation Miracle Tuff-Weld Grip Nail Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 4 HVAC Insulation June 30, 2010 G. Jacketing 1. 2. 2.2 All service jacketing by insulation manufacturer PVC jacketing by insulation manufacturer. MATERIALS A. Jackets and Coverings: 1. 2. 3. 0.016-inch stainless steel smooth surface with moisture barrier. 0.016-inch aluminum smooth surface with moisture barrier. All service jacket laminate (ASJ): a. b. c. d. 4. Aluminum foil vapor retarder. Glas-Scrim reinforcing. Kraft paper backing. Double adhesive longitudinal jacket lap seal, two component butt strip seal. (SSL) PVC Plastic Jacket a. Jacket: (ASTM C921). One piece molded type fitting covers and sheet material, off white color (Manville Zeston 2000) (1) (2) (3) (4) (5) (6) b. 5. B. -40 degrees F. 150 degrees F. ASTM E96; 0.002 perm inches ASTM E84; 25. ASTM E84; 50. 20 mil Connections of brush-on welding adhesive or pressure sensitive color matching vinyl tape. Canvas Jacket: UL listed fabric, 6 oz/sq yd (220g/sq m), plain weave cotton treated with dilute fire retardant lagging adhesive. Adhesives and Coatings: 1. Foster Product Names and Figure Numbers or equal as follows: a. b. c. d. e. C. Minimum Service Temperature: Maximum Service Temperature: Moisture Vapor Transmission: Maximum Flame Spread: Maximum Smoke Developed: Thickness: Lagging Adhesive: 30-36 UL label. Vapor-Barrier Coating: Tite-fit 30-35 UL label. Vaporseal Adhesive: Spark-fas 85-20 UL label. Duct Adhesive: Spark-fas 85-20 UL label. Outdoor Mastic: Monolar mastic 60-38 UL label. Wire, Banding, and Fastening Devices: Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 5 HVAC Insulation June 30, 2010 1. 2. 3. Manufacturers: Pabco, Marathon, Vimesco, Ideal or Venture. Tie Wire: 18 gauge stainless steel with twisted ends on maximum 12 inch centers. Bands: 3/4-inch nominal width wing seals, of minimum thickness as follows: a. b. 4. 5. D. Aluminum: 0.007 inch indoors. Where exposed to weather, 0.020 inch. Stainless Steel: 0.010 inch. Staples: Outward clinching type of corrosion-resistant steel. Weld pins to Support and Fasten Duct Insulation: Minimum 1/8- speed washer or integral flange of minimum 1-3/8 inches diameter. Ductwork, Casings, Housings and Plenums Insulation: Type as scheduled for services listed. 1. Type DW: Flexible fibrous glass blanket with vapor barrier. a. b. 1-DW: Manville "Standard" Microlite, 1-1/2 inch thick duct wrap. Thermal conductivity at 75 degrees F mean, K=0.26 BTU/hr.-degrees F/inch installed "R" 4.5, 1 pcf. Factory applied jacket on each of the above: 1) 2) 3) 4) 5) 6) c. 2. Foil-scrim-kraft laminate (FSK): Aluminum foil facing. Glass scrim reinforcing. Kraft paper backing. Maximum vapor permanence: 0.02 perms. One 2 inch flange, vapor sealed. Minimum insulation as noted above and to comply with local energy code. In the absence of more stringent requirements: minimum R-value R-5 for ductwork indoors and R-8 for ductwork outdoors. Please refer to section 233113 Metal Ducts for duct liner requirements PART 3 EXECUTION 3.1 INSTALLATION A. General: 1. 2. Provide insulation as required for all packaged equipment whether furnished with equipment or not. Before applying insulation: a. b. Test ductwork for tightness; obtain review and acceptance. Clean surfaces of dust, grease, rust, extra flux and foreign matter. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 6 HVAC Insulation June 30, 2010 c. B. Ensure surface is clean and dry before application. Ensure insulation is dry before and during installation. Jackets and Facings: 1. 2. Vaporsealed types: Continuous. Staples not permitted. For ducts, plenums, casings, housings, and equipment: a. Vaporseal fibrous glass blanket: 1) 2) 3) b. C. Fibrous glass board: Seal joints and breaks in facings with 4-inch wide tape to match facing and adhere with vapor seal adhesive. Adhesives and Coatings: 1. 2. 3. 4. D. Apply in accordance with manufacturer's recommendations. Adhere jackets and facings with wet coat of adhesive. Lap sealing: 4 inches. Surfaces to be adhered: Completely coated with adhesive. Wiring, Banding, and Fastening Devices: 1. Secure insulation to ductwork and equipment in accordance with the following minimum requirements: a. Ductwork mechanical fasteners: 1) 2) 3) 4) 5) 6) 7) 8) 9) b. E. 2-inch lap strip at one end. Peel insulation for 2-inch lap strip along longitudinal joints. Seal lap strips with vaporseal adhesive. Weld pins or grip nails. Spacing: Minimum 12 inch centers and minimum 2 rows per side of duct. Maximum permissible load: 5 pounds for 2 inch by 2 inch baseplate. 10 pounds for 2-3/4 inch by 2-3/4 inch baseplate. Clip off pin penetrations flush with insulation surface or facing. Seal pins and washers: With 2 inch square pieces of vapor barrier material to match facing. Adhere with vaporseal adhesive. Field quality control: Repair separation of joints or cracking of insulation due to thermal movement or poor workmanship. Plenum and Duct Insulation: 1. 2. Comply with published recommendations of manufacturer. Unless otherwise shown, apply insulation externally. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 7 HVAC Insulation June 30, 2010 3. Ensure insulation is continuous through inside walls. a. 4. 5. 6. Finish insulation neatly at hangers, supports and other protrusions. Locate insulation cover seams in least visible locations. Where ducts run in groups too close to be individually insulated and finished: a. b. 7. 8. 9. 10. Pack around ducts with fireproof self-supporting insulation material. Properly seal. Completely fill all spaces between ducts with rigid or flexible insulation material. Insulate and finish exterior surfaces of groups as specified for particular service. Where ducts cannot be insulated after erection, insulate prior to installation. Where specified thickness of insulation exceeds available thickness in single layer, provide insulation in 2 or more layers with joints staggered. Finish with systems at operating conditions. Wrap: Duct and plenum wrap. a. Application, rectangular, round and oval duct: 1) 2) 3) 4) 5) 6) 7) 8) 9) b. Apply the duct wrap over clean, dry sheet metal ductwork that has been sealed airtight at all seams and joints. Install duct wrap to allow maximum fullness at corners. Avoid excessive compression. Minimum thickness at corners is 1 inch. Butt insulation tightly at joints. Secure with 4 inch strips of adhesive at 8 inches on center, 2 inch lap strip at one end. Apply with one hundred percent coverage of adhesive, similar to Foster's 85-15. Overlap vapor barrier facing a minimum of 2 inches. Remove insulation from lap prior to stapling. Staple all vapor barrier seams approximately 6 inches on center with outward clinching staples, and seal lap strips with a foil vapor barrier tape, or vapor barrier mastic, such as 3M No. 35. When ducts are over 24 inches in width, additionally secure the duct wrap to the bottom of rectangular ducts with mechanical fasteners spaced on 12-inch centers, but not less than 1 pin on each surface, to prevent sagging of insulation. Seal penetration of facing to provide a vapor tight system. Duct and plenum rigid board wrap: 1) 2) 3) Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 In addition to above general requirements: Score insulation to cover standing seams. Secure with mechanical fasteners spaced 16 inches on centers or closer as required to hold insulation firmly to duct. 230700- 8 HVAC Insulation June 30, 2010 4) 11. 12. 3.2 Seal all joints and pin penetrations with pressure sensitive aluminum foil tape. Reinforce all exposed edges with corner bead. Insulation as specified herein shall be applied to all new ductwork, plenums, etc. and to existing ductwork, etc., where existing insulation is damaged. Install fire wrap as specified by the manufacturer and in accordance with all stated direction. SCHEDULE: DUCT AND PLENUM INSULATION A. Notes for Insulation Application Schedule: 1. 2. When both insulation and lining have been specified for a specific section of ductwork, the amount of external insulation may be reduced to achieve an overall assembly insulation value (U) equivalent to that of the specified duct insulation. Provide fire-rated duct wrap where specified on the drawing. a. B. Wrap may be used to extend rating to suitable fire damper location as required only where noted on the drawing or agreed with the Engineer. Application Schedule: Ductwork shall be acoustically lined and/or insulated as follows: Item Supply All supply ductwork Other return air ductwork Outside air ducts in occupied spaces and mechanical rooms 1-DW 1-DW Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 230700- 9 Return Exhaust HVAC Insulation June 30, 2010 SECTION 230993 SEQUENCE OF OPERATIONS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Related Sections included the following: 1. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and equipment. B. Related Sections include the following: 1. 1.3 Division 15 Section "HVAC Instrumentation and Controls" for control equipment and devices and submittal requirements. DEFINITIONS A. DDC: Direct-digital controls. B. BMS: Building management system 1.4 SEQUENCE OF OPERATIONS A. Supply Fan and Electric Heating Coil 1. 2. 3. The supply fan and electric heating coil shall be controlled via space thermostat/controller. The BMS contractor shall provide and install. The supply fan and electric heating coils shall started/stopped by the BMS local controller based on a time of day schedule or a manual command from the controller. On a call for ventilation, the supply fan shall be cycled on/off to maintain setpoint. On a call for heating, the supply fan and electric heating coil (sequential 2-stage heating operation to maintain heating setpoint) shall be cycled on/off to maintain setpoint. Provide time delay and dead band to prevent short cycling between fan on/off and 2-stage heating control. The electric heating coil shall be disabled if supply fan is off as proven by air flow switch. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230993- 1 Sequence of Operations June 30, 2010 SECTION 233113 METAL DUCTS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. B. Requirements of Section 230500 shall also govern work specified together with all applicable paragraphs of other Division 23 sections. 1.2 SUMMARY A. Section Includes: 1. 2. 3. 4. 5. 6. B. Related Sections: 1. 2. 3. 4. 1.3 Single-wall rectangular ducts and fittings. Single-wall round and flat-oval ducts and fittings. Sheet metal materials. Duct liner. Sealants and gaskets. Hangers and supports. Division 23 Section "Testing, Adjusting, and Balancing for HVAC" for testing, adjusting, and balancing requirements for metal ducts. Division 23 Section "Nonmetal Ducts" for fibrous-glass ducts, thermoset fiberreinforced plastic ducts, thermoplastic ducts, PVC ducts, and concrete ducts. Division 23 Section "HVAC Casings" for factory- and field-fabricated casings for mechanical equipment. Division 23 Section "Air Duct Accessories" for dampers, sound-control devices, duct-mounting access doors and panels, turning vanes, and flexible ducts. PERFORMANCE REQUIREMENTS A. Delegated Duct Design: Duct construction, including sheet metal thicknesses, seam and joint construction, reinforcements, and hangers and supports, shall comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" and performance requirements and design criteria indicated in "Duct Schedule" Article. B. Airstream Surfaces: Surfaces in contact with the airstream shall comply with requirements in ASHRAE 62.1-2004. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 1 Metal Ducts June 30, 2010 1.4 SUBMITTALS A. Product Data: For each type of the following products: 1. 2. B. Liners and adhesives. Sealants and gaskets. Shop Drawings: 1. Prior to fabrication of ductwork, submit “shop standards,” including (but not limited to) a. b. c. d. e. f. g. h. i. j. k. l. 2. Submit test reports for the following a. b. C. Fabrication, assembly, and installation, including plans, elevations, sections, components, and attachments to other work. Factory- and shop-fabricated ducts and fittings. Duct layout indicating sizes, configuration, materials, metal gauges, liner material, extend of internal lining, and static-pressure classes, changes in pressure class, transitions. Elevation of top of ducts. Dimensions of main duct runs from building grid lines. Fittings. Reinforcement and spacing. Seam and joint construction. Penetrations through fire-rated and other partitions. Equipment installation based on equipment being used on Project. Locations for duct accessories, including volume dampers, fire & smoke dampers, turning vanes, and access doors and panels. Hangers and supports, including methods for duct and building attachment, and vibration isolation. Submit structural calculations (refer to §1.4.D.5). Flamespread of resins (refer to UL-723). Air leakage (refer to §3.9.B). Delegated-Design Submittal: 1. 2. 3. 4. 5. Sheet metal thicknesses. Joint and seam construction and sealing. Reinforcement details and spacing. Materials, fabrication, assembly, and spacing of hangers and supports. Design Calculations: Calculations, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation for selecting hangers and supports. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 2 Metal Ducts June 30, 2010 D. Coordination Drawings: Dimensioned plans, drawn at 3/8” = 1’-0” scale, on which the following items are shown and coordinated with each other, with each trade in a separate color, using input from installers of the items involved: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. Duct installation in congested spaces, indicating coordination with general construction, building components, and other building services. Indicate proposed changes to duct layout. Unless otherwise noted, duct sizes shown on the contract drawings are clear internal airway dimensions, and allowance shall be made for internal lining as appropriate. Suspended ceiling components. Structural members to which duct will be attached. Size and location of initial access modules for acoustical tile. Penetrations of smoke barriers and fire-rated construction. Required openings in structural and architectural systems. Location of supports and suspension systems. Locations and critical dimensions of structural steel Major electrical conduit and cable tray routes Dimensions of actual equipment to be installed Dimensioned code compliant equipment access including access door locations and swings All conflicts between trades should be resolved prior to submission to the Architect/Engineer. Locations of walls and partitions, doors, door swings, lighting and all other information required to assure complete coordination among the various trades Items penetrating finished ceiling with sizes and elevations including the following: a. b. c. d. e. f. g. Lighting fixtures. Air outlets and inlets. Speakers. Sprinklers runs. Access panels. Perimeter moldings. Plumbing piping runs. E. Welding certificates. F. Field quality-control reports. 1.5 QUALITY ASSURANCE A. Reference Standards: 1. 2. National Fire Protection Association (NFPA): NFPA No. 90-A. "Air Conditioning and Ventilating Systems". Sheet Metal and Air Conditioning Contractors’ National Association, Inc. (SMACNA), 8224 Old Court House Road, Vienna, Virginia, 22180. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 3 Metal Ducts June 30, 2010 a. b. c. d. e. 3. 4. 5. 6. 7. 8. 9. Balancing and Adjustment Manual: In this Specification shall mean the first edition of the “Manual for the Balancing and Adjustment of Air Distribution System”. "HVAC Duct Construction Standards-Metal and Flexible", 2005. "Round Industrial Duct Construction Standards", 1977. "Rectangular Industrial Duct Construction Standards", 1980. “HVAC Air Duct Leakage Test Manual”, 1985. American Conference of Governmental Industrial Hygienists (ACGIH). "Industrial Ventilation-A Manual of Recommended Practice", 20th edition. Factory Mutual (FM) Standard 7-78. NFPA 91. National Bureau of Standards (NBS) Voluntary Product Standard 15-69. North American Insulation Manufacturers Association (NAIMA): “Fibrous Glass Duct Liner Standard” ASTM 411-61: “Test for Hot Surface Performance of High Temperature Surface Insulation.” ASTM E-84/UL 723/NFPA 255: "Test for Surface Burning Characteristics of Building Materials." B. Welding Qualifications: Qualify procedures and personnel according to [AWS D1.1/D1.1M, "Structural Welding Code - Steel," for hangers and supports.] [AWS D1.2/D1.2M, "Structural Welding Code - Aluminum," for aluminum supports.] [AWS D9.1M/D9.1, "Sheet Metal Welding Code," for duct joint and seam welding.] C. Welding Qualifications: Qualify procedures and personnel according to the following: 1. 2. 3. AWS D1.1/D1.1M, "Structural Welding Code - Steel," for hangers and supports. AWS D1.2/D1.2M, "Structural Welding Code - Aluminum," for aluminum supports. AWS D9.1M/D9.1, "Sheet Metal Welding Code," for duct joint and seam welding. D. ASHRAE Compliance: Applicable requirements in ASHRAE 62.1-2004, Section 5 "Systems and Equipment" and Section 7 - "Construction and System Start-Up." E. ASHRAE/IESNA Compliance: Applicable requirements in ASHRAE/IESNA 90.12004, Section 6.4.4 - "HVAC System Construction and Insulation." F. Mockups: 1. Before installing duct systems, build mockups representing static-pressure classes in excess of 3-inch wg (750 Pa). Build mockups to comply with the following requirements, using materials indicated for the completed Work: a. b. c. Five transverse joints. One access door(s). Two typical branch connections, each with at least one elbow. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 4 Metal Ducts June 30, 2010 d. e. f. g. h. i. j. k. 2. G. Two typical flexible duct or flexible-connector connections for each duct and apparatus. One 90-degree turn(s) with turning vanes. One fire damper(s). One subduct extension including stainless riser. One Lab supply branch connection to riser. One each lab supply and exhaust flat oval ductwork. One 24” dia. stainless exhaust stack. Perform leakage tests specified in "Field Quality Control" Article. Revise mockup construction and perform additional tests as required to achieve specified minimum acceptable results. Approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion. Delivery and Storage 1. 2. 3. 4. 5. 6. 7. All ductwork shall be delivered to the job site in a dry and clean state. All ductwork shall be stored in a manner and location to minimize physical damage to any part of the ductwork (including internal lining), and stored in a dry and clean location. All ductwork shall be stored in a clean and dry environment and protected from dust and dirt ingress. All ductwork shall be delivered to the job site with shop-installed caps on all openings. Caps shall be made of heavy gauge polythene sheets securely taped to duct on all sides. Any ductwork not protected in this manner will be rejected and removed from the jobsite and replaced at no increase in the Contract Sum. Ductwork that has been contaminated by dust shall be cleaned in accordance with proper standards. All lined ductwork shall be cleaned using the methodology outlined in the NAIMA booklet “Cleaning Fibrous Glass Insulated Air Duct Systems.” Ductwork with lining that has been contaminated by liquids shall be fully dried. Prior to installation. Installation of any damaged or refurbished ductwork shall be at the discretion of the Engineer. PART 2 PRODUCTS 2.1 SINGLE-WALL RECTANGULAR DUCTS AND FITTINGS A. General Fabrication Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" based on indicated static-pressure class unless otherwise indicated. B. Transverse Joints: T-24 flanged with corner pieces according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 1-4, "Transverse (Girth) Joints," for static-pressure class, applicable sealing requirements, materials involved, Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 5 Metal Ducts June 30, 2010 duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." C. Longitudinal Seams: Pittsburgh lock with a 3/8-inch minimum pocket according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 1-5, "Longitudinal Seams - Rectangular Ducts," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." D. Elbows, Transitions, Offsets, Branch Connections, and Other Duct Construction: Select types and fabricate according to SMACNA's "HVAC Duct Construction Standards Metal and Flexible," Chapter 2, "Fittings and Other Construction," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." E. Ductwork not insulated and larger than 18" shall be either cross broken or beaded. F. All mitered elbows shall be provided with hollow vanes having different inside and outside curvatures, vanes shall be equal to "Ducturns" as manufactured by Tuttle and Bailey. G. Unless otherwise shown on the contract drawings, all elbows shall have a throat radius equal to the width of the duct in the direction of the elbow. H. All branch ducts shall be provided with take-off pieces including 45 degree angled sides as per SMACNA Figure 2-6. Straight taps shall not be acceptable. 2.2 SINGLE-WALL ROUND AND FLAT-OVAL DUCTS AND FITTINGS A. General Fabrication Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Chapter 3, "Round, Oval, and Flexible Duct," based on indicated static-pressure class unless otherwise indicated. 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. b. c. d. e. Lindab Inc. McGill AirFlow LLC. SEMCO Incorporated. Sheet Metal Connectors, Inc. Spiral Manufacturing Co., Inc. B. Flat-Oval Ducts: Indicated dimensions are the duct width (major dimension) and diameter of the round sides connecting the flat portions of the duct (minor dimension). C. Transverse Joints: Joint RT-1 (beaded sleeve joint) and fabricate according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-2, Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 6 Metal Ducts June 30, 2010 "Transverse Joints - Round Duct," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." 1. D. Longitudinal Seams: Select seam types and fabricate according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-1, "Seams - Round Duct and Fittings," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." 1. 2. E. 2.3 Transverse Joints in Ducts Larger Than 60 Inches (1524 mm) in Diameter: Flanged. Fabricate round ducts larger than 90 inches (2286 mm) in diameter with buttwelded longitudinal seams. Fabricate flat-oval ducts larger than 72 inches (1830 mm) in width (major dimension) with butt-welded longitudinal seams. Tees and Laterals: Select types and fabricate according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-4, "90 Degree Tees and Laterals," and Figure 3-5, "Conical Tees," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." SHEET METAL MATERIALS A. General Material Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" for acceptable materials, material thicknesses, and duct construction methods unless otherwise indicated. Sheet metal materials shall be free of pitting, seam marks, roller marks, stains, discolorations, and other imperfections. B. Galvanized Sheet Steel: Comply with ASTM A 653/A 653M. 1. 2. 3. Galvanized Coating Designation: G60 (Z180) both sides. Galvanized Coating Designation for external/exposed ductwork: G90 (Z275) both sides. Finishes for Surfaces Exposed to View: Mill phosphatized in compliance with ASTM D2092. C. Stainless-Steel Sheets: Comply with ASTM A 480/A 480M, Type 304 or 316, as indicated in the "Duct Schedule" Article; cold rolled, annealed, sheet. Exposed surface finish shall be No. 2B, No. 2D, No. 3, or No. 4 as indicated in the "Duct Schedule" Article. D. Aluminum Sheets: Comply with ASTM B 209 (ASTM B 209M) Alloy 3003, H14 temper; with mill finish for concealed ducts, and standard, one-side bright finish for duct surfaces exposed to view. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 7 Metal Ducts June 30, 2010 E. Reinforcement Shapes and Plates: ASTM A 36/A 36M, steel plates, shapes, and bars; black and galvanized. 1. Where black- and galvanized-steel shapes and plates are used to reinforce aluminum ducts, isolate the different metals with butyl rubber, neoprene, or EPDM gasket materials. F. Tie Rods: Galvanized steel, 1/4-inch (6-mm) minimum diameter for lengths 36 inches (900 mm) or less; 3/8-inch (10-mm) minimum diameter for lengths longer than 36 inches (900 mm). G. All ductwork shall have the metal gauge visibly marked on all sections by manufacturer. 2.4 DUCT LINER A. Fibrous-Glass Duct Liner: Comply with ASTM C 1071, NFPA 90A, or NFPA 90B; and with NAIMA AH124, "Fibrous Glass Duct Liner Standard." 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. b. c. d. 2. Johns Manville. CertainTeed Corporation; Insulation Group. Knauf Insulation. Owens Corning. Performance: a. Type 1-AL, Flexible: 0.24 Btu x in./h x sq. ft. x deg F at 75 deg F mean temperature. 1) 2) b. Type 2-AL, Flexible: 0.24 Btu x in./h x sq. ft. x deg F at 75 deg F mean temperature. 1) 2) c. 1” thickness Noise reduction coefficient 0.70 tested in accordance with ASTM C 423 and ASTM E 795. 2” thickness Noise reduction coefficient 0.95 tested in accordance with ASTM C 423 and ASTM E 795. Type CL, Flexible High Performance: 0.23 Btu x in./h x sq. ft. x deg F at 75 deg F 1) 2) Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 1” thickness Noise reduction coefficient 0.75 tested in accordance with ASTM C 423 and ASTM E 795. 233113 - 8 Metal Ducts June 30, 2010 3. Water-Based Liner Adhesive: Comply with NFPA 90A or NFPA 90B and with ASTM C 916. a. 4. For indoor applications, use adhesive that has a VOC content of 80 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). NFPA-90A coating on side facing air stream. 1) B. Natural-Fiber Duct Liner: 85 percent cotton, 10 percent borate, and 5 percent polybinding fibers, treated with a microbial growth inhibitor and complying with NFPA 90A or NFPA 90B. 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. b. 2. 3. 4. For indoor applications, use adhesive that has a VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). Insulation Pins and Washers: 1. 2. D. Bonded Logic, Inc. Reflectix Inc. Maximum Thermal Conductivity: 0.24 Btu x in./h x sq. ft. x deg F (0.034 W/m x K) at 75 deg F (24 deg C) mean temperature when tested according to ASTM C 518. Surface-Burning Characteristics: Maximum flame-spread index of 25 and maximum smoke-developed index of 50 when tested according to ASTM E 84; certified by an NRTL. Liner Adhesive: As recommended by insulation manufacturer and complying with NFPA 90A or NFPA 90B. a. C. Suitable for velocity up to 4000-fpm. Cupped-Head, Capacitor-Discharge-Weld Pins: zinc-coated steel pin, fully annealed for capacitor-discharge welding, 0.135-inch- (3.5-mm-) diameter shank, length to suit depth of insulation indicated with integral 1-1/2-inch (38-mm) galvanized carbon-steel washer. Insulation-Retaining Washers: Self-locking washers formed from 0.016-inch(0.41-mm-) thick galvanized steel; with beveled edge sized as required to hold insulation securely in place but not less than 1-1/2 inches (38 mm) in diameter. Shop Application of Duct Liner: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-19, "Flexible Duct Liner Installation." Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 9 Metal Ducts June 30, 2010 1. 2. 3. 4. 5. 6. 7. 8. Adhere a single layer of indicated thickness of duct liner with at least 90 percent adhesive coverage at liner contact surface area. Attaining indicated thickness with multiple layers of duct liner is prohibited. Apply adhesive / edge seal to transverse edges of liner facing upstream and downstream that do not receive metal nosing. Butt transverse joints without gaps, and coat joint with adhesive. Fold and compress liner in corners of rectangular ducts or cut and fit to ensure butted-edge overlapping. Do not apply liner in rectangular ducts with longitudinal joints, except at corners of ducts, unless duct size and dimensions of standard liner make longitudinal joints necessary. Apply adhesive coating on longitudinal seams in ducts with air velocity of 2500 fpm (12.7 m/s). Secure liner with mechanical fasteners 4 inches (100 mm) from corners and at intervals not exceeding 12 inches (300 mm) transversely; at 3 inches (75 mm) from transverse joints and at intervals not exceeding 18 inches (450 mm) longitudinally. Secure transversely oriented liner edges facing the airstream with metal nosings that have either channel or "Z" profiles or are integrally formed from duct wall. Fabricate edge facings at the following locations: a. b. c. 9. Secure insulation between perforated sheet metal inner duct of same thickness as specified for outer shell. Use mechanical fasteners that maintain inner duct at uniform distance from outer shell without compressing insulation. a. 10. E. Sheet Metal Inner Duct Perforations: 3/32-inch (2.4-mm) diameter, with an overall open area of 23 percent. Terminate inner ducts with buildouts attached to fire-damper sleeves, dampers, turning vane assemblies, or other devices. Fabricated buildouts (metal hat sections) or other buildout means are optional; when used, secure buildouts to duct walls with bolts, screws, rivets, or welds. Where round ducts are specified to be lined, use 1. 2.5 Fan discharges. Intervals of lined duct preceding unlined duct. Upstream edges of transverse joints in ducts where air velocities are higher than 2500 fpm (12.7 m/s) or where indicated. Prefabricated circular fiberglass lining inserts. SEALANT AND GASKETS A. General Sealant and Gasket Requirements: Surface-burning characteristics for sealants and gaskets shall be a maximum flame-spread index of 25 and a maximum smokedeveloped index of 50 when tested according to UL 723; certified by an NRTL. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 10 Metal Ducts June 30, 2010 B. Two-Part Tape Sealing System as manufactured by Hardcast: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. C. Water-Based Joint and Seam Sealant as manufactured by Foster: 1. 2. 3. 4. 5. 6. 7. 8. 9. D. Tape: DT-5400, woven cotton fiber impregnated with mineral gypsum and modified acrylic/silicone activator to react exothermically with tape to form hard, durable, airtight seal. Tape Width: 4 inches (102 mm). Sealant: RTA-50, modified styrene acrylic for exterior; FTA-20 for interior. Water resistant. Mold and mildew resistant. Maximum Static-Pressure Class: 10-inch wg (2500 Pa), positive and negative. Service: Indoor and outdoor. Service Temperature: Minus 40 to plus 200 deg F (Minus 40 to plus 93 deg C). Substrate: Compatible with galvanized sheet steel (both PVC coated and bare), stainless steel, or aluminum. For indoor applications, use sealant that has a VOC content of 250 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). Application Method: Brush on. Solids Content: Minimum 65 percent. Shore A Hardness: Minimum 20. Water resistant. Mold and mildew resistant. VOC: Maximum 75 g/L (less water). Maximum Static-Pressure Class: 10-inch wg (2500 Pa), positive and negative. Service: Indoor or outdoor. Substrate: Compatible with galvanized sheet steel (both PVC coated and bare), stainless steel, or aluminum sheets. Flanged Joint Sealant: Comply with ASTM C 920. 1. 2. 3. 4. 5. 6. General: Single-component, acid-curing, silicone, elastomeric. Type: S. Grade: NS. Class: 25. Use: O. For indoor applications, use sealant that has a VOC content of 250 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). E. Flange Gaskets: Butyl rubber, neoprene, or EPDM polymer with polyisobutylene plasticizer. F. Round Duct Joint O-Ring Seals: 1. Seal shall provide maximum leakage class of 3 cfm/100 sq. ft. at 1-inch wg (0.14 L/s per sq. m at 250 Pa) and shall be rated for 10-inch wg (2500-Pa) staticpressure class, positive or negative. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 11 Metal Ducts June 30, 2010 2. 3. 2.6 EPDM O-ring to seal in concave bead in coupling or fitting spigot. Double-lipped, EPDM O-ring seal, mechanically fastened to factory-fabricated couplings and fitting spigots. HANGERS AND SUPPORTS A. Hanger Rods for Noncorrosive Environments: Cadmium-plated or galvanized lowcarbon mild steel rods, full threaded or threaded at each end, two removeable nuts at each end. B. Hanger Rods for Corrosive Environments: Electrogalvanized, all-thread rods or galvanized rods with threads painted with zinc-chromate primer after installation. C. Strap and Rod Sizes: Same materials as ducts, except that straps for stainless steel ducts in unfinished spaces may be galvanized steel. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Table 4-1 (Table 4-1M), "Rectangular Duct Hangers Minimum Size," and Table 4-2, "Minimum Hanger Sizes for Round Duct." D. Duct Attachments: Sheet metal screws, rivets, or self-tapping metal screws; same material as duct materials. 1. 2. 3. E. Zinc or cadmium plated on galvanized duct. Minimum screw size: Number 10. Minimum rivet size: 4 pounds, blind rivets are not acceptable. Trapeze and Riser Supports: 1. 2. 3. Supports for Galvanized-Steel Ducts: Galvanized-steel shapes and plates. Supports for Stainless-Steel Ducts: Stainless-steel shapes and plates. Supports for Aluminum Ducts: Aluminum or galvanized steel coated with zinc chromate. F. Power / Powder actuated anchors are not acceptable. G. Machine bolts and nuts: Galvanized or cadmium plated steel. H. Concrete inserts: Steel or malleable iron of the continuously slotted type of Universal inserts. I. Self-drilled expanding fastener: Hilti type. J. Expansion shields: “Star Slugin”, single unit type, unless otherwise specified Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 12 Metal Ducts June 30, 2010 PART 3 EXECUTION 3.1 DUCT INSTALLATION A. Drawing plans, schematics, and diagrams indicate general location and arrangement of duct system. Indicated duct locations, configurations, and arrangements were used to size ducts and calculate friction loss for air-handling equipment sizing and for other design considerations. Install duct systems as indicated unless deviations to layout are approved on Shop Drawings and Coordination Drawings. B. Install ducts according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" unless otherwise indicated. C. Install round and flat-oval ducts in maximum practical lengths. D. Install ducts with fewest possible joints. E. Install factory- or shop-fabricated fittings for changes in direction, size, and shape and for branch connections. F. Unless otherwise indicated, install ducts vertically and horizontally, and parallel and perpendicular to building lines. G. Install ducts close to walls, overhead construction, columns, and other structural and permanent enclosure elements of building. H. Install ducts with a clearance of 1 inch (25 mm), plus allowance for insulation thickness. I. Route ducts to avoid passing through transformer vaults and electrical equipment rooms and enclosures. J. Where ducts pass through non-fire-rated interior partitions and exterior walls and are exposed to view, cover the opening between the partition and duct or duct insulation with sheet metal flanges of same metal thickness as the duct. Overlap openings on four sides by at least 1-1/2 inches (38 mm). K. Where ducts pass through fire-rated interior partitions and exterior walls, install fire dampers. Comply with requirements in Division 23 Section "Air Duct Accessories" for fire and smoke dampers. L. Protect duct interiors from moisture, construction debris and dust, and other foreign materials. Comply with SMACNA's "Duct Cleanliness for New Construction Guidelines." M. Install ductwork in adherence to ceiling height shown on Drawings. Establish necessary space requirements so as to maintain required clearances around all equipment. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 13 Metal Ducts June 30, 2010 N. Reinforce all ducts to prevent buckling, breathing, vibrations or noise. Such reinforcing shall be as recommended in the references specified herein. O. Avoid penetration of ducts. Where penetrations are unavoidable ductwork details shall be based on SMACNA Figure 2-8 and agreed with the Engineer before fabrication. P. At exposed duct penetrations of walls, floors, and ceilings, provide sheet metal angle type escutcheons. Q. Duct openings: Provide openings where required to accommodate thermometers, smoke detectors, controllers, etc. R. Provide pilot tube openings where required for testing of systems: 1. 2. Complete with metal cap with spring device or screw to ensure against air leakage. For pilot tube tests install Ventlok No. 699 or 699-2 instrument. S. Where openings are provided in insulated ductwork, install insulation material inside metal trim angle to cover complete perimeter of insulation edge. T. Waterproof seams and joints in ductwork exposed to the weather by application twopart tape sealing system.. U. At ceiling supply diffusers, extend horizontal branch duct 1 foot beyond diffuser. V. Cap all erected ductwork to prevent ingress of dust and dirt at the end of each working day. W. All ductwork shall be fully protected from damage during the construction phase. X. Do not use sheet metal screws in the bottom panels of ducts having soldered, welded or brazed seams. Y. Unless otherwise specified or shown support vertical ducts from each floor slab or by purpose made brackets fixed to the structure. Z. Do not suspend ducts from plumbing, conduits or related supports. AA. All sections of the duct designated as lined shall be completely covered with lining material and the material shall be cut to ensure tight flush butt joints without gaps. All joints shall be coated and sealed. BB. Install metal nosing on all leading and trailing edges of lined ductwork. CC. The ductwork lining material shall be secured with mechanical fasteners as recommended by the manufacturer and adhered to the sheet metal with a full coverage of the manufacturers recommended adhesive which shall be a UL listed adhesive. Pin Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 14 Metal Ducts June 30, 2010 length should be as recommended by the liner manufacturer. Adhesive shall not contain volatile solvents. DD. Duct dimensions indicated are net inside dimensions required for airflow. Increase duct size to allow for lining / insulation thickness. 3.2 INSTALLATION OF EXPOSED DUCTWORK A. Protect ducts exposed in finished spaces from being dented, scratched, or damaged. B. Trim duct sealants flush with metal. Create a smooth and uniform exposed bead. Do not use two-part tape sealing system. C. Grind welds to provide smooth surface free of burrs, sharp edges, and weld splatter. When welding stainless steel with a No. 3 or 4 finish, grind the welds flush, polish the exposed welds, and treat the welds to remove discoloration caused by welding. D. Maintain consistency, symmetry, and uniformity in the arrangement and fabrication of fittings, hangers and supports, duct accessories, and air outlets. E. Repair or replace damaged sections and finished work that does not comply with these requirements. 3.3 DUCT SEALING A. Seal ducts to the following seal classes according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible": 1. 2. 3.4 Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." All Ducts: Seal Class A. HANGER AND SUPPORT INSTALLATION A. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Chapter 4, "Hangers and Supports." B. Building Attachments: Concrete inserts, self-drilled expanding fastener, and expansion shields as appropriate for construction materials to which hangers are being attached. 1. 2. 3. 4. 5. Where practical, install concrete inserts before placing concrete. Do not use power / powder-actuated concrete fasteners. Refer to 230548 (Mechanical Sound and Vibration) for isolation requirements. Upper attachments to be in accordance with SMACANA Figure 4-2-1, 2, 3, 6, 7, and 8 only. Support ductwork so that horizontal ducts are without sag or sway, vertical ducts are without buckle, and all ducts are free from the possibility of deformation, collapse, or vibration. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 15 Metal Ducts June 30, 2010 C. Hanger Spacing: Comply with SMACNA's "HVAC Duct Construction Standards Metal and Flexible," Table 4-1 (Table 4-1M), "Rectangular Duct Hangers Minimum Size," and Table 4-2, "Minimum Hanger Sizes for Round Duct," for maximum hanger spacing; install hangers and supports within 24 inches (610 mm) of each elbow and within 48 inches (1200 mm) of each branch intersection. D. Hangers Exposed to View: Threaded rod and angle or channel supports. E. Support vertical ducts with steel angles or channel secured to the sides of the duct with welds, bolts, sheet metal screws, or rivets; support at each floor and at a maximum intervals of 16 feet (5 m). F. Install upper attachments to structures. Select and size upper attachments with pull-out, tension, and shear capacities appropriate for supported loads and building materials where used. 3.5 CONNECTIONS A. Make connections to equipment with flexible connectors complying with Division 23 Section "Air Duct Accessories." B. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" for branch, outlet and inlet, and terminal unit connections. 3.6 PAINTING A. 3.7 Paint interior of metal ducts that are visible through registers and grilles and that do not have duct liner. Apply one coat of flat, black, latex paint over a compatible galvanizedsteel primer. Paint materials and application requirements are specified in Division 09 painting Sections. FIELD QUALITY CONTROL A. Perform tests and inspections. B. Leakage Tests: 1. 2. 3. 4. 5. Comply with SMACNA's "HVAC Air Duct Leakage Test Manual." Submit a test report for each test. Test 20% of all systems. Systems to be identified by the Engineer. Disassemble, reassemble, and seal segments of systems to accommodate leakage testing and for compliance with test requirements. Test for leaks before applying external insulation. Conduct tests at static pressures equal to maximum design pressure of system or section being tested. If static-pressure classes are not indicated, test system at maximum system design pressure. Do not pressurize systems above maximum design operating pressure. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 16 Metal Ducts June 30, 2010 6. 7. Give seven business days' advance notice for testing for witnessing by Owner’s Representative. Procedure: a. b. c. d. e. f. g. h. i. j. k. C. Seal openings in ducts and plenums to be tested. Connect test apparatus to test section using flexible duct connection or hose. Close damper on blower suction side, to prevent excessive buildup of pressure. Start blower and gradually open damper on suction side of blower. Build up pressure in test section. Test supply air, return, exhaust and outside air to 100 percent of duct construction pressure rating. Determine amount of air leakage by makeup air flow measurements. Total allowable leakage is to be calculated using the formula F=C L x p 0.65 Where F = Allowable leakage per 100 square feet C L = Leakage classification P = Duct pressure classification Repair air leaks as required and retest when seals have cured until leakage rate is acceptable. Noise generated from duct leakage is not acceptable. Remove temporary blanks and seals as appropriate. Visually mark tested sections with certification sticker and initials of field test inspector. Submit certification of test results. Duct System Cleanliness Tests: 1. 2. Visually inspect duct system to ensure that no visible contaminants are present. Test sections of metal duct system, chosen randomly by Owner, for cleanliness according to "Vacuum Test" in NADCA ACR, "Assessment, Cleaning and Restoration of HVAC Systems." a. b. Acceptable Cleanliness Level: Net weight of debris collected on the filter media shall not exceed 0.75 mg/100 sq. cm. Installation shall meet or exceed the requirements of SMACNA standard “IAQ guideline for occupied building under construction (latest edition).” 1) c. Follow the guidelines set for by LEED (latest version) for credit 3.1 (construction IAQ management). All temporary filters shall have a minimum efficiency of MERV-8. D. Duct system will be considered defective if it does not pass tests and inspections. E. Prepare test and inspection reports. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 17 Metal Ducts June 30, 2010 3.8 DUCT CLEANING A. Clean new and existing duct system(s) before testing, adjusting, and balancing. Provide a minimum of 20-man days of cleaning, or as instructed by the Owner. B. Use service openings for entry and inspection. 1. 2. 3. C. Particulate Collection and Odor Control: 1. 2. D. When venting vacuuming system inside the building, use HEPA filtration with 99.97 percent collection efficiency for 0.3-micron-size (or larger) particles. When venting vacuuming system to outdoors, use filter to collect debris removed from HVAC system, and locate exhaust downwind and away from air intakes and other points of entry into building. Clean the following components by removing surface contaminants and deposits: 1. 2. 3. 4. 5. 6. 7. E. Create new openings and install access panels appropriate for duct static-pressure class if required for cleaning access. Provide insulated panels for insulated or lined duct. Patch insulation and liner as recommended by duct liner manufacturer. Comply with Division 23 Section "Air Duct Accessories" for access panels and doors. Disconnect and reconnect flexible ducts as needed for cleaning and inspection. Remove and reinstall ceiling to gain access during the cleaning process. Air outlets and inlets (registers, grilles, and diffusers). Supply, return, and exhaust fans including fan housings, plenums (except ceiling supply and return plenums), scrolls, blades or vanes, shafts, baffles, dampers, and drive assemblies. Air-handling unit internal surfaces and components including mixing box, coil section, air wash systems, spray eliminators, condensate drain pans, filters and filter sections, and condensate collectors and drains. Coils and related components. Return-air ducts, dampers, actuators, and turning vanes except in ceiling plenums and mechanical equipment rooms. Supply-air ducts, dampers, actuators, and turning vanes. Dedicated exhaust and ventilation components and makeup air systems. Mechanical Cleaning Methodology: 1. 2. 3. Clean metal duct systems using mechanical cleaning methods that extract contaminants from within duct systems and remove contaminants from building. Use vacuum-collection devices that are operated continuously during cleaning. Connect vacuum device to downstream end of duct sections so areas being cleaned are under negative pressure. Use mechanical agitation to dislodge debris adhered to interior duct surfaces without damaging integrity of metal ducts, duct liner, or duct accessories. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 18 Metal Ducts June 30, 2010 4. Clean fibrous-glass duct liner with HEPA vacuuming equipment; do not permit duct liner to get wet. Replace fibrous-glass duct liner that is damaged, deteriorated, or delaminated or that has friable material, mold, or fungus growth. Clean coils and coil drain pans according to NADCA 1992. Keep drain pan operational. Rinse coils with clean water to remove latent residues and cleaning materials; comb and straighten fins. Provide drainage and cleanup for wash-down procedures. 5. 6. 3.9 START UP A. 3.10 A. Air Balance: Comply with requirements in Division 23 Section "Testing, Adjusting, and Balancing for HVAC." DUCT SCHEDULE Fabricate ducts with galvanized sheet steel except as otherwise indicated and as follows: 1. Lined ductwork: double wall with perforated liner. Coordinate locations of ductwork requiring liner with the contract drawings. Exposed ductwork in occupied areas: round or flat oval. Coordinate locations of exposed ductwork in occupied areas with the contract drawings. 2. B. System Pressure Classification Seal Class Supply and return Outdoor air 4” 3” A A Round Leakage Class 3 3 Intermediate Reinforcement: 1. 2. Galvanized-Steel Ducts: Galvanized steel. Stainless-Steel Ducts: a. b. 3. C. Rectangular Leakage Class 6 6 Exposed to Airstream: Match duct material. Not Exposed to Airstream: Match duct material. Aluminum Ducts: Aluminum. Liner: 1. Application Schedule: Ductwork shall be acoustically lined as follows: Item Supply Return Exhaust Transfer Ducts All ducts shown on drawings as being acoustically lined 2-AL 2-AL 2-AL 2-AL 1-AL 1-AL Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 19 Metal Ducts June 30, 2010 D. Elbow Configuration: 1. Rectangular Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-2, "Rectangular Elbows." a. Velocity 1000 fpm (5 m/s) or Lower: 1) 2) b. Velocity 1000 to 1500 fpm (5 to 7.6 m/s): 1) 2) 3) 2. Radius Type RE 1 with minimum 1.0 radius-to-diameter ratio. Radius Type RE 3 with minimum 0.5 radius-to-diameter ratio and two vanes. Mitered Type RE 2 with vanes complying with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-3, "Vanes and Vane Runners," and Figure 2-4, "Vane Support in Elbows." Rectangular Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-2, "Rectangular Elbows." a. b. c. 3. Radius Type RE 1 with minimum 0.5 radius-to-diameter ratio. Mitered Type RE 4 without vanes. Radius Type RE 1 with minimum 1.5 radius-to-diameter ratio. Radius Type RE 3 with minimum 1.0 radius-to-diameter ratio and two vanes. Mitered Type RE 2 with vanes complying with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-3, "Vanes and Vane Runners," and Figure 2-4, "Vane Support in Elbows." Round Duct: Comply with SMACNA's "HVAC Duct Construction Standards Metal and Flexible," Figure 3-3, "Round Duct Elbows." a. Minimum Radius-to-Diameter Ratio and Elbow Segments: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Table 3-1, "Mitered Elbows." Elbows with less than 90-degree change of direction have proportionately fewer segments. 1) 2) 3) b. c. Velocity 1000 fpm (5 m/s) or Lower: 0.5 radius-to-diameter ratio and three segments for 90-degree elbow. Velocity 1000 to 1500 fpm (5 to 7.6 m/s): 1.0 radius-to-diameter ratio and four segments for 90-degree elbow. Radius-to Diameter Ratio: 1.5. Round Elbows, 12 Inches (305 mm) and Smaller in Diameter: Stamped or pleated. Round Elbows, 14 Inches (356 mm) and Larger in Diameter: Welded. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 20 Metal Ducts June 30, 2010 E. Branch Configuration: 1. Rectangular Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-6, "Branch Connections." a. b. 2. Rectangular Main to Rectangular Branch: 45-degree entry. Rectangular Main to Round Branch: Spin in. Round and Flat Oval: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-4, "90 Degree Tees and Laterals," and Figure 3-5, "Conical Tees." Saddle taps are permitted in existing duct. a. b. Velocity 1000 fpm (5 m/s) or Lower: 90-degree tap. Velocity 1000 to 1500 fpm (5 to 7.6 m/s): Conical tap. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233113 - 21 Metal Ducts June 30, 2010 SECTION 233300 AIR DUCT ACCESSORIES PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. B. Requirements of Section 230500 shall also govern work specified together with all applicable paragraphs of other Division 23 sections. 1.2 SUMMARY A. Section Includes: 1. 2. 3. 4. 5. 6. 7. 8. 9. B. Related Sections: 1. 2. 1.3 Manual volume dampers. Control dampers. Fire dampers. Flange connectors. Turning vanes. Duct-mounted access doors. Flexible connectors. Flexible ducts. Duct accessory hardware. Division 23 Section "HVAC Gravity Ventilators" for roof-mounted ventilator caps. Division 28 Section "Fire Detection and Alarm" for duct-mounted fire and smoke detectors. SUBMITTALS A. Product Data: For each type of product indicated. 1. B. For duct silencers, include pressure drop and dynamic insertion loss data. Include breakout noise calculations for high transmission loss casings. Shop Drawings: For duct accessories. Include plans, elevations, sections, details, product data and attachments to other work, include with ductwork shop drawings 1. Detail duct accessories fabrication and installation in ducts and other construction. Include dimensions, weights, loads, and required clearances; and Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 1 Air Duct Accessories June 30, 2010 method of field assembly into duct systems and other construction. Include the following: a. b. c. d. e. f. g. h. i. j. Special fittings. Manual volume damper installations. Concealed volume damper operators, with locations shown on the ductwork shop drawings, and details/method of installation to finished surfaces. Control damper installations. Fire-damper, smoke-damper, combination fire- and smoke-damper, ceiling, and corridor damper installations, including sleeves; and ductmounted access doors and remote damper operators. Include installation details for angles, sleeves, breakaway connections, out-of-wall installations, and factory insulation. Duct security bars. Wiring Diagrams: For power, signal, and control wiring. Duct access doors Duct test holes Duct Silencers: 1) 2) 3) 4) 5) 6) 7) 8) Submit shop drawings and product data under provisions of this Division and Division 1 as applicable. Shop Drawings: Indicate assembly, materials, thicknesses, dimensional data, pressure losses, acoustical performance, layout, and connection details. Product Data: Provide catalog information indicating, materials, dimensional data, pressure losses, acoustical performance and conformance with Reference Standards applicable. Test Reports: Indicate dynamic insertion loss and noise generation values of silencers meet or exceed specified sound transmission loss values. Do not exceed static pressure drops indicated in the equipment schedules. Manufacturers Installation Instructions: Indicate Installation requirements which maintain integrity of sound isolation. Manufacturers Field Reports: Submit under provisions of General Conditions and Division 1 as applicable. Indicate installation is complete and in accordance with instructions. Submittals and Report: Definitions conform to ANSI S1.1. Schedule of acoustic lining, showing type, thickness and location. C. Coordination Drawings: Reflected ceiling plans, drawn to scale, on which ceilingmounted access panels and access doors required for access to duct accessories are shown and coordinated with each other, using input from Installers of the items involved. D. Source quality-control reports. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 2 Air Duct Accessories June 30, 2010 E. Operation and Maintenance Data: For air duct accessories to include in operation and maintenance manuals. F. Manufacturer’s installation instructions. 1.4 QUALITY ASSURANCE A. Reference Standards: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. NFPA 90A - Installation of Air Conditioning and Ventilating Systems. NFPA 90B - Installation of Warm Air Heating and Air Conditioning Systems. SMACNA - Low Pressure Duct Construction Standards. UL 33 - Heat Responsive Links for Fire-Protection Service. UL 555 and UL 555S- Fire Dampers and Smoke Dampers. ADC 1062 - Certification, Rating and test Manual. AMCA 500- Test Method for Louvers, Dampers and Shutters. ARI 650 - Air Outlets and Inlets. ASHRAE 70 - Method of Testing for Rating the Air Flow Performance of Outlets and Inlets. AMCA 300 - Test Code for Sound Rating. AMCA 301 - Methods for Calculating Fan Sound Ratings from Laboratory Test Data. AMCA 302 - Application of Sound Loudness Ratings for Non-Ducted Air Moving Devices. AMCA 303 - Application of Sound Power Level Ratings for Ducted Air Moving Devices Recommended Typical dBa Calculation. ANSI S1.1 - Acoustical Terminology (Including Mechanical Shock and Vibration). ANSI S1.8 - Preferred Reference Quantities for Acoustical Levels. ANSI S1.13 - Methods for Measurement of Sound Pressure Levels. ARI 575 - Measuring Machinery Sound Within Equipment Rooms. ASA 16 (ANSI S1.36) - Survey Methods for Determination of Sound Power Levels of Noise Sources. ASA 47 (ANSI S1.4) - Specification for Sound Level Meters. ASA 49 (ANSI S12.1) - Preparation of Standard Procedures to Determine the Noise Emission from Sources. ASHRAE 68 - Method of Testing In-Duct Sound Power Measurement Procedure for Fans. ASHRAE Handbook - Systems Volume, Chapter “Sound and Vibration Control”. ASTM E90 - Method for Laboratory Measurement of Airborne Sound Transmission of Building Partition. ASTM E477 - Method of Testing Duct Liner Materials and Prefabricated Silencers for Acoustical and Airflow Performance. ASTM E596 - Method for Laboratory Measurement of the Noise Reduction of Sound Isolating Enclosures. NEBB - Procedural Standards for Measuring Sound and Vibration. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 3 Air Duct Accessories June 30, 2010 B. 1.5 Comply with AMCA 500-D testing for damper rating. EXTRA MATERIALS A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. 2. Fusible Links: Furnish quantity equal to 10 percent of amount installed. Special tools for concealed volume damper operator: one per floor. PART 2 PRODUCTS 2.1 MATERIALS A. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" for acceptable materials, material thicknesses, and duct construction methods unless otherwise indicated. Sheet metal materials shall be free of pitting, seam marks, roller marks, stains, discolorations, and other imperfections. B. Galvanized Sheet Steel: Comply with ASTM A 653/A 653M. 1. 2. Galvanized Coating Designation: G60 (Z180). Exposed-Surface Finish: Mill phosphatized. C. Stainless-Steel Sheets: Comply with ASTM A 480/A 480M, Type 304, and having a No. 2 finish for concealed ducts and finish to be specified by architect for exposed ducts. D. Aluminum Sheets: Comply with ASTM B 209 (ASTM B 209M), Alloy 3003, Temper H14; with mill finish for concealed ducts and standard, 1-side bright finish for exposed ducts. E. Extruded Aluminum: Comply with ASTM B 221 (ASTM B 221M), Alloy 6063, Temper T6. F. Reinforcement Shapes and Plates: Galvanized-steel reinforcement where installed on galvanized sheet metal ducts; compatible materials for aluminum and stainless-steel ducts. G. Tie Rods: Galvanized steel, 1/4-inch (6-mm) minimum diameter for lengths 36 inches (900 mm) or less; 3/8-inch (10-mm) minimum diameter for lengths longer than 36 inches (900 mm). 2.2 MANUAL VOLUME DAMPERS A. Standard, Steel, Manual Volume Dampers: Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 4 Air Duct Accessories June 30, 2010 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. b. c. 2. 3. 4. Standard leakage rating with linkage outside airstream. Suitable for horizontal or vertical applications. Frames: a. b. c. d. e. 5. c. d. 7. B. Dampers less than 12 inches (300mm): single blade. Dampers 12 inches (300mm) and greater: Opposed-blade design, 8 inches (200mm) wide. Stiffen damper blades for stability. Galvanized-steel, 16 gauge. Blade Axles: ½ inch (13mm) minimum steel, extending 6 inches (150mm) beyond frame. ½ inch (13mm) jackshaft for multisection dampers for singlesided actuation. Bearings: a. b. 8. Hat-shaped, galvanized-steel channels, 16 gauge minimum thickness. Mitered and welded corners. Flanges for attaching to walls and flangeless frames for installing in ducts. Dampers less than 12”: 4½ inches (115mm) wide. Dampers 12” and larger: minimum 5 inches (89mm) wide. Blades: a. b. 6. Ruskin Company. Air Balance Inc.; a division of Mestek, Inc. American Warming and Ventilating; a division of Mestek, Inc. Molded synthetic, 48 inches (1220mm) maximum spacing. Dampers in ducts with pressure classes of 3-inch wg (750 Pa) or less and greater than 18 inches (450mm) shall have axles full length of damper blades and bearings at both ends of operating shaft. Tie Bars and Brackets: Galvanized steel. Standard, Aluminum, Manual Volume Dampers: 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. b. c. 2. 3. Ruskin Company. Air Balance Inc.; a division of Mestek, Inc. American Warming and Ventilating; a division of Mestek, Inc. Standard leakage rating. Suitable for horizontal or vertical applications. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 5 Air Duct Accessories June 30, 2010 4. 5. Frames: Hat-shaped, 0.10-inch- (2.5-mm-) thick, aluminum sheet channels; frames with flanges for attaching to walls and flangeless frames for installing in ducts. Blades: a. b. c. d. e. 6. 7. Blade Axles: Nonferrous metal. Bearings: a. b. 8. 2.3 Multiple or single blade. Parallel- or opposed-blade design. Stiffen damper blades for stability. Roll-Formed Aluminum Blades: 0.10-inch- (2.5-mm-) thick aluminum sheet. Extruded-Aluminum Blades: 0.050-inch- (1.2-mm-) thick extruded aluminum. Molded synthetic. Dampers in ducts with pressure classes of 3-inch wg (750 Pa) or less shall have axles full length of damper blades and bearings at both ends of operating shaft. Tie Bars and Brackets: Aluminum. CONTROL DAMPERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. Ruskin Company. Greenheck Fan Corporation. American Warming and Ventilating; a division of Mestek, Inc. B. Low-leakage rating, with linkage outside airstream, and bearing AMCA's Certified Ratings Seal for both air performance and air leakage. Less than 10cfm/sqft at 4 inches WG. C. Frames: 1. 2. 3. 4. 5. 6. 7. D. Hat shaped. Galvanized-steel channels, 16 gauge. Mitered and welded corners. Flanges for attaching to walls and flangeless frames for installing in ducts. Dampers less than 12 inches (300mm): 4½ inches (115mm) wide. Dampers 12 inches (300mm) and larger: minimum 5 inches (89mm) wide. Stainless steel jamb seals. Blades: Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 6 Air Duct Accessories June 30, 2010 1. 2. 3. 4. 5. E. Blade Axles: 1/2-inch- (13-mm-) diameter; plated steel extending minimum 6 inches (150mm) beyond frame; blade-linkage hardware of zinc-plated steel and brass; ends sealed against blade bearings. ½ inch (13mm) jackshaft for multisection dampers for single-sided actuation. 1. F. Operating Temperature Range: From minus 25 to plus 180 deg F (minus 32 to plus 83 deg C). Bearings: 1. 2. 3. 2.4 Multiple blade with maximum blade width of 6 inches (150 mm). Opposed-blade design. Galvanized steel. 16 gauge. Blade Edging: PVC. Molded synthetic. Dampers in ducts with pressure classes of 3-inch wg (750 Pa) or less and greater than 18 inches (450mm) shall have axles full length of damper blades and bearings at both ends of operating shaft. Thrust bearings at each end of every blade. DAMPER REGULATORS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following complete with dial regulator, square end bearing, and spring end bearing for accessible damper locations: 1. 2. B. Shaft length 12 inches (300mm) or less: 1. 2. 3. 4. 5. 6. C. Ventfabrics, Inc. Young Regulator Co. ¼ inch (6mm) dial regulator. Die cast steel with heavy gauge dial. 3/32 inch (2.5mm) steel handle. ¾ inch (19mm) hexagonal nut. All steel components zinc plated. Provide elevated dial or shaft extension for use on insulated ducts. Shaft length greater than 12 inches (300mm) and less than 20 inches (500mm): 1. 2. 3. 4. 5. 6. 3/8 inch (9.5mm) dial regulator. Die cast steel with heavy gauge dial. 3/32 inch (2.5mm) steel handle. ¾ inch (19mm) hexagonal nut. All steel components zinc plated. Provide elevated dial or shaft extension for use on insulated ducts. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 7 Air Duct Accessories June 30, 2010 D. Shaft length 20 inches (500mm) or greater: 1. 2. 3. 4. 5. 6. 2.5 Die-cast steel. Self-locking regulator with locking nut. Heavy steel stamped handle. Serrated teeth to prevent slippage with flat spring between the two pieces. Gasket. Provide elevated dial or shaft extension for use on insulated ducts. FIRE DAMPERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. Ruskin Company. Greenheck Fan Corporation. Air Balance Inc.; a division of Mestek, Inc. B. Type: Dynamic; rated and labeled according to UL 555 by an NRTL. C. Closing rating in ducts up to 4-inch wg (1-kPa) static pressure class and minimum2000fpm (10-m/s) velocity. D. Fire Rating: 1-1/2 hours in a 2 hour wall, ½ hour in a 1 hour wall. E. Frame: Curtain type with blades outside airstream; fabricated with roll-formed, 0.034inch- (0.85-mm-) thick galvanized steel; with mitered and interlocking corners. F. Mounting Sleeve: Factory- or field-installed, galvanized sheet steel. 1. 2. Minimum Thickness: 0.052 or 0.138 inch (1.3 or 3.5 mm) thick, as indicated, and of length to suit application. Exception: Omit sleeve where damper-frame width permits direct attachment of perimeter mounting angles on each side of wall or floor; thickness of damper frame must comply with sleeve requirements. G. Mounting Orientation: Vertical or horizontal as indicated. H. Blades: Roll-formed, interlocking, 0.034-inch- (0.85-mm-) thick, galvanized sheet steel. In place of interlocking blades, use full-length, 0.034-inch- (0.85-mm-) thick, galvanized-steel blade connectors. I. Horizontal Dampers: Include blade lock and stainless-steel closure spring. J. Heat-Responsive Device: Replaceable, 165 deg F (74 deg C) rated, fusible links. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 8 Air Duct Accessories June 30, 2010 2.6 FLANGE CONNECTORS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. Ductmate Industries, Inc. Nexus PDQ; Division of Shilco Holdings Inc. Ward Industries, Inc.; a division of Hart & Cooley, Inc. B. Description: roll-formed, factory-fabricated, slide-on transverse flange connectors, gaskets, and components. C. Material: Galvanized steel. D. Gage and Shape: Match connecting ductwork. 2.7 TURNING VANES A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. 4. 5. B. Ductmate Industries, Inc. Duro Dyne Inc. METALAIRE, Inc. SEMCO Incorporated. Ward Industries, Inc.; a division of Hart & Cooley, Inc. Manufactured Turning Vanes for Metal Ducts: Curved blades of galvanized sheet steel; support with bars perpendicular to blades set; set into vane runners suitable for duct mounting. 1. Acoustic Turning Vanes: Fabricate airfoil-shaped aluminum extrusions with perforated faces and fibrous-glass fill. C. Manufactured Turning Vanes for Nonmetal Ducts: Fabricate curved blades of resinbonded fiberglass with acrylic polymer coating; support with bars perpendicular to blades set; set into vane runners suitable for duct mounting. D. General Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible"; Figures 2-3, "Vanes and Vane Runners," and 2-4, "Vane Support in Elbows." E. Vane Construction: 1. Single wall a. b. For use with lower than 3 inch wg (750 Pa) pressure classification system, except as noted. ¾ inch (19mm) trailing edge and 2 inch (50mm) radius. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 9 Air Duct Accessories June 30, 2010 c. d. 2. Double wall a. b. 3. 2.8 Type Y blades for ducts 36 inches (915mm) or less in width. Type Z blades for ducts greater than 36 inches (915mm) in width. For use with 3 inch wg (750Pa) and higher pressure classification systems. Small double thickness vanes with 2 inch (50mm) inside radius. Vane length not to exceed 36 inches (915mm). Provide separate equal size section for greater lengths. DUCT-MOUNTED ACCESS DOORS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. B. Ventfabrics, Inc. Greenheck Fan Corporation. American Warming and Ventilating; a division of Mestek, Inc. Duct-Mounted Access Doors: Fabricate access panels according to SMACNA's "HVAC Duct Construction Standards - Metal and Flexible"; Figures 2-10, "Duct Access Doors and Panels," and 2-11, "Access Panels - Round Duct." 1. Door: a. b. c. d. e. f. g. 2. 3. Double wall, rectangular, minimum 18 inch x 18 inch (450mmx450mm), or as indicated. Galvanized sheet metal fabricated of the same material, finish and gauge as the ductwork (minimum 20 gauge). Vision panel if indicated Hinges and Latches: 1-by-1-inch (25-by-25-mm) butt or piano hinge and cam latches. Fabricate doors airtight and suitable for duct pressure class. Design lock edge of doors with a bevel of 1/8-inch (3mm) in 1 inch (25mm) and fill interior hollow space with insulation, thermally equivalent to the ductwork insulation. Lap inner face of door over duct opening, a minimum of 1/4-inch (6mm) on all four edges of the free duct opening. Frame duct opening for each door with a continuous 1 inch by 1 inch (25mmx25mm) by 12 gauge sheet metal angle, of the same material as the duct in which installed, riveted to the exterior surface of the duct opening. Frame: Galvanized sheet steel, with bend-over tabs and foam gaskets. Number of Hinges and Locks: a. Access Doors up to 18 Inches (460 mm) Square: Two hinges and two sash locks, with inside striker for contacting inside of door framing to provide a compression fit. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 10 Air Duct Accessories June 30, 2010 b. 4. 5. 6. 2.9 Access Doors 24 inches and greater (600 mm): Three hinges and two compression latches. Butt hinges: Provide galvanized steel with brass pins, approximately 2 inches by 1-1/2 inches wide (50mmx38mm) for doors under 24 inches (610mm) high; hinges 3 inches by 2 inches wide (75mmx50mm) for doors 24 inches (610mm) higher and greater. Casement fasteners: Steel or cast aluminum with a galvanized or aluminized finish. Door latches: operable rustproof zinc/aluminum alloy latch accessible from inside and outside duct. Steel and sponge rubber washers to prevent leakage. Beveled flange to work against frame to achieve compression. DUCT ACCESS PANEL ASSEMBLIES A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. Ductmate Industries, Inc. Flame Gard, Inc. 3M. B. Labeled according to UL 1978 by an NRTL. C. Panel and Frame: Minimum thickness 0.0428-inch (1.1-mm) stainless steel. D. Fasteners: Stainless steel. Panel fasteners shall not penetrate duct wall. E. Gasket: Comply with NFPA 96; grease-tight, high-temperature ceramic fiber, rated for minimum 2000 deg F (1093 deg C). F. Minimum Pressure Rating: 10-inch wg (2500 Pa), positive or negative. 2.10 A. FLEXIBLE CONNECTORS Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. Duro Dyne Inc. Ventfabrics, Inc. Ductmate Industries, Inc. B. Materials: Flame-retardant or noncombustible fabrics, in compliance with ASTM E84. C. Coatings and Adhesives: Comply with UL 181, Class 1. D. Metal-Edged Connectors: Factory fabricated with a fabric strip 3-inches (75 mm) wide attached to 2 strips of 3-inch- (75-mm-) wide, 16 gauge, galvanized sheet steel or Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 11 Air Duct Accessories June 30, 2010 0.032-inch- (0.8-mm-) thick aluminum sheets. Provide metal compatible with connected ducts. E. Indoor System, Flexible Connector Fabric: Glass fabric double coated with neoprene. 1. 2. 3. F. Outdoor System, Flexible Connector Fabric: Glass fabric double coated with weatherproof, synthetic rubber resistant to UV rays and ozone. 1. 2. 3. G. 3. Minimum Weight: 16 oz./sq. yd. (542 g/sq. m). Tensile Strength: 285 lbf/inch (50 N/mm) in the warp and 185 lbf/inch (32 N/mm) in the filling. Service Temperature: Minus 67 to plus 500 deg F (Minus 55 to plus 260 deg C). High-Corrosive-Environment System, Flexible Connectors: Glass fabric with chemical-resistant coating. 1. 2. 3. I. Minimum Weight: 24 oz./sq. yd. (810 g/sq. m). Tensile Strength: 530 lbf/inch (93 N/mm) in the warp and 440 lbf/inch (77 N/mm) in the filling. Service Temperature: Minus 50 to plus 250 deg F (Minus 45 to plus 121 deg C). High-Temperature System, Flexible Connectors: Glass fabric coated with silicone rubber. 1. 2. H. Minimum Weight: 26 oz./sq. yd. (880 g/sq. m). Tensile Strength: 480 lbf/inch (84 N/mm) in the warp and 360 lbf/inch (63 N/mm) in the filling. Service Temperature: Minus 40 to plus 200 deg F (Minus 40 to plus 93 deg C). Minimum Weight: 14 oz./sq. yd. (474 g/sq. m). Tensile Strength: 450 lbf/inch (79 N/mm) in the warp and 340 lbf/inch (60 N/mm) in the filling. Service Temperature: Minus 67 to plus 500 deg F (Minus 55 to plus 260 deg C). Thrust Limits: Combination coil spring and elastomeric insert with spring and insert in compression, and with a load stop. Include rod and angle-iron brackets for attaching to fan discharge and duct. 1. 2. 3. 4. 5. 6. Frame: Steel, fabricated for connection to threaded rods and to allow for a maximum of 30 degrees of angular rod misalignment without binding or reducing isolation efficiency. Outdoor Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load. Minimum Additional Travel: 50 percent of the required deflection at rated load. Lateral Stiffness: More than 80 percent of rated vertical stiffness. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure. Elastomeric Element: Molded, oil-resistant rubber or neoprene. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 12 Air Duct Accessories June 30, 2010 7. J. 2.11 A. Connector construction shall be such to resist static pressure of ductwork systems as specified in 233113 (ductwork) or as shown on the drawings. FLEXIBLE DUCTS Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. 3. 4. 5. B. 2. 3. 4. 5. Pressure Rating: 10-inch wg (2500 Pa) positive and 0.5-inch wg (125 Pa) negative. Maximum Air Velocity: 5000 fpm (25 m/s). Temperature Range: Minus 20 to plus 200 deg F (Minus 29 to plus 93 deg C). Water Vapor Permeance: 0.17 grains per sq. ft. per hour per inch of Hg. (Test Method: ASTM E 96, Procedure A) Insulation R-Value: R-4.2 minimum at 75 deg F. Flexible Duct Connectors: 1. 2. E. Pressure Rating: 10-inch wg (2500 Pa) positive and 1-inch wg (250 Pa) negative. Maximum Air Velocity: 5000 fpm (20 m/s). Temperature Range: Minus 20 to plus 200 deg F (Minus 29 to plus 93 deg C). Insulated, Flexible Duct: UL 181, Class 1, black polymer film supported by helically wound, spring-steel wire; fibrous-glass insulation; metallized polyester vapor-barrier film. Provide 100% separation of airstream and fiberglass through non-perforated core. Individual lengths with factory fabricated steel compression clamp connection collars at both ends. 1. D. Thermaflex MKE Cody Company, Inc. Flexmaster U.S.A., Inc. McGill AirFlow LLC. Ward Industries, Inc.; a division of Hart & Cooley, Inc. Noninsulated, Flexible Duct: UL 181, Class 1, black polymer film supported by helically wound, spring-steel wire. 1. 2. 3. C. Coil Spring: Factory set and field adjustable for a maximum of 1/4-inch (6-mm) movement at start and stop. Clamps: Stainless-steel band with cadmium-plated hex screw to tighten band with a worm-gear action in sizes 3 through 18 inches (75 through 460 mm), to suit duct size. Non-Clamp Connectors: Liquid adhesive plus tape. Regenerative Noise: Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 13 Air Duct Accessories June 30, 2010 1. Noise due to air turbulence within the duct shall not exceed the following sound power levels for a 12-inch diameter duct with an air speed of 1,000 feet per minute. Octave band center frequency (Hz) Sound power levels (dB) referenced to 10-12 watts 2.12 125 250 500 1000 2000 30 31 30 22 20 DUCT ACCESSORY HARDWARE A. Instrument Test Holes: Cast iron or cast aluminum to suit duct material, including screw cap and gasket. Size to allow insertion of pitot tube and other testing instruments and of length to suit duct-insulation thickness. Permanent test holes shall be factory fabricated, air tight flanged fittings with screw cap. Provided extended neck fitting to clear insulation as required. B. Adhesives: High strength, quick setting, neoprene based, waterproof, and resistant to gasoline and grease. C. Blanking Plate: 16 gauge galvanized sheet metal, painted matt black cut to size as required. D. Blanking Panel: Construct from 18 gauge galvanized sheet metal sandwich with 1 inch thick (25mm), 1 1/2 lb cu. ft density rigid board fiberglass insulation. Attach insulation to metal with adhesive fasteners and edge tape. Overlap front and back metal plates and tack weld at 3 inch (76mm) centers. E. Perforated Plate: Construct from 16 gauge galvanized steel with circular holes equally distributed and equally sized to achieve the free area required. Galvanized after perforating. F. Flashing: 16 gage ducts through roof, galvanized steel, flashed and counterflashed, and provided with storm collars to secure watertight construction. G. Bird Screens: 14 gauge, 1/2-inch (12mm) galvanized wire mesh set in galvanized steel frame. H. Equalizing Grid: 3 inch (76mm) thick aluminum honeycomb grid with 3/8-inch (9.5mm) openings securely fastened inside a 16 gauge galvanized steel duct section 6 inches (150mm) long. Grid and casing in outside air intake duct shall be 304 stainless steel. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 14 Air Duct Accessories June 30, 2010 PART 3 EXECUTION 3.1 INSTALLATION A. Install duct accessories according to applicable details in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" for metal ducts and in NAIMA AH116, "Fibrous Glass Duct Construction Standards," for fibrous-glass ducts. B. Install duct accessories of materials suited to duct materials; use galvanized-steel accessories in galvanized-steel and fibrous-glass ducts, stainless-steel accessories in stainless-steel ducts, and aluminum accessories in aluminum ducts. C. Install backdraft or control dampers at outlet of exhaust fans or exhaust ducts as close as possible to exhaust fan unless otherwise indicated. D. Install volume dampers at points on supply, return, and exhaust systems where branches extend from larger ducts. Where dampers are installed in ducts having duct liner, install dampers with hat channels of same depth as liner, and terminate liner with nosing at hat channel. 1. 2. Install steel volume dampers in steel ducts. Install aluminum volume dampers in aluminum ducts. E. Set dampers to fully open position before testing, adjusting, and balancing. F. Provide concealed remove volume damper operators for all volume dampers in inaccessible locations. Operator shall be installed within the ceiling or wall such that the unit is flush with the finished surface. Operators for diffusers shall not be located in active supply portions of the diffuser, but may be installed in blank-off locations and/or return diffusers. Coordinate location of operator with the Architect. G. Install test holes at fan inlets and outlets, and as required for testing and balancing, and elsewhere as indicated. H. Install fire, smoke, and combination fire and smoke dampers according to UL listing. I. Demonstrate resetting of fire dampers / fire & smoke dampers to the AHJ. J. Provide fire and smoke dampers, fire dampers at locations where ducts and outlets pass through fire rated components. Install with required perimeter mounting angles, sleeves, breakaway duct connections, corrosion resistant springs, bearings, bushings and hinges. Install all dampers in accordance with SMACNA fire damper guide and manufacturer’s instructions. K. Install duct access doors on sides of ducts to allow for inspecting, adjusting, and maintaining accessories and equipment at the following locations: 1. 2. On both sides of duct coils. Upstream and downstream from duct filters. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 15 Air Duct Accessories June 30, 2010 3. 4. 5. 6. 7. 8. 9. At outdoor-air intakes and mixed-air plenums. Downstream from manual volume dampers, control dampers, and equipment. Adjacent to and close enough to fire or smoke dampers, to reset or reinstall fusible links. Access doors for access to fire or smoke dampers having fusible links shall be pressure relief access doors and shall be outward operation for access doors installed upstream from dampers and inward operation for access doors installed downstream from dampers. At each change in direction and at maximum 50-foot (15-m) spacing. Upstream from turning vanes. Control devices requiring inspection. Elsewhere as indicated. L. Install access doors with swing against duct static pressure. M. Access Door Sizes: 1. 2. 3. 4. Two-Hand Access: 12 by 12 inches (300 by 300 mm). Head and Shoulders Access: 18 by 18 inches (450 by 450 mm). Body Access: 25 by 14 inches (635 by 355 mm). Body plus Ladder Access: 25 by 17 inches (635 by 430 mm). N. Label access doors according to Division 23 Section "Identification for HVAC Equipment" to indicate the purpose of access door. O. On doors of systems where fan is scheduled for 4 inches static pressure or greater, provide painted signs appropriately worded as follows: 1. 2. P. Install flexible connectors to connect ducts to motorized equipment. 1. Q. CAUTION – DOOR CLOSES WITH AIR PRESSURE CAUTION – DOOR OPENS WITH AIR PRESSURE Connectors shall not be less than 6 inches long or more than 10 inches long. Provide ductwork connected to air inlet and outlet devices, with all necessary transformation pieces, flexible fabric connections, as required. 1. 2. For round duct connection, install fabric connectors a minimum of 3 inches (76mm) in length for ducts having a maximum diameter of 18 inches (450mm) and a minimum of 5 inches (125mm) in length for duct diameters over 18 inches (450mm) in size. Secure fabric connectors tightly to fans, casings and ducts as follows: a. b. Secure round connectors with 12 gauge by 1 inch (25mm) wide galvanized steel draw bands. Secure bands with bolts and nuts. Secure rectangular connectors with 1 inch by 1/8-inch (25mmx3mm) thick flat galvanized steel bars, with screws or bolts on 8 inch (200mm) centers maximum, or with sheet metal slip joints. Tightly crimp fabric into sheet Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 16 Air Duct Accessories June 30, 2010 metal joint and secure complete joint with sheet metal screws on 6-inch centers maximum. 3. 4. 5. 6. Allow at least 3 inch (76mm) slack in connections. Fabric connectors may be factory pre-fabricated pre-assembled units, with minimum 24 gauge metal edges, secured to fabric with double lock seams. Do not paint fabric connectors. Install also in ducts at structural expansion joints. R. Connect terminal units to supply ducts directly. Do not use flexible ducts to change directions. S. Connect diffusers or light troffer boots to ducts with maximum 36-inch (920-mm) lengths of flexible duct clamped or strapped in place. T. Connect flexible ducts to metal ducts with draw bands. Duct collars exceeding 12” dia. Shall have draw bands positioned behind a bead on the metal collar, per SMACNA. U. Install duct test holes where required for testing and balancing purposes. V. Install thrust limits at centerline of thrust, symmetrical on both sides of equipment. Attach thrust limits at centerline of thrust and adjust to a maximum of 1/4-inch (6-mm) movement during start and stop of fans. W. Provide wire mesh screens on all duct openings that do not contain grilles or access panels. 3.2 FIELD QUALITY CONTROL A. Tests and Inspections: 1. 2. 3. 4. Operate dampers to verify full range of movement. Inspect locations of access doors and verify that purpose of access door can be performed. Operate fire, smoke, and combination fire and smoke dampers to verify full range of movement and verify that proper heat-response device is installed. Inspect turning vanes for proper and secure installation. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233300 - 17 Air Duct Accessories June 30, 2010 SECTION 233416 CENTRIFUGAL HVAC FANS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. 1.3 Backward-inclined centrifugal fans. Forward-curved centrifugal fans. PERFORMANCE REQUIREMENTS A. Project Altitude: Base fan performance ratings on actual Project site elevations above sea level. B. Operating Limits: Classify according to AMCA 99. 1.4 SUBMITTALS A. Product Data: Include rated capacities, furnished specialties, and accessories for each type of product indicated and include the following: 1. 2. 3. 4. 5. 6. B. Non-generic certified fan performance curves with system specific operating conditions indicated. Certified fan sound-power ratings. Motor ratings and electrical characteristics, plus motor and electrical accessories. Material thickness and finishes, including color charts. Dampers, including housings, linkages, and operators. Accessories. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection. 1. 2. Wiring Diagrams: Power, signal, and control wiring. Design Calculations: Calculate requirements for selecting vibration isolators and for designing vibration isolation bases. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 1 Centrifugal HVAC Fans June 30, 2010 3. Vibration Isolation Base Details: Detail fabrication, including anchorages and attachments to structure and to supported equipment. Include auxiliary motor slides and rails, and base weights. C. Coordination Drawings: Show fan room layout and relationships between components and adjacent structural and mechanical elements. Show support locations, type of support, and weight on each support. Indicate and certify field measurements. D. Field quality-control test reports. E. Operation and Maintenance Data: For centrifugal fans to include in emergency, operation, and maintenance manuals. 1.5 QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. B. AMCA Compliance: Products shall comply with performance requirements and shall be licensed to use the AMCA-Certified Ratings Seal. C. NEMA Compliance: Motors and electrical accessories shall comply with NEMA 1. D. AMCA 99 - Standards Handbook. E. AMCA 210 - Laboratory Methods of Testing Fans for Rating Purposes. F. AMCA 300 - Test Code for Sound Rating Air Moving Devices. G. AMCA 301 - Method of Calculating Fan Sound Ratings from Laboratory Test Data. H. ANSI/ABMA 9 - Load Ratings and Fatigue Life for Ball Bearings. I. ANSI/ABMA 11 - Load Ratings and Fatigue Life for Roller Bearings. J. Casing corrosion compliance: All external casings shall be able to sustain 1000 hour salt spray test in accordance with ASTM B117 - Test Method of Salt Spray [Fog] Testing. 1.6 DELIVERY, STORAGE, AND HANDLING A. Deliver fans as factory-assembled units, to the extent allowable by shipping limitations, with protective crating and covering. B. Disassemble and reassemble units, as required for moving to the final location, according to manufacturer's written instructions. C. Lift and support units with manufacturer's designated lifting or supporting points. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 2 Centrifugal HVAC Fans June 30, 2010 D. 1.7 Protect motors, shafts, and bearing from weather and construction dust. COORDINATION A. Coordinate size and location of structural-steel support members. B. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified in Division 03. C. Coordinate installation of roof curbs, equipment supports, and roof penetrations. These items are specified in Division 07 Section "Roof Accessories." 1.8 WARRANTY A. 1.9 The manufacturer shall provide the parts warranty for equipment manufactured and all vendor supplied components. The said warranty shall cover replacement of all defective parts for a period of 12 months from equipment start up. EXTRA MATERIALS A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Belts: One set for each belt-driven unit. PART 2 PRODUCTS 2.1 BACKWARD-INCLINED CENTRIFUGAL FANS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. B. Greenheck. Loren Cook Company. Description: Factory-fabricated, -assembled, -tested, and -finished, belt-driven centrifugal fans consisting of housing, wheel, fan shaft, bearings, motor, drive assembly, and support structure. 1. 2. 3. Where noted, fan shall be UL listed for use as “Power Ventilators for Smoke Control Systems” for 500 deg F (260 deg C) maximum temperature for a minimum of 4 hours of operation. Fans shall be capable of accommodating static pressure variations of ±10%. Statically and dynamically balance fans to eliminate vibration or noise transmission to occupied areas. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 3 Centrifugal HVAC Fans June 30, 2010 C. Housings: Class 1 continuously welded heavy gauge steel formed panels to make curved-scroll housings with shaped cutoff; with doors to allow access to internal parts and components. 1. 2. 3. 4. 5. 6. Panel Bracing: Steel angle- or channel-iron member supports for mounting and supporting fan scroll, wheel, motor, and accessories. Horizontally split, bolted-flange housing. Spun inlet cone with flange. Outlet flange. Coatings: 2 mil (minimum) Polyester Urethane, exceeding the ASTM B117 1000 hour salt spray test. Provide lifting lugs. D. Backward-Inclined Wheels: Single-width-single-inlet galvanized steel construction with curved inlet flange, backplate, non-overloading curved backward-inclined blades welded to flange and backplate and fastened to shaft with set screws. E. Shafts: Statically and dynamically balanced and selected for continuous operation at maximum rated fan speed and motor horsepower, with final alignment and belt adjustment made after installation. 1. 2. F. Grease-Lubricated Shaft Bearings: Self-aligning, pillow-block-type, ball or roller bearings with adapter mount and two-piece, cast-iron housing. 1. 2. 3. G. Turned, ground, and polished hot-rolled steel with keyway. Ship with a protective coating of lubricating oil. Designed to operate at no more than 70 percent of first critical speed at top of fan's speed range. Ball-Bearing Rating Life: ABMA 9, Ll0 at 200,000 hours. Roller-Bearing Rating Life: ABMA 1, L50 at 400,000 hours. Extend lubrication lines to outside of casing and terminate with grease fittings. Belt Drives: Factory mounted, with final alignment and belt adjustment made after installation. 1. 2. 3. 4. 5. Service Factor Based on Fan Motor Size: 1.5. Fan Pulleys: Cast iron or cast steel with split, tapered bushing; dynamically balanced at factory with keyway. Motor Pulleys: Adjustable pitch for use with motors through 15 hp; fixed pitch for use with larger motors, matched belts, and drive rated as recommended by manufacturer or minimum 1.5 times nameplate rating of the motor. Select pulley so pitch adjustment is at the middle of adjustment range at fan design conditions. Belts: Oil resistant, nonsparking, and nonstatic; matched sets for multiple belt drives. Belt Guards: Fabricate to comply with OSHA and SMACNA requirements of diamond-mesh wire screen welded to steel angle frame or equivalent, prime coated. Secure to fan or fan supports without short circuiting vibration isolation. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 4 Centrifugal HVAC Fans June 30, 2010 6. H. Accessories: 1. 2. 3. 4. 5. 6. 7. 8. 9. I. Scroll Access Doors: Shaped to conform to scroll, with quick-opening latches and gaskets. Cleanout Door: Bolted gasketed door allowing access to fan scroll, of same material as housing. Scroll Drain Connection: NPS 1 (DN 25) steel pipe coupling welded to low point of fan scroll. Companion Flanges: Rolled flanges for duct connections of same material as housing. Fixed Inlet Vanes: Steel construction with fixed cantilevered inlet guide vanes welded to inlet bell. Inlet Screens: ½ inch (12mm) wire mesh grid screen of same material as housing. Shaft Cooler: Metal disk between bearings and fan wheel, designed to dissipate heat from shaft. High Temperature Shaft Seals: Airtight seals installed around shaft on drive side of single-width fans. Weather Cover: Enameled-steel sheet with ventilation slots, bolted to housing. Motors: Comply with requirements in Division 23 Section "Common Motor Requirements for HVAC Equipment." 1. 2.2 Include provisions for adjustment of belt tension, lubrication, and use of tachometer with guard in place. Motor Mount: Adjustable for belt tensioning. Enclosure Type: Totally enclosed, fan cooled. SQUARE INLINE CENTRIFUGAL FANS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. 2. B. Description: Factory-fabricated, -assembled, -tested, and -finished, belt-driven inline centrifugal fans consisting of housing, wheel, fan shaft, bearings, motor, drive assembly, and support structure. 1. 2. C. Greenheck. Loren Cook Company. Fans shall be capable of accommodating static pressure variations of ±10%. Statically and dynamically balance fans to eliminate vibration or noise transmission to occupied areas. Housings: Heavy gauge galvanized steel of square design with square duct mounting collars. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 5 Centrifugal HVAC Fans June 30, 2010 1. 2. Access panels: two panels perpendicular to the motor mounting panel shall be provided to allow full access to all interior fan components. Factory supplied mounting brackets for hung installation. D. Backward-Inclined Wheels: Aluminum construction and shall include a wheel cone carefully matched to the inlet cone for precise running tolerances. Wheels shall be statically and dynamically balanced. E. Shafts: Statically and dynamically balanced and selected for continuous operation at maximum rated fan speed and motor horsepower, with final alignment and belt adjustment made after installation. 1. 2. 3. F. Turned, ground, and polished hot-rolled steel with keyway. Ship with a protective coating of lubricating oil. Designed to operate at no more than 70 percent of first critical speed at top of fan's speed range. Ball-Bearing Rating Life: ABMA 9, L10 at 100,000 hours. Belt Drives: Factory mounted, with final alignment and belt adjustment made after installation. 1. 2. 3. 4. 5. 6. Service Factor Based on Fan Motor Size: 1.5. Fan Pulleys: Cast iron, and securely attached to the wheel and motor shafts; dynamically balanced at factory with keyway. Motor Pulleys: Adjustable pitch for use with motors through 15 hp; fixed pitch for use with larger motors, matched belts, and drive rated as recommended by manufacturer or minimum 1.5 times nameplate rating of the motor. Select pulley so pitch adjustment is at the middle of adjustment range at fan design conditions. Belts: Oil resistant, nonsparking, and nonstatic; matched sets for multiple belt drives. Belt Guards: Fabricate to comply with OSHA and SMACNA requirements of diamond-mesh wire screen welded to steel angle frame or equivalent, prime coated. Secure to fan or fan supports without short circuiting vibration isolation. Include provisions for adjustment of belt tension, lubrication, and use of tachometer with guard in place. Motor Mount: Adjustable for belt tensioning. G. Accessories: H. Motors: Comply with requirements in Division 23 Section "Common Motor Requirements for HVAC Equipment." 1. Motors and drives shall be mounted out of the airstream, and readily accessible for maintenance. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 6 Centrifugal HVAC Fans June 30, 2010 2.3 SOURCE QUALITY CONTROL A. Sound-Power Level Ratings: Comply with AMCA 301, "Methods for Calculating Fan Sound Ratings from Laboratory Test Data." Factory test fans according to AMCA 300, "Reverberant Room Method for Sound Testing of Fans." Label fans with the AMCACertified Ratings Seal. B. Fan Performance Ratings: Establish flow rate, pressure, power, air density, speed of rotation, and efficiency by factory tests and ratings according to AMCA 210, "Laboratory Methods of Testing Fans for Rating." C. Fan impeller balancing: balance fan impellers in accordance with AMCA Standard 20496. PART 3 EXECUTION 3.1 INSTALLATION A. Install centrifugal fans level and plumb. B. Support suspended units from structure using threaded steel rods and spring hangers having a static deflection of 2 inch (50 mm). Vibration-control devices are specified in Division 23 Section "Vibration and Seismic Controls for HVAC Equipment." C. Install units with clearances for service and maintenance. D. Label fans according to requirements specified in Division 23 Section "Identification for HVAC Equipment." E. Do not operate fans for any purpose until ductwork is clean, filters are in place, bearings lubricated, and fan has been test run under observation. F. Install fans as indicated. Install with resilient mountings specified in Section 230548 “Vibration and Seismic Controls for HVAC Equipment” and with flexible electrical leads. G. Install flexible connections specified in Section 233300 “Air Duct Accessories” between fan inlet and discharge ductwork. Ensure metal bands of connectors are parallel with minimum one inch flex between ductwork and fan while running. H. Install fan restraining snubbers. Flexible connectors shall not be in tension while running. I. Provide sheaves required for final air balance. J. Provide safety screen where inlet or outlet is exposed. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 7 Centrifugal HVAC Fans June 30, 2010 3.2 CONNECTIONS A. Duct installation and connection requirements are specified in other Division 23 Sections. Drawings indicate general arrangement of ducts and duct accessories. Make final duct connections with flexible connectors. Flexible connectors are specified in Division 23 Section "Air Duct Accessories." B. Install ducts adjacent to fans to allow service and maintenance. C. Ground equipment according to Division 26 Section "Grounding and Bonding for Electrical Systems." D. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power Conductors and Cables." 3.3 FIELD QUALITY CONTROL A. Perform the following field tests and inspections and prepare test reports: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. B. 3.4 Verify that shipping, blocking, and bracing are removed. Verify that unit is secure on mountings and supporting devices and that connections to ducts and electrical components are complete. Verify that proper thermal-overload protection is installed in motors, starters, and disconnect switches. Verify that cleaning and adjusting are complete. Disconnect fan drive from motor, verify proper motor rotation direction, and verify fan wheel free rotation and smooth bearing operation. Reconnect fan drive system, align and adjust belts, and install belt guards. Adjust belt tension. Adjust damper linkages for proper damper operation. Verify lubrication for bearings and other moving parts. Verify that manual and automatic volume control and fire and smoke dampers in connected ductwork systems are in fully open position. Refer to Division 23 Section "Testing, Adjusting, and Balancing for HVAC" for testing, adjusting, and balancing procedures. Remove and replace malfunctioning units and retest as specified above. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. STARTUP SERVICE A. Engage a factory-authorized service representative to perform startup service. B. Refer to “Owner’s Commissioning Requirements” for additional requirements. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 8 Centrifugal HVAC Fans June 30, 2010 3.5 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain centrifugal fans. Refer to Division 01 Section "Demonstration and Training" and “Owner’s Commissioning Requirements” for additional requirements. Roosevelt Hall Addition Brooklyn College Brooklyn, NY Project #6032.20 233416 - 9 Centrifugal HVAC Fans June 30, 2010 SECTION 230993 SEQUENCE OF OPERATIONS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Related Sections included the following: 1. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and equipment. B. Related Sections include the following: 1. 1.3 Division 15 Section "HVAC Instrumentation and Controls" for control equipment and devices and submittal requirements. DEFINITIONS A. DDC: Direct-digital controls. B. BMS: Building management system 1.4 SEQUENCE OF OPERATIONS A. Supply Fan and Electric Heating Coil 1. 2. 3. The supply fan and electric heating coil shall be controlled via space thermostat/controller. The BMS contractor shall provide and install. The supply fan and electric heating coils shall started/stopped by the BMS local controller based on a time of day schedule or a manual command from the controller. On a call for ventilation, the supply fan shall be cycled on/off to maintain setpoint. On a call for heating, the supply fan and electric heating coil (sequential 2-stage heating operation to maintain heating setpoint) shall be cycled on/off to maintain setpoint. Provide time delay and dead band to prevent short cycling between fan on/off and 2-stage heating control. The electric heating coil shall be disabled if supply fan is off as proven by air flow switch. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 230993- 1 Sequence of Operations June 30, 2010 SECTION 238216 AIR COILS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. 1.3 This Section includes the following types of air coils that are not an integral part of air-handling units: 1. Electric SUBMITTALS A. Product Data: For each type of product indicated. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for each air coil. Include rated capacity and pressure drop for each air coil. B. Shop Drawings: Diagram power, signal, and control wiring. C. Coordination Drawings: Reflected ceiling plans, drawn to scale, on which coil location and ceiling-mounted access panels are shown and coordinated with each other. D. Field quality-control test reports. E. Operation and Maintenance Data: manuals. 1.4 For air coils to include in operation and maintenance QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. B. ASHRAE Compliance: 1. Comply with ASHRAE 33 for methods of testing heating coils. 2. Comply with applicable requirements in ASHRAE 62.1-2004, Section 5 - "Systems and Equipment" and Section 7 - "Construction and Startup." Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 238216- 1 Air Coils June 30, 2010 PART 2 - PRODUCTS 2.1 ELECTRIC COILS A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: B. Manufacturers: Subject to compliance with requirements, provide products by one of the following: C. Basis-of-Design Product: Subject to compliance with requirements, provide INDEECO or a comparable product by one of the following: 1. 2. 3. 4. 5. INDEECO. Brasch Manufacturing Co., Inc. Chromalox, Inc., Wiegand Industrial Division; Emerson Electric Company. Dunham-Bush, Inc. Trane. D. Coil Assembly: Comply with UL 1995. E. Heating Elements: Open-coil resistance wire of 80 percent nickel and 20 percent chromium, supported and insulated by floating ceramic bushings recessed into casing openings, and fastened to supporting brackets. F. High-Temperature Coil Protection: Disk-type, automatically reset, thermal-cutout, safety device; serviceable through terminal box without removing heater from duct or casing. 1. Secondary Protection: Load-carrying, manually reset or manually replaceable, thermal cutouts; factory wired in series with each heater stage. G. Frames: Galvanized-steel channel frame, for slip-in mounting. H. Airflow Switch: A diaphragm-operated differential pressure switch to prevent the heater from operating unless the air is flowing. It senses pressure between process air and the terminal housing. I. Control Panel: Unit mounted with disconnecting means and overcurrent protection. Include the following controls: 1. 2. 3. 4. 5. 6. 7. 8. Magnetic contactor. Mercury contactor. Toggle switches; one per step. Step controller. Time-delay relay. Pilot lights; one per step. Airflow proving switch. Thermal Cutouts Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 238216- 2 Air Coils June 30, 2010 J. Refer to Division 23 Section "Instrumentation and Control for HVAC" for thermostat. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine ducts, plenums, and casings to receive air coils for compliance with requirements for installation tolerances and other conditions affecting coil performance. B. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. Install coils level and plumb. B. Install coils in metal ducts and casings constructed according to SMACNA's "HVAC Duct Construction Standards, Metal and Flexible." C. Straighten bent fins on air coils. D. Clean coils using materials and methods recommended in writing by manufacturers, and clean inside of casings and enclosures to remove dust and debris. 3.3 CONNECTIONS A. Ground equipment according to Division 26 Section "Grounding and Bonding for Electrical Systems." B. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power Conductors and Cables." 3.4 FIELD QUALITY CONTROL A. Perform the following field tests and inspections and prepare test reports: 1. 2. Operational Test: After electrical circuitry has been energized, operate electric coils to confirm proper unit operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. END OF SECTION 238216 Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 238216- 3 Air Coils June 30, 2010 SECTION 231600 ELECTRICAL COMMON WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS A. The Specifications and Contract Drawings shall form part of the Contract Documents. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. B. Where General and Supplement Conditions and General Requirements clauses are repeated in these Specifications, it is to call special attention to them, or as a further qualification. No General and Supplement Conditions and/or General Requirements clause referring to the work of this Section shall be considered waived unless specifically stated herein. C. Unless otherwise shown on the Contract Drawings, or unless otherwise specified in other Sections of these Specifications, the requirements specified in this Section are applicable to all electrical work of this Contract. Additional requirements applicable to individual Sections of these Specifications are specified in those Sections, or are shown on the Contract Drawings. 1.2 SUMMARY A. Provide all labor, materials, supplies, tools, machinery, equipment, scaffolding, transportation, rigging, storage, utilities, supervision and required permits and licenses necessary to complete the electrical work under this contract. B. Provide a complete working electrical installation with all equipment called for in proper operating condition. Documents do not undertake to show or list every item to be provided. When an item not shown or listed is clearly necessary for proper operation of equipment that is shown or listed, provide the item, which will allow the system to function properly at no increase in Contract Price. C. Coordinate the electrical work with the work of the other trades to resolve conflicts without impeding job progress or the construction schedule. D. Examine all Contract Documents including those of other trades in order to determine the extent of the Work required to be completed under this Section. Failure to examine all Contract Documents for this project will not relieve this contractor of the responsibility to perform all the Work required for a complete, fully operational and satisfactory installation. E. Bidders are deemed aware, based on the background and experience, of materials, which may be required in the discharge of their responsibilities, even though unspecified. Claims for extras for unspecified shoring or supporting materials will not be considered if the need for such materials would have been reasonably obvious to the bidders skilled and experienced in the work to be done and the submittal of a bid shall be deemed a waiver of any such claims. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 1 Electrical Common Work June 30, 2010 F. 1.3 Provide notice with bid proposal of any concrete or structural work required by this Section that is not indicated on the Structural or Architectural Drawings. DEFINITIONS A. “Architect”: the Architect of record. B. “Engineer”: the Engineer of record. C. “Contractor”: the individual, partnership or corporation to whom the Contract for the Electrical work has been awarded. D. "Provide": Shall mean furnish and install. E. "Furnish": to supply all materials, labor, equipment, testing apparatus, controls, tests, accessories, and all other items customarily required for the proper and complete application. F. "Install": to join; unite; fasten; link; attach; set up or otherwise connect together; complete, tested, and ready for normal satisfactory operation. G. “As Directed”: as directed by the Architect or the Engineer. H. “Submit”: I. “Finished Spaces” Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels. J. “Exposed, Interior Installations” Exposed to view indoors. Examples include finished occupied spaces and electrical equipment rooms. K. “Exposed, Exterior Installations” Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include equipment yards or rooftop locations. L. “Concealed, Interior Installations” Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and in wall conduits. M. “Concealed, Exterior Installations” Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures. Examples include installations within unheated shelters. N. "Connect": Shall mean make final electrical connections for a complete operating piece of equipment. O. “Equal”: Shall be of the same quality, appearance and utility to that specified, as determined by the Owner’s Representative. Contractor bears the burden of proof of equality. P. “Electrical Work”: The installation, alteration, maintenance, or repair of electric wires and wiring apparatus and other appliances used or to be used for the transmission of electricity for electric light, heat, power, signaling, communication, alarm or data transmission. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 submit to the Architect and/or the Engineer for review. 231600- 2 Electrical Common Work June 30, 2010 1.4 CODES, STANDARDS, FILING AND PERMITS A. The Electrical installation shall comply with the latest revised versions of all applicable laws, rules, regulations, standards, codes and ordinances of the federal, state and local authorities having jurisdiction and other requirements specified in other Specifications and Contract Drawings. B. If any of the provisions of the laws, rules, regulations, standards, codes, ordinances and requirements of the Contract Drawings or Specifications is in conflict with one another, the most stringent requirements shall govern. C. Nothing in the Contract Drawings or Specifications shall be construed to permit Work not conforming to the applicable laws, ordinances, rules, and regulations. It is not the intent of the Contract Drawings or Specifications to repeat the requirements of codes except where necessary for completeness or clarity. Any modifications required by the above said authorities having jurisdiction shall be made without additional cost to the Owner. Where Contract Drawings and Specifications requirements are in excess of the rules, regulations and code requirements, and are permitted under the code, the Contract Drawings and Specifications shall govern. D. All materials and equipment, materials and methods shall comply with all applicable requirements of laws, codes, ordinances, legislations, etc., of all federal, state and local authorities whether listed on the contract documents or not. E. Obtain the required permits from the local authorities for this work and pay for all fees required by the local, State, and Federal authorities for permits, inspections and review, including special agency construction and operating permits. Make corrections in the work as required by the Owner's Representative or Inspector to pass all such regulations. F. All equipment and materials shall be approved for use in New York City and listed with MEA numbers. Submit MEA number for all equipment during the submittal process. G. The Contractor shall be responsible for filing drawings, inspection arrangement with authorities having jurisdiction, and obtaining approval from N.Y.C Advisory Board, New York City Fire Department and Con Edison. The Contractor shall be responsible for all related fees. 1.5 REFERENCES A. Work shall be performed in accordance with all applicable requirements of the listed edition of all governing codes, rules, standards and regulations including but not limited to the following codes and standards, whether listed or not: 1. 2. 3. 4. 5. 6. 7. American Concrete Institute (ACI) American with Disabilities Acts (ADA) American National Standards Institute (ANSI) American Society for Testing Materials (ASTM) Electrical Industries Association/Telecommunication Industries Association (EIA/TIA) Environmental Protection Agency (EPA) Electrical Testing Laboratories (ETL) Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 3 Electrical Common Work June 30, 2010 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 1.6 Federal Aviation Administration (FAA) Factory Mutual (FM) Illuminating Engineering Society (IES) Institute of Electrical and Electronics Engineers (IEEE). National Electrical Manufacturer's Association (NEMA) National Fire Protection Association (NFPA) National Electrical Testing Association (NETA) National Electrical Code (NFPA-70) NYC Amendments to the 2005 NEC New York City Building Code (NYCBC) New York City Fire Code New York City Electric Code Advisory Board NYC Electrical Code Revision and Interpretation Committee (E.C.R.I.C.) New York City Electrical Code (NYCEC) New York City Seismic Code (NYCSC) Energy Conservation Construction Code of New York State (ECCCNYS) Occupational Safety and Health Administration (OSHA) Underwriters' Laboratories (UL) GENERAL REQUIREMENTS A. This specification and drawings are intended to serve jointly as a basis upon which the contractor shall submit a contract price for material and labor provisions. B. It is not intended that the plans or specifications show or state every detailed requirement of the work, but rather that they furnish adequate information for an experienced contractor to make a completely acceptable installation. The general conditions from a part of these specifications whether attached hereto or not, shall be carefully examined before submitting a proposal. Where general conditions clauses are repeated in this section, it shall be understood as calling special attention to them, or as a further qualification, and shall not be assumed as omitting any other clauses. No general conditions referring to the work included herein shall be considered as waived unless specifically stated herein. C. Before submitting a proposal, examine all plans relating to this work, verify all governing conditions at the site, become fully informed as to the extent and character of the work required and its relation to the work of other trades. Submission of a cost proposal (bid) will be judged as evidence that the site examination has been made. No consideration will be granted for any alleged misunderstanding of the materials to be furnished for work to be done, it being understood that the submission of a proposal is in agreement to all conditions referred to herein or indicated on the plans. D. Proposal must include everything required to provide a complete installation as contemplated in specifications and plans, whether specifically shown or specified or not. Included are labor, materials, equipment, lights, tools, scaffolding, etc., necessary to the complete installation of everything described, shown or reasonably implied. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 4 Electrical Common Work June 30, 2010 E. Any discrepancies between these specifications and the accompanying plans, or these specifications and plans and the specifications of other trades, shall be brought to the attention of the architect prior to the submission of the bid. Failure to comply with the above shall allow the architect to make a final and binding decision at a later date and no allowance will be given if the more expensive of the item in question is selected. F. This contractor shall be responsible for his work, its completion and final acceptance and shall replace any items which may be damaged, lost or stolen, without any additional cost to the owner. G. The work called for in these plans and specification shall be coordinated with the structure, work of all related trades, and shall be so arranged that there will be no delay in the proper installation and completion of any part or parts of each respective work. Wherein it may be interrelated with this contract all work can proceed in its natural sequence without unnecessary delay. The contractor is responsible for any additional cost and delays in the work resulting from substitution under this division; including, but not limited to: any changes, indecision, installation, or the work or other trades. H. Electrical drawings are diagrammatic (except where dimensioned) and indicate the general arrangement of systems and work. Follow architectural, structural and manufacturer's shop drawings for greater accuracy. Consult engineer in case of doubt or conflict. Unless noted, fixed dimensions are based on the product of one manufacturer. Verify dimensions with the shop drawings of the materials actually approved or purchased. I. Exact location of all equipment, panels, pull boxes, feeders, fixtures, etc. shall be approved by the architect and owner prior to the installation of the same. J. Contractor shall furnish all necessary outlets, supports, fittings and accessories to fulfill applicable codes, regulations and the best practices of the trade for installation of all electrical work. K. Exposed conduits can be installed but in no case shall be installed less than nine feet above the finished floor or as noted. Conduits installed in area where hung ceiling or other furred spaces are indicated shall be installed concealed. Should any work require subsequent modification or relocation to avoid interferences or conflicts with other work, such changes shall be made without additional cost to the owner. L. Any necessary electric service interruptions shall be at a time convenient to the building owner. M. All penetrations through slabs and fire rated partitions shall be fire stopped using an approved method to maintain the fire resistance rating. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 5 Electrical Common Work June 30, 2010 1.7 SCOPE OF WORK A. Without intending to limit and/or restrict the volume of work required and solely for the convenience of the contractor, the work of this division shall, in general comprise the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 1.8 Removal of electrical system as required and as indicated on plans.\ Modification to existing electrical system, updating of existing panel boards. Furnishing and installing new lighting fixtures and lamps. Furnishing and installing new conduits, branch circuit wiring, etc. Furnishing and installing new raceways, outlet boxes, wiring and connections for lighting fixtures, switches, receptacles and low tension outlets. Connections to all electrical equipment furnished by other trades or by the owner. Power wiring for all motors, including installing all required disconnect switches and mounting of starters. Modification of existing branch circuits, updating existing dimmer panels. Temporary light and power. Testing and load balancing. Grounding. Removal and restoration of existing work. Cutting, channeling and patching. Fire alarm system. WORK NOT INCLUDED A. Furnishing motors, motor starter and control devices connected to equipment furnished under other divisions of the specifications. However, electrical contractor will erect and wire same, furnish and install auxiliary motor disconnects as required by drawings or code. B. Finish painting. C. Motor control wiring and electrical interlocks (u.o.n.). D. Telephone wiring and devices. 1.9 CODES PERMITS AND INSPECTIONS A. Electrical work shall comply with the applicable requirements of the New York City electrical codes, NYBC, OSHA code, and other authorities exercising jurisdiction over all electrical construction work and the project. B. Nothing contained in these specifications or plans shall be so construed as to conflict with any local, municipal, and national board of the Fire Underwriters Regulations governing the installation of work specified herein. All such laws, ordinances and regulations, where they apply to this work, are hereby incorporated into and made a part Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 6 Electrical Common Work June 30, 2010 of the specifications. All such requirements shall be satisfied at no additional expense to the owner. C. 1.10 All required permits and inspection certificates shall be obtained, paid for, and made available at the completion of the work. GUARANTEES AND CERTIFICATIONS A. All work shall be guaranteed to be free from defects. Defective materials or workmanship, as well as damage to the work of any/all trades resulting from the same, shall be replaced or repaired as direct for the duration of one year from the date of acceptance. B. The date of acceptance shall be the date of the final payment for the work or the date of a formal notice of acceptance, whichever is earlier. C. Non-durable items, such as electric lamps, shall be replaced up to the date of acceptance, such that they shall have had no more than 100 hours use prior to this date. 1.11 SHOP DRAWINGS AND EQUIPMENT SUBMISSIONS A. Prior to purchasing any equipment or materials, a list of their manufacturers shall be submitted for approval. B. Prior to assembling or installing the work, catalog information and factory assembly drawings, as required for a complete explanation and description of all fixtures, devices and items of equipment, shall be submitted for approval. C. Field installation drawings as required to explain fully all procedures involved in erecting, mounting and connecting all pieces of equipment. D. No equipment shall be fabricated, delivered, erected or reconnected other than equipment from drawings approved by the engineer. Shop drawings in the number directed shall be submitted for the following: 1. 2. 3. 4. 5. E. 1.12 A. Relays and dimmers Lighting fixtures Wiring devices and plates Fire alarm system devices and riser diagram Occupancy sensors It shall be understood that approval of drawings will not bind the engineer or the owner to the final acceptance of such equipment as the completed installation and test of equipment as a whole must be provided and guaranteed herein as specified. SAMPLES Upon request by architect or owner, submit for approval one sample of each of the following: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 7 Electrical Common Work June 30, 2010 1. 2. 3. 1.13 Each type of lighting fixture. Each type of wiring device. Each type of wiring device plate. RECORD DRAWINGS A. Remove all equipment unless otherwise shown; however, all changes cannot be detailed completely on the drawings, some removals and relocations of existing electric work will be necessary for satisfactory performance of this and other trades. Take into consideration in proposal all required changes. B. Reproducible record drawings shall be supplied by the contractor upon which corrections shall be made to provide an accurate and complete record of the work as installed. 1.14 DEMOLITION AND REMEDIAL WORK A. Remove all electrical equipment, wiring and other electrical work as required. Disconnect load and line end of conductors feeding devices which are to be removed or abandoned, and remove conductors no longer in use. Cut back to floor, wall or ceiling, and plug both ends of concealed conduits made obsolete by this alteration. Remove exposed or abandoned circuits and outlets. Remove material and equipment and dispose of as directed. B. Wherever it is required to disconnect or remove any part of an existing circuit, immediately reconnect that circuit or reestablish service in the remaining portion of the circuit. C. The work shall also include the removal of materials as directed. Prior to removing equipment and material from project site, the building manager or owner will inspect and advise which items will be stored. D. Where existing receptacles and or switches are located in columns and or exterior walls, remove receptacle and cap outlet box. Receptacles shown on partitions to be removed shall have all wiring and conduit removed as well. All floor receptacles and telephone outlets shall be removed and openings capped flush. E. Where present work is damaged in the execution of this contract, or where openings are left due to the removal or conduits equipment or apparatus, the same shall be repaired or closed up to correspond in material, quality, shape and finish with that or similar and adjoining work without extra cost to the owner, unless otherwise called for. F. Should any damage due to the execution of this contract occur to the furniture, fixtures or any other equipment or apparatus, such damages shall be properly repaired with the supply of new articles and made good without extra charge. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 8 Electrical Common Work June 30, 2010 G. 1.15 Where removal of existing electrical equipment will result in outages in area not to be demolished, this contractor shall coordinate in advance and obtain the approval of the building manager or owner. QUALITY ASSURANCE A. All workers performing under this Division shall be skilled workers of the trade involved. Where specialty work, such as splicing or welding are required, submit proof of training, experience and work history for each worker, for review by the Engineer. Only approved workers shall perform specialty work. B. All electrical work shall be performed by an electrical contractor licensed in the state, which the work is to be performed. C. All electrical materials and equipment for which there is a nationally recognized standard shall bear the conformance labeling of the third party inspection authority, such as Underwriters Laboratories Inc., Factory Mutual, ETL or other recognized agency listed, in accordance with the requirements of the local Authority having jurisdiction. D. Carcinogenic material, including Asbestos shall not be furnished or installed. E. All calculations required by this and other various Sections of these Specifications, or as shown on the Drawings, shall be certified and sealed by a Professional Engineer licensed in the state in which the work is to be performed, and shall be submitted to the Engineer for review. F. With the exceptions as specified and/or indicated on the Drawings or in the Specifications, the Contractor shall apply, install, connect, erect, use, clean, commission and condition manufactured articles, materials, and equipment per Manufacturer's current printed instructions and recommendations. Copies of such printed recommendations shall be kept at the Project site and made available as required. G. Where the manufacturer's recommendations conflict with the Contract Documents, the conflict shall be brought to the Engineer's attention immediately. 1.16 GUARANTEE A. Submit a single guarantee stating that all portions of the work are in accordance with Contract Documents. Warrant all work against faulty and improper material and workmanship for a period of one year from date of substantial completion and/or acceptance, except that where guarantees or warranties for longer terms are specified herein, such longer term shall apply. At no additional cost to Owner, within 24 hours after notification, correct any deficiencies, which occur during the warranty period (including all parts, material, labor, etc.), all to the satisfaction of the Owner or his designated representative. In default thereof, the Owner may have such work done and charge all costs to the Contractor. This Contractor shall require similar guarantees from his Subcontractors. B. During the warranty period, the Contractor shall guarantee the following in a form satisfactory to the Owner: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 9 Electrical Common Work June 30, 2010 1. 2. All equipment meets the design capacities and performance characteristics specified. The systems shall operate without malfunction. C. The start of the Contractor’s warranty period shall commence on the issue of a “Certificate of Substantial Completion”, by the Owner or the Owner’s Representative for each item of material, equipment, or system. D. The Subcontractor shall confer with the Construction Manager prior to the bid date concerning the project schedule and determine if there is a need to operate any items of equipment or systems for temporary light, power, heating and/or cooling or other reasons prior to “Substantial Completion”. All required extended warranty costs for equipment, materials, and systems shall be included in the Subcontractor’s bid. E. Warrant that all components, subsystems and systems will perform their specified functions from the date of turnover and commercial operation through the useful life of the system. In the event components fail for any reason, be responsible to repair, replace and reimburse the Owner for all costs associated with the component, subsystem or system that failed to perform the specified function. 1.17 SCHEDULING The following is a summary of the scheduling milestones described in the text of the Specifications. The Contractor shall start on or schedule the following upon receiving notice to proceed. 1. 2. 3. 4. 5. 6. 7. 8. 1.18 A. Immediately upon award of this Contract, this Contractor shall have a preconstruction meeting with the Architect and Engineer. On or before three (3) weeks after notice to proceed, submit a complete, typed list of the subcontractors, equipment manufacturers and suppliers they intend to use to the Engineer for review. On or before six (6) weeks after notice to proceed, prepare an index of all his Electrical shop drawings and brochures for the Project. As requested by the Construction Manager, the Contractor shall submit "Coordination Drawings" to the Engineer for review. As requested by the Construction Manager, the Contractor shall provide a detailed schedule of completion indicating when each system is to be completed and outlining when tests will be performed. Submit proposed test procedures, recording forms and test equipment for review by the Engineer prior to execution of testing. Submit six (6) final copies of the Operation and Maintenance books to the Owner for review at least ten (10) weeks before Final Review of the Project. Submit three (3) final copies of the Record Set to the Owner for review at least four (4) weeks before Final Review of the Project. TESTS Before an application for the final acceptance of the work will be considered, all tests deemed necessary by the architect to show proper execution of the work shall have been Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 10 Electrical Common Work June 30, 2010 performed and completed in the presence of an architect's representative. Schedule of all testing procedures shall be arranged to suit the convenience of the architect. B. Any defects or deficiencies discovered in any of the electrical work shall be corrected. C. Insulation resistance tests shall be performed on all re-utilized wiring and equipment. Measured insulation resistance shall conform to requirements of the latest edition of the N.Y.C. Electrical code. 1.19 IDENTIFICATION A. Electrical contractor shall furnish and install type-written directories behind transparent plastic covers in metal frames, in all new and existing panels indicating type and location of load being served by individual circuit breakers. B. All parts of equipment, such as panels, junction boxes, safety switches motor starter, circuit breakers, conductors and similar items shall be identified by name, at supply end, "load supplied" and at load end, "load supplied from". 1.20 MODIFICATION TO EXISTING PANELS A. Contractor shall re-assign circuits to rephase panel as required by new work. B. Update panel directories to accurately reflect changes. 1.21 DELIVERY, STORAGE, AND HANDLING A. Include all shipping, delivery, hauling, hoisting, shoring, and placement in the building of equipment and materials specified herein. The Contractor shall be responsible for the timely delivery of equipment to the project site as required by the construction schedule. If any item of equipment is received prior to the time, it is required, the Contractor shall be responsible for its proper storage and protection until it may be required. The Contractor shall pay for all costs of storage in a bonded warehouse. B. Delivery: Deliver equipment, fixtures, devices and conduits with factory-fabricated containers and protective means. Maintain containers and protective means through shipping, storage, and handling to prevent damage and to prevent exposure to dirt, debris, and moisture. C. Storage: Store in a clean, dry, ventilated space free from temperature extremes. Maintain factory wrapping or provide a heavy canvas/plastic cover to protect equipment from dirt, water, construction debris, and traffic. D. Handling: Handle in accordance with manufacturer’s written instructions. Be careful to prevent internal component damage, breakage, denting and scoring. Damaged units shall not be installed and shall be replaced with new units. E. If any item of equipment is not delivered to or installed at the Project site in a timely manner as required by the Project construction schedule, the Contractor shall be solely responsible for disassembly, re-assembly, manufacturer's supervision, shoring, general Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 11 Electrical Common Work June 30, 2010 construction modifications, delays, overtime costs, etc. No additional cost or delays shall be incurred by the Owner F. All other trades’ equipment, materials and work shall be protected from damage in areas where electrical work is being carried out. All damage shall be corrected in a manner acceptable to the Engineer and the Owner without additional cost to the Owner. G. The Contractor shall be responsible for all work, materials and equipment until finally inspected, tested and accepted; protect work against theft, injury or damage; and carefully store material and equipment received on site, which is not immediately installed. All the equipment, materials and the work shall be covered and protected during construction to prevent entry of dust, dirt, obstructing material and to prevent damage due to weather, water, spray-on fireproofing, construction debris, etc., in a manner acceptable to the Engineer and/or Owner. H. All equipment, materials, devices, etc stored off site and delivered to the site must be kept in the manufacturers’ original unopened protective packaging with shipping bars, retainers and positioning devices in place until installation. Store all items subject to moisture damage in dry and heated space with factory covering in place. PART 2 PRODUCTS 2.1 MATERIALS FURNISHED A. New, bearing label of Underwriter's Laboratories, or other testing laboratory acceptable to authority having jurisdiction, where labeling exists for the class of equipment. B. Equipment and materials furnished shall be new and unused, prior to this installation, first grade commercial quality and shall be essentially the standard cataloged products of a manufacturer regularly engaged in the manufacture of the products. Only those items specifically shown on the Drawings as existing relocated or Owner furnished shall be reused in this installation. Rebuilt or remanufactured equipment will not be permitted. C. Since manufacturing methods vary, reasonable minor variations are expected; however, performance and material requirements specified herein are the minimum standards acceptable. The Engineer retains the sole right to judge the equality of equipment that deviates from the Contract Documents, to reject any substitutions submitted by the Contractor, and to require the specified materials and equipment, which conform to the requirements of the Contract Documents, be furnished. D. Equipment and materials that have defects or damage during transportation, installation, or operation is considered as totally damaged. They shall be replaced new. The materials and equipment, which have minor damage, may be repaired if written approval is given by the Engineer and Owner. If equipment and materials are approved for repairs, they shall be repaired in a manner acceptable to the Owner and Engineer at no additional cost to the Owner. The Contractor shall be responsible for all costs associated with the repairs, replacement, including but not limited to, all preparations prior to re-testing, extended warranties, re-commissioning of the equipment, etc. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 12 Electrical Common Work June 30, 2010 E. Where no specific make of material or equipment is mentioned, use any product of reputable manufacturer, which conforms to requirements of system and other applicable specification sections. F. Provide an authorized representative to constantly supervise Work specified in this Division; check all materials prior to installation for conformance with Drawings, Specifications, and reviewed Shop Drawings. 2.2 SAFETY SWITCHES A. Safety switches shall be of size noted on the drawing, or as required, fusible or non fusible and each contained in a general purpose nema 1 enclosure. All switches shall be heavy duty type and shall have quick-make, quick-break mechanism. B. All switches shall be of proper horsepower rating as applicable and have dual interlocks designed to interlock the switch box door with the switch operating mechanism. C. Safety switches shall be in nema 1 enclosure, horsepower rated, heavy duty type, with quick-make, quick-break mechanism and cover interlock. Handle shall be capable of being padlocked in "off" position. Switch shall be fused or unfused, as indicated. Outdoor switches shall have nema 3r enclosure. 2.3 EQUIPMENT AND MATERIALS A. All equipment and materials for permanent installation shall be the products of recognized manufacturers and shall be new unless otherwise designated. B. New equipment and materials shall: 1. 2. 3. 4. 5. C. For items which are to be installed but not purchased as part of the electrical work, the electrical work shall include: 1. 2. D. Where normally subjected to underwriters laboratory inc listing or labeling services, be so listed or labeled. Be without blemish or defect. Not be used for temporary light and power purposes without architect's authorization. Be in accordance with the latest applicable N.E.M.A. Standard. Be approved by building manager or owner. The coordination of their delivery. Their field make-up and internal wiring as may be necessary for their operation. Electrical raceway and supporting systems shall be furnished and installed complete, with all materials, fittings, connections and accessories necessary to provide in each instance, a complete operating installation, as described herein, and indicated on the drawings, and/or as approved by building manager or owner. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 13 Electrical Common Work June 30, 2010 E. 2.4 The drawings are diagrammatic and generally indicative of the work to be installed, but do not show all bends, fittings, and boxes which may be required. The contractor shall carefully investigate the job conditions including structural and finish conditions affecting all his work and arrange all work accordingly, furnishing such fittings, boxes and similar items as may be required to meet such conditions. WIRING MATERIALS A. All wires and cable shall be type XHHW for feeders and THHN or THWN for branch circuits in conduit. No wire smaller than #12 awg shall be used for light or power services. B. Wire #10 awg and smaller shall be solid, wire # 8 awg and larger shall be single conductor stranded. C. For 120/208v service, wiring shall be consistently color coded throughout, red, blue, black for line (phase) conductors and white for neutral conductor, switch leg shall be separately identified. Ground conductor where specified shall be green. For 277/480v service, wiring shall be consistently color coded throughout, brown, orange, yellow for line (phase) conductors and white for neutral conductor. Ground conductor where specified shall be green. D. MINIMUM SIZE: 1. 2. 3. Lighting and power: #12 awg, unless otherwise indicated. Control: # 14 awg. Circuit over 75 feet in length from the point of supply to the first outlet shall be # 10 awg. E. Splices in branch circuit work shall be made by means of type 'r' "Scotchlock" connectors. F. Electrical insulation tape shall be vinyl plastic type with pressure adhesive "scotch" electrical type. G. Branch circuitry numbers indicated on the drawings on multi-circuit homeruns are for identification of devices or equipment they are connected to and do not necessarily refer to dimming panel circuit numbers. Assignment of branch circuit numbers shall be part of this work and indicated on panel directories. Branch circuits shall be connected to circuits on dimming panels so as to secure a reasonable balance all circuits. Where more than one circuit with a common neutral is installed in the same conduit, each phase wire shall be connected to a different leg of the system. H. All conductors shall be color coded throughout and numbered and tagged at each junction box, pull box, panel and device with suitable fireproof tags or adhesive identification bands. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 14 Electrical Common Work June 30, 2010 2.5 TAPS, SPLICES AND TERMINATIONS A. All copper cable lug connections to copper bus bars remains and branches shall use copper solderless connectors having either 2-bolt cast copper clamps, or compression connectors, Thomas & Betts series 54000, with manufacturer's recommended hexagonal dies and hydraulic compression tools. B. All copper conductors #10 awg and smaller shall be spliced with Thomas & Betts Stakon connectors series pt-1 or equal. All copper conductors #8 awg and larger shall be terminated, spliced and tapped with t & b color-keyed compression connectors series 54000 or equal. For splices, the Burndy type KPU-C connector or equal will be acceptable. C. Connectors for lighting fixtures from branch circuit wiring shall be made with twist-on type connectors, t & b series pt-1 or equal. 2.6 CONDUITS AND RACEWAYS A. Except as otherwise indicated or specified, all wiring inside and above hung ceiling use EMT. B. Liquid tight flexible, galvanized steel conduit, with continuous copper bonding conductor, shall be used for connections, not exceeding 18 in length, to motors and at other locations where vibration, movement or oil vapor atmospheres are encountered. C. Unless otherwise indicated or specified, all wiring shall be installed concealed in ceilings, walls, slabs, pipe chases and furred spaces whenever possible. D. Conduit and fittings shall conform to latest acceptable New York City code and all other codes having jurisdiction. E. Conduit shall be 3/4" trade size minimum, unless otherwise indicated or specified. F. All conduits which are to remain empty for future introduction of conductors shall be provided with a #12 nylon drag wire with identification tag at both ends. G. Metal clad cable (bx) can be used for lighting and appliance branch circuitry in voids of ceiling and partitions, provided that this type of wiring is acceptable to the Brooklyn College representative, and in compliance with governing electrical code. Verify all of the above prior to submittal of bid proposal. 2.7 FITTINGS A. For rigid conduit, shall be of the threaded type. Fittings for EMT shall be steel, concrete tight, with insulation throats, T&B series 5123 and 5120, or approved equal. Fittings for flexible conduit shall be steel, with nylon insulated throats. Bushings for conduits one (1") inch and larger shall be of the insulated type, T&B series 222, or approved equal. Grounding bushings shall be O.Z. Type BLG, or approved equal. Conduit terminations, Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 15 Electrical Common Work June 30, 2010 except conduit for telephone, signal and other low tension services, shall have double locknuts, t & b series 141. 2.8 JUNCTION BOXES A. 2.9 Junction box and pull boxes shall be provided where indicated or specified and where necessary to facilitate the installation of equipment or wiring. OUTLET BOXES A. Each outlet for lighting fixture, wall switch, wall receptacle, telephone or other use shall be provided with an outlet box suitable for the use for which the outlet is to be put and to the location in which it occurs, secured firmly in place and set true and square with the finished surface. B. Connection to recessed ceiling fixtures supplied with pigtails may be arranged so that more than one but not more than four, such fixtures are connected into a single outlet box. No fixture shall be supplied from an outlet in another room. C. Ceiling outlets serving individual fixtures and installed in plastered ceilings or concrete slabs shall be four (4) inch square with covers. Depth of boxes shall be as required by code, to accommodate the conduits, number of wires, splices, and devices to be installed. All outlets for the attachment of fixtures to be provided with fixture studs securely anchored to the boxes. D. Through wall boxes for back to back wiring not permitted. E. Where more than one wiring device is mounted in the same location, such device shall be gang mounted under a common faceplate. F. Junction boxes to be 4" x 4" x 2 - 1/8" deep with flat metal covers, unless otherwise noted or required by code. Junction boxes above suspended ceiling for lighting shall be 4'11/16" x 4'11/16" x 2-1/8" deep, to be installed adjacent to recessed fixture in such manner as to be accessible through the opening in the ceiling in which the fixture is installed. 2.10 EMERGENCY LIGHTS AND NIGHT LIGHTS A. Shall be equipped with emergency battery packs. B. Shall be equipped with emergency battery packs. 2.11 A. FASTENINGS, SUPPORTS, AND HANGERS All parts of the electrical installation shall be adequately supported from the building construction using approved clamp screws with the inserts of expansion anchors, expansion bolts and toggle bolts" in no case shall the hung ceiling members or wires be used to support conduit". Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 16 Electrical Common Work June 30, 2010 B. 2.12 All fastening, supports, clamps, anchors, and similar items shall be of type suitable for the purpose. WIRING DEVICES A. All devices shall be specification grade, U.L. Approved. B. Single pole switch, 20 amp, 125 volts. C. Duplex receptacle, 20 amp, 2 pole, 3 wire, 125 volt, ground type. D. Single receptacle, 20 amp, 2 pole, 3 wire, 125 volts, grounding type, GFI where required. E. Color and type of all device plates shall be approved by architect prior to purchase/installation. PART 3 EXECUTION 3.1 Temporary Electric and Lighting A. Temporary Electric Services 1. 2. 3. 4. 5. 6. The Electrical Contractor is cautioned to carefully consider the possible sources of temporary electric service and the probable location of the General Contractor's office. The General Contractor will apply to the Client or local utilities for the temporary electric service and will pay for all electric power used during construction, including electric heating. The Electrical Contractor shall furnish, install and pay for all necessary conduit, wire, metering, poles, switches, receptacles, lights and accessories to provide a 200 amp, 120/208 volt, 3 phase, 4 wire temporary electric service with the main disconnect switch, meter, and a 42 circuit load center at a location specified by the General Contractor. Consult the client/utility company for fees required and include same in Electrical Contract. Labor, receptacles, boxes, fixtures, wire, etc. required by the various Contractors inside their offices shall be paid for by the respective Contractors. Lighting fixtures shall be placed every 40 ft. along each corridor or where corridors do not occur, along the long axis of all rooms and areas greater than 25 ft. in length. Provide a 100 watt lamp in a rubber coated socket with wire guard, spliced into branch feeder conductor at every 20 ft. The branch circuit wiring may be 3-wire type "NMC" and the wire guard shall be bonded to the ground conductor. Receptacle circuits shall consist of 1-gang handy box with grounded duplex receptacles a maximum of 50 ft. on center with a maximum of 4 per circuit. All receptacle circuits shall be protected by its own overcurrent device in a panelboard. Install wiring and equipment above 6'-6" and below the finished Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 17 Electrical Common Work June 30, 2010 ceiling. Extend circuits as required and protect in an appropriate panelboard on each floor level. Provide GFCI protected receptacles and circuits as required by NEC and OSHA. 7. Contractors requiring extension cords shall provide their own cords and plugs up to capacity of 20 amperes. For services to larger items of equipment and welders, this Contractor shall extend proper feeders as requested at the expense of the Contractors requiring the service. 8. The Electrical Contractor shall maintain the temporary light and power system for the duration of the work and shall remove it from the site when directed. Temporary wiring and equipment shall remain the property of the Electrical Contractor. 9. The use of the permanent electrical system for temporary services during the latter stages of construction shall be allowed through an appropriate metered branch circuit breaker. Expedite completion of permanent system as practicable to this end. Maintain the temporary system during this period. 10. Warranty periods on equipment, materials and systems commences upon Client’s acceptance of the building or systems. Temporary use of permanent equipment shall not jeopardize or alter warranty requirements. 11. The complete temporary service shall comply with the Client, utility OSHA, and all Code requirements. B. Continuity of Service 1. 2. 3. C. Work shall be so planned and executed as to provide reasonable continuous service of existing systems throughout the construction period. Where necessary to disrupt services for short periods of time for connection, alteration or switch-over, the Client shall be notified in advance and outages scheduled at the Client's reasonable convenience. Submit, on request, a written step-by-step sequence of operations proposed to accomplish this work. The outline must include tentative dates, times of day for disruption, downtime and restoration of services. Submit the outline sufficiently in advance of the proposed work to allow the Architect or Engineer to review the information with the Client. Upon approval, final planning and the work shall be done in close coordination with the Client. Shutdown of systems and work undertaken during shutdowns shall be bid as being done during normal working hours. If the Client should require such work be performed outside of normal working hours, reimbursement shall be made for premium time expenses only, without mark-up. The Contractor shall make all necessary arrangements with the Owner for the new installation of temporary lighting and power services tailored for this project and the setting of temporary meters in accordance with the Utility Company's requirements. He shall pay for the installation and maintenance of all temporary light and power wiring, including, but not limited to conduits, wire, switches, fuse boxes, receptacles, distribution panel boards, fused disconnect switches, ground fault interruption equipment, fixtures, lamps, fuses and any other incidental material and/or equipment required to provide sufficient illumination and power, as required by the state Labor Board, O.S.H.A., or all other authorities having jurisdiction for all areas of the site Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 18 Electrical Common Work June 30, 2010 where work will be performed by this Contractor, his subcontractors, or any other contractors. D. Irrespective of the union working hours for the electricians, the Electrical Contractor shall maintain and pay the entire regular and overtime labor costs of keeping the temporary light and power system energized from a period 15 minutes before the established starting time of the building trade which starts work earliest to a period of 15 minutes after the established stopping time of the trade which stops work latest. This shall apply to every working day of the week during the life of the contract, unless otherwise directed, or until such time that the maintenance of the temporary light and power system is no longer required by reason of the activation of and use of the permanent light and power systems. E. When the electricians are entitled to a holiday or holidays under union rules and other building trade workmen are required to work and do not have the same holiday or holidays, the Electrical Contractor shall maintain and pay the entire overtime labor costs of keeping the temporary light and power system energized for the full day or those full days, as the case may be, including the extra 15 minutes before the start and after the close of the working day, as stated in the preceding paragraph. F. Should this Contractor or any contractor require temporary light or power, or both, before or after the hours set forth in the preceding paragraphs, this Contractor or other contractors shall pay the extra cost of keeping the systems energized and in serviceable condition. G. Remove the temporary light and power systems, when directed. This Contractor shall replace and make good all damage to the permanent systems, as required, replacing all damaged parts. Under no circumstances shall temporary wiring be left in finished hung ceiling spaces. H. When the permanent lighting and power systems are installed and operational, this Contractor shall make the changeover. The cost of making the changeover of the electric services from the temporary lines to service from permanent lines shall be borne by this Contractor. 3.2 INSTALLATION OF EQUIPMENT A. Install electrical equipment as specified in individual specification sections, and in accordance with manufacturer’s recommendations. B. Rough-in locations for fixtures and equipment shall be determined from the unit itself or from the approved shop drawings. C. Provide all necessary anchoring devices and supports (refer to Paragraph 3.2 Seismic Protection). 1. 2. 3. D. Use structural supports suitable for equipment, or as indicated. Check loadings and dimensions of equipment with shop drawings. Do not cut or weld to building structural members Arrange for necessary openings to allow for admittance of equipment. Where equipment cannot be installed as structure is being erected, provide and arrange for building-in of boxes, sleeves, or other devices to allow later installation. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 19 Electrical Common Work June 30, 2010 E. Install equipment to permit easy access for normal maintenance. 1. 2. F. Maintain easy access to switches, motors, drives, pullboxes, receptacles, etc. Notify the Owner’s Representative in writing of relocation items, which interfere with access. Equipment Pads, Mats and Mounting 1. 2. 3. 4. 5. 6. 7. 8. Concrete pads for various pieces of equipment systems will be furnished by other Division. Contractor shall provide fully dimensioned pad layouts to the General Contractor. Shop Drawings shall be used for dimensional guidance in sizing pads, anchor bolts, locations, etc. Pads shall be provided for floor-mounted equipment, equipment mounted on legs and/or support stands and they shall conform to the shape of the piece of equipment it serves with a minimum 3 in. margin around the equipment and supports. Pads shall be a minimum of 4 in. high and made of a minimum 28-day, 3000 psi concrete reinforced with 6”x6”, 6/6 gauge welded wire mesh. Top and sides of the pad shall be toweled to smooth finishes, equal to those of the floors, with all corners bullnosed to 3 / 4” radius. Pads shall be dowelled into slab with #4 bars at each corner embedded 3” and grouted with non-shrink grout. Concrete waterproof curbs shall be provided around all vertical bus floor penetrations. These curbs shall be a 4 in. high and shall be poured as part of the floor slab. Coordinate exact dimensions of slab penetration and curb with the busduct manufacturer. Furnish and install galvanized anchor bolts for all equipment placed on concrete equipment pads, inertia blocks, or on concrete slabs. Bolts shall be the size and number recommended by the Manufacturer of the equipment and as required for seismic restraint. Anchor bolts shall be anchored to the structural floor slab and shall be located by means of suitable templates. When equipment is placed on vibration isolators, the equipment shall be secured to the isolator and the isolator secured to the floor, pad, or supported as recommended by the vibration isolation manufacturer. Equipment pads for switchboards, switchgears, transformers shall have level mounting channels embedded in the concrete as specified in the applicable sections. Where equipment is mounted on gypsum board partitions, the mounting screws shall pass through the gypsum board and be securely attached to the partition studs or framework. Rubber Mats a. b. c. Install a continuous one-piece rubber mats in front of each electrical equipment such as switchboard, motor control center, switchgear, generator paralleling switchgear, Uninterruptible Power Supply equipment, substation transformers, each side of a generator set, etc. Rubber mats when installed shall lay flat without curling. Rubber mats shall conform to ASTM D 178, Type 2 Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 20 Electrical Common Work June 30, 2010 G. Penetrations: 1. 2. 3. 4. 5. 6. 7. H. Expansion/Deflection 1. 2. I. Avoid, if possible, the penetration of any waterproof membranes such as roofs, machine room floors, basement walls, and the like. If such penetration is necessary, perform it prior to the waterproofing and furnish all sleeves or pitchpockets required. Advise the Architect and Engineer and obtain written permission before penetrating any waterproof membrane, even where such penetration is shown on the Drawings. If Contractor penetrates any walls or surfaces after they have been waterproofed, he shall restore the waterproof integrity of that surface as directed by the Architect/Engineer at his own expense. Pack space between conduits, sleeves, cable trays and seal unused sleeves in nonfire rated walls with non-combustible materials. Refer to specifications for details and requirements. Conduit enters the building through a concrete foundation wall below grade level; a watertight entrance seal shall be used. The seal shall be OZ/Gedney. Make penetrations through floors, walls and any damp-proofed/water-proofed surfaces, damp-proof/waterproof by appropriate means to maintain integrity of system penetrated. Refer to specifications for details and requirements. Seal around penetrations and between conduits, cable trays, sleeves, etc and seal unused sleeves, in fire rated walls with UL listed fireproofing material to maintain integrity fire rating. Refer to specifications for details and requirements. The Contractor shall be responsible for the timely placing of sleeves for all piping passing through walls, partitions, beams, floors, and roofs, while the same are under construction. Equip all cable trays and conduits, including those embedded in concrete, which cross building expansion or control joints, with expansion fittings. Where conduits are subjected to expansion and movement in any directions or to vibration transmitted by equipment or vehicular traffic, install a combination expansion and deflection fittings. Support 1. 2. 3. Provide required supports and hangers for conduit and equipment, so that loading will not exceed allowable loadings of structure. Submittal of a bid shall be deemed a representation that such bid has included allowable loadings and has included in estimates the costs associated in furnishing required supports. The design of the supports for conduits, busduct and equipment shall be certified and sealed by a Professional Engineer licensed in the State in which the work is to be performed. Where busduct, conduits, etc., are routed vertically through shafts, the Contractor shall provide and install all necessary miscellaneous structural members to support the loads imposed by the risers. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 21 Electrical Common Work June 30, 2010 4. Where equipment (transformers, busducts, conduit racks, etc.) are supported from structural slabs, the Contractor shall provide all miscellaneous structural members to support the load plus a 250 lb. live load. 5. The Contractor shall submit Shop Drawings of the riser support system inside vertical shafts to the project Structural Engineer for approval, including details of how the riser support structure is to be attached to the building structure 6. Miscellaneous structural support members installed in Switchboard Rooms, electric closets, central plants, Mechanical Rooms, and where exposed to public view shall be galvanized. 7. Include supporting frames or racks extending from floor slab to ceiling slab for work indicated as being supported from walls where the walls are incapable of supporting the weight. In particular, provide such frames or racks in electric closets. 8. Include supporting frames or racks for equipment, intended for vertical surface mounting, which is required in a freestanding position. Supporting frames or racks shall be of standard angle, standard channel or specialty support system steel members. They shall be rigidly bolted or welded together and adequately braced to form a substantial structure. They shall be firmly secured to the floor slab with expansion anchors designed to support the system and the equipment. Racks shall be of ample size to assure a skillful arrangement of all equipment mounted on them and shall not impinge code required work space of other equipment, devices, access panel, junction boxes, pull boxes, etc. 9. Wall mounted equipment may be directly secured to wall by means of steel bolts. Maintain at least 1" air space between equipment and supporting wall. Groups or arrays of equipment may be mounted on adequately sized steel angles, channels, or bars. Prefabricated steel channels providing a high degree of mounting flexibility, such as those manufactured by Kindorf, Glob-Strutt and Unistrut, may be used for mounting arrays of equipment. 10. No equipment, including outlet, pull and junction boxes and fittings, shall depend on electric conduits, raceways, or cables for support, except that threaded hub type fittings having a gross volume not in excess of 100 cubic inches may be supported from heavy wall conduit, where the conduit in turn is securely supported from the structure within five inches of the fitting on two opposite sides. 11. Nothing shall rest on, or depend for support on, suspended ceilings media (tiles, lath, plaster, as well as splines, runners, bars and the like in the plane of the ceiling). If suspended ceilings are use to support lighting fixtures, they shall be designed to support the weight of the fixtures. Branch circuit conduit up to 3/4" may be permitted to be supported from ceiling hanger rods if the allowable loading of the rods is not exceeded and approved by the Architect and Engineer. 12. For items, which are shown, as being ceiling mounted at locations where fastening to the building construction element above is not possible, provide suitable auxiliary channel or angle iron bridging, tying to the building structural elements. J. DISSIMILAR METALS 1. Dissimilar metals shall mean those metals, which are incompatible with one another in the presence of moisture. Where dissimilar metals come in contact, Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 22 Electrical Common Work June 30, 2010 2. K. Voltage Check 1. 2. 3.3 paint the joint both inside and out with approved coating to exclude moisture from the joint, or provide a suitable insulating barrier separating the metals. Transitions in raceways, from one metal to a dissimilar metal shall only be made at boxes or other enclosures. At completion of job, check voltage at several points of utilization on the system, which has been installed under this Contract. During test, energize all installed loads. Adjust taps on transformers to give proper voltage, which is 118 to 122 volts for 120-volt nominal systems and proportionately equivalent for higher voltage systems. If proper voltage cannot be obtained, inform the Architect and the Owner. GROUNDING A. All enclosures and other noncurrent carrying metallic parts of electrical equipment, raceway systems and equipment ground buses shall be effectively grounded to the building grounding systems through the system ground conductors. Metallic conduits and other raceways and enclosures for conductors shall be metallically joined together into a continuous electrical conductor, as to provide effective electrical continuity. B. Equipment located remotely from the ground conductors shall be grounded to the nearest available cold water piping. Motor frames shall be grounded through their conduits. C. Ground continuity shall be maintained throughout. D. Ground motors by connecting a conductor from a grounding bushing in the starter to the motor frame. Conductor shall be installed in the conduit with the circuit conductors. 3.4 MOUNTING HEIGHTS A. Heights of wall mounted outlets and equipment shall be in accordance with the following (unless otherwise noted). Dimensions are above finished floor unless otherwise noted). 1. 2. 3. 4. 5. 6. Outlets (receptacle and telephone) in walls, partitions or columns to center line: 1'-3" if mounted horizontally and 1'-6" if mounted vertically. Switch (toggle) outlet in walls, partitions or columns -3'-10" to center line. Individual motor starter - 5'-0" to center line. Fire alarm pull station - 3'-10" to center line. Group mounted (motor starters or distribution system switching devices) 6'- 6" maximum to center line of highest pushbutton or switching device handle requiring manual operation, 1'-0" minimum to bottom of lowest enclosure. Fire alarm strobe - 6'-8" to center line. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 23 Electrical Common Work June 30, 2010 7. 8. 3.5 Mounting heights of pendant mounted lighting fixtures shall be as directed in the field by the architect or as indicated on architectural drawings. Details shown on architectural drawings and field instructions issued by the architect take precedence over the above list and shall be adhered to. SEISMIC PROTECTION A. Seismic restraints for equipment, conduits, cable trays, devices, luminaries, equipment housekeeping pads and equipment supports shall be provided and shall comply with the latest Seismic and applicable codes. Refer to the applicable specification sections for other requirements. B. Seismic restraint design shall be certified and sealed by a Professional Engineer licensed in the State in which the work is to be performed. 3.6 EQUIPMENT NOISE AND VIBRATION A. Equipment and systems, as defined herein, shall be quiet and free of apparent vibration while in operation. B. Vibration shall not be apparent to the senses in occupied areas of the building. Both the balancing of rotating machinery and the installation of vibration isolators are required. C. Any additional precautions deemed necessary to provide a quiet installation shall be done as part of the Work of this Section, subject to review by the Engineer and without additional cost to the Owner. After the systems are in operation, it shall be the responsibility of the Contractor to make any changes to equipment or Work 3.7 SETTING OF PROTECTIVE DEVICE A. 3.8 Prior to final completion of the Project, set all protective device relays and internal settings based on the accepted coordination study. IDENTIFICATION A. The Contractor shall identify all piping, conduit, machinery, and equipment in accordance with SECTION 26 05 53 – IDENTIFICATION for ELECTRICAL SYSTEMS. B. The Contractor shall submit a schedule for equipment identification. 3.9 CUTTING AND PATCHING A. Field verify openings indicated on the Drawings. Provide all cutting and patching required for electrical work. B. Sleeves and inserts: Provide all sleeves, inserts, and openings necessary for the installation of the Electrical Work. Provide sleeves in all floors (except where fire proofing is required) and concrete walls. C. Openings for all electrical equipment shall be field verified: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 24 Electrical Common Work June 30, 2010 1. 2. 3. 4. 5. 6. 7. 3.10 Special forming, recesses, chases, and curbs, for the correct reception and installation of the electrical equipment, as shown on the Drawings, are specified in other divisions. Ascertain that provisions have been made for the Work. If such provisions are not made in time, the Contractor shall bear all extra costs incurred in late cutting and patching to accommodate the work. The work shall be carefully laid out in advance. Where cutting, channeling, chasing or drilling of floors, walls, partitions, ceilings or other surfaces is necessary for the proper installation, support or anchorage of raceway, outlets or other equipment, the work shall be carefully done and where required, fire rating integrity shall be restored. Any damage to the piping, equipment or defaced finish plaster, woodwork, metalwork, etc. shall be repaired by skilled mechanics of the trades involved at no additional cost to the Owner. Refer to architectural specifications for details and requirements. The Contractor shall do no cutting, channeling, chasing or drilling of unfinished masonry, tile, floor slab, etc., unless he first obtains permission from the Architect and Structural Engineer. If permission is granted, the Contractor shall perform this work in a manner approved by the Architect/Engineer. If holes and/or sleeves are not properly installed and cutting and patching becomes necessary, it shall be done at no additional expense to the Owner. The Contractor shall undertake no cutting or patching without first securing the Architect's written approval. Where other Trades are required to do cutting and patching, furnish to the Construction Manager necessary information so that openings for this work can be built into the floors and walls in time. Such cooperation is required to keep cutting of walls and floors to a minimum. Should Contractor neglect to perform preliminary work, and should cutting be required in order to install equipment, conduits, etc, the expense of this cutting and restoring of surfaces to their original condition shall be borne by this Contractor. FIRE ALARM SYSTEM A. Provide programming and all modifications required to the existing fire alarm terminal cabinet and fire alarm control panel to accommodate system revisions, deletion of existing devices and addition of new devices. B. New devices and system shall be capable of interfacing and operating with the existing system. The contractor is responsible without additional cost to the owner for any modifications and additional devices necessary should another manufacturer be installed. C. Contact the existing fire alarm system maintenance vendor and designate this vendor as a sub-contractor for fire alarm system installation. The fire alarm system maintenance vendor is simplex grinnellinc. Contact Enver Perezic at office number 212-372-4200 or cell number 917-416-8146. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 25 Electrical Common Work June 30, 2010 D. 3.11 The riser diagram is shown to provide a general representation of the connection of the new and existing devices. The contractor is responsible for installing required wiring based on the local code requirement. PROTECTION AND CLEANING A. Protection: Fully protect all finished parts of the materials and equipment against physical damage from whatever cause during the progress of the work and until completion. B. During construction, cap all conduits to prevent the entrance of sand and dirt. C. Cleaning: After installation has been completed, the Contractor shall clean all systems as follows: 1. 2. Equipment with Factory Finish: Clean exterior thoroughly to remove grease, oil, plaster, cement and dirt, and leave surfaces clean and polished. Equipment to be painted: a. b. c. d. 3. 4. 5. Clean exterior of piping and equipment exposed in completed structure, removing rust, plaster, cement and dirt by wire brushing. Remove grease, oil and similar materials by wiping with clean rags and solvents. Equipment furnished under this Section shall have factory-applied finish. If the factory finish is damaged during shipment, storage, installation, etc., it shall be repainted by this Contractor subject to the Engineer’s approval. Touch-up painting is acceptable only for minor finish damage. Provide a heavy field coat of black asphalt paint on all steel conduits, cradles, vibration isolating mounts, and the like, that will be encased or partially encased in building construction, set in cement or fill, before items are built into the general construction. Where conduits, mounting channels, outlet, junction, or pull boxes are mounted on a painted surface, or a surface to be painted they shall be painted, by this contractor, to match the surface. Contractor shall take care to avoid accumulation of debris, boxes, crates, etc., resulting from the installation of the work. Contractor shall remove from the premises each day all debris, boxes, etc., and keep the premises clean, subject to the Architect/Engineer's instructions, which shall be promptly carried out. Contractor shall clean up all luminaries and equipment at the completion of the project. All switchboards, switchgears, busway, panelboards, wireways, transformers, transfer switches, trench ducts, cabinets, enclosures, etc. shall be thoroughly vacuumed clean prior to energizing equipment and at the completion of the project. Equipment shall be opened for observation by the Architect/Engineer as required. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 26 Electrical Common Work June 30, 2010 3.12 FINAL ACCEPTANCE TESTS A. The entire electrical installation shall be pre-tested, inspected, thoroughly cleaned, and damaged finishes touched up after final completion prior to final acceptance testing being performed. Not less than 30 days prior to the final acceptance testing, furnish the pre-test results and a test plan, to the Engineer for review, outlining all aspects of the testing, including tests to be performed and the expected results. B. The Contractor shall provide a detailed schedule of completion indicating when each system is to be completed and outlining when tests will be performed. Completion schedule shall be submitted to the Architect, Engineer, and Owner for review at the time requested by the Construction Manager after the notice to proceed has been given by the Owner. This schedule shall be updated periodically by the Contractor as the Project progresses. Each update shall be submitted to the Architect, Engineer, and Owner for review. C. Provide complete documentation of all component and system tests prior to Owner acceptance and turnover of components or systems. In addition, the Owner reserves the right to review all test objectives, test plans and test cases, and witness all preoperational tests. Provide the Owner with a comprehensive schedule detailing the preparation of testing documentation and the conduct of all component or system tests. D. Operate all electrical systems and equipment for a period of 24 hours, unless in the opinion of the Engineer, a different test period is required, to prove the operation and performance of a system and its equipment. E. Should the foregoing test reveal any defects, promptly correct such defects and re-run the tests until the entire installation conforms to the requirements of these Specifications and the Drawings. F. Tests requiring certified reports and those requiring factory or field inspection shall be conducted and reported to the Engineer in conformance with standards specified in the applicable sections. G. In addition to the tests outlined above, after completion of the electrical system and prior to occupancy, the following equipment and devices, as a minimum, shall be thermo graphically inspected. 1. 2. 3. 4. Feeder splices and Connections. Transformer. Panelboards. All cable connections rated 100 amperes (#3 AWG) or greater. H. The inspection shall be made by an independent inspection company. The inspection shall be made with all equipment, motors, lighting fixtures, and miscellaneous loads operating and with equipment covers removed. I. Inspection reports complete with color photographs of the infrared scan and control photographs indicating the ambient temperature and any hot spots of each item inspected shall be submitted to the Engineer for approval. Any equipment, connections or devices indicated to be operating improperly performing equipment shall be replaced or repaired by the Contractor at no cost to the Owner. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 27 Electrical Common Work June 30, 2010 J. 3.13 A. The date for the final performance acceptance testing shall comply with the Project construction schedule and shall be sufficiently in advance of the Contract completion date to permit the execution of the testing by the Contractor prior to occupancy and the closeout of the Contract. Specific attention is required for any special spaces such as Tenant Areas, which will be governed, by a separate construction and turnover schedule from that provided for the overall project. Any adjustments and/or alterations, which the final acceptance tests indicate as necessary for the proper and satisfactory functioning of all equipment and systems, shall be completed prior to the closeout of the Contract. Re-tests shall not relieve the Contractor of completion date responsibility. DEMONSTRATION AND OPERATION INSTRUCTIONS After completion of all testing, and prior to placing equipment or systems in operation, demonstrate the features and operation of the equipment or systems to the Engineer, Owner, operational and maintenance personnel so that they are familiarized with the equipment and systems, in particularly the following equipment and systems: 1. 2. 3. 4. 5. Panelboards. Transformer. Lighting Control system Fire alarm and smoke detection systems. Other equipment and control systems shown on the Drawings. B. Provide the necessary accessories, test equipment, and personnel, for each demonstration. C. Complete all arrangements for the demonstrations through the Engineer. D. Upon the completion of each demonstration or instructional session, obtain "sign-off" from the Engineer and Owner. The "sign-off" shall state that the demonstration or instructions for use were provided, that they were complete and were given to the designated personnel. E. The Contractor shall provide the services of a factory trained specialist to supervise the commissioning, startup, and operation of all equipment specified herein and to instruct the Owner's operators during an operating instruction period at or near the Project site. The operating instruction period shall be defined as straight time working hours and shall not include nights, weekends, or travel time to and/or from the Project. See individual sections of these specifications for additional instructions by manufacturertrained specialists. F. The Owner shall be notified in writing at least two (2) weeks before each operating instruction period begins. The Contractor shall commence no instruction period until the Owner has issued his written acceptance of the starting time. 3.14 A. FINAL REVIEW At a time designated, the entire installation shall be reviewed for compliance with the Contract Drawings and Specifications. The Contractor shall be available at all times during this Review. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 28 Electrical Common Work June 30, 2010 B. The Contractor shall demonstrate prior to the Final Review that all systems and all equipment have been properly adjusted and comply with the requirements of the Contract Documents. After these demonstration tests are completed satisfactorily, but prior to the Final Review field visit, by the Engineer the Contractor shall submit to the Engineer a written certification that 1) attests to Contract Document compliance for this Project, and 2) certifies that the equipment and materials installed in this Project under this Section contain no asbestos or PCB. C. Certificates and Documents required herein shall be in order and presented to the Architect and Engineer at least two (2) weeks prior to the Final Review. D. After the Final Review, any changes or corrections noted as necessary for the Work to comply with these Specifications and the Drawings shall be accomplished immediately in order to secure final acceptance of the Work. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 231600- 29 Electrical Common Work June 30, 2010 SECTION 260519 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. 3. B. 1.3 Building wires and cables rated 600 V and less. Connectors, splices, and terminations rated 600 V and less. Sleeves and sleeve seals for cables. Related Work: Consult all other Sections, determine the extent and character of related work and properly coordinate work specified herein with that specified elsewhere to produce a complete installation. REFERENCES A. 1.4 Comply with the latest edition of the following applicable specifications and standards except as otherwise shown or specified: 1. 2. NFPA 70 NEMA WC 5 3. 4. 5. 6. 7. UL 83 UL 486A UL 486C UL 493 IEEE 82 National Electrical Code (NEC). Thermoplastic Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy Thermoplastic-Insulated Wires and Cables Wire Connectors and Soldering Lugs for use with Copper Conductors Splicing Wire Connectors Thermoplastic-Insulated Underground Feeder and Branch Circuit Cables Test Procedure for Impulse Voltage Tests on Insulated Conductors. SUBMITTALS A. Submit in accordance with the requirements of Section 260000, the following items: 1. 2. 3. 4. Data/catalog cuts for each product and component specified herein, listing all physical and electrical characteristics and ratings indicating compliance with all listed standards. Clearly mark on each data sheet the specific item(s) being submitted and the proposed application. Submit manufacturer's installation instructions. The Contractor shall submit "Megger" test report from testing agency to the Owner’s Representative as specified in 3.1 for approval of the work. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260519- 1 Low Voltage Electrical Power Conductors and Cables June 30, 2010 1.5 QUALITY ASSURANCE A. All materials, equipment and parts comprising the units specified herein shall be new and unused, and of current manufacturer. 1. 1.6 The Contractor shall provide a "Megger" insulation tester that applies a minimum of 500 volts direct current for the tests when requested by the Owner’s Representative at no additional cost. COORDINATION A. Set sleeves in cast-in-place concrete, masonry walls, and other structural components as they are constructed. PART 2 PRODUCTS 2.1 CABLES A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. B. General Cable. Rome. Or equal. Conductors shall have Underwriters Laboratories, Inc. (UL) listed 600 volts insulation of type specified below or elsewhere in the Specifications. 1. Branch Circuits - Lighting and Power a. b. c. 2. 3. 4. 5. #14 AWG and smaller, shall be solid conductors. #12 AWG and larger, shall be stranded conductors. The insulation shall be type THHN Feeders (100A and more): the insulation shall be type XHHW-2 or THHN. For conductors installed in exposed conduit outside of Buildings, in exposed conduit in tunnel and conduit within or just under roofing material, provide type XHHW. Control Circuits: Use 600 volts U.L. type THHN/THWN conductors except where subject to abnormally high temperatures such as on or near boilers. Wiring through fluorescent fixtures in continuous rows shall be type THHN. C. All conductors shall be copper. Aluminum conductors shall not be used for any type of wiring on this project. D. Minimum conductor size shall be #12 AWG except for control wiring where #14 AWG may be used. E. Branch Circuit and Feeder Wiring for all systems shall be continuous from switch to terminal or farthest outlet. No joint shall be made except in pull, junction, or outlet boxes, or in gutters. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260519- 2 Low Voltage Electrical Power Conductors and Cables June 30, 2010 F. All systems of wiring shall be so installed that when completed the systems will be free from short circuits and from grounds, other than required grounds. G. Provide all conductors used for power, lighting, control signal and communications systems, operating at 600 volts and below, with a minimum insulation rating of 600 volts. H. All conductors shall be delivered to the site on their original cable reels or in their original unbroken packages and shall be inspected and approved by the Owner’s Representative before opening. I. All conductors shall be new and shall have been manufactured within 12 months of the date of delivery to the site and continuously stored where protected from the heat or weather. J. Types of conductor insulation for general use may be any of the following, subject to limitations listed, in addition to those in the NEC. 1. 2. 3. 4. K. 2.2 Type XHHW - No restrictions, except do not use 90 degree C ampacity rating unless terminations are rated for 90 degree C. Use for exterior and wet area applications. Type THHN. Do not use for conductors in slab. Do not use in wet locations. Use Type THHN or XHHW, (90 degrees C. rated) types for connecting fluorescent fixtures and for running through fixture housings. Use conductors such as type FEP with high temperature insulation as identified in the NEC for connections to resistance heating elements or in other areas subject to temperature exceeding the rating of XHHW. Wire size ampacity shall equal or exceed its overload protective device. Where wire sizes shown on the drawings are greater than the apparent ampacity requirements, the size shown shall prevail to compensate for voltage drop. CONNECTORS A. Connections to equipment shall be made with pressure type terminals. On stranded wire, use spade type terminals or terminals approved for use with stranded wire. Connections shall contain only single conductors unless approved for multiples. 1. 2. For conductors No. 10 AWG and smaller, applied crimp type terminals shall be T&B "Sta-Kon" or approved equal. For No. 8 AWG and larger conductors, applied crimp type terminals shall be Burndy, T&B or approved equal. B. Where tape is applied over wires and connectors on 600 volt or lower voltage applications, it shall consist of a minimum of two (2) half-lapped layers of Scotch "88" or Plymouth No. 4240 for both indoor and outdoor applications, except Scotch 33 Plus or Plymouth No. 4453 is acceptable for use indoors. Underground splices shall be made using kits approved for the application. C. Where fireproofing of cables is noted on the drawings or required by Code, each cable shall be arc and fireproofed with one (1) half-lapped layer of Scotch Brand 77 Electric Arc and Fireproofing Tape. Tape shall be secured with a 2-layer band of Scotch Brand 69 Glass Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260519- 3 Low Voltage Electrical Power Conductors and Cables June 30, 2010 Electrical Tape over the last wrap. Installation shall comply with manufacturer's recommendation. 2.3 LUBRICANTS A. When necessary to use a lubricant for pulling wires, lubricant must be listed by Underwriters' Laboratories, Inc. Only cable lubricants approved for the type of jacket material or insulation shall be used, and must be of such consistency that it will dry completely when exposed to air. Lubricant must leave no obstruction or tackiness that will prevent pulling out old wires or pulling in new wires or additional wires, and, after drying, must leave a film of lubrication, which will promote easy movement of the wires. The lubricant shall contain no waxes, greases, silicones, or polyalkylene glycol oils or waxes. Lubricant shall be Ideal "Yellow 190", 3M “WL”” Wire Pulling Lubricant, or approved equal. B. It is not allowed to use oil, grease, graphite, or similar substances for pulling conductors in raceways. C. Pulling of size #1/0 or larger conductors shall be done with an approved cable pull machine. Other methods; e.g. using vehicles, and block and tackle to install conductors are not acceptable. 2.4 MISCELLANEOUS A. Cable supports: Vertical cable supports shall be manufactured by O.Z. type "M” series, Adalet "SVM" series, or equal. B. Insulating Tape: Insulating tapes shall be plastic self-adhering type manufactured by Minnesota Mining and Manufacturing "Scotch" #33 Electrical tape, Manville Bulldog #166, or equal. C. Conductor ties: Ties shall be plastic with cinching holders manufactured by T & B "Ty-Rap" series, Panduit "Pan-Rap" series, or equal. D. Sealants: Conductor sealant shall be silicone type manufactured by Dow-Corning #795, General Electric #SCS 1000 or equal. 2.5 SLEEVES FOR CABLES A. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, galvanized steel, plain ends. B. Cast-Iron Pipe Sleeves: Cast or fabricated "wall pipe," equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless otherwise indicated. C. Sleeves for Rectangular Openings: Galvanized sheet steel with minimum 0.052 thickness as indicated and of length to suit application. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260519- 4 Low Voltage Electrical Power Conductors and Cables June 30, 2010 D. Coordinate sleeve selection and application with selection and application of firestopping specified in Division 07 Section "Penetration Firestopping." PART 3 EXECUTION 3.1 EXAMINATION A. Verify interior of building has been protected from weather. B. Verify mechanical work likely to damage wire and cable has been completed. C. Verify raceway installation is complete and supported. 3.2 PREPARATION A. Completely and thoroughly swab raceway before installing any wire. B. Clean all outlet and J-boxes before installing any wire. C. Branch circuit conductors shall be pulled without resorting to levers or heavy pulling devices. D. Do not install permanent wiring, without special permission from the Owner’s Representative, until plastering is done and dirt removed. 3.3 INSTALLATION A. Branch circuit conductor identification means shall be permanently posted at each panel board. This identification shall be installed on the inside of the door and shall identify conductor colors for each voltage system in the building. B. All wires, both low and line voltage, shall be installed in code approved raceways unless exceptions are approved by the Owner’s Representative in writing. C. Branch Circuit Wiring Methods: Fluorescent Fixtures shall not be used as a raceway for branch circuit conductors except where installed end-to-end to form a continuous assembly and UL listed for through-wiring. D. Wiring in vertical raceways shall be supported with strain relief devices, Kellem's grips or approved equal. E. Make all branch circuit and fixture joints for #10 AWG and smaller wire with connectors. F. Make all branch circuit joint of #8 AWG and larger with screw pressure lugs, and insulate with electrical tape to 150% of the insulating value of the conductor insulation. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260519- 5 Low Voltage Electrical Power Conductors and Cables June 30, 2010 G. Tape all connections made with non-insulated type connectors with insulating tape to 150 percent of the insulating value of conductor insulation. H. Each circuit must correspond to the branch circuit number indicated on the panel schedule shown on the Drawings except where departures are approved by the Owner’s Representative. I. Where conductors in conduit pass through exterior walls, a sealing compound of moistureresistant material shall be applied in the ends of the conduits to seal around the conductors. J. Tag all conductors of power circuits and the various signal systems. Conductors shall be tagged in each junction box, pull box, wireways or auxiliary gutter and at each device, motor outlet, panelboard, and switchboard or other conductor termination. Tag shall show feeder number, date energized; voltage, what the cable feeds - "to" and "from", size, phase and origin, indicating panelboard and circuit number. Cable tags shall, be non-corrosive type attached to cable with "wire tie wraps". K. Wiring within all equipment enclosures shall be neatly grouped and tied together. L. Pigtails shall be extended from branch wiring in outlet boxes for attachment to devices. Loops in through wiring will not be acceptable. M. Conductors in outlet boxes shall have a minimum of eight inches of extra conductors. N. Inspect wire and cable for physical damage and proper connection. O. Verify continuity of each branch circuit conductor. P. Tighten bolted connections to manufacturer's recommended torque values. Q. Terminations for signal and control circuits shall utilize crimp-on spade lugs. R. Splices in damp or wet locations, or where located in pullboxes or manholes, shall utilize cast resin type, watertight connections. S. Do not run conductors from different panelboards in same raceway. T. Do not run conductors with different voltages in same raceway. U. Re-tighten all bolt type connectors 24 to 48 hours after initial installation and before taping. 3.4 WIRE COLOR A. Conductor Color Coding and Identification: Conductors larger than #10 shall have colored tape wrapped around each conductor and circuit number identification tags, in junction boxes, pull Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260519- 6 Low Voltage Electrical Power Conductors and Cables June 30, 2010 boxes, manholes, switchgear, panels, cabinets, and wherever a break or termination in the conductor occurs, etc. Conductors #10 AWG and smaller shall have color coded insulation as follows: 1. Wire Color Code Neutral Phase A Phase B Phase C Ground Switch Traveler, (3- or 4-way) 2. 3.5 208/120 V White Black Red Blue Green Switch Leg 120 V --Black w/white stripe Red w/white stripe Blue w/white stripe --Purple w/black stripe Equipment ground conductor shall be green, and Isolated ground conductor shall be green with yellow stripe. FIELD QUALITY CONTROL A. Perform inspections and tests listed in NETA ATS, section 7.3.1. B. Prior to energizing conductors, test using a 500 Volt megger to determine insulation resistance, and a check for short circuits. C. Tests shall be made prior to final connection of equipment. D. All conductors failing to comply with the manufacturers' minimum standard or recommendations shall be replaced at Contractor's expense. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260519- 7 Low Voltage Electrical Power Conductors and Cables June 30, 2010 SECTION 260529 HANGERS & SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. 3. 4. 5. B. Related Sections include the following: 1. 2. 3. 4. 1.3 Hangers and supports for electrical equipment and systems. Construction requirements for concrete bases. Equipment supports. Equipment anchoring and supports. Fastening hardware. Section 260548 Vibration and Seismic Controls for Electrical Systems for products and installation requirements necessary for compliance with seismic criteria. Section 055000 – Metal Fabrications: Hangers. Section 095300 – Acoustical Ceiling Suspension Assemblies. Section 260533 – Raceway and Boxes. DEFINITIONS A. EMT: Electrical metallic tubing. B. IMC: Intermediate metal conduit. C. RMC: Rigid metal conduit. 1.4 PERFORMANCE REQUIREMENTS A. Design support and anchorage systems to resist all gravity and seismic forces in accordance with the requirements of the Building Code. B. Delegated Design: Design supports for multiple raceways, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated. C. Design supports for multiple raceways capable of supporting combined weight of supported systems and its contents. D. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260529- 1 Hangers & Supports for Electrical Systems June 30, 2010 E. 1.5 Rated Strength: Adequate in tension, shear, and pullout force to resist maximum loads calculated or imposed for this Project, with a minimum structural safety factor of 3 times the applied force. SUBMITTALS A. 1.6 Submit dimensioned layout drawings, details, locations and structural calculations for gravity and seismic support systems. Include plans, elevations and all necessary information to satisfy the Authority Having Jurisdiction. Calculations shall be prepared and signed by a Registered Structural Engineer. QUALITY ASSURANCE A. Coordinate installation of roof curbs, equipment supports, and roof penetrations. These items are specified in Division 07 Section "Roof Accessories." PART 2 PRODUCTS 2.1 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS A. Steel Slotted Support Systems: Comply with MFMA-4, factory-fabricated components for field assembly. 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. b. c. 2. 3. Unistrut; Cooper B-Line, Inc.; Thomas & Betts Corporation. Metallic Coatings: Hot-dip galvanized after fabrication and applied according to MFMA4. Channel Dimensions: Selected for applicable load criteria. B. Raceway and Cable Supports: As described in NECA 1 and NECA 101. C. Conduit and Cable Support Devices: Steel and malleable-iron hangers, clamps, and associated fittings, designed for types and sizes of raceway or cable to be supported. 1. 2. Hot-dip galvanized, cast malleable iron, one hole type strap with cast clamp-backs and spacers as required. OZ/Gedney "14-G" series strap and "141G" series spacer; Efcor "231" series strap and "131" series spacer; Thomas & Betts "1276" series strap and "1350" series spacer, or equal. D. Support for Conductors in Vertical Conduit: Factory-fabricated assembly consisting of threaded body and insulating wedging plug or plugs for non-armored electrical conductors or cables in riser conduits. Plugs shall have number, size, and shape of conductor gripping pieces as required to suit individual conductors or cables supported. Body shall be malleable iron. E. Structural Steel for Fabricated Supports and Restraints: ASTM A 36/A 36M, steel plates, shapes, and bars; black and galvanized. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260529- 2 Hangers & Supports for Electrical Systems June 30, 2010 F. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces include the following: 1. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete, steel, or wood, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used. a. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1). 2). 3). 2. Mechanical-Expansion Anchors: Insert-wedge-type, stainless steel, for use in hardened portland cement concrete with tension, shear, and pullout capacities appropriate for supported loads and building materials in which used. a. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1). 2). 3). 3. 4. b. 6. 7. 8. 9. Cooper B-Line, Inc. Ramset/Red Head; MKT Fastening, LLC. Drilled sleeve type expansion anchors, Ramset "Dynabolt," "Red-Head" RM series or equal. Concrete Inserts: Steel or malleable-iron, slotted support system units similar to MSS Type 18; complying with MFMA-4 or MSS SP-58. a. 5. Remington. ITW Ramset. MKT Fastening, LLC. Pressed galvanized steel, spot insert, with oval slot capable of accepting support nuts of 1/4-inch to 1/2-inch diameter thread. Unistrut No. M24 with "M2506" series nut; Superstrut No. 425 with "AB-102" series nut, Kinline No. 279 with "660" series nut, or equal. Clamps for Attachment to Steel Structural Elements: MSS SP-58, type suitable for attached structural element. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325. Toggle Bolts: All-steel springhead type. Hanger Rods: Galvanized rod, sized for the load unless otherwise shown or specified. deck inserts a. b. Steel plate 3/16-inch thick with threaded galvanized steel rod sized for load. Superstrut No. C-475 series, Kinline No. 293 series, or equal. PART 3 EXECUTION 3.1 APPLICATION A. Comply with NECA 1 and NECA 101 for application of hangers and supports for electrical equipment and systems except if requirements in this Section are stricter. Roosevelt Hall Renovation 260529- 3 Hangers & Supports for Electrical Brooklyn College Systems Brooklyn, NY June 30, 2010 Project #6032.20 B. Maximum Support Spacing and Minimum Hanger Rod Size for Raceway: Space supports for EMT, IMC, and RMC as required by NFPA 70. Minimum rod size shall be 1/4 inch in diameter. C. Multiple Raceways or Cables: Install trapeze-type supports fabricated with steel slotted support system, sized so capacity can be increased by at least 25 percent in future without exceeding specified design load limits. D. 3.2 1. Secure raceways and cables to these supports with two-bolt conduit clamps. Spring-steel clamps designed for supporting single conduits without bolts may be used for 11/2-inch and smaller raceways serving branch circuits and communication systems above suspended ceilings and for fastening raceways to trapeze supports INSTALLATION A. Provide supporting devices as noted in other Sections of Division 26. B. Fasten hanger rods, conduit clamps, outlet and junction boxes to building structure using precast inserts, expansion anchors, preset inserts or beam clamps. C. Use hollow wall fasteners in hollow masonry walls. D. Use expansion anchors or preset inserts in solid masonry walls. E. Use self-drilling anchors or expansion anchors on concrete surfaces. F. Powder activated anchors may only be used if first accepted in writing by the Architect. G. Use sheet metal screws in sheet metal studs and wood screws in wood construction. H. Do not fasten supports to piping, ductwork, mechanical equipment, or conduit. I. Do not drill structural steel members unless first accepted in writing by the Architect. J. Fabricate supports from structural steel or steel channel, rigidly welded or bolted to present a neat appearance. Use hexagon head bolts with spring lock washers under all nuts. K. Install surface-mounted cabinets and panelboards with a minimum of four anchors. Provide additional support backing in stud walls prior to sheet rocking as required to adequately support cabinets and panels. L. Bridge studs top and bottom with channels to support flush-mounted cabinets and panelboards in stud walls. M. Anchor free-standing equipment on concrete pads where indicated. 3.3 PAINTING A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces. 1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780. Roosevelt Hall Renovation 260529- 4 Hangers & Supports for Electrical Brooklyn College Systems Brooklyn, NY June 30, 2010 Project #6032.20 B. 3.4 LAYOUT A. Layout support devices to maintain headroom, neat mechanical appearance and to support equipment loads. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260529- 5 Hangers & Supports for Electrical Systems June 30, 2010 SECTION 260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This section includes Labor, materials and equipment necessary to complete the installation required for the item specified under this Division, including but not limited to: 1. 2. 3. 4. 5. 6. 7. 8. 9. B. Related Sections include the following: 1. 1.3 Rigid steel conduit and fittings. Flexible metallic conduit and fittings. Liquid tight flexible metallic conduit and fittings. Electrical metallic tubing and fittings. Rigid non-metallic conduit and fittings. Outlet boxes. Pull and Junction boxes. Floor boxes. Miscellaneous products. Related work: Consult all other Sections, determine the extent and character of related work and properly coordinate work specified herein with that specified elsewhere to produce a complete installation. DEFINITIONS A. RGS: Rigid Galvanized Steel. B. IMC: Intermediate Metal Conduit. C. FMC: Flexible Metal Conduit. D. LFMC: Liquid tight Flexible Metal Conduit. E. EMT: Electrical Metallic Tubing. 1.4 REFERENCES A. Comply with the latest edition of the following applicable specifications and standards except as otherwise shown or specified. 1. 2. 3. 4. 5. ANSI C80.1 ANSI C80-3 ANSI/NEMA FS 1 ANSI/NFPA 70 FS WW-C-563A - Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 Rigid Steel Conduit, Zinc-Coated Electrical Metallic Tubing, Zinc-Coated Fittings and Supports for Conduit and Cable Assemblies National Electrical Code (NEC) Electrical Metallic Tubing 260533- 1 Raceway and Boxes for Electrical Systems June 30, 2010 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 1.5 FS WW-C-566 FS WW-C-581 NEMA TC 2NEMA TC 3 NEMA NEMA OS-1 Supports NEMA OS-2 Supports NEMA 250 UL 1 UL 6 UL 651 UL 797 - Specification for Flexible Metal Conduit Specification for Galvanized Rigid Conduit Electrical Plastic Tubing and Conduit PVC Fittings for Use with Rigid PVC Conduit and Tubing FB-1 Fittings and Supports for Conduit and Cable Assemblies Sheet-Steel Outlet Boxes, Device Boxes, Covers and Box Nonmetallic Outlet Boxes, Device Boxes, Covers and Box Enclosures for Electrical Equipment (1000 volts maximum) Flexible Metal Conduit Rigid Metal Conduit Rigid Nonmetallic Electrical Conduit Electrical Metallic Tubing SUBMITTALS A. Submit in accordance with the requirements of Section 260000, the following items: 1. 2. 3. 4. 5. 1.6 Data/catalog cuts for each product and component specified herein, listing all physical and electrical characteristics and ratings indicating compliance with all listed standards. Clearly mark on each data sheet the specific item(s) being submitted and the proposed application. Submit manufacturer's installation instruction. Provide written instructions for raceway products requiring glues, special tools, or specific installation techniques. Submit samples for each fitting (2 samples of each type). List of conduit types indicating where each type will be used. QUALITY ASSURANCE A. All materials, equipment and parts comprising the units specified herein shall be new. 1. B. Only products and applications listed in this Section may be used on the project unless otherwise submitted and approved by the Owner’s Representative. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. PART 2 PRODUCTS 2.1 RIGID GALVANIZED STEEL (RGS) A. Manufacturers: 1. 2. B. Allied Tube and Conduit Or equal Rigid or Immediate Galvanized Steel Conduit (RGS or IMC): 1. Provide standard weight, highest quality prime steel that is hot-dipped galvanized inside and out. It should have uniform wall thickness with smooth and defect free interior. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 2 Raceway and Boxes for Electrical Systems June 30, 2010 2. 3. 4. 5. 2.2 Fitting shall be zinc coated, ferrous metal and threaded type. Split or bolt-on type is not acceptable. All fittings, couplings and connectors shall be threaded type. Treads shall be hot dipped galvanized after cutting. Electro-galvanizing is not permitted. Grounding bushings, malleable iron; insulated; Steel City BG-801; Midwest Series GLL. FLEXIBLE METAL CONDUIT (FMC) A. Manufacturers: 1. 2. 3. AFC Alflex Or equal B. Conduit: Provide conduit manufactured from single strip, standard weight steel hot-dipped galvanized on all four sides prior to conduit fabrication. Flexible aluminum and flexible lightweight steel conduit will not be allowed. C. Fittings: Flexible Conduit Connectors and Couplings: Provide die cast fittings of the type that screw into the inside of the conduit with threaded edges at 90 degrees to the fitting body to insure a force fit. Binding screw type will not be acceptable. Fittings shall be manufactured by AFC, O-Z Gedney, T&B, Steel City or equal. D. General: flexible conduit and fittings shall provide positive ground continuity. Include a separate green grounding conductor in each run. 2.3 LIQUIDTIGHT FLEXIBLE METAL CONDUIT (LFMC) A. Manufacturers: 1. 2. 3. Sealtite Flexible type “UA” Flex-Seal type “XL” Or equal B. Conduit: Liquid-tight conduit shall be manufactured from single strip standard weight steel, hot dipped galvanized on all four sides prior to conduit fabrication, and shall be provided with an extruded polyvinyl chloride cover. C. Fittings: Fittings shall be malleable iron, zinc plated, with locknut and O-ring seal and slim diameter with small turning radius. Fittings shall be manufactured by O-Z Gedney-4Q series, T&B- 5200 series or Appleton Flexible Fittings-ST series. D. General: Liquidtight conduit and fittings shall provide positive ground continuity. Include a separate green grounding conductor in each run. 2.4 ELECTRICAL METALIC TUBING (EMT) A. Manufacturers: 1. 2. 3. Allied Tube and Conduit Western Or equal Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 3 Raceway and Boxes for Electrical Systems June 30, 2010 B. Conduit: Provide tubing of high grade steel electrically welded with exterior protective coating of hot galvanized zinc, applied by the electro galvanized process. Interior surface shall be coated with aluminum lacquer or enamel. Tubing shall be dipped in a chromic acid bath to chemically form a corrosion-resistant protective coating of zinc chromate over galvanized surface. C. Fittings: Fitting shall be steel, watertight, gland ring compression type, wrench tightened connectors and couplings. Die Cast, set screw or indenter types will not be acceptable. Fittings shall be manufactured by Appleton, O-Z Gedney, Cooper/Crouse-Hinds or equal. 2.5 WIREWAY A. Manufacturers: 1. 2. 3. Wiremold B-line Or equal B. Provide metal wireway where indicated on drawings or as required. The size shall be minimum 6”x6” unless otherwise noted. The finish shall be rust inhibiting primer coating with grey enamel finish. C. Outdoor units shall be raintight with screw covers and furnished with full gaskets. 2.6 OUTLET BOXES A. Manufacturers: 1. 2. 3. 4. B. Standard Outlet Box: 1. 2. 3. 4. 5. 6. 7. 8. C. Appleton Steel City Raco Or equal Outlet boxes and covers shall be galvanized pressed steel and plugged holes, and shall be hot dipped galvanized or sherardized. The minimum box size shall be 4” square by 2-1/8” deep. Telephone and data outlets shall be a minimum of 4-11/16” square by 2-1/8” deep. Light fixture outlet boxes shall be equipped with fixture-supporting device, as required by the unit to be installed. Switch Outlets: Use solid gang boxes for three or more switches for mounting behind a common single plate. Fire Alarm boxes shall be 4” square with plaster rings to suit type of device. Special boxes shall be as specified in Section 28 31 00. For boxes concealed in walls or ceiling, provide the solid gang, galvanized steel knockout type. Sectional boxes shall not be used. Light fixture outlet boxes shall be equipped with fixture-supporting device, as required by the unit to be installed. Concrete Box: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 4 Raceway and Boxes for Electrical Systems June 30, 2010 1. 2. D. Provide galvanized steel, 4” octagon rings with mounting lugs, backplate and adapter ring as required. Select height as necessary to position knockouts above concrete reinforcing steel Surface Mounted Cast Metal Boxes, type “FS” or “FD”: 1. 2. Provide galvanized cast iron alloy; flat flanged, surface mounted junction box with threaded hubs and mounting lugs as required. Furnish box with cast cover plate of same material as the box with ground flange, neoprene gasketed, and stainless steel screws. E. Cast Metal Pull and Junction Box: Provide standard cast malleable iron outlet or device boxes wherever possible; otherwise use cadmium plated, cast malleable iron boxes with bolt-on, interchangeable conduit hub plates with neoprene gaskets. Manufactured by O.Z. Gedney, Alhambra Foundry Co. or equal. F. Flush mounted pullboxes and junction boxes: Provide overlapping covers with flush head cover retaining screws, prime coated. 2.7 PULL AND JUNCTION BOXES A. Sheet Metal Pull and Junction Box 1. 2. Provide standard outlet or concrete ring boxes wherever possible; otherwise use minimum 16 gauge galvanized sheet metal, NEMA 1 boxes, sized to Code requirements with covers secured by cadmium plated machine screws located 6 inches on centers. ANSI/NEMA OS 1. B. Cast Metal Pull and Junction Box: Provide standard cast malleable iron outlet or device boxes wherever possible; otherwise use cadmium plated, cast malleable iron boxes with bolt-on, interchangeable conduit hub plates with neoprene gaskets. Manufactured by O.Z. Gedney, Alhambra Foundry Co. or equal. C. Flush mounted pullboxes and junction boxes: Provide overlapping covers with flush head cover retaining screws, prime coated. D. Precast Concrete Boxes: Provide high density reinforced concrete pull and junction box with end and side knockouts and non-settling shoulders. Use cast iron lid with hold down bolts or use traffic rated covers in areas subject to vehicular traffic. Manufactured by Associated, Quickset, Jensen/Brooks or equal. E. Cast Flush Floor Box: 1. 2. 3. Single or multi-gang floor boxes shall be cast iron with brushed aluminum coverplates and carpet flange (or any type of flange required for other types of floors) for flush applications in concrete floor. Furnish with provisions for adjustments before and after pour. Provide with all accessories such as receptacles, compartment dividers, coverplates, options, rings, etc. as indicated for application on drawings. Furnish the box in either shallow or deep sizes as determined by the concrete floor depth and in ganged configurations shown on drawings. Use Walker #880 series or equal. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 5 Raceway and Boxes for Electrical Systems June 30, 2010 2.8 MISCELLANEOUS A. Sleeves shall be zinc coated galvanized steel pipe or 16 gauge galvanized sheet metal. B. Sealant: Fire rated equal to wall or ceiling penetrated. Silicon foam Dow-Corning #2001, 3M, "Pensil #851," or approved equal. Sealant compound for exterior walls shall be moistureresistant material made by 3M, GE, Dow-Corning or equal. C. Conduit unions shall be "Erickson" couplings manufactured by Thomas and Betts, Type 4Series manufactured by O-Z/Gedney or equal. D. Conduit seals shall be Crouse-Hinds Type "EYS" or EZS," Appleton Type "ESUF" or "ESUM," or approved equal, with sealing compound as recommended by the manufacturer for hazardous or refrigerated areas. E. Conduit Outlet Body: Provide Cadmium plated cast iron alloy, oblong conduit outlet bodies with threaded conduit hubs and neoprene gasket, cast iron covers where required. Condulets shall be cast iron with threaded hubs and gasket. Type "LBD" or "LBDN" series, manufactured by Appleton, Crouse-Hinds or equal. F. Expansion couplings shall be OZ Type "AX" or "DX," Crouse-Hinds Type "XJ" or "SD" or equal, complete with bonding jumper. G. Conduit unions shall be "Erickson" couplings manufactured by Thomas and Betts, Type 4Series manufactured by O-Z/Gedney or equal. H. Anchors not cast into concrete shall be expansion shield type, Phillips "Red Head," Hilti, or equal. I. Acoustic pads shall be pliable, putty-like pads, one-eighth-inch thick. Manufactured by Lowry Pads, L.H. Dotty or equal. J. In areas having special membrane waterproofing in or on the floor slab, a Josam 26420, or equal approved by the Architect, riser sleeve with clamping ring and auxiliary conduit sleeve extending 4 inches above finished floor or 8 inches above finished roof shall be used. Waterproofing membrane for roof floor construction shall be secured by the clamping ring. These are to be used in areas having special membrane waterproofing in or on the floor slab and at roof decks. K. Multiple conduits extending through the roof may be fitted with a manufactured pipe curb weatherproofing assembly equal to Pate, Pca, Lpca and Mpca as an alternative to that specified in paragraph 2.7 above. L. Escutcheon plates shall be split-ring chromium plated pressed steel. Plates shall be sized to cover the surface penetration and sleeve. Plates shall be installed on exposed piping in finished rooms and areas where conduits penetrate walls, floors, ceilings or overhead structure. 2.9 SLEEVES AND OPENINGS A. Sleeves and formed openings shall be placed in walls, partitions, floor slabs and poured concrete roof decks for the passage of conduit, cable, wireway and cable tray. Sleeves and formed openings are not required: 1. In floor slabs on grade. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 6 Raceway and Boxes for Electrical Systems June 30, 2010 2. 3. 4. 5. 6. 7. Where conduit is installed before the wall, partition or slab is constructed. Openings are cut for conduit passage and patched with equal or comparable material to close the space around the conduit. In stud and gypsum board or plaster walls and partitions, which are not fire-rated. For conduit passing thru masonry walls and partitions and stud and gypsum board or plaster walls and partitions. Sleeves are required however, for which expansion, contraction and other movement can be expected. In core drilled openings in solid concrete not requiring water protection. Sleeves are required, however, at core drilling thru hollow pre-cast slabs and concrete block walls, to facilitate containment of required firestopping material. In large floor openings for multiple pipe and duct risers, which are within a fire-rated shaft, unless the opening is to be closed off with concrete or other material after conduits, are set. B. Sleeves for passage of conduit and cables shall be schedule 40 black steel pipe or galvanized rigid conduit. Rectangular sleeves for cables, wireway and cable tray shall be 18 gauge galvanized steel in poured concrete floors, walls and roof decks; 26 gauge galvanized sheet steel in other than poured concrete. C. Sleeves shall be sized to afford 0.25" to 0.75" clearance space. PART 3 EXECUTION 3.1 EXAMINATION A. 3.2 Thoroughly examine site conditions for acceptance of raceway and box installation to verify conformance with manufacturer and specification tolerances. Do not commence with installation until all conditions are made satisfactory. PREPARATION A. Raceway: 1. 2. 3. B. Boxes: 1. 2. 3.3 Deliver conduits and raceways to site in standard lengths, and store in dry and enclosed locations. Installation of raceways shall be coordinated with building structure and other trades, and shall be complete with bends, fittings, junction, and pull boxes to meet all codes and make complete operating systems. Provide the type of conduit permitted in these Specifications or required for each location or condition per applicable codes and jurisdictions whichever is more stringent. Install all outlet boxes flush with building walls, ceilings and floors except where boxes are installed in mechanical and electrical rooms, in cabinetry, above accessible ceilings or where exposed work is called for on the Drawings. Locate pullboxes and junction boxes in concealed locations above removable ceilings (shall be accessible) or exposed in electrical rooms, utility rooms or storage areas. INSTALLATION - RACEWAY A. General Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 7 Raceway and Boxes for Electrical Systems June 30, 2010 1. Conduit and raceway shall not be run in foundation, column, concrete slab, nor in the plane of the concrete shear wall without written approval of the Owner’s Representative for each conduit run. 2. Conduit shall be continuous from outlet to outlet, from outlet to cabinet, junction box, pull box and shall enter and be secured to all boxes, etc., in such a manner that each system will be mechanically and electrically continuous from service to all outlets. 3. Junction boxes or pull boxes shall be installed to avoid excessive runs and bends between outlets. 4. Conceal conduit above ceiling, below floors or in walls, unless otherwise noted. 5. A separate conduit shall be installed for each homerun indicated on the Drawings. 6. Wherever conduit extends through roof, furnish and install galvanized sheet metal flashing. Flashing shall extend six inches above roof. 7. From each panel which is flush mounted in a wall, stub from top of the panel, a minimum of four 1-inch conduits to the nearest ceiling space or other accessible location and cap for future use. 8. Paint conduits with identifying colors for each system, per Section 26 05 53. 9. In long runs of conduit, provide sufficient pull boxes inside buildings to facilitate pulling wires and cables. Support all pull boxes from structure independent of conduit supports, with spacing not to exceed 200 feet. These pullboxes are not necessarily indicated on drawings. Pull boxes shall be provided for every 100 feet of telecommunications conduit runs. 10. Conduit support shall be dedicated to support the conduit system only and shall not support any other item. B. Size of Conduits 1. 2. 3. 4. 5. 6. C. The size of the conduits for the various circuits shall be as indicated on the Drawings. No conduit shall be smaller than 3/4" unless otherwise noted. 1/2" conduit may be used for switch leg only up to 3 wires plus ground from switch to first J-box. Conduit size shall be increased to facilitate the pulling of wires. Conduit size shall be increased to the next larger size where it shall be installed in slab or underground. Minimum conduit size for underground shall be 1". Conduit Placement 1. Conduit Supports: a. b. c. Conduits larger than 1 inch shall be suspended with pipe hangers. Pipe hangers for individual conduits shall be Grinnell #108 and #110R, Super Strut #M-718-5R, or equal, malleable iron split pipe rings, suspended from hanger rods. Rods shall be 3/8-inch for 2-inch and smaller conduits, and 1/2-inch for 2-1/2-inch and larger conduits. Concealed areas: Support conduits 1-inch and smaller with pipe clamps either suspended from structural slabs with a rod at least 3/8 –inch diameter with adjustable pipe ring, or mounted on wall form channel supports. Attach to concrete with Phillips "Red Head," Hilti, or equal drilled anchors of appropriate load capacity. Hangers and racks shall be attached to concrete with insets, set at the time the concrete is poured, and to steel members with beam clamps or machine bolts. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 8 Raceway and Boxes for Electrical Systems June 30, 2010 d. 2. Where two or more conduits 1-1/2 inch and larger are suspended from ceiling, use trapeze type hanger suspended from rods. Where rigid metal conduits and electrical metallic tubing are supported from Building members, supports shall be installed as follows: a. Conduit Sizes 1). 2). b. c. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 3/4" to 1-1/4" within 18" of each outlet inclusive and on either side of couplings and fittings and at a spacing not to exceed 8 feet. 1-1/2" and larger within 3 feet of each junction or pullbox and terminal cabinet and at a spacing not to exceed 8 feet. When conduits are supported from trapezes, the supports shall be spaced not more than 8 feet apart. Conduit trapezes shall consist of suitable Unistrut or Kindorf fittings, or equal, in accordance with the manufacturer's printed recommendation. Secure exposed conduit runs on concrete, plaster or other construction in place with cast conduit clamps affixed with metallic expansion anchors or toggle bolts and cadmium plated machine or lag screws. All exposed conduits shall be installed parallel to and perpendicular to the building structure. Do not strap or fasten rigid conduit to mechanical equipment, or to equipment subject to vibration or mounted on shock absorbing bases. Conduits which are installed above dry type or suspended ceilings shall not be secured to ceiling support wires. Support such conduit independent of ceiling suspension systems. Support conduit to structure above suspended ceilings 8" minimum above ceiling to allow removal of ceiling tile. Do not support from T-bars or T-bar hanger wires. Maintain two inch clearance above recessed light fixtures. Support conduits adjacent to walls with preformed channels. Provide plated or galvanized hangers, rods, channels and metallic support and fastening material. Do not use perforated metal strap or wood as support material. Conduit 1-inch and smaller, in metal and stud partitions, shall be tied to the furring channels with 2# 14 gauge galvanized tie wire spaced not more than 5 feet apart. Conduits 1 inch and smaller for service to lighting fixtures (other than home runs) may be supported in the same way. Conduit clamps and hanger rods attached to concrete structures shall be secured by machine bolts or rods screwed into anchors. Anchors not cast into the concrete shall be of the expansion shield type, Phillips "Red Head," Hilti, or equal. Provide independent support for conduits rising from floor for motor connections if over 18 inches above floor. Do not support any conduit to motor, ductwork or mechanical equipment. Conduit shall not be run closer than 12 inches to any hot water pipe, steam pipe, heater flue or vent. Maintain minimum of 6" clearance between conduit and other piping. Provide condulets as required. Conduit bends will not be permitted around the corners of beams, walls or equipment. All condulet covers shall be accessible. Condulets 2 inches or larger shall be Crouse-Hinds Type "LBD," Appleton "LBD," or equal. Conduits in furred spaces shall be routed to clear access openings. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 9 Raceway and Boxes for Electrical Systems June 30, 2010 18. Where steel conduits enter a concrete floor below a surface mounted panelboard, they shall be encased in a concrete curb of sufficient height to match the height of the finished base tile. 19. Holes for conduits through existing concrete walls, manhole, or floors shall be made by the "core-drill" method. The size and location shall be approved by the Owner’s Representative. 20. Upon completing the installation of any run of conduit, the runs shall be tested to see that they are free from all obstructions and have a smooth interior. Each end of each conduit run shall be plugged with "pennies" and bushings and left plugged until ready to pull circuit wires. D. Cuts and Joints 1. Cut conduit squarely and ream ends to remove burrs. Close open ends of conduits, unless in a closed box or cabinet, with approved conduit caps or closures as soon as installed and keep closed until ready to pull in conductors. 2. Ream the ends of all conduits, and clean conduits before pulling conductors. 3. Use pipe joint compound (pipe dope) and oil applied to the male threads only and tighten joints securely. For underground or under slab conduits, apply a heavy coat of Pabco P & B No. 2 paint after installation to surfaces within 6" on both sides of fittings and to areas where wrenches or other tools have been applied. On exposed conduits, repair scratches and other defects with galvanizing repair stick, Enterprise Galvanizing "Galvabar", or equal. 4. Where conduit is underground, under slabs or grade, exposed to the weather, or in wet locations, make joints liquid tight and gas tight. 5. Cut threads on rigid conduit to standard taper and to length such that bare metal exposed by the threading operation will be completely covered by the couplings or fittings used. In addition, cut the lengths of the thread such that joints will become secure and wrench tight before conduit ends butt together in couplings and before conduit ends butt into the ends or shoulders or other fittings. Securely tighten threaded connections. 6. For rigid steel conduit use conduit unions to connect two rigidly held conduits. Running thread will not be accepted. 7. Right and left hand couplings shall not be used. 8. Secure rigid conduits to panels, pull boxes, wireways and enclosures with locknuts, inside and out, and provide high impact plastic or insulated throat steel bushings at terminations in pull boxes, wireways, signal cabinets, boxes and enclosures. For rigid steel conduit, provide steel insulating bushings with plastic liner. For EMT provide insulated throat connectors secured with locknut on interior of box or enclosure. For flex conduit, provide insulated throat steel twist-in connectors secured with locknut on interior of the box or enclosure, or steel twist-in connectors with plastic bushing, and locknut. At panelboards, switchboards and gear specified with ground bus, terminate conduits with ground bushing bonded to ground bus with code size conductor. Use approved couplings or unions; running thread, threadless coupling, or split coupling connections are not permitted. 9. Use insulated bushings and locknuts on all conduits where entering pullboxes, junction boxes, outlet boxes, cabinets and similar enclosures, and for all signal and telephone conduit terminated in cabinets or backboards. For 1-inch or larger bushings, shall be with grounding lugs, O.Z. Type BLG. or equal. Bushings shall be installed before any wire is pulled. 10. Conduit connections to panel cabinets and pull boxes shall have grounding wedge lugs between the bushing and the box or locknuts designed to bite into the metal. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 10 Raceway and Boxes for Electrical Systems June 30, 2010 11. Where conduits or wireways cross expansion joint, provide approved expansion or deflection fittings, or combinations of fittings that allow deflection in all directions. For seismic joints provide liquidtight flex. E. Sleeve 1. 2. 3. F. Wherever conduits pass through concrete walls, suspended slabs or metal deck floors furnish and install sleeves of ample size to permit installation of conduit. Sleeves shall be installed prior to pouring of concrete and shall have ends flush with the wall or extend 2 inches above floor surfaces. Verify locations with the Owner’s Representative. Finish around Sleeves: Rough edges shall be finished smooth. Space between conduit and sleeves where conduit passes through exterior walls shall be sealed to permit movement of conduit, but prevent entrance of water. Space between conduit and sleeves where conduits pass through fire rated interior walls and slabs shall be sealed with approved materials to provide a fire barrier conforming to the requirement of the Codes as listed in General Requirements. Sleeve shall be 1" to 2" bigger than conduit size. Empty Conduit 1. G. 3.4 For 1-1/2” and smaller conduits, provide nylon or polypropylene ropes, 1/8-inch O.D., in all conduits more than 5 feet in length left empty for future use. Minimum of 5 feet of rope shall be left at each end of the conduit. 2. For 2” and larger conduits, provide nylon or polypropylene ropes, 3/8-inch O.D., in all conduits more than 5 feet in length left empty for future use. Minimum of 5 feet of rope shall be left at each end of the conduit. 3. Tag all empty conduits at each accessible end with a permanent tag identifying the purpose of the conduit and the location of the other end. In wet, corrosive outdoor or underground locations, use brass, bronze, or copper 16 gauge tags or lead tags secured to conduit ends with #16 or larger galvanized wire. Inscribe on the tags, with steel punch dies, clear and complete identifying information. 4. Cap the open ends of conduits with approved manufactured conduit seals until ready to pull in conductors. 5. All open ends of conduits for communications cabling shall be furnished with plastic bushing. Conduit crossing building expansion joints shall have expansion provisions with grounding continuity; use special expansion fittings or other NEC approved method. INSTALLATION - BOXES A. General 1. 2. 3. 4. 5. Install outlet boxes at the locations and elevations shown on the Drawings or specified herein. Make adjustments to locations as required by structural conditions and to suit coordination requirements of other trades. Locate switch outlet boxes on the latch side of doorways unless otherwise indicated. Locate outlet boxes above hung ceilings having concealed suspension systems, adjacent to openings for removable recessed lighting fixtures or ceiling access panel. Do not install outlet boxes back-to-back, separate boxes by at least 6". In fire rated walls separate boxes by at least 24” and wall stud. Adjust position of outlet boxes in finished masonry walls to suit masonry course lines. Coordinate cutting of masonry walls to achieve neat openings for boxes. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 11 Raceway and Boxes for Electrical Systems June 30, 2010 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. B. Provide fire-proofing pad add additional sheet rock as necessary to maintain original fire rating of walls where boxes are installed on rated walls. For boxes mounted in exterior walls, make sure that there is insulation behind outlet boxes to prevent condensation in boxes. For outlets mounted above counters, benches or backsplashes, coordinate location and mounting heights with built-in units. Adjust mounting height to agree with required location for equipment served. Provide separate pull boxes and J-Box for different voltage conductors. Also provide separate boxes for general loads, communications, fire alarm, lighting, signal and miscellaneous systems. In concrete or drywall construction, set recessed boxes so that the front of the plaster ring or front of the box for those without plaster rings is not more than 1/4” behind the final finished surface. Set all recessed boxes in other types of construction so that the fronts are flush with the finished surface. Where these settings are not achieved, provide a 24-gauge or heavier galvanized steel liner flush with finished surface. For outlets flush in exterior walls, use weatherproof joints and connections all around. Outlets shall have cast covers and be fitted with gaskets. Covers for flush outlets shall finish flush with plaster or other finished surface. Label the cover of each accessible junction box with panel and circuit designation and function per Section 26 05 53. Paint the outside and inside of all boxes containing fire alarm devices with red paint. Provide acoustic pad or membrane around all outlet boxes and switches located in party walls of offices, meeting rooms and all quiet areas. Install boxes in accordance with manufacturer's written instructions, as shown on drawings and as specified herein. Locate electrical boxes as shown on Drawings and as required for splices, taps, wire pulling, equipment connections and Code compliance. Install junction or pullboxes where required to limit bends in conduit runs to not more than 270 degrees or where pulling tension achieved would exceed the maximum allowable for the cable to be installed. Note that these boxes are not shown on the Drawings. Install raised covers (plaster rings) on all outlet boxes in stud walls or in furred, suspended or exposed concrete ceilings. Covers shall be of a depth to suit the wall or ceiling finish. Use extension rings with blank covers for making exposed conduit connections to flush wall or ceiling boxes. Leave no unused openings in any box. Install close-up plugs as required to seal openings. Conduits entering boxes shall be thru tight-fitting bored or punched holes, or threaded hubs, and shall be secured firmly. For boxes not specified or indicated, use boxes and mounting height as required by equipment and recommended by equipment manufacturer. J-Boxes shall not be installed on mechanical or vibrational equipment unless used for power or control of the same equipment. No J-Box shall be installed on air ducts or pipes. Install galvanized steel coverplates on boxes in unfinished areas, above accessible ceilings and on surface mounted outlets. Provide cast metal boxes with gasketed cast metal cover plates where boxes are exposed in damp or wet locations. Use conduit outlet bodies to facilitate pulling of conductors or to make changes in conduit direction only. Do not make splices in conduit outlet bodies. Provide precast concrete boxes in exterior planting areas, walkways, roads etc. Provide 6” deep gravel base under each box. Supports: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 12 Raceway and Boxes for Electrical Systems June 30, 2010 1. 2. 3. 4. 5. 3.5 Provide boxes installed in metal stud walls with brackets designed for attaching directly to the studs or mount boxes on specified box supports. Mount boxes, installed in suspended ceilings of gypsum board or lath and plaster construction, to 16 gauge metal channel bars attached to main ceiling runners. Support boxes independently of conduit system. Support boxes, installed in suspended ceilings supporting acoustical tiles or panels, directly from the structure above wherever pendant mounted lighting fixtures are to be installed from the box. Support boxes, mounted above suspended acoustical tile ceilings, directly from the structure above. APPLICATION A. Rigid steel conduit (RGS or IMC) shall be used for the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. B. EMT conduit shall be used for the following: 1. 2. 3. 4. 5. C. Feeder for 208 volt and higher. EMT conduit shall be used for all sizes up to 1-1/2 inches in dry locations as in stud partitions and furred ceiling space. EMT conduit may be used up to 4-inches for Telecommunication and Voice/Data System. EMT conduit may be used up to 1-1/2 inches for Fire Alarm System wiring where conduit is concealed and where it is not main run and riser. EMT conduit shall not be used for underground, exterior, where it is prohibited and where rigid steel conduit is required. Flexible steel conduit shall be used in dry locations where indicated, and as follows: 1. 2. 3. 4. 5. D. Where required by Code. Where exposed to weather. Where in slabs and in concrete. Where exposed to physical damage In electrical, mechanical, or any machine room. Where exposed and below 7'-6" of above finished floor. In corrosive area. In damp and wet locations. In utility areas & loading dock. Fire alarm main runs and risers. Where required by Code. For connection to recessed light fixture from junction box or pull box, maximum of 6'. Where structural condition prevents the use of other type of conduit and for a maximum length of 24". For final connection to motors, transformers, and vibrating equipment. Lengths shall be limited to a minimum of 24" and maximum of 36". Minimum length of flexible steel conduit shall be 24" and maximum of 72" unless otherwise noted. Liquidtight Flexible conduit shall be installed in lieu of the flexible steel, as follows: 1. 2. Where required by Code. In plenum area. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 13 Raceway and Boxes for Electrical Systems June 30, 2010 3. 4. 5. 6. 7. 8. 9. 3.6 In damp and/or wet location. Where exposed to weather. Between the seismic joints. For connections to electric water heaters Any connections made below sinks. Provide polyvinyl covers listed for the application of area of use. Minimum length of flexible liquidtight conduit shall be 24" and maximum 72" unless otherwise noted. SEISMIC BRACING A. Provide seismic bracing for conduits three 3/4", or two 1", and/or one 1-1/2" and larger or multi size combination, wherever conduit is suspended more than 10" to the bottom of the conduit from its anchoring point on the structure. All such bracing as described herein or below shall be run from the raceway to the structure, and anchored to the latter in an approved manner. B. Provide diagonal bracing every 16' to the structure from hangers and changes in direction. C. Seismic bracing as described above shall be provided immediately upon completion of each conduit run, to prevent obstruction of conduits by other utilities or construction work. 3.7 SEAL A. Conduits terminating where termination is subject to moisture or where conduit penetrates exterior wall shall be sealed. B. Seal all conduits from exterior outlets at first interior junction to prevent moisture from entering the building through the conduit. Slope exterior conduits away from the building. C. Seal all fire rated wall or ceiling penetrations. Sealant material and method shall be UL listed. D. Provide conduit seal for all conduits that passes through the following areas: 1. 2. 3. 4. 5. 3.8 As indicated on the Drawings. Classified (hazardous) area. Conduits serving sump pump and sewage ejector pits. Refrigerated area. Temperature controlled rooms such as cold room or warm room. BENDS A. Except as otherwise indicated on the Drawings, bends in conduit 2 inches or larger for underground conduit shall have a radius or curvature of the inner edge, equal to not less than 10 times the internal diameter of the conduit. Any deviations from this radius shall be approved by the Owner’s Representative. B. Conduit connections to pull boxes shall be made with a long radius. Bends for 600-volt cable shall have a radius of not less than five (5) times the diameter of the cable. Shielded cables rated above 600 volts shall have a bending radius of not less than 12 times the cable overall diameter. Nesting of conduits shall be made when two or more conduits are run in parallel. C. Keep bends and offsets in conduit runs to an absolute minimum. For the serving utilities, make large radius bends to meet their requirements. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 14 Raceway and Boxes for Electrical Systems June 30, 2010 D. For bends and offsets in conduit 1 inch and larger, use larger radius factory fittings or a hydraulic bender. Replace flattened, deformed or kinked conduit. E. Apply heat for bends so that conduit does not distort or discolor. Use a spring mandrel as required to assure full inside diameter at all bends. 3.9 FIRESTOPPING A. Apply firestopping to electrical penetrations of fire-rated floor and wall assemblies to restore original fire-resistance rating of assembly. Firestopping materials and installation requirements are specified in Division 07 Section "Penetration Firestopping." Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260533- 15 Raceway and Boxes for Electrical Systems June 30, 2010 SECTION 260548 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 SUMMARY A. This section includes Labor, materials and equipment necessary to complete the installation required for the item specified under this Division, including but not limited to: 1. Vibration Isolation B. Related Work: Consult all other Sections, determine the extent and character of related work and properly coordinate work specified herein with that specified elsewhere to produce a complete installation. C. Description of work: Provide vibration isolation for electrical equipment to prevent the transmission of vibration forces and structure transmitted sound to the building structure as indicated on the Drawings and as specified herein. 1.2 PERFORMANCE REQUIREMENTS A. Seismic-Restraint Loading: 1. 2. Site Class as Defined in the IBC: C. Assigned Seismic Use Group or Building Category as Defined in the IBC: III. a. b. c. d. 3. 4. 1.3 Component Importance Factor: 1.5. Component Response Modification Factor: 3.5; for distributed systems (bus ducts, conduits and cable tray). Component Response Modification Factor: 2.5; for equipment. Component Amplification Factor: 1.0. Design Spectral Response Acceleration at Short Periods (0.2 Second): 0.246. Design Spectral Response Acceleration at 1.0-Second Period: 0.073. SUBMITTALS A. Product Data: For the following: 1. 2. Include rated load, rated deflection, and overload capacity for each vibration isolation device. Illustrate and indicate style, material, strength, fastening provision, and finish for each type and size of seismic-restraint component used. a. b. Tabulate types and sizes of seismic restraints, complete with report numbers and rated strength in tension and shear as evaluated by an agency acceptable to authorities having jurisdiction. Annotate to indicate application of each product submitted and compliance with requirements. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260548- 1 Vibration and Seismic Controls for Electrical Systems June 30, 2010 3. B. Restrained-Isolation Devices: Include ratings for horizontal, vertical, and combined loads. Delegated-Design Submittal: For vibration isolation and seismic-restraint details indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 1. Design Calculations: Calculate static and dynamic loading due to equipment weight and operation, seismic forces required to select vibration isolators and seismic restraints. a. 2. 3. 4. Indicate materials and dimensions and identify hardware, including attachment and anchorage devices. Field-fabricated supports. Seismic-Restraint Details: a. b. c. 1.4 Coordinate design calculations with wind-load calculations required for equipment mounted outdoors. Comply with requirements in other Division 26 Sections for equipment mounted outdoors. Design Analysis: To support selection and arrangement of seismic restraints. Include calculations of combined tensile and shear loads. Details: Indicate fabrication and arrangement. Detail attachments of restraints to the restrained items and to the structure. Show attachment locations, methods, and spacings. Identify components, list their strengths, and indicate directions and values of forces transmitted to the structure during seismic events. Indicate association with vibration isolation devices.] Preapproval and Evaluation Documentation: By an agency acceptable to authorities having jurisdiction, showing maximum ratings of restraint items and the basis for approval (tests or calculations). QUALITY ASSURANCE A. All materials, equipment and parts comprising the units specified herein shall be new B. Unless prior written approval of the Owner’s Representative is obtained, all materials and systems specified in this Section shall be purchased from a single vibration isolation materials manufacturer, who has supplied vibration isolation system equipment for at least 5 years, to assure single responsibility for the performance of all isolation materials used. C. The completed installation must control vibration and noise to within the specified limits. Systems, equipment, or parts that vibrate or generate vibration unduly or that generate or emit undue noise while in operation shall: (1) be adjusted, repaired, or replaced as appropriate to obtain acceptable levels of vibration or noise, or (2) be supported on or fitted with suppression or absorption devices or means that effectively prevent the transmission of vibration or noise beyond the offending item. Undue noise and vibration is defined as that which exceeds the manufacturer's specifications or the limits established in these specification. D. Replace, at no extra cost to the owner, isolators that do not produce the required deflection, are incorrectly loaded above or below their correct operating height, or which do not produce the required isolation as approved. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260548- 2 Vibration and Seismic Controls for Electrical Systems June 30, 2010 E. After completion of vibration isolation installation, provide field inspection by qualified manufacturer's representative to ensure that all vibration isolators are installed in accordance with manufacturer's printed recommendations and provide a written report. F. Comply with seismic-restraint requirements in the IBC unless requirements in this Section are more stringent. G. Seismic-restraint devices shall have horizontal and vertical load testing and analysis and shall bear anchorage preapproval OPA number from OSHPD, preapproval by ICC-ES, or preapproval by another agency acceptable to authorities having jurisdiction, showing maximum seismic-restraint ratings. Ratings based on independent testing are preferred to ratings based on calculations. If preapproved ratings are not available, submittals based on independent testing are preferred. Calculations (including combining shear and tensile loads) to support seismicrestraint designs must be signed and sealed by a qualified professional engineer. H. Comply with NFPA 70. PART 2 PRODUCTS 2.1 MATERIALS A. Manufacturer 1. All vibration isolation mounts shall be supplied by one of the following manufacturers: a. b. c. B. General 1. 2. 3. 4. C. Mason Industries Inc. Kinetics Vibration Mountings & Controls Inc. Provide vibration isolators with either known un-deflected heights or other markings so that, after adjustment, when carrying their load, the deflection under load can be verified, thus determining that the load is within the proper range of the device and that the correct degree of vibration isolation is being provided according to the design. Provide isolators that operate in the linear portion of their load versus deflection curve. Furnish load versus deflection curves from the manufacturer that are linear, over a deflection range 50% above the design deflection. Where specific type of vibration isolation hardware equipment is not shown or specified, furnish isolators recommended by the isolation manufacturer compatible with equipment arrangements shown. All neoprene mountings shall have a shore hardness of 40-65 after minimum aging of 30 days, or corresponding open-aging. Vibration Isolators 1. Neoprene mountings shall have a minimum static deflection of 0.3". All metal surfaces shall be neoprene covered and have friction pads both top and bottom. Bolt holes shall be provided on the bottom and a tapped hole and cap screw on top. Steel rails shall be used above the mountings under equipment such as small vent sets to compensate for the overhang. Mountings shall be type ND as manufactured by Mason Industries, Inc. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260548- 3 Vibration and Seismic Controls for Electrical Systems June 30, 2010 2. D. Mount Type FS (Spring Mounting): Laterally stable spring isolators (single or multiple steel springs) seismic restraint housing and complete with 1/4" neoprene acoustical pads between the base-plate and the support. Spring diameter shall be no less than 0.8 of the compressed height of the spring at design load. Springs shall be so designed that the ratio of horizontal stiffness to vertical stiffness is approximately 1. Provide all mountings with leveling bolts, rigidly bolted to the equipment. Provide height saving mounting brackets where applicable, height adjustment bolts. Isolators shall be Mason Type “SLR” or equal. Seismic-Restraint Devices 1. 2. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: General Requirements for Restraint Components: Rated strengths, features, and application requirements shall be as defined in reports by an agency acceptable to authorities having jurisdiction. a. 3. 4. 5. 6. 7. 8. Structural Safety Factor: Allowable strength in tension, shear, and pullout force of components shall be at least 1.2 times the maximum seismic forces to which they will be subjected. Channel Support System: MFMA-3, shop- or field-fabricated support assembly made of slotted steel channels with accessories for attachment to braced component at one end and to building structure at the other end and other matching components and with corrosion-resistant coating; and rated in tension, compression, and torsion forces. Restraint Cables: ASTM A 492 stainless-steel cables with end connections made of steel assemblies with thimbles, brackets, swivels, and bolts designed for restraining cable service; and with a minimum of two clamping bolts for cable engagement. Hanger Rod Stiffener: Steel tube or steel slotted-support-system sleeve with internally bolted connections to hanger rod. Do not weld stiffeners to rods. Bushings for Floor-Mounted Equipment Anchor: Neoprene bushings designed for rigid equipment mountings, and matched to type and size of anchors and studs. Bushing Assemblies for Wall-Mounted Equipment Anchorage: Assemblies of neoprene elements and steel sleeves designed for rigid equipment mountings, and matched to type and size of attachment devices. Resilient Isolation Washers and Bushings: One-piece, molded, oil- and water-resistant neoprene, with a flat washer face. PART 3 EXECUTION 3.1 EXAMINATION A. 3.2 Thoroughly examine site conditions for acceptance of equipment installation to verify conformance with manufacturer and specification tolerances. Do not commence with installation until all conditions are made satisfactory. PREPARATION A. Housekeeping pads shall be provided for all floor mounted electrical equipment. Unless otherwise indicated, pads shall be 4” high with #4 reinforcing rods 12”on center each direction, Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260548- 4 Vibration and Seismic Controls for Electrical Systems June 30, 2010 1-1/2” above bottom of pad. For thicker pads provide #4 rods both top and bottom 2” below and above. B. Foundation drawings, details, templates, pipe sleeves, vibration isolators, foundation bolts and anchored plates shall be provided by the Contractor. C. The Contractor shall be fully responsible for all base and foundation dimensions and bolt locations. D. All vibration isolators must be installed in strict accordance with the manufacturers written instructions and all certified submittal data. E. Installation of vibration isolators must not cause any change of position of equipment, in stresses or misalignment. 3.3 INSTALLATION A. All electrical conduits 2 1/2" (64mm) in diameter and larger, cable trays and ladder trays shall be restrained with cable restraints or solid brace to meet design loading. B. Transverse restraints shall occur at 30' intervals or both ends if the electrical run is less than the specified interval. Transverse restraints shall be installed at each electrical services turn and at each end of the electric run. C. Longitudinal restraints shall occur at 60' intervals with at least one restraint per electric run. Transverse restraints for one electric section may also act as a longitudinal restraint for a duct for an electric section connected perpendicular to it if the restraints are installed within 4' of the intersection of the electric run and if the restraints are sized for the larger electric run. D. Wall mounted panels, transformers and motor starters shall be mounted with bushings. Floor mounted panels shall be mounted on bushings. E. Connection to the structure must be made with a non-friction connection. F. Exclusions: 1. 2. 3. 4. All conduit less than 2 1/2" (64mm) diameter suspended by individual hanger rods. All conduits suspended by clevis hangers where the distance from the top of the pipe to the suspension point is 12" or less. All trapezed conduits, bus ducts and cable trays where the distance from the suspension point to the trapeze member is 12" or less. If any suspension location in the run exceeds the above, the entire run must be braced. G. Electrical connections to vibration isolation equipment shall be flexible, having a fully-looped flex (or grossly slack shallow U) installed on isolated equipment with static deflection over 0.1". Flexible conduit to be at least 3 feet or 20 diameters long, whichever is the longer. H. All floor supported transformers located within the building shall be mounted on vibration isolation Type ND neoprene mounts. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260548- 5 Vibration and Seismic Controls for Electrical Systems June 30, 2010 I. No rigid connections between equipment and the building structure shall be made that degrades the noise and vibration control system herein specified. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260548- 6 Vibration and Seismic Controls for Electrical Systems June 30, 2010 SECTION 260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 SUMMARY A. This section includes labor, materials and equipment necessary to complete the installation required for the item specified under this Division, including but not limited to: 1. 2. 3. 4. 5. 6. B. 1.2 Electrical equipment nameplates Panelboard directories Wire and cable identification Junction box identification Warning and caution signs Engraved device coverplates Related work: Consult all other Sections, determine the extent and character of related work and properly coordinate work specified herein with that specified elsewhere to produce a complete installation. SUBMITTALS A. Submit in accordance with the requirements of Section 260500: Electrical Requirements, the following items: 1. 2. Data/catalog cuts for each product and component specified herein. Submit a nameplate schedule to the Owner’s Representative for review before the nameplates are installed. PART 2 PRODUCTS 2.1 MANUFACTURERS A. Conduit and wire markers: Manufactured by Thomas & Betts, Brady or equal. B. Inscription Tape: Manufactured by Kroy, Merlin or equal. 2.2 NAMEPLATES A. Type NP: Engraved, plastic lamacoid labels, Signs, and Instruction Plates. 1. 2. Engrave lamacoid tags 1/16-inch minimum thickness for signs up to 4 inches in length, 1/8 inch thick for larger sizes. Engraved nameplates shall be punched for mechanical fasteners. B. The lettering shall be Condensed Gothic with space between the lines equal to the width of the letters. C. Color and letter height as specified in Part 3: Execution. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260553- 1 Identification for Electrical Systems June 30, 2010 2.3 PANELBOARD DIRECTORIES A. Directories: A 6 inch x 8 inch minimum size circuit directory frame and card with clear plastic covering shall be provided inside the inner panel door. B. Circuit numbering: Starting at the top, odd numbered circuits in sequence down the left hand side and even numbered circuits down the right hand side. 2.4 WIRE AND TERMINAL MARKERS A. 2.5 Provide self-adhering, pre-printed, machine printable or write-on, self-laminating vinyl wrap around strips. Blank markers shall be inscribed using the printer or pen recommended by manufacturer for this purpose. CONDUCTOR PHASE MARKERS A. 2.6 Colored vinyl plastic electrical tape, 3/4" wide, for identification of phase conductors. Scotch 35 Brand Tape, Manville or equal. ENGRAVED DEVICE COVERPLATES A. Coverplate material shall be as specified in Section 262726: Wiring Devices. B. Engraving: 1. 2. 2.7 1/8” high letters Paint filled letters – Black for normal power. INSCRIPTION TAPE LABELING A. Coverplate material shall be as specified in Section 262726: Wiring Devices. B. Provide self-adhesive labeling tape: 1. 2. 1/8” high letters Clear tape with Black lettering for normal power. PART 3 EXECUTION 3.1 EXAMINATION A. 3.2 Thoroughly examine site conditions for acceptance of identification device installation to verify conformance with manufacturer and specification tolerances. Do not commence with installation until all conditions are made satisfactory. NAMEPLATES A. B. Nameplates for normal power system distribution equipment and devices shall be black w/white lettering. Nameplates for emergency power system distribution equipment and devices shall be red w/white lettering. Roosevelt Hall Renovation 260553- 2 Identification for Electrical Systems Brooklyn College June 30, 2010 Brooklyn, NY Project #6032.20 C. Nameplates for signal systems equipment and devices shall be blue /white lettering. D. Nameplates for Fire Alarm systems equipment and devices shall be red w/white lettering. E. Installation: 1. 2. 3. Degrease and clean surfaces to receive nameplates. Install nameplates parallel to equipment lines. Secure nameplates to equipment fronts using machine screws. F. The lettering on the nameplate shall indicate the name of equipment, the specific unit number, voltage, phases, which panel, switchboard or motor control center the equipment is served from, or to where it provided power to, and any other reference data pertinent to the operation. Names and numbers shall coincide with those listed on the drawings. Sample: Panel 3A; 277/480 V, 3 phase, 4 wire, fed from US-1. G. Provide type 'Nameplate' color coded nameplates that present, as applicable, the following information: 1. 2. 3. 4. 5. Equipment or device designation Amperage, KVA or horsepower rating, where applicable Voltage or signal system name Source of power or control Typical examples: a. b. H. Minimum letter height shall be as follows: 1. 2. 3. 4. 3.3 Transformers: “TB/S; 45kVA fed from USB”. Disconnects: “AH-1; 25HP; fed from MCCB” For panelboards and switchboards. 1/2-inch letters to identify equipment designation. Use 1/4-inch letters to identify the remaining items. For individual circuit breakers, disconnect switches and motor starters in switchboards use 3/8-inch letters to identify equipment designation. Use 1/8- inch letters to identify the remaining items. For individual mounted circuit breakers, disconnect switches, enclosed switches and motor starters use 3/8-inch letters to identify equipment designation. Use 1/8-inch letters to identify the remaining items. For equipment cabinets, terminal cabinets, control panels and other cabinet enclosed apparatus use 1/4-inch letters to identify equipment designation. PANELBOARD DIRECTORIES A. Provide typewritten directories arranged in numerical order denoting loads served by room number or area for each circuit. B. Fill out branch circuit directory indicating circuit number and area served, rooms, group of rooms, lighting, convenience outlets, motors, etc. Card index shall be neatly typed. C. Mount panelboard directories in a metal frame under clear plastic cover inside every panelboard. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260553- 3 Identification for Electrical Systems June 30, 2010 3.4 WIRE AND CABLE IDENTIFICATION A. Provide wire markers on each conductor in panelboards, pull boxes, outlet and junction boxes and at load connection. Identify with branch circuit or feeder number for power and lighting circuits and with control wire number as indicated on equipment manufacturer's shop drawings for control wiring. B. Provide colored phase markers for conductors as noted in Section 260519. Apply colored, pressure sensitive plastic tape in half-lapped turns for a distance of 3 inches from terminal points and in boxes where splices or taps are made. Apply the last two laps of tape with no tension to prevent possible unwinding. Do not cover cable identification markings by taping. 3.5 JUNCTION BOX IDENTIFICATION A. 3.6 The cover of junction, pull, and connection boxes for lighting, power and signal systems, located above suspended ceilings and below ceilings in non-public areas, shall be clearly marked with a permanent ink felt pen. Identify the circuit(s) (panel designation and circuit numbers) contained in each box, unless otherwise noted or specified. WARNING, CAUTION AND INSTRUCTION SIGNS A. Provide warning, caution, or instruction signs where required by NEC, where indicated, or where reasonably required to assure safe operation and maintenance of electrical systems and of the items to which they connect. Install engraved plastic lamacoid instruction signs with legend where instructions or explanations are needed for system or equipment operation. Install butyrate signs with metal backing for outdoor items. B. Elevator Machine Rooms(s): Provide warning sign for each elevator controller disconnect to read "Warning - Part of the Control Panel is not De-energized by this Switch." C. Elevator car light and fan switch: Provide signage indicating elevator number serving and function of each switch. D. Warning signs to be included on doors or immediately above doors of all electrical equipment rooms, vaults or closets containing equipment energized above 150 volts to ground. The sign shall state "DANGER - HIGH VOLTAGE", with "DANGER" in 1-1/2" letters and "HIGH VOLTAGE" in 1 inch letters. 3.7 ENGRAVED OR LABELED DEVICE COVERPLATE A. Application: 1. Provide engraved coverplates for devices as outlined below: a. b. c. d. B. Receptacles Outlets in surface raceways. Multi-ganged (four or more) switch arrangement. Special purpose switches, i.e. projection screens, shades, exhaust fans, etc. Each receptacle outlet shall be engraved with 3/16” black filled letters, circuit number and panel name; Example Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260553- 4 Identification for Electrical Systems June 30, 2010 1. 3.8 LP-1A/23 CONDUIT IDENTIFICATION A. Conduit and junction boxes: 1. 2. Color code or label all junction boxes and exposed conduit at 10 ft. intervals. Coding shall be painted or labels of the pre-manufactured type permanently mounted with metal or plastic band. Provide a color identification scheme under heavy plastic cover hanging in the electrical rooms; identification shall be: a. b. Normal - Black Fire Alarm - Red B. All conduit for signal system shall be color coded with 6" wide spray paint for every 10' of length as follows: C. All outlet boxes (inside and outside) for signal system shall be color coded. 3.9 INSTALLATION A. Nameplates shall be secured with either #4 Phillips, round head corrosion resistant steel self-tapping screws or with pop rivets, one on each end. B. Signs shall be permanently mounted with cadmium plated, steel screws. C. Receptacles shall have circuit number and panelboards identification label permanently attached to face of respective cover plate. D. Warning Signs: 1. 2. 3. Contractor shall provide OSHA warning signs where required by National Electrical Code and OSHA. Low and medium voltage equipment enclosures, vaults, doors and fences shall be provided with "DANGER KEEP OUT" warning signs, showing proper voltage. Non-load-break disconnects and cutouts shall have "CAUTION" warning sign to read "DO NOT OPEN UNDER LOAD". Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 260553- 5 Identification for Electrical Systems June 30, 2010 SECTION 262200 LOW VOLTAGE DISTRIBUTION TRANSFORMER PART 1 GENERAL 1.1 SUMMARY A. B. 1.2 This section includes labor, materials and equipment necessary to complete the installation required for the item specified under this Division, including but not limited to: 1. Dry type ventilated transformers. Related Work: Consult all other Sections, determine the extent and character of related work and properly coordinate work specified herein with that specified elsewhere to produce a complete installation. REFERENCES A. Comply with the latest edition of the following applicable specifications and standards except as otherwise shown or specified. 1. 2. 3. 4. ANSI C57 ANSI/NEMA ST 1 NEMA ST 20 ANSI/NEMA TP-1 Transformers a. 5. 1.3 Pertaining to Power/Distribution Transformer. Specialty Transformers Dry Type Transformers for General Applications. Guide for Determining Energy Efficiency for Distribution For Reference only. US DOE does not consider NEMA TP-1 efficiency levels to reflect low life cycle cost. Transformers in this specification are substantially more efficient than NEMA TP-1 levels, meeting US Department of Energy proposed Candidate Standard Level (CSL) 3 efficiency. ANSI/NEMA TP-2 Standard Test Method for Measuring Energy Consumption of Distribution Transformers SUBMITTALS A. Submit in accordance with the requirements of Section 260500, the following items: 1. 2. 3. 4. Data/catalog cuts for each product and component specified herein, listing all physical and electrical characteristics and ratings indicating compliance with all listed standards. Insulation system impregnate data sheet as published by supplier. Basic Performance characteristics including insulation class, temperature rise, core and coil materials, impedances & audible noise level, unit weight Inrush Current (typical 3 cycle recovery) a. b. Short Circuit Current data: Primary (Sym. O/P S/C) & Secondary (L-N/G S/C) Efficiency Data 1). 2). 3). 4). No load and full load losses per NEMA ST20 Linear load Efficiency data @ 1/6 load Linear load efficiency data @ 1/4, 1/2, 3/4 & full load Linear Load Efficiency @ 35% loading tested per NEMA TP-2. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262200- 1 Low Voltage Distribution Transformer June 30, 2010 5). 5. 6. 7. 1.4 Efficiency under K7 load profile at 15%, 25%, 50%, 75%, 100% of nameplate rating. c. Copy of Linear & Nonlinear load test report for a representative 75kVA transformer Description of manufacturer’s factory nonlinear load test program. I a. n light of the significant degradation of transformer performance when feeding nonlinear load compared to linear load, it is mandatory that the manufacturer test the transformers under nonlinear load representative of real world load mix. Transformers that have not been subject to testing under nonlinear load will not be considered for this project due to the uncertainty related to their real world performance. b. Given the lack of a standard for testing transformers under nonlinear load, the manufacturer must have a nonlinear Load Test Program operating in the production environment that is audited and documented per quality standard ISO 9001. c. The nonlinear load bank shall consist of a phase-neutral loading with a k7 profile, representative of a mix of typical commercial equipment. d. Meters and CTs shall both be revenue class accurate. CTs shall be operated within their approved accuracy loading range. Dual meters shall gather simultaneous primary and secondary energy and harmonic data. Meter and CT details including model, accuracy, serial numbers and calibration information. e. Efficiency: Measurements shall be taken at multiple load levels and plotted to show compliance with specification and correlation to the designed efficiency curve. f. Efficiency shall be determined purely by measurements using method and instrumentation per NEMA TP-2 Standard. Other methods are not acceptable. g. Harmonic data including current and Voltage THD at the different load levels shall be included with the test report. Submit manufacturer's installation instructions. EMF test result at full rated current QUALITY ASSURANCE A. All materials, equipment and parts comprising the units specified herein shall be new. 1. 1.5 Contractor shall pay for the services of a qualified testing laboratory to perform the specified tests. The Contractor shall notify the Owner’s Representative at least five (5) working days in advance of performance of work requiring testing. The Contractor shall provide all material required for testing STORAGE AND HANDLING A. Store and handle in strict compliance with manufacturer’s instructions and recommendations. Protect from potential damage from weather and construction operations. Store so condensation will not form on or in the transformer housing and if necessary, apply temporary heat where required to obtain suitable service conditions. B. Handle transformer using proper equipment for lifting and handling, use when necessary lifting eye and/or brackets provided for that purpose. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262200- 2 Low Voltage Distribution Transformer June 30, 2010 1.6 WARRANTY A. Transformer shall carry a 25-year pro-rated warranty, which shall be standard for the product line. PART 2 PRODUCTS 2.1 MANUFACTURERS A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. 2.2 Powersmiths Culter Hammer Square D GENERAL A. Copper-wound, 3-phase, common core, ventilated, dry-type, isolation transformer built to NEMA ST20 and relevant NEMA, UL and IEEE standards; shall be U.L. and CSA Listed and bear the label. B. All terminals, including those for changing taps, must be readily accessible by removing a front cover plate. Windings shall be continuous with terminations brazed or welded. C. Provide ground bar kit and neutral to ground bond jumper terminated at ground bar. Provide mechanical lugs mounted on the ground bar for input ground bond, output ground bond and external ground. 2.3 BASIC REQUIREMENTS: A. Type: ANN, convection air cooled B. Insulation Class: 220°C system C. Temperature rise: 130°C D. Taps: 2 x ± 2.5% (2FCAN, 2FCBN) E. Core construction: high grade non-aging, fully processed silicon steel laminations or better F. Coil conductors: continuous copper windings, with terminations brazed or welded up to 75kVA and bolted 112.5 kVA and up. G. Inrush current: 10 times full load rating (max.) H. Excitation current: 5% of full load current rating (max.) I. Enclosure: Ventilated NEMA 3R enclosure designed to prevent hand or rod contact with live parts. J. Enclosure Finish: ANSI 61 Grey suitable for UL50. K. Anti-vibration pads shall be used between the core and the enclosure Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262200- 3 Low Voltage Distribution Transformer June 30, 2010 L. Transformer shall be UL listed. M. Ground core & coil assembly to enclosure with a flexible copper grounding strap or equivalent. N. Mounting: 1. 2. Ventilated units up to 750 lbs.: Suitable for wall, floor or ceiling mounting (drip plate required). Ventilated units over 750 lbs.: Suitable for floor mounting only. O. EMF level, not to be higher than 10mG top, 10mG side and 10mG at one meter. P. Enclosures shall be fabricated of heavy gage sheet steel construction. Enclosure shall have suitable ventilating openings. Enclosure shall be provided with lifting lugs and jacking plates as required. Q. Transformers shall be furnished complete with mounting channels and mounting bolts. Metal parts, excepting cores and core mounting frames shall be cleaned, rust-proofed and be given a heavy coating of an inert primer. R. All transformers shall have a basic impulse insulation level of 10 KV. The following tests shall be done at the factory: 1. 2. 3. S. Applied voltage test to each winding and from each winding to ground. Induced voltage test - two times normal voltage. Ratio, polarity and sound level: Sound level tests shall be performed in test rooms with an ambient sound level not exceeding 24 dBs. Sound levels shall meet NEMA ST-20 and not exceed the following: 1. 2. 3. 4. 15-50 KVA 51-150 KVA 151 to 300 KVA 301 to 500 KVA - 45 dB 50 dB 55 dB 60 dB T. Transformers shall have a minimum overload capacity per ANSI Standard. Certified temperature test of electrical duplicate units shall be supplied upon request. U. Terminal compartments for both primary and secondary lines shall be located in the bottom of the transformer to ensure termination of cable leads in ambient temperature levels and to provide for side or bottom entrance of conduit. 2.4 POWERSMITHS E-SAVER ENERGY EFFICIENT DRY TYPE TRANSFORMER A. Electrostatic Shield: Each winding is independently single shielded with a full-width copper electrostatic shield. B. 200% rated neutral, UL Listed & Labeled K-Rating: K-7 or higher. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262200- 4 Low Voltage Distribution Transformer June 30, 2010 C. Insulation System: 1. 2. 3. 4. 5. Shall be NOMEX-based with an Epoxy Co-polymer impregnant for lowest environmental impact, long term reliability and long life expectancy Class: 220 degrees C Impregnant Properties for low emissions during manufacturing, highest reliability and life expectancy. Epoxy co-polymer VOC: less than 1.65 lbs/gal (low emissions during manufacturing) D. Maximum No Load Losses shall not exceed: 120W, 75kVA. E. Efficiency at 15% loading shall meet or exceed: 75kVA: 98.2%. F. DOE 10 CFR Part 430 CSL 3 Efficiency requirements tested per NEMA TP-2: 75kVA: 98.6%. G. Efficiency under k-7 nonlinear load at 50% of nameplate rating: 75kVA: 98.4% H. Impedance: I. Enclosure type: NEMA 2, drip-proof. J. Maximum Footprint for 130 degree C rise model in a NEMA 1 enclosure: 33” Wide x 22” Deep x 40” High for 75kVA. Between 3.5% and 5.8% unless otherwise noted. PART 3 EXECUTION 3.1 EXAMINATION A. 3.2 Thoroughly examine site conditions for acceptance of transformer installation to verify conformance with manufacturer and specification tolerances. Do not commence with installation until all conditions are made satisfactory. PREPARATION A. Insure all conduit stub-ups for bottom entry into transformer are in place and located as required per shop drawings. B. Where noted on the drawings provide a 4” high concrete housekeeping pad beneath equipment. Coordinate actual sizes of equipment base with shop drawings and extend pad 3” in all directions beyond overall dimension of base. Provide reinforcing bars as required structurally within pad to insure proper support of equipment. 3.3 INSTALLATION A. Install transformer in accordance with manufacturer's written instructions, as shown on the drawings and as specified herein. B. Transformers shall be installed to provide adequate air circulation for the removal of the heat they produce, in accordance with manufacturer recommendations. C. Transformers not specifically designed for wall mounting, shall be spaced a minimum of 6" from adjacent walls, and equipment. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262200- 5 Low Voltage Distribution Transformer June 30, 2010 D. Transformers shall be anchored and braced to withstand seismic forces. E. Loosen and/or remove all shipping bolts in accordance with manufacturer's instructions. F. All floor supported transformers located within the building shall be mounted on vibration isolation Type ND neoprene mounts to suppress the transformer noise from the building structure. Select and arrange the mounts in accordance with the weight and mounting of the transformers. These mounts are in addition to any internal vibration pads. Vibration isolating mounts shall be seismically rated for the application. G. All conduits shall be isolated form the transformer enclosures by the use of neoprene grommets at conduit entrances to enclosure and the use of a grounding bushing. Flexible jumpers shall be installed for grounding continuity from enclosure to conduits or bus ducts. 3.4 TERMINATIONS A. Provide all transformers with lugs for both primary and secondary conductor sizes for conductors shown on Drawing. Connect lug to termination point with appropriate size bolt, nut flat and Belleville washers. B. Provide high-pressure compression lugs, for primary and secondary phase and neutral terminations for transformers 45 KVA and larger. Utilize only the tool and dies designed for uses in installing the lugs provided. C. Use flexible conduit indoors in dry locations or liquidtight flexible conduit in damp/wet locations, 24” minimum in length, for primary and secondary connections to transformer case. Make connections to side panels of enclosure, except for floor mounted transformers fed from directly below enclosure. D. Where feeders come from the floor below, they shall terminate at the end of transformer enclosure with a metal grounding bushing with neoprene throat insert. Ground the bushing to the transformer enclosure. 3.5 GROUNDING A. Provide transformer with a dual rated four-barrel solderless grounding lug with a 5/8" -11 threaded hole. Drill transformer enclosure with 11/16" bit and attach lug to enclosure utilizing a torque bolt and Dragon Tooth transition washer. Connect the following: 1. 2. 3. 4. 3.6 Primary feeder ground. Secondary feeder ground. Grounding electrode. Main bond jumper to neutral (when present). IDENTIFICATION A. 3.7 Provide transformer nameplate as described in Section 260553. FIELD QUALITY CONTROL A. Field inspection and testing shall be performed under provisions of Section 260126. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262200- 6 Low Voltage Distribution Transformer June 30, 2010 3.8 ADJUSTING A. The Contractor shall set the taps on all transformers, which are a part of this contract as necessary to provide satisfactory operating voltages with all present loads energized, including the new loads and any existing loads. A check shall be made in the presence of the Owner’s Representative at a panel fed from each transformer that is the farthest from the transformer. B. The Contractor shall provide all instruments and accessories required to perform the checks. Voltmeters shall be accurate with 3/4 or 1% and shall have scales permitting the voltage readings to be made on the upper half of the scale. Calibration of the meters shall be satisfactory to the owner. C. Infrared Scanning: Two months after Substantial Completion, perform an infrared scan of transformer connections. 1. 2. 3. 3.9 Use an infrared-scanning device designed to measure temperature or detect significant deviations from normal values. Provide documentation of device calibration. Perform 2 follow-up infrared scans of transformers, one at 4 months and the other at 11 months after Substantial Completion. Prepare a certified report identifying transformer checked and describing results of scanning. Include notation of deficiencies detected, remedial action taken, and scanning observations after remedial action. CLEANING A. Prior to energizing of transformer the contractor shall thoroughly clean the interior of enclosure of all construction debris, scrap wire, etc. using manufacturer's approved methods and materials. B. Upon completion of project prior to final acceptance the contractor shall thoroughly clean both the interior and exterior of transformer per manufacturers recommended materials and methods. Remove paint splatters and other spots, dirt, and debris. C. Touch-up paint any marks, blemishes, or other finish damage suffered during installation. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262200- 7 Low Voltage Distribution Transformer June 30, 2010 SECTION 262416 PANELBOARDS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY 1.2 A. Section Includes: 1. 2. Distribution & Power Panelboards. Lighting and appliance branch-circuit panelboards. PERFORMANCE REQUIREMENTS 1.3 A. Seismic Performance: Panelboards shall withstand the effects of earthquake motions determined according to the UBC. 1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event." SUBMITTALS 1.4 A. Product Data: For each type of panelboard, switching and overcurrent protective device, transient voltage suppression device, accessory, and component indicated. Include dimensions and manufacturers' technical data on features, performance, electrical characteristics, ratings, and finishes. B. Shop Drawings: For each panelboard and related equipment. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Include dimensioned plans, elevations, sections, and details. Show tabulations of installed devices, equipment features, and ratings. Detail enclosure types and details for types other than NEMA 250, Type 1. Detail bus configuration, current, and voltage ratings. Short-circuit current rating of panelboards and overcurrent protective devices. Detail features, characteristics, ratings, and factory settings of individual overcurrent protective devices and auxiliary components. Include wiring diagrams for power, signal, and control wiring. Include time-current coordination curves for each type and rating of overcurrent protective device included in panelboards. Submit structural calculations for equipment anchorage. Submit manufacturer's installation instructions. Complete bill of material listing all components. Warranty. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262416- 1 Panel Boards June 30, 2010 C. Qualification Data: For qualified testing agency. D. Seismic Qualification Certificates: Submit certification that panelboards, overcurrent protective devices, accessories, and components will withstand seismic forces defined in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." Include the following: 1. 2. 3. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements. E. Panelboard Schedules: For installation in panelboards. Submit final versions after load balancing. F. Operation and Maintenance Data: For panelboards and components to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following: 1. 2. Manufacturer's written instructions for testing and adjusting overcurrent protective devices. Time-current curves, including selectable ranges for each type of overcurrent protective device that allows adjustments. QUALITY ASSURANCE 1.5 A. Testing Agency Qualifications: Member company of NETA or an NRTL. 1. Testing Agency's Field Supervisor: Currently certified by NETA to supervise on-site testing. B. Source Limitations: Obtain panelboards, overcurrent protective devices, components, and accessories from single source from single manufacturer. C. Product Selection for Restricted Space: Drawings indicate maximum dimensions for panelboards including clearances between panelboards and adjacent surfaces and other items. Comply with indicated maximum dimensions. D. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. E. Comply with NFPA 70. F. FS W-C-375 Circuit Breakers, Molded Case, Branch Circuit and Service G. FS W-P-115 Power Distribution Panel H. NEMA AB 1 Molded Case Circuit Breakers. I. NEMA PB 1 Panelboards J. NEMA PB 1.1 Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 Instructions for Safe Installation, Operation and Maintenance of 262416- 2 Panel Boards June 30, 2010 K. Panelboards Rated 600 Volts or Less DELIVERY, STORAGE, AND HANDLING 1.6 A. Remove loose packing and flammable materials from inside panelboards; install temporary electric heating (250 W per panelboard) to prevent condensation. B. Handle and prepare panelboards for installation according to NEMA PB 1. PROJECT CONDITIONS 1.7 A. Environmental Limitations: 1. Do not deliver or install panelboards until spaces are enclosed and weathertight, wet work in spaces is complete and dry, work above panelboards is complete, and temporary HVAC system is operating and maintaining ambient temperature and humidity conditions at occupancy levels during the remainder of the construction period. COORDINATION 1.8 A. Coordinate layout and installation of panelboards and components with other construction that penetrates walls or is supported by them, including electrical and other types of equipment, raceways, piping, encumbrances to workspace clearance requirements, and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels. B. Coordinate sizes and locations of concrete bases with actual equipment provided. Cast anchorbolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified in Division 03. WARRANTY 1.9 A. Units and components offered under this Section shall be covered by 1-year parts and labor warranty for malfunctions resulting from defects in materials and workmanship. Warranty shall begin upon acceptance by the Owner’s Representative. PART 2 PRODUCTS 2.1 GENERAL REQUIREMENTS FOR PANELBOARDS A. Fabricate and test panelboards according to IEEE 344 to withstand seismic forces defined in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." B. Enclosures: Flush- and surface-mounted cabinets. 1. Rated for environmental conditions at installed location. a. b. c. d. e. Indoor Dry and Clean Locations: NEMA 250, Type 1. Outdoor Locations: NEMA 250, Type 3R. Hazardous Areas, Loading Dock: NEMA 250, Type 4X stainless steel. Other Wet or Damp Indoor Locations: NEMA 250, Type 4. Indoor Locations Subject to Dust, Falling Dirt, and Dripping Noncorrosive Liquids: NEMA 250, Type 12. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262416- 3 Panel Boards June 30, 2010 2. 3. 4. 5. Hinged Front Cover: Entire front trim hinged to box and with standard door within hinged trim cover. Skirt for Surface-Mounted Panelboards: Same gage and finish as panelboard front with flanges for attachment to panelboard, wall, and ceiling or floor. Gutter Extension and Barrier: Same gage and finish as panelboard enclosure; integral with enclosure body. Arrange to isolate individual panel sections. Finishes: a. b. c. d. Panels and Trim: galvanized steel, factory finished immediately after cleaning and pretreating with manufacturer's standard two-coat, baked-on finish consisting of prime coat and thermosetting topcoat. Door in door construction Back Boxes: Same finish as panels and trim. Directory Card: Inside panelboard door, mounted in metal frame with transparent protective cover. C. Incoming Mains Location: Top or bottom to suit incoming feeder. D. Phase, Neutral, and Ground Buses: 1. 2. Material: Hard-drawn copper, 98 percent conductivity. Equipment Ground Bus: Adequate for feeder and branch-circuit equipment grounding conductors; bonded to box. E. Conductor Connectors: Terminals for feeder conductors to the panelboard mains, neutral, ground and branch circuit breaker wiring shall be suitable for the type of conductor specified. F. Future Devices: Mounting brackets, bus connections, filler plates, and necessary appurtenances required for future installation of devices. G. Panelboard Short-Circuit Current Rating: Fully rated to interrupt symmetrical short-circuit current available at terminals; coordinate with short circuit study results. DISTRIBUTION & POWER PANELBOARDS 2.2 A. Manufacturers: Subject to compliance with requirements, provide products by one of the following 1. 2. 3. B. Enclosures 1. 2. C. Cutler Hammer Square D; a brand of Schneider Electric. Siemens Energy & Automation, Inc. Panel box shall be galvanized code gauge sheet steel with removable end walls. Enclosures shall be surface mounted. Fronts 1. 2. Provide a four piece front to cover wiring gutter and wiring access areas. Hinged door fronts shall be provided with door-in-door. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262416- 4 Panel Boards June 30, 2010 3. D. Interiors 1. 2. 3. 4. 5. 6. 7. 8. E. An inner door shall cover the circuit protective devices and shall be able to be locked. Panelboard interior shall be designed and assembled such that circuit protective devices shall be solidly connected to the distribution panel vertical bus. The bus bars shall be attached to the feeder device by bolts and to the vertical bus by bolts and anti-turn methods. Circuit breaker connectors shall be designed so that circuit breakers may be removed without disturbing adjacent devices. Panelboards shall have three vertically aligned bus bars. Bus bars shall be copper. The bus bars shall have sufficient cross sectional area to meet UL 67 temperature rise requirements through actual tests. The bus bars shall be standard density rated for 1000 amperes per square inch copper. Bus bars shall be phase-sequenced and rigidly supported by high impact resistant, insulated bus supporting assemblies to prevent vibration or short circuit mechanical damage. Neutral bus shall be fully rated or 200 percent rated where indicated on the drawings. All solderless terminations shall be suitable for copper UL listed wire or cable and shall be tested and listed in conjunction with appropriate UL standards. Terminations shall be rated for use with conductor ampacity as assigned in the NEC 75 degree C table. Ground wire terminations shall be provided as an optional kit for installation by panelboard installer without voiding UL label. Main and Branch Devices 1. 2. 3. 4. 5. 6. 7. 8. Main circuit breakers shall be RMS sensing circuit breaker. Single pole branch circuit breakers shall be quick-make, quick break, and trip indicating, molded-case circuit breaker and shall not exceed 10% of the total number of poles. Circuit breaker case shall have ON/OFF and International I/O position indicators. Breaker faceplate shall list current rating, UL and IEC certification standards, and AIC ratings. Circuit breakers shall be factory sealed and shall be date coded on breaker case. Breakers shall be UL listed for reverse connection without restrictive line or load markings. Circuit breakers shall be able to mount in any operating position. All circuit protective devices shall have a short circuit interrupting capacity as shown on the plans. Main breakers and lugs shall be convertible by installer for top or bottom incoming feed. LIGHTING AND APPLIANCE BRANCH-CIRCUIT PANELBOARDS 2.3 A. Manufacturers: Subject to compliance with requirements, provide products by one of the following 1. 2. 3. B. Cutler Hammer. Square D; a brand of Schneider Electric. Siemens Energy & Automation, Inc. Panelboards: NEMA PB 1, lighting and appliance branch-circuit type. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262416- 5 Panel Boards June 30, 2010 C. Branch Overcurrent Protective Devices: Bolt-on circuit breakers, replaceable without disturbing adjacent units. D. Ratings Lighting and appliance panelboards shall be rated as indicated in drawings. Maximum current ratings for mains, sub-feeds and branches, respectively, shall be as specified in drawings. Enclosure 1. 2. E. 1. 2. 3. 4. 5. F. Bus bars 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. G. Boxes shall be a nominal 20 inches wide and 6 inches deep with wire bending space per National Electric Code. Fronts shall be reinforced steel with concealed hinges and concealed trim adjusting screws. Hinged door fronts shall be provided with door-in-door construction. All door locks shall be corrosion proof with retractable latches and shall be keyed for a single key. Interiors shall permit top or bottom incoming cables. The bus bars shall be phase sequenced, fully insulated and supported by high impact Noryl (or equal) interior base assemblies. Bus bars shall be fabricated using copper with minimum bus size of 225Amps. a. Copper bus bars shall have sufficient cross sectional area to meet UL 67 temperature rise requirements through actual tests to provide a current density of 1000A per square inch. Bus bars shall be mechanically supported by zinc finished galvanneal steel frames to prevent vibration and damage from short circuits. Terminations shall be UL tested and listed and suitable for UL copper wire. Provide [1] continuous bus bar per phase. Each bus bar shall have sequentially phased branch circuit connectors for bolt-on branch circuit breakers. Split solid neutral bus shall be plated and located in main compartment for all incoming neutral cables to be same length. Two hundred percent (200%) rated neutral shall be provided on 120/208V panels where indicated on schedules or contract drawings. Lugs shall be rated for 75 degree C terminations. Main lugs for copper conductors shall be bolted compression lugs. Lug bodies shall bolt in place, suitable for number, size, trip ratings, and conductor material. Circuit Breakers 1. 2. 3. 4. 5. 6. The main circuit breaker shall be RMS sensing type circuit breaker. Molded case circuit breakers shall be bolt-on devices. All circuit breakers shall have thermal and magnetic trip elements in each pole. [2] [3] pole breakers shall have internal common trip crossbars for simultaneous tripping of each pole. Circuit breakers shall not be restricted to any mounting location due to physical size. Main and sub-feed circuit breakers may be vertically or horizontally mounted. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262416- 6 Panel Boards June 30, 2010 7. 8. 9. 10. 11. 12. 13. 14. 15. Branch breaker panelboard connections shall be copper to copper. All panelboard terminations shall be rated as indicated in drawings. All breakers shall have an over center mechanism and be quick make and quick break. All breakers shall have handle trip indication and a trip indicator in window of circuit breaker housing. Breaker handle and faceplate shall indicate rated ampacity. Circuit breaker escutcheon shall have standard ON/OFF markings. Type HID for feeding fluorescent and high-intensity discharge (HID) lighting circuits HACR Type circuit breaker for use with motor, heating, air-conditioning and refrigeration equipment, with the UL Mark. Where indicated in schedules provide the following type CB: a. b. Current-Limiting Circuit Breakers: Frame sizes 400 A and smaller; let-through ratings less than NEMA FU 1, RK-5. GFCI Circuit Breakers: Single- and two-pole configurations with Class A groundfault protection (6-mA trip). TRANSIENT VOLTAGE SUPPRESSION DEVICES 2.4 A. Surge Protection Device Description, refer to Section 264313. PART 3 EXECUTION 3.1 EXAMINATION A. Receive, inspect, handle, and store panelboards according to NEMA PB 1.1. B. Examine panelboards before installation. Reject panelboards that are damaged or rusted or have been subjected to water saturation. C. Examine elements and surfaces to receive panelboards for compliance with installation tolerances and other conditions affecting performance of the Work. D. Proceed with installation only after unsatisfactory conditions have been corrected. INSTALLATION 3.2 A. Install panelboards in accordance with manufacturer's written instructions, as shown on the drawings and as specified herein. B. Panelboard cabinets shall be rigidly supported in place independent of the conduits with two rows of Unistrut. Set panels plumb and symmetrical with building lines in conformance with PB1.1. Furnish and install all construction channel bolts, angles, etc., required to mount the equipment furnished under this Section. C. Mounting height shall be 6’-0” to top of panelboard or 6’-6” to the centerline of highest mounted breaker handle. D. Provide mounting hardware brackets, busbar drillings and filler pieces for all unused spaces. E. "Train" interior wiring; bundle and clamp, using specified plastic wire wraps specified under Section 260519. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262416- 7 Panel Boards June 30, 2010 F. Replace panel pieces, doors, or trim exhibiting dents, bends, warps or poor fit that may impede ready access, security or integrity. G. Conduits terminating in concentric, eccentric or oversized knockouts at panelboards shall have ground bushings and bonding jumpers installed interconnecting all such conduits and the panelboard. H. Check and tighten all bolts and connections with a torque wrench using manufacturer's recommended values. I. Provide two 1” and two 3/4" spare conduits stubbed-out of flush mounted panelboards to the nearest accessible ceiling space or other accessible location and cap for future use. J. Visually inspect panelboard for rust and corrosion. If signs of rust and corrosion are present, restore or replace panelboard to new condition. K. In damp and wet locations mount panelboards with a minimum one inch of air space between cabinet and the wall or other supports. L. All surfaces of surface mounting cabinets and fronts shall be given one coat of metal primer and a finish coat of baked on gray enamel. M. Panelboards located in mechanical areas shall have weatherproof gaskets on trims and doors. N. Provide close up plugs in all unused openings in the cabinet. O. Comply with mounting and anchoring requirements specified in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." P. Mount panelboard cabinet plumb and rigid without distortion of box. Mount recessed panelboards with fronts uniformly flush with wall finish and mating with back box. IDENTIFICATION 3.3 A. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs complying with Division 26 Section "Identification for Electrical Systems." B. Create a directory to indicate installed circuit loads after balancing panelboard loads; incorporate Owner's final room designations. Obtain approval before installing. Use a computer or typewriter to create directory; handwritten directories are not acceptable. C. Panelboard Nameplates: Label each panelboard with a nameplate complying with requirements for identification specified in Division 26 Section "Identification for Electrical Systems." D. Device Nameplates: Label each branch circuit device in distribution panelboards with a nameplate complying with requirements for identification specified in Division 26 Section "Identification for Electrical Systems." FIELD QUALITY CONTROL 3.4 A. Testing Agency: Engage a qualified testing agency to perform tests and inspections. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections. Roosevelt Hall Renovation 262416- 8 Panel Boards Brooklyn College June 30, 2010 Brooklyn, NY Project #6032.20 B. 1. C. Acceptance Testing Preparation: 1. 2. D. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing. Test insulation resistance for each panelboard bus, component, connecting supply, feeder, and control circuit. Test continuity of each circuit. Tests and Inspections: 1. 2. 3. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest. Perform the following infrared scan tests and inspections and prepare reports: a. b. c. Initial Infrared Scanning: After Substantial Completion, but not more than 60 days after Final Acceptance, perform an infrared scan of each panelboard. Remove front panels so joints and connections are accessible to portable scanner. Follow-up Infrared Scanning: Perform an additional follow-up infrared scan of each panelboard 11 months after date of Substantial Completion. Instruments and Equipment: 1) Use an infrared scanning device designed to measure temperature or to detect significant deviations from normal values. Provide calibration record for device. E. Panelboards will be considered defective if they do not pass tests and inspections. F. Prepare test and inspection reports, including a certified report that identifies panelboards included and that describes scanning results. Include notation of deficiencies detected, remedial action taken and observations after remedial action. ADJUSTING 3.5 A. Adjust moving parts and operable component to function smoothly, and lubricate as recommended by manufacturer. B. Set field-adjustable circuit-breaker trip ranges as specified in Division 26 Section "Overcurrent Protective Device Coordination Study." PROTECTION 3.6 A. Temporary Heating: Apply temporary heat to maintain temperature according to manufacturer's written instructions. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262416- 9 Panel Boards June 30, 2010 SECTION 262726 WIRING DEVICES PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. This Section includes the following: 1. 2. 3. 4. 5. 6. 7. 1.3 Receptacles, receptacles with integral GFCI, and associated device plates. Wall-box motion sensors. Isolated-ground receptacles. Snap switches and wall-box dimmers. Wall-switch and exterior occupancy sensors. Cord and plug sets. Floor service outlets, poke-through assemblies, service poles, and multioutlet assemblies. DEFINITIONS A. EMI: Electromagnetic interference. B. GFCI: Ground-fault circuit interrupter. C. Pigtail: Short lead used to connect a device to a branch-circuit conductor. D. RFI: Radio-frequency interference. E. TVSS: Transient voltage surge suppressor. 1.4 SUBMITTALS A. Submit in accordance with the requirements of Section 26 00 00, the following items: 1. 2. 3. 4. 5. 6. B. Data/catalog cuts for each product and component specified herein, listing all physical and electrical characteristics and ratings indicating compliance with all listed standards. Clearly mark on each data sheet the specific item(s) being submitted and the proposed application. Provide color finishes for Owner’s Representative to select from. Submit manufacturer's installation instructions. Submit one sample of each type of device and cover plate. Where engraved device coverplates are noted on the drawings or in the specifications, conform to the requirements of Section 26 05 53. Operation and Maintenance Data: For wiring devices to include in all manufacturers' packing label warnings and instruction manuals that include labeling conditions. 1.5 QUALITY ASSURANCE Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 1 Wiring Devices June 30, 2010 A. Source Limitations: Obtain each type of wiring device and associated wall plate through one source from a single manufacturer. Insofar as they are available, obtain all wiring devices and associated wall plates from a single manufacturer and one source. B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. C. Comply with NFPA 70. D. NEMA WD 1 General Purpose Wiring Devices E. NEMA WD 2 Semiconductor Dimmers for Incandescent Lamps F. NEMA WD 5 Specific–Purpose Wiring Devices G. NEMA WD 6 Wiring Device Configurations H. WS-896-E Federal Specification I. WC-596-F Federal Specification PART 2 PRODUCTS 2.1 MANUFACTURERS A. Manufacturers' Names: Shortened versions (shown in parentheses) of the following manufacturers' names are used in other Part 2 articles: 1. 2. 3. 4. 2.2 Cooper Wiring Devices; a division of Cooper Industries, Inc. (Cooper). Hubbell Incorporated; Wiring Device-Kellems (Hubbell). Leviton Mfg. Company Inc. (Leviton). Pass & Seymour/Legrand; Wiring Devices & Accessories (Pass & Seymour). STRAIGHT BLADE RECEPTACLES A. Convenience Receptacles, 125 V, 20 A: Comply with NEMA WD 1, NEMA WD 6 configuration 5-20R, and UL 498. 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. d. B. Cooper; 5351 (single), 5352 (duplex). Hubbell; HBL5351 (single), CR5352 (duplex). Leviton; 5891 (single), 5352 (duplex). Pass & Seymour; 5381 (single), 5352 (duplex). Isolated-Ground, Duplex Convenience Receptacles, 125 V, 20 A: Comply with NEMA WD 1, NEMA WD 6 configuration 5-20R, and UL 498. 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: a. Hubbell; CR 5253IG. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 2 Wiring Devices June 30, 2010 b. c. 2. 2.3 Leviton; 5362-IG. Pass & Seymour; IG6300. Description: Straight blade; equipment grounding contacts shall be connected only to the green grounding screw terminal of the device and with inherent electrical isolation from mounting strap. Isolation shall be integral to receptacle construction and not dependent on removable parts. GFCI RECEPTACLES A. General Description: Straight blade, feed through type. Comply with NEMA WD 1, NEMA WD 6, UL 498, and UL 943, Class A, and include indicator light that is lighted when device is tripped. B. Duplex GFCI Convenience Receptacles, 125 V, 20 A: 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: a. b. 2.4 Cooper; GF20. Pass & Seymour; 2084. SNAP SWITCHES A. Comply with NEMA WD 1 and UL 20. B. Switches, 120 V, 20 A: 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. d. C. Pilot Light Switches, 20 A: 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. d. 2. D. Cooper; 2221 (single pole), 2222 (two pole), 2223 (three way), 2224 (four way). Hubbell; CS1221 (single pole), CS1222 (two pole), CS1223 (three way), CS1224 (four way). Leviton; 1221-2 (single pole), 1222-2 (two pole), 1223-2 (three way), 1224-2 (four way). Pass & Seymour; 20AC1 (single pole), 20AC2 (two pole), 20AC3 (three way), 20AC4 (four way). Cooper; 2221PL for 120 V. Hubbell; HPL1221PL for 120 V. Leviton; 1221-PLR for 120 V. Pass & Seymour; PS20AC1-PLR for 120 V. Description: Single pole, with neon-lighted handle, illuminated when switch is "ON." Key-Operated Switches, 120 V, 20 A: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 3 Wiring Devices June 30, 2010 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: a. b. c. d. 2. 2.5 Cooper; 2221L. Hubbell; HBL1221L. Leviton; 1221-2L. Pass & Seymour; PS20AC1-L. Description: Single pole, with factory-supplied key in lieu of switch handle. WALL-BOX DIMMERS A. Dimmer Switches: Modular, full-wave, solid-state units with integral, quiet on-off switches, with audible frequency and EMI/RFI suppression filters. B. Control: Continuously adjustable slider; with single-pole or three-way switching. Comply with UL 1472. C. Incandescent Lamp Dimmers: 120 V; control shall follow square-law dimming curve. On-off switch positions shall bypass dimmer module. 1. D. 2.6 600 W; dimmers shall require no derating when ganged with other devices. Illuminated when "OFF.". Fluorescent Lamp Dimmer Switches: Modular; compatible with dimmer ballasts; trim potentiometer to adjust low-end dimming; dimmer-ballast combination capable of consistent dimming with low end not greater than 20 percent of full brightness. OCCUPANCY SENSOR SWITCH (MOTION SENSOR) A. Wall sensor switch shall be infrared type, dual-voltage operation, 120/277V and compatible with electronics ballasts fully adjustable time-delay and sensitivity with heavy-duty IR Fresnel lens. Model #SOM101 by Hubbell or equal. For rooms with bi-level switching provide Model #SOM102 by Hubbell or equal with color same as switches. B. Ceiling sensor shall be dual technology (ultrasonic and infrared sensing) type. Cover 500 - 2000 square feet. Model #OMNI-DT/OMNI-DT-RP by Hubbell or equal. C. Ceiling sensor control unit (switch pack) shall be 120/277V and installed in J-box next to lighting circuit J-box. 2.7 COVERPLATES A. General 1. 2. 3. 4. B. Provide all coverplates with rounded edges and corners, smooth and free of grooves, embossing or other embellishment. Provide mounting screws to match the plate finish. Provide gang type coverplates where two or more devices are installed at one location. Individual gangable coverplates are not acceptable. Provide plates of one design, throughout the project unless otherwise specified. Metal Coverplates Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 4 Wiring Devices June 30, 2010 1. 2. 3. C. Provide smooth, stainless steel plates, American Iron and Steel Institute (AISI) Type 302, 0.040" thick with satin smooth finish. Provide removable plastic film to protect coverplates during installation. Remove film at time of final acceptance. Use Hubbell #S Series or equal. Weatherproof Coverplates 1. General a. b. c. 2. While in use covers: a. b. D. Provide weatherproof coverplate for one GFCI receptacle. Provide gasketed, spring loaded, vertically self-closing covers suitable for use in damp and wet locations while a plug is inserted into the receptacle as described in NEC. Use Pass & Seymour clear cover #WIUC10 series for GFCI receptacles or equal. Material / Finish 1. 2.8 Provide weatherproof coverplate for one GFI receptacle. Provide gasketed, spring loaded, vertically self-closing covers suitable for use in damp and wet locations as described in UL 514 and NEC. Furnish base plates, covers, hinge pins, spring and screws with corrosion resistant type material. Use Hubbell, die-cast aluminum cover #WP-26 series for GFCI receptacles or equal. As Selected by architect, unless otherwise noted. SURFACE RACEWAY A. Wiremold AL 4000 series raceway shall have (2) two wiring compartments with field removable cover(s). Multiple compartment raceway shall have an integral dividing barrier isolating wiring compartments and provided with fittings that maintain the separation of compartments. B. Covers must be removable with a standard straight blade screwdriver without marring. Raceways having two covers must allow each cover to be removed separately without allowing access into the compartment(s) enclosed by the other cover. C. Raceway shall be manufactured of extruded #6063-T5 aluminum with a heavy etched Architectural Class II clear anodized finish (AA-C22A31). D. Provide duplex receptacle every 24” and modular communication below. 1. E. In lab areas provide GFCI type receptacles. Wiring Devices 1. Wiring devices and other connectors shall be factory installed, electrically wired, and covers labeled with (insert labeling choice) as identified in the building plans. Each receptacle shall be identified noting the panel number and circuit number from which it is Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 5 Wiring Devices June 30, 2010 fed. Receptacles rated higher than a NEMA 5-20R configuration shall also be provided with voltage, phase and amperage identified in the same manner. Raceway sections shall be provided with 12" [304.8mm] pigtails at feed locations for ease of installation. Grounding shall be maintained by means of factory installed NEC sized grounding conductor(s) and utilize insulation displacement connectors as required. F. Communication Outlets 1. G. Fittings 1. H. The multioutlet assembly is to consist of factory assembled product with a full complement of fittings including, but not limited to, elbows (90º, internal and external), slide couplings for joining raceway sections, blank end caps for closing open ends of the raceway, and flat tees. Communication Devices and Accessories 1. 2.9 Raceway covers shall have either holecut provision for communications outlets, if Wiremold Interlink Cabling System data connectors are used, or the voice and data/LAN outlets shall be factory mounted to the cover plates. The raceway must be capable of containing, but not limited to, snap-in modular jacks (3-pair, 4-pair, 4-pair keyed and MMJ), coaxial and F-connectors and communication grommets. Wiring connections of these devices shall be completed at the jobsite by the appointed contractor. The raceway manufacturer will provide a complete line of connectivity outlets and modular inserts for UTP (including Category 5), STP (150 ohm) Fiber Optic, Coaxial and other cabling types with face plates and bezels to facilitate mounting. A complete line of preprinted station and port identification labels, snap-in icon buttons as well as write-on station identification labels shall be available. FINISHES A. Color: Wiring device catalog numbers in Section Text do not designate device color. 1. 2. 3. 4. Wiring Devices Connected to Normal Power System: As selected by Architect, unless otherwise indicated or required by NFPA 70 or device listing. Wiring Devices Connected to Emergency Power System: Red. Computer Wiring Devices: Blue. Isolated-Ground Receptacles: Orange [As specified above, with orange triangle on face. PART 3 EXECUTION 3.1 INSTALLATION A. Comply with NECA 1, including the mounting heights listed in that standard, unless otherwise noted. B. Install devices with the vertical centerline plumb and with all edges of the device flush against the adjacent wall surfaces. C. Mount switches at 42” above finished floor unless otherwise noted. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 6 Wiring Devices June 30, 2010 D. Manual dimmers shall be installed in individual outlet boxes. Do not install in ganged boxes with other devices. E. De-rate ganged dimmer switches as instructed by manufacturer. Do not use common neutrals in dimmer circuits. F. Mount receptacles vertically with the centerline 18” above finished floor and with grounding slot at bottom. G. Mount GFCI receptacles above counters in bathrooms and at counters within 6'-0" of sinks, whether indicated as GFCI type or not. H. Cover plates on pressed steel outlet boxes in furred areas, attics, etc., or exposed in mechanical equipment rooms shall be of the same material as the outlet box. I. Cover plates in locations concealed from public view shall have the circuit numbers and source feed point hand labeled with marking black pen (permanent marker). See Section 260553 for labeling. J. All low voltage wiring for controls, occupancy sensors, etc., shall be in conduit. K. Provide labeling for all lock switches, pilot switches, switches from which equipment or circuit controlled cannot be readily seen, three or more switches under a common plate and for switches as indicated. L. Provide coverplates for all outlet boxes, switches, receptacles, etc. M. Install blank coverplates on all outlet boxes in which no device is required or installed. N. Provide coverplates that completely cover wall opening and seat against wall. O. Coordination with Other Trades: 1. 2. 3. 4. P. Take steps to insure that devices and their boxes are protected. Do not place wall finish materials over device boxes and do not cut holes for boxes with routers that are guided by riding against outside of the boxes. Keep outlet boxes free of plaster, drywall joint compound, mortar, cement, concrete, dust, paint, and other material that may contaminate the raceway system, conductors, and cables. Install device boxes in brick or block walls so that the cover plate does not cross a joint unless the joint is troweled flush with the face of the wall. Install wiring devices after all wall preparation, including painting, is complete. Conductors: 1. 2. 3. 4. Do not strip insulation from conductors until just before they are spliced or terminated on devices. Strip insulation evenly around the conductor using tools designed for the purpose. Avoid scoring or nicking of solid wire or cutting strands from stranded wire. The length of free conductors at outlets for devices shall meet provisions of NFPA 70, Article 300, without pigtails. Existing Conductors: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 7 Wiring Devices June 30, 2010 a. b. c. Q. Cut back and pigtail, or replace all damaged conductors. Straighten conductors that remain and remove corrosion and foreign matter. Pigtailing existing conductors is permitted provided the outlet box is large enough. Device Installation: 1. 2. 3. 4. 5. 6. 7. 8. 9. Replace all devices that have been in temporary use during construction or that show signs that they were installed before building finishing operations were complete. Keep each wiring device in its package or otherwise protected until it is time to connect conductors. Do not remove surface protection, such as plastic film and smudge covers, until the last possible moment. Connect devices to branch circuits using pigtails that are not less than 6 inches in length. When there is a choice, use side wiring with binding-head screw terminals. Wrap solid conductor tightly clockwise, 2/3 to 3/4 of the way around terminal screw. Use a torque screwdriver when a torque is recommended or required by the manufacturer. When conductors larger than No. 12 AWG are installed on 15- or 20-A circuits, splice No. 12 AWG pigtails for device connections. Tighten unused terminal screws on the device. When mounting into metal boxes, remove the fiber or plastic washers used to hold device mounting screws in yokes, allowing metal-to-metal contact. R. Arrangement of Devices: Unless otherwise indicated, mount flush, with long dimension vertical and with grounding terminal of receptacles on top. Group adjacent switches under single, multigang wall plates. S. Adjust locations of floor service outlets and service poles to suit arrangement of partitions and furnishings. 3.2 IDENTIFICATION A. Comply with Division 26 Section "Identification for Electrical Systems." 1. 3.3 Receptacles: Identify panelboard and circuit number from which served. Use hot, stamped or engraved machine printing and durable wire markers or tags inside outlet boxes. FIELD QUALITY CONTROL A. Perform tests and inspections and prepare test reports. 1. 2. 3. B. In healthcare facilities, prepare reports that comply with recommendations in NFPA 99. Test Instruments: Use instruments that comply with UL 1436. Test Instrument for Convenience Receptacles: Digital wiring analyzer with digital readout or illuminated LED indicators of measurement. Tests for Convenience Receptacles: 1. 2. 3. 4. Line Voltage: Acceptable range is 105 to 132 V. Test proper polarity of all receptacles. Test ground continuity of all wiring devices Ground Impedance: Values of up to 2 ohms are acceptable. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 8 Wiring Devices June 30, 2010 5. 6. 7. GFCI Trip: Test for tripping values specified in UL 1436 and UL 943. Using the test plug, verify that the device and its outlet box are securely mounted. The tests shall be diagnostic, indicating damaged conductors, high resistance at the circuit breaker, poor connections, inadequate fault current path, defective devices, or similar problems. Correct circuit conditions, remove malfunctioning units and replace with new ones, and retest as specified above. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262726- 9 Wiring Devices June 30, 2010 SECTION 262813 FUSES PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. Section Includes: 1. 2. 1.3 Cartridge fuses rated 600-V ac and less for use in control circuits, enclosed switches enclosed controllers and motor-control centers. Spare-fuse cabinets. SUBMITTALS A. Product Data: For each type of product indicated. Include construction details, material, dimensions, descriptions of individual components, and finishes for spare-fuse cabinets. Include the following for each fuse type indicated: 1. Ambient Temperature Adjustment Information: If ratings of fuses have been adjusted to accommodate ambient temperatures, provide list of fuses with adjusted ratings. a. b. 2. 3. 4. 5. 6. B. For each fuse having adjusted ratings, include location of fuse, original fuse rating, local ambient temperature, and adjusted fuse rating. Provide manufacturer's technical data on which ambient temperature adjustment calculations are based. Dimensions and manufacturer's technical data on features, performance, electrical characteristics, and ratings. Current-limitation curves for fuses with current-limiting characteristics. Time-current coordination curves (average melt) and current-limitation curves (instantaneous peak let-through current) for each type and rating of fuse. Coordination charts and tables and related data. Fuse sizes for elevator feeders and elevator disconnect switches. Operation and Maintenance Data: For fuses to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following: 1. 2. 3. 4. Ambient temperature adjustment information. Current-limitation curves for fuses with current-limiting characteristics. Time-current coordination curves (average melt) and current-limitation curves (instantaneous peak let-through current) for each type and rating of fuse. Coordination charts and tables and related data. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262813- 1 Fuse June 30, 2010 1.4 QUALITY ASSURANCE A. Source Limitations: Obtain fuses, for use within a specific product or circuit, from single source from single manufacturer. B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. C. Comply with NEMA FU 1 for cartridge fuses. D. Comply with NFPA 70. E. Comply with UL 248-11 for plug fuses. 1.5 COORDINATION A. 1.6 Coordinate fuse ratings with utilization equipment nameplate limitations of maximum fuse size and with system short-circuit current levels. EXTRA MATERIALS A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Fuses: Equal to 10 percent of quantity installed for each size and type, but no fewer than two of each size and type. PART 2 PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. 2. 3. 2.2 Cooper Bussmann, Inc. Ferraz Shawmut, Inc. Littelfuse, Inc. SPARE-FUSE CABINET A. Characteristics: Wall-mounted steel unit with full-length, recessed piano-hinged door and keycoded cam lock and pull. 1. 2. 3. 4. Size: Adequate for storage of spare fuses specified with 25 percent spare capacity minimum. Finish: Gray, baked enamel. Identification: "SPARE FUSES" in 1-1/2-inch high letters on exterior of door. Fuse Pullers: For each size of fuse, where applicable and available, from fuse manufacturer. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262813- 2 Fuse June 30, 2010 PART 3 EXECUTION 3.1 EXAMINATION A. Examine fuses before installation. Reject fuses that are moisture damaged or physically damaged. B. Examine holders to receive fuses for compliance with installation tolerances and other conditions affecting performance, such as rejection features. C. Examine utilization equipment nameplates and installation instructions. Install fuses of sizes and with characteristics appropriate for each piece of equipment. D. Evaluate ambient temperatures to determine if fuse rating adjustment factors must be applied to fuse ratings. E. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 FUSE APPLICATIONS A. Cartridge Fuses: 1. 2. 3. 4. 3.3 Feeders Class: RK1, time delay Motor Branch Circuits: Class RK5, time delay. Other Branch Circuits: Class J, fast acting. Control Circuits: Class CC, fast acting. INSTALLATION A. Install fuses in fusible devices. Arrange fuses so rating information is readable without removing fuse. B. IDENTIFICATION C. Install labels complying with requirements for identification specified in Division 26 Section "Identification for Electrical Systems" and indicating fuse replacement information on inside door of each fused switch and adjacent to each fuse block, socket, and holder. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262813- 3 Fuse June 30, 2010 SECTION 262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. SUMMARY A. Section Includes: 1. 2. 3. 4. 5. 6. 1.3 Fusible switches. Nonfusible switches. Receptacle switches. Shunt trip switches. Molded-case circuit breakers (MCCBs). Enclosures. DEFINITIONS A. NC: Normally closed. B. NO: Normally open. C. SPDT: Single pole, double throw. 1.4 PERFORMANCE REQUIREMENTS A. Seismic Performance: Enclosed switches and circuit breakers shall withstand the effects of earthquake motions determined according to IBC. 1. 1.5 The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event." SUBMITTALS A. Product Data: For each type of enclosed switch, circuit breaker, accessory, and component indicated. Include dimensioned elevations, sections, weights, and manufacturers' technical data on features, performance, electrical characteristics, ratings, accessories, and finishes. 1. 2. 3. 4. Enclosure types and details for types other than NEMA 250, Type 1. Current and voltage ratings. Short-circuit current ratings (interrupting and withstand, as appropriate). Include evidence of NRTL listing for series rating of installed devices. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262816- 1 Enclosed Switches and Circuit Breakers June 30, 2010 5. 6. B. Detail features, characteristics, ratings, and factory settings of individual overcurrent protective devices, accessories, and auxiliary components. Include time-current coordination curves (average melt) for each type and rating of overcurrent protective device; include selectable ranges for each type of overcurrent protective device. Shop Drawings: For enclosed switches and circuit breakers. Include plans, elevations, sections, details, and attachments to other work. 1. Wiring Diagrams: For power, signal, and control wiring. C. Qualification Data: For qualified testing agency. D. Seismic Qualification Certificates: For enclosed switches and circuit breakers, accessories, and components, from manufacturer. 1. 2. 3. E. Field quality-control reports. 1. 2. 3. F. Test procedures used. Test results that comply with requirements. Results of failed tests and corrective action taken to achieve test results that comply with requirements. Operation and Maintenance Data: For enclosed switches and circuit breakers to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following: 1. 2. 1.6 Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements. Manufacturer's written instructions for testing and adjusting enclosed switches and circuit breakers. Time-current coordination curves (average melt) for each type and rating of overcurrent protective device; include selectable ranges for each type of overcurrent protective device. QUALITY ASSURANCE A. Testing Agency Qualifications: Member company of NETA or an NRTL. 1. B. Testing Agency's Field Supervisor: Currently certified by NETA to supervise on-site testing. Source Limitations: Obtain enclosed switches and circuit breakers, overcurrent protective devices, components, and accessories, within same product category, from single source from single manufacturer. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262816- 2 Enclosed Switches and Circuit Breakers June 30, 2010 C. Product Selection for Restricted Space: Drawings indicate maximum dimensions for enclosed switches and circuit breakers, including clearances between enclosures, and adjacent surfaces and other items. Comply with indicated maximum dimensions. D. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. E. Comply with NFPA 70. 1.7 COORDINATION A. Coordinate layout and installation of switches, circuit breakers, and components with equipment served and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels. PART 2 PRODUCTS 2.1 MANUFACTURES A. Manufacturers: Subject to compliance with requirements, provide products by one of the following 1. 2. 3. 2.2 Cutler Hammer. Square D; a brand of Schneider Electric. General Electric FUSIBLE SWITCHES A. Type HD, Heavy Duty, Single Throw, [240] or [600]-V ac, 1200 A and Smaller: UL 98 and NEMA KS 1, horsepower rated, with clips or bolt pads to accommodate specified fuses, lockable handle with capability to accept three padlocks, and interlocked with cover in closed position. B. Accessories: 1. 2. 3. 4. 2.3 Equipment Ground Kit: Internally mounted and labeled for copper and aluminum ground conductors. Neutral Kit: Internally mounted; insulated, capable of being grounded and bonded; labeled for copper and aluminum neutral conductors. Class R Fuse Kit: Provides rejection of other fuse types when Class R fuses are specified. Provide UL listed lugs; 75°C rated, for copper conductors, suitable for size and number of conductors indicated on the drawing. NONFUSIBLE SWITCHES A. Type HD, Heavy Duty, Single Throw, [240] or [600]-V ac, 1200 A and Smaller: UL 98 and NEMA KS 1, horsepower rated, lockable handle with capability to accept three padlocks, and interlocked with cover in closed position. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262816- 3 Enclosed Switches and Circuit Breakers June 30, 2010 B. Accessories: 1. 2. 3. 2.4 Equipment Ground Kit: Internally mounted and labeled for copper and aluminum ground conductors. Neutral Kit: Internally mounted; insulated, capable of being grounded and bonded; labeled for copper and aluminum neutral conductors. Provide UL listed lugs; 75°C rated, for copper conductors, suitable for size and number of conductors indicated on the drawing. SHUNT TRIP SWITCHES A. Basis-of-Design Product: Subject to compliance with requirements, provide comparable product by one of the following: 1. 2. 3. Cooper Bussmann, Inc. Ferraz Shawmut, Inc. Littelfuse, Inc. a. b. c. d. General Requirements: Comply with [ ASME A17.1,] UL 50, and UL 98, with 200-kA interrupting and short-circuit current rating when fitted with Class J fuses. Switches: Three-pole, horsepower rated, with integral shunt trip mechanism and Class J fuse block; lockable handle with capability to accept three padlocks; interlocked with cover in closed position. Control Circuit: 120-V ac; obtained from source of enough capacity to operate shunt trip, connected pilot, and indicating and control devices. Accessories: 1) 2) 3) 4) 5) 6) 2.5 Oiltight key switch for key-to-test function. Oiltight red ON pilot light. interlocked auxiliary contacts that change state when switch is opened and closed. Form C alarm contacts that change state when switch is tripped. Three-pole, double-throw, fire-safety and alarm relay; 120-V ac coil voltage. Three-pole, double-throw, fire-alarm voltage monitoring relay complying with NFPA 72. MOLDED-CASE CIRCUIT BREAKERS A. General Requirements: Comply with UL 489, NEMA AB 1, and NEMA AB 3, with interrupting capacity to comply with available fault currents. B. Thermal-Magnetic Circuit Breakers shall be RMS sensing circuit breaker; Inverse time-current element for low-level overloads and instantaneous magnetic trip element for short circuits. C. Adjustable short time and magnetic trip setting for circuit-breaker frame sizes 150 A and larger. D. Features and Accessories: 1. 2. Standard frame sizes, trip ratings, and number of poles. Provide UL listed lugs; 75°C rated, for copper conductors, suitable for size and number of conductors indicated on the drawing. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262816- 4 Enclosed Switches and Circuit Breakers June 30, 2010 3. 4. 2.6 Application Listing: Appropriate for application; Type SWD for switching fluorescent lighting loads; Type HID for feeding fluorescent and high-intensity discharge lighting circuits. Provide Shunt Trip for Elevator Power Supply: Trip coil energized from separate circuit, with coil-clearing contact. ENCLOSURES A. Enclosed Switches and Circuit Breakers: NEMA AB 1, NEMA KS 1, NEMA 250, and UL 50, to comply with environmental conditions at installed location. 1. 2. 3. 4. 5. 6. Indoor, Dry and Clean Locations: NEMA 250, Type 1. Outdoor Locations: NEMA 250, Type 3R. [Kitchen] [Wash-Down] Areas: NEMA 250, Type 4X. Other Wet or Damp, Indoor Locations: NEMA 250, Type 4]. Indoor Locations Subject to Dust, Falling Dirt, and Dripping Noncorrosive Liquids: NEMA 250, Type 12. Hazardous Areas Indicated on Drawings: NEMA 250, Type 8. PART 3 EXECUTION 3.1 EXAMINATION A. Examine elements and surfaces to receive enclosed switches and circuit breakers for compliance with installation tolerances and other conditions affecting performance of the Work. B. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. Install individual wall-mounted switches and circuit breakers with tops at uniform height unless otherwise indicated. B. Comply with mounting and anchoring requirements specified in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." C. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from enclosures and components. D. Install fuses in fusible devices. E. Comply with NECA 1. 3.3 IDENTIFICATION A. Comply with requirements in Division 26 Section "Identification for Electrical Systems." 1. 2. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs. Label each enclosure with engraved metal or laminated-plastic nameplate. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262816- 5 Enclosed Switches and Circuit Breakers June 30, 2010 3.4 FIELD QUALITY CONTROL A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections. 1. B. Acceptance Testing Preparation: 1. 2. C. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing. Test insulation resistance for each enclosed switch and circuit breaker, component, connecting supply, feeder, and control circuit. Test continuity of each circuit. Tests and Inspections: 1. 2. 3. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest. Test and adjust controls, remote monitoring, and safeties. Replace damaged and malfunctioning controls and equipment. D. Enclosed switches and circuit breakers will be considered defective if they do not pass tests and inspections. E. Prepare test and inspection reports, including a certified report that identifies enclosed switches and circuit breakers and that describes scanning results. Include notation of deficiencies detected, remedial action taken, and observations after remedial action. 3.5 ADJUSTING A. Adjust moving parts and operable components to function smoothly, and lubricate as recommended by manufacturer. B. Set field-adjustable circuit-breaker trip ranges as specified in Division 26 Section "Overcurrent Protective Device Coordination Study". Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262816- 6 Enclosed Switches and Circuit Breakers June 30, 2010 SECTION 262913 ENCLOSED CONTROLLERS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. Section includes the following enclosed controllers rated 600 V and less: 1. 2. 1.3 Full-voltage manual. Full-voltage magnetic. DEFINITIONS A. CPT: Control power transformer. B. MCCB: Molded-case circuit breaker. C. MCP: Motor circuit protector. D. N.C.: Normally closed. E. N.O.: Normally open. F. OCPD: Overcurrent protective device. G. SCR: Silicon-controlled rectifier. 1.4 PERFORMANCE REQUIREMENTS A. Seismic Performance: Enclosed controllers shall withstand the effects of earthquake motions determined according to IBC. 1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event." SUBMITTALS 1.5 A. Product Data: For each type of enclosed controller. Include manufacturer's technical data on features, performance, electrical characteristics, ratings, and enclosure types and finishes. B. Shop Drawings: For each enclosed controller. Include dimensioned plans, elevations, sections, details, and required clearances and service spaces around controller enclosures. 1. Show tabulations of the following: a. b. Each installed unit's type and details. Factory-installed devices. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 1 Enclosed Controllers June 30, 2010 c. d. e. 2. Nameplate legends. Short-circuit current rating of integrated unit. Features, characteristics, ratings, and factory settings of individual OCPDs in combination controllers. Wiring Diagrams: For power, signal, and control wiring. C. Qualification Data: For qualified testing agency. D. Seismic Qualification Certificates: For enclosed controllers, accessories, and components, from manufacturer. 1. 2. 3. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements. E. Field quality-control reports. F. Operation and Maintenance Data: For enclosed controllers to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following: 1. 2. 3. 4. Routine maintenance requirements for enclosed controllers and installed components. Manufacturer's written instructions for testing and adjusting circuit breaker and MCP trip settings. Manufacturer's written instructions for setting field-adjustable overload relays. Manufacturer's written instructions for testing, adjusting, and reprogramming reducedvoltage solid-state controllers. G. Load-Current and Overload-Relay Heater List: Compile after motors have been installed, and arrange to demonstrate that selection of heaters suits actual motor nameplate full-load currents. H. Load-Current and List of Settings of Adjustable Overload Relays: Compile after motors have been installed, and arrange to demonstrate that switch settings for motor running overload protection suit actual motors to be protected. 1.6 QUALITY ASSURANCE A. Testing Agency Qualifications: Member Company of NETA or an NRTL. 1. Testing Agency's Field Supervisor: Currently certified by NETA to supervise on-site testing. B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. C. Comply with NFPA 70. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 2 Enclosed Controllers June 30, 2010 D. 1.7 IEEE Compliance: Fabricate and test enclosed controllers according to IEEE 344 to withstand seismic forces defined in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." DELIVERY, STORAGE, AND HANDLING A. Store enclosed controllers indoors in clean, dry space with uniform temperature to prevent condensation. Protect enclosed controllers from exposure to dirt, fumes, water, corrosive substances, and physical damage. B. If stored in areas subject to weather, cover enclosed controllers to protect them from weather, dirt, dust, corrosive substances, and physical damage. Remove loose packing and flammable materials from inside controllers; install temporary electric heating, with at least 250 W per controller. 1.8 COORDINATION A. Coordinate layout and installation of enclosed controllers with other construction including conduit, piping, equipment, and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels. B. Coordinate sizes and locations of concrete bases with actual equipment provided. Cast anchorbolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified in Division 03. C. Coordinate installation of roof curbs, equipment supports, and roof penetrations. 1.9 EXTRA MATERIALS A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. 2. 3. 4. Fuses for Fused Switches: Equal to 10 percent of quantity installed for each size and type, but no fewer than three of each size and type. Control Power Fuses: Equal to 10 percent of quantity installed for each size and type, but no fewer than three of each size and type. Indicating Lights: 3 of each type and color installed. Auxiliary Contacts: Furnish two spare(s) for each size and type of magnetic controller installed. PART 2 PRODUCTS 2.1 MANUFACTURERS: A. Subject to compliance with requirements by one of the following: a. b. c. 2.2 Cutler Hammer. Siemens Energy & Automation, Inc. Square D; a brand of Schneider Electric. MANUAL MOTOR STARTERS Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 3 Enclosed Controllers June 30, 2010 A. Fractional Horsepower Manual Starters: AC general-purpose Class A manually operated, fullvoltage controller for fractional horsepower induction motors, with thermal overload unit and toggle operator. B. Manual Motor Starters 1. 2. 3. 4. AC general purpose Class A manually operated non-reversing full-voltage controller for induction motors rated in horsepower, with integral overload relay and pushbutton operator. Provide red pilot light and auxiliary contacts, 1 N.O. and 1 N.C. Provide provisions for padlocking in the OFF position. The starter shall have accessories such as auxiliary contacts, trip alarm, undervoltage release, and shunt trip available for field installation. C. Starter size and number of poles shall be as required for connections shown on drawings. Furnish in conformance with NEMA ICS 2. D. Enclosure: NEMA ICS 6; Type 1 for indoor and Type 3R for outdoor applications, unless otherwise noted. 2.3 FULL-VOLTAGE CONTROLLERS A. General Requirements for Full-Voltage Controllers: Comply with NEMA ICS 2, general purpose, Class A. B. Magnetic Controllers: Full voltage, across the line, electrically held. 1. 2. Configuration: Non-reversing. Contactor Coils: Pressure-encapsulated type with coil transient suppressors. a. 3. 4. 5. Power Contacts: Totally enclosed, double-break, silver-cadmium oxide; assembled to allow inspection and replacement without disturbing line or load wiring. All starters shall be such that disconnection of power conductors shall automatically disconnect control power. Each starter unit shall have the following accessories: a. b. c. 6. 7. 8. Operating Voltage: Depending on contactor NEMA size and line-voltage rating, manufacturer's standard matching control power or line voltage. Two N.O. and two N.C. auxiliary contacts. Heavy-duty oil tight H-O-A switch. Heavy-duty oil tight pilot lights with push-to-test feature; Green for motor OFF; Red for motor running and Amber for alarm condition or power available. Multispeed motors shall be equipped with additional pilot light for indication of each speed (high and low). The operating handle shall have a means to lock the handle in the OFF position. Control Circuits: 120-V ac; obtained from integral CPT, with primary and secondary fuses of sufficient capacity to operate integral devices and remotely located pilot, indicating, and control devices. Bimetallic Overload Relays: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 4 Enclosed Controllers June 30, 2010 a. b. c. d. 9. C. External overload reset push button. Combination Magnetic Controller: Factory-assembled combination of magnetic controller, OCPD, and disconnecting means. 1. MCCB Disconnecting Means: a. b. c. d. D. 2.4 Inverse-time-current characteristic. Class 20 tripping characteristic. Heaters in each phase matched to nameplate full-load current of actual protected motor and with appropriate adjustment for duty cycle. Ambient compensated. UL 489, NEMA AB 1, and NEMA AB 3, with interrupting capacity to comply with available fault currents; thermal-magnetic MCCB, with inverse time-current element for low-level overloads and instantaneous magnetic trip element for short circuits. Front-mounted, adjustable instantaneous/short time trip settings for circuit-breaker frame sizes 100 A and larger. Lockable Handle: Accepts three padlocks and interlocks with cover in closed position. N.O. alarm contact that operates only when MCCB has tripped. All starters shall be full-voltage, non-reversing, (FVNR), minimum NEMA size 1, unless otherwise noted. ENCLOSURES A. Enclosed Controllers: NEMA ICS 6, to comply with environmental conditions at installed location. 1. 2. 3. 4. 5. 6. 2.5 Dry and Clean Indoor Locations: Type 1. Outdoor Locations: Type 3R. Wash-Down Areas: Type 4X. Other Wet or Damp Indoor Locations: Type 4. Indoor Locations Mechanical Areas Subject to Dust, Falling Dirt, and Dripping NonCorrosive Liquids: Type 12. Hazardous Areas: Type 8. ACCESSORIES A. Breather and drain assemblies, to maintain interior pressure and release condensation in Type 8 enclosures installed outdoors or in unconditioned interior spaces subject to humidity and temperature swings. B. Space heaters, with N.C. auxiliary contacts, to mitigate condensation in enclosures installed outdoors or in unconditioned interior spaces subject to humidity and temperature swings. C. Sun shields installed on fronts, sides, and tops of enclosures installed outdoors and subject to direct and extended sun exposure. D. Cover gaskets for Type 1 enclosures. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 5 Enclosed Controllers June 30, 2010 PART 3 EXECUTION 3.1 EXAMINATION A. Examine areas and surfaces to receive enclosed controllers, with Installer present, for compliance with requirements and other conditions affecting performance of the Work. B. Examine enclosed controllers before installation. Reject enclosed controllers that are wet, moisture damaged, or mold damaged. C. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 3.3 INSTALLATION A. Install motor control equipment in accordance with manufacture’s instructions and as specified herein. Maintain code clearances in front of all equipment. B. Check full load ampere and service factor rating of each motor after installed and furnish the proper size overload heater elements to protect the motor. C. Wall-Mounted Controllers: Install enclosed controllers on walls with tops at uniform height unless otherwise indicated, and by bolting units to wall or mounting on lightweight structuralsteel channels bolted to wall. For controllers not at walls, provide freestanding racks complying with Division 26 Section "Hangers and Supports for Electrical Systems." D. Provide a permanent directory card with frame and transparent protector with typewritten information identifying each motor by number, location, service, HP, electrical characteristics, full load amps and overload heater size. Directory shall be displayed on the front of the motor controller. E. The interlock and control wiring, which are required but not prewired, shall be done in the field. F. Motor starters and disconnect switches shall be conveniently accessible; all NEC / NYCEC minimum clearances from walls, pipes, ducts, equipment, etc., shall be maintained. Locate as inconspicuously as possible in finished spaces. G. Seismic Bracing: Comply with requirements specified in Division 26 Section "Vibration and Seismic Controls for Electrical Systems." H. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from enclosures and components. I. Install fuses in control circuits if not factory installed. Comply with requirements in Division 26 Section "Fuses." J. Install heaters in thermal overload relays. Select heaters based on actual nameplate full-load amperes after motors have been installed. K. Install, connect, and fuse thermal-protector monitoring relays furnished with motor-driven equipment. L. Comply with NECA 1. IDENTIFICATION Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 6 Enclosed Controllers June 30, 2010 A. Identify enclosed controllers, components, and control wiring. Comply with requirements for identification specified in Division 26 Section "Identification for Electrical Systems." 1. 2. 3. 3.4 Identify field-installed conductors, interconnecting wiring, and components; provide warning signs. Label each enclosure with engraved nameplate. Label each enclosure-mounted control and pilot device. FIELD QUALITY CONTROL A. Testing Agency: Engage a qualified testing agency to perform tests and inspections. B. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections. 1. C. Acceptance Testing Preparation: 1. 2. D. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing. Test insulation resistance for each enclosed controller, component, connecting supply, feeder, and control circuit. Test continuity of each circuit. Tests and Inspections: 1. 2. 3. 4. 5. 6. 7. 8. Inspect controllers, wiring, components, connections, and equipment installation. Test and adjust controllers, components, and equipment. Test insulation resistance for each enclosed-controller element, component, connecting motor supply, feeder, and control circuits. Test continuity of each circuit. Verify that voltages at controller locations are within plus or minus 10 percent of motor nameplate rated voltages. If outside this range for any motor, notify Owner before starting the motor(s). Test each motor for proper phase rotation. Perform each electrical test and visual and mechanical inspection stated in NETA Acceptance Testing Specification. Certify compliance with test parameters. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest. Test and adjust controls, remote monitoring, and safeties. Replace damaged and malfunctioning controls and equipment. E. Enclosed controllers will be considered defective if they do not pass tests and inspections. F. Prepare test and inspection reports including a certified report that identifies enclosed controllers and that describes scanning results. Include notation of deficiencies detected, remedial action taken and observations after remedial action. G. After installation and connection to load, each controller shall be independently tested at full load by an approved agency. Submit reports for the following: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 7 Enclosed Controllers June 30, 2010 1. 3.5 Preset the thermal overload relay setting at 125% of the fla (Full Load amps) of the driven equipment motor. Operate the driven equipment for a minimum of two (2) hours. If the thermal overload relay operates, gradually increase the setting in 5% increments till the operation is successful. Indicate hp rating of the driven load and provide final overload relay settings at the controller. ADJUSTING A. Set field-adjustable switches, auxiliary relays, time-delay relays, timers, and overload-relay pickup and trip ranges. B. Adjust the trip settings of MCPs and thermal-magnetic circuit breakers with adjustable instantaneous trip elements. Initially adjust to six times the motor nameplate full-load ampere ratings and attempt to start motors several times, allowing for motor cooldown between starts. If tripping occurs on motor inrush, adjust settings in increments until motors start without tripping. Do not exceed eight times the motor full-load amperes (or 11 times for NEMA Premium Efficient motors if required). Where these maximum settings do not allow starting of a motor, notify Owner before increasing settings. C. Set field-adjustable circuit-breaker trip ranges as specified in Division 26 Section "Overcurrent Protective Device Coordination Study." 3.6 PROTECTION A. Temporary Heating: Apply temporary heat to maintain temperature according to manufacturer's written instructions until enclosed controllers are ready to be energized and placed into service. B. Replace controllers whose interiors have been exposed to water or other liquids prior to Substantial Completion. 3.7 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain enclosed controllers and to use and reprogram microprocessorbased, reduced-voltage solid-state controllers. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 262913- 8 Enclosed Controllers June 30, 2010 SECTION 264313 TRANSIENT-VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. SUMMARY A. Section includes field-mounted TVSS for low-voltage 120 V power distribution and control equipment. B. Related Sections: 1. 2. 1.3 Division 26 Section "Panelboards" for factory-installed TVSS. Division 26 Section "Wiring Devices" for devices with integral TVSS. DEFINITIONS A. ATS: Acceptance Testing Specifications. B. SVR: Suppressed voltage rating. C. TVSS: Transient voltage surge suppressor(s), both singular and plural; also, transient voltage surge suppression. D. NTRL: Nationally Recognized Testing Laboratory E. TOV: Temporary Over Voltage 1.4 SUBMITTALS A. Product Data: For each type of product indicated. Include rated capacities, operating weights, operating characteristics, furnished specialties, and accessories. Include listed documents: 1. 2. 3. B. SVR ratings Symmetrical fault current withstand ratings Independent third Party Test Lab report showing device is capable of surviving specified number of 8x20us waveform. Product Certificates: For SPDs, signed by third-party NRTL testing agencies certifying compliance with the following standards: 1. 2. 3. 4. UL 1283. UL 1449 Second Edition 2005 Revision (effective 2/9/2007) IEEE C62.34 Secondary Surge Arrester . NEMA LS-1 (1992) Low Voltage Surge Protective Devices.. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 264313- 1 Transient-Voltage suppression for LowVoltage Electrical Power Circuits June 30, 2010 C. Field quality-control reports. D. Operation and Maintenance Data: For TVSS devices to include in emergency, operation, and maintenance manuals. E. Warranties: Sample of special warranties. 1.5 QUALITY ASSURANCE A. Testing Agency Qualifications: An independent testing agency, with the experience and capability to conduct the testing indicated, that is a member company of the International Electrical Testing Association or is a nationally recognized testing laboratory (NRTL) as defined by OSHA in 29 CFR 1910.7, and that is acceptable to authorities having jurisdiction. 1. Testing Agency's Field Supervisor: Person currently certified by the International Electrical Testing Association or the National Institute for Certification in Engineering Technologies to supervise on-site testing specified in Part 3. B. Source Limitations: Obtain suppression devices and accessories through one source from a single manufacturer. C. Product Options: Drawings indicate size, dimensional requirements, and electrical performance of suppressors and are based on the specific system indicated. Refer to Division 01 Section "Product Requirements." D. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. E. Comply with IEEE C62.41, "IEEE Guide for Surge Voltages in Low Voltage AC Power Circuits," and test devices according to IEEE C62.45, "IEEE Guide on Surge Testing for Equipment Connected to Low-Voltage AC Power Circuits." F. Comply with NEMA LS 1 1992, "Low Voltage Surge Protection Devices." G. Comply with UL 1283, "Electromagnetic Interference Filters," H. Comply with UL 1449, "Transient Voltage Surge Suppressors." and listed as a SPD device. I. Tested and listed by a NRTL as a complete assembly to a symmetrical fault current rating greater than or equal to the rating of the connected panel, in accordance with NEC Article 285 J. Fed by a fuse or circuit breaker in Panel Board with SVR rating to include fuse or breaker in series with SPD. K. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a testing agency, and marked for intended location and application. L. Comply with IEEE C62.41.2 and test devices according to IEEE C62.45. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 264313- 2 Transient-Voltage suppression for LowVoltage Electrical Power Circuits June 30, 2010 1.6 COORDINATION A. Coordinate location of field-mounted TVSS devices to allow adequate clearances for maintenance. B. Coordinate TVSS devices with Division 26 Section "Electrical Power Monitoring and Control." 1.7 WARRANTY A. Special Warranty for Wall Mounted SPD: Manufacturer's standard form in which manufacturer agrees to repair or replace components of surge suppressors that fails in materials or workmanship within fifteen years from date of Substantial Completion. PART 2 PRODUCTS 2.1 PANELBOARD SUPPRESSORS A. Surge Protection Device Description: Modular design with field-replaceable module mounted externally to the Panelboard, with EMI Filtering (also known as sine-wave-tracking) type with the following features and accessories: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. B. Peak Single-Impulse Surge Current Rating: 1. 2. 3. 4. C. Fuses, rated at 200 thousand ampere interrupting capacity (AIC). Fabrication using bolted compression lugs for internal wiring. Integral disconnect capable of passing full rated surge current, or dedicated fuse or breaker. Multiple suppression circuits with current sharing. Field Replaceable protection module. Utilizing copper bus bars and for bolted connections to phase buses, neutral bus, and ground bus. Utilizing wire connections to phase buses, neutral bus, and ground bus. LED indicator lights for power and protection status. Monitoring system capable of indicating the number of transient surges, over voltages, under voltage events. Audible alarm, with silencing switch, to indicate when protection has failed. Dual set of dry contacts rated at 5 A and 250-V ac, for remote monitoring of protection status. Coordinate with the building power monitoring and control system. Field testable with test data from factory provided for comparison Senses percentage of protection available indicating true protection level available Monitors neutral-to-ground voltage and current Panelboards rated 600 Amps & above Panelboards rated 400 Amps Buss Panelboards rated 225 Amps Buss Panelboards rated 100 Amps Buss 150 kA per mode/300 kA per phase. 125 kA per mode/250 kA per phase. 100 kA per mode/200 kA per phase. 80 kA per mode/160 kA per phase. Protection modes and UL 1449 SVR for grounded wye circuits with voltages of [480Y/277] [208Y/120], 3-phase, 4-wire circuits shall be as follows: 1. Line to Neutral: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 [900 V for 480Y/277] 264313- 3 [400 V for 208Y/120]. Transient-Voltage suppression for LowVoltage Electrical Power Circuits June 30, 2010 2. 3. D. [500 V for 208Y/120]. [500 V for 208Y/120]. Line to Line: Line to Ground: [2000 V for 480 V] [1000 V for 240 V]. [1500 V for 480 V] [800 V for 240 V]. EMI-RFI noise rejection or attenuation values shall be in compliance with test and evaluation procedures outlined in NEMA LS-1-1992 1. 2.2 [900 V for 480Y/277] [900 V for 480Y/277] Protection modes and UL 1449 SVR for voltages of 240 or 480-V, 3-phase, 3-wire, delta circuits shall be as follows: 1. 2. E. Line to Ground: Neutral to Ground: Attenuation: 30dB or greater from 50kHz to 100MHz SUPPRESSORS FOR ELECTRONIC-GRADE PANELBOARD EXTENSIONS A. Surge Protection Device Description: Modular design with field-replaceable modules, with EMI Filtering (also known as sine-wave-tracking) type with the following features and accessories: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. B. Peak Single-Impulse Surge Current Rating: 1. 2. 3. 4. C. Fuses, rated at 200 thousand ampere interrupting capacity (AIC). Fabrication using bolted compression lugs for internal wiring. Integral disconnect capable of passing full rated surge current or dedicated fuse or breaker. Multiple suppression circuits with current sharing. Field Replaceable protection module. Utilizing copper bus bars and for bolted connections to phase buses, neutral bus, and ground bus. Utilizing wire connections to phase buses, neutral bus, and ground bus. LED indicator lights for power and protection status. Monitoring system capable of indicating the number of transient surges, over voltages, under voltage events. Audible alarm, with silencing switch, to indicate when protection has failed. Dual set of dry contacts rated at 5 A and 250-V ac, for remote monitoring of protection status. Coordinate with the building power monitoring and control system. Field testable with test data from factory provided for comparison Senses percentage of protection available indicating true protection level available Monitors neutral-to-ground voltage and current Panelboards rated 600 Amps & above Panelboards rated 400 Amps Buss Panelboards rated 225 Amps Buss Panelboards rated 100 Amps Buss 150 kA per mode/300 kA per phase. 125 kA per mode/250 kA per phase. 100 kA per mode/200 kA per phase. 80 kA per mode/160 kA per phase. Protection modes and UL 1449 SVR for grounded wye circuits with voltages of [480Y/277] [208Y/120], 3-phase, 4-wire circuits shall be as follows: 1. 2. Line to Neutral: Line to Ground: Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 [900 V for 480Y/277] [900 V for 480Y/277] 264313- 4 [400 V for 208Y/120]. [500 V for 208Y/120]. Transient-Voltage suppression for LowVoltage Electrical Power Circuits June 30, 2010 3. D. [900 V for 480Y/277] [500 V for 208Y/120]. Protection modes and UL 1449 SVR for voltages of 240 or 480-V, 3-phase, 3-wire, delta circuits shall be as follows: 1. 2. 2.3 Neutral to Ground: Line to Line: Line to Ground: [2000 V for 480 V] [1000 V for 240 V]. [1500 V for 480 V] [800 V for 240 V]. ENCLOSURES A. Indoor Enclosures: NEMA 250 Type 1. B. Outdoor Enclosures: NEMA 250 Type 3R. PART 3 EXECUTION 3.1 INSTALLATION A. Equipment shall be installed following manufacturer's recommendations and guidelines in compliance with NEC Article 280/250 for grounding and bonding; NEC Article 110-9 and 11010 for over-current protection. B. All TVSS devices specified in this specification section shall be designed and installed such that normal operation of the system shall not be impaired by the installation of these devices. C. Suppressors shall be installed as close as practical to the electric panel to be protected, consistent with available space. D. Install devices for panelboard and auxiliary panels with conductors or buses between suppressor and points of attachment as short and straight as possible. Do not exceed manufacturer's recommended lead length. Do not bond neutral and ground. SPD shall not be integrated with Switchgear or Switchboard as recommended by IEEE-1100, Section 8.4.2.5. 3.2 FIELD QUALITY CONTROL A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections. 1. 2. B. Verify that electrical wiring installation complies with manufacturer's written installation requirements. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing. Tests and Inspections: 1. 2. Perform each visual and mechanical inspection and electrical test stated in NETA ATS, "Surge Arresters, Low-Voltage Surge Protection Devices" Section. Certify compliance with test parameters. After installing TVSS devices but before electrical circuitry has been energized, test for compliance with requirements. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 264313- 5 Transient-Voltage suppression for LowVoltage Electrical Power Circuits June 30, 2010 3. Complete startup checks according to manufacturer's written instructions. C. TVSS device will be considered defective if it does not pass tests and inspections. D. Prepare test and inspection reports. 3.3 STARTUP SERVICE A. Do not energize or connect electrical equipment to their sources until TVSS devices are installed and connected. B. Do not perform insulation resistance tests of the distribution wiring equipment with the TVSS installed. Disconnect before conducting insulation resistance tests, and reconnect immediately after the testing is over. 3.4 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to maintain TVSS devices. Roosevelt Hall Renovation Brooklyn College Brooklyn, NY Project #6032.20 264313- 6 Transient-Voltage suppression for LowVoltage Electrical Power Circuits June 30, 2010