| Facade | External Wall Insulation | Accessories | Sto-Rotofix Plus Application Guide General information It is to be noted that the details, illustrations, general technical information and drawings contained on the following pages only represent general suggestions and details which serve solely to outline the essential modes of functioning of the products concerned. No dimensional exact tolerances apply. The applicator/client is responsible for verifying the applicability and completeness of the system in the specific construction project concerned. Adjacent trades are shown in schematic form only. All specifications and details are to be adapted according to the on-site situation and do not constitute detailed or installation planning for the respective trades. The technical specifications and information on the products in the technical data sheets and in the system descriptions/approvals must be observed. 2 | Contents Contents 4 Introduction 4 5 Sto-Rotofix Plus General EWI installation advice 6 Installation 6 7 8 9 10 11 Insertion of Sto-Rotofix Plus spiral plug into insulation Drilling into substrate Placing the screw dowel Fixing Sto-Rotofix Plus Adjusting Sto-Rotofix Plus Finishing 12 Fixing Patterns & Details 12 EPS 13 Mineral Fibre Board 14 Articles 15 Guide Contents | 3 Introduction Sto-Rotofix Plus Sto-Rotofix Plus is an innovative fixing system for mechanically fixed external wall insulation systems onto masonry and cement particle board substrates. The Sto-Rotofix Plus system can be used with tongue-and-groove EPS boards or square-edged mineral fibre insulation boards. The Sto-Rotofix Plus unit combines the ease-of-use associated with ETICS anchors with the flexibility of a rail system. Features & Benefits • Provides a cavity behind the insulation board. Easily overcomes irregular or out of tolerance backgrounds. • Allows for post-installation adjustment of the insulation. • Allows for post-installation inspection of the fixing pattern. • Reduction in thermal bridging over surface mounted ETICS anchors. • Reduction of installation time compared to a typical mechanically fixed system installation. • Ideal for thick or stepped insulation requirements, as fixing length is not dependent on the insulation thickness. • Seamless finishes possible (tolerant to deflection movement). • Sto-Rotofix Plus is supplied with BBA certification for StoTherm Classic onto masonry and lightweight steel frame substrates. Other StoTherm systems are currently being assessed by the BBA. 4 | Sto-Rotofix Plus The technical specifications and information on the products in the technical data sheets and approvals must be observed. Introduction General EWI installation advice Check the state of the substrate precisely and then select the appropriate fixing system for the external wall insulation system. The substrate must be pre-treated as appropriate to the system. Measure the correct temperature and given building moisture before application. The lowest temperature allowed for the application of most Sto products is 5°C. Sto QS products are available for winter working to a minimum application temperature of 1°C. • • • • • • • Before work begins, doors, windows, shutter boxes and horizontal covers (e.g. window sills) must be in place and weatherproofed. Before installation, the required materials must be organised according to the respective stages of the installation process. Materials stored on site must be kept in dry conditions. All on-site factors, including projections, connections, expansion joints and unevenness, must be clarified in advance. Information on the use, installation and storage of system components can be found in Sto technical data sheets and detail drawings (available on request). The applicable standards and regulations are to be observed at all times, as well as the official approval for the system. In accordance with the official approval, all system components must be sourced from Sto Ltd. If you have any queries regarding installation, please refer to your Sto sales or technical representative. The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 5 Installation Insertion of Sto-Rotofix Plus spiral plug into insulation 1 Create a recess in the insulation For EPS insulation over 100mm thickness, we recommend using a countersink milling tool to create a recess in the insulation. For mineral fibre board (MFB), a recess is only recommended post-installation if the surface is damaged. 2 Drill a hole through the insulation Using the green jolley tool, drill a hole through the insulation board. This helps to reduce debris behind the cavity, which is especially important for MFB installation. 3 Screw Sto-Rotofix spiral plug into insulation Ensure the drill hole is free of debris, then screw the Sto-Rotofix spiral plug through the insulation until it touches the substrate using a suitable slow-speed drill. The plug must always be inserted at a 90° angle to the insulation board. Note Operations 1 to 3 can be carried out away from the wall if required. A frame can be constructed to support insulation boards and provide initial cavity offset. 6 | Sto-Rotofix Plus The technical specifications and information on the products in the technical data sheets and approvals must be observed. Installation Drilling into substrate 4 Drill hole into substrate Using the correct drill bit, drill a hole into the substrate through the hole in the StoRotofix Plus spiral plug. Use a drill stop to set anchorage depth. While the drill bit is turning, ventilate the hole several times. For cement particle board: Using a suitable drill with a 10mm HSS drill bit (without hammer action), drill through CP board / steel. For masonry: Use suitable drill with a 10mm hammer drill bit to suit length. Do not use the hammer drill function on hollow brick/block. See article list on pg15. For 120T/160T fixing: Allow for 50mm embedment. For E1/E100 fixing into existing render: Allow 70mm into sound substrate + render thickness. The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 7 Installation Placing the screw dowel 5 Insert screw dowel Insert the appropriate screw dowel fixing into the plug by hand. Ensure the fixing is correctly placed using the appropriate Sto-Rotofix Plus positioning tool. If required, a hammer can be used on the the positioning tool. Grey positioning tool For 120T/160T fixing into cement particle board and unrendered masonry. (50mm anchorage) Red positioning tool For E1/E100 fixing into rendered masonry or aerated concrete. (70mm anchorage + 30mm render) Positioning tools 8 | Sto-Rotofix Plus The technical specifications and information on the products in the technical data sheets and approvals must be observed. Installation Fixing Sto-Rotofix Plus 6 Screw fixing Screw and secure the fixing into the substrate using a suitable power screwdriver /drill with the Sto-Rotofix Plus Jolley tool. Warning! Do not secure the fixing if the wall temperature is below 0°C The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 9 Installation Adjusting Sto-Rotofix Plus 7 Align the insulation Align the insulation as required for the project using string lines. The distance to the wall may be: Max. 30mm with the Sto-Rotofix Plus green plug or max. 70mm with the Sto-Rotofix Plus black plug. We recommend that once insulation thickness exceeds 140mm, the Sto-Rotofix Plus black spiral plug should be used. Use square end of positioning tool (grey or red) to adjust fixing in/out. 10 | Sto-Rotofix Plus The technical specifications and information on the products in the technical data sheets and approvals must be observed. Installation Finishing 8a Fill the recess For EPS insulation over 100mm, the recess gap can be filled using a Sto-Thermocap EPS pushed into place. For MFB insulation, where the recess is not normally formed, the gap behind the fixing can be filled with MFB offcuts or PU foam. For EPS/MFB 80/90mm, do not recess. Use PU foam to rectify minor holes generated by fixing/placement of Sto-Rotofix Plus units. 8b The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 11 Fixing Pattern (EPS) EPS (4 fixings / m2) Edge Starter Track EPS (6 fixings / m2) Edge Starter Track Fixing pattern for K90 T&G EPS Grade K90 Size 1000 x 500mm Thickness 80-200mm (standard) Height for UK > 18m (Refer to technical services) Wind loads < 1.5 KN/m2 = 4 fixings/m2 fixing pattern * < 2.4 KN/m2 = 6 fixings/m2 fixing pattern > 2.4 KN/m2 = Refer to technical services (or as specified) *Use fixing calculator tool to determine average fixing rates per m2 12 | Sto-Rotofix Plus The technical specifications and information on the products in the technical data sheets and approvals must be observed. Fixing Pattern (EPS) Window/door fixing pattern (EPS) The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 13 Fixing Pattern (MFB) Mineral Fibre Board (1000 x 500) 500 mm Edge Starter Track Mineral Fibre Board (1200 x 600) 600 mm Edge Starter Track Fixing pattern for MFB Size 1000 x 500mm / 1200 x 600mm Thickness 80-200mm Height for UK > 18m Wind loads < 1.51 KN/m2 = 8 fixings/m2 * > 1.51 KN/m2 = 12 fixings/m2 (or as specified) * The 1200 x 600mm MFB fixing pattern above gives 8.33 fixings/m2 14 | Sto-Rotofix Plus The technical specifications and information on the products in the technical data sheets and approvals must be observed. Fixing Pattern (MFB) Window/door fixing pattern (MFB) The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 15 Fixing Pattern (Firebreaks) Standard detail for adhesive firebreak 16 | Sto-Rotofix Plus The technical specifications and information on the products in the technical data sheets and approvals must be observed. Fixing Pattern (Firebreaks) Standard detail for cavity firebreak The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 17 Articles 00935-007 00935-008 00935-001 00935-002 03621-003 03622-002 03621-007 00951-001 00951-002 00951-003 00951-005 08258-008 00952-001 00952-002 00952-003 Sto-Rotofix Green 120T fixing Sto-Rotofix Black 160T fixing Sto-Rotofix Green E1 fixing Sto-Rotofix Black E100 fixing Sto-Thermo Cap, non ETA, EPS Sto-Thermo Cap, non ETA, mineral fibre Sto-Thermo Cap, non ETA, Grey EPS Sto-Rotofix Drill Bit B3, 140mm, grey Sto-Rotofix Drill Bit X2, 160mm, white Sto-Rotofix Drill Bit B3, 180mm, green/blue Sto-Rotofix Drill Bit E100, 220mm, black Sto-Thermo Countersink Mill Sto-Rotofix Positioning Tool, red Sto-Rotofix Positioning Tool, grey Sto-Rotofix Jolley Tool 18 | Sto-Rotofix Plus 100 piece carton 100 piece carton 100 piece carton 100 piece carton 200 piece carton 200 piece carton 200 piece carton 1 piece 1 piece 1 piece 1 piece 1 piece 1 piece 1 piece 1 piece The technical specifications and information on the products in the technical data sheets and approvals must be observed. Guide Concrete/uncoated dense masonry. Cement particle (CP) board 12mm thickness. Positioning tool requirement: Grey Drill bit requirement: Masonry drill bit 10mm with hammer action. Use HSS drill bit for CP board Anchorage length: 50mm for masonry. Allow 38mm projection through CP board. Insulation Cavity range (mm) Description and colour EPS K90 T&G 10-30 120T (green) 10-70 160T (black) 10-30 120T (green) 10-70 160T (black) MFB Lightweight concrete block (aerated). Rendered dense masonry/concrete. Positioning tool requirement: Red Drill bit requirement: Masonry drill bit 10mm (without hammer action for aerated block) Anchorage length: 70mm plus render thickness (max 30mm) if req‘d. Insulation Cavity range (mm) Description and colour EPS K90 T&G 10-30 E1 (green) 10-70 E100 (black) 10-30 E1 (green) 10-70 E100 (black) MFB The technical specifications and information on the products in the technical data sheets and approvals must be observed. Sto-Rotofix Plus | 19 Head Office Southern Office & Distribution Centre Sto Ltd. Sto Ltd. 2 Gordon Avenue Antura Hillington Park Kingsland Business Park Glasgow G52 4TG Wade Road Tel Basingstoke RG24 8EN +44 (0)141 892 8000 Fax +44 (0)141 404 9001 Tel info.uk@sto.com Fax +44 (0)1256 810887 +44 (0)1256 332770 www.sto.co.uk Midlands Training & Distribution Centre Sto Ltd. Unit 700 Catesby Park Kings Norton Birmingham B38 8SE Tel +44 (0)121 459 5149 Fax +44 (0)121 459 0632 Ireland Office & Distribution Centre Sto Ltd. Unit 69 Western Parkway Business Park Lower Ballymount Road Dublin 12 Tel +353 (0)1460 2305 Fax +353 (0)1460 2455 info.ie@sto.com GB 10.07.2012 www.sto.ie