1 IN THE HIGH COURT OF KARNATAKA AT BANGALORE DATED THIS THE 21ST DAY OF JUNE 2012 BEFORE THE HON’BLE MR.JUSTICE AJIT J GUNJAL WRIT PETITION No.1310/2012(GM-TEN) BETWEEN: M/S SRI KRISHNA SHELTERS PVT LTD REP. BY THE CHAIRMAN AND MANAGING DIRECT SRI K A RAGHAVENDRA S/O LATE K N A RAO AGED 48 YEARS, OFFICE AT NO.59, "SRI KRISHNA SUDHA", WEST ANJANEYA TEMPL STREET OFF. BASAVANGUDI MAIN ROAD, GANDHIBAZAAR BANGALORE 4 ... PETITIONER (BY SRI.RAVI SHANKAR, ADVOCATE FOR M/S LEX NEXUS) AND 1.NATIONAL INSTITUTE OF UNANI MEDICINE (NIUM) KOTTIGEPALYA MAGADI ROAD, BANGALORE. REPRESENTED BY ITS DIRECTOR. 2.HSCC INDIA LTD., GOVT OF INDIA ENTERPRISE HAVING ITS REGD./CORPORATE OFFICE NO.E-6(A), SECTOR I NOIDA U.P. 201301 2 REPRESENTED BY ITS GENERAL MANAGER. 3. M/S K M V PROJECTS LTD., AMENDED AS PER NO.8-3-948/949, LEVEL 4, SOLITAIRE PLAZA COURT ORDER 29.3.12 BESIDE IMAGE HOSPITAL, AMEERPET, HYDERABAD-500 073, ALSO AT NO.302, 3RD FLOOR, NO.7, EAST PARK ROAD, KUMARA PARK EAST, BANGALORE-20 REP. BY ITS DIRECTOR. .. RESPONDENTS (BY SRI : VISHNU BHAT ADVOCATE FOR R1 & R2, SHRI DHYAN CHINNAPPA ADVOCATE FOR M/S.BEST LAW PARTNERS, FOR R-3) ----THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA WITH A PRAYER TO DIRECT THE RESPONDENTS TO CONSIDER THE BID DOCUMENTS PRODUCED AS PER ANNEXURE C DATED 9.11.2011. TO THE WRIT PETITION. THIS WRIT PETITION COMING ON FOR PRELIMINARY HEARING ‘B’ GROUP THIS DAY, THE COURT MADE THE FOLLOWING: - ORDER A notice inviting tender was published on 8.10.2011 with an estimated cost of the project at Rs.1250 lakhs. Copy of the tender notification is at Annexure-A. The petitioner along with others was an aspirant. The 3 petitioner claims that it possesses qualification for eligibility criteria for pre-qualification and submitted all the necessary documents in compliance of Clause 3 in proof of minimum eligibility criteria. The condition of the tender was that average annual financial turnover during the last three consecutive years should be at 30% of the estimated cost and petitioner by was demonstrated by producing the required balance sheets. The petitioner submitted its tender document with all other requirements such as solvency certificate and the bidding capacity was also made available. furnished the details of equipment capabilities personnel It had also capabilities, and financial capabilities. Suffice it to say that during the scrutiny of the pre- qualification documents which was held on 09.11.2011, it was noticed that the petitioner had not attested his signature to Volume 6 of the document which was an essential submitting ingredient to their conditions the tender document. before Under these 4 circumstances, respondents 1 and 2 invoked Clause 21 of the Tender document and requested the petitioner to counter sign Volume 6 of the tender document. It is the case of the petitioner that the said document was counter signed and was sent to the tendering authority. But however the tendering authority choose to reject the tender of the petitioner on the ground that at the inception itself Volume 6 was not signed. According to the petitioner, once the tendering authority exercises Clause 21 of the tender document the bid of the petitioner ought to have been considered with reference to Clause 21 and the signature has been put on the Volume 6 and sent at a later point of time. The tender of the petitioner was rejected on 29.11.2011 though specifically not by any communication but however by returning the bank guarantee, the rejection of the said tender is questioned by the petitioner before this Court. 5 2. Notice was issued to the respondents 1 and 2 and they have entered appearance and have filed statement of objections inter alia contending that as on the date when the tender was opened and qualification was being the considered, pre-bid necessary information which was sought from the petitioner was not forthcoming. Hence, its tender was rejected and they justify their action with reference to various correspondence inter se between them. has filed this writ petition The petitioner on 10.1.2012 seeking for certain reliefs. But however during this interregnum, the third respondent was awarded the tender work. Hence, on an application made by the petitioner, the third respondent is impleaded. On being notified of the proceedings, the third respondent has also filed its objections inter alia contending that the bid of the petitioner was rightly rejected, more so having regard to Clause 15 and 21 of the tender document. their contention It is also that after awarding of the contract, 6 work order has been issued and work is substantially in progress. Hence at this point of time question of considering the case of the petitioner does not arise inasmuch as the rejection was just and proper, having regard to the fact that the query which was raised by the tendering authority was not complied within a specified time and even as on the date, when the prequalification bid was opened and was being considered, query was not replied. 3. In support of the petition, Mr.Ravishankar for the petitioner places reliance on Clause 21 of the document which according to him would come to his assistance. He submits that petitioner was Volume 6 was not signed and the asked by the respondents 1 and 2 to counter sign Volume 6. It appears according to him, there were two more tenderers who were similarly placed and accordingly were asked to counter sign. He would assert that the said Volume 6 was signed and 7 sent to respondents 1 and 2 by reached them before bid submits courier and it had was finalized. He that the petitioner’s tender further could not have been rejected solely on the premise that Volume 6 was not signed. Mr.Ravishankar further submits having given to understand that that his bid would be considered after obtaining the signature on Volume 6, it would amount to legitimate expectation. Hence, rejection is bad. 4. Mr.Bhat in support of the statement of objections filed by respondents 1 and 2 justifies the rejection on the ground that as on the date when the tender was being considered Volume 6 signed by the petitioner was not received by them. In the circumstances, since tender conditions were not complied their rights in rejecting the tender. they were within 8 5. Mr.Dhyan Chinnappa, learned Counsel appearing for the respondent no.3 reiterated what is stated in the statement of objections and submits that the petitioner though was the lowest bidder was not eligible at all for consideration since he had not complied with the tender formalities inasmuch as Volume 6 was not signed. He further submits that though it was open for the respondents to outrightly reject the said tender nevertheless they choose to exercise Clause 21 and requested the petitioner to sign Volume 6 and submit Volume 6 after the signature. That having not been done, rejection is justified. He further submits that third respondent has expended substantial amount and the work is in progress. At this point of time, if the tender which is awarded to respondent no.3 is set aside, it would put the onus on respondent no.3 as well as the Exchequer inasmuch as the entire process is required to start all over again, with reference to other bidders also. 9 6. Indeed insofar as the intervention of the Courts under Article 226 of the Constitution of India with reference to the tender has been set at rest by the Apex Court in the various decisions. The Apex Court in many number of judicial pronouncements has observed that the Courts should be slow in stepping in and upsetting the tender process unless it is found that it is accentuated by mala fides or rejection of the tender is on an unreasonable premise or a ground. The fact that the tender of a tenderee is rejected and if he is lowest bidder does not necessarily entitle it to consider if other things are equal. 7. In the case on hand apparently the communication was issued by the respondents 1 and 2 on 15.11.2011 which would read as under: “With reference to your offer No.nil dated 8thNovember 2011 submitted by you on 09.11.2011 for the subject works. Your are requested to submit the following clarifications/details. 10 1.Audited Balance Sheet for FY-2005-06 and FY-2006-07. 2.Membership No. of CA.206099 3.Bidding Capacity details duly certified by CA 7 notarized. Chartered A/C. 4.Biodataof key officials as per clause no.3.3 of Vol-I. 5.Registration/Undertaking for labour cess registration as perclauseno.4.1 of Vol-I 6.Volume-VI of Tender document(comprising of tender drawing) duly signed is not submitted by you. You are requested to submit the above clarification by 21.11.2011 through courier/speed post/by hand/fax”. Indeed the said communication is issued on the basis of tender document clause 21.1. Indeed it is to be noticed that a clarification was sought for in respect of information already submitted by bidders, the clarification of bids from bidders vide HSCC letter dated 15.11.2011. During the opening of pre-qualification applications, it was found that M/s.Sri Krishna Shelters, that is the petitioner and another Company had not submitted Volume 6 drawing bids. comprising of tender The bids were thereafter sent to 11 Evaluation Committee. Under this circumstance, necessary information was sought. It is significant to note that the petitioner responded communication dated 15.11.2011 to the immediately on 18.11.2011 which would read as under: “Following documents are forwarded herewith for your further necessary action please: 1) Audited Balance Sheet for FY 2005-06 and 2006-07. 2)Membership Number of CA 206099. 3)Bidding capacity details duly certified by CA and notarized. 4) Biodata of Key officials as per clause No:303 of Vol.-I. 5)Undertaking for Labour cess registration as per clause No.4.1 of Vol.-I. It is submitted that the Vol.VI of Tender documents (comprising of tender drawings) forwarded was not signed due to over sight. However, it is confirmed that all our rates quoted for each items are based on tender drawings(Vol.IV tender documents) and specification in the BOQ, we accept in case if there in any variations.” However, it is significant to note that Volume 6 of the tender document comprising of the tender documents was not signed. But however they would reiterate that 12 the rates quoted for each items are based on tender drawing and they accept if there are any variations. It would necessarily mean that the tender documents was not Volume no.6 of the sent along with the communication dated 18.11.2011. Indeed the said document was sent on 28.11.2011 signed by the Managing Director for necessary action. Apparently by the time the document reached the respondents, Committee had finalised the the tender in favour of the third respondent and work order was issued on 6.2.2012. It is also to be noticed that the bank guarantee which was furnished by the petitioner was returned on 28.12.2011 and it was open for the petitioner to take shelter under Clause 21 of the tender documents. Before considering Clause 21 of the tender document, it is necessary to look into Clause 15 of the tender document which is in respect submission of bid. 15.1 would read as under: of 13 “The bid shall be submitted in accordance with the procedure detailed herein. Specified document shall be enclosed in an envelope of appropriate size which shall be sealed (i) Envelope No.1 Shall contain the Bid securities as mentioned in Clause 12 of the Instructions to the bidders. (ii) Envelope-II shall contain covering letter and offer bid documents Volume I, II, III, IV and VI duly signed and stamped with necessary documents as described in the pre-qualification document including the following. Bids containing any conditions are liable to be rejected”. Clause 15 also details as to the documents which are required to be sent along with the tender document. It is significant to note that the petitioner did not send as many as five documents along with the Volume 6 of the tender document not duly signed by it. respondents 1 and 2 Indeed the sought for clarification under Clause 21. Clause 21 is in respect of clarification of bids. Clause 21.1 would speak about the assistance in examination, evaluation and comparison of bids. The Engineer may ask bidders individually for clarification of their bids including the break down of unit prices. 14 A request for clarification and response writing in reply or fax, shall be in no change in the substance shall be sought. Indeed having regard to the Clause 21 necessary information was sought. If the necessary information was supplied on or before 21.11.2011, as sought for by the respondents 1 and 2, tender or the bid of the petitioner considered. probably the could have been The rejection of tender of the petitioner is on the premise that even on a subsequent extended date, Volume 6 duly signed was not sent to the competent authority for consideration. Indeed this would amount to not specifying the tender conditions as per the tender documents. 8. It is no doubt true that Clause 19.6 was pressed into service to indicate that if the conditions of the tender are not specified, it is not imminent that it should be rejected but however that by itself cannot be said that it is not within the powers of the tendering 15 authority to reject the bid if bidder has not complied with the conditions of the tender document. 9. Insofar as the legitimate expectation is concerned, the Apex Court has observed in the case of PUNJAB COMMUNICATONS LIMITED VS. UNION OF INDIA AND OTHERS reported in (1999) 4 SCC 727 as under: “27.The basic principles in this branch relating to “legitimate expectation” were enunciated by Lord Diplock in Council of Civil Service Unions v.Minister for the Civil Service at pp.408-409. It was observed in that case that for a legitimate expectation to arise, the decisions of the administrative authority must affect the person by depriving him of some benefit or advantage which either (i) he had in the past been permitted by the decision-maker to enjoy and which he can legitimately expect to be permitted to continue to do until there has been communicated to him some rational grounds for withdrawing it on which he has been given an opportunity to comment; or (ii) he has received assurance from decision-maker that they will not withdrawn without giving him first opportunity of advancing reasons the be an for 16 contending that withdrawn”. The Apex OF they should not be Court in the case of FOOD CORPORATION INDIA 1993(1) SCC 71 and NAVAJYOTHI CO.OPERATIVE HOUSING SOCIETY 1992(4) SCC 477 has observed that the legitimate expectation is not the same thing as anticipation. It is also different from a mere wish or desire or a hope. Nor is it a claim or demand based on a right. A mere disappointment would not give rise to legal consequences. The Apex Court has observed thus: “The legitimacy of an expectation can be inferred only if it is founded on the sanction of law or custom or an established procedure followed in regular and natural sequence. …..Such expectation should be justifiably legitimate and protectable”. The Apex Court in the case of PUNJAB COMMUNICATON has quoted thus from the case of R. VS. SECRETARY under: OF STATE FOR TRANSPORT as 17 “ The Court is not the Judge of the merits of the decision-maker’s policy. …the public authority in question is the Judge of the issue whether ‘overriding public interest’ justifies such a change in policy….But that is no more than saying that a change in policy, like any discretionary decision by a public authority, must not transgress Wednesbury principles”. Ultimately, the Apex Court was of the view that the appellant therein was not able to establish that he was entitled for the benefit under the Doctrine of Legitimate Expectation. I am of the view that no different view can be taken in the present set of circumstances. 10. The Courts interference in a case of tender has been set at rest as observed by various decisions of the Apex Court. To quote a few in AIR INDIA LIMITED VS.COCHIN INTERNATIONAL AIRPORT LIMITED (2000) 1 SCR 1505 at 18.4 has observed thus: “The award of a contract, whether it is by a private party or by a public body or the State, is essentially a commercial transaction. In arriving at a commercial 18 decision considerations which are paramount are commercial considerations. The State can choose its own method to arrive at a decision. It can fix its own terms of invitation to tender and that is not open to judicial scrutiny. It can enter into negotiations before finally deciding to accept one of the offers made to it. Price need not always be the sole criterion for awarding a contract. It is free to grant any relaxation, for bona fide reasons, if the tender conditions permit such a relaxation, for bona fide reasons, if the tender conditions permit such a relaxation”. The Apex Court in the case of RAUNAQ INTERNATIONAL LIMITED VS. IVR CONSTRUCTIONS LIMITED reported in AIR 1999 SC 393 observed thus: “When a writ petition is filed in the High Court challenging the award of a contract by a public authority or he State, the Court must be satisfied that there is some element of public interest involved in entertaining such a petition. If, for example, the dispute if purely between two tenderers, the Court must be very careful to see if there is any element of public interest involved in the litigation. A mere difference in the prices offered by the two tenderers may or may not be decisive in deciding whether any public interest is involved in intervening in such a commercial transaction. It is important to 19 bear in mind that by Court intervention, the proposed project may be considerably delayed thus escalating the cost far more than any saving which the Court would ultimately effect in public money by deciding the dispute in favour of one tenderer or the other tenderer. Therefore, unless the Court is satisfied that there is a substantial amount of public interest, or the transaction is entered into mala fide, the Court should not intervene under Article 226 in disputes between two rival tenderers”. Having said so, I am of the view that it is not open at this point of time for the petitioner to question the tender process. Indeed it is also to be noticed that the petitioner cannot cry respondents 1 and 2 foul with the of as its tender could have been rejected at the inception itself. But however by exercising Clause 21 had extended time clarification. action That not having been to submit the done and the clarification not having reached the respondents 1 and 2 in time, I am of the view that there is a very little scope to interfere with the tender process. It is also to be noticed that no material is forthcoming to show that 20 at a later point of time before the bid was finalised required clarification bid left unattended in the first instance was sent. In the absence of any material, it cannot be said that the Volume 6 was signed and sent. Having said so, I am of the view that question of interference does not arise. Writ petition stands rejected. SD/JUDGE sh