IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER of a Board of Inquiry appointed under s149J of the Resource Management Act 1991 to consider a private plan change request made by Tainui Group Holdings Limited and Chedworth Properties Limited in relation to the Ruakura Development proposal ("Plan Change"). STATEMENT OF EVIDENCE OF CHRISTOPHER MARK HORNE FOR TRANSPOWER NEW ZEALAND LIMITED: PLANNING MATTERS 26 MARCH 2014 J D K Gardner-Hopkins/ E J Hudspith Phone 64 4 499 9555 Fax 64 4 499 9556 PO Box 10-214 DX SX11189 Wellington Contents EXECUTIVE SUMMARY ......................................................................................... 1 1. BACKGROUND AND OVERVIEW ................................................................. 3 Qualifications and Experience ........................................................................ 3 Involvement with the Plan Change................................................................. 4 Code of Conduct............................................................................................. 4 Scope of Evidence.......................................................................................... 4 2. OVERVIEW OF STATUTORY CONTEXT ..................................................... 6 Statutory Considerations - Plan Changes ...................................................... 6 The National Policy Statement for Electricity Transmission .......................... 7 Regional Policy Statement and Proposed Regional Policy Statement ........ 13 Relevance of the NZECP34: Why it does not provide sufficient protection ...................................................................................................... 15 3. TRANSPOWER'S APPROACH TO CORRIDOR MANAGEMENT.............. 17 The issues .................................................................................................... 17 4. EVALUATION OF The relief sought by Transpower .................................... 20 Objective 25H.4.16 and Policies .................................................................. 23 Costs and benefits ........................................................................................ 33 Part 2 Considerations ................................................................................... 33 5. CONCLUSIONS............................................................................................ 34 1 EXECUTIVE SUMMARY A. In general terms my planning evidence addresses: (a) The relevant statutory considerations for plan changes; (b) The National Policy Statement on Electricity Transmission ("NPSET"); (c) The operative and Proposed Waikato Regional Policy Statement; (d) The New Zealand Electrical Code of Practice for Electrical Safe Distances NZECP 34:2001 ("the NZECP34"); B. (e) Transpower's approach to corridor management; and (f) An evaluation of the Relief Sought by Transpower. In terms of the relevant statutory provisions, I set out my understanding of the legal tests for plan changes based on the "Long Bay Criteria". C. I then go on to summarise the NPSET and discuss how the Plan Change must give effect to it, with a specific focus on Policies 10 and 11. In general terms Policy 10 requires that decision makers, to the extent reasonably possible, manage activities to avoid reverse sensitivity on the electricity transmission network managed by Transpower. It also requires activities to be managed to ensure that the operation, maintenance, upgrading and development of the electricity transmission network is not compromised. In general terms Policy 11 requires local authorities to identify appropriate buffer corridors within which sensitive activities will generally not be provided for in district plans. D. I then outline the relevant provisions of the Waikato Regional Policy Statement and Proposed Waikato Regional Policy Statement, and identify where these support the corridor management approach being sought by Transpower, including the management of activities that are not "sensitive activities" in terms of the NPSET. 2696759 E. I outline how the NZECP34 is a mandatory code for electrical safety, and discuss how it has a narrower focus than the RMA and how the NZECP34 alone will not achieve the broader objectives of the NPSET. F. I then outline Transpower's corridor management approach including the specific amendments sought in its submission on the Plan Change, and the preference Mr Noble has expressed in his evidence to avoid the risks arising from having container storage and mobile plant operating beneath the HAM-WHU-A transmission line. I understand why Transpower is taking that position, and it is an outcome that the Board will have to evaluate. That task has not been assisted by the fact that the Applicants did not in their primary evidence respond to the concerns raised by Transpower in its submission. I then evaluate the proposed relief sought by Transpower in light of the relevant statutory criteria. G. I generally support the amendments Transpower has sought to the Plan Change as providing a better overall outcome in terms of achieving the purpose of the RMA and giving effect to the NPSET, as compared with the provisions included in the Plan Change as notified. I also outline some further amendments I consider would be appropriate. In general terms these include amendment to a policy, changes to the detailed earthworks controls sought, and addition of further exemptions from non-complying activity status for buildings and structures in a National Grid Yard. A final set of proposed Plan Change amendments are included in Attachment A to my evidence. 2696759 3 1. BACKGROUND AND OVERVIEW Qualifications and Experience 1.1 My full name is Christopher Mark Horne. 1.2 I am a resource management consultant and director of the resource and environmental management consulting company, Incite. I hold the qualifications of Bachelor of Arts (Geography) and Master of Regional and Resource Planning, both gained at the University of Otago. I am a member of the New Zealand Planning Institute. 1.3 I have over 20 years of professional experience in the field of resource management, and have represented a variety of public and private clients on a range of matters that raise planning issues. A significant part of my experience relates to network utility infrastructure, including both project consenting, planning advice, and hearing support on resource management documents, including changes that may affect the operation or deployment of infrastructure. In this regard, I have acted for Telecom, Chorus, Vodafone, Police Radio Network, Vector, Transpower, Watercare Services and the New Zealand Transport Agency ("NZTA"). 1.4 I am on the panel of approved statutory planning advisors for the NZTA in Auckland, and in that capacity have been involved in numerous plan changes and structure plans involving urban growth and intensification around Auckland, with a particular emphasis of that work being on protecting the operation of regionally significant land transport infrastructure. I also recently acted for Transpower in a major greenfield plan change proposal at Drury South in Auckland, where similar buffer corridor provisions to those being sought by Transpower in these proceedings were being sought, and were ultimately agreed to by the applicant and adopted in the plan change decisions. 1.5 My abbreviated curriculum vitae, setting out my experience most relevant to these proceedings, is attached as Attachment D to this evidence. 1.6 My evidence is given in support of Transpower's submission on the private plan change request made by Tainui Group Holdings Limited and 2696759 4 Chedworth Properties Limited ("Applicants") in relation to the Ruakura development proposal ("Plan Change"). Involvement with the Plan Change 1.7 I was approached by Transpower in November 2013, with a request as to whether or not I could provide expert assistance in relation to the Plan Change. I considered Transpower's position together with some of the background materials relating to the project, had discussions with Transpower representatives, and formed an initial opinion that I could provide support to Transpower. 1.8 I assisted Transpower with the preparation of its submission on the Plan Change, and began the task of preparing my evidence in February this year. 1.9 I am familiar with the corridor management approach Transpower is generally pursuing around New Zealand. I am also familiar with the relevant sections of the Plan Change, Transpower's involvement in the Plan Change and the area that the Plan Change will affect. 1.10 I have driven around the Plan Change area with representatives of Transpower on two occasions to view the location of existing Transpower infrastructure in relation to the Plan Change area. I undertook the first of these site visits before I began preparing this evidence. Code of Conduct 1.11 I confirm I have read the 'Code of Conduct for Expert Witnesses' contained in the Environment Court Consolidated Practice Note 2011. I agree to comply with this Code of Conduct. In particular, unless I state otherwise, this evidence is within my sphere of expertise and I have not omitted to consider material facts known to me that might alter or detract from the opinions I express. Scope of Evidence 1.12 My evidence will cover the following topics: (a) The relevant regulatory / policy framework. Here I summarise the key statutory considerations or 'tests' that need to be applied, as I understand them, including: 2696759 5 (i) Overview of statutory considerations for plan changes. (ii) The National Policy Statement on Electricity Transmission ("NPSET"), including the requirement to "give effect to" the NPSET. (iii) Relevant provisions of the Regional Policy Statement and Proposed Regional Policy Statement. (iv) The relevance of the New Zealand Electrical Code of Practice for Electrical Safe Distances NZECP 34: 2001 ("NZECP34"). Here I explain my view, informed by the other evidence for Transpower, that the NZECP34 does not provide adequate protection or ensure the sustainable management of the National Grid as a nationally significant resource, and why I consider further controls are both appropriate and necessary through the Plan Change. (b) Transpower's approach to corridor management, and its concerns with the Plan Change, including: (c) (i) Direct effects on the National Grid; (ii) Safety risks and other hazards; (iii) Interference with access and maintenance; and (iv) Reverse sensitivity issues. Evaluation of the relief sought by Transpower. I consider the particular relief sought by Transpower in light of the relevant statutory criteria and concerns outlined above. 1.13 In preparing my evidence I have considered the draft evidence of Mr Copeland, and Mr Noble. 2696759 6 2. OVERVIEW OF STATUTORY CONTEXT Statutory Considerations - Plan Changes 2.1 While the Board will be familiar with the legal tests applicable to plan change proceedings, it is appropriate that I highlight my understanding of the key tests. I am familiar with the Long Bay criteria,1 which expand on the tests laid down in Eldamos.2 2.2 From my interpretation of the Long Bay criteria, I understand that: (a) The Plan Change should, most broadly, assist the Council in carrying out its functions so as to achieve the purpose of the Act.3 (b) The Board, in resolving the Plan Change, must "give effect to" the NPSET,4 and the Regional Policy Statement.5 (c) The Board is required to have regard to the Proposed Regional Policy Statement.6 (d) Each proposed objective in the Plan Change is to be evaluated by the extent to which it is the "most appropriate" way to achieve the purpose of the Act.7 My understanding of what is meant by "most appropriate" is that the decision maker has to choose the "optimum planning solution" available to it, based on the submissions and evidence that it has received.8 (e) The policies are to implement the objectives and the rules are to implement the policies.9 (f) Each proposed policy or method (including each rule) is to be examined having regard to its efficiency and effectiveness, as to 1 2 3 4 5 6 7 8 9 Long Bay-Okura Great Park Society Inc v North Shore City Council EnvC Auckland A078/ 2008, 16 July 2008 at [34]. Eldamos Investments Ltd v Gisborne District Council EnvC Wellington W047/2005, 22 May 2005 at [128]. RMA, ss 31, 72, and 74(1). RMA, ss 75(3)(a). RMA, s 75(3)(c). RMA, s 74(2)(a)(i). s 32(3) (a). Auckland Memorial Park Limited v Auckland Council [2014] EnvC 9, at [25]. s 75(1). 2696759 7 whether it is the "most appropriate" method for achieving the objectives10 of the plan, taking into account: (i) the benefits and costs of the proposed policies and methods (including rules)11; and (ii) the risk of acting or not acting if there is uncertain or insufficient information about the subject matter of the policies, rules, or other methods.12 (g) In making a rule the Board must have regard to the actual or potential effect of activities on the environment.13 2.3 I note than s32 of the RMA has recently been amended but that change did not come into force until after the Plan Change was notified. On this basis I understand that the proposal must continue to be assessed under the previous version of s32. I understand that the reason s32 has been amended is to provide for more rigour in s32 analysis and decision making in the future by ensuring a high quality of information is provided to inform planning decisions, providing more direction on what is required in s32 evaluations (particularly in regard to quantifying benefits and costs if practical), and ensuring there is adequate consideration given to opportunities for economic growth and employment. The National Policy Statement for Electricity Transmission 2.4 National Policy Statements are an RMA planning instrument designed to help local government balance competing national benefits with local costs. District plans are required to give effect to national policy statements (s75(3)(a) RMA), and councils are required to give effect to the NPSET (s55(2B)). 2.5 In my opinion, provisions in district plans to protect the National Grid electricity transmission network should be substantially consistent throughout New Zealand, and the NPSET helps ensure there is a nationally consistent approach on this issue of national importance. 10 11 12 13 s 32(3)(b), prior to recent amendments since the Plan Change was notified. s 32(4)(a). s 32(4)(b). s 76(3). 2696759 8 2.6 The NPSET came into effect on 10 April 2008. The RMA requires local authorities to give effect to its provisions in plans. The NPSET includes a single objective and 14 supporting policies. The objective is as follows: To recognise the national significance of the electricity transmission network by facilitating the operation, maintenance and upgrade of the existing transmission network and the establishment of new transmission resources to meet the needs of present and future generations, while (a) Managing the adverse environmental effects of the network; and (b) Managing the adverse effects of other activities on the network. 2.7 This objective recognises the national significance of the electricity transmission network both in terms of deployment of new transmission infrastructure, and the operation, maintenance and upgrading of existing infrastructure. It also recognises that the network itself can result in adverse effects that need to be managed, but also that other activities can have adverse effects on the existing network that need to be managed. The provisions Transpower is seeking as part of this Plan Change are most relevant to managing the adverse effects of activities by other parties on the existing transmission network. These effects are summarised later in my evidence, and are addressed in more detail in the evidence of Mr Noble. 2.8 The NPSET contains 14 policies. Policy 1 recognises the national benefits of transmission and the need for decision makers to recognise and provide for the national, regional and local benefits of sustainable, secure and efficient electricity transmission. Policies 2 – 9 guide the management of the environmental effects of transmission, setting out a general set of responsibilities for both decision makers and Transpower. 2.9 For present purposes the most relevant policies are 10 and 11, which I will consider in more detail shortly. These policies cover the management of the adverse effects of third parties on the transmission network. 2.10 Policy 12 addresses the need for territorial authorities to identify the electricity transmission network on their relevant planning maps, while Policies 13 and 14 address long term strategic planning for transmission 2696759 9 assets (e.g. recognition of the designation process in district plans and objectives, policies and methods in regional planning instruments, to facilitate long term planning for electricity transmission assets). 2.11 Policies 10 and 11 are particularly important when it comes to existing lines infrastructure: Policy 10 In achieving the purpose of the Act, decision makers must to the extent reasonably possible manage activities to avoid reverse sensitivity effects on the electricity transmission network and to ensure that operation, maintenance, upgrading, and development of the electricity transmission network is not compromised. [my emphasis] Policy 11 Local authorities must consult with the operator of the national grid, to identify an appropriate buffer corridor within which it can be expected that sensitive activities will generally not be provided for in plans and/or given resource consent. To assist local authorities to identify these corridors, they may request the operator of the national grid to provide local authorities with its medium to long term plans for the alteration or upgrading of each affected section of the national grid (so as to facilitate the long-term strategic planning of the grid). 2.12 Policy 11 requires local authorities to consult with Transpower and identify an "appropriate buffer corridor" within which it can be expected that "sensitive activities" will generally not be provided for in plans and/or given resource consent. I acknowledge that the applicant has included buffer corridors in the Plan Change, and as stated in paragraph 278 of Mr Peter Hall's planning evidence for the Applicants, the intention of the Plan Change provisions is to give effect to the NPSET by including an electricity corridor rule to manage the adverse effects of the network and manage the adverse effects of other activities on the network. However, I note that he does not make any specific comment on Transpower's proposed amendments other than to note that discussions with Transpower are underway to refine the buffer corridor provisions, and that his conclusions in respect of the NPSET are subject to the resolution of 2696759 10 these matters. As I return to later, the failure of the Applicants in their evidence to explain why they did not design their proposal to avoid significant conflicts with the National Grid lines means there is limited information presently available as to how practical it might be to avoid or eliminate the risks that are of most concern to Transpower. 2.13 "Sensitive activities" are defined in the NPSET to include schools, residential buildings and hospitals. However, the definition does not preclude other activities (for example childcare centres) also being considered as a sensitive activity. Transpower has sought a more specific definition to in the Plan Change to provide clearer direction on what is a sensitive activity, and to provide better alignment with its position on the Proposed Hamilton District Plan. 2.14 While zones such as the Medium Density and General Residential Zone allow for sensitive activities and thus clearly justify buffer corridor provisions, other 'less sensitive' zones such as the Ruakura Logistics Zone also provide for sensitive activities such as childcare centres as a restricted discretionary activity. Accordingly, sensitive activities could also potentially be located near to National Grid lines even in the nonresidential type zones in the Plan Change if sufficient buffer corridor provisions are not included in the Plan Change. Therefore, suitable buffer corridors with related policy provisions and rules are required in nonresidential zones as well, to ensure that Policy 11 is given effect to. 2.15 Policy 11 also requires that sensitive activities within buffer corridors should not be generally provided for in plans and/or given resource consent. Accordingly, in my opinion Policy 11 clearly supports a noncomplying activity status for these activities within the National Grid Yard. This particular position is consistent with the Plan Change provisions for transmission corridors as included in the Plan Change as notified (subject to some terminology changes requested in Transpower's submission). 2.16 In my view, the buffer corridor referred to in Policy 11 should not be confined to the management of sensitive activities alone, and also assists in giving effect to the requirements of Policy 10 and to manage the risks imposed by other activities on the network. Policy 10 is not limited to sensitive activities, and requires decision makers under the RMA, to the extent reasonably possible, to manage activities to avoid reverse sensitivity effects on the National Grid transmission network, and to 2696759 11 ensure that operation, maintenance, upgrading and development of the electricity transmission network is not compromised. This is why the word "and" is emphasised above. Managing reverse sensitivity is only one aspect of what is required through this policy. Effects of "non-sensitive" activities on the lines could include electrical hazards and security of supply risks, limitations on access for maintenance, and limitations on practical options available for maintenance, repair and upgrading of existing lines. 2.17 "Reverse sensitivity" (as a separate concept to direct effects) refers to the "effects" on an existing activity where a new sensitive activity locates (inappropriately) near the existing activity leading to the setting and imposition of restrictions on the existing, lawfully established activity. While this is mainly relevant to a "sensitive activity" in the sense that this term is used in the NPSET, I also note that even commercial operations may introduce an element of reverse sensitivity (e.g. occupants of commercial premises objecting against line upgrades etc.).14 2.18 Transpower's submission seeks to ensure that Policy 10 is given effect to in the Plan Change. It also seeks some additional controls for buildings and earthworks, and for activities that are not sensitive activities, which are different from the provisions included in the Plan Change as notified. For reasons I will outline later in my evidence, I consider that the changes proposed by Transpower give effect to Policy 10 of the NPSET. I note that in general terms the provisions proposed by Transpower in relation to non-sensitive activities are designed to avoid direct risk to the network (e.g. destabilising towers or creating electrical hazards), minimise safety risks to people and property in close proximity to transmission lines, ensure access to transmission lines and towers for maintenance, repair and upgrading is retained, and practical options for undertaking repair, maintenance and upgrading are not unnecessarily impeded. 2.19 A critical function that buffer corridor provisions provide is with respect to safety, as electricity transmitted at high voltage can cause serious harm or injuries to people who come close to lines. While the probability of a failure event is low, the risk of serious harm is high. Details of the risks to 14 I note also that the NPSET addresses reverse sensitivity effects in Policy 10, and separately addresses sensitive activities in Policy 11. 2696759 12 people and property are outlined in the evidence of Mr Noble.15 In particular, he records his concerns about the heightened risks of having container storage and mobile plant operating within the National Grid Yard of the HAM-WHU-A line, and his strong preference for those risks to be avoided or eliminated by reconfiguration of the inland port proposal (or the Applicants committing to undergrounding or relocating the relevant part of the line). Conclusions on the NPSET 2.20 As I will set out later in my evidence, Transpower's submission seeks some changes to the policy framework, definitions, buffer corridor rules and earthworks/subdivision provisions. Some of these changes are quite minor and are largely required to reflect changes in terminology, provide better consistency with provisions being sought in the Proposed Hamilton District Plan, or to address cross referencing to the relevant sections of the Hamilton District Plan. Other provisions represent more significant changes such as introducing non-complying activity status for buildings associated with non-sensitive activities within the National Grid Yard (which I refer to as 'underbuild'). 2.21 In respect of the logistics and freight handling activities in the Ruakura Logistics Zone, and particularly the container stacking and movement associated with a proposed rail siding, Transpower's preference is that these activities not be located beneath the HAM-WHU-A line (i.e. outside of the National Grid Yard) for the reasons set out in Mr Noble's evidence. I note that relocation of this activity away from this general location may be unrealistic as it aligns with the location within the Proposed Hamilton District Plan Structure Plan that has not been opposed by Transpower in submissions on that document. This may be a legal question to be addressed by Counsel for Transpower. Accordingly, if the Board is minded to approve such activities beneath the lines despite the concerns raised by Transpower, Transpower seeks that resource consent be required as a controlled activity for these activities within a National Grid Yard. It would not want to re-litigate the appropriateness of those activities through discretionary consent application. 15 Evidence of Roy Noble, paras 9.1 - 9.29. 2696759 13 2.22 Transpower also seeks new provisions for subdivision within the National Grid Corridor. These are simply intended to assist with the layout of development close to the lines, so that it can be sensibly configured, including the layout of roads across the National Grid. 2.23 In my opinion the overall package of measures included in the Plan Change as notified to protect National Grid transmission lines does not adequately give effect to relevant provisions of the NPSET in its current form. In particular, the Plan Change does not adequately provide for management of all development and activities that pose a risk to, or potentially compromise, the operation, maintenance, upgrading, and development of the electricity transmission network. I outline the particular concerns below, in light of which I consider the provisions of the Plan Change do not give effect to the NPSET as required under s 75(3) of the RMA. Regional Policy Statement and Proposed Regional Policy Statement 2.24 The inappropriate subdivision, use and development of land has been identified in the Waikato Regional Policy Statement ("WRPS") as a significant resource management issue for infrastructure as it can result in conflicts and incompatibilities between activities. This may significantly compromise the operation of regionally significant infrastructure.16 2.25 To address this issue, the objective seeks to ensure that the continued operation of regionally significant infrastructure is maintained or enhanced. Policy 1 of this objective is: Avoidance of significant adverse effects (including cumulative effects) on the safe and efficient operation of regionally significant infrastructure. Where significant adverse effects on regionally infrastructure cannot be avoided they shall be remedied or mitigated. 2.26 Therefore, it is appropriate to include buffer corridor mechanisms within the Plan Change to give effect to the WRPS. Further, the mechanisms proposed by Transpower, particularly in regard to non-sensitive activities, will mitigate the adverse effects of urban development adjacent to and beneath existing Transpower transmission lines. 16 WRPS 3.13 Structures (Infrastructure): Issue. 2696759 14 2.27 The Board must also "have regard to" the Proposed Waikato Regional Policy Statement 2010 ("PWRPS").17 While this document is not yet operative, decisions have been released, and although there are still some outstanding appeals, in my view significant weight should now be given to it. It includes a more comprehensive package of objectives and policies in regard to urban development and infrastructure compared to the WRPS. 2.28 Policy 6.3 of the PWRPS addresses coordinating growth and infrastructure. In particular, this policy seeks that management of the built environment (among other things) ensures that: (a) The nature, timing and sequencing of new development is coordinated with the development, finding, implementation and operation of transport and other infrastructure, in order to: (i) Optimise the efficient and affordable provision of both the development and the infrastructure; (ii) Maintain or enhance the operational effectiveness, viability and safety of existing and planned infrastructure; (iii) Protect investment in existing infrastructure; and (iv) Ensure new development does not occur until provision for appropriate infrastructure is in place. [my emphasis] 2.29 Further, the policy seeks to ensure the efficient and effective functioning of infrastructure is maintained, and the ability to maintain and upgrade that infrastructure is retained. Therefore, in addition to managing reverse sensitivity issues, this policy clearly supports Transpower's approach to keeping the National Grid yard largely clear of buildings to ensure maintenance access is retained, and the risk of direct effects is reduced. 2.30 Policy 6.6 addresses significant infrastructure and energy resources. Of note, the policy states: 17 RMA, s 74(2)(a)(i). 2696759 15 (a) Management of the built environment ensures that the effectiveness and efficiency of existing and planned regionally significant infrastructure is protected. 2.31 Included in the specific implementation methods for this policy is the specific promotion of the development of a transmission corridor management approach. 2.32 Accordingly, both the WRPS and PWRPS promote the use of measures to protect significant infrastructure, with the PWRPS more explicitly promoting the use of a transmission corridor approach to protect transmission lines. While the Plan Change already has a buffer corridor approach to manage reverse sensitivity from sensitive activities, the package of provisions proposed by Transpower provides better alignment with regional policy imperatives in terms of providing better protection to the safe and efficient operation of the transmission network in relation to higher risk activities such as use of mobile plant National Grid Yard, and managing underbuild in terms of both increased risk to the transmission network and providing more constraints on the operation and maintenance of the transmission network. Accordingly, in my opinion the package of measures proposed in the Plan Change does not adequately give effect to the WRPS or have sufficient regard to the PWRPS in relation to measures to protect the safe and efficient operation of National Grid transmission lines. In my view the Transpower approach is generally a better planning solution (I comment further on the particular changes sought by Transpower below). 2.33 Relevant extracts from the WRPS and PWRPS are included in Attachment B. Relevance of the NZECP34: Why it does not provide sufficient protection 2.34 The NZECP34 is a mandatory code of practice that sets minimum safe distances from transmission lines to protect persons, property, vehicles and mobile plant from harm or damage from electrical hazards. The NZECP34 establishes clearance distances to buildings, structures and mobile plant, the ground, and other lines, as well as how close buildings, structures and excavations can occur in relation to poles and towers. 2696759 16 2.35 The NZECP34 sits outside of the RMA regime and must be complied with in addition to any RMA controls. Therefore, at face value it may appear to be unnecessary to include additional controls on buildings and structures (that are not sensitive activities). 2.36 However, it is important to note that the NZECP34 is focussed only on minimum standards for safety. This narrower focus means the NZECP34 cannot and is not intended to achieve the broader policy objectives sought by the NPSET, nor can it meet the wider sustainable management purpose of the RMA. Therefore, in the context of these proceedings, it does not include a regime to manage development (including avoiding sensitive development) underneath or in close proximity to transmission lines that could compromise the operation and maintenance of the network, or provide any guidance for decision making on subdivision that may enable the establishment of such development. It also does not address providing access to transmission lines and support structures for maintenance purposes. 2.37 A number of practical examples illustrating where allowing either buildings or mobile yard type activities to be undertaken under transmission lines, and the issues encountered, are set out in the evidence of Mr Noble. I understand that once a building is constructed under transmission lines in accordance with the NZECP34, there a number of risks to the network (and the safety of others) in terms of the erection of ancillary structures such as aerials on building roofs, roof maintenance works including temporary scaffolds etc, which make location of buildings underneath transmission lines undesirable. As outlined in the evidence of Mr Noble, I understand that these types of infringement do not tend to be actively enforced by the Ministry of Business, Innovation and Employment who have been tasked with enforcing the NZECP34. I understand similar issues are encountered with earthworks not being undertaken in compliance with NZECP34. Accordingly, given the safety issue involved, I support a suitable RMA regime to better manage these risks. 2696759 17 3. TRANSPOWER'S APPROACH TO CORRIDOR MANAGEMENT The issues 3.1 Policies 10 and 11 of the NPSET do not set out actual specific controls to be included in district plans. Accordingly, Transpower has developed a corridor management approach that it promotes to local authorities for inclusion in district plans to provide for a degree of consistency nationally. The preferred corridor provisions continue to be refined as the NPSET beds in and relevant issues are worked through in district plan reviews and plan change processes. Accordingly, the exact provisions sought for this Plan Change have been further refined from those initially sought on the Proposed Hamilton District Plan. 3.2 Where urban land use changes occur adjacent to and under transmission lines, industrial type activities and open space zones are generally preferred by Transpower to more sensitive land uses such as residential zones. However, I understand that even some industrial type land uses can present a risk to the operation of existing transmission lines. The Ruakura Logistics Zone in particular will provide for stacking of containers and mobile plant to move these containers around. As set out in the evidence of Mr Noble18 this activity in particular presents a risk to the transmission lines and safety of people operating mobile equipment as evidenced by previous experience with operation of the inland port in Onehunga, Auckland. 3.3 From my own observations of the Plan Change area, the lines on some spans come quite close to the ground. Accordingly, there appears to me to be an obvious risk for use of mobile plant and stacking of containers in these areas without suitable management of these activities. As general relief in its submission, Transpower has sought that consideration be given to alternative locations for sites and activities (such as those proposed for the Ruakura Logistics Zone) which may compromise the operation, maintenance and upgrading of transmission lines. In his evidence Mr Noble is of the view that the proposed container storage and freight handling activities in particular that would be enabled by the Plan Change should not occur at all under the transmission lines (with 18 Evidence of Roy Noble, paras 17.3 - 17.4. 2696759 18 particular concern expressed at concept plans19 in the Applicants' evidence showing container stacking and management areas under and adjacent to the HAM-WHU-A line), and that this activity would be better relocated to another part of the site. 3.4 I agree with Mr Noble that, ideally, there would be no high risk activities such as container storage and movement by mobile plant directly under the transmission lines. However, I accept that this aligns with where the inland port activity is shown in the Proposed Hamilton District Plan Structure Plan, and its location is not opposed by Transpower as part of that process. Therefore, a complete relocation is perhaps unrealistic. Again, this may be a legal question to be addressed by Counsel for Transpower. At present, the Applicants have provided no substantive evidence responding to the Transpower submission, so it is unclear how much flexibility they do have to rearrange their preferred layout. The Board will need to consider the extent to which this aspect of the preferred relief sought by Transpower would be disenabling of the port activities, and weigh that against ensuring the health and safety of people around the lines. I am not in a position to be able to comment on how practical it would be to configure the site to avoid the need to stack and move containers associated with an inland port within a National Grid Yard. The potential impact could be substantial on the Applicants' development concept of the area. However, I also understand that from a practical perspective, substantive container stacking as shown in the Applicants' concept plans under the HAM-WHU-A line may not be feasible in any case due to the practical limitations of the NZECP34, which in practice may necessitate undergrounding or moving the line to accommodate this activity if it were required to be undertaken in this location. 3.5 Transpower has also sought new provisions in its submission that would require consent as a controlled activity for certain logistics and freight handling activities located within a National Grid Yard. I understand Transpower's position is that this is a 'fall back' position should the Board be of a mind to allow these activities within National Grid Yards. During my initial involvement in this process I was of the understanding that this position was an acceptable outcome to Transpower. However, more recently Transpower has formed the view, as expressed in Mr Noble's evidence, that the risks are such that it should not be located under the 19 See evidence in chief of John Goodwin, appendix 3, page 3. 2696759 19 lines. In my view, should freight handling activities not be able to be located to completely avoid National Grid Yards, then it would be reasonable to limit these particular controlled activity controls to the Ruakura Logistics Zone only, given the higher risk profile of activities in the Ruakura Logistics Zone compared to other business/industrial areas (e.g. moving containers around with mobile equipment) and their ongoing nature. 3.6 Based on Mr Noble's evidence, my understanding of the principal reasons for the corridor approach being sought by Transpower is as follows: (a) Safety risks (primarily risk of electric shock); (b) Impacts on security of supply due to the increased risk of third parties contacting the lines causing outages; (c) Threatened security of supply (power outages) due to Transpower's access to the lines being blocked or restricted and/or Transpower not being able to maintain, upgrade or develop lines as required; (d) Activities that are sensitive to transmission lines locating near to them (such as dwellings and schools); (e) Risks from activities locating close to lines and then asking for their operation to be constrained in some way (reverse sensitivity); and (f) Risks to the infrastructure corridors and Transpower's options for maintaining, upgrading and development of the lines. 3.7 Mr Noble's evidence outlines Transpower's general corridor management approach. This approach differs between existing urban areas, and proposed new urban areas.20 For proposed urban areas that are currently rural, Transpower is seeking a more restrictive planning regime compared with existing urban areas where there are less options available to make reasonable use of land affected by transmission corridors. For example, I understand that Transpower has been pursuing non-complying activity status for buildings that are non-sensitive activities in greenfields areas 20 Evidence of Roy Noble, para 18.35. 2696759 20 being changed to an urban land use, but has pursued a less restrictive activity status in existing urban areas (subject to complying with the NZECP34) as the lines are already compromised in urban areas that are built up, and land owners have fewer options available to avoid development under lines. I consider this distinction to be appropriate. 4. EVALUATION OF THE RELIEF SOUGHT BY TRANSPOWER 4.1 In this section I consider the relief sought by Transpower, including its appropriateness with regard to the statutory requirements and relevant planning documents. I consider in particular the relief Transpower is seeking in terms of non-complying activities within the National Grid Yards, the controlled activity consents for logistics and freight handling facilities, subdivision within National Grid Corridors, and earthworks. 4.2 The Plan Change seeks to bring rural land into an urban use, with a mix of land uses ranging from intensive residential land use through to industrial land use. In that context Transpower in its submission on the Plan Change has taken the view that it is appropriate to take a proactive approach to ensure (in broad terms) that: (a) The terminology is amended to provide definitions for National Grid Yard and National Grid Corridor, to provide consistency with its national position on these matters. Current terms used in the Plan Change are Electricity Transmission Yard and Electricity Transmission Corridor. (b) Within the National Grid Yard (which is generally 12m either side of the centreline, but reduced to 10m from the centreline of a 110kV National Grid line on single poles): New buildings21 and sensitive activities do not generally locate within the corridor, by requiring them to obtain non-complying activity consents. Some small buildings22 are provided for as exceptions. The Plan Change as lodged provided for new buildings and additions for sensitive land uses within this corridor as a non-complying activity, but this did not apply to buildings in general (i.e. buildings for non-sensitive activities) other than where they would 21 22 There are limited or no existing buildings under or near Transpower's existing lines. 2 Above 2.5m high or 10m in area. 2696759 21 be within 12m of an existing National Grid support structure. In my view it would also be reasonable to allow for other small scale structures such as fences, lighting poles or traffic management structures as exceptions to the non-complying rule, subject to them meeting the electrical safety distances in the NZECP34. (c) As noted in Mr Noble's evidence, Transpower's first preference is to avoid logistics and freight handling related activities involving mobile plant and container stacking within a National Grid Yard. However, should the Board allow for these activities, despite the concerns raised by Transpower, then these activities will require consent as a controlled activity under the changes proposed by Transpower. That will enable Transpower to participate and have input into how those activities may be managed to minimise safety issues (but not reopen the debate about whether the activities are appropriate at all in that location). This provision was not included in the Plan Change as notified. As previously outlined, I would support this provision being limited to the Ruakura Logistics Zone only. (d) Within the wider National Grid Corridor (14m from the centreline for single pole 110kV lines,23 16m from the centreline for 110kV pi-pole lines,24 2m for 110kV lines on towers and 37m for 220kV lines), activities can generally be permitted25 but subdivision26 will require restricted discretionary consent, so as to better ensure a pattern of development that avoids adverse effects on the transmission lines such as reliance on building platforms within a National Grid Yard. A set of assessment criteria for subdivision to guide decision making on such applications is proposed. This was not included in the Plan Change as notified, but is generally aligned with the subdivision rules approach within National Grid Corridors, and the associated assessment criteria, being sought by Transpower in its submission on the Proposed Hamilton District Plan. 23 24 25 26 Transpower's submission on the Plan Change refers to 16m in respect of pi-poles, but following a close site visit, it has established that there are only single poles on site. As such, a lesser distance of 14m is appropriate. There are no pi-poles within the Plan Change Area. Subject to the requirements of NZECP34, which may be unlikely to be triggered at these distances, in any event. The likely precursor to any intensive development. 2696759 22 (e) Within the National Grid Corridor any buildings not complying with the safe clearance distances in the NZECP34 are noncomplying activities. The Plan Change as lodged only applied this to the narrower National Grid Yard. (f) For earthworks within 20m of the lines, or earthworks not complying with the permitted standards in the NZECP34, restricted discretionary activity consents will be required. The existing Rural Zone provisions in the Waikato Section of the Hamilton District Plan include an existing rule for earthworks within 20m of transmission lines. In this regard, the submission simply seeks a cross reference back to this existing provision to ensure the link to that rule is not lost. (g) Improved clarity is provided for network utilities within the National Grid Yard and Corridor, the amendments proposed confirm that the provisions of the network utilities rules in the Hamilton Section of the Hamilton District Plan apply (as opposed to the rules for buildings and structures in Table 25H.13). (h) A general non-complying activity default rule is added for any building or structure within the National Grid Yard not otherwise provided for in Table 25H.13 for improved clarity. (i) Transpower is clearly identified as an affected party where resource consents are required within the National Grid Yard or Corridor (in terms of the National Grid Yard and Corridor rules). 4.3 The above outcomes (sought in the various rules/tables included with Transpower's submission on the Plan Change), are to be supported by amendments to existing Objective 25H.4.16 and supporting policies. In my opinion, particularly given the limited controls sought within the wider National Grid Corridor (primarily focused on subdivision), Transpower is taking a reasonable and highly supportable approach. 4.4 I now discuss in more detail matters where there is variance in the Transpower position from the Plan Change as notified. 2696759 23 Objective 25H.4.16 and Policies 4.5 The Plan Change includes a specific set of objectives and policies for the Plan Change area. Of most direct relevance to Transpower is Objective 25H.4.16 and two supporting policies 25H.4.16a and 25H.4.16b, that address network utilities generally and transmission corridors specifically. The objective is relatively broad and relates to the importance of network utilities to support the development and functioning of Hamilton, while the two policies are specific to subdivision, use and development, and sensitive land uses, in relation to the electricity transmission network. Minor amendments to these proposed provisions have been sought by Transpower. In my opinion these provisions are consistent with the corridor provisions being sought by Transpower. 4.6 In my view the amendments sought improve upon the relevant objective and supporting policies in that they: (a) ensure there is a clear direction for the Plan Change rules and methods to include mechanisms to provide for network utilities (including transmission assets); (b) use revised terminology to provide consistency with other relief sought by Transpower; and (c) provide better consistency with wording on policy provisions either notified in or being sought in submissions by Transpower on the Proposed Hamilton District Plan. 4.7 Transpower has also sought two other policies for network utilities (which were included in the notified version of the Proposed Hamilton District Plan with the same or very similar wording), in order to further assist with giving effect to Policies 10 and 11 of the NPSET. These are: (a) A new policy 25H.4.16c which seeks recognition of the positive effects and importance of network utilities to the Waikato Region and Hamilton, and the national benefits of National Grid infrastructure; and (b) A new Policy 25H.4.16d, that states: "reverse sensitivity effects on network utilities shall be avoided". While this wording is identical to the wording of the equivalent policy in the Proposed 2696759 24 Hamilton District Plan,27 I consider complete avoidance of an adverse effect is a difficult test to meet. Because Policy 10 of the NPSET requires decision makers to manage activities to "avoid" adverse reverse sensitivity effects on the electricity transmission network to the extent reasonably possible, I support similar amendments to this policy to provide better alignment with Policy 10 of the NPSET. 4.8 In my opinion, with the exception noted in regard to requested policy 25H.4.16d, the amendments sought by Transpower are consistent with Policies 10 and 11 of the NPSET, and would be helpful in assisting the Council in assessing future resource consent applications affecting the transmission corridors. Terminology and Definitions 4.9 Transpower is seeking changes in the terminology and definitions used in the Plan Change, to provide consistency both with its national position and its position on the Proposed Hamilton District Plan. The definitions sought generally align with those included in the Plan Change for the "Electricity Transmission Yard" and "Electricity Transmission Corridor", although an explanatory diagram is now proposed, and a reduced corridor width is proposed for 110kV lines on single poles. Transpower also has a preference for the wording National Grid Yard and National Grid Corridor, given the terms focus on the National Grid lines rather than local distribution lines. 4.10 I note that the definition sought for the National Grid Corridor only provides a corridor width for pi poles28 (i.e. "double poles"), whereas there are only single poles located within the plan change area. This was an oversight, and the definitions should also include a corridor width for single poles. The correct corridor width for a single pole is 14m from the centre line of the National Grid Transmission Line (being 2m less than the distance indicated in the submission). Similarly the National Grid Yard width for 110kV lines on single poles should be reduced to 10m from the centre line of the transmission line (although retained at 12m from the support structure). 27 28 Policy 25.7.2.1f. 16m from centreline for pi-poles. 2696759 25 4.11 I also note that in some instances outside of the Plan Change area, Transpower has replaced steel lattice towers with large tubular steel towers. These could technically be considered single poles, but functionally are delivering the equivalent function of a lattice steel tower. I have suggested a minor amendment to the definition of National Grid Corridor (see Attachment A) to ensure these large tubular steel towers (when used to replace existing towers) are treated in the same manner as a lattice tower, and not in the same manner as the much smaller scale single poles. 4.12 Transpower proposes a change in terminology from Sensitive Land Use to Sensitive Activity to align with the terminology used in the NPSET. Further, as the definition of Sensitive Activity in the NPSET is not exclusive, a specific definition is proposed to provide clear guidance on what specific activities are caught by the relevant rules and policy provisions. In my view it is appropriate to use equivalent terminology to the NPSET but provide a more detailed definition so it is clear when the relevant district plan provisions are triggered. Non-Complying Activities within National Grid Yards 4.13 In many respects, Transpower's requested rules within National Grid Yards and Corridors are aligned with the Plan Change provisions as notified. However, one significant difference is Transpower's proposed rule that would result in buildings (that are not part of a Sensitive Activity) located within a National Grid Yard being a non-complying activity. I understand that the applicant prefers the ability to undertake "underbuild" where this is not for a Sensitive Activity, if following an assessment under the NZECP34 it can be shown to meet the required safety separation distances. 4.14 I have outlined above why I do not consider it appropriate to solely rely on the provisions of NZECP34 to manage underbuild. Non-complying activity status supported by suitable policies provides the best means, in my view, of protecting the National Grid Yard, by clearly signalling that such activities are generally not provided for. Therefore, it will both discourage applications for incompatible activities in the first place (and thus reduce the need to commit significant resources to defend Transpower's position on National Grid Yards), while also ensuring there is a low probability of incompatible development being granted consent. 2696759 26 4.15 The Ministry for the Environment's National Policy Statement on Electricity Transmission, Implementation Guidance for Local Authorities (2010) ("Implementation Guidance") notes that Policy 10 requires the Council to manage third party activities that are sensitive to the effects of the electricity transmission, as well as third party activities that would compromise the operation, upgrading and development of the electricity transmission network.29 This is consistent with my reading of Policy 10, as I explain above. Accordingly, in my opinion it is appropriate for the district plan to control the activities of third parties, other than a Sensitive Activity where these may result direct effects on transmission lines that may inhibit the operation, maintenance and upgrading of the network. The Implementation Guidance30 also notes that it may not be reasonable 4.16 or practicable to avoid all adverse effects, both because of the operational and technical constraints of Transpower, and also because of the potential impositions on property owners that controls would have on the use of their land. On this basis, Transpower has adopted a different approach for considering buildings and structures in existing urban areas, and those where the land is currently rural and proposed for urban development. 4.17 In my opinion, this approach strikes an appropriate balance by protecting the National Grid transmission lines and avoiding adverse reverse sensitivity effects to the extent that is reasonably possible. In the case of the Ruakura Plan Change area, the applicant has selected the area for which rezoning is requested with full knowledge of the existence of transmission lines that currently cross rural land. Currently that land has a much lower risk profile in terms of reverse sensitivity effects and effects on the operation, maintenance, upgrading and development of these lines compared with urban land. 4.18 Further, the Applicants have various options they could consider to avoid underbuild occurring within the transmission corridor, which may include: (a) Designing the development at the master planning and/or subdivision phase so that car parking, reserves or roads are placed within the National Grid Yard, rather than buildings. 29 30 Implementation Guidance, at 3.4. National Policy Statement on Electricity Transmission: Implementation Guidance for Local Authorities, Ministry for the Environment, 2010. 2696759 27 (b) Fund the relocation or undergrounding of the existing transmission lines. Such solutions have been implemented at Westgate/Massey North Town Centre (underground) and Highbrook Business Park (part relocation on tubular steel towers and part undergrounding) in Auckland, and undergrounding beneath Barrington Road in a subdivision to the immediate north of the Plan Change area which I understand is called Somerset Heights (see Attachment C). I also understand that the applicant is in discussions with Transpower to underground or relocate the existing transmission lines that traverse the proposed residential zoned land in the northern part of the Plan Change area (area adjoining and to the immediate south of Greenhill Road). 4.19 For these reasons, in my opinion, it is appropriate for buildings, including those not associated with a Sensitive Activity, to be classed as noncomplying activities in the Plan Change where they are located within the National Grid Yard (as sought in Transpower's submission). However, I would also support providing for some small scale buildings and structures as exceptions to the non-complying activity rule where they comply with the electrical safety distances of the NZECP34 as previously outlined. This could also include, for example, fencing, lighting and traffic management barriers (including as required to manage activities under the lines). Controlled Activity Consents for Logistics and Freight Handling Facilities 4.20 As outlined in the evidence of Mr Noble, there have been instances at the inland port at Onehunga in Auckland (known as Metroport) where mobile plant associated with moving containers have come into contact with Transpower lines. While the NZECP34 does include required clearance distances for mobile plant from lines, this relies on the site operators following good management practices. Past experience at Onehunga demonstrates that incidents can occur. Therefore, it would appear that this particular activity is a less than ideal land use within a National Grid Yard. 4.21 The proposed Ruakura Logistics Zone in particular will enable similar activities to those undertaken at Metroport. From my own observations of 2696759 28 the Plan Change area, some of the line spans come very close to the ground, which at face value will limit both the practicality of placing large buildings and stacks of containers within the National Grid Yard in any case, but also result in some risks from the operation of mobile plant crossing under lines if not appropriately managed. The consequences of damage to lines crossing the Ruakura Logistics Zone are addressed in Mr Noble's evidence31. 4.22 While Transpower prefers avoidance of this particular activity within a National Grid Yard, if the Board does not consider this to be appropriate (despite Mr Noble's concerns about safety and the risk of damage to infrastructure), the rule proposed in the submission would result in logistics and freight handling activities that involve the operation of cranes, straddle carriers, forklifts and other such equipment requiring resource consent as a controlled activity within a National Grid Yard. Requiring a controlled activity consent would not stop these general activities being able to establish within National Grid Yards (if the Board has already found that the benefits outweigh the risks), but will put in place a regime to assist in better managing these areas in site layout and operation. Ancillary buildings other than storage containers (such as the site offices or warehousing) would not be covered by this controlled activity rule, so would fall to be assessed in accordance with the rules for buildings in the National Grid Yard. The matters for control sought in Transpower's submission include: (a) Access or crossing points, including where crossing should be avoided; (b) Signage; (c) Any management processes or procedures to ensure safe and efficient operations; and (d) Location and duration of storage of containers, including provision for their movement, should access by Transpower to the National Grid Yard be required. 4.23 In my opinion, while I accept Transpower's first preference would be to avoid these activities locating within National Grid Yards, if this is not 31 Evidence of Roy Noble, paras 18.6 - 18.35. 2696759 29 found to be a practical outcome while still delivering the strategic inland port activity and/or aligning with the structure plan within the Proposed Hamilton District Plan, then the above measures are in my view an appropriate mechanism for implementing the relevant objective and policy framework in the Plan Change for protecting the National Grid Transmission Lines, while not unnecessarily inhibiting the reasonable use of the land. I note that the specific matters on which conditions may be imposed would benefit from more direction around the ability to impose conditions to implement physical measures such as vehicle barriers and 'overhead gates' to directly control the location of vehicle crossing points and the practical height of mobile plant and containers where crossing under lines. Subdivision within National Grid Corridors 4.24 Transpower is seeking new restricted discretionary activity subdivision rules where subdivision is undertaken within the National Grid Corridor. This generally provides for subdivision as a restricted discretionary activity, but also as a non-complying activity where a practical building platform cannot be provided outside of the National Grid Yard. The noncomplying activity rule is designed to avoid creating new lots where a subsequent building would be a non-complying activity under the proposed rules for buildings in National Grid Yard. 4.25 Section 25H.14 of the Plan Change sets out the rules from the operative Hamilton City Plan which will also apply to Ruakura. This includes a cross reference to existing rules applying to subdivision and development. The subdivision rules cross referenced do not include any specific subdivision provisions in relation to subdivision within National Grid Corridors. In my opinion, this is inconsistent with Policy 25H.4.16a of the Plan Change. 4.26 In regard to the restricted discretionary activity status that is sought for subdivisions, new matters of discretion are proposed, based on what Transpower has sought elsewhere. In general terms, these criteria require consideration of the following: (a) The extent to which the subdivision design including the location of roads, reserves, landscaping and building platforms allows for activities to be set back from National Grid transmission lines. 2696759 30 (b) The extent to which subdivision design and layout and consequential development will minimise the potential for reverse sensitivity effects. (c) Provision for contained reasonable access by Transpower to its lines. (d) The extent to which the design and development will minimise risk of injury and property damage from lines. (e) Compliance with the NZECP34 (noting that excavation and/or raised ground levels can also be an issue requiring consideration). (f) 4.27 Outcomes of consultation with Transpower. The intent of these provisions is to ensure that any subdivision proposals within the National Grid Corridor are appropriately assessed, including whether there is a suitable building platform provided outside of the National Grid Yard, whether earthworks will affect support structure stability or ground clearance distances under the NZECP34, whether Transpower will retain reasonable access to its infrastructure, and the likely location of any trees etc. In my view, ensuring such matters are assessed at the subdivision stage is a sensible and appropriate method for ensuring compatibility between land development and existing National Grid electricity transmission infrastructure, and gives effect to Policy 10 of the NPSET. Earthworks 4.28 Section 25H.14 of the Plan Change sets out rules from the operative Hamilton City Plan which also apply to Ruakura. This includes a cross reference to Rule 6.7 Earthworks and Site Development. Those rules do not include specific controls for earthworks near National Grid Transmission Lines. However, Rule 25.23.1(ba) of the Hamilton District Plan: Waikato Section (Rural Zone) does include a rule requiring consent as a restricted discretionary activity for earthworks within 20m of the centreline of electricity transmission lines with a voltage of 110kV or more where the activity generates adverse effects of dust on the transmission line, or raises the ground level. 2696759 31 4.29 To address the potential for earthworks to undermine the stability of transmission line support structures or reduce safe ground clearance levels, Transpower's submission sought both a reinstatement of the linkage to Rule 25.23.1(ba), and that any earthworks not complying with the permitted standards of the NZECP34 also become a restricted discretionary activity, with matters of discretion limited to the effects of the earthworks on the operation, maintenance, upgrading and development of the National Grid transmission network. A summary of the relevant standards in the NZECP34 where the written consent of the pole/tower owner is required for earthworks are as follows: (a) For poles and any stay wires (section 2.2.1 of the NZECP34) (i) is at a greater depth than 300mm within 2.2m of the pole or stay wire; or (ii) is at a greater depth than 750mm between 2.2m and 5m of the pole or stay wire; or (iii) creates an unstable batter. Note: the above standards for work around poles do not apply to vertical holes, not exceeding 500mm in diameter, beyond 1.5m from a pole or stay wire (section 2.2.2 of the NZECP34). (b) For Towers (section 2.2.3 of the NZECP34): (i) is at a greater depth than 300mm within 6m of the outer edge of the visible foundation of the tower; or (ii) is at a greater depth that 3m between 6m and 12m of the outer edge of the visible foundation of the tower; or (iii) creates an unstable batter. Note: the above standards for work around poles and towers do not apply to normal agricultural cultivation, or the repair, sealing or resealing of the existing surface of any road, footpath, or driveway (section 2.2.4 of the NZECP34). (c) No material shall be deposited under or near an overhead electric line so as to reduce the conductor distance to ground to 2696759 32 less than the distances required by Table 4 of the Code (section 4.3.1 and Table 4 of the NZECP34). As outlined in the evidence of Mr Noble,32 in the absence of RMA 4.30 controls, compliance with the earthworks provisions of the NZECP34 have often not been enforced by the Ministry of Business, Innovation and Employment. Accordingly, in my view it is appropriate to impose an earthworks rule based on the NZECP34 permitted activity standards as set out above. I note that should a rule linked to compliance with the permitted earthworks provisions of the NZECP34 be implemented, the cross reference back to the former rule in the Waikato Section of the Hamilton District Plan would become unnecessary as a sufficient level of control around earthworks near transmission lines and support structures would be provided. 4.31 In my view, restricted discretionary activity status is appropriate, as it allows for necessary earthworks to occur where it is demonstrated that they will not undermine transmission line support structures, result in outcomes where it is no longer practical to access support structures, or reduce ground level clearances under transmission lines to unsafe levels. I note that earthworks that in any case would comply with the NZECP34 will also not require resource consent under the proposed provisions. For better certainty for plan users, the detailed earthworks controls as outlined above could be included directly in the Plan Change as opposed to a more general requirement to comply with the earthworks control set out in the NZECP34. That is the approach that has been taken in Transpower's submission on the Proposed Hamilton District Plan. Affected Party Status for Transpower 4.32 Transpower's submission requests that it be identified as an affected party from whom written consent would be required for a restricted discretionary activity subdivision, or any land use consent required under Table 25H.13, to proceed without notification. 4.33 The rules relating to National Grid Yards and Corridors are designed to protect the National Grid transmission line assets owned and operated by Transpower. Accordingly, in my opinion it is completely appropriate for Transpower to have an input into any resource consent applications 32 Evidence of Roy Noble, paras 19.15. 2696759 33 where the need for consent is triggered due to the rules designed to protect these assets. On this basis, I support rules that require Transpower to be specifically identified as and affected party for any applications triggering National Grid Yard and National Grid Corridor related rules to be considered on a non-notified basis, and to be served as an affected party for any application where limited notification is required. Costs and benefits 4.34 In considering the specific provisions sought by Transpower, it is also important to consider the costs and benefits. As with any regulation, there will be benefits and costs associated with the different options for the suite of proposed plan provisions. In this part of my evidence, I refer to broader benefits and costs in a planning sense, relying on the evidence of Mr Copeland which concludes that the benefits of the corridor management approach outweigh local costs. 4.35 Specific economic benefits to Transpower, landowners and electricity consumers include: (a) reduced costs for inspection, operation, maintenance, replacement and upgrading of the National Grid; (b) reduced electricity supply outages; (c) improved safety to person and property; (d) less disruption to the port and other business operations when Transpower is required to undertake work on the National Grid; and (e) 4.36 lower electricity line charges for electricity consumers. In my opinion, the current Plan Change provisions do not effectively ensure these benefits are realised as they rely on an incomplete policy and rules framework, and in regard to underbuild and earthworks inappropriately rely on an external code of practice (NZECP34). Part 2 Considerations 4.37 The Purpose of the RMA as set out in s 5 is to promote the sustainable management of natural and physical resources. 2696759 In my opinion, the 34 proposed suite of amendments sought by Transpower promotes sustainable management in that it provides for an appropriate level of protection for an existing infrastructure network that is of national significance, sustains the potential of nationally significant physical resources to meet the reasonably foreseeable needs of future generations, and enables the broader community to provide for its social, economic and cultural well-being, and health and safety, without unreasonably inhibiting the reasonable use of compatible activities on adjacent land. 4.38 While it may be argued there is some localised cost to the developer of the land due to the corridor provisions proposed, based on the evidence of Mr Copeland it is my view that this would outweighed by the benefits to the wider community. 4.39 In terms of s 5(2)(c) the use of buffer corridors to assist with the management of reverse sensitivity will in my view provide the best opportunity for Transpower to avoid, remedy or mitigate the adverse effects on other parties of operating its existing transmission lines. 4.40 I do not consider any matters in ss 6 or 8 of the RMA to be directly relevant to Transpower's submission. In terms of s 7, Other Matters, s 7(b) requires the Board to have regard to the efficient use and development of natural and physical resources. The National Grid transmission lines are a significant physical resource identified in the NPSET as being of national significance. Transpower's proposed provisions in my view ensure the effects of third party activities are adequately managed so as to not compromise the operation, maintenance, upgrading and development of the electricity transmission network. 4.41 Overall, I consider the suite of provisions proposed by Transpower to be consistent with Part 2 of the RMA. 5. CONCLUSIONS 5.1 The Plan Change includes a number of provisions, including an objective and related policies, and buffer corridor provisions within the Plan Change methods, which provide a measure of protection the National Grid transmission lines. While these are generally appropriate in regard to the 2696759 35 location of Sensitive Activities, in my view the overall package of measures in the Plan Change does not in its present form adequately give effect to the NPSET. 5.2 The applicant has undertaken a relatively comprehensive s 32 evaluation of the various options considered. However, I have concluded that the amendments generally as sought by will provide a better overall outcome in terms of assisting the Hamilton City Council in undertaking its functions so as to achieve the purpose of the RMA, giving effect to the NPSET and RPS, including objectives that are the most appropriate way to achieve the purpose of the RMA, and including policies and methods which are the most appropriate way of achieving the objectives. 5.3 I generally support the provisions proposed by Transpower in its submission, with the amendments outlined in my evidence, as included in Attachment A. Christopher Horne 26 March 2014 2696759 Attachment A Plan Change provisions with mark ups 2696759 Additional changes from submission shown in highlight Tracked Changes to Table 25H.13 25H.13 Works within Transmission National Grid Corridors National Grid transmission lines are identified on the planning map. These rules relates to the transmission National Grid yard and wider transmission National Grid corridors associated with these lines. Activities not otherwise included in this table are assessed in accordance with the relevant zone provisions. In respect of logistics and freight handling activities within the National Grid Yard, item (g) in the table below represents Transpower's alternative or secondary relief. Transpower's primary relief sought is that the proposed inland port activities be configured so that logistics and freight handling activities involving the use of mobile plant are located outside the National Grid Yard. a) New buildings or additions to the building envelope of existing buildings for a sensitive land use activity b) Maintenance, repair and internal alterations to existing buildings that do not result in the alteration of the building envelope and/or an increase in floor space for a sensitive land use activity. c) Changes of activity to a sensitive land use activity. d) Any buildings within 12m of the outer visible edge of a transmission National Grid support structure. e) Any building within the Electricity Transmission Yard National Grid Corridor, that does not comply with the safe clearance distances specified in NZECP34:2001 f) Mobile Machinery and equipment g) Any activity or building that is not otherwise mentioned in any section of this table f)Any new building or structure less than 2.5m 2 high and 10m in area, and any fencing, lighting and traffic management barriers (including as required to manage activities under the lines), subject to compliance with NZECP 34:2001. g) Within the Ruakura Logistics Zone, logistics Within Greenfield Electricity Transmission National Grid Yard NC Within Greenfield Electricity Transmission National Grid Corridor P P P NC P NC NC NC NC P P P P P P C P and freight-handling activities that involve the operation of cranes, straddle carriers, forklifts, or other such equipment, but excluding associated buildings and structures other than storage containers. h) Any building or structure within the National Grid Yard other than provided for in a) to g) above i) Network utilities j) Earthworks NC NA Refer to [insert cross reference to Rule 3.3 Roads and Network Utilities rules in Hamilton District Plan] [delete text in red] Refer to Rule 25.23.1 (ba) of Hamilton District Plan: Waikato Section (Rural Zone). In addition to Rule 25.23.1 (ba), all earthworks within a National Grid Corridor or Yard that do not comply with the permitted standards of NZECP34:2001 are a Restricted Discretionary Activity. All earthworks within a National Grid Yard or National Grid corridor that do not comply with the following earthworks standards are a Restricted Discretionary Activity. For National Grid poles and any stay wires: o is at a greater depth than 300mm within 2.2m of the pole or stay wire; or o is at a greater depth than 750mm between 2.2m and 5m of the pole or stay wire; or o creates an unstable batter. Note: the above standards for work around poles do not apply to vertical holes, not exceeding 500mm in diameter, beyond 1.5m from a pole or stay wire (section 2.2.2 of the NZECP). For National Grid Towers (steel lattice towers or any replacement tubular steel tower): o is at a greater depth than 300mm within 6m of the outer edge of the visible foundation of the tower; or o is at a greater depth that 3m between 6m and 12m of the outer edge of the visible foundation of the tower; or 2 o creates an unstable batter. Note: the above standards for work around poles and towers do not apply to normal agricultural cultivation, or the repair, sealing or resealing of the existing surface of any road, footpath, or driveway. No material shall be deposited under or near an overhead National Grid transmission line so as to reduce the conductor distance to ground to less than the distances required by Table 4 of NZECP 34:2001). Note: Compliance with the New Zealand Electrical Code of Practice for Electrical Safe Distances (NZECP34:2001) is mandatory under the Electricity Act 1992. All activities regulated by NZECP34, including buildings, structures, earthworks and the operation of mobile plant, must comply with that regulation. Activities should be checked for compliance even if they are permitted by the District Plan. Other Amendments to Request Relief Sought in Transpower Submission Add new Policy 25H.4.16d: 25H.4.16d Reverse sensitivity effects on network utilities shall be avoided to the extent reasonably possible. Add a new definition of National Grid Yard as follows: National Grid Yard (shown in red in attached diagram) means any land located within 12m of the centreline of National Grid transmission line (reduced to 10m from the centreline of 110kV transmission lines on single poles), or within 12m of the visible outer edge of any National Grid support structure. Note: the National Grid Yard does not apply to underground cables or any transmission lines (or sections of lines) that are designated by Transpower. (Include diagram provided below in definitions section). Add a new definition of National Grid Corridor as follows: National Grid Corridor means the area measured either side of the centreline of above ground National Grid transmission lines as follows: - 14 metres for 110kV transmission lines on single poles 16 metres for 110kV transmission lines on pi poles 32 metres 110kV transmission lines on towers (including tubular steel towers where these replace steel lattice towers) 37 metres for 220kV transmission lines Note: the National Grid Corridor does not apply to underground cables or any transmission lines (or sections of lines) that are designated by Transpower. 3 (Include diagram provided below in definitions section). To replace the diagram above with the version below (updated in respect of single pole Yard width) Figure X: Diagram to explain the definitions of National Grid Yard and National Grid Corridor. For controlled activities included in Table 25H.13, include as a condition/development standard a requirement to comply with NZECP34:2001. Further, include as a matter of control: The effects of the activity on the operation, maintenance, upgrading, and development of the National Grid transmission network. For logistics and freight-handling activities within National Grid Yards (that involve the operation of cranes, straddle carriers, forklifts, or other such equipment), appropriate matters of control could be: Access or crossing points, including where crossing should be avoided Signage Any management processes or procedures to ensure safe and efficient operations Location and duration of storage of containers, including provision for their movement should access by Transpower to the National Grid Yard be required 4 Any physical measures that can be implemented such as vehicle barriers and ‘overhead gate’ structures to directly control the location of vehicle crossing points and the practical height of mobile plant and containers where crossing under lines 5 Attachment B Extracts from Waikato Regional Policy Statement and Proposed Waikato Regional Policy Statement 2696759 Attachment C HAM-MER A Underground, Barrington Drive 2696759 1800000 1800000 HAM-MER A Underground, Barrington Drive 12 /0 3 /2 01 4 7: 00 :3 6 a.m . Projection: NZTM 2000 Scale: 1:10,000 Plan Size: A4L 0 Kilom eters 0.3 25 Copyright Transpower N ew Zealand L im ited and l icens ors . All rights reserved. If y ou have receiv ed this doc ument from Transpower y ou must use it only for the purpos e Transpower prov ided i t to y ou. If you have rec eiv ed this docum ent from someone other than Trans power, you mus t not us e the doc ument and mus t des troy it or return it to Transpower Attachment D Abbreviated Curriculum Vitae of Christopher Horne 2696759 Chris Horne – Director Qualifications and Affiliations Master of Regional and Resource Planning, Otago University, 1992 Bachelor of Arts (Geography), Otago University, 1990 Member, of the NZ Planning Institute (NZPI) Resource Management Law Association (RMLA) Key Skills Advice, submissions and expert evidence on policy and plans under the RMA Consent strategy advice and management of the consenting process for infrastructure rollouts and public works Site selection/feasibility studies Resource consent applications, notices of requirement Environmental effects assessments Public consultation Expert evidence and mediation Experience Chris is the Auckland based director of Incite, a resource management and environmental consultancy with a team of planning professionals spread throughout New Zealand. Chris has 20 years of professional experience in resource management/planning in the New Zealand. This has included a broad range of public and private sector clients. This includes significant experience in the areas of infrastructure and public works. He was a representative of the telecommunications industry involved in the development of the National Environmental Standard for Telecommunications, and has been seconded on two occasions as the environmental planning manager for the Telecom group of companies prior to the demerger between Telecom and Chorus. He is also a statutory planning advisor for the NZTA in the Auckland and Northland regions, and has been involved in numerous urban growth issues affecting the strategic land transport network. Chris is a named consultant on the approved supplier panel for Transpower project work. Selected Projects Projects/experience outlined below is focused on the areas considered most relevant to the Ruakura Board of Enquiry proceedings. Transpower Corridor Protection Planning advisor to Transpower for submissions on urban plan change at Ruakura and Whakatane District Plan review. Planning advisor to Transpower and planning evidence for urban plan change at Drury South, Papakura. Auckland Unitary Plan Planning advisor to Chorus, Telecom, Vodafone and NZ Police Radio Networks for the Proposed Auckland Unitary Plan. Participation in collaborative process by Auckland Utility Operators Group (AUOG) leading to joint submission by AUOG members on Proposed Auckland Unitary Plan. Incite : PO Box 3082 : Auckland 1140 : New Zealand Phone +64 9 369 1465 : Mob +64 274 794 980 E-mail : chris@incite.co.nz Environmental Planning Manager Secondment to Telecom in 2001 and Telecom business unit Chorus in 2011 (prior to its demerger from Telecom) as the Environmental Planning Manager for the Telecom Group. The role included managing consultant planners and lawyers and advice to internal stakeholders on appropriate responses to policies and plans prepared under the RMA and other environmental legislation, management of designation roll over processes, and strategic oversight and advice on infrastructure roll out programmes. Telecommunications National Environmental Standard Co-author of a scoping document and proposed national environmental standards for telecommunications prepared on behalf of several industry stakeholders, and appointment as an industry representative to a reference group including the telecommunications industry, local government and central government representatives. The industry proposals were largely adopted as regulations following a public consultation process on the industry proposals led by the Ministry for the Environment. NZTA Statutory Planning Advisor Contracted to the NZTA as an approved statutory planning advisor for the Auckland and Northland regions. This has included planning advice, assistance with submissions, expert planning evidence at Council hearings and the Environment Court, and planning support in mediation processes for numerous urban growth related applications and plan change proposals. Transpower Substation Upgrades Planning advisor and consents project manager for outline plans and resolution of stormwater issues for upgrades of transformers and related infrastructure at substations in Penrose and Ruakura (2009). Vector Global Tree Trimming Approval Resource consent application and AEE (2005/2006) for a global tree trimming approval on Waiheke Island for tree removal/trimming to allow the Vector electricity network to comply with the Electricity (Hazards from Trees) Regulations 2003. Designation of Telecommunications Sites Planning advisor, consents manager and expert planning witness for the designation of 14 strategic telecommunications sites in the Auckland Isthmus (confirmed in 2011), 9 telecommunications sites in the former North Shore City (confirmed in October 2013), and expansion to the designation at the Warkworth Satellite Earth Station (confirmed in November 2013). These projects are a mix of Chorus and Telecom sites. Network Utilities General Vodafone 2014 – planning advisor and consenting lead for a new TransTasman submarine cable. Telecom 1995 - present, consenting strategy advisor, assistance with submissions and expert planning evidence on RMA plans, and consent approvals for a wide range of mobile networks and terrestrial/marine cable projects throughout New Zealand. Chorus 2011 – present, ongoing planning advice, assistance with submissions and expert planning evidence on RMA plans, and consent approvals for cable and radio networks projects, including leading consultant team for aerial UFB rollout in Auckland and Wellington. NZ Police 2006 – present, management of all RMA services relating to upgrading and rollout of the Police and emergency services radio network in the upper North Island. Assistance with submissions and on RMA plans. Watercare Services 2004-2005, planning feasibility assessment and consenting (territorial and regional authority consents) for a new bulk supply water pipeline between North Incite : PO Box 3082 : Auckland 1140 : New Zealand Phone +64 9 369 1465 : Mob +64 274 794 980 E-mail : chris@incite.co.nz Shore City Peninsula. and Whangaparaoa Incite : PO Box 3082 : Auckland 1140 : New Zealand Phone +64 9 369 1465 : Mob +64 274 794 980 E-mail : chris@incite.co.nz