March 2016 Electric Underground Service Installation Requirements Builder/Owner/Developer Responsibilities PSE requires the following conditions to make the worksite construction ready ahead of scheduled service: Permits Electrical permit must be approved and the Department of Labor & Industries (L&I) sticker must be affixed on the electric meter base. Trench Work The worksite must be prepared to PSE specifications. o The site must be at final grade or have final grade marked in the area of construction and trench line route. For unique site preparation requirements, contact your Project Manager. o Installation of trench, work pits, sand for bedding and shading, and conduit must meet PSE specifications. o Conduit for electric service lines shall be used under all paved surfaces, decks, rockeries, bulkheads, or obstacles to access the service line. Gas Service Other Than PSE If gas service will not be provided by PSE, please consult with the other utility for any additional clearance requirements. If any clearances conflict with PSE’s electric service clearances,use the greater of the conflicting distances. Customer Provided Materials Builder/Developer must provide: o Conduit o 3/8I minimum diameter pull rope o Backfill o Shading Meter Location An acceptable meter location that allows for required access and clearance shall be provided. o Acceptable electric meter locations include the front wall of the building facing typical public access, or the front 1/3 of the side wall. o PSE electric meters require 18 inches of maintenance clearance on either side of the electric meter and 36 inches in front of the meter. Call PSE’s Customer Construction Services: 1-888-321-7779 or visit PSE.com/CustomerConstruction for questions or information not covered in this handout. Become familiar with what can delay your project and cause it to be red-tagged: Construction debris or water in the trench or work pits. Trenches excavated to the incorrect depth. Failure to maintain minimum separations between utilities and drainage pipes. Sand and backfill material are not available, inaccessible, or inadequate. Meter location is not acceptable or fails to meet minimum clearances. Permits are not approved or visible. Conduit color and size are incorrect, or conduit is installed improperly. Effective on: 03/01/16 Canceling: 03/01/15 Page 1 of 6 Meter Locations and Clearances ÅÅ ÅÅ ÅÅ ÅÅ ÅÅ ÅÅ ÅÅ ÅÅ ÅÅ ÉÉÉÉÉÉ ÅÅ ÉÉÉÉÉÉ ÅÅ ÉÉÉÉÉÉ ÅÅ ÉÉÉÉÉÉ ÅÅ ÅÅ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚ 18I Min Front Wall 6i Max 4i Min 18I 1i Walkway Driveway ÉÉ ÉÉ ÉÉ Typical Public Access 3i Electric Meter Height Aboveground ÉÉ ÉÉÉÉÉÉ ÉÉ ÉÉÉÉ ÉÉ Front 1/3 of Side Wall Front 1/3 of Side Wall Any Obstruction Meters must be located where they can be easily identified and accessed by PSE. Meters may be located on the front wall of the house relative to the driveway, or on the front third of either side wall relative to the driveway (see diagram above). Grounding Rod(s) per NEC 36I Clearance in Front of Meter Meters shall not be located outside the shaded area in the diagram above. Electric Meter Base Wiring and Service Conduit Placement ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ No Customer Conduit No Customer Conduit Alternate Neutral Lug Position No Customer Conduit Customer Installed Conduit PSE's Service Line Effective on: 03/01/16 Canceling: 03/01/15 Page 2 of 6 No Customer Conduit No Customer Conduit Preferred Entrance to Panel for Customer Wire ÉÉÉÉ ÉÉÉÉ CAUTION! ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ ÉÉÉÉÉÉ No Customer Conduit No Customer Wire in this Area PSE's service conduit must not enter the center of the meter base. Customer Installed Conduit PSE's Service Line Trenching for Electric Service Lines in Conduit and Direct‐Buried Installations ÚÚÚÚ ÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ Electric Service Cable Direct‐Buried Installation Electric Service Cable in Conduit Installation ÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚ Final Grade 12I Typical 24I Min (6I Min) (To Excavated Dirt Pile) Final Grade Backfill for Conduit Free of rocks larger than 8I in diameter. 24I Min to 36I Max Cover * 12I Typical 24I Min (6I Min) (To Excavated Dirt Pile) Final Backfill for Direct‐Buried See requirements below. 24I Min to 36I Max Cover * 3I Sand Shading 3I Sand Bedding Electric Service Cable Direct‐Buried Electric Service Cable in Conduit * Check with local permitting agency for depth of cover requirements for any PSE facility installed in public right-of-way. 36I cover may be required over PSE facilities. Backfill Requirements for Direct‐Buried Installations Sand Bedding: The customer shall provide and install clean sand to a minimum depth of 3I prior to electric service cable installation. Sand Shading: The customer shall provide additional clean sand in piles that are readily accessible near the trench. This shading sand is to be installed by the PSE crew after direct-buried electric installation. Enough sand shall be provided so that the installation can be covered to a depth of 3I. Final Backfill For Direct Bury: The backfill layer above the sand shading shall be soil that is free from rocks larger than 8I in diameter, construction debris, glass, sharp rocks, and frozen clods. The standard shading depth shall be per the trench figures shown above. Customer-owned Facilities included in the trench: Please contact PSE directly for clearance requirements. Conduit Requirements for Electric Service PSE recommends the use of conduit for all electric service installations. o Conduit will be required when the service length is 100 feet or less, or where the service line could become obstructed and difficult to access, inhibiting direct access to the service line cable for maintenance, repair, or replacement purposes. PSE will install underground electric service lines in customer provided conduit that runs from the meter riser to the property line power stub. Customer-provided conduit may be continuous or discontinuous for runs of 100 feet or less. Customer-provided conduit must be discontinuous for runs in excess of 100 feet. Electric Meter Base and Conduit Service Riser Installation Requirements The electric meter base shall be secured to a stud or structural member. The electric service riser shall be fastened securely to a structural wall using a minimum of two conduit straps. Reducer couplings shall not be used at the meter base. The sum total of the degrees of bends in the electric conduit run (including the bend required at the bottom of the meter base riser) shall not exceed 180_. o The customer assumes responsibility for damage caused by water entering a customer’s meter base or equipment. o o o o Continuous Conduit Size and Dimension Requirements for Electric Services 100 feet or Less Meter Base Service Wire Service Panel Size Min Lug Size Bottom Knockout Size 200 Amp Without Heat Pump 4/0 2‐1/2I 1/0 or 4/0 200 Amp With Heat Pump 4/0 2‐1/2I 4/0 320 Amp and Larger 350‐kcmil 3I 4/0 or 350‐kcmil Conduit Service Riser Diameter & Type 2‐1/2I Grey Sch 40 PVC 2‐1/2I Grey Sch 40 PVC 3I Grey Sch 40 PVC Conduit Diameter & Type 2‐1/2I Grey Sch 40 PVC 2‐1/2I Grey Sch 40 PVC 3I Grey Sch 40 PVC Minimum Bend Radius 24I 24I 24I Non‐Continuous Conduit Size and Dimension Requirements for Electric Services Greater Than 100 feet Meter Base Service Wire Service Panel Size Min Lug Size Bottom Knockout Size 200 Amp Without Heat Pump 4/0 2‐1/2I 1/0 or 4/0 200 Amp With Heat Pump 4/0 2‐1/2I 4/0 320 Amp and Larger 350‐kcmil 3I 4/0 or 350‐kcmil Effective on: 03/01/16 Canceling: 03/01/15 Page 4 of 6 Conduit Service Riser Diameter & Type 2‐1/2I Grey Sch 40 PVC 2‐1/2I Grey Sch 40 PVC 3I Grey Sch 40 PVC Conduit Diameter & Type 3I Grey Sch 40 PVC 3I Grey Sch 40 PVC 3I Grey Sch 40 PVC Minimum Bend Radius 24I 24I 24I 1 3 2 8 7 Meter and Service Connections Work Pit 6 GAS TV & TEL POWER 12I Typical 12I Typical 48I Electric Meter Gas Meter FINISHED WALL * See Form 3060 for separation requirements to other utilities. Work Pit Dimensions When non‐continuous conduit is installed * 30I to 48I (Approx) ÇÇ ÇÇ ÇÇ ÇÇ ÇÇ ÇÇ ÇÇ ÇÇ ÇÇ * 12I Min 9 5 4 ÚÚÚÚÚÚÚ 333333 ÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚ 333333 ÚÚÚÚÚÚÚ 333333 333333 ÚÚÚÚÚÚÚ 333333 ÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚ 333333 ÚÚÚÚÚÚÚ 333333 ÚÚÚÚÚ 333333 ÚÚÚÚÚ 333333 ÚÚÚÚÚ 333333 ÚÚÚÚÚ 333333 ÚÚÚÚÚ ÚÚÚÚÚ ÚÚÚÚÚ Conduit Elbows − Customer Provided. 24I min bend radius. See Conduit Requirements for Electric Service on Page 4. Electric Service Conduit − Customer Provided. Gas Meter − Utility Provided. 5 6 7 6 4 5 3 1 4i Min 2 11 Non‐Continuous Conduit 10 5 Detailed information on choosing between continuous or non‐continuous conduit options can be found in Chapter 2 of PSE's Single‐Family Residential Handbook. NOTE: Continuous conduit is restricted to distances of 100i or less. 6 4 3 2 1 Continuous Conduit Non‐Continuous and Continuous Conduit Options 11 Electric Meter − Utility Provided. 10 1/2 Yard Bedding and Shading Sand − Sand shall be provided on-site by the customer and placed within hand-shoveling distance to the work pit for bedding and shading of direct-buried facilities. A larger work pit may require more sand (see backfill requirements on Page 4). Sand shall be washed, clean, and free of debris or rocks larger than 1/4I. For non-continuous installations only. Work Pit − See work pit dimensions detail on this page. Conduit Straps (2 Minimum) − Customer Provided. 4 9 Conduit Service Riser − Customer Provided. 3 Finish Grade − Finish grade shall be clearly marked. 3/8I Pull Rope − For runs over 60i. 2 8 Electric Meter Base − Customer Provided, and secured to stud or structural member. 1 Work Pit Legend 3333 3333 3333 3333 3333 3333 Effective on: 03/01/16 Canceling: 03/01/15 Page 3 of 6 Property Line/Intersection Point Work Pit ÚÚÚÚÚ ÚÚ ÚÚÚÚÚ333333 333333333333 ÚÚÚÚÚ ÚÚ ÚÚÚÚÚ 333333333333 333333 ÚÚÚÚÚ ÚÚ ÚÚÚÚÚ 333333333333 333333 ÚÚÚÚÚ ÚÚ ÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚ ÚÚÚÚÚ 333333333333 ÚÚÚÚÚ 333333 ÚÚÚÚÚÚÚÚÚÚ ÚÚÚ 333333333333 333 ÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚ 333333333333 333 ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ 3 A 5 28I to 32I Min Deep (24I Min Cover) 2 Work Pit Legend 1 2 Electric Service Conduit − Customer Provided. 3 3/4 Yard Bedding and Shading Sand − Sand shall be provided on-site by the customer and placed within hand-shoveling distance to the work pit for bedding and shading of direct-buried facilities. A larger work pit may require more sand (see backfill requirements in this handout). Sand shall be washed, clean, and free of debris or rocks larger than 1/4I. 4 Gas Service and Conduit 5 Electric Stub Marker − Utility Provided. 6 Gas Stub Marker − Utility Provided. 7 CATV/TEL 4 A 1 7 6 Pipes and Wires Utility Installed 3/8I Pull Rope − For runs over 60i for electric. Section A-A Electric and Joint Utility Work Pit Dimensions Electric and Joint Utility ÚÚÚÚÚÚ ÚÚÚÚÚÚ ÚÚÚ ÚÚÚÚÚÚ ÚÚÚÚÚÚ ÚÚÚ ÚÚÚÚÚÚ ÚÚÚ A 12I POWER 48I (Approx) 4I TV & TEL GAS 12I Min. ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚ ÚÚ ÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚ ÚÚ ÚÚÚÚÚÚÚÚÚÚ 6 48I (Approx) Trench to Building 5 Final Grade 7 A Electric Service Service Intercept Locations When the Electric Service Trench Terminates at a Utility Pole: RRRRRRR RRRRRRR RRRRRRR RRRRRRR RRRRRRR RRRRRRR PSE Transformer at Top of Pole PEDESTAL PADMOUNT TRANSFORMER ÎÎÎÎÎÎÎÎÎ ÂÂÂÂÂÂÂ ÎÎÎÎÎÎÎÎÎ ÂÂÂÂÂÂÂ ÎÎÎÎÎÎÎÎÎ ÂÂÂÂÂÂÂ ÎÎÎÎÎÎÎÎÎ ÂÂÂ ÂÂÂÂÂÂÂ ÎÎÎÎÎÎÎÎÎ ÂÂÂ ÂÂÂÂÂÂÂ ÎÎÎÎÎÎÎÎÎ ÚÚÚÚÚ ÎÎÎÎÎÎÎÎÎÚÚÚÚÚ HANDHOLE STUBOUT If you have questions regarding the location or intercept requirements for your electric service, contact Customer Construction Services or your Project Manager. Road Side Field Side Quadrant 1 Quadrant 2 Quadrant 3 Quadrant 4 5I Min Utility Pole Riser Conduit (PSE Provided) PSE‐ Provided Standoff Bracket & Conduit Dig the trench to the quadrant of the pole that is beneath the existing transformer. If possible, the trench should end on the quadrant of the pole that is most protected from vehicular traffic. Stop the conduit 4 feet from the pole in the work pit with the pole butt exposed. Effective on: 03/01/16 Canceling: 03/01/15 Page 5 of 6 Temporary Electric Service Requirements 1 Top of meter base shall not be above top of structure 8 Items Owned and Installed by Customer 3 2 6i Maximum 5i Preferred 4i Minimum 5i Max. 1 4I x 4I x 10i continuous single structure 2 2I x 4I bracing (post should be braced from two directions) 3 Meter socket and distribution panel (up to 200 A, 120/240 V) 4 Ground wire, according to the NEC 5 6 Ground rod(s), according to the NEC Service entrance conductors in accordance with NEC Items Owned and Installed by PSE 4 7 Transformer, handhole, pedestal, or stubout 8 Meter ÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚ ÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚÚ 7 2i Min Cover 3i Min 5 6 NOTE: Trench and backfill from meter base to transformer, handhole, pedestal, or stubout is customer provided. Customer Post, Meter Base, and Panel PSE Stubout 6i Maximum 5i Preferred 4i Minimum Stubout conduit covering the temporary connection NOTE: 4ix4i work pit required to allow working room for the tools necessary to connect temporary service 26I Customer owned temporary service conductors 4i 4i PSE Conductor View a video for the proper preparation of temporary power and installation requirements at this site: http://PSE.com/ServiceRequirementVideos Effective on: 03/01/16 Canceling: 03/01/15 Page 6 of 6 E2016 Puget Sound Energy 6080 03/16