FLOWMETER FACILITY - 1 DETAILED SPECIFICATIONS – FLOWMETER FACILITY INDEX Paragraph - Number 2-17-1 2-17-2 2-17-3 2-17-4 2-17-5 2-17-6 2-17-7 2-17-8 2-17-9 General Operation & Maintenance Manuals Start-Up Service Field Test Spare Parts Guarantee Fiberglass Metering Manhole Parshall Flume Flowmeter Instrumentation FLOWMETER FACILITY - 2 2-17-1 GENERAL The Contractor shall furnish and install a wastewater flowmeter facility complete and operable consisting of a Parshall flume, ultrasonic type flowmeter, instrumentation, electrical, fiberglass metering manhole, concrete work, earthwork, control cabinet, piping, and all necessary appurtenances and fittings, as shown on the drawings and specified herein. 2-17-2 OPERATION AND MAINTENANCE MANUALS The Contractor shall furnish to the Owner five (5) copies of operation and maintenance manuals for each of the following items: - Flowmeter and instrumentation 2-17-3 START-UP SERVICE The Contractor shall provide the services of a factory trained, qualified representative for no less than two days to inspect the completed installation, make all adjustments necessary to place the system in trouble free operation, and instruct the operating personnel in the proper care and operation of the equipment, prior to the final acceptance of the project. The Contractor shall inform the Engineer at least 48-hours in advance of the start-up service. 2-17-4 FIELD TEST When the flowmeter facility is complete and ready for operation, then the station shall be inspected and tested for compliance to the contract documents. Tests of the equipment shall be made in the presence of the Engineer, the Contractor, the Electrical Subcontractor (if used), and the Owner's representative. The field test shall include, but not be limited to, the following: (a) Flowmeter The flowmeter shall be tested to determine satisfactory performance for indicating and recording the proper flow rate for the level of fluid in the Parshall flume. (b) Parshall Flume The Parshall flume shall be inspected to determine if it was installed level within the tolerances indicated by the manufacturer's installation instructions. (c) Control Cabinet The control cabinet shall be inspected to determine if it is watertight, and all electrical components are properly mounted and overate correctly. FLOWMETER FACILITY - 3 (d) Inspection A thorough inspection of all mechanical and electrical equipment and controls, piping, fittings, brackets, mountings, seals, conduit, components, and features shall be made while the station is being tested to determine performance and compliance with design requirements and specifications. (e) Structure The station shall be inspected for performance, structural soundness, and water tightness. (f) Repairs, Adjustments and Replacements The Contractor shall make any and all necessary repairs, adjustments, and replacements until performance has been demonstrated to the satisfaction of the Engineer. The Contractor shall bear the cost of any repair, adjustment, and replacement. 2-17-5 SPARE PARTS The Contractor shall provide spare parts for routine maintenance and repair as recommended by the equipment manufacturer and one year supply of chart paper for the recorder which is calibrated and suitable for use with the flow recorder. 2-17-6 GUARANTEE The equipment shall be guaranteed against defects in material and workmanship for a period of one year from the date of Owner's final inspection and acceptance. Any defective equipment or workmanship shall be repaired or replaced without delay by the Contractor without cost or obligation to the Owner during the guarantee period. 2-17-7 FIBERGLASS METERING MANHOLES Fiberglass metering manhole shall conform to ANSI/ASTM D-3753 for standard specifications for fiberglass reinforced manholes. The fiberglass manhole shall include Parshall flume, internal ladder and internal instrument rack as an integral component of the structure. The manhole cover shall be lightweight, 48 inches in diameter, with hinged fiberglass cover with hasp for locking. All cover accessories shall be stainless steel. The fiberglass pipe end adapters shall be provided with flexible watertight, neoprene connecting boots, with stainless steel clamps. Fiberglass manhole and appurtenances shall be as manufactured by Plasti-Fab, Inc., or approved equal. FLOWMETER FACILITY - 3 2-17-8 PARSHALL FLUME The Parshall flume shall be installed as shown in the Drawings according to the manufacturer's installation instructions. The Parshall flume shall be molded fiberglass reinforced polyester resin with an upper temperature limit of at least 150OF and shall have a permanent white gel-coating on all wetted surfaces. The flume shall have a throat width of 3 inches, a height of 24 inches and be molded in one piece with ample wall thickness and reinforcing ribs to prevent distortion during shipment, installation and operation. The flume shall be self-supporting and require no external supporting structure. Interior dimensions shall conform to those shown in the latest revision of U.S. Department of Interior, Bureau of Reclamation, Water Measurement Manual. A staff gauge graduated in feet, with 50 divisions per foot, shall be attached vertically flush to the inside of one wall of the converging section of the flume. The staff gauge shall be located two-thirds the distance from the throat of the flume to the upstream end of the flume's converging section. A 1/4-inch I.D. PVC or stainless steel air tube, pressure tested at 150 psi, shall be formed integrally into the wall of the flume and penetrate the wall of the flume at the bottom, of the wall directly opposite the staff gauge, without creating any roughness or flow obstruction on the inside surface of the flume. The top of the air tube shall be provided with a removable plug. The Parshall flume shall be Plasti-Fab 3-inch PF-DRX-BT Parshall Flume, or equivalent. Contractor shall submit shop drawings of Parshall Flume for review prior to fabrication. 2-17-9 FLOWMETER INSTRUMENTATION (a) Scope The work included in this subsection consists of furnishing, installing and placing in operation all the instruments, controls, electric service entrance, and appurtenances, including all conduit, wiring and circuitry necessary to provide the monitoring, transmitting and recording functions indicated on the Drawings and herein specified for use in measuring untreated domestic wastewater flow through a Parshall flume. Flowmeter instrumentation shall be a complete system as manufactured by Fischer & Porter, or approved equal. (b) Submittals In order to provide an integrated system and undivided responsibility, prior to release for manufacture, it shall be the Contractor's responsibility to coordinate and submit a total package containing the following information. 1. A complete wiring diagram inclusive of all instrumentation with appropriate component identification as indicated in Subparagraph 9.2.c. below. FLOWMETER FACILITY – 5 2. Component manufacturing data sheets with factory wiring diagrams for all components either in the system or to which the systems connect. 3. Component manufacturing data sheets shall indicate all pertinent data and identify each component by item number and nomenclature as indicated on the Drawings and in the Specifications. 4. Detailed dimensional drawings of Parshall flume, instrumentation, and instrument enclosure. All literature and drawings being submitted for approval shall be bound in volumes. Sales bulletins and other general publications are not acceptable as material for approval when not accompanied by additional literature and drawings pertaining specifically to this project. After the material has been forwarded for approval, the manufacturer of the equipment shall make available the services of a project engineer and other qualified personnel as required to assist the Contractor in reviewing the submittal with the Engineer. (c) Miscellaneous All special tools and test equipment required for the maintenance, testing, or adjustment of the mechanism shall be furnished by the Contractor. (d) Design Criteria All of the equipment shall be the manufacturer's latest and proven design. Specifications and Drawings call attention to certain features, but do not purport to cover all details entering into the design of the instrumentation system. The completed system shall be compatible with the functions required and with the equipment furnished under the Contract. All electrical components of the system shall operate on 120 volt, single phase, 60 cycle current, except as otherwise noted in the Specifications. Control Cabinet for flowmetering equipment shall be located next to electric service entrance as shown by the Drawings. The control cabinet manufacturer shall design, furnish and install all interior wiring and components within the control panels complete and ready for connection of external wiring by the Contractor. The Contractor shall make all connections of exterior wiring between the equipment and the control cabinet terminal boards. However, the control cabinet manufacturer shall furnish complete wiring diagram showing the electrical circuits inside the cabinet and interconnections between the panel and the external instruments and components. Interconnecting FLOWMETER FACILITY - 6 wiring between the panels and the equipment specified under other sections shall be identified and numbered on the diagram. All terminals shall be identified and numbered. All cabinet wiring shall have numbered tags attached to each wire for identification. All cabinet wiring shall be not less than Number 16 gauge stranded copper wire type THWN. Inside each cabinet there shall be provided a copy of interconnecting wiring diagram. All necessary fuses or switches required by the control cabinet manufacturer for his equipment shall be provided with the equipment. Any other devices necessary to obtain proper operation of the control systems from the available energy sources shall be furnished with the control cabinet. Cooling fan, thermostat, lightning and surge protection, and other ancillary devices required by flowmeter manufacturer for proper operation shall be provided and the cost of such equipment shall be included in the bid price for the project. All components shall be tagged with the item nomenclature given in the Specifications or Drawings. number and All instruments to be cabinet mounted shall be of the same appearance as to provide a clean and neat installation. All instruments shall be constructed to operate, function and last in a tropical climate as found in Pinellas County, Florida. Components shall be factory finished to the manufacturer's standard for the service intended. Accuracy of completed flowmeter installation shall be within +/-I% of flow at upper span setting. Span range shall be field adjustable. Initial upper span setting and meter calibration shall be for a maximum flow of 0.8 MGD. (e) Sensing Element Ultrasonic Type: Flow sensing element shall be the Fischer & Porter transponder, used with the Type 5OUS Open Channel, Flowmeter, and located as shown by the drawings and as recommended by the manufacturer. Transponder shall be installed within the fiberglass metering manhole suspended from a 3/16-inch diameter stainless steel bar. Connecting cable between transponder and transmitter shall be run within conduit from the manhole to the flowmeter housing. The connecting cable shall not pass directly from the transponder, to the flowmeter housing, without conduit outlet filled with silicone located outside both the transponder enclosure and the flowmeter housing in order to positively prevent wastewater gasses in the flume area from entering the flowmeter housing. (f) Flowmeter Flowmeter shall be the Fischer & Porter Model 5OUSI111A-1 ultrasonic FLOWMETER FACILITY - 7 open channel flowmeter with 133CO38UOl counter (totalizer) and Fischer & Porter Model 51-132ICB-ilBCXII 30 day strip chart recorder, or approved equal. Totalizer shall be eight digit, non resettable, and sealed in U.S. gallons. Transmitter indicator and the recorder shall register 0-100% span. Future maximum flow rate for the facility will be 0.8 MGD but the initial maximum flow rate shall be set for 0.2 MGD. Flowmeter shall be capable of being connected to telemetry equipment in the future. (g) Flowmeter Housing The housing for the flowmeter equipment shall be 14 gauge Type 304 stainless steel, NEMA 3R weatherproof construction for mounting on a stainless steel enclosure for the transponder as indicated by the drawings. Housing shall include ventilation fan, with thermostat control. Insect screens shall be provided over all vents. The Housing shall have a sub-panel on which equipment is mounted, a hinged and lockable blind front panel, and a bolted rear panel which will allow access for making electrical connections to equipment.