FIRE PROTECTION Fire protection rates refined in Maine A task force established by the Maine PUC recommends new fire protection charges. Christopher P.N. Woodcock and Normand R. Lamie T he state of Maine and the Maine Public Utilities Commission (PUC) have been at the forefront in developing new allocation methods and rate design for fire protection charges. As discussed in AWWA’s Manual M26,1 the Maine Water Utilities Association Committee on Fire Protection Charges published a survey 35 years ago indicating the percentage of total revenues that ought to be derived from fire protection charges (see the sidebar on pages 54 and 55). This curve was adopted by the Maine PUC as a guideline that has been used in rate proceedings. The “Maine In response to assertions by Maine Public Utility Commission curve” has been pub(PUC) staff members that private fire protection charges lished in various AWWA duplicated public fire protection charges and should be rate manuals since it first substantially reduced or eliminated, the Maine PUC established appeared in the third edia Task Force to examine the issue. This article describes the tion of the M1 Manual.2 approach the task force recommended for determining private In 1987, the Maine PUC fire protection charges, an approach that was adopted by the formally adopted use of Maine PUC. The task force’s alternative suggestion is also the curve in the absence presented. of a fully allocated costof-service study. Copyright (C) 1996 American Water Works Association OCTOBER 1996 53 Because Maine water utilities and the Maine PUC have seemed to be on the cutting edge in the development of innovative treatment of fire protection charges, recent developments in Maine’s treatment of fire protection charges are particularly noteworthy. PUC opposes proposed increase In 1991, a proposed water rate increase by the Portland Water District was brought before the Maine PUC, which regulates the rates of investor-owned water utilities and quasi-municipal water districts, in Docket No. 91-162.3 One element of contention was the water district’s proposed public and private fire protection charges. The district had conducted a costof-service study using the guidelines in AWWA’s various manuals. Fire protection costs were allocated between public and private fire service based on the relative potential demands as measured by the crosssectional area of public hydrant branches and private sprinkler connections. This method conforms generally with the guidelines contained in AWWA’s rate manuals.1,2,4 PUC staff members took exception to the proposed private fire protection charges, asserting that they were not based on the cost of providing service. They argued that no capacity costs should be allocated to private fire service—that the fire capacity designed into the system was all for general or public fire protection purposes. PUC staff members testified that private fire protection simply takes advantage of the capacity installed for public protection—a service the property owner already pays for through property tax. It was noted that the current private fire sprinkler systems only activate the sprinkler heads nearest the fire and thus tend to put out fires faster and use less water. Last, it was argued that private fire sprinklers save lives and reduce property damage, and their use should therefore be encouraged. In summary, the staff members recom- mended that private fire service charges only recover the costs associated with account maintenance and the cost of the part of the service line the utility owns and maintains. The PUC agreed that “private sprinkler systems put a much smaller demand on the water system than fire hydrants and should thus be allocated a reduced portion of backup facility costs.”5 It found that a sprinkler structure seldom needs the support of a public fire protection system and that the rate-making process should consider the reduced demands. However, the PUC could not determine the degree to which demands may be reduced. After the Portland case, two other dockets 6,7 brought the issue of fire protection charges to the forefront. Lausten et al v. Camden & Rockland Water Company requested a PUC investigation into the private fire protection charges of Maine’s largest investorowned water company. Maine Association of Fire Sprinkler Contractors v. Maine Public Utilities Commission requested an investigation by the PUC into the connection fees for private fire protection. In light of the various dockets associated with the issue of private fire protection charges, the questions raised in the Portland case, and the concern that implementation of the PUC staff recommendations would result in a fundamental policy change, the commissioners ordered a further investigation into the issue with a proposed rule-making. PUC invites comment on eight issues In August 1994, the Maine PUC issued a proposed rule-making on private fire protection8 and invited comments on eight specific issues: • Should backup capacity and facilities be allocated to private fire protection? If so, is there a double charging? What is the correct backup capacity? • What is the proper basis for the billing of private fire protection? Should it be the size of the connec- Public Versus Private Fire Protection When the Maine Water Utilities Association Committee on Fire Protection Charges presented its repor t in 1961, the intent of its proposed cur ve was clearly to reflect total fire protection revenues. No mention of private fire protection or sprinkler connections is made in the March 1961 ar ticle in the Journal of the Maine Water Utilities Association. 13 However, the ar ticle also discusses the recover y of “the fire protection charge” through proper ty taxes, suggesting that the total fire protection charge was the same as public fire protection. The curve published with the article is labeled, “Determination of Percentage of Gross Revenue for Public Fire Protection Charge.” The lack of dis- tinction between public and private fire protection charges may well be due to the sparse number of private fire connections in smaller, more rural communities in the late 1950s when the committee prepared its repor t. When the Maine Public Utilities Commission (PUC) adopted the curve in 1987 (as Chapter 69),15 the use of private sprinklers was far more common. In discussing the use of the curve in section 2 of Chapter 69, the Maine PUC clearly refers to “the percentage of gross revenue that a water utility shall allocate to public fire protection charges” [italics added]. The cur ve included in Chapter 69 is copied from the 1961 article and carries the same title, “Determi- Copyright (C) 1996 American Water Works Association 54 JOURNAL AWWA Private fire protection service helps prevent injuries and reduces fire department personnel and equipment costs. tion? Should it be the size of the riser after it enters the building? • Should charges for different types of private fire service differ (sprinklers versus private hydrants)? On what basis should the charges differ? Should private fire hydrant charges differ from public hydrants? • Should benefits to the owner of having a private sprinkler be considered? • Should the determination of charges account for the fact that buildings that have sprinkler systems use less water to fight fires than other buildings? • Are there reasons for encouraging private fire protection devices? Should they be considered in rate setting? • How quickly should new rules be implemented? • Under what circumstances should private fire service be metered? The proposed rule-making resulted in numerous comments from diverse interests throughout Maine. Sprinkler providers were interested in pro- nation of Percentage of Gross Revenue for Public Fire Protection Charge.” When the Maine cur ve was first published in AWWA’s manual M1,2 the discussion again only involved public fire protection. There is no mention of a private fire service or sprinkler component to the fire protection charges. The first mention of private fire protection charges in AWWA’s rate-related manuals is in the first edition of manual M26.1 In this manual, it is suggested that if charges are to be levied for private fire or sprinkler service, the total fire protection revenues ought to be split between public and private fire service based on the relative demands of each type of service. Splitting total fire protection costs between public and private fire ser vice based on relative demand potential is also discussed in the fourth edition of AWWA’s manual M1. Clearly, the various AWWA rate manuals viewed private fire protection as moting cost-effective sprinkler systems. Fire officials were interested in fire protection systems that would reduce fires, save lives, and protect health and safety. Municipal officials were concerned about shifting costs from private fire service to public fire protection because an increase in costs would result in increased property taxes. Some municipalities also raised the concern that the recovery of public fire protection charges through property taxes was inequitable, because tax-exempt properties were able to avoid any responsibility. The water utilities expressed a belief that the service being provided should be paid for by those who benefit. Task force attempts to balance interests After receiving numerous comments from interested parties, the PUC decided to appoint a Private Fire Protection Task Force by its order of Apr. 11, 1995.9 It charged the task force with considering all stakeholders involved in the complicated issue of private fire protection and with developing recommendations that accommodate all legitimate interests. The ultimate goal of the task force was to balance the complex interrelationship of municipal customer, utility, business, and society while satisfying the PUC’s long-standing policy of setting cost-based rates for private fire service.10 The task force had 20 members, including representatives from the Public Advocate’s Office, several water utility districts, the Maine Municipal Association, the Maine Rural Water Association, the Maine part of total fire protection costs. Although the Maine curve is also presented in the fourth edition of manual M1,4 it is included in the section “Rate Design for Small Utilities,” in which only public fire protection charges are discussed. Method A, recommended by the Maine Task Force, uses the Maine curve to determine public (municipal) fire protection, not total fire protection revenue. Based on the number of hydrants and the demand requirements, a unit cost per gallon per minute is derived for public fire protection. This unit rate is proposed for private fire protection under method A. As a result, the total fire protection revenues include both the public fire revenues derived from the curve and the private fire protection revenues. This amounts to a somewhat different treatment of the interrelationship of public and private fire protection costs and related charges than is presented in the recent AWWA rate manuals. Copyright (C) 1996 American Water Works Association OCTOBER 1996 55 Maine PUC Fire Protection Task Force: Example of Method A, Demand-based private fire protection charges Step 1: Determine total revenue needs. From rate filing $1,750,080.00 Step 2: Determine total revenues from municipal fire protection. From Maine PUC Chapter 65 “curve” (15.7 percent) $274,763 Step 3: Determine total fire flow demand for municipal fire protection. Residential hydrants Commercial hydrants Industrial hydrants Total Number 343 128 68 539 ISO Flow Demand gpm (m3/s) 500 (0.032) 1,000 (0.063) 1,000 (0.063) Total Demand gpm (m3/s) 171,500 (10.82) 128,000 (8.07) 68,000 (4.29) 367,500 (23.18) Step 4: Determine unit cost of fire flow demand for municipal fire protection (MFP). Total revenue from MFP (from Step 2) $274,763 Total fire flow demand from MFP (from Step 3) 367,500 gpm (23.18 m3/s) Unit cost for fire protection $0.74765/gpm ($11,852/m3/s) Step 5: Determine total fire flow demand of private fire protection. Private hydrants Sprinklers with 0–99-gpm (0–0.006-m 3/s) demand Sprinklers with 100–199-gpm (0.006–0.013-m 3/s) demand Sprinklers with 200–399-gpm (0.013–0.025-m 3/s) demand Sprinklers with 400–599-gpm (0.025–0.038-m 3/s) demand Sprinklers with 600–999-gpm (0.038–0.063-m 3/s) demand Sprinklers above 1,000-gpm (0.063-m 3/s) demand Total private fire protection Number X Average Flow gpm (m3/s) 23,500 (1.482) 2,080 (0.131) Number 47 26 Average Flow Demand gpm (m3/s) 500 (0.032) 80 (0.005) 4 196 (0.012) 784 (0.049) 130 200 (0.013) 26,000 (1.640) 32 535 (0.034) 17,120 (1.080) 3 881 (0.056) 2.643 (0.167) 2 1,800 (0.114) 3,600 (0.227) 244 Step 6: Determine total cost for private fire protection (PFP). Total private fire protection demand (from Step 5) Unit cost of fire protection (from Step 4) Total revenue from PFP 75,727 (4.777) $75, 727 gpm (4.777 m3/s) $0.74765/gpm ($11,852/m3/s) $56, 618 Step 7: Allocate private fire protection based on individual flow demand. Number Average Cost Private hydrants 47 $373.83 Sprinklers with 0–99-gpm (0–0.006-m 3/s) demand 26 59.81 Sprinklers with 100–199-gpm (0.006–0.013-m 3/s) demand 4 146.54 Sprinklers with 200–399-gpm (0.013–0.025-m 3/s) demand 130 149.53 Sprinklers with 400–599-gpm (0.025–0.038-m 3/s) demand 32 399.99 Sprinklers with 600–999-gpm (0.038–0.063-m 3/s) demand 3 658.68 Sprinklers above 1,000-gpm (0.063-m 3/s) demand 2 1,345.78 Copyright (C) 1996 American Water Works Association 56 JOURNAL AWWA Revenues $17,570.01 1,555.06 586.16 19,438.90 12,799.68 1,976.04 2,691.56 Merchants Association, fire chiefs, the State Fire Marshal’s Office, the Maine Association of Fire Sprinkler Contractors, and an investor-owned water company. The task force selected two co-chairs and was provided a coordinator from the PUC’s staff and a facilitator. It met 11 times over five months. During deliberations, several presentations were provided from outside sources to inform the members. These presentations included viewpoints on how issues affect representative groups and society in general, the thoughts of the PUC staff members who had originally recommended revisions to private fire protection charges, and a national perspective from the chair of AWWA’s Rates and Charges Subcommittee. Based on the input they received and their internal discussions, task force members prepared a report. The task force submitted its report11 to the Maine PUC Jan. 10, 1996. The report recommended that private fire service charges be assessed based on actual demands created by individual customers—the socalled method A, described in detail on page 56. A further recommendation (method B) was that all fire protection charges, private and public, be demandbased. Because method B was a late consideration, the task force had insufficient time to fully explore its effects and implications. As a result, method B was recommended for further analysis. In summary, the task force made the following recommendations: • Private fire protection customers should be charged for the costs associated with providing demand capacity created by their private fire system in accordance with method A. • The allocation of costs between public and private fire protection charges should be determined on a case-by-case basis for each utility based on relative demand flows required for each service. • Method A charges for private fire protection services (hydrants and sprinklers) are based on the design flow demand required by the customer’s fire protection system; demand is not to exceed the flow available at the utility’s main. • Method A should not automatically be imposed on water utilities. Utilities may implement the methodology for fire protection at their discretion. • The legislature should consider authorizing municipalities to exempt fire sprinkler systems from property taxation. • The legislature should investigate the fiscal effect of allowing municipalities to impose a service charge on tax-exempt properties for public fire protection services and investigate the equity of the current method of charging only taxable properties. • Municipalities and water utilities should jointly investigate innovative ways to encourage the installation of fire sprinkler systems. • The task force recommends further analysis of a method by which a utility or municipality would apportion the total fire flow demand of the municipality (private plus public) structure by structure as outlined in method B.11 Task force categorizes its recommendations In responding to the eight issues posed by the PUC in its original proposal, the task force divided its recommendations into two categories: those within the jurisdiction of the PUC and those not within the PUC’s authority but that should be pursued. Six recommendations within PUC’s jurisdiction. Six of the recommendations were believed to be within the PUC’s jurisdiction: (1) Should backup capacity and facility costs be allocated to private fire protection customers? Because private fire service customers use a service provided by the water utility, it was felt they should pay. A cost allocation study will divide total fire protection costs between public and private fire service. Revenues from public fire protection charges are thus reduced by the amount allocated to private fire protection, so there is no double charging from the perspective of utility revenue. The task force acknowledged, however, that from the perspective of the customer who has a private fire connection, the combination of the tax payment for public fire protection and the private fire service charge could appear as a double charge. (2) What is the proper basis for billing of private fire protection service? The task force recommended that billing be done on the basis of design flow demand required by the customer’s private fire protection system (demand not to exceed the capacity available in the main). Fire demands are related to building construction and occupancy, not the size of the connection. The design flows should be determined using the National Fire Protection Association’s (NFPA’s) Standard 1312 and associated standards. It should be the customer’s responsibility to furnish the utility with design flow demand information. If the information is not available, it was recommended that the charges be based on the best estimate of the utility using available information. The estimate should not exceed the maximum flow available through connections of similar size. Sprinkler design data for many structures are available from the offices of the Maine state fire marshal; it is unknown if fire marshals in other states have such data. If a property has multiple systems, the charges should be based on the cumulative demand of each system. This proposal would eliminate any incentives to undersize or oversize connections. This also addresses issues when connections are oversized or undersized because of unique pressure situations at the point of connection. (3) How should charges for different types of private fire protection installations differ (hydrants versus sprinkler systems)? There should be no difference, because the design flow is what matters to the utility. The only differences between costs for sprinkler systems and private hydrants should be to reflect other utility services such as inspection or maintenance services. In general, it was believed that private hydrant charges should be less than public hydrant Copyright (C) 1996 American Water Works Association OCTOBER 1996 57 charges to reflect the fact that there is no utility investment in private hydrants, and typically no maintenance or replacement costs are involved. (4) In rate-making, should the fact be considered that private fire installations normally reduce water demands for fire fighting compared with structures without private fire protection systems? The task force addressed two issues in relation to this topic: the total volume of water required to extinguish fires and the instantaneous demands required. Whether fire protection is public or private, the total volume of water required for fire fighting is minimal compared with total utility production and is thus of little relevance. Most costs are associated with providing capacity to meet instantaneous demands. With charges based on the design demand flow, the variability in demand potential will be reflected. (5) Under what conditions should private fire protection services be metered? It was felt that metering degraded the reliability of fire protection systems. Because the volume of water used is minimal, there is typically no need to meter this service. (A detector check meter may be appropriate to ensure that no water is used for purposes other than fire fighting.) The PUC’s rules dealing with circumstances in which a meter may be suitable were deemed appropriate. (6) What is a reasonable period during which utilities might establish and phase in new recommendations? The task force recommended that method A not be automatically imposed; rather, utilities should be allowed to implement demand-based private fire service charges at their own discretion unless ordered to do so more quickly by the PUC. If use of the new method results in a significant shifting of charges, the new method should be phased in on a case-by-case basis. Some issues beyond PUC’s jurisdiction. Several issues raised by the PUC and about which the task force provided recommendations were believed to be beyond the PUC’s jurisdiction. (1) Are there reasons to encourage installation of private fire protection services? The task force concluded there were a number of convincing reasons to encourage private fire protection service. If structures have sprinkler systems, fire flow demand is dramatically reduced, because fires are extinguished more quickly. Sprinkler systems prevent injuries, reduce fire department personnel and equipment costs, and benefit the community when jobs are saved and businesses are not disrupted. The more properties that have private sprinkler service, the lower the insurance rates for all properties and citizens. Based on the analysis, the task force recommended that the legislature consider legislation that would permit municipalities to exempt If structures have sprinkler systems, fire flow demand is dramatically reduced because fires are extinguished more quickly. fire sprinkler systems from property taxes or allow a tax credit to all property owners with sprinkler systems. (2) What can be done to address the issue of tax-exempt organizations that do not contribute to public fire service charges? The only dependable current source of funds available to municipalities for this service is the local property tax. The task force recommended that the legislature investigate the fiscal effects of allowing municipalities to impose a service charge on tax-exempt properties for public fire protection service. Two methods were discussed. The first would be a charge to tax-exempt properties similar to what they would pay for the service if they were not taxexempt. The second method would eliminate the distinction between public and private fire service and allow all customers to be charged for fire service based on demand. It was clear that this issue required further analysis. Method A makes use of “Maine curve” Under the proposed demand-based system of private fire protection charges (method A), it is first necessary to determine the total cost of service and related revenues that could be derived from public or municipal fire protection. The task force recommended the continued use of the allocation curve first developed in 196113 by the Maine Water Utilities Association Committee on Fire Protection Charges (see the sidebar on page 56). It was found that when compared with the allocations that result from cost-of-service studies, this curve provides a remarkably accurate determination of the revenues that should be derived from public fire protection charges. In the absence of a fully allocated cost-of-service study, this curve should continue to be used to derive the public fire service revenue requirements. The curve is determined as follows: using Insurance Services Office or NFPA design flow ratings for fire hydrants, the total fire flow demand for all public fire hydrants is estimated. Dividing the public fire protection revenue requirements by the estimated total public fire flow demand results in a unit cost for fire flow demand. The fire flow demand for each individual private fire protection system is determined. All fire sprinklers in new buildings in Maine must have a fire flow design that is approved by the state fire marshal’s office. The demands for systems in older buildings can be estimated using NFPA code manuals. To determine the private fire protection charge for a building, the design fire flow demand (in gallons per minute or Copyright (C) 1996 American Water Works Association 58 JOURNAL AWWA cubic metres per day) is multiplied by the derived unit cost for fire flow demand. Method B to be analyzed in greater depth The task force considered another demand-based concept for total (public and private) fire protection charges known as method B. The distinction is that method A applies only to private fire protection; method B expands the approach and requires the determination of fire flow demand for all buildings, whether they have sprinkler systems or not. Under method B, the total system capacity and facility costs related to fire protection are determined and then divided by the total fire demands from all properties in the protected area. Ideally, this method would include tax-exempt properties. This method would allow utilities to directly charge the properties without relying on municipal property taxes. All charges would be based on the property’s design or needed fire flow. This method is intended to create incentives to install private fire protection systems, thereby reducing system demands and providing greater public benefits. Conceptually, the task force favored method B but had insufficient time to test its effects or analyze its implications. Because its implementation would require change to Maine’s statutes relating to fire protection charges, the task force recommended that a legislative task force be created to analyze this option in greater depth. In addition, the utility and municipal members of the task force were concerned that implementation and administration of method B could be expensive and cumbersome. The two co-chairs of the task force have discussed trying method B on a demonstration basis with one or two utilities in the near future. Several task force members issued a minority report, which was included in the task force report. This minority report stated a clear preference for method B over method A. Maine PUC endorses recommendations In response to the report of the task force,11 the Maine PUC issued an Order Adopting the Task Force Recommendations14 on Mar. 26, 1996. The PUC initiated a rule-making to adopt method A, demandbased private fire protection. In its March 1996 order, the PUC instructed its staff members to draft proposed rules to implement method A. The order expresses the PUC’s desire to not immediately force the new method on all water utilities and to develop a workable method that does not burden the state’s utilities. The PUC also endorsed the recommendation that method B be further developed and investigated. Recognizing the work and effort of members of the private fire protection task force, the PUC invited them to continue analysis with a broad representation of other interested parties. Conclusion The Maine PUC has once again taken steps to help define appropriate levels and mechanisms for fire pro- tection charges. Basing private fire service charges on the fire demands of specific customers may cause some initial administrative concerns and confusion. As with most new ideas, these initial concerns are expected to lessen over time. In the long run, it is hoped that the ideas developed by the task force will become accepted by and useful to a wide range of water suppliers. References 1. Water Rates and Related Charges. Manual M26, AWWA, Denver (1986). 2. Water Rates. Manual M1, AWWA, Denver (3rd ed., 1983). 3. Docket 91-162, Maine PUC, Augusta, Maine (1991). 4. Water Rates. Manual M1, AWWA, Denver (4th ed., 1991). 5. Order of Maine PUC, Augusta, Maine (May 4, 1992). 6. Docket 92-091, Maine PUC, Augusta, Maine (ongoing). 7. Docket 92-285, Maine PUC, Augusta, Maine (ongoing). 8. Docket 94-285, Maine PUC, Augusta, Maine (Aug. 1994). 9. Order of Maine PUC, Augusta, Maine (Apr. 11, 1995). 10. Notice of Invitation, Docket 94-285, Maine PUC, Augusta, Maine (May 23, 1995). 11. Recommendations to Maine PUC of Fire Protection Task Force (Jan. 10, 1996). 12. Standard for the Installation of Fire Sprinkler Systems in One- and Two-Family Dwellings and Mobile Homes. Natl. Fire Protection Assn., Patterson, N.Y. (1991). 13. Report of the Maine Water Utilities Association Committee on Fire Protection Charges. Jour. Maine Water Utilities Assn., 3:35 (Mar. 1961). 14. Order of Maine PUC, Augusta, Maine (Mar. 26, 1996). 15. Chapter 69 of Maine statutes, Augusta, Maine (1987). About the authors: Christopher P.N. Woodcock is president of Woodcock & Associates Inc., 231 Boston Post Rd., POB 118, Wayland, MA 01778, a utility rate and financial consulting firm. He was engaged by the Maine PUC to advise the task force. He is the primary author of the sections on fire protection charges in AWWA’s Manual M26, and his work has been published in several professional journals. Woodcock is chair of AWWA’s Rates and Charges Subcommittee and is active in the New England Water Works Association and Water Environment Federation. He holds a BS in engineering and a BA in economics, both from Tufts University, Medford, Mass. Normand R. Lamie is general manager of the Auburn Water District, 268 Court St., POB 414, Auburn, ME 04212-0414. Copyright (C) 1996 American Water Works Association OCTOBER 1996 59