GENSET PAD PLAN GENSET PAD SECTION

advertisement
9'-0" MIN, SEE NOTE 1
GENSET PER ELECTRICAL
DRAWINGS
CONCRETE SLAB ON GRADE18" THICK W/#4 AT 12" EACH
WAY TOP AND BOTTOM
STANDBY GENSET WITH
SOUND INCLOSURE
SLAB PER PLAN
10" MIN,
TYP
EPOXY DOWEL SEE NOTE 1
2"
CLR
A
-
TYP
1'-0", TYP
6",
TYP
FINISH GRADE
1'-0"
TYP
3" CLR,
TYP UNO
STANDARD HOOK, TYPICAL
4'-0" MIN, SEE NOTE 1
NOTES:
NOTES:
1.
INSTALL 12"Ø THREADED ROD, ASTM F593, W/4" MIN EMBED INTO SLAB
USING HILTI HIT-RE 500-SD EPOXY ANCHORING SYSTEM, INSTALL
ANCHOR AT EACH MOUNTING HOLE PROVIDED IN EQUIPMENT.
2.
SEE
1.
MINIMUM DIMENSIONS INDICATED FOR BID PURPOSES,
CONTRACTOR TO VERIFY ACTUAL EQUIPMENT DIMENSIONS
WITH EQUIPMENT MANUFACTURER AND INCREASE SIZES AS
NEEDED.
3
S-502
2
A
GENSET PAD SECTION
-
1
0
1/2'
1'
GENSET PAD PLAN
-
2'
0
1"=1'-0"
Reuse of Documents
Drawn
This document and the ideas and designs incorporated
herein, as an instrument of professional service, is the
property of GHD Inc. and shall not be reused in whole or
in part for any other project without GHD Inc.'s written
authorization. © GHD Inc. 2012
No
Revision
Plot Date:
Note: * indicates signatures on original issue of drawing or last revision of drawing
31 December 2012 - 3:03 PM
Plotted by: Chris Richards
Drawn
Cad File No:
Date
N:\US\san francisco\Projects\10344 sf dpw\8410177 sfdpw firestation 6 egu replacement\06-CAD\Sheets\103448410177 S501.dwg
1'
2'
SEB
Designer CSC
Client
Project
Drafting CAR
Check
GHD Inc.
Job
Project
Manager Director
1/2'
1"=1'-0"
718 Third Street Eureka California 95501 USA
T 1 707 443 8326 F 1 707 444 8330
W www.ghd.com
Design
Check
CSC
Approved
(Project Director)
Date
Scale
AS INDICATED
Title
Contract No.
This Drawing shall not be used
for Construction unless Signed
and Sealed For Construction
Original Size
7437A-1
S-501
Sht
5
of
12
-
SHEET GENERAL NOTES
2
1
3
(N) JUNCTION BOX
(BELOW (E) MCB)
6"
FROM EDGE
2
(E) POWER PANEL 16
15
(E) EGU CONTROL PANEL
AND METERING
N(ATS)
6
LB
LB
SEE SHEET E-501 FOR DETAILS.
3.
SEE SHEET E-601 FOR SINGLE LINE DIAGRAM.
4.
MAINTAIN 5-FOOT MINIMUM CLEAR SPACE BETWEEN GENERATOR FUEL TANK AND
BUILDING IN ACCORDANCE WITH NFPA 30 T22.4.1.1(B).
5.
PAINT EXPOSED CONDUIT TO MATCH ADJACENT SURFACES.
6.
PATCH UNUSED OPENINGS AND REPAIR DAMAGE PER SPECIFICATIONS.
15
(E) METER MAIN
TO CELL TOWER
ON ROOF, N.I.C.
(N) AUTOMATIC
TRANSFER SWITCH
3
(E) MAIN CIRCUIT BREAKER
1
24" AFF
J-BOX (BEHIND
GUTTER)
2.
(E) JUNCTION
BOX
4
(N) WIRE GUTTER
MIN 4" AFF
2
SEE SHEET E-101 FOR ADDITIONAL INFORMATION ON CONDUIT ROUTING.
14
A
5
4
1.
(E) SERVICE METER
KEYNOTES
14
(E) MAIN PANELBOARD
EDGE OF WALL (APPROX)
15
3
REMOVE TILE BEHIND GUTTER AS REQUIRED
FOR INSTALLATION. CLEAN, PATCH, AND
PAINT REMAINING EXPOSED SURFACE.
(N) WIRE GUTTER
1
ENLARGED PLAN
SERVICE AREA
2
ROUTE INTERIOR CONDUIT
ALONG ORIGINAL PATH.
2.
PROVIDE (N) 6"x6"x6"-DEEP JUNCTION BOX IN WALL BELOW (E) PULLING COMPARTMENT
(BELOW (E) MAIN CIRCUIT BREAKER).
3.
PROVIDE (N) 6"x6"x48", MIN. 10 GAUGE SHEET METAL WIRE GUTTER ON WALL BELOW (E)
METER, (E) MAIN CIRCUIT BREAKER AND (E) MAIN PANELBOARD. ALIGN IN FRONT OF (N)
RECESSED JUNCTION BOX.
4.
PROVIDE LB AND CONDUIT BETWEEN (N) GUTTER AND (N) ATS. SEE SINGLE LINE
DIAGRAM FOR CONDUCTOR AND CONDUIT SIZES. ROUTE CONDUIT/FITTING TIGHT TO
WALL.
0
1'
2'
5.
PROVIDE CONDUIT BETWEEN (N) ATS AND (E) MAIN PANELBOARD. SEE SINGLE LINE
DIAGRAM FOR CONDUCTOR AND CONDUIT SIZES.
6.
PROVIDE (N) SURFACE MOUNT EGU ANNUNCIATOR PANEL ON WALL. MOUNT CENTER OF
(N) EGU ANNUNCIATOR PANEL AT +44" AFF.
7.
PROVIDE CONCRETE PAD FOR (N) EGU. COORDINATE EXACT DIMENSIONS AND
PENETRATIONS WITH EGU VENDOR. CONCRETE PAD DIMENSIONS SHALL BE 12" WIDER
AND LONGER THAN EGU (6" EACH SIDE).
8.
PROVIDE GROUND ROD TEST WELL ADJACENT TO CONCRETE PAD. SEE DETAILS SHEET
E-501.
9.
COORDINATE EXACT LOCATIONS OF CONDUIT STUB-UPS WITH MANUFACTURER SHOP
DRAWINGS.
10.
PROVIDE (N) EMERGENCY GENERATOR UNIT, SUB BASE TANK, AND MOUNTING
ACCESSORIES AND MOUNT ON CONCRETE PAD. SEE SINGLE LINE DIAGRAM AND
SPECIFICATIONS FOR EQUIPMENT RATINGS.
11.
PROVIDE GENERATOR FRAME GROUND. SEE DETAIL 1/E501 FOR CONNECTION
BETWEEN EGU FRAME, REBAR AND CU GND ROD.
12.
PROVIDE (N) NEMA 3R JUNCTION BOX ABOVE WINDOW. ROUTE CONDUIT AROUND
WINDOW. AVOID CONFLICT WITH (E) WALL-MOUNTED LIGHT.
13.
PROVIDE (N) JUNCTION BOX MOUNTED TO CEILING IN OFFICE.
14.
PROVIDE 1-1/2" CONDUIT FOR EGU EMERGENCY FEEDER BETWEEN (N) EGU AND (N)
ATS. SEE SINGLE LINE DIAGRAM FOR CONDUCTOR SIZES.
15.
PROVIDE CONTROL WIRING BETWEEN (N) EGU, (N) EGU ANNUNCIATOR PANEL, AND (N)
ATS IN MINIMUM 1-1/4" CONDUIT. COORDINATE WIRE TYPE AND QUANTITY WITH EGU
MANUFACTURER.
16.
PROVIDE (2) #12 AWG AND #12 GND IN MINIMUM 1" CONDUIT FROM (N) EGU BACK TO (N)
CIRCUIT BREAKER IN (E) POWER PANEL FOR (N) EGU BATTERY CHARGER AND JACKET
HEATER.
17.
REUSE (E) BRICK SALVAGED DURING DEMOLITION TO FILL AREA AROUND GENERATOR
PAD. FOLLOW EXISTING PATTERN AND RESTORE SURFACE TO ORIGINAL CONDITION.
4'
1/2"=1'-0"
2
3
(N) JUNCTION BOX 13
12 (E) WINDOW
6
(E) DOOR
E-501
(N) JUNCTION BOX 12
(E) WALL-MOUNTED LIGHT
TURN CONDUIT UP WALL TO +96"
AFG APPROX. (ABOVE WINDOW)
F
PROVIDE (N) AUTOMATIC TRANSFER SWITCH ON WALL AS INDICATED. SEE SINGLE LINE
DIAGRAM AND SPECIFICATIONS FOR EQUIPMENT RATINGS. MOUNT BOTTOM OF ATS AT
+24" AFF.
16
SERVICE AREA ELEVATION
E
1.
HATCHED AREA INDICATES
5'-0" MINIMUM CLEAR
SPACE BETWEEN
BUILDING AND FUEL TANK
14
15
INSTALL CONDUIT
BELOW GRADE
16
MINIMUM CLEARANCE PER
GENERATOR MANUFACTURER
RECOMMENDATIONS
6"
9
(TYP.)
SALVAGED BRICK 17
8
(N) CONCRETE
GENERATOR PAD
6"
GROUND ROD
TEST WELL
7
4" CURB
(N) EGU 10
8'-0"
(E) WALL
48"
48"
3
ENLARGED PLAN
GENERATOR AREA
48"
(N) REMOVABLE BOLLARD
(TYP. OF 3)
0
1'
2'
4'
1/2"=1'-0"
Reuse of Documents
Drawn
This document and the ideas and designs incorporated
herein, as an instrument of professional service, is the
property of GHD Inc. and shall not be reused in whole or
in part for any other project without GHD Inc.'s written
authorization. © GHD Inc. 2012
No
Revision
Plot Date:
Note: * indicates signatures on original issue of drawing or last revision of drawing
31 December 2012 - 3:09 PM
Plotted by: Chris Richards
Drawn
Cad File No:
Date
N:\US\san francisco\Projects\10344 sf dpw\8410177 sfdpw firestation 6 egu replacement\06-CAD\Sheets\103448410177 E202.dwg
Designer CAR
Client
Project
Drafting BNB
Check
GHD Inc.
Job
Project
Manager Director
SMG
718 Third Street Eureka California 95501 USA
T 1 707 443 8326 F 1 707 444 8330
W www.ghd.com
Design
Check
BNB
Approved
(Project Director)
Date
Scale
1/4" = 1'-0"
Title
Contract No.
This Drawing shall not be used
for Construction unless Signed
and Sealed For Construction
Original Size
7437A-1
E-202
Sht
10
of
12
-
SHEET GENERAL NOTES
1.
Reuse of Documents
Drawn
This document and the ideas and designs incorporated
herein, as an instrument of professional service, is the
property of GHD Inc. and shall not be reused in whole or
in part for any other project without GHD Inc.'s written
authorization. © GHD Inc. 2012
No
Revision
Plot Date:
Note: * indicates signatures on original issue of drawing or last revision of drawing
31 December 2012 - 2:53 PM
Plotted by: Chris Richards
Drawn
Cad File No:
Date
N:\US\San Francisco\Projects\10344 SF DPW\8410177 SFDPW Firestation 6 EGU Replacement\06-CAD\Sheets\103448410177 E701.dwg
Designer CAR
Client
Project
Drafting BNB
Check
GHD Inc.
Job
Project
Manager Director
SMG
CONTRACTOR TO COMPLETE PERMIT APPLICATION CHECKLIST FOR
DIESEL GENERATORS, DIESEL FIRE PUMPS, AND FUEL TANKS SERVING
GENERATORS AND FIRE PUMPS, LOCATED ON DRAWINGS E-701 AND
E-702. APPLICATION IS PARTIALLY COMPLETED WITH INFORMATION
AVAILABLE DURING DESIGN. CONTRACTOR TO REVIEW, UPDATE, AND
CORRECT AS NECESSARY FOR BUILDING DEPARTMENT.
718 Third Street Eureka California 95501 USA
T 1 707 443 8326 F 1 707 444 8330
W www.ghd.com
Design
Check
BNB
Approved
(Project Director)
Date
Scale
NO SCALE
Title
Contract No.
This Drawing shall not be used
for Construction unless Signed
and Sealed For Construction
Original Size
7437A-1
E-701
Sht
11
of
12
-
SHEET GENERAL NOTES
1.
Reuse of Documents
Drawn
This document and the ideas and designs incorporated
herein, as an instrument of professional service, is the
property of GHD Inc. and shall not be reused in whole or
in part for any other project without GHD Inc.'s written
authorization. © GHD Inc. 2012
No
Revision
Plot Date:
Note: * indicates signatures on original issue of drawing or last revision of drawing
31 December 2012 - 2:51 PM
Plotted by: Chris Richards
Drawn
Cad File No:
Date
N:\US\San Francisco\Projects\10344 SF DPW\8410177 SFDPW Firestation 6 EGU Replacement\06-CAD\Sheets\103448410177 E702.dwg
Designer CAR
Client
Project
Drafting BNB
Check
GHD Inc.
Job
Project
Manager Director
SMG
CONTRACTOR TO COMPLETE PERMIT APPLICATION CHECKLIST FOR
DIESEL GENERATORS, DIESEL FIRE PUMPS, AND FUEL TANKS SERVING
GENERATORS AND FIRE PUMPS, LOCATED ON DRAWINGS E-701 AND
E-702. APPLICATION IS PARTIALLY COMPLETED WITH INFORMATION
AVAILABLE DURING DESIGN. CONTRACTOR TO REVIEW, UPDATE, AND
CORRECT AS NECESSARY FOR BUILDING DEPARTMENT.
718 Third Street Eureka California 95501 USA
T 1 707 443 8326 F 1 707 444 8330
W www.ghd.com
Design
Check
BNB
Approved
(Project Director)
Date
Scale
NO SCALE
Title
Contract No.
This Drawing shall not be used
for Construction unless Signed
and Sealed For Construction
Original Size
7437A-1
E-702
Sht
12
of
12
-
Download