University of Massachusetts Amherst, Paige

advertisement
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
University of Massachusetts
Procurement Department
140 Hicks Way
407 Goodell Building
Amherst, MA 01003
May 2, 2013
Addendum #5
Contract Number: UMA 13-43
Project Number: 10-000916
Speedtype:
137715
Title: Paige Laboratory Renovations
The attention of the bidders submitting proposals for the above subject project is called to
the following addendum to the specifications and drawings. The items set forth herein,
whether of omission, addition, substitution, or clarifications, are all to be included in and
form a part of the proposal submitted.
The number of this Addendum (5) must be entered in the appropriate space “B. This bid includes
addenda numbered (list all addenda) ______” found on Page 51 – Form For General Bid, and/or Page
59 - Form for Sub-Bid “B. This sub-bid includes addenda numbered (list all addenda)_____.
CHANGES TO THE DRAWINGS:
1. General:
DRAWINGS
Reissued:
New:
None
None
SKETCHES
Issued:
Reissued:
ASK029, ASK030, ASK031, SSK001
None
2. Structural: The following changes relate to Bidder Question #75:
A. Section 2/ S-301:
-
Change title to read:
“SECTION FOR EXISTING OPENINGS WITH A MAXIMUM WIDTH OF 12” ONLY”.
-
Revise note to read:
“PLACE FORM AND SHORING BELOW & INFILL EXISTING OPENING w/ NW
CONCRETE (OPTION TO USE A 22 GA-9/16" GALV. FORM DECK TO BE
ATTACHED TO THE UNDERSIDE OF THE EXISTING SLAB w/ POWER DRIVEN
PINS @ 6" MAX. SPACING AROUND THE OPENING)”.
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
B. Key Note 2 on drawings S-201, S-202 and S-203 shall be revised to read:
“INFILL EXISTING FLOOR OPENING WITH S7. SEE 7/ S-300 SIMILAR.”
C. Key Note 3 on drawings S-201, S-202 and S-203 shall be revised to read:
“INFILL EXISTING FLOOR OPENING WITH NORMAL WEIGHT CONCRETE SLAB PER
TYPICAL INFILL DETAILS 2 OR 11 /S-301 AS APPLICABLE.”
D. Section 7/S-300: Note 1 shall be revised to read:
“SEE FRAMING NOTES ON CORRESPONDING FRAMING PLAN FOR TYPE OF SLAB
INFILL. PLACE DECK TO SPAN BETWEEN EXIST. PRIMARY SUPPORTS BELOW.
FASTEN FORM DECK TO PERIMETER STEEL FRAME BY #12 SELF TAPPING SCREWS
@ 12" O.C. (4 SCREWS MIN. ALONG EA. DECK EDGE).”
E. Section 12/ S-301: Note 1 shall be revised to read:
“SEE FRAMING NOTES ON CORRESPONDING FRAMING PLAN FOR TYPE OF SLAB
INFILL. PLACE DECK TO SPAN BETWEEN EXIST. PRIMARY SUPPORTS BELOW.
FASTEN FORM DECK TO PERIMETER STEEL FRAME BY #12 SELF TAPPING SCREWS
@ 12" O.C. (4 SCREWS MIN. ALONG EA. DECK EDGE).”
3. Structural: The following changes relate to Bidder Question #63:
a. Section 14/ S-301: Note specifying metal roof deck shall be revised to read:
“3”-18ga. GALV. METAL ROOF DECK TO BE FIELD WELDED TO W10 STEEL
BEAMS BELOW (2 SPAN TYPICAL).”
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
REVISIONS TO EXISTING SPECIFICATION SECTIONS:
1. Section 23 00 00, add the following paragraph 2.04. D. DIRECT BURIED PIPING
“D. DIRECT BURIED PRE-INSULATED PIPING
1. For direct-buried piping, pre-insulated, drainable, dryable systems are required. The following
systems are currently permitted to be bid on UMass Amherst projects:
a. Perma-Pipe / Ricwil Inc., Multi — Therm 500 System
b. Rovanco Piping Systems, Inc. — Insul 800 System
c. Tricon Piping Systems, Inc., Steel-Con Plus System
d. Thermacor Process, L.P., Duotherm 505 (HDPE) System
2. Service pipe and outer conduit miters may be implemented by the contractor in accordance with
the manufacturer’s recommendations but under no circumstances may the miter exceed 10
degrees.
3. The service pipe insulation for the pre-insulated direct-buried piping shall incorporate an additive
which makes it water repellent and water wicking resistant. Insulation product shall be tested in
affirmative compliance with the U.S. Navy’s “96 Hour Conduit Boiling Test” requirements. Each
service pipe shall be in a separate steel outer conduit. The conduit shall be ASTM A — 139
smooth wall, spiral or ERW welded steel, of sizes 10 gauge for up to 26” diameter, 6 gauge for
28-36” diameter, and 4 gauge for 38-42” diameter.
4. The steel outer conduit shall be insulated with spray applied polyurethane foam on all straight
lengths and fittings. The urethane foam shall meet ASTM C591 and have the minimum
characteristics of .18 K-factor, density of 2 pcf and a closed cell content of 90 to 95% with a
compressive strength of 40 psi. Quality assurance procedures for the foam insulation shall include
either a visual check prior to jacketing, infrared, or radiographic (x-ray) testing to insure there are
no insulation voids. Manufacturer shall provide documented test results, to include interpretation,
for infrared or radiographic testing for a minimum of all the piping on the first truckload
delivered to the project site. Testing shall be provided on at least one length of each size pipe as
well as at least one of each size pipe elbow and anchor. Additional truckloads shall not be
shipped until the University has accepted the test results. If the test results are rejected, insulation
must be corrected and new test results submitted. If any test is rejected, all product associated
with this project must be tested accordingly.
5. High density polyethylene (HDPE) factory installed jackets are required for all preinsulated
piping systems. HDPE jacket shall be a minimum of 150 mils thick for all pipe sizes.
6. Joint sealing system shall be CANUSA SuperCase CSC — X joint sealing system. Where service
pipe and outer conduit field miters between 3 and 10 degrees are necessary and are permitted by
the manufacturer, instead apply the CANUSA CSC—X WA wrap around joint sealing system
over the foam. The joint sealing system shall be fully certified to EN 489 requirements.
7. Keep the pipe system interior clean and dry at all times during installation. Grade top perimeter of
excavations to prevent surface water run-off into excavation. Maintain bottom of all excavations
stable, dry and free of water on a continual basis. Pipe shall be laid in the dry trench conditions.
At no time shall water in the trench be permitted to flow into the pipe system interior. Contractor
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
8.
9.
10.
11.
12.
PERKINS+WILL
UMA 13-43
May 2, 2013
shall anticipate the potential for existing water main breaks. At any time that Work is not in
progress, or the trench is unattended, the end of the pipe(s) shall be suitably closed to prevent the
entry of animals, earth, water etc. THE UNIVERSITY WILL NOT ACCEPT ANY PRE
INSULATED PIPING INTO WHICH WATER HAS ENTERED DURING CONSTRUCTION.
DRYING PROCEDURES ARE NOT ACCEPTABLE. ALL WET PIPING SHALL BE
REMOVED. Piping manufacturer shall submit a written warranty to the University, with copy to
the installing contractor, for the piping to be executed upon installation by the installing
contractor from the date of substantial completion for a period of ten years to repair piping
systems and replace components damaged by failure. Likewise, the installing contractor shall
submit a written warranty to the University for the field joints to be executed upon installation
from the date of substantial completion for a period of five years to repair field joints and replace
field joints damaged by failure.
a. A factory employed and certified field technician shall be required on site to provide
inspection during the critical periods of installation defined as:
b. Unloading of the first load of material.
c. Inspection of the initial trench and bedding.
d. Initial hydrostatic test for at least one section of piping.
e. Pouring of at least the first anchor blocks.
f. Final verification of pipe pitch.
g. Initial backfill of at least one area, but not necessarily all compacting.
h. Any other observations required by the manufacturer to provide required Warranty.
Provide two days of instruction on field joint construction to include both demonstration of field
joint construction methods as well as observation of at least the first two field joint installations
by construction staff
Factory Field Technician requirements:
a. Technically qualified, factory trained piping system installation instructor with a
minimum of five years of experience. If this instructor does not have experience
installing the specified CANUSA joint sealing system, a CANUSA factory trained joint
sealing system installation instructor shall also be provided for the duration of the field
joint construction inspection and instruction activity described above.
b. A resume shall be submitted to the Owner for approval. If the Owner does not approve
the proposed Technician, the Manufacturer shall submit an alternate for approval.
c. A substitute Technician shall not be provided unless approved in advance by the Owner.
At the Owners discretion, removal of the Technician may be requested, which will
require the Manufacturer to submit an alternate Technician for approval.
d. All costs associated with the Technician shall be included in the bid.
Manufacturer’s Sales
Representative requirements. Either the Factory Field Technician or the Manufacturer’s Sales
Representative shall provide the following additional inspections:
a. Unloading of remaining loads of material.
b. Hydrostatic test for all other piping.
c. Pouring of remaining anchor blocks.
A daily field report shall be required from the factory technician and sales representative detailing
work observed while on site. Field reports shall be submitted to the Installing Contractor and
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
Owners representative. Field reports shall include the condition and quality of materials used in
accordance with the contract documents and manufacturer’s written instructions. Field reports
shall also include any discrepancies, installation concerns, unsatisfactory work performed and the
Technician’s/Representative’s recommendations for appropriate and corrective action to be taken.
13. Upon completion of the pipe installation the contractor shall deliver to the Owners
Representative, a notarized certificate from the manufacturer stating that the installation has been
made in accordance with the manufacturer’s recommendations and warranty requirements.
Manufacturer’s Sales Representatives will not be acceptable to perform pipe installation
inspections identified above as being performed by the Factory Field Technician.
14. Pre-insulated piping manufacturers shall also include Thermal Stress Analysis as part of their
Scope of Services for the piping they provide. The thermal stress analysis shall be performed
using industry recommended software and an accompanying report shall be submitted to the
University prior to piping fabrication. Submittals shall include required concrete anchor sizes.
15. Pipe hangers, supports, anchors, alignment guides, expansion loops, expansion joints, and flexible
ball joints shall be specified and shown on design drawings. In steam manholes, tunnels, and
vaults it is preferred that pipe supports be attached to walls or to 4” high concrete pads, to keep
them above any liquid on the floor. Pipe supports may be suspended from cast in place manhole
roofs. Anchors shall be welded to the pipe, but anchor connection to the building structure must
be bolted. Provide structural support for all kinetic forces including seismic and wind loads.”
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
RESPONSE TO BIDDER QUESTIONS:
60. BIDDER QUESTION 060: On detail 4 -S-302 parapet bracing. Is this part of sub bid 051200 or
055100?
Parapet bracing is part of 05 12 00 Structural Steel Framing.
61. BIDDER QUESTION 061: In specifications section 055100 pg. 1 summary section A-20 stair
nosings, are nosing to be used for all exterior concrete treads and what is the design intent –
aluminum, galv?
No metal nosings at exterior stairs are required, see details on A11-21 and A11-22.
62. BIDDER QUESTION 062: Who supplies sump pit steel & grating? 055100 or others?
Sump pit steel and grating should be provided by 05 51 00 Miscellaneous Metal
Fabrications and Ornamental Iron.
63. BIDDER QUESTION 063: On drawing A11.23 detail 4 who provides canopy steel & framing?
See “Addendum 5 CHANGES TO THE DRAWINGS: 2. Structural” and ASK029,
ASK030, ASK031 and SSK-001 for revisions to North Canopy. Steel indicated in Structural
Drawings is part of 05 12 00 Structural Steel Framing. All other steel shown exclusively in
Architectural drawings to be in 05 51 00 Miscellaneous Metal Fabrications and Ornamental
Iron.
64. BIDDER QUESTION 064: Who supplies c10 ledger framing at new elevator?
Steel indicated in Structural Drawings is part of 05 12 00 Structural Steel Framing. All
other steel shown exclusively in Architectural drawings to be in 05 51 00 Miscellaneous
Metal Fabrications and Ornamental Iron.
65. BIDDER QUESTION 065: On drawing S-201, 202, 203, 204, col line D & E & G & F. Key
notes 4/5 Detail 4 S-301 OWJ framing – who supplies angles and plates?
Angles and plates in referenced locations shall be provided as part of 05 12 00 Structural
Steel Framing.
66. BIDDER QUESTION 066: In specifications 055100 pg.1 summary section A-6, 7 includes
supply and install wood rails, These will be supplied and installed by Section 062023 wood only?
Wood rails at interior stairs shall be provided and installed by 06 20 23 Interior Finish
Carpentry.
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
67. BIDDER QUESTION 067: On drawing S-202, Framing notes 9 – is this typical for all windows?
And what size angles are existing?
See Head Details on A00-61 and Exterior Elevations on A11-01 for locations of removal and
replacement of angles. Assume angles are 4” x 3 1/2” x 5/16”, field verify to match existing.
68. BIDDER QUESTION 068: On drawing A12-03, detail 1 specified on drawing A00-70, CODE
mtl2, what is the color intent of panels?
Clear anodized finish for Aluminum panels, see specification for more information
69. BIDDER QUESTION 069: Question regarding masonry infills in corridor – is toothing required
@ the C04 locations?
Yes, C04 indicates infill with terra cotta tile to match adjacent wall conditions, so toothing is
required.
70. BIDDER QUESTION 070: Could you please confirm that roof curbs for mechanical equipment
are provided by the HVAC sub? Note 1 for the roof detail on M04-03 calls for the GC to provide
roof curbs and flashing.
Roof curbs and flashing for duct penetrations as noted on M04-03 shall be provided by the
General Contractor. The GC shall also provide and coordinate the sleepers for the
condensing units to be installed on the roof.
71. BIDDER QUESTION 071: Who is responsible for removing the masonry, including toothing,
and existing lintels to be replaced at exterior locations noted on A11-01? It makes sense for the
mason to be responsible for all work associated with this detail. This is also shown on page S-302
and 2 and 5/ A00-61.
Masonry is responsible.
72. BIDDER QUESTION 072: Please clarify the extent of existing to remain metal bar joists that get
cleaned and painted. The only references to this work we can find are in 1 & 11/A10-53. Is this
limited to Lobby/ Lounge 299B? Also, who is responsible for the cleaning?
Cleaning and painting of Existing to Remain Bar Joists is limited to Lobby/Lounge 299B
and Elevator Lobby 199B. See Room Finish Schedule. Section 09 91 23 Interior Painting is
responsible for cleaning and preparation of bar joists to be painted.
73. BIDDER QUESTION 073: Detail 1/A10-53 shows 1” acoustic spray. Detail 11/A10-53 shows 1
½” acoustic spray. Please clarify where it changes from 1” to 1 ½” thickness?
Detail 11/A10-53 is revised to indicate 1” of acoustic spray insulation. Provide 1” thickness
of acoustic spray insulation at both locations.
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
74. BIDDER QUESTION 074: Addendum #2, Changes to Drawings, Item 5 references drawing
A10-20. That page is not in our set or listed on the Index of Drawings. Please clarify?
Item 5 of Addendum #2 is revised to reference A11-20.
75. BIDDER QUESTION 075: There is no metal deck shown for the concrete deck infills. Would it
make sense for either the misc. metals or structural steel sub to tack decking to the new support
steel at the perimeters of these infills instead of trying to form the concrete from below with
plywood?
See “Addendum 5 CHANGES TO THE DRAWINGS: 2. Structural” for clarification
relating to this question.
76. BIDDER QUESTION 076: The detail for the elevator penthouse slab does not show a pour stop
(5 & 6/S-300). Please advise if required and who provides it?
Yes, provide pour stop at elevator penthouse slab per Pour Stop Schedule 10/S101. 05 12 00
Structural Steel Framing shall be responsible for pour stop.
77. BIDDER QUESTION 077: Is the mason responsible for making the site seating in detail
10/A11-22?
Yes.
78. BIDDER QUESTION 078: Who is responsible for removing and modifying the existing bar
joists at the new elevator shaft location?
05 12 00 Structural Steel Framing shall be responsible for removing and modifying the
existing bar joists at the new elevator shaft locations. See Detail 4/S301.
79. BIDDER QUESTION 079: Please clarify who is responsible for salvaging and reinstalling
granite shown in detail 7/A11-21. Is this the work of the filed sub-bid mason?
Yes. Masonry.
80. BIDDER QUESTION 080: Please provide specs for the following: LPS piping 2-1/2”& larger?
LPC piping 2-1/2”& larger? MPS piping 2"& smaller? MPS piping 2-1/2"& larger? MPC piping
2"& smaller?
LPS piping shall be schedule 40, ASTM A-53, Type E, Grade B. On piping 2.5” and larger,
joints shall be Class 150 flanged or butt welded. On piping 2” and smaller, joints shall be
Class 150 flanged or butt welded. Threaded fittings and joints are allowed on piping 2” and
smaller, but schedule 80 piping must be used.
MPS piping shall be schedule 40, ASTM A-53, Type E, Grade B. On piping 2.5” and larger,
joints shall be Class 300 flanged or butt welded. On piping 2” and smaller, joints shall be
Class 300 flanged or butt welded. Shutoff duty valves 2” and small shall be socket weld,
800lb, gate valves.
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
All low pressure and medium pressure condensate piping shall be schedule 80, ASTM A-53,
Type E, Grade B with schedule 80 butt welding fittings of seamless steel or forged steel
socket weld fittings 2000 pounds WOG. Malleable iron unions and threaded fittings and
joints are allowed on piping 2” and smaller. Shutoff duty valves 2” and smaller shall be
socket weld, 800lb, gate valves.
81. BIDDER QUESTION 081: Is there a spec for the HVAC pipe insulation per 230000 2.6 for LPS,
MPS, LPC, MPC?
Refer to piping system types and temperatures in Table A in specification section 23 00 00
paragraph 2.06.
To clarify, all steam and condensate pipe insulation on pipe 2” and larger shall be 3”
thickness. All steam and condensate pipe insulation on pipe 1.5” and smaller shall be 1.5”
thickness.
82. BIDDER QUESTION 082: Is there a spec for the buried 6”CHWS&R on C-100?
Refer to the added specification section 23 00 00 paragraph 2.04.D, included in this
Addendum 5.
83. BIDDER QUESTION 083: Does the 230000 HVAC filed-sub bidder own the buried
6”CHWS&R on C-100?
Per Drawing M02-01, the HVAC contractor shall own buried 6” CHW&R piping 10’ from
building.
84. BIDDER QUESTION 084: Has most demolition been completed and/or awarded under a
separate contract? If most demolition has been awarded separately, how does the abatement
Appendix A&B in back of book 3 of 3 refer to this contract?
Required demolition is indicated on Demolition Drawings. There was an early Demo
Package that will be complete by early May. Demolition to be performed as indicated on
Demolition Drawings such as Window Removal is called for in the Abatement Report
Appendix A.
85. BIDDER QUESTION 085: Please clarify which section/trade owns epoxy floor type EP-1 as
indicated in room finish schedule in A00/70? Finish legend shows vendor/manufacturer option as
Stonehard, who's product and specification is described in Section 092763-Resinuos Flooring,
2.1, A, 34. This Section not being part of Section 09 00 03 - Painting. Please direct?
Epoxy Floor type EP-1 shall be provided by 09 67 23 Resinous Flooring.
86. BIDDER QUESTION 086: Please confirm exposed steel column shown in Mechanical Room
113 / A04-01 (F-2A Level 1) will not require intumescent painting or ptd gwb enclosure?
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
Construction Note 01 applies to Stl Column at F-2A on Level 1 (see Addendum 2 Changes
to the Drawings, Item 2.a.) Yes, Provide Ptd GWB enclosure at Stl Column at F-2A on
Level 1.
87. BIDDER QUESTION 087: Please clarify the work required for connecting to the existing Acid
Waste System?
Answer: The acid waste neutralizing system located on the lower level is an existing to
remain system. During the demolition phase, piping draining to this system was
disconnected at the 4” inlet to the tank and removed entirely. The piping is now capped.
The scope of work includes all new acid waste piping shown on the drawings in its entirety.
This piping will connect to the 4” capped connection. There is also an existing acid waste
sump pit in the same room as the neutralizing system. This pit received waste underground
from all fixtures on the lower level and then pumped it up into the neutralizing tank. This
pit will now receive new underground acid waste piping as shown on the drawings. Finally,
the sump pit pump, acid neutralization system, and all appurtenances will need to be
restarted and tested to ensure proper working functionality.
88. BIDDER QUESTION 088: Please find out what UMass wants for a transformer. The spec
header says dry type and that is the norm @ UMASS but the spec reads as an oil filled unit.
Please advise which one they want?
Answer: Dry Type
89. BIDDER QUESTION 089: There was added gas piping in one of the addendums, but there is no
spec for turrets. Please provide.
Answer: The gas turrets to be located on the walls adjacent to the lab benches shall be a
Chicago Faucets model #986-937CHAGVCP, wall mounted single needle valve with wall
flange or equal.
90. BIDDER QUESTION 090: Please provide specs for the following items related to the RO
system: RO faucet/outlet, RO pipe and fittings.
Answer: RO pipe and fittings shall be unpigmented Type 1 homopolymer polypropylene
with socket fusion fittings or equal. RO faucet shall be a Chicago Faucets model #869BPVC, deck mounted type.
91. BIDDER QUESTION 091: Is the RO water system existing? Please clarify the work required
for the installation of the RO system.
Answer: The RO water system is an existing system that is currently located on the lower
level. Drawing P01-01 notes the location and that it is to be relocated. The scope of work
includes all new RODI water piping shown on the drawings in its entirety. This piping will
connect to the existing relocated RODI water system as shown on the plans. Finally, the
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
existing RODI water system shall be restarted and tested to ensure proper working
functionality.
92. BIDDER QUESTION 092: Detail 6/A10.60 shows three tiers of shelving at the typical mobile
benches when viewed from the front, but only two tiers when viewed form the side. Which is
correct?
Provide 2 tiers of adjustable shelving above mobile workbenches.
93. BIDDER QUESTION 093: Card readers have been shown for all perimeter doors except for the
east exterior entrance on level 2, it is next to the east stairwell 299D. Do you want a reader to
control access on this perimeter door as well?
See Door Schedule. Hardware Set 01 is indicated for Door 299G-1 at East Entry, which
includes a Card Reader.
94. BIDDER QUESTION 094: Are all readers and access control equipment to be the UMass
Amherst standard SOFTWARE HOUSE?
Yes.
95. BIDDER QUESTION 095: Door contacts have been shown but Rex Pir motion detectors used to
shunt alarms on exit are missing, the standard is model DS150i do you want them included for
each door?
Motion Detectors are not required.
96. BIDDER QUESTION 096: Are any of the card access doors going to be equipped with handicap
door operators?
Yes, Hardware Set 05 is indicated for Door 199F-1. See Door Schedule.
97. BIDDER QUESTION 097: Door 101-1 is shown on the Door Schedule to receive a new frame.
It is not shown on the demolition plan to remove the existing frame. Please clarify.
Existing frame at Door 101-1 location shall be removed.
98. BIDDER QUESTION 098: Door 101-2 is shown on the floor plans as a pair of doors. Door 1012 is indicated on the Door Schedule to receive frame Type 2 – a single door with a side-lite.
Which is correct?
Door 101-2 is a pair of doors and should be Frame Type 1.
99. BIDDER QUESTION 099: Door 207, 210 and 218 are shown on the Door Schedule to receive a
new frame. It is not shown on the demolition plan to remove the existing frame. Please clarify.
Existing frame at Door 207, 210, and 218 shall be removed.
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
100. BIDDER QUESTION 100: There is not a metal frame indicated on the Door Schedule for the
cased openings to 299N and 299M, from Lounge 299B. Please clarify what is required for
“Metal Frames” at these locations.
See Detail 2/A10-51 for typical detail at opening into 299 M and 299N.
101. BIDDER QUESTION 101: Door 307 and 318 are shown on the Door Schedule to receive a new
frame. It is not shown on the demolition plan to remove the existing frame. Please clarify.
Existing frame at Door 307, and 318 shall be removed.
102. BIDDER QUESTION 102: Addendum 2 changed the door frame type at Door #316 to Type 3.
Should it have been Door #315?
Door 316 shall be Frame Type 1. Door 315 shall be Frame Type 3.
103. BIDDER QUESTION 103: There is not a metal frame indicated on the Door Schedule for the
new cased openings to 399N and 399M, from Lobby 399B. Please clarify what is required for
“Metal Frames” at these locations?
See Detail 2/A10-51 for typical detail at opening into 399 M and 399N.
104. BIDDER QUESTION 104: Series of related questions regarding Louver infill Details:
a. Structural Detail 5/S-302 indicates to use 8” CMU back-up. Architectural detail 3/A11-24
indicates to use “Clay Tile”. Which is correct?
Yes. CMU is acceptable where not visible (Updates Response to Bidder Question 53
in Addendum 3).
b. Structural Detail 4/S-302 indicates to “Remove the Lintel”. Architectural detail 3/A11-24
shows the lintel to remain. Which is correct?
Architectural detail 3/A11-24 is revised to show lintel to be removed.
c. If the louver lintel is to be removed, is this by the Mason FSB?
Yes.
105. BIDDER QUESTION 105: Typical structural wall infill details indicate to use CMU. This
contradicts some of the architectural details. Which is correct?
CMU is acceptable where not visible. See Architectural Drawings for locations of Terra
Cotta Tile infill to match existing adjacent walls.
University of Massachusetts Amherst, Paige Laboratory
161 Holdsworth Way, Amherst, MA 01003
Addendum #5
PERKINS+WILL
UMA 13-43
May 2, 2013
106. BIDDER QUESTION 106: Addendum 1 deleted glass type GL-6, fire rated glazing. The door
schedule on page A00-50 of the drawings show many type G doors having a 45 minute rating.
Please advise as to what type of glass is to be used in the doors with a fire rating considering the
fire rated product listed in the specifications was deleted?
Fire Rated glass is not required for Lites in Door Type G (lites shall be 4” x 24” which is
under 100 square inches)
107. BIDDER QUESTION 107: None of the doors, hollow metal frames or storefront specify a glass
type to be used. Please provide information regarding what glass type is used in each door,
frame and storefront?
Door Type A: GL-2
Door Type B: GL-2
Door Type E: GL-2
Door Type G: GL-2
Sidelites in Frame Type 2 and 3: GL-2
Window Type N, M, P: GL-1
Glazing in Storefront shown on A11-30 (Vestibule 299H): GL-2
108. BIDDER QUESTION 108: Please clarify the flexible membrane strips at masonry openings in
spec. section 072100 Thermal Insulation vs. the modified bituminous strip air barriers in spec.
section 072713. For example, we are looking at details 5 and 6/ A11-24: is it your intent to have
the membrane strip shown here installed by the insulation contractor or by the filed sub-bid
waterproofer. Also referring to details 1 and 2/A11-24 is it your intent to have the peel and stick
new AV barrier installed by the filed sub-bid waterproofer?
Membrane strip shown in details 5 and 6 on A11-24 shall be installed by the filed sub-bid
waterproofer. Peel and Stick AV barrier shown in details 1 and 2 on A11-24 shall be
installed by the filed sub-bid waterproofer.
End of Addendum #5
By: John O. Martin
Director of Procurement
P E R KI NS
+ WILL
225 Franklin Street, Suite 1100
Boston, MA 02110
t 617.478.0300
f 617.478.0321
www.perkinswill.com
E
D
UNIVERSITY OF
MASSACHUSETTS
DESIGN AND CONSTRUCTION
MANAGEMENT
5
PAIGE
LABORATORY
RENOVATIONS
A11-23
3
4
5' - 4"
A10-52
A11-24
DEMO EXISTING
161 Holdsworth Way
Amherst, MA 01003
LEVEL 02
111' - 0"
FINISHED METAL PANEL,
FLAT & CORRUGATED SURFACE
DEMO
RAIN LEADER, BEHIND
SCREEN WALL
2' - 6"
PTD GALV STEEL BEAMS,
SEE STRUCTURAL
5/1/2013 2:29:51 PM
c:\temp\155081.000 - Paige Laboratory (CENTRAL)_currans.rvt
ALUM STOREFRONT
ENTRY DOORS & FRAME
8
Sheet Information
A11-23
Date
05.02.13
Project Number
10-000916
Contract Number
Drawn
UMA 13-43
Author
Checked
Checker
Approved
Approver
Reference Sheet
A11-23
Title
LEVEL 01
100' - 0"
1
NORTH ENTRY - ELEVATION
3/8" = 1'-0"
NORTH ENTRY
ELEVATION
Sheet
ASK029
Copyright © 2012 Perkins+Will
P E R KI NS
+ WILL
225 Franklin Street, Suite 1100
Boston, MA 02110
t 617.478.0300
f 617.478.0321
www.perkinswill.com
UNIVERSITY OF
MASSACHUSETTS
6' - 10
6' - 10
DESIGN AND CONSTRUCTION
MANAGEMENT
1/2"
PAIGE
LABORATORY
RENOVATIONS
1/2"
161 Holdsworth Way
Amherst, MA 01003
PTD GALV STEEL BEAMS,
SEE STRUCTURAL
EXPOSED, PTD GALV
METAL DECK
c:\temp\155081.000 - Paige Laboratory (CENTRAL)_currans.rvt
4
Sheet Information
05.02.13
Project Number
10-000916
Contract Number
Drawn
UMA 13-43
Author
Checked
Checker
Approved
Approver
Reference Sheet
A11-23
Title
NORTH ENTRY
CANOPY REFLECTED
CEILING PLAN
D
5/1/2013 2:29:51 PM
Date
1
E
ENLARGED REFLECTED CEILING PLAN @ NORTH ENTRY CANOPY
3/8" = 1'-0"
F
Sheet
ASK030
Copyright © 2012 Perkins+Will
P E R KI NS
+ WILL
225 Franklin Street, Suite 1100
Boston, MA 02110
t 617.478.0300
f 617.478.0321
www.perkinswill.com
UNIVERSITY OF
MASSACHUSETTS
DESIGN AND CONSTRUCTION
MANAGEMENT
PAIGE
LABORATORY
RENOVATIONS
3
1
ASK029
A11-23
5
6' - 10
1/2"
161 Holdsworth Way
Amherst, MA 01003
A11-23
1/2"
6' - 10
EQ
EQ
EQ
EQ
3 7/8" / 12"
"
13' - 9
EQ
EQ
EQ
3 7/8" / 12"
PTD GALV STEEL BEAM & STL
PLATE, BOLT CONNECTION
AT MASONRY WALL & BEAM,
SEE STRUCTURAL
6
A11-23
RD
FLAT SEAM METAL ROOFING
METAL PANEL INTEGRAL
GUTTER CAP PIECE,
CAULK IN PLACE
c:\temp\155081.000 - Paige Laboratory (CENTRAL)_currans.rvt
9
A11-23
EQ
EQ
4
Sheet Information
Date
05.02.13
Project Number
10-000916
Contract Number
Drawn
UMA 13-43
Author
Checked
Checker
Approved
Approver
Reference Sheet
A11-23
Title
NORTH ENTRTY
CANOPY ENLARGED PLAN
VIEW
D
E
F
5/1/2013 2:29:52 PM
Sheet
1 ENLARGED PLAN VIEW OF NORTH CANOPY
3/8" = 1'-0"
ASK031
Copyright © 2012 Perkins+Will
PE RKI NS
+ WI L L
D
E
F
225 Franklin Street, Suite 1100
Boston, MA 02110
t 617.478.0300
f 617.478.0321
www.perkinswill.com
14
H.D. GALV. W10x22
CANTILEVERS (3 TOTAL)
S-301
UNIVERSITY OF
MASSACHUSETTS
CONT. H.D.
GALV. W14x13
SEE ARCH DWG
S6
x13
T
CON
W4
ALV.
CONT. H.D.
GALV. MC4x13.8
H.D. GALV.
MC10x15.3
.G
. H.D
1/2" x 9"x9" HD GALV. STEEL
PLATE w/ (4) 3/4" DIA. GALV.
EPOXY ANCHOR w/ 8"
EMBEDMENT.
DESIGN AND CONSTRUCTION
MANAGEMENT
PAIGE
LABORATORY
RENOVATIONS
161 Holdsworth Way
Amherst, MA 01003
4
(2) W8x24 STEEL LINTEL
ABOVE NEW OPENING BELOW
KEY NOTE 5
NEW C8x13.7
SUSPEND END OF W10x22
TO EXIST. 12WF31 (F.V.)
SEE 15/ S-301
SUSPEND END OF W10x22
TO EXIST. 6 I 12.5 (F.V.)
EXIST. 6I 12.5
EXIST. 12WF31
S5
NEW MC10x25
KEY NOTE 4
7
S-300
Sheet Information
10-000916
UMA 13-43
Author
Checked
Checker
Approved
Approver
Reference Sheet
F
8W
58
05.02.13
Project Number
Drawn
S3
EXIST. 14WF38
Date
Contract Number
S7
S1
S-201
Title
NORTH ENTRY
CANOPY
58
8W
F
EXIST. 14WF34
L6x4x3/8
HANGER EA.
END
NEW MC10x25
NEW MC10x25
40
EXIST. 14WF34
S1
NEW MC10x25
BELOW
F
8W
3
EXIST. STEEL
OWJ (F.V.)
NEW MC10x25
NEW MC10x25
C12x25
NOTES:
1.
1
PARTIAL EXISTING LEVEL 2 FRAMING PLAN & ALTERATIONS
Scale: 3/16" = 1'-0"
0
2
4
6
8
10 FT
2.
THIS PARTIAL FRAMING PLAN PROVIDES FRAMING INFORMATION FOR
THE NORTH CANOPY ONLY. SEE DRAWING S-201 FOR ALL OTHER
INFORMATION NOT SHOWN OR NOTES.
S6 INDICATES NEW 3" - 18 Ga GALVANIZED METAL ROOF DECK. THE
ORIENTATION OF DOUBLE ARROWS INDICATES THE DIRECTION OF
THE SPAN OF THE METAL ROOF DECK.
Sheet
SSK 001
Date: 5/1/13
File name: Paige-S-Plans_May01-13.vwx
© LY Consulting Engineers, Inc. 2013
Download