BD-FP Central Data Bank List of Building Materials A. General Department: Buildings Type of building material: Fire protection materials for structural use Applications: For protection of structural elements to resist the action of fire for the specified periods B. Acceptance criteria Testing standards: Fire test/assessment should be carried out in accordance with BS 476: Parts 20 to 24: 1987. Conditions of Acceptance: • To satisfy section 6.5 of the Code of Practice for Fire Resisting Construction 1996, valid and full fire test/assessment report shall be submitted to demonstrate that the concerned product or material has been tested in accordance with or assessed against BS 476: Parts 20 to 24: 1987 by a laboratory accredited under HOKLAS or recognized under mutual recognition agreements/arrangements with HOKLAS, or one of the assessing organizations listed in PNAP 251. • Details of application such as surface preparation, application of primer, top coating etc, shall be strictly in accordance with the manufacturer’s specifications/recommendations and are compatible with those adopted in the fire tests. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Bollom Fireshield J.W. Bollom & Company Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 001 Details of Test or Assessment Report Intumescent Coating Protection of steel I-beams up to 11/2 hrs. FRP; steel I-columns, CHS & RHS columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1991. Validity Date Report CC81169 May 1991 May 1993 Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire protection coating should be in accordance with appendix 2 of the report no. CC81169. BD-FP 002 Cafco 280, 800 & Cafco Blaze-Shield Isolatek International (See remarks) Cementitious mineral fibre Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council 376.3 December 1993 January 1997 18/01/2005 No-objection letter issued in 1994. Updated information on place of manufacture to be provided by the manufacturer. Thickness of fire protection material should be in accordance with data sheets attached to BD’s letter Ref. (37) in BD GR/BM/2(23). Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Cafco 280 Cafco Europe Sarl Foetz, Luxembourg Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 003 Details of Test or Assessment Report Cementitious mineral fibre Upgrade structural concrete slab up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Centre Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1996. Validity Date Report WFRC No. C81024 January 1994 March 1998 BS 8110: Part 2: 1985 Required thickness of fire protection material should be in accordance with Tables 1, 2 & 3 in the assessment report WFRC No. C81024. Both structural stability and insulation requirements should be considered and the higher of the thickness applied. BD-FP 004 Cape Supalux Board Cape Building Products Limited (See remarks) Fibre reinforced calcium silicate board 2 hrs. fire protection to timber floor in terms of load bearing capacity, integrity and insulation. As the system does not form an integral part of the structure, the actual application and acceptability of the system should be considered on a job-by-job basis. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council TE6640 January 1989 N/A 18/01/2005 No-objection letter issued in 1993. Updated information on place of manufacture to be provided by the manufacturer. The fire protection system shall be as described in the report no. TE6640. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Cape Supalux Board Cape Building Products Limited Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 005 Details of Test or Assessment Report Fibre reinforced calcium silicate board. (See remarks) Protection of steel beams and columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report CC82875 February 1993 February 1996 Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire protection material should be in accordance with Tables 9 to 18 in the report no. CC82875. BD-FP 006 Cape Vermiculux Board Cape Building Products Limited (See remarks) Vermiculux board Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A Building Research Establishment The Loss Prevention Council FRS.3/06/15 FCA/MEF CC82017D RHE/MB March 1981 December 1991 18/01/2005 December 1994 No-objection letter issued in 1992. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting board shall be in accordance with BRE’s assessment letter ref. FRS.3/06/15FCA/MEF . Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Cape Vermiculux Board Cape Building Products Limited (See remarks) BD-FP 008 Conlit 100 Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 007 Details of Test or Assessment Report Vermiculux board Protection of fixed by expansion R.C. slabs up to bolts with or without 4 hrs. FRP. steel hat-sections. As the system does not form an integral part of the structure, the actual application and acceptability of the system should be considered on a job-by-job basis. Rockwool Limited Resin bonded rock fibre insulation (See remarks) board Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1992. Validity Date Report CC10626/R HE November 1990 November 1992 BS 8110: Part 1: 1985 Updated information on place of manufacture to be provided by the manufacturer. The fire protection system shall be as described in the report no. CC10626/RHE. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council CC10806/R HE, CC81338A/ RHE August 1989 May 1991 18/01/2005 May 1993 No-objection letter issued in 1991. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting board shall be in accordance with the data indicated in “Fire Protection for Structural Steel in Buildings (2nd Edition)” published by the Association of Structural Fire Protection Contractors and Manufacturers Ltd. (ASFPCM). Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Conlit 150 & 150P Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 009 Details of Test or Assessment Report Rockwool Limited Mineral fibre fire-resisting board (See remarks) Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report CC81338 May 1991 N/A Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Figures 1 & 2 in the report no. CC81338. BD-FP 010 Cryosil Cryotherm Insulation Limited (See remarks) Silicate bonded vermiculite board Protection of steel beams and columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council CC81951 December 1991 December 1994 18/01/2005 No-objection letter issued in 1992. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Figure 1 in the report no. CC81951. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Floor (System) Cape Durasteel Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 011 Details of Test or Assessment Report Durasteel 3DF2 panels (9.5mm thick) enclosing a core of Rocksil LR/AT 140 (overall thickness 120mm). Fire resisting floor for up to 4 hrs. FRP in terms of loadbearing capacity, integrity and insulation. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report TE82867 December 1992 N/A Updated information on place of manufacture to be provided by the manufacturer. Clear spans of the two way floor slab limited to 4.17m x 3.5m. The construction details should be in accordance with that shown in the technical evaluation TE82867. Imposed load limited to 5kPa maximum. Strength design of the steelwork is to be carried out and considered separately by the RSE. BD-FP 012 Fendolite MII Mandoval Coatings Limited (See remarks) Premix based on vermiculite and Portland cement. Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council CC82278A July 1992 July 1995 18/01/2005 No-objection letter issued in 1993. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Table 5 in the report no. CC82278A. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Firetex M70/M71 W & J Leigh & Co. (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 013 Details of Test or Assessment Report Intumescent Coating Protection of steel I-beams up to 11/2 hrs. FRP; BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Consultants Assessment Remarks / Comments 18/01/2005 No-objection letter issued in 1995. Validity Date Report WFRC No. C81691 WFRC No. C80529 Protection of SHS and CHS steel columns up to 1 hr. FRP; Date of Posting on CDB WFRC No. C47373 March 1995 April 1997 Updated information on place of manufacture to be provided by the manufacturer. December 1992 June 1989 Protection of steel I-columns and RHS steel beams up to 2 hrs. FRP. BD-FP 014 Firetex M70 Intubuild W & J Leigh & Co. (See remarks) Intumescent Coating Protection of steel columns up to 1 hr. FRP. Required thickness of fire-resisting material should be in accordance with Tables 1 to 7 in the report WFRC No. C47373. Thickness quoted refers to total dry film thickness including the primer and any top sealer, where the thickness of the primer and any top sealer together do not exceed 0.125mm. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council TE5944 November 1986 N/A 18/01/2005 No-objection letter issued in 1990. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with the test report no. TE5944. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Glulite Fire Protection Board Cryotherm Insulation Limited Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 015 Details of Test or Assessment Report Resin-bonded mineral fibre board. (See remarks) Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report CC80705B/ RHE October 1990 October 1992 Updated information on place of manufacture to be provided by the manufacturer. Panels are glued with Rockbond WR adhesive, fastened to the noggins with Rockbond WR adhesive and wire nails. BD-FP 016 Impact Fire Board Pilkington Insulation Limited (See remarks) Fibre reinforced cement board. Protection of steel beams and columns up to 2 hrs. FRP. Special consideration is required when the web depth exceeds 686mm or flange width exceeds 325mm. Required thickness of fire-resisting material should be in accordance with Figures 1 & 2 in the report no. CC80705B/RHE. BS 476: Parts 20 & 21: 1987 N/A Warrington Fire Research Consultants WFRC No. C44908 Re-Issue No. 1 October 1988 October 1990 18/01/2005 No-objection letter issued in 1990. Updated information on place of manufacture to be provided by the manufacturer. Dry thickness of the material should be in accordance with Tables 4 & 4A in the report WFRC No. C44908 (Re-Issue No. 1). Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Interbond FP-HFA 900 International Paint Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 017 Details of Test or Assessment Report Intumescent Coating Protection of hollow steel sections up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Consultants Warrington Fire Research Consultants Protection of steel I sections up to 11/2 hrs. FRP. Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report WFRC No. C44900 WFRC No. C49685 August 1988 July 1990 August 1990 Updated information on place of manufacture to be provided by the manufacturer. July 1992 Required thickness of fire-resisting material should be in accordance with Table 2 in the reports WFRC No. C44900 & WFRC No. C49685. BD-FP 018 Mandolite CP2 Mandoval Coatings Limited (See remarks) Pre-mix based on vermiculite and Portland cement. Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A Warrington Fire Research Consultants WFRC No. C52252 November 1990 N/A 18/01/2005 No-objection letter issued in 1991. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 12 & 13 in the report WFRC No. C52252. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Mandolite CP2 Mandoval Coatings Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 019 Details of Test or Assessment Report Pre-mix based on vermiculite and Portland cement. Upgrade reinforced concrete slabs up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 BS 8110: Part 2: 1985 Accreditation Assessing Body Organization N/A Warrington Fire Research Centre Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1992. Validity Date Report WFRC No. CP92117 March 1992 April 1994 Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 1, 2 & 3 in the reports WFRC No. CP92117. Both structural stability and insulation requirements should be considered and the greater of the thicknesses applied. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Mandolite CP2 Mandoval Coatings Limited Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 020 Details of Test or Assessment Report Pre-mix based on vermiculite and Portland cement. (See remarks) Upgrade reinforced concrete beams, columns and walls up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Centre BS 8110: Part 2: 1985 Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report WFRC No. C80520 December 1992 WFRC No. CP92117 January 1995 Updated information on place of manufacture to be provided by the manufacturer. April 1994 March 1992 Required thickness of fire-resisting material should be in accordance with Table 2 in the report WFRC No. CP92117. The minimum sizes of reinforced concrete beams, columns and walls should not be less than those specified in the Code of Practice for Fire Resisting Construction. BD-FP 021 Monokote MK5 & MK6 W.R. Grace & Co. Construction Products Division (See remarks) Sprayed-applied cementitious fire-proofing plaster. Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A Warrington Fire Research Centre C80173-AH B/mj May 1992 N/A 18/01/2005 No-objection letter issued in 1992. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with data sheet referred to in the letter Ref. C80173-AHB/mj. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Monokote Zonolite Z-106 W.R. Grace & Co. Construction Products Division Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 022 Details of Test or Assessment Report Sprayed-applied cementitious fire protection material. Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Ian Smith (Consultancy) Limited Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1992. Validity Date Report CIS/ER/329/ B November 1988 N/A Updated information on place of manufacture to be provided by the manufacturer. (See remarks) Required thickness of fire-resisting material should be in accordance with Table 2 attached to Ian Smith (Consultancy) Ltd’s letter Ref. CIS/ER/329/B. BD-FP 023 New Promalit Eternit UK Limited (See remarks) Lightweight rockwool board. Protection of steel beams and columns up to 3 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A Building Research Establishment FRO512/2 FT92/259/B S April 1993 N/A 18/01/2005 No-objection letter issued in 1993. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with the table in BRE’s letter Ref. FRO512/2 FT92/259/BS. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Nullifire S602 & S603 Nullifire Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 024 Details of Test or Assessment Report Intumescent Coating Protection of steel I-beams and I-columns, RHS and CHS columns up to 1 hr. FRP. Protection of RHS beams up to 11/2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Certifire Limited Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1990. Validity Date Report CF103 May 1987 and revised on March 1990. N/A Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 3, 4 & 5 in the certificate no. CF103. Thickness quoted refer to total dry film thickness including the primer and any top sealer, where the thickness of the primer and any top sealer together do not exceed 0.1mm. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Nullifire S605 Nullifire Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 025 Details of Test or Assessment Report Intumescent Coating. Protection of steel I-beams and I-columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Certifire Limited Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1990. Validity Date Report CF103 May 1987 and revised on March 1990. N/A Updated information on place of manufacture to be provided by the manufacturer. Protection of CHS columns up to 1 hr. FRP. Required thickness of fire-resisting material should be in accordance with Tables 6, 7, 8 & 9 in the certificate no. CF103. Thickness quoted refer to total dry film thickness including the primer and any top sealer, where the thickness of the primer and any top sealer together do not exceed 0.1mm. BD-FP 026 Nullifire S607 Nullifire Limited (See remarks) Intumescent Coating Protection of steel I-beams up to 11/2 hrs. FRP. Protection of steel I-columns, RHS and CHS columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 N/A Certifire Limited CF103 May 1987 and revised on October 1992. N/A 18/01/2005 No-objection letter issued in 1993. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 10, 11 & 12 in the certificate no. CF103. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Nullifire Firec F333 Nullifire Limited Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 027 Details of Test or Assessment Report Intumescent Coating. (See remarks) Protection of steel I-beams and I-columns and CHS up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Certifire Limited Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1990. Validity Date Report CF103 May 1987 and revised on March 1990. N/A Updated information on place of manufacture to be provided by the manufacturer. Protection of solid circular tie bars up to 3 hrs. FRP. BD-FP 028 Panelcrete Impact Fire Board Panelcrete Limited Fibre reinforced concrete board (See remarks) Protection of steel beams and columns up to 2 hrs. FRP. Application limited to I-section with web depth not exceeding 686mm and flange width not exceeding 325mm. Required thickness of fire-resisting material should be in accordance with Tables 10 to 14 in the certificate no. CF103. Thickness quoted refer to total dry film thickness including the primer and any top sealer, where the thickness of the primer and any top sealer together do not exceed 0.1mm. BS 476: Parts 20 & 21: 1987 N/A Warrington Fire Research Consultants WFRC No. C44908 Re-Issue No. 1 October 1988 October 1990 18/01/2005 No-objection letter issued in 1994. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 4 & 4A in the report WFRC No. C44908 (Re-Issue No. 1). Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Promatect H Eternit UK Limited, Blackburn, UK. Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 029 Details of Test or Assessment Report Fibre-reinforced calcium silicate insulating board. Protection of steel beams and columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1992. Validity Date Report CC82518/R HE June 1992 June 1995 Required thickness of fire-resisting material should be in accordance with Figure 1 in the report no. CC82518/RHE. or Eternit N.V. Kapelle-op-den-bo s Belgium. BD-FP 030 Promatect L Eternit UK Limited, Blackburn, UK. Fibre reinforced calcium silicate insulating board N/A The Loss Prevention Council CC82519/R HE June 1992 June 1995 18/01/2005 Required thickness of fire-resisting material should be in accordance with Figure 1 in the report no. CC82519/RHE. or Eternit N.V. Kapelle-op-den-bo s Belgium. BD-FP 031 Pyrok CV25 Pyrok Building Products Limited (See remarks) Cement-based fire resisting plaster containing vermiculite. No-objection letter issued in 1992. N/A Building Research Establishment FRO512/-FT 91/409/BS February 1992 N/A 18/01/2005 No-objection letter issued in 1992. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with the BRE’s letter Ref. FRO512/-FT91/409/B S. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Pyrok CV27 Pyrok Building Products Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 032 Details of Test or Assessment Report Cement-based fire resisting plaster containing vermiculite. Upgrade reinforced concrete slabs up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Centre BS 8110: Part 2: 1985 Assessment Date of Posting into CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report WFRC No. C80277 September 1992 WFRC No. 41664 June 1987 October 1994 Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 1, 2 & 3 in the report WFRC 41664. Both structural stability and insulation requirements should be considered and the greater of the thicknesses applied. BD-FP 033 Quelfire Steelcote 60 Quelfire Limited (See remarks) Intumescent Coating Protection of steel I- beams up to 11/2 hrs. FRP. Protection of steel I-columns and RHS beams up to 2 hrs. FRP. Protection of RHS and CHS columns up to 1 hr. FRP. Protection of circular hollow and cruciform cast iron columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 N/A Warrington Fire Research Consultants WFRC No. C51739 October 1990 October 1992 18/01/2005 No-objection letter issued in 1993. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 1 to 6 in the report WFRC No. C51739. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Rockcem Cryotherm Insulation Limited Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 034 Details of Test or Assessment Report Premix based on rock-fibre and Portland cement. (See remarks) Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Building Research Establishment Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report A22/3349 FCA/IC June 1984 N/A Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with the BRE’s letter Ref. A22/3349 FCA/IC. BD-FP 035 Spiralite Fire Protection Board Cryotherm Insulation Limited (See remarks) Resin-bonded mineral fibre board. Protection of steel beams and columns up to 2 hrs. FRP. Panels are fastened to the noggins with Spiralite coil screws. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council CC10786/81 887A RHE/MB July 1989 and reviewed in November 1991 November 1993 18/01/2005 No-objection letter issued in 1993. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Table 1 in the report no. CC10786/81887A RHE/MB. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Spraydon F. G. Thermoduric Limited Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 036 Details of Test or Assessment Report Spray applied mineral wool. (See remarks) Protection of structural steelwork up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Centre Warrington Fire Research Consultants Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1993. Validity Date Report WFRC No. C80980 November 1993 WFRC No. C43587 March 1988 November 1995 Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Summary Table 1 in the report WFRC No. C43587. BD-FP 037 Sprayed Limpet Mineral Wool Pilkington Insulation Limited (See remarks) Sprayed mineral wool Protection of structural steelwork up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A N/A N/A* * Test or assessment report could not be retrieved. N/A N/A 18/01/2005 No-objection letter issued in 1994. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with the data indicated on page 73 of “Fire Protection for Structural Steel in Buildings (2nd Edition)” published by the Association of Structural Fire Protection Contractors and Manufacturers Ltd. (ASFPCM). Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Sprayed Limpet Vermiculite Pilkington Insulation Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 038 Details of Test or Assessment Report Sprayed vermiculite cement Protection of structural steelwork up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A N/A Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1994. Validity Date Report N/A* N/A N/A * Test or assessment report could not be retrieved. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with the data indicated on pages 75 & 77 of “Fire Protection for Structural Steel in Buildings (2nd Edition)” published by the Association of Structural Fire Protection Contractors and Manufacturers Ltd. (ASFPCM). BD-FP 039 Steelguard FM Mebon Limited (See remarks) Intumescent Coating Protection of steel I- beams, I-columns and RHS beams up to 11/2 hrs. FRP. Protection of RHS columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council CC80320 December 1990 December 1992 18/01/2005 No-objection letter issued in 1992. CC81382 Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Tables 5 & 6 in the report no. CC80320, Table 2 in the report no. CC81382. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Steelmaster Mebon Limited (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 040 Details of Test or Assessment Report Intumescent Coating Protection of steel I-beams, I-columns and RHS beams up to 11/2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A The Loss Prevention Council Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1992. Validity Date Report CC81987 December 1991 December 1993 CC81987A Updated information on place of manufacture to be provided by the manufacturer. Protection of RHS and CHS columns up to 1 hr. FRP. BD-FP 041 TD Board Thermoduric Limited (See remarks) Mineral Wool Protection of steel beams and columns up to 4 hrs. FRP. Required thickness of fire-resisting material should be in accordance with Tables 5 & 6 in the report no. CC81987, Table 2 in the report no. CC81987A. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council CC83128 December 1992 18/01/2005 No-objection letter issued in 1993. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Figures 1 & 2 in the report no. CC83128. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Unitherm 38091 Herberts GmbH. (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 042 Details of Test or Assessment Report Intumescent Coating Protection of steel I-beams and I-columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Centre Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1994. Validity Date Report WFRC No. C81065 March 1994 April 1996 Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Table 1 in the report WFRC No. C81065. BD-FP 043 Unitherm A60 Herberts GmbH. (See remarks) Intumescent Coating Protection of steel I-beams and I-columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 N/A Warrington Fire Research Consultants WFRC No. C44347 May 1988 18/01/2005 No-objection letter issued in 1991. Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Figure 3 in the report no. CC44347. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Unitherm Fire Protection Coating Dispersal, Water Soluble Herberts GmbH. (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 044 Details of Test or Assessment Report Intumescent Coating Protection of internal steel I-beams up to 11/2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Warrington Fire Research Centre Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1992. Validity Date Report WFRC No. C80058 March 1992 April 1994 Updated information on place of manufacture to be provided by the manufacturer. Protection of internal steel I-columns up to 1 hr. FRP. Required thickness of fire-resisting material should be in accordance with Table 1 in the report WFRC No. C80058. BD-FP 045 Vicuclad Eternit UK Limited, Blackburn, UK. or Eternit N.V. Kapelle-op-den-bo s Belgium Insulation boards produced from mixing vermiculite with inorganic binders. Protection of steel beams and columns up to 2 hrs. FRP in screw-fix Vicuclad system. Protection of steel beams and columns up to 4 hrs. FRP in bonded Vicuclad system. BS 476: Parts 20 & 21: 1987 N/A The Loss Prevention Council CC82520/R HE June 1992 June 1995 18/01/2005 No-objection letter issued in 1992. Required thickness of fire-resisting material should be in accordance with Figure 1 in the report no. CC82520/RHE. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Zonolite W.R. Grace & Co. (See remarks) Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 046 Details of Test or Assessment Report Cementitious fibre-reinforced material. Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization N/A Ian Smith (Consultancy) Limited. Assessment Date of Posting on CDB Remarks / Comments 18/01/2005 No-objection letter issued in 1989. Validity Date Report CIS/ER/329/ B November 1988 N/A Updated information on place of manufacture to be provided by the manufacturer. Required thickness of fire-resisting material should be in accordance with Table 2 in Ian Smith (Consultancy) Ltd’s letter ref. CIS/ER/329/B. BD-FP 047 Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. Single pack solvent based intumescent coating Protection of steel I-beams and I-columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 Protection of steel I-beams and I-columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C110854 Koahsiung, Taiwan BD-FP 048 Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. Koahsiung, Taiwan Single pack solvent based intumescent coating WFRC No. C123992 UKAS Warrington Fire Research Centre WFRC No. C125252 8 April 2002 1 November 1999 19 June 2002 valid until 1 April 2007 28/04/2005 lapse on 1 December 2001 valid until 1 July 2007 28/04/2005 Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 049 Date of Posting on CDB Details of Test or Assessment Report Accreditation Assessing Body Organization Assessment Remarks / Comments Validity Date Report Single pack solvent based intumescent coating Protection of 4-side exposed RHS and CHS up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C125331 19 June 2002 valid until 1 July 2007 28/04/2005 Single pack solvent based intumescent coating Protection of 3-side exposed RHS up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C126749 27 August 2002 valid until 1 September 2007 28/04/2005 WFRC No. C115007 31 July 2000 valid until 1 August 2002 FCO-1299 (Revision) 22 October 2003 lapse on 31 July 2007 FCO-0812 (Revision) 9 November 2001 lapse on 1 March 2005 Koahsiung, Taiwan BD-FP 050 Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. Koahsiung, Taiwan BD-FP 051 Vermitex AF L&A Fazzini Gypsum-vermiculite Protection of Manufacturing Pty coating steel I-sections Ltd. up to 2 hrs. FRP. Greenacre NSW, Australia AS 1530.4 and BS 476: Part 21 NATA CSIRO 28/04/2005 According to the manufacturer’s recommendation, Vermitex AF is for internal application. CSIRO opinion no. FCO-0812 (Revision) assessed compatibility of Vermitex spray protection system with certain types of primer. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Vermitex DX Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 052 Date of Posting on CDB Details of Test or Assessment Report L&A Fazzini Cement-vermiculite Manufacturing Pty coating Ltd. Protection of steel I-sections up to 2 hrs. FRP. AS 1530.4 and BS 476: Part 21 Accreditation Assessing Body Organization NATA CSIRO Greenacre NSW, Australia Assessment Remarks / Comments Validity Date Report FCO-1299 (Revision) 22 October 2003 lapse on 31 July 2007 FCO-0812 (Revision) 9 November 2001 lapse on 1 March 2005 28/04/2005 According to the manufacturer’s recommendation, Vermitex DX is for external application. CSIRO opinion no. FCO-0812 (Revision) assessed compatibility of Vermitex spray protection system with certain types of primer. BD-FP 053 Cafco 300 Isolatek International New Jersey, USA BD-FP 054 Hilti HIT-HY 150 Hilti Corporation Kaufering, Gemany Single package factory controlled premix based on vermiculite and gypsum Protection of 3-side exposed UB and UC sections up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Recognized by PNAP 251 Building Research Establishment Hybrid resin system Injection system for making nominal anchorage connections of Grade 460 rebars of diameters up to 25mm in reinforced concrete elements up to 4 hrs. FRP. BS 476: Part 20: 1987 UKAS Warrington Fire Research Centre CC 206998 WFRC No. C121086 17 April 2002 next review date: 4 March 2007 28/04/2005 25 September 2002 valid until 1 October 2007 28/04/2005 Load carrying capacity of the injection system for rebar fixing under the effects of fire should be assessed with an appropriate factor of safety compatible with the structural design of the parent structure. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Hilti HIT-RE 500 Hilti Corporation Durasteel board Intumex Asia Pacific Pte. Ltd. Blackburn, UK Name of Report No. Date of Test / Accreditation Assessing Body Organization Assessment Date of Posting on CDB Remarks / Comments Validity Date Report Epoxy resin system Injection system for making nominal anchorage connections of Grade 460 rebars of diameters up to 40mm in reinforced concrete elements up to 4 hrs. FRP. BS 476: Part 20: 1987 UKAS Warrington Fire Research Centre WFRC No. C121086 25 September 2002 valid until 1 October 2007 28/04/2005 Load carrying capacity of the injection system for rebar fixing under the effects of fire should be assessed with an appropriate factor of safety compatible with the structural design of the parent structure. 9.5mm thick Durasteel board Fire resisting steel platform floors covered with two layers of Durasteel (constructions are given in the assessment reports) when exposed to fire for 1 hr. FRP in terms of loadbearing capacity, integrity and insulation. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC Assessment Report No. 138676 19 May 2004 valid until 1 June 2009 03/08/2005 The construction details should be identical to those covered in the assessment reports. Kaufering, Gemany BD-FP 056 Name of Laboratory Laboratory / (City and BD-FP 055 Details of Test or Assessment Report Maximum imposed load to be 7.5kPa.. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Unitherm 38091 Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 057 Dupont Intumescent coating Performance Coatings GmbH & Co. Protection of RHS and CHS beams and columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Warrington Fire Research Centre Assessment WFRC Assessment Report No. C126392 Issue 3 WFRC No. C105708 WFRC No. C125342 Issue 2 WFRC Assessment Report No. 140896 Cafco 300 Isolatek International New Jersey, USA Single package factory controlled premix based on vermiculite and gypsum Protection of steel I-columns, RHS and CHS beams and columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Recognized by PNAP 251 Building Research Establishment Remarks / Comments Validity Date Report Stuttgart, Gemany BD-FP 058 Date of Posting on CDB Details of Test or Assessment Report CC 206998 22 July 2004 8 February 1999 13 August 2002 14 July 2004 17 April 2002 N/A 03/08/2005 See WFRC Assessment Report No. C126392 Issue 3 valid until 1 September 2007 valid until 1 August 2009 next review date: 4 March 2007 03/08/2005 Section 1.6.2 of Fire Protection for Structural Steel in Buildings published by the Association for Specialist Fire Protection contains recommendations for determination of spray thickness for hollow sections based on technical data for steel I-sections. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Cafco SprayFilm WB3 Cafco International Intumescent coating UK Guangzhou, China BD-FP 060 Firetherm Firesteel Classic Name of Name of Firetherm Solvent based Intumescent & intumescent coating Insulation Supplies Ltd. Protection of steel I-beams, I-columns, RHS and CHS beams and columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Protection of steel I-beams and I-columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Warrington Fire Research Centre Nullifire S606 Nullifire Limited Intumescent coating UKAS Warrington Fire Research Centre Nullifire S605 Nullifire Limited BD-FP 063 Interchar 963 International Paint Limited Shanghai, China Building Research Establishment Date Report WFRC Assessment Report No. C139823 27 May 2004 16 June 2004 valid until 1 June 2009 03/08/2005 valid until 1 July 2009 WFRC No. 123080 28 January 2001 valid until 1 February 2007 WFRC No. 100784 22 October 1997 CC 92856A 10 April 2003 next review date: 10 April 2008 CC 92856B 10 April 2003 next review date: 10 April 2008 03/08/2005 see WFRC No. 123080 BS 476: Parts 20 & 21: 1987 Intumescent coating Protection of 4-side exposed RHS up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 Recognized by PNAP 251 Building Research Establishment CC 93058B Review 2 21 July 2003 next review date: 21 July 2008 26/10/2005 Intumescent coating Protection of 3-side exposed steel channels and angles up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC Assessment Report No. 136405 15 January 2004 valid until 1 February 2009 03/02/2006 Coventry, UK Recognized by PNAP 251 Validity Protection of 4-side exposed I sections, RHS and CHS columns up to 2 hrs. FRP. Coventry, UK BD-FP 062 Assessment WFRC Assessment Report No. 139822 Dartford, UK BD-FP 061 Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 059 Date of Posting on CDB Details of Test or Assessment Report 03/08/2005 Remarks / Comments Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Phoenix 167 Phoenix Fire Protection (Asia) Ltd. Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 064 Date of Posting on CDB Details of Test or Assessment Report Accreditation Assessing Body Organization Assessment Validity Date Report Intumescent coating Protection of 4-side exposed hollow columns up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC Assessment Report No. 143912 20 December 2004 valid until 1 January 2010 03/02/2006 Intumescent coating Protection of 3-side and 4-side exposed I beam sections up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C126964 30 September 2002 valid until 1 October 2007 03/02/2006 WFRC No. C126965 30 September 2002 Mannheim, Germany BD-FP 065 Phoenix 168 Phoenix Fire Protection (Asia) Ltd. Mannheim, Germany BD-FP 066 Cafco 280 Cafco International Cementitious mineral fibre Indiana, USA Protection of steel beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 Recognized by PNAP 251 Building Research Establishment CC 376.3 17 March 2003 valid until 1 October 2007 next review date: 17 March 2008 21/04/2006 Remarks / Comments Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Floor Assemblies Intumex Asia Pacific Pte. Ltd. Blackburn, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 067 Date of Posting on CDB Details of Test or Assessment Report Single layer of 9.5mm thick Durasteel board, fastened above and below a framework of steel channels, enclosing a cavity containing 140kg/m3 density rock wool with a minimum overall thickness of 80mm. Fire resisting floor assemblies (construction details are given in the assessment reports) for up to 2 hrs. FRP in terms of loadbearing capacity, integrity and insulation. Maximum imposed load to be 10kPa. Primary members of the steel framework are located parallel with and on top of main structural supporting beams at 1m, 1.2m or 2.4m centers as given in the assessment reports. Cross members are spaced at 600mm max. centers. BS 476: Parts 20 & 21: 1987 Assessment Accreditation Assessing Body Organization Recognized by PNAP 251 Building Research Establishment CC 94333 Warrington Fire Research Centre WFRC Assessment report No. 136396 UKAS Remarks / Comments Validity Date Report 22 March 2002 22 March 2004 next review date: 22 March 2007 valid until 1 April 2009 21/07/2006 The construction details should be identical to those covered in the assessment reports. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. The assembly shall be supported by structural steel beams that are fitted with a proprietary fire protection system of suitable thickness for the relevant fire resistance period and for the section factor of the beams. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Floor Assembly Intumex Asia Pacific Pte. Ltd. Blackburn, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 068 Details of Test or Assessment Report Two layers of 9.5mm thick Durasteel board, fastened to the top of a steel framework. Fire resisting floor assembly (construction details are given in the assessment report) for up to 1 hr. FRP (fire attack from either above or below) in terms of loadbearing capacity, integrity and insulation. Maximum imposed load to be 10kPa. The steel framework consists of primary supporting members at maximum 2400mm centers welded to secondary supporting members at maximum 600mm centers. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Warringtonfire Assessment Date of Posting on CDB Remarks / Comments 21/07/2006 The construction details should be identical to those covered in the assessment report. Validity Date Report WF Assessment Report No. 148104 12 September 2005 valid until 1 October 2010 All requirements given in the assessment report should be checked to ensure compatibility with proposed application. The steel framework of the floor shall be designed to be able to bear the specified uniformly distributed imposed load of up to a maximum of 10kPa. When it is required to withstand fire attack from below, the steel framework shall be cladded with a proprietary fire protection system of suitable thickness for the relevant fire resistance period at the designed critical steel temperature and for the section factors of the members. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Standard Manufacture Country) Phoenix Fire Protection (Asia) Ltd. Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and Phoenix 270 Remarks / Comments valid until July 2010 20/10/2006 A critical temperature of 550℃ has been assumed for 4-side exposed steel sections. valid until 1 June 2008 20/10/2006 For use on reinforced concrete beams, columns and walls, the minimum size requirements specified in the Code of Practice for Fire Resisting Construction 1996 and the criterion of stability should be satisfied. Testing and Place of BD-FP 069 Date of Posting on CDB Details of Test or Assessment Report Intumescent coating Accreditation Assessing Body Organization Assessment Validity Date Report Protection of 4-side exposed Isections up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Recognized by PNAP 251 International Fire Consultants Ltd. Field of Application Report IFCA/05199 July 2005 Upgrade reinforced concrete slabs, beams, columns and walls up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C132081C 19 May 2003 Mannheim, Germany BD-FP 070 Mandolite CP2 Cafco International Pre-mix based on vermiculite and Alfreton, Portland cement. Derbyshire, UK BS 8110: Part 2: 1985 WFRC No. C80520 Issue No. 2 WFRC No. C132081A WFRC No. CP92117 Rev.1 BD-FP 071 Nullifire System E Carboline USA Intumescent coating Protection of 4-side exposed CHS up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C124329A WFRC No. C100578 19 January 1993 19 May 2003 5 March 1992 19 April 2002 30 September 1997 valid until 1 February 1995 valid until 1 June 2008 valid until 1 April 1994 valid until 1 May 2007 valid until 1 November 1999 For use on reinforced concrete slabs, the criteria of stability and insulation should be satisfied. 20/10/2006 A critical temperature of 550℃ has been assumed for 4-side exposed steel sections. Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Phoenix 270 Phoenix Fire Protection (Asia) Ltd. Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 072 Date of Posting on CDB Details of Test or Assessment Report Accreditation Assessing Body Organization Assessment Validity Date Report Intumescent coating Protection of 4-side exposed hollow sections up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Recognized by PNAP 251 International Fire Consultants Ltd. Field of Application Report IFCA/05196 July 2005 Dupont Intumescent coating Performance Coatings GmbH & Co. Protection of steel I-beams and I-columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre Assessment Summary WFRC No. 133394 10 July 2003 valid until July 2010 22/01/2007 Mannheim, Germany BD-FP 073 Unitherm 38091 Stuttgart, Gemany WFRC No. 133000 WFRC No. C125126 N/A valid until 1 July 2008 20 June 2003 3 July 2002 WFRC No. C128560 27 November 2002 WFRC No. C105561 Issue 2 8 February 1999 valid until 1 August 2007 valid until 1 December 2007 valid until 1 March 2001 22/01/2007 Remarks / Comments Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Renitherm PMA 1200 Audax-Keck GmbH Pyrok CV27 Axiom Engineering Ltd. Hong Kong Name of Report No. Date of Test / Accreditation Assessing Body Organization Assessment Date Report Protection of 3-side and 4-side exposed I sections up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warringtonfire WF Assessment Report No. 156366 12 July 2006 valid until 1 August 2011 22/01/2007 Cement-based fire resisting plaster containing vermiculite. Upgrade reinforced concrete slabs up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C139153 21 April 2004 valid until 1 May 2009 22/01/2007 BS 8110: Part 2: 1985 Remarks / Comments Validity Intumescent coating Weiherstrasse, Germany BD-FP 075 Name of Laboratory Laboratory / (City and BD-FP 074 Date of Posting on CDB Details of Test or Assessment Report WFRC No. 41664 June 1987 Required thickness of fire-resisting material should be in accordance with Tables 1, 2 & 3 in the report WFRC 41664. Both structural stability and insulation requirements should be considered and the greater of the thicknesses applied. BD-FP 076 Firetherm Firesteel Classic 120 Firetherm Solvent based Intumescent & intumescent coating Insulation Supplies Ltd. Kent, UK Protection of 3-side exposed steel channel sections / I-section up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC No. C130413 6 March 2003 valid until 1 April 2008 3/8/2007 Assessment applicable to steel I-section up to a maximum web size of 686mm and flange size of 305mm Reference List of Fire Protection Materials for Structural Use BD-FP Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Hilti HIT-RE 500 Hilti Corporation Epoxy resin system Kaufering, Gemany BD-FP 078 Firetherm Firesteel Classic 120 Firetherm Solvent based Intumescent & intumescent coating Insulation Supplies Ltd. Kent, UK BD-FP 079 Nullifire S605 Nullifire Limited Coventry, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 077 Details of Test or Assessment Report Solvent based intumescent coating Injection system for making nominal anchorage connections of Grade 460 rebars of diameters up to 40mm in reinforced concrete elements up to 2 hrs. FRP. BS 476: Part 20: 1987 Protection of 3-sides/ 4-sides exposed steel hollow beam sections up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Protection of Built up Box Sections up to 2 hrs FRP and SHS up to 1 hr. FRP (4-side exposed for both sections) BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Bodycote Warringtonfire Assessment Date of Posting on CDB Remarks / Comments 21.1.2008 Load carrying capacity of the injection system for rebar fixing under the effects of fire should be assessed with an appropriate factor of safety compatible with the structural design of the parent structure. Validity Date Report WF 166402 26 October 2007 valid until 1 November 2012 UKAS HOKLAS Warrington Fire Research Centre WFRC No. C130414 Research Engineering Development Façade Consultants Limited R07K15 6 March 2003 valid until 21.1.2008 1 April 2008 24 October 2007 Valid until 21 July 2008 21/1/2008 The relationship between protection thickness, section factor, and fire resistance of structural steel shall refer to BRE assessment report number CC 93058B. The assessment of the built up box section under the fire test report R07K15 was based on fire test of a rolled hollow section. Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Nullifire S606 Nullifire Limited Coventry, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 080 Details of Test or Assessment Report Solvent based intumescent coating Protection of SHS beam sections with 3-side exposed and maximum span of 1.3m for 2 hrs FRP BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization HOKLAS Research Engineering Development Façade Consultants Limited Assessment Date of Posting on CDB Remarks / Comments 21/1/2008 The relationship between protection thickness, section factor, and fire resistance of structural steel shall refer to BRE assessment report number CC92856B. Validity Date Report R07L03 9 November 2007 Valid until 8 November 2009 Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Floor Assemblies Intumex Asia Pacific Pte. Ltd. Blackburn, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 081 Date of Posting on CDB Details of Test or Assessment Report Single layer of 9.5mm thick Durasteel board, fastened above and below a framework of steel channels, enclosing a cavity containing 140kg/m3 density rock wool with a minimum overall thickness of 120mm. Fire resisting floor assemblies (construction details are given in the assessment reports) for up to 4 hrs. FRP in terms of load-bearing capacity, integrity and insulation. Maximum imposed load to be 5.0kPa. Primary members of the steel framework are located parallel with and on top of main structural supporting beams at 1m, 1.2m or 2.4m centers as given in the assessment reports. Cross members are spaced at 600mm c/c. Additional 2 nos. of cover strips shall be required for the top and bottom flange of the channel sections for insulation use. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Warrington Fire Research Centre Assessment Remarks / Comments Validity Date Report WFRC Assessment report No. 136396 22 March 2004 valid until 1 April 2009 25/4/2008 The construction details should be identical to those covered in the assessment reports. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. The assembly shall be supported by structural steel beams that are fitted with a proprietary fire protection system of suitable thickness for the relevant fire resistance period and for the section factor of the beams. Maximum load ratio of structural steel elements inside the assembly shall be less than or equal to 0.5 to BS5950: Part 1 Fire stop/ sealant shall be provided for the interface between the perimeter of the Durasteel floor and the surrounding structures Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Protected Steel Stair Intumex Asia Pacific Pte. Ltd. Blackburn, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 082 Date of Posting on CDB Details of Test or Assessment Report Single layer of 9.5mm thick Durasteel board, fastened above and below a framework of steel angles and cold formed steel sheet, enclosing a cavity containing 140kg/m3 density rock wool with a minimum overall thickness of 120mm. Protected stairs (construction details are given in the assessment reports) for up to 4 hrs. FRP in terms of loadbearing capacity, integrity and insulation. Maximum imposed load to be 5.0kPa. Cold formed steel sheet supported by steel angles create the treads and risers of the stair assembly as well as supporting the Durasteel board on top. Back-to-back steel angle spaced at 1.2m c/c hanging the Durasteel board at the underside of the stairs. The main structural beam (I-section or hollow section) along the staircase is enclosed inside the assembly BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Warrington Fire Research Centre Assessment Remarks / Comments Validity Date Report WFRC Assessment report No. 141176 31 August 2004 valid until 1 September 2009 25/4/2008 The construction details should be identical to those covered in the assessment reports. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. Maximum load ratio of structural steel elements inside the assembly shall be less than or equal to 0.5 to BS5950: Part 1 Either full thickness or at least half the required thickness of rock wool shall be fitted between the Durasteel and the main structural steel members supporting the stair. Fire stop/ sealant shall be provided for the interface between the perimeter of the Durasteel floor and the surrounding structures Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 083 Details of Test or Assessment Report Single pack solvent based intumescent coating Protection of steel I-beams and I-columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Bodycote Warringtonfire Assessment Date of Posting on CDB Remarks / Comments 22/7/2008 This is resulted from the expiry pf BD-FP048 Validity Date Report WF No. 164158 20 August 2007 valid until1 June 2012 Koahsiung, Taiwan BD-FP 084 Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. It should be read in conjunction with fire assessment report WFRC No. 125252 Single pack solvent based intumescent coating Protection of steel angle, channel and T-section to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No. 164158 20 August 2007 valid until1 June 2012 22/7/2008 It should be read in conjunction with Bodycote Warringtonfire assessment letter dated 22.10.2007regarding sections with re-entrant details. Single pack solvent based intumescent coating Protection of 4-side exposed RHS and CHS up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No. 164159 20 August 2007 valid until 1 June 2012 22/7/2008 This is resulted from the expiry of BD-FP049 Koahsiung, Taiwan BD-FP 085 Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. Koahsiung, Taiwan BD-FP 086 Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. It should be read in conjunction with fire assessment report WFRC No. 125331 Single pack solvent based intumescent coating Protection of 3-side exposed RHS up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No. 164160 20 August 2007 valid until 1 June 2012 22/7/2008 Koahsiung, Taiwan BD-FP 087 Southwest A/D Type 5GP A/D Fire Single component, Protection Systems factory blended cementitious spray Toronto, Canada applied coating This is resulted from the expiry of BD-FP050 It should be read in conjunction with fire assessment report WFRC No. 115007 Protection of beam or column of I-section and hollow section up to 4 hrs FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No. 163280 WF No. 160007 WF No. 160008 20 June 2007 N/A N/A Valid until 1 July 2012 22/7/2008 A/D Type 5GP is not intended for direct exposure to weather or excessive physical abuse. Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Floor Assemblies Intumex Asia Pacific Pte. Ltd. Blackburn, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 088 Date of Posting on CDB Details of Test or Assessment Report Single layer of 9.5mm thick Durasteel board, fastened above and below a framework of steel channels, enclosing a cavity containing 140kg/m3 density rock wool with a minimum overall thickness of 80mm. Fire resisting floor assemblies (construction details are given in the assessment reports) for up to2 hrs. FRP in terms of load-bearing capacity, integrity and insulation. Maximum imposed load to be 10kPa. Any point load shall be distributed over an area of 300mmx300mm. Primary members of the steel framework are located parallel with and on top of main structural supporting beams at 1m centers as given in the assessment reports. Cross members are spaced at 600mm c/c. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization Recognized by PNAP 251 Building Research Establishment Assessment Remarks / Comments Validity Date Report CC 94333 Review 2 20 July 2007 valid until 20 July 2012 22/7/2008 The construction details should be identical to those covered in the assessment reports. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. The assembly shall be supported by structural steel beams that are fitted with a proprietary fire protection system of suitable thickness for the relevant fire resistance period and for the section factor of the beams. Maximum load ratio of supporting steel elements shall not exceed 0.53 to BS5950: Part 1 Fire stop/ sealant shall be provided for the interface between the perimeter of the Durasteel floor and the surrounding structures Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Phoenix 168 Phoenix Fire Protection (Asia) Ltd. Name of Name of Intumescent coating (water based) Protection of 3-side and 4-side exposed I beam sections up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Bodycote Warringtonfire Mannheim, Germany BD-FP 090 Phoenix 270-120 Phoenix Fire Protection (Asia) Ltd. Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 089 Details of Test or Assessment Report Assessment Date of Posting on CDB Remarks / Comments 22/7/2008 This is resulted from the expiry of BD-FP 065 Validity Date Report WF No. 160031 1 December 2006 WF No. 160032 1 December 2006 Intumescent coating ( water based) Protection of 4-side exposed hollow column sections up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No. 174358 19 June 2008 Intumescent coating ( water based) Protection of high strength steel rod (MacAlloy Bars) up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No. 167802 16 October 2007 valid until 1 December 2011 It should be read in conjunction with fire assessment report WFRC No. C126964 and C126965 valid until 1August 2010 22/7/2008 It should be read in conjunction with fire assessment report WF No. 156367 (expired on 1.8.2008) valid until 1November 2009 22/7/2008 It should be read in conjunction with fire assessment report WF No. 156367 (expired on 1.8.2008) Wigan , UK BD-FP 091 Phoenix 270-120 Phoenix Fire Protection (Asia) Ltd. Wigan , UK Limiting temperature for tension rod shall be evaluated based on the tensile force of the member under consideration. BD-FP 092 Phoenix 270-120 Phoenix Fire Protection (Asia) Ltd. Intumescent coating ( water based) Protection of 4-side exposed I- beam sections up to 2 hrs FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No. 174358 19 June 2008 valid until 1August 2010 22/10/2008 Protection of 3-side exposed hollow beam section; 4-side exposed hollow column section and steel angle section up to 2 hrs FRP. BS 476: Parts 20 & 21: 1987 HOKLAS Rearch Engineering Development Façade Consultants Limited R08C06 9 April 2008 valid until 8 April 2013 22/10/2008 Wigan , UK BD-FP 093 Tanda AP25 Warwick Building Material Ltd Single component, factory blended cementitious spray Guangzhou, China or trowel applied coating It should be read in conjunction with fire assessment report WF No. 156367 (expired on 1.8.2008) Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Nullifire S605 Nullifire Limited Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 094 Details of Test or Assessment Report Solvent-borne intumescent coating Coventry, UK Protection of 3-side exposed I-section beams and 4-side exposed I-section columns & beams up to 2 hrs FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Bodycote Warringtonfire Assessment Date of Posting on CDB Remarks / Comments 23/1/2009 This is resulted from the expiry of BD-FP 025 Validity Date Report WF No 165959 22 January 2008 Valid until 1 February 2013 The relationship between protection thickness, section factor, and fire resistance period of structural steel shall refer to Table 1 & 2 of report WF No. 165959. Protection of 4-side exposed CHS columns up to 1 hr. FRP. BD-FP 095 Nullifire System E Nullifire Limited Intumescent coating Coventry, UK Protection of 4-side exposed CHS up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF No 164410A 25 May 2007 Valid until 23/1/2009 1 June 2012 This is resulted from the expiry of BD-FP 071 It should be read in conjunction with fire assessment report WFRC No. C100578 & WFRC No. C124329A (expired on 1.11.1999 & 1.5.2007 respectively) BD-FP 096 Cafco 300 Promat International Bankok, Thailand Plaster/ vermiculite based product for internal use. Protection of 3-side exposed I-section beams and 4-side exposed I-section columns up to 4 hrs FRP BS 476: Parts 20 & 21: 1987 Recognized by PNAP 251 Building Research Establishment CC 206998 Review 1 30 April 2007 next review 30 April 2012 23/1/2009 This is resulted from the expiry of BD-FP 058 It should be read in conjunction with fire assessment report CC 206998 Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) BD-FP 098 Cafco Mandolite CP2 Durasteel Floor Assemblies Promat International Spray applied, single package factory controlled premix, Bangkok ,Thailand based on vermiculite and Portland cement for internal use. Upgrade reinforced concrete slabs and beams up to 4 hrs. FRP. Intumex Asia Pacific Pte. Ltd. Insulated ceiling membrane construction to achieve 4 hours FRP for the underside of a composite floor slab formed by steel profile sheeting. Blackburn, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 097 Details of Test or Assessment Report Single layer of 9.5mm thick Durasteel board, fastened below a framework of steel channels spaced at 1000 center, enclosing a cavity containing 140kg/m3 density rock wool with a minimum overall thickness of 120mm. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Bodycote Warringtonfire Assessment Date of Posting on CDB Remarks / Comments 23/1/2009 This is resulted from the expiry of BD-FP 070 Validity Date Report WF Report No. 173530/A Issue 2 28 May 2008 valid until 1 June 2013 It should be read in conjunction with fire assessment report WFRC No CP92117 Revision 1 The ceiling membrane is hung at the slab soffit by M20 steel threaded hanger rods spaced at 1200mm. The ceiling membrane will not be subjected to imposed load except self weight. BS 476: Parts 22: 1987 Recognized by PNAP 251 Building Research Establishment CC208842 Review 1 6 July 2007 valid until 6 July 2012 23/1/2009 The construction details should be identical to those covered in the assessment reports. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. Fire stop/ sealant shall be provided for the interface between the perimeter of the Durasteel floor and the surrounding structures Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Promatect H Eternit Guangzhou Co. Ltd Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 099 Details of Test or Assessment Report Fibre-reinforced calcium silicate insulating board. Protection of steel beams and columns up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization Recognized by PNAP 251 Building Research Establishment Assessment Date of Posting on CDB Remarks / Comments 23/1/2009 This is resulted from the expiry of BD-FP 029 Validity Date Report CC84975 Review 5 9 January 2007 9 January 2012 Guangzhou, China BD-FP 100 Monokote Type Z-146 Grace Korea Inc Inchon, Korea The relationship between protection thickness, section factor, and fire resistance period of structural steel shall refer to Table 3 of report CC84975 Review 5 Sprayed-applied cementitious fire protection material. Protection of 3-side exposed or 4-sides exposed I-section beams and columns for FRP up to 1 hr. BS 476: Parts 20 & 21: 1987 UKAS NATA Warrington Fire Research Centre WFRC Report No. 145418 8 March 2005 1 April 2010 23/1/2009 It should be read in conjunction with fire assessment report WFRC No C81831 for I-section and C109505 for hollow section. FCO-1299 1 July 2007 31 July 2012 30/4/2009 According to the manufacturer’s recommendation, Vermitex AF is for internal application. R08C06 9 April 2008 8 April 2013 30/4/2009 Protection of 4-side exposed hollow section beams and column for FRP up to 1 hr. BD-FP 101 Vermitex AF L&A Fazzini Gypsum-vermiculite Protection of steel Manufacturing Pty coating I-sections, hollow Ltd. section and angle section up to 1 hr. Greenacre NSW, FRP. Australia AS 1530.4 and BS 476: Part 21 BD-FP 102 Tanda AP25 Warwick Building Material Ltd BS 476: Parts 20 & 21: 1987 Single component, factory blended cementitious spray Guangzhou, China or trowel applied coating Protection of 3-side and 4-side exposed I-section up to 4 hrs FRP. HOKLAS CSIRO Rearch Engineering Development Façade Consultants Limited Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Hilti HIT-HY 150 Hilti Corporation Interchar 963 International Paint Limited Interchar 973 International Paint Limited Vermiculux Board Intumex Asia Pacific Glasgow, UK BD-FP 107 Cafco SprayFilm WB3 Assessing Body Organization Load carrying capacity of the injection system for rebar fixing under the effects of fire should be assessed with an appropriate factor of safety compatible with the structural design of the parent structure. Date Report UKAS Bodycote Warringtonfire WF Report No. 166402 26 October 2007 1 November 2012 30/04/2009 Intumescent coating Protection of 3-side and 4-side exposed steel angles up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WFRC Assessment Report No. 136405 15 January 2004 1 February 2014 12/08/2009 WF Report No. 179990 26 January 2009 NA Intumescent coating Protection of 4-side exposed I-section beams and column up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 159150 3 September 2007 1 September 2012 12/08/2009 Low density lightweight non-combustible board made from a blend of calcium silicate, vermiculite and reinforced with selected inorganic fibres and fillers Protection of 4-side exposed I-section beams and columns up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A Building Research Establishment CC 83123 Review 3 14 July 2008 14 July 2013 12/08/2009 Required thickness of fire-resisting board shall be in accordance with Table 14 of BRE’s assessment report .CC 83123 Review 3 Protection of steel channel section up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 176738A 19 September 2008 1 October 2013 4/11/2009 It should be read in conjunction with Warringtonfire’s supplementary letter 176738/RHE. Cafco International Intumescent coating UK Guangzhou, China Accreditation Assessment Validity BS 476: Part 20: 1987 Shanghai, China BD-FP 106 Report No. Date of Test / Remarks / Comments Injection system for making nominal anchorage connections of Grade 460 rebars of diameters up to 25mm in reinforced concrete elements up to 4 hrs. FRP. Shanghai, China BD-FP 105 Name of Date of Posting on CDB Hybrid resin system Kaufering, Gemany BD-FP 104 Name of Laboratory Laboratory / (City and BD-FP 103 Details of Test or Assessment Report Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Floor Assemblies Intumex Asia Pacific Pte. Ltd. Blackburn, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 108 Details of Test or Assessment Report Single layer of 9.5mm thick Durasteel board, fastened above and below a framework of steel channels, enclosing a cavity containing 140kg/m3 density rock wool with a minimum overall thickness of 80mm. Fire resisting floor assemblies (construction details are given in the assessment reports) for up to 2 hrs. FRP in terms of load-bearing capacity, integrity and insulation. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Bodycote Warringtonfire Assessment Date of Posting on CDB Remarks / Comments 4/11/2009 It should be read in conjunction with fire assessment report No WFRC 141038. Validity Date Report WF Report No. C181794C 30 March 2009 1 April 2014 The construction details should be identical to those covered in the assessment reports. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. Maximum imposed load to be 7.5kPa. Additional 2 nos. of cover strips shall be required for the top and bottom flange of the channel sections for insulation use. BD-FP 109 Firetherm Firesteel Classic 120 Firetherm Solvent based Intumescent & intumescent coating Insulation Supplies Ltd. Kent, UK Protection of 3-sides/ 4-sides exposed steel hollow beam sections and 3-side exposed steel channel sections / I-section up to 2 hrs. FRP. Maximum load ratio of structural steel elements inside the assembly shall be less than or equal to 0.5 to BS5950: Part 1 Fire stop/ sealant shall be provided for the interface between the perimeter of the Durasteel floor and the surrounding structures BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. C155649/A 15 June 2006 1 July 2011 WF Report No. C155649/B 15 June 2006 1 July 2011 4/11/2009 It should be read in conjunction with fire assessment report WFRC C130414 & C130413 Assessment applicable to steel I-section up to a maximum web size of 686mm and flange size of 305mm Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Unitherm 38091 Sika Korrosionsshutz GmbH. Name of Name of Accreditation Assessing Body Organization Unitherm 38091 Cafco SprayFilm WB3 Firecut F-1 Report BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 162163, C105561 Issue 2, C125126, 133000 and summary report WF No. 133394. 19 March 2007 1 April 2012 22/2/2010 Intumescent coating Protection of steel RHS up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 162164, C105708, C125342 Issue 2, 140896 and summary report WF No. 126392 Issue 3.. 19 March 2007 1 April 2012 22/2/2010 Cafco International Intumescent coating UK Protection of steel RHS, channel and angle section up to 2 hrs. FRP BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 176738B for RHS, 176738A for channel and angle sections 4 April 2009 1 October 2013 22/2/2010 Protection of steel channel section up to 1 hr. FRP BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 149330 Issue 2 18 November 2005 1 December 2010 25/8/2010 Protection of steel channel and hollow section up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 169583B & 169583C 19 December 2007 1 January 2013 17/10/2011 Sika Korrosionsshutz GmbH. Guangzhou, China BD-FP 113 Date Protection of steel I-beams and I-columns up to 2 hrs. FRP. Stuttgart, Gemany BD-FP 112 Assessment Yung Chi Paint & Varnish Mfg. Co. Ltd Cementitious coating 19 September 2009 Kaohsiung, Taiwan BD-FP 114 Isolatek WB3 Isolatek International Stanhope, USA Water-based in tumescent coating Remarks / Comments Validity Intumescent coating Stuttgart, Gemany BD-FP 111 Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 110 Date of Posting on CDB Details of Test or Assessment Report It should be read in conjunction with Warringtonfire’s supplementary letter 176738/RHE.for channel and angle section. Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Supalux Board Intumex Asia Pacific Nullifire S606 Nullifire Limited Monokote MK6 W.R. Grace & Co. Incheon City, South Korea BD-FP 118 Firecut F-1 Yung Chi Paint & Vanish Mfg. Co. Ltd. Report No. Date of Test / Accreditation Assessing Body Organization Assessment Remarks / Comments Validity Date Report Protection of steel hollow section up to1 hr. FRP. BS 476: Parts 20 & 21: 1987 N/A Building Research Establishment CC 82876 Review 2 Issue 2 27 March 2006 11 August 2010 17/10/2011 Required thickness of fire-resisting board shall be in accordance with the provision shown in BRE’s assessment report CC 82876 Review 2 Issue 2 Intumescent coating Protection of steel hollow section, channel section, I-section up to 1 hrs. FRP. BS 476: Parts 20 & 21: 1987 N/A Building Research Establishment CC 92856A Review 3 19 March 2008 next review date: 10 April 2013 17/10/2011 The relationship between protection thickness, section factor, and fire resistance of structural steel shall refer to BRE assessment report number CC92856A, Review 3. and CC92856B Review 3 Sprayed-applied cementitious fire-proofing plaster. Upgrading of FRP of RC slab and beam from 1 hr to 2 hrs. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 186522 3 September 2009 1 November 2014 17/10/2011 It should be read in conjunction with fire assessment report WFRC No C107230 Cementitious fire rated coating Protection of steel channel section up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Warrington Fire Research Centre WFRC Report No. 149330 18 November 2005 1 December 2010 17/10/2011 Single component, factory blended cementitious spray or trowel applied coating Protection of steel channel section up to 4 hrs FRP. BS 476: Parts 20 & 21: 1987 HOKLAS Rearch Engineering Development Façade Consultants Limited R08C06 9 April 2008 valid until 8 April 2013 17/10/2011 Solvent based intumescent coating Protection of steel I-section up to 2 hrs FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 170770 28 May 2009 1 June 2014 17/10/2011 Coventry, UK BD-FP 117 Name of Date of Posting on CDB Non-combustible board Guangzhou, China BD-FP 116 Name of Laboratory Laboratory / (City and BD-FP 115 Details of Test or Assessment Report CC92856B Review 3 Kaohsiung, Taiwan BD-FP 119 Tanda AP25 Warwick Building Material Ltd Guangzhou, China BD-FP 120 Hensotherm 3KS Rudolf Hensel GmbH Bornsen, Germany Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Nullifire S707-60 Nullifire Limited Cafco SprayFilm WB3 Cafco International UK Name of Report No. Date of Test / Accreditation Assessing Body Organization Assessment Date of Posting on CDB Remarks / Comments Validity Date Report Intumescent coating Protection of steel I-section up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 205546 6 June 2011 next review date: 1 June 2016 21/9/2012 It should be read in conjunction with fire assessment report WF Report No 154065 Intumescent coating Protection of steel I-section up to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 176738A 19 September 2008 1 October 2013 21/9/2012 It should be read in conjunction with fire assessment report WF Report No 152624 Issue 3. Cementitious fire rated coating Protection of steel I-section, steel channel section and angle section up to 4 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WFRC Report No. 179160 11 December 2008 1 January 2014 21/9/2012 Water borne intumescent coating Protection of 3-sides/ 4-sides exposed steel I-section and 4-side exposed steel hollow section up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Report No. 169988 28 January 2008 1 February 2013 3/7/2013 Coventry, UK BD-FP 122 Name of Laboratory Laboratory / (City and BD-FP 121 Details of Test or Assessment Report Guangzhou, China BD-FP 123 Firecut F-1 Yung Chi Paint & Vanish Mfg. Co. Ltd. Kaohsiung, Taiwan BD-FP 124 Firetherm Firesteel 120WB Firetherm Intumescent & Insulation Supplies Ltd. Kent, UK Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) Durasteel Floor Assemblies Intumex Asia Pacific Pte. Ltd. Blackburn, UK / Zhejiang, PRC Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 125 Date of Posting on CDB Details of Test or Assessment Report Single layer of 9.5mm thick Durasteel board, fastened above and below a framework of steel channels, enclosing a cavity containing 140kg/m3 density rock wool with a minimum overall thickness of 80mm. Fire resisting floor assemblies (construction details are given in the assessment report) for up to 1 hr. FRP in terms of load-bearing capacity, integrity and insulation. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization Department of Standards Malaysia UKAS Fire Science Research Group (Malaysia) Exova Warringtonfire Assessment Validity Date Report FSRG 2014/005 WF Report No. 189172 27 February 2014 21 December 2009 NA 9 June 2014 1 January 2015 The assembly shall be supported by structural members with fire protection system for the relevant fire resistance period. Additional 1 no. of 9.5mm thick Durasteel cover strip shall be required for the top and bottom flange of the channel sections for insulation use. Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. BD-FP 127 Firecut FM-900 Yung Chi Paint & Varnish Mfg Co Ltd. Koahsiung, Taiwan Fire stop/ sealant shall be provided for the interface between the perimeter of the Durasteel floor and the surrounding structures Single pack solvent based intumescent coating Protection of steel I-sections with 3-side or 4-side exposed up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 UKAS Exova Warringtonfire WF Review Report No. 316831 23 March 2012 1 April 2017 9 June 2014 Single pack solvent based intumescent coating Protection of steel angle, channel and I-sections with 3-side or 4-side exposed to 1 hr. FRP. BS 476: Parts 20 & 21: 1987 UKAS Bodycote Warringtonfire WF Review Report No. 307644 16 May 2011 1 June 2016 9 June 2014 Koahsiung, Taiwan The construction details should be identical to those covered in the assessment report. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications. Maximum imposed load to be 10kPa. BD-FP 126 Remarks / Comments It should be read in conjunction with Bodycote Warringtonfire fire assessment report WF No. 167317. It should be read in conjunction with Bodycote Warringtonfire assessment report WF No. 145918. Reference List of Fire Protection Materials for Structural Use Ref. No. Product Name of Name Manufacturer Material Category Application Compliance Testing and Place of Standard Manufacture Country) BD-FP 129 Ramset EPCON G5 Injection Adhesive with Grade 460 high yield deformed bars of diameters 12mm to 40mm ITW Red Head Firetex FX-5090 Sherwin-Williams Protective & Marine Coating Epoxy injection system Illinois, USA Intumescent coating (water based) Bolton, UK Name of Name of Report No. Date of Test / Laboratory Laboratory / (City and BD-FP 128 Details of Test or Assessment Report Injection system for making anchorage connections of Grade 460 rebars of diameters 12mm to 40mm in reinforced concrete elements up to 4 hrs. FRP. BS 476: Part 20: 1987 Protection of steel I-sections and hollow sections with 3-side or 4-side exposed up to 2 hrs. FRP. BS 476: Parts 20 & 21: 1987 Accreditation Assessing Body Organization UKAS Exova Warringtonfire Assessment Date of Posting on CDB Remarks / Comments 01/09/2014 It should be read in conjunction with Warringtonfire assessment report no. 45838.4. Validity Date Report EWFA Report No. 25276-00 30 September 2010 30 November 2015 Load carrying capacity of the injection system for rebar fixing under the effects of fire should be assessed with an appropriate factor of safety compatible with the structural design of the parent structure. UKAS Exova Warringtonfire WF Report No. 336628 28 January 2014 1 February 2019 WF Report No. 347568 9 July 2015 1 June 2020 31 August 2016 The construction details should be identical to those covered in the assessment reports. All requirements given in the assessment reports should be checked to ensure compatibility with proposed applications.