IESO Expedited System Impact Assessment NORMAN T1 REPLACEMENT AND SUBSTATION UPGRADE 2013-EX670 FINAL REPORT Executive Summary Conditional Approval for Connection H2O Power LP (the “connection applicant”) is proposing to replace the main output transformer T1 at Norman GS, add a new HV circuit breaker and replace the existing HV disconnect switch. This assessment concluded that the proposed changes are expected to have no material adverse impact on the reliability of the IESO-controlled grid. Therefore, the IESO recommends that a Notification of Conditional Approval for Connection be issued for Norman T1 replacement and other proposed substation upgrades, subject to implementation of the requirements outlined in this report. The connection applicant shall satisfy all applicable requirements and standards specified in the Market Rules and the Transmission System Code. The following requirements summarize some of the general requirements that are applicable to the proposed project, and presented in detail in section 2 of this report. Requirements Voltage The connection applicant shall ensure that the 115 kV equipment is capable of continuously operating between 113 kV and 132 kV, as specified in Appendix 4.1 of the Market Rules. Protective relaying must be set to ensure that transmission equipment remains in-service for voltages up to 5% above the maximum continuous value. Appendix 2 of the Transmission System Code states that the maximum rated interrupting time for the 115 kV breakers must be ≤ 5 cycles. Thus, the connection applicant shall ensure that the installed breakers meet the required interrupting time specified in the Transmission System Code. Fault interrupting devices must be able to interrupt fault currents at the maximum continuous voltage of 132 kV. Protections The connection applicant shall ensure that the protection systems are designed to satisfy all the requirements of the Transmission System Code and any additional requirements identified by the transmitter. New protection systems must be coordinated with the existing protection systems. Reactive Power The proposed facility shall inject or withdraw reactive power continuously (i.e. dynamically) at a connection point up to 33% of its rated active power at all levels of active power output except where a lesser continually available capability is permitted by the IESO. Fault Levels The connection applicant shall ensure that the new equipment at the facility be designed to withstand the fault levels in the area. If any future system changes result in an increased fault level higher than the equipment’s capability, the connection applicant is required to replace the equipment with higher rated equipment capable of withstanding the increased fault level, up to maximum fault level specified in Appendix 2 of the Transmission System Code. Final Report Public Page 1 of 6 Norman T1 Replacement and Substation Upgrade 2013-EX670 Connection Equipment Design The connection applicant shall ensure that the connection equipment is designed to be fully operational in all reasonably foreseeable ambient temperature conditions. The connection equipment must also be designed so that the adverse effects of its failure on the IESOcontrolled grid are mitigated. Telemetry If applicable according to Section 7.3 of Chapter 4 of the Market Rules, the connection applicant shall provide to the IESO the applicable telemetry data listed in Appendix 4.15 of the Market Rules on a continual basis. The data shall be provided with equipment that meets the requirements set forth in Appendix 2.2, Chapter 2 of the Market Rules, in accordance with the performance standards set forth in Appendix 4.19, subject to Section 7.6A of Chapter 4 of the Market Rules. The whole telemetry list will be finalized during the IESO Facility Registration/Market Entry process. As part of the IESO Facility Registration/Market Entry process, the connection applicant must also complete end to end testing of all necessary telemetry points with the IESO to ensure that standards are met and that sign conventions are understood. All found anomalies must be corrected before IESO final approval to connect any phase of the project is granted. Revenue Metering If revenue metering equipment is being installed as part of this project, the connection applicant should be aware that revenue metering installations must comply with Chapter 6 of the IESO Market Rules. For more details the connection applicant is encouraged to seek advice from their Metering Service Provider (MSP) or from the IESO metering group. Facility Registration/Market Entry The connection applicant must complete the IESO Facility Registration/Market Entry process in a timely manner before IESO final approval for connection is granted. As part of the IESO Facility Registration/Market Entry process, the connection applicant must provide evidence to the IESO confirming that the equipment installed meets the Market Rules requirements and matches or exceeds the performance predicted in this assessment. This evidence shall be either type tests done in a controlled environment or commissioning tests done on-site. In either case, the testing must be done not only in accordance with widely recognized standards, but also to the satisfaction of the IESO. Until this evidence is provided and found acceptable to the IESO, the Facility Registration/Market Entry process will not be considered complete and the connection applicant must accept any restrictions the IESO may impose upon this project’s participation in the IESO-administered markets or connection to the IESO-controlled grid. The evidence must be supplied to the IESO within 30 days after completion of commissioning tests. Failure to provide evidence may result in disconnection from the IESO-controlled grid. If the submitted models and data differ materially from the ones used in this assessment, then further analysis of the project will need to be done by the IESO. Final Report Public Page 2 of 6 Norman T1 Replacement and Substation Upgrade 1. 2013-EX670 Project Description H2O Power LP is planning to replace the main output transformer T1 at Norman GS, add a new HV breaker, and replace the HV disconnect switch. All associated line, transformer, and LV bus protections will also be replaced as part of the project. The expected in-service date for the new equipment is August 2014. 1.1 Transformer The technical specifications of the existing and replacement transformer are given in Table 1. All values for replacement equipment are specified at the time of order. Actual values to be provided prior to in-service dates. Transformer Existing T1 Replacement T1 Configuration Three phase Three phase Transformation (kV) 121.5/6.6 125/6.6 Winding Configuration Delta/Wye-Grounded via 6.4 Ω resistor 10.8 MVA ONAN 14.4 MVA ONAF 18.0 MVA ONAF 18.0MVA Delta/ Wye-Grounded via 6.4 Ω resistor 10.0 MVA ONAN 13.3 MVA ONAF 16.6 MVA ONAF 16.6 MVA 18.54 MVA (summer) 24.66 MVA (winter) Not applicable To be provided Positive Sequence Impedance R= not available X=7.8% @ 10.8 MVA R= to be provided X= 7.8% @ 10.0 MVA Off-load tap-changer Tap 1: Tap 2: Tap 3: Tap 4: Tap 5: Tap 6: Tap 7: Tap 1: Tap 2: Tap 3: Tap 4: Tap 5: In service off-load tap position Tap 3: 121.5 kV Thermal Rating Continuous Thermal Rating (summer 35°C) 10-DAY Thermal Rating (summer 35°C) 15-MIN Thermal Rating (summer 35°C) 114.8 kV 118.2 kV 121.5 kV 124.9 kV 128.3 kV 132.6 kV 135.0 kV 118.75 kV 121.875 kV 125.0 kV 128.125 kV 131.25 kV Tap 3: 125.0 kV Table 1: Comparison of Existing and New Transformer Parameters at Norman GS Final Report Public Page 3 of 6 Norman T1 Replacement and Substation Upgrade 1.2 2013-EX670 Connection Equipment The specifications of the new HV circuit breaker are given in Table 2. The specifications of the existing and replacement 115 kV disconnect switch are compared in Table 3. HV Breaker Specifications (A1L2) Maximum Continuous Operating Voltage 145 kV Continuous Current Rating 1200 A Short Circuit Symmetrical Current Rating 40 kA Interrupting Medium SF6 50 msec Rated Interrupting Time Table 2: New HV Breaker Specifications at Norman GS The specifications of the existing and replacement 115 kV disconnect switch are compared in Table 3. HV Disconnect Switch Specifications (A1L2-L) Existing Maximum Continuous Rated Voltage 138 kV Load Interrupting Current 600 A Replacement 145 kV 1200 A Table 3: Existing and New HV Disconnect Switch Specifications at Norman GS Appendix 4.1 of the Market Rules states that under normal operating conditions, the voltages in the 115 kV system in northern Ontario are maintained within the range of 113 kV to 132 kV. Thus, the IESO requires that the 115 kV equipment in northern Ontario must have a maximum continuous voltage rating of at least 132 kV. Protective relaying must be set to ensure that transmission equipment remains in-service for voltages up to 5% above the maximum continuous value specified in Appendix 4.1 of the Market Rules, to allow the power system to recover from transient disturbances. 1.3 Protections Major new protection associated with the project includes Transformer differential protection for T1 Line distance protection for 115 kV circuit K2M All new protection will consist of redundant A and B protection relays with separate DC power supplies in accordance with the NPCC requirements. The existing Remote Trip protection connecting Norman GS with Kenora GS and Rabbit Lake TS will be retained. The connection applicant shall ensure that the protection systems are designed to satisfy all the requirements of the Transmission System Code and any additional requirements identified by the transmitter. New protection systems must be coordinated with the existing protection systems. Final Report Public Page 4 of 6 Norman T1 Replacement and Substation Upgrade 2. Assessments 2.1 Reactive Power Capability 2013-EX670 The generation facility is directly connected to the IESO-controlled grid, and thus, the connection applicant shall ensure that the facility has the capability to inject or withdraw reactive power continuously (i.e. dynamically) at a connection point up to 33% of its rated active power at all levels of active power output except where a lesser continually available capability is permitted by the IESO. If necessary, shunt capacitors must be installed to offset the reactive power losses within the facility. If generators do not have dynamic reactive power capabilities, dynamic reactive compensation devices must be installed to make up the deficient reactive power. The five generators at Norman GS provide a maximum generation of 13.2 MW. Table 4 presents the ranges of reactive power output for G1 to G5 calculated at the HV bus at each transformer tap position. The voltage on the Rabbit Lake bus was fixed at 124.433 kV which is the historical average voltage over the past 2 years. Norman GS Reactive Power Output Qmin = -5.4 MVAR; Qmax = 8.0 MVAR OLTC tap Tap 1: 118.75 kV Tap 2: 121.875 kV Tap 3: 125.0 kV (proposed I/S postion) Tap 4: 128.125 kV Tap 5: 131.25 kV MVAR absorption at Norman bus using 0.95 pu terminal voltage & minimum generation of 0 MW MVAR injection at Norman bus using 1.05 pu terminal voltage & maximum generation of 13.2 MW (VRabbit Lake = 124.433 kV) -5.7 MVAR -5.7 MVAR (VRabbit Lake = 124.433 kV) 0.9 MVAR 2.5 MVAR -5.7 MVAR 5.6 MVAR -2.7 MVAR 0.1 MVAR 6.1 MVAR 6.1 MVAR Table 4: Reactive Power Outputs at the HV side of Norman GS Table 4 indicates that the generation facility is capable of injecting and absorbing more than 33% of its rated active power at all levels of active power output while on the proposed off load tap position #3, thus meeting the reactive power capability requirements of the Market Rules. However, should the real time operation require a different transformer tap position in the future, the IESO reserves the right to request the off load tap position to be modified to a different value. 2.2 Transformer Thermal Assessment At a power factor of 0.9, the maximum generator output is 14.44 MVA (13.2 MW, 6.3 MX) which is within the continuous rating of the new transformer. Final Report Public Page 5 of 6 Norman T1 Replacement and Substation Upgrade 2.3 2013-EX670 Short Circuit Assessment The Transmission System Code requires the new equipment to be designed to withstand the fault levels in the area where the equipment is installed. Thus, the connection applicant shall ensure that the new equipment at the facility is designed to withstand the fault levels in the area. If any future system changes result in an increased fault level higher than the equipment’s capability, the connection applicant is required to replace the equipment with higher rated equipment capable of withstanding the increased fault level, up to maximum fault level specified in the Transmission System Code. Appendix 2 of the Transmission System Code establishes the maximum fault levels for the transmission system. For the 115 kV system, the maximum 3 phase and single line to ground symmetrical fault levels are 50 kA. Appendix 2 of the Transmission System Code states that the maximum rated interrupting time for the 115 kV breakers must be ≤ 5 cycles. Thus, the connection applicant shall ensure that the installed breakers meet the required interrupting time specified in the Transmission System Code. Fault interrupting devices must be able to interrupt fault currents at the maximum continuous voltage of 132 kV. The short circuit level of the Norman 115 kV bus is about 6.0 kA in the existing system, which is far below the interrupting capability of the proposed circuit breaker. It is not expected that the T1 replacement has significant impact on the local short circuit level, thus, short circuit studies were not conducted. 2.4 Protection System Assessment Hydro One has confirmed that the line protection setting for K2M will not change. - End of Document - Final Report Public Page 6 of 6