Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 TABLE OF CONTENTS TECHNICAL SPECIFICATIONS SECTION TITLE DIVISION 1 – GENERAL REQUIREMENTS 01010 Statement of Work 01300 Submittals 01330 Submittal Procedures 01400 Quality Requirements 01410 Testing Services 01500 Construction Facilities and Temporary Services 01600 Materials and Equipment 01700 Contract Closeout 01710 Final Cleaning 01720 Project Record Documents DIVISION 3 – CONCRETE 03300 Cast-In-Place Concrete DIVISION 16 - ELECTRICAL 16060 Grounding and Bonding 16075 Electrical Identification 16120 Conductors and Cables 16700 Communications ATTACHMENT A – AVIAT EQUIPMENT LIST (CONTRACTOR TO PROCURE) ATTACHMENT B – BILL OF MATERIALS ATTACHMENT C – SITE SUMMIT FOUNDATION REPAIR REPORT ATTACHMENT D – QA/QC CHECKLIST Table of Contents Specifications Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Table of Contents Specifications Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01010 STATEMENT OF WORK PART 1 - GENERAL 1.01 PROJECT OVERVIEW The Site Summit communications site project includes repair of an existing antenna tower concrete foundation, installation of a 50’ communications tower on the repaired foundation, installation of an ice bridge between the tower and existing equipment shelter, and installation of microwave equipment in an existing equipment shelter to be a turn-key site when complete. The new microwave link will communicate with equipment at the Houston site where similar microwave equipment. A summary of work required at the site is provided in Table I below. Complete details of all work required are provided in the drawings for the site. All work shall be completed prior to November 1, 2016. Table I. Site Summit and Houston Work Summary A. Applicable Contact Information Owner/Contracting Authority: Alaska Railroad (ARRC) Aviat Equipment Sales and Point of Contact: Statement of Work 01010-1 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 Laurent Brigdan Territory Manager Laurent.Brigdan@aviatnet.com Tel: 206-340-1015 Anita Kretzschmer Sales Engineer Anita.Kretzschmer@aviatnet.com Tel: 408-501-6217 1.02 PROJECT LOCATION INFORMATION Figure 1 below provides a map showing the locations of Site Summit and Houston is provided to show the general direction of antenna alignments at Site Summit. The Site Summit site is located in Anchorage, AK at 61 15’ 30.30” N 149 31’ 44.40” W. The Houston site is located in Houston, AK at 61 37’ 06.10” N 149 49’ 04” W. Figure 1. Project Site Map Statement of Work 01010-2 Alaska Railroad Site Summit and Houston Microwave Sites 1.03 Rev. 2 March 23, 2016 GENERAL LOCATION ACCESS INFORMATION ARRC escort shall be required to access the sites and access via vehicle is preferred, weather permitting. All contractors working at Site Summit apply for access through the Joint Base Elmendorf Richardson (JBER) Security office. Information required for the application will be Name, Address, Driver’s License #, Social Security Number and Photo ID. Prior to work commencing at the site, the contractor shall submit a list of contractors who have been approved for access by the JBER Security office to the ARRC Project Manager. Helicopter may be the only transportation option during early spring and late fall months. Helicopter flights shall be coordinated with JBER. If helicopter is the only transportation option available, the contractor shall provide helicopter transportation to and from the site for one ARRC employees per work day. Houston site is located in Houston, AK off Millers Reach Rd at 61 37' 06.10" N 149 49' 40" W 1.04 GENERAL PROJECT REQUIREMENTS 1.05 1.05 A. All concrete installations shall conform to the requirements defined in Section 03300. B. All grounding system and equipment installations shall adhere to the grounding and bonding requirements defined in Section 16060. C. All wires and cables shall be labeled per the requirements defined in Section 16075. D. All conductors and cables shall installed in accordance with the requirements defined in Section 16120. SPECIAL PROJECT REQUIREMENTS A. Contractor shall perform repairs of a concrete tower foundation on site per the engineer’s structural report provided in Attachment C. A summary of the work to be performed is provided in Section 1.05 below. Upon completion of foundation repair, the tower shall not be installed until the foundation repair has been inspected and approved by the tower foundation repair report structural engineer. Contact information for the engineer will be supplied by ARRC. The contractor is responsible for scheduling the inspection and any associated costs and coordination for site access. B. The contractor shall attest that their personnel are trained, knowledgeable, and able to work in remote Alaska backcountry enduring the weather, temperature extremes, wildlife, remoteness to medical care, etc. DESCRIPTION OF WORK The work of this project shall include the furnishings of all labor, materials and equipment and the demolition, furnishing, installation, maintenance and operation of all work identified in the Contract Documents. The work generally shall include, but not be limited to the following: Statement of Work 01010-3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 A. TOWER FOUNDATION REPAIR a. Any tower anchor bolts that are greater than 3/16” out of plumb shall be repaired per the Site Summit Tower Foundation Repair drawings and engineer’s report in Attachment C. b. In general, the repair will require removal of base grout, cut damaged bolts above existing leveling nut, couple new bolt length to existing anchor bolt, readjust leveling nuts to meet level tolerance and reapply base grout. B. MICROWAVE EQUIPMENT INSTALLATION a. Contractor shall procure and install a Valmont Model 108-M830-50 50 foot tall tower. b. Procure and install Valmont Ice Bridge from West side of Tower, to East side of Shelter. c. Install a new ground system for the tower consisting of ground rods and a ground ring. Final method will disturb the least amount of native soil. Ground bars shall be mounted on the interior of shelter, outside shelter beneath cable penetration ports, and on the tower with proper connections to the exterior ground system. The new tower ground system shall be bonded to the existing facility ground. d. Contractor will install one dish antenna on the tower at 20 feet above grade according the site drawings for the link to Houston. e. Contractor will install an Aviat IRU600 microwave radio and route EW63 waveguide from the radio to the newly installed dish antenna. f. An 8-port wall entry panel will need to be purchased and installed by the contractor for waveguide penetration into the shelter. Blank port fillers shall be installed on all ports not in use. g. Install dehydrator and distribution manifold, connect all waveguide transmission lines to the dehydrator. h. Antenna alignment and radio configuration shall be per Section 16700. This site will communicate with Houston. Contractor shall verify proper antenna alignment and link margin. i. Desire of the contract is to have a fully functional communications site at the end of the contract. This includes network management bringing site information back to ARRC. C. HOUSTON a. Contractor will procure and install one dish antenna on the existing tower at 42 feet above grade according the site drawings for link to Site Summit. b. Contractor will procure and install an Aviat IRU600 microwave radio and route EW63 waveguide from the radio to the newly installed dish antenna. c. Connect all waveguide transmission lines to the existing dehydrator. d. Antenna alignment and radio configuration shall be per Section 16700. This site will communicate with Site Summit. Contractor shall verify proper antenna alignment and link margin. Statement of Work 01010-4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 D. SYSTEM ACCEPTANCE a. The contractor shall submit a system acceptance test procedure to be performed after completion of work listed above. The system acceptance test will be designed to demonstrate connectivity to the sites from the ARRC back office and ability to access new equipment status telemetry and control (where applicable) remotely from the ARRC back office. 1.06 1.07 RELATED DOCUMENTS A. Contract. B. Site Drawings. C. Attachment C – Site Summit Tower Foundation Report D. Section 01300 – Submittals E. Section 01330 – Submittal Procedures F. Section 01400 – Quality Requirements G. Section 01410 – Testing Services H. Section 01500 – Construction Facilities and Temporary Services I. Section 01600 – Materials and Equipment J. Section 01700 – Contract Closeout K. Section 01710 – Final Cleaning L. Section 01720 – Project Record Documents M. Section 03300 – Cast-in-place Concrete N. Section 16060 – Grounding and Bonding O. Section 16075 – Electrical Identification P. Section 16120 – Conductors and Cables Q. Section 16700 – Communications CONTRACTOR RESPONSIBILITIES A. Furnish all materials, tools, equipment, supervision, administration and Statement of Work 01010-5 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 transportation, and perform all labor and services necessary to furnish, deliver, construct, install, connect and/or to interconnect, test, maintain, and operate as required to complete all work described in the Specifications and indicated in the Contract Drawings. B. As necessary for proper execution and completion of work and as applicable at time of receipt of bids, secure and pay for: 1. Permits 2. Governmental Fees 3. Licenses (ARRC will provide frequency licenses) C. Give written notices necessary for, and incidental to, the due and lawful prosecution of the Work. D. Notify the Owner’s designated representative at least 7 days in advance of the date the individual construction stages or elements will be fully complete and ready for inspection. E. Notify the Owner’s designated representative at least 14 days in advance of the date the entire work will be substantially complete and ready for inspection. F. Notify the Owner’s designated representative at least 21 days in advance of the date the entire work will be complete and ready for final inspection. G. Existing utilities are indicated on the Contract Drawings are approximate. It is the Contractor responsibility to verify and/or determine, by his/her own research, the locations and depths of existing utilities prior to working in or adjacent to areas containing existing utilities. H. Until final acceptance of the Work by Owner, the Contractor(s) shall have the charge and care thereof and shall take every reasonable precaution against injury or damage to any part thereof by the action of the elements, theft, vandalism, or from any other cause, whether arising from the execution or from the nonexecution of the Work. The Contractor shall rebuild, repair, restore, and make good, to the satisfaction of the Owner’s designated representative all injuries or damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof at no cost to Owner. I. Contractor’s Field Staff 1. Safety Officer: The Prime Contractor shall assign a designated on-site Safety Officer. The Contractor’s Superintendent may perform the duties of the Safety Officer in addition to his own. The presence of Safety Officer at the site is mandatory while work is being performed. Statement of Work 01010-6 Alaska Railroad Site Summit and Houston Microwave Sites 1.08 CONTRACTOR USE OF WORKSITE A. 1.09 Rev. 2 March 23, 2016 General 1. The Contractor shall confine operations at the site to areas permitted by Owner, according to the schedule and the Contract Documents and shall not unreasonably encumber the site with any materials or equipment. 2. Keep existing driveways and entrances serving the site clear and available at all times, except as otherwise specified in the Construction Documents. 3. Keep the worksite available for the Owner’s operations during the construction period, unless otherwise noted in the construction phasing. 4. Consider the safety of the work personnel and that of people and property on and adjacent to worksite, when determining amount, location, movement, installation, and use of materials and equipment on worksite. 5. Do not load finished Work with equipment and products, which would endanger the integrity of the finished Work. 6. Move stored products as often as necessary, which interfere with foreseeable operations of Owner, public and private utilities, and other Contractors at no additional expense to Owner. Security of stored materials shall be the Contractor's responsibility. Secure additional storage and work areas needed for construction operations at no additional expense to Owner. 7. Protect the general public and Owner’s operations from constructionrelated activities. Conduct work in and on streets in a manner that will ensure that pedestrian and vehicular traffic will either not be obstructed or obstructed to the least possible degree. 8. Any temporary disruption of Owner’s operations will not be permitted at this site. WORK SEQUENCE A. General. 1. Prior to starting any work and seven calendar days after the notice to proceed, the Contractor shall submit to Owner for approval a complete construction schedule showing all phases of construction and the duration of the tasks for the entire project. The schedule shall be generated through Microsoft Project, or other acceptable scheduling software package as approved by ARRC, and shall show details for week day, weekend and holiday work, as well as work-day hours. Statement of Work 01010-7 Alaska Railroad Site Summit and Houston Microwave Sites 2. 1.10 Work is not permitted on the following holidays: 4th of July, Labor Day and Veterans Day. OWNER OCCUPANCY AND USE A. 1.11 Rev. 2 March 23, 2016 Owner reserves the right to use, or cause to be used, any portion of the Work as soon as it is made ready for use. Such use shall not be construed as acceptance of the Work by Owner. Contractor shall be responsible for maintenance and upkeep of all newly installed work and the site until final acceptance of the Work. EXISTING CONDITIONS A. The existing conditions represented in the Contract Drawings are based on the best available information obtained from one or any combination of the following sources: field survey, as-built documents, reference drawings, or visual investigation. Every effort has been made to present as much information as is possible to obtain. B. On the basis of the information presented on the Contract Drawings, visual and physical verifications shall confirm the conditions presented. If verified conditions are close to those represented on the Contract Drawings, the Contractor shall, in addition to reporting the verification to the Owner’s designated representative, proceed with the Work at no additional cost to Owner. If conditions are significantly different to those presented on the Contract Drawings, the Contractor shall, in addition to reporting the verification to the Owner’s designated representative, submit a detailed scheme for completing the required work for review and comment without additional cost to Owner. The Contractor shall allow 21 days for review and comment. C. The Contract Documents establishes specific criteria and standards of performance. The Contractor shall use its discretion to determine means of compliance and is responsible for coordinating with other Contractors at the site in order to achieve compliance. END OF SECTION 01010 Statement of Work 01010-8 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Statement of Work 01010-9 Rev. 2 March 23, 2016 Alaska Railroad Site Summit and Houston Microwave Sites SECTION 01300 SUBMITTALS PART 1 - GENERAL 1.01 1.02 1.03 DESCRIPTION A. This section of the Specifications covers all submittals including shop drawing submission and concurrence requirements, and further complements the requirements of the Contract. Make the submittals required by the Contract Documents, and revise and resubmit as necessary to establish compliance with the specified requirements. B. Submittals that are not required will not be reviewed. C. The Contractor may require subcontractors to provide drawings, installation diagrams, and similar information to help coordinate the work, but such data shall remain between the Contractor and the subcontractors and will not be reviewed unless it is required by other pertinent sections of the Specifications. RELATED WORK: A. Section 01010, Summary of Work. C. Section 01700, Contract Closeout. QUALITY ASSURANCE A. Submittals Coordination of Submittals: 1. Prior to making each submittal, the Contractor shall carefully review and coordinate all aspects of each item being submitted. Shop drawings of systems containing closely related items and components should be submitted as a single submission showing the interrelationship of the components required for that system. 2. The Contractor shall verify prior to submission that each shop drawing is well prepared and that the submittal conforms in all respects with the specified requirements. The drawings shall provide complete information regarding proper fabrication and installation. 3. The Contractor shall sign each submittal and affix a stamp with specific written indication that the Contractor has satisfied all responsibilities under the Contract Documents with respect to review of the submission. 01300-1 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 4. Shop drawings shall be tailored to the specific project need including coordination of various trades and should include material descriptions, quantities, dimensions, design criteria and similar data to enable the Owner to review information as required. The shop drawings must show clear and complete information for the fabrication and installation of materials. 5. Orient the plan(s) on the shop drawing(s) in the same manner as the plans on the Contract Drawings. 6. Shop drawings with reproduction(s) of the Contract Drawings will not be accepted. 7. Structural fabrication and erection drawings shall be prepared, checked, signed and sealed, by a Professional Engineer licensed in the State of Alaska with proven qualifications and similar experience. Unless the Contract Documents indicate specific steel connections, the Contractor shall design and provide sufficient details for the Engineer’s review and approval. B. Responsibility: The Contractor is solely responsible and accountable for: 1.04 1. Means, methods, techniques, sequences and procedures, construction including fabrication, assembly, installation/erection, and safety precautions and programs incidental to any submittal reviewed and approved by Owner. 2. Accuracy of all submittals and shop drawings and final installation. 3. Arranging submittals and shop drawing standards meetings with Owner and/or the Engineer approval. SUBSTITUTIONS A. "Or Equals" Substitutions: 1. Restricted Items: Where items of equipment and/or materials are specifically identified in the Specifications or on the Drawings by a manufacturer's name, model or catalogue number, only such specific items may be used. When several materials are specified by name for one use, the Contractor may select any of those specified. Materials specified by manufacturer's trade name shall comply with manufacturer's printed Specifications and Submittals 01300-2 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 data. 2. Equals Considered: Whenever a material or article required is specified or shown on the plans by using the name of the proprietary product or of a particular manufacturer or vendor, any material or article which will, in the opinion of Engineer, perform adequately the duties imposed by general design will be considered equal and satisfactory, provided material or article so proposed is of equal substance and function in the Engineer’s opinion. It shall not be purchased or installed without the Engineer’s written approval. "Or Equal" requests will be considered only when substantiated by the Contractor's submittal of data documenting the "or equal" nature of materiel or article within thirty-five (35) calendar days after the date of receipt of “Notice to Proceed”. B. SUBSTITUTIONS FOR UNAVAILABILITY 1. 1.05 Substitutions will be considered when a product becomes unavailable through no fault of the Contractor. The Contractor shall document each request with complete data substantiating compliance of proposed substitution with Contract Documents, or there is a clear benefit to Owner, including cost. A request constitutes a representation that the Contractor: a. Have investigated proposed product and determined that it meets or exceeds the quality level of the specified product. b. Shall provide the same warranty for the substitution as for the specified product. c. Shall coordinate installation and make changes to other work that may be required for the Work to be complete with no additional cost to Owner. 2. Shall waive claims for additional costs or time extension that may subsequently become apparent. 3. Shall reimburse Owner for review or redesign services associated with reapproval by Owner. SUBMITTALS A. Owner’s and or its Engineer’s action on submittals will be indicated in either of the following: 1. NO EXCEPTIONS TAKEN Submittals 01300-3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 2. PROCEED AS NOTED; REVISE AND RESUBMIT FOR RECORD 3. DO NOT PROCEED; REVISE AND RESUBMIT REJECTED 4. NOT APPLICABLE B. After checking and verifying all field measurements and, after complying with the applicable procedures of the Contract, Contractor shall submit shop drawings, catalog cuts, samples and substitution(s) for the Engineer’s review and approval. The Contractor shall coordinate between the sub-contractor/Fabricator/Detailer and the Engineer for each complex submittal requiring detailed coordination, including all structural items. A meeting may indicate this coordination. The purpose of the meeting(s) shall be to establish guidelines for details and information necessary to prepare the shop drawings. C. Submittals not in compliance with the Contract will be returned to the Contractor for revision. Any loss of time and additional costs associated with re-submittal(s) will be the Contractor's responsibility. D. Each submission and re-submission shall give specific written notice on the transmittal of each variation that the shop drawings or samples may have from the requirements of the Contract Documents and, in addition, shall cause a specific notation to be made on each shop drawing submitted for review and approval of each such variation. E. Each resubmission shall clearly identify and make specific notation(s) on each shop drawing concerning the: 1. Changes that are made as a result of Engineer’s comments on the previous submittal(s). 2. Changes that are not made, although commented on by the Engineer on the previous submittal(s). The Contractor shall provide detailed explanation and justification as to why the Engineer's comments are not addressed. 3. Changes that are solely made by the Contractor, but not commented on by the Engineer on the previous submittal(s). The Contractor shall provide a detailed explanation and justification for such changes. F. Submittals that are "Proceed as Noted" by the Engineer are for the purpose of expediting procurement fabrication installation of the intended work. The Contractor shall incorporate all corrections and resubmit to the Engineer the original sepias and required copies of drawings within 30 days of the "Proceed as Noted" action. Submittals 01300-4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 Payment for completed work that is related to "Proceed as Noted" submittal will not be made until the corrected and final re-submittal is accepted in writing by the Engineer. PART 2 - PRODUCTS 2.01 SHOP DRAWINGS A. Scale and measurements: Shop drawings shall be made accurately to a scale sufficiently large to show all pertinent aspects of the item and its method of connection to the Work. Owner's review of those aspects of submittal that pertain to the construction process including fabrication, assembly, installation/erection will be complimentary. B. Types of prints required: 1. 2.02 2.03 Shop drawings shall be submitted in the form of one sepia transparencies of each sheet plus six blue line or black line prints of each sheet. C. Review comments will be shown on the sepia transparency and one set will be returned to the Contractor. The Contractor may make and distribute such copies as are required for its purposes. D. When agreed upon by the owner or his representative, select submittals may be made in electronic format in the form of “.pdf” files. MANUFACTURERS' LITERATURE A. The Contractor shall submit only the original printed literature, catalog cuts and product data sheets available from the manufacturer(s). B. Where content of submitted literature from manufacturer includes data not pertinent to the submittal, the Contractor shall clearly show which portions of the contents are being submitted for review. C. The Contractor shall submit six copies. One will be returned to the contractor. SAMPLES A. The Contractor shall provide sample(s) identical to the precise article proposed to be installed. Identify as described under "Identification of submittals" below. Submittals 01300-5 Alaska Railroad Site Summit and Houston Microwave Sites B. 2.04 Rev. 2 March 23, 2016 Number of samples required: 1. Unless otherwise specified, the Contractor shall submit samples in the number required to be returned, plus one which will be retained by the Owner’s Engineer. 2. By prearrangement in specific cases a single sample may be submitted for review and, when approved, be installed in the Work at a location agreed upon by the Owner. COLORS AND PATTERNS A. Unless the precise color and pattern is specifically called out in the Contract Documents, and whenever a choice of color or pattern is available in the specified products, the Contractor shall submit accurate color and pattern charts to Owner for selection. PART 3 - EXECUTION 3.01 IDENTIFICATION OF SUBMITTALS A. Within 21 days of Notice to Proceed Contractor shall submit a complete list of all submittals for the project. Submittals are required for all items as defined in the Contract Specifications, and for all Items identified on the Contract Drawings. B. The Contractor shall consecutively number all submittals under "Transmittal". C. 3.02 1. When re-submittal(s) is made for any reason, the Contractor shall transmit under a new letter of transmittal with a new transmittal number. 2. On re-submittals, the Contractor shall cite the prior transmittal number(s) under "submission number". The Contractor shall maintain an accurate submittal log for the duration of the Work, showing current status of all submittals at all times. The Contractor shall make the submittal log available to Owner for review upon request. GROUPING OF SUBMITTALS A. Unless otherwise specified, the Contractor shall make submittals in groups containing all associated items to assure that information is available for checking each item when it is received. Submittals 01300-6 Alaska Railroad Site Summit and Houston Microwave Sites B. 3.03 Rev. 2 March 23, 2016 Partial and poorly prepared submittals will be rejected by the Engineer as not complying with the requirements of the Contract. The Contractor will be liable for delays so occasioned. TIMING OF SUBMITTALS A. The Contractor shall make submittals consistently with early start dates shown on the approved baseline schedule, but sufficiently in advance of early scheduled dates for installation to provide time required for reviews, for securing necessary approvals, for possible revisions and re-submittals, and for placing orders and securing delivery. B. In scheduling, the Contractor shall allow 21 calendar days for review and processing by the Engineer following its receipt of the submittal. This review time will be increased for the submittal(s) that are so extensive that 21 calendar days of turn around period is unreasonable as determined by the Engineer. This determination shall be binding on the Contractor. C. 3.04 Continued submission of material and repetitious submittals, which clearly fail to meet the requirements of the Contract Documents and may cause delays in the completion of the Contract, or any such delay, shall be the sole responsibility of the Contractor. OWNER'S REVIEW A. Review and Processing by the Engineer shall not relieve the Contractor from responsibility for errors that may exist in the submitted data. B. Revisions: 1. The Contractor shall make required revisions as noted on initial submittal. 2. If the Contractor considers any required revision to be a change, it shall so notify Owner as provided for in the "Agreement". Such notification shall be made no later than 10 calendar days from the date of return of such submittals, by Owner or its Engineer, to the Contractor. 3. The review of the shop drawings waives the original contract requirements of the Contract Documents only if the Contractor clearly states and highlights the proposed deviation in a prominent fashion on the shop drawing itself, and only as specially stated in writing by Owner, that the Contract Document requirements are waived. END OF SECTION 01300 Submittals 01300-7 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.01 A. 1.02 A. RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. SUMMARY Section Includes: 1. 2. B. Related Requirements: 1. 2. 1.03 Submittal schedule requirements. Administrative and procedural requirements for submittals. Section 01400 "Quality Requirements" for submitting test and inspection reports, and schedule of tests and inspections. Section 01720 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data. DEFINITIONS A. Action Submittals: Written and graphic information and physical samples that require Customer’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals." B. Informational Submittals: Written and graphic information and physical samples that do not require Customer’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals." 1.04 A. SUBMITTAL SCHEDULE Revise "Submittal Schedule" Paragraph below to suit Project. If there is an office submittal review sequence policy, insert specific requirements. See the Evaluations for discussion on submittal review sequence policies. Submittal Procedures 01330-1 Alaska Railroad Site Summit and Houston Microwave Sites B. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Customer and additional time for handling and reviewing submittals required by those corrections. 1. 2. 3. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule. a. 4. A. Submit revised submittal schedule to reflect changes in current status and timing for submittals. Format: Arrange the following information in a tabular format: a. b. c. d. e. f. g. h. i. j. 1.05 Rev. 2 March 23, 2016 Scheduled date for first submittal. Specification Section number and title. Submittal Category: Action; informational. Name of subcontractor. Description of the Work covered. Scheduled date for Customer’s final release or approval. Scheduled dates for purchasing. Scheduled date of fabrication. Scheduled dates for installation. Activity or event number. SUBMITTAL FORMATS Submittal Information: Include the following information in each submittal: 1. 2. 3. 4. 5. 6. 7. 8. Project name. Date. Name of Customer. Name of Construction Manager. Name of Contractor. Name of firm or entity that prepared submittal. Names of subcontractor, manufacturer, and supplier. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals. Submittal Procedures 01330-2 Alaska Railroad Site Summit and Houston Microwave Sites 9. 10. 11. 12. 13. 14. 15. 16. 17. Rev. 2 March 23, 2016 Category and type of submittal. Submittal purpose and description. Number and title of Specification Section, with paragraph number and generic name for each of multiple items. Drawing number and detail references, as appropriate. Indication of full or partial submittal. Location(s) where product is to be installed, as appropriate. Other necessary identification. Remarks. Signature of transmitter. B. Options: Identify options requiring selection by Customer. C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Customer on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet. D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number. E. Submittals for Web-Based Project Software: Prepare submittals as PDF files, or other format indicated by Project software website. 1.06 A. SUBMITTAL PROCEDURES Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections. 1. Email: Prepare submittals as PDF package, and transmit to Customer by sending via email. Include PDF transmittal form. Include information in email subject line as requested by the Customer. a. 2. 3. B. The Customer will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file. Web-Based Project Software: Prepare submittals in PDF form, and upload to web-based Project software website. Enter required data in web-based software site to fully identify submittal. Paper: Prepare submittals in paper form, and deliver to Customer. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. 1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. Submittal Procedures 01330-3 Alaska Railroad Site Summit and Houston Microwave Sites 2. 3. 4. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination. a. C. The Customer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on the Customer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals. 1. 2. 3. D. Rev. 2 March 23, 2016 Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. The Customer will advise Contractor when a submittal being processed must be delayed for coordination. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal. Resubmittal Review: Allow 15 days for review of each resubmittal. Resubmittals: Make resubmittals in same form and number of copies as initial submittal. 1. 2. 3. Note date and content of previous submittal. Note date and content of revision in label or title block and clearly indicate extent of revision. Resubmit submittals until they are marked with approval notation from the Customer’s action stamp. E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms. F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from the Customer’s action stamp. 1.07 A. SUBMITTAL REQUIREMENTS Additional copies may be required for each type of submittal in remaining paragraphs below for projects with a construction manager or a commissioning authority. Submittal Procedures 01330-4 Alaska Railroad Site Summit and Houston Microwave Sites B. Rev. 2 March 23, 2016 Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. 1. 2. 3. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data. Mark each copy of each submittal to show which products and options are applicable. Include the following information, as applicable: a. b. c. d. e. f. g. h. 4. For equipment, include the following in addition to the above, as applicable: a. b. c. d. 5. Manufacturer's catalog cuts. Manufacturer's product specifications. Standard color charts. Statement of compliance with specified referenced standards. Testing by recognized testing agency. Application of testing agency labels and seals. Notation of coordination requirements. Availability and delivery time information. Wiring diagrams that show factory-installed wiring. Printed performance curves. Operational range diagrams. Clearances required to other construction, if not indicated on accompanying Shop Drawings. Submit Product Data before Shop Drawings, and before or concurrent with Samples. C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of key personnel and owners, and other information specified. D. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal. E. Certificates: 1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated. Submittal Procedures 01330-5 Alaska Railroad Site Summit and Houston Microwave Sites 2. 3. 4. 5. 6. F. Rev. 2 March 23, 2016 Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified. Test and Research Reports: 1. 2. 3. 4. 5. 6. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information: a. b. c. d. e. f. Submittal Procedures Name of evaluation organization. Date of evaluation. Time period when report is in effect. Product and manufacturers' names. Description of product. Test procedures and results. 01330-6 Alaska Railroad Site Summit and Houston Microwave Sites g. 1.08 Rev. 2 March 23, 2016 Limitations of use. CUSTOMER REVIEW A. Most architects (and construction managers) use a stamp to indicate action taken on submittals. Retain "Action Submittals" Paragraph below if using such a stamp, or substitute another system to comply with office policy or Owner's requirements. AIA Document A201 states that "the Architect will review and approve or take other appropriate action upon the Contractor's submittals." AIA Document A232 states that Construction Manager will review and approve submittals before transmitting those recommended for approval to Architect. Retain second option if using PDF or paper submittals. B. Action Submittals: Customer will review each submittal, indicate corrections or revisions required, and return it. C. Informational Submittals: Customer will review each submittal and will not return it, or will return it if it does not comply with requirements. Customer will forward each submittal to appropriate party. D. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from the Customer. E. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review. F. Submittals not required by the Contract Documents will be returned by Customer without action. PART 2 - PRODUCTS 2.01 SHOP DRAWINGS A. Scale and measurements: Shop drawings shall be made accurately to a scale sufficiently large to show all pertinent aspects of the item and its method of connection to the Work. Customer's review of those aspects of submittal that pertain to the construction process including fabrication, assembly, installation/erection will be complimentary. B. Types of prints required: 1. Submittal Procedures Shop drawings shall be submitted in the form of one sepia transparencies of each sheet plus six blue line or black line prints of each sheet. 01330-7 Alaska Railroad Site Summit and Houston Microwave Sites 2.02 Rev. 2 March 23, 2016 C. Review comments will be shown on the sepia transparency and one set will be returned to the Contractor. The Contractor may make and distribute such copies as are required for its purposes. D. When agreed upon by the Customer or his representative, select submittals may be made in electronic format in the form of “.pdf” files. MANUFACTURERS' LITERATURE A. The Contractor shall submit only the original printed literature, catalog cuts and product data sheets available from the manufacturer(s). B. Where content of submitted literature from manufacturer includes data not pertinent to the submittal, the Contractor shall clearly show which portions of the contents are being submitted for review. C. The Contractor shall submit six copies. One will be returned to the contractor. PART 3 - EXECUTION 3.01 IDENTIFICATION OF SUBMITTALS A. Within 21 days of Notice to Proceed Contractor shall submit a complete list of all submittals for the project. Submittals are required for all items as defined in the Contract Specifications, and for all Items identified on the Contract Drawings. B. The Contractor shall consecutively number all submittals under "Transmittal". C. 3.02 1. When re-submittal(s) is made for any reason, the Contractor shall transmit under a new letter of transmittal with a new transmittal number. 2. On re-submittals, the Contractor shall cite the prior transmittal number(s) under "submission number". The Contractor shall maintain an accurate submittal log for the duration of the Work, showing current status of all submittals at all times. The Contractor shall make the submittal log available to the Customer for review upon request. GROUPING OF SUBMITTALS A. Unless otherwise specified, the Contractor shall make submittals in groups Submittal Procedures 01330-8 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 containing all associated items to assure that information is available for checking each item when it is received. B. 3.03 Partial and poorly prepared submittals will be rejected by the Engineer as not complying with the requirements of the Contract. The Contractor will be liable for delays so occasioned. TIMING OF SUBMITTALS A. The Contractor shall make submittals consistently with early start dates shown on the approved baseline schedule, but sufficiently in advance of early scheduled dates for installation to provide time required for reviews, for securing necessary approvals, for possible revisions and re-submittals, and for placing orders and securing delivery. B. In scheduling, the Contractor shall allow 21 calendar days for review and processing by the Engineer following its receipt of the submittal. This review time will be increased for the submittal(s) that are so extensive that 21 calendar days of turn around period is unreasonable as determined by the Engineer. This determination shall be binding on the Contractor. C. 3.04 Continued submission of material and repetitious submittals, which clearly fail to meet the requirements of the Contract Documents and may cause delays in the completion of the Contract, or any such delay, shall be the sole responsibility of the Contractor. CUSTOMER'S REVIEW A. Review and Processing by the Engineer shall not relieve the Contractor from responsibility for errors that may exist in the submitted data. B. Revisions: 1. The Contractor shall make required revisions as noted on initial submittal. 2. If the Contractor considers any required revision to be a change, it shall so notify the Customer as provided for in the "Agreement". Such notification shall be made no later than 10 calendar days from the date of return of such submittals, by the Customer or its Engineer, to the Contractor. 3. The review of the shop drawings waives the original contract requirements of the Contract Documents only if the Contractor clearly states and highlights the proposed deviation in a prominent fashion on the shop drawing itself, and only as specially stated in writing by the Customer, that the Contract Document requirements are waived. Submittal Procedures 01330-9 Alaska Railroad Site Summit and Houston Microwave Site Rev. 2 March 23, 2016 END OF SECTION 01300 Submittal Procedures 01330-10 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01400 QUALITY REQUIREMENTS PART 1 - GENERAL 1.01 A. 1.02 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. SUMMARY B. Section includes administrative and procedural requirements for quality assurance and quality control. C. Testing and inspection services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. 1. 2. 3. 4. 1.03 Specific quality-assurance and quality-control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and quality-control procedures that facilitate compliance with the Contract Document requirements. Requirements for Contractor to provide quality-assurance and quality-control services required by the Owner or authorities having jurisdiction are not limited by provisions of this Section. Specific test and inspection requirements are not specified in this Section. DEFINITIONS A. Experienced: When used with an entity or individual, "experienced" unless otherwise further described means having successfully completed a minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction. B. Field Quality-Control Tests: Tests and inspections that are performed on-site for installation of the Work and for completed Work. C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, assembly, and similar operations. Quality Requirements 01400-1 Alaska Railroad Site Summit and Houston Microwave Sites 1. Rev. 2 March 23, 2016 Use of trade-specific terminology in referring to a trade or entity does not require that certain construction activities be performed by accredited or unionized individuals, or that requirements specified apply exclusively to specific trade(s). D. Product Tests: Tests and inspections that are performed by a nationally recognized testing laboratory (NRTL) according to 29 CFR 1910.7, by a testing agency accredited according to NIST's National Voluntary Laboratory Accreditation Program (NVLAP), or by a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements. E. Source Quality-Control Tests: Tests and inspections that are performed at the source; for example, plant, mill, factory, or shop. F. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency. G. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements. H. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Contractor's quality-control services do not include contract administration activities performed by the Customer. 1.04 CONFLICTING REQUIREMENTS A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements are specified and the standards or requirements establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Customer for direction before proceeding. B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Customer for a decision before proceeding. Insert an article on special compliance with a governing code only if necessary. Such provisions typically belong in the Supplementary Conditions. Quality Requirements 01400-2 Alaska Railroad Site Summit and Houston Microwave Sites 1.05 Rev. 2 March 23, 2016 INFORMATIONAL SUBMITTALS A. Contractor's Quality-Control Plan: For quality-assurance and quality-control activities and responsibilities. B. Qualification Data: For Contractor's quality-control personnel. C. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority. D. Schedule of Tests and Inspections: Prepare in tabular form and include the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. Specification Section number and title. Entity responsible for performing tests and inspections. Description of test and inspection. Identification of applicable standards. Identification of test and inspection methods. Number of tests and inspections required. Time schedule or time span for tests and inspections. Requirements for obtaining samples. Unique characteristics of each quality-control service. E. Reports: Prepare and submit certified written reports and documents as specified. F. Permits, Licenses, and Certificates: For Owner's record, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work. 1.06 CONTRACTOR'S QUALITY-CONTROL PLAN A. Quality-Control Plan, General: Submit quality-control plan within 21 days of Notice of Award. Submit in format acceptable to the customer. Identify personnel, procedures, controls, instructions, tests, records, and forms to be used to carry out Contractor's quality-assurance and quality-control responsibilities. Coordinate with Contractor's Construction Schedule. B. Quality-Control Personnel Qualifications: Engage qualified personnel trained and experienced in managing and executing quality-assurance and quality-control procedures similar in nature and extent to those required for Project. 1. Project quality-control manager may also serve as Project superintendent. Quality Requirements 01400-3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 C. Submittal Procedure: Describe procedures for ensuring compliance with requirements through review and management of submittal process. Indicate qualifications of personnel responsible for submittal review. D. Testing and Inspection: In quality-control plan, include a comprehensive schedule of Work requiring testing or inspection, including the following: 1. 2. 3. Contractor-performed tests and inspections including Subcontractor-performed tests and inspections. Include required tests and inspections and Contractorelected tests and inspections. Distinguish source quality-control tests and inspections from field quality-control tests and inspections. Special inspections required by authorities having jurisdiction and indicated on the Statement of Special Inspections. Owner-performed tests and inspections indicated in the Contract Documents. E. Continuous Inspection of Workmanship: Describe process for continuous inspection during construction to identify and correct deficiencies in workmanship in addition to testing and inspection specified. Indicate types of corrective actions to be required to bring work into compliance with standards of workmanship established by Contract requirements. F. Monitoring and Documentation: Maintain testing and inspection reports including log of approved and rejected results. Include work Customer has indicated as nonconforming or defective. Indicate corrective actions taken to bring nonconforming work into compliance with requirements. Comply with requirements of authorities having jurisdiction. 1.09 A. REPORTS AND DOCUMENTS Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Date of issue. Project title and number. Name, address, telephone number, and email address of testing agency. Dates and locations of samples and tests or inspections. Names of individuals making tests and inspections. Description of the Work and test and inspection method. Identification of product and Specification Section. Complete test or inspection data. Test and inspection results and an interpretation of test results. Record of temperature and weather conditions at time of sample taking and testing and inspection. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements. Name and signature of laboratory inspector. Quality Requirements 01400-4 Alaska Railroad Site Summit and Houston Microwave Sites 13. 1.08 Rev. 2 March 23, 2016 Recommendations on retesting and reinspecting. QUALITY ASSURANCE A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements. B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. As applicable, procure products from manufacturers able to meet qualification requirements, warranty requirements, and technical or factory-authorized service representative requirements. C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. D. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful inservice performance. E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in the State of Alaska and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar in material, design, and extent to those indicated for this Project. F. Specialists: Certain Specification Sections require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated. 1. Requirements of authorities having jurisdiction shall supersede requirements for specialists. G. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project. H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project. Quality Requirements 01400-5 Alaska Railroad Site Summit and Houston Microwave Sites 1.11 A. QUALITY CONTROL Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services. 1. 2. 3. B. Rev. 2 March 23, 2016 Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspection they are engaged to perform. Payment for these services will be made from testing and inspection allowances, as authorized by Change Orders. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Perform additional quality-control activities, whether specified or not, to verify and document that the Work complies with requirements. 1. 2. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not. Engage a qualified testing agency to perform quality-control services. a. 3. 4. 5. 6. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspection will be performed. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service. Testing and inspection requested by Contractor and not required by the Contract Documents are Contractor's responsibility. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct. C. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents. D. Testing Agency Responsibilities: Cooperate with the Customer and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections. 1. Notify Customer and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services. Quality Requirements 01400-6 Alaska Railroad Site Summit and Houston Microwave Sites 2. 3. 4. 5. 6. Rev. 2 March 23, 2016 Determine the locations from which test samples will be taken and in which insitu tests are conducted. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work. Do not perform duties of Contractor. E. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Section 013300 "Submittal Procedures." F. Manufacturer's Technical Services: Where indicated, engage a manufacturer's technical representative to observe and inspect the Work. Manufacturer's technical representative's services include participation in preinstallation conferences, examination of substrates and conditions, verification of materials, observation of Installer activities, inspection of completed portions of the Work, and submittal of written reports. G. Associated Contractor Services: Cooperate with agencies and representatives performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following: 1. 2. 3. 4. 5. 6. 7. H. Coordination: Coordinate sequence of activities to accommodate required qualityassurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspection. 1. I. Access to the Work. Incidental labor and facilities necessary to facilitate tests and inspections. Adequate quantities of representative samples of materials that require testing and inspection. Assist agency in obtaining samples. Facilities for storage and field curing of test samples. Delivery of samples to testing agencies. Preliminary design mix proposed for use for material mixes that require control by testing agency. Security and protection for samples and for testing and inspection equipment at Project site. Schedule times for tests, inspections, obtaining samples, and similar activities. Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar quality-control services required by the Contract Documents. Coordinate and submit concurrently with Contractor's Construction Schedule. Update as the Work progresses. Quality Requirements 01400-7 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.01 A. TEST AND INSPECTION LOG Test and Inspection Log: Prepare a record of tests and inspections. Include the following: 1. 2. 3. 4. B. Maintain log at Project site. Post changes and revisions as they occur. Provide access to test and inspection log for Customer’s reference during normal working hours. 1. 3.02 A. Date test or inspection was conducted. Description of the Work tested or inspected. Date test or inspection results were transmitted to Customer. Identification of testing agency or special inspector conducting test or inspection. Submit log at Project closeout as part of Project Record Documents. REPAIR AND PROTECTION General: On completion of testing, inspection, sample taking, and similar services, repair damaged construction and restore substrates and finishes. 1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. B. Protect construction exposed by or for quality-control service activities. C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services. END OF SECTION 01400 Quality Requirements 01400-8 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Quality Requirements 01400-9 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01410 TESTING SERVICES PART 1 - GENERAL 1.01 DESCRIPTION A. Work Included: The Contractor shall employ a testing and inspection agency fully licensed and competent in the field of testing specific elements of the project. The Contractor shall submit such testing agencies and their qualifications for Owner’s prior written approval. B. C. Related Work: 1. Section 01600, Materials and Equipment. 2. Divisions 2 through 16 Specification Sections as relevant. Payment for Testing and Inspection: 1. 1.02 1.03 The Contractor shall pay for all necessary testing and inspection services. QUALITY ASSURANCE A. The testing laboratory shall be approved by Owner. B. Testing, when required, shall be the strictest of all pertinent codes and regulations, including selected standards of the American Society for Testing and Materials. C. All site testing and taking of the specimens and samples shall be performed in the presence of the Construction Manager. PRODUCT HANDLING A. The Contractor shall comply with pertinent provisions of Section 01600. B. The Contractor shall promptly process and submit required copies of test reports and related instructions to assure necessary retesting and replacement of materials without any possible delay in the progress of the Work. Testing Services 01410-1 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 PART 2 - PRODUCTS 2.01 RETESTING A. 2.02 When initial tests indicate non-compliance with the Contract Documents, subsequent retesting occasioned by the non-compliance shall be performed by the same testing agency, at no additional cost to Owner. CONTRACTOR'S CONVENIENCE TESTING A. Inspecting and testing performed exclusively for the Contractor's convenience shall be the sole responsibility of the Contractor. PART 3 - EXECUTION 3.01 COOPERATION WITH TESTING LABORATORY A. 3.02 Representatives of the testing laboratory shall have access to the Work at all times and at all locations where the Work is in progress. The Contractor shall provide facilities for such access to enable the laboratory to perform its functions properly. SCHEDULES FOR TESTING A. Establishing Schedule: 1. By advance discussion with the Testing Laboratory, the Contractor shall determine the time required for the laboratory to perform its tests and to issue each of its findings. 2. The Contractor shall provide all required time within the approved construction schedule. END OF SECTION 01410 Testing Services 01410-2 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Testing Services 01410-3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01500 CONSTRUCTION FACILITIES AND TEMPORARY SERVICES PART 1 - GENERAL 1.01 DESCRIPTION A. Work Included: The Contractor shall provide temporary facilities and controls needed for the performance of its Work including, but not necessarily limited to: 1.02 1.03 1.04 1. Temporary utilities such as heat, water, electricity, and telephone; 2. Sanitary facilities 3. Enclosures such as tarpaulins, barricades, and canopies 4. First-aid facilities 5. Temporary fencing and other safety devices for pedestrian and vehicular traffic as well as isolating the construction area. RELATED SECTIONS A. Contract Agreement. B. Section 01010, Summary of Work. C. Section 01300, Submittals. SUBMITTALS A. The Contractor shall comply with pertinent provisions of Section 01300, Submittals and this Section. B. The Contractor shall provide shop drawings including means, methods and procedures related to all temporary facilities. PRODUCT HANDLING The Contractor shall maintain and protect all temporary facilities and controls in proper and safe condition throughout progress of the Work. 1.05 TEMPORARY UTILITIES AND SERVICES Construction Facilities and Temporary Services 01500-1 Alaska Railroad Site Summit and Houston Microwave Sites A. B. Water 1. The Contractor shall provide drinking water from an approved source, so piped or transported as to keep it safe and fresh and served from single service containers or satisfactory types of drinking stands or fountains. All such facilities and services shall be furnished in strict accordance with existing governing health regulations. 2. The Contractor shall protect pipes and water servicing equipment from freezing during inclement weather. Sanitary facilities: 2. C. Rev. 2 March 23, 2016 The Contractor shall furnish for the work force on this project, the necessary toilet conveniences, secluded from public observation. The conveniences shall be kept in a clean, sanitary condition and shall comply with the requirements and regulations of the agencies having jurisdiction. Power and Lighting: 1. The Contractor shall provide, maintain and pay for all costs of temporary electrical and lighting services required at the site for the proper performance and inspection of work. The level of lighting shall not be less than the existing. Remove services and lighting after completion of work and repair of all damages. 2. The Contractor shall provide area distribution boxes so located that the individual trades may furnish and use 100 ft. maximum length extension cords to obtain power and lighting at points where needed for work, inspection, and safety. 3. The Contractor shall provide all necessary items such as breakers, transformers, panel boards, and cable required for the service. The Contractor shall provide a complete distribution system expanded as required during the construction including wiring devices, outlets, distribution panels, transformers, cable and other related work necessary to provide a temporary power system for use during construction. 4. The Contractor shall pay all costs associated with the utility tie-ins, physical plant, maintenance of system throughout construction, removal of same at project completion and any other items necessary in providing temporary power and light. 5. The temporary power and lighting system shall at all times conform with the applicable codes and regulations of OSHA, NEMA, UL, and the local Construction Facilities and Temporary Services 01500-2 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 municipality. D. Telephones: 1. E. The Contractor shall make necessary arrangements and pay costs for installation, maintenance and operation of direct line (non pay type) telephone services in Owner’s field office at the site. Heating: The Contractor shall provide and maintain heat necessary for proper conduct of operations. 1.06 1.09 ACCESS, STORAGE AND PARKING AREAS A. The Contractor shall establish a construction Compound in which the Contractor provided Owner’s office trailers will be located adjacent to the Contractor's office trailers. The physical location of the compound will require written approval of the Owner’s designated representative. B. The Contractor shall provide a minimum of 3 parking spaces adjacent to the Owner’s trailer within the compound for Owner’s personnel vehicles. C. The Contractor shall provide all necessary security for this compound area. The Contractor shall provide all necessary keys to the Owner's designated representative so as to provide access to the compound at any time. D. The Contractor shall submit to the Owner’s designated representative a plan layout of the Compound within 14 days after Notice to Proceed (NTP). E. The Contractor shall coordinate the provision of utility services for all trailers and be responsible for all installation charges, removal costs at Project completion, and any periodic or other charges incidental to the provision of those utility services. F. Upon final acceptance of the Work, the Contractor shall clean up the work areas and leave them in a neat and orderly condition. The Contractor shall dismantle and remove all temporary fencing and barricades and other temporary items installed, unless otherwise directed by the Owner’s designated representative. Repair damaged areas to their original condition. ENCLOSURES AND TEMPORARY FENCING A. Furnish, erect and maintain any necessary temporary barricades, warning, danger and detour signs, suitable and adequate lights and take all other precautions to protect the work, employees and the public. Construction Facilities and Temporary Services 01500-3 Alaska Railroad Site Summit and Houston Microwave Sites 1.10 Rev. 2 March 23, 2016 DUST CONTROL A. The Contractor shall control the generation of dust on the project. Accomplish dust control by water sprinkling or by other methods approved by the Owner’s designated representative to keep all parts of the disturbed areas free from dust causing a nuisance to others. Failure to properly control dust will result in the Owner’s designated representative ordering Contractor to stop work activity until such time as the Contractor demonstrates, to the satisfaction of the Owner’s designated representative, that he has the necessary facilities to control dust. No time extensions will be allowed for this delay and the facilities shall be established at no additional cost to Owner. END OF SECTION 01500 Construction Facilities and Temporary Services 01500-4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Construction Facilities and Temporary Services 01500-5 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01600 MATERIALS AND EQUIPMENT PART 1 - GENERAL 1.01 DESCRIPTION Work of this section includes: 1.02 1.03 A. Products B. Transportation and handling C. Storage and protection D. Product options E. Substitutions RELATED WORK A. Contract. B. Section 01010, Summary of Work. C. Section 01300, Submittals. QUALITY ASSURANCE: The Contractor shall include in its Quality Assurance Program, such procedures as are required to assure full protection of work and materials. 1.04 MANUFACTURER’S RECOMMENDATIONS: The Contractor shall comply with manufacturer’s recommendations on product handling, storage, and protection except as noted in the Contract Documents or otherwise approved by Owner. 1.05 PRODUCTS A. The Contractor shall not reuse materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents. Materials and Equipment 01600-1 Alaska Railroad Site Summit and Houston Microwave Sites B. 1.06 The Contractor shall provide interchangeable components of the same manufacture, for components being replaced. TRANSPORTATION AND HANDLING A. The Contractor shall transport and handle products in accordance with manufacturer's instructions. B. The Contractor shall promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged. C. The Contractor shall provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage. D. The Contractor shall deliver products to the job site in their manufacturer's original container, with labels intact and legible. E. 1.07 Rev. 2 March 23, 2016 1. The Contractor shall maintain packaged materials with seals unbroken and labels intact until time of installation. 2. The Contractor shall promptly remove damaged material and unsuitable Items from the job site, and promptly replace with material meeting the specified requirements, at no additional cost to Owner. Owner may reject, as non-complying, such material and products, that do not bear satisfactory identification as to manufacturer, grade, quality, and other pertinent information. STORAGE AND PROTECTION A. The Contractor shall store and protect products in accordance with manufacturers' instructions, with seals and labels intact and legible. B. The Contractor shall store sensitive products in weather tight, climate controlled enclosures. C. For exterior storage of fabricated products, the contractor shall place on sloped supports, above ground. D. The Contractor may make off-site arrangements for storage and staging, and deliver material to the site as required so as not to affect work progress of other contractors and create unsafe conditions. E. The Contractor shall protect all finished surfaces and equipment. F. The Contractor shall provide protection for finished floor surfaces prior to Materials and Equipment 01600-2 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 allowing equipment or materials to be moved over such surfaces. G. 1.08 1.09 The Contractor shall maintain finished surfaces and equipment clean, unmarred, and suitable protected until final acceptance by Owner. REPAIRS AND REPLACEMENTS: A. In event of damage, the Contractor shall promptly make replacements and repairs at no additional cost to Owner. B. Additional time required to secure replacements and to make repairs will not be considered by Owner as justification for extension to contract time. PRODUCT OPTIONS A. Products Specified by reference standards or by description only: Any Product meeting those standards or description. B. Products Specified by naming one or more manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed, except as otherwise provided in the Contract Documents. PART 2 - PRODUCTS Not used. PART 3 - EXECUTION Not used. END OF SECTION 01600 Materials and Equipment 01600-3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Materials and Equipment 01600-4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01700 CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 1.02 1.03 DESCRIPTION A. This Section specifies the requirements for closing out the project in addition to those requirements specified in the Contract Agreement. B. Definitions: Project closeout is the term used to describe collective project requirements that are to be fulfilled near the end of the Contract Time in preparation for final acceptance and occupancy of the Work by the Owner, as well as final payment to the Contractor and the normal termination of the Contract. 1. Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16. 2. Time of closeout is directly related to “Substantial Completion;” therefore, the time of closeout may be either a single time period for the entire Work or a series of time periods for individual elements of the Work that have been certified as substantially complete at different dates. This time variation, if any, shall be applicable to the other provisions of this section. RELATED DOCUMENTS A. Contract. B. Section 01710 - Final Cleaning. C. Section 01720 - Project Record Documents. PREREQUISITES TO SUBSTANTIAL COMPLETION A. General: Complete the following before requesting the Owner’s inspection for certification of substantial completion, either for the entire Work or for portions of the Work. List known exceptions in the request: 1. In the progress payment request that coincides with, or is the first request following, the date substantial completion is claimed, show either 100% completion for the portion of the Work claimed as "substantially complete", or list incomplete items, the value of incomplete work, and Contract Closeout 01700-1 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 reasons for the Work being incomplete. Include supporting documentation for completion as indicated in the Contract Documents. B. 2. Submit written certification to the Owner that the Project, or designated portion thereof, is substantially complete. 3. Submit list of items to be completed or corrected, and material delivery dates of major items as applicable. 4. Submit a statement showing an accounting of changes to the Contract Sum. 5. Advise Owner of pending insurance change-over requirements. 6. Submit three copies of all specific warranties for materials and equipment, workmanship/maintenance bonds, maintenance agreements, final certifications and similar documents. The effective time limits of all guarantees and warranties shall commence on the date of Final Acceptance. 7. Obtain and submit releases enabling Owner’s full, unrestricted use of the Work and access to services and utilities. Where required, include occupancy permits, operating certificates and similar releases. 8. Deliver tools, spare parts, extra stock of material and similar physical items to the Authority. 9. Make the final change-over of locks and transmit the keys to Owner. Advise Owner’s personnel of the change-over in security provisions. 10. Complete start-up testing of systems, and instruction of the Owner's operating and maintenance personnel. Discontinue or change over and remove temporary facilities and services from the project site, along with construction tools and facilities, mock-ups, and similar elements. 11. Complete final cleaning up requirements, including touch-up painting of marred surfaces. 12. Touch-up and otherwise repair and restore marred exposed finishes. Inspection Procedures: Upon receipt of the Contractor’s requests for inspection, the Owner will either proceed with inspection or advise the Contractor of unfulfilled prerequisites. Contract Closeout 01700-2 Alaska Railroad Site Summit and Houston Microwave Sites 1.04 Rev. 2 March 23, 2016 1. Following the initial inspection, the Owner will either prepare the certificate of substantial completion, or will advise the Contractor of work which must be performed before the certificate will be issued. The Owner will repeat the inspection when requested and when assured that the Work has been substantially completed. 2. Results of the completed inspection will form the initial "punch-list" for final acceptance. 3. The punch-list shall include a reasonable time period to effectuate the work which is mutually agreed upon by all parties. PREREQUISITES TO FINAL ACCEPTANCE A. General: Complete the following before requesting the Owner's final inspection for certification of final acceptance, and final payment as required by the Agreement. List known exceptions, if any, in the request. 1. Submit the final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required. 2. Submit an updated final statement, accounting for final additional changes to the Contract Sum. 3. Submit a certified copy of the Owner's final punch-list of itemized work to be completed or otherwise resolved for acceptance and has been endorsed and dated by the Owner. 4. Submit final meter readings for utilities, a measured record of stored fuel, and similar data either of the date of substantial completion, or else when the Authority took possession of and responsibility for corresponding elements of the Work. 5. Submit consent of surety. 6. Submit evidence of final, continuing insurance coverage complying with insurance requirements. 7. Submit record drawings, maintenance manuals if not submitted previously as specified in Section 01300, final project photographs, damage or settlement- survey, property survey, and similar final record information. 8. Submit written certification that: a. Contract Closeout Contract Documents have been reviewed. 01700-3 Alaska Railroad Site Summit and Houston Microwave Sites B. Rev. 2 March 23, 2016 b. Work has been completed in accordance with Contract Documents. c. Equipment and systems have been tested in the presence of Authority representatives and are operational. Re-inspection Procedure: The Owner will re-inspect the Work upon receipt of the Contractor's notice that the work, including punch-list items resulting from earlier inspections, has been completed, except for those times whose completion has been delayed because of circumstances that are acceptable to the Owner. 1. Upon completion of re-inspection, the Owner will either prepare a certificate of final acceptance, or will advise the Contractor of work that is incomplete or of obligations that have not been fulfilled, but are required for final acceptance. 2. If necessary, the re-inspection procedure will be repeated. PART 2 - PRODUCTS Not used. PART 3 - EXECUTION Not used. END OF SECTION 01700 Contract Closeout 01700-4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Contract Closeout 01700-5 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01710 FINAL CLEANING PART 1 - GENERAL 1.01 DESCRIPTION A. 1.02 RELATED WORK A. 1.03 This section details work for preparing the site and/or facility for substantial completion. Section 01500, Construction Facilities and Temporary Controls. QUALITY ASSURANCE: A. In addition to the standards described in this Section the Contractor shall comply with pertinent requirements of governmental agencies having jurisdiction. B. "Clean," for the purpose of the Article, and except as may be specifically provided otherwise, shall be interpreted as meaning the level of cleanliness generally provided by skilled cleaners using commercial quality building and site maintenance equipment and materials. PART 2 - PRODUCTS 2.01 CLEANING MATERIAL AND EQUIPMENT A. 2.02 The Contractor shall provide required personnel, equipment, and materials needed to achieve the specified standard of cleanliness. COMPATIBILITY A. The Contractor shall use only the cleaning materials and equipment which are compatible with the surface being cleaned, as recommended by the manufacturer of the material and acceptable to Owner. B. The Contractor shall replace surfaces damaged from improper use of material and/or cleaning methods. PART 3 - EXECUTION Final Cleaning 01710-1 Alaska Railroad Site Summit and Houston Microwave Sites 3.01 Rev. 2 March 23, 2016 FINAL CLEANING A. The Contractor shall, prior to turning over the substantially completed area to Owner’s Maintenance and Operation Section, remove from the area all tools, surplus materials, equipment, scrap, debris, and waste. If any of the contractor's work continues in the substantially completed area, the Contractor shall continue the cleaning until completion. Schedule final cleaning on dates approved by Owner. B. Site: C. D. 1. Unless otherwise specifically directed by Owner, the Contractor shall sweep grade areas within the contract limit and paved areas adjacent to the site. 2. The Contractor shall completely remove resultant debris. 3. The Contractor shall remove graffiti, if any, from all surfaces and restore surface to original condition. Structures 1. The Contractor shall visually inspect all existing and finished surfaces and remove all traces of soil, waste materials, smudges, graffiti and other foreign matter. 2. The Contractor shall remove all traces of splashed materials from structure within contract limit and from adjacent surfaces. 3. If necessary to achieve a uniform degree of cleanliness, the Contractor shall wash the exterior of the structure with high pressure water and detergent. 4. In the event of stubborn stains not removable with detergent, the Contractor shall utilize light sandblasting or other cleaning methods at no additional cost to Owner. 5. The Contractor shall remove paint droppings, spots, stains and dirt from existing and finished surfaces. Finished Surface: 1. Final Cleaning The Contractor shall remove all labels and tags which are strictly used for the convenience of manufacturing, assembly, installation and identifications. 01710-2 Alaska Railroad Site Summit and Houston Microwave Sites 2. E. Rev. 2 March 23, 2016 The Contractor shall clean stained steel surfaces of all foreign material. Finish surfaces with application of buffed polish material as recommended by the manufacturer. Equipment: 1. The Contractor shall wipe surfaces of all mechanical and electrical equipment including system components to a dirt free condition. Touch up the surfaces to match with the overall finish of the equipment/system component. 2. Insure that the equipment and system components are properly identified as required by the Contract Documents. END OF SECTION 01710 Final Cleaning 01710-3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Final Cleaning 01710-4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 01720 PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.01 DESCRIPTION A. 1.02 1.03 Work Included: 1. Throughout progress of the Work, the Contractor shall maintain an accurate record of changes to the Contract Drawings and Specifications. 2. The Contractor shall, at the time of substantial completion, but prior to requesting for reduction in retainage, transfer the changes to a set of Final Record Documents. RELATED WORK A. Documents affecting work of this Section include, but are not necessarily limited to the Contract Agreement and Division 1 of these Specifications. B. Other requirements affecting Project Record Documents may appear in pertinent other Sections of these Specifications. QUALITY ASSURANCE A. Accuracy of Records: 1. The Contractor shall thoroughly coordinate changes within the Record Documents, making adequate and proper entries on each page of Specifications and each sheet of Drawings and other documents where such entry is required to show the change properly. 2. Accuracy of records shall be such that future search for items as installed may rely reasonably on information obtained from the approved Final Record Documents. B. The Contractor shall make entries on the Record Documents on a weekly basis to include all work performed during the last week. C. The Contractor shall use professional draftsperson to prepare job set as well as to transfer "job set" information to Final Record Documents. Project Record Documents 01720-1 Alaska Railroad Site Summit and Houston Microwave Sites 1.04 SUBMITTALS A. 1.05 Rev. 2 March 23, 2016 The Contractor shall comply with pertinent provisions of Section 01300, Submittals. PRODUCT HANDLING A. The Contractor shall maintain the job set of Record Documents completely protected from deterioration and from loss and damage until completion of the Work and transfer of all recorded data to the Final Record Documents. PART 2 - PRODUCTS 2.01 RECORD DOCUMENTS A. Job set: Following receipt of Owner's Notice to Proceed, the Contractor, shall secure from Engineer one complete set of all documents comprising the Contract Documents. B. Final Record Documents: The Final Record Documents are to include: 1. Updated mylars of original Contract Drawings. 2. Additional as-built mylars to include all changes during the Contract period, that could not be included on the original contract drawings. 3. Updated Specifications to include Contract Specifications with all changes made during the Contract period. 4. “As installed” versions of same size mylars of all fabrication, detail and installation drawings. 5. Electronic drawings and specifications- Drawings in AutoCAD formatted with approved version, layering and pen tables; Specifications in Microsoft Word, Version 2003 or newer. PART 3 - EXECUTION 3.01 MAINTENANCE OF JOB SET A. The Contractor shall, immediately upon receipt of the job set described in Paragraph 2.1 A. above, identify each of the Documents with the title "RECORD Project Record Documents 01720-2 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 DOCUMENTS - JOB SET." B. C. D. E. Preservation: 1. The Contractor shall, devise a suitable method for protecting the job set in consideration of the Contract duration, the probable number of occasions upon which the job set must be taken out for new entries; the transfer of information on Final Record Documents and for examination, and the conditions under which these activities will be performed. 2. The Contractor shall not use the job set for any purpose except entry of new data, for review by Engineer and transfer of data to Final Record Documents. 3. Maintain the job set at the site of Work. Making entries on Drawings: 1. The Contractor shall utilize an erasable colored pencil (not ink or indelible pencil) to clearly describe the change by graphic line and note as required. 2. The Contractor shall date all entries. 3. The Contractor shall call attention to the entry by a "cloud" drawn around the area or areas affected. 4. The Contractor shall in the event of overlapping changes, use different colors for the overlapping changes. Specifications: 1. The Contractor shall transfer all Contract changes to respective Specifications and/or drawings set immediately, as the change is incorporated in the field. 2. The Contractor shall make appropriate entries in the Specifications and drawings as soon as the change is incorporated in the field. Conversion of schematic layouts: 1. The Contract drawings may indicate arrangements of conduits, circuits, piping, ducts, and similar items shown schematically, and is not intended to portray precise physical layout. Final physical arrangement is determined by the Contractor, subject to Owner's written approval. However, design of future modifications of the facility requires accurate information as to the final physical layout of Project Record Documents 01720-3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 items which must be schematically shown on the Record Drawings. 2. 3.2 Show on the job set of Record Drawings, by dimension accurate to within (English Dimensioning Standards), the centerline of each run of items such as are described in subparagraph 3.1E.1 above. a. The Contractor shall clearly identify the item by accurate note such as "cast iron drain", "galvanized conduit," and the like. b. The Contractor shall show, by symbol or note, the vertical location of the item ("under slab," "in ceiling plenum," "exposed," and the like). c. The Contractor shall make all identification sufficiently descriptive that it may be related reliably to the Specifications. FINAL PROJECT RECORD INFORMATION A. The purpose of the Final Project Record Documents is to provide factual information regarding all aspects of the Work, both concealed and visible, to enable future modifications of the Work to proceed without lengthy and expensive site measurement, investigation, and examination. B. Accuracy of Record Data Prior to Transfer: 1. C. The Contractor is solely responsible for accurate transfer of all field changes and preparing additional mylars and specification pages. Transfer of Data to Drawings: 1. The Contractor shall carefully transfer change data shown on the job set to the Final Record Documents coordinating the changes as required. 2. The Contractor shall clearly indicate at each affected detail and master drawing a full description of changes made during construction, and the actual location of items. 3. The Contractor shall call attention to each entry by drawing a "cloud" around the areas affected. 4. The Contractor shall make changes neatly, consistently, and with the proper media to assure longevity and clear reproduction. 5. The Contractor shall prepare additional mylars in the same size as the original contract drawings for changes to details (including installation and fabrication drawings) incorporated in the construction that could not be corrected on the record drawings. These mylars shall be adequately Project Record Documents 01720-4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 identified and cross referenced with pertinent Record Drawing(s) to make it part of the Final Record Documents. D. Transfer of Data to Specifications: 1. E. 3.3 The Contractor shall accurately and legibly transfer all information from job set to Final Project Record Specifications sets. Review and Submittal: 1. The Contractor shall submit the completed set of Final Record Documents to Owner. 2. The Contractor shall participate in review meetings as required. 3. The Contractor shall make required changes and promptly deliver the Final Project Record Documents to Owner. 4. The Contractor shall sign each sheet of the record drawings including contractor stamp. CHANGES SUBSEQUENT TO ACCEPTANCE A. The Contractor has no responsibility for recording changes in the Work subsequent to Final Completion, except for changes resulting from work performed under Warranty. END OF SECTION 01720 Project Record Documents 01720-5 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Project Record Documents 01720-6 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. SUMMARY A. This Section specifies cast-in place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes, for the following: 1. 1.3 DEFINITIONS A. 1.4 Pole Foundations Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements. SUBMITTALS A. Product Data: For each type of product indicated. B. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments. 1. C. Indicate amounts of mixing water to be withheld for later addition at Project site. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication, bending, and placement. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement. Cast-in-Place Concrete 03300 - 1 Alaska Railroad Site Summit and Houston Microwave Sites D. Qualification Data: For manufacturer and testing agency. E. Material Certificates: For each of the following, signed by manufacturers: 1. 2. 3. F. 1.5 Cementitious materials. Admixtures. Steel reinforcement and accessories. Field quality-control test reports. QUALITY ASSURANCE A. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment. B. Testing Agency Qualifications: An independent agency, acceptable to the owner, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated, as documented according to ASTM E 548. C. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents: 1. 2. D. 1.6 Rev. 2 March 23, 2016 ACI 301, "Specification for Structural Concrete," Sections 1 through 5. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials." Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures. DELIVERY, STORAGE, AND HANDLING A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage. PART 2 - PRODUCTS 2.1 FORM-FACING MATERIALS A. Round Concrete Column Forms 1. Multi-layer recycled paperboard, spirally wound and laminated with adhesive of diameter as indicated on the drawings. Interior surface shall be smooth, with plastic coating. a. Manufacturer: Sonotube Cast-in-Place Concrete 03300 - 2 Alaska Railroad Site Summit and Houston Microwave Sites B. 2.2 Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiberreinforced plastic form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal. STEEL REINFORCEMENT A. 2.3 Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed. REINFORCEMENT ACCESSORIES A. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows: 1. 2.4 For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports. CONCRETE MATERIALS A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project: 1. B. C. Portland Cement: ASTM C 150, Type II, gray Normal-Weight Aggregates: ASTM C 33, Class 3S coarse aggregate or better, graded. Provide aggregates from a single source. 1. 2. 2.5 Rev. 2 March 23, 2016 Maximum Coarse-Aggregate Size: ¾ inch nominal. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement. Water: ASTM C 94/C 94M and potable. ADMIXTURES A. Air-Entraining Admixture: ASTM C 260. B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride. Cast-in-Place Concrete 03300 - 3 Rev. 2 March 23, 2016 Alaska Railroad Site Summit and Houston Microwave Sites 1. 2. 3. 4. 5. 6. 2.6 2.7 CURING MATERIALS A. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry. B. Moisture-Retaining Cover: polyethylene sheet. C. Water: Potable. ASTM C 171, polyethylene film or white burlap- RELATED MATERIALS A. 2.8 Water-Reducing Admixture: ASTM C 494/C 494M, Type A. Retarding Admixture: ASTM C 494/C 494M, Type B. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type G. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber or ASTM D 1752, cork or self-expanding cork. CONCRETE MIXTURES, GENERAL A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301. 1. Use a qualified independent testing agency for preparing and reporting proposed mixture designs based on laboratory trial mixtures. B. Limit water-soluble, chloride-ion content in hardened concrete to 0.30 percent by weight of cement. C. Admixtures: Use admixtures according to manufacturer's written instructions. 1. 2. 3. Cast-in-Place Concrete Use water-reducing or plasticizing admixture in concrete, as required, for placement and workability. Use water-reducing and retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions. Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial slabs and parking structure slabs, concrete required to be 03300 - 4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 watertight, and concrete with a water-cementitious materials ratio below 0.50. 2.9 CONCRETE MIXTURES FOR BUILDING ELEMENTS A. Equipment Pads: Proportion normal-weight concrete mixture as follows: 1. 2. 3. 4. 2.10 FABRICATING REINFORCEMENT A. 2.11 Minimum Compressive Strength: 4000 psi at 28 days. Maximum Water-Cementitious Materials Ratio: 0.50. Slump Limit: 8 inches for concrete with verified slump of 2 to 4 inches before adding water-reducing admixture or plasticizing admixture, plus or minus 1 inch. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for ¾ inch nominal maximum aggregate size. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice." CONCRETE MIXING A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish batch ticket information. 1. When air temperature is between 85 and 90 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes. PART 3 - EXECUTION 3.1 FORMWORK A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads. B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117. C. Limit concrete surface irregularities, designated by ACI 347R as abrupt or gradual, as follows: 1. Cast-in-Place Concrete Class A, 1/8 inch for smooth-formed finished surfaces. 03300 - 5 Alaska Railroad Site Summit and Houston Microwave Sites D. Construct forms tight enough to prevent loss of concrete mortar. E. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical. 1. 2. 3.2 Install keyways, reglets, recesses, and the like, for easy removal. Do not use rust-stained steel form-facing material. F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds. G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations. H. Chamfer exterior corners and edges of permanently exposed concrete. I. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items. J. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete. K. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment. L. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement. EMBEDDED ITEMS A. 3.3 Rev. 2 March 23, 2016 Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded. STEEL REINFORCEMENT A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement. Cast-in-Place Concrete 03300 - 6 Alaska Railroad Site Summit and Houston Microwave Sites 3.4 Rev. 2 March 23, 2016 B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that would reduce bond to concrete. C. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars. D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces. CONCRETE PLACEMENT A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed. B. Do not add water to concrete during delivery, at Project site, or during placement unless approved by Engineer. C. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation. 1. 2. 3. D. Deposit concrete in horizontal layers of depth to not exceed formwork design pressures and in a manner to avoid inclined construction joints. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures. 1. 2. Cast-in-Place Concrete When average high and low temperature is expected to fall below 40 deg F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials. 03300 - 7 Alaska Railroad Site Summit and Houston Microwave Sites 3. 3.5 Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs. FINISHING FORMED SURFACES A. 3.6 Rev. 2 March 23, 2016 Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects. Remove fins and other projections that exceed specified limits on formed-surface irregularities. CONCRETE PROTECTING AND CURING A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing. B. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for the remainder of the curing period. C. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including floors and slabs, concrete floor toppings, and other surfaces. D. Cure concrete according to ACI 308.1, by one or a combination of the following methods: 1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials: a. b. c. 2. Cast-in-Place Concrete Water. Continuous water-fog spray. Absorptive cover, water saturated, and kept continuously wet. Cover concrete surfaces and edges with 12-inch lap over adjacent absorptive covers. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape. 03300 - 8 Alaska Railroad Site Summit and Houston Microwave Sites 3.7 Rev. 2 March 23, 2016 FIELD QUALITY CONTROL A. Testing and Inspecting: Engage a qualified testing and inspecting agency to perform tests and inspections and to submit reports. B. Inspections: C. Concrete Tests: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements: 1. Testing Frequency: Obtain one composite sample for each day's pour of each concrete mixture exceeding 5 cu. yd., but less than 25 cu. yd., plus one set for each additional 50 cu. yd. or fraction thereof. a. 2. 3. 4. 5. Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture. Perform additional tests when concrete consistency appears to change. Air Content: ASTM C 231, pressure method, for normal-weight concrete; one test for each composite sample, but not less than one test for each day's pour of each concrete mixture. Concrete Temperature: ASTM C 1064/C 1064M; one test hourly when air temperature is 40 deg F and below and when 80 deg F and above, and one test for each composite sample. Compression Test Specimens: ASTM C 31/C 31M. a. 6. 8. Cast-in-Place Concrete Cast and field cure two sets of two standard cylinder specimens for each composite sample. Compressive-Strength Tests: ASTM C 39/C 39M; test one set of two field-cured specimens at 7 days and one set of two specimens at 28 days. a. 7. When frequency of testing will provide fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used. A compressive-strength test shall be the average compressive strength from a set of two specimens obtained from same composite sample and tested at age indicated. Strength of each concrete mixture will be satisfactory if every average of any three consecutive compressive-strength tests equals or exceeds specified compressive strength and no compressive-strength test value falls below specified compressive strength by more than 500 psi. Test results shall be reported in writing to Engineer, concrete manufacturer, and Contractor within 48 hours of testing. Reports of 03300 - 9 Alaska Railroad Site Summit and Houston Microwave Sites 9. 10. 11. 12. Rev. 2 March 23, 2016 compressive-strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Engineer but will not be used as sole basis for approval or rejection of concrete. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Engineer. Testing and inspecting agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C 42/C 42M or by other methods as directed by Engineer. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements. Correct deficiencies in the Work that test reports and inspections indicate dos not comply with the Contract Documents. END OF SECTION 03300 Cast-in-Place Concrete 03300 - 10 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Cast-in-Place Concrete 03300 - 11 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 SUMMARY OF THE WORK A. 1.3 1.4 Contract drawings and other specifications. This Section includes grounding of electrical systems and equipment. Grounding requirements specified in this Section may be supplemented by special requirements of systems described in other Sections and as shown on the drawings. SUBMITTALS A. Product Data: For each type of product indicated. B. Product Data: For the following: 1. Grounding Electrodes. 2. Grounding Conductors 3. Bonding Conductors 4. Connectors 5. Test Wells QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. 1. Grounding and Bonding Comply with UL 467. 16060 - 1 Alaska Railroad Site Summit and Houston Microwave Sites B. Rev. 2 March 23, 2016 Comply with NFPA 780 and UL 96 when interconnecting with lightning protection system. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Grounding Conductors, Cables, Connectors, and Rods: a. b. c. d. e. f. g. h. i. j. 2. Test Wells: a. b. 2.2 Hager, Model: GAW910. Or Approved Equal GROUNDING CONDUCTORS A. Underground Conductors: Bare, tinned, stranded, unless otherwise indicated. B. Bare Copper Conductors: Comply with the following: 1. C. Assembly of Stranded Conductors: ASTM B 8. Copper Bonding Conductors: As follows: 1. 2.3 Chance/Hubbell. Copperweld Corp. Erico Inc.; Electrical Products Group. ILSCO. Kearney/Cooper Power Systems. Korns: C. C. Korns Co.; Division of Robroy Industries. O-Z/Gedney Co.; a business of the EGS Electrical Group. Raco, Inc.; Division of Hubbell. Thomas & Betts, Electrical. Or Approved Equal Grounding Cable: No. 2 AWG stranded copper conductor. CONNECTOR PRODUCTS Grounding and Bonding 16060 - 2 Alaska Railroad Site Summit and Houston Microwave Sites 2.4 A. Comply with IEEE 837 and UL 467; listed for use for specific types, sizes, and combinations of conductors and connected items. B. Bolted Connectors: Bolted-pressure-type connectors, or compression type. C. Welded Connectors: Exothermic-welded type, in kit form, and selected per manufacturer's written instructions. GROUNDING ELECTRODES A. Ground Rods: Copper-clad steel. 1. 2.5 Rev. 2 March 23, 2016 Size: ¾” diameter by 96 inches in length. Test Wells A. Size: 9” diameter. B. Material: HDPE C. Cover: Twist-Lock HDPE, labeled accordingly. D. Connections within test wells shall be mechanical type. PART 3 - EXECUTION 3.1 APPLICATION A. Use only copper conductors for both insulated and bare grounding conductors in direct contact with earth, concrete, masonry, crushed stone, and similar materials. B. In raceways, use insulated equipment grounding conductors, unless otherwise specified. C. Exothermic-Welded Connections: Use for connections to structural steel and for underground connections. D. Equipment Grounding Conductor Terminations: Use bolted pressure clamps. E. Grounding Bus: indicated. 1. Grounding and Bonding Install beneath cable wall entry ports, and elsewhere as Use insulated spacer; space 1 inch from wall and support from wall a minimum of 6 inches above finished floor, unless otherwise indicated. 16060 - 3 Alaska Railroad Site Summit and Houston Microwave Sites 2. 3.2 3.3 Rev. 2 March 23, 2016 At doors, route the bus up to the top of the door frame, across the top of the doorway, and down to the specified height above the floor. F. Underground Grounding Conductors: Use tinned copper conductor, No. 2 AWG minimum. Bury at least 30 inches below grade for perimeter ground loop unless specified otherwise in the drawing. G. Install test wells flush with finished grade. EQUIPMENT GROUNDING CONDUCTORS A. Comply with NFPA 70, Article 250, for types, sizes, and quantities of equipment grounding conductors, unless specific types, larger sizes, or more conductors than required by NFPA 70 are indicated. B. Install equipment-grounding conductors in all feeders and circuits. CONNECTIONS A. General: Make connections so galvanic action or electrolysis possibility is minimized. Select connectors, connection hardware, conductors, and connection methods so metals in direct contact will be galvanically compatible. 1. Use electroplated or hot-tin-coated materials to ensure high conductivity and to make contact points closer to order of galvanic series. B. Exothermic-Welded Connections: Comply with manufacturer's written instructions. Welds that are puffed up or that show convex surfaces indicating improper cleaning are not acceptable. C. Equipment Grounding Conductor Terminations: For No. 8 AWG and larger, use pressure-type grounding lugs. No. 10 AWG and smaller grounding conductors may be terminated with winged pressure-type connectors. D. Noncontact Metal Raceway Terminations: If metallic raceways terminate at metal housings without mechanical and electrical connection to housing, terminate each conduit with a grounding bushing. Connect grounding bushings with a bare grounding conductor to grounding bus or terminal in housing. Bond electrically noncontinuous conduits at entrances and exits with grounding bushings and bare grounding conductors, unless otherwise indicated. E. Tighten screws and bolts for grounding and bonding connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A. Grounding and Bonding 16060 - 4 Alaska Railroad Site Summit and Houston Microwave Sites 3.4 Rev. 2 March 23, 2016 F. Compression-Type Connections: Use hydraulic compression tools to provide correct circumferential pressure for compression connectors. Use tools and dies recommended by connector manufacturer. Provide embossing die code or other standard method to make a visible indication that a connector has been adequately compressed on grounding conductor. G. Moisture Protection: If insulated grounding conductors are connected to ground rods or grounding buses, insulate entire area of connection and seal against moisture penetration of insulation and cable. FIELD QUALITY CONTROL TESTING A. Testing: Contractor will perform the following field quality-control testing: B. Testing: Perform the following field quality-control testing: 1. 2. 3. After installing grounding system but before permanent electrical circuitry has been energized, test for compliance with requirements. Test completed grounding system at each location where a maximum ground-resistance level is specified. Measure ground resistance at the single point ground ensuring that resistance to ground does not exceed 10 ohms. Where the resistance to ground exceeds 10 ohms install an additional 8 or 10 Ft. ground rod and retest. Repeat this process until the 10-ohm objective is met. If resistance to ground exceeds these values notify Engineer promptly and include recommendations to reduce ground resistance. Provide drawings locating each ground rod and ground rod assembly and other grounding electrodes, identify each by letter in alphabetical order, and key to the record of tests and observations. Include the number of rods driven and their approximate depth at each location. Describe measures taken to improve test results. END OF SECTION 16060 Grounding and Bonding 16060 - 5 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Grounding and Bonding 16060 - 6 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 16075 ELECTRICAL IDENTIFICATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 1.3 1.4 All Contract drawings. SUMMARY A. This Section includes electrical identification materials and devices required to comply with ANSI C2, NFPA 70, OSHA standards, and authorities having jurisdiction. B. In the event DTE requirements are different, comply with DTE standards. SUBMITTALS A. Product Data: For each electrical identification product indicated. B. Schedule of Nomenclature: An index of electrical equipment and system components used in identification signs and labels. C. Samples: For each type of label and sign to illustrate color, lettering style, and graphic features of identification products. QUALITY ASSURANCE A. Comply with ANSI C2. B. Comply with NFPA 70. C. Comply with ANSI A13.1 and NFPA 70 for color-coding. PART 2 - PRODUCTS 2.1 RACEWAY AND CABLE LABELS A. Comply with ANSI A13.1, Table 3, for minimum size of letters for legend and for minimum length of color field for each raceway and cable size. Electrical Identification 16075 - 1 Alaska Railroad Site Summit and Houston Microwave Sites 1. 2. 2.2 Rev. 2 March 23, 2016 Color: Black letters on orange field. Legend: Indicates voltage. B. Adhesive Labels: Preprinted, flexible, self-adhesive vinyl with legend overlaminated with a clear, weather- and chemical-resistant coating. C. Pre-tensioned, Wraparound Plastic Sleeves: Flexible, preprinted, color-coded, acrylic band sized to suit the diameter of the line it identifies and arranged to stay in place by pre-tensioned gripping action when placed in position. D. Colored Adhesive Tape: Self-adhesive vinyl tape not less than 3 mils thick by 1 to 2 inches wide. E. Tape Markers: Vinyl or vinyl-cloth, self-adhesive, wraparound type with preprinted numbers and letters. F. Aluminum, Wraparound Marker Bands: Bands cut from 0.014-inch- thick aluminum sheet, with stamped or embossed legend, and fitted with slots or ears for permanently securing around wire or cable jacket or around groups of conductors. G. Plasticized Card-Stock Tags: Vinyl cloth with preprinted and field-printed legends. Orange background, unless otherwise indicated, with eyelet for fastener. H. Aluminum-Faced, Card-Stock Tags: Weather-resistant, 18-point minimum card stock faced on both sides with embossible aluminum sheet, 0.002 inch thick, laminated with moisture-resistant acrylic adhesive, punched for fasteners, and preprinted with legends to suit each application. I. Brass or Aluminum Tags: 2 by 2 by 0.05-inch metal tags with stamped legend, punched for fastener. NAMEPLATES AND SIGNS A. Safety Signs: Comply with 29 CFR, Chapter XVII, Part 1910.145. B. Engraved Plastic Nameplates and Signs: Engraving stock, melamine plastic laminate, minimum 1/16 inch thick for signs up to 20 sq. in. and 1/8 inch thick for larger sizes. 1. 2. C. Engraved legend with black letters on white face. Punched or drilled for mechanical fasteners. Baked-Enamel Signs for Interior Use: Preprinted aluminum signs, punched or drilled for fasteners, with colors, legend, and size required for the application. 1/4-inch grommets in corners for mounting. Electrical Identification 16075 - 2 Alaska Railroad Site Summit and Houston Microwave Sites 2.3 Rev. 2 March 23, 2016 D. Exterior, Metal-Backed, Butyrate Signs: Weather-resistant, nonfading, preprinted, cellulose-acetate butyrate signs with 0.0396-inch galvanized-steel backing; and with colors, legend, and size required for the application. 1/4-inch grommets in corners for mounting. E. Fasteners for Nameplates and Signs: Self-tapping, stainless-steel screws or No. 10/32, stainless-steel machine screws with nuts and flat and lock washers. MISCELLANEOUS IDENTIFICATION PRODUCTS A. Cable Ties: Fungus-inert, self-extinguishing, one-piece, self-locking, Type 6/6 nylon cable ties. 1. 2. 3. 4. B. Minimum Width: 3/16 inch. Tensile Strength: 50 lb minimum. Temperature Range: Minus 40 to plus 185 deg F. Color: According to color-coding. Paint: Formulated for the type of surface and intended use. 1. 2. 3. 4. Primer for Galvanized Metal: Single-component acrylic vehicle formulated for galvanized surfaces. Primer for Concrete Masonry Units: Heavy-duty-resin block filler. Primer for Concrete: Clear, alkali-resistant, binder-type sealer. Enamel: Silicone-alkyd or alkyd urethane as recommended by manufacturer. PART 3 - EXECUTION 3.1 INSTALLATION A. Identification Materials and Devices: Install at locations for most convenient viewing without interference with operation and maintenance of equipment. B. Lettering, Colors, and Graphics: Coordinate names, abbreviations, colors, and other designations with corresponding designations in the Contract Documents or with those required by codes and standards. Use consistent designations throughout Project. C. Sequence of Work: If identification is applied to surfaces that require finish, install identification after completing finish work. D. Self-Adhesive Identification Products: Clean surfaces before applying. E. Install painted identification according to manufacturer's written instructions and as follows: Electrical Identification 16075 - 3 Alaska Railroad Site Summit and Houston Microwave Sites 1. 2. 3. F. Rev. 2 March 23, 2016 Clean surfaces of dust, loose material, and oily films before painting. Prime surfaces using type of primer specified for surface. Apply one intermediate and one finish coat of enamel. Color Banding Raceways and Exposed Cables: Band exposed and accessible raceways of the systems listed below: 1. 2. 3. Bands: Pretensioned, wraparound plastic sleeves; colored adhesive tape; or a combination of both. Make each color band 2 inches wide, completely encircling conduit, and place adjacent bands of two-color markings in contact, side by side. Band Locations: At changes in direction, at penetrations of walls and floors, at 50-foot maximum intervals in straight runs, and at 25-foot maximum intervals in congested areas. Apply the following colors to the systems listed below: a. Fire Alarm System: Red. G. Caution Labels for Indoor Boxes and Enclosures for Power and Lighting: Install pressure-sensitive, self-adhesive labels identifying system voltage with black letters on orange background. Install on exterior of door or cover. H. Circuit Identification Labels on Boxes: Install labels externally. 1. 2. 3. I. Exposed Boxes: Pressure-sensitive, self-adhesive plastic label on cover. Concealed Boxes: Plasticized card-stock tags. Labeling Legend: Permanent, waterproof listing of panel and circuit number or equivalent. Color-Coding of Secondary Phase Conductors: Use the following colors for service, feeder and branch-circuit phase conductors: 1. 480/277/208/120-V Conductors: a. b. c. 2. Factory apply color the entire length of conductors, except the following field-applied, color-coding methods may be used instead of factory-coded wire for sizes larger than No. 10 AWG: a. Electrical Identification Phase A: Black. Phase B: Red. Phase C: Blue. Colored, pressure-sensitive plastic tape in half-lapped turns for a distance of 6 inches from terminal points and in boxes where splices or taps are made. Apply last two turns of tape with no tension to prevent possible unwinding. Use 1-inch- wide tape in colors specified. Adjust tape bands to avoid obscuring cable identification markings. 16075 - 4 Alaska Railroad Site Summit and Houston Microwave Sites b. J. 2. 3. 2. 3. Conductors to Be Extended in the Future: Indicate source and circuit numbers. Multiple Power or Lighting Circuits in the Same Enclosure: Identify each conductor with source, voltage, circuit number, and phase. Use colorcoding to identify circuits' voltage and phase. Multiple Control and Communication Circuits in the Same Enclosure: Identify each conductor by its system and circuit designation. Use a consistent system of tags, color-coding, or cable marking tape. Apply warning, caution, and instruction signs as follows: 1. M. Legend: 1/4-inch- steel letter and number stamping or embossing with legend corresponding to indicated circuit designations. Tag Fasteners: Nylon cable ties. Band Fasteners: Integral ears. Apply identification to conductors as follows: 1. L. Colored cable ties applied in groups of three ties of specified color to each wire at each terminal or splice point starting 3 inches from the terminal and spaced 3 inches apart. Apply with a special tool or pliers, tighten to a snug fit, and cut off excess length. Power-Circuit Identification: Metal tags or aluminum, wraparound marker bands for cables, feeders, and power circuits in vaults, pull and junction boxes, manholes, and switchboard rooms. 1. K. Rev. 2 March 23, 2016 Warnings, Cautions, and Instructions: Install to ensure safe operation and maintenance of electrical systems and of items to which they connect. Install engraved plastic-laminated instruction signs with approved legend where instructions are needed for system or equipment operation. Install metal-backed butyrate signs for outdoor items. Equipment Identification Labels: Engraved plastic laminate. Install on each unit of equipment, including central or master unit of each system. This includes power, lighting, communication, signal, and alarm systems, unless units are specified with their own self-explanatory identification. Unless otherwise indicated, provide a single line of text with 1/2-inch- high lettering on 1-1/2-inchhigh label; where two lines of text are required, use labels 2 inches high. Use white lettering on black field. Apply labels for each unit of the following categories of equipment using mechanical fasteners: 1. 2. 3. 4. 5. Electrical Identification Panelboards, electrical cabinets, and enclosures. Access doors and panels for concealed electrical items. Disconnect switches. Enclosed circuit breakers. Control devices. 16075 - 5 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 END OF SECTION 16075 Electrical Identification 16075 - 6 Rev. 2 March 23, 2016 Alaska Railroad Site Summit and Houston Microwave Sites SECTION 16120 CONDUCTORS AND CABLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 SUMMARY A. 1.3 1.4 All Contract drawings and specifications. This Section includes wires and cables and associated connectors, splices, and terminations for wiring systems rated 600 V and less. SUBMITTALS A. Product Data: For each type of product indicated. B. Qualification Data: For testing agency. C. Field Quality-Control Test Reports: agency engaged by Contractor. From a qualified testing and inspecting QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. B. Comply with NFPA 70. PART 2 - PRODUCTS 2.1 CONDUCTORS AND CABLES A. Available Manufacturers: 1. 2. 3. 4. Conductors and Cables American Insulated Wire Corp.; a Leviton Company. General Cable Corporation. Senator Wire & Cable Company. Southwire Company. 16120 - 1 Alaska Railroad Site Summit and Houston Microwave Sites 5. 2.2 Rev. 2 March 23, 2016 Okonite B. Refer to Part 3 "Conductor and Insulation Applications" Article for insulation type, cable construction, and ratings. C. Conductor Material: Copper solid conductor for No. 10 AWG and smaller, stranded for No. 8 AWG and larger. D. Conductor Insulation Types: Type THHN-THWN, XHHW. E. Single and Multiconductor Cable as noted on the drawings. CONNECTORS AND SPLICES A. Available Manufacturers: 1. 2. 3. 4. 5. 6. B. AFC Cable Systems, Inc. AMP Incorporated/Tyco International. Hubbell/Anderson. O-Z/Gedney; EGS Electrical Group LLC. 3M Company; Electrical Products Division. Approved Equal Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated. PART 3 - EXECUTION 3.1 3.2 CONDUCTOR AND INSULATION APPLICATIONS A. Feeders in above ground conduit: Type THHN-THWN, single conductor. B. Feeders in underground conduits and ducts: Type THHN-THWN, three conductors. INSTALLATION A. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values. B. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway. Conductors and Cables 16120 - 2 Alaska Railroad Site Summit and Houston Microwave Sites 3.3 3.4 Rev. 2 March 23, 2016 C. Support conduits and cables according to National Electrical Code. D. Seal around cables penetrating fire-rated elements. E. Identify and color-code conductors and cables according to Section 16075 "Electrical Identification." CONNECTIONS A. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B. B. Make splices and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors. C. Wiring at Outlets: Install conductor at each outlet, with at least 12 inches of slack. FIELD QUALITY CONTROL A. Testing: Perform the following field quality-control testing: 1. 2. B. After installing conductors and cables and before electrical circuitry has been energized, test for compliance with requirements. Perform each electrical test and visual and mechanical inspection stated in NETA ATS, Section 7.3.1. Certify compliance with test parameters. Test Reports: Prepare a written report to record the following: 1. 2. 3. Test procedures used. Test results that comply with requirements. Test results that do not comply with requirements and corrective action taken to achieve compliance with requirements. END OF SECTION 16120 Conductors and Cables 16120 - 3 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 NO TEXT THIS PAGE Conductors and Cables 16120 - 4 Alaska Railroad Site Summit and Houston Microwave Sites Rev. 2 March 23, 2016 SECTION 16700 COMMUNICATIONS PART I – GENERAL 1.1 RELATED DOCUMENTS A. Contract drawing package B. Division 3 specification sections 1.2 SUMMARY A. This section includes all communications devices and associated connectors, splices, and termination. 1.3 SUBMITTALS A. Product Data and Factory Acceptance Test Results: For communications devices, antennas, cabling, and related mounting equipment. B. Drawings: Show final installation details for devices, cabling, and racks. C. Test Procedure: Provide test procedure that demonstrates proper installation of transmission line and antenna alignment such that adequate signal strength is applied and received from radio at opposing end of the link. D. RF signal strength test results: Document installed radios provide adequate signal strength for 6.425 – 7.125 GHz frequency range. 1. Receive signal strength at all Aviat Radios (6.425-7.125 GHz) should be at least -80 dBm at opposite end of the link at the radio interface. PART II – PRODUCTS A. The contract drawing packages contain a Bill of Materials reference lists. The Contractor is responsible for procuring all parts not listed as “Provided by ARRC.” B. All products listed as “Provided by ARRC” will be procured by ARRC and are to be installed by the contractor unless noted otherwise. PART III – EXECUTION Communications 16700 - 1 Alaska Railroad Site Summit and Houston Microwave Sites 3.1 3.2 Rev. 2 March 23, 2016 FACTORY ACCEPTANCE TEST A. All RF communications equipment (including by not limited to: radios, waveguide, antennas, etc.) shall complete factory acceptance testing by the manufacturer or an approved test agency to demonstrate equipment meets specifications. B. All factory acceptance test results shall be submitted to the owner. INSTALLATION A. All communications equipment will be installed and wired as described in the contract drawing packages and the project Summary of Work (Section 01010). B. Once installation is complete all wiring must be verified by the Contractor. C. The Contractor must test all radio links to verify receive signal strength meets the minimum requirement as detailed in this section. Additionally the Contractor must verify EIRP levels generated by each antenna do not exceed the limits defined by the frequency license. D. The Contractor is responsible for configuring all communications equipment with network settings to be defined by ARRC. END OF SECTION 16700 Communications 16700 - 2 Alaska Railroad Site Summit and Houston Microwave Sites Attachment A AVIAT Equipment List (Contractor to Procure) Rev. 2 March 23, 2016 Proposal Number Proposal Date Issue No Territory Manager System Engineer Sales Engineer Terms Delivery Expiration Currency Freight AVIAT U.S., INC. 5200 Great America Parkway Santa Clara, CA 95054 Company Alaska Railroad Corp Attn Address : : : : : : : : : : : NA140715-20857 3/14/2016 D L. Brigdan C. Menor A. Kretzschmer North End Project Phase 2 EQUIPMENT LIST DESCRIPTION ITEM 1.000 1.100 1.101 1.102 1.103 1.104 1.105 1.106 1.107 Eclipse Microwave Radio Indoor RFU IRU600 V3 RFSEC ASSY 2+0 1 ANT MAIN, 2RU, U5/U5 GHZ IRU600 V3 RFSEC ASSY 1+0 REPEATER, 2RU, U5/U5 GHZ WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 1+0/MHSB 1ANT, RPTR(MAIN) WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 2+0/FD, RPTR (RPTR) WG EXT KIT IRU600 V3 6GHZ SH2-PO2, 1+0/MHSB 1ANT, RPTR(MAIN) WG EXT KIT IRU600 V3 6GHZ SH2-PO2, 2+0/FD, RPTR (RPTR) EXT BRKT KIT IRU600 2 SHELF - As requested by customer on 03/07, flex waveguide is provided for the Houston and Summit sites as it is not known at this time the exact placement of the radios into the existing racks. The flex waveguide is part of the Bill of Material of Item 3.202. 1.200 1.201 1.202 1.203 1.204 1.205 1.206 1.207 1.208 1.209 1.210 1.211 1.212 1.213 Packet Node - INUe ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT KIT BRACKET 2RU (179-530064-001_R001) NODE PROTECTION CARD, HIGH OUTPUT AUX, ALARM I/O CARD RAC 60E, QPSK-256 QAM, High Gain, No XPIC, ACM and SYNC-E DAC GE3 GIGABIT ETHERNET SWITCH CARD NODE SW LICENSE, 400 Mbps TOTAL RADIO PAYLOAD CAPACITY NODE SW LICENSE, 800 Mbps TOTAL RADIO PAYLOAD CAPACITY LICENCE UPGRADE EZA-08006 TO EZA-08007 400 Mbps TO 800 Mbps IRU600 600 Nodal High power option 2 x RFU IRU600 600 Nodal High power option 4 x RFU UPGRADE IRU 600 Nodal High power option 4 x RFU LAYER 1 LINK AGGREGATION NODAL ON DAC GE / DAC GE3 - For the Chulitna site, additional modules and upgrade licenses will be installed to existing INUe supplied and installed in the Phase 1 project. 1.300 1.301 1.302 1.303 1.304 Eclipse Accessories CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500mm (747420016) ETHERNET CABLE, RJ45 CAT 5/CAT 5e, 2m (6.5') (037-579124-002V_REVA) TAA GIGATRUE 3 CAT6A 650MHZ PATCH CABLE,F/UTP,SLIMLINE,LOCKABLE,GRAY,2.1M/7FT ALARM I/O HD15 10M WIREWRAP (037-579315-001V) 1.400 1.401 1.402 1.403 1.404 1.405 1.406 1.407 1.408 Recommended Eclipse Spares RFU, MP, IRU600v3, 5.8/L6 GHz, 5725-6450 MHz FAN TRAY KIT, IRU 600 V3 ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT NODE PROTECTION CARD, HIGH OUTPUT AUX, ALARM I/O CARD RAC 60E, QPSK-256 QAM, High Gain, No XPIC, ACM and SYNC-E DAC GE3 GIGABIT ETHERNET SWITCH CARD CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500mm (747420016) PRODUCT CODE PART NUMBER UNIT PRICE SYSTEM PRICE QTY QTY SUMMIT PRICE QTY HOUSTON PRICE 1 1 1 1 1 1 EXX-000-204 179-530064-001 EXS-002 EXA-001 EXR-660-002 EXD-181-002 EZE-08006 EZE-08007 EZA-08007-LU6 EZF-62 EZF-64 EZG-64 EZF-01 1 1 1 1 2 2 1 1 1 1 1 2 2 1 1 1 1 1 2 2 1 1 1 1 1 1 1 037-579461-500 037-579124-002 LOC-C6APC80S-GY-07 037-579315-001 1 1 2 1 1 1 2 1 1 1 2 1 2 1 2 1 2 EV104-M5-M5-300 EV105-M5-M5-300 179-530135-AA101 179-530135-AA102 179-530135-BB201 179-530135-BB202 179-530089-001 ERM-U53-301 179-530149-001 EXX-000-204 EXS-002 EXA-001 EXR-660-002 EXD-181-002 037-579461-500 2.000 Racks and Accessories 2.100 Racks 2.101 2.102 2.103 2.104 2.105 RACK ASSY CRATED, 7' CHATSWORTH ALUMINUM, 1 BREAKER PNL W/10 BLANK COVERS AND NO BREAKERS Installation Kit, Aluminum Rack, Concrete Floor (AV179-530119-001WA) Isolation Kit, 19" Rack (AV179-530121-001WA) CIRCUIT BREAKER 20 AMP SNAPAK (030017750I) 1 BREAKER PNL W/10 BLANK COVERS AND NO BREAKERS - New radio at Chulitna will be installed on existing rack supplied and installed during Phase 1. - New racks not required at Houston or Summit as new radios will be installed into existing racks. It is assumed that ARR will re-use the existing Breaker Panel at Houston but that a new Breaker Panel is required at Summit. 179-530307-0113 179-530119-001 179-530121-001 PWR-000053-TRM 179-530307-9910 3/14/2016 - 11:41 AM Page 1 of 2 EQUIPMENT LIST DESCRIPTION ITEM Antennas and Waveguide Systems Antennas ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT HYP RAD ANTENNA, 5.925-6.425GHZ, 3.0M/10FT, HP, DUAL POL, CPR137G, WHT HYP RAD ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT TEG RAD, HIGH WIND ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, UHP, DUAL POL, CPR137G, WHT TEF RAD TERMINATION LOAD,WAVEGUIDE,06 GHZ,CPR137G INBOARD SIDE STRUT KIT FOR 6FT MICROWAVE ANTENNAS; 10.5 FT (520570-10) OUTBOARD SIDE STRUT KIT FOR 8/10/12FT MICROWAVE ANTENNAS (520570-4) LEG MOUNT,UP TO 6 FEET ANTENNA DIAMETER,UP TO 8 INCHES DEPTHIAMETER LEG,WITH WAVEGUIDE 3.108 EQUIPMENT PROTECTION SHIELD KIT (MTC3513LMS) FACE MOUNT,ICE SHIELD KIT,UP TO 14 FEET FACE,SUPPORTS UP TO 8 INCHES DEPTHIAMETER LEG 3.109 (MTC3513FMS) 3.000 3.100 3.101 3.102 3.103 3.104 3.105 3.106 3.107 3.200 Waveguide 3.201 ELLIPTICAL WAVEGUIDE STANDARD, 5.925-7.125 GHZ, BLACK PE JACKET, PER FOOT (EW63-F) 3.202 3.203 3.204 3.205 3.206 3.207 EW63INSTALL-KIT (ONE KIT PER WAVEGUIDE RUN). CONSISTING OF THE FOLLOWING: AND-24312A / LDF HOISTING SUPPORT GRIP / QTY 1 AND-163SE / 5.925-7.125GHz CPR137G FIXED-TUNES CONNECTOR / QTY 2 AND-55001-137 / PRESSURE WINDOW FOR WR137/ QTY 1 FWG-063200-900 / FLEX WAVEGUIDE WR137, 5.85-8.2 GHz, CPR137G/CPR137G, 36 IN / QTY 1 AND-244106A-70 / FLEXT-TWIST HANGER ASSEMBLY FOR WR137, 6GHz / QTY 1 AND-241088-4 / GOUNDING KIT (24IN, 2 HOLE, LUG ATTACHED) / QTY 3 HARDWARE-KIT (ONE KIT PER 100FT). CONSISTING OF THE FOLLOWING: AND-UA-3 / AND UNIV ANGLE ADPTR KIT, SNAP-IN, 3/4IN THROUGH HOLE / QTY 3 AND-UAAI / UNIVERSAL ANGLE ADAPTER INSERT KIT / QTY 3 AND-31771-6 / THREAD ROD SUPPORT 24IN (610MM) LONG, KIT OF 5 / QTY 2 AND-31769-1 / 1IN HARDWARE KIT, KIT OF 10 / QTY 3 VAL EW63 X1 HOLE BOOT KIT (BAEW63) VAL EW63 X2 HOLE BOOT KIT (BAEW632) WG CUSHION EW-63, 1 HOLE (Bag of 5 Kits) (SREW63-K) EW63 X2 HOLES CUSHION (Bag of 5 Kits) (SREW632-K) - As requested by customer on 03/07, flex waveguide is provided for the Houston and Summit sites instead of waveguide extension kits as it is not known at this time the exact placement of the radios into the existing racks. The flex waveguide is part of the Bill of Material of Item 3.202 so does not need to be listed separately. - Per the Frequency Coordination completed on 03/11/2016, the Chulitna to Bald to Douglas to Willow can only be licensed with the channels on different polarity. As a result, 2 waveguide runs are now required per radio. 3.300 Wall Entry Panels 3.301 ENTRANCE PANEL, 2 PORT, 1 X 2 IN (204673-2A) 3.302 4 PORT ENTRANCE PANEL, 4 INCH, 1 x 4 (204673-4) - A 2-port panel was supplied at Chulitna in Phase 1 where only 1 -port was used. However, the Chulitna radio now requires an additional 2-ports for the new radio to Bald Mtn. - There is an existing Entry Panel at Houston with available openings to accommodate the new WG run. 3.400 Waveguide Pressurization system DEHYDRATOR, LOW-PRESS MEM, WALL MNTBL, 3.0-5.0 PSIG, W/DSC ALRM, 115 VAC, 50/60 HZ, 4 SEP-VLVD 3.401 PRTS (PMT200B-81315) 3.401 DISTRIBUTION MANIFOLD,2-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE 3.402 DISTRIBUTION MANIFOLD,4-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE - A new dehydrator was supplied at Chulitna in Phase 1. 4.000 4.100 4.101 4.102 4.103 Professional Services Factory Services CONFIG ENG / DOCUMENTATION / DRAFTING RADIO INTEGRATION & TESTING FACTORY ACCEPTANCE TESTING 4.200 4.201 4.202 4.203 4.204 Program Management & Engineering Services PROGRAM MANAGEMENT NETWORK/SYSTEM ENGINEERING NETWORK IP & NMS PLAN/DESIGN PROJECT/SITE ENGINEERING (SITE SURVEYS) 4.300 Support Services 4.301 WARRANTY PLUS IW - NA&C, 24 MONTHS, IRU-600 4.302 WARRANTY PLUS NW - NA&C, 12 MONTHS, IRU-600 PRODUCT CODE PART NUMBER AND-HPX6-59-P1A/K AND-HPX10-59-P1A AND-WHPX6-59-P3A/K AND-UHX6-59-P3A/L AND-39099-137 AND-520570-10 AND-520570-4 UNIT PRICE SYSTEM PRICE QTY QTY SUMMIT PRICE QTY HOUSTON PRICE 1 1 1 1 1 1 1 1 1 1 AND-EW63-F 50 50 90 AND-EW63INSTALL-KIT 1 1 1 AND-HARDWARE-KIT LOC-BAEW63 LOC-BAEW632 LOC-SREW63-K LOC-SREW632-K 1 1 1 1 1 1 4 4 6 AND-204673-2A AND-204673-4 1 1 AND-PMT200B-81315 AND-6600D-2 AND-6600D-4 1 1 1 1 1 1 2 2 2 2 2 2 179-530147-001 179-530145-001 SVCS-IN-SIPQ-AE SVCS-IN-SIPQ-RI SVCS-IN-SIPQ-AT SVCS-IN-PM-PM SVCS-PN-EN-SE SVCS-PN-EN-SE SVCS-IN-SS-PE SNA-BWXXA1002438 SNA-BNWXA1001238 This sales quotation and any resulting Customer order (“Order”) are subject to Aviat Networks standard terms and conditions of sale (“Conditions”), which are available at the following web site: http://www.aviatnetworks.com/media/files/AVWN_STCS.pdf. However, if an Order is issued under or in connection with an applicable master agreement between Aviat and Customer (an “Existing Agreement”), then the Existing Agreement will govern and control the Order. 3/14/2016 - 11:41 AM Page 2 of 2 Alaska Railroad Site Summit and Houston Microwave Sites Attachment B Bill of Materials Rev. 2 March 23, 2016 MAT. REF. NO. MANUFACTURERS PART NO. DESCRIPTION MANUFACTURER QTY 5 AND-39099-137 TERMINATION LOAD,WAVEGUIDE,06 GHZ,CPR137G AVIAT 1 8 179-530147-001 AND-WHPX6-59-P3A/K TOWER LEG MOUNT KIT, SUPPORTS UP TO 8" DIA LEG & UP TO 6' ANTENNA AVIAT 1 10 ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT TEG RAD, HIGH WIND AVIAT 1 20 AND-EW63-F ELLIPTICAL WAVEGUIDE STANDARD, 5.925-7.125 GHZ, BLACK PE JACKET, PER FOOT AVIAT 50 AND-EW63INSTALL-KIT EW63INSTALL-KIT (ONE KIT PER WAVEGUIDE RUN). CONSISTING OF THE FOLLOWING: AND-24312A / LDF HOISTING SUPPORT GRIP / QTY 1 AND-163SE / 5.925-7.125GHZ CPR137G FIXED-TUNES CONNECTOR / QTY 2 AND-55001-137 / PRESSURE WINDOW FOR WR137/ QTY 1 FWG-063200-900 / FLEX WAVEGUIDE WR137, 5.85-8.2 GHZ, CPR137G/CPR137G, 36 IN / QTY 1 AND-244106A-70 / FLEXT-TWIST HANGER ASSEMBLY FOR WR137, 6GHZ / QTY 1 AND-241088-4 / GOUNDING KIT (24IN, 2 HOLE, LUG ATTACHED) / QTY 3 AVIAT AND-HARDWARE-KIT HARDWARE-KIT (ONE KIT PER 100FT). CONSISTING OF THE FOLLOWING: AND-UA-3 / AND UNIV ANGLE ADPTR KIT, SNAP-IN, 3/4IN THROUGH HOLE / QTY 3 AND-UAAI / UNIVERSAL ANGLE ADAPTER INSERT KIT / QTY 3 AND-31771-6 / THREAD ROD SUPPORT 24IN (610MM) LONG, KIT OF 5 / QTY 2 AND-31769-1 / 1IN HARDWARE KIT, KIT OF 10 / QTY 3 AVIAT 22 24 25 VAL EW63 X1 HOLE BOOT KIT (BAEW63) REMARKS ESTIMATED QUANTITY PROVIDED, IN FEET 1 1 AVIAT AVIAT 1 WG CUSHION EW-63, 1 HOLE (BAG OF 5 KITS) (SREW63-K) E576 CABLE WALL ENTRY PANEL, 4", 2X4 VALMONT 1 BAZERO BOOT ASSEMBLY KIT, 4 IN., BLANK, NO HOLES VALMONT 8 50 EV104-M5-M5-300 IRU600 V3 RFSEC ASSY 2+0 1 ANT MAIN, 2RU, U5/U5 GHZ AVIAT 1 53 179-530135-AA102 WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 2+0/FD, RPTR (RPTR) AVIAT 1 57 EXX-000-204 ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT AVIAT 1 58 179-530064-001 KIT BRACKET 2RU (179-530064-001_R001) AVIAT 1 59 EXS-002 NODE PROTECTION CARD, HIGH OUTPUT AVIAT 1 60 EXA-001 AUX, ALARM I/O CARD AVIAT 1 61 EXR-660-002 RAC 60E, QPSK-256 QAM, HIGH GAIN, NO XPIC, ACM AND SYNC-E AVIAT 2 62 EXD-181-002 AVIAT 2 63 EZE-08006 DAC GE3 GIGABIT ETHERNET SWITCH CARD NODE SW LICENSE, 400 MBPS TOTAL RADIO PAYLOAD CAPACITY AVIAT 1 66 EZF-62 1 EZF-01 IRU600 600 NODAL HIGH POWER OPTION 2 X RFU LAYER 1 LINK AGGREGATION NODAL ON DAC GE / DAC GE3 AVIAT 69 AVIAT 1 80 AND-PMT200B-81315 DEHYDRATOR, LOW-PRESS MEM, WALL MNTBL, 3.0-5.0 PSIG, W/DSC ALRM, 115 VAC, 50/60 HZ, 4 SEP-VLVD PRTS AVIAT 1 81 AND-6600D-2 DISTRIBUTION MANIFOLD,2-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE AVIAT 1 100 037-579461-500 CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500MM (747420016) AVIAT 1 101 037-579124-002 ETHERNET CABLE, RJ45 CAT 5/CAT 5E, 2M (6.5') (037-579124-002V_REVA) AVIAT 1 102 LOC-C6APC80S-GY-07 TAA GIGATRUE 3 CAT6A 650MHZ PATCH CABLE,F/UTP,SLIMLINE,LOCKABLE,GRAY,2.1M/7FT AVIAT 2 104 037-579315-001 ALARM I/O HD15 10M WIREWRAP (037-579315-001V) AVIAT 1 109 179-530307-9910 RACK ASSY, NO RACK, NO CRATE, 1 BREAKER PNL W/10 BLANK COVERS AND NO BREAKERS AVIAT 1 110 PWR-000053-TRM CIRCUIT BREAKER 20 AMP SNAPAK (030017750I) AVIAT 2 OR EQUIVALENT IF INSTALLED IN EXISTING NEG 48VDC DP 112 MG41227-K MAIN GROUND BUS BAR, INTERIOR, WALL MOUNT, 12" VALMONT 1 OR EQUIVALENT 113 MG41227-K EXTERIOR GROUND BUS BAR, WALL MOUNT, 12" VALMONT 1 OR EQUIVALENT 114 220498 GROUNDING KIT, STANDARD EW63 COMMSCOPE 2 OR EQUIVALENT 27 LOC-BAEW63 LOC-SREW63-K 42 43 117 GROUND ROD, COPPER, 8', 3/4" DIA 4 4 120 108-M830-50 ANTENNA TOWER, 50' 800 SERIES SELF-SUPPORTING TOWER, VERTICAL WAVEGUIDE LADDER, CLIMBING LADDER VALMONT 1 122 IB24D-A ICE BRIDGE KIT, 24" SPAN, 13' 4" DIRECT BURIAL, 3.5" OD VALMONT 2 130 CABLE TRAY, 6" MANUFACTURER QTY ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT HYP RAD AVIAT 1 AND-39099-137 TERMINATION LOAD,WAVEGUIDE,06 GHZ,CPR137G AVIAT 1 AND-520570-10 INBOARD SIDE STRUT KIT FOR 6FT MICROWAVE ANTENNAS; 10.5 FT (520570-10) AVIAT 1 8 179-530147-001 TOWER LEG MOUNT KIT, SUPPORTS UP TO 8" DIA LEG & UP TO 6' ANTENNA AVIAT 1 20 AND-EW63-F ELLIPTICAL WAVEGUIDE STANDARD, 5.925-7.125 GHZ, BLACK PE JACKET, PER FOOT AVIAT 90 AVIAT 1 AND-EW63INSTALL-KIT EW63INSTALL-KIT (ONE KIT PER WAVEGUIDE RUN). CONSISTING OF THE FOLLOWING: AND-24312A / LDF HOISTING SUPPORT GRIP / QTY 1 AND-163SE / 5.925-7.125GHZ CPR137G FIXED-TUNES CONNECTOR / QTY 2 AND-55001-137 / PRESSURE WINDOW FOR WR137/ QTY 1 FWG-063200-900 / FLEX WAVEGUIDE WR137, 5.85-8.2 GHZ, CPR137G/CPR137G, 36 IN / QTY 1 AND-244106A-70 / FLEXT-TWIST HANGER ASSEMBLY FOR WR137, 6GHZ / QTY 1 AND-241088-4 / GOUNDING KIT (24IN, 2 HOLE, LUG ATTACHED) / QTY 3 HARDWARE-KIT (ONE KIT PER 100FT). CONSISTING OF THE FOLLOWING: AND-UA-3 / AND UNIV ANGLE ADPTR KIT, SNAP-IN, 3/4IN THROUGH HOLE / QTY 3 AND-UAAI / UNIVERSAL ANGLE ADAPTER INSERT KIT / QTY 3 AND-31771-6 / THREAD ROD SUPPORT 24IN (610MM) LONG, KIT OF 5 / QTY 2 AND-31769-1 / 1IN HARDWARE KIT, KIT OF 10 / QTY 3 AVIAT 1 MAT. REF. NO. MANUFACTURERS PART NO. 1 AND-HPX6-59-P1A/K 5 6 22 24 DESCRIPTION REMARKS 25 AND-HARDWARE-KIT LOC-BAEW63 VAL EW63 X1 HOLE BOOT KIT (BAEW63) AVIAT 1 27 LOC-SREW63-K WG CUSHION EW-63, 1 HOLE (BAG OF 5 KITS) (SREW63-K) AVIAT 6 50 EV104-M5-M5-300 IRU600 V3 RFSEC ASSY 2+0 1 ANT MAIN, 2RU, U5/U5 GHZ AVIAT 1 53 179-530135-AA102 WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 2+0/FD, RPTR (RPTR) AVIAT 1 57 EXX-000-204 ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT AVIAT 1 58 179-530064-001 KIT BRACKET 2RU (179-530064-001_R001) AVIAT 1 59 EXS-002 NODE PROTECTION CARD, HIGH OUTPUT AVIAT 1 60 EXA-001 AUX, ALARM I/O CARD AVIAT 1 61 EXR-660-002 RAC 60E, QPSK-256 QAM, HIGH GAIN, NO XPIC, ACM AND SYNC-E AVIAT 2 62 EXD-181-002 AVIAT 2 63 EZE-08006 DAC GE3 GIGABIT ETHERNET SWITCH CARD NODE SW LICENSE, 400 MBPS TOTAL RADIO PAYLOAD CAPACITY AVIAT 1 66 EZF-62 1 EZF-01 IRU600 600 NODAL HIGH POWER OPTION 2 X RFU LAYER 1 LINK AGGREGATION NODAL ON DAC GE / DAC GE3 AVIAT 69 AVIAT 1 80 AND-PMT200B-81315 DEHYDRATOR, LOW-PRESS MEM, WALL MNTBL, 3.0-5.0 PSIG, W/DSC ALRM, 115 VAC, 50/60 HZ, 4 SEP-VLVD PRTS AVIAT 1 81 AND-6600D-2 DISTRIBUTION MANIFOLD,2-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE AVIAT 1 100 037-579461-500 CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500MM (747420016) AVIAT 1 101 037-579124-002 ETHERNET CABLE, RJ45 CAT 5/CAT 5E, 2M (6.5') (037-579124-002V_REVA) AVIAT 1 102 LOC-C6APC80S-GY-07 TAA GIGATRUE 3 CAT6A 650MHZ PATCH CABLE,F/UTP,SLIMLINE,LOCKABLE,GRAY,2.1M/7FT AVIAT 2 104 037-579315-001 ALARM I/O HD15 10M WIREWRAP (037-579315-001V) AVIAT 1 110 PWR-000053-TRM CIRCUIT BREAKER 20 AMP SNAPAK (030017750I) AVIAT 2 OR EQUIVALENT IF INSTALLED IN EXISTING NEG 48 VDC DP 114 220498 GROUNDING KIT, STANDARD EW63 COMMSCOPE 2 OR EQUIVALENT OR EQUIVALENT, GC TO PERFORM SITE SURVEY TO CONFIRM (E) ENTRY PORT DIA Alaska Railroad Site Summit and Houston Microwave Sites Attachment C Site Summit Foundation Repair Report Rev. 2 March 23, 2016 Site Summit Tower Foundation Report For: Blaine Sears Project Manager, PTC, Telecom By: Andrew P. Adams, PE Consulting Engineer Date Prepared: 7/17/15 ♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net July 17, 2015 Blaine Sears Project Manager, PTC, Telecom 825 Whitney Rd Anchorage, AK 99501 Mr. Sears: Andrew P. Adams, PE Consulting Engineer is pleased to provide the structural analysis for the existing tower foundation located at Site Summit, Alaska. Analysis for this project is based on information from the original tower design drawings provided by the Alaska Railroad. The original drawings are provided in an appendix to this report. The goal of this analysis is to determine the suitability of the existing foundation to support a like-kind tower replacement. The tower loading will be based on the following requirements. Dish Dish Dish Dish Dish Original Tower Equipment Summary Type Size Area 10’ 78.5 sf 8’ 50.24 sf 10’ 78.5 sf 6’ 28.25 sf 6’ 28.25 sf Elevation 50’ 50’ 40’ 40’ 30’ Summary of Results: Provisions in the International Existing Building Code 2009, which is currently is the governing state code for existing structures, allows for structural modifications without detailed soil and foundation analysis if certain limits are met. Per IEBC section 3403.3, there is a gravity load increase allowance of 5% and per IEBC section 3403.4, there is a lateral load increase allowance of 10% before modifications are required. However, the original tower design was based on the EIA-222-E, and the current code standards is TIA-222-G. Because of this code change, and additional load parameters requested by the AKRR, the following configuration permits the maximum allowable loading for the existing foundation. Minimum Wind Speed: 125 MPH no ice 60 MPH ½” ice Dish Dish Dish Dish Proposed Equipment Configuration Type Size Area 8’ 50.24 sf 6’ 50.24 sf 6’ 28.25 sf 6’ 28.25 sf Elevation 40’ 40’ 30’ 30’ ♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net Foundation Reaction Comparison Max Axial** 13.4 kips 10.8 kips -22.4% Original Design Proposed Design Percent Change Max Shear 35.6 kips 37 kips +4% Max Moment 1373 kip-ft 1181 kip-ft -14% **The change in foundation reactions assumes the new tower will not have walking platforms. The tower vendor may provide additional limitations to the loading based on the tower’s component capacity. Recommendations: The results of the analysis show no modifications are required to the existing foundation. However, due to some damage to the foundation anchorage, the tower foundation shall be repaired as shown on the provided drawings. Respectfully, Andrew P. Adams, P.E. 7/21/15 ♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net Appendix A: Reaction Summary ♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net 9 50.0 ft 40 30 DESIGNED APPURTENANCE LOADING 8 FT DISH 6 T1 913.7 TYPE ELEVATION TYPE ELEVATION 8 FT DISH 40 6 FT DISH 30 6 FT DISH 40 6 FT DISH 30 MATERIAL STRENGTH GRADE Fy A572-50 50 ksi Fu GRADE Fy Fu 65 ksi TOWER DESIGN NOTES 913.7 2L2x2x1/8 T2 HSS4.5x.237 40.0 ft 1. Tower designed for Exposure C to the TIA-222-G Standard. 2. Tower designed for a 125 mph basic wind in accordance with the TIA-222-G Standard. 3. Tower is also designed for a 60 mph basic wind with 0.25 in ice. Ice is considered to increase in thickness with height. 4. Deflections are based upon a 60 mph wind. 5. Tower Structure Class II. 6. Topographic Category 2 with Crest Height of 1500.00 ft 7. Weld together tower sections have flange connections. 8. Connections use galvanized A325 bolts, nuts and locking devices. Installation per TIA/EIA-222 and AISC Specifications. 9. Tower members are "hot dipped" galvanized in accordance with ASTM A123 and ASTM A153 Standards. 10. Welds are fabricated with ER-70S-6 electrodes. 913.7 5 @ 10 2L2x2x1/8 A572-50 A572-50 T3 HSS1.9x.145 30.0 ft T4 954.9 20.0 ft ALL REACTIONS ARE FACTORED UPLIFT: -74698 lb SHEAR: 12293 lb 10.0 ft 10 N.A. HSS5.563x.258 MAX. CORNER REACTIONS AT BASE: DOWN: 77597 lb SHEAR: 12572 lb AXIAL 10816 lb T5 982.4 SHEAR 6871 lb 60 mph WIND - 0.2500 in ICE AXIAL 6624 lb Weight (lb) 4678.4 Face Width (ft) 11 # Panels @ (ft) Sec. Horizontals Top Girts Diagonal Grade Diagonals Leg Grade Legs SHEAR 37065 lb Section MOMENT 212160 lb-ft 0.0 ft MOMENT 1181357 lb-ft REACTIONS - 125 mph WIND Andrew P, Adams, PE Job: Project: PO BOX 876303 Wasilla, AK 99687 Phone: (907) 947-9303 FAX: (877) 796-2690 Client: Drawn by: Code: Date: TIA-222-G Andrew Adams 07/20/15 Path: App'd: Scale: NTS Dwg No. C:\Users\Andrew Adams\Desktop\122213 T RANSFER FROM DESKTOP\Andy's Folder\Engineering Work\02 Working\Alaska Railroad Site Summit\TNX FIles\site summit tower.eri E-1 Appendix B: Foundation Modification Drawing ♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net Andrew P. Adams No. SE13603 7/21/15 EXISTING ANCHOR BOLT ASSEMBLY SCALE: 3/4" = 1'-0" REPAIR ANCHOR BOLT ASSEMBLY SCALE: 3/4" = 1'-0" ANCHOR REPLACEMENT GUIDANCE SCALE: NTS Alaska Railroad Site Summit and Houston Microwave Sites Attachment D QA/QC Checklists Rev. 2 March 23, 2016 Site Summit Telecom Site QA Checklist Initial the box when the task has been completed, dated and add any notes. Initial DRAWINGS/PLANS Correct Drawing up to date/Note Rev. Level No red lines TELECOM SHELTER Cable Wall Entry port installed on wall of shelter, near shelter door Cable Trays installed where indicated by drawings, secured to shelter ceiling Main Ground Bus Bar installed on interior shelter wall below cable entry ports Exterior Ground Bus Bar installed on exterior shelter wall below cable entry ports INTERIOR GROUND SYSTEM Interior main ground bar bonded to exterior ground bar using #2 AWG green insulated ground wire Rack ground bars installed at top of all racks, bonded to main ground bar using #6 AWG green insulated wire Cable trays bonded to interior ground system with #10 AWG green insulated ground wire Ground resistance test complete to Main Ground Bar, results approved by owner TOWER FOUNDATION Foundation Repair Approved By Engineer EXTERIOR GROUND SYSTEM #2 AWG copper ground ring installed around tower foundation, buried minimum of 30" below grade Copper ground rods installed in locations with ground wells per drawings #2 AWG copper ground wire exothermically welded to exterior ground bar, shelter ground ring, and tower ground ring Two (2) #2 AWG coopper ground wires exothermically welded to shelter ground ring and tower ground ring, buried less than 30" Ground resistance test complete, results approved by owner TOWER Tower properly bolted to foundation on all 4 legs Tower level All four Tower legs bonded and grounded to ground ring Ground Plate installed on tower close to ice bridge Climbing studs installed Climbing fall arrestor cable system secure and installed properly ICE BRIDGE ASSEMBLY Concrete foundation constructed according to specifications Ice bridge runs level with shelter Vertical cable ladder installed on tower near interface with Ice Bridge Ice bridge assemblies and foundation bonded to exterior ground system Date NOTES Site Summit Telecom Site QA Checklist Initial the box when the task has been completed, dated and add any notes. Initial ANTENNA INSTALLATION Dish antennas installed on proper tower leg, aligned per the drawings Antenna supports bonded to tower steel using ground wire Radome covers installed and secured INTERIOR EQUIPMENT Dehydrator and manifold installed near cable entry ports All rack mounted hardware securely mounted, all items included All rack mounted hardware chassis grounded to nearest ground bar using #10 AWG green insulated ground wire POWER AND WIRING Measured radio input voltage is -48 VDC All wiring between equipment as shown in one-line diagrams All Power Distribution Panel breaker ratings confirmed All DC power wiring installed in red EMT conduit Tags w/wire name correct per drawings Cable and wire Tested and Terminated recorded As installed panel schedules provided by contractor RF CABLES All cables and waveguides run straight, with no cross-overs All cables and waveguide adhere to manufacturer minimum bend radius specifications All cables and waveguides secured no less than every 4' All waveguide outer conductors are grounded to Exterior Ground Bar at Cable Entry into shelter All waveguide connected to dehydrator, all joints sealed All waveguide and cable outer conductor bonded to Tower Ground Bar at Tower-Ice Bridge interface All RF connectors tight All waveguide and cable tightly connected to antenna interface VSWR test performed, results approved by owner All waveguide penetrations through cable entry port sealed Waveguide pressure test performed, results approved by owner NET MONITORING All equipment configured with correct network settings Connectivity established with back office over radio links Sensor functionality confirmed for all newly installed sensors, correct status telemetry reported to back office Control command functionality confirmed for all newly installed control devices Event response tests performed to simulate the following: Tripped breakers, other tests requested by ARRC Date NOTES Site Summit Telecom Site QA Checklist Initial the box when the task has been completed, dated and add any notes. Initial FINAL QA/QC INSPECTION Overall visual inspection of site Name, Signature and Date of ALL persons Initialing: _____________________________________________ _____________________________________________ Final Completed Copies Go to: Contractors Rep ARRC Project Manager ARRC Telecom Date NOTES Microwave Telecom Site QA Checklist Initial the box when the task has been completed, dated and add any notes. Initial DRAWINGS/PLANS Correct Drawing up to date/Note Rev. Level No red lines TELECOM SHELTER Cable Wall Entry port installed according to drawings Cable Trays installed where indicated by drawings, secured to shelter ceiling Main Ground Bus Bar installed on interior shelter wall below cable entry ports Exterior Ground Bus Bar installed on exterior shelter wall below cable entry ports All wall penetrations are sealed INTERIOR GROUND SYSTEM Interior main ground bar bonded to exterior ground bar using #2 AWG green insulated ground wire Rack ground bars installed at top of all racks, bonded to halo wire or main ground bar using #6 AWG green insulated wire Cable trays bonded to interior ground system with #10 AWG green insulated ground wire Ground resistance test complete to Main Ground Bar, results approved by owner EXTERIOR GROUND SYSTEM #2 AWG copper ground ring installed around tower foundation, buried minimum of 30" below grade #2 AWG copper ground ring installed around shelter, buried less than 30" Copper ground rods installed in locations with ground wells per drawings #2 AWG copper ground wire exothermically welded to exterior ground bar and shelter ground ring Shelter ground ring and tower ground ring bonded together using #2 AWG ground wires or exothermic weld, buried minimum of 30" below grade Ground resistance test complete, results approved by owner ANTENNA INSTALLATION Dish antennas installed on proper tower leg, aligned per the drawings Antenna supports bonded to tower steel using ground wire Radome covers installed and secured INTERIOR EQUIPMENT Dehydrator and manifold installed near cable entry ports All rack mounted hardware securely mounted, all items included All rack mounted hardware chassis grounded to nearest ground bar using #10 AWG green insulated ground wire POWER AND WIRING All wiring between equipment as shown in one-line diagrams All Power Distribution Panel breaker ratings confirmed Date NOTES Microwave Telecom Site QA Checklist Initial the box when the task has been completed, dated and add any notes. Initial All DC power wiring installed in red EMT conduit Tags w/wire name correct per drawings Cable and wire Tested and Terminated recorded Correct voltage confirmed at all equipment power supply inputs As installed panel schedules provided by contractor RF CABLES All cables and waveguides run straight, with no cross-overs All cables and waveguide adhere to manufacturer minimum bend radius specifications All cables and waveguides secured no less than every 4' All coaxial cables include surge protection on interior side of cable entry port into shelter Surge protectors bonded to Main Ground Bar with #6 AWG green insulated ground wire All waveguide outer conductors are grounded to Exterior Ground Bar at Cable Entry into shelter All waveguide connected to dehydrator, all joints sealed All waveguide and cable outer conductor bonded to Tower Ground Bar at Tower-Ice Bridge interface All RF connectors tight All waveguide and cable tightly connected to antenna interface VSWR test performed, results approved by owner All waveguide penetrations through cable entry port sealed Waveguide pressure test performed, results approved by owner NET MONITORING All equipment configured with correct network settings Connectivity established with back office over radio links Sensor functionality confirmed for all newly installed sensors, correct status telemetry reported to back office Control command functionality confirmed for all newly installed control devices Event response tests performed to simulate the following: Tripped breakers and any other tests required by ARRC FINAL QA/QC INSPECTION Overall visual inspection of site Name, Signature and Date of ALL persons Initialing: _____________________________________________ _____________________________________________ Date NOTES Microwave Telecom Site QA Checklist Initial the box when the task has been completed, dated and add any notes. Initial Final Completed Copies Go to: Contractors Rep ARRC Project Manager ARRC Telecom Date NOTES