ARRC Site Summit and Houston Sites Techinical

advertisement
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
TABLE OF CONTENTS
TECHNICAL SPECIFICATIONS
SECTION
TITLE
DIVISION 1 – GENERAL REQUIREMENTS
01010
Statement of Work
01300
Submittals
01330
Submittal Procedures
01400
Quality Requirements
01410
Testing Services
01500
Construction Facilities and Temporary Services
01600
Materials and Equipment
01700
Contract Closeout
01710
Final Cleaning
01720
Project Record Documents
DIVISION 3 – CONCRETE
03300
Cast-In-Place Concrete
DIVISION 16 - ELECTRICAL
16060
Grounding and Bonding
16075
Electrical Identification
16120
Conductors and Cables
16700
Communications
ATTACHMENT A – AVIAT EQUIPMENT LIST (CONTRACTOR TO PROCURE)
ATTACHMENT B – BILL OF MATERIALS
ATTACHMENT C – SITE SUMMIT FOUNDATION REPAIR REPORT
ATTACHMENT D – QA/QC CHECKLIST
Table of Contents
Specifications
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Table of Contents
Specifications
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01010
STATEMENT OF WORK
PART 1 - GENERAL
1.01
PROJECT OVERVIEW
The Site Summit communications site project includes repair of an existing antenna
tower concrete foundation, installation of a 50’ communications tower on the repaired
foundation, installation of an ice bridge between the tower and existing equipment
shelter, and installation of microwave equipment in an existing equipment shelter to be a
turn-key site when complete. The new microwave link will communicate with equipment
at the Houston site where similar microwave equipment. A summary of work required at
the site is provided in Table I below. Complete details of all work required are provided
in the drawings for the site.
All work shall be completed prior to November 1, 2016.
Table I. Site Summit and Houston Work Summary
A. Applicable Contact Information
Owner/Contracting Authority:
Alaska Railroad (ARRC)
Aviat Equipment Sales and Point of Contact:
Statement of Work
01010-1
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
Laurent Brigdan
Territory Manager
Laurent.Brigdan@aviatnet.com
Tel: 206-340-1015
Anita Kretzschmer
Sales Engineer
Anita.Kretzschmer@aviatnet.com
Tel: 408-501-6217
1.02
PROJECT LOCATION INFORMATION
Figure 1 below provides a map showing the locations of Site Summit and Houston is provided to
show the general direction of antenna alignments at Site Summit.
The Site Summit site is located in Anchorage, AK at 61 15’ 30.30” N 149 31’ 44.40” W.
The Houston site is located in Houston, AK at 61 37’ 06.10” N 149 49’ 04” W.
Figure 1. Project Site Map
Statement of Work
01010-2
Alaska Railroad
Site Summit and Houston Microwave Sites
1.03
Rev. 2
March 23, 2016
GENERAL LOCATION ACCESS INFORMATION
ARRC escort shall be required to access the sites and access via vehicle is preferred, weather
permitting. All contractors working at Site Summit apply for access through the Joint Base
Elmendorf Richardson (JBER) Security office. Information required for the application will be
Name, Address, Driver’s License #, Social Security Number and Photo ID. Prior to work
commencing at the site, the contractor shall submit a list of contractors who have been approved
for access by the JBER Security office to the ARRC Project Manager. Helicopter may be the
only transportation option during early spring and late fall months. Helicopter flights shall be
coordinated with JBER. If helicopter is the only transportation option available, the contractor
shall provide helicopter transportation to and from the site for one ARRC employees per work
day. Houston site is located in Houston, AK off Millers Reach Rd at 61 37' 06.10" N 149 49' 40"
W
1.04 GENERAL PROJECT REQUIREMENTS
1.05
1.05
A.
All concrete installations shall conform to the requirements defined in Section
03300.
B.
All grounding system and equipment installations shall adhere to the grounding
and bonding requirements defined in Section 16060.
C.
All wires and cables shall be labeled per the requirements defined in Section
16075.
D.
All conductors and cables shall installed in accordance with the requirements
defined in Section 16120.
SPECIAL PROJECT REQUIREMENTS
A.
Contractor shall perform repairs of a concrete tower foundation on site per the
engineer’s structural report provided in Attachment C. A summary of the work to
be performed is provided in Section 1.05 below. Upon completion of foundation
repair, the tower shall not be installed until the foundation repair has been
inspected and approved by the tower foundation repair report structural engineer.
Contact information for the engineer will be supplied by ARRC. The contractor
is responsible for scheduling the inspection and any associated costs and
coordination for site access.
B.
The contractor shall attest that their personnel are trained, knowledgeable, and
able to work in remote Alaska backcountry enduring the weather, temperature
extremes, wildlife, remoteness to medical care, etc.
DESCRIPTION OF WORK
The work of this project shall include the furnishings of all labor, materials and equipment and
the demolition, furnishing, installation, maintenance and operation of all work identified in the
Contract Documents. The work generally shall include, but not be limited to the following:
Statement of Work
01010-3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
A. TOWER FOUNDATION REPAIR
a. Any tower anchor bolts that are greater than 3/16” out of plumb shall be repaired
per the Site Summit Tower Foundation Repair drawings and engineer’s report in
Attachment C.
b. In general, the repair will require removal of base grout, cut damaged bolts above
existing leveling nut, couple new bolt length to existing anchor bolt, readjust
leveling nuts to meet level tolerance and reapply base grout.
B. MICROWAVE EQUIPMENT INSTALLATION
a. Contractor shall procure and install a Valmont Model 108-M830-50 50 foot tall
tower.
b. Procure and install Valmont Ice Bridge from West side of Tower, to East side of
Shelter.
c. Install a new ground system for the tower consisting of ground rods and a ground
ring. Final method will disturb the least amount of native soil. Ground bars shall
be mounted on the interior of shelter, outside shelter beneath cable penetration
ports, and on the tower with proper connections to the exterior ground system.
The new tower ground system shall be bonded to the existing facility ground.
d. Contractor will install one dish antenna on the tower at 20 feet above grade
according the site drawings for the link to Houston.
e. Contractor will install an Aviat IRU600 microwave radio and route EW63
waveguide from the radio to the newly installed dish antenna.
f. An 8-port wall entry panel will need to be purchased and installed by the
contractor for waveguide penetration into the shelter. Blank port fillers shall be
installed on all ports not in use.
g. Install dehydrator and distribution manifold, connect all waveguide transmission
lines to the dehydrator.
h. Antenna alignment and radio configuration shall be per Section 16700. This site
will communicate with Houston. Contractor shall verify proper antenna alignment
and link margin.
i. Desire of the contract is to have a fully functional communications site at the end
of the contract. This includes network management bringing site information back
to ARRC.
C. HOUSTON
a. Contractor will procure and install one dish antenna on the existing tower at 42
feet above grade according the site drawings for link to Site Summit.
b. Contractor will procure and install an Aviat IRU600 microwave radio and route
EW63 waveguide from the radio to the newly installed dish antenna.
c. Connect all waveguide transmission lines to the existing dehydrator.
d. Antenna alignment and radio configuration shall be per Section 16700. This site
will communicate with Site Summit. Contractor shall verify proper antenna
alignment and link margin.
Statement of Work
01010-4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
D. SYSTEM ACCEPTANCE
a. The contractor shall submit a system acceptance test procedure to be performed
after completion of work listed above. The system acceptance test will be
designed to demonstrate connectivity to the sites from the ARRC back office and
ability to access new equipment status telemetry and control (where applicable)
remotely from the ARRC back office.
1.06
1.07
RELATED DOCUMENTS
A.
Contract.
B.
Site Drawings.
C.
Attachment C – Site Summit Tower Foundation Report
D.
Section 01300 – Submittals
E.
Section 01330 – Submittal Procedures
F.
Section 01400 – Quality Requirements
G.
Section 01410 – Testing Services
H.
Section 01500 – Construction Facilities and Temporary Services
I.
Section 01600 – Materials and Equipment
J.
Section 01700 – Contract Closeout
K.
Section 01710 – Final Cleaning
L.
Section 01720 – Project Record Documents
M.
Section 03300 – Cast-in-place Concrete
N.
Section 16060 – Grounding and Bonding
O.
Section 16075 – Electrical Identification
P.
Section 16120 – Conductors and Cables
Q.
Section 16700 – Communications
CONTRACTOR RESPONSIBILITIES
A.
Furnish all materials, tools, equipment, supervision, administration and
Statement of Work
01010-5
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
transportation, and perform all labor and services necessary to furnish, deliver,
construct, install, connect and/or to interconnect, test, maintain, and operate as
required to complete all work described in the Specifications and indicated in the
Contract Drawings.
B.
As necessary for proper execution and completion of work and as applicable at
time of receipt of bids, secure and pay for:
1.
Permits
2.
Governmental Fees
3.
Licenses (ARRC will provide frequency licenses)
C.
Give written notices necessary for, and incidental to, the due and lawful
prosecution of the Work.
D.
Notify the Owner’s designated representative at least 7 days in advance of the
date the individual construction stages or elements will be fully complete and
ready for inspection.
E.
Notify the Owner’s designated representative at least 14 days in advance of the
date the entire work will be substantially complete and ready for inspection.
F.
Notify the Owner’s designated representative at least 21 days in advance of the
date the entire work will be complete and ready for final inspection.
G.
Existing utilities are indicated on the Contract Drawings are approximate. It is the
Contractor responsibility to verify and/or determine, by his/her own research, the
locations and depths of existing utilities prior to working in or adjacent to areas
containing existing utilities.
H.
Until final acceptance of the Work by Owner, the Contractor(s) shall have the
charge and care thereof and shall take every reasonable precaution against injury
or damage to any part thereof by the action of the elements, theft, vandalism, or
from any other cause, whether arising from the execution or from the nonexecution of the Work. The Contractor shall rebuild, repair, restore, and make
good, to the satisfaction of the Owner’s designated representative all injuries or
damages to any portion of the work occasioned by any of the above causes before
final acceptance and shall bear the expense thereof at no cost to Owner.
I.
Contractor’s Field Staff
1.
Safety Officer: The Prime Contractor shall assign a designated on-site
Safety Officer. The Contractor’s Superintendent may perform the duties
of the Safety Officer in addition to his own. The presence of Safety
Officer at the site is mandatory while work is being performed.
Statement of Work
01010-6
Alaska Railroad
Site Summit and Houston Microwave Sites
1.08
CONTRACTOR USE OF WORKSITE
A.
1.09
Rev. 2
March 23, 2016
General
1.
The Contractor shall confine operations at the site to areas permitted by
Owner, according to the schedule and the Contract Documents and shall
not unreasonably encumber the site with any materials or equipment.
2.
Keep existing driveways and entrances serving the site clear and available
at all times, except as otherwise specified in the Construction Documents.
3.
Keep the worksite available for the Owner’s operations during the
construction period, unless otherwise noted in the construction phasing.
4.
Consider the safety of the work personnel and that of people and property
on and adjacent to worksite, when determining amount, location,
movement, installation, and use of materials and equipment on worksite.
5.
Do not load finished Work with equipment and products, which would
endanger the integrity of the finished Work.
6.
Move stored products as often as necessary, which interfere with
foreseeable operations of Owner, public and private utilities, and other
Contractors at no additional expense to Owner. Security of stored
materials shall be the Contractor's responsibility. Secure additional
storage and work areas needed for construction operations at no additional
expense to Owner.
7.
Protect the general public and Owner’s operations from constructionrelated activities. Conduct work in and on streets in a manner that will
ensure that pedestrian and vehicular traffic will either not be obstructed or
obstructed to the least possible degree.
8.
Any temporary disruption of Owner’s operations will not be permitted at
this site.
WORK SEQUENCE
A.
General.
1.
Prior to starting any work and seven calendar days after the notice to
proceed, the Contractor shall submit to Owner for approval a complete
construction schedule showing all phases of construction and the duration
of the tasks for the entire project. The schedule shall be generated through
Microsoft Project, or other acceptable scheduling software package as
approved by ARRC, and shall show details for week day, weekend and
holiday work, as well as work-day hours.
Statement of Work
01010-7
Alaska Railroad
Site Summit and Houston Microwave Sites
2.
1.10
Work is not permitted on the following holidays: 4th of July, Labor Day
and Veterans Day.
OWNER OCCUPANCY AND USE
A.
1.11
Rev. 2
March 23, 2016
Owner reserves the right to use, or cause to be used, any portion of the Work as
soon as it is made ready for use. Such use shall not be construed as acceptance of
the Work by Owner. Contractor shall be responsible for maintenance and upkeep of all newly installed work and the site until final acceptance of the Work.
EXISTING CONDITIONS
A.
The existing conditions represented in the Contract Drawings are based on the
best available information obtained from one or any combination of the following
sources: field survey, as-built documents, reference drawings, or visual
investigation. Every effort has been made to present as much information as is
possible to obtain.
B.
On the basis of the information presented on the Contract Drawings, visual and
physical verifications shall confirm the conditions presented. If verified
conditions are close to those represented on the Contract Drawings, the Contractor
shall, in addition to reporting the verification to the Owner’s designated
representative, proceed with the Work at no additional cost to Owner. If
conditions are significantly different to those presented on the Contract Drawings,
the Contractor shall, in addition to reporting the verification to the Owner’s
designated representative, submit a detailed scheme for completing the required
work for review and comment without additional cost to Owner. The Contractor
shall allow 21 days for review and comment.
C.
The Contract Documents establishes specific criteria and standards of
performance. The Contractor shall use its discretion to determine means of
compliance and is responsible for coordinating with other Contractors at the site
in order to achieve compliance.
END OF SECTION 01010
Statement of Work
01010-8
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Statement of Work
01010-9
Rev. 2
March 23, 2016
Alaska Railroad
Site Summit and Houston Microwave Sites
SECTION 01300
SUBMITTALS
PART 1 - GENERAL
1.01
1.02
1.03
DESCRIPTION
A.
This section of the Specifications covers all submittals including shop drawing
submission and concurrence requirements, and further complements the
requirements of the Contract. Make the submittals required by the Contract
Documents, and revise and resubmit as necessary to establish compliance with the
specified requirements.
B.
Submittals that are not required will not be reviewed.
C.
The Contractor may require subcontractors to provide drawings, installation
diagrams, and similar information to help coordinate the work, but such data shall
remain between the Contractor and the subcontractors and will not be reviewed
unless it is required by other pertinent sections of the Specifications.
RELATED WORK:
A.
Section 01010, Summary of Work.
C.
Section 01700, Contract Closeout.
QUALITY ASSURANCE
A.
Submittals
Coordination of Submittals:
1.
Prior to making each submittal, the Contractor shall carefully review and
coordinate all aspects of each item being submitted. Shop drawings of
systems containing closely related items and components should be
submitted as a single submission showing the interrelationship of the
components required for that system.
2.
The Contractor shall verify prior to submission that each shop drawing is
well prepared and that the submittal conforms in all respects with the
specified requirements. The drawings shall provide complete information
regarding proper fabrication and installation.
3.
The Contractor shall sign each submittal and affix a stamp with specific
written indication that the Contractor has satisfied all responsibilities
under the Contract Documents with respect to review of the submission.
01300-1
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
4.
Shop drawings shall be tailored to the specific project need including
coordination of various trades and should include material descriptions,
quantities, dimensions, design criteria and similar data to enable the
Owner to review information as required. The shop drawings must show
clear and complete information for the fabrication and installation of
materials.
5.
Orient the plan(s) on the shop drawing(s) in the same manner as the plans
on the Contract Drawings.
6.
Shop drawings with reproduction(s) of the Contract Drawings will not be
accepted.
7.
Structural fabrication and erection drawings shall be prepared, checked,
signed and sealed, by a Professional Engineer licensed in the State of
Alaska with proven qualifications and similar experience.
Unless the Contract Documents indicate specific steel connections, the
Contractor shall design and provide sufficient details for the Engineer’s
review and approval.
B.
Responsibility:
The Contractor is solely responsible and accountable for:
1.04
1.
Means, methods, techniques, sequences and procedures, construction
including fabrication, assembly, installation/erection, and safety
precautions and programs incidental to any submittal reviewed and
approved by Owner.
2.
Accuracy of all submittals and shop drawings and final installation.
3.
Arranging submittals and shop drawing standards meetings with Owner
and/or the Engineer approval.
SUBSTITUTIONS
A.
"Or Equals" Substitutions:
1.
Restricted Items: Where items of equipment and/or materials are
specifically identified in the Specifications or on the Drawings by a
manufacturer's name, model or catalogue number, only such specific items
may be used.
When several materials are specified by name for one use, the Contractor
may select any of those specified. Materials specified by manufacturer's
trade name shall comply with manufacturer's printed Specifications and
Submittals
01300-2
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
data.
2.
Equals Considered: Whenever a material or article required is specified or
shown on the plans by using the name of the proprietary product or of a
particular manufacturer or vendor, any material or article which will, in
the opinion of Engineer, perform adequately the duties imposed by general
design will be considered equal and satisfactory, provided material or
article so proposed is of equal substance and function in the Engineer’s
opinion. It shall not be purchased or installed without the Engineer’s
written approval.
"Or Equal" requests will be considered only when substantiated by the
Contractor's submittal of data documenting the "or equal" nature of
materiel or article within thirty-five (35) calendar days after the date of
receipt of “Notice to Proceed”.
B.
SUBSTITUTIONS FOR UNAVAILABILITY
1.
1.05
Substitutions will be considered when a product becomes unavailable
through no fault of the Contractor. The Contractor shall document each
request with complete data substantiating compliance of proposed
substitution with Contract Documents, or there is a clear benefit to Owner,
including cost. A request constitutes a representation that the Contractor:
a.
Have investigated proposed product and determined that it meets
or exceeds the quality level of the specified product.
b.
Shall provide the same warranty for the substitution as for the
specified product.
c.
Shall coordinate installation and make changes to other work that
may be required for the Work to be complete with no additional
cost to Owner.
2.
Shall waive claims for additional costs or time extension that may
subsequently become apparent.
3.
Shall reimburse Owner for review or redesign services associated with reapproval by Owner.
SUBMITTALS
A.
Owner’s and or its Engineer’s action on submittals will be indicated in either of
the following:
1. NO EXCEPTIONS TAKEN
Submittals
01300-3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
2. PROCEED AS NOTED; REVISE AND RESUBMIT FOR RECORD
3. DO NOT PROCEED; REVISE AND RESUBMIT REJECTED
4. NOT APPLICABLE
B.
After checking and verifying all field measurements and, after complying with the
applicable procedures of the Contract, Contractor shall submit shop drawings,
catalog cuts, samples and substitution(s) for the Engineer’s review and approval.
The Contractor shall coordinate between the sub-contractor/Fabricator/Detailer
and the Engineer for each complex submittal requiring detailed coordination,
including all structural items. A meeting may indicate this coordination. The
purpose of the meeting(s) shall be to establish guidelines for details and
information necessary to prepare the shop drawings.
C.
Submittals not in compliance with the Contract will be returned to the Contractor
for revision. Any loss of time and additional costs associated with re-submittal(s)
will be the Contractor's responsibility.
D.
Each submission and re-submission shall give specific written notice on the
transmittal of each variation that the shop drawings or samples may have from the
requirements of the Contract Documents and, in addition, shall cause a specific
notation to be made on each shop drawing submitted for review and approval of
each such variation.
E.
Each resubmission shall clearly identify and make specific notation(s) on each
shop drawing concerning the:
1.
Changes that are made as a result of Engineer’s comments on the previous
submittal(s).
2.
Changes that are not made, although commented on by the Engineer on
the previous submittal(s).
The Contractor shall provide detailed
explanation and justification as to why the Engineer's comments are not
addressed.
3.
Changes that are solely made by the Contractor, but not commented on by
the Engineer on the previous submittal(s). The Contractor shall provide a
detailed explanation and justification for such changes.
F.
Submittals that are "Proceed as Noted" by the Engineer are for the purpose of
expediting procurement fabrication installation of the intended work. The
Contractor shall incorporate all corrections and resubmit to the Engineer the
original sepias and required copies of drawings within 30 days of the "Proceed as
Noted" action.
Submittals
01300-4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
Payment for completed work that is related to "Proceed as Noted" submittal will
not be made until the corrected and final re-submittal is accepted in writing by the
Engineer.
PART 2 - PRODUCTS
2.01
SHOP DRAWINGS
A.
Scale and measurements: Shop drawings shall be made accurately to a scale
sufficiently large to show all pertinent aspects of the item and its method of
connection to the Work.
Owner's review of those aspects of submittal that pertain to the construction
process including fabrication, assembly, installation/erection will be
complimentary.
B.
Types of prints required:
1.
2.02
2.03
Shop drawings shall be submitted in the form of one sepia transparencies
of each sheet plus six blue line or black line prints of each sheet.
C.
Review comments will be shown on the sepia transparency and one set will be
returned to the Contractor. The Contractor may make and distribute such copies
as are required for its purposes.
D.
When agreed upon by the owner or his representative, select submittals may be
made in electronic format in the form of “.pdf” files.
MANUFACTURERS' LITERATURE
A.
The Contractor shall submit only the original printed literature, catalog cuts and
product data sheets available from the manufacturer(s).
B.
Where content of submitted literature from manufacturer includes data not
pertinent to the submittal, the Contractor shall clearly show which portions of the
contents are being submitted for review.
C.
The Contractor shall submit six copies. One will be returned to the contractor.
SAMPLES
A.
The Contractor shall provide sample(s) identical to the precise article proposed to
be installed. Identify as described under "Identification of submittals" below.
Submittals
01300-5
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
2.04
Rev. 2
March 23, 2016
Number of samples required:
1.
Unless otherwise specified, the Contractor shall submit samples in the
number required to be returned, plus one which will be retained by the
Owner’s Engineer.
2.
By prearrangement in specific cases a single sample may be submitted for
review and, when approved, be installed in the Work at a location agreed
upon by the Owner.
COLORS AND PATTERNS
A.
Unless the precise color and pattern is specifically called out in the Contract
Documents, and whenever a choice of color or pattern is available in the specified
products, the Contractor shall submit accurate color and pattern charts to Owner
for selection.
PART 3 - EXECUTION
3.01
IDENTIFICATION OF SUBMITTALS
A.
Within 21 days of Notice to Proceed Contractor shall submit a complete list of all
submittals for the project. Submittals are required for all items as defined in the
Contract Specifications, and for all Items identified on the Contract Drawings.
B.
The Contractor shall consecutively number all submittals under "Transmittal".
C.
3.02
1.
When re-submittal(s) is made for any reason, the Contractor shall transmit
under a new letter of transmittal with a new transmittal number.
2.
On re-submittals, the Contractor shall cite the prior transmittal number(s)
under "submission number".
The Contractor shall maintain an accurate submittal log for the duration of the
Work, showing current status of all submittals at all times. The Contractor shall
make the submittal log available to Owner for review upon request.
GROUPING OF SUBMITTALS
A.
Unless otherwise specified, the Contractor shall make submittals in groups
containing all associated items to assure that information is available for checking
each item when it is received.
Submittals
01300-6
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
3.03
Rev. 2
March 23, 2016
Partial and poorly prepared submittals will be rejected by the Engineer as not
complying with the requirements of the Contract. The Contractor will be liable
for delays so occasioned.
TIMING OF SUBMITTALS
A.
The Contractor shall make submittals consistently with early start dates shown on
the approved baseline schedule, but sufficiently in advance of early scheduled
dates for installation to provide time required for reviews, for securing necessary
approvals, for possible revisions and re-submittals, and for placing orders and
securing delivery.
B.
In scheduling, the Contractor shall allow 21 calendar days for review and
processing by the Engineer following its receipt of the submittal.
This review time will be increased for the submittal(s) that are so extensive that
21 calendar days of turn around period is unreasonable as determined by the
Engineer. This determination shall be binding on the Contractor.
C.
3.04
Continued submission of material and repetitious submittals, which clearly fail to
meet the requirements of the Contract Documents and may cause delays in the
completion of the Contract, or any such delay, shall be the sole responsibility of
the Contractor.
OWNER'S REVIEW
A.
Review and Processing by the Engineer shall not relieve the Contractor from
responsibility for errors that may exist in the submitted data.
B.
Revisions:
1.
The Contractor shall make required revisions as noted on initial submittal.
2.
If the Contractor considers any required revision to be a change, it shall so
notify Owner as provided for in the "Agreement". Such notification shall
be made no later than 10 calendar days from the date of return of such
submittals, by Owner or its Engineer, to the Contractor.
3.
The review of the shop drawings waives the original contract requirements
of the Contract Documents only if the Contractor clearly states and
highlights the proposed deviation in a prominent fashion on the shop
drawing itself, and only as specially stated in writing by Owner, that the
Contract Document requirements are waived.
END OF SECTION 01300
Submittals
01300-7
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01330
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.01
A.
1.02
A.
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
SUMMARY
Section Includes:
1.
2.
B.
Related Requirements:
1.
2.
1.03
Submittal schedule requirements.
Administrative and procedural requirements for submittals.
Section 01400 "Quality Requirements" for submitting test and inspection reports,
and schedule of tests and inspections.
Section 01720 "Project Record Documents" for submitting record Drawings,
record Specifications, and record Product Data.
DEFINITIONS
A.
Action Submittals: Written and graphic information and physical samples that require
Customer’s responsive action. Action submittals are those submittals indicated in
individual Specification Sections as "action submittals."
B.
Informational Submittals: Written and graphic information and physical samples that do
not require Customer’s responsive action. Submittals may be rejected for not complying
with requirements. Informational submittals are those submittals indicated in individual
Specification Sections as "informational submittals."
1.04
A.
SUBMITTAL SCHEDULE
Revise "Submittal Schedule" Paragraph below to suit Project. If there is an office
submittal review sequence policy, insert specific requirements. See the Evaluations for
discussion on submittal review sequence policies.
Submittal Procedures
01330-1
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in
chronological order by dates required by construction schedule. Include time required
for review, ordering, manufacturing, fabrication, and delivery when establishing dates.
Include additional time required for making corrections or revisions to submittals noted
by Customer and additional time for handling and reviewing submittals required by
those corrections.
1.
2.
3.
Coordinate submittal schedule with list of subcontracts, the schedule of values,
and Contractor's construction schedule.
Initial Submittal: Submit concurrently with startup construction schedule. Include
submittals required during the first 60 days of construction. List those submittals
required to maintain orderly progress of the Work and those required early
because of long lead time for manufacture or fabrication.
Final Submittal: Submit concurrently with the first complete submittal of
Contractor's construction schedule.
a.
4.
A.
Submit revised submittal schedule to reflect changes in current status and
timing for submittals.
Format: Arrange the following information in a tabular format:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
1.05
Rev. 2
March 23, 2016
Scheduled date for first submittal.
Specification Section number and title.
Submittal Category: Action; informational.
Name of subcontractor.
Description of the Work covered.
Scheduled date for Customer’s final release or approval.
Scheduled dates for purchasing.
Scheduled date of fabrication.
Scheduled dates for installation.
Activity or event number.
SUBMITTAL FORMATS
Submittal Information: Include the following information in each submittal:
1.
2.
3.
4.
5.
6.
7.
8.
Project name.
Date.
Name of Customer.
Name of Construction Manager.
Name of Contractor.
Name of firm or entity that prepared submittal.
Names of subcontractor, manufacturer, and supplier.
Unique submittal number, including revision identifier. Include Specification
Section number with sequential alphanumeric identifier; and alphanumeric suffix
for resubmittals.
Submittal Procedures
01330-2
Alaska Railroad
Site Summit and Houston Microwave Sites
9.
10.
11.
12.
13.
14.
15.
16.
17.
Rev. 2
March 23, 2016
Category and type of submittal.
Submittal purpose and description.
Number and title of Specification Section, with paragraph number and generic
name for each of multiple items.
Drawing number and detail references, as appropriate.
Indication of full or partial submittal.
Location(s) where product is to be installed, as appropriate.
Other necessary identification.
Remarks.
Signature of transmitter.
B.
Options: Identify options requiring selection by Customer.
C.
Deviations and Additional Information: On each submittal, clearly indicate deviations
from requirements in the Contract Documents, including minor variations and
limitations; include relevant additional information and revisions, other than those
requested by Customer on previous submittals. Indicate by highlighting on each
submittal or noting on attached separate sheet.
D.
PDF Submittals: Prepare submittals as PDF package, incorporating complete
information into each PDF file. Name PDF file with submittal number.
E.
Submittals for Web-Based Project Software: Prepare submittals as PDF files, or other
format indicated by Project software website.
1.06
A.
SUBMITTAL PROCEDURES
Prepare and submit submittals required by individual Specification Sections. Types of
submittals are indicated in individual Specification Sections.
1.
Email: Prepare submittals as PDF package, and transmit to Customer by sending
via email. Include PDF transmittal form. Include information in email subject line
as requested by the Customer.
a.
2.
3.
B.
The Customer will return annotated file. Annotate and retain one copy of
file as a digital Project Record Document file.
Web-Based Project Software: Prepare submittals in PDF form, and upload to
web-based Project software website. Enter required data in web-based software
site to fully identify submittal.
Paper: Prepare submittals in paper form, and deliver to Customer.
Coordination: Coordinate preparation and processing of submittals with performance of
construction activities.
1.
Coordinate each submittal with fabrication, purchasing, testing, delivery, other
submittals, and related activities that require sequential activity.
Submittal Procedures
01330-3
Alaska Railroad
Site Summit and Houston Microwave Sites
2.
3.
4.
Submit all submittal items required for each Specification Section concurrently
unless partial submittals for portions of the Work are indicated on approved
submittal schedule.
Submit action submittals and informational submittals required by the same
Specification Section as separate packages under separate transmittals.
Coordinate transmittal of submittals for related parts of the Work specified in
different Sections so processing will not be delayed because of need to review
submittals concurrently for coordination.
a.
C.
The Customer reserves the right to withhold action on a submittal requiring
coordination with other submittals until related submittals are received.
Processing Time: Allow time for submittal review, including time for resubmittals, as
follows. Time for review shall commence on the Customer’s receipt of submittal. No
extension of the Contract Time will be authorized because of failure to transmit
submittals enough in advance of the Work to permit processing, including resubmittals.
1.
2.
3.
D.
Rev. 2
March 23, 2016
Initial Review: Allow 15 days for initial review of each submittal. Allow
additional time if coordination with subsequent submittals is required. The
Customer will advise Contractor when a submittal being processed must be
delayed for coordination.
Intermediate Review: If intermediate submittal is necessary, process it in same
manner as initial submittal.
Resubmittal Review: Allow 15 days for review of each resubmittal.
Resubmittals: Make resubmittals in same form and number of copies as initial
submittal.
1.
2.
3.
Note date and content of previous submittal.
Note date and content of revision in label or title block and clearly indicate extent
of revision.
Resubmit submittals until they are marked with approval notation from the
Customer’s action stamp.
E.
Distribution: Furnish copies of final submittals to manufacturers, subcontractors,
suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary
for performance of construction activities. Show distribution on transmittal forms.
F.
Use for Construction: Retain complete copies of submittals on Project site. Use only
final action submittals that are marked with approval notation from the Customer’s
action stamp.
1.07
A.
SUBMITTAL REQUIREMENTS
Additional copies may be required for each type of submittal in remaining paragraphs
below for projects with a construction manager or a commissioning authority.
Submittal Procedures
01330-4
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
Rev. 2
March 23, 2016
Product Data: Collect information into a single submittal for each element of
construction and type of product or equipment.
1.
2.
3.
If information must be specially prepared for submittal because standard
published data are unsuitable for use, submit as Shop Drawings, not as Product
Data.
Mark each copy of each submittal to show which products and options are
applicable.
Include the following information, as applicable:
a.
b.
c.
d.
e.
f.
g.
h.
4.
For equipment, include the following in addition to the above, as applicable:
a.
b.
c.
d.
5.
Manufacturer's catalog cuts.
Manufacturer's product specifications.
Standard color charts.
Statement of compliance with specified referenced standards.
Testing by recognized testing agency.
Application of testing agency labels and seals.
Notation of coordination requirements.
Availability and delivery time information.
Wiring diagrams that show factory-installed wiring.
Printed performance curves.
Operational range diagrams.
Clearances required to other construction, if not indicated on accompanying
Shop Drawings.
Submit Product Data before Shop Drawings, and before or concurrent with
Samples.
C.
Qualification Data: Prepare written information that demonstrates capabilities and
experience of firm or person. Include lists of completed projects with project names and
addresses, contact information of key personnel and owners, and other information
specified.
D.
Design Data: Prepare and submit written and graphic information indicating compliance
with indicated performance and design criteria in individual Specification Sections.
Include list of assumptions and summary of loads. Include load diagrams if applicable.
Provide name and version of software, if any, used for calculations. Number each page
of submittal.
E.
Certificates:
1.
Certificates and Certifications Submittals: Submit a statement that includes
signature of entity responsible for preparing certification. Certificates and
certifications shall be signed by an officer or other individual authorized to sign
documents on behalf of that entity. Provide a notarized signature where indicated.
Submittal Procedures
01330-5
Alaska Railroad
Site Summit and Houston Microwave Sites
2.
3.
4.
5.
6.
F.
Rev. 2
March 23, 2016
Installer Certificates: Submit written statements on manufacturer's letterhead
certifying that Installer complies with requirements in the Contract Documents
and, where required, is authorized by manufacturer for this specific Project.
Manufacturer Certificates: Submit written statements on manufacturer's letterhead
certifying that manufacturer complies with requirements in the Contract
Documents. Include evidence of manufacturing experience where required.
Material Certificates: Submit written statements on manufacturer's letterhead
certifying that material complies with requirements in the Contract Documents.
Product Certificates: Submit written statements on manufacturer's letterhead
certifying that product complies with requirements in the Contract Documents.
Welding Certificates: Prepare written certification that welding procedures and
personnel comply with requirements in the Contract Documents. Submit record of
Welding Procedure Specification and Procedure Qualification Record on AWS
forms. Include names of firms and personnel certified.
Test and Research Reports:
1.
2.
3.
4.
5.
6.
Compatibility Test Reports: Submit reports written by a qualified testing agency,
on testing agency's standard form, indicating and interpreting results of
compatibility tests performed before installation of product. Include written
recommendations for primers and substrate preparation needed for adhesion.
Field Test Reports: Submit written reports indicating and interpreting results of
field tests performed either during installation of product or after product is
installed in its final location, for compliance with requirements in the Contract
Documents.
Material Test Reports: Submit reports written by a qualified testing agency, on
testing agency's standard form, indicating and interpreting test results of material
for compliance with requirements in the Contract Documents.
Preconstruction Test Reports: Submit reports written by a qualified testing
agency, on testing agency's standard form, indicating and interpreting results of
tests performed before installation of product, for compliance with performance
requirements in the Contract Documents.
Product Test Reports: Submit written reports indicating that current product
produced by manufacturer complies with requirements in the Contract
Documents. Base reports on evaluation of tests performed by manufacturer and
witnessed by a qualified testing agency, or on comprehensive tests performed by a
qualified testing agency.
Research Reports: Submit written evidence, from a model code organization
acceptable to authorities having jurisdiction, that product complies with building
code in effect for Project. Include the following information:
a.
b.
c.
d.
e.
f.
Submittal Procedures
Name of evaluation organization.
Date of evaluation.
Time period when report is in effect.
Product and manufacturers' names.
Description of product.
Test procedures and results.
01330-6
Alaska Railroad
Site Summit and Houston Microwave Sites
g.
1.08
Rev. 2
March 23, 2016
Limitations of use.
CUSTOMER REVIEW
A.
Most architects (and construction managers) use a stamp to indicate action taken on
submittals. Retain "Action Submittals" Paragraph below if using such a stamp, or
substitute another system to comply with office policy or Owner's requirements.
AIA Document A201 states that "the Architect will review and approve or take other
appropriate action upon the Contractor's submittals." AIA Document A232 states that
Construction Manager will review and approve submittals before transmitting those
recommended for approval to Architect. Retain second option if using PDF or paper
submittals.
B.
Action Submittals: Customer will review each submittal, indicate corrections or
revisions required, and return it.
C.
Informational Submittals: Customer will review each submittal and will not return it, or
will return it if it does not comply with requirements. Customer will forward each
submittal to appropriate party.
D.
Partial submittals prepared for a portion of the Work will be reviewed when use of
partial submittals has received prior approval from the Customer.
E.
Incomplete submittals are unacceptable, will be considered nonresponsive, and will be
returned for resubmittal without review.
F.
Submittals not required by the Contract Documents will be returned by Customer
without action.
PART 2 - PRODUCTS
2.01
SHOP DRAWINGS
A.
Scale and measurements: Shop drawings shall be made accurately to a scale
sufficiently large to show all pertinent aspects of the item and its method of
connection to the Work.
Customer's review of those aspects of submittal that pertain to the construction
process including fabrication, assembly, installation/erection will be
complimentary.
B.
Types of prints required:
1.
Submittal Procedures
Shop drawings shall be submitted in the form of one sepia transparencies
of each sheet plus six blue line or black line prints of each sheet.
01330-7
Alaska Railroad
Site Summit and Houston Microwave Sites
2.02
Rev. 2
March 23, 2016
C.
Review comments will be shown on the sepia transparency and one set will be
returned to the Contractor. The Contractor may make and distribute such copies
as are required for its purposes.
D.
When agreed upon by the Customer or his representative, select submittals may
be made in electronic format in the form of “.pdf” files.
MANUFACTURERS' LITERATURE
A.
The Contractor shall submit only the original printed literature, catalog cuts and
product data sheets available from the manufacturer(s).
B.
Where content of submitted literature from manufacturer includes data not
pertinent to the submittal, the Contractor shall clearly show which portions of the
contents are being submitted for review.
C.
The Contractor shall submit six copies. One will be returned to the contractor.
PART 3 - EXECUTION
3.01
IDENTIFICATION OF SUBMITTALS
A.
Within 21 days of Notice to Proceed Contractor shall submit a complete list of all
submittals for the project. Submittals are required for all items as defined in the
Contract Specifications, and for all Items identified on the Contract Drawings.
B.
The Contractor shall consecutively number all submittals under "Transmittal".
C.
3.02
1.
When re-submittal(s) is made for any reason, the Contractor shall transmit
under a new letter of transmittal with a new transmittal number.
2.
On re-submittals, the Contractor shall cite the prior transmittal number(s)
under "submission number".
The Contractor shall maintain an accurate submittal log for the duration of the
Work, showing current status of all submittals at all times. The Contractor shall
make the submittal log available to the Customer for review upon request.
GROUPING OF SUBMITTALS
A.
Unless otherwise specified, the Contractor shall make submittals in groups
Submittal Procedures
01330-8
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
containing all associated items to assure that information is available for checking
each item when it is received.
B.
3.03
Partial and poorly prepared submittals will be rejected by the Engineer as not
complying with the requirements of the Contract. The Contractor will be liable
for delays so occasioned.
TIMING OF SUBMITTALS
A.
The Contractor shall make submittals consistently with early start dates shown on
the approved baseline schedule, but sufficiently in advance of early scheduled
dates for installation to provide time required for reviews, for securing necessary
approvals, for possible revisions and re-submittals, and for placing orders and
securing delivery.
B.
In scheduling, the Contractor shall allow 21 calendar days for review and
processing by the Engineer following its receipt of the submittal.
This review time will be increased for the submittal(s) that are so extensive that
21 calendar days of turn around period is unreasonable as determined by the
Engineer. This determination shall be binding on the Contractor.
C.
3.04
Continued submission of material and repetitious submittals, which clearly fail to
meet the requirements of the Contract Documents and may cause delays in the
completion of the Contract, or any such delay, shall be the sole responsibility of
the Contractor.
CUSTOMER'S REVIEW
A.
Review and Processing by the Engineer shall not relieve the Contractor from
responsibility for errors that may exist in the submitted data.
B.
Revisions:
1.
The Contractor shall make required revisions as noted on initial submittal.
2.
If the Contractor considers any required revision to be a change, it shall so
notify the Customer as provided for in the "Agreement". Such notification
shall be made no later than 10 calendar days from the date of return of
such submittals, by the Customer or its Engineer, to the Contractor.
3.
The review of the shop drawings waives the original contract requirements
of the Contract Documents only if the Contractor clearly states and
highlights the proposed deviation in a prominent fashion on the shop
drawing itself, and only as specially stated in writing by the Customer, that
the Contract Document requirements are waived.
Submittal Procedures
01330-9
Alaska Railroad
Site Summit and Houston
Microwave Site
Rev. 2
March 23, 2016
END OF SECTION 01300
Submittal Procedures
01330-10
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01400
QUALITY REQUIREMENTS
PART 1 - GENERAL
1.01
A.
1.02
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
SUMMARY
B.
Section includes administrative and procedural requirements for quality assurance and
quality control.
C.
Testing and inspection services are required to verify compliance with requirements
specified or indicated. These services do not relieve Contractor of responsibility for
compliance with the Contract Document requirements.
1.
2.
3.
4.
1.03
Specific quality-assurance and quality-control requirements for individual work
results are specified in their respective Specification Sections. Requirements in
individual Sections may also cover production of standard products.
Specified tests, inspections, and related actions do not limit Contractor's other
quality-assurance and quality-control procedures that facilitate compliance with
the Contract Document requirements.
Requirements for Contractor to provide quality-assurance and quality-control
services required by the Owner or authorities having jurisdiction are not limited
by provisions of this Section.
Specific test and inspection requirements are not specified in this Section.
DEFINITIONS
A.
Experienced: When used with an entity or individual, "experienced" unless otherwise
further described means having successfully completed a minimum of five previous
projects similar in nature, size, and extent to this Project; being familiar with special
requirements indicated; and having complied with requirements of authorities having
jurisdiction.
B.
Field Quality-Control Tests: Tests and inspections that are performed on-site for
installation of the Work and for completed Work.
C.
Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an
employee, Subcontractor, or Sub-subcontractor, to perform a particular construction
operation, including installation, erection, application, assembly, and similar operations.
Quality Requirements
01400-1
Alaska Railroad
Site Summit and Houston Microwave Sites
1.
Rev. 2
March 23, 2016
Use of trade-specific terminology in referring to a trade or entity does not require
that certain construction activities be performed by accredited or unionized
individuals, or that requirements specified apply exclusively to specific trade(s).
D.
Product Tests: Tests and inspections that are performed by a nationally recognized
testing laboratory (NRTL) according to 29 CFR 1910.7, by a testing agency accredited
according to NIST's National Voluntary Laboratory Accreditation Program (NVLAP),
or by a testing agency qualified to conduct product testing and acceptable to authorities
having jurisdiction, to establish product performance and compliance with specified
requirements.
E.
Source Quality-Control Tests: Tests and inspections that are performed at the source;
for example, plant, mill, factory, or shop.
F.
Testing Agency: An entity engaged to perform specific tests, inspections, or both.
Testing laboratory shall mean the same as testing agency.
G.
Quality-Assurance Services: Activities, actions, and procedures performed before and
during execution of the Work to guard against defects and deficiencies and substantiate
that proposed construction will comply with requirements.
H.
Quality-Control Services: Tests, inspections, procedures, and related actions during and
after execution of the Work to evaluate that actual products incorporated into the Work
and completed construction comply with requirements. Contractor's quality-control
services do not include contract administration activities performed by the Customer.
1.04
CONFLICTING REQUIREMENTS
A.
Conflicting Standards and Other Requirements: If compliance with two or more
standards or requirements are specified and the standards or requirements establish
different or conflicting requirements for minimum quantities or quality levels, comply
with the most stringent requirement. Refer conflicting requirements that are different,
but apparently equal, to Customer for direction before proceeding.
B.
Minimum Quantity or Quality Levels: The quantity or quality level shown or specified
shall be the minimum provided or performed. The actual installation may comply
exactly with the minimum quantity or quality specified, or it may exceed the minimum
within reasonable limits. To comply with these requirements, indicated numeric values
are minimum or maximum, as appropriate, for the context of requirements. Refer
uncertainties to Customer for a decision before proceeding. Insert an article on special
compliance with a governing code only if necessary. Such provisions typically belong
in the Supplementary Conditions.
Quality Requirements
01400-2
Alaska Railroad
Site Summit and Houston Microwave Sites
1.05
Rev. 2
March 23, 2016
INFORMATIONAL SUBMITTALS
A.
Contractor's Quality-Control Plan: For quality-assurance and quality-control activities
and responsibilities.
B.
Qualification Data: For Contractor's quality-control personnel.
C.
Testing Agency Qualifications: For testing agencies specified in "Quality Assurance"
Article to demonstrate their capabilities and experience. Include proof of qualifications
in the form of a recent report on the inspection of the testing agency by a recognized
authority.
D.
Schedule of Tests and Inspections: Prepare in tabular form and include the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
Specification Section number and title.
Entity responsible for performing tests and inspections.
Description of test and inspection.
Identification of applicable standards.
Identification of test and inspection methods.
Number of tests and inspections required.
Time schedule or time span for tests and inspections.
Requirements for obtaining samples.
Unique characteristics of each quality-control service.
E.
Reports: Prepare and submit certified written reports and documents as specified.
F.
Permits, Licenses, and Certificates: For Owner's record, submit copies of permits,
licenses, certifications, inspection reports, releases, jurisdictional settlements, notices,
receipts for fee payments, judgments, correspondence, records, and similar documents
established for compliance with standards and regulations bearing on performance of
the Work.
1.06
CONTRACTOR'S QUALITY-CONTROL PLAN
A.
Quality-Control Plan, General: Submit quality-control plan within 21 days of Notice of
Award. Submit in format acceptable to the customer. Identify personnel, procedures,
controls, instructions, tests, records, and forms to be used to carry out Contractor's
quality-assurance and quality-control responsibilities. Coordinate with Contractor's
Construction Schedule.
B.
Quality-Control Personnel Qualifications: Engage qualified personnel trained and
experienced in managing and executing quality-assurance and quality-control
procedures similar in nature and extent to those required for Project.
1.
Project quality-control manager may also serve as Project superintendent.
Quality Requirements
01400-3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
C.
Submittal Procedure: Describe procedures for ensuring compliance with requirements
through review and management of submittal process. Indicate qualifications of
personnel responsible for submittal review.
D.
Testing and Inspection: In quality-control plan, include a comprehensive schedule of
Work requiring testing or inspection, including the following:
1.
2.
3.
Contractor-performed tests and inspections including Subcontractor-performed
tests and inspections. Include required tests and inspections and Contractorelected tests and inspections. Distinguish source quality-control tests and
inspections from field quality-control tests and inspections.
Special inspections required by authorities having jurisdiction and indicated on
the Statement of Special Inspections.
Owner-performed tests and inspections indicated in the Contract Documents.
E.
Continuous Inspection of Workmanship: Describe process for continuous inspection
during construction to identify and correct deficiencies in workmanship in addition to
testing and inspection specified. Indicate types of corrective actions to be required to
bring work into compliance with standards of workmanship established by Contract
requirements.
F.
Monitoring and Documentation: Maintain testing and inspection reports including log
of approved and rejected results. Include work Customer has indicated as
nonconforming or defective. Indicate corrective actions taken to bring nonconforming
work into compliance with requirements. Comply with requirements of authorities
having jurisdiction.
1.09
A.
REPORTS AND DOCUMENTS
Test and Inspection Reports: Prepare and submit certified written reports specified in
other Sections. Include the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Date of issue.
Project title and number.
Name, address, telephone number, and email address of testing agency.
Dates and locations of samples and tests or inspections.
Names of individuals making tests and inspections.
Description of the Work and test and inspection method.
Identification of product and Specification Section.
Complete test or inspection data.
Test and inspection results and an interpretation of test results.
Record of temperature and weather conditions at time of sample taking and
testing and inspection.
Comments or professional opinion on whether tested or inspected Work complies
with the Contract Document requirements.
Name and signature of laboratory inspector.
Quality Requirements
01400-4
Alaska Railroad
Site Summit and Houston Microwave Sites
13.
1.08
Rev. 2
March 23, 2016
Recommendations on retesting and reinspecting.
QUALITY ASSURANCE
A.
General: Qualifications paragraphs in this article establish the minimum qualification
levels required; individual Specification Sections specify additional requirements.
B.
Manufacturer Qualifications: A firm experienced in manufacturing products or systems
similar to those indicated for this Project and with a record of successful in-service
performance, as well as sufficient production capacity to produce required units. As
applicable, procure products from manufacturers able to meet qualification
requirements, warranty requirements, and technical or factory-authorized service
representative requirements.
C.
Fabricator Qualifications: A firm experienced in producing products similar to those
indicated for this Project and with a record of successful in-service performance, as well
as sufficient production capacity to produce required units.
D.
Installer Qualifications: A firm or individual experienced in installing, erecting,
applying, or assembling work similar in material, design, and extent to that indicated for
this Project, whose work has resulted in construction with a record of successful inservice performance.
E.
Professional Engineer Qualifications: A professional engineer who is legally qualified
to practice in the State of Alaska and who is experienced in providing engineering
services of the kind indicated. Engineering services are defined as those performed for
installations of the system, assembly, or product that are similar in material, design, and
extent to those indicated for this Project.
F.
Specialists: Certain Specification Sections require that specific construction activities
shall be performed by entities who are recognized experts in those operations.
Specialists shall satisfy qualification requirements indicated and shall be engaged for
the activities indicated.
1.
Requirements of authorities having jurisdiction shall supersede requirements for
specialists.
G.
Manufacturer's Technical Representative Qualifications: An authorized representative
of manufacturer who is trained and approved by manufacturer to observe and inspect
installation of manufacturer's products that are similar in material, design, and extent to
those indicated for this Project.
H.
Factory-Authorized Service Representative Qualifications: An authorized representative
of manufacturer who is trained and approved by manufacturer to inspect installation of
manufacturer's products that are similar in material, design, and extent to those
indicated for this Project.
Quality Requirements
01400-5
Alaska Railroad
Site Summit and Houston Microwave Sites
1.11
A.
QUALITY CONTROL
Owner Responsibilities: Where quality-control services are indicated as Owner's
responsibility, Owner will engage a qualified testing agency to perform these services.
1.
2.
3.
B.
Rev. 2
March 23, 2016
Owner will furnish Contractor with names, addresses, and telephone numbers of
testing agencies engaged and a description of types of testing and inspection they
are engaged to perform.
Payment for these services will be made from testing and inspection allowances,
as authorized by Change Orders.
Costs for retesting and reinspecting construction that replaces or is necessitated by
work that failed to comply with the Contract Documents will be charged to
Contractor.
Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are
Contractor's responsibility. Perform additional quality-control activities, whether
specified or not, to verify and document that the Work complies with requirements.
1.
2.
Unless otherwise indicated, provide quality-control services specified and those
required by authorities having jurisdiction. Perform quality-control services
required of Contractor by authorities having jurisdiction, whether specified or not.
Engage a qualified testing agency to perform quality-control services.
a.
3.
4.
5.
6.
Contractor shall not employ same entity engaged by Owner, unless agreed
to in writing by Owner.
Notify testing agencies at least 24 hours in advance of time when Work that
requires testing or inspection will be performed.
Where quality-control services are indicated as Contractor's responsibility, submit
a certified written report, in duplicate, of each quality-control service.
Testing and inspection requested by Contractor and not required by the Contract
Documents are Contractor's responsibility.
Submit additional copies of each written report directly to authorities having
jurisdiction, when they so direct.
C.
Retesting/Reinspecting: Regardless of whether original tests or inspections were
Contractor's responsibility, provide quality-control services, including retesting and
reinspecting, for construction that replaced Work that failed to comply with the
Contract Documents.
D.
Testing Agency Responsibilities: Cooperate with the Customer and Contractor in
performance of duties. Provide qualified personnel to perform required tests and
inspections.
1.
Notify Customer and Contractor promptly of irregularities or deficiencies
observed in the Work during performance of its services.
Quality Requirements
01400-6
Alaska Railroad
Site Summit and Houston Microwave Sites
2.
3.
4.
5.
6.
Rev. 2
March 23, 2016
Determine the locations from which test samples will be taken and in which insitu tests are conducted.
Conduct and interpret tests and inspections and state in each report whether tested
and inspected work complies with or deviates from requirements.
Submit a certified written report, in duplicate, of each test, inspection, and similar
quality-control service through Contractor.
Do not release, revoke, alter, or increase the Contract Document requirements or
approve or accept any portion of the Work.
Do not perform duties of Contractor.
E.
Manufacturer's Field Services: Where indicated, engage a factory-authorized service
representative to inspect field-assembled components and equipment installation,
including service connections. Report results in writing as specified in Section 013300
"Submittal Procedures."
F.
Manufacturer's Technical Services: Where indicated, engage a manufacturer's technical
representative to observe and inspect the Work. Manufacturer's technical
representative's services include participation in preinstallation conferences,
examination of substrates and conditions, verification of materials, observation of
Installer activities, inspection of completed portions of the Work, and submittal of
written reports.
G.
Associated Contractor Services: Cooperate with agencies and representatives
performing required tests, inspections, and similar quality-control services, and provide
reasonable auxiliary services as requested. Notify agency sufficiently in advance of
operations to permit assignment of personnel. Provide the following:
1.
2.
3.
4.
5.
6.
7.
H.
Coordination: Coordinate sequence of activities to accommodate required qualityassurance and quality-control services with a minimum of delay and to avoid necessity
of removing and replacing construction to accommodate testing and inspection.
1.
I.
Access to the Work.
Incidental labor and facilities necessary to facilitate tests and inspections.
Adequate quantities of representative samples of materials that require testing and
inspection. Assist agency in obtaining samples.
Facilities for storage and field curing of test samples.
Delivery of samples to testing agencies.
Preliminary design mix proposed for use for material mixes that require control
by testing agency.
Security and protection for samples and for testing and inspection equipment at
Project site.
Schedule times for tests, inspections, obtaining samples, and similar activities.
Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar
quality-control services required by the Contract Documents. Coordinate and submit
concurrently with Contractor's Construction Schedule. Update as the Work progresses.
Quality Requirements
01400-7
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.01
A.
TEST AND INSPECTION LOG
Test and Inspection Log: Prepare a record of tests and inspections. Include the
following:
1.
2.
3.
4.
B.
Maintain log at Project site. Post changes and revisions as they occur. Provide access to
test and inspection log for Customer’s reference during normal working hours.
1.
3.02
A.
Date test or inspection was conducted.
Description of the Work tested or inspected.
Date test or inspection results were transmitted to Customer.
Identification of testing agency or special inspector conducting test or inspection.
Submit log at Project closeout as part of Project Record Documents.
REPAIR AND PROTECTION
General: On completion of testing, inspection, sample taking, and similar services,
repair damaged construction and restore substrates and finishes.
1.
Provide materials and comply with installation requirements specified in other
Specification Sections or matching existing substrates and finishes. Restore
patched areas and extend restoration into adjoining areas with durable seams that
are as invisible as possible.
B.
Protect construction exposed by or for quality-control service activities.
C.
Repair and protection are Contractor's responsibility, regardless of the assignment of
responsibility for quality-control services.
END OF SECTION 01400
Quality Requirements
01400-8
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Quality Requirements
01400-9
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01410
TESTING SERVICES
PART 1 - GENERAL
1.01
DESCRIPTION
A.
Work Included:
The Contractor shall employ a testing and inspection agency fully licensed and
competent in the field of testing specific elements of the project. The
Contractor shall submit such testing agencies and their qualifications for
Owner’s prior written approval.
B.
C.
Related Work:
1.
Section 01600, Materials and Equipment.
2.
Divisions 2 through 16 Specification Sections as relevant.
Payment for Testing and Inspection:
1.
1.02
1.03
The Contractor shall pay for all necessary testing and inspection
services.
QUALITY ASSURANCE
A.
The testing laboratory shall be approved by Owner.
B.
Testing, when required, shall be the strictest of all pertinent codes and
regulations, including selected standards of the American Society for Testing
and Materials.
C.
All site testing and taking of the specimens and samples shall be performed in
the presence of the Construction Manager.
PRODUCT HANDLING
A.
The Contractor shall comply with pertinent provisions of Section 01600.
B.
The Contractor shall promptly process and submit required copies of test
reports and related instructions to assure necessary retesting and replacement
of materials without any possible delay in the progress of the Work.
Testing Services
01410-1
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
PART 2 - PRODUCTS
2.01
RETESTING
A.
2.02
When initial tests indicate non-compliance with the Contract Documents,
subsequent retesting occasioned by the non-compliance shall be performed by
the same testing agency, at no additional cost to Owner.
CONTRACTOR'S CONVENIENCE TESTING
A.
Inspecting and testing performed exclusively for the Contractor's convenience
shall be the sole responsibility of the Contractor.
PART 3 - EXECUTION
3.01
COOPERATION WITH TESTING LABORATORY
A.
3.02
Representatives of the testing laboratory shall have access to the Work at all
times and at all locations where the Work is in progress. The Contractor shall
provide facilities for such access to enable the laboratory to perform its
functions properly.
SCHEDULES FOR TESTING
A.
Establishing Schedule:
1.
By advance discussion with the Testing Laboratory, the Contractor shall
determine the time required for the laboratory to perform its tests and to
issue each of its findings.
2.
The Contractor shall provide all required time within the approved
construction schedule.
END OF SECTION 01410
Testing Services
01410-2
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Testing Services
01410-3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01500
CONSTRUCTION FACILITIES AND TEMPORARY SERVICES
PART 1 - GENERAL
1.01
DESCRIPTION
A.
Work Included:
The Contractor shall provide temporary facilities and controls needed for the
performance of its Work including, but not necessarily limited to:
1.02
1.03
1.04
1.
Temporary utilities such as heat, water, electricity, and telephone;
2.
Sanitary facilities
3.
Enclosures such as tarpaulins, barricades, and canopies
4.
First-aid facilities
5.
Temporary fencing and other safety devices for pedestrian and vehicular
traffic as well as isolating the construction area.
RELATED SECTIONS
A.
Contract Agreement.
B.
Section 01010, Summary of Work.
C.
Section 01300, Submittals.
SUBMITTALS
A.
The Contractor shall comply with pertinent provisions of Section 01300,
Submittals and this Section.
B.
The Contractor shall provide shop drawings including means, methods and
procedures related to all temporary facilities.
PRODUCT HANDLING
The Contractor shall maintain and protect all temporary facilities and controls in proper
and safe condition throughout progress of the Work.
1.05
TEMPORARY UTILITIES AND SERVICES
Construction Facilities and Temporary Services
01500-1
Alaska Railroad
Site Summit and Houston Microwave Sites
A.
B.
Water
1.
The Contractor shall provide drinking water from an approved source, so
piped or transported as to keep it safe and fresh and served from single
service containers or satisfactory types of drinking stands or fountains.
All such facilities and services shall be furnished in strict accordance with
existing governing health regulations.
2.
The Contractor shall protect pipes and water servicing equipment from
freezing during inclement weather.
Sanitary facilities:
2.
C.
Rev. 2
March 23, 2016
The Contractor shall furnish for the work force on this project, the
necessary toilet conveniences, secluded from public observation. The
conveniences shall be kept in a clean, sanitary condition and shall comply
with the requirements and regulations of the agencies having jurisdiction.
Power and Lighting:
1.
The Contractor shall provide, maintain and pay for all costs of temporary
electrical and lighting services required at the site for the proper
performance and inspection of work. The level of lighting shall not be
less than the existing. Remove services and lighting after completion of
work and repair of all damages.
2.
The Contractor shall provide area distribution boxes so located that the
individual trades may furnish and use 100 ft. maximum length extension
cords to obtain power and lighting at points where needed for work,
inspection, and safety.
3.
The Contractor shall provide all necessary items such as breakers,
transformers, panel boards, and cable required for the service. The
Contractor shall provide a complete distribution system expanded as
required during the construction including wiring devices, outlets,
distribution panels, transformers, cable and other related work necessary
to provide a temporary power system for use during construction.
4.
The Contractor shall pay all costs associated with the utility tie-ins,
physical plant, maintenance of system throughout construction, removal of
same at project completion and any other items necessary in providing
temporary power and light.
5.
The temporary power and lighting system shall at all times conform with
the applicable codes and regulations of OSHA, NEMA, UL, and the local
Construction Facilities and Temporary Services
01500-2
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
municipality.
D.
Telephones:
1.
E.
The Contractor shall make necessary arrangements and pay costs for
installation, maintenance and operation of direct line (non pay type)
telephone services in Owner’s field office at the site.
Heating:
The Contractor shall provide and maintain heat necessary for proper conduct of
operations.
1.06
1.09
ACCESS, STORAGE AND PARKING AREAS
A.
The Contractor shall establish a construction Compound in which the Contractor
provided Owner’s office trailers will be located adjacent to the Contractor's office
trailers. The physical location of the compound will require written approval of
the Owner’s designated representative.
B.
The Contractor shall provide a minimum of 3 parking spaces adjacent to the
Owner’s trailer within the compound for Owner’s personnel vehicles.
C.
The Contractor shall provide all necessary security for this compound area. The
Contractor shall provide all necessary keys to the Owner's designated
representative so as to provide access to the compound at any time.
D.
The Contractor shall submit to the Owner’s designated representative a plan
layout of the Compound within 14 days after Notice to Proceed (NTP).
E.
The Contractor shall coordinate the provision of utility services for all trailers and
be responsible for all installation charges, removal costs at Project completion,
and any periodic or other charges incidental to the provision of those utility
services.
F.
Upon final acceptance of the Work, the Contractor shall clean up the work areas
and leave them in a neat and orderly condition. The Contractor shall dismantle
and remove all temporary fencing and barricades and other temporary items
installed, unless otherwise directed by the Owner’s designated representative.
Repair damaged areas to their original condition.
ENCLOSURES AND TEMPORARY FENCING
A.
Furnish, erect and maintain any necessary temporary barricades, warning, danger
and detour signs, suitable and adequate lights and take all other precautions to
protect the work, employees and the public.
Construction Facilities and Temporary Services
01500-3
Alaska Railroad
Site Summit and Houston Microwave Sites
1.10
Rev. 2
March 23, 2016
DUST CONTROL
A.
The Contractor shall control the generation of dust on the project. Accomplish
dust control by water sprinkling or by other methods approved by the Owner’s
designated representative to keep all parts of the disturbed areas free from dust
causing a nuisance to others. Failure to properly control dust will result in the
Owner’s designated representative ordering Contractor to stop work activity until
such time as the Contractor demonstrates, to the satisfaction of the Owner’s
designated representative, that he has the necessary facilities to control dust. No
time extensions will be allowed for this delay and the facilities shall be
established at no additional cost to Owner.
END OF SECTION 01500
Construction Facilities and Temporary Services
01500-4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Construction Facilities and Temporary Services
01500-5
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01600
MATERIALS AND EQUIPMENT
PART 1 - GENERAL
1.01
DESCRIPTION
Work of this section includes:
1.02
1.03
A.
Products
B.
Transportation and handling
C.
Storage and protection
D.
Product options
E.
Substitutions
RELATED WORK
A.
Contract.
B.
Section 01010, Summary of Work.
C.
Section 01300, Submittals.
QUALITY ASSURANCE:
The Contractor shall include in its Quality Assurance Program, such procedures as are
required to assure full protection of work and materials.
1.04
MANUFACTURER’S RECOMMENDATIONS:
The Contractor shall comply with manufacturer’s recommendations on product handling,
storage, and protection except as noted in the Contract Documents or otherwise approved
by Owner.
1.05
PRODUCTS
A.
The Contractor shall not reuse materials and equipment removed from existing
premises, except as specifically permitted by the Contract Documents.
Materials and Equipment
01600-1
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
1.06
The Contractor shall provide interchangeable components of the same
manufacture, for components being replaced.
TRANSPORTATION AND HANDLING
A.
The Contractor shall transport and handle products in accordance with
manufacturer's instructions.
B.
The Contractor shall promptly inspect shipments to ensure that products comply
with requirements, quantities are correct, and products are undamaged.
C.
The Contractor shall provide equipment and personnel to handle products by
methods to prevent soiling, disfigurement, or damage.
D.
The Contractor shall deliver products to the job site in their manufacturer's
original container, with labels intact and legible.
E.
1.07
Rev. 2
March 23, 2016
1.
The Contractor shall maintain packaged materials with seals unbroken and
labels intact until time of installation.
2.
The Contractor shall promptly remove damaged material and unsuitable
Items from the job site, and promptly replace with material meeting the
specified requirements, at no additional cost to Owner.
Owner may reject, as non-complying, such material and products, that do not bear
satisfactory identification as to manufacturer, grade, quality, and other pertinent
information.
STORAGE AND PROTECTION
A.
The Contractor shall store and protect products in accordance with manufacturers'
instructions, with seals and labels intact and legible.
B.
The Contractor shall store sensitive products in weather tight, climate controlled
enclosures.
C.
For exterior storage of fabricated products, the contractor shall place on sloped
supports, above ground.
D.
The Contractor may make off-site arrangements for storage and staging, and
deliver material to the site as required so as not to affect work progress of other
contractors and create unsafe conditions.
E.
The Contractor shall protect all finished surfaces and equipment.
F.
The Contractor shall provide protection for finished floor surfaces prior to
Materials and Equipment
01600-2
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
allowing equipment or materials to be moved over such surfaces.
G.
1.08
1.09
The Contractor shall maintain finished surfaces and equipment clean, unmarred,
and suitable protected until final acceptance by Owner.
REPAIRS AND REPLACEMENTS:
A.
In event of damage, the Contractor shall promptly make replacements and repairs
at no additional cost to Owner.
B.
Additional time required to secure replacements and to make repairs will not be
considered by Owner as justification for extension to contract time.
PRODUCT OPTIONS
A.
Products Specified by reference standards or by description only: Any Product
meeting those standards or description.
B.
Products Specified by naming one or more manufacturers: Products of
manufacturers named and meeting specifications, no options or substitutions
allowed, except as otherwise provided in the Contract Documents.
PART 2 - PRODUCTS
Not used.
PART 3 - EXECUTION
Not used.
END OF SECTION 01600
Materials and Equipment
01600-3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Materials and Equipment
01600-4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01700
CONTRACT CLOSEOUT
PART 1 - GENERAL
1.01
1.02
1.03
DESCRIPTION
A.
This Section specifies the requirements for closing out the project in addition to
those requirements specified in the Contract Agreement.
B.
Definitions: Project closeout is the term used to describe collective project
requirements that are to be fulfilled near the end of the Contract Time in
preparation for final acceptance and occupancy of the Work by the Owner, as well
as final payment to the Contractor and the normal termination of the Contract.
1.
Specific requirements for individual units of work are included in the
appropriate sections in Divisions 2 through 16.
2.
Time of closeout is directly related to “Substantial Completion;” therefore,
the time of closeout may be either a single time period for the entire Work
or a series of time periods for individual elements of the Work that have
been certified as substantially complete at different dates. This time
variation, if any, shall be applicable to the other provisions of this section.
RELATED DOCUMENTS
A.
Contract.
B.
Section 01710 - Final Cleaning.
C.
Section 01720 - Project Record Documents.
PREREQUISITES TO SUBSTANTIAL COMPLETION
A.
General: Complete the following before requesting the Owner’s inspection for
certification of substantial completion, either for the entire Work or for portions
of the Work. List known exceptions in the request:
1.
In the progress payment request that coincides with, or is the first request
following, the date substantial completion is claimed, show either 100%
completion for the portion of the Work claimed as "substantially
complete", or list incomplete items, the value of incomplete work, and
Contract Closeout
01700-1
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
reasons for the Work being incomplete. Include supporting documentation
for completion as indicated in the Contract Documents.
B.
2.
Submit written certification to the Owner that the Project, or designated
portion thereof, is substantially complete.
3.
Submit list of items to be completed or corrected, and material delivery
dates of major items as applicable.
4.
Submit a statement showing an accounting of changes to the Contract
Sum.
5.
Advise Owner of pending insurance change-over requirements.
6.
Submit three copies of all specific warranties for materials and equipment,
workmanship/maintenance bonds, maintenance agreements, final
certifications and similar documents. The effective time limits of all
guarantees and warranties shall commence on the date of Final
Acceptance.
7.
Obtain and submit releases enabling Owner’s full, unrestricted use of the
Work and access to services and utilities. Where required, include
occupancy permits, operating certificates and similar releases.
8.
Deliver tools, spare parts, extra stock of material and similar physical
items to the Authority.
9.
Make the final change-over of locks and transmit the keys to Owner.
Advise Owner’s personnel of the change-over in security provisions.
10.
Complete start-up testing of systems, and instruction of the Owner's
operating and maintenance personnel. Discontinue or change over and
remove temporary facilities and services from the project site, along with
construction tools and facilities, mock-ups, and similar elements.
11.
Complete final cleaning up requirements, including touch-up painting of
marred surfaces.
12.
Touch-up and otherwise repair and restore marred exposed finishes.
Inspection Procedures: Upon receipt of the Contractor’s requests for inspection,
the Owner will either proceed with inspection or advise the Contractor of
unfulfilled prerequisites.
Contract Closeout
01700-2
Alaska Railroad
Site Summit and Houston Microwave Sites
1.04
Rev. 2
March 23, 2016
1.
Following the initial inspection, the Owner will either prepare the
certificate of substantial completion, or will advise the Contractor of work
which must be performed before the certificate will be issued. The Owner
will repeat the inspection when requested and when assured that the Work
has been substantially completed.
2.
Results of the completed inspection will form the initial "punch-list" for
final acceptance.
3.
The punch-list shall include a reasonable time period to effectuate the
work which is mutually agreed upon by all parties.
PREREQUISITES TO FINAL ACCEPTANCE
A.
General: Complete the following before requesting the Owner's final inspection
for certification of final acceptance, and final payment as required by the
Agreement. List known exceptions, if any, in the request.
1.
Submit the final payment request with final releases and supporting
documentation not previously submitted and accepted. Include certificates
of insurance for products and completed operations where required.
2.
Submit an updated final statement, accounting for final additional changes
to the Contract Sum.
3.
Submit a certified copy of the Owner's final punch-list of itemized work to
be completed or otherwise resolved for acceptance and has been endorsed
and dated by the Owner.
4.
Submit final meter readings for utilities, a measured record of stored fuel,
and similar data either of the date of substantial completion, or else when
the Authority took possession of and responsibility for corresponding
elements of the Work.
5.
Submit consent of surety.
6.
Submit evidence of final, continuing insurance coverage complying with
insurance requirements.
7.
Submit record drawings, maintenance manuals if not submitted previously
as specified in Section 01300, final project photographs, damage or
settlement- survey, property survey, and similar final record information.
8.
Submit written certification that:
a.
Contract Closeout
Contract Documents have been reviewed.
01700-3
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
Rev. 2
March 23, 2016
b.
Work has been completed in accordance with Contract Documents.
c.
Equipment and systems have been tested in the presence of
Authority representatives and are operational.
Re-inspection Procedure: The Owner will re-inspect the Work upon receipt of the
Contractor's notice that the work, including punch-list items resulting from earlier
inspections, has been completed, except for those times whose completion has
been delayed because of circumstances that are acceptable to the Owner.
1.
Upon completion of re-inspection, the Owner will either prepare a
certificate of final acceptance, or will advise the Contractor of work that is
incomplete or of obligations that have not been fulfilled, but are required
for final acceptance.
2.
If necessary, the re-inspection procedure will be repeated.
PART 2 - PRODUCTS
Not used.
PART 3 - EXECUTION
Not used.
END OF SECTION 01700
Contract Closeout
01700-4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Contract Closeout
01700-5
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01710
FINAL CLEANING
PART 1 - GENERAL
1.01
DESCRIPTION
A.
1.02
RELATED WORK
A.
1.03
This section details work for preparing the site and/or facility for substantial
completion.
Section 01500, Construction Facilities and Temporary Controls.
QUALITY ASSURANCE:
A.
In addition to the standards described in this Section the Contractor shall comply
with pertinent requirements of governmental agencies having jurisdiction.
B.
"Clean," for the purpose of the Article, and except as may be specifically provided
otherwise, shall be interpreted as meaning the level of cleanliness generally
provided by skilled cleaners using commercial quality building and site
maintenance equipment and materials.
PART 2 - PRODUCTS
2.01
CLEANING MATERIAL AND EQUIPMENT
A.
2.02
The Contractor shall provide required personnel, equipment, and materials needed
to achieve the specified standard of cleanliness.
COMPATIBILITY
A.
The Contractor shall use only the cleaning materials and equipment which are
compatible with the surface being cleaned, as recommended by the manufacturer
of the material and acceptable to Owner.
B.
The Contractor shall replace surfaces damaged from improper use of material
and/or cleaning methods.
PART 3 - EXECUTION
Final Cleaning
01710-1
Alaska Railroad
Site Summit and Houston Microwave Sites
3.01
Rev. 2
March 23, 2016
FINAL CLEANING
A.
The Contractor shall, prior to turning over the substantially completed area to
Owner’s Maintenance and Operation Section, remove from the area all tools,
surplus materials, equipment, scrap, debris, and waste. If any of the contractor's
work continues in the substantially completed area, the Contractor shall continue
the cleaning until completion. Schedule final cleaning on dates approved by
Owner.
B.
Site:
C.
D.
1.
Unless otherwise specifically directed by Owner, the Contractor shall
sweep grade areas within the contract limit and paved areas adjacent to the
site.
2.
The Contractor shall completely remove resultant debris.
3.
The Contractor shall remove graffiti, if any, from all surfaces and restore
surface to original condition.
Structures
1.
The Contractor shall visually inspect all existing and finished surfaces and
remove all traces of soil, waste materials, smudges, graffiti and other
foreign matter.
2.
The Contractor shall remove all traces of splashed materials from structure
within contract limit and from adjacent surfaces.
3.
If necessary to achieve a uniform degree of cleanliness, the Contractor
shall wash the exterior of the structure with high pressure water and
detergent.
4.
In the event of stubborn stains not removable with detergent, the
Contractor shall utilize light sandblasting or other cleaning methods at no
additional cost to Owner.
5.
The Contractor shall remove paint droppings, spots, stains and dirt from
existing and finished surfaces.
Finished Surface:
1.
Final Cleaning
The Contractor shall remove all labels and tags which are strictly used for
the convenience of manufacturing, assembly, installation and
identifications.
01710-2
Alaska Railroad
Site Summit and Houston Microwave Sites
2.
E.
Rev. 2
March 23, 2016
The Contractor shall clean stained steel surfaces of all foreign material.
Finish surfaces with application of buffed polish material as recommended
by the manufacturer.
Equipment:
1.
The Contractor shall wipe surfaces of all mechanical and electrical
equipment including system components to a dirt free condition. Touch
up the surfaces to match with the overall finish of the equipment/system
component.
2.
Insure that the equipment and system components are properly identified
as required by the Contract Documents.
END OF SECTION 01710
Final Cleaning
01710-3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Final Cleaning
01710-4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 01720
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.01
DESCRIPTION
A.
1.02
1.03
Work Included:
1.
Throughout progress of the Work, the Contractor shall maintain an
accurate record of changes to the Contract Drawings and Specifications.
2.
The Contractor shall, at the time of substantial completion, but prior to
requesting for reduction in retainage, transfer the changes to a set of Final
Record Documents.
RELATED WORK
A.
Documents affecting work of this Section include, but are not necessarily limited
to the Contract Agreement and Division 1 of these Specifications.
B.
Other requirements affecting Project Record Documents may appear in pertinent
other Sections of these Specifications.
QUALITY ASSURANCE
A.
Accuracy of Records:
1.
The Contractor shall thoroughly coordinate changes within the Record
Documents, making adequate and proper entries on each page of
Specifications and each sheet of Drawings and other documents where
such entry is required to show the change properly.
2.
Accuracy of records shall be such that future search for items as installed
may rely reasonably on information obtained from the approved Final
Record Documents.
B.
The Contractor shall make entries on the Record Documents on a weekly basis to
include all work performed during the last week.
C.
The Contractor shall use professional draftsperson to prepare job set as well as to
transfer "job set" information to Final Record Documents.
Project Record Documents
01720-1
Alaska Railroad
Site Summit and Houston Microwave Sites
1.04
SUBMITTALS
A.
1.05
Rev. 2
March 23, 2016
The Contractor shall comply with pertinent provisions of Section 01300,
Submittals.
PRODUCT HANDLING
A.
The Contractor shall maintain the job set of Record Documents completely
protected from deterioration and from loss and damage until completion of the
Work and transfer of all recorded data to the Final Record Documents.
PART 2 - PRODUCTS
2.01
RECORD DOCUMENTS
A.
Job set:
Following receipt of Owner's Notice to Proceed, the Contractor, shall secure from
Engineer one complete set of all documents comprising the Contract Documents.
B.
Final Record Documents:
The Final Record Documents are to include:
1.
Updated mylars of original Contract Drawings.
2.
Additional as-built mylars to include all changes during the Contract
period, that could not be included on the original contract drawings.
3.
Updated Specifications to include Contract Specifications with all changes
made during the Contract period.
4.
“As installed” versions of same size mylars of all fabrication, detail and
installation drawings.
5.
Electronic drawings and specifications- Drawings in AutoCAD formatted
with approved version, layering and pen tables; Specifications in
Microsoft Word, Version 2003 or newer.
PART 3 - EXECUTION
3.01
MAINTENANCE OF JOB SET
A.
The Contractor shall, immediately upon receipt of the job set described in
Paragraph 2.1 A. above, identify each of the Documents with the title "RECORD
Project Record Documents
01720-2
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
DOCUMENTS - JOB SET."
B.
C.
D.
E.
Preservation:
1.
The Contractor shall, devise a suitable method for protecting the job set in
consideration of the Contract duration, the probable number of occasions
upon which the job set must be taken out for new entries; the transfer of
information on Final Record Documents and for examination, and the
conditions under which these activities will be performed.
2.
The Contractor shall not use the job set for any purpose except entry of
new data, for review by Engineer and transfer of data to Final Record
Documents.
3.
Maintain the job set at the site of Work.
Making entries on Drawings:
1.
The Contractor shall utilize an erasable colored pencil (not ink or indelible
pencil) to clearly describe the change by graphic line and note as required.
2.
The Contractor shall date all entries.
3.
The Contractor shall call attention to the entry by a "cloud" drawn around
the area or areas affected.
4.
The Contractor shall in the event of overlapping changes, use different
colors for the overlapping changes.
Specifications:
1.
The Contractor shall transfer all Contract changes to respective
Specifications and/or drawings set immediately, as the change is
incorporated in the field.
2.
The Contractor shall make appropriate entries in the Specifications and
drawings as soon as the change is incorporated in the field.
Conversion of schematic layouts:
1.
The Contract drawings may indicate arrangements of conduits, circuits,
piping, ducts, and similar items shown schematically, and is not intended
to portray precise physical layout.
Final physical arrangement is determined by the Contractor, subject to
Owner's written approval. However, design of future modifications of the
facility requires accurate information as to the final physical layout of
Project Record Documents
01720-3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
items which must be schematically shown on the Record Drawings.
2.
3.2
Show on the job set of Record Drawings, by dimension accurate to within
(English Dimensioning Standards), the centerline of each run of items
such as are described in subparagraph 3.1E.1 above.
a.
The Contractor shall clearly identify the item by accurate note such
as "cast iron drain", "galvanized conduit," and the like.
b.
The Contractor shall show, by symbol or note, the vertical location
of the item ("under slab," "in ceiling plenum," "exposed," and the
like).
c.
The Contractor shall make all identification sufficiently descriptive
that it may be related reliably to the Specifications.
FINAL PROJECT RECORD INFORMATION
A.
The purpose of the Final Project Record Documents is to provide factual
information regarding all aspects of the Work, both concealed and visible, to
enable future modifications of the Work to proceed without lengthy and
expensive site measurement, investigation, and examination.
B.
Accuracy of Record Data Prior to Transfer:
1.
C.
The Contractor is solely responsible for accurate transfer of all field
changes and preparing additional mylars and specification pages.
Transfer of Data to Drawings:
1.
The Contractor shall carefully transfer change data shown on the job set to
the Final Record Documents coordinating the changes as required.
2.
The Contractor shall clearly indicate at each affected detail and master
drawing a full description of changes made during construction, and the
actual location of items.
3.
The Contractor shall call attention to each entry by drawing a "cloud"
around the areas affected.
4.
The Contractor shall make changes neatly, consistently, and with the
proper media to assure longevity and clear reproduction.
5.
The Contractor shall prepare additional mylars in the same size as the
original contract drawings for changes to details (including installation
and fabrication drawings) incorporated in the construction that could not
be corrected on the record drawings. These mylars shall be adequately
Project Record Documents
01720-4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
identified and cross referenced with pertinent Record Drawing(s) to make
it part of the Final Record Documents.
D.
Transfer of Data to Specifications:
1.
E.
3.3
The Contractor shall accurately and legibly transfer all information from
job set to Final Project Record Specifications sets.
Review and Submittal:
1.
The Contractor shall submit the completed set of Final Record Documents
to Owner.
2.
The Contractor shall participate in review meetings as required.
3.
The Contractor shall make required changes and promptly deliver the
Final Project Record Documents to Owner.
4.
The Contractor shall sign each sheet of the record drawings including
contractor stamp.
CHANGES SUBSEQUENT TO ACCEPTANCE
A.
The Contractor has no responsibility for recording changes in the Work
subsequent to Final Completion, except for changes resulting from work
performed under Warranty.
END OF SECTION 01720
Project Record Documents
01720-5
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Project Record Documents
01720-6
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 03300
CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this
Section.
SUMMARY
A.
This Section specifies cast-in place concrete, including formwork, reinforcement,
concrete materials, mixture design, placement procedures, and finishes, for the
following:
1.
1.3
DEFINITIONS
A.
1.4
Pole Foundations
Cementitious Materials: Portland cement alone or in combination with one or
more of the following: blended hydraulic cement, fly ash and other pozzolans,
ground granulated blast-furnace slag, and silica fume; subject to compliance with
requirements.
SUBMITTALS
A.
Product Data: For each type of product indicated.
B.
Design Mixtures: For each concrete mixture. Submit alternate design mixtures
when characteristics of materials, Project conditions, weather, test results, or other
circumstances warrant adjustments.
1.
C.
Indicate amounts of mixing water to be withheld for later addition at
Project site.
Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication,
bending, and placement. Include bar sizes, lengths, material, grade, bar
schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps,
mechanical connections, tie spacing, hoop spacing, and supports for concrete
reinforcement.
Cast-in-Place Concrete
03300 - 1
Alaska Railroad
Site Summit and Houston Microwave Sites
D.
Qualification Data: For manufacturer and testing agency.
E.
Material Certificates: For each of the following, signed by manufacturers:
1.
2.
3.
F.
1.5
Cementitious materials.
Admixtures.
Steel reinforcement and accessories.
Field quality-control test reports.
QUALITY ASSURANCE
A.
Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed
concrete products and that complies with ASTM C 94/C 94M requirements for
production facilities and equipment.
B.
Testing Agency Qualifications: An independent agency, acceptable to the owner,
qualified according to ASTM C 1077 and ASTM E 329 for testing indicated, as
documented according to ASTM E 548.
C.
ACI Publications: Comply with the following unless modified by requirements in
the Contract Documents:
1.
2.
D.
1.6
Rev. 2
March 23, 2016
ACI 301, "Specification for Structural Concrete," Sections 1 through 5.
ACI 117, "Specifications for Tolerances for Concrete Construction and
Materials."
Concrete Testing Service: Engage a qualified independent testing agency to
perform material evaluation tests and to design concrete mixtures.
DELIVERY, STORAGE, AND HANDLING
A.
Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent
bending and damage.
PART 2 - PRODUCTS
2.1
FORM-FACING MATERIALS
A.
Round Concrete Column Forms
1.
Multi-layer recycled paperboard, spirally wound and laminated with
adhesive of diameter as indicated on the drawings. Interior surface shall
be smooth, with plastic coating.
a.
Manufacturer: Sonotube
Cast-in-Place Concrete
03300 - 2
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
2.2
Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiberreinforced plastic form ties designed to resist lateral pressure of fresh concrete on
forms and to prevent spalling of concrete on removal.
STEEL REINFORCEMENT
A.
2.3
Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed.
REINFORCEMENT ACCESSORIES
A.
Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting,
and fastening reinforcing bars and welded wire reinforcement in place.
Manufacture bar supports from steel wire, plastic, or precast concrete according to
CRSI's "Manual of Standard Practice," of greater compressive strength than
concrete and as follows:
1.
2.4
For concrete surfaces exposed to view where legs of wire bar supports
contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI
Class 2 stainless-steel bar supports.
CONCRETE MATERIALS
A.
Cementitious Material: Use the following cementitious materials, of the same
type, brand, and source, throughout Project:
1.
B.
C.
Portland Cement: ASTM C 150, Type II, gray
Normal-Weight Aggregates: ASTM C 33, Class 3S coarse aggregate or better,
graded. Provide aggregates from a single source.
1.
2.
2.5
Rev. 2
March 23, 2016
Maximum Coarse-Aggregate Size: ¾ inch nominal.
Fine Aggregate: Free of materials with deleterious reactivity to alkali in
cement.
Water: ASTM C 94/C 94M and potable.
ADMIXTURES
A.
Air-Entraining Admixture: ASTM C 260.
B.
Chemical Admixtures: Provide admixtures certified by manufacturer to be
compatible with other admixtures and that will not contribute water-soluble
chloride ions exceeding those permitted in hardened concrete. Do not use
calcium chloride or admixtures containing calcium chloride.
Cast-in-Place Concrete
03300 - 3
Rev. 2
March 23, 2016
Alaska Railroad
Site Summit and Houston Microwave Sites
1.
2.
3.
4.
5.
6.
2.6
2.7
CURING MATERIALS
A.
Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or
kenaf, weighing approximately 9 oz./sq. yd. when dry.
B.
Moisture-Retaining Cover:
polyethylene sheet.
C.
Water: Potable.
ASTM C 171, polyethylene film or white burlap-
RELATED MATERIALS
A.
2.8
Water-Reducing Admixture: ASTM C 494/C 494M, Type A.
Retarding Admixture: ASTM C 494/C 494M, Type B.
Water-Reducing and Retarding Admixture:
ASTM C 494/C 494M,
Type D.
High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F.
High-Range,
Water-Reducing
and
Retarding
Admixture:
ASTM C 494/C 494M, Type G.
Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II.
Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated
cellulosic fiber or ASTM D 1752, cork or self-expanding cork.
CONCRETE MIXTURES, GENERAL
A.
Prepare design mixtures for each type and strength of concrete, proportioned on
the basis of laboratory trial mixture or field test data, or both, according to
ACI 301.
1.
Use a qualified independent testing agency for preparing and reporting
proposed mixture designs based on laboratory trial mixtures.
B.
Limit water-soluble, chloride-ion content in hardened concrete to 0.30 percent by
weight of cement.
C.
Admixtures: Use admixtures according to manufacturer's written instructions.
1.
2.
3.
Cast-in-Place Concrete
Use water-reducing or plasticizing admixture in concrete, as required, for
placement and workability.
Use water-reducing and retarding admixture when required by high
temperatures, low humidity, or other adverse placement conditions.
Use water-reducing admixture in pumped concrete, concrete for heavy-use
industrial slabs and parking structure slabs, concrete required to be
03300 - 4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
watertight, and concrete with a water-cementitious materials ratio below
0.50.
2.9
CONCRETE MIXTURES FOR BUILDING ELEMENTS
A.
Equipment Pads: Proportion normal-weight concrete mixture as follows:
1.
2.
3.
4.
2.10
FABRICATING REINFORCEMENT
A.
2.11
Minimum Compressive Strength: 4000 psi at 28 days.
Maximum Water-Cementitious Materials Ratio: 0.50.
Slump Limit: 8 inches for concrete with verified slump of 2 to 4 inches
before adding water-reducing admixture or plasticizing admixture, plus or
minus 1 inch.
Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for
¾ inch nominal maximum aggregate size.
Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."
CONCRETE MIXING
A.
Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to
ASTM C 94/C 94M, and furnish batch ticket information.
1.
When air temperature is between 85 and 90 deg F, reduce mixing and
delivery time from 1-1/2 hours to 75 minutes; when air temperature is
above 90 deg F, reduce mixing and delivery time to 60 minutes.
PART 3 - EXECUTION
3.1
FORMWORK
A.
Design, erect, shore, brace, and maintain formwork, according to ACI 301, to
support vertical, lateral, static, and dynamic loads, and construction loads that
might be applied, until structure can support such loads.
B.
Construct formwork so concrete members and structures are of size, shape,
alignment, elevation, and position indicated, within tolerance limits of ACI 117.
C.
Limit concrete surface irregularities, designated by ACI 347R as abrupt or
gradual, as follows:
1.
Cast-in-Place Concrete
Class A, 1/8 inch for smooth-formed finished surfaces.
03300 - 5
Alaska Railroad
Site Summit and Houston Microwave Sites
D.
Construct forms tight enough to prevent loss of concrete mortar.
E.
Fabricate forms for easy removal without hammering or prying against concrete
surfaces. Provide crush or wrecking plates where stripping may damage cast
concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5
horizontal to 1 vertical.
1.
2.
3.2
Install keyways, reglets, recesses, and the like, for easy removal.
Do not use rust-stained steel form-facing material.
F.
Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve
required elevations and slopes in finished concrete surfaces. Provide and secure
units to support screed strips; use strike-off templates or compacting-type screeds.
G.
Provide temporary openings for cleanouts and inspection ports where interior area
of formwork is inaccessible. Close openings with panels tightly fitted to forms
and securely braced to prevent loss of concrete mortar. Locate temporary
openings in forms at inconspicuous locations.
H.
Chamfer exterior corners and edges of permanently exposed concrete.
I.
Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and
bulkheads required in the Work. Determine sizes and locations from trades
providing such items.
J.
Clean forms and adjacent surfaces to receive concrete. Remove chips, wood,
sawdust, dirt, and other debris just before placing concrete.
K.
Retighten forms and bracing before placing concrete, as required, to prevent
mortar leaks and maintain proper alignment.
L.
Coat contact surfaces of forms with form-release agent, according to
manufacturer's written instructions, before placing reinforcement.
EMBEDDED ITEMS
A.
3.3
Rev. 2
March 23, 2016
Place and secure anchorage devices and other embedded items required for
adjoining work that is attached to or supported by cast-in-place concrete. Use
setting drawings, templates, diagrams, instructions, and directions furnished with
items to be embedded.
STEEL REINFORCEMENT
A.
General: Comply with CRSI's "Manual of Standard Practice" for placing
reinforcement.
Cast-in-Place Concrete
03300 - 6
Alaska Railroad
Site Summit and Houston Microwave Sites
3.4
Rev. 2
March 23, 2016
B.
Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign
materials that would reduce bond to concrete.
C.
Accurately position, support, and secure reinforcement against displacement.
Locate and support reinforcement with bar supports to maintain minimum
concrete cover. Do not tack weld crossing reinforcing bars.
D.
Set wire ties with ends directed into concrete, not toward exposed concrete
surfaces.
CONCRETE PLACEMENT
A.
Before placing concrete, verify that installation of formwork, reinforcement, and
embedded items is complete and that required inspections have been performed.
B.
Do not add water to concrete during delivery, at Project site, or during placement
unless approved by Engineer.
C.
Deposit concrete continuously in one layer or in horizontal layers of such
thickness that no new concrete will be placed on concrete that has hardened
enough to cause seams or planes of weakness. If a section cannot be placed
continuously, provide construction joints as indicated. Deposit concrete to avoid
segregation.
1.
2.
3.
D.
Deposit concrete in horizontal layers of depth to not exceed formwork
design pressures and in a manner to avoid inclined construction joints.
Consolidate placed concrete with mechanical vibrating equipment
according to ACI 301.
Do not use vibrators to transport concrete inside forms. Insert and
withdraw vibrators vertically at uniformly spaced locations to rapidly
penetrate placed layer and at least 6 inches into preceding layer. Do not
insert vibrators into lower layers of concrete that have begun to lose
plasticity. At each insertion, limit duration of vibration to time necessary
to consolidate concrete and complete embedment of reinforcement and
other embedded items without causing mixture constituents to segregate.
Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect
concrete work from physical damage or reduced strength that could be caused by
frost, freezing actions, or low temperatures.
1.
2.
Cast-in-Place Concrete
When average high and low temperature is expected to fall below 40
deg F for three successive days, maintain delivered concrete mixture
temperature within the temperature range required by ACI 301.
Do not use frozen materials or materials containing ice or snow. Do not
place concrete on frozen subgrade or on subgrade containing frozen
materials.
03300 - 7
Alaska Railroad
Site Summit and Houston Microwave Sites
3.
3.5
Do not use calcium chloride, salt, or other materials containing antifreeze
agents or chemical accelerators unless otherwise specified and approved in
mixture designs.
FINISHING FORMED SURFACES
A.
3.6
Rev. 2
March 23, 2016
Smooth-Formed Finish: As-cast concrete texture imparted by form-facing
material, arranged in an orderly and symmetrical manner with a minimum of
seams. Repair and patch tie holes and defects. Remove fins and other projections
that exceed specified limits on formed-surface irregularities.
CONCRETE PROTECTING AND CURING
A.
General: Protect freshly placed concrete from premature drying and excessive
cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection
and ACI 301 for hot-weather protection during curing.
B.
Formed Surfaces: Cure formed concrete surfaces, including underside of beams,
supported slabs, and other similar surfaces. If forms remain during curing period,
moist cure after loosening forms. If removing forms before end of curing period,
continue curing for the remainder of the curing period.
C.
Unformed Surfaces: Begin curing immediately after finishing concrete. Cure
unformed surfaces, including floors and slabs, concrete floor toppings, and other
surfaces.
D.
Cure concrete according to ACI 308.1, by one or a combination of the following
methods:
1.
Moisture Curing: Keep surfaces continuously moist for not less than
seven days with the following materials:
a.
b.
c.
2.
Cast-in-Place Concrete
Water.
Continuous water-fog spray.
Absorptive cover, water saturated, and kept continuously wet.
Cover concrete surfaces and edges with 12-inch lap over adjacent
absorptive covers.
Moisture-Retaining-Cover Curing:
Cover concrete surfaces with
moisture-retaining cover for curing concrete, placed in widest practicable
width, with sides and ends lapped at least 12 inches, and sealed by
waterproof tape or adhesive. Cure for not less than seven days.
Immediately repair any holes or tears during curing period using cover
material and waterproof tape.
03300 - 8
Alaska Railroad
Site Summit and Houston Microwave Sites
3.7
Rev. 2
March 23, 2016
FIELD QUALITY CONTROL
A.
Testing and Inspecting: Engage a qualified testing and inspecting agency to
perform tests and inspections and to submit reports.
B.
Inspections:
C.
Concrete Tests: Testing of composite samples of fresh concrete obtained
according to ASTM C 172 shall be performed according to the following
requirements:
1.
Testing Frequency: Obtain one composite sample for each day's pour of
each concrete mixture exceeding 5 cu. yd., but less than 25 cu. yd., plus
one set for each additional 50 cu. yd. or fraction thereof.
a.
2.
3.
4.
5.
Slump: ASTM C 143/C 143M; one test at point of placement for each
composite sample, but not less than one test for each day's pour of each
concrete mixture. Perform additional tests when concrete consistency
appears to change.
Air Content: ASTM C 231, pressure method, for normal-weight concrete;
one test for each composite sample, but not less than one test for each
day's pour of each concrete mixture.
Concrete Temperature: ASTM C 1064/C 1064M; one test hourly when air
temperature is 40 deg F and below and when 80 deg F and above, and one
test for each composite sample.
Compression Test Specimens: ASTM C 31/C 31M.
a.
6.
8.
Cast-in-Place Concrete
Cast and field cure two sets of two standard cylinder specimens for
each composite sample.
Compressive-Strength Tests: ASTM C 39/C 39M; test one set of two
field-cured specimens at 7 days and one set of two specimens at 28 days.
a.
7.
When frequency of testing will provide fewer than five
compressive-strength tests for each concrete mixture, testing shall
be conducted from at least five randomly selected batches or from
each batch if fewer than five are used.
A compressive-strength test shall be the average compressive
strength from a set of two specimens obtained from same
composite sample and tested at age indicated.
Strength of each concrete mixture will be satisfactory if every average of
any three consecutive compressive-strength tests equals or exceeds
specified compressive strength and no compressive-strength test value
falls below specified compressive strength by more than 500 psi.
Test results shall be reported in writing to Engineer, concrete
manufacturer, and Contractor within 48 hours of testing. Reports of
03300 - 9
Alaska Railroad
Site Summit and Houston Microwave Sites
9.
10.
11.
12.
Rev. 2
March 23, 2016
compressive-strength tests shall contain Project identification name and
number, date of concrete placement, name of concrete testing and
inspecting agency, location of concrete batch in Work, design compressive
strength at 28 days, concrete mixture proportions and materials,
compressive breaking strength, and type of break for both 7- and 28-day
tests.
Nondestructive Testing:
Impact hammer, sonoscope, or other
nondestructive device may be permitted by Engineer but will not be used
as sole basis for approval or rejection of concrete.
Additional Tests: Testing and inspecting agency shall make additional
tests of concrete when test results indicate that slump, air entrainment,
compressive strengths, or other requirements have not been met, as
directed by Engineer. Testing and inspecting agency may conduct tests to
determine adequacy of concrete by cored cylinders complying with
ASTM C 42/C 42M or by other methods as directed by Engineer.
Additional testing and inspecting, at Contractor's expense, will be
performed to determine compliance of replaced or additional work with
specified requirements.
Correct deficiencies in the Work that test reports and inspections indicate
dos not comply with the Contract Documents.
END OF SECTION 03300
Cast-in-Place Concrete
03300 - 10
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Cast-in-Place Concrete
03300 - 11
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 16060
GROUNDING AND BONDING
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
SUMMARY OF THE WORK
A.
1.3
1.4
Contract drawings and other specifications.
This Section includes grounding of electrical systems and equipment. Grounding
requirements specified in this Section may be supplemented by special
requirements of systems described in other Sections and as shown on the
drawings.
SUBMITTALS
A.
Product Data: For each type of product indicated.
B.
Product Data: For the following:
1.
Grounding Electrodes.
2.
Grounding Conductors
3.
Bonding Conductors
4.
Connectors
5.
Test Wells
QUALITY ASSURANCE
A.
Electrical Components, Devices, and Accessories: Listed and labeled as defined
in NFPA 70, Article 100, by a testing agency acceptable to authorities having
jurisdiction, and marked for intended use.
1.
Grounding and Bonding
Comply with UL 467.
16060 - 1
Alaska Railroad
Site Summit and Houston Microwave Sites
B.
Rev. 2
March 23, 2016
Comply with NFPA 780 and UL 96 when interconnecting with lightning
protection system.
PART 2 - PRODUCTS
2.1
MANUFACTURERS
A.
Manufacturers: Subject to compliance with requirements, provide products by
one of the following:
1.
Grounding Conductors, Cables, Connectors, and Rods:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
2.
Test Wells:
a.
b.
2.2
Hager, Model: GAW910.
Or Approved Equal
GROUNDING CONDUCTORS
A.
Underground Conductors: Bare, tinned, stranded, unless otherwise indicated.
B.
Bare Copper Conductors: Comply with the following:
1.
C.
Assembly of Stranded Conductors: ASTM B 8.
Copper Bonding Conductors: As follows:
1.
2.3
Chance/Hubbell.
Copperweld Corp.
Erico Inc.; Electrical Products Group.
ILSCO.
Kearney/Cooper Power Systems.
Korns: C. C. Korns Co.; Division of Robroy Industries.
O-Z/Gedney Co.; a business of the EGS Electrical Group.
Raco, Inc.; Division of Hubbell.
Thomas & Betts, Electrical.
Or Approved Equal
Grounding Cable: No. 2 AWG stranded copper conductor.
CONNECTOR PRODUCTS
Grounding and Bonding
16060 - 2
Alaska Railroad
Site Summit and Houston Microwave Sites
2.4
A.
Comply with IEEE 837 and UL 467; listed for use for specific types, sizes, and
combinations of conductors and connected items.
B.
Bolted Connectors: Bolted-pressure-type connectors, or compression type.
C.
Welded Connectors: Exothermic-welded type, in kit form, and selected per
manufacturer's written instructions.
GROUNDING ELECTRODES
A.
Ground Rods: Copper-clad steel.
1.
2.5
Rev. 2
March 23, 2016
Size: ¾” diameter by 96 inches in length.
Test Wells
A.
Size: 9” diameter.
B.
Material: HDPE
C.
Cover: Twist-Lock HDPE, labeled accordingly.
D.
Connections within test wells shall be mechanical type.
PART 3 - EXECUTION
3.1
APPLICATION
A.
Use only copper conductors for both insulated and bare grounding conductors in
direct contact with earth, concrete, masonry, crushed stone, and similar materials.
B.
In raceways, use insulated equipment grounding conductors, unless otherwise
specified.
C.
Exothermic-Welded Connections: Use for connections to structural steel and for
underground connections.
D.
Equipment Grounding Conductor Terminations: Use bolted pressure clamps.
E.
Grounding Bus:
indicated.
1.
Grounding and Bonding
Install beneath cable wall entry ports, and elsewhere as
Use insulated spacer; space 1 inch from wall and support from wall a
minimum of 6 inches above finished floor, unless otherwise indicated.
16060 - 3
Alaska Railroad
Site Summit and Houston Microwave Sites
2.
3.2
3.3
Rev. 2
March 23, 2016
At doors, route the bus up to the top of the door frame, across the top of
the doorway, and down to the specified height above the floor.
F.
Underground Grounding Conductors: Use tinned copper conductor, No. 2 AWG
minimum. Bury at least 30 inches below grade for perimeter ground loop unless
specified otherwise in the drawing.
G.
Install test wells flush with finished grade.
EQUIPMENT GROUNDING CONDUCTORS
A.
Comply with NFPA 70, Article 250, for types, sizes, and quantities of equipment
grounding conductors, unless specific types, larger sizes, or more conductors than
required by NFPA 70 are indicated.
B.
Install equipment-grounding conductors in all feeders and circuits.
CONNECTIONS
A.
General: Make connections so galvanic action or electrolysis possibility is
minimized. Select connectors, connection hardware, conductors, and connection
methods so metals in direct contact will be galvanically compatible.
1.
Use electroplated or hot-tin-coated materials to ensure high conductivity
and to make contact points closer to order of galvanic series.
B.
Exothermic-Welded Connections:
Comply with manufacturer's written
instructions. Welds that are puffed up or that show convex surfaces indicating
improper cleaning are not acceptable.
C.
Equipment Grounding Conductor Terminations: For No. 8 AWG and larger, use
pressure-type grounding lugs. No. 10 AWG and smaller grounding conductors
may be terminated with winged pressure-type connectors.
D.
Noncontact Metal Raceway Terminations: If metallic raceways terminate at
metal housings without mechanical and electrical connection to housing,
terminate each conduit with a grounding bushing. Connect grounding bushings
with a bare grounding conductor to grounding bus or terminal in housing. Bond
electrically noncontinuous conduits at entrances and exits with grounding
bushings and bare grounding conductors, unless otherwise indicated.
E.
Tighten screws and bolts for grounding and bonding connectors and terminals
according to manufacturer's published torque-tightening values. If manufacturer's
torque values are not indicated, use those specified in UL 486A.
Grounding and Bonding
16060 - 4
Alaska Railroad
Site Summit and Houston Microwave Sites
3.4
Rev. 2
March 23, 2016
F.
Compression-Type Connections: Use hydraulic compression tools to provide
correct circumferential pressure for compression connectors. Use tools and dies
recommended by connector manufacturer. Provide embossing die code or other
standard method to make a visible indication that a connector has been adequately
compressed on grounding conductor.
G.
Moisture Protection: If insulated grounding conductors are connected to ground
rods or grounding buses, insulate entire area of connection and seal against
moisture penetration of insulation and cable.
FIELD QUALITY CONTROL TESTING
A.
Testing: Contractor will perform the following field quality-control testing:
B.
Testing: Perform the following field quality-control testing:
1.
2.
3.
After installing grounding system but before permanent electrical circuitry
has been energized, test for compliance with requirements.
Test completed grounding system at each location where a maximum
ground-resistance level is specified. Measure ground resistance at the
single point ground ensuring that resistance to ground does not exceed 10
ohms. Where the resistance to ground exceeds 10 ohms install an
additional 8 or 10 Ft. ground rod and retest. Repeat this process until the
10-ohm objective is met. If resistance to ground exceeds these values
notify Engineer promptly and include recommendations to reduce ground
resistance.
Provide drawings locating each ground rod and ground rod assembly and
other grounding electrodes, identify each by letter in alphabetical order,
and key to the record of tests and observations. Include the number of
rods driven and their approximate depth at each location. Describe
measures taken to improve test results.
END OF SECTION 16060
Grounding and Bonding
16060 - 5
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Grounding and Bonding
16060 - 6
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 16075
ELECTRICAL IDENTIFICATION
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
1.3
1.4
All Contract drawings.
SUMMARY
A.
This Section includes electrical identification materials and devices required to
comply with ANSI C2, NFPA 70, OSHA standards, and authorities having
jurisdiction.
B.
In the event DTE requirements are different, comply with DTE standards.
SUBMITTALS
A.
Product Data: For each electrical identification product indicated.
B.
Schedule of Nomenclature: An index of electrical equipment and system
components used in identification signs and labels.
C.
Samples: For each type of label and sign to illustrate color, lettering style, and
graphic features of identification products.
QUALITY ASSURANCE
A.
Comply with ANSI C2.
B.
Comply with NFPA 70.
C.
Comply with ANSI A13.1 and NFPA 70 for color-coding.
PART 2 - PRODUCTS
2.1
RACEWAY AND CABLE LABELS
A.
Comply with ANSI A13.1, Table 3, for minimum size of letters for legend and for
minimum length of color field for each raceway and cable size.
Electrical Identification
16075 - 1
Alaska Railroad
Site Summit and Houston Microwave Sites
1.
2.
2.2
Rev. 2
March 23, 2016
Color: Black letters on orange field.
Legend: Indicates voltage.
B.
Adhesive Labels: Preprinted, flexible, self-adhesive vinyl with legend overlaminated with a clear, weather- and chemical-resistant coating.
C.
Pre-tensioned, Wraparound Plastic Sleeves: Flexible, preprinted, color-coded,
acrylic band sized to suit the diameter of the line it identifies and arranged to stay
in place by pre-tensioned gripping action when placed in position.
D.
Colored Adhesive Tape: Self-adhesive vinyl tape not less than 3 mils thick by 1
to 2 inches wide.
E.
Tape Markers: Vinyl or vinyl-cloth, self-adhesive, wraparound type with
preprinted numbers and letters.
F.
Aluminum, Wraparound Marker Bands: Bands cut from 0.014-inch- thick
aluminum sheet, with stamped or embossed legend, and fitted with slots or ears
for permanently securing around wire or cable jacket or around groups of
conductors.
G.
Plasticized Card-Stock Tags: Vinyl cloth with preprinted and field-printed
legends. Orange background, unless otherwise indicated, with eyelet for fastener.
H.
Aluminum-Faced, Card-Stock Tags: Weather-resistant, 18-point minimum card
stock faced on both sides with embossible aluminum sheet, 0.002 inch thick,
laminated with moisture-resistant acrylic adhesive, punched for fasteners, and
preprinted with legends to suit each application.
I.
Brass or Aluminum Tags: 2 by 2 by 0.05-inch metal tags with stamped legend,
punched for fastener.
NAMEPLATES AND SIGNS
A.
Safety Signs: Comply with 29 CFR, Chapter XVII, Part 1910.145.
B.
Engraved Plastic Nameplates and Signs: Engraving stock, melamine plastic
laminate, minimum 1/16 inch thick for signs up to 20 sq. in. and 1/8 inch thick for
larger sizes.
1.
2.
C.
Engraved legend with black letters on white face.
Punched or drilled for mechanical fasteners.
Baked-Enamel Signs for Interior Use: Preprinted aluminum signs, punched or
drilled for fasteners, with colors, legend, and size required for the application.
1/4-inch grommets in corners for mounting.
Electrical Identification
16075 - 2
Alaska Railroad
Site Summit and Houston Microwave Sites
2.3
Rev. 2
March 23, 2016
D.
Exterior, Metal-Backed, Butyrate Signs:
Weather-resistant, nonfading,
preprinted, cellulose-acetate butyrate signs with 0.0396-inch galvanized-steel
backing; and with colors, legend, and size required for the application. 1/4-inch
grommets in corners for mounting.
E.
Fasteners for Nameplates and Signs: Self-tapping, stainless-steel screws or
No. 10/32, stainless-steel machine screws with nuts and flat and lock washers.
MISCELLANEOUS IDENTIFICATION PRODUCTS
A.
Cable Ties: Fungus-inert, self-extinguishing, one-piece, self-locking, Type 6/6
nylon cable ties.
1.
2.
3.
4.
B.
Minimum Width: 3/16 inch.
Tensile Strength: 50 lb minimum.
Temperature Range: Minus 40 to plus 185 deg F.
Color: According to color-coding.
Paint: Formulated for the type of surface and intended use.
1.
2.
3.
4.
Primer for Galvanized Metal:
Single-component acrylic vehicle
formulated for galvanized surfaces.
Primer for Concrete Masonry Units: Heavy-duty-resin block filler.
Primer for Concrete: Clear, alkali-resistant, binder-type sealer.
Enamel: Silicone-alkyd or alkyd urethane as recommended by
manufacturer.
PART 3 - EXECUTION
3.1
INSTALLATION
A.
Identification Materials and Devices: Install at locations for most convenient
viewing without interference with operation and maintenance of equipment.
B.
Lettering, Colors, and Graphics: Coordinate names, abbreviations, colors, and
other designations with corresponding designations in the Contract Documents or
with those required by codes and standards. Use consistent designations
throughout Project.
C.
Sequence of Work: If identification is applied to surfaces that require finish,
install identification after completing finish work.
D.
Self-Adhesive Identification Products: Clean surfaces before applying.
E.
Install painted identification according to manufacturer's written instructions and
as follows:
Electrical Identification
16075 - 3
Alaska Railroad
Site Summit and Houston Microwave Sites
1.
2.
3.
F.
Rev. 2
March 23, 2016
Clean surfaces of dust, loose material, and oily films before painting.
Prime surfaces using type of primer specified for surface.
Apply one intermediate and one finish coat of enamel.
Color Banding Raceways and Exposed Cables: Band exposed and accessible
raceways of the systems listed below:
1.
2.
3.
Bands: Pretensioned, wraparound plastic sleeves; colored adhesive tape;
or a combination of both. Make each color band 2 inches wide,
completely encircling conduit, and place adjacent bands of two-color
markings in contact, side by side.
Band Locations: At changes in direction, at penetrations of walls and
floors, at 50-foot maximum intervals in straight runs, and at 25-foot
maximum intervals in congested areas.
Apply the following colors to the systems listed below:
a.
Fire Alarm System: Red.
G.
Caution Labels for Indoor Boxes and Enclosures for Power and Lighting: Install
pressure-sensitive, self-adhesive labels identifying system voltage with black
letters on orange background. Install on exterior of door or cover.
H.
Circuit Identification Labels on Boxes: Install labels externally.
1.
2.
3.
I.
Exposed Boxes: Pressure-sensitive, self-adhesive plastic label on cover.
Concealed Boxes: Plasticized card-stock tags.
Labeling Legend: Permanent, waterproof listing of panel and circuit
number or equivalent.
Color-Coding of Secondary Phase Conductors: Use the following colors for
service, feeder and branch-circuit phase conductors:
1.
480/277/208/120-V Conductors:
a.
b.
c.
2.
Factory apply color the entire length of conductors, except the following
field-applied, color-coding methods may be used instead of factory-coded
wire for sizes larger than No. 10 AWG:
a.
Electrical Identification
Phase A: Black.
Phase B: Red.
Phase C: Blue.
Colored, pressure-sensitive plastic tape in half-lapped turns for a
distance of 6 inches from terminal points and in boxes where
splices or taps are made. Apply last two turns of tape with no
tension to prevent possible unwinding. Use 1-inch- wide tape in
colors specified. Adjust tape bands to avoid obscuring cable
identification markings.
16075 - 4
Alaska Railroad
Site Summit and Houston Microwave Sites
b.
J.
2.
3.
2.
3.
Conductors to Be Extended in the Future: Indicate source and circuit
numbers.
Multiple Power or Lighting Circuits in the Same Enclosure: Identify each
conductor with source, voltage, circuit number, and phase. Use colorcoding to identify circuits' voltage and phase.
Multiple Control and Communication Circuits in the Same Enclosure:
Identify each conductor by its system and circuit designation. Use a
consistent system of tags, color-coding, or cable marking tape.
Apply warning, caution, and instruction signs as follows:
1.
M.
Legend: 1/4-inch- steel letter and number stamping or embossing with
legend corresponding to indicated circuit designations.
Tag Fasteners: Nylon cable ties.
Band Fasteners: Integral ears.
Apply identification to conductors as follows:
1.
L.
Colored cable ties applied in groups of three ties of specified color
to each wire at each terminal or splice point starting 3 inches from
the terminal and spaced 3 inches apart. Apply with a special tool
or pliers, tighten to a snug fit, and cut off excess length.
Power-Circuit Identification: Metal tags or aluminum, wraparound marker bands
for cables, feeders, and power circuits in vaults, pull and junction boxes,
manholes, and switchboard rooms.
1.
K.
Rev. 2
March 23, 2016
Warnings, Cautions, and Instructions: Install to ensure safe operation and
maintenance of electrical systems and of items to which they connect.
Install engraved plastic-laminated instruction signs with approved legend
where instructions are needed for system or equipment operation. Install
metal-backed butyrate signs for outdoor items.
Equipment Identification Labels: Engraved plastic laminate. Install on each unit
of equipment, including central or master unit of each system. This includes
power, lighting, communication, signal, and alarm systems, unless units are
specified with their own self-explanatory identification. Unless otherwise
indicated, provide a single line of text with 1/2-inch- high lettering on 1-1/2-inchhigh label; where two lines of text are required, use labels 2 inches high. Use
white lettering on black field. Apply labels for each unit of the following
categories of equipment using mechanical fasteners:
1.
2.
3.
4.
5.
Electrical Identification
Panelboards, electrical cabinets, and enclosures.
Access doors and panels for concealed electrical items.
Disconnect switches.
Enclosed circuit breakers.
Control devices.
16075 - 5
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
END OF SECTION 16075
Electrical Identification
16075 - 6
Rev. 2
March 23, 2016
Alaska Railroad
Site Summit and Houston Microwave Sites
SECTION 16120
CONDUCTORS AND CABLES
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
SUMMARY
A.
1.3
1.4
All Contract drawings and specifications.
This Section includes wires and cables and associated connectors, splices, and
terminations for wiring systems rated 600 V and less.
SUBMITTALS
A.
Product Data: For each type of product indicated.
B.
Qualification Data: For testing agency.
C.
Field Quality-Control Test Reports:
agency engaged by Contractor.
From a qualified testing and inspecting
QUALITY ASSURANCE
A.
Electrical Components, Devices, and Accessories: Listed and labeled as defined
in NFPA 70, Article 100, by a testing agency acceptable to authorities having
jurisdiction, and marked for intended use.
B.
Comply with NFPA 70.
PART 2 - PRODUCTS
2.1
CONDUCTORS AND CABLES
A.
Available Manufacturers:
1.
2.
3.
4.
Conductors and Cables
American Insulated Wire Corp.; a Leviton Company.
General Cable Corporation.
Senator Wire & Cable Company.
Southwire Company.
16120 - 1
Alaska Railroad
Site Summit and Houston Microwave Sites
5.
2.2
Rev. 2
March 23, 2016
Okonite
B.
Refer to Part 3 "Conductor and Insulation Applications" Article for insulation
type, cable construction, and ratings.
C.
Conductor Material: Copper solid conductor for No. 10 AWG and smaller,
stranded for No. 8 AWG and larger.
D.
Conductor Insulation Types: Type THHN-THWN, XHHW.
E.
Single and Multiconductor Cable as noted on the drawings.
CONNECTORS AND SPLICES
A. Available Manufacturers:
1.
2.
3.
4.
5.
6.
B.
AFC Cable Systems, Inc.
AMP Incorporated/Tyco International.
Hubbell/Anderson.
O-Z/Gedney; EGS Electrical Group LLC.
3M Company; Electrical Products Division.
Approved Equal
Description: Factory-fabricated connectors and splices of size, ampacity rating,
material, type, and class for application and service indicated.
PART 3 - EXECUTION
3.1
3.2
CONDUCTOR AND INSULATION APPLICATIONS
A.
Feeders in above ground conduit: Type THHN-THWN, single conductor.
B.
Feeders in underground conduits and ducts: Type THHN-THWN, three
conductors.
INSTALLATION
A.
Use manufacturer-approved pulling compound or lubricant where necessary;
compound used must not deteriorate conductor or insulation. Do not exceed
manufacturer's recommended maximum pulling tensions and sidewall pressure
values.
B.
Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable
grips, that will not damage cables or raceway.
Conductors and Cables
16120 - 2
Alaska Railroad
Site Summit and Houston Microwave Sites
3.3
3.4
Rev. 2
March 23, 2016
C.
Support conduits and cables according to National Electrical Code.
D.
Seal around cables penetrating fire-rated elements.
E.
Identify and color-code conductors and cables according to Section 16075
"Electrical Identification."
CONNECTIONS
A.
Tighten electrical connectors and terminals according to manufacturer's published
torque-tightening values. If manufacturer's torque values are not indicated, use
those specified in UL 486A and UL 486B.
B.
Make splices and taps that are compatible with conductor material and that
possess equivalent or better mechanical strength and insulation ratings than
unspliced conductors.
C.
Wiring at Outlets: Install conductor at each outlet, with at least 12 inches of
slack.
FIELD QUALITY CONTROL
A.
Testing: Perform the following field quality-control testing:
1.
2.
B.
After installing conductors and cables and before electrical circuitry has
been energized, test for compliance with requirements.
Perform each electrical test and visual and mechanical inspection stated in
NETA ATS, Section 7.3.1. Certify compliance with test parameters.
Test Reports: Prepare a written report to record the following:
1.
2.
3.
Test procedures used.
Test results that comply with requirements.
Test results that do not comply with requirements and corrective action
taken to achieve compliance with requirements.
END OF SECTION 16120
Conductors and Cables
16120 - 3
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
NO TEXT THIS PAGE
Conductors and Cables
16120 - 4
Alaska Railroad
Site Summit and Houston Microwave Sites
Rev. 2
March 23, 2016
SECTION 16700
COMMUNICATIONS
PART I – GENERAL
1.1
RELATED DOCUMENTS
A. Contract drawing package
B. Division 3 specification sections
1.2
SUMMARY
A. This section includes all communications devices and associated connectors,
splices, and termination.
1.3
SUBMITTALS
A. Product Data and Factory Acceptance Test Results: For communications devices,
antennas, cabling, and related mounting equipment.
B. Drawings: Show final installation details for devices, cabling, and racks.
C. Test Procedure: Provide test procedure that demonstrates proper installation of
transmission line and antenna alignment such that adequate signal strength is applied and received from radio at opposing end of the link.
D. RF signal strength test results: Document installed radios provide adequate signal
strength for 6.425 – 7.125 GHz frequency range.
1. Receive signal strength at all Aviat Radios (6.425-7.125 GHz) should be at
least -80 dBm at opposite end of the link at the radio interface.
PART II – PRODUCTS
A. The contract drawing packages contain a Bill of Materials reference lists. The
Contractor is responsible for procuring all parts not listed as “Provided by
ARRC.”
B. All products listed as “Provided by ARRC” will be procured by ARRC and are to
be installed by the contractor unless noted otherwise.
PART III – EXECUTION
Communications
16700 - 1
Alaska Railroad
Site Summit and Houston Microwave Sites
3.1
3.2
Rev. 2
March 23, 2016
FACTORY ACCEPTANCE TEST
A.
All RF communications equipment (including by not limited to: radios, waveguide, antennas, etc.) shall complete factory acceptance testing by the manufacturer or an approved test agency to demonstrate equipment meets specifications.
B.
All factory acceptance test results shall be submitted to the owner.
INSTALLATION
A. All communications equipment will be installed and wired as described in the
contract drawing packages and the project Summary of Work (Section 01010).
B. Once installation is complete all wiring must be verified by the Contractor.
C. The Contractor must test all radio links to verify receive signal strength meets the
minimum requirement as detailed in this section. Additionally the Contractor
must verify EIRP levels generated by each antenna do not exceed the limits defined by the frequency license.
D. The Contractor is responsible for configuring all communications equipment with
network settings to be defined by ARRC.
END OF SECTION 16700
Communications
16700 - 2
Alaska Railroad
Site Summit and Houston Microwave Sites
Attachment A
AVIAT Equipment List
(Contractor to Procure)
Rev. 2
March 23, 2016
Proposal Number
Proposal Date
Issue No
Territory Manager
System Engineer
Sales Engineer
Terms
Delivery
Expiration
Currency
Freight
AVIAT U.S., INC.
5200 Great America Parkway
Santa Clara, CA 95054
Company Alaska Railroad Corp
Attn
Address
:
:
:
:
:
:
:
:
:
:
:
NA140715-20857
3/14/2016
D
L. Brigdan
C. Menor
A. Kretzschmer
North End Project Phase 2
EQUIPMENT LIST
DESCRIPTION
ITEM
1.000
1.100
1.101
1.102
1.103
1.104
1.105
1.106
1.107
Eclipse Microwave Radio
Indoor RFU
IRU600 V3 RFSEC ASSY 2+0 1 ANT MAIN, 2RU, U5/U5 GHZ
IRU600 V3 RFSEC ASSY 1+0 REPEATER, 2RU, U5/U5 GHZ
WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 1+0/MHSB 1ANT, RPTR(MAIN)
WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 2+0/FD, RPTR (RPTR)
WG EXT KIT IRU600 V3 6GHZ SH2-PO2, 1+0/MHSB 1ANT, RPTR(MAIN)
WG EXT KIT IRU600 V3 6GHZ SH2-PO2, 2+0/FD, RPTR (RPTR)
EXT BRKT KIT IRU600 2 SHELF
- As requested by customer on 03/07, flex waveguide is provided for the Houston and Summit sites as it is not known at
this time the exact placement of the radios into the existing racks. The flex waveguide is part of the Bill of Material of
Item 3.202.
1.200
1.201
1.202
1.203
1.204
1.205
1.206
1.207
1.208
1.209
1.210
1.211
1.212
1.213
Packet Node - INUe
ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT
KIT BRACKET 2RU (179-530064-001_R001)
NODE PROTECTION CARD, HIGH OUTPUT
AUX, ALARM I/O CARD
RAC 60E, QPSK-256 QAM, High Gain, No XPIC, ACM and SYNC-E
DAC GE3 GIGABIT ETHERNET SWITCH CARD
NODE SW LICENSE, 400 Mbps TOTAL RADIO PAYLOAD CAPACITY
NODE SW LICENSE, 800 Mbps TOTAL RADIO PAYLOAD CAPACITY
LICENCE UPGRADE EZA-08006 TO EZA-08007 400 Mbps TO 800 Mbps
IRU600 600 Nodal High power option 2 x RFU
IRU600 600 Nodal High power option 4 x RFU
UPGRADE IRU 600 Nodal High power option 4 x RFU
LAYER 1 LINK AGGREGATION NODAL ON DAC GE / DAC GE3
- For the Chulitna site, additional modules and upgrade licenses will be installed to existing INUe supplied and installed in
the Phase 1 project.
1.300
1.301
1.302
1.303
1.304
Eclipse Accessories
CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500mm (747420016)
ETHERNET CABLE, RJ45 CAT 5/CAT 5e, 2m (6.5') (037-579124-002V_REVA)
TAA GIGATRUE 3 CAT6A 650MHZ PATCH CABLE,F/UTP,SLIMLINE,LOCKABLE,GRAY,2.1M/7FT
ALARM I/O HD15 10M WIREWRAP (037-579315-001V)
1.400
1.401
1.402
1.403
1.404
1.405
1.406
1.407
1.408
Recommended Eclipse Spares
RFU, MP, IRU600v3, 5.8/L6 GHz, 5725-6450 MHz
FAN TRAY KIT, IRU 600 V3
ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT
NODE PROTECTION CARD, HIGH OUTPUT
AUX, ALARM I/O CARD
RAC 60E, QPSK-256 QAM, High Gain, No XPIC, ACM and SYNC-E
DAC GE3 GIGABIT ETHERNET SWITCH CARD
CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500mm (747420016)
PRODUCT CODE
PART NUMBER
UNIT
PRICE
SYSTEM
PRICE
QTY
QTY
SUMMIT
PRICE
QTY
HOUSTON
PRICE
1
1
1
1
1
1
EXX-000-204
179-530064-001
EXS-002
EXA-001
EXR-660-002
EXD-181-002
EZE-08006
EZE-08007
EZA-08007-LU6
EZF-62
EZF-64
EZG-64
EZF-01
1
1
1
1
2
2
1
1
1
1
1
2
2
1
1
1
1
1
2
2
1
1
1
1
1
1
1
037-579461-500
037-579124-002
LOC-C6APC80S-GY-07
037-579315-001
1
1
2
1
1
1
2
1
1
1
2
1
2
1
2
1
2
EV104-M5-M5-300
EV105-M5-M5-300
179-530135-AA101
179-530135-AA102
179-530135-BB201
179-530135-BB202
179-530089-001
ERM-U53-301
179-530149-001
EXX-000-204
EXS-002
EXA-001
EXR-660-002
EXD-181-002
037-579461-500
2.000 Racks and Accessories
2.100 Racks
2.101
2.102
2.103
2.104
2.105
RACK ASSY CRATED, 7' CHATSWORTH ALUMINUM, 1 BREAKER PNL W/10 BLANK COVERS AND NO BREAKERS
Installation Kit, Aluminum Rack, Concrete Floor (AV179-530119-001WA)
Isolation Kit, 19" Rack (AV179-530121-001WA)
CIRCUIT BREAKER 20 AMP SNAPAK (030017750I)
1 BREAKER PNL W/10 BLANK COVERS AND NO BREAKERS
- New radio at Chulitna will be installed on existing rack supplied and installed during Phase 1.
- New racks not required at Houston or Summit as new radios will be installed into existing racks. It is assumed that ARR
will re-use the existing Breaker Panel at Houston but that a new Breaker Panel is required at Summit.
179-530307-0113
179-530119-001
179-530121-001
PWR-000053-TRM
179-530307-9910
3/14/2016 - 11:41 AM
Page 1 of 2
EQUIPMENT LIST
DESCRIPTION
ITEM
Antennas and Waveguide Systems
Antennas
ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT HYP RAD
ANTENNA, 5.925-6.425GHZ, 3.0M/10FT, HP, DUAL POL, CPR137G, WHT HYP RAD
ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT TEG RAD, HIGH WIND
ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, UHP, DUAL POL, CPR137G, WHT TEF RAD
TERMINATION LOAD,WAVEGUIDE,06 GHZ,CPR137G
INBOARD SIDE STRUT KIT FOR 6FT MICROWAVE ANTENNAS; 10.5 FT (520570-10)
OUTBOARD SIDE STRUT KIT FOR 8/10/12FT MICROWAVE ANTENNAS (520570-4)
LEG MOUNT,UP TO 6 FEET ANTENNA DIAMETER,UP TO 8 INCHES DEPTHIAMETER LEG,WITH WAVEGUIDE
3.108 EQUIPMENT PROTECTION SHIELD KIT (MTC3513LMS)
FACE MOUNT,ICE SHIELD KIT,UP TO 14 FEET FACE,SUPPORTS UP TO 8 INCHES DEPTHIAMETER LEG
3.109 (MTC3513FMS)
3.000
3.100
3.101
3.102
3.103
3.104
3.105
3.106
3.107
3.200 Waveguide
3.201 ELLIPTICAL WAVEGUIDE STANDARD, 5.925-7.125 GHZ, BLACK PE JACKET, PER FOOT (EW63-F)
3.202
3.203
3.204
3.205
3.206
3.207
EW63INSTALL-KIT (ONE KIT PER WAVEGUIDE RUN). CONSISTING OF THE FOLLOWING:
AND-24312A / LDF HOISTING SUPPORT GRIP / QTY 1
AND-163SE / 5.925-7.125GHz CPR137G FIXED-TUNES CONNECTOR / QTY 2
AND-55001-137 / PRESSURE WINDOW FOR WR137/ QTY 1
FWG-063200-900 / FLEX WAVEGUIDE WR137, 5.85-8.2 GHz, CPR137G/CPR137G, 36 IN / QTY 1
AND-244106A-70 / FLEXT-TWIST HANGER ASSEMBLY FOR WR137, 6GHz / QTY 1
AND-241088-4 / GOUNDING KIT (24IN, 2 HOLE, LUG ATTACHED) / QTY 3
HARDWARE-KIT (ONE KIT PER 100FT). CONSISTING OF THE FOLLOWING:
AND-UA-3 / AND UNIV ANGLE ADPTR KIT, SNAP-IN, 3/4IN THROUGH HOLE / QTY 3
AND-UAAI / UNIVERSAL ANGLE ADAPTER INSERT KIT / QTY 3
AND-31771-6 / THREAD ROD SUPPORT 24IN (610MM) LONG, KIT OF 5 / QTY 2
AND-31769-1 / 1IN HARDWARE KIT, KIT OF 10 / QTY 3
VAL EW63 X1 HOLE BOOT KIT (BAEW63)
VAL EW63 X2 HOLE BOOT KIT (BAEW632)
WG CUSHION EW-63, 1 HOLE (Bag of 5 Kits) (SREW63-K)
EW63 X2 HOLES CUSHION (Bag of 5 Kits) (SREW632-K)
- As requested by customer on 03/07, flex waveguide is provided for the Houston and Summit sites instead of waveguide
extension kits as it is not known at this time the exact placement of the radios into the existing racks. The flex waveguide
is part of the Bill of Material of Item 3.202 so does not need to be listed separately.
- Per the Frequency Coordination completed on 03/11/2016, the Chulitna to Bald to Douglas to Willow can only be
licensed with the channels on different polarity. As a result, 2 waveguide runs are now required per radio.
3.300 Wall Entry Panels
3.301 ENTRANCE PANEL, 2 PORT, 1 X 2 IN (204673-2A)
3.302 4 PORT ENTRANCE PANEL, 4 INCH, 1 x 4 (204673-4)
- A 2-port panel was supplied at Chulitna in Phase 1 where only 1 -port was used. However, the Chulitna radio now
requires an additional 2-ports for the new radio to Bald Mtn.
- There is an existing Entry Panel at Houston with available openings to accommodate the new WG run.
3.400 Waveguide Pressurization system
DEHYDRATOR, LOW-PRESS MEM, WALL MNTBL, 3.0-5.0 PSIG, W/DSC ALRM, 115 VAC, 50/60 HZ, 4 SEP-VLVD
3.401 PRTS (PMT200B-81315)
3.401 DISTRIBUTION MANIFOLD,2-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE
3.402 DISTRIBUTION MANIFOLD,4-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE
- A new dehydrator was supplied at Chulitna in Phase 1.
4.000
4.100
4.101
4.102
4.103
Professional Services
Factory Services
CONFIG ENG / DOCUMENTATION / DRAFTING
RADIO INTEGRATION & TESTING
FACTORY ACCEPTANCE TESTING
4.200
4.201
4.202
4.203
4.204
Program Management & Engineering Services
PROGRAM MANAGEMENT
NETWORK/SYSTEM ENGINEERING
NETWORK IP & NMS PLAN/DESIGN
PROJECT/SITE ENGINEERING (SITE SURVEYS)
4.300 Support Services
4.301 WARRANTY PLUS IW - NA&C, 24 MONTHS, IRU-600
4.302 WARRANTY PLUS NW - NA&C, 12 MONTHS, IRU-600
PRODUCT CODE
PART NUMBER
AND-HPX6-59-P1A/K
AND-HPX10-59-P1A
AND-WHPX6-59-P3A/K
AND-UHX6-59-P3A/L
AND-39099-137
AND-520570-10
AND-520570-4
UNIT
PRICE
SYSTEM
PRICE
QTY
QTY
SUMMIT
PRICE
QTY
HOUSTON
PRICE
1
1
1
1
1
1
1
1
1
1
AND-EW63-F
50
50
90
AND-EW63INSTALL-KIT
1
1
1
AND-HARDWARE-KIT
LOC-BAEW63
LOC-BAEW632
LOC-SREW63-K
LOC-SREW632-K
1
1
1
1
1
1
4
4
6
AND-204673-2A
AND-204673-4
1
1
AND-PMT200B-81315
AND-6600D-2
AND-6600D-4
1
1
1
1
1
1
2
2
2
2
2
2
179-530147-001
179-530145-001
SVCS-IN-SIPQ-AE
SVCS-IN-SIPQ-RI
SVCS-IN-SIPQ-AT
SVCS-IN-PM-PM
SVCS-PN-EN-SE
SVCS-PN-EN-SE
SVCS-IN-SS-PE
SNA-BWXXA1002438
SNA-BNWXA1001238
This sales quotation and any resulting Customer order (“Order”) are subject to Aviat Networks standard terms and conditions of sale (“Conditions”), which are available at the following web site:
http://www.aviatnetworks.com/media/files/AVWN_STCS.pdf. However, if an Order is issued under or in connection with an applicable master agreement between Aviat and Customer (an “Existing Agreement”),
then the Existing Agreement will govern and control the Order.
3/14/2016 - 11:41 AM
Page 2 of 2
Alaska Railroad
Site Summit and Houston Microwave Sites
Attachment B
Bill of Materials
Rev. 2
March 23, 2016
MAT. REF. NO.
MANUFACTURERS PART NO.
DESCRIPTION
MANUFACTURER
QTY
5
AND-39099-137
TERMINATION LOAD,WAVEGUIDE,06 GHZ,CPR137G
AVIAT
1
8
179-530147-001
AND-WHPX6-59-P3A/K
TOWER LEG MOUNT KIT, SUPPORTS UP TO 8" DIA LEG & UP TO 6' ANTENNA
AVIAT
1
10
ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT TEG RAD, HIGH WIND
AVIAT
1
20
AND-EW63-F
ELLIPTICAL WAVEGUIDE STANDARD, 5.925-7.125 GHZ, BLACK PE JACKET, PER FOOT
AVIAT
50
AND-EW63INSTALL-KIT
EW63INSTALL-KIT (ONE KIT PER WAVEGUIDE RUN). CONSISTING OF THE FOLLOWING:
AND-24312A / LDF HOISTING SUPPORT GRIP / QTY 1
AND-163SE / 5.925-7.125GHZ CPR137G FIXED-TUNES CONNECTOR / QTY 2
AND-55001-137 / PRESSURE WINDOW FOR WR137/ QTY 1
FWG-063200-900 / FLEX WAVEGUIDE WR137, 5.85-8.2 GHZ, CPR137G/CPR137G, 36 IN / QTY 1
AND-244106A-70 / FLEXT-TWIST HANGER ASSEMBLY FOR WR137, 6GHZ / QTY 1
AND-241088-4 / GOUNDING KIT (24IN, 2 HOLE, LUG ATTACHED) / QTY 3
AVIAT
AND-HARDWARE-KIT
HARDWARE-KIT (ONE KIT PER 100FT). CONSISTING OF THE FOLLOWING:
AND-UA-3 / AND UNIV ANGLE ADPTR KIT, SNAP-IN, 3/4IN THROUGH HOLE / QTY 3
AND-UAAI / UNIVERSAL ANGLE ADAPTER INSERT KIT / QTY 3
AND-31771-6 / THREAD ROD SUPPORT 24IN (610MM) LONG, KIT OF 5 / QTY 2
AND-31769-1 / 1IN HARDWARE KIT, KIT OF 10 / QTY 3
AVIAT
22
24
25
VAL EW63 X1 HOLE BOOT KIT (BAEW63)
REMARKS
ESTIMATED QUANTITY PROVIDED, IN FEET
1
1
AVIAT
AVIAT
1
WG CUSHION EW-63, 1 HOLE (BAG OF 5 KITS) (SREW63-K)
E576
CABLE WALL ENTRY PANEL, 4", 2X4
VALMONT
1
BAZERO
BOOT ASSEMBLY KIT, 4 IN., BLANK, NO HOLES
VALMONT
8
50
EV104-M5-M5-300
IRU600 V3 RFSEC ASSY 2+0 1 ANT MAIN, 2RU, U5/U5 GHZ
AVIAT
1
53
179-530135-AA102
WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 2+0/FD, RPTR (RPTR)
AVIAT
1
57
EXX-000-204
ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT
AVIAT
1
58
179-530064-001
KIT BRACKET 2RU (179-530064-001_R001)
AVIAT
1
59
EXS-002
NODE PROTECTION CARD, HIGH OUTPUT
AVIAT
1
60
EXA-001
AUX, ALARM I/O CARD
AVIAT
1
61
EXR-660-002
RAC 60E, QPSK-256 QAM, HIGH GAIN, NO XPIC, ACM AND SYNC-E
AVIAT
2
62
EXD-181-002
AVIAT
2
63
EZE-08006
DAC GE3 GIGABIT ETHERNET SWITCH CARD
NODE SW LICENSE, 400 MBPS TOTAL RADIO PAYLOAD CAPACITY
AVIAT
1
66
EZF-62
1
EZF-01
IRU600 600 NODAL HIGH POWER OPTION 2 X RFU
LAYER 1 LINK AGGREGATION NODAL ON DAC GE / DAC GE3
AVIAT
69
AVIAT
1
80
AND-PMT200B-81315
DEHYDRATOR, LOW-PRESS MEM, WALL MNTBL, 3.0-5.0 PSIG, W/DSC ALRM, 115 VAC, 50/60 HZ, 4 SEP-VLVD PRTS
AVIAT
1
81
AND-6600D-2
DISTRIBUTION MANIFOLD,2-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE
AVIAT
1
100
037-579461-500
CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500MM (747420016)
AVIAT
1
101
037-579124-002
ETHERNET CABLE, RJ45 CAT 5/CAT 5E, 2M (6.5') (037-579124-002V_REVA)
AVIAT
1
102
LOC-C6APC80S-GY-07
TAA GIGATRUE 3 CAT6A 650MHZ PATCH CABLE,F/UTP,SLIMLINE,LOCKABLE,GRAY,2.1M/7FT
AVIAT
2
104
037-579315-001
ALARM I/O HD15 10M WIREWRAP (037-579315-001V)
AVIAT
1
109
179-530307-9910
RACK ASSY, NO RACK, NO CRATE, 1 BREAKER PNL W/10 BLANK COVERS AND NO BREAKERS
AVIAT
1
110
PWR-000053-TRM
CIRCUIT BREAKER 20 AMP SNAPAK (030017750I)
AVIAT
2
OR EQUIVALENT IF INSTALLED IN EXISTING NEG 48VDC DP
112
MG41227-K
MAIN GROUND BUS BAR, INTERIOR, WALL MOUNT, 12"
VALMONT
1
OR EQUIVALENT
113
MG41227-K
EXTERIOR GROUND BUS BAR, WALL MOUNT, 12"
VALMONT
1
OR EQUIVALENT
114
220498
GROUNDING KIT, STANDARD EW63
COMMSCOPE
2
OR EQUIVALENT
27
LOC-BAEW63
LOC-SREW63-K
42
43
117
GROUND ROD, COPPER, 8', 3/4" DIA
4
4
120
108-M830-50
ANTENNA TOWER, 50' 800 SERIES SELF-SUPPORTING TOWER, VERTICAL WAVEGUIDE LADDER, CLIMBING LADDER
VALMONT
1
122
IB24D-A
ICE BRIDGE KIT, 24" SPAN, 13' 4" DIRECT BURIAL, 3.5" OD
VALMONT
2
130
CABLE TRAY, 6"
MANUFACTURER
QTY
ANTENNA, 5.925-6.425GHZ, 1.8M/6FT, HP, DUAL POL, CPR137G, WHT HYP RAD
AVIAT
1
AND-39099-137
TERMINATION LOAD,WAVEGUIDE,06 GHZ,CPR137G
AVIAT
1
AND-520570-10
INBOARD SIDE STRUT KIT FOR 6FT MICROWAVE ANTENNAS; 10.5 FT (520570-10)
AVIAT
1
8
179-530147-001
TOWER LEG MOUNT KIT, SUPPORTS UP TO 8" DIA LEG & UP TO 6' ANTENNA
AVIAT
1
20
AND-EW63-F
ELLIPTICAL WAVEGUIDE STANDARD, 5.925-7.125 GHZ, BLACK PE JACKET, PER FOOT
AVIAT
90
AVIAT
1
AND-EW63INSTALL-KIT
EW63INSTALL-KIT (ONE KIT PER WAVEGUIDE RUN). CONSISTING OF THE FOLLOWING:
AND-24312A / LDF HOISTING SUPPORT GRIP / QTY 1
AND-163SE / 5.925-7.125GHZ CPR137G FIXED-TUNES CONNECTOR / QTY 2
AND-55001-137 / PRESSURE WINDOW FOR WR137/ QTY 1
FWG-063200-900 / FLEX WAVEGUIDE WR137, 5.85-8.2 GHZ, CPR137G/CPR137G, 36 IN / QTY 1
AND-244106A-70 / FLEXT-TWIST HANGER ASSEMBLY FOR WR137, 6GHZ / QTY 1
AND-241088-4 / GOUNDING KIT (24IN, 2 HOLE, LUG ATTACHED) / QTY 3
HARDWARE-KIT (ONE KIT PER 100FT). CONSISTING OF THE FOLLOWING:
AND-UA-3 / AND UNIV ANGLE ADPTR KIT, SNAP-IN, 3/4IN THROUGH HOLE / QTY 3
AND-UAAI / UNIVERSAL ANGLE ADAPTER INSERT KIT / QTY 3
AND-31771-6 / THREAD ROD SUPPORT 24IN (610MM) LONG, KIT OF 5 / QTY 2
AND-31769-1 / 1IN HARDWARE KIT, KIT OF 10 / QTY 3
AVIAT
1
MAT. REF. NO.
MANUFACTURERS PART NO.
1
AND-HPX6-59-P1A/K
5
6
22
24
DESCRIPTION
REMARKS
25
AND-HARDWARE-KIT
LOC-BAEW63
VAL EW63 X1 HOLE BOOT KIT (BAEW63)
AVIAT
1
27
LOC-SREW63-K
WG CUSHION EW-63, 1 HOLE (BAG OF 5 KITS) (SREW63-K)
AVIAT
6
50
EV104-M5-M5-300
IRU600 V3 RFSEC ASSY 2+0 1 ANT MAIN, 2RU, U5/U5 GHZ
AVIAT
1
53
179-530135-AA102
WG EXT KIT IRU600 V3 6GHZ SH1-PO1, 2+0/FD, RPTR (RPTR)
AVIAT
1
57
EXX-000-204
ECLIPSE, INTELLIGENT NODE UNIT 2RU, INC IDCE, FAN, NCCV2, HIGH OUTPUT
AVIAT
1
58
179-530064-001
KIT BRACKET 2RU (179-530064-001_R001)
AVIAT
1
59
EXS-002
NODE PROTECTION CARD, HIGH OUTPUT
AVIAT
1
60
EXA-001
AUX, ALARM I/O CARD
AVIAT
1
61
EXR-660-002
RAC 60E, QPSK-256 QAM, HIGH GAIN, NO XPIC, ACM AND SYNC-E
AVIAT
2
62
EXD-181-002
AVIAT
2
63
EZE-08006
DAC GE3 GIGABIT ETHERNET SWITCH CARD
NODE SW LICENSE, 400 MBPS TOTAL RADIO PAYLOAD CAPACITY
AVIAT
1
66
EZF-62
1
EZF-01
IRU600 600 NODAL HIGH POWER OPTION 2 X RFU
LAYER 1 LINK AGGREGATION NODAL ON DAC GE / DAC GE3
AVIAT
69
AVIAT
1
80
AND-PMT200B-81315
DEHYDRATOR, LOW-PRESS MEM, WALL MNTBL, 3.0-5.0 PSIG, W/DSC ALRM, 115 VAC, 50/60 HZ, 4 SEP-VLVD PRTS
AVIAT
1
81
AND-6600D-2
DISTRIBUTION MANIFOLD,2-PORT,0-15.0 PSIG,25 FEET OF TUBING PER PORT,WALL MOUNTABLE
AVIAT
1
100
037-579461-500
CABLE PROT / BRIDGEING GE3, DIRECT FIT, 500MM (747420016)
AVIAT
1
101
037-579124-002
ETHERNET CABLE, RJ45 CAT 5/CAT 5E, 2M (6.5') (037-579124-002V_REVA)
AVIAT
1
102
LOC-C6APC80S-GY-07
TAA GIGATRUE 3 CAT6A 650MHZ PATCH CABLE,F/UTP,SLIMLINE,LOCKABLE,GRAY,2.1M/7FT
AVIAT
2
104
037-579315-001
ALARM I/O HD15 10M WIREWRAP (037-579315-001V)
AVIAT
1
110
PWR-000053-TRM
CIRCUIT BREAKER 20 AMP SNAPAK (030017750I)
AVIAT
2
OR EQUIVALENT IF INSTALLED IN EXISTING NEG 48 VDC DP
114
220498
GROUNDING KIT, STANDARD EW63
COMMSCOPE
2
OR EQUIVALENT
OR EQUIVALENT, GC TO PERFORM SITE SURVEY TO CONFIRM (E) ENTRY PORT DIA
Alaska Railroad
Site Summit and Houston Microwave Sites
Attachment C
Site Summit Foundation Repair Report
Rev. 2
March 23, 2016
Site Summit Tower
Foundation Report
For:
Blaine Sears
Project Manager, PTC, Telecom
By:
Andrew P. Adams, PE
Consulting Engineer
Date Prepared: 7/17/15
♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net
July 17, 2015
Blaine Sears
Project Manager, PTC, Telecom
825 Whitney Rd
Anchorage, AK 99501
Mr. Sears:
Andrew P. Adams, PE Consulting Engineer is pleased to provide the structural analysis for the
existing tower foundation located at Site Summit, Alaska. Analysis for this project is based on
information from the original tower design drawings provided by the Alaska Railroad.
The original drawings are provided in an appendix to this report. The goal of this analysis is to
determine the suitability of the existing foundation to support a like-kind tower replacement. The
tower loading will be based on the following requirements.
Dish
Dish
Dish
Dish
Dish
Original Tower Equipment Summary
Type
Size
Area
10’
78.5 sf
8’
50.24 sf
10’
78.5 sf
6’
28.25 sf
6’
28.25 sf
Elevation
50’
50’
40’
40’
30’
Summary of Results:
Provisions in the International Existing Building Code 2009, which is currently is the governing state
code for existing structures, allows for structural modifications without detailed soil and foundation
analysis if certain limits are met. Per IEBC section 3403.3, there is a gravity load increase allowance of
5% and per IEBC section 3403.4, there is a lateral load increase allowance of 10% before modifications
are required. However, the original tower design was based on the EIA-222-E, and the current code
standards is TIA-222-G. Because of this code change, and additional load parameters requested by the
AKRR, the following configuration permits the maximum allowable loading for the existing foundation.
Minimum Wind Speed: 125 MPH no ice
60 MPH ½” ice
Dish
Dish
Dish
Dish
Proposed Equipment Configuration
Type
Size
Area
8’
50.24 sf
6’
50.24 sf
6’
28.25 sf
6’
28.25 sf
Elevation
40’
40’
30’
30’
♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net
Foundation Reaction Comparison
Max Axial**
13.4 kips
10.8 kips
-22.4%
Original Design
Proposed Design
Percent Change
Max Shear
35.6 kips
37 kips
+4%
Max
Moment
1373 kip-ft
1181 kip-ft
-14%
**The change in foundation reactions assumes the new tower will not have walking platforms.
The tower vendor may provide additional limitations to the loading based on the tower’s component
capacity.
Recommendations:
The results of the analysis show no modifications are required to the existing foundation. However, due
to some damage to the foundation anchorage, the tower foundation shall be repaired as shown on the
provided drawings.
Respectfully,
Andrew P. Adams, P.E.
7/21/15
♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net
Appendix A: Reaction Summary
♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net
9
50.0 ft
40
30
DESIGNED
APPURTENANCE LOADING
8 FT DISH
6
T1
913.7
TYPE
ELEVATION
TYPE
ELEVATION
8 FT DISH
40
6 FT DISH
30
6 FT DISH
40
6 FT DISH
30
MATERIAL STRENGTH
GRADE
Fy
A572-50
50 ksi
Fu
GRADE
Fy
Fu
65 ksi
TOWER DESIGN NOTES
913.7
2L2x2x1/8
T2
HSS4.5x.237
40.0 ft
1. Tower designed for Exposure C to the TIA-222-G Standard.
2. Tower designed for a 125 mph basic wind in accordance with the TIA-222-G Standard.
3. Tower is also designed for a 60 mph basic wind with 0.25 in ice. Ice is considered to increase
in thickness with height.
4. Deflections are based upon a 60 mph wind.
5. Tower Structure Class II.
6. Topographic Category 2 with Crest Height of 1500.00 ft
7. Weld together tower sections have flange connections.
8. Connections use galvanized A325 bolts, nuts and locking devices. Installation per TIA/EIA-222
and AISC Specifications.
9. Tower members are "hot dipped" galvanized in accordance with ASTM A123 and ASTM A153
Standards.
10. Welds are fabricated with ER-70S-6 electrodes.
913.7
5 @ 10
2L2x2x1/8
A572-50
A572-50
T3
HSS1.9x.145
30.0 ft
T4
954.9
20.0 ft
ALL REACTIONS
ARE FACTORED
UPLIFT: -74698 lb
SHEAR: 12293 lb
10.0 ft
10
N.A.
HSS5.563x.258
MAX. CORNER REACTIONS AT BASE:
DOWN: 77597 lb
SHEAR: 12572 lb
AXIAL
10816 lb
T5
982.4
SHEAR
6871 lb
60 mph WIND - 0.2500 in ICE
AXIAL
6624 lb
Weight (lb) 4678.4
Face Width (ft) 11
# Panels @ (ft)
Sec. Horizontals
Top Girts
Diagonal Grade
Diagonals
Leg Grade
Legs
SHEAR
37065 lb
Section
MOMENT
212160 lb-ft
0.0 ft
MOMENT
1181357 lb-ft
REACTIONS - 125 mph WIND
Andrew P, Adams, PE Job:
Project:
PO BOX 876303
Wasilla, AK 99687
Phone: (907) 947-9303
FAX: (877) 796-2690
Client:
Drawn by:
Code:
Date:
TIA-222-G
Andrew Adams
07/20/15
Path:
App'd:
Scale:
NTS
Dwg No.
C:\Users\Andrew Adams\Desktop\122213 T RANSFER FROM DESKTOP\Andy's Folder\Engineering Work\02 Working\Alaska Railroad Site Summit\TNX FIles\site summit tower.eri
E-1
Appendix B: Foundation Modification Drawing
♦PO BOX 876303 ♦ Wasilla, AK 99687 ♦ 573-586-8735 ♦ andrewpadams@gci.net
Andrew P. Adams
No. SE13603
7/21/15
EXISTING ANCHOR BOLT ASSEMBLY
SCALE:
3/4" = 1'-0"
REPAIR ANCHOR BOLT ASSEMBLY
SCALE:
3/4" = 1'-0"
ANCHOR REPLACEMENT GUIDANCE
SCALE:
NTS
Alaska Railroad
Site Summit and Houston Microwave Sites
Attachment D
QA/QC Checklists
Rev. 2
March 23, 2016
Site Summit Telecom Site QA Checklist
Initial the box when the task has been completed, dated and add any notes.
Initial
DRAWINGS/PLANS
Correct Drawing up to date/Note Rev. Level
No red lines
TELECOM SHELTER
Cable Wall Entry port installed on wall of shelter, near shelter door
Cable Trays installed where indicated by drawings, secured to shelter ceiling
Main Ground Bus Bar installed on interior shelter wall below cable entry ports
Exterior Ground Bus Bar installed on exterior shelter wall below cable entry ports
INTERIOR GROUND SYSTEM
Interior main ground bar bonded to exterior ground bar using #2 AWG green insulated
ground wire
Rack ground bars installed at top of all racks, bonded to main ground bar using #6
AWG green insulated wire
Cable trays bonded to interior ground system with #10 AWG green insulated ground
wire
Ground resistance test complete to Main Ground Bar, results approved by owner
TOWER FOUNDATION
Foundation Repair Approved By Engineer
EXTERIOR GROUND SYSTEM
#2 AWG copper ground ring installed around tower foundation, buried minimum of
30" below grade
Copper ground rods installed in locations with ground wells per drawings
#2 AWG copper ground wire exothermically welded to exterior ground bar, shelter
ground ring, and tower ground ring
Two (2) #2 AWG coopper ground wires exothermically welded to shelter ground ring
and tower ground ring, buried less than 30"
Ground resistance test complete, results approved by owner
TOWER
Tower properly bolted to foundation on all 4 legs
Tower level
All four Tower legs bonded and grounded to ground ring
Ground Plate installed on tower close to ice bridge
Climbing studs installed
Climbing fall arrestor cable system secure and installed properly
ICE BRIDGE ASSEMBLY
Concrete foundation constructed according to specifications
Ice bridge runs level with shelter
Vertical cable ladder installed on tower near interface with Ice Bridge
Ice bridge assemblies and foundation bonded to exterior ground system
Date
NOTES
Site Summit Telecom Site QA Checklist
Initial the box when the task has been completed, dated and add any notes.
Initial
ANTENNA INSTALLATION
Dish antennas installed on proper tower leg, aligned per the drawings
Antenna supports bonded to tower steel using ground wire
Radome covers installed and secured
INTERIOR EQUIPMENT
Dehydrator and manifold installed near cable entry ports
All rack mounted hardware securely mounted, all items included
All rack mounted hardware chassis grounded to nearest ground bar using #10 AWG
green insulated ground wire
POWER AND WIRING
Measured radio input voltage is -48 VDC
All wiring between equipment as shown in one-line diagrams
All Power Distribution Panel breaker ratings confirmed
All DC power wiring installed in red EMT conduit
Tags w/wire name correct per drawings
Cable and wire Tested and Terminated recorded
As installed panel schedules provided by contractor
RF CABLES
All cables and waveguides run straight, with no cross-overs
All cables and waveguide adhere to manufacturer minimum bend radius specifications
All cables and waveguides secured no less than every 4'
All waveguide outer conductors are grounded to Exterior Ground Bar at Cable Entry
into shelter
All waveguide connected to dehydrator, all joints sealed
All waveguide and cable outer conductor bonded to Tower Ground Bar at Tower-Ice
Bridge interface
All RF connectors tight
All waveguide and cable tightly connected to antenna interface
VSWR test performed, results approved by owner
All waveguide penetrations through cable entry port sealed
Waveguide pressure test performed, results approved by owner
NET MONITORING
All equipment configured with correct network settings
Connectivity established with back office over radio links
Sensor functionality confirmed for all newly installed sensors, correct status telemetry
reported to back office
Control command functionality confirmed for all newly installed control devices
Event response tests performed to simulate the following:
Tripped breakers, other tests requested by ARRC
Date
NOTES
Site Summit Telecom Site QA Checklist
Initial the box when the task has been completed, dated and add any notes.
Initial
FINAL QA/QC INSPECTION
Overall visual inspection of site
Name, Signature and Date of ALL persons Initialing:
_____________________________________________
_____________________________________________
Final Completed Copies Go to:
Contractors Rep
ARRC Project Manager
ARRC Telecom
Date
NOTES
Microwave Telecom Site QA Checklist
Initial the box when the task has been completed, dated and add any notes.
Initial
DRAWINGS/PLANS
Correct Drawing up to date/Note Rev. Level
No red lines
TELECOM SHELTER
Cable Wall Entry port installed according to drawings
Cable Trays installed where indicated by drawings, secured to shelter ceiling
Main Ground Bus Bar installed on interior shelter wall below cable entry ports
Exterior Ground Bus Bar installed on exterior shelter wall below cable entry ports
All wall penetrations are sealed
INTERIOR GROUND SYSTEM
Interior main ground bar bonded to exterior ground bar using #2 AWG green insulated
ground wire
Rack ground bars installed at top of all racks, bonded to halo wire or main ground bar
using #6 AWG green insulated wire
Cable trays bonded to interior ground system with #10 AWG green insulated ground
wire
Ground resistance test complete to Main Ground Bar, results approved by owner
EXTERIOR GROUND SYSTEM
#2 AWG copper ground ring installed around tower foundation, buried minimum of
30" below grade
#2 AWG copper ground ring installed around shelter, buried less than 30"
Copper ground rods installed in locations with ground wells per drawings
#2 AWG copper ground wire exothermically welded to exterior ground bar and shelter
ground ring
Shelter ground ring and tower ground ring bonded together using #2 AWG ground
wires or exothermic weld, buried minimum of 30" below grade
Ground resistance test complete, results approved by owner
ANTENNA INSTALLATION
Dish antennas installed on proper tower leg, aligned per the drawings
Antenna supports bonded to tower steel using ground wire
Radome covers installed and secured
INTERIOR EQUIPMENT
Dehydrator and manifold installed near cable entry ports
All rack mounted hardware securely mounted, all items included
All rack mounted hardware chassis grounded to nearest ground bar using #10 AWG
green insulated ground wire
POWER AND WIRING
All wiring between equipment as shown in one-line diagrams
All Power Distribution Panel breaker ratings confirmed
Date
NOTES
Microwave Telecom Site QA Checklist
Initial the box when the task has been completed, dated and add any notes.
Initial
All DC power wiring installed in red EMT conduit
Tags w/wire name correct per drawings
Cable and wire Tested and Terminated recorded
Correct voltage confirmed at all equipment power supply inputs
As installed panel schedules provided by contractor
RF CABLES
All cables and waveguides run straight, with no cross-overs
All cables and waveguide adhere to manufacturer minimum bend radius specifications
All cables and waveguides secured no less than every 4'
All coaxial cables include surge protection on interior side of cable entry port into
shelter
Surge protectors bonded to Main Ground Bar with #6 AWG green insulated ground
wire
All waveguide outer conductors are grounded to Exterior Ground Bar at Cable Entry
into shelter
All waveguide connected to dehydrator, all joints sealed
All waveguide and cable outer conductor bonded to Tower Ground Bar at Tower-Ice
Bridge interface
All RF connectors tight
All waveguide and cable tightly connected to antenna interface
VSWR test performed, results approved by owner
All waveguide penetrations through cable entry port sealed
Waveguide pressure test performed, results approved by owner
NET MONITORING
All equipment configured with correct network settings
Connectivity established with back office over radio links
Sensor functionality confirmed for all newly installed sensors, correct status telemetry
reported to back office
Control command functionality confirmed for all newly installed control devices
Event response tests performed to simulate the following:
Tripped breakers and any other tests required by ARRC
FINAL QA/QC INSPECTION
Overall visual inspection of site
Name, Signature and Date of ALL persons Initialing:
_____________________________________________
_____________________________________________
Date
NOTES
Microwave Telecom Site QA Checklist
Initial the box when the task has been completed, dated and add any notes.
Initial
Final Completed Copies Go to:
Contractors Rep
ARRC Project Manager
ARRC Telecom
Date
NOTES
Download