IEC 61850 Station – Program, Construction Testing & Construction, Commissioning Lessons Learned April 3, 2012 Jerry Fortier – Northeast Utilities Mike Kloiber – Burns & McDonnell 61850 Design Background • New IEC61850 P&C Design Began Fall 2009 • Core Team Formed to Evaluate/Select Equipment & I t Integration ti Services S i – Executive E ti Sponsorship S hi off P Program • Design Refinement Process • Northeast Utilities (NU) Simulator was Commissioned to Facilitate Training & Testing • Additional Design Refinement Process First NU 61850 Deployment – Greater Springfield Reliability Project Greenfield Sites • Cadwell C d ll S Switching it hi Station St ti – 115kV five - Position Ring Bus • Fairmont Switching Station – 115kV five -Bay Bay Breaker-andBreaker and a-Half Yard Brownfield Sites • Agawam Substation – 115kV four - Bay Breaker-and-a-half Yard ((345kV Yard Added)) • North Bloomfield Substation – 115kV /345kV (345kV Yard Additions) Cadwell Substation – Bundled Approach • First Greenfield Rollout of 61850 Design • Located in Massachusetts • Turn-Key T K Project P j t • Relay Panels, Panels Automation Equipment and Integration Services Bundled Together g in Procurement Process Cadwell Substation - Testing Factory Acceptance Testing (FAT) • Complete Integration System Testing at Siemens Facilityy • Full Network Connectivity of Equipment • Two Teams Working in Parallel • Automation Team – Northeast Utilities Utilities, Siemens • Relaying Team – Northeast Utilities, Burns & McDonnell, Siemens, American Electric Test Cadwell Substation – Testing Automation Team – Testing Responsibilities • Data Concentrators • Human-Machine Interface Units • Alarm Al &C Control t lF Functionality ti lit • Network Monitoring/Reporting • Redundancy/Fail-over Testing Relaying Team – Testing Responsibilities • Logic Diagrams • Relay Settings • GOOSE Messaging • Trip T i Ti Timing i • Redundancy/Fail-over Testing Cadwell Substation - Testing Site Acceptance Testing (SAT) • Acceptance Testing of Relay Protection Elements • Complete Integration System Testing Onsite • Same Teams as FAT • Additional Interface Testing with Area Control Center • Direct Tripping/Operation of Breakers & Motor MotorOperated Disconnect Switches Cadwell Substation - Status • Tested & Commissioned • Test-Energized g • Turned Over to Area Control Center • Awaiting Construction of Remaining Transmission Lines Agawam Substation – Un-Bundled Approach • • • • • First brownfield rollout of 61850 Design Located in Massachusetts Began g as 115kV four-Bayy Breaker-and-a-half Yard Reclassification as Bulk Power Station Relay Panels & Automation Equipment Procured separate from Integration Services Contract • 61850 Rollout in Steps Agawam Substation – 61850 Rollout • First Step Included 61850 Infrastructure, Infrastructure Line and Two Breakers • Using g Interface Relays y to Seam 61850 to Hardwired Circuits • Capacitor Bank Conversion • “A” Bus Conversion • Bay-4 Line and Breaker Conversion • New Bay-5 Bay 5 Integration • Total of 12 Steps in Rollout Sequence Agawam Substation – 61850 Rollout After Before Agawam Substation - Testing Factory Acceptance Testing (FAT) • • • • FAT at Panel Vendor similar to Cadwell Other Steps FAT at NU Simulator SAT Similar to Cadwell Onsite Testing/Commissioning Required Additional Scheduled Outages • Increased Sensitivity to Working in Energized Station Agawam Substation - Status Just Entered Outage for Step 5 • Convert “B” Bus to 61850 • Convert 115kV Terminal and three Breakers • Complete Integration of Bay-4 Next Step Will Integrate: • Two new Autotransformer Banks • Four new Gas Gas-Insulated Insulated Bus Segments • New 2-Bay 345kV Yard Remaining GSRP Stations - Status Fairmont Switching g Station • Greenfield – 115-kV - Five Bay Breaker-and-One-Half Design • Phase 2 Construction Scheduled to Commence Later This Year • Testing and Commissioning Scheduled for Mid Year 2013 North Bloomfield Substation • Brownfield – 115-kV/345kV – 345kV Additions • Phase 2 Construction Scheduled to Commence Mid Year 2012 • Testing and Commissioning Scheduled for Early 2013 • NU to Self-Perform IEC61850 Integration Configuration Lessons Learned DOCUMENTATION IS CRITICAL! Develop and Maintain: • Sequencing Documents “Pl th “Plan the W Workk – Work W k the th Plan” Pl ” • Testing/Commissioning Procedures • Configuration Control Procedures • As-Built Document Procedures Maintain Open Communications with • Project Management • Outage Planning • Area Control Center • Engineering E i i • Testing Group Lessons Learned Minimize Variables During Implementation • Firmware Changes • Un-necessary System Enhancements or Functionality Brownfield Sites: • Have a Restoration Plan • Understand Impact of Each Step Lessons Learned – Robust Training NU IEC 61850 Five Day Training Module Day 1: IEC61850 Basics IEC61850 Standards and methods Managing and configuring devices GOOSE principles Station LAN basics Siemens Substation Automation Lab system architecture Day 2: IEC61850 Relay Configuration and GOOSE Messages ICD file properties and creation Goose Message definition and configuration g and interconnecting g techniques q Networking Programming the Siemens Bay Controller with DIGSI Lessons Learned – Robust Training Cont. Day 3: DIGSI 61850 System Configuration and the SCD File Managing multi-vendor ICD files Using DIGSI to manage the GOOSE messages Creating the global SCD (system Definition) file Review of the Lab system SCD Day 4: SICAM PAS Data Concentrator Overview and Configuration SICAM PAS UI – the user interface SICAM PAS Configuration – managing databases Importing and configuration using the SCD file Mapping data to the other interfaces (Control Center, HMIs) Lab system Database Day 5: SICAM PASCC HMI Overview and Project Management Overall project structure and tools within PASCC/WinCC I Importing ti and d managementt off the th SICAM PAS database d t b Basics of Project creation and management Lab system features and functionality QUESTIONS!