"|.leil-< fuffifrEF.H mlqft frfr6s,,",T"ifX?,"i:,??f

advertisement
E]_sf
&quot;|.leil-&lt; fuffifrEF.H
mlqft
Oflice of the
Chief Engineer
frfr6s,,&quot;,T&quot;ifX?,&quot;i:,??f;,,,
DHAKA POWER DISTRIBUTION COMPANY LIMITED
(An Enterprise of the Govemment of the People's Republic of Bangladesh)
Gulshan-1, Dhaka-1212
Ph: 989545 8/F ax: 8823264
E-mail c e d@dpdc. or g. bd
:
www.dpdc.org.bd
Memo No. : DPDCiCEDiPSEEIIP I AFD
Subject:
Date:
1201 5 1223
l5/1212015
Addendum No. 3 of Bid Document against 6'Lot-l: Design, Manufacture, Supply,
Installation, Testing and Commissioning of 7 nos. new 132/33 kV GIS Sub-stations
at char Sayedpur, Fatulla, Jigatola, Kazla, Motijheel, New Ramna and postogola
on Turnkey basis.&quot;
(Invitation
fo
r Bid
No. :
DPDC/PSEEIIP/AFD I 2015
139,
Date :
0 6 I 0S
I 20
t5)
Addendum No. 3 of Bid Document against &quot;Lot-l: Design, Manufacture, Supply, Installation, Testing
and Commissioning of 7 nos. new 132133 kV GIS Sub-stations at Char Sayedpur, Fatulla, Jigatola,
Kazla, Motijheel, New Ramna and Postogola on Turnkey basis&quot; is hereby issued, which will be an
integral part of the bidding document.
All
other terms and conditions
will remain
unchanged.
Yours Sincerely,
Chief Engineer, Development
&amp;,
Project Director,
Construction of New 132133 kV and 33111 kV Substations
E-mail: ced@dpdc.org.bd
Cony to:
Director, DPDC.
2. Executive Director, Engineering/ operation/ Finance/ Adminishation, DpDC
3. Chief Engineer, Planning &amp; Design/Company Secretary, DPDC.
4. Superintending Engineer, Implementation, 132/33 kV Substation, DpDC.
5. Executive Engineer, 132133 kV Substation, DPDC.
6. Office copy/ Master File.
1. Managing
DHAKA POWER DISTRIBUTION COMPANY LTD.
Lot-l: Design, Manufacture, Supply, Installation, Testing and Commissioning of 7 nos. new
132133
kV GIS Sub-stations at Char Sayedpur, Fatulla, Jigatola, Kazla, Motijheel, New Ramna
and Postogola onTurnkey basis.
[Invitation for Bid No. DPDC/PSEEIIP/AFD/2 015l39,Date: 06/08/20 1 5]
Addendum No.3
Memo No.:
DPDC/PSEEIIP/AFD|Z\|'|LL5
sl.
Reference
Stated in the Bid Document
Volume -3 of 3,
Schedule- I, page SI-5
Type test reports of 132 kV, 2000A &amp;33
Date:lsnztz}t5.
Amendment
No.
I
&amp; Addendum-l,
No.35
S1.
kV, 2000A GIS breaker including
PT, Disconnector, 132
CT,
kV
12504' Air
Insulated Switchgear including CT, CVT,
Disconnector, 132 &amp; 33 kV Surge
Arrester, 132 kV 1x800 mm'zXLPE Cu
Cable, 33 kV 1x800 mm2 XLPE Cu
Cable and 11 KV 1x500 mm2 XLPE Cu
Cables, 132 kV &amp; 33 kV Plug in GIS End
Termination, 132 kV , 33 kV &amp; 11 kV
Indoor/outdoor Cable Accessories and
11
kV 25004 Air Insulated Switchgear shall
be
submitted
from arry
Laboratory which
is
member
Testing
of STL,
otherwise the bid will be rejected.
The type test reports of higher capacity
and/or higher voltage class for above
mentioned equipment and cable shall also
be
acceptable
for
evaluation purpose
only. However the prospective bidders
shall have to confirm with a commitment
letter with the technical proposal to
conduct complete type test excluding
destructive test as per latest version of
IEC
standard
from any
Testing
Laboratory which is a member of STL,
on offered type equipment and cable
which will be selected by DPDC
nominated engineers at random prior to
PSI, if any. All costs related to these tests
shall be borne by the contractor.
Replace this paragraph by
of 132 kV,20004 &amp; 33 kV,
20004 GIS breaker including CT, PT,
&quot;Type test reports
Disconnector, 132 kV 12504. Air Insulated
Switchgear including CT, CVT, Disconnector,
132 &amp; 33 kV Surge Arrestero 132 kV 1x800 mm?
XLPE Cu Cable, 33 kV 1x800 mmz XLPE Cu
Cable and I I KV 1x500 mm2 XLPE Cu Cables,
132 kV &amp; 33 kV Plug in GIS End Termination,
132 kV,33 kV &amp; 11 kV Indoor/outdoor Cable
Accessories and 11 kV 25004 Air Insulated
Switchgear or type test reports ofhigher capacity
and/or higher voltage class shall be submitted
from any Testing Laboratory which is member of
STL, otherwise the bid will be rejected.
The prospective bidders shall have to confirm
with a commitment letter in case of not submitted
test report of offered type of above equipment
and cable, with the technical proposal to conduct
complete t)?e test excluding destructive test as
per latest version of IEC standard from any
internationally reputed independent testing
laboratory or Manufacturer's own accredited
Testing Laboratory, on offered type equipment
and cable which will be selected &amp; witnessed by
DPDC nominated engineers at random prior to
PSI, if any. All costs related to these tests shall be
borne by the contractor.&quot;
Note: Accredited certificates are to be approved
by the government.of the respective country.
W
2
Volume -3 of 3,
Schedule- I, page SI-2
Type Tests and Special Tests Reports of
132/33
kV,
801120
MVA
Power
Transformer as per relevant IEC shall be
submitted from any Testing Laboratory
which is a member of STL; otherwise the
bid will be rejected. However, the bidder
will be considered for further evaluation
if the bidder complies the following
conditions:
&quot;The type test reports of higher capacity
and./or higher voltage class for power
transformer shall also be acceptable for
evaluation purpose only. However the
prospective bidders shall have to confirm
with a
commitment letter
technical proposal
to conduct
type test and loss
with
the
complete
determination
excluding destructive test as per latest
version ofIEC standard from any Testing
Laboratory which is a member of STL,
on offered 132/33 kY, 80/120 MVA
Power Transformer which
will
be
selected by DPDC nominated engineers
at random prior to PSI, if any. A11 costs
related to these tests shall be borne by the
contractor&quot;.
Replace this paragraph by
&quot;Type Tests and Special Tests Reports of 132/33
kV, 80/120 MVA Power Transformer or type test
reports of higher capacity and/or higher voltage
class for power transformer as per relevant IEC
shall be submitted from any Testing Laboratory
which is a member of STL or witnessed by
representative of STL at Manufacturerrs own
accredited Testing Laboratory or witnessed by
representative of STL at any internationally
reputed independent testing laboratory;
otherwise the bid
will
be rejected.
The prospective bidders shall have to confirm
with a commitment letter with the technical
proposal to conduct complete type test and loss
determination excluding destructive test as per
latest version ofIEC standard from any
internationally reputed independent testing
laboratory or Manufacturer,s own accredited
Testing Laboratory, on offered 132/33 kY,
80/120 MVA Power Transformer which will be
selected &amp; witnessed by DPDC nominated
engineers at random prior to PSI, if any. Al1 costs
related to these tests shall be borne bv the
contractor&quot;.
Note: Accredited certificates are to be approved
by the government ofthe respective country.
b,+\.
k
W
3
Volume -3 of 3,
Schedule- I, page SI-2
Type Tests and Special Tests Reports of
33lll kV, 28/35 MVA
Power
Transformer as per relevant IEC shall be
submitted from any Testing Laboratory
which is a member of STL; otherwise the
bid will be rejected. However, the bidder
will be considered for further evaluation
if the bidder complies the following
conditions:
Type test &amp; special test reports of 33lll
kY, 20/28 MVA transformer from any
Testing Laboratory which is a member of
STL
will be acceptable for
evaluation
Replace this paragraph by
&quot;Type Tests and Special Tests Reports of 33/11
kY,28/35 MVA Power Transformer or Type test
&amp;
special test reports of 33/11 kV, 20128 MVA
or higher capacity at 33/ll kV
voltage class as per relevant IEC shall be
transformer
submitted from any Testing Laboratory which is
a
member
of STL or
witnessed by
representative of STL at Manufacturers own
accredited Testing Laboratory or witnessed by
representative of STL at any internationally
reputed independent testing laboratory;
otherwise the bid
will
be rejected.
purpose only, However the prospective
bidders shall have
commitment letter
proposal
to confirm with a The prospective bidders shall have to confirm
with the technical with a commitment letter with the technical
to conduct
complete type test
and loss determination excluding
destructive test as per latest version of
IEC standard from any Testing
Laboratory which is a member of STL,
on offered transformers 33/ll kV 28/35
MVA, which will be selected by DPDC
nominated engineers at random prior to
PSI, if any. All costs related to these tests
shall be borne by the contractor.
proposal to conduct complete type test and loss
determination excluding destructive test as per
latest version of IEC standard from any
internationally reputed independent testing
laboratory or Manufacturer's own accredited
Testing Laboratory, on offered transformers
33/11 kV 28/35 MVA, which will be selected &amp;
witnessed by DPDC nominated engineers at
random prior to PSI, if any. All costs related to
these tests shall be borne by the contractor.
Note: Accredited certificates are to be approved
by the government ofthe respective country&quot;.
4
Volume-3 of 3,
Schedule-B: Price
Schedules
A. CHAR
SAYEDPUR, B.
FATULLAH, C.
JIGATOLA, E.
MOTIJHEEL &amp; F.
NEW RAMNA I32
KV GIS,33 KV GIS
&amp; 11 KV AIS
SUBSTATION
Schedule No. B1&amp;B2:
19.
AIS Surge Arresters
19.02 33 kV
Circuit
33 kV Single phase surge arresters
for two new 33i11 kV power
by &quot;33 kV Single phase surge arresters for
two new 132R3 kV &amp; two new 33/11 kV
power transformers: 4 Sets&quot;
transformers: 2 Sets
Schedule No. B4:
AIS Surge Arresters
33 kV Circuit
33 kV Single phase surge arresters
for two new 33/11 kV power
transformers: 2 Sets
fr&quot;V&gt;--
Replace the quoted item &quot;33 kV Singte
phase surge arresters for two new 33i11
kV power transformers: 2 Sets&quot;
t-l
w
Volume-3 of 3,
Schedule No. B1&amp;B2:
Schedule-B: Price
17.
Schedules
AIS Surge Arresters
17.02 33 kV
D. KAZLA
and G.
POSTOGOLA 132
KV GIS,33 KV GIS
&amp; 11 KV AIS
SUBSTATION
Replace the quoted item &quot;33 kV Single
phase surge arresters for two new 33/11
kV power transformers: 2 Sets&quot;
Circuit
33 kV Single phase surge arresters
for two new 33/11 kV power
transformers:2 Sets
by &quot;33 kV Single phase surge arresters for
two new 13283 kV &amp; two new 33/11 kV
power transformers: 4 Sets&quot;
Schedule No. B4:
AIS Surge Arresters
33 kV Circuit
33 kV Single phase surge arresters
for two new 33/11 kV power
transformers:2 Sets
5
Volume-3 of 3,
Control, Protection,
Schedule-B: Price
Automation &amp; Metering
132 KY Control Panel for OHL
Line at Madanganj S/S: I Lot,
132 KV Relay Panel for O/H Line
at Madanganj S/S: I Lot,
Schedules
Schedule
No.Bl,B2,B4
A. CHAR
Substation
SAYEDPUR &amp; G.
POSTOGOLA 132
KV GIS,33 KV GIS
&amp; II KVAIS
SUBSTATION
6
Volume-3 of 3,
C. Civil and Allied Works at Char
Schedule-B: Price
KV Substation.
1. Construction of temporary
switch cum control room for
accommodating 33, 11 KV
Syedpur 33111
Schedules
Schedule No.
84
A. CHAR
SAYEDPUR I32 KV
GIS, 33
KV GIS &amp;
KV AIS
SUBSTATION
lilt-
11
switches, control and relay panels,
battery and battery charger etc., in
a safe place:
k
Delete Item no.
*7.07 132 KV Contol Panel for OHL
Line at Madanganj S/S: I Lot
7.08 132 KV Relay Panel for O/FI Line at
Madanganj S/S: I Lot&quot;
from Schedule 81, 82 &amp;B4 of A. CHAR
SAYEDPUR &amp;
Delete Item no.
&quot;5.07 132 KV Control Panel for OHL Line
at Madanganj SS.: I Lot
5.08 132 KV Relay Panel for OHL Line at
Madanganj SS.: I Lot&quot;
from Schedule B1, B2 &amp;B4 of
G. POSTOGOLA Substation.
Delete quoted item
&quot;1. Construction of temporary switch cum
control room for accommodating 33, l1 KV
switches, control and relay panels, battery
and battery charger etc., in a safe place: I
Lot&quot;.
I Lot.
ry*
1
Volume-3 of 3,
C. Civil and Allied Works
Schedule-B: Price
Fatullah 33111 KV Substation.
Schedules
1
84
B. FATULLAHI32
KV GIS,33 KV GIS
&amp; II KVAIS
SUBSTATION
Schedule No.
Delete the quoted items
at
&quot;1. Temporary arrangement of maintaing 33
source to the existing Transformers
KV
Temporary affangement of
maintaing 33 KV source to the
existing Transformers including
ffansfer of protection etc.with the
cooperation of DPDC: I Lot
including transfer of protection etc.with the
cooperation of DPDC: I Lot
2. Relocation of existing VHF Tower to a
suitable permanent locationand maintaing the
communication
2. Relocation of existing VHF Tower
to a suitable permanent locationand
maintaing the communication with
the cooperation of DPDC:1 Lot
3. Demolishing the unused Control
Room for 132 KV GIS Building with
basement and other top floors: 1 Lot
4. Recovery of equipment and other
cooperation of
3. Demolishing the unused Control Room for
132 KY GIS Building with basement and
other top floors: I Lot
4. Recovery ofequipment and other associated
materials, temporarily used for continuing the
electricity after energizing the newly built
substaion and demolishing the temporary switch
cum control room: 1 Lof'.
associated materials, temporarily used
for
with the
DPDC:I Lot
continuing the electricity after
energizing the newly built substaion
and demolishing the temporary switch
cum control room: I Lot
8
Volume-3 of 3,
9. Earthing and
Schedule-B: Price
Protection
Schedules
9.01 Earthing System
Schedule No.
Bl
A. CHAR
SAYEDPUR I32 KV
GIS, 33 KV GIS &amp; I I
KV AIS
SUBSTATION
9
Volume-2
SECTION
of
3,
3
132 KV
GAS
INSULATED
SWITCHGEAR
Replace quoted item &quot;9.01 Earthing
Lightning
System for Complete Substation: Lot,
9.02 Lightning Protection System for
for
Complete Substation: Lot,
Complete Substation: Lot&quot;
9.02 Lightning Protection System
for Complete Substation: Lot.
By
3.9.3 Cunent Transformers:
Replace this paragraph by
Current transformers,
where
specified, shall be SF6 gas insulated,
shall
compatible
the
&quot;Current transformers, where specified, shall
be SF6 gas insulated or secondary of CT
may be outside of gas chamber, shall be
switchgear and shall preferably not
contain any hygroscopic insulating
material which could affect the SF6
gas in either the cunent transformer
or in the associated switchgear
in the associated switchgear chamber&quot;.
be
&quot;9.01 Earthing System for Complete
Substation: I Lot,
9.02 Lightning Protection System for
Complete Substation: I Lot&quot;
with
compatible with the switchgear and shall
preferably not contain any hygroscopic
insulating material which could affect the
SF6 gas in either the current kansformer or
chamber.
W
u
-€,91,,,{-
10
Volume-2
SECTION
of
3,
33 KV
15.3
33 KV GAS INSULATED
GAS
15.3.1 Switchgear Design
Replace this paragraph by
&quot;The current transformer must be of the dielectrically non-stressed toroidal-core type
SWITCHGEAR
15
and
mounted outside or inside the enclosures&quot;.
Performance
INSULATED
SWITCHGEAR
The current transformer must be of
the
di-electrically
non-stressed
toroidal-core type mounted outside
11
Volume-3 of 3,
the enclosures.
5. Civil Works, Control Building
Schedule-B: Price
and Foundation
Schedules
Schedule No.
84:
B. FATULLAHI32
Replace the quoted item &quot;Transformer
foundations(l32 KV-2nos.&amp; 33 KV-3 nos)
including oilpit etc.:
1
Lot&quot;
i) Transformer foundations(l32
KV-2nos.&amp; 33 KV-3 nos) including
by &quot;Transformer foundations(l32 KV-
oilpit etc.:
2nos.
1
Lot
&amp; 33 KV-2 nos.) including oil pit
etc.: 1 Lot&quot;
KV GIS,33 KV GIS
&amp; 11 KV AIS
SUBSTATION
t2
Volume-3 of 3,
3. Civil Works, Control Building
Replace the quoted item &quot;Transformer
Schedule-B: Price
and Foundation
foundations(l32 KV-2nos.&amp; 33 KV-3 nos)
including oilpit etc.: lLot&quot;
Schedules
Schedule No.
i) Transformer foundations(132
KV-2nos. &amp; 33 KV-3 nos) including
84:
E. MOTIJHEEL I32
KV GIS,33 KV GIS
oilpit etc.: I Lot
by &quot;Transformer foundations(l32 KV2nos. &amp; 33 KV-2 nos.) including oil pit
etc.:
1
Lot&quot;
&amp; 1I KV AIS
SUBSTATION
13
RatedBurdenofVoltagelPotentia1Transformerforl32kVGIS,36kVGisffi
both metering and protection instead of Rated Burden stated in the GTP or elsewhere of bid document. Rated
Burden of Voltage/Potential Transformer for 132 kV AIS will be as per bid document.
t4
Degree of protection for l
p4&gt;-
f-,1
lkV HV compartment will
be Ip5X.
8,#t6-
Download