FINAL REPORT QP 311 – Kingdom Community Wind Project Interconnection Feasibility Study July, 2010 Prepared by: QP 311 Feasibility Study Final Report i Contains Critical Energy Infrastructure Information For ISO New England and Vermont Electric Power Company July 19, 2010 Table of Contents Executive Summary ....................................................................................................................... iv 1 Background ............................................................................................................................. 1 1.1 Study Objective............................................................................................................... 1 1.2 Project Description.......................................................................................................... 1 1.3 Technical Specifications ................................................................................................. 3 1.3.1 Project Generator Modeling Data ........................................................................... 3 1.3.2 Project Transformer Modeling Data ....................................................................... 4 1.3.3 Project Transmission Line Modeling Data ............................................................. 4 2 Study Area .............................................................................................................................. 6 2.1 Transmission System ...................................................................................................... 6 3 Base Case Development ......................................................................................................... 7 3.1 Base Case Origin and Year ............................................................................................. 7 3.2 Area Load........................................................................................................................ 7 3.3 Planned Projects.............................................................................................................. 7 3.4 Base Case Naming Convention ...................................................................................... 7 3.5 Voltage Operational Analysis ......................................................................................... 8 3.6 Analytical Tools.............................................................................................................. 9 4 Steady State Analysis Methodology ....................................................................................... 9 4.1 Steady State Voltage Limits............................................................................................ 9 4.2 Steady State Thermal Limits........................................................................................... 9 4.3 Steady State Base Case Dispatch and Interface Conditions ......................................... 10 4.4 Steady State Contingency List ...................................................................................... 11 5 Steady State Analysis Results............................................................................................... 12 5.1 Baseline System ............................................................................................................ 12 5.1.1 Voltage Performance ............................................................................................ 12 5.1.2 Thermal Performance............................................................................................ 13 5.2 QP 311 In-Service......................................................................................................... 14 5.2.1 Voltage Performance ............................................................................................ 16 5.2.2 Thermal Performance............................................................................................ 17 6 Short Circuit Analysis........................................................................................................... 18 7 Delta V on Capacitor Switching ........................................................................................... 19 8 Cost Estimates for Required Network Upgrades .................................................................. 19 9 Conclusion ............................................................................................................................ 20 Appendices Appendix A - Project Information ................................................................................................. A Appendix B - Study Methodology..................................................................................................B Appendix C - Preliminary One-Line Diagram................................................................................C Appendix D - Steady State Contingency List ................................................................................ D Appendix E - Steady State Base Case Summaries.......................................................................... E Appendix F - Steady State Base Case Draw Files .......................................................................... F Appendix G - Steady State Contingency Voltage Results............................................................. G Appendix H - Steady State Contingency Thermal Results............................................................ H QP 311 Feasibility Study Final Report July 19, 2010 ii Contains Critical Energy Infrastructure Information List of Tables Table 1-1 QP 311 Generator Modeling Data.................................................................................. 4 Table 1-2 QP 311 Transformer Modeling Data.............................................................................. 4 Table 1-3 QP 311 Transmission Line Modeling Data .................................................................... 4 Table 1-4 QP 311 Collector String Modeling Data ........................................................................ 5 Table 4-1 Steady State Voltage Criteria ......................................................................................... 9 Table 4-2 Steady State Thermal Criteria ...................................................................................... 10 Table 4-3 Local Area Dispatches.................................................................................................. 11 Table 5-1 Peak Load Contingencies Resulting in Voltage Violations Pre-Project ...................... 13 Table 5-2 Losses Due to Addition of Q311 Project...................................................................... 14 Table 5-3 Newport Area Pre Contingency Voltages .................................................................... 15 Table 5-4 Additional Capacitors for K42 Contingency................................................................ 15 Table 5-5 Reactive Compensation Proposed for the Project ........................................................ 16 Table 5-6 Post Contingency Capacitor Switching at Jay Tap Switching SS................................ 16 Table 6-1 Kingdom Community Wind Short-circuit Fault Duties .............................................. 19 List of Figures Figure 1-1 Pre Project Simplified One Line Diagram .................................................................... 2 Figure 1-2 Post-Project Simplified One Line Diagram .................................................................. 3 Figure 2-1 Project Geographical Map............................................................................................. 6 Figure 3-1 Steady State Base Case Naming Convention................................................................ 8 QP 311 Feasibility Study Final Report July 19, 2010 iii Contains Critical Energy Infrastructure Information Executive Summary RLC Engineering, LLC (RLC) conducted a Feasibility Study (the “Study”) under the ISO New England Inc. (ISO) Open Access Transmission Tariff (“Tariff”) Schedule 22-Standard Large Generator Interconnection Procedures (“LGIP”). The Study was performed on behalf of ISO New England Inc. (ISO) and Vermont Electric Power Company (VELCO) for the Interconnecting Customer at Queue Position 311 (QP 311) to construct a 63 MW Wind Farm Project (the “Project”) located in Lowell, Vermont in Orleans County. The wind farm is proposed to consist of twenty-one 3.0 MW Vestas V90 wind turbines connecting into the new Vermont Electric Cooperative (VEC) 46 kV Lowell Substation. The Project has a proposed inservice date of October 2012. Based on a prior study conducted by VELCO and VEC, the following changes are proposed to occur prior to the Project in-service date: o Construct Jay Tap Switching Station 4 miles west of the North Troy Substation on the existing 46 kV transmission line (the VT Public Service Board (PSB) has opened Docket 7604 to review VEC’s Jay Tap Switching Station construction permit application) o Install five 46 kV breakers at Jay Tap Switching Station o Install four 2.7 MVAr shunt capacitors at Jay Tap Switching Station The primary objective of this Study was to determine if interconnecting QP 311 (the Project) would have significant adverse impact on the reliability and operating characteristics of the VELCO or VEC transmission systems, the transmission facilities of another Transmission Owner, or the system of a Market Participant. Steady state conditions and short circuit testing were analyzed in this Study. The purpose of the Study was to: (i) Analyze the steady-state and short circuit impact of the Project (ii) Determine any upgrades to the transmission system that would be required to mitigate any adverse impacts that the Project could otherwise pose on the reliability and operating characteristics of the New England transmission system (iii) Determine any upgrades required to mitigate any degradation to transmission transfer capability Project Description To accommodate the interconnection of the Project, a portion of the existing 34.5 kV transmission system around Lowell will need to be upgraded to 46 kV and a new 46 kV line will need to be constructed to interconnect with the VELCO 115 kV transmission system. The following is an overview of the facilities required for the interconnection of the Project: QP 311 Feasibility Study Final Report July 19, 2010 iv Contains Critical Energy Infrastructure Information • • • • • • • • • • • Install a new 115/46 kV autotransformer on the K41 Line between Highgate and Moshers Tap to connect to the Jay Tap 46 kV Substation Install one 46 kV breaker between the Jay Tap Switching Station bus and the 46kV terminal of the autotransformer Upgrade 2 miles of existing 46 kV transmission line from Jay Tap Switching Substation to a tap point (Crossroad) to 795 kcmil ACSR and add three 46 kV Switches at Crossroad tap point Construct 2 miles of new 46 kV transmission line from Crossroad tap point to the Jay 17 Substation with 795 kcmil ACSR Upgrade the 34.5 kV Jay 17 Substation to 46 kV and install a 46/12.47 kV transformer at Jay 17 Substation Upgrade 10.4 miles of transmission line (to 795 kcmil ACSR) from Jay 17 Substation to VEC Lowell Substation Construct a VEC Lowell 46 kV Substation and install three 46 kV breakers and add a 46/12.47 kV transformer Construct 5.4 miles of new 46 kV transmission line (795 kcmil ACSR) connecting QP 311 Substation to VEC Lowell 46 kV Substation Construct a 46/34.5 kV substation in Lowell, Vermont (QP 311 Substation) Install twenty-one 3.0 MW Vestas V90 wind turbines equipped with their own dedicated 1000 V/34.5 kV GSU Construct two 34.5kV collector strings connecting the wind turbines with each tying into the QP 311 Substation at 34.5 kV See Section 1.2 for a complete discussion of interconnection details. Steady State Steady state voltage and thermal analyses examined system performance without the proposed Project in order to establish a baseline for comparison. System performance was re-evaluated with the Project and compared with the previous baseline performance to demonstrate the impact of the Project on area transmission reliability under the guidelines of the Network Capability Interconnection Standard (NCIS). Several redispatch conditions under the NCIS were evaluated at each load and transmission operating configuration. Steady state analysis was evaluated at a summer 2013 peak load level of 31,470 MW and at a summer 2013 shoulder load level of 22,024 MW for ISO New England. The shoulder load (D1) dispatch represented the block load being supplied from Hydro Quebec (HQ) and the Highgate HVDC converter at full output to stress the area in an exporting condition. The peak load (D2) dispatch represented the block load being supplied from Vermont and the Highgate HVDC converter out of service to stress the area in an importing condition. Additional sensitivity dispatches were performed at peak load with the Highgate HVDC converter on and the block load supplied from either Vermont or HQ. The objective of modeling these various dispatch scenarios was to examine the proposed Project and the ability of the transmission system to reliably serve customer demand under various stressed system conditions. QP 311 Feasibility Study Final Report July 19, 2010 v Contains Critical Energy Infrastructure Information Based upon the steady state results, the Project as originally proposed posed an adverse impact on the reliability and operating characteristics of the transmission system, and would require transmission system upgrades. For many single element contingencies (K28, K38, K42 and K60) voltage violations of reliability criteria were associated with the Project due to heavy reactive power losses on the 46 kV transmission system and the post-Project transmission configuration. With reactive losses exceeding 20 MVAr along the 46 kV transmission corridor connecting the project to the Jay Tap Switching Station and over 20 MVAr of reactive losses within the Project facilities, the Project generators alone were incapable of providing the reactive support needed to sustain acceptable voltage criteria. Also, the post-Project transmission configuration has the 12W Switch open at N. Troy which removes the reactive support of the Jay Tap Switching Substation shunt capacitors to the Newport area which is deficient in reactive resources when the block load is served by Vermont. Based upon the steady state results, for pre-Project and post-Project dispatches with the block load on Vermont, contingencies involving the loss of the Irasburg 115/46 kV transformer (H39 transformer and K41 Line stuck breaker) resulted in cases diverging due to the loss of voltage support for the Montgomery, Eden Corners and Johnson Substation areas. The reliability issues associated with these contingencies were not addressed in this Feasibility Study. Several system upgrades and project modifications were analyzed to provide necessary system voltage support. The following upgrades and modifications are recommended to reliably maintain system voltage criteria: • • • • • • • Add 4 MVAr dynamic reactive support at the Project’s 34 kV bus The QP 311 46/34.5 kV transformer tapped winding must be modified to the 102.5% tap Increase the size of each of the four planned 2.7 MVAr shunt capacitor banks at the Jay Tap Switching Substation to 5.4 MVAr for a total increase to the system of 10.8 MVAr Provide automatic capacitor bank switching at Jay Tap to maintain reliable 46 kV system voltage (or provide dynamic reactive power control) The Jay Tap Switching Substation 115/46 kV transformer tapped winding must be set to the 97.5% tap Add a 5.4 MVAr cap at the Newport-B2 bus for area voltage support Add a transfer trip scheme to trip the QP 311 units upon loss of 46 kV line or Jay Tap Switching Station 115/46 kV transformer When the Project is dispatched locally under stressed exporting conditions (maximum generation and shoulder load), no thermal reliability issues exist which require mitigation. The 46kV transmission lines between Irasburg and Central Vermont Public Service Company’s Johnson Substation are at thermal capacity by generation in the area following contingencies of the K38 Line (Lyndonville-Sheffield 115kV Line). An additional sensitivity redispatch demonstrated that lowering the Sheffield dispatch with the Project was effective to relieve the loading on the underlying 46 kV transmission system. QP 311 Feasibility Study Final Report July 19, 2010 vi Contains Critical Energy Infrastructure Information Short Circuit Short circuit analysis was performed to determine the fault current levels on the new 46kV transmission system proposed for the Project. The maximum fault duty was approximately 4400A for a three phase to ground fault and 4900A for a single phase to ground fault at the Jay Tap 46kV S/S with the Project in-service. These fault duties are low and should be considered in the engineering design studies for the transmission system upgrades required for the Project. Cost Estimate VEC provided a cost estimate of approximately $1,184k to construct the necessary required network upgrades. The cost projections are based on “installed costs” and do not include the cost for environmental assessment, permitting or temporary facilities required for outage protection. VEC has communicated that subject to receipt of timely regulatory approval, the upgrades can be implemented in time to fit the planned commercial operations schedule for the Project. With the addition of the upgrades listed above to the Project as currently defined, the Project poses no significant adverse impact on the reliability and operating characteristics of the VELCO or VEC transmission systems, the transmission facilities of another Transmission Owner, or the system of a Market Participant. QP 311 Feasibility Study Final Report July 19, 2010 vii Contains Critical Energy Infrastructure Information 1 Background 1.1 Study Objective The primary objective of this Study was to determine if interconnecting QP 311 (the Project) would have significant adverse impact on the reliability and operating characteristics of the VELCO or VEC transmission systems, the transmission facilities of another Transmission Owner, or the system of a Market Participant. Steady state and short circuit conditions were analyzed in this Study. 1.2 Project Description The Project consists of the following proposed electrical components and construction activities: • Split the K41 Line 12.57 miles from Mosher’s Tap end with a three-breaker ring bus and install a new 115/46 kV autotransformer to connect the 46kV Jay Tap Switching Station with the VELCO 115kV transmission system • Install one 46 kV breaker between the Jay Tap Switching Station bus and the 46kV terminal of the autotransformer • Construct a 2 mile 46 kV 795 kcmil ACSR transmission line from the Jay 17 Substation to a tap point (Crossroad) on the existing 46 kV transmission line 2 miles west of the North Troy Substation • Upgrade the existing 46 kV transmission line between Jay Tap Switching Substation and the tap point (Crossroad) to 795 kcmil ACSR • Install three 46 kV Switches at the Crossroad tap point • Upgrade the 34.5 kV Jay 17 Substation to 46 kV and replace the 34.5/12.47 transformer with a 46/12.47 kV transformer • Construct a VEC Lowell 46 kV Substation • Install three 46 kV breakers at VEC Lowell Substation • Install a 46/12.47 kV transformer at VEC Lowell Substation • Upgrade 10.4 miles of transmission line (to 795 kcmil ACSR) from VEC Lowell 46 kV Substation to Jay 17 46kV Substation • Construct a new 46/34.5 kV substation in Lowell, Vermont (QP 311 Substation) • Install one 46 kV breaker at QP 311 Substation • Install twenty-one 3.0 MW Vestas V90 wind turbines equipped with their own dedicated 1.0/34.5 kV GSU (actually 3-wdg but modeled as 2-wdg) • Construct two collector strings connecting the wind turbines with each tying into the QP 311 Substation at 34.5 kV • Construct 5.4 miles of 46 kV transmission line (795 kcmil ACSR) connecting QP 311 Substation to VEC Lowell 46 kV Substation • Install a 34.5 kV breaker on each collector line at the QP311 substation Post-Project, area support for the VEC Lowell Substation and Jay 17 Substation will shift from the VELCO Irasburg # 42 Substation to the new 115/46 kV Jay Tap Substation. However, the existing Montgomery, Eden Corners and Johnson Substations will remain supported out of the VELCO Irasburg #42 Substation. A transmission line which connects the new VEC Lowell 46 kV Substation and existing 46 kV line to Irasburg # 42 Substation for emergency purposes QP 311 Feasibility Study Final Report July 19, 2010 1 Contains Critical Energy Infrastructure Information remained open for the entire Study. In addition, the North Troy substation will be separated from the Jay Tap and Richford 46 kV substations. Figure 1-1 below shows the area transmission configuration pre-Project. Figure 1-2 below shows the transmission configuration post-Project. The Project will be modeled in detail as shown in Appendix C. The Project has a proposed in-service date of October 2012. To Highgate 115 kV To Moshers Tap 115 kV K41 Line North Troy Switch 14W Open Switch 118 closed Jay Tap Switching Station 46 kV Switch 12W Closed To Newport Center To E. Berkshire 2 Miles 2 Miles Switch 12E Closed To Jay Substation #40 Richford Jay 17 Substation 34.5 kV 2.7 MVAr 2.7 MVAr 2.7 MVAr Xfmr 34.5/ 12.47 kV 7.5 MVA 2.7 MVAr Pre Project Configuration VEC / Lowell 34.5 kV Substation Xfmr 34.5/12.47kV To Lowell 12kV To Montgomery / Eden Corners / Johnson Xfmr 46 / 34.5 kV VELCO Irasburg Substation #42 Figure 1-1 Pre Project Simplified One Line Diagram QP 311 Feasibility Study Final Report July 19, 2010 2 Contains Critical Energy Infrastructure Information To Highgate 115 kV Moshers Tap 115 kV K41 Line Xfmr 115 / 46 kV 40 / 66.7 MVA 8.5 % Z Project North Troy Switch 118 closed pre and post Project Jay Tap Switching Station 115 / 46 kV Switch 14W Open pre and post Project 2 Miles To E. Berkshire GSU Switch KCW-E Open Switch 12W Open Post Proj. To Newport Center Crossroad 2 Miles Switch 12E Closed 34.5 / 1.0 kV Richford To Jay (40) Collector #1 M G 2 Miles Switch KCW-W Closed 3.16 MVA* Switch KCW-S Closed Jay 17 Substation 46 kV 2.7 MVAr Eleven units each consisting of 3 MW and -0.875 to 0.609 MVAr* 2.7 MVAr M Kingdom 46 kV Bus GSU 34.5 / 1.0 kV 10.4 Miles 2.7 MVAr 2.7 MVAr Xfmr 46 / 12.47 kV 7.5 MVA 5.4 Miles 3.16 MVA* Collector #2 Xfmr 46 / 34.5 kV 40 / 66.7 MVA 7.5 % Z G Ten units each consisting of 3 MW and -0.875 to 0.609 MVAr* Queue 311 N.O. Xfmr 46 / 12.47 kV 7.5 MVA Xfmr 46 / 34.5 kV 7.5 MVA Substation * Twenty-one units and GSU’s to be modeled in detail and not as an aggregate. Reference Appendix C for detai VEC / Lowell 46 kV Substation To Montgomery / Eden Corners / Johnson To Lowell 12kV VELCO Irasburg #42 Figure 1-2 Post-Project Simplified One Line Diagram 1.3 Technical Specifications The following tables contain data as provided by the developer and ISO for the Project. The installed maximum capability for the Project is 63 MW. Each of the twenty-one 3.0 MW Vestas V90 wind turbines has its own 1.0/34.5 kV GSU and was modeled in detail as shown in Appendix C. 1.3.1 Project Generator Modeling Data The Vestas V90 wind turbine MVAr capability, as provided by the developer, has a power factor range of 0.96 leading (consuming) to 0.98 lagging (generating). The generators were set to operate in power factor control mode. The units were set to a fixed MVAr output that attempted to maintain unity power factor at the point of interconnection (Kingdom 46 kV Bus) while maintaining acceptable area voltages. Table 1-1 below provides the generator operating characteristics. QP 311 Feasibility Study Final Report July 19, 2010 3 Contains Critical Energy Infrastructure Information QP 311 Generator Modeling Data Type MVA PF range MW Vestas V90 wind turbine 3.06 -0.96 to 0.98 3.0 MVAr Capability Leading / Lagging / Consuming Generating 0.875 0.609 Table 1-1 QP 311 Generator Modeling Data 1.3.2 Project Transformer Modeling Data Table 1-2 below summarizes the data required to model the Project transformers. The interconnection and GSU transformers are fixed tap transformers with a range of +2 x 2.5%. Transformer GSU Interconnection Transformer at QP 311 Transformer at Jay Tap Switching Station Jay 17 SS VEC Lowell SS QP 311 Transformer Data Nameplate Capacity Tap Ratio Present Tap (MVA) 34.5/1.0 Center 3.16 102.5% 46/34.5 40/53.3/66.7 R (pu) X (pu) 0.0065 0.0948 0.0022 0.0750 40/53.3/66.7 0.0025 0.0850 46/12.47 Center 7.5/9.3 46/12.47 Center 7.5/9.3 Table 1-2 QP 311 Transformer Modeling Data 0.0050 0.0050 0.0700 0.0700 (High Side) 115/46 97.5% (High Side) 1.3.3 Project Transmission Line Modeling Data Table 1-3 and Table 1-4 summarize the modeling data for the transmission lines for the Project. Transmission line ratings were determined using available reference data. QP 311 Transmission Line Data Length MVA Transmission Line Conductor (Miles) Rating QP 311 SS to Lowell SS 795 KCMIL ACSR 5.40 76 VEC Lowell SS to Jay 17 SS 795 KCMIL ACSR 10.40 76 Jay 17 SS to Crossroad tap point (pole #155) on existing 46 kV line 2miles west 795 KCMIL ACSR 2.0 76 of North Troy SS Crossroad tap point (pole #155) to Jay 795 KCMIL ACSR 2.0 76 Tap Switching SS Table 1-3 QP 311 Transmission Line Modeling Data QP 311 Feasibility Study Final Report R (pu) X (pu) 0.0367 0.1598 0.0707 0.3078 0.0134 0.0602 0.0134 0.0602 July 19, 2010 4 Contains Critical Energy Infrastructure Information From To Gen 1 Gen 2 Gen 3 Gen 4 JB-1 Gen 5 JB-2 Gen 6 JB-3 Gen 7 Gen 8 Gen 8 Gen 9 Gen 10 JB-4 Coll Isol Coll Tap Gen 2 Gen 3 JB-1 JB-1 JB-2 JB-2 JB-3 JB-3 Coll Tap JB-4 JB-4 Gen 9 Gen 10 Gen 11 Coll Isol Coll Tap KCW 34 From To Coll 2 Tap Gen 12 Gen 13 Gen 14 Coll 2 Tap JB3-3 JB3-3 JB3-2 JB3-2 JB3-1 JB3-1 Gen 19 Gen 20 Coll 2 Tap Gen 12 Gen 13 Gen 14 Gen 15 JB3-3 Gen 16 JB3-2 Gen 17 JB3-1 Gen 18 Gen 19 Gen 20 Gen 21 KCW 34 QP 311 Collector 1 Data Length Conductor Type (FT) 1/0 AWG 800 1/0 AWG 1000 1/0 AWG 1600 1/0 AWG 200 500 KCMIL 820 1/0 AWG 200 500 KCMIL 810 500 KCMIL 200 750 KCMIL 200 1/0 AWG 200 500 KCMIL 1200 1/0 AWG 800 1/0 AWG 810 1/0 AWG 950 500 KCMIL 300 795 KCMIL DRAKE 300 795 KCMIL DRAKE 5800 QP 311 Collector 2 Data Length Conductor Type (FT) 500 KCMIL 500 1/0 AWG 900 1/0 AWG 850 1/0 AWG 820 500 KCMIL 3150 1/0 AWG 200 500 KCMIL 810 1/0 AWG 200 500 KCMIL 810 1/0 AWG 200 1/0 AWG 1000 1/0 AWG 850 1/0 AWG 825 795 KCMIL DRAKE 6800 MVA R (pu) X (pu) 10.0 10.0 10.0 10.0 23.4 10.0 23.4 23.4 28.4 10.0 23.4 10.0 10.0 10.0 23.4 70 70 0.0147 0.0184 0.0294 0.0037 0.0044 0.0037 0.0044 0.0011 0.0009 0.0037 0.0065 0.0147 0.0149 0.0175 0.0016 0.0007 0.0128 0.0065 0.0082 0.0130 0.0016 0.0048 0.0016 0.0048 0.0012 0.0010 0.0016 0.0071 0.0065 0.0066 0.0077 0.0018 0.0029 0.0562 MVA R (pu) X (pu) 23.4 10.0 10.0 10.0 23.4 10.0 23.4 10.0 23.4 10.0 10.0 10.0 10.0 70 0.0027 0.0166 0.0156 0.0151 0.0169 0.0037 0.0044 0.0037 0.0044 0.0037 0.0184 0.0156 0.0152 0.0151 0.0029 0.0073 0.0069 0.0067 0.0185 0.0016 0.0048 0.0016 0.0048 0.0016 0.0082 0.0069 0.0067 0.0658 Table 1-4 QP 311 Collector String Modeling Data QP 311 Feasibility Study Final Report July 19, 2010 5 Contains Critical Energy Infrastructure Information 2 Study Area 2.1 Transmission System The primary area of concern for this study is the northwestern portion of VEC’s service territory as shown in Figure 2-1 below. The sub transmission system in this area is heavily networked. The Project interconnects into the sub transmission system near the North Troy 46 kV Substation and also ties into the K41 115 kV transmission line between Highgate and Moshers tap. The Project is connected by a radial 46 kV Line as shown above in Figure 1-2 Project Interconnection Project Location Figure 2-1 Project Geographical Map QP 311 Feasibility Study Final Report July 19, 2010 6 Contains Critical Energy Infrastructure Information 3 Base Case Development 3.1 Base Case Origin and Year The base case originated from VELCO and included a model of VELCO’s sub-transmission system. The base case was revised to reflect proposed area projects. 3.2 Area Load Using the NEPOOL 2009 Capacity, Energy, Load and Transmission (CELT) Report and the methodology described in Appendix B –1, steady state analyses using a 2013 peak load forecast of 31,470 MW and a 2013 shoulder load forecast of 22,024 MW were completed. 3.3 Planned Projects The following list of planned facilities was present in the base case received from VELCO: • Comerford QP 148 • Sheffield Wind Project QP 172 • Swanton Project QP 224 • Lyndonville Station The following list of planned facilities was added to the base case received from VELCO: • Wind QP 166 (Q195 now a three-terminal line with section to Littleton closed) • Biomass Project QP 229 • Biomass QP 251 • Biomass QP 307 • Lyndonville Transmission Project Capacitors • Vermont Southern Loop transmission Project • QP 274 3.4 Base Case Naming Convention Steady State base case designations were formatted as follows: QP 311 Feasibility Study Final Report July 19, 2010 7 Contains Critical Energy Infrastructure Information pk13_ p1_dx Dispatch Identifier D1 = Highgate On D2 = Highgate Off Project Identifier p0 = Project out of service p1 = Project in service Load Level Identifier PK = peak load SH = shoulder load Followed by load model year Figure 3-1 Steady State Base Case Naming Convention Several cases were developed for the Study at a summer 2013 peak load level of 31,470 MW and at a summer 2013 shoulder load level of 22,024 MW for ISO New England. Dispatch D1 - The shoulder load (D1) dispatch represented the block load being supplied from HQ and the Highgate HVDC converter at full output to stress the area in an exporting condition. Dispatch D2 - The peak load (D2) dispatch represented the block load being supplied from Vermont and the Highgate HVDC converter was analyzed out of service to stress the area in an importing condition. Sensitivity Dispatch 3- The peak load (D3) dispatch represented the block load being supplied from Vermont and the Highgate HVDC converter at full output. Sensitivity Dispatch 4- The peak load (D4) dispatch represented the block load being supplied from HQ and the Highgate HVDC converter at full output to stress the K42 Line. The objective of modeling these various dispatch scenarios was to examine the proposed Project and the ability of the transmission system to reliably serve customer demand under various stressed system conditions. 3.5 Voltage Operational Analysis The Study included an accurate and detailed model of the Project. All collector branches, individual high and low-voltage busses for the wind generators and GSU's were modeled using the configurations, network impedances, unit reactive capabilities and facility ratings provided. The detailed model allowed analysis of real and reactive power flows and losses across individual elements of the Project and made it possible to accurately test and monitor particular QP 311 Feasibility Study Final Report July 19, 2010 8 Contains Critical Energy Infrastructure Information voltage control strategies. Being able to monitor the terminal voltage at each individual wind turbine generator made it possible to ensure units at the end of the collector strings remain within voltage limits. The Project was adjusted (upgrades were added) to compensate for the reactive losses of its collector system and interconnection facilities. The Study concluded that by adding a 4 MVAr dynamic reactive device at the Project’s 34kV bus for voltage control and setting the winding of the QP 311 46/34.5 kV transformer tap to 102.5% of nominal allowed voltages at the Project collector strings and generator buses to be maintained within criteria for area contingencies (Loss of K42, K41W and K38 Lines) which otherwise resulted in voltages outside criteria. 3.6 Analytical Tools A steady state analysis was performed using the GE Power Systems, PSLF load flow software package, Version 17. Short-circuit analyses were completed using the Aspen One Liner Program. 4 Steady State Analysis Methodology Steady state thermal and voltage analyses examined system performance without the proposed Project in order to establish a baseline for comparison. System performance was then reevaluated with the Project and compared with the previous baseline performance to demonstrate the impact of the Project on area transmission reliability. 4.1 Steady State Voltage Limits Table 4-1 identifies the voltage criteria used by VELCO in the primary Study area for steady state voltage assessment. Acceptable Voltage Range Voltage Class 230 kV and above Pre-Contingency (Normal Conditions) 0.98 to 1.05pu Post-Contingency (Emergency Conditions) 0.95 to 1.05pu 115 kV 0.95 to 1.05pu 0.95 to 1.05pu Below 115 kV 0.95 to 1.05pu 0.90 to 1.05pu Table 4-1 Steady State Voltage Criteria 4.2 Steady State Thermal Limits Table 4-2 contains the thermal loading performance criteria applied to transmission lines and transformers in the Study. QP 311 Feasibility Study Final Report July 19, 2010 9 Contains Critical Energy Infrastructure Information System Condition Time Interval Maximum Allowable Facility Loading Pre-Contingency (all lines in) Continuous Normal Rating Post-Contingency Less than 15 minutes after contingency occurs More than 15 minutes after contingency occurs Short Time Emergency (STE) Rating Long Time Emergency (LTE) Rating Table 4-2 Steady State Thermal Criteria 4.3 Steady State Base Case Dispatch and Interface Conditions Two load dispatches were analyzed for the study. • D1 - Shoulder Load with Highgate on at 210 MW and the block load shifted to HQ to create a maximum export condition • D2 - Peak Load with Highgate off and the block load on Vermont. Additional sensitivity dispatches were also performed at peak load with Highgate on and the block load on either Vermont or HQ. For the Study, four base cases were developed to analyze the impact of the Project on area reliability under stressed system conditions. Case A - Pre-Project (No Jay Tap 115/46 kV Substation) Case B - Project On-Line with no redispatch Case C - Project On-Line with redispatch against remote generation (Western Massachusetts) Case D - Project On-Line with redispatch against local generation (Sheffield and Swanton) Table 4-3 identifies these dispatch scenarios. QP 311 Feasibility Study Final Report July 19, 2010 10 Contains Critical Energy Infrastructure Information Dispatch 2 (Peak Load) Generator Dispatch 1 (Shoulder Load) B C* D* 99 29 71 667 42 121 144 19 8 0 0 63 210 130 A - Pre Project * 99 29 71 667 42 161 144 40 8 3 42 0 0 / 210* 130 99 29 71 667 42 161 144 40 8 3 42 63 0 130 99 29 71 667 42 161 144 40 8 3 42 63 0 / 210* 130 99 29 71 667 42 161 144 19 8 3 0 63 0 / 210* 130 9 9 9 9 9 9 3 3 3 3 3 3 6.5 3 6.5 3 6.5 3 6.5 3 14 14 14 14 14 14 14 14 66 66 3 66 66 66 3 66 A - Pre Project B C D Wind (QP 166) Biomass (QP 229) Biomass (QP 251) Vermont Yankee Gorge (QP 274) Moore Comerford Wind (QP 172) Coventry Barton Swanton GT QP 311 Highgate PV 20 Highgate Falls (Swanton Hydro) Sheldon Springs Hydro Fairfax Hydro Lower Lamoille (Peterson, Milton, Clark Falls) 99 29 71 667 42 121 144 40 8 0 42 0 210 130 99 29 71 667 42 121 144 40 8 0 42 63 210 130 99 29 71 667 42 121 144 40 8 0 42 63 210 130 9 9 3 3 Altresco (W. Mass) Base Case * Sensitivity with Highgate on and block load either on Vermont or HQ Table 4-3 Local Area Dispatches Detailed interface transfer and dispatch summaries for each of the baseline cases are included in Appendix E. Draw files representing the baseline cases are included in Appendix F. 4.4 Steady State Contingency List The original contingency file provided by VELCO was reviewed and modified for the Study. Contingency analysis was conducted with approximately 50 contingencies encompassing single element, transformer, generation and 115kV stuck breaker outages within the northwestern portion of Vermont’s transmission system. The Highgate Special Protection System (SPS) is always enabled (armed) and its action is modeled as appropriate in the contingencies listed in Appendix D. When the flow through the Highgate HVDC converter is from Quebec to Vermont, the SPS will reduce the converter import into Vermont to a pre-specified level (usually 150 MW) for loss of any of the following Lines: QP 311 Feasibility Study Final Report July 19, 2010 11 Contains Critical Energy Infrastructure Information • • • • • Georgia – Sandbar (K19 Line) Georgia – Essex (K21 Line) Sandbar – Essex (K22 Line) Sandbar – So. Hero – Plattsburgh (PV-20 line) Essex – Williston (K23) and Essex - Berlin (K24) o If the K23 or K24 line is out of service, loss of the other line will cause runback to the pre-specified level Contingencies annotated with RB* include the Highgate SPS to model the runback. For this study it is assumed that a transfer trip scheme will be in place to trip the QP 311 units upon loss of the transmission line connecting QP 311 (VEC Lowell) 46 kV Substation to Jay 17 46 kV Substation or loss of the Jay Tap 115/46 kV transformer. Appendix D provides a listing of the contingencies used in the Study. 5 Steady State Analysis Results 5.1 Baseline System 5.1.1 Voltage Performance Baseline System – All Lines In Under shoulder load conditions, steady state voltage analysis reported no violations of reliability criteria for the baseline with all lines in-service for any of the base cases. Under peak load conditions in Dispatch 2 (including sensitivity dispatches), steady state voltage analysis reported violations of normal criteria (less than 95%) for the baseline with all lines inservice for 46kV buses in several Vermont load regions. During peak load conditions with the block load supported by Vermont, the area has insufficient transmission voltage regulation and reactive resources to maintain voltages above the normal criteria. These voltage issues are mainly distributed throughout the underlying 46kV and 34kV subtransmission networks. Baseline System – Post Contingency Under shoulder load conditions in Dispatch 1, post-contingency voltage analysis reported no violations of reliability criteria for the baseline with one exception, the Stowe DCT contingency which causes loss of 115kV and 34.5 kV lines supporting the Stowe area. Under peak load conditions in Dispatch 2 (and sensitivity dispatch 3) with the block load on Vermont and Highgate offline, contingencies involving loss of the Irasburg 115/46 kV H39 transformer resulted in solutions diverging due to the loss of voltage support for the Montgomery, Eden Corners and Johnson Substation areas. Under peak load conditions in Dispatch 2 with the block load on Vermont and Highgate offline, post-contingency steady state voltage analysis reported violations of reliability criteria (less than 90%) for multiple contingencies. The following contingencies listed in Table 5-1 resulted in QP 311 Feasibility Study Final Report July 19, 2010 12 Contains Critical Energy Infrastructure Information voltages below criteria in the baseline pre-Project cases. The Barre 34.5 kV capacitor bank is available but offline based on the switching criteria in the study methodology. Outage Barre X63 Xfmr D-204 K19 K19_RB K28 K28_Stuck Bkr K38 K42 K60 Stowe Stowe DCT Fairfax X67 Xfmr Violations kV Barre / Granite Area Busses Newport / Wenlock Area Busses East Fairfax / Sandbar Area Busses East Fairfax / Sandbar Area Busses Newport / Richford / Wenlock Area Busses Newport / Richford / Wenlock Area Busses Newport / Richford / Wenlock Area Busses Newport / Wenlock Area Busses Newport / Richford / Wenlock Area Busses Area Busses Between Johnson and Middlebury Area Busses From Newport Through Middlebury East Fairfax Area Busses Ashland/Beebe Case Diverged with Block on Vermont Case Diverged with Block on Vermont 34.5 46 34.5 34.5 46 46 46 46 46 34.5 115 - 34.5 34.5 34.5 U199/X178 Irasburg H39 Xfmr K41 Stuck breaker Table 5-1 Peak Load Contingencies Resulting in Voltage Violations Pre-Project Reliability issues associated with these contingencies were not addressed in the Study. In the Sensitivity Dispatch 3 with Highgate online and block load on Vermont the following differences were seen from the D2 dispatch which had Highgate offline: o The D-204 Line remained within voltage criteria o The K42 Line outage resulted in voltages above the 105% criteria for the East Fairfax and VEC Pleasant Valley buses In the Sensitivity Dispatch 4 with Highgate online and block load on HQ the following differences were seen from the D2 dispatch which had Highgate offline and the block load on Vt: o The D-204 Line remained within voltage criteria o The K28 Line contingency resulted in voltages just above the 105% criteria for the Sheffield area o The K41 stuck breaker and Jay SS 40 transformer contingencies resulted in voltages above the 105% criteria for the Irasburg area o The K42 Line outage resulted in voltages above the 105% criteria for the East Fairfax and VEC Pleasant Valley buses o The Richford Transformer contingency resulted in voltages above the 105% criteria for the Jay area 5.1.2 Thermal Performance Baseline System – All Lines In Under both shoulder and peak load conditions (including sensitivity dispatches), steady state thermal analysis reported no violations of reliability criteria for the baseline with all lines inservice. In Dispatch 1 with shoulder load and maximum generation, the Littleton to Comerford QP 311 Feasibility Study Final Report July 19, 2010 13 Contains Critical Energy Infrastructure Information D204 Line is near 100% of its normal rating which confirms the Northern Vermont and New Hampshire 115 kV areas are at their maximum export limit. Baseline System – Post Contingency Under both peak and shoulder load conditions, steady state thermal analysis reported violations of reliability criteria for the baseline system post contingency. These violations are pre-existing thermal overloading concerns. Under Dispatch 1 for shoulder load conditions, loss of the Barre 115/34 kV X63 transformer resulted in overloading the Berlin to Mountain View 34 kV line, which is outside the local study area. The U-199/X-178 contingency overloaded the 230 kV Comerford to Littleton D204 Line to 105.9% and the 115 kV Littleton to Q195 Tap line to 104.8 % of their LTE ratings. Loss of the K21 overloads the 115 kV Sandbar to Essex K22 Line to 102.6% of its LTE rating, which is mitigated by the Highgate Runback SPS. Under Dispatch 2 peak load conditions (including the sensitivity dispatches with Highgate online and the block load on either Vermont or HQ), loss of the Barre 115/34 kV X63 transformer and F206 Line resulted in overloading 34.5 kV circuits in central Vermont, which are outside the local study area. For the K19 and Fairfax 115/34 kV X67 transformer contingencies, overloads involving the 34 kV Nason St to Nason V line were reported. Additionally the St Albans 115/34 kV transformer contingency overloads the parallel St Albans to Nason 115-34 kV transformer. For the Sensitivity Dispatch 4 with Highgate online and the block load on HQ, loss of the F206 Line also resulted in loading the Lowell VEC to VEC 21 Tap line to just over 100% LTE. 5.2 QP 311 In-Service When the Project is in service approximately 42 MVAr in reactive power losses were reported. These losses occur from the Jay Tap Switching Station to the point of interconnection and include the Project collector strings and transformer losses. Table 5-2 demonstrates where the losses occur for QP 311. Location MVAr Loss Jay Tap Switching Station to VEC Lowell 46 kV Line Losses Project Interconnection 46 kV Line Losses Project Collector, Project 46/34.5 Transformer and GSU Losses Total Reactive Power Losses 21.4 6 14.3 41.7 Table 5-2 Losses Due to Addition of Q311 Project As discussed in Section 1.3, the Vestas V90 units are capable of providing approximately 0.6 MVAr per machine for a total of almost 13 MVAr for the entire wind farm. Along with the addition of a 4 MVAR dynamic reactive device as discussed in Section 3.5, the Project compensates for less than half of the total increase in losses when the Project is at full output. Another change impacting voltage/reactive power performance with the Project is the change in the 12W switch position at North Troy to Normally Open. With the 12W open, the four 2.7 MVAr capacitor banks at Jay Tap Switching Station are isolated from the Newport area which QP 311 Feasibility Study Final Report July 19, 2010 14 Contains Critical Energy Infrastructure Information exacerbates the low voltage conditions in Dispatch 2 under peak load conditions with Vermont serving the block load in the Newport area. With the 12W open after the Project, reactive support was added at the Newport 46 kV bus to help alleviate these low voltages. The addition of a 5.4 MVAr capacitor bank at the Newport-B2 bus brought bus voltages within the immediate Newport area above pre-Project levels as demonstrated in Table 5-3. Newport Area Voltages Post-Project Pre Project Before Newport Newport B-2 46 kV S Bay2 46 kV Coventry 46 kV Moshers Corner 46 kV Newport2 46 kV N. Troy 46 kV 0.94pu 0.94pu 0.92pu 0.95pu 0.95pu 0.95pu Post-Project Cap 5.4MVAr Shunt at Newport 46 kV 0.91pu 0.92pu 0.92pu 0.92pu 0.92pu 0.92pu 0.96pu 0.96pu 0.96pu 0.96pu 0.96pu 0.96pu Table 5-3 Newport Area Pre Contingency Voltages Under peak load conditions, steady state voltage analysis reported violations of reliability criteria post contingency with the Project as originally proposed. Loss of the K42 resulted in the case solution diverging due to voltage collapse. This demonstrated the need for additional reactive resources in order to alleviate the reactive losses resulting from the Project. Additional shunt capacitors were evaluated at VEC Lowell 46 kV substation as well as at Jay Tap substation. Adding an additional 10.8MVAr of shunt capacitors at the Jay Tap Switching Station maintained voltages within criteria for the K42 contingency as demonstrated in Table 5-4. A 5.4MVAr capacitor at VEC Lowell 46 kV substation did not maintain reliability criteria for loss of the K42 Line. The recommendation for the Project is to increase the four 2.7 MVAr capacitor banks to 5.4 MVAr capacitor banks. This could be accomplished by adding or changing capacitor cans in each bank. K 42 Contingency Loss of Highgate – St. Albans - Georgia Post-Project Post-Project Pre-Project Highgate 115 kV Jay Tap Switching 115 kV Moshers Tap 115 kV Irasburg 115 kV Jay Tap Switching 46 kV VEC Lowell 46 kV Kingdom 46 kV 0.96pu N/A 0.98pu 0.99pu 0.93pu N/A N/A Post-Project No Additional Shunt Capacitor VEC Lowell 46 kV or Jay Tap 115/46 kV SS Additional 5.4 MVAr Shunt Capacitor VEC Lowell 46 kV SS Additional 10.8 MVAr Shunt Capacitor Jay Tap 115/46 kV SS Case Diverged 0.94pu 0.95pu 0.97pu 0.97pu 1.0pu 1.0pu 1.0pu 0.97pu 0.99pu 1.0pu 1.0pu 1.0pu 1.0pu 1.0pu Table 5-4 Additional Capacitors for K42 Contingency QP 311 Feasibility Study Final Report July 19, 2010 15 Contains Critical Energy Infrastructure Information Table 5-5 demonstrates the reactive compensation proposed for the Project. These upgrades are in-service for all the analyses performed with the Project in-service. Amount (MVAr) Increase Jay Tap Capacitors 4 2.7 Newport 34 kV Capacitors 1 5.4 Generator capability 21 0.609 DVAR 1 ±4.0 Additional Reactive Compensation Location # of Devices Total MVAr 10.8 5.4 12.8 ±4.0 25 to 33.0 Table 5-5 Reactive Compensation Proposed for the Project 5.2.1 Voltage Performance QP 311 – All Lines In Under shoulder load conditions, steady state voltage analysis reported no violations of reliability criteria for the Project configuration with all lines in-service. Under peak load conditions, steady state voltage analysis reported violations of reliability criteria for the Project configuration with all lines in-service for several 46 kV buses. These violations were seen pre-project and the addition of the Project and associated upgrades do not aggravate these low voltage conditions. QP311 – Post Contingency In all dispatches, loss of the 46 kV transmission line from Jay Tap Switching Station to the Project results in high voltages for the remaining substations connected to Jay Tap 46 kV Substation. Voltages of 1.10pu occur and would require post-contingency automatic capacitor switching. Table 5-6 demonstrates the amount of shunts needed to be tripped for acceptable voltage criteria in the shoulder load D1 dispatch. The application of a dynamic reactive device at Jay Tap 46 kV Substation may be needed to control the temporary high-voltage condition based on the Transmission Owner’s design criteria. Also in Dispatch 1, the Stowe DCT remains unacceptable but closely matches the pre-Project results. Post Contingency Capacitor Switching at Jay Tap Switching SS Jay Voltage Rich Voltage Device Tripped Jay Tap Switching Voltage 1.10pu 1.10pu None 1.11pu 1 Bank of 5.4MVAr 1.09pu 1.09pu 1.08pu 2nd Bank of 5.4MVAr 1.07pu 1.06pu 1.06pu 3rd Bank of 5.4MVAr 1.05u 1.04pu 1.04pu All Banks 1.03pu 1.03pu 1.02pu Table 5-6 Post Contingency Capacitor Switching at Jay Tap Switching SS Under the Dispatch 2 peak load cases (including the sensitivity dispatches), a significant number of voltage reliability criteria violations exist as seen in the pre project case. The results clearly demonstrate that the Project does not significantly impact the area reliability under this dispatch and load condition. QP 311 Feasibility Study Final Report July 19, 2010 16 Contains Critical Energy Infrastructure Information Under Dispatch 2 peak load dispatch conditions with the block load on Vermont and Highgate offline, contingencies involving loss of the Irasburg 115/46 kV H38 transformer resulted in solutions diverging due to the loss of voltage support for the Montgomery, Eden Corners and Johnson Substation areas. This is a pre-Project condition and the Project as configured has no affect. 5.2.2 Thermal Performance In the three base cases with the Project, two scenarios (Case B and C) were developed with no redispatch in the local area. The third scenario (Case D) was developed with a local redispatch with Swanton removed and Sheffield reduced. Refer to Table 4-3 for specific details. The reasons for including the analysis with multiple redispatch conditions were to determine if local congestion exists and whether the local units used in the redispatch cases were critical to support of load in the various northern Vermont load pockets. By having multiple redispatch cases, the analysis was able to distinguish between an adverse impact and local reliability dependencies on specific generation. QP 311 – All Lines In Under Dispatch 1 for shoulder load conditions, steady state thermal analysis reported violations of reliability criteria for the Project in-service configuration when the project was not redispatched with local generation (Cases B and C). In this scenario excess generation in the area occurs and the Comerford to Littleton Tap D204 line overloads to 108% of the normal rating. This is related to area dispatch and is not experienced when local generation is dispatched off to accommodate the Project (Case D). Therefore, local area congestion may require restrictions of generation during off-peak load periods. Under Dispatch 2 for peak load conditions (including the sensitivity dispatches), steady state thermal analysis reported no violations of reliability criteria for the Project configuration with all lines in-service. QP 311– Post Contingency Under Dispatch 1 for shoulder load conditions, loss of the Barre 115/34 X63 transformer resulted in overloads outside the local study area. Other contingencies including loss of the U-199/X-178 Line, B202 Line, K21 Line, K38 Line, K39 Line and K42 Line all resulted in overloading in the study area when the project was not redispatched with local generation (Cases B and C). This is related to area dispatch and is not experienced when local generation is dispatched off to accommodate the Project (Case D). Therefore, local area congestion may require restrictions of generation during off-peak load periods. Under Dispatch 1 for shoulder load conditions, reported loadings increased with the Project for the K38 contingency with local generation dispatched off (Case D). With the Project, some load at Lowell and Jay 17 is transferred to the new 46 kV line that interconnects the Project to the Jay Tap Switching Station. This configuration change combined with generation from the Project and remaining Sheffield generation online results in higher flows on the 46 kV transmission lines between Irasburg and CVPS Johnson Substations. An alternative redispatch with Sheffield offline and Swanton at partial output showed lower loadings on this path. No upgrades are recommended since loading was below the emergency rating and an alternative redispatch scenario relieved the congestion issue. QP 311 Feasibility Study Final Report July 19, 2010 17 Contains Critical Energy Infrastructure Information Under Dispatch 2 for peak load conditions (Highgate off and block load on Vermont), when area generation was dispatched off (Case D) to accommodate the Project, the K19, K19 with runback (RB), St Albans 115/34 kV transformer (X61 or X64) and East Fairfax 115/34 kV transformer (X67) contingencies resulted in higher overloads on the Nason V - St Albans and the Nason St Nason V transmission lines. This is a result of peak load conditions, lack of area generation and Swanton generation reductions. The overloads were similar when local generation was not redispatched to accommodate the Project (Cases B and C). Under the Sensitivity Dispatch 4 (block load being supplied from HQ and the Highgate HVDC converter at full output to stress the K42 Line) when area generation was not dispatched off to accommodate the Project the K38 contingency resulted in the Highgate-St Albans 115kV Line (K42) exceeding LTE rating. Redispatching local area generation (Case D) relieves the loading on the K42. 6 Short Circuit Analysis Short circuit studies were conducted to assess the impact of the Project on fault current levels within the VELCO area. The twenty-one VESTAS wind turbine generators were represented as two separate aggregate machines consisting of eleven and ten units. The wind generators were modeled as an equivalent synchronous generator per manufacturer’s technical manuals. The subtransient impedance is used for short-circuit fault calculations from the wind generators. The generator step-up transformers (GSU’s) were also modeled as two sets of aggregates by multiplying the base MVA by the number of corresponding units to obtain the new MVA rating; the per-unit impedance is the same for the aggregate as for a single transformer. The Kingdom 46/34.5 kV transformer, along with the collector string impedance was modeled as described in Table 1-2 and Table 1-4. The transformer was modeled as a grounded wye – delta with the 34.5 kV side being grounded as per the preliminary one line in Appendix C. The 115 / 46 kV Jay Tap transformer was modeled as a three winding wye – wye with a delta tertiary as per VELCO’s typical installation and as described in Table 1-2. One line drawings indicate the voltage for many of the buses as 46 kV. The supplied ASPEN model has these same buses modeled as 48 kV. Line impedances were entered as per unit values based on the 48 kV base of the ASPEN model. Following VELCO’s short-circuit analysis guidelines, faults were simulated with an assumed pre-fault voltage “Flat” option, with 1.05 p.u. voltage. For X/R calculations where X was not defined, a value of X = 0.0001 p.u. was used. For calculations where R was not defined, the ANSI X/R ratio was used assuming R = max( X / g , Rc ) with Rc = 0.0001pu and g = 125 for generators, 40 for transformers, and 10 for all others. Aspen Oneliner Version 11.5 program was utilized to determine short circuit values. The below gives a comparison of the short-circuit fault duties of affected buses and includes the fault duties with and without the Project in service. QP 311 Feasibility Study Final Report July 19, 2010 18 Contains Critical Energy Infrastructure Information Without Kingdom Wind Generation Bus Fault Location Bus Voltage (kV) Three Phase ANSI X/R Jay Jay Tap Jay 17 VEC/Lowell Kingdom Kingdom 115 48 48 48 48 34.5 3001 3263 2527 1592 1335 1552 5.4 10.1 7.9 6.2 5.8 6.8 With Kingdom Wind Generation Delta Amps Three Single Single Three Single ANSI X/R ANSI X/R ANSI X/R Phase Phase Phase Phase Phase 2870 3924 2746 1651 1159 2150 5.1 10.2 5.5 4 4.4 7.2 3396 4390 3782 3357 3569 6218 5.7 9.4 8.1 8.5 11.3 14.3 3090 4888 3563 2530 1772 6342 5.2 9.8 5.1 3.7 4.4 16.6 395 1127 1255 1765 2234 4666 220 964 817 879 613 4192 Table 6-1 Kingdom Community Wind Short-circuit Fault Duties Fault duties are low and should be considered in engineering design studies of the new 46 kV transmission system supporting the Project. No issues at these levels are expected. 7 Delta V on Capacitor Switching With the recommended change in capacitor size following the addition of the Project, a study was conducted to determine the relative change in voltage (Delta – V) on capacitor switching. Based on the available short-circuit duty listed in Table 6-1 above, the short-circuit MVA at the Jay Tap 46 kV bus without the Project is 260 MVA. Therefore, the maximum capacitor size to remain within 3% voltage change is 7.8 MVAr. The largest capacitors to switch at Jay Tap is 5.4 MVAr and within the acceptable range. The 5.4 MVAr capacitors will have an expected DeltaV of 2%. 8 Cost Estimates for Required Network Upgrades The following is a cost estimate provided by VEC to construct the necessary required network upgrades. The cost projections are based on “installed costs” and do not include the cost for environmental assessment, permitting or temporary facilities required for outage protection. VEC has communicated that subject to receipt of timely regulatory approval, the upgrades can be implemented in time to fit the planned commercial operations schedule for the Project. 1. Increase from 4 x 2.7MVAr 46kV capacitor bank at the Jay Tap station to 4 x 5.4MVAr bank and associated switching equipment for voltage control. Assume 2 switches per 5.4MVAr capacitor rack (3 switches for 10.8MVAr with CB switching one stage of fixed 2.7MVAr) and 2.7MVAr per layer allowing for the switching on and off of 2.7MVAr of capacitors incrementally if required. Material: $260k (based on VEC Jay Switching Station quote for 10.8MVAr bank) to include 2 switches and 10.8MVAr of capacitors less the estimated cost of 2 steel racks. $100k for 2 additional switches per breaker bay x 2 = $200k. Total Material: $460k. Estimated Labor: $50k. Total Estimated Cost + 20% contingency: $612k. 2. Addition of a 5.4MVAr capacitor at the 46kV Newport-B2 bus. Based on a single 5.4MVAr capacitor bank for VEC Jay Switching Station material. Material: $143k for 1 switch and 5.4MVAr capacitors including the cost of two steel racks each with 2.7MVAr of capacitors on first layer (expandable to 5.4MVAr per rack by installing additional 2.7MVAr of capacitors on second layer). $60k for vacuum circuit QP 311 Feasibility Study Final Report July 19, 2010 19 Contains Critical Energy Infrastructure Information breaker. Misc relays, interconnection materials: $40k. Total Material: $243k. Estimated Labor: including concrete foundations and substation additions to accommodate the capacitor bank: $150k. Total Estimated Cost + 20% contingency: $472k. 3. A protection scheme to trip the wind farm upon loss of the 46kV line or Jay Tap station 115/46kV transformer. Assuming the use of Schweitzer relays, Transfer Trip systems can be easily employed over the planned Project communications and fiber optic cable upgrades. Transfer trip of the wind farm due to a loss of the 46 kV line and/or loss of the 115/46 kV transformer could be designed and implemented at an incremental cost not to exceed $100,000. 9 Conclusion Based upon the steady state results, the Project as originally requested posed significant adverse impact on the reliability and operating characteristics of the transmission system, and would require additional transmission system upgrades. For many single element contingencies (K28, K38, K42 and K60) voltage violations of reliability criteria were associated with the Project and the post-Project transmission configuration. Significant reactive losses occur along the 46 kV transmission corridor connecting the project to the Jay Tap Switching Station. The Project generators alone were incapable of providing the MVAr needed to sustain acceptable voltage criteria. Also, post-Project transmission configuration has the 12W Switch open at N. Troy which removes the reactive support of the Jay Tap Switching Substation shunt capacitors to the Newport area. Several system upgrades and project modifications were analyzed to provide necessary system support. The following upgrades and modifications are recommended to maintain system voltage criteria: • • • • • • • Add 4 MVAr dynamic reactive support at the Project’s 34 kV bus The QP 311 46/34.5 kV transformer tapped winding must be modified to the 125% tap Increase the size of each of the four 2.7 MVAr shunt capacitor banks at the Jay Tap Switching Substation to 5.4 MVAr for a total increase to the system of 10.8 MVAr Provide automatic capacitor bank switching at Jay Tap to maintain reliable 46 kV system voltage (or provide dynamic reactive power control) The Jay Tap Switching Substation 115/46 kV transformer tapped winding must be set to the 97.5% tap Add a 5.4 MVAr cap at the Newport-B2 bus for area voltage support Add a trip scheme to trip the QP 311 units upon loss of 46 kV line or Jay Tap Switching Station 115/46 kV transformer When the Project is dispatched locally under stressed exporting conditions (maximum generation and shoulder load), no thermal reliability issues exist which require mitigation. The Study concluded that by adding a 4 MVAr DVAR at the Project’s 34 kV bus for dynamic reactive capability and voltage support and adjusting the QP 311 46/34.5 kV transformer tap to QP 311 Feasibility Study Final Report July 19, 2010 20 Contains Critical Energy Infrastructure Information 1.025 maintained the project collector strings and generator bus voltages within criteria for area contingencies. Increasing the Jay Tap Switching Substation cap banks to 5.4 MVAR as well as optimizing the Jay Tap 115/46 kV transformer to 0.975 was required to assist in maintaining reliable voltages along the 12.4 mile radial line connecting the Project to the VELCO 115 kV transmission system. Delta-V for the 5.4 MVAr capacitor banks at the Jay Tap 46 kV Substation is under the 3% limit specified by VELCO. Post-project transmission configuration has the 12W switch open, which isolates the North Troy 46 kV substation and points east (Newport area) from the shunt capacitors located at Jay Tap Switching Substation. Adding a 5.4 MVAr cap at the Newport-B2 bus provides needed support to maintain area voltages at pre-project levels due to the 12W switch being open. Short-circuit fault duties are below 5,000 A and expected to be well within the momentary and interrupting duties of standard equipment rated for 46 kV. No upgrades due to short-circuit are expected since the short-circuit current contribution is low for system fault conditions from wind turbine generators. VEC provided a cost estimate of approximately $1,184k to construct the necessary required network upgrades. The cost projections are based on “installed costs” and do not include the cost for environmental assessment, permitting or temporary facilities required for outage protection. VEC has communicated that subject to receipt of timely regulatory approval, the upgrades can be implemented in time to fit the planned commercial operations schedule for the Project. With the addition of the upgrades listed above to the Project as currently defined, the Project poses no significant adverse impact on the reliability and operating characteristics of the VELCO or VEC transmission systems, the transmission facilities of another Transmission Owner, or the system of a Market Participant. QP 311 Feasibility Study Final Report July 19, 2010 21 Contains Critical Energy Infrastructure Information Appendix A - Project Information Included in Appendix A: Appendix A-1: QP 311 Interconnection request QP 311 Feasibility Study Final Report July 19, 2010 A Contains Critical Energy Infrastructure Information Appendix B - Study Methodology Included in Appendix B: Appendix B-1: General Study Methodology Appendix B-2: Steady State Analysis Methodology QP 311 Feasibility Study Final Report July 19, 2010 B Contains Critical Energy Infrastructure Information Appendix C - Preliminary One-Line Diagram QP 311 Feasibility Study Final Report July 19, 2010 C Contains Critical Energy Infrastructure Information Appendix D - Steady State Contingency List QP 311 Feasibility Study Final Report July 19, 2010 D Contains Critical Energy Infrastructure Information Appendix E - Steady State Base Case Summaries Included in Appendix E: Appendix E-1: 2013 Summer Shoulder Load – D1 Dispatch Appendix E-2: 2013 Summer Peak Load – D2 Dispatch Appendix E-3: 2013 Summer Peak Load – D3 Sensitivity Dispatch Appendix E-4: 2013 Summer Peak Load – D4 Sensitivity Dispatch QP 311 Feasibility Study Final Report July 19, 2010 E Contains Critical Energy Infrastructure Information Appendix F - Steady State Base Case Draw Files Included in Appendix F: Appendix F-1: Dispatch A - Baseline Pre-Project o Summer 2013 Shoulder Load – D1 Dispatch o Summer 2013 Peak Load – D2 Dispatch o Summer 2013 Peak Load – D3 Sensitivity Dispatch o Summer 2013 Peak Load – D4 Sensitivity Dispatch Appendix F-2: Dispatch B - No Redispatch o Summer 2013 Shoulder Load – D1 Dispatch o Summer 2013 Peak Load – D2 Dispatch Appendix F-3: Dispatch C - Redispatch Against Remote Generation (Western Massachusetts) o Summer 2013 Shoulder Load – D1 Dispatch o Summer 2013 Peak Load – D2 Dispatch o Summer 2013 Peak Load – D3 Sensitivity Dispatch o Summer 2013 Peak Load – D4 Sensitivity Dispatch Appendix F-4: Dispatch D - Redispatch Against local generation (Sheffield and Swanton) o Summer 2013 Shoulder Load – D1 Dispatch o Summer 2013 Peak Load – D2 Dispatch o Summer 2013 Peak Load – D3 Sensitivity Dispatch o Summer 2013 Peak Load – D4 Sensitivity Dispatch QP 311 Feasibility Study Final Report July 19, 2010 F Contains Critical Energy Infrastructure Information Appendix G - Steady State Contingency Voltage Results Included in Appendix G: Appendix G-1: 2013 Summer Shoulder Load – D1 Dispatch Appendix G-2: 2013 Summer Peak Load – D2 Dispatch Appendix G-3: 2013 Summer Peak Load – D3 Sensitivity Dispatch Appendix G-4: 2013 Summer Peak Load – D4 Sensitivity Dispatch QP 311 Feasibility Study Final Report July 19, 2010 G Contains Critical Energy Infrastructure Information Appendix H - Steady State Contingency Thermal Results Included in Appendix H: Appendix H-1: 2013 Summer Shoulder Load – D1 Dispatch Appendix H-2: 2013 Summer Peak Load – D2 Dispatch Appendix H-3: 2013 Summer Peak Load – D3 Sensitivity Dispatch Appendix H-4: 2013 Summer Peak Load – D4 Sensitivity Dispatch QP 311 Feasibility Study Final Report July 19, 2010 H Contains Critical Energy Infrastructure Information