EXECUTIVE SUMMARY: SHORT CIRCUIT TEST OF GUY WIRES BACKGROUND OF THE PROJECT When upgrading Statnetts OHL’s from 300 kV to 420 kV, the distance between phase conductors and steel guy wires may be reduced in the centre phase of some towers. Consequently the risk of flashover to these components is increased. However, the present design is not intended to handle flashovers to and fault current through the guy wires, and thus the idea came up at Statnett to try to utilize armour rods (no. vernespiraler) to protect the guy wire in the region closest to the conductors. GOAL OF THE PROJECT The goal of the project was to identify possible positive effect of armour rods towards arc resistance of guy wires of steel. Furthermore it was intended to investigate the possibilities of utilizing carbon fiber rod as guy wire in future tower designs. GENERAL PROJECT INFORMATION The project was started in September 2012 and final report delivered in February 2014. Five guy wires of the type utilised by Statnett were tested. The length of the steel wire was approximately 15 m, and the wire had a cross section of 190 mm2. One specially prepared sample of a carbon fibre rod intended to simulate a guy wire of this type of material was provided for test by N-Tec in Norway. The rod was 5 m long and had a square shaped cross section of 20x20 mm. At the ends, two plates of carbon fibre material had been attached in order to allow for mechanical connection. All tests were performed at ABB high power laboratory in Ludvika, Sweden. TRL at the start of project was considered as TRL 2, at the end of the project the level increased to TRL 5. R&D METHOD The guy wire to be tested was strained horizontally 1 m above the floor by approximately 30 kN and grounded at both ends using cables connected to a steel structure simulating the tower. An arc was initiated 3 m from one end, at a test current terminal positioned approximately 0.2 m from the wire. In order to initiate the arc, the terminal was connected to the test object by a thin copper wire. Tests were performed with different current amplitudes and durations. A summary of the performed tests is shown in Table 1. Table 1 Selected test sequence Test Date Object A B C D E F G Dec. 18, 2012 Dec. 18, 2012 Dec. 18, 2012 Dec. 18, 2012 Jan. 7, 2013 Jan. 7, 2013 Jan. 7, 2013 Steel, No1 Steel, No2 Steel, No3 Carbon fibre rod Steel, No4 Steel, No5 Steel, No5 (observe: same as in test F) Armour rod No No Yes Yes No No Current [kArms] 15 15 15 15 15 5 10 Duration [s] 0,2 0,7 0,7 0,7 0,2 0,7 0,7 RESULTS OF THE PROJECT Tests of steel wires showed that the duration of arc exposure has a great impact on the magnitude of damages. At tests at 15 kA lasting for 0.2 s, the steel wire without armour rods was burned to a degree where only a few strands broke. However, at test durations of 0.7 s, a current amplitude of 5 kA was sufficient to damage the bare steel wire resulting in partial breaking. At 15 kA the same duration resulted in complete breaking of the wire. At the highest stress tested (15 kA and 0.7 s), the sample without armour rods broke completely, while the sample fitted with armour rods was damaged to a smaller extent and did not break. Consequently, it can be concluded that there is a positive effect of armour rods in this application. Under the assumption that selected test durations are representative, obtained test results indicate that application of armour rods to guy wires does provide sufficient protection towards damages from arcing and fault current. The carbon fibre rod did not withstand the test. It more or less exploded due to the heat generated from the current. Thus, if carbon fibre components are to be utilized in OHL towers, special attention should be paid to handling of arcs and fault currents. IMPLEMENTATION OF RESULTS It is strongly recommended to use armour rod for guy wires when there is a possibility of short circuit to the guy wires. Conversely the use of carbon fiber rod as guy wire is not recommended for such a situation. DISSIMINATION OF RESULTS The results of this project were documented in the main report delivered to Statnett and have not been used in any other publication. Damages to guy wire after test (15.6 kArmss, 0.74 s) Remainings of carbon fibre rod after test (15.3 kArmss, 0.74 s)