Nakusp Waste Transfer Electrical Services Prepared For

advertisement
Nakusp Waste Transfer
Electrical Services
Prepared For:
WSP Canada Inc.
303-535 Victoria Avenue North
Cranbrook, British Columbia
V1C 6S3 Canada
Prepared By:
Colbran Higgins Engineering Ltd.
PO Box 84118, 3625 Shaganappi Trail NW.
Calgary, Alberta
T3A 5C4
Issue: Tender
Date: March 27, 2015
Project: Nakusp Waste Transfer
Technical Specifications
CMS Division 26: - Electrical
Section 26 03 10 - Minor Electrical Demolition for Remodeling
Section 26 05 33 Conduit
Section 26 05 26 Grounding and Bonding
Section 26 41 00 Lightning Protection
Section 26 08 00 Testing and Commissioning
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Part 1
Section 26 03 10
General
Page 3 of 20
GENERAL
1.1
GENERAL CONDITONS
.1
Refer to the General Conditions as outlined in the Canadian Standards
Construction Documents CCDC 2, 2008 along with Supplementary General
Conditions which form an integral part of this specification and will be made part
of the contract.
1.2
SUMMARY OF WORK
.1
This Specification covers the installation of all civil and electrical work associated
with the electrical service revisions for the installation of the scale, traffic lights
and cameras at the Nakusp Waste Transfer Station.
o
o
o
o
1.3
Add new BCH service on existing pole.
power and communication to security cameras,
power to scale signal lights,
re-locate, re-feed existing seacan power,
MATERIALS AND WORKMANSHIP
.1
Materials and equipment for patching and extending work: As specified in
individual Sections.
.2
All materials and workmanship shall be in accordance with the best standard
practice and shall in all cases be in accordance with the local by-laws or
Provincial Regulations or if no regulations exist, thin in accordance with the
Canadian Electrical Code.
1.4
APPROVALS
.1
1.5
All requests for material substitutions and submission for approval of equivalent
equipment shall be submitted in writing to the consultant prior to tender closing.
Project record Documents
.1
The contractor shall keep a set of white prints to be used only for the preparation
of electrical project record documents. These shall be kept up to date and show
all variations of the original electrical drawings.
.2
On completion of the work these shall be turned over to the consultant.
.3
Underground conduit or duct runs shall be accurately located with dimensions
shown relating duct run to a permanent structure or element.
.4
Provide profile drawings of the installed electrical power and communication
service ducts.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 03 10
General
Page 4 of 20
1.6
Project record documents shall be available for inspection at all times through
the progress of the project.
1.7
Utility and inspector requirements
.1
All work shall be inspected at the appropriate time by the electrical inspector. It
shall be the contractor’s responsibility to notify the inspector at the required
stages of construction.
.2
Underground ducts installed for utility services shall be inspected and approved
by utility inspectors prior to back filling.
1.8
Responsibility
.1
1.9
The contractor is to take measurements at the building, set out all work and be
responsible for accuracy of same. Contractor is to provide all labour,
transportation material and plan necessary for the fulfilment of this section of the
section and give persona and constant attention to the work.
Arrangement of Work
.1
1.10
All work or material necessary for the proper completion of this project, although
not specified herein, is to be done or supplied without additional charge, it being
understood that the amount of this tender covers everything for a complete and
first class job.
Examination of the Site
.1
1.11
Before submitting his tender, the contractor shall visit the site and familiarize
themselves with the existing conditions. No claims for extras arising from site
circumstances will be accepted.
Cooperation of the Contractor
.1
1.12
Arrange work so as not to interfere in any way with other work carried on at the
site. Do any and all electrical work required by the Owner and attend upon and
give every facility for expediting the work.
Codes, Permits, and Inspections
.1
1.13
The installation shall comply with all the by-laws applying to electrical installation
in effect locally and with the regulation of the Canadian Electrical Code and BC
Department of Labour, Worksafe BC, where such regulation do not conflict with
those bylaws. The contractor shll obtain all permits and pay all fees required.
After completion of the work, the contractor shall furnish to the consultant for the
owner, a certificate of final inspection and approval form the local inspection
department.
Warranty
.1
The entire electrical system shall be left in proper working order and without
additional charges, any work or material which develop defects shall be replaces,
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 03 10
General
Page 5 of 20
except for ordinary wear and tear, within one year from the date of substantial
completion referred to in the General Conditions.
Part 2
Measurement and Payment Terms
2.1
Review and Inspection of the work
.1
The following progress items are to be provided to Electrical Engineer as work
progresses:
.1
.2
.3
.4
2.2
Copies of all permits.
Copies of all inspection reports from.
Digital photos of underground work prior to backfill showing scale measurement.
Any other items requested by Electrical Engineer during course of work.
Payment Terms
.1
One third of accepted tender amount after rough in phase.
.2
One third of accepted tender amount after site is energized.
.3
One third of accepted tender amount after final inspection by local authority and
Site review by Electrical Engineer and review of deficiencies (if any).
.2
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Part 3
3.1
Section 26 03 10
Minor Electrical Demolition for Remodelling
Page 6 of 20
General
STANDARDS
.1
Part 4
4.1
All Civil work associated with electrical and underground systems associated with
this contract shall comply with Master Municipal Construction Documents
(MMCD).
Products
MATERIALS AND EQUIPMENT
.1
All materials shall be supplied and installed by contractor.
.2
Materials shall comply with MMCD, Utility Specifications and Standards.
.3
All materials and workmanship shall be in accordance with the best standard
practice and shall in all cases be in accordance with the local by-laws or
Provincial Regulations or if no regulations exist, thin in accordance with the
Canadian Electrical Code.
4.2
OTHER SERVICES
.1
4.3
There are existing services such as electrical, telephone, water, gas, oil,
drainage etc. Exercise maximum care to avoid interference or damages to these.
Repairs created by damage to other services caused by the contractor shall be
paid for by the contractor.
APPROVALS
.1
4.4
All requests for material substitutions and submission for approval of equivalent
equipment shall be submitted in writing to the consultant prior to tender closing.
PROJECT RECORD DOCUMENTS
.1
The contractor shall keep a set of white prints to be used only for the preparation
of electrical project record documents. These shall be kept up to date and show
all variations of the original electrical drawings.
.2
On completion of the work these shall be turned over to the consultant.
.3
Underground conduit or duct runs shall be accurately located with dimensions
shown relating duct run to a permanent structure or element.
.4
Provide profile drawings of the installed electrical power and communication
service ducts.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 03 10
Minor Electrical Demolition for Remodelling
Page 7 of 20
4.5
Project record documents shall be available for inspection at all times through
the progress of the project.
4.6
UTILITY AND INSPECTOR REQUIREMENTS
4.7
RESPONSIBILITY
.1
4.8
The contractor is to take measurements at the building, set out all work and be
responsible for accuracy of same. Contractor is to provide all labour ,
transportation material and plan nc3ssar for the fulfilment of this section of the
section and give persona and constant attention to the work.
ARRANGEMENT OF WORK
.1
4.9
All work or material necessary for the proper completion of this project, although
not specified herein , is to be done or supplied without additional charge, it being
understood that the amount of this tender covers everything for a complete and
first class job.
EXAMINATION OF THE SITE
.1
4.10
Before submitting his tender, the contractor shall visit the site and familiarize
themselves with the existing conditions. No claims for extras arising from site
circumstances will be accepted.
CODES, PERMITS, AND INSPECTIONS
.1
4.11
The installation shall comply with all the by-laws applying to electrical installation
in effect locally and with the regulation of the Canadian Electrical Code and BC
Department of Labour, Worksafe BC, where such regulation do not conflict with
those bylaws. The contractor shll obtain all permits and pay all fees required.
After completion of the work, the contractor shall furnish to the consultant for the
owner, a certificate of final inspection and approval form the local inspection
department.
WARRANTY
.1
Part 5
5.1
The entire electrical system shall be left in proper working order and without
additional charges, any work or material which develop defects shall be replaces,
except for ordinary wear and tear, within one year from the date of substantial
completion referred to in the General Conditions.
EXECUTION
EXAMINATION
.1
Verify existing conditions before starting work.
.2
Verify field measurements and circuiting arrangements are as shown on
drawings.
.3
Verify that abandoned wiring and equipment serve only abandoned facilities.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 03 10
Minor Electrical Demolition for Remodelling
Page 8 of 20
.4
Demolition Drawings are based on existing reported conditions. Report
discrepancies to WSP Canada Inc. before disturbing existing installation.
.5
Beginning of demolition means installer accepts existing conditions.
5.2
PREPARATION
.1
Disconnect electrical systems in walls, floors, and ceilings scheduled for removal.
.2
Coordinate utility service outages with Utility Company, BC Hydro (Nakusp).
.3
Provide temporary wiring and connections to maintain existing systems in service
during construction. When work must be performed on energized equipment or
circuits, use personnel experienced in such operation
.4
Existing Electrical Service: Maintain existing system in service until new system
is complete and ready for service. Disable system only to make switch overs and
connections. Obtain permission from WSP Canada Inc. at least twenty-four (24)
hours before partially or completely disabling system. Minimize outage duration.
Make temporary connections to maintain service in areas adjacent to work area
as required.
5.3
DEMOLITION AND EXTENSION OF EXISTING ELECTRICAL WORK
.1
Remove, relocate, and extend existing installations to accommodate new
construction.
.2
Remove abandoned wiring to source of supply.
.3
Remove exposed abandoned conduit, including abandoned conduit above
accessible ceiling finishes. Cut conduit flush with walls and floors, and patch
surfaces.
.4
Disconnect abandoned outlets and remove devices. Remove abandoned outlets
if conduit servicing them is abandoned and removed. Provide blank cover for
abandoned outlets which are not removed.
.5
Disconnect and remove abandoned panelboards and distribution equipment.
.6
Disconnect and remove electrical devices and equipment serving utilization
equipment that has been removed.
.7
Disconnect and remove abandoned luminaires. Remove brackets, stems,
hangers, and other accessories.
.8
Repair adjacent construction and finishes damaged during demolition and
extension work.
.9
Maintain access to existing electrical installations which remain active. Modify
installation or provide access panel as appropriate.
.10
Extend existing installations using materials and methods [compatible with
existing electrical installations, or] as specified.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
5.4
Section 26 03 10
Minor Electrical Demolition for Remodelling
Page 9 of 20
CLEANING AND REPAIR
.1
Clean and repair existing materials and equipment which remain or are to be
reused.
.2
Luminaires: Remove existing luminaires for cleaning. Use mild detergent to
clean all exterior and interior surfaces; rinse with clean water and wipe dry.
Replace lamps, broken electrical parts, ballasts.
END OF SECTION
Part 6
6.1
General
SECTION INCLUDES
.1
Metal conduit.
.2
PVC coated metal conduit.
.3
Flexible metal conduit.
.4
Liquid tight flexible metal conduit.
.5
Electrical metallic tubing.
.6
Nonmetal conduit.
.7
Electrical nonmetallic tubing.
6.2
REFERENCES
.1
CSA-C22.1-12 - Canadian Electrical Code, Part I (22nd Edition), Safety Standard
for Electrical Installations.
.2
CSA-C22.2 No. 45.1-07 (R2012) - Electrical Rigid Metal Conduit - Steel.
.3
CSA-C22.2 No. 45.2-08 (R2013) - Electrical rigid metal conduit - Aluminum, red
brass, and stainless steel.
.4
CSA-C22.2 No. 56-13 - Flexible Metal Conduit and Liquid-Tight Flexible Metal
Conduit.
.5
CSA-C22.2 No. 83.1-07 (R2012) - Electrical Metallic Tubing - Steel.
.6
CSA-C22.2 No. 211.1-06 (R2011) - Rigid Types EB1 and DB2/ES2 PVC
Conduit.
.7
CSA-C22.2 No. 211.2-06 (R2011) - Rigid PVC (Unplasticized) Conduit.
.8
CSA-C22.2 No. 227.1-06 (R2011) - Electrical Nonmetallic Tubing.
.9
NFPA 70 - National Electrical Code (NEC), 2014 Edition.
.10
CSA (Canadian Standards Association).
.11
UL (Underwriters Laboratories Inc.).
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
6.3
Section 26 03 10
Minor Electrical Demolition for Remodelling
Page 10 of 20
ADMINISTRATIVE REQUIREMENTS
.1
Coordination:
.1
6.4
Coordinate with other work having a direct bearing on work of this
section.
DELIVERY, STORAGE, AND PROTECTION
.1
Accept conduit on site. Inspect for damage.
.2
Protect conduit from corrosion and entrance of debris by storing above grade.
Provide appropriate covering.
.3
Protect PVC conduit from sunlight.
Part 7
Products
7.1
CONDUIT REQUIREMENTS
.1
Minimum Size: as specified in applicable code.
.2
Wet and Damp Locations: Use [rigid aluminum conduit] [thick wall non-metallic
conduit] [electrical metallic tubing] [intermediate metal conduit] [rigid steel
conduit] [non-metallic tubing].
.3
Dry Locations:
.1
.2
Concealed: Use [thick wall non-metallic conduit] [rigid steel conduit] [nonmetallic tubing] [intermediate metal conduit] [electrical metallic tubing]
[rigid aluminum conduit].
Exposed: Use [intermediate metal conduit] [electrical metallic tubing]
[thick wall non-metallic conduit] [rigid [steel] [aluminum] conduit].
.4
Description: Interlocked [steel] [aluminum] construction with PVC jacket.
.5
Fittings: [CSA-C22.2 No. 56].
.6
Description: [CSA-C22.2 No. 227.1].
.7
Fittings and Conduit Bodies: [CSA-C22.2 No. 227.1].
Part 8
8.1
Execution
EXAMINATION
.1
Verify existing conditions before starting work.
.2
Verify that field measurements are as shown on Drawings.
.3
Verify routing and termination locations of conduit prior to rough-in.
.4
Conduit routing is shown on Drawings in approximate locations unless
dimensioned. Route as required to complete wiring system.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
8.2
Section 26 03 10
Minor Electrical Demolition for Remodelling
Page 11 of 20
INSTALLATION
.1
Install conduit to CSA-C22.1.
.2
Install non-metallic conduit to manufacturer's written instructions.
.3
Arrange supports to prevent misalignment during wiring installation.
.4
Support conduit using coated steel or malleable iron straps, lay-in adjustable
hangers, clevis hangers, and split hangers.
.5
Group related conduits; support using conduit rack.
.6
Construct rack using steel channel [provide space on each for 25% additional
conduits].
.7
Fasten conduit supports to building structure and surfaces to Section 26 05 29.
.8
Do not support conduit with wire or perforated pipe straps. Remove wire used for
temporary supports.
.9
Do not attach conduit to ceiling support wires.
.10
Arrange conduit to maintain headroom and present neat appearance.
.11
Route exposed conduit parallel and perpendicular to walls.
.12
Route conduit installed above accessible ceilings parallel and perpendicular to
walls.
.13
Route conduit through roof openings for piping and ductwork or through suitable
roof jack with pitch pocket.
.14
Route conduit in and under slab from point-to-point.
.15
Do not cross conduits in slab.
.16
Maintain adequate clearance between conduit and piping.
.17
Cut conduit square using saw or pipe cutter; de-burr cut ends.
.18
Bring conduit to shoulder of fittings; fasten securely.
.19
Join non-metallic conduit using cement as recommended by manufacturer.
.1
.2
.3
Wipe non-metallic conduit dry and clean before joining.
Apply full even coat of cement to entire area inserted in fitting.
Allow joint to cure for 20 minutes, minimum.
.20
Use conduit hubs [or sealing locknuts] to fasten conduit [to cast boxes] [to sheet
metal boxes in damp and wet locations].
.21
Install no more than equivalent of three 90-degree bends between boxes.
.1
Use conduit bodies to make sharp changes in direction, as around
beams.
.22
Avoid moisture traps; provide junction box with drain fitting at low points in
conduit system.
.23
Provide suitable fittings to accommodate expansion and deflection where conduit
crosses [seismic] [control] expansion joints.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 03 10
Minor Electrical Demolition for Remodelling
Page 12 of 20
.24
Provide suitable pull string in each empty conduit except sleeves and nipples.
.25
Use suitable caps to protect installed conduit against entrance of dirt and
moisture.
.26
Ground and bond conduit to Section 26 05 26.
.27
Identify conduit to Section 26 05 53.
END OF SECTION
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Part 9
9.1
Section 26 05 26
Grounding and Bonding
Page 13 of 20
General
SECTION INCLUDES
.1
Grounding electrodes and conductors.
.2
Equipment grounding conductors.
.3
Bonding.
9.2
REFERENCES
.1
CSA-C22.1-12 - Canadian Electrical Code, Part I (22nd Edition), Safety Standard
for Electrical Installations.
.2
NETA ATS-2013 - Standard for Acceptance Testing Specifications for Electrical
Power Equipment and Systems.
.3
NFPA 70 - National Electrical Code (NEC), 2014 Edition.
.4
NFPA 99 - Health Care Facilities, 2012 edition.
.5
CSA (Canadian Standards Association).
.6
UL (Underwriters Laboratories Inc.).
9.3
SYSTEM DESCRIPTION
.1
Metal underground water pipe.
.2
Metal frame of the building.
.3
Concrete-encased electrode.
.4
Ground ring specified in Section 33 79 19.
.5
Metal underground gas piping system.
.6
Rod electrode.
.7
Plate electrode.
.8
Active electrode.
9.4
PERFORMANCE REQUIREMENTS
.1
9.5
Grounding System Resistance: 25ohms.
SUBMITTALS FOR REVIEW
.1
9.6
Product Data: Provide for grounding electrodes and connections.
SUBMITTALS FOR INFORMATION
.1
Test Reports: Indicate overall resistance to ground [and resistance of each
electrode].
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
.2
9.7
Section 26 05 26
Grounding and Bonding
Page 14 of 20
Installation Data: Indicate application conditions and limitations of use stipulated
by product testing agency specified under Regulatory Requirements. Include
instructions for storage, handling, protection, examination, preparation, and
installation of product.
CLOSEOUT SUBMITTALS
.1
Record Documentation: Record actual locations of components and grounding
electrodes.
.2
Certificate of Compliance: Indicate approval of installation by [authority having
jurisdiction].
9.8
QUALITY ASSURANCE
.1
9.9
Products of This Section: Manufactured to ISO 9000 certification requirements.
REGULATORY REQUIREMENTS
.1
Part 10
10.1
Products: Listed and classified by CSA as suitable for the purpose specified and
indicated.
Products
ROD ELECTRODES
.1
10.2
Material: Copper.
ACTIVE ELECTRODES
.1
Material: Metallic-salt-filled copper-tube electrode.
.2
Shape: Straight
10.3
WIRE
.1
Material: Stranded copper.
.2
Foundation Electrodes: 2 AWG.
.3
Grounding Electrode Conductor: Size to meet CSA-C22.1 requirements.
Part 11
11.1
Execution
EXAMINATION
.1
Verify existing conditions before starting work.
.2
Verify that final backfill and compaction has been completed before driving rod
electrodes.
11.2
INSTALLATION
.1
Install to manufacturer's written instructions.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 05 26
Grounding and Bonding
Page 15 of 20
.2
Install rod electrodes at locations indicated. Install additional rod electrodes as
required to achieve specified resistance to ground.
.3
Provide bonding to meet Regulatory Requirements.
.4
Bond together metal siding not attached to grounded structure; bond to ground.
.5
Bond together reinforcing steel and metal accessories in [fountain] [pool]
structures.
.6
Install transient suppression plate [where indicated].
.7
Provide isolated grounding conductor for circuits supplying personal computers.
.8
Provide grounding and bonding in patient care areas to meet requirements of
NFPA 99 .
.9
Equipment Grounding Conductor: Provide separate, insulated conductor within
each feeder circuit raceway. Terminate each end on suitable lug, bus, or
bushing.
.10
Interface with site grounding system.
.11
Interface with lightning protection system.
END OF SECTION
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Part 12
Section 26 41 00
Lightning Protection
Page 16 of 20
General
12.1
SECTION INCLUDES
.1
Air terminals and interconnecting conductors.
.2
Grounding and bonding for lightning protection.
12.2
REFERENCES
.1
CAN/CSA-B72-M87 (R2013) - Installation Code for Lightning Protection
Systems.
.2
IEEE 837-2002 - IEEE Standard for Qualifying Permanent Connections Used in
Substation Grounding.
.3
NFPA 780 - Standard for the Installation of Lightning Protection Systems, 2014
Edition.
.4
UL 96-2005 - Lightning Protection Components (5th Edition).
.5
UL 96A-2007 - Installation Requirements for Lightning Protection Systems (12th
Edition).
.6
CSA (Canadian Standards Association).
12.3
SYSTEM DESCRIPTION
.1
Assembly of components includes conductor system protecting consisting of
roof-mounted mechanical equipment; grounding electrodes; and interconnecting
conductors.
12.4
ADMINISTRATIVE REQUIREMENTS
.1
Project management and coordination procedures.
.2
Coordination:
.1
.2
12.5
Coordinate with other work having a direct bearing on work of this
section.
Coordinate work with roofing and exterior and interior finish installations.
SUBMITTALS FOR REVIEW
.1
Section 01 33 00: Submission procedures.
.2
Product Data: Provide dimensions and materials of each component, and
include indication of listing to UL 96 .
.3
Shop Drawings: Indicate layout of air terminals, grounding electrodes, and
bonding connections to structure and other metal objects. Include terminal,
electrode, and conductor sizes, and connection and termination details.
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
12.6
Section 26 41 00
Lightning Protection
Page 17 of 20
SUBMITTALS FOR INFORMATION
.1
Submission procedures.
.2
Manufacturer's Certificate: Certify that Products meet or exceed [specified
requirements].
.3
Certificate of Compliance: Submit certificate of compliance from CSA indicating
approval of lightning protection systems.
12.7
CLOSEOUT SUBMITTALS
.1
Submission procedures.
.2
Record Documentation: Record actual locations of air terminals, grounding
electrodes, bonding connections, and routing of system conductors in project
record documents.
12.8
QUALITY ASSURANCE
.1
Products of This Section: Manufactured to ISO 9000 certification requirements.
.2
Perform CAN/CSA-B72.
.3
Installer Qualifications: Authorized installer of manufacturer with minimum years’
experience and certified by the Lightning Protection Institute.
12.9
REGULATORY REQUIREMENTS
.1
Product Listing: UL 96 .
Part 13
Products
Part 14
Execution
14.1
EXAMINATION
.1
Section 01 70 00: Verify existing conditions before starting work.
.2
Verify that field measurements are as [indicated] [indicated on Shop Drawings].
14.2
INSTALLATION
.1
Connect conductors using mechanical connectors. Protect adjacent construction
elements and finishes from damage.
.2
Bond exterior metal bodies on building to lightning protection system [and
provide intermediate level interconnection loops 18 m on centre.
END OF SECTION
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 08 00
Testing &Commissioning
Page 1 of 20
SECTION 26 08 00
COMMISSIONING OF ELECTRICAL SYSTEMS
PART 1 – GENERAL
Part 15
OPERATING AND MAINTENANCE MANUALS
Part 16
GENERAL
.1
Supply operating and maintenance instructions for all electrical systems included
in the electrical contract.
.2
Manuals shall be completed, approved and turned over to the Owner no later
than the time of substantial completion.
.3
Service manuals, data sheets, and other manufacturer’s information provided in
the manuals must be original material in all copies of the manual. Photocopies
are not acceptable.
16.2
PART 2 – PRODUCTS
.1
Two original copies shall be prepared and permanently numbered #1, #2.
.2
Manuals shall have expandable hard covered; three post binders of extra heavy
weight capable of withstanding several decades of use. Hinges shall be metal.
Binder thickness shall not exceed 3”.
16.3
CONTENTS
.1
Operating and maintenance instructions for each electrical system shall be
included. An outline of the sections shall include:
.2
1) Index
.3
2) Testing and Commissioning Reports
.4
3) Inspection Reports
.5
6) Permits
o Final Electrical Inspection Certificate
7) Project Documentation
o Project Record Documents
o Warranties
8) Construction photographs.
26 08 00 - 1
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
Section 26 08 00
Testing &Commissioning
Page 2 of 20
The General section shall include a complete list of companies involve dint eh
project including electrical contractor and all sub-contractors. For each, list
company name, address, phone number, and contact person.
16.4
SCHEMATIC DIAGRAMS
1) Simple schematic layout to enable technical personnel who may be unfamiliar
with they installation to quickly understand essentials without getting invoice
din the specific details of equipment.
2) Schematic diagram shall have a clear graphic presentation with only essential
notes.
3) The presentation should aim at providing information to a reader with some
general knowledge of similar systems but how is new to this particular
project.
16.5
EQUIPMENT AND COMPONENTS
.1
This section identifies and describes the details and specifications of each
component. Inn schematics and functional data, the items are listed to show
their function in the system without defining technical details of each component
.2
Provide the complete detail needed to order replacement parts of every
component.
.3
Provide reference to original size, type setting etc of each component
16.6
SHOP DRAWINGS
.1
16.7
This section shall include all shop drawings for the system. Drawings shall be
clear and readable. 1”x17” drawings are preferred.
OPERATING PROCEDURES
.1
This section provides a detailed description of the step-by step procedure the
operator must follow to properly operate each portion of each system involved.
16.8
This section in particular must we written in clearly detailed terms. It can be
assumed that operator have a basic knowledge and training, but not
necessarily on this particularly system or layout. This section is intended das
a guide for operators faced with conditions that are new or seldom
encountered. As an operator becomes more familiar with the operation, he
may refer to the is section less
16.9
EACH SYSTEMS IS TO BE PRESENTED IN THE FOLLOW ORDER:
.1
Start-up procedures
.2
Normal operating procedures
.3
Special procedures.
.4
Trouble-shooting.
26 08 00 - 2
THE REGIONAL DISTRICT OF
CENTRAL KOOTENAY
NAKUSP WASTE
TRANSFER STATION UPGRADES
16.10
.1
16.11
Section 26 08 00
Testing &Commissioning
Page 3 of 20
MAINTENANCE PROCEDURES
GENERAL
TESTING AND CERTIFICATION DATA
.1
Data sheets of all system tests or verifications shall be provided. This shall
include factory, as well as, site testing and commissioning.
.2
All adjustable devices shall have a data sheet recording equipment, adjustment
range and final settings.
.3
All inspector and manufactures certificates shall be included
Where equipment or systems are provide that have long-term warranties from
the manufacturer, they shall be included in this section. Original copy should e
retained in #1 copy with photocopies inserted in other copes of the manuals.
26 08 00 - 3
Download