2012 First International Conference on Renewable Energies and Vehicular Technology Optimal Design of a renewable energy power plant for an isolated site in Senegal Abdoulaye Kébé1,2, Sengprasong Phrakonkham1, Ghislain Remy1, Demba Diallo1, Claude Marchand1 1 Laboratoire de Génie Electrique de Paris (LGEP) / SPEE-Labs, CNRS UMR 8507; SUPELEC; Université Pierre et Marie Curie P6; Université Paris-Sud; 11 rue Joliot Curie, Plateau de Moulon F91192 Gif sur Yvette CEDEX, demba.diallo@lgep.supelec.fr 2 Université Cheikh Anta Diop, Laboratoire de Traitement de L’Information, Dakar, Sénégal ABSTRACT The exploitation of resources of renewable energy has become inescapable today. Indeed, facing the oil cost increase, the survival of the economies, particularly of the non oil-producing countries requires the evaluation and the exploitation of their energy potential. The purpose of this paper is to make an analysis of the electrical energy situation in Senegal and to show the relevance in the implementation of a hybrid power plant using renewable energy resources. The design is done to minimize the Annualized Cost of System under the constraints related to the components and the availability of the energy measured with the Loss of Supply Probability. Index Terms— Isolated site, Optimization, Micro-Grid, Hybridization, Renewable Power Sources This paper is organized as follows: In the first section, we assess the electrification rate in Senegal and present the renewable energy resources. In the second one, the concept of micro-grid is introduced and the different configurations are analysed and compared. In the third section, the isolated site and the corresponding load profile are presented. In the fourth one, the hybridization of the energy sources and the optimal design are presented. 1. INTRODUCTION The sustainable development adopted by several countries as a modality of any economic and social growth is today at the crossroads. Indeed, one of the main consequences of the world energy crisis is the increase of the fossil resource prices. This has undermined the efforts of several countries, in particular those in the early stages of development [1]. In sub-Saharan Africa this energy crisis has led to an aggravation of the situation of the national companies of electricity, that were already facing tremendous difficulties. Indeed, since the middle of the 80s, these companies have been suffering from a degradation of their technical and economic performances [2], mainly because of mismanagement. This is a characteristic of most of the state-owned companies without a clear roadmap including the challenges such as the increase of consumption, preventive maintenance requirements and the development of renewable energies. Moreover, the absence of forecast has led to the continuous decrease of the productivity gains. In fact, combined with the weakness of the power production capacity, the increase of the interest rates and the cost of the inputs put a large number of companies in financial deficit. As an example, the Senegalese national company of electricity (SENELEC) is bogged down in a chronic budget deficit of more than $400 million and a production deficit of more than 100 MW. In 2010, the Senegalese endured 2950 hours (equivalent to 4 months!) of power cut [3]. The main reasons are the outdated state of the power plants, the transportation and distribution network, the lack of fuel and the failure of the maintenance policy. 2. ELECTRIFICATION IN SENEGAL 2.1. State of Art of electrification in Senegal The consumption of electricity represents 8.8% of the total of energy consumption, far behind biomass (43%) and oil products (47%) [4].The production of electricity is based on oil products with 600,000 tons (35% of the national consumption of hydrocarbons). Furthermore, the high demand of the low voltage clientele grows at a rate above 6% and the capacities of production are insufficient [3]. This leads to deficits of production due to delays in the implementation of new basic groups. Figure 1 shows the evolution of the cover rate in electricity from 2000 till 2006. Figure 1. Evolution of the electrification rate [4] 978-1-4673-1170-0/12/$31.00 ©2012 IEEE 336 Therefore, the capacity of the offer was reduced by the decline of the availability of the group (77 to 70% between 2003 and 2006) [5], because of the outdated state of the equipment and problems of maintenance. So gensets with prohibitive operating costs were used at an abnormally high rate. Despite the recourse to rented gensets, the selling cost of energy is 91 F CFA/kWh (0.138€) compared to the production one which is 97 F CFA/kWh (0.14€) [3]. Moreover, the records of rise in the oil price (25% for the heavy fuel oil, and 22% for the diesel oil) in 2006 lead to 130 billion F CFA (293 344 957 €) for fuel expenses [5]. All these factors combined with a penalizing mode of price setting, dysfunctions in the exploitation and maintenance of production units (average return on 31%) [5], the recourse to expensive financing ended in a deficit between 2005 and 2006 of several billion F CFA. Recently, an audit ordered by authorities in charge of electrical energy revealed among other reasons that the crisis in the sector of the electricity results largely from economic performances registered by Senegal during the last ten years with a growth of the GDP (Gross Domestic Product) of 5 % a year which is translated by the growth of the demand of electricity by 10% a year, and a politic of systematic electrification to allow the largest number of Senegalese to access to electricity. In 2000, SENELEC had only 398,000 subscribers and meadows of 3 millions of Senegalese had access to electricity while today SENELEC has more than 885,000 subscribers and thus more than 7 millions Senegalese have access to electricity, as shown in Figure 1. It is also necessary to note that every Senegalese consumes more electricity today than before. Indeed, 63% of the current customers of SENELEC are in the group of consumers of more than 150kWh [3]. From the point of view of production, the fleet of power stations is largely obsolete, not reliable, very expensive, unsuitable and insufficient in terms of capacity. There is a structural deficit of production of 100 MW with regard to the demand. Therefore, consumers face frequent power cuts and the industrial equipment suffers from a continuous degradation [3]. An old equipment of production and transport (12 years on average), among which 140MW is more than 20 years old. The 6.6 kV network of Dakar was built in the 1930's and is more than 80 years old [3]. The production cost for some power plant reaches up to 2.2. Policy of development for the energy sector The previous analysis clearly indicates that the government must seriously tackle the energy sector by defining an ambitious policy. It should aim at: - Guaranteeing the energy supply of the country, - Widening the access of the populations to the modern services of energy, - Reducing the vulnerability of the country to the volatility of the world oil market. Therefore, an efficient policy for the energy sector should focus on the development and the exploitation of the national energy potentialities, in particular renewable energies (solar, wind, marine, biomass) and the biofuels. The Senegalese government has defined its policy concerning the development of energy [5] based on the following axes: - Restructure the subsector of electricity with the introduction of private partners in the capital and the management of SENELEC, - Enhance rural electrification, - Strengthen the conditions of competition in the subsector of hydrocarbons, - Intensify the promotion of sedimentary pond, - Strengthen the sustainable management of ligneous resources by greater empowerment of local authorities. 2.3. Renewable Energy Sources 2.3.1. Photovoltaic Energy Senegal is situated at 12°8-16°41 latitude north and 11°21-17°32 longitude west. The average solar radiation is 5.8 kW/m2/day for an illumination of 1000W/m2 registered during 3000 hours a year [6], as shown in Figure 2. Several 167 F CFA (0.254€) per kWh while the electricity is sold projects have been realised or are in progress e.g. installation between 108 (0.164€) and 120 F CFA/kWh (0.183€) [3]. The non respect of the maintenance program over several of 11 solar power plants (10–40 kWp) in the islands of years increased and continued the vicious cycle of the power Saloum (4000 households), installation of 2648 solar cuts: the maintenance program has been realized at 59% in lanterns, electrification of 662 community centres (health 2007 against only 25% in 2010. 337 centres, schools, mosques, churches), and a solar power network. plant of 7MW in the southern region, Ziguinchor (on study) 2.3.3. Other Natural Resources Senegal, because of its favourable geographical position, [6]. benefits from 500 km of coast. At present, we have no information on any study on offshore wind, tidal, wave or any other source of energy potential from the ocean. However, any site situated on the “Grande Côte” augurs an interesting potential of hybridisation between solar, wind and marine energies. Figure 2. Irradiance map in Senegal 2.3.2. Wind energy So far, Senegal has no wind farm. However, studies led by various researchers and organizations reveal an interesting wind potential along the west coast called “Grande Côte” in Senegal. In this area, the wind speed measured at 10 m high ranges from 3.8 to 4.2 m/s, as shown in Figure 3. Figure 4. Location of the site 3. THE SELECTED ISOLATED SITE 3.1. Presentation of the site The selected site, MBoro sur Mer, is a village located on “Grande Côte” at 5km from the municipality of MBoro, Figure 4. It consists of about fifty concessions distributed on approximately 500 m long. The main activities are fishing and truck farming. Figure 3. Wind map in Senegal 3.2. Energy resources Currently, several wind farm projects are being considered and planned e.g. 50MW in the northern region (Saint Louis), 125 MW, 10.2 MW, 10.2 MW, 40 to 60 MW on the west coast respectively at Taïba NDiaye, Kayar, Potou and MBoro [7]. Concerning the site of Kayar, the project aims at installing a dozen of 850 kW wind turbines 71 to 74m high [8]. The production will be fed into the interconnected 3.2.1. Wind energy Figure 5 presents the daily wind speed (in m/s) at the site of MBoro in 2003. Regarding the data collected, wind speed fluctuates in a low range of values corresponding to a maximum wind speed of 30 km/h. 338 Figure 5. Wind speed measured at 20m at MBoro every Figure 7. September, daily radiation in Dakar 10min 3.2. Load Profile Previous measures made at the same site at 15 m high To determine an estimation of the required power to feed the village, we have determined the number of electrical devices and their rated power. The results are illustrated in Table 1: between 1998 and 1999 [9] gave an average wind speed equal to 4.2 m/s, as shown in Figure 6. Results show a globally stable average wind speed that makes available low speed wind turbine for such site. Table 1. Power estimation Type of device Rated output (W) Number Total power (W) TV set 60 44 2640 Lamp 15 257 3855 Radio set 5 45 225 DVD 25 20 500 Taking into account the habits of the populations and their rhythm of life, we have determined the following 4 ranges of operation: - Range 1 (from 1 am to 6 am): no professional activity. Only the street lighting is switched on, P = 765W - Range 2 (from 6 am to 2 pm): economic and school activities. Only some devices (radio sets for the elders for example) work, P = 225W - Range 3 (from 2 pm to 8 pm): between lunch break and the end of the afternoon. Children are back home and watch television for example, P = 2640W - Range 4 (from 8 pm to 1 am): all families are gathered at home; it’s the highest period of energy consumption. The power is estimated at P=7,220W. Figure 6. Average variation of the wind speed at 15 and 30 m high at MBoro 3.2.2 Solar energy potential By observing the irradiance map of Senegal in Figure 2, we notice that the irradiation is rather homogeneous on the “Grande Côte” from Dakar to St-Louis. We can thus consider that the irradiation observed in MBoro is equivalent to that of Dakar. A value of 5.4 kWh/m2 can be considered. In Figure 7, we can observe the daily irradiation measured in Dakar in September 2010. The energy consumption behavior is summarized in Figure 8 depicted as a load profile. 339 energy flows through an AC bus. AC/AC converters should be inserted to enable stable coupling of the components. If a battery is used as storage device, a bidirectional AC/DC static converter is required. It may also feed DC loads through a DC bus [16]. This configuration is better suitable for islands and villages including several points of generation without a centralised connection. Figure 8. Load power profile 4. MICRO-GRID 4.1. Definition and Concept Figure 9. Micro-grid DC configuration For the AC-DC configuration depicted in Figure 11, the energy flows through DC and AC buses. If a battery is used as a storage device, a bidirectional AC/DC static converter is required. DC loads can be fed through the master AC/DC static converter or directly from the DC bus. On the AC bus, AC generating components may be connected directly or through AC/AC converters to enable stable coupling of the components [17]. This configuration is suitable for small systems with a fairly constant load. The concept of Micro-grid has appeared as a new paradigm of the well-known classical power grid [10]. Hybrid Power Systems combine the advantages of conventional and renewable power conversion systems [10]. They appear as necessity rises to feed isolated sites with electrical energy. The first solution is to connect the area to the national power utility [11]. Unfortunately because of geographical constraints or due to the weakness of the grid or because of non-profitability, this solution has very often been abandoned. The alternative has been to produce, store and distribute electrical energy locally. Therefore, a small (compared to the national one by size and power) grid has been built [12]. A connection to the national grid could be considered but is not mandatory. The power could range from 1 to 100kW. The advantages lie in the possibilities to design and tune the network to minimise the cost or/and to fulfil environmental constraints for example [13-14]. The main disadvantage is the absence of backup in case of power cuts if there is no connection to the main grid. However, the solution is still attractive as it boosts the use of locally available renewable energy sources. Figure 10. Micro-grid AC configuration 4.2. Micro-Grid Configurations There are essentially 3 types of micro grid configurations: DC, AC and AC-DC coupled [15-16]. For the DC coupled configuration depicted in Figure 9, all the components are connected to a DC bus. Rectifiers are required to connect AC generators. AC loads are connected to the DC bus through inverters [16]. The storage device is usually a battery, controlled and protected from overcharge and discharge by a charge controller. This configuration is best suited for small systems with a fairly constant load. In AC configuration depicted in Figure 10, the electrical Figure 11. Micro-grid DC-AC configuration 340 Tables 2, 3 and 4 sum up the main advantages and inconvenients of the three configurations: Table 2. DC Configuration analysis Advantages ‐ ‐ ‐ ‐ we have focused on a Micro-grid AC configuration only. 5. APPLICATION TO THE ISOLATED SITE Inconvenients ‐ Direct use of energy Few losses Few equipments Easy expansion 5.1. Simulation models Required to increase the capacity of the inverter or to add a second inverter in case of point brought up what provokes a low weak Higher cost of DC equipment No available backup for AC in case of breakdown ‐ ‐ The hybrid system simulated consists of photovoltaic panels, wind turbines and battery storage. The load is connected to these sources through a 220V AC grid, as shown in Figure 12. The produced energy excess is used to charge the batteries, depending on their state of charge (SOC) [18]. Whenever the load demand is higher than the energy produced, the batteries will supply the difference. Table 3. AC Configuration analysis Advantages ‐ ‐ ‐ Inconvenients ‐ Possibility of increasing the voltage with a passive component (the transformer) Cheap equipment of connection Possibility to use the frequency as means of control ‐ Losses due to multiple conversions Requirements to synchronize all the sources Figure 12. Diagram of the hybrid system The simulation has been be conducted under the Matlab R2011b/Simulink environment for a period of 24 hours using average data recorded in Senegal, as described in Section 3. The Genetic Algorithm (GA), integrated in the Global Optimization Toolbox of Matlab/Simulink, has been used as the optimization tool. Mainly because the MI-LXPM algorithm have been implemented in GA function of Matlab (above version R2011b). So, we are now able to design system using Integer value of the variables. Integer programming has involved several modifications of the basic GA algorithm: Special creation, crossover, and mutation functions enforce variables to be integers [19]. Table 4. AC-DC Configuration analysis Advantages ‐ ‐ ‐ ‐ Efficiency Possibility to connect AC load directly Less requirement for the inverter Allow to feed loads raised from an important AC source Inconvenients ‐ Less efficient consumption of fuel in case of partial load Precisely, the genetic algorithm attempts to minimize a penalty function, not the fitness function. The penalty function includes a term for infeasibility [20]. This penalty function is combined with binary tournament selection to select individuals for subsequent generations. The penalty function value of a member of a population is: - If the member is feasible, the penalty function is the fitness function, as depicted in Figure 13. - If the member is infeasible, the penalty function is the maximum fitness function among feasible members of the population, plus a sum of the constraint violations of the (infeasible) point. From a practical point of view, there is no ‘best configuration’. For each application, a thorough analysis has to be conducted and it takes into account all the various aspects from the accessibility of the site, environmental aspects, safety concerns and technological choices. In the next section, for the application on an isolated site, 341 each, leading to 2000h of time computation to evaluate all cases. Using GA, the calculations takes only 30 minutes on an Intel(R) Core(TM) i7 CPU Q720 at 1.60GHz with 8,00 Go of Memory. 5.3. Results Table 5 shows the various solutions obtained by the optimization: Figure 13. Evolution of the penalty during generations Table 5. Optimization Results 5.2. Optimization problem The optimization of the system is determined for a period of 20 years. We have been considering that the load profile and the potential of sources will remain unchanged on the studied period. The costs are converted to the prices practiced in Senegal and expressed in euro [25]. The main parameters used for the sizing of the components are detailed in the lines: - The meteorological data (speeds of wind) were measured on the site of MBoro at a height of 20m, whereas the solar radiation data results from the site of Dakar. The radiation can be considered as equivalent to that of the MBoro because of the relatively close geographical positions of both sites. - The photovoltaic panels under consideration are of the SP 130 [21] and BP 250 type [22], with 130Wp, 24 V and 50Wp, 12V respectively. - The wind turbine is of the WH3-G2 type with a rated output of 1kW, for a beam of 2m and a mast height of 11m [23]. - The battery has a capacity of 75Ah for a voltage of 12V [24]. The battery charger works with a DC Bus of 12V and the inverter uses a 48V DC input. Nwt Npvp1 0 0 1 4 2 3 Npvp2 Nbatp 0 4 4 3 4 4 Ninv 8 8 8 ACS ($) ΔP (kW) SOC (%) 38,404 41,989 51,845 0.77 0.09 10.78 42.00 50.84 54.68 Figure 14. Evolution of the batteries SOC, the wind turbine and load power (kW) Analyses of the results lead to several conclusions: - The initial SOC is important in the design of the system. In order to reduce the maintenance, batteries are used between 40 and 90% of the rated energy storage, as presented in Figure 14. The initial SOC value was set to 50% and not 40% to allow short power consumption unforeseen in the morning. - To avoid intermittent power sources to let the system under-supply, batteries have been also oversized using final SOC > initial SOC as a criteria. More SOC margin can then be preferred in order to avoid a loss of power supply when having a higher power demand in the evening. - Solution number 1, shown in Table 5, has the lowest ACS but cannot satisfy the SOC constraint (final SOC >= 50%). - Solution number 2 ranked 2nd but meets the constraint set - Solution number 3 is most expensive while meeting the SOC constraint. However, it shows that even a 1kW wind turbine is not sufficiently cheap compared The system has been optimized with one objective function, namely the annualized cost of system (ACS) of the hybrid system subjected to the batteries characteristics and zero loss of power supply probability (LPSP) [25-28]. Five variables are considered here for the optimization as can be seen in Table 5. The GA configuration used a Population Size of 128, an Elite Count of 6, a Crossover Fraction of 0.8 and a Generations number limited to 50. Variables are evaluating in a restricted domain: LB = [0 0 0 0 0], UB = [10 20 20 200 10]. This integer problem could also have been solved using Design Of Experiment (DOE) instead of GA. However, due to the high number of cases to evaluate initially, around 8 million evaluations with a computation time of around 1s 342 [13] to photovoltaic panels. Indeed, the first acceptable solution including a wind turbine is around 10k$ more expensive. [14] E. Ortjohann, M. Lingemann, O. Omari,A. Schmelter, N. Hmasic, A. Mohd, W. Sinsukthavorn, D. Morton, "Modular Architecture for Decentralized Hybrid Power Systems", 13th Int. Power Electronics and Motion Control Conference (EPE-PEMC 2008), 2008. 6. CONCLUSION In this paper, we have first presented an analysis of the electrical energy situation in Senegal. Then a hybrid renewable energy system composed of renewable energy sources i.e. wind turbines, PV and batteries as store for an isolated site in MBoro, Senegal has been designed. The designed system was optimized with the objective to minimize the annualized cost of system (ACS) under constraints of components and with zero Loss of Power Supply Probability. If the cheapest solution is selected while satisfying the load demand and not violating the constraints, the solution with an ACS of $41,989 is the most viable economically. However, if a wind turbine is considered alongside PV to build a hybrid system, a 3rd solution is preferable but on the expense of more budget. [15] M. Starke, L. M. Tolbert, B. Ozpineci, "AC vs. DC Distribution: A Loss Comparison", [16] M. Starke, F. Li, L. M. Tolbert, B. Ozpineci, "AC vs. DC Distribution: Maximum Transfer Capability", [17] S. Roussain, "Bus Configurations in Hybrid Systems", Hybrid Info Summer, Issue 7, 2004. [18] M.K. Deshmukh, S.S. Deshmukh, "Modeling of hybrid renewable energy systems", Renewable and Sustainable Energy Reviews, Vol. 12, pp. 235-249, 2008. [19] D. Kalyanmoy. "An efficient constraint handling method for genetic algorithms", Computer Methods in Applied Mechanics and Engineering, Vol.186, No.2–4, pp. 311–338, 2000. [20] D. Kusum, K. Pratap Singh, M.L. Kansal, and C. Mohan, "A real coded genetic algorithm for solving integer and mixed integer optimization problems", Applied Mathematics and Computation, Vol.212, No.2, pp. 505–518, 2009. [21] http://www.solarcellsales.com/techinfo/docs/ SP130A.pdf, accessed January 2012. [22] http://www.solarcellsales.com/techinfo/docs/BP2.pdf, January 2012. [23] http://weole-energy.com/eolienne-gamme-weole-horizon.php, accessed February 2012. [24] http://www.batterymart.com/p-12v-75ah-sealed-lead-acidbattery.html, accessed February 2012. 7. REFERENCES [1] http://kropot.free.fr/energrenouv.htm, accessed Nov. 2011. [2] J. GIROD IEPE /CNRS, "le développement énergétique en Afrique Subsaharienne, après l’ère des réformes", pp. 63, Octobre 2010. [3] http://www.bonjourlafrique.com/ accessed Nov. 2011 [4] Ministère de l’énergie Sénégal, "Système d’Information Energétique du Sénégal (SIE)", Rapport 2007. [5] A. Diop, S.A. Sarr, "Lettre de Politique de Développement du Secteur de l’Energie (février 2008)", Ministre d’Etat, Ministre de l’Energie, Ministre de l’Economie et des Finances, Dakar, http://www.crse.sn/upl/LettrePolitique-2008.pdf, Sénégal, 2008. [6] www.aser.sn, Agence sénégalaise (2011), accessed June 2011. d’électrification [7] L. Seck, "Le développement de l’énergie éolienne au Sénégal", Colloque de TERNA, 2009. [8] Deutsche WinGuard GmbH, "Enquête sur le potentiel de vent et du rendement énergétique du parc éolien de Kayar au Sénégal", 2008. [9] I. Youm, J. Sarr, M. Sall, A. NDiaye and MM. Kane, "Analysis of wind energy potential along the northern coast of Senegal", Revue des énergies renouvelables, Vol. n°8, pp. 95-108, 2005. [10] E. Ortjohann, A. Mohd, A. Schmelter, N. Hamsic, M. Lingemann, "Simulation and Implementation of an Expandable Hybrid Power System", University of Applied Sciences South Westphalia/Division Soest, Lübecker Ring 2, 59494 Soest, Germany [11] C. Kirubi, C. et al., "Community-Based Electric Micro-Grids Can Contribute to Rural Development: Evidence from Kenya World Development" (2009), doi:10.1016/j.worlddev.2008.11.005 [12] G. Venkataramanan, C. Marnay, "A larger role for microgrids’ IEEE power and Energie magazine, May/Jun. 2008. S. Phrakonkham, J.Y. Lechenadec, D. Diallo, G. Remy, C. Marchand, "Review of Micro-Grid Configuration and Dedicated Hybrid System Optimization Software Tools: Application to Laos", Engineering Journal, Vol.14, Issue 3, pp. 15-34, July 2010. accessed [25] S. Phrakonkham, A. Kebe, G. Remy, D. Diallo, C. Marchand, "Optimized Sizing of AC Coupled Hybrid Sources for Isolated Villages", Congrès Electrotechnique du Futur, EF’2011, 14-15 Décembre 2011, Belfort, France, 2011. rurale [26] R. Belfkira, "Dimensionnement et optimisation de centrales hybrides de production d’énergie électrique à base d’énergies renouvelables : application aux sites isoles", PhD Thesis, Université du Havre, France, 2010. [27] P.D. Nguyen Ngoc, "Optimisation de systèmes de production intermittents non conventionnels couplés au réseau électrique ", PhD Thesis, INPG, France, 2010. [28] E. Koutroulis, D. Kolokotsa, A. Potirakis, K. Kalaitzakis, "Methodology for optimal sizing of stand-alone photovoltaic/windgenerator systems using genetic algorithms", Solar Energy, Vol.80, pp. 1072-1088, 2006. 343