LHC Program Status: Accelerator, ATLAS, CMS

advertisement
LHC Program Status:
Accelerator, ATLAS, CMS
Mike Tuts
Columbia University
September 8, 2005
Outline
z
Some physics benchmarks
z
z
Status of LHC accelerator
z
z
US contributions (LARP)
Status of ATLAS and CMS experiments
z
z
z
z
Higgs, SUSY
Focus on US activities
Maintenance and Operations
Computing
Future upgrades
z
z
Luminosity increases
Upgrade R&D
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
2
Physics at the LHC
z
You are all familiar with the compelling
physics case for the LHC
z Electroweak
symmetry breaking – Higgs?
z Supersymmetry - dark matter candidates?
z Nature of spacetime - large extra dimensions?
z…
z
Two large High pT experiments, ATLAS &
CMS, are reaching completion at CERN
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
3
LHC Accelerator
z
LHC: pp, √s = 14 TeV, L = 1034 cm-2s-1 (nominal design)
z
z
Start at 10fb-1/yr → 100fb-1/yr at nominal design
May be able to be pushed to 2.3 × 1034 without major upgrades
Time to
halve
statistical
errors
Integrated
luminosity
z Reach 1034 in
2011 then flat
„ Reach 2×1034
in 2016 then flat
Peak luminosity
for the year
Jim Strait: http://www.cerncourier.com/main/article/45/3/29/1
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
4
Higgs
z
A standard benchmark is the discovery potential for the
Standard Model Higgs
z
z
z
z
For MH greater than ~200GeV discovery comes soon (H→4l)
For MH < 200 may take a few years at low luminosity (many ch)
Plenty of experimental issues: calibration, Etmiss, uniformity,…
The challenge is to be ready on day one!
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
5
Higgs Sensitivity
z
ATLAS + CMS
combined cover the
full region of interest
with ~10fb-1
A. De Roeck,
http://susy- 2005.dur.ac.uk/PLENARY/SAT/deroeck_durham.ppt
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
6
Supersymmetry
CMS simulation
z
z
If the SUSY mass
scales is less than a
few TeV the LHC
should discover it
Using mSUGRA as a
model, we start to
cover an interesting
regions in a month,
and 1.5-2TeV within
the first year
I. Hinchliffe
http://susy-2005.dur.ac.uk/PLENARY/MON/hinchliffe.pdf
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
7
LHC Accelerator Status
CMS
LHCb
ALICE
ATLAS
From http://lhc-machine-outreach.web.cern.ch/lhc-machine-outreach/
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
8
LHC Machine - Dipoles
z
z
Dipole fabrication is past
the ½ way point (1232
total) – see LHC
“dashboard”
~100 dipoles are installed
in sector 8-1
Dipole magnets installed in tunnel
http://lhc-new-homepage.web.cern.ch/
lhc-new-homepage/DashBoard/index.asp
Dipole being lowered down shaft
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
9
LHC Machine - QRL
z
You may recall that
the last machine crisis
was the cryogenics
services line (QRL)
that had to be
repaired
z
z
QRL installed in tunnel, supports
For dipoles visible
Appears under control
Dipoles cannot be
installed until after
QRL is in
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
10
LHC Machine - Schedule
This schedule somewhat old,
but “readable” -- detailed
schedule at
http://sylvainw.home.cern.ch/
sylvainw/planning-follow-up/Schedule.pdf
September 8, 2005
From http://lhc-machine-outreach.web.cern.ch/lhc-machine-outreach/upcoming.htm
M. Tuts, P5 Meeting - LHC Status
11
LHC Machine Status
z
Objectives
z
z
z
Status
z
z
z
z
Finish installation by February 2007
First collisions in summer 2007
Industrial component production is consistent with this goal
Ramping up of QRL activities and magnet installation critical to
maintain schedule
Installation and interconnection of cryomagnets has started
Actions
z
z
z
Partial test of sector 7-8 in Fall 2005
Commissioning of sectors 7-8 & 8-1 in Summer 2006
Looking for external collaborators to help with commissioning
From Lyn Evans at HCP2005
http://indico.cern.ch/getFile.py/access?resId=0&materialId=slides&contribId=4&sessionId=3&subContId=0&confId=0512
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
12
z
z
z
z
z
z
LARP
US LHC Accelerator R&D Program
Delivered IR quads (photo below)
Fundamental accelerator physics
Commissioning of the accelerator
Beam instrumentation, tune feedback, and collimation
Superconducting Nb3Sn magnet R&D for upgrade and
demonstration of viability of large-aperture, high-field, long IR
quadrupoles
T. Ferbel HEPAP 7/11/2005 http://www.science.doe.gov/hep/HEPAP/July2005/Ferbel_HEPAP_05.pdf
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
13
Experiments: CMS & ATLAS
z
z
Two high pT detectors: CMS, ATLAS
Major participation by US groups
z
z
z
Construction project nearly complete
z
z
z
Total $250M (DOE) + $81M (NSF) –capped
>97% complete this month (CD4A)
Research Program ramping up
z
z
z
~30% of overall CMS (~310 physicists and climbing)
~20% of overall ATLAS (~240 physicists and climbing)
M&O, Computing, Upgrade R&D
FY05 $36.6M → FY08 $66M (ATLAS + CMS)
Core program supports physicists
z
Critical to the success of the physics goals
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
14
US Research Program Funding
z
Guidance provided by DOE & NSF
From T. Ferbel HEPAP July 11, 2005 presentation
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
15
CMS
z
CMS = Compact Muon Solenoid
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
16
CMS Status
z
z
z
z
CMS being
assembled in above
ground SX5 bldg
Solenoid recently
rotated for insertion
Cool down end of
year
Start lowering April
2006
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
17
US CMS
z
43 US Institutions
z
Endcap Muon (EMU)
z
z
Hadron Calorimeter (HCAL)
z
z
Boston, UC Davis, UCLA, US San Diego, Caltech, FNAL, Florida, Iowa,
Maryland, MIT, Ohio State, Princeton, Rice, Wisconsin
EM Calorimeter (ECAL)
z
z
Boston, Fairfield, FNAL, Florida International, Florida State, Florida Tech,
Illinois Chicago, Iowa, Iowa State, Maryland, Minnesotta, Mississippi,
Nebraska, Notre Dame, Princeton, Purdue, Rochester, Texas Tech
Trigger & Data Acquisition (TriDAS)
z
z
UC Davis, UCLA, UC Riverside, Carnegie Mellon, FNAL, Florida, Florida
Tech, Northeastern, Ohio State, Purdue, Rice, Wisconsin
Caltech, FNAL, Minnesota, Northeastern, Princeton, Yale
Tracking - Forward Pixels (FPIX) & Silicon Tracker (SCT)
z
September 8, 2005
Brown, Colorado, Cornell, UC Davis, UC Riverside, UC Santa Barbara,
FNAL, Illinois Chicago, Iowa, Johns Hopkins, Kansas, Kansas State,
Louisiana Tech, Mississippi, Nebraska, Northwestern, Purdue, Rochester,
Rutgers, Texas Tech, Vanderbilt, Virginia
M. Tuts, P5 Meeting - LHC Status
18
US CMS M&O Manpower
M&O Manpower
160
z
The research
program supports
technical manpower
Core program
generally supports
physicists
z
140
120
100
Manpower
z
Phys-M&O
Engr-M&O
Tech-M&O
80
60
40
20
0
03
04
05
06
07
FY
Fermilab hosts US
CMS physics center
(LPC) to mitigate
travel costs
From D. Green
http://uscms.fnal.gov/uscms/review/review2005c/presentations/Green-LEH_RP_08_05.ppt
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
19
CMS – HCAL & CSC
z
z
CSC w/ electronics
on YE
HF (Forward)
assembled in Bldg 186
September 8, 2005
HCAL Commisioning
underway
Endcap CSC done,
being installed &
commissioned (~2/3)
HO (outer)
Panels installed
M. Tuts, P5 Meeting - LHC Status
HB (barrel)
absorber complete
HE (end)
absorber complete
20
CMS Commissioning
z
Single muon track in
CSC
z
First muons seen by
CMS
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
21
CMS - Tracking
z
z
z
Strong Silicon tracker
group
TOB module
production ramped up
(40% complete);
excellent yield
Strong FPIX team;
start production end
2005
September 8, 2005
Tracker outer Barrel (TOB)
M. Tuts, P5 Meeting - LHC Status
22
Overall CMS Detector Status
z
z
z
z
z
z
z
US CMS deliverables >97% complete
Magnet – some delay, complex cabling
HCAL – progressing well
Muon – DTs install & commission; RPCs going
well; CSCs 2/3 installed
ECAL – crystal production critical
Tracker – new organization in place, aim for
commissioned TK by Nov 2006
TriDAS – on schedule
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
23
ATLAS
z
ATLAS = A Toroidal Lhc ApparatuS
MAGNETS
Central Solenoid
8 Barrel Toroids
End Cap Toroids
INNER DETECTOR
Pixels
Silicon Strip
Transition Radiation Tracker
CALORIMETERS
MUON SYSTEM
Monitored Drift Tubes
Cathode Strip Chambers
Resistive Plate Chambers
Thin
Gap8,Chambers
September
2005
Diameter 25m
Length 46m
Weight 7,000 tons
M. Tuts, P5 Meeting - LHC Status
EM - Liquid Argon – Lead
HAD - Scintillator Tile
24
ATLAS Status
z
z
Major milestone with
8th Barrel Toroid (BT)
installed in pit
Barrel calorimeter
being commissioned
in pit
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
25
ATLAS – BT & ECT
z
z
All 8 BT installed, functional test by end 2005
End Cap Toroids (ECT) being assembled,
install in pit 4/06, 2nd one 6/06
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
26
US ATLAS
z
34 Institutions
z
Inner Detector
z
z
z
Tile Calorimeter (TileCal)
z
z
Arizona, BNL, Columbia, Pitt, SMU, Stony Brook
Muon System (EMU)
z
z
ANL, Chicago, UIUC, MSU, UT Arlington
Liquid Argon Calorimeter (LAr)
z
z
Silicon: LBNL, Iowa State, New Mexico, UCSC, Ohio State,
Oklahoma, Albany, Wisconsin
TRT: Duke, Hampton, Indiana, Penn, Yale
Arizona, BNL, Boston, Brandeis, Harvard, UC Irvine, UMass,
Michigan, MIT, Stony Brook, Tufts, Washington,
Trigger and Data Acquisition (TDAQ)
z
September 8, 2005
ANL, UC Irvine, MSU, Wisconsin
M. Tuts, P5 Meeting - LHC Status
27
US ATLAS M&O Manpower
Sr. Scientist
Administrator
Designer
Comp.Prof.
Tech
EE
ME
Gen Lab
M&O FTEs
60.0
z
Technical manpower
is generally supported
by the Research
program
Physicists by the core
program
z
Recent preliminary
survey (use % of
research time)
50.0
40.0
FTEs
z
30.0
20.0
10.0
0.0
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Fiscal Year
US ATLAS M&O Manpower
Sumof Val ue
600
500
66
400
80
97
76
85
300
200
100
75
30
100
0
63
46
37
66
62
40
37
101
111
142
146
86
89
FY08
FY09
52
Pr ogr am
Type
82
Non-ATLAS- Seni or Sci enti st
Non-ATLAS- Postdoc
ATLAS- Student
58
111
Non-ATLAS- Student
128
ATLAS- Seni or Sci enti st
ATLAS- Postdoc
87
38
58
76
FY05
FY06
FY07
Year
US ATLAS physicists + redirection
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
28
ATLAS – Calorimeters
z
z
z
Comissioning of Liquid
Argon Calorimeter (LAr)
and Tile Calorimeter
(TileCal)
First underground cosmic
events in TileCal!
End Calorimeters (EC): 1
ready (10/05 to pit), other
cooling down (12/05 to
pit)
Barrel Calorimeters
End Calorimeter
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
29
ATLAS - Muons
z
z
z
z
Huge system, high
precision
RPCs and TGCs are well
in production (for trigger)
MDTs and CSCs being
commissioned
Big Wheel C installed
5/06; Small wheels
lowered into pit 11-12/06;
Big wheel A installed 4/07
September 8, 2005
Muon big wheel sector
M. Tuts, P5 Meeting - LHC Status
Chamber installation
30
ATLAS – Inner Detector
z
z
z
z
Progress in 3 layers of
pixels but float lost in
problems
Silicon tracker (SCT)
module mounting on 4
cylinders
Transition Radiation
Tracker (TRT) barrel
modules mounted
Lower barrel ID into pit
3/06; ID installed & tested
10/06
September 8, 2005
Silicon Tracker
Pixel disk
M. Tuts, P5 Meeting - LHC Status
TRT Barrel
31
Overall ATLAS Detector Status
z
z
z
z
z
z
z
z
US ATLAS deliverables >97% complete
Magnets – solenoid tested in LAr cryostat, barrel toroids
installed, endcap toroids being assembled
Calorimeter – barrel installed, one endcap ready, other
under test, electronics delays
Tile Calorimeter – barrel being commissioned, extended
barrels assembly this year
Muon System – chamber production on track, installation
started
Inner Detector – significant progress but pixel schedule
tight, TRT being commissioned
TDAQ – generally on schedule
Ready for beam 4/11/07!
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
32
Computing
The Research Program contains the computing
z Similar overall structure for CMS & ATLAS
z
z Tier
0 (at CERN)
z Raw
z Tier
data, reconstruction
1 (National Centers)
z Each
host part of raw data, re-reconstruction, derived
data sets, analysis
z FNAL (US CMS one of ~6): total CMS need in 2008 is 15
MSI2k; 7PB (note different running assumptions than
ATLAS)
z BNL (US ATLAS one of ~10): total ATLAS need in 2008
is 24 MSI2k; 14 PB
September 8, 2005
z Tier
M. Tuts, P5 Meeting - LHC Status
2 (“Regional” Centers)
33
US ATLAS Computing
z
Large effort going into preparing facilities and
user support for data taking
z
z
Ramp up of T1 and T2 underway
Projected US needs exceed target funding
z
Will require application of Management Reserve
FY06
FY07
FY08
FY09
CPU T1 (MSI2k)
1.1
2.7
8.0
14.3
CPU T2 (MSI2k)
2.2
5.2
6.5
8.3
Disk T1 (PB)
0.5
1.7
4.6
6.9
Disk T2 (PB)
0.6
1.7
2.5
3.5
FTE
52
64
64
66
11.3
15.8
18.6
18.6
Funding AY M$
ATLAS Comp TDR
http://doc.cern.ch//archive/electronic/cern/preprints/lhcc/public/lhcc-2005-022.pdf
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
34
US CMS Computing
z
z
z
z
Significant US leadership in overall CMS computing
Ramp up 0f 7 Tier 2s, including DISUN T2Cs and Tier 1
center
Projected US needs exceed target funding – no reserve
Network being put in place
CPU T1 (MSI2k)
FY06
FY07
FY08
0.7
1.8
4.3
CPU LPC-CAF (MSI2k)
3.0
CPU T2 (MSI2k)
7.0
Disk T1 (PB)
0.1
0.7
2.0
Disk LPC-CAF (MSI2k)
0.5
Disk T2 (PB)
1.4
FTE
Funding AY M$
FY09
62
64
66
66
14.9
16.4
17.5
17.5
CMS computing TDR
http://doc.cern.ch//archive/electronic/cern/preprints/lhcc/public/lhcc-2005-023.pdf
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
35
Grid Computing
z
Grid3 was a success
z
z
z
Produced 1/3 events for ATLAS
data challenge
… but need less manpower
intensive production system
Grid3 evolving to Open Science
Grid (OSG)
z
national production-quality grid
computing infrastructure for large
scale science, built and operated
by a consortium of U.S.
universities and national
laboratories
z
z
z
http://www.opensciencegrid.org/index.php?option=com_frontpage&elMenu=Home
~14,000 CPUs comparable to
LHC Computing Grid
LHC experiments may be initial
drivers but more sciences coming
on board
Funding mechanisms being
developed
http://lcg.web.cern.ch/LCG/
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
36
US Research Program Issues
z
ATLAS & CMS
z
z
Management Reserve below committee recommendation of 20%
(<10%)
Rapid growth in additional collaborators; pressure on RP funding
from “common costs” share (by PhD)
z
z
Incremental travel/COLA costs place large burden on core
program funding (US ATLAS ~2 M$/yr, US CMS ~2.6 M$/yr) –
next slide has more details
z
z
z
Slow progress, but directorate aware
Housing and office space at CERN
z
z
Analysis and support centers attempt to mitigate
US CMS also planning remote operations center
Getting good collaborative tools at CERN
z
z
particularly acute for CMS (estimate >$1M/yr additional)
New hostel in a few years
Raised at Orbach CERN visit – establish a “US LHC User’s
Group”?
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
37
US Travel/Cola
z
z
z
z
We have been asked by the agencies to understand the incremental costs
of travel and cost of living support at CERN – preliminary results
ATLAS $1.9M(FY05$) shortfall in FY09
CMS $1M COLA + $1.6M Travel
Some attempt to mitigate these travel costs through
z
z
US CMS: LPC and Remote Operations Center at Fermilab
US ATLAS: 3 Analysis Support Centers at LBNL, ANL, BNL
Sumof Val ue
6000
5000
986
1060
1254
4000
Pr ogr am
1412
From preliminary
ATLAS survey
Type
3000
Non-ATLAS- Tr avel FY05k$
1606
2000
3565
4264
4071
ATLAS- Tr avel FY05k$
2928
1000
1763
0
FY05
FY06
FY07
FY08
FY09
Year
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
38
Upgrade – Physics Motivation
z
Consider only luminosity upgrade
z
z
Extend LHC mass reach by ~30%
z
z
z
z
SM parameters, Higgs couplings
Parameter measurements for new physics (e.g. SUSY)
More demanding on detector upgrade because of pileup
environment
Increased sensitivity to rare processes and rare decay
modes
z
z
Less demanding on detector upgrade because of robust signals
Improve on precision measurements
z
z
1034 → 1035 cm-2s-1
More demanding on detector upgrade because of pileup
environment
Both ATLAS and CMS have held a number of recent
upgrade workshops
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
39
LHC vs SLHC
z
Studies have started under the following assumptions (ATLAS)
z
Note that bunch spacing is not settled and has significant impact on
electronics and pile-up
See for example ATLAS Upgrade Workshops (Genoa July 18, 2005)
http://agenda.cern.ch/fullAgenda.php?ida=a053875
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
40
Upgrade - Timescales
z
Luminosity increase demands new tracker upgrades for
both experiments
z
z
Working backwards (approximately)…
z
z
z
z
z
And other potential system upgrades
~2015 Machine upgrade (IR quads replaced), tracker installation
~2010 Tracker construction start
~2009 Final design TDR
2005 R&D start
These are complex detectors with issues that demand
long lead times to solve – R&D must get underway now
z
Issues: stave development, 3D pixels, stripixels, new
materials,…
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
41
CMS Upgrade
z
z
z
Replace Tracker
Rebuild L1 Trigger processors
Only VERY rough cost estimates available
z
z
z
Tracker ~ 100-200 MCHF
Other systems ?
US fraction? ~1/3? ⇒ $50M
From G. Hall at July 2005 ATLAS Upgrade Workshop
http://agenda.cern.ch/askArchive.php?base=agenda&categ=a053875&id=a053875s4t1/transparencies
FY05
US R&D 215
September 8, 2005
FY06
FY07
FY08
FY09
530
623
683
761
M. Tuts, P5 Meeting - LHC Status
42
ATLAS Upgrade
z
z
z
Principal upgrade – replace inner detectors (silicon +
TRT → Si pixel + short strips/ stripixel + outer
microstrips)
Other systems sensitive to increased radiation levels and
pile-up, e.g. calorimeter electronics
Only VERY rough cost estimates available
z
z
z
Tracker ~ 180 MCHF
Other systems ?
US fraction? ~20%?
Partly from G. Darbo report on ATLAS Upgrade Workshop 8/3/05
http://agenda.cern.ch/askArchive.php?base=agenda&categ=a054316&id=a054316s1t1/transparencies
US R&D
September 8, 2005
FY05
FY06
FY07
FY08
FY09
500
2,500
2,107
3,237
3,237
M. Tuts, P5 Meeting - LHC Status
43
Conclusions
z
z
Construction Projects are winding down,
Research Programs are ramping up
Accelerator seems on schedule for 2007 start
z
z
CERN management seems committed to that date
Challenges of Research Program
z
z
z
Funding remains tight
Commissioning – now!
Preparation for physics
z
z
z
z
Analysis models & collaborative tools
Core program support (travel/COLA, students)
Upgrade R&D required now
2007 is not far away!
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
44
Backup Slides
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
45
The “Real” Accelerator Schedule
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
46
ATLAS Schedule
ID
Name
Duration
Start
14
1
30
PHASE 1: Infrastructure
Experimental Cavern UX15
542 days
542 days
Fri 4/4/03
Fri 4/4/03
154
PHASE 2: Barrel Toroid & Barrel Calorimeter
672 days
Wed 9/3/03
155
Phase 2a: ATLAS Bedplates and Feet
174 days
Wed 9/3/03
166
Phase 2b: Barrel Toroid
430 days
Mon 3/15/04
450
Phase 2c: Barrel Calorimeter
592 days
Wed 1/7/04
298 days
285 days
Mon 8/16/04
Mon 8/22/05
717
780
781
Phase 2d: Racks, Pipes & Cables
PHASE 3: End-cap Calorimeters & Muon Barrel
833
Phase 3a: Pipes & Cables
Phase 3b: Endcap Calorimeter C
230 days
246 days
Mon 8/22/05
Tue 9/6/05
971
Phase 3c: Muon Barrel
148 days
Tue 8/30/05
231 days
246 days
Thu 11/3/05
Mon 12/5/05
101 days
Mon 12/5/05
189 days
181 days
Wed 3/1/06
Mon 3/20/06
1221
1372
1373
1477
1509
Phase 3d: Endcap Calorimeter A
PHASE 4: Big Wheels C, Inner Detector
Phase 4a: Big Wheels, side C
Phase 4b: Inner Detector
PHASE 5: End-cap Toroid
1510
Phase 5a: Flexible chains
65 days
Thu 4/13/06
1519
Phase 5b: End-Cap Toroid A
Phase 5c: End-Cap Toroid C
121 days
122 days
Mon 3/20/06
Fri 6/9/06
54 days
Tue 10/24/06
33 days
42 days
5 days
Tue 10/24/06
Fri 11/10/06
Tue 11/28/06
1558
1601
1602
1632
1670
1671
PHASE 6: Beam Vacuum, Small Wheels, Start closing
Phase 6a: Beam Vacuum & Small Wheels, side A
Phase 6b: Beam Vacuum & Small Wheels, side C
Full Magnet Test
1672
PHASE 7: Big Wheels A, Forward Shielding & End wall chambers
Phase 7a: Big Wheels, side A
175 days
148 days
Wed 8/30/06
Wed 8/30/06
1775
Phase 7b: Forward Shielding & End wall Chambers (EO)
82 days
Wed 1/17/07
1821
Phase 7c: Beam Pipe closing and bake-out
Beam Pipe closed
11 days
0 days
Wed 4/4/07
Wed 4/11/07
1836
1841
1842
Global Commissioning
ATLAS Ready For Beam
60 days
0 days
Tue 12/5/06
Wed 4/11/07
1843
Cosmic tests
40 days
Wed 3/7/07
September 8, 2005
M. Tuts, P5 Meeting - LHC Status
April 2003
15
16
17
M
18
19
47
ATLAS Computing Timeline
2003
• POOL/SEAL release (done)
• ATLAS release 7 (with POOL persistency) (done)
• LCG-1 deployment (done)
2004
• ATLAS complete Geant4 validation (done)
• ATLAS release 8 (done)
• DC2 Phase 1: simulation production (done)
2005
• DC2 Phase 2: intensive reconstruction (only partially done…)
• Combined test beams (barrel wedge) (done)
• Computing Model paper (done)
2006
• Computing Memoranda of Understanding (ready for signatures)
• ATLAS Computing TDR and LCG TDR (done)
• Computing System Commissioning
2007
September 8, 2005
• Physics Readiness Report
• Start cosmic ray run
• GO!
M. Tuts, P5 Meeting - LHC Status
48
Download