1 CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT Facilities Planning & Management Department August 23, 2011 Addendum No. 1 REQUEST FOR INFORMAL BID NO.: 11-12-01 nd 2 Floor Training Room Remodel, 7600 Dublin Center All Prospective Bidders: This addendum is issued to clarify, add, delete, correct and/or change the contract documents to the extent indicated and is hereby made a part of the above noted contract documents on which the contract will be based. Any modifications/changes made by this addendum affect only the portions or paragraphs specifically identified herein; all remaining portions of the proposal to remain in force. It is the responsibility of all bidders to conform to this addendum. Acknowledge receipt of this addendum in the space provided on the bid form. Failure to do so may subject Bidder to Disqualification. The original Bid Documents are modified by the revision as follows: 1. Notice of Change: SPECIFICATIONS Item Specification Section Description AD1.1 Bid Documents Subcontractors List: Deleted reference to Howell Electric, Inc AD1.2 Terms and Special Conditions of Contract for Labor and Materials Replace Paragraph 3.2-A with the following: Delayed Substantial Completion Milestone-Training Room 285 and IDF Room 2.6. If the contractor fails to achieve Substantial Completion of Training Room 285 and IDF Room 2.6 by November 1, 2011, including adjustments thereto, in accordance with the Contract Documents, the Contractor shall be subject to assessment of Liquidated Damages in the amount of Five Hundred Dollars ($500) per calendar day from November 1, 2011 until Substantial Completion of Training Room 285 and IDF Room 2.6 is achieved. Replace Paragraph 19.2 with the following: The Contractor shall be responsible for obtaining approvals from permitting and approval agencies, including the City of Dublin. District 5020 Franklin Drive, Pleasanton, California 94588 will reimburse Contractor for permit fees assessed by permitting and approval agencies, including the City of Dublin. DRAWINGS Item Addendum Dwg. No. Sheet AD1.3 AD1.4 A0.3A A0.3B AD1-A0.3A AD1-A0.3B Description Revised scope of work Revised scope of work Sketches 1 None BIDDER QUESTIONS 1 Bid Question 1 Question: Is this a prevailing wage project? Howell Electric is unable to perform a prevailing wage project. Our last project with Chabot College was not. Answer: All public works projects at the District are Prevailing Wage projects and must adhere to the Public Contract Code. The other project you are referring to did not administered through this office. Respondent: Victoria Lamica, CLPCCD 2 Bid Question 2 Question: Is there a clean document (drawing) to access? Answer: Contact Victoria Lamica to obtain a clean document. Respondent: Victoria Lamica, CLPCCD END OF ADDENDUM #1 5020 Franklin Drive, Pleasanton, CA 94588 If you have any questions regarding this Addendum No.1, please contact the Office of the Facilities Planning & Management in writing, via email. All other terms and conditions of Request for Informal Bid No. 11-12-01 to remain the same. Regards, Victoria L. Lamica Contracts Manager vlamica@clpccd.org C: Bid File 5020 Franklin Drive, Pleasanton, CA 94588 CHABOT LAS POSITAS COMMUNITY COLLEGE DISTRICT 7600 DUBLIN CENTER 2ND FLOOR TRAINING ROOM REMODEL SECTION 1: PROGRAM 2.1 TRAINING ROOM 270 AND CLOSETS A & B: TRAINING ROOM FOR FLEXIBLE LECTURE FORMAT. POWER IN FLOOR PROVIDES FLEXIBILITY IN SEATING ARRANGEMENTS. DATA IS NOT REQUIRED FOR FLOOR BOXES . 2.2 SUITE 265 2.3 2.4 TRAINING ROOM 285 BREAKROOM 287 2.5 2.6 2.7 STORAGE ROOM 285A IDF ELECTRICAL ROOM SECTION 2: PRODUCTS FINISHES CARPET BASE PAINT FLOORING CEILING TILE EXISTING SUITE 265 IS SUBDIVIDED TO CREATE SUITE 270. SUITE 265 IS REESTABLISHED WITH A SMALLER AREA. ROOM TO ACCOMMODATE STANDARD CLASSROOM TABLES FOR APPROXIMATELY 32. THE DEMISING WALL ADDED TO CREATE THE TRAINING ROOM, PROVIDES ADDITIONAL AREA FOR BOTH A BREAKROOM AND STORAGE. SEE 2.4 ST RECONFIGURE THE CURRENT BREAKROOM WHICH OVERLAPS IDF ON 1 FLOOR. ACCOMMODATE REMOVAL AND NEW POWER IN TRAINING ROOMS; IDF, BREAKROOM ETC. TANDUS; HAPHAZARD 03366 ; 6’ ROLL GOODS: IN 265, REUSE EXISTING ALL BUT 265: RUBBER BASE: BURKE 523 BLACK BROWN IN 265, MATCH EXISTING TRAINING ROOM AND CLOSETS: KM # 41 SNIP OF TANNIN LRV 63; BREAKROOM, STORAGE AND IDF: KM # 42 WISE OWL LRV 51 SUITE 265: PAINT TO MATCH REMAINING WALLS ACCENT : KM #73 CORTEZ LRV 13 ST BREAKROOM AND STORAGE: MATCH EXISTING 1 FLOOR BREAKROOM; IDF: RETAIN EXISTING ARMSTRONG “MINABOARD GEORGIAN, 2X4, OR MATCH EXISTING, SUCH AS IN SUITE 270 KITCHEN CABINETS SALVAGE AND REUSE EXISTING KITCHEN BASE AND WALL CABINETS FROM SUITE 270 KITCHENETTE; PROVIDE NEW COUNTER TOP TO MATCH CURRENT (AT CONTRACTORS OPTION, EXISTING COUNTERTOP CAN BE REUSED IF IT IS NOT DAMAGED DURING THE REMOVAL.. METAL STUDS/ GYPSUM BD. 3 5/8” X 18 GA METAL STUDS @ 16” O/C WITH 1 LAYER OF 5/8” TYPE X GYPSUM TYPICAL AND 2 LAYERS 5/8” GYP WALL BD EACH SIDE, ATTACH WITH #6 SMS @ 8” O.C EDGE AND 12 O.C. FIELD. HARDWARE PROVIDE CODE COMPLIANT HARDWARE; HARDWARE IS TO MATCH EXISTING ST HARDWARE CURRENTLY LOCATED ON THE 1 FLOOR DISTRICT OFFICES. WHITEBOARD AND ELECTRONIC SMART BD OWNER-PROVIDED, GC INSTALLED. GC TO PICK UP FROM LPC WAREHOUSE AND INSTALL POWER PROVIDE AND/OR REPLACE ALL LIGHT SWITCHES WITH ROCKER STYLE IF NOT CURRENTLY INSTALLED. FLOOR: EVOLUTION 6AT, ONE CIRCUIT FOR EVERY 2 POKETHRUS; ST MECHANICAL SEE 1 FLOOR CLASSROOM, MATCH CONTROLLER, SUPPLY AND RETURN GRILLS AS NECESSARY PLUMBING CONNECT TO EXISTING WET WALL; DOWNTIME FOR EXISTING BREAKROOMS ON OTHER FLOORS IS A MAXIMUM OF 1 CALENDAR DAY. IF RESTROOMS INVOLVED, WORK MUST BE DONE DURING NON-BUSINESS HOURS. LIGHT FIXTURES CLEAR PRISMATIC FLUORESCENT FIXTURE LENS SIMILAR TO THOSE CURRENTLY IN ST SUITE 265 OR MATCH 1 FLOOR CLASSROOM EMERGENCY/EXIT LIGHTS PROVIDE EMERGENCY LIGHT AND LED EXIT LIGHT; PREFER INTEGRATED UNIT ST SIMILAR TO 1 FLOOR CLASSROOM. FLOOR POWER BOX LEGRAND EVOLUTION SERIES POKE-THOUGH DEVICES, 6AT SERIES SPEAKERS/PROJECTOR BRACKET AND PROJECTION SCREEN PROVIDE AND INSTALL RECESSED CEILING SPEAKERS -TANNOY CMS501 BM PER MANUFACTURER’S RECOMMENDATIONS; PROVIDE AND INSTALL PROJECTOR BRACKET ST SIMILAR TO 1 FLOOR CLASSROOMS, IN COMPLIANCE WITH CODE; PROVIDE AND INSTALL MOTORIZED PROJECTION SCREEN, RECESSED IN CEILING – Da-Lite Screen Company OR EQUAL, 120” in 285 and 144” in 270 WITH 16:10 ASPECT RATIO. ROOFING FOR ALL ROOF PENETRATIONS, PATCH ROOF IN ACCORDANCE WITH MANUFACTURER INSTRUCTIONS TO ENSURE ROOF WARRANTY IS MAINTAINED. SECTION 3: SCOPE OF WORK GENERAL: All work to be compliant with current codes for the City of Dublin. Architectural 1. General Scope of Work: Provide all engineering, submittals, shop drawings, labor, materials, apparatus, tools, equipment, transportation, temporary construction, and special services as required for the ARCHITECTURAL Work as called for in the Contract Drawings and Specifications. Specifications as noted herein and on the drawings are specific requirements for this scope of work. Architectural, as defined, shall include but not limited to all walls, ceilings, insulation, finishes, accessories, cabinets, doors and hardware. In general, this scope of work shall include the following: all engineering required to accommodate demolition and removal of components no longer required and new work. Review existing conditions and provide field verifications insuring that existing walls, floors and ceilings remain code-compliant. Do not begin demolition until you have identified all conditions to adjoining tenant spaces and hallways. It is the responsibility of the contractor to control and secure the areas of work. Demo will include removal and disposal per City of Dublin requirements. Unless otherwise indicated, all materials and finishes to be installed per manufacturers recommendations The contractor shall include all acoustic controls between adjacent tenant spaces and public areas such as hallways. The contractor shall provide record drawings at the completion of project showing all changes that were completed within this contract in PDF and CAD format. Mechanical and Plumbing 1. General Scope of Work: Provide all engineering, submittals, shop drawings, labor, materials, apparatus, tools, equipment, transportation, temporary construction, and special services as required for the MECHANCIAL and PLUMBING Work as called for in the Contract Drawings and Specifications. Specifications as noted herein and on the drawings are specific requirements for this scope of work. Mechanical systems, as defined, shall include all duct work, VAVs, diffusers, thermostats, controls, air & water balance, Ductless Split System, condensate pump, DX piping and coring. In general, this scope of work shall include the following: all engineering required to accommodate demolition and removal of components no longer required and new mechanical work. Review existing conditions and provide field verifications insuring that existing systems and HVAC systems downstream of your work remains operational. Do not disconnect services until you have identified all services and what they serve and have obtained approval to do so. It is the responsibility of the Mechanical contractor to safe off, cap, and demo of all MECHANICAL equipment, fixtures, piping, accessories, etc. as needed to accommodate new layout. Demo may include removal and disposal of existing duct work, thermostat control wire/boxes, diffusers, etc. The Mechanical contractor shall provide labeling for all new work. Labeling includes tags for valves, VAVs, etc. nd Ensure all 2 floor HVAC systems are functioning at completion of renovation. The Mechanical contractor shall provide record drawings at the completion of project showing all changes that were completed within this contract in PDF and CAD format. Electrical 1. General Scope of Work: Provide all engineering, submittals, shop drawings, labor, materials, apparatus, tools, equipment, transportation, temporary construction, and special services as required for the ELECTRICAL Work as called for in the Contract Drawings and Specifications. Specifications as noted herein and on the drawings are specific requirements for this scope of work. Electrical systems, as defined, shall include all power, lighting, fire alarm, grounding and raceways/boxes and as required for all low voltage work. In general, this scope of work shall include the following: all engineering required to accommodate demolition and removal of components no longer required and new electrical work, new circuits, relocation of electrical circuits, installation of new breakers, and grounding. Review existing conditions and provide field verifications insuring that existing systems and power downstream of your work remains operational. Do not disconnect services until you have identified all circuits and what they serve and have obtained approval to do so. It is the responsibility of the ELECTRICAL contractor to safe off, cap, and demo of all ELECTRICAL equipment, fixtures, piping, accessories, etc. as needed to accommodate new layout. Demo will include removal and disposal of existing circuit wire(s)/cable(s)/conduit(s) back to existing electrical panel or low voltage termination point. Intercept, extend, relocate and/or reconnect existing lights to accommodate layout adjustments, circuits and occupancy sensor. Relocated and reconnect existing or provide and install emergency lights per code. Relocate and reconnect existing or provide and install fire alarm devices to accommodate new layouts All penetrations of rated walls to re-establish rated assembly. Provide and install junction box, stub 3/4” conduit and to ceiling to accommodate all power in new and existing walls. Provide and install 4-11/16” J boxes and stub 1 ¼” conduit to ceiling space at all data locations. The Electrical contractor shall include all audio visual conduits including empty 4 – 11/16” J boxes and 2” conduit to ceiling space to accommodate new Smartboards, teaching stations and AV equipment. Provide power above the ceiling to the projection screen motors and for wireless connectivity equipment. The Electrical contractor shall include all Fire Alarm scope as required to accommodate new layout. The Electrical contractor shall include all Telecomm/Data Conduit and Grounding. The Electrical contractor shall assume that the existing electrical panel(s) located on the 2nd floor will have adequate spares and circuits to accommodate new electrical scope. The Electrical contractor shall provide labeling for all new work. Labeling includes fire alarm devices, light fixtures, electrical outlets, etc. nd Ensure all 2 floor Power, Lighting and Fire Alarm systems are functioning at completion of renovation. The Electrical contractor shall provide record drawings at the completion of project showing all changes that were completed within this contract in PDF and CAD format. 1 Fire Suppression System 1. General Scope of Work: Provide all engineering, submittals, shop drawings, labor, materials, apparatus, tools, equipment, transportation, temporary construction, and special services as required for the FIRE SUPPRESSION SYSTEM Work as required to accommodate new layout. It is the responsibility of the Plumbing contractor to safe off, cap, and demo of all Plumbing equipment, fixtures, piping, accessories as needed to accommodate new layout. Connect Plumbing in existing wet wall; downtime for existing breakrooms on other floors is a maximum of 1 calendar day. if restrooms involved, work must be done during non-business hours. The Mechanical Contractor shall include Air and Water Balancing. The Mechanical contractor shall include all Control scope as required to accommodate new layout. The Mechanical contractor shall include coordinate with electrical contractor to determine power requirements for Ductless Split System. 2 1 3 1. 08.22.2011 ADD. #1 HARDWARE 2.1 TRAINING ROOM 270 ARCHITECTURAL SALVAGE FINISHES FLOORS WALLS CEILING PARTITIONS COORDINATE WITH MECHANICAL. ELECTRICAL, PLUMBING, AV, TECHNOLOGY, FIRE SPRINKLERS 1. KITCHEN CABINETS, SINK AND FAUCET TO BE USED IN NEW BREAKROOM 2. 3. 4. 5. REMOVE EXISTING FLOORING MATERIAL AND BASE TO BARE CONCRETE; REMOVE ALL EXISTING FLOOR MONUMENTS; PATCH; PROVIDE AND INSTALL NEW CARPET AND BASE CLEAN, PATCH AND PAINT INCLUDING PRIME AT NEW WALLS AND INFILL OF WALL AREA REVISE AND MATCH EXISTING CEILING TILE AND REWORK EXISTING CEILING GRID: ACCOMMODATE ALL SYSTEMS SUCH AS AV, AUTOMATIC SPRINKLER SYSTEM RECONFIGURATION, SPEAKERS, TECHNOLOGY, LIGHTING AND POWER 6. 7. 8. 9. 10. 11. 12. 13. 14. DOORS INSULATION FIT-UP MECHANICAL DISTRIBUTION CONTROLS 15. REVISE DOOR LOCATION AND CONFIGURATION PER PLANS; PROVIDE AND INSTALL HARDWARE 16. ALL NEW WALLS CONTIGUOUS WITH ADJACENT SUITES TO HAVE ACOUSTIC BATT INSULATION AND SEALANTAT PENETRATIONS 17. WHITEBOARDS PER PLANS 1. REVISE CEILING SUPPLY AND RETURN DUCTS, EQUIPMENT AND DIFFUSERS/GRILL FOR INDEPENDENT OPERATION OF SUITE PER CODE; CLEAN DUCTWORK; 2. RELOCATE PER PLANS AND CONFIRM CONTROLS OPERATION. ELECTRICAL POWER FLOORS, 1. WALLS, 2. CEILINGS and ABOVE CEILING 3. 4. 5. EQUIPMENT 1. 2. 3. 4. LIGHTING FIXTURES DEMOLISH EXISTING KITCHEN AREA, RETAINING FURRED WALL TO ADJOINING SUITE 275. DEMOLISH OFFICE WALLS ADD NEW FLOOR TO DECK DEMISING WALL BETWEEN SUITE 270 AND 265. IF CURRENT DEMISING WALL TO SUITE 275 DOES NOT EXTEND TO CEILING, EXTEND FURRED WALL TO UNDERSIDE OF DECK WITH ACOUSTIC BATT AND 2 LAYERS OF GYP ON 270 SIDE; ALL PENETRATIONS AND DUCTWORK TO PROVIDE ACOUSTIC SEPARATION ADD NEW WALLS FOR CLOSETS TO UNDERSIDE OF CEILING WALL ASSEMBLY AT NEW RECESSED DOORS TO BE 1-HOUR RATED TO RETAIN CURRENT 1-HOUR CORRIDOR PROVIDE BACKING FOR ALL WALL-MOUNTED EQUIPMENT 1. 2. REMOVE AND PATCH BACK CONCEALED FLOOR BOXES, AS REQUIRED. DO NOT REMOVE EXISTING WALL RECEPTICLES UNLESS SHOWN WITHIN DEMO LIMITS OR REQUESTED BY OWNER. IF DESIGNATED, REMOVE AND PATCH BACK. PROVIDE AND INSTALL POWER DISTRIBUTION ON FLOOR AS SHOWN; CENTER SECTION OF THE POKE-THRU IS TO BE PIPED WITH A 1 ¼” CONDUIT AND BLANK FOR FUTURE CABLING. PROVIDE AND INSTALL RECEPTICLES AS SHOWN ON WALLS, CEILING AND ABOVE. REVISE CIRCUITS AS REQUIRED BY CODE; 1 CIRCUIT PER ROW OF 4 SEATS OR PER 2 FLOOR BOX MAX. UNLESS OTHERWISE APPROVED. PROVIDE POWER FOR PROJECTION SCREEN ABOVE CEILING.POWER-OPERATED PROJECTION SCREEN; ADJACENT TO CEILING-PROJECTION BRACKET, PROVIDE RECEPTICAL FOR CEILING PROJECTOR IN CEILING TILE. TEACHING STATION ( OWNER-PROVIDED, OWNER INSTALLED) ELECTRONIC SMART BOARDS (OWNER PROVIDED, GC INSTALLED, INCLUDING PICKUP FROM LPC WAREHOUSE IN LIVERMORE) RETAIN FIXTURE AND LENS; RE-LAMP WITH T8, RELOCATE SWITCH AS SHOWN; PROVIDE ABC SWITCHING FOR LIGHTS. FRONT LIGHTS ARE TO BE C SWITCHING CONTROLED FROM BEHIND TECHER’S DESK. REMAINING SWITCHING PER TITLE 24. 4 SWITCHES EMERGENCY/ EXIT LIGHTS FIRE ALARM REMOVE AND REPLACE, AS NECESSARY REMOVE, RELOCATE IF INDICATED AND REPLACE EMERGENCY LIGHT AND EXIT LIGHT. 1. PROVIDE AND INSTALL PER CODE DATA 1. PROVED (1) 3” CONDUIT BETWEEN CLOSET 270A AND 285 THAT PROVIDES ACCESS FROM ADJACENT CEILING TILE COORDINATE WITH DISTRICT’S TELECOMMUNICATIONS CONTRACTOR 2. FIRE SPRINKLER SYSTEM 1. TECHNOLOGY SECURITY HARDWARE PROVIDE AND INSTALL PER CODE TO BE INSTALLED CONCURRENTLY BY OWNER’S CONTRACTOR; COORDINATE SCHEDULE WITH ELECTRICAL SCOPE. SEE PRODUCTS ABOVE 2.3 SUITE 285 ARCHITECTURAL FINISHES FLOORS WALLS CEILING 3. 4. PROVIDE AND INSTALL POWER-OPERATED PROJECTION SCREEN PER CODE PROVIDE AND INSTALL BRACKET FOR PROJECTOR MOUNTED TO UNDERSIDE OF ROOF DECK; BRACE PROVIDE AND INSTALL SPEAKERS PER PLAN WITH CONNECTIVITY TO TEACHER’S STATION AND AV EQUIPMENT SMARTBOARDS PER PLAN COORDINATE WITH MECHANICAL. ELECTRICAL, PLUMBING, AV, TECHNOLOGY, FIRE SPRINKLERS FINISHES FLOORS WALLS 1. 2. CEILING 3. PARTITIONS DOORS INSULATION MECHANICAL DISTRIBUTION CONTROLS ELECTRICAL POWER FLOORS/WALLS EQUIPMENT LIGHTING FIXTURES SWITCHES EMERGENCY/ EXIT LIGHTS FIRE ALARM 4. 5. 6. 1. 2. 3. SALVAGE FOR AND REPAIR EXISTING FLOORING MATERIAL AND BASE CLEAN, PATCH AND PAINT TO MATCH EXISTING INCLUDING PRIME AT NEW/PATCHED WALLS ONLY. SALVAGE AND REUSE EXISTING CEILING TILE AND REWORK EXISTING GRID; REPLACE AND MATCH AS REQUIRED. REWORK EXISTING CEILING GRID. COMPLETE DEMOLITION OF OFFICE IMPACTED BY NEW WALL. REVISE DOOR LOCATION AND CONFIGURATION PER PLANS ALL NEW WALLS CONTIGUOUS WITH ADJACENT SUITES TO HAVE ACOUSTIC BATT INSULATION REVISE CEILING SUPPLY AND RETURN DUCTS, EQUIPMENT AND DIFFUSERS/GRILL FOR INDEPENDENT OPERATION OF SUITE; PER CODE; CLEAN DUCTWORK RELOCATE PER PLANS AND CONFIRM CONTROLS OPERATION. 1. 2. PROVIDE PER PLANS FOR NEW WALL NONE 3. 4. 5. REUSE FIXTURE AND LENS; ADD TO MATCH; RELOCATED PER PLAN PROVIDE PER CODE 6. PROVIDE AND INSTALL AS REQUIRED BY CODE FIRE SPRINKLER SYSTEM RECONFIGURE TO COMPLY WITH CODE. TECHNOLOGY/AV NOT REQUIRED SECURITY 5 1. 2. 3. 4. 5. 6. REMOVE EXISTING FLOORING MATERIAL AND BASE TO BARE CONCRETE; REMOVE ALL EXISTING FLOOR MONUMENTS; PATCH; PROVIDE AND INSTALL NEW CARPET AND BASE CLEAN, PATCH AND PAINT INCLUDING PRIME AT NEW WALLS AND INFILL OF WALL AREA REVISE AND MATCH EXISTING CEILING TILE AND REWORK EXISTING CEILING GRID ACCOMMODATE ALL SYSTEMS SUCH AS AV, AUTOMATIC SPRINKLER SYSTEM RECONFIGURATION, SPEAKERS, TECHNOLOGY, LIGHTING AND POWER 7. 8. 9. DOORS 10. REVISE DOOR LOCATION AND CONFIGURATION PER PLANS; PROVIDE AND INSTALL HARDWARE INSULATION 11. ALL NEW WALLS CONTIGUOUS WITH ADJACENT SUITES TO HAVE ACOUSTIC BATT INSULATION AND SEALANTAT PENETRATIONS FIT-UP 12. WHITEBOARDS PER PLANS 13. COORDINATE WITH DISTRICT TECHNOLOGY PLAN AND CONTRACTOR 2.2 SUITE 265 ARCHITECTURAL COORDINATE WITH MECHANICAL. ELECTRICAL, PLUMBING, AV, TECHNOLOGY, SPRINKLERS PARTITIONS AUDIO/VISUAL 1. 2. SEE PRODUCTS ABOVE MECHANICAL DISTRIBUTION CONTROLS 1. REVISE CEILING SUPPLY AND RETURN DUCTS, EQUIPMENT AND DIFFUSERS/GRILL FOR INDEPENDENT OPERATION OF SUITE PER CODE; CLEAN DUCTWORK; 2. RELOCATE PER PLANS AND CONFIRM CONTROLS OPERATION. ELECTRICAL POWER FLOORS, 1. WALLS, 2. CEILINGS and ABOVE CEILING 3. 4. EQUIPMENT 5. 6. 7. 8. LIGHTING FIXTURES DEMOLISH INTERIOR WALLS ADD NEW FLOOR TO DECK DEMISING WALL BETWEEN SUITE 285 AND 287-8. PROVIDE BACKING FOR ALL WALL-MOUNTED EQUIPMENT REMOVE AND PATCH BACK CONCEALED FLOOR BOXES, AS REQUIRED. DO NOT REMOVE EXISTING WALL RECEPTICLES UNLESS SHOWN WITHIN DEMO LIMITS OR REQUESTEDBY OWNER. IF DESIGNATED, REMOVE AND PATCH BACK. PROVIDE AND INSTALL RECEPTICLES AS SHOWN ON WALLS, CEILING AND ABOVE. REVISE CIRCUITS AS REQUIRED BY CODE; 1 CIRCUIT PER ROW OF 4 SEATS OR PER FLOOR BOX MAX. UNLESS OTHERWISE APPROVED. POWER-OPERATED PROJECTION SCREEN; PROVIDE POWER FOR PROJECTION SCREEN ABOVE CEILING. ADJACENT TO CEILING-PROJECTION BRACKET, PROVIDE POWER AND EMPTY AV JUNCTION BOX FOR CEILING PROJECTOR IN CEILING TILE TEACHING STATION ( OWNER-PROVIDED, OWNER INSTALLED) ELECTRONIC SMART BOARDS (OWNER PROVIDED, GC INSTALLED, INCLUDING PICKUP FROM LPC WAREHOUSE IN LIVERMORE) 9. RETAIN FIXTURE AND LENS; RE-LAMP WITH T8, RELOCATE SWITCH AS SHOWN; 10. PROVIDE ABC SWITCHING FOR LIGHTS. FRONT LIGHTS ARE TO BE C SWITCHING CONTROLED FROM BEHIND TECHER’S DESK. REMAINING SWITCHING PER TITLE 24. SWITCHES EMERGENCY/ EXIT LIGHTS FIRE ALARM 11. REMOVE AND REPLACE, AS NECESSARY 12. REMOVE, RELOCATE IF INDICATED AND REPLACE EMERGENCY LIGHT AND EXIT LIGHT. 13. PROVIDE AND INSTALL PER CODE DATA 14. PROVED (2) 3” CONDUIT BETWEEN 285 AND IDF ROOM THAT PROVIDES ACCESS FROM ADJACENT CEILING TILE 15. COORDINATE WITH DISTRICT’S TELECOMMUNICATIONS CONTRACTOR 6 AD1 - A FIRE SPRINKLER SYSTEM 1. TECHNOLOGY SECURITY HARDWARE SWITCHES EMERGENCY/ EXIT LIGHTS FIRE ALARM PROVIDE AND INSTALL PER CODE TO BE INSTALLED CONCURRENTLY BY OWNER’S CONTRACTOR; COORDINATE SCHEDULE WITH ELECTRICAL SCOPE. 7. 8. PROVIDE AND INSTALL PROVIDE AND INSTALL EMERGENCY LIGHT AND EXIT LIGHT PER CODE. 9. PROVIDE AND INSTALL PER CODE SEE PRODUCTS ABOVE FIRE SPRINKLER SYSTEM 1. TECHNOLOGY SECURITY HARDWARE N/A 1. 2. AUDIO/VISUAL N/A AUDIO/VISUAL 3. 4. PROVIDE AND INSTALL POWER-OPERATED PROJECTION SCREEN PER CODE PROVIDE AND INSTALL BRACKET FOR PROJECTOR MOUNTED TO UNDERSIDE OF ROOF DECK; BRACE PROVIDE AND INSTALL SPEAKERS PER PLAN WITH CONNECTIVITY TO TEACHER’S STATION AND AV EQUIPMENT SMARTBOARDS PER PLAN PROVIDE AND INSTALL PER CODE SALVAGE FINISHES FLOORS ARCHITECTURAL COORDINATE WITH MECHANICAL. ELECTRICAL, PLUMBING, AV, TECHNOLOGY, SPRINKLERS 1. INSTALL CABINETS, SINK AND FAUCET SALVAGED FROM SUITE 265 2. PROVIDE AND INSTALL NEW COUNTERTOP TO MATCH EXISTING. AT CONTRACTORS OPTION, EXISTING COUNTERTOP CAN BE REUSED IF IT IS NOT DAMAGE DURING REMOVAL. 3. 4. 5. WALLS 6. CEILING 7. PARTITIONS REMOVE EXISTING FLOORING MATERIAL AND BASE TO BARE CONCRETE; REMOVE ALL EXISTING FLOOR MONUMENTS; PATCH; PROVIDE AND INSTALL NEW RESILIENT SHEET FLOORING AND BASE SIMILAR TO KITCHENETTE IN 265; CLEAN AND POLISH. CLEAN, PATCH AND PAINT INCLUDING PRIME AT NEW WALLS AND INFILL OF WALL AREA REVISE AND MATCH EXISTING CEILING TILE AND REWORK EXISTING CEILING GRID. 8. DEMOLISH OFFICE WALLS 9. ADD NEW FLOOR TO DECK DEMISING WALL BETWEEN 287 AND 288. 10. PROVIDE BACKING FOR ALL WALL-MOUNTED EQUIPMENT DOORS 11. PROVIDE AND INSTALL NEW DOOR PER PLANS; PROVIDE AND INSTALL HARDWARE INSULATION 12. ALL NEW WALLS CONTIGUOUS WITH ADJACENT SUITES TO HAVE ACOUSTIC BATT INSULATION AND SEALANT AT PENETRATIONS FIT-UP MECHANICAL DISTRIBUTION CONTROLS PLUMBING WALLS CEILING PARTITIONS DOORS INSULATION MECHANICAL DISTRIBUTION CONTROLS CONTROLS 1. 2. REVISE CEILING SUPPLY AND RETURN DUCTS, EQUIPMENT AND DIFFUSERS/GRILL FOR INDEPENDENT OPERATION OF ROOM PER CODE; CLEAN DUCTWORK; MAY SHARE HVAC EQUIPMENT AND CONTROLS WITH 288 3. RELOCATE PER PLANS AND CONFIRM CONTROLS OPERATION. 1, 2. CONNECT TO EXISTING WET WALL; REUSE EXISTING SINK AND FIXTURES REMOVE AND PATCH BACK CONCEALED FLOOR BOXES, AS REQUIRED. DO NOT REMOVE EXISTING WALL RECEPTICLES UNLESS SPECIFIED OR APPROVED BY OWNER. IF DESIGNATED, REMOVE AND PATCH BACK. PROVIDE AND INSTALL RECEPTICLES AS SHOWN. REVISE CIRCUITS AS REQUIRED BY CODE AND AS DESIGNATED ON PLANS 5. OWNER-PROVIDED, OWNER-INSTALLED VENDING EQUIPMENT 6. RETAIN FIXTURE AND LENS; RE-LAMP WITH T8, PROVIDE AND INSTALL SWITCH AS SHOWN; 7 COORDINATE WITH MECHANICAL. ELECTRICAL, PLUMBING, AV, TECHNOLOGY, SPRINKLERS 1. 2. 3. 4. 5. 6. REMOVE EXISTING MATERIAL TO BARE CONCRETE; PROVIDE AND INSTALL RESILIENT SHEET FLOORING AND BASE CLEAN AND POLISH. CLEAN, PATCH AND PAINT INCLUDING PRIME FOR NEW WALLS: REPLACE CEILING TILES TO MATCH AND REWORK EXISTING CEILING GRID. SEE 2.4 7. 8. PROVIDE PAIR OF DOORS PER PLAN SEE 2.4 1. 2. REVISE CEILING SUPPLY AND RETURN DUCTS, EQUIPMENT AND DIFFUSERS/GRILL FOR INDEPENDENT OPERATION OF ROOM PER CODE; CLEAN DUCTWORK; MAY SHARE HVAC EQUIPMENT AND CONTROLS WITH 288 3. RELOCATE PER PLANS AND CONFIRM CONTROLS OPERATION. ELECTRICAL POWER FLOORS, 1. WALLS, 2. CEILINGS and ABOVE CEILING 3. 4. TACK BOARD PER PLANS ELECTRICAL POWER FLOORS, 1. WALLS, 2. CEILINGS and ABOVE CEILING 3. 4. EQUIPMENT LIGHTING FIXTURES FINISHES FLOORS EQUIPMENT LIGHTING FIXTURES SWITCHES EMERGENCY/ EXIT LIGHTS FIRE ALARM REMOVE AND PATCH BACK CONCEALED FLOOR BOXES, AS REQUIRED. DO NOT REMOVE EXISTING WALL RECEPTICLES UNLESS SHOWN WITHIN DEMO LIMITS OR REQUESTED BY OWNER. IF DESIGNATED, REMOVE AND PATCH BACK. PROVIDE AND INSTALL RECEPTICLES AS SHOWN. REVISE CIRCUITS AS REQUIRED BY CODE AND AS DESIGNATED ON PLANS 5. NONE 6. 7. 8. RETAIN FIXTURE AND LENS; RE-LAMP WITH T8 PROVIDE AND INSTALL PROVIDE AND INSTALL EMERGENCY LIGHT AND EXIT LIGHT PER CODE. 9. PROVIDE AND INSTALL PER CODE FIRE SPRINKLER SYSTEM 1. PROVIDE AND INSTALL PER CODE TECHNOLOGY SECURITY HARDWARE AUDIO/VISUAL CEILING PARTITIONS DOORS INSULATION FIT-UP MECHANICAL DISTRIBUTION SEE PRODUCTS ABOVE 2.5 STORAGE ROOM 288 2.4 BREAKROOM 287 ARCHITECTURAL FINISHES FLOORS WALLS ELECTRICAL POWER FLOORS WALLS EQUIPMENT LIGHTING FIXTURES EXISTING TO REMAIN; PATCH, CLEAN AND POLISH PROVIDE AND INSTALL ¾” PLYWOOD BACKER ON WALL, SEE TECHNOLOGY FOR POWER REQUIREMENTS AND DISTRIBUTION FOR LOCATION. ” EXISTING TO REMAIN N/A N/A N/A COORDINATE WITH DISTRICT TECHNOLOGY PLAN AND CONTRACTOR PROVIDE AND INSTALL (1) 2 TON MITSUBISHI DUCTLESS SPLIT SYSTEM. PROVIDE AND INSTALL (1) CONDENSATE PUMP AND PIPING TO DRAIN. PROVIDE AND INSTALL DX PIPING PROVIDE MISC CORING NEEDED FOR WORK. PROVIDE AND INSTALL CONTROL WITHIN ROOM. CORE THREE 4” DIAMETER HOLES PER PLAN. COORDINATE WITH TECHNOLOGY PLANS PROVIDE AND INSTALL POWER DISTRIBUTION AS SHOWN AS REQUIRED BY TECHNOLOGY SCOPE DOCUMENT. COORDINATE WITH MECHANICAL EQUIPMENT; IDF EQUIPMENT PROVIDED, OWNER-INSTALLED REMOVE AND REPLACE FIXTURE TO COORDINATE WITH MECHANICAL AND IT EQUIPMENT. FIRE ALARM TECHNOLOGY SECURITY HARDWARE PROVIDE AND INSTALL AS REQUIRED BY CODE COORDINATE WITH DISTRICT TECHNOLOGY PLAN AND CONTRACTOR SEE PRODUCTS ABOVE 3.10 ELECTRICAL ROOM ACCOMMODATE REMOVAL AND NEW POWER IN PROJECT AREA MODIFY TO ACCOMMODATE TECHNOLOGY PER SEPARATE DOCUMENT ELECTRICAL POWER REVISE PANELS TO ACCOMMODATE REMOVAL AND REDISTRIBUTION OF POWER FOR THIS PROJECT. LABEL ALL CHANGES COORDINATE WITH DISTRICT TECHNOLOGY PLAN AND CONTRACTOR 1 NOT REQUIRED SEE PRODUCTS ABOVE NOT REQUIRED 2.6 IDF SEE SEPARATE TECHNOLOGY DOCUMENT; COORDINATE POWER REQUIREMENTS WITH ELECTRICAL SCOPE; ARCHITECTURAL COORDINATE WITH MECHANICAL. ELECTRICAL, PLUMBING, AV, TECHNOLOGY, SPRINKLERS 8 9 1. 08.22.2011 ADD. #1 AD1 - B