Power Quality: Fouad Dagher

advertisement
Power Quality: Fouad Dagher
NY's Regional Energy Efficiency Conference
Parts of the Electric System
1. Generating Station: Produces
Electricity.
2. Transmission Lines: Move
electricity great distances at high
voltage. Typically 115,000+ volts.
3. Transmission Substation:
Redirects power delivery and provides
switching/fault protection.
4. Distribution Substation: Lowers the
voltage for delivery on local streets
and provides switching/fault
protection.
5. Distribution Lines: Delivers
electricity to neighborhoods. Typically
lower than 15,000 volts.
6. Service Wires: Connects individual
buildings to the grid. Typically lower
than 480 volts.
2
Power System Components
Generation – Large central high voltage plants & small DG
Transmission – 765 to 115 KV
Sub-Transmission – 69 to 23 KV
Primary Distribution – 13.2 to 4.16 KV
Secondary Distribution – 480, 208, 120 volts
3
Dunkirk Coal Plant - 600 MW
Wind Turbines on Lake Erie 20 MW
4
Lewiston Pumped Storage Plan 2,300 MW
Manchester St Gas fired plant 450 MW
5
WNY Transmission System
345 kV Cross State System
G NYPA
G
G Dunkirk
230 kV New York
G NYPA
G
G Dunkirk
115 kV System (WNY)
23 kV System
13.2 kV Dist
4.8 kV Dist
4.16 kV Dist
6
Sec Customers
120/240 V,
208Y/120 V,
480Y/277 V
34.5 kV Subtran
HV Customers
230/115/34.5/
13.2/4.8/4.16 KV
Sec Customers
120/240 V,
208Y/120 V,
480Y/277 V
Distribution Equipment (Cont.)
Š Disconnect Switch
Š Open or close to
temporarily
reconfigure a
feeder.
7
Distribution Equipment (Cont)
Š Capacitor Bank
Š Improves power factor on
the feeder
Š Helps to raise feeder
voltage during peak
loading condition
Š Can cause a voltage
surge or transient when
turned on
Š This version operates
automatically , most are
fixed banks that are
‘always on’.
8
Distribution System Equipment
Š Pole top recloser
Š Opens to clear faults
Š Automatic reclosing
to restore the circuit
after a temporary
fault.
Š Collects fault
information
Š Monitors voltage and
current
9
Distribution Equipment (Cont.)
Š 3 Phase Riser pole
Š Overhead to
underground
transition
Š Fused cutouts can
open to protect
equipment from fault
current
Š Lightning arrestors
protect equipment
from high magnitude
transients
10
Distribution Equipment (Cont)
Š Three Phase Pad
Mounted Transformer
Š Typical device used
to provide service to
a business or
building
Š Steps voltage from
distribution voltage
to service voltage
Š Generally the line of
demarcation between
utility and customer
is the secondary
terminal, also known
as the service point.
11
Distribution Equipment (Cont.)
Š Overhead 3 phase
Transformer Bank
Š Provides 3 phase service
voltage to customers
served from an overhead
system
Š Fused cutouts and
lightning arrestors protect
equipment from fault and
surge conditions
Š For overhead service to a
building the service point
is the connection between
the triplex and the service
conductors at the
building.
Š For underground service
laterals, the service point
is at the transformer.
12
We have a large system to maintain
Asset
Elements
Distribution Poles
1,212,965
Transmission Poles
600,000
Transmission towers
22,000
Overhead Transformers
13
Pad Mount Transformer
57,000
Switchgears
2,700
23 kV – 345 kV - Circuit Miles
9,300 mi.
Primary Voltage - Circuit Miles
42,000 miles
Secondary Voltage - Circuit Miles
18,250 miles
Substations
894
Problems
Animal Contacts
15
Tree Contact
16
Motor Vehicle Accidents
17
Storms
18
Equipment Failure
19
“Direct” Distribution System Disturbances
Fault occurs on the feeder
Substation A
directly serving the customer.
Circuit Breaker
Š If the fault occurs on the main
‘back-bone’, customers on the
customer load
Fuses
feeder will experience up to
Circuit Reclosers
three re-close attempts and
maybe a total loss of power for
customer load
an extended period of time.
Š If the fault occurs on a ‘sidebranch’, a fuse may isolate the
fault. Customers on the branch
circuit will lose power and other
customer’s on the feeder will
20
experience a brief ‘blink’ or ‘dip’
Switches
customer load
“Indirect” Distribution System Disturbances
Substation A
Substation B
fault occurs on an
Circuit Breaker
‘adjacent’ feeder within the
same substation as the line
customer load
Fuses
Circuit Reclosers
Š Customer’s on adjacent
customer load
Switches
serving the customer.
customer load
normally open tie switch
feeders may experience
several brief ‘blinks’ or ‘dips’
as the substation attempts
to restore power – recloser
normally open tie switch
21
attempts.
What is National Grid Doing to improve reliability?
Program
Feeder Hardening
Targets
Lightning, Tree, Deteriorated
Equipment, Animal Protection
22
U/G Distribution Programs
Cable and OFC Replacement
O/H Fused Cutout Replacement
Replace Faulty Cutouts
Vegetation Management
Growth Management Cycle
Augmented Clearance for Trees
Problem Trees
Inspection Programs
Substation, OH & U/G Systems
Specific Area Activities
Special Projects
Why does my equipment trip during faults on utility
system?
Š Not enough voltage – if there is not enough voltage to
provide the energy, equipment will trip.
Š Undervoltage circuitry – meant to monitor the voltage and
trips the circuit if voltage goes below a predefined level.
Š Unbalance protection- faults don’t affect all phases equally
voltage imbalance will result.
Š Emergency off circuitry that monitors several parameters
may be too sensitive to voltage sag.
23
What can I do to protect against voltage “dips”
Š Identify cost of protection vs. downtime losses
Š Assess whole plant vs. individual equipment
protection
Š Work with equipment manufacturers to adjust
tolerances
Š Determine the source of the problem. Example, is the
process control causing whole process to shut down?
24
Other Disturbances: transients, Surges, spikes
Š Extremely fast voltage changes above the
normal range
Š lightning strikes
Š equipment start-ups/ shutdowns
Š capacitor switching operations
25
Solutions for Transients
Š Surge Protectors
Š Uninterruptible Power Supplies with built in Surge Suppression
Š Isolation Transformer / Line reactors
Š Constant Voltage Transformer
26
Surge Protectors- considerations
Š Use in cascaded fashion for full protection
Š One for the whole facility
Š One at the sub-Panel
Š One at point-of-use
Š Installation
Š Routing of conductors - shortest
conductor length possible provides the
most effective protection
Š Rating
Š Clamping Voltage
Š Total Energy Dissipation
Š UL 1449 2nd Edition
27
Define the Problem
Š Conduct a thorough site investigation, which includes inspecting
wiring and grounding systems. Pay extra attention to ground loops
(do you have “illegal” bonds?)
Š Establish a good understanding of the problem and its magnitude
and what it is affecting. (UPS alarm may be beeping but no
equipment is shutting off.)
Š Monitor the incoming power for disturbances (monitor voltage
and current) and at possibly the service entrance and at the affected
equipment.
Š Investigate equipment sensitivity to power disturbances (What
can the equipment tolerate?).
Š Determine the load disruption and consequential effects (Is a
fraction HP drive tripping a whole production line?)
Š Seek the help of people with experience rather than sales people.
28
Questions?
29
Download