Town of Newfane Secondary Clarifier No. 1 Rehabilitation 2955-00-14 SECTION 013323 - SHOP DRAWINGS AND PRODUCT SAMPLES This Section Supplements Article 3.2 of the General Conditions. PART 1 - GENERAL 1.1 A. 1.2 SUBMITTALS Submissions shall be required for all manufactured, assembled, and custom items on Drawings or as required in the specifications. SUBMISSION REQUIREMENTS A. Shop Drawings: Prepare project specific information, drawn accurately to scale. Do not base Shop Drawings on reproduction of the Contract Documents or standard printed data. Fully illustrate contract requirements in the shop drawing submittal. Contractor shall submit shop drawings in PDF electronic format, unless otherwise requested by the Owner or Engineer. B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. Submit product data before or concurrent with samples as required. Contractor shall submit product data in PDF electronic format, unless otherwise requested by the Owner or Engineer. C. Samples: Submit samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual components as delivered and installed. Transmit samples that contain multiple, related components such as accessories together in one submittal package. D. Cross out irrelevant information and highlight the specified features, in color other than red, on all shop drawings and product data submitted. 1.3 IDENTIFICATION A. 1.4 Use enclosed "Submittal Form" with each submittal. Fill out completely. APPROVAL PROCEDURE A. The Engineer will review submittals and return them stamped with one or more of the following actions: 1. Stamped "No Exceptions Taken" a. No corrections or resubmission required. Fabrication may proceed. SHOP DRAWINGS AND PRODUCT SAMPLES 013323-1 Town of Newfane Secondary Clarifier No. 1 Rehabilitation 2955-00-14 1.5 2. Stamped "Provide as Corrected" a. Proceed with fabrication if Contractor complies with noted corrections. b. If Contractor cannot comply with noted corrections, fabrications shall not proceed and Contractor shall resubmit. 3. Stamped "Revise and Resubmit" a. Do not proceed with fabrication. b. Resubmit for review. 4. Stamped "Rejected" a. Do not proceed with fabrication. b. Submit appropriate product for review. DISTRIBUTION A. Engineer will return one (1) marked up electronic copy of reviewed shop drawings, Product Data and sample to Contractor. B. Contractor to make distribution to subcontractors, suppliers, etc. as required. C. Contractors are responsible to verify dimensions in the field. D. Contractors shall verify quantities of materials to be supplied. E. Coordinate each submittal with requirements of work and of contract documents. F. Contractor's responsibility for errors and omissions in submittals is not relieved by Engineer's review of submittals. G. Contractor's responsibility for deviations in submittals from requirements of contract documents is not relieved by Engineer's review of submittals, unless Engineer gives written acceptance of specific deviations. H. Notify Engineer, in writing at time of submission, of deviations in submittals from requirements of contract documents. I. If submittals deviate from the contract documents and Engineer is not notified in writing of such deviation, then review is invalid. 1.6 RECORD DRAWINGS A. The Owner will provide two (2) sets of drawings to the Contractor to maintain and submit as record drawings unless otherwise indicated in the specification sections. These prints shall be maintained at the site and shall at all times, absolutely, clearly, and completely show the actual installations in accordance with the Contract requirements. All changes in the work of subcontractors shall be recorded. SHOP DRAWINGS AND PRODUCT SAMPLES 013323-2 Town of Newfane Secondary Clarifier No. 1 Rehabilitation 2955-00-14 B. Upon completion of the work and after checking any subcontractor's record drawings and all required drawings, the Contractor shall submit a complete set of marked-up record drawings to the Owner within 14 days to be used for the final inspection, and acceptance and for verification. Upon completion of the work, the record drawings shall become the property of the Owner. END OF SECTION 013323 (following submittal cover sheet) SHOP DRAWINGS AND PRODUCT SAMPLES 013323-3 Town of Newfane Secondary Clarifier No. 1 Rehabilitation 2955-00-14 SUBMITTAL COVER SHEET PROJECT: A/E SUBMITTAL No.: OWNER: A/E: WENDEL A/E PROJECT #:__2955-49 PRIME CONTRACTOR: CHECK ONE: ( ) NEW SUBMITTAL ( ) RESUBMITTAL DATE: ORIGINAL A/E SUBMITTAL NO. (IF RESUBMITTAL): CHECK ONE: THIS SUBMITTAL IS ( ) AS SPECIFIED ( ) A SUBSTITUTE, REMARKS: TYPE OF SUBMITTAL: (CHECK ALL THAT APPLY) ( ) SHOP DRAWINGS ( ) SAMPLE ( ) COLOR SELECTION ( ) SCHEDULE ( ) WARRANTY ( ) TEST REPORT PRODUCT DATE/CATALOG CUT RECORD DOCUMENT PERFORMANCE DATA OPERATIONS & MAINTENANCE DATA OTHER DESCRIPTION OF SUBMITTAL: PRODUCTNAME: REFERENCES: SPEC SECTION NO.: MANUFACTURER: PARAGRAPH: ADDRESS: DRAWING NO.: PHONE NUMBER: SECTION/DETAIL: SUBCONTRACTOR: PHONE NO.: SUPPLIER: PHONE NO.: CONTRACTOR STAMP SHOP DRAWINGS AND PRODUCT SAMPLES A/E STAMP 013323-4