he new requirements for selective coordination of circuit were to expand and take down an entire panelboard. emergency and legally required standby systems in However, selective coordination won’t prevent the smaller­ Sections 700.18 and 701.27 of the 2005 National scale problem from occurring, nor will it ensure that Electrical Code (NEC) are challenging electrical additional lives will be saved if an escalated problem was engineers to intensively consider how systems respond to prevented. Even with selectivity, it’s still possible for a large­ short circuits. scale problem to occur, such as a feeder fault, and create the Meeting this challenge raises questions regarding the code requirements, how other aspects of system design are same type of situation that would be mitigated by selective coordination. compromised and what constitutes compliance. While the For a selectively coordinated emergency system to benefi t probability of owners benefi ting from selectively coordinated the occupants of a building other than a hospital, a connected electrical systems is small, the likelihood of incurring chain of events must occur: signifi cant costs to ensure selective coordination is a certainty with the 2005 NEC. As electrical engineers consider the impact of selective coordination, there is a growing consensus that this is the 1. A building must be occupied. 2. There must be an event that mandates exiting the building. wrong direction for the NEC, and that this area of design 3. The event must disrupt a portion of the emergency should be returned to engineering judgment. In fact, there electrical system, in which no other life safety were more than a dozen proposed changes to the 2008 NEC support exists. to delete these new requirements or better defi ne them. Unfortunately, the just-released NEC Report on Proposals 4. The disruption must be of a nature that it would interrupt more of the electrical system than showed that there were not enough Code Panel votes to return would occur if the system were not selectively this design area to engineering judgment. However, there is coordinated. This type of event is usually an an opportunity to address and respond to this issue, as NFPA infrequent, high-level fault. Code Panels will vote again in December and are accepting public comments on these proposals until Oct. 20. 5. The extended disruption of the electrical system must result in injury or death of an occupant. The probability of all of the above occurring is miniscule. Selective coordination might prevent a small-scale If the fi rst four occur, it may still be possible to avoid injury problem from becoming larger — e.g., if a fault on a single or death through the use of alternative systems — e.g., using the normal lighting system to exit, using a redundant exit or how to determine if overcurrent devices will selectively path or exiting in the dark. coordinate. The methodology for coordination studies is An emergency system is most likely to fail under everyday described in several publications such as ANSI/IEEE Std operation. In this scenario, the building’s normal power 242, IEEE Recommended Practice for Protection, and IEEE system is available to support alternatives, and an emergency Coordination of Industrial and Commercial Power Systems. system failure can be treated like the failure of any other However, these publications are not acknowledged by the circuit. NEC. Extending this logic, it becomes obvious that if selective Determination of selective coordination is dependent on coordination were needed, it would be required as much or information provided by manufacturers, who describe the more for normal systems than for emergency systems! If operating characteristics of fuses and circuit breakers using faults on non-selectively coordinated systems frequently graphical curves that plot overcurrent performance data created unwanted large outages, we would see it in our vs. time curves (TCs). The de facto standard for TCs has everyday lives; building blackouts would halt workplace the time axis beginning at 0.01 seconds. Most overcurrent production and create unlimited safety hazards. protective devices start to operate in time periods of less than More than 99.9999% of electrical systems in existence 0.01 seconds, and all current-limiting fuses operate in less today were designed using engineering judgment and do not than 0.004 seconds. To address time periods of less than 0.01 meet the 2005 NEC’s strict defi nition of being selectively seconds, manufacturers have developed overcurrent device coordinated; yet once energized, they operate with high coordination tables. There are no industry standards for the reliability. While these systems are not selectively coordinated test procedures that are used in developing these tables, and for every fault condition, the vast majority will selectively no guarantee that various manufacturers are developing these coordinate for the most common types of faults, which are selective coordination tables under similar circumstances. low-level arcing faults. The tables are often subject to disclaimers such as “reasonable expectation of selective coordination”. A selective coordination standard would need to be Demonstrating compliance with the code places engineers similar to the series rating portion of UL 489. A series-rated and inspectors in somewhat of an untenable position. The NEC circuit breaker can be applied at fault current levels that are gives exact requirements for determining loads, sizing wires above its listed rating if used with a tested upstream breaker. and overcurrent devices, and many other aspects of design, When applied in the fi eld, series­rated circuit breakers are but it does not describe how to perform a coordination study specifi cally labeled and referenced to an upstream protective device. Two Design Methods Eventually, the NEC will have to include similar requirements for selectively coordinated devices and require testing per standard criteria. Until appropriate standards are in place, engineers cannot ascertain if a system is selectively coordinated. Figure 1. Method A will not selectively coordinate for high-level faults that rarely occur. Method B will selectively coordinate, subject to manufacturer verifi cation. If testing standards for selective coordination are developed, the public would benefi t from Page 2 the assurance of independent verifi cation of selectively upstream equipment to pass through more energy coordinated systems. while waiting for downstream equipment to operate. Manufacturers could submit their devices to a testing laboratory, which would subsequently verify selective coordination in accordance with the standard. Unfortunately, the quantity of devices combined with performance variations at different fault levels leads to a huge number of permutations and associated testing expense. Manufacturers would not likely submit their devices for verifi cation of selective coordination with the devices of other manufacturers. Accordingly, it may be necessary for all overcurrent protective devices in a selectively coordinated system to be made by a single manufacturer. Facility owners are often locked into proprietary systems that can only be modifi ed by using the products of the original manufacturer. Fire alarm systems are a good example. The listing or communication protocol requirements for fi re alarm systems force the entire system in a building to be made by a single manufacturer. For the most part, once you get outside of a single panelboard or switchboard, electrical power systems are • Larger equipment will increase the maintenance requirements. • Multiple panels will increasingly be strung together to achieve selectivity ratios. • If circuit breakers are used, arc­fl ash hazards will increase, and automatic transfer switches may be forced to withstand fault currents longer than the three-cycle duration required by UL Standard 1008. • Introducing additional impedance into a system helps circuit breakers to selectively coordinate. Some undesirable methods of achieving this include higher impedance transformers or current-limiting reactors that increase energy losses; extending circuit runs longer than is necessary; and forgoing spare capacity to minimize wire size. • If fuses are used where circuit breakers may have been the original choice, the advantages of circuit breakers are lost, including rapid resetting after a known overload trip; compact size; prevention of single phasing; and no risk of incorrect fuse or unavailable fuse replacements. being an exception. However, this may change due to further • Selective coordination increases the cost of electrical systems. developments in selective coordination. For expansions, Selective coordination of systems with ground fault renovations and similar changes to an existing system protection is very problematic. Ground fault protection is set where selective coordination is mandated, it’s quite possible below the rating of its associated overcurrent device, which that a manufacturer can now — or in the near future — set often makes it impossible to maintain trip ratios that permit pricing with limited or no competition. Competition would selective coordination with downstream devices. immune from proprietary restrictions, with series ratings only exist if a complete change-out was an alternative. If a proprietary bid was set for the emergency system, it would also be possible for a manufacturer to extend additional costs Selectively coordinated systems will benefi t building onto the normal power system as part of a packaged system occupants only under a narrow set of circumstances for which quote. there is no record of any signifi cant occurrences. While the NEC requirements for selective coordination are clear, the methods of compliance are vague, and the groundwork has When one aspect of a design becomes an absolute been set to further limit competition in the industry. Prior requirement, compromises are often made to other aspects to 2005, the benefi ts of selective coordination could be of the design. Ideally, engineers could simply improve a compared against other safety and performance aspects of an system. However, it’s likely that the following compromises electrical system. With the 2005 NEC, selective coordination will arise with selectively coordinated systems: • Electrical equipment will increase in size, either to meet a manufacturer’s minimum ratios between upstream and downstream equipment or to allow takes precedence and overrides engineering judgment. To respond to the NFPA proposals on selective Page 3 coordination of legally-required Sample Space Requirements standby systems. At this time the proposal is being rejected by Code Panel 13, and selective coordination of legally required standby systems will be retained in the 2008 NEC. Whether you’re for or against selective coordination, you can provide useful feedback to the appropriate Code Panels by commenting on the above proposals. Even if the Code Panel is supporting Figure 2. All four layouts show a 75-kVA transformer and a 225-amp branch circuit panelboard. The two layouts on the left represent what most designs would look like prior to meeting the selective coordination criteria. The two layouts on the right represent selectively coordinated designs. your viewpoint at this time, they would still like to hear your input. Of particular value coordination for the 2008 NEC, visit the www.NFPA.org. to the Code Panels is verifi able information that identifi es The deadline for comments is Oct. 20, 2006. specifi c instances where selective coordination has or has A summary of key proposals is as follows: Proposal 13-77. This proposal adds selective coordination not been a problem. Inadequate ground fault settings are the to fi re pump feeders as part of a proposed alignment with a most common problem and should be distinguished from draft of NFPA 20. At this time it is being rejected by NEC other problems. Code Panel 13. Proposal 13-135 (also see Proposal 13-137). This proposal was to delete Section 700.27 and the requirements for selective coordination from the 2008 NEC. At this time the Jim Degnan, P.E., LEED®AP is proposal is being rejected by NEC Code Panel 13. Unless principal at Sparling, an electrical the panel receives comments that substantiate a reversal, engineering and technology selectivity will be retained for the 2008 NEC. Code Panel consulting fi rm with offi ces in Seattle 13 refers to their statement in Proposal 13-135 for all other and Portland. He can be reached at proposals regarding article 700.27. jdegnan@sparling.com. Proposal 13-139 (also see Proposals 13-146). This proposal would keep selective coordination in the NEC but only require it for specifi c types of faults, most notably high­resistance faults, which are the most common type. If accepted, the concerns listed in this article regarding verifi cation, competition and design consequences would be signifi cantly relieved. At this time the proposal is being rejected by Code Panel 13. Proposal 13-159. Similar to proposal 13-135, this proposal calls for removal of Section 701.27, which calls for selective Page 4