Network & Substations HV SUBSTATION PROJECT Speaker : SIMON BATTANI & NICOLAS CHIDIAC Company : MATELEC 1 HV SUBSTATION PROJECT CONFERENCE OUTLINE - ENGINEERING & CONTRACTING DIVISION HISTORY. - ACTIVITIES PROCESS: MANAGEMENT & PROCUREMENT. PRIMARY & SECONDARY ENGINEERING. ENGINEERING CONSTRUCTION & ERECTION. TESTING & COMMISSIONING. - CASE STUDY FOR 400kV CHEFFIA S/S IN ALGERIA. 2 HV SUBSTATION PROJECT ENGINEERING & CONTRACTING DIVISION HISTORY 3 HV SUBSTATION PROJECT BRIEF HISTORY Established E t bli h d in i 1987 for f the th realization li ti off complex l HV HV, MV and d LV projects. The Division starts with 5 engineers in the Construction of the Congress Palace 60/20kV S/S in Syria and the Rehabilitation of Jamhour & Bsalim 150kV S/S in Lebanon. Kept growing up and making new challenge in working for new markets k and d diff different standards. d d Nowadays, the division count more than 100 Engineers, works in more than 10 countries and have build around 60 Substations. 4 HV SUBSTATION PROJECT ACHIEVED PROJECTS Algeria : Construction of (13) 400, 220 & 60kV GIS & AIS S/S. Extension of (9) 220 & 60kV AIS S/S. Nigeria : Construction of (2) 330 & 132kV AIS S/S. Extension of (1) 330/132kV AIS S/S. Senegal : Construction of (1) 67.5MW Power Plant with 90/15kV AIS S/S. Egypt yp : Construction of ((1)) 66/11kV GIS S/S. KSA : Construction of (1) 34.5/13.8kV Indoor S/S. Lebanon : Construction & Extension of more than (15) 220 & 66kV GIS & AIS S/S. Rehabilitation off more than (60) ( ) 66/15-11kV AIS S/S. Syria : Construction of (10) 230 & 66kV GIS & AIS S/S. Extension of (2) 220/66kV GIS S/S. 5 HV SUBSTATION PROJECT LEBANON MAIN PROJECT Beirut Central District 220/66/20kV GIS S/S: (4) 220kV U/G Cable, (3) TR 220/20kV 80MVA. (4) 66kV U/G Cable, (2) TR 66/20kV 40MVA. ( ) 20kV (5) kV Incoming, I i (62) ( ) 20kV kV O/G, O/G (5) ( ) 20kV kV Coupler. C l Client : Solidere Consultant : Dar El Handasah 6 HV SUBSTATION PROJECT LEBANON MAIN PROJECT ARAMOUN 220/150/20kV GIS S/S: (8) 220kV O/G Feeder, (2) TR 220/20kV 70MVA. (2) 150kV O/G Feeder, (1) TR 220/150kV 100MVA. ( ) 20kV (2) kV Incoming, I i (22) ( ) 20kV kV O/G, O/G (1) ( ) 20kV kV Coupler. C l Client : EDL Consultant : EDF 7 HV SUBSTATION PROJECT NIGERIA MAIN PROJECT GANMO 330/132/33kV AIS Breaker and a Half S/S: (4) 330kV Line, (2) Auto TR 330/132kV 150MVA. (2) 132kV Line, (2) TR 132/330kV 60MVA. ( ) 33kV (2) kV IIncoming, i (6) ( ) 33kV kV O/G. O/G Client : Niger Delta Power Holding Consultant : STUCKY 8 HV SUBSTATION PROJECT SYRIA MAIN PROJECT BANIAS 230/66kV GIS S/S: (9) 230kV Line, (6) 230kV Inc. Generator, (3) TR 230/66kV 125MVA. (8) 66kV Line, (3) 66kV Incoming, (1) 66kV Inc. Gaz Turbine, ( ) 66kV (3) kV Starting St ti Transformer, T f (3) ( ) TR 66/20kV / kV 30MVA. MVA Client : PEEGT 9 HV SUBSTATION PROJECT ALGERIA MAIN PROJECT MEKKERA 60/10kV GIS S/S: (5) 60kV U/G Cable, (3) TR 60/10kV 30MVA. (4) 10kV Incoming, (24) 10kV O/G, (2) 10kV Coupler. Client : SONELGAZ 10 HV SUBSTATION PROJECT ACTIVITIES PROCESS MANAGEMENT & PROCUREMENT - ENGINEERING & CONTRACTING DIVISION HISTORY. - ACTIVITIES PROCESS - MANAGEMENT & PROCUREMENT. - PRIMARY & SECONDARY ENGINEERING. - CONSTRUCTION & ERECTION. - TESTING & COMMISSIONING. COMMISSIONING - CASE STUDY FOR 400kV CHEFFIA S/S IN ALGERIA. 11 HV SUBSTATION PROJECT PLANNING Very Important Work to Accomplish The Essential Goal : Respect The Deadlines of all the Project Activities. All these Activities (Design, Approval, Procurements, Construction, Erection, Testing & Commissioning, …etc) are Mentioned in Primavera Tables with the Starting & Finishing Days to Facilitate their Follow Up. 12 HV SUBSTATION PROJECT BUDGET A Critical Activity y to Respect p The Budget g of Each Order And To Stay Within the Overall Project Budget. All the Purchase Order are Done in ERP Software which Automatically Compare the Sum of Each Order to the Correspondent p Item Budget in the Main Contract. 13 HV SUBSTATION PROJECT PROCUREMENTS Telecom Equipments ABB HV Equipments -–ABB Prot. Relay & Microscada Switzerland (8 ((6((9 pages) ppages). gg ) ) ABB Finland p pages) Once the Equipments are Defined & Approved, Procurements Responsible Put the Order Using ERP Software. They Check Th Ch k the th Budget B d t and d Follow up the Suppliers to Respect the Deadline, Send the Filled Routine Test and to Prepare the Factory Acceptance Test in Manufacturer House. 14 HV SUBSTATION PROJECT ACTIVITIES PROCESS PRIMARY & SECONDARY ENGINEERING - ENGINEERING & CONTRACTING DIVISION HISTORY. - ACTIVITIES PROCESS - MANAGEMENT & PROCUREMENT. - PRIMARY & SECONDARY ENGINEERING. - CONSTRUCTION & ERECTION. ERECTION - TESTING & COMMISSIONING. - CASE STUDY FOR 400kV CHEFFIA S/S IN ALGERIA. 15 HV SUBSTATION PROJECT PRIMARY & SECONDARY ENGINEERING The Engineers of Matelec are Skilled & Experienced in Executing all the Necessary Activities to Design in House: Different Types of New GIS & AIS Substations (Single BB, Double BB, UI type BB, Breaker and a Half, …). Extensions of Existing S/S Choosing Feasible & Optimized Solution to have Minimum Cut-Out Period with Respect to the Existing Status . Engineers Mains Scope of Works: Primary & Secondary Engineering (SLD, General Layout & Sections, Scada Architecture, Functional DWG, Grounding System, Design Criteria, Calculation Note, Auxiliary Services, Services Civil Guide, Guide Gantries & Metallic Structure, Structure …etc) …etc), Definition & Checking the Supplier Primary & Secondary Engineering (HV, MV & LV Equipments). Coordination with the Client & the Responsible p of the other Activities (Management, Procurement, Construction & Erection, Testing & Commissioning). All the Engineering Activities are Done According to the International Standards Client Requirements and to the Following ISO Design Chart Standards, Chart. 16 HV SUBSTATION PROJECT Project Planning PRIMARY & SECONDARY ENGINEERING Sales DESIGN CHART Create Design Requirement Design Requirement Review Purchasing NO Detail Design Make Design In house ? Detail Design - Internal Review YES Conceptual Design Customer Approval Conceptual Design -Internal Review Customer Approval Required R i d No YES Get Customer Approval Required Get Customer Approval NO Design Release Plan Design Verification & Validation P j t Realization Project R li ti 17 YES Purchasing HV SUBSTATION PROJECT PRIMARY & SECONDARY ENGINEERING Clientt requirements Cli i t stated t t d iin th the contractual t t l references Required Standards (IEC or ANSI,…) Climatic and environmental Condition System characteristics Particular of System Insulation level Creepage distances Clearances in Air BASIC DESIGN CRITERIA 18 HV SUBSTATION PROJECT The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. 19 PRIMARY & SECONDARY ENGINEERING HV SUBSTATION PROJECT PRIMARY & SECONDARY ENGINEERING GENERAL LAYOUT DRAWING 220kV LEVEL DOUBLE BUSBAR TYPE 220kV LEVEL SECTION DOUBLE BUSBAR TYPE 66kV LEVEL SECTION UI BUSBAR TYPE 66kV LEVEL UI BUSBAR TYPE 20 HV SUBSTATION PROJECT 21 PRIMARY & SECONDARY ENGINEERING HV SUBSTATION PROJECT PRIMARY & SECONDARY ENGINEERING Loads Distribution Wind Load Stress Analysis in Bar Nodes Displacement Perspective View Stress Diagram 22 HV SUBSTATION PROJECT The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, The image and cannot thenbeopen display theed. file Your again.computer If the redmay x still not appears, hav e enough y ou may memory hav e to to delete open The the the image image, image cannot and or the then beimage display insert may ed. it again. hav Your e been computer corrupted. may not Restart hav eyenough our computer, memoryand to then open open the image, the fileoragain. the image If themay red xhav stille appears, been corrupted. y ou mayRestart hav e to y our delete computer, the image andand then then open insert theitfile again. again. If the red x still appears, y ou may hav e to delete the image and then insert it again. The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. 23 PRIMARY & SECONDARY ENGINEERING HV SUBSTATION PROJECT 24 SOFTWARE TOOLS USED IN ENGINEERING HV SUBSTATION PROJECT ACTIVITIES PROCESS CONSTRUCTION & ERECTION - ENGINEERING & CONTRACTING DIVISION HISTORY. HISTORY - ACTIVITIES PROCESS - MANAGEMENT & PROCUREMENT. - PRIMARY & SECONDARY ENGINEERING. ENGINEERING - CONSTRUCTION & ERECTION. - TESTING & COMMISSIONING. - CASE STUDY FOR 400kV CHEFFIA S/S IN ALGERIA. ALGERIA 25 HV SUBSTATION PROJECT CONSTRUCTION & ERECTION For our turnkey projects, our qualified subcontractors partners are handling the construction and erection works under Matelec team supervision p Matelec site manager and supervisors are daily present to follow up the site work progress and to assure the best quality of work. Matelec supervisors liaise with the client representatives by conducting regular meetings to discuss the work progress and solve arising g problems p Matelec specialists handle the site quality control as well as the safety rules and regulations. regulations 26 HV SUBSTATION PROJECT CONSTRUCTION & ERECTION Full coordination between the engineering Department and the Site Upon drawings approval, a complete file including documents and drawings is prepared by the engineering department and sent to site for constructions and erection phase The engineering department is always ready to find f a solution for unexpected technical inconvenience and arising site problems p A regular progress report is prepared by the site supervision to follow up and update the site planning 27 HV SUBSTATION PROJECT ACTIVITIES PROCESS TESTING & COMMISSIONING - ENGINEERING & CONTRACTING DIVISION HISTORY. - ACTIVITIES PROCESS - MANAGEMENT & PROCUREMENT. - PRIMARY & SECONDARY ENGINEERING. - CONSTRUCTION & ERECTION. - TESTING & COMMISSIONING. - CASE STUDY FOR 400kV CHEFFIA S/S IN ALGERIA. 28 HV SUBSTATION PROJECT TESTING & COMMISSIONING For Every Substation, a Testing Engineer from Matelec is Dedicated to Manage the Testing & Commissioning Activities of the S/S. He Performs Several Tests (Functional Test, CT/VT Test, CB/DS/ES Test Test, …..etc) etc) & Prepares the Filled Site Test Documents for the Client. He is Supported by Matelec Specialists for the Testing of Certain Equipments (Protection Relays Setting, Scada System, Fault Recorder, Telecom, ….etc) and in some case Supplier Specialist Perform the Testing g & Commissioning g of their Equipments q p for example GIS Equipments. All the Tests are Done According to Protocols Prepared in Matelec House with Respect to the Relevant International Standard, Manufacturer Recommendations & Client Requirement. They are Completely p y or Partially y Witnessed by y the Client. 29 HV SUBSTATION PROJECT LIST & EXAMPLE OF PROTOCOLS TESTING & COMMISSIONING The image cannot The beimage displaycannot ed. Your be computer display ed.may Yournot computer hav e enough may not memory hav e enough to openmemory the image, to open or thethe image image, mayorhav thee image been corrupted. may hav e been Restart corrupted. y our computer, Restart yand ourthen computer, open the andfilethen again. open If the the red file again. x still appears, If the redy ou x still may appears, hav e toy ou delete maythe hav image e to delete and then the insert imageitand again. then insert it again. The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. - HV, MV & LV Equipments Test (Power & Aux. Transformer, CB, DS, ES, CT, VT, SA, LT Charger, LT, Charger Battery, Battery Diesel Group,…). Group ) - Functional Test (Line, Transf, Coupler, ..) . - Panels Test (AC, DC, Common, Busbar Prot., Fault & Event Recorder, Telecom, ...). - System Test ((Scada, Transformer Monitoring on Line, Metering, …..). - HV, MV & LV Cables Test. - Control, Control Prot. Prot & Metering Relays Test. Test - Details Procedure for Testing & Commissioning in Case of S/S Extension. 30 LIST OF SUBMITTED PROTOCOLS (More than 40) HV SUBSTATION PROJECT Multi Function System for Current, Voltage & Power Transformers T t Tests. TESTING EQUIPMENTS T 3000 (ISA-Italy) CPC 100 (Omicron) Circuit Breaker Analyzer and Micro Ohmmeter. CBA – 1000 ((ISA-Italy) y) Multi Tasking Equipment for Testing P t ti Relays, Protection R l Energy Meters & Transducers. 31 CMC 256 (Omicron) DRT-6 DRT 6 (ISA (ISA-Italy) Italy) HV SUBSTATION PROJECT CASE STUDY CHEFFIA S/S 400/220/31.5kV - ENGINEERING & CONTRACTING DIVISION HISTORY. - ACTIVITIES PROCESS - MANAGEMENT & PROCUREMENT. PROCUREMENT - ALGERIA - - PRIMARY & SECONDARY ENGINEERING. - CONSTRUCTION & ERECTION. - TESTING & COMMISSIONING. COMMISSIONING - CASE STUDY FOR 400kV CHEFFIA S/S IN ALGERIA. 32 HV SUBSTATION PROJECT LOCATION & IMPORTANCE 400kV Network in Algeria 400kV Power Plant 400kV Substation 400kV Line 33 HV SUBSTATION PROJECT LOCATION & IMPORTANCE 400kV Network in Algeria 400kV Power Plant 400kV Substation 400kV Line 34 HV SUBSTATION PROJECT 400kV SLD The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. 1 Double Bus Bar 5000A, 40kA 3 Incoming 400kV 2 Line 400kV 1 International Line 400kV 3 AutoTransf 400/220/31.5kV400/220/31 5kV400/220/31.5kV 5kV-300MVA 1 Coupler 400kV 35 SUBSTATION COMPOSITION HV SUBSTATION PROJECT 220kV SLD 1 Double Bus Bar 4000A, 31.5kA 3 Incoming Auto TR 220kV 4 Line 220kV 1 Coupler 220kV 36 SUBSTATION COMPOSITION HV SUBSTATION PROJECT SUBSTATION GENERAL LAYOUT The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. 30 00 meters 400 meters 400kV S/S 400kV ATR 400kV L.K. 220kV L.K. 220kV S/S 37 Control Building 400kV LAYOUT & SECTIONS HV SUBSTATION PROJECT The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. 150 m. 30 m. 21 m. 21 m. L.K. 38 ATR 400/220kV & 220kV SA SA, CT, ES, CB & ES of ATR Busbar 1 & 2 and BDS 1 & BDS 2 ES, CB, ES, CT, DS/ES LT DS/ES, LT, CVT CVT, & SA of Line ATR 400/220kV Line 400kV SCADA ARCHITECTURE HV SUBSTATION PROJECT Dot Matrix Printer Color Printer GPS for f N Network k Synchronizing 2 Operators Industrial PCs 2 Central Units Redundant Hot--Standby Configuration Hot 1 Engineering PC Ethernet Switches (61850) Fall Back Switch for Master Connection To 220kV Loop To 400kV Loop 39 To 220kV Loop To 400kV Loop HV SUBSTATION PROJECT The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again. From 400kV SCADA Loop 40 SCADA ARCHITECTURE CTRL, PROT. & METERING SCHEME HV SUBSTATION PROJECT Case of 400kV Int. Line - Jendouba Control & Metering Relays (1 panel +S1): +S1) Bay Unit REC670 (ABB) SynchroSwitch L183 (ABB) 2 Meters Cl 0.2 A1800 (Elster) Protection Relays (2 panels +R1 & +R2): Panel +R1: Main 1 Distance Prot. REL670 (ABB) Main 2 Distance Prot. D60 (GE) Breaker Failure 7VK611 (Siemens) Autorecloser REC670 (ABB) Directional E/F 7SJ621(Siemens) P el +R2 Panel +R2: Directional Active Power F60 (GE) Frequency Relay F35 (GE) Decoupling Relay DRS-N1 (ICE) 41 CTRL, PROT. & METERING SCHEME HV SUBSTATION PROJECT Case of 400/220/31.5kV AutoTransfo Control & Metering Relays (1 panel +S1): +S1) Bay Unit REC670 (ABB) SynchroSwitch T183 (ABB) Protection Relays (2 panels +R1 & +R2): Panel +R1: Main 1 TR Differential RET670 (ABB) Main 2 TR Differential T60 (GE) Breaker Failure 7VK611 (Siemens) 400kV O/C Prot. REJ523 (ABB) Panel +R2: 220 & 31.5kV O/C Prot. REJ523 (ABB) Overload O e lo d Prot. P ot REX521 (ABB) E/F Prot. REJ521 (ABB) Lockout Relay HAS (GE) 42 HV SUBSTATION PROJECT 43 CHEFFIA S/S PHOTOS HV SUBSTATION PROJECT 44 CHEFFIA S/S FINAL RECEPTION HV SUBSTATION PROJECT WHY MATELEC 45 HV SUBSTATION PROJECT WHY MATELEC ? Working with MATELEC for HV Substation Turnkey Projects, means choosing the following Advantages & Benefits: - Skilled & Experienced Teams in all the Activities. - Application of IEC, ANSI & ISO Standards. - Respect R t & Ad Adoption ti off Cli Clientt St Standards d d &R Requests. t - Willpower not to Exceed the Deadlines and to Accomplish a High Quality Projects. Projects - An Effective & Quick After Sale Services. - Partnership P t hi with ith the th Client. Cli t 46 HV SUBSTATION PROJECT THANK YOU 47 HV SUBSTATION PROJECT QUESTIONS SESSION 48