The power grid

advertisement

Erik Koldby. ABB A/S: Symposium Energy and CO

2

The power grid

Emissions / Politics – Global CO

2

Economics 2009-08-19--20

© ABB Group

August 19, 2009 | Slide 1

Agenda

© ABB Group

August 19, 2009 | Slide 2

Some basics

The existing grid

Distributed generation, increasing amount of wind

Liberalization, unbundling, market structure

Cables

How to handle more wind in the grid

Energinet.dk’s proposal for future grid

HVDC Technologies

A long HVDC interconnection

Power from shore

Offshore wind plans, HVDC Light for wind

The next Danish offshore wind farms

Coming interconnections

Offshore grid visions

Challenges for an offshore HVDC grid

Some basics - AC versus DC

+

AC

Simple transformers circuit breakers motors

Easy tapping

-

Cable power / distance limitations

Width of right of way

Synchronism may be a challenge

© ABB Group

August 19, 2009 | Slide 3

DC

No power / distance limitations

Width of right of way

Synchronism is not a problem

Cost of converters

Losses at short distances

Some basics - Losses

© ABB Group

August 19, 2009 | Slide 4

Losses are proportional to resistance (R) and second power of current (I 2 ) Thus a doubling of voltage and half value of current will reduce the losses to ¼

The electrical power industry have a many decade long tradition for capitalization of losses

Example: A cheap high loss transformer is compared with an expensive low loss transformer by adding the loss capitalization to the price

Price evaluation

P

0

= Price

(1+i) n - 1 i x (1+i) n purchace kwh

+ P x 8760

0 x C

0

+ P

L x C

L

P

L

(1+i) n - 1 i x (1+i) n kwh x 8760 x

( )

R

2

The existing grid

The N-1 criteria

© ABB Group

August 19, 2009 | Slide 5

Distributed generation

Local CHP

Main fuel: natural gas

Prioritized production

No power and U/f control in local CHP’s

Focussing on energy efficiency

Today a paradigm shift towards focus on utilisation of wind energy

© ABB Group

August 19, 2009 | Slide 6

Increasing amount of wind power in the grid

1997 2002

© ABB Group

August 19, 2009 | Slide 7

Symbols indicating increasing turbine size

Liberalization, unbundling, market structure

Competition

Market

Splitting companies active in production as well as transmission/distribution

Mergers

One state owned TSO (transmission system operator)

State owned major producer

© ABB Group

August 19, 2009 | Slide 8

The challenge from the visual impact

© ABB Group

August 19, 2009 | Slide 9

Percentage of grid in cables

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

0%

19

76

19

80

19

85

19

90

19

95

19

97

19

99

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

400-132 kV

60-30 kV

20-6 kV

0,4 kV

Year –

See note 1

Note 1: Not all years are included in the beginning but from 1999 every year is included

Note 2: 1993 political decision: All new HVDC lines must be in cables

See note 2

Cable design and production

© ABB Group

August 19, 2009 | Slide 10

Future: How to handle more wind in the grid

Balancing measures

Integration in other sectors

Short term Medium term Long term

Interconnections Distributed offshore wind

Stronger existing grid

Flexible consumption

“negative spot prices”

Heat pumps on

CHP’s

Flexible production

Domestic heat pumps

Electrical heating on CPH’s

Plug-in hybrid cars

Electrical cars

Hydrogen storage

Compressed air energy storage

Battery storage

Use (electrolysis based) hydrogen in transportation

Use (electrolysis based) hydrogen in gas sector

© ABB Group

August 19, 2009 | Slide 11

Future development of the 132-150kV grid

Overhead lines to be removed The new structure – in underground cables

© ABB Group

August 19, 2009 | Slide 12

HVDC Technologies

HVDC Classic

Current source converters

Line-commutated thyristor valves

Requires 50% reactive compensation

(35% HF)

Converter transformers

Minimum short circuit capacity > 2x converter rating

HVDC Light

Voltage source converters

Self-commutated IGBT valves

Requires no reactive power compensation (15% HF)

Standard transformers

No minimum short circuit capacity, black start

© ABB Group

August 19, 2009 | Slide 13

HVDC Cables - Different Technology VSC / LCC

VSC HVDC

PEX Plastic Insulation

Low weight, land cable 10 kg/m

Low number of joints for land installation

Prefabricated joints (1 day/joint)

Flexible allows coiling and installation from barge, more than 200 ships avaliable

Flexible production line, a.c. and d.c. cables in same production line

Max cable voltage 320 kV

LCC HVDC

Oil impregnated insulation

High weight, land cable 25 kg/m

High number of joints for land installations

Tailored joints ( 5 days/joint)

Requires special ship for installation, 3 available globally

Dedicated production line for d.c. Cables

Max cable voltage 500 kV

© ABB Group

August 19, 2009 | Slide 14

Comparison LCC HVDC and VSC HVDC

Technology Convertor

Relative size

Technology Cable

Typical delivery time

Static reactive support

Dynamic reactive support

Independent control of active and reactive power

Scheduled maintenance

LCC HVDC (since 1954)

Thyristor valve, grid commutation

VSC HVDC (since 1997)

Transistor valve (IGBT), self commutation

4

Oil paper

Field joints ( 5 days)

Sea cable installation special ship

( 3 available)

36 month

Yes

No

No

1

Extruded

Prefabricated land joints ( 1 day )

Sea cable installation from barge ( > 200 available)

24 month

Yes

Yes

Yes

Typically < 1 % Typically < 0,5 %

Losses typical system

AC network losses

© ABB Group

August 19, 2009 | Slide 15

2,5 – 4,5 %

Not affected

4 – 6 %

Can be reduced by stabilising the ac-voltage

The development of HVDC Light

®

1997

Hellsjön

+/- 10 kV

1999

7 MW - 50 MW

+/- 80 kV

2001 up to 330 MW up to +/- 150 kV

2004 up to 550 MW up to +/- 150 kV

2007 up to 1100 MW up to +/- 300 kV

MW / kV

1200

Increased power and voltage

Power in MW

1000

Voltage in kV

800

600

550550

700

1100

400

220

330

350

200

3 3 3

50 60

0

1997 1999 2000 2002 2004 2006

© ABB Group

August 19, 2009 | Slide 16

4

3,5

3

2,5

2

1,5

1

0,5

0

Fewer components, lower losses

Relative no. of components

Losses in %

1997 1999 2000 2002 2005

NorNed – 580 km Norway to the Netherlands

© ABB Group

August 19, 2009 | Slide 17

Transmission 6.400 MW and 2.000 km

800 kV AC Efficiency

88 %

800 kV UHVDC

94 %

© ABB Group

August 19, 2009 | Slide 18

Troll A HVDC Light  project – Power from shore

Troll A

SM

MotorFormer

4-pole, 40MW

0 - 65 Hz

56kV

~

=

70 km

+/- 60kV

HVDC Light

=

~

Kollsnes

138kV

© ABB Group

August 19, 2009 | Slide 19

Offshore wind plans

© ABB Group

August 19, 2009 | Slide 20

Existing or planned offshore windfarms Each dot ~200 MW

Possible locations for future offshore windfarms. Each dot ~200 MW

It is assumed that Denmark can install 200 MW/year

Tjæreborg HVDC Light 

2000

8 MW, 8 kV

AC connections to 10 kV

Main reason for project:

Testing HVDC - VSC technology with wind turbines

© ABB Group

August 19, 2009 | Slide 21

BorWin 1 Technical Data:

• In operation: 1990-1992

• Power rating:

• DC voltage: ± 450 kV

2000 MW

• DC line: 1480 km

© ABB Group

August 19, 2009 | Slide 22

BorWin1 Single line diagram

© ABB Group

August 19, 2009 | Slide 23 Figure 2 – Overview of the BorWin 1 HVDC project

The next Danish offshore wind farms

© ABB Group

August 19, 2009 | Slide 24

Anholt / Djursland

400 MW

AC grid connection

Kriegers Flak

Germany: 330 MW

Sweden: 549 MW

Denmark: 600 - 800 MW

Vision: Grid connection and interconnection

Coming interconnections

Skagerrak 4

600 MW

400 kV

Balanced bipole (again)

Cobra cable

(Denmark – Netherlands)

600 – 700 MW

Could be first step in am

North Sea offshore grid

© ABB Group

August 19, 2009 | Slide 25

The Desertec vision

Participants:

(July 13, 2009)

ABB

ABENGOA

Solar

Cevital

Deutsche Bank

E.ON

HSH Nordbank

MAN Solar

Millennium

Münchener Rück

M+W Zander

RWE

SCHOTT Solar

SIEMENS

© ABB Group

August 19, 2009 | Slide 26

ABB vision 1992

Hydro

200 GW

© ABB Group

August 19, 2009 | Slide 27

Wind

300 GW

25.000 km 2

5.000 x 10km

Solar

700 GW

8.000 km 2

90 x 90km

Unexpected partners share the vision

© ABB Group

August 19, 2009 | Slide 28

Some challenges for an offshore HVDC grid

Technical

VSC HVDC

Voltage

Circuit breaker

Operation

Political

Frame conditions

No references

Economical

Uncertainty in planning, Delays

© ABB Group

August 19, 2009 | Slide 29

Quebec – New England multiterminal HVDC system

Radisson

Technical Data:

• In operation: 1990-1992

• Power rating: 2000 MW

• DC voltage: ± 450 kV

• DC line: 1480 km

© ABB Group

August 19, 2009 | Slide 30

If you need to contact me:

Erik Koldby

Senior Engineer

ABB A/S, Dept. PT-FES

Håndværkervej 23

DK-7000, Fredericia, DENMARK

Phone: +45 7924 7981

Mobile: +45 2028 8281 email: erik.koldby@dk.abb.com

© ABB Group

August 19, 2009 | Slide 31

© ABB Group

August 19, 2009 | Slide 32

Download