01300 SUBMITTALS (9/05) A. SCOPE (8/03) This Section outlines the items that the Manufacturer must prepare or assemble for submittal prior to or during the progress of the work. There is no attempt herein to state all of the procedures and requirements for each submittal. The Manufacturer's attention is directed to the individual Specification Sections in these Contract Documents that contain in detail additional and special submittal requirements. The Engineer reserves the right to direct and modify the procedures and requirements for submittals as necessary to accomplish the specific purpose of each submittal. Should the Manufacturer be in doubt as to the procedure, purpose, or extent of any submittal, he should direct his inquiry as noted below. All submittals shall indicate the Contract title and number: Pump Station VSD Replacement, Two 150 HP Motors Purchase – K01003C04 All technical submittals to the Engineer shall be addressed to: Steven Franks TN & ASSOCIATES 1033 N. Mayfair Road, Suite 200 Milwaukee, WI 53226 All administrative submittals and requests for payment shall be directed to Thomas W. Marcussen Senior Project Manager Milwaukee Metropolitan Sewerage District 260 West Seeboth Street Milwaukee, WI 53204-1446 B. ADMINISTRATIVE SUBMITTALS (8/03) The Contractor shall provide all of the submittals required by the Bidding Requirements, the GENERAL CONDITIONS, the SUPPLEMENTAL CONDITIONS, Division 1, GENERAL REQUIREMENTS, and as may be specifically required elsewhere in these Contract Documents. BID BREAKDOWN The following breakdown of the lump sum bid is to be given with the Bid Form. The price breakdown shall be fairly apportioned to the items listed, and shall meet with the Owner's approval prior to the Contractor's first request for partial payment. If so requested, the Contractor shall substantiate any price or prices with additional detail price breakdown. 01300 1 LUMP SUM BID ITEMS Bid Breakdown Greenfield Park Pump Station Furnish and deliver two 150 HP vertical induction type electrical motors Provide training session, functional testing, and O&M manuals for 150 HP motors Provide preventive maintenance visits to the pump station. Cost TOTAL BID C. TECHNICAL SUBMITTALS (9/05) GENERAL (7/02) Requirements in this Section are a general summary and in addition to any specific requirements for submittals specified in other Sections of these Contract Documents. All documents shall be in the English language. Data submitted shall in no case be any larger than 11" x 17". Data submitted shall have sufficient detail for determination of compliance with the Contract Documents. Review of substitutions, schedules and lists of materials submitted or requested by the Manufacturer shall not add to the Contract amount, and any additional costs that may result therefrom shall be solely the obligation of the Manufacturer. The Owner shall not be responsible for providing engineering or other services to protect the Manufacturer from additional costs accruing from such approvals. The Owner is not precluded, by virtue of review, acceptance, or approval, from obtaining a credit for construction savings resulting from allowed concessions in the work or materials therefor. No equipment or material for which listings, drawings, or descriptive material are required shall be fabricated or purchased until the Engineer has on hand copies of such approved lists and the appropriately stamped final shop drawings. Submittals will be acted upon by the Engineer as promptly as possible, and in all cases within 14 days of receipt, (except for O & M manual initial submittals, which will be acted upon within 45 days of receipt), and returned to the Manufacturer. Delays caused by the need for resubmittals shall not constitute reason for an extension of Contract time. 01300 2 SHOP DRAWING SUBMITTAL PROCEDURE (7/02) The Manufacturer shall submit to the Engineer for his review 6 copies of shop drawings, electrical diagrams, and catalog cuts for fabricated items and manufactured items (including mechanical and electrical equipment) furnished under this Contract. The initial submittal of shop drawings shall be accurate, distinct, and complete, and shall contain all required information, including satisfactory identification of items, units, and assemblies in relation to the applicable parts of these Contract Documents. Unless otherwise approved by the Engineer, shop drawings shall be submitted only by the Manufacturer, who shall indicate by a signed stamp on the shop drawings, or other acceptable means, that they (the Manufacturer) have checked and approved the shop drawings, and that the work shown is in accordance with the Contract Documents and has been checked for dimensions and relationship with other work. The practice of submitting incomplete or unchecked shop drawings for the Engineer to correct or finish will not be acceptable, and shop drawings which, in the opinion of the Engineer, indicate that they have not been checked by the Manufacturer will be stamped, notated as "Rejected" and returned to the Manufacturer for resubmission in the proper form. When shop drawings have been reviewed by the Engineer, two sets of the submittal copies will be returned to the Manufacturer appropriately stamped and notated. If major changes or corrections are necessary, the shop drawing may be notated as “Rejected - See Remarks” and only one set will be returned to the Manufacturer with such deficiencies indicated, and the Manufacturer shall correct and resubmit the shop drawings in the same manner and quantity as specified for the initial submittal, unless otherwise indicated by the Engineer. If changes or corrections to be made by the Manufacturer necessitate a resubmittal for the Engineer's further review, the shop drawings copies will be notated, "Amend and ReSubmit." Shop drawing copies returned to the Manufacturer and notated with either "Make Corrections" or "No Exceptions Taken" are to be considered appropriately stamped final shop drawings. If changes are made by the Manufacturer (in addition to those requested by the Engineer) on the resubmitted shop drawings, such changes shall be clearly explained by the Manufacturer in a transmittal letter accompanying the resubmitted shop drawings. The review of shop drawings and catalog cuts by the Engineer shall not relieve the Manufacturer from responsibility for interfacing with the Installation Contractor for work that will impact the record drawing, correctness of dimensions, fabrication details, and space requirements, or for deviations from the Plans and Specifications, unless the Manufacturer has called attention to such deviations in writing by a letter accompanying 01300 3 the shop drawings submitted and the Engineer approves the change or deviation in writing at the time of that submittal; nor shall review by the Engineer relieve the Manufacturer from the responsibility for errors in the shop drawings. When the Manufacturer does call such deviations to the attention of the Engineer, the Manufacturer shall state in his letter whether or not such deviations cause any deduction or extra cost adjustment. The Manufacturer agrees that shop drawing submittals processed by the Engineer do not become Contract Documents and are not Change Orders; that the purpose of the shop drawing review is to establish a reporting procedure and means to assess the Manufacturer’s understanding of the project requirements, and is intended for the Manufacturer's convenience in organizing his work and to permit the Engineer to monitor the Manufacturer's progress. SHOP DRAWING REQUIREMENTS (7/02) Shop drawings referred to herein shall include shop drawings and other submittals for both shop and field-fabricated items. The Manufacturer shall submit, as applicable, the following for all prefabricated or manufactured equipment, materials, and systems: GENERAL Shop drawings or equipment drawings, including dimensions, size and location of connections to other work, weight of equipment, and components and total assembly. Catalog information and cuts. Assembly plan and instructions. Supporting calculations for equipment and associated supports, or hangers required or specified to be designed by equipment manufacturers or suppliers. Complete Manufacturer's Specifications, including materials description and paint system. Performance data. Suggested spare parts list with current price information. List of special tools required for checking, testing, parts replacement, and maintenance. (Special tools are those which have been specially designed or adapted for use on parts of the equipment, and which are not customarily and routinely carried by maintenance mechanics.) List of special tools furnished with the equipment. 01300 4 List of materials and supplies required for the equipment prior to and during startup. List of materials and supplies furnished with the equipment. Special handling instructions. Requirements for storage protection and maintenance prior to installation and while in storage. Requirements for routine maintenance required prior to plant startup. List of all exceptions to the Contract Documents requested by the Manufacturer. ELECTRICAL Wiring and control diagrams of systems and equipment. The submittals shall include satisfactory identification of items, units, and assemblies in relation to the Specification Section number and the system or equipment identification or tag number shown on the Plans, or as provided in the applicable Specification Section. Should the Manufacturer propose any item on his shop drawings, or incorporate an item into the work, and that item should subsequently prove to be defective or otherwise unsatisfactory, regardless of the Engineer's preliminary review, the Manufacturer shall, at its own cost, replace the item with another item that will perform satisfactorily. SUBMITTALS REQUIRED FOR FOREIGN-MANUFACTURED ITEMS (9/82) In addition to the submittal requirements stated above, the Manufacturer shall submit the names and addresses of companies within the United States that maintain technical service representatives and a complete inventory of spare parts and accessories for each foreign-made item proposed for incorporation into the work. Failure of the Manufacturer to prove the foregoing capabilities shall be cause for rejection of the foreignmanufactured items. OPERATION AND MAINTENANCE (O&M) MANUALS (7/02) The Manufacturer shall furnish twelve copies of a complete manual containing installation, operation, maintenance, and lubrication requirements for each component of mechanical and electrical equipment or system plus one reproducible copy of all submittals larger than 11 inches by 17 inches. The production quality shall be equivalent to offset printing. If offset printed (or equivalent) materials are not available, photocopying from original documents using a properly adjusted plain paper copier will be accepted. However, photocopies of materials containing photographs will not be 01300 5 accepted. It is understood that the Owner has the right to produce additional copies for his own use. All equipment manufacturers and/or suppliers shall be made aware of these requirements and all associated costs shall be included in the costs for furnishing the equipment or system. Initially, six copies of the O&M manual shall be submitted to the Engineer on or prior to delivery of the equipment. Manufacturer shall update the original 6 copies of the O&M manuals to reflect any as built changes that may take place during startup and comments from the Engineer. All as built updates to the O&M manual shall be submitted to the Engineer within 3 weeks of successful completion of functional testing of the motors. At this time six additional copies of the as-built O&M manuals shall be submitted to complete the required 12 copies. Note that final payment for services will not be rendered until the O&M manuals are complete. Each O&M Manual shall include, but not be limited to, the following: Diagrams and illustrations. Detailed description of the function of each principal component of the system. Performance and nameplate data. Installation instructions. Procedure for starting. Proper adjustment. Test procedures. Operating procedure. Shutdown instructions. Emergency operating instructions and troubleshooting guide. Equipment use Safety precautions. Bill of material/parts list Maintenance and overhaul instructions shall include detailed assembly drawings with part numbers, parts list, instructions for ordering spare parts, and complete preventive maintenance instructions required to assure satisfactory performance and longevity of the equipment. Lubrication instructions shall list points to be greased or oiled; shall recommend type, 01300 6 grade, and temperature range of lubricants; and shall recommend frequency of lubrication. List of electrical relay settings and control and alarm contact settings. Electrical interconnection wiring diagram for equipment furnished, including all control systems. The O&M manual submittal shall be preceded by an Equipment Data Form, completely filled out, (see Sample Equipment Data Form at the end of this Section), bound with a binder clip and placed in an expansion type manila file pocket. Each file pocket shall be clearly labeled with the equipment description and tag number. The file pockets shall be submitted to the Engineer in similarly labeled expanding wallets with ties. Whenever possible, material shall be 8-1/2 inches by 11 inches or 11 inches by 17 inches z-folded to 8-1/2 inches by 11 inches. If necessary, materials larger than 11 inches by 17 inches may be provided. They shall be folded to approximately 8-1/2 inches by 11 inches so that the title block is clearly visible without unfolding. All material shall be tailored to the specific function that the equipment serves in the facility. If material covers more than one product type or includes equipment information not relevant to the project, the applicable information for the equipment supplied shall be clearly indicated by highlighting the information using a yellow felt tip marker manufactured for that purpose. Highlighting that obliterates the information when photocopied is not acceptable. The relevant information shall also be indicated by an arrow located in the margin. If catalog cuts are included in the submittal, the catalog name and number, and the company name, address and telephone number shall be provided on the catalog cut or typewritten on a separate sheet of paper. EQUIPMENT DATA FORMS (9/85) As part of the O&M Manual submittal, the Manufacturer shall provide an Equipment Data Form completely filled out for each equipment item. A sample Equipment Data Form will be found at the end of this Section. The equipment data shall be typewritten on printed forms available from the Engineer and submitted with the O&M Manual for review by the Engineer. The manufacturer's standard form, or photocopies of the sample form, will not be acceptable as a substitute for the printed forms. The term "Maintenance Operation" as used in the Equipment Data Form shall be understood to mean any routine operation required to assure the satisfactory performance and longevity of the equipment. Examples of typical Maintenance Operations are lubrication, belt tensioning, adjustment of pump packing glands, and routine adjustments. The maintenance summary portion may take as many pages as required. However, the order and format shown must be adhered to. Only 8-1/2-inch by 11-inch paper will be accepted. The maintenance operations and their frequencies must be typed on the forms. 01300 7 In completing the recommended spare parts list portion of the Equipment Data Form, the data provided in the "Part No." and "Description" columns shall be consistent with the terminology used in the equipment manufacturer's Bill of Material/Parts List provided with the O & M Manuals. Spare parts provided by this Contract must be identified by placing two asterisks after the part number. The term "Unit" is the unit of measure for ordering the part, e.g., each, lot of 3, box of 100, etc. The term "Quantity" is the number of units recommended. The term "Unit Cost" is the purchase price of a unit at the time the Equipment Data Form is completed. MATERIAL AND EQUIPMENT COLORS (7/02) The Engineer will provide a schedule of selected colors within 30 days after approval of materials and equipment and after receiving samples of the manufacturers' standard colors for those items requiring Owner's selection. CERTIFICATES OF COMPLIANCE (9/82) A Certificate of Compliance shall be furnished for materials specified to a recognized standard or code prior to the use of any materials specified for the work. The Engineer may permit the use of certain materials or assemblies prior to sampling and testing if accompanied by a Certificate of Compliance. The Certificate shall be signed by the manufacturer of the material or the manufacturer of assembled materials and shall state that the materials comply in all respects with the requirements of the Specifications. A Certificate of Compliance shall be furnished with each lot of material delivered to the work and the lot so Certified shall be clearly identified in the Certificate. All materials used on the basis of a Certificate of Compliance may be sampled and tested at any time. The fact that material is used on the basis of a Certificate of Compliance shall not relieve the Manufacturer of responsibility for incorporating material in the work that conforms to the requirements of the Contract Documents and any such material not conforming to the requirements will be subject to rejection whether in place or not. The Engineer reserves the right to refuse permission for use of material on the basis of a Certificate of Compliance. D. PAYMENT (7/02) Payment for the work specified in this Section will be included as part of the total lump sum amount stated in the Bid. 01300 8 SAMPLE EQUIPMENT DATA FORM (9/85) PROJECT NAME _________________________________________________________ CONTRACT NO. _________________________________________________________ MANUFACTURER _________________________________________________________ EQUIPMENT NO. _________________________________ ASSET NO. _________________ DESCRIPTION ____________________________________ MMIS NO. __________________ LOCATION ___________________________________________________________________ MANUFACTURER ____________________________________________________________ PURCHASED FROM _____________________________ PURCHASE DATE _____________ VENDOR ORDER NO. ___________________________ PURCHASE PRICE _____________ LOCAL SUPPLIER ______________________________ PHONE _______________________ ADDRESS ____________________________________________________________________ MODEL NO. ___________________________________ SHIPPING WT/UNIT ____________ NO. OF UNITS ___________ SERIAL NOS. ________________________________________ 01300 9 MAINTENANCE SUMMARY EQUIPMENT NO. _____________________________ ASSET NO. _____________________ DESCRIPTION ________________________________ MMIS NO. ______________________ MAINTENANCE OPERATION FREQUENCY List briefly each maintenance operation required and refer to specific information in Manufacturer's Maintenance Manual if applicable. Refer by symbol to "Lubricant List" for Lubrication Operation List required frequency of each maintenance operation ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- ------------------------------------------------------------------- -------------------------------------------- 01300 10 RECOMMENDED SPARE PARTS LIST EQUIPMENT NO. __________________________________ ASSET NO. ________________ DESCRIPTION _____________________________________ MMIS NO. _________________ SPARE PARTS LIST PART NO. COST DESCRIPTION UNIT QUANTITY UNIT ----------- -------------------------- ---------- ---------- ------------ ----------- -------------------------- ---------- ---------- ------------ ----------- -------------------------- ---------- ---------- ------------ ----------- -------------------------- ---------- ---------- ------------ ----------- -------------------------- ---------- ---------- ------------ ----------- -------------------------- ---------- ---------- ------------ ----------- -------------------------- ---------- ---------- ------------ ----------- -------------------------- ---------- ---------- ------------ Note: Identify parts provided by this Contract with two asterisks. ===================================================================== ADDITIONAL DATA AND REMARKS --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- ****** 01300 11