Natural Gas Pipework Installation to Multi-Occupancy Dwellings guidelines for designers / builders 3 Contents Definition of multi-occupancy dwellings 3 Merer locations: n General Requirements n Installation up to the Meter 3 3 External Locations n Meter Cabinets (Pre-Fabricated) n Meter Banks (Purpose-Built) 4 4 Internal Locations n Meters in a Common Area n Meters in Underground Car-Park / Open Basement Area Marking of Meters 5 6/7 8 Installation Pipework (from Meter to Riser) n External Underground Pipework n Internal Underground Pipework 9 10 External Riser Options n Pipework concealed in Rain Water Down-pipe n External Risers behind Cladding / Brick 11 12 Internal Riser Options n Open Riser n Gas Pipework in Protected Shafts n Internal Ducts - Continuous n Internal Ducts - Stopped n Internal Ducts - Filled 13 13 14 15 16 Installation Pipework - (from riser to welling) 17 n Pipework within the Screed n Pipework at Ceiling Level n Bringing Installation Pipework beyond one Apartment to Another Appendix n Pipes in Voids n Isolation Valve 18 Terminology n Terminology & Useful References 19 Gas pipework and other services 20 Irish standards 20 n Your Next Residential Scheme 20 2 Definition Piped natural gas can be supplied safely and efficiently to multiple dwellings and the requirements relating to the installation are to be found in the current edition of I.S. 813, “Domestic Gas Installations”. A multiple dwelling of 5 or more floors including a basement but excluding any plant housing on roof is regarded as a multi storey building and construction and use should comply with the Local Government (Multi-Story Buildings) Act of 1988. A multi-occupancy dwelling is a building containing more than two dwelling units. A multiple dwelling can be any of the following: n A purpose built apartment building n An existing single dwelling modified to accommodate a number of separate dwellings, or NOTE: n Dwelling units contained in a mixed use building e.g. shops / offices downstairs with dwelling units above. This Booklet is intended for guidance to the requirements of I.S.813. This Booklet should not conflict with or be substituted for I.S.813 Meters locations All meters must be earth bonded in accordance with the current edition of the ETCI regulations. Refer to Booklet 2 for further details. General Meter Requirements Provision must be made for easy access to, reading or removal of a meter. Installation up to the Meter Design and or location must protect the meter and it’s connections against the possibility of corrosion. Bord Gáis provide and lay all external underground gas mains, and service pipework up to the point of a meter location. Meters must not be located where they may be exposed to extreme temperatures or ignition sources (e.g. switch gear). For trench requirements relating to gas mains and services, consult Booklet 1 of the Bord Gáis Technical Manual pages 2, 3 and 4. Meters must not be located where they may be exposed to accidental damage. For details of external installation pipework requirements from the meter to the dwelling, please consult pages 9 & 10 of this booklet. Meters may not be located in a position open to a stairway unless contained within a compartment per detail on page 5. Meters must not occupy a space in any part of a multi-occupancy building which may hinder escape in the event of an emergency. All downstream installation pipework, fittings and auxiliaries of the meter, should be designed so to operate normally at pressures up to 20mbar. 3 External meter locations Meters may only be located within the building when site design cannot facilitate them externally. The preferred location for meters supplying units in a multi-occupancy building is in an enclosure, external to the building. The structural housing of externally located meters may be either pre-fabricated or purpose-built (See page 9 - 12, booklet 1 of this guide, and information below). Dimensions of each six meter cabinet: 1160mm high x 750mm wide x 300mm deep. Isolation Valve positioned 2m minimum from external Gas Meters Fig. 1 Pre-fabricated Meter Cabinet 600mm min. cover Outlet Pipework 63mm P.E. service pipe Fig. 2 Purpose-Built Meter Manifold (Suitable for numerous meter arrangements, See Booklet 1 page 12) Note: Pre-fabricated Meter Cabinet: The compartment must meet the structural and fire resistant requirements applicable to that part of the building. All voids within and around the compartment must be fully sealed and fire proofed to prevent the ingress of air or gas to the cavity wall or other voids. The cabinet may be concealed with walls at either side as shown in figure 1. It is not permitted to recess a multiple meter cabinet into the external wall of the building, unless all of the requirements below are met. Purpose-built Meter Compartment: If the enclosure opens to the outside but is set within the building structure then all pipe sleeves or entries into the building must be sealed with an approved fire sealing material. Access doors should not be lockable. This meter arrangement may be located away from the building or recessed into the outer leaf of the building structure. Ventilation must be provided to atmosphere in the form of a fully louvred door or in the case of a solid door, vents must be located at the top and the bottom of the door. Each vent must provide a minimum of 5,000mm2 free area or 0.5% of the compartment floor area, which ever is greater. If recessed into the structure of the building or to be placed within the building line, meters must be in a completely sealed compartment with the exception of access and ventilation provided by louvred doors to the outside air. This arrangement is only permitted on a low pressure site i.e. service pressure ≤ 100mBar. 4 Internal meter locations Meters in Common Areas: n Access doors to the cabinet / compartment must be lockable and meters must remain accessible at all times If the meters supplying the units in a multi-occupancy building cannot be located externally then they may be located within the building line subject to the following: n The enclosure, including access doors, must meet the structural and fire resistant requirements applicable to that part of the building. n Low pressure gas network must be available i.e. service pressure ≤ 100mBar. n The ventilation to the outside atmosphere must be provided through suitably sized and constructed ducts, provided at high and low level. Ducts should be protected and constructed to prevent fire damage. n If the compartment is above ground level, each vent should provide 5,000mm2 minimum free area or 0.5% of compartment floor area, which ever is greater. Separation between the exits of each ventilating duct to atmosphere must be at least 450mm apart. If the compartment is to be positioned below ground level, Bord Gáis must be consulted for ventilation requirements. n Meters should be positioned in an area of free ventilation as close as possible to the external wall where the gas service pipe enters. n Meters may not be located beneath a stairs, unless they are placed within a minimum two hour fire resistant and sealed compartment ventilated directly to the outside of the building. This compartment must not obstruct exits from the building. n Provision should be made for a steel service to enter into the building through a suitable sleeve where traversing a cavity or void. (See figure 3 below). n The dimensions required for different meter arrangements, are available on page 12 of Booklet 1. n Care must be taken when locating the external isolation valve where it Ducts are required to provide ventilation for meter compartment. Ducts should be sleeved through cavities, suitably fire rated and provide minimum air openings as detailed above. is freely accessible, e.g. not in a parking area where vehicles may restrict access. The enclosure, including access doors, must meet the structural and fire retardant requirements per Building Regulations. Minimum compartment dept of 400mm must be provided for the manifold, not including provision for enclosure or protective barrier External Isolation Valve Area Isolation Valve 600mm min Steel Manifold 100mm min cover From Mains At early construction provide Sleeve for Steel Service Pipe. (Service pipe and manifold provided by Bord Gáis) Fig. 3 Multiple Meter Enclosure - within building 5 Note: Polyethylene pipework is not permitted inside the building. Meters located in the underground car park / open basement area Meters located in an underground car park or open basement area must have direct access to natural ventilation. Mechanical ventilation may not be relied upon. Top-entry cabinets pre-fabricated off site. Option A: External Isolation Valve 600mm minimum cover required Dimensions of each six meter cabinet: 1160mm high x 750mm wide x 300mm deep. Area Isolation Valve 300mm min. Contains Six Meters Contains Six Meters P.E. Pipe Top-entry cabinets open to naturally ventilated area At early construction provide suitable sleeve for Steel Service Pipe (Service pipe and manifold provided by Bord Gáis) 1800mm max. Fig. 4 Top-entry cabinets in Underground Car Park / Open Basement Area Read in conjuncion with pg 7. n Meters must always be positioned so to avoid the possibility of impact. n Provision should be made for the steel service to enter into the building through an appropriate sleeve where traversing a cavity or void. n If it is required that the meters or gas service be located in a dedicated room within the basement or in a basement lacking natural ventilation, Bord Gáis must be consulted for specifications and ventilation requirements. n The gas service must pass through a ventilated area that is publicly accessible (i.e. providing access for Bord Gáis maintenance at all times). The gas service may not pass through a protected corridor / stairway / shaft, refuse area or private premise (i.e. dwelling or commercial unit). n Care should be taken when locating the external isolation valve so it is freely accessible at all times, e.g. not in a parking area where vehicles may restrict access. n Electrical current carrying equipment or cables must not be in contact with or suspended from gas equipment or plant. 6 On-site fabricated meter manifold. Supply pipework supported at ceiling level. Option B: External Isolation Valve 600mm minimum cover required Area Isolation Valve 300 mm min From Mains P.E. Pipe Steel manifold open to naturally ventilated area At early construction provide suitable sleeve for Steel Service Pipe (Service pipe and manifold provided by Bord Gáis) If manifold is at a level exposed to possible impact, additional provision must be made with a protective barrier. Manifold located at high level, minimum depth required is 400mm. Fig. 5 Meters in Underground Car Park / Open Basement Area Read in conjuncion with pg 6. n The meter installation must not be located directly beneath a ventilation grill or in a position liable to cause ingress of water, unless weather protected. n For the dimensions required for differing meter manifold arrangements, please consult Booklet 1, page 12. n If required at low level a protective barrier must be placed around the meters. Sufficient impact resistance provided by the builder. Top-Entry Cabinets v’s Steel Manifold: The top-entry cabinet is tailored for better on-site co-ordination as the heating installer can connect directly to the cabinet. The steel manifold offers greater flexibility in available meter configurations, but requires on-site fabrication. n In the case of the steel manifold protection from tamper and impact may be provided by the provision of a suitable steel cage. The use of a steel mesh casing will allow for ease of meter reading. The area isolation valve must remain accessible at all times. 7 Marking of meters All meters in a multiple meter installation must be clearly marked to indicate the dwelling number and floor number supplied by that meter. Apartment: 1 Floor: Ground Apartment: 2 Floor: Ground Apartment: 3 Floor: 1st Apartment: 4 Floor: 1st Apartment: 5 Floor: 2nd Apartment: 6 Floor: 2nd Fig. 6 Marking of Meters The marking of meters is essential for safe operation, maintenance and accurate billing of gas consumed. Note: Meters will not be fitted if the supply pipework is not brought to within 450mm of the meter position, or pipework is not labeled indicating the dwelling or premise it is to supply. 8 Installation pipework (from meter to riser) External Underground n Minimum sand surround or fine fill cover in trench of 150mm. Should the meters be located a distance away from the building, all pipe runs should travel underground up to the base of the external wall. Pipework from the base of the external wall may travel externally (See figure 7) or pass directly into the building (See figure 8). Polyethylene pipework can only be used externally and must not be taken into the building. All metallic underground pipework must be suitably protected against corrosion and galvanic action. Metallic pipework may not be jointed mechanically underground. Jointing P.E. pipework underground by mechanical fittings, electro fusion or butt fusion is acceptable. A competent operative must perform jointing. P.E. pipework must, if taken above ground for any distance, be protected against: All underground installation pipework should be covered to sufficient depth to minimise the risk of impact, or loading damage. n Exposure to high temperature Installation pipework from the meter under soft ground or under vehicular traffic must have: n Exposure to sunlight n Impact or abrasion damage n Minimum trench cover of 375mm (additional protective sleeve required when placing supply pipework beneath vehicular traffic). Consult Booklet 2 pages 12, 13 and 14. Cover or Sheath Metal may be used for Aesthetic Purposes (See Section 4) PVC Coated Copper Road (vehicular traffic) 375mm min cover From Meter PVC Coated Copper Foundation Protective sleeve Fig. 7 Installation Pipework - Rising on External Wall 9 Installation pipework under concrete paths, (pedestrian traffic only, See figure 8) should have: n Minimum cover of 25mm between sleeve / wrapping and concrete finish. n Pipework in sleeve or protective wrapping (See Booklet 2 for further details) n All underground pipework should be pressure tested before initial wrapping or covering takes place. Protect exposed pipework from possible damage Sleeve Path (Pedestrian traffic only) 25mm min screed cover 25mm min cover Concrete FROM METER Protective sleeve Foundation Fig. 8 Installation Pipework -Entry Through Outside Wall Internal Underground Open Basement / Car Park Area: n be coated / protected against corrosion n avoid structural beams where possible n be adequately supported (See Booklet 2, “Bord Gáis Technical Manual”) n be sleeved through any void or cavity n be colour coded per pg 18. Pipework from the meter should be brought to ceiling level immediately. Pipework travelling along ceilings of an open basement / car park area (See figure 9), should: n take the shortest path practical from the meter to the rising duct See Internal DuctContinuous pg.14 See Section 4 and Internal DuctStopped pg.14 FROM METER Sleeve and Fire Stop OPTION 1 Fig. 9 Installation Pipework - From Meters in Open Basement / Car-Park to Riser. 10 OPTION 2 External riser options Pipework concealed in Rainwater Down-pipe Individual units can be supplied by installation pipework constructed as external “risers” on to an outside wall. For aesthetic reasons such ‘risers’ can be hidden within an enclosure outside the fabric of the building (See figure 11B) or within a false rainwater down-pipe, behind pre-fabricated expanded metal duct, suitably weather proofed (Note details below). Fig. 10 External Risers - Hidden If placing installation pipework behind a false PVC rainwater down-pipe (backing removed), the downpipe should be left open top and bottom and secured to the wall. The pipework within should also be adequately supported. External Riser Behind Cladding / Brick (See figures 11A, 11B & 11C) If an external riser is to be hidden within an enclosure in the outer fabric of the building, it should be itself sealed from entry to the building and open to the outside air. Openings to the outside air should be provided at the top and bottom of the riser (additional ventilation openings can be provided at intermediary positions if desired). The minimum free area of each opening must be 5,000mm2 or 1/500th the cross sectional area of the enclosure, which ever is greater. Concealed external riser 11 View A-A Ventilation Opening Possible Meter Location (See Figure 11C below and Booklet 1 page 11) External Cladding or Brick Construction Ventilation Opening Fig. 11A Installation Pipework behind Cladding / Brick Outer Fabric of Building Dwelling 2 Dwelling 3 Dwelling 1 Sleeve and Seal Rise 1 Rise 2 Rise 3 External Cladding or Brick Construction Fig. 11B Plan View of Brick or Cladding. View A-A Lintel Isolation Valve & Service perpendicular to Building Line 600mm min 100mm min slab Fig. 11C Meter Compartment Detail 12 Internal riser options Open Riser Installation pipework rising vertically and left open to the room through which it passes, is acceptable from a standards compliance point of view, however it is unlikely that such a method of piping would be aesthetically acceptable to the designer or occupants. Supporting bracket to be of plastic or same material as pipework In the case of an open riser the pipework should only pass through a common area or the dwelling or premise it is supplying. Should internal open pipework be used it should be: n Sleeved through and fire stopped at each floor (per fig. 19) and, n Constructed of welded steel or continuous / brazed or solder jointed copper tubing and, Fig 12 Support of pipework required so as to prevent corrosion caused by contact with aggressive surfaces n Protected against corrosion. Rising Pipework within Ducts The routing of gas installation pipework through ducts is the most frequently applied solution. This may be achieved in one of the following ways, selection dependent on the configuration of the building, the building programme and the aesthetic parameters set out by the designer (See pages 14, 15 & 16). Note: Gas Pipework in Protected Shafts: If a protected shaft contains a stairway and/or lift, it should not also contain a pipe intended to carry gaseous or liquid fuels. This type of protected shaft must not contain a ventilating duct (other than a duct provided for the purposes of pressurising the stairway to keep it smoke free). Definition of a Protected Shaft: A protected shaft is defined as a shaft which enables persons, air or objects to pass from one compartment to another and is enclosed with fire resisting construction. For further clarification, consult The Building Regulations, Section B. 13 Internal Duct – continuous Detail 1 Third floor apartment Third floor apartment Second floor apartment Second floor apartment First floor apartment First floor apartment Fire sealed at low level Vent to outside air (Fire rated construction) Ground floor apartment Ground floor apartment Car - Entrance / exit Detail 1 Exit Basement Car-park Fig. 13 Installation Pipework in Internal continuous ventilated duct figure 16 and 17 of this booklet. Always consult the Building Regulations (TGD’s), Section B. The construction of the “Continuous Internal Duct” must reflect the fire prevention and structural requirements of the building. Other services may be contained within this duct (See pg 20 of this booklet). The duct must be constructed so to be impervious to gas / air throughout it’s length. The continuous internal duct, as illustrated above, must be supplied with adequate circulating air directly from and to outside air. This must be provided via openings at both extremes of the fire rated duct. The minimum free area of each opening must be 5,000mm2 or 1/500th the cross sectional area of the duct, which ever is greater. Note: Ventilation ducts can be routed horizontally over any distance to the base or the top of this duct. Ducts for this purpose should be fire rated or protected against fire. n If the building arrangement does not suit a Continuous Duct, Then a Stopped Duct (Fig 14) or Filled Duct 9Fig 15) may be adopted. The pipework from the duct can continue its path horizontally in an enclosure once it has exited the continuous duct, provided the lateral duct or sleeve is left open to the duct air, but otherwise sealed per n Low level vents from service shaft / duct should not terminate in the carpark / basement. 14 Internal Duct - stopped Flame Resistant Construction Third floor apartment Third floor apartment Customer Isolation Valve Second floor apartment Second floor apartment First floor apartment Ground floor apartment Customer Isolation Valve First floor apartment Sleeved thru & fire stopped at each floor Ground floor apartment Vent top & bottom at each floor Meters Vent to outside air Open Basement Basement Car-park Exit Fig. 14 Installation Pipework- Stopped and vented top and bottom within each floor. This type of duct is essentially to hide an “open riser” within the building, details on page 13. The stopped duct should be vented to outside air or to the area containing the duct where appropriate, but not to a private premise. The continuous duct option (page 14) or filled duct option (page 16) must take preference where gas pipework travels through either a protected shaft containing a stairs or lift, or a private premise. Sealed sleeves and fire stops should be properly constructed at each floor. Always consult the Building Regulations (TGD’s). Other services may be contained within this duct (See Section 9, Page 20 of this booklet). Requirements The Stopped Duct, constructed on each floor should have fixed air openings (vents) top and bottom. The fixed openings should be a minimum of 5,000mm2 or 1/500th the cross sectional area of the duct, which ever is greater. Note: Consult page 13 – Gas Pipework within Protected Shafts. For alternative options consult pages 14 and 16. 15 Internal Duct - Filled Vermiculite & Cement Mix fill Third floor apartment Second floor apartment Second floor apartment Filled Duct Customer Isolation Valve Grout concrete (no gap) First floor apartment Ground floor apartment Third floor apartment First floor apartment Ground floor apartment Installation pipework Meters Vent to outside air Open Basement Open Basement Exit Fig. 15 Installation Pipework within soil pipe with fire-rated surround filling. The Filled Duct is adopted where provision of ventilation openings is not suitable. In essence, the gas pipework is placed in a duct with the space between the pipework and duct walls filled with a vermiculitecement mix. The installation procedure is as follows: n Factory coated gas pipework is suitably positioned and supported along the service route (the factory coating provides protection from the corrosive effects of the filling material). n All joints must be protected against corrosion, minimum two layers required, (welded or soldered joints are only permitted). n A duct of suitable material is fixed around the gas pipework, allowing adequate space for the filling material. n All pipework from the meter to the apartments are pressure tested by the Registered Gas Installer. n All openings in the duct are sealed and made good, with exception of filling points. n The vermiculite-cement material is mixed at a ratio dictated by vermiculite manufacturers instructions. n The vermiculite-cement mix is lightly compacted into the void with the duct capped off where necessary. Note: The filled duct may not be included within a service shaft containing ventilation ducting or air conditioning. 16 Installation pipework (From the service riser to the apartment) Pipework should not traverse a private premise to supply another dwelling. Where gas supply pipework is laid close to heating system pipework, provision must be made for expansion and contraction of buried pipework. Supply pipework may be continued horizontally from the “service riser” to travel outside the building structure or internally within the floor screed (note figures 16A and 17A below). The pipework should only exit the screed in the apartment being supplied. Pipework may traverse a corridor or common area to arrive at the dwelling being supplied. Pipework exposed to concrete must be protected against corrosive elements with protective wrap or PVC coating. Pipework placed in screed must have a minimum cover of 25mm. Only soldered or welded joints are permitted within the screed. Entry from Outside Air or Internal Continuous Duct Entry from Outside Air or Internal Continuous Duct Customer Isolation Valve (C.I.V. - See Appendix) Ceiling Screed (minimum cover of 25mm) PVC coated or wrapped copper Fire resistant sleeve and mastic Fire Resistant Mastic C.I.V. 16A Fig. 16A Gas pipework entering via screed 16B Fig. 16B Gas pipework entering at high-level Entry from Outside Air or Internal Continuous Duct Dwelling 1 Screed (minimum cover of 25mm) C.I.V. Corridor / Common Area Fire resistant sleeve and mastic Continuous PVC coated or wrapped copper 17A Fig. 17A Gas pipework entering via screed Entry from Outside Air / Internal Duct-Continuous Fire Rated Sleeve Gas Pipework Fire Resistant Mastic Dwelling 1 Ceiling Ceiling Void Corridor / Common Area Specification of Plasterboard dictated by Building Regulations (TGD’s), Section B c for alternative options, consult Appendix - “Pipes in Voids” Fig. 17B Gas pipework entering via ceiling void 17 C.I.V. 17B Appendix Pipes in Voids Where pipes are to be located in voids, any one of the following should be applied: n n The pipe section is welded or continuous throughout its length within the void or, Air vents terminating in open air must be provided. Openings must be a minimum of 500 square mm for every square metre of void surface area or, n The pipe should be contained within a vented, continuous sleeve (as per figure 17B) or, n The void filled with an inert material. Customer Isolation Valve (C.I.V.) Irrespective of supply route, where pipework enters into the apartment (point of entry) a customer isolation valve should: n be located as close as practicable to the entry point of gas pipework to the dwelling and must remain accessible at all times, n be fitted with a handle easy to operate and capable of fully stopping flow with one quarter turn. n be permanently marked to show its purpose (Gas Isolation) and show the “on” and “off” positions. Fig. 18 Customer Isolation Valve (C.I.V.) n The point of entry is deemed to be where the pipework enters through the wall of the complex or exits the screed. n See page 11 of Booklet 2. Fire Stop at Floor Identification of Gas Pipework All pipework traversing through floors should be fire stopped as shown. This does not apply if constructing duct as per page 14. Fire resistant mastic Fig. 19 Fire Stop through Floor n All gas pipework should be identifiable as containing Natural Gas, This can be achieved by colour coding the pipework bright yellow (Yellow Ochre 08 c 35) or by banding. Sleeve n The operator of the building should, on commissioning and handover, be given a drawing showing the location of all gas pipework in the building. Fire resistant mastic 18 Terminology: Building Line The outermost extent of the building structure (archway, balcony or basement) cast vertically on to ground level. Sleeve Rigid (usually non-metallic) pipe material impervious to gas. The annulus between the sleeve and gas pipe acts as a conduit for gas in the event of leakage. Coating Coating may be a factory applied light wrapping, paint or other suitable substance applied to a pipe to protect against corrosion. Void A space in a building lacking any air flow, Any enclosed, generally inaccessible and unventilated space. Duct / Shaft Purpose provided space constructed of building materials for the enclosure of installation pipework or other building services. Wrap Material used to protect pipes from corrosion and also providing some degree of impact protection Useful References Fire Resistant Duct Duct - constructed from material rated as fire resistant (See Building Regulations). Pipework Materials: Booklet 2, BGE Technical Manual Fire Stopped Building component / material designed to prevent the spread of fire through walls or ceilings for a given minimum time. Typical Appliance Consumptions: Booklet 2, BGE Technical Manual or the CIBSE Guide Section C4 Pipe Sizing: Booklet 2, BGE Technical Manual or the CIBSE Guide Section C4 Free Ventilation Ventilation not reliant upon mechanical activation. Installation Pipework Refers to any gas pipework, fittings, meters or ancillaries downstream of the point of delivery nominated by Bord Gáis. This point may be either a combination of a regulator and valve or a meter. Pipework Supports and Fixings: Booklet 2, BGE Technical Manual Mechanical Joint Compression, flange or union type pipe joint. Natural Ventilation Sufficient air movement in a space to ensure one air change per hour (minimum). Naturally Ventilated Basement A naturally ventilated basement is a space below or partially below a building with air openings of sufficient size to cause free air flow at all times. Should gas service pipework or meter installations be required in this space, the minimum air opening requirements must coincide with the Building Regulations (Technical Guidance Documents, Section B 3.5.2.4). Open Riser Rising pipework not enclosed as it passes through living or shared spaces in the building. Riser Installation pipework rising vertically through a building to supply one or more dwellings. 19 Natural gas pipework and other services Service shafts carrying gas pipes should be provided with adequate and suitable means of ventilation, top and bottom, preferably by natural means (See figures 10, 11 & 13). The ventilation should discharge in a safe manner to the open air. Where a vertical service shaft is divided horizontally by fire-stops (fig.14) or other means, each section between stops should be treated as a separate service shaft. Hot Water. (<10BAR) Permitted Gas Pipework should be protected against corrosion Ventilation and Air conditioning. Permitted Gas pipework should be enclosed in a purpose constructed corrosion resistant sealed duct or sleeve with ventilation at each end direct to outside air. Before fitting the ventilation openings and putting into service the duct / sleeve shall be successfully pressure tested to the normal working pressure of the enclosed gas pipe Cold and Chilled Water Permitted Gas Pipework should be protected against corrosion Electricity Permitted Adequate spacing and insulation should be provided based upon the electrical voltage Telecommunications and Data Permitted Adequate spacing and insulation should be provided. Appliance Flues Not Permitted Irish standards FOR GAS MAINS AND SERVICES FOR DOWNSTREAM OF THE METER Bord Gáis install all gas mains and services in accordance with the latest edition of the following Irish Standards: Irish Standard I.S. 813:2002 “Domestic Gas Installations” applies to installations downstream of the meter. This Gas Standard applies to installations downstream of the point of delivery and includes the requirements for meters, appliances and associated pipework in single and multiple occupancy dwellings. I.S. 329 “Code of Practice for Gas Distribution Mains” & All of the above standards can be obtained from the NSAI (National Standards Authority of Ireland). Telephone (01) 8073878. I.S. 265 “Installation of Gas Service Pipes”. For Your Next Development: Phone New Connections at: 1850 411 511 GSDC 3009e Send Development Site Drawings to: plans@bge.ie RGII Tel: 353(0)1 499 7998 Website www.rgii.ie Website: www.bordgais.ie July 2010 Document no: 25698 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the publishers. Information correct at time of printing. The advice above is a guide line only and based on the most authoritative information available at the date of issue and users should ensure that it is relevant to the specific circumstances in which they seek to apply it. Professional advice should always be sought. Users should ensure they have up to date information. © Bord Gáis 20