30" MINIMUM 12" 1" x 45° CHAMFERED EDGE 2" MINIMUM BEYOND BOLT COVER PROVIDE BONDING BUSHING (TYPICAL) 3" MINIMUM BEYOND BOLT CIRCLE 12" PROVIDE STRAIN RELIEF BOLT CIRCLE BY MANUFACTURER OF POLE PROVIDE DOUBLE NUTS AND WASHERS, AFTER LEVELING POLE FILL UNDER BASE PLATE WITH GROUT. PROVIDE TWO DRAINAGE HOLES ON OPPOSITE SIDES. POLE BOLT COVER WITH SAME GEOMETRY AS POLE RIGID STEEL CONDUIT UP TO TEN FEET AND SCHEDULE 40 PVC ABOVE TEN FEET. E WEATHERSEAL BY CUSTOMER F 96" GROUND CLAMP FOR METALLIC CONDUIT ONLY. SLOPE TOP FINISH FROM CENTER TO EDGE FOR DRAINING 1" x 45° CHAMFERED EDGE ALL SIDES PRIMARY SECONDARY PAD MOUNTED TRANFORMER NOTES: A SCOPE - THIS STANDARD COVERS SPECIFICATIONS FOR THE CONSTRUCTION OF PADMOUNT TRANSFORMER FOUNDATION AND GROUNDING. NOTE: GROUNDING BY ELECTRICAL INSTALLER. B CONDUIT - INSTALL AS SHOWN BEFORE SLAB IS POURED. USE 36" RADIUS BENDS, WITH COUPLINGS, NIPPLES AND BUSHINGS AS REQUIRED. BENDS FOR PRIMARY CABLES SHALL BE GALVINAZED RIGID STEEL. TERMINATIONS OF CONDUITS SHALL BE LOCATED EXACTLY AS SHOWN IN FIGURE 1, SOLID OR DOTTED, DEPENDING UPON NUMBER OF DUCTS. TO TELEPHONE GRID (IF AVAILABLE) 1a THE NIPPLE AND BUSHING SHOULD BE INSTALLED AFTER THE TRANSFOMER IS PLACED AND BEFORE THE CABLES ARE PULLED. ES-5 FRONT SEE NOTE 4 2'-6" FINISHED GRADE 3/4" RE-BAR 7'-0" LONG, ONE AT EACH ANCHOR BOLT, SECURE ANCHOR BOLTS AND RE-BAR TOGETHER WITH GALVANIZED TIE WIRE 2'-0" EXTRA 3' (TYP. FOR 2) RISER STRAPES POLE C 9'-0" EXPANSION FITTING NOTE: THE SHORT TIME FUSING CURRENT OF 1/0, 7 STRAND BARE COPPER WIRE IS 15,000 AMPERES FOR ONE SECOND. IF THE MAXIMUM FAULT CURRENT AT THE PARTICULAR LOCATION EXCEEDES THIS VALUE CONSULT DISTRIBUTION ENGINEERING. (FIGURE 1) 1'-0" FINISHED GRADE E 6" GROUND CLAMP #6 RE-BAR ACCROSS CENTER OF CAGE TO SUPPORT CONDUITS, SECURE WITH TIE WIRE TO HORIZONTAL RE-BAR (TYPICAL) D GRAVEL AND SAND - SHALL BE PLACED AS SHOWN IN FIGURES 1 AND 2; THE GRAVEL BEING COMPACTED AND THE SAND THOROUGHLY WETTED JUST BEFORE PLACING THE CONCRETE. E CONCRETE SLAB - INSTALL CONCRETE IN ACCORDANCE WITH MIX #4 - STD 0211 - UNLESS OTHERWISE SPECIFIED. ALL EXPOSED EDGES TO HAVE A 3/4" CHAMFER. F REINFORCING - TO BE #4 - GRADE 60 BARS AND SHALL CONFORM TO ASTM STANDARD. A-615 OF LATEST DATE. REINFORCING RODS TO BE LOCATED IN CENTER OF THE SLAB, WITH A MINIMUM OF 2" INCH CLEARANCE FROM FACE OF CONCRETE. 4" 12" 2" 12" 18"MINIMUM GROUND GRID - INSTALL #1/0, 7 STRAND BARE COPPER WIRE LOOP 1' - 0" BELOW GRADE. BOND TO ALL EXPOSED METALLIC CONDUIT AND LEAVE 3' - 0" OF WIRE ABOVE PAD FOR GROUNDING TRANSFORMER AT TWO OPPOSITE POINTS IN THE CABLE CONDUIT OPENINGS. INSTALL TWO 8' GALVINIZED STEEL (3/4") GROUND RODS AND APPROVED CONNECTORS BELOW GROUND. LEAVE GRID EXPOSED UNTIL INSPECTED BY THE UTILITY CO. GROUND ROD (TYP. FOR 2) GALVANIZED RIGID STEEL CONDUITS AS REQUIRED, REFER TO PLANS FOR EXACT SIZES AND QUANTITIES, PROVIDE THREADED FITTING ON EACH END (TYPICAL) UNDISTURBED EARTH 24" 96" GROUND GALVANIZED ANCHOR BOLTS FURNISHED BY MANUFACTURER OF POLE 5'-0" C 6" #6 RE-BAR, WRAP VERTICAL RE-BAR HORIZONTALLY 12" INCH. ON CENTER (RE-BAR CAGE) ACCESS D B D 6" MINIMUM COMPACTED FILL, SEE NOTE 2 4500 PSI MINIMUM CONCRETE 6" MINIMUM CRUSHED STONE TEN FOOT GROUND ROD WITH BONDING 1 1/2" MAXIMUM (SEE NOTE 3) (FIGURE 2) GALVINIZED RIGID STEEL SWEEP WITH RADIUS OF 10 TIMES DIAMETER. NOTES: 1. ANCHOR BOLT NOTES: DETAIL IS FOR REFERENCE ONLY, REFER TO UTILITY PAD DETAIL (NSTAR) FOR EXACT DIMENSIONS AND REQUIREMENTS. TOP NUT 1. DETAIL IS FOR REFERENCE ONLY, REFER TO UTILITY RISER DETAIL (NSTAR) FOR EXACT DIMENSIONS AND REQUIREMENTS. 2. SEE PLANS AND DETAILS FOR EXACT QUANTITIES OF CONDUITS AND RISERS. LOCK WASHER WASHER NTS NTS LEVELING NUT 3. STUB SPARE CONDUITS 6" AFG. AT BOTTOM OF UTILITY POLE, CAP WITH PULL STRING TIED AT BOTH ENDS. THREE PHASE - 15kV MAXIMUM 500 - 2500KVA - 208Y/120 POLE BASE NOTES: 1. LOCATE ANCHOR BOLTS SUCH THAT THE POLE AND BOLT COVER ARE CENTERED ON THE POLE BASE. CONDUIT PLASTIC CONDUIT SPACERS POLE BASE 3/4" REBAR BOTH DIRECTIONS 8" ON CENTER FOR 3' BEYOND END OF CONCRETE ON BOTH SIDES, COVER REBAR WITH 3" MINIMUM OF CONCRETE NTS 2. BACKFILL AROUND PRECAST POLE BASE WITH 90% PERCENT COMPACTED FILL PLACED A MAXIMUM OF 8" INCHES AT A TIME. FILL SHALL BE DE-VOID OF OBJECTS OVER 2" INCHES IN DIAMETER AND VOID OF DE-COMPOSIBLE MATERIAL. TYPICAL BOLT DETAIL NTS 3. BOLT PROJECTION/LEVELING, COORDINATE EXACT DIMENSIONS WITH MANUFACTURER'S RECOMMENDATIONS. 4. TOP OF POLE BASE SHALL BE 3" INCH ABOVE FINISHED GRADE FOR ALL POLES LOCATED OUTSIDE OF PARKING AREAS, POLES LOCATED WITHIN PARKING AREAS SUBJECT TO VEHICAL DAMAGE SHALL BE 2'-6"AFG. TOP OF POLE BASE LOCATED IN SIDE WALK AREAS WITH DECORATIVE BRICK PAVERS SHALL BE 1" AFG, UNLESS OTHERWISE INDICATED. COMPACTED NATIVE BACKFILL VOID OF OBJECTS OVER 2 INCH DIAMETER AND VOID OF DECOMPOSABLE MATERIAL. MAGNETIC WARNING TAPE FINISHED GRADE 5. IN LIEU OF POURED ON SITE CONCRETE POLE BASES, PROVIDE PRE-CAST EQUAL POLE BASE WITH REBAR AND CONDUIT SLEEVES AS REQUIRED. MAGNETIC WARNING TAPE COMPACTED NATIVE BACKFILL VOID OF OBJECTS OVER 2 INCH DIAMETER AND VOID OF DECOMPOSABLE MATERIAL. FINISHED GRADE 3" DIRECT BURIED CONDUIT, SEE PLANS 18" CONCRETE POUR NO. 1 DUCTBANK LEGEND: 12" 30" MIN. 24" MIN. P DUCTBANK SECTION NOTES: POWER, SITE LIGHTING 4" 4" 1. ALL DUCTBANKS SHALL BE ENCASED IN CONCRETE (U.O.I.) WITH SPACERS 5'-0" ON CENTERS AND AT EACH COUPLING AND 3" INCHES OF CONCRETE ALL AROUND. TV P SP SP T P 2. CONDUITS SHALL MAINTAIN CLEARANCE OF 30" INCHES FROM FINISHED GRADE (U.O.I.) TO TOP OF CONDUITS. 4. DUCTBANK SECTIONS SHOWS GENERAL CONFIGURATION ONLY TO REFLECT QUANTITY OF CONDUITS AND AMOUNT OF CONCRETE, EXACT CONFIGURATION AND ROUTING SHALL BE AS REQUIRED BY FIELD CONDITIONS AND COORDINATION WITH OTHER TRADE'S UTILITIES. 5. PROVIDE RE-BAR IN DUCTBANKS INSTALLED UNDER PAVED AREAS. 3" SAND 6" INCHES MINIMUM ALL AROUND CONDUITS 6" 8. ALL DUCTBANKS BELOW PAVED AREAS SHALL BE ENCASED IN CONCRETE, OTHER DUCTBANKS NOT BELOW PAVED AREAS SHALL HAVE 6" MINIMUM SAND ALL AROUND CONDUITS. Electrical Consultants T TELEPHONE/COMMUNICATIONS (VERIZON) TV CABLE TELEVISION (CATV) (COMCAST) SP SPARE, EMPTY WITH PULLSTRING CONCRETE POUR NO. 2 NOTES: 1. ALL DUCTBANKS SHOULD BE MONOLITHIC, IF NOT PRACTICABLE THEN ALL JOINTS BETWEEN POURS NOT MADE IMMEDIATLY ONE AFTER THE OTHER (LESS THAN 30 MINUTES BETWEEN POUR) SHALL HAVE JOINTS CONSTRUCTED AS INDICATED TO MINIMIZE THE POSSIBILITY OF DUCTBANK SHEARING AT THE JOINTS. 2. 3000 PSI MINIMUM CONCRETE. PLASTIC SADDLE SPACERS 5'-0" O.C. MINIMUM 6. WHEN THE INTERVAL BETWEEN CONCRETE POURS IS EXPECTED TO EXCEED 4 HOURS, THEN #4 REINFORCING BARS 6' FEET LONG, SHALL BE INSTALLED IN THE CORNERS AND BETWEEN DUCTS ON THE TOP AND BOTTOM ROWS. 7. BACKFILLING SHALL NOT COMMENCE LESS THAN TWO HOURS AFTER CONCRETE POURING AND BEFORE INSPECTIONS BY LOCAL AUTHORITIES. POWER, ACTIVE UNDISTURBED EARTH OR 90% PERCENT COMPACTED FILL 3000 PSI MINIMUM CONCRETE ENCASEMENT 4" INCHES MINIMUM ALL AROUND NTS P 3" 6" T 3. PROVIDE AND INSTALL DUCTBANK MARKERS EVERY 200' FEET ALONG ENTIRE LENGTH OF DUCTBANKS SECTIONS. MAXIMUM 30° SLOPE AT END OF FIRST POUR DUCTBANK LEGEND: 12" NTS 3" UNDISTURBED EARTH OR 90% PERCENT COMPACTED FILL NTS