Project descriPtion - St. Cloud State University

advertisement
October 2012
ST. CLOUD STATE UNIVERSITY
Predesign Submittal
RENOVATION OF EASTMAN HALL FOR STUDENT HEALTH RELATED SERVICES
OCTOBER 2011
Table of Contents
section 1.0:
Predesign Summary Statement . . . . . . . . . . . . . . . . . 1.1
1.1 Project Participants. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.2 Project Information. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.3 Project Budget. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.4 Project Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.5 Alternative Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.6 Campus Plan. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
section 2.0:
Project Background Narrative. . . . . . . . . . . . . . . . . . 2.1
2.1 Statutory and Other Requirements. . . . . . . . . . . . . . . 2.2
2.2 Project Rationale/Summary of Needs. . . . . . . . . . . . 2.2
2.3 Relationship to 2010 Comprehensive Plan. . . . . . . . 2.5
2.4 Space Utilization. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6
2.5 Facilities Systems Summary . . . . . . . . . . . . . . . . . . . . 2.6
2.6 Code Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.17
2.7 Sustainability Highlights. . . . . . . . . . . . . . . . . . . . . . . . 2.17
section 3.0:
Project Description. . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1
3.1 Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2
3.2 Existing Floor Plans. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.5
3.3 Project Scope and Program . . . . . . . . . . . . . . . . . . . . 3.10
3.4Design Concepts. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.17
3.5 Systems Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.27
Sustainability. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.1
section 4.0:
1.2
1.3
1.5
1.5
1.6
1.6
4.1 Energy Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.2
section 5.0:
Financial Information-Capital Expenditures. . . . . . 5.1
5.1 Project Budget. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2
section 6.0:
Ongoing Operating Expenditures. . . . . . . . . . . . . . . 6.1
section 7.0:
Project Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7.1
7.1 Project Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7.3
section 8.0:
Technology Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.1
section 9.0:
Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.1
9.1 Multi-tiered Program. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.1
9.2 Student Health Services-Org. Charts. . . . . . . . . . . . . 9.2
9.3 Meeting Minutes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.3
9.4 Planning Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.4
9.5 Room Data Sheets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.5
9.6 Existing Building Plans. . . . . . . . . . . . . . . . . . . . . . . . . . 9.6
9.7 Soils Report (Existing Footings). . . . . . . . . . . . . . . . . . 9.7
9.8 Structural Testing (Existing Structure). . . . . . . . . . . . 9.8
9.9 Furniture, Fixtures & Equipment . . . . . . . . . . . . . . . . . 9.9
9.10 Asbestos Survey . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.10
9.11 Lead Paint Testing Report. . . . . . . . . . . . . . . . . . . . . . . 9.11
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
This page was left blank intentionally.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.0
Predesign summary statement
1.2
1.0 Predesign Summary Statement
1.1 PROJECT PARTICIPANTS
This Predesign Report describes the proposed renovation of Eastman Hall at St. Cloud State University for the purpose
of co-locating Student Health Services, Counseling and Psychological Services and related services. Developing the
strategy for this project was a collaborative effort of dedicated faculty, leadership, staff, students and consultants.
Key contributors to the Predesign effort include:
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
St. Cloud State University Planning Participants
Earl H. Potter III, PhD
President
Steve Ludwig
Former Vice President for Administrative Affairs
Wanda Overland, PhD Vice President for Student Life and Development
Monica Devers, PhD
Interim Dean – School of Health and Human Services
Corie Beckermann
Director – Student Health Services
Brent Nielsen, MD
Medical Director - Student Health Services
John Eggers, PhD
Director – Counseling & Psychological Services
Rob Reff, PhD
Former Assistant Dean of Students for Outreach Programs
Jennifer Johnson
Coordinator of Alcohol Prevention and Community Programs
Troy Shafer
Health Educator
David Bacharach, PhD Human Performance Lab
Glenn Street, PhD
Human Performance Lab
Student Health Services Staff
Counseling and Psychological Services Staff
Daryl Scholz
Information Technology
Tim Norton
Director - Facilities Management
John Frischmann
Facilities Construction Coordinator
Architect - BWBR
Rick Dahl
Jason Nordling
Mike Gordan
Connie Cook
Principal
Project Manager
Project Designer
Medical Planner
Structural Engineering – Ericksen Roed & Associates
Steve Clark
Structural Engineer
Mechanical/Electrical Engineering – Dunham Associates
Nic Igl
Nathan Wriedt
Mechanical Engineer
Electrical Engineer
Cost Estimating – Faithful + Gould
John Pidgeon
Jeremy Soukup
Chief Estimator
Senior Estimator
1.0 Predesign Summary Statement
SCSU VISION STATEMENT
Through active discovery, applied knowledge and
creative interaction, we positively transform our
students and the communities where they live and work.
SCSU VISION DEFINED
St. Cloud State University makes a positive, long-term
impact on the lives of our students. We provide rigorous
and relevant academic experiences with engaged,
active learning opportunities in an intellectually
vibrant, inclusive and diverse campus community.
Our graduates are well-prepared to act as responsible
global citizens and professionals who remain actively
connected with our university.
SCSU MISSION STATEMENT
We prepare our students for life, work and citizenship
in the twenty-first century.
PREDESIGN SUMMARY
This predesign is for the renovation of Eastman Hall, colocating Student Health Services (SHS), Counseling and
Psychological Services (CAPS), the Human Performance
Lab (HPL) and U-Choose in Eastman Hall. The project
aligns with the University’s mission of preparing students
for life, work, and citizenship. Specifically, our strategic
focus of an Integrated Student Experience frames the
OCTOBER 2011
ST. CLOUD STATE UNIVERSITY l EASTMAN HALL PREDESIGN – DESIGN REVIEW
Existing St. Cloud State University – Eastman Hall
design through linkages between learning in and outside
of the classroom, linkages between career choices and
experiential learning, work force development through
partnerships and community outreach and accessible
service delivery.
From the inception of this work our commitment is to
align the project design to support sustainability and
stewardship of place by repurposing a historic facility,
currently not in use, that highlights its location by the
Mississippi River. This project increases square footage
but not cubic footage with the use of air space in the
gymnasium, resulting in increased energy efficiency and
facility productivity.
The co-location of these programs will address the
fractured and insufficient spaces that limit our ability
to serve students. In addition to creating efficiencies by
co-locating SHS and CAPS, the renovation will provide
students with easier access to U Choose (the campus
alcohol and drug education program), health education
services and HPL, in the School of Health and Human
Services. It will provide an improved pharmacy, the
addition of diagnostic imaging and enhanced laboratory
space to support clinic functions. Improving these
professional spaces will allow academic programs,
such as radiologic technology, to offer more real world,
collaborative experiences to students.
When the renovation is completed, it is anticipated that
the existing SHS location in Hill Hall will return to its
original use as a residence hall and the existing CAPS clinic
space in Stewart Hall and HPL program in Halenbeck Hall
will be re-purposed for academic space. This work is not
included in the predesign, and will be determined in more
detail in the future.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.2 PROJECT information
1.3
1.4
1.0 Predesign Summary Statement
PROJECT RATIONALE AND
RELATIONSHIP TO AGENCY STRATEGIC
FRAMEWORK:
MnSCU Strategic Framework:
Ensure access to an extraordinary education for all
Minnesotans:
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
• Supports redesign of the classroom experience
in needed health related areas such as radiologic
technology, medical laboratory science, nursing,
community health, counseling and kinesiology. This
includes multi-purpose spaces that are flexible and
utilize technology to enhance learning.
• Expansion of program space in the medical clinic,
pharmacy, counseling, human performance lab,
health promotion and alcohol and drug programs
along with the addition of on-site radiologic imaging
provides opportunities for St. Cloud Technical and
Community College (SCTCC) and SCSU students to
have clinical experiences, job shadowing, research
opportunities, internship and practicum experiences.
Because CAPS is an accredited counseling center,
SCSU serves as a location for students to obtain
clinical experiences to complete their academic
degrees from state higher education institutions and
due to space limitations, we are limited in our ability
to provide this experience to more students.
• Supports employer expectations that students will
have applied learning experiences to better prepare
them for the work force.
• Supports our commitment to development of the
whole student. Given the changing demographics
and needs of the student body, greater integration
and collaboration of programs is required. For
example, we have seen an increase of 398% from
2001 to 2011 in our students with mental/emotional
disabilities requesting support services. Our studentveteran population has increased from 521 students
in 2011 to over 600 today. These changes require
us to build partnerships and linkages throughout
campus to help these students succeed.
Be the partner of choice to meet Minnesota’s workforce and
community needs:
• Enhance collaboration with SCTCC for student
services. We have seen an increase in SCTCC visits
to our clinic from 18 visits in 2002 to 312 visits in
2012.
• The
completed project will encourage more
experiential learning opportunities, preparing students
for the workforce, For instance, the remodeled
space will provide greater opportunities to
engage students in Medical Lab Science program
via shared use of our clinic labs, designed large
enough to serve as a working/ teaching space.
• Accommodate anticipated demand for university
graduates in health sciences – projected to
increase 23.27% (3,033 total new hires needed)
from 2009 to 2019 for medical/radiological/
nuclear med technicians (Source:
DEED
analysis & DEED Labor Market Info Office, MN
Employment Projections.
• Strengthen ties with the local professional and
medical communities including CentraCare,
Central MN Heart Center, St Cloud Hospital and
the St Cloud Police Department, and city of St.
Cloud.
• Health care remains among the top areas for job
opportunities for 2010 and beyond. Registered
nurses are among the top occupations in demand
for all regions of Minnesota.
Deliver to students, employers, communities and taxpayers
the highest value/most affordable option:
• The entire amount of Eastman hall’s deferred
maintenance will be eliminated ($3.836 million),
decreasing need for future R & R expenditures
• Existing systems will be replaced with more
energy-efficient systems
• The building’s Facility Condition Index (FCI) will
be decreased from .31 to 0.00, reducing the
need to use campus R & R funds
• Renovating an existing structure is more cost
effective
• Multi-purpose rooms will provide increased
opportunity for academic collaboration
• Backfilling current CAPS space in Stewart
hall and HPL program in Halenbeck Hall with
co-located Academic programs will aid SCSU
re-organization efforts & return spaces back to
academic use.
• Although not on the Historic register, renovating
and re-purposing this structure by adding a
floor within the building has important local and
regional significance.
1.0 Predesign Summary Statement
Existing Building New 3rd Floor
Total = 45,997 GSF
(totally renovated)
Program area
= 58,853 GSF
= 810,000 Gross Cubic Feet
= 15,562 GSF
= 61,559 GSF
= 810,000 Gross Cubic Feet
$ 9.796M Construction Cost
$ 978 K Contingency
$ 2.829M Escalation (to Feb. 2016)
$ 3.476M Soft Costs
$ 17.079M Total Project Costs
3rd Quarter
2016 Occupancy
1.3 Project Budget
This capital budget request is for the renovation of
Eastman Hall, co-locating Student Health Services (SHS),
Counseling and Psychological Services (CAPS), Human
Performance Lab (HPL) and U-Choose in Eastman
Hall. The project aligns with the University’s mission
of preparing students for life, work, and citizenship.
Specifically, our strategic focus of an Integrated Student
Experience frames the design through linkages between
learning in and outside of the classroom, linkages
between career choices and experiential learning, work
force development through partnerships and community
outreach and accessible service delivery.
From the inception of this work, our commitment is to
align the project design to support sustainability and
stewardship of place by repurposing a historic facility,
currently not in use, that highlights its location by the
Mississippi River. This project increases square footage
but not cubic footage with the use of air space in the
gymnasium, resulting in increased energy efficiency and
facility productivity.
The co-location of these programs will address the
fractured and insufficient spaces that limit our ability
to serve students. In addition to creating efficiencies by
co-locating SHS and CAPS, the renovation will provide
students with easier access to U Choose (the campus
alcohol and drug education program), health education
services and HPL, in the School of Health and Human
Service. It will provide an improved retail pharmacy,
the addition of diagnostic imaging and enhanced
laboratory space to support clinic functions. Improving
these professional spaces will allow existing academic
programs, such as radiologic technology, to offer more
real world, collaborative experiences to students.
When the renovation is completed, it is anticipated
that the existing SHS space in Hill Hall will return to its
original use as a residence hall and the existing CAPS
clinic in Stewart Hall and HPL program in Halenbeck Hall
will be re-purposed for academic space. The costs for
any such re-purposing are not included in this project.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Project Data
1.5
O Lot
7th St.
1st Ave.
2nd Ave.
3rd Ave.
Miller Pay Lot
Performing
Arts
Center
Whitney
Atwood Memorial
Center
Sk
yw
ay
Admissions
Parking
James W. Miller
Learning Resources Center
L Lot
shs
Hill Hall
Public Safety
Center
X Lot
Garvey
Commons
I Lot
525
Building
MTC Bus Stop
Administrative
Services
Building
Kiehl
Visual
Arts
Center
D Lot
Stewart Hall
Centennial
Hall
Ritshe Auditorium
51
Barden
City Park
4
Building
caps
Skyway
Lewis
House
8th St.
P
Lot
Headley
Hall
Brown Hall
H Lot
Wick
Addition
American
Indian
Center
6
E Lot
Skalicky
Plaza
E Lot
Eastman
Hall
J
Lot
Engineering
and Computing
Center
N Lot
South
Pay Lot
Child Care
Center
Shoemaker Hall
University Drive
Walkway
M Lot
R
Lot
11th St.
Facilities Management
G Heating
Lot Plant
J
Lot
TO S
ELKE
FIELD
Univ
ersity
Bridg
e
G Lot
Hydroelectric
Plant
Student
Rec.
Ctr.
8
eastman
hall
Chiller
Plant
hpl
Halenbeck
Hall
Riverview
IPP
Richard
Green
House
Robert H.
Wick
Science
Building
SISS
V Lot
9th St.
F Lane
Education
Building
DAM
Husky
Stadium
National
Hockey
Center
MISSISSIPPI RIVER
12th St.
Husky
Pay Lot
13th St.
Herb Brooks Way
10
14th St.
K Lot
U
Lo
t
9
K Lot
Husky
Hub
11
Beaver Islands Trail Head
St. Cloud
City Utilities
16th St.
Q Lot
Bike Path
nd
sT
rai
l
Husky
Challenge
Course
Q Lot
I
ver
Bea
sla
Beaver Islands
15th St.
12
ER
ISELF
5
MIS
South
Office
Center
I RIV
Skyway
Mis
siss
H Lo
ipp
t
i Riv
er W
alk
Skyway
4th Ave. S
The adjacent map highlights the location
of Eastman Hall as well as the existing
Student Health Services (SHS) location
in Hill Hall, the existing Counseling and
Psychological Services (CAPS) location
in Stewart Hall, and the existing Human
Performance Lab (HPL) in Halenbeck Hall.
Mitchell Hall
Women's
Center
6th St.
B
Lot
Lawrence Hall
2
Ervin House
Sherburne
Hall
A-2
Lot
Case
Hall
N
Benton
Hall
Stearns
Hall
4th Avenue
Parking Ramp
(public)
A-A Lot
A
S Lot
Stateview
South
C Lot
5th St.
B
North Benton
Hall
A-1
Lot
Holes
Hall
A-3
Lot
Stateview
Lot
G Lot
Eastman Hall is centrally located on campus
for ease of access, and offers great views
of the Mississippi River and access to the
riverside biking/walking path. It is also located
near a mass transit line, a critical mass of
student housing, and health-related academic
departments.
C
Stateview
North
1
7
1.6 CAMPUS PLAN
D
3rd Ave. S
With the space needs identified in this
predesign, there is currently no other existing
space on campus (other than Eastman
Hall) that could accommodate the required
space to achieve the goal of consolidation
of healthcare services as outlined in this
document. Compared to the cost of building a
new building for approximately $25.03 million,
the investment in renovating this well sited
and structurally sound building will provide
great value, and many more years of use to
an 83 year old building that is currently highly
underutilized.
4th Ave.
C
XX
Lot
Lot
3
1.5 ALTERNATIVE OPTIONS
4th St.
P Lane
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
E
O Lane
It is anticipated that the funding for the
remainder of the design phases and
construction would be pursued with the
Minnesota Legislative bonding bill in 2014,
with construction beginning in the third quarter
of 2015. A 12 month construction period is
expected, so the midpoint of construction
would be about February 2016, with completion
scheduled for the third quarter of 2016.
Coborn Plaza
Apartments and
Welcome Center
Downtown
V Lot
1.4 Project SCHEDULE
5th Ave.
1.0 Predesign Summary Statement
C ommunity
G arden
1.6
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2.0
Project background narrative
2.2
2.0 Project Background Narrative
2.1 statutory and other
requirements
Since there have been no prior funding requests for this
project, there are no previous statutory requirements tied
to this project.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
The following requirements will apply to the project after
funding approval:
• MS 16B.32
Energy Use
• MS 16B.325
Sustainable Building Guidelines
• MS 16B.326
Heating and Cooling Systems; State Funded Buildings
• MS 16B.335 (1a)
Construction/Major Remodeling Review (Legislature)
• MS 16B.335 (1b)
Project Exempt From this Review (Legislature)
• MS 16B.335 (2)
Other Projects (Legislative Notification)
• MS 16B.335 (3)
Predesign Requirement
(Administration)
• MS 16B.335 (4)
Energy Conservation Requirements (Agency)
• MS 16B.335 (5)
Information Technology Review (Office of Technology).
visits. Eastman’s location in relationship to healthrelated academic programs not only addresses the
space needs for the provision of quality student
health care services, but also provides for rich
integrated academic partnerships for students.
2. An extraordinary education is one that prepares
students for life, work, and citizenship. This includes
the development of the whole person who is able
to manage their health and well-being. Mental and
2.2 project RATIONALE
There are three basic elements in the project rationale:
1. The framework which informs strategic plans for
the university is the Integrated Student Experience
facilitated by rethinking of our programs and activities
across the institution with embedded needs for spatial
reconfiguration. Eastman Hall is in close proximity to
academic buildings housing health-related programs
such as nursing, radiologic and medical technology,
counseling and community health. Opportunities
for increased experiential training and outside the
classroom learning will provide a richer academic
experience and better prepare our students
for employment in the future. For example, the
addition of an x-ray unit in Eastman would provide
radiologic technology students with on-campus job
shadowing opportunities, access to x-ray equipment
to practice imaging of test objects, the ability to
coordinate outside the classroom learning about
x-ray equipment installation, maintenance, and
repairs. Additionally, students could participate in
quality assurance testing and regulatory agency
SHS Pharmacy Window
2.0 Project Background Narrative
Stewart Hall Corridor
Map of Off Campus Services
Connections
1. St. Cloud State University
10
11
12
2. Psychology Associates
1.0 miles
16
17
7
5
9
3. CentraCare Clinic
13
15
4
3
1.8 miles
4. St. Cloud Hospital
2.0 miles
5. CentraCare Clinic
2.5 miles
6. Solutions Behavioral Healthcare
3.0 miles
6
2
7. Center for Family Counseling
3.2 miles
14
8. St. Cloud Medical Group
South Campus
1
3.3 miles
9. VA Medical Center
4.7 miles
10. St. Cloud Medical Group
North Campus
5.5 miles
11. Center for Diagnostic Imaging
5.5 miles
12. CentraCare Surgery Center
5.6 miles
13. St. Cloud Tech. Community College
14. City of St. Cloud
15. Central Minnesota Heart Center
8
16. Whitney Senior Center
17. St. Cloud YMCA
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
physical health issues can have a profound impact on
students’ ability to engage fully in the opportunities
presented to them while in college. These issues
affect their physical, emotional and cognitive wellbeing and can lead to poor academic performance
and lower graduation rates. Our integrated care
approach in assisting students in the form of a
case worker and Behavioral Intervention Team has
resulted in saving of student lives. However, our
progress is impeded because our fractured and
insufficient spaces no longer can meet student
needs and influences our delivery of quality service.
The co-location of SHS, CAPS, HPL and U Choose
will lead to better coordination of patient care,
reduced stigma for mental health, increased access
to support services and better space utilization for
both SCSU and SCTCC students.
2.3
2.4
2.0 Project Background Narrative
According to the 2011 American College Health
Association (ACHA) - National College Health
Assessment report, nearly 30% of college students
have experienced stress and/or depression during
the school year that made it difficult for them to
function, and ultimately negatively affected their
academic performance. Nearly 20% of students
have experienced anxiety that negatively affected
their academic performance, with 50% of those
experiencing “overwhelming anxiety”.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
CAPS is currently located in Stewart Hall, which is
primarily used for academic purposes. The high
student traffic and loitering in the corridors between
classes by students in this busy facility decrease the
likelihood of students feeling comfortable accessing
help because of perceived stigmas The renovation
of Eastman would provide adequate space for the
co-location of these programs to increase access of
care by decreasing stigma.
The March 2010 ACHA White Paper, Considerations
for Integration of Counseling and Health Services on
College and University Campuses, suggests taking
a more integrated approach may provide the best
foundation for providing holistic care to students,
allowing better alignment of support services. 73%
of survey respondents with integrated health and
counseling services reported they were better able to
meet student needs and their utilization of services
increased by 71%. Additionally, improvements
were also noted in comprehensiveness of services
and programs, quality of clinical services, client
satisfaction, efficiency of administrative processes
and staff communication.
3. Better and more effective space is required for
SHS to retain national accreditation status with the
Accreditation Association for Ambulatory Health
Care (AAAHC). The possibility of losing national
accreditation status is a real and pending threat. In
the most recent (2010) AAAHC site visit report, the
surveyors included multiple comments regarding
the SHS facility only partially meeting compliance
standards relative to patient privacy, accessibility,
inadequate heating and cooling systems and staffing
ratios.
“Results of the current study suggest that these centers
have found integration to result in an improvement
in many aspects of clinical service. Centers reported
that they were more easily able to meet the demands
of their students and had a more efficient utilization of
their services. Most reported that their services were
more comprehensive and reflected a more seamless
approach to health and mental health care. While staff
morale was initially sometimes negatively affected, as
the model persisted, turf concerns and other related
issues were subsumed by the perceived improvements
in service to students. Overall, satisfaction by the
consumers was reported as very high” – ACHA
2.0 Project Background Narrative
In the past three years SHS has averaged a little
more than 10,000 patient visits per year and
CAPS has provided almost 3,600 visits per year,
a 30% increase in the past five years. Of the
visits listed above, SCTCC students visit SHS
approximately 300 times per year. The utilization
of all of these services is expected to grow based
on our increasing need, an uptick in use due to the
upgrade in facilities, less stigma for users and a
more cohesive “one stop shop”.
With Eastman Hall being located near a campus edge,
it will support the master plan to push services and
programs that have community connections closer to the
perimeter of the campus. There will be parking stalls near
the building that will be designated “visitor parking”, which
will provide improved parking access It will also make
access to the services offered more convenient to students
who are living off-campus. By incorporating a ground floor
gathering space, café, and exterior patio area overlooking
the river, it will provide interior and exterior spaces that
“allow and encourage lingering/gathering/incidental social
interactions.”
• An integrated health service facility is identified as
a need in the master plan to compete with St. Cloud
State’s peer institutions.
• Support our commitment to sustainability by
incorporating high end building systems. (see
following data for more sustainability detail)
• Expand links to the river emphasizing the existing
river walk, will take advantage of river views and
expand river oriented uses and activities.
AGENDA







In a 2010 comparison to peer institutions, SCSU
SHS’s “student to provider” ratio based on head
count was 5,309 to 1, compared to 4,334 to 1
at MN State University Mankato, 4,124 to 1 at
Western Kentucky University, and 894 to 1 at
Towson University. With appropriate space,
additional providers could be added allowing better
access to care and improved “student to provider”
ratios.
Introductions
Goals & Objectives
Predesign
An accreditation visit was made was 2010. The
Understanding
resulting report pointed out several deficiencies,
such as inadequate “student/provider” ratio, poor
provisionsof
for privacy
and improper accessibility.
Recap
previous
When the accreditation team returns in July,
2013, it will be important to demonstrate progress
meeting
comments
toward addressing these concerns.
Technology
2.3 RELATIONSHIP TO 2010 AGENCY
COMPREHENSIVE PLAN
Sustainability
This project supports many of the items discussed in the
Concept
Plans
2010 campus master
plan.
OCTOBER 2011
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
SHS is currently housed on the ground floor of Hill
Hall in space that was formerly a student residence
hall, a space not originally designed to deliver
these services. Among the issues with the existing
space: a “hidden” clinic entrance on the back side
of the building, inadequately-sized spaces, an
inefficient layout, lack of storage space, ambulance
access issues and a lack of space for growth such
as imaging and specialist provider exam space.
Recently, as many as 250 x-ray studies and 800
specialist consultations were sent off-campus.
This required students to find transportation to off
campus sites that many times are not conveniently
served by public transportation.
2.5
2.6
2.0 Project Background Narrative
2.4 SPACE UTILIZATION
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
The Eastman Hall building was originally designed and
used as an athletic facility for the campus. Currently,
the building is closed and is not being utilized at all. The
building is not being utilized based on a number of factors
including: lack of accessibility (toilet rooms, no elevator,
etc.), lack of appropriate classroom spaces, poor heating
and cooling systems, and poor technology infrastructure.
The renovated space will dramatically increase the quality
of the spaces, and also the utilization of the building.In
future projects, Hill Hall space vacated by Student Health
will be returned to use as a residence hall, Stewart Hall
space vacated by Counseling and Psychological Services
will be returned to academic use, and the space in
Halenback Hall vacated by the Human Performance Lab
will be returned to academic use.
2.5 FACILITY SYSTEMS SUMMARY
The existing Eastman Hall building was originally
constructed in 1929 to serve as the primary athletic
facility on the St. Cloud State campus and has a current
FCI score of .31. It is a three story steel and concrete
framed structure with uninsulated brick exterior walls,
and non-structural brick walls separating the gymnasium
spaces. According to the existing drawings, the floor to
floor height from first to second is 13’-0”, between second
and third is 12’-7”, and third floor clearance is 8’-6”.
Eastman Hall currently houses a pool (closed to use in
2009), locker rooms, and office space on the first floor,
a large central gymnasium with smaller flanking gyms on
the second floor, and a bleacher mezzanine in the large
gymnasium and some small office suites on the third floor.
There are some hazardous materials that will need to
abated before any of the interior selective demolition
takes place. The hazardous materials testing reports are
included in the appendix for reference. PCB containing
transformers were replaced in 1986, and some asbestos
was abated in the building in 1993. The building exterior
was refurbished most recently in 1989, and appears to be
in good condition. The roof was partially replaced in 1999
and 2006, so should not need replacement until 2039 at
the earliest.
As indicated in the Comprehensive Campus Plan, the
existing building is marginally suitable for use in its current
state, and will need to undergo significant renovation to be
reused. Renovations will include replacement of all exterior
window and door systems, and added insulation. As noted
2.0 Project Background Narrative
South façade showing the extent of
window replacement required.
Close up of the southernmost east entrance.
Light fixtures and aluminum entrances will be
replaced. The grade will be altered to make this
entrance accessible via a new east plaza.
OCTOBER 2011
Hall HALL
West facade/entrance.
New windows
will be
ST. CLOUD STATE UNIVERSITY l Eastman
EASTMAN
PREDESIGN – DESIGN
REVIEW
installed where the tall arch topped windows previously existed.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
in the included mechanical and electrical narratives the entire
heating and cooling system, controls, plumbing, electrical service
and distribution, lighting, and fire alarm system will be replaced
with new systems that are compliant with current building codes
and sustainability requirements.
2.7
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2.8
2.0 Project Background Narrative
Existing “cellar” doors to the basement level.
These should be replaced if this entrance will
be maintained.
Existing area well grates on the south side.
East façade showing the extent of window replacement required.
2.0 Project Background Narrative
Entrance door on the south end of
the east side of Eastman Hall that
will exit onto the new plaza.
North façade of the building showing the
extent of window replacement required.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Entrance door on the east side of Eastman Hall that
will be used for staff and ambulance access. This
area will be regraded and sidewalk will be added.
2.9
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2.10
2.0 Project Background Narrative
Partial north façade.
Close up of typical window openings on the
north side of Eastman Hall. The existing
windows and glass block will all be replaced
with new thermally broken aluminum windows.
2.0 Project Background Narrative
Existing north-south corridor in the office
area on the west side of the 1st floor.
Existing unused classroom on the 2nd floor.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Existing primary north-south corridor
on the 1st floor with terrazzo flooring.
2.11
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2.12
2.0 Project Background Narrative
Existing classroom on the 1st floor. This is
the only functioning room in the building.
Existing classroom on the 1st floor.
2.0 Project Background Narrative
Existing locker room space on the
south end of the 1st floor.
Existing pool on the 1st floor – looking south. The existing pool deck is several feet below the 1st
floor, and will be built up to support a new floor at the same elevation as the existing 1st floor.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Existing locker room space on the
south end of the 1st floor.
2.13
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2.14
2.0 Project Background Narrative
Existing pool on the 1st floor – looking north.
Existing secondary gym space (fitness center) on the 2nd floor – looking east. These
smaller gyms are located north and south of the main gym space on the 2nd floor.
2.0 Project Background Narrative
Existing primary gym space on the 2nd floor – looking east. The mezzanine seating will be removed
and replaced with a new floor which will divide the existing two story space into two floors.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Existing main gymnasium space on the 2nd floor – looking west.
Windows will be re-installed in the existing openings of the west wall.
2.15
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2.16
2.0 Project Background Narrative
Existing basement area. The concrete floor
slab was added in place of the original dirt
floor. Note the partially exposed column
footings, which will be stabilized to support
the loads of the new 3rd floor.
Existing stairway from the 1st floor to the
basement mechanical space.
Existing basement area.
2.0 Project Background Narrative
This predesign is based upon conformance with the
following current building codes and standards. A
complete code review will be required during the design
phase of the project. Current codes and standards
include:
• International Building Code (IBC), 2006 Edition
• MN Amendments to the IBC, 2007 Edition
• MN Accessibility Code, MN Rules Chapter 1341
• MN Energy Code, MN Rules Chapter 1323
• International Fire Code (IFC), 2006 Edition
• MN Amendments to the IFC, 2007 Edition
• International Mechanical Code (IMC), 2006
Edition
• MN Amendments to the IMC, 2009 Edition
• MN State Plumbing Code, 2009 Edition
• National Electrical Code, 2008 Edition
• Americans with Disabilities Act (ADA)
• Guidelines for the Rehabilitation of Existing
Buildings (GREB), 2000
• B3 MN State Sustainable Building Guidelines
• MnSCU Design Standards
Accessibility for the building will be vastly improved by
this project. These improvements include making all of
the existing first floor building entrances accessible, the
addition of elevators, and new accessible toilet rooms,
locker rooms, and showers.
2.7 Sustainability highlights
The most important sustainability concept for this project
is that it involves the reuse of an existing building and site.
Because this project is a renovation of an existing building,
it will most likely not comply with State of Minnesota B3
requirements, but will utilize sustainable measures where
possible. These measures include:
• Replacement of existing single pane windows with
high performance thermally broken windows.
• The addition of insulation to the interior of all
exterior walls to improve energy efficiency and
thermal comfort.
• Low flow plumbing fixtures.
• Variable air volume air handling systems to minimize
air transport energy.
• Energy recovery of exhaust air.
• High efficiency, variable flow heating hot water
systems.
• New lighting systems which will include high
efficiency fixtures, occupancy sensors, and time
sweep controls.
• Daylight harvesting, especially the areas on the east
and west side of the building with the largest window
areas.
• Building commissioning.
Geothermal systems were discussed, but will not be viable
because the building footprint covers a majority of the
available site area. Photovoltaics could be explored, but
will involve further study into the existing roof structure
capacity to determine feasibility.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2.6 Code Summary
2.17
This page was left blank intentionally.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.0
Project description
3.2
3.0 Project Description
3.1 site
Eastman Hall is located in the east central zone of the campus along the Mississippi River, and is bounded by 1st
Avenue on the west and University Drive on the south. Its central location makes it accessible equally from all
points of campus, and its adjacency to University Drive makes it a very visible building. The site is identified in the
Comprehensive Campus Plan as a “secondary gateway” to the campus. After renovation, the building occupants
will have great views of the river, and access to the adjacent river walk.
If possible, space should be provided in the existing “J” lot south of the building for staff and short term parking
for patient and facility use. Ambulance access will be provided from the parking area that currently exists on the
east side of the building.
M is s is s ip
1st Ave
p i R ive r
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
The building is across the street from the Wick Science Building and a bus stop, which will allow easy access by
students in the Health Sciences programs, and it is also close to Shoemaker Hall, which is home to about 325 students. The new location of the Student Health and Related Services will also make it more convenient to students
who may be injured while involved in activities in nearby Halenbeck Hall.
Eastman
Hall
U n i ve r s i t y D r
i ve
St. Cloud State University Campus Map
3.0 Project Description
Riverview
Wick Science
Building
Bus
Stop
1st Ave
Ambulance
Access
Eastman
Hall
VIEWS
Mi
ss
iss
ipp
iR
i ve
r
Repurposed
existing parking
for Student
Health
Shoemaker
Hall
Eastman Hall Site
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Brown Hall
3.3
This page was left blank intentionally.
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.2 existing floor planS
Basement Level
SWIMMING POOL
MECHANICAL ROOM
B2
STORAGE
B1
UP
UP
UP
Area to be completely renovated
0
St. Cloud State University
Eastman Hall (EH)
Floor : Basement
Date : October 20, 2011
E
N
S
W
1”=20’
3.5
10
20
30
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.2 existing floor planS
Level 1
UP
UP
DOWN
DOWN
SHOWER
102C
TOILET
107D
SHOWER
107E
SWIMMING POOL
105
TOILET
102B
MENS LOCKER ROOM
107
CUST.
STOR.
107C
SAUNA
102A
RAMP
DOWN
WOMENS LOCKER ROOM
102
OFFICE
103
TOILET
TOILET
SAUNA
107B
OFFICE
106
JAN.
DOWN
STORAGE
125
TOILET
107A
CORRIDOR 16B
UP
UP
STORAGE
104
OFFICE
116
OFFICE
114
OFFICE
112
OFFICE
115
OFFICE
113
OFFICE
111
OFFICE
110
OFFICE
118
TOIL.
CLASS ROOM
101
OFFICE
117
OFFICE
109
Area to be completely renovated
VEST
VEST
OFFICE
121
OFFICE
119
TOIL.
OFFICE
120
0
St. Cloud State University
Eastman Hall (EH)
Floor : First
Date : October 20, 2011
E
N
S
W
1”=20’
3.6
10
20
30
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.2 existing floor planS
Level 2
DN
DN
UP
UP
GYMNASIUM
201
FITNESS CENTER
204
MAIN GYMNASIUM
203
UP
UP
DN
DN
CLASS ROOM
202
CLASS ROOM
205
Area to be completely renovated
0
St. Cloud State University
Eastman Hall (EH)
Floor : Second
Date : October 20, 2011
E
N
S
W
1”=20’
3.7
10
20
30
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.2 existing floor planS
Level 3
DN
DN
C
D
UPPER
FITNESS CENTER
UPPER
GYMNASIUM
BALCONY
42A
UPPER
MAIN GYMNASIUM
BALCONY
42B
DOWN
DOWN
303
304
OFFICE
301
Area to be completely renovated
OFFICE
302
OFFICE
305
OFFICE
306
TOILET
TOILET
0
St. Cloud State University
Eastman Hall (EH)
Floor : Third
Date : October 20, 2011
E
N
S
W
1”=20’
3.8
10
20
30
This page was left blank intentionally.
3.10
3.0 Project Description
3.3 PROJECT SCOPE and Program
The planning process for this predesign involved many
rounds of meetings with all of the groups included in
the space program in order to determine the extent of
their space needs and optimal location and adjacencies.
The concept planning options in this section reflect the
culmination of those discussions. Many other options
that were studied are included in the appendix at the
end of this document, as well as the minutes from the
planning meetings.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
The proposed building program consists of 58,853 s.f.
which includes:
• Student Health Services: 19,897 s.f.
• Counseling and Psychological Services: 9,982 s.f.
• Building support, storage, mechanical, and electrical
spaces: 8,320 s.f.
• U Choose and Health Education spaces: 6,565 s.f.
• Common areas such as gathering space, café, retail,
check-in and reception, multipurpose room, and
restrooms: 7,029 s.f.
• Human Performance Lab: 5,159 s.f.
• Pharmacy space: 1,901 s.f.
The first floor of the building will house a large gathering/
social space near the building entrance that will include
seating and interactive digital health kiosks, a classroom
for 30-40 people, and a multi-purpose room that can
be used as a classroom or conference space as well as
for activities and student services. It will also include a
pharmacy, and a café/retail space for serving healthy
food and beverages that will have views to the river to
the east and access to an exterior patio space. A digital
radiography room will also be located on the first floor,
and it will be large enough to allow small classes to
engage in various learning activities within the space.
The Student Health Services area is anticipated to be
located on the second floor of the building in what is
currently the gymnasium spaces, and includes space
for 15 exam rooms, 4 consultation rooms (can be
used as future exam rooms), 4 nurse station areas, a
shared office for up to 3 physicians, a shared office for
up to 3 nurse practitioners, a shared office for up to 2
physician assistants, waiting space for up to 25 people,
administrative offices, and all needed support spaces. In
addition, at least one of the consultation rooms will be
set up as an “E-exam” space that can be used for video
consultation with off-campus specialists, and students
traveling abroad. Ambulance access will be from the
first floor, and utilize the new service elevator. A lab to
support the clinic will be located adjacent to the clinic on
the second floor.
The Counseling and Psychological Services (CAPS) area
will be located on the newly constructed third floor of the
building along with the U Choose and Health Education
areas. Because a variety of uses are located on the third
floor and the use of the adjacent spaces is less intensive
than Stewart Hall where Counseling and Psychological
Services is currently located, patients accessing this
area will have greater anonymity than if it had its own
isolated area in the building. This will, in turn, help to
de-stigmatize the counseling area, and make the use
of these services more appealing to the student body.
The CAPS area includes space for 10 clinical therapy
offices, two alcohol and other drug counselors, two
graduate assistants, 4 practicum interns, a psychiatrist
office, two mid-level practitioners, two case managers,
two case manager interns, a large group therapy room,
and all needed support spaces. It is anticipated that the
psychiatrist will utilize the Student Health Services clinic
for exams.
The final space program is included on the following
pages. For clarity, spaces used for academic purposes
are highlighted and account for approximately 6% of the
overall program space.
Total Program: 58,853 BGSF
34% Student Health Services
17% Counseling & Psychological Services
14% Building Support
12% Common Areas
11% U Choose/Health Education
9% Human Performance Lab
3% Pharmacy
3.0 Project Description
SUMMARY
SCSUPROGRAM
STudent health
Related services
Program Summary
Component/Area
Total
NASF
Bldg Grossup
Total
GSF
1 Common Area/Building Support
13,800
1.25
17,249
2 Student Health Services
15,919
1.25
19,898
3 Counseling & Psychological Services
7,985
1.25
9,982
4 U Choose & Health Education
5,252
1.25
6,565
5 Human Performance Lab
4,128
1.25
5,159
Program Total
47,083 NASF
58,853 GSF
Basement
10,347 *
14,541
1st Floor
13,818
14,822
2nd Floor
13,807
14,597
3rd Floor
1,212
2,038
Existing Eastman Hall
Existing Total
39,184 NASF
* Minus crawl spaces and pool
2012-10-02 SCSU Program.xlsx
Page 1
45,997 GSF
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
SCSU STUDENT HEALTH RELATED SERVICES
3.11
3.12
3.0 Project
Description
Section 1
SCSU Student Health Related Services
Summary Information
Section 1
Room/Area
Unit
Total
NSF
NSF
Comments
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.1 Common Areas
Check-In/Reception
Self Check-in Kiosk
Multipurpose Room
Commons Area/Intro Waiting Area
Public Restrooms
Lactation Room
Locker/Shower Rooms
Triage Room
Treatment Room
Gathering Space/Café/Retail
1
7
1
1
2
1
2
0
3
1
300
20
650
200
200
75
350
100
120
1500
Subtotal
300
140
650
200
400
75
700
0
360
1,500
4,325
Building general
Health and Counseling Services combined
Conferences, classes, large meetings, dividable.
NSF
1.2 Pharmacy
Waiting
OTC Retail Sales
Prescription Pick-up/Drop-off
Dispensing/Computer Work Stations
Drug Storage
Pharmacist Office
Consultation Room
Record Storage
1
1
3
3
1
1
1
1
180
120
60
60
180
90
90
150
Subtotal
180
120
180
180
180
90
90
150
1,170
Room/Area
Unit
NSF
Total
NSF
Waiting for 10-12
Integrate with waiting
Semi-private
1 Pharmacist and 2 Techs. 3'-4' of counter space each.
Need storage for vials, bottles. etc.
Adjacent to pick up/drop-off.
Adjacent to pick up/drop-off.
NSF
Comments
1.3 Info Technology
I.T. Office
Data Closets
1
3
80
80
80
240
320
Subtotal
NSF
1.4 Building Support
Storage
Mechanical
Electrical
Data
Clean Holding
Soiled Holding
2012-10-02 SCSU Program.xlsx
Receiving
Custodial
Trash
Recycling
1
1
1
1
1
1
1
1
1
1
80
3150
500
150
150
150
300
120
100
100
80
3,150
500
150
150
150
Page
300 2
120
100
100
4,800
NSF
Subtotal
10,615
NSF
Total
13,800
NASF
Subtotal
END OF SPACE PROGRAM
1.30
i 1
Section
3.0 Project Description
Section 2
3.13
SCSU Student Health Related Services
Section 2
Room/Area
Unit
NSF
Total
NSF
Comments
2.1 Patient Reception / Business Office/Administration
SHS Director's Office
SHS Associate Director Office
SHS Administrative Assistant
Work Room
Cashier
Insurance Billing / Coder
Insurance Advocate
1
1
1
1
3
2
1
150
120
100
120
60
120
120
150
120
100
120
180
240
120
1,030
Subtotal
Includes space for conferencing.
NSF
2.2 Medical Records
Inactive Storage
Supply Storage
1
1
50
100
50
100
150
Subtotal
NSF
2.3 Student Health Services
Waiting Room
Appointment Desk
Conference Room
MD Office
NP Office
PA Office
Medical Directors Office
Nursing Manager (RN)
Referrals/Manager's Office
Work Room
Exam Rooms
Consult Rooms
Nursing Station
Triage Nurse
Observation (IV's)
Procedure Room
Injection Room
2012-10-02 SCSU Program.xlsx
1
2
1
1
1
1
1
1
450
60
300
150
180
120
150
90
450
120
300
150
180
120
150
90
1
1
18
4
4
2
1
1
1
150
120
110
110
150
110
110
200
110
150
120
1,980
440
600
220
110
200
110
Page 4
Seating for 25 people.
20 people.
Shared office for 2 MD
Open area for 3 NP
Open area for 2 PA
2-3 per provider
1 E-Exam
Window preferred
Near Lab & Nurse Station
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Summary Information
3.14
3.0 Project
Section 2 Description
Room/Area
Supply Storage
SCSU
Student Health
Clean
Utility
Soiled Holding
Patient Toilets
Summary
Information
Staff Break room
Section
(cont’d)
Building2Services
Subtotal
Unit
NSF
1
150
1
4
1
1
100
65
500
40
Related Services
1
150
Room/Area
Unit
NSF
Total
NSF
150
150
100
260
500
40
Total
NSF
6,690
Comments
Autoclave
Share with counseling
Comments
NSF
2.1 Patient Reception / Business Office/Administration
2.4 Laboratory
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Lab Subwait
SHS Director's Office
Reception
SHS
Associate
Director
Office
Phlebotomy
Work
Space
SHS
Administrative
Assistant
Phlebotomy Stations
Work
PatientRoom
Toilet
Staff Toilet
Cashier
Lab
Insurance
Billing / Coder
Office
Insurance
Advocate
Storage
1
1
1
1
1
1
2
1
1
3
1
2
1
1
1
150
150
60
120
120
100
110
120
65
65
60
400
120
90
120
120
1,030
Subtotal
Subtotal
1,290
2.2
Records
2.5 Medical
Radiology
Inactive Storage
Supply
SubwaitStorage
Radiography Exam Room
Dressing
Room
Subtotal
Toilet
Technician Work Room
Control Area
2.3 Student Health
Viewing/Consultation
Storage
Waiting
Room
Wheelchair
Storage
Appointment Desk
Conference
Subtotal Room
MD Office
NP Office
PASubtotal
Office
Medical Directors Office
Nursing Manager (RN)
150
150
60
120
120
100
220
120
65
65
180
400
240
90
120
120
Services
Total
Referrals/Manager's Office
Work Room
Exam
ENDRooms
OF SPACE PROGRAM
Consult Rooms
Nursing Station
Triage Nurse
Observation (IV's)
Procedure Room
Injection Room
2012-10-02
2012-10-02 SCSU
SCSU Program.xlsx
Program.xlsx
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
50
50
100
100
120
120
450
450
75
75
150
65
65
100
100
100
100
75
75
100
100
450
450
25
25
60
120
300
300
1,110
150
150
180
180
120 10,270
120
150
150
1.55
90
90
1
150
1
120
18
110
Section
2
4
110
4
150
2
110
1
110
1
200
1
110
15,919
150
120
1,980
440
600
220
110
200
110
Page
Page 4
5
For 8 people
Includes space for conferencing.
2 Technicians
Semi-private
Unisex, connected to Lab, with exhaust fans.
Unisex, connected to Lab, with exhaust fans.
NSF
NSF
For 6 people
Sized for academic use - student observation
NSF
Alcove. No PACS
Seating for 25 people.
20
people.
NSF
Shared office for 2 MD
Open area for 3 NP
Open
NSF area for 2 PA
NASF
2-3 per provider
1 E-Exam
Window preferred
Near Lab & Nurse Station
3.0 Project Description
Section 3
3.15
SCSU Student Health Related Services
Section 3
Room/Area
Unit
NSF
Total
NSF
Comments
3.1 Counseling
Waiting Room
Work Room
Administration Support
File & Archive Storage
Storage/AV Storage
Directors Office
Associate Directors Office
Clinical Therapy Offices
AOD Counselor
Grad Assistant
Practicum Intern
Psychiatrist
Mid Level Psychiatric Practitioner
Case Manager
Case Manager Intern
Conference Room
Group Room
Testing/Biofeedback/SAD/ Relax.
Staff Toilet
Patient Toilet
1
1
1
1
1
1
1
10
2
2
4
1
2
2
2
1
1
3
2
2
550
200
160
200
75
150
120
150
150
120
120
150
120
150
120
200
250
100
65
65
550
200
160
200
75
150
120
1,500
300
240
480
150
240
300
240
200
250
300
130
130
25-30 People
8 File Cabinets + 1 or 2 more
Includes space for conferencing.
3 currently, grow to 4
Near Health Services. Share exam with Health Services.
12 People
Need space for 8-12. More square in plan than rectangular
Comfortable/Blackout window shades/noise control
Subtotal
5,915
NSF
Total
7,985
NASF
END OF SPACE PROGRAM
2012-10-02 SCSU Program.xlsx
1.35
Section 3
Page 6
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Summary Information
3.16
3.0 Project
Description
Section 4
SCSU Student Health Related Services
Summary Information
Section 4
Room/Area
Unit
NSF
Total
NSF
Comments
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
4.1 Health Education/ U Choose Student Services
Health Educator Offices
U Choose Administrator Office
Coordinator Office
Offices
2
1
2
3
120
120
100
100
240
120
200
300
Health Promotion Marketing
Peer Ed. Area
Resource Area/Husky Neighbors
Storage Space
Classroom
Graduate Assistant/Student Workspace
1
1
1
1
1
1
120
350
500
400
700
850
120
350
500
400
700
850
Staff Toilet
Student Toilet
2
2
65
65
130
130
Dietician, Grad Assistant
Suicide Prevention, Community Outreach.
8-10 Peer Ed. (Coop with Husky Neighbors)
TV, 12-15 people per group, Relaxed feel.
40 Students (22 hrs./wk) Tables & Chairs
16-20 workers. "War Room", Kitchenette
Subtotal
4,040
NSF
Total
5,252
NASF
1.30
END OF SPACE PROGRAM
Section 5
Section 4
SCSU Student Health Related Services
Summary Information
Section 5
Room/Area
Unit
NSF
Total
NSF
Comments
5.1 Human Performance Lab
Reception/Waiting
Offices
Conference/Resource Room
Underwater weigh room
1
3
1
1
150
120
200
150
150
360
200
150
Locker/Shower
Exam Room
Lab
Metal/Wood Workshop
Electronics Workshop
0
2
1
1
1
150
120
250
385
60
0
240
250
385
60
Physiology Testing Room
Graduate
Student
2012-10-02
SCSU Program.xlsx
Storage
Toilet
1
1
1
2
350
750
150
65
350
750
Page 7 10 Graduate Students
150
10 Graduate Students
130
Used for academic conferences and resources
Connected to Locker/Shower
Under counter refrigerator, vented hood, storage.
Subtotal
3,175
NSF
Total
4,128
NASF
END OF SPACE PROGRAM
1.30
Section 5
3.0 Project Description
Final DESIGN CONCEPT
Proposed build out of Existing Basement Level
NOTES:
-MECHANICAL,
STRUCTURAL &
EXISTING BUILDING
CONSTRAINTS
GENERAL BUILDING STORAGE
NEED TO BE FIELD
BUILDING
SERVICE
VERIFIED IN ORDER
TO DETERMINE THE
AHU - 2
AHU - 1
MECHANICAL
(2) AHUs
IMPACT ON THE
TOTAL PROGRAM
HUMAN PERFORMANCE LAB
WORKSHOP
MEDICAL
STAFF LOCKERS / TOILETS / SHOWERS RECORD
S
DATA
FUNCTIONAL LEGEND
COMMON AREA
PHARMACY
LABORATORY
ELECTR
ICAL
MEDICAL RECORDS
INFORMATION TECHNOLOGY
HUMAN
PERFORMANCE
LAB
MECHANICAL
SUPPORT
SHS
RADIOLOGY
CAPS
HEALTH ED. / U CHOOSE STUDENT SERVICES
HUMAN PERFORMANCE LAB
LEVEL B
UNUSABLE SPACE TO BE VERIFIED
NON-BUSINESS HOURS ACCESS
Level B
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.4 DESIGN CONCEPTS
3.17
3.0 Project Description
EXTENT OF FLOOR INFILL
CONSTRUCTION FOR LEVEL 1
SERVICE ENTRY /
AMBULANCE
ACCESS
PLAZA
ENTRY
NOTES:
-EXISTING POOL &
SURROUNDING AREA
TO BE FILLED IN.
TWO STORY SPACE
ABOVE
RECEIVING / CLEAN/
SOILED / CUSTODIAL /
TRASH / RECYCLING /
BIOHAZARD STORAGE
GATHERING SPACE
CAFÉ, RETAIL
RADIOLOGY
PHARMACY
BLDG
SERV
CMFRT
CLASSROOM
DATA
ELEC
PUBLIC
TOILETS
INFO
RECEPT
PUBLIC
TOILETS
SHS
ADMIN
OFFICES
RETAIL
FUNCTIONAL LEGEND
COMMON AREA
PHARMACY
LABORATORY
GATHERING SPACE/
INTERACTIVE KIOSKS
MEDICAL RECORDS
INFORMATION TECHNOLOGY
SUPPORT
SHS
MULTI-PURPOSE
ROOM
BUSINESS
OFFICE
INS ADVOC
CASHIER
RADIOLOGY
CAPS
HEALTH ED. / U CHOOSE STUDENT SERVICES
LEVEL 1
HUMAN PERFORMANCE LAB
UNUSABLE SPACE TO BE VERIFIED
NON-BUSINESS HOURS ACCESS
MAIN
ENTRY
MAIN
ENTRY
Level 1
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Final DESIGN CONCEPT
Proposed build out of Existing Level 1
3.18
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Final DESIGN CONCEPT
Proposed build out of Existing Level 2
TWO STORY SPACE
STUDENT
HEALTH
SERVICES
LABORATORY
DATA
ELEC
BLDG
SERV
FUNCTIONAL LEGEND
CHECK-IN/
RECEPTION
CHECKIN
KIOSKS
COMMON AREA
PHARMACY
LABORATORY
MEDICAL RECORDS
INFORMATION TECHNOLOGY
SUPPORT
SHS
RADIOLOGY
CAPS
EXAM
TRIAGE
#3
STUDENT
HEALTH
SERVICES
580 DGSF
EXAM
EXAM
#2
#1
HEALTH ED. / U CHOOSE STUDENT SERVICES
HUMAN PERFORMANCE LAB
3.19
STUDENT HEALTH SERVICES
STUDENT
HEALTH
SERVICES
LEVEL 2
UNUSABLE SPACE TO BE VERIFIED
NON-BUSINESS HOURS ACCESS
Level 2
3.0 Project Description
EXTENT OF NEW FLOOR
CONSTRUCTION FOR LEVEL 3
EXISTING STAIR TO LEVEL 3
EXISTING STAIR TO LEVEL 3
NOTES:
-EXISTING 2 STORY
HEIGHT SPACE ON
LEVEL 2 WILL BE SPLIT
TO ACCOMMODATE
COUNSELING
FLOOR IN-FILL FOR
LEVEL 3.
COUNSELING
MECHANICAL
(1) AHU
DATA
ELEC
AHU - 3
U CHOOSE &
HEALTH EDUCATION
APPT
DESK
CAPS
WAITING
(15-20 PPL)
BLDG
SERV
FUNCTIONAL LEGEND
EXISTING STAIR TO LEVEL 3
COMMON AREA
PHARMACY
LABORATORY
MEDICAL RECORDS
INFORMATION TECHNOLOGY
SUPPORT
SHS
U CHOOSE &
HEALTH
EDUCATION
U CHOOSE &
HEALTH EDUCATION
RADIOLOGY
BUILD OUT OF
EXISTING LEVEL 3
CAPS
HEALTH ED. / U CHOOSE STUDENT SERVICES
HUMAN PERFORMANCE LAB
UNUSABLE SPACE TO BE VERIFIED
CLASSROOM
EXISTING STAIR TO LEVEL 3
DASHED LINE INDICATES EXTENT
LEVEL 3
BUILD OUT OF EXISTING LEVEL 3
OF FLOOR IN-FILL
IN FILL FOR LEVEL 3.
3
NON-BUSINESS HOURS ACCESS
Level 3
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Final DESIGN CONCEPT
Proposed build out of Existing/New Level 3
3.20
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Clinic Options
Option 1 – Traditional Clinic Model
SCALE: 1/16”=1’-0”
3.21
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Clinic Options
Option 2 – Core Clinic Model (Preferred Model)
SCALE: 1/16”=1’-0”
3.22
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Clinic Options
Option 3 – Core Clinic Model
SCALE: 1/16”=1’-0”
3.23
3.0 Project Description
3.0 Project Description
NEW FLOOR
3RD LEVEL
2ND LEVEL
1ST LEVEL
EXISTING
FLOOR SLAB
NEW FLOOR
SLAB INFILL
NEW PLAZA
BASEMENT
EXISTING POOL
TO BE INFILLED
| EASTMAN HALL RENOVATION
3.2011111.00
08.01.2012
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
proposed section
Addition of Levels
3.24
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Concept Images





















 
3.25
     
Plaza
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.26
3.0 Project Description

East Plaza Image

East Plaza Image
3.0 Project Description
Overview
Eastman Hall was built in 1929 as a physical education building. It contains three gymnasiums, a pool,
locker rooms, and classrooms. SCSU Health and Counseling Services proposes to renovate this building
for use in health care and counseling. The renovations include adding a new floor between the roof and
the gymnasium floors, creating new openings for elevators, mechanical shafts and open spaces, and
removing substantial portions of the masonry walls that surround the main gymnasium to improve
circulation.
Existing Structure
The existing building was designed by C. H. Johnson in 1929 and consists of three structural floors and
roof framing. The Basement Level, at EL 83'-0" and 85'-0", consists of a slab on grade. At some time in the
past, the original dirt floor at the western portion of the building at EL 91'-6" was replaced by a concrete
slab on grade at EL 85'-0". Thus, the new slab was located at approximately the bottom of footing
elevation of the adjacent columns. A retaining wall structure was constructed near the western exterior
wall to retain soil around the wall footing since it is located at EL 91'-6", well above the new floor level.
The dirt floor at the northeastern section of the basement was also replaced with slab on grade, and the
sloping areas of the floor were replaced with CMU walls.
Level 1, at EL 96'-6", consists of concrete joists and beams with a 2 1/2" top slab. Level 2, at EL 109'-6",
consist of a similar concrete joist beam system, and includes steel beams encased in concrete over the
pool area. Level 3, at EL 121'-8", consists of a relatively small area of the concrete joist and beam system.
The new structural floor will be constructed at this elevation.
The roofs over the small gymnasiums, at EL 131'-2"and 130'-8", consist of concrete joist and beam system,
with steel beams encased in concrete for the major spans. The roof over Main Gymnasium consists of
steel trusses that span approximately 80' supporting purlins spanning between trusses. The purlins
support metal deck. The truss depth varies from approx 7' to 9'.
New Structural Floor
At Level 3 in both the Main and adjacent gymnasiums, a new floor will be constructed between the
existing gymnasium floors and the roof. The structure will consist of composite steel beams supporting 2"
composite metal deck and 2.5" light weight concrete. Beams will be supported by steel columns located
over existing concrete columns.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Schematic Structural Narrative
Renovation of Eastman Hall for
SCSU Health and Counseling Services
St. Cloud State University
3.5 Systems Narrative – Structural
St. Cloud, Minnesota
3.27
3.28
3.0 Project Description
Modifications to Existing Structure
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
In order to create the desired open space above the Level 1 Gathering Space/Café/Retail area, five
individual openings approximately 9' square will be cut through the existing concrete joists. The openings
will be located in front of the large windows, and will allow the existing concrete encased steel beams to
continue through to the east wall.
At the existing pool, the area within the pool walls will be filled with sand or flowable fill, and a new slab
on grade will be constructed. The pool walls will be extended up to the Level 1 elevation with CMU. The
area surrounding the pool will be framed at the Level 1 elevation with steel beams and composite deck
similar to the new floor at Level 3. The existing pool walls with the CMU extension will act as bearing walls
for this framing. Depending on the capacity of the existing concrete columns, it may be necessary to
demolish the existing concrete slabs that form the bleachers along the west side of the pool to help offset
some of the new loads .
The repurposing requires new elevator shafts and mechanical shafts. Elevators will be located in an effort
to minimize the interaction between the existing footings and the new elevator pits to avoid
underpinning. However, the proposed location for the service elevator adjacent to the northeast stairs will
require underpinning for the existing footings. Openings through the existing framing will be located in
an effort to minimize the impact on the existing framing. Where this is not feasible, a new CMU wall will
be constructed around the shaft to support the existing framing. This CMU shaft will extend down to the
Basement Level and include new footings.
Investigation and Reinforcing of the Existing Structure
To ensure that all of the elements of the existing structure are capable of supporting the new loads
associated with the proposed modifications, we recommend budgeting for the following testing.
Investigate the bearing capacity of the soil at each column footing, and reinforce the soil with chemical
grouting or other appropriate method as required. As more data on the existing soil conditions is
obtained, patterns may emerge that make it unnecessary to investigate each footing. However, because
the current data shows large variations in properties, we recommend budgeting for testing at each
footing.
Investigate the reinforcing contained in all footings. The existing drawings provide only a limited amount
of information on selected footings. We recommend using GPR to identify thickness and reinforcement in
all footings. If footings need to be reinforced, reinforcing will likely consist of pouring 8" to 12" of
additional concrete over the existing footing and providing dowels into the existing footing to ensure that
the two act compositely. If punching shear is a problem, dowels into the column will also be required.
Investigate all existing concrete columns using GPR or radiographic methods. The existing drawings
provide no information on the amount of steel rebar contained within the existing concrete columns. If an
existing column cannot support the new load, one method to reinforce the existing columns is to add new
steel tube column adjacent to the existing concrete column to share load. Where needed, the new steel
column would likely extend from below Level 3 to the top of the existing column footing. The footing may
need to be modified to support the load from the new steel tube column.
3.0 Project Description
Building Code: International Building Code as adopted by the State of Minnesota
Design Live Loads: The preferred design live load for the Lab, Office, and Exam spaces is 60 psf.
This allows for better flexibility in the future. However, the existing structure's capacity may dictate
that code minimums are used.
Slabs on Grade
125 psf
Level 1
100 psf
Corridors above Level 1 80 psf
Lab
60 psf
Office
60 psf (Code minimum 50 psf)
Exam
60 psf (Code minimum 40 psf)
Mechanical AHU
80 psf (Approximate equipment weight)
Roofs
35 psf + drifting
Partitions
15 psf
Wind Loads:
90 MPH
Exposure 'B'
Material Strengths
Concrete:
Composite Slab
All Other Concrete
f'c = 3000 psi, light weight
f'c = 4000 psi
Reinforcement:
Fy = 60,000 psi
Structural Steel:
Fy = 50,000 psi – wide flange sections
Fy = 46,000 psi – tubes
Fy = 36,000 psi – misc. steel, angles, plates
Masonry:
f'm = 1500 psi
Masonry Grout:
f'c = 3000 psi
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Design Criteria
3.29
3.30
3.0 Project Description
Systems Narrative – mechanical
PRE-DESIGN NARRATIVE
MECHANICAL DIVISIONS 21, 22, & 23
I.
MECHANICAL SYSTEMS ASSESSMENT
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Dunham Engineering prepared an assessment of the mechanical system serving Eastman Hall at St. Cloud
State University in St. Cloud Minnesota. The purpose of this study is to identify modifications to the
existing mechanical systems to accommodate planned remodeling. The assessment includes non-intrusive
observations, review of existing plans, and discussions with building maintenance staff regarding the state
of the heating, ventilation, air conditioning and plumbing systems.
Interviews with St. Cloud State facility management staff with knowledge of the systems indicate that the
system is currently not functioning. In general, the HVAC system has exceeded its service life, and it is not
anticipated that the systems will adequately serve the building once remodeled and renovated. The
systems are outdated vintage 1929, inefficient and do not meet current ASHRAE codes and ventilation
requirements as described below. Replacement and modifications are recommended.
Division 23 HVAC Systems:
The existing HVAC systems consist of three air handling systems and numerous toilet exhaust fans. The
perimeter rooms are heated with steam fin-tube radiation. Steam is provided from the Campus central
plant.
1.
Existing Air Handling Units (AHU): The existing AHU’s were installed as part of the 1929 building
construction. They serve the pool and gymnasium and provide make up air for the toilet room
exhaust. The AHU’s are in poor condition with failing insulation promoting mold growth, failing
motor bearings and leaking casings.
Recommendation is to replace as part of a system overhaul.
2.
Exhaust Fans: The exhaust fans have exceeded their service life as defined by ASHRAE. The
dampers do not function and require replacement.
Recommendation is to replace as part of a system overhaul.
3.
Steam System: The steam supplied to the building is from the campus central plant and is
provided at 115 PSI. The steam pressure is reduced to 10 psi at a pressure reducing station. The
owner indicated that the pressure reducing station is original and is past its service life. The steam
piping, condensate piping and traps are original to the building. The steam and condensate
piping is showing wear due to age. The steam piping, condensate piping and traps are beyond
their service life as described by ASHRAE.
Recommendation is to replace the pressure reducing station with one that is sized to allow for the
new heating of the remolded building. Steam and condensate piping and traps should be replaced
as part of a system overhaul.
a.
Radiation: The existing radiation is cast iron radiator type. The equipment is original to the
building.
Recommendation is to replace as part of a system overhaul.
b.
Unit Heaters and Convectors: The unit heaters are beyond their service life. Maintenance
staff stated that they are unreliable.
Recommendation is to replace as part of a system overhaul.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 1
Comm. #0412068
3.0 Project Description
Cooling System: No hydronic cooling systems currently exists.
Recommendation is to add hydronic chilled water cooling as part of a system overhaul.
5.
Controls: The heating system, AHU’s, control valves and dampers are controlled via pneumatic
control system. Due to the age of the system, there are a number of leaks. This system is
inefficient and outdated.
Recommendation is to replace with a direct digital control (DDC) control system as part of a system
overhaul.
6.
Miscellaneous Code Concerns:
a. Ventilation: The current system does not meet current codes as described in ASHRAE
Standards 62, 55 and 90. Modifications to the system are required to update to current
standards.
b. Fire and Fire/Smoke Dampers: New fire and fire/smoke dampers will be required as
required by code and any modified Architectural plan layouts.
Division 22 Plumbing Systems:
1.
Domestic Water System: The domestic water supply system is original to the building.
Maintenance staff noted various pin-hole leaks in the system. The system has exceeded the
service life and is need of replacement. Pipe insulation was observed to be removed or missing
from distribution piping in the Lower Level.
Recommendation is to replace as part of a system overhaul.
2.
Sanitary Waste System: The above ground and underground sanitary waste system is original to
the 1929 building. The piping system observed in the lower level appeared in good condition for
its age, although the piping may have reduced capacity due to corrosion and sediment on the
inside of the piping. The sanitary waste system has exceeded its service life and is need of
replacement.
Recommendation is to replace as part of a system overhaul.
3.
Storm Water System: The above ground and underground storm water system is original to the
1929 building. The piping system observed in the lower level appeared in good condition for its
age, although the piping may have reduced capacity due to corrosion and sediment on the inside
of the piping. The storm water system connects to the sanitarily system, in violation of current
code requirements. Pipe sizes appear to be smaller in size than is required by current code for the
roof area served. The storm water system has exceeded its service life and is need of replacement
and does not meet code.
Recommendation is to replace as part of a system overhaul.
4.
Plumbing Accessories:
a.
Water Heaters: There is one steam-to-water domestic water heater installed in the lower
level to serve the building hot water needs. The building water heaters are over 80 years
old. Current code requires that domestic water heaters be double wall. It is unlikely that
the heaters are double wall.
Recommendation is to replacement of the water heaters due to their age.
b.
Circulation Pump: The circulation pump is in poor condition and is in need of
replacement.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 2
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
4.
3.31
3.32
3.0 Project Description
Recommendation is to replace as part of a system overhaul.
c.
Fixtures and Trim: The building fixture and trim are in some cases original to the 1929
building. The fixtures and trim are at the end of their service life and are no longer
serviceable due to the lack of available parts.
Recommendation is to replace as part of a system overhaul.
Division 21 Fire Protection Sprinkler System:
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.
II.
There is no fire protection system installed in the building. .
Recommendation is for a new fire protection system to be installed as part of the renovations.
DESIGN CONDITIONS
1.
Outdoor:
o
a. Winter = -20 F DB
o
o
b. Summer = 91 F DB / 73 F WB
2.
Indoor:
o
a. Winter = 72 F
o
b. Summer = 75 F /50%RH
3.
“U” Values:
a. Walls = To be determined
b. Roof = To be determined
c. Windows = To be determined
4.
Occupancy Levels for load and ventilation rate calculations:
a.
Designed to meet ASHRAE design conditions unless noted as follows:
1) Conference, Waiting, Commons = Number of Chairs +1.
2) Private Office = 2.
3) Exam = 2
5.
Ventilation Air Quantities:
a. Designed to meet AIA and ASHRAE guide lines for Health Care Occupancies.
b. Designed to meet ASHRAE 62-2004 requirements per space usage.
c. Toilet Room Ventilation = 75 CFM per toilet/urinal or 2 CFM/SF, whichever is larger.
III.
CODES AND STANDARDS
1.
Codes and Standards: The following codes and standards will be used in the building design:
a.
2007 Minnesota Building Code (which adopts the 2006 International Building Code with
State Amendments)
b. 2009 Minnesota State Mechanical Code (which adopts the 2006 IMC with State
Amendments)
c. State of Minnesota Plumbing Code
d. 2007 State Fire Code (which adopts the 2006 IFC with State Amendments, and NFPA)
e. Federal ADA Guidelines.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 3
Comm. #0412068
3.0 Project Description
IV.
DEMOLITION
1.
V.
Demolish all abandoned piping and equipment noted to be removed in subsequent sections.
SITE UTILITIES
1.
Domestic Water Service: The existing 3” domestic water service is located in the Lower Level of the
building. A new service is recommended to be provided with a new city water meter will be installed.
2.
Fire Protection Water Service: A new 8” fire protection water service will be provide in the Lower Level.
3.
Sanitary Sewer:
a.
4.
Storm Sewer:
a.
5.
VI.
The existing sanitary sewer for the building shall be removed and replaced with a new
service. The estimated size of the new service is 6”.
A new 10” storm sewer is required to serve the building.
Natural Gas: There is no natural gas required to serve the building.
DIVISION 21 – FIRE PROTECTION SYSTEM
1.
General: Provide a new wet pipe fire protection system to serve the building. The floors of the
building will be served via zone valves located from the wet pipe riser for each floor. The wet
pipe riser shall be located either at the stair riser or in accessible location adjacent to a vertical
riser location. Each stair well shall have a stand pipe connection complying with Minnesota Code
and NFPA 14. Provide hydraulic calculation showing compliance with Minnesota State Fire Code
(NFPA 13 and 14 by reference), including Minnesota amendments. Note that the incoming water
pressure is approximately 65 PSI, per the MN amendments and fire pump is not required.
2.
Sprinkler Heads: Concealed type in all spaces with ceilings. Upright in rooms without ceilings and
in plenum spaces, including mechanical equipment rooms.
3.
Sprinkler Piping:
a.
VII.
Sprinkler piping shall be:
i.
Schedule 40 black steel with threaded joints and malleable fittings.
ii.
No schedule 10 or CPVC piping is allowed.
DIVISION 22 – PLUMBING SYSTEMS
1.
General: Demolish the existing domestic water hot, cold and circulating system. Demolish the
existing waste and vent piping located above and below grade.
2.
Domestic Water Systems:
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 4
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
f. ASHRAE 62-2004, Standard for Acceptable Indoor Air Quality.
g. State of Minnesota Energy Code.
h. Applicable NFPA Standards.
i. SMACNA Duct Construction Standards.
j. MNSCU Standards Revision Date 2010.
k. SCSU Standards.
3.33
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.34
3.0 Project Description
3.
4.
a.
Domestic Water: Provide new domestic water piping from the main water service to the
water heater and provide hot and cold water to each plumbing fixture. A 120 degree
domestic hot water loop with circulating pump will be installed to serve all fixtures.
b.
Sanitary Waste and Vent System: Sanitary waste and vent piping will be provided to each
plumbing fixture. Provide a clean out above the spill line for each fixture. Provide new
underground waste piping to the exterior of the building.
c.
Booster Pump: No booster pump is anticipated. Inlet pressure is 65psi.
d.
Water Softener: No water softener to be installed as hardness level of incoming water is
below MNSCU requirements.
e.
Water Heaters: Provide two (2) steam to water double wall instantaneous water heaters.
Water heaters to be set at 120 degrees. These water heaters will be located in the lower level
mechanical room.
Roof Drainage System:
a.
Primary Roof Drains: Provide new primary roof drains and primary roof drainage system for
the building. Route to 5 feet from the building. Proposed size is 10”.
b.
Overflow Roof Drains: Provide new overflow roof drains and overflow roof drainage system
for the building. Route to 5 feet from the building. Proposed size is 10”.
Plumbing Fixtures (no alternate manufacturers are allowed):
a.
Water closets: Wall hung, flush valve with infrared sensor, hardwired , 1.28 gallons per flush.
i. Sloan royal flush valve with American Standard china.
b. Urinals: Wall hung, flush valve with infrared sensor, hardwired, 0.13 gallons per flush.
i. Sloan model WEUS-1000.
c. Public Lavatories : Vitreous china, wall hung with infrared sensor mixing faucet, hardwired.
i. Sloan Faucet model EAF-200 with Chicago 1025-CP stops and American Standard
China.
d. Sinks: Stainless steel counter mounted sinks of scheduled sizes with wrist blade faucets.
i. Chicago faucet model 1100-GN2AE3-317CP with Chicago 1025 stops.
e. Showers: Shower stall specified by architect.
i. Trim: Simmons Pressure balance anti scald mixing valve Chicago 600 CP shower head.
One Josam floor drain per shower.
f. Floor Drains: Provide one floor drain per toilet group and one floor drain per shower group
(outside of shower).
g. Floor Sinks: Provide one floor sink per AHU and adjacent to water heaters and pumps.
h. Electric Water Coolers: Wall hung high/low ADA compliant with bottle filler.
i. Service Sinks: Floor-mounted 24”x 24” receptors in custodial closets and wall mounted sinks
in Mechanical Rooms with mixing faucets.
j. Wall hydrants: Recessed, non-freeze type with keyed operator. Assume 6 hydrants for pricing.
5.
Emergency Plumbing Fixtures: Domestic hot and cold water will be connected to point-of-use
mixing valves to provide tepid water at all emergency fixtures. Provide in Mechanical Rooms,
Main Janitorial Room, and Laundry Room.
a.
Combination units, ADA compliant combination shower with eye/face wash, six aerated
sprays and rectangular stainless steel bowl. Painted galvanized steel stanchion with a deluge
shower head activated by a high visibility yellow pull rod, Speakman SE-603-ADA or equal.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 5
Comm. #0412068
3.0 Project Description
6.
Plumbing Materials:
a. Domestic water piping: Type L copper with 95/5 soldered joints.
b. Sanitary waste and vent: Service weight cast iron with no-hub couplings above grade and
hub-and-spigot joints below grade.
c. Rain water piping: Service weight cast iron with no-hub couplings above grade and hub-andspigot joints below grade.
7.
Plumbing Insulation:
a.
b.
8.
VIII.
Type: Rigid preformed fiberglass type with vapor proof all service jacket.
Application: Domestic cold, hot, and circulated hot water piping, and all rainwater piping.
Estimated Quantity:
a.
64 sinks, 6 showers, 1 café (3 sinks 5 floor drains), 7 floor sinks.
DIVISION 23 – HEATING SYSTEM
1.
General: The building is supplied from the campus central plant with high pressure steam. All new
piping and equipment will be provided with in the building.
2.
Steam and Condensate Systems:
3.
a.
Pressure Reducing Station: Provide a new pressure reducing station. This station shall consist
of a 1/3 and 2/3 pressure reducing valve. This unit will be located in the Lower Level
mechanical room. Provide a steam flash tank. Pipe new steam piping to the equipment
served.
b.
Condensate Return System: Provide a new condensate return system consisting of pressure
assisted steam powered condensate pumps. Pipe condensate piping to the tunnel for
connection to existing piping.
Hydronic Systems:
a.
180 degree heating water will be created in two (2) 100% redundant steam to water
convertors, located in the Lower Level Mechanical room.
b. Hydronic heating water will be pumped to air handling unit heating coils, radiation and
building terminal units. Two (2) circulating pumps sized for 100% of the load
(primary/standby) will pump heating water to the system.
c.
4.
The primary/standby pumping system will use base-mounted, end-suction pumps mounted
on concrete isolation bases for acoustical isolation.

Basis of design: B&G 1500 series.
Terminal Units:
a.
b.
c.
Provide new finned tube radiation in each perimeter room. Provide a DDC temperature
sensor and control valve for each zone.
Provide duct mounted heating coils for zone temperature control, 1 or 2 rows as required,
on the discharge of the VAV boxes.
Provide “quick recovery” cabinet unit heaters in vestibules and exit stairwells.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 6
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
b. Water Tempering Equipment, thermostatic mixing valve designed to produce 85-degree
potable water for a 15-minute test. In case of failure, unit will continue a cold-water flow,
mixing valve to be by Symmons. System will be a non-recirculating type.
3.35
3.36
3.0 Project Description
d.
e.
2.
Piping Materials:
a.
b.
c.
d.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Provide horizontal unit heaters in mechanical equipment and storage rooms.
Provide radiant ceiling panels in the toilet rooms adjacent to the showers.
High Pressure Steam: Schedule 40 seamless steel pipe with flanged, or welded fittings for
pipe sizes 2-1/2” and larger. Schedule 40 seamless steel pipe with butt-welded fittings for
pipe sizes 2” and below.
Low Pressure Steam: Schedule 40 seamless steel pipe with flanged, or welded fittings for
pipe sizes 2-1/2” and larger. Schedule 40 seamless steel pipe with screwed or butt-welded
fittings for pipe sizes 2” and below.
Condensate: Schedule 80 seamless steel with flanged, or welded fittings for pipe sizes 2-1/2”
and larger. Schedule 80 black steel with screwed fittings for pipe sizes 2” and below.
Hydronic Heating Water: Schedule 40 black steel with flanged, welded, or cut grooved
mechanical couplings for pipe sizes 2-1/2” and larger. Schedule 40 black steel with screwed
fittings or Type ‘L’ copper with soldered fittings for pipe sizes 2” and below.
3.
Piping Installation: Pump piping connections will be made with flexible connectors.
4.
Piping Insulation:
a.
b.
5.
Type: Rigid preformed fiberglass type with vapor proof all service jacket.
Application: All steam, condensate and hydronic water piping.
Estimated Size:
1) 4500 MBH steam reducing station
2) Two 370 GPM, 90 ft HD pumps
3) 68 VAV zones.
IX.
DIVISION 23 – COOLING SYSTEM
1.
General: Provide a new cooling system for this building by extending piping from the central
plant piping located in the tunnel adjacent to the building.
2.
Chilled Water System: The building will be served from the central chilled water plant. Campus
chilled water piping to the new building will be provided via a separate contract. Campus chilled
water will be provided to the new building through a pair of 8” supply and return mains. The
chilled water pumping system will be via the secondary pumps located in the central plant. The
design chilled systems will be a 12 degF dT (42 degF EWT and 54 degF LWT).
3.
BTU Meters: BTU Meters will be provided for monitoring of the chilled water system.
4.
Piping Materials:
a.
Exposed in Mechanical Room spaces:
4) Schedule 40 black steel with flanged, welded, or cut grooved mechanical couplings for
pipe sizes 3-1/2" and larger.
5) Schedule 40 black steel with screwed fittings or Type 'L' copper with soldered fittings for
pipe sizes 3" and below.
b. Concealed in chases, or above ceilings:
1) Schedule 40 black steel with flanged or welded for pipe sizes 3-1/2" and larger.
2) Schedule 40 black steel with screwed fittings or Type 'L' copper with soldered fittings for
pipe sizes 3" and below.
Chilled Water Piping Insulation:
5.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 7
Comm. #0412068
3.0 Project Description
Type: Rigid preformed fiberglass type with vapor proof all service jacket.
Exterior Insulation Type: Rigid preformed fiberglass with all service jacket.
Application: All chilled water piping. Control valve bodies, fittings, and pump volutes will be
insulated to prevent condensation.
6.
Elevator Equipment Room Cooling: The elevator equipment room will be cooled with nominal 1ton split system cooling units. The units will be connected to grade-mounted air cooled
condensing units.
7.
Refrigerant Piping Materials:
a.
8.
Refrigerant Piping Insulation:
a.
b.
9.
X.
Refrigerant: Type ACR copper.
Type: Flexible elastomeric insulation for irregular shapes.
Application: All refrigerant piping. Control valve bodies and fittings will be insulated to
prevent condensation.
Estimated Size:
1) 190 Ton Capacity
DIVISION 23 - AIR HANDLING SYSTEMS
1.
General: Demolish all existing ductwork, air handling units and exhaust fans and provide new
systems as described here-in.
2.
AHU-1: The system serving the Basement and First Floor (Human Performance Lab, Receiving,
Café, Radiology etc.) will be an variable volume, constant temperature air handling unit ducted to
VAV boxes that supply air via a mixing system (i.e. overhead diffusers). The unit will consist of a
indoor modular air handling unit with a plate type energy recovery core. This unit will be located
in the basement mechanical room. Basis of design is McQuay. Cabinet construction will be 2”
thick insulated double wall with solid internal liner unless noted as perforated liner. This unit will
be a variable volume, constant temperature, air handling unit. The estimated capacity is:
a.
22,500 CFM with 72 tons cooling.
AHU-1 will have the following components:
a. Inlet plenum section. (Back inlet). Cabinet liner shall be perforated
b. Return / Relief Fan: Single inlet plenum centrifugal return/relief fan with Variable Speed Drive
mounted on spring vibration isolators.
c. Side access filter section with 35% (MERV 7) efficient pre-filters.
d. Pumped water coil preheat section with coil discharge air temperature controls, and
circulation pump
e. Aluminum Plate energy recovery section
f. Access/Inspection Section for control sensor installation
g. Pumped water coil heating section with coil discharge air temperature controls, and circulation
pump
h. Access/Inspection Section for control sensor installation
i. Chilled water cooling and dehumidification coils with discharge control
j. Access/Inspection Section for control sensor installation
k. Single inlet centrifugal plenum supply fan with Variable Speed Drive, low discharge sound
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 8
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
a.
b.
c.
3.37
3.38
3.0 Project Description
l.
m.
n.
o.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.
characteristics, and mounted on spring vibration isolators.
Access/Inspection Section to allow for in swing door.
Side access final filter section with 95% (MERV 14) efficient cartridge filters.
Discharge plenum section.
Exhaust air energy recovery (plate or wheel type)
AHU-2: The system serving the Second Floor (Health Services.) will be an variable volume,
constant temperature air handling unit ducted to VAV boxes that supply air via a mixing system
(i.e. overhead diffusers). The unit will consist of a indoor modular air handling unit with a plate
type energy recovery core. This unit will be located in the basement mechanical room. Basis of
design is McQuay. Cabinet construction will be 2” thick insulated double wall with solid internal
liner unless noted as perforated liner. This unit will be a variable volume, constant temperature,
air handling unit. The estimated capacity is:
a.
24,000 CFM with 65 tons cooling.
AHU-2 will have the following components:
a.
b.
Inlet plenum section. (Back inlet). Cabinet liner shall be perforated
Return / Relief Fan: Single inlet plenum centrifugal return/relief fan with Variable Speed Drive
mounted on spring vibration isolators.
c. Side access filter section with 35% (MERV 7) efficient pre-filters.
d. Pumped water coil preheat section with coil discharge air temperature controls, and
circulation pump
e. Aluminum Plate energy recovery section
f. Access/Inspection Section for control sensor installation
g. Pumped water coil heating section with coil discharge air temperature controls, and circulation
pump
h. Access/Inspection Section for control sensor installation
i. Chilled water cooling and dehumidification coils with discharge control
j. Access/Inspection Section for control sensor installation
k. Single inlet centrifugal plenum supply fan with Variable Speed Drive, low discharge sound
characteristics, and mounted on spring vibration isolators. .
l.
Access/Inspection Section to allow for in swing door.
m. Side access final filter section with 95% (MERV 14) efficient cartridge filters.
n. Discharge plenum section.
o. Exhaust air energy recovery (plate or wheel type)
4.
AHU-3: The system serving the Third Floor (Counseling and U Choose) will be an variable volume,
constant temperature air handling unit ducted to VAV boxes that supply air via a mixing system
(i.e. overhead diffusers). The unit will consist of a indoor modular air handling unit with a plate
type energy recovery core. This unit will be located in the basement mechanical room. Basis of
design is McQuay. Cabinet construction will be 2” thick insulated double wall with solid internal
liner unless noted as perforated liner. This unit will be a variable volume, constant temperature,
air handling unit. The estimated capacity is:
a.
18,500 CFM with 50 tons cooling.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 9
Comm. #0412068
3.0 Project Description
a. Inlet plenum section. (Back inlet). Cabinet liner shall be perforated
b. Return / Relief Fan: Single inlet plenum centrifugal return/relief fan with Variable Speed Drive
mounted on spring vibration isolators.
c. Side access filter section with 35% (MERV 7) efficient pre-filters.
d. Pumped water coil preheat section with coil discharge air temperature controls, and
circulation pump
e. Aluminum Plate energy recovery section
f. Access/Inspection Section for control sensor installation
g. Pumped water coil heating section with coil discharge air temperature controls, and circulation
pump
h. Access/Inspection Section for control sensor installation
i. Chilled water cooling and dehumidification coils with discharge control
j. Access/Inspection Section for control sensor installation
k. Single inlet centrifugal plenum supply fan with Variable Speed Drive, low discharge sound
characteristics, and mounted on spring vibration isolators. .
l. Access/Inspection Section to allow for in swing door.
m. Side access final filter section with 95% (MERV 14) efficient cartridge filters.
n. Discharge plenum section.
o. Exhaust air energy recovery (plate or wheel type)
5.
Exhaust Ventilation: Utility set exhaust fans will provide the exhaust needs for the building. Fans
will be equipped with motorized isolation dampers in the ductwork for isolation. Located fans in
the mezzanine mechanical room. Provide fans for services as follows:
a.
b.
c.
d.
e.
6.
Toilet room exhaust (Assume 4 fans)
Laboratory fume hood exhaust (Assume 1 fan)
Kitchenette exhaust (Assume 1 Fan)
Work room exhaust (Assume 1 Fan)
Trash room exhaust (Assume 1 Fan)
Distribution Systems:
a.
b.
Ductwork Systems (All): Low-pressure ductwork systems shall be G90 galvanized steel,
rectangular or round. Exposed ductwork shall have a mill phosphatized finish to accept field
painting. Supply ductwork upstream of VAV terminal units will be constructed to SMACNA
4” pressure class with seal class ‘A’ All supply ductwork downstream of VAV terminal units,
all return/relief, and general exhaust will be constructed to SMACNA 2” pressure class
(positive/negative) with seal class ‘A’.
Duct Insulation: Two-inch thick fiberglass board with foil face in mechanical equipment
rooms for supply, and outside air ductwork. One-and-one-half-inch thick fiberglass board
with foil face in mechanical equipment rooms for return, and relief air ductwork. One-andone-half-inch thick flexible fiberglass with foil face for supply, return, and exhaust air in
unconditioned spaces (i.e. shafts and above ceilings).
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 10
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
AHU-3 will have the following components:
3.39
3.40
3.0 Project Description
7.
Air Inlets and Outlets: Supply air will be distributed using wall or ceiling registers with double
deflection adjustable vanes, round ceiling diffusers in areas with exposed ductwork, and square
louvered-face ceiling diffusers in rooms with ceilings. Return and exhaust air inlets will be wall
o
registers and grilles with fixed 45 degree vanes or grates with 1” cube openings, and ceiling egg
crate registers and grilles.
8.
Sound Control: Specified sound criteria for spaces will be as follows: Offices, Conference, Lobby
(RC-35N), Toilet Room (RC-40N).
a.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
b.
c.
XI.
Noise generated at the air handling units will be attenuated using manufactured duct
mounted sound attenuators with perforated internal liners covering faced fiberglass
insulation.
Noise generated by air movement in ductwork will be controlled through established design
criteria, including low air velocity, and radius elbows. Flow splitters, and terminal duct
mounted attenuators will not be used.
Spring vibration isolators will be used on fans, pump isolation bases, ductwork, and piping
located in the Mechanical Equipment Rooms.
BUILDING AUTOMATION SYSTEM (BAS):
1.
XII.
General: The building automation system will include automatic controls for monitoring and
control of building temperature, humidity, outside air, and pressure. System components will
include microprocessor based stand-alone field panels, electronic sensors, electric operators, and
wiring. All controls for this building will be connected to the existing Central Operators
personnel computer workstation at the facilities building. The new controls will be by Trane to
integrate with the current automation system.
BUILDING COMMISSIONING:
1.
XIII.
Commissioning of building mechanical systems (HVAC, Plumbing, Controls) will be implemented
at the design development phase, and continued through construction completion.
Commissioning will be independent via the owner.
B3 MINNESOTA SUSTAINABLE BUILDING GUIDELINES:
1.
The design will comply with State of Minnesota B3 Requirements, and will utilize sustainable
concepts where applicable:
a. Variable air volume air handling system to minimize air transport energy
b. Energy recovery of exhaust air
c. Modulate the minimum outdoor air air via space CO2 Sensors for demand control
ventilation.
d. Variable flow heating hot water systems to match heating energy to required building loads
e. Low flow plumbing fixtures
XIV.
ENERGY EFFICIENCY OPTIONS:
1.
In lieu of providing a mixing system and three air handling units as stated above, for a chilled
beam system could be provided as follows:
a.
b.
Provide 3 eight foot active chilled beams per 1000 ft. space.
Provide 1 four foot active chilled beam for each office and exam space.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 11
Comm. #0412068
3.0 Project Description
Provide a 100% outside air, air handling unit sized at 22000 CFM. Provide air handling unit similar
to AHU-1 described above with the addition a of a desiccant dehumidification wheel.
d. Provide minimum outside air ductwork to each chilled beam.
e. Provide ducted return to each space.
f. Heating system is unchanged from description above. In addition, pipe hydronic heating water to
each chilled beam.
g. Cooling system:
1) In addition to the chilled water system described above, provide a plate heat exchanger
and two chilled water pumps. Pipe chilled water to each active chilled beam.
2) Provide a dry cooler for economizer operation. Estimate size 125 tons.
Eastman Hall Mechanical 50% Pre-Design
March 27, 2012
Page 12
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
c.
3.41
3.42
3.0 Project Description
Systems Narrative – Electrical
PRE-DESIGN NARRATIVE
ELECTRICAL
DIVISION 26
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
I.
Electrical Systems Assessment
A.
Dunham Engineering prepared an assessment of the electrical system serving Eastman
Hall on the St Cloud State University Campus. The purpose of this study is to identify
modifications to the existing mechanical and electrical systems to accommodate
planned remodeling. The assessment includes non-intrusive observations, review of
existing plans, and discussions with building maintenance staff of the power, lighting,
communication security, life safety (fire alarm devices), heating, ventilation, air
conditioning and plumbing systems.
B.
Interviews with SCSU facility management staff with knowledge of the systems indicate
that the general conditions of the systems are they are the end of life (with some
exceptions which are noted within this document). Their preference would be for a
complete replacement of the all the existing systems to current standards and code
compliance.
C.
Medium Voltage:
1.
The existing building medium voltage components are relatively new (less than
10 years old) and are in good condition. The equipment is located on the north
side of the building, at grade, and feeds down into an underground vault off the
existing tunnel. Within the vault, there is a 600A service disconnect for Eastman
Hall and also an 800A service disconnect that feeds Riverview from the Eastman
Hall transformer. The existing medium voltage transformer is currently adequate
for the existing space program and the Riverview feed, but will not accommodate
the proposed change in space program to Eastman Hall.
a.
Proposed: Disconnect Eastman Hall from the existing medium voltage
transformer (leave in place for continued feeding of Riverview), and a new
appropriately sized transformer for the proposed space programming will
be provided.
D.
Power Distribution:
1.
The existing building electrical distribution system equipment varies from
relatively new fusible disconnect switches (a 600A Siemens distribution board
located in the basement in the northwest corner; a two section 400A Siemens
board in the boiler room on the south side basement) to panel boards that are
greater than 40 years old. The existing electrical distribution system is currently
adequate for the existing space program, but will not accommodate the
proposed change in space program.
a.
Recommendation: Replace entire existing electrical distribution system
with a new building service infrastructure. The existing Siemens
switchboards will be provided to the Owner for spare parts.
E.
Power Receptacles:
Electrical 90% Pre-Design
June 1, 2012
Page 1
Comm. #0412068
3.0 Project Description
The existing power receptacle installation is a mix of old and newer devices
connected to the existing electrical installation.
a.
Recommendation: Replace all existing power receptacles to new style
receptacles that correspond to the building’s new space programming.
F.
Lighting:
1.
Lighting throughout the building is mostly older, low-efficiency fluorescent, HID
(high intensity discharge), and incandescent fixtures. The fluorescents are mostly
T12 lamps with low-efficiency magnetic ballasts. Lighting in the Gymnasium and
the Pool areas provided by HID light fixtures with large magnetic ballasts.
a.
Recommendation: Replace all existing lighting with new energy efficient
fluorescent (T8, T5, T5HO) and LED fixtures, corresponding to the
building’s new space programming.
G.
Life Safety Egress Lighting:
1.
The existing Egress Lighting is achieved from self contained battery units in
scattered areas.
a.
Recommendation: Egress lighting will be achieved via a new emergency
power feed to designated light fixtures, which will be new and
accommodate the building’s new space programming. Replace all existing
exit signs with new high efficiency, longer lasting LED illuminated exit
lights.
H.
Emergency Electrical Power:
1.
Dunham did not observe an existing connection to the campus emergency
system radial feed derived from the campus central plant, and does not believe
there is currently emergency electrical power in the facility other than selected
battery operated lighting.
a.
Recommendation: Provide a new transformer and Automatic Transfer
Switch to connect to the SCSU Campus Emergency Radial Distribution
System.
II. NEW ELECTRICAL GENERAL REQUIREMENTS
A.
The work described in this document includes all materials, labor, equipment and
services to construct and install a complete operating electrical and low voltage roughin system for the renovation of Eastman Hall at St. Cloud State University in St. Cloud
Minnesota.
III. DESIGN CONDITIONS
A.
Exterior Environmental Conditions: Electrical systems shall withstand the following
environmental conditions without mechanical or electrical damage or degradation of
performance capability:
1.
Ambient Temperature: -20 to 104 deg F
2.
Relative Humidity: 0 to 95 percent.
3.
Altitude: 1031 feet
Electrical 90% Pre-Design
June 1, 2012
Page 2
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.
3.43
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.44
3.0 Project Description
B.
Interior Environmental Conditions: Electrical systems shall withstand the following
environmental conditions without mechanical or electrical damage or degradation of
performance capability:
1.
Ambient Temperature: 65 to 75 deg F
2.
Relative Humidity: 0 to 95 percent.
3.
Altitude: 1031 feet
C.
Interruption of Existing Electric or Communication Services: Do not interrupt services to
facilities occupied by Owner or others unless permitted under the following conditions
and then only after arranging to provide temporary electric service according to
requirements indicated:
1.
Notify Owner/Owner's Representative no fewer than 5 working days in advance
of proposed interruption of electric service.
2.
Do not proceed with interruption of electric service without Owner's/Owner's
Representative's written permission.
IV. CODES AND STANDARDS
A.
Codes and Standards: Materials, products, devices, fixtures, and forms shall meet or
exceed the requirements of National Electrical Code (NEC), American National
Standards Institute (ANSI), Institute of Electrical and Electronics Engineers (IEEE),
National Manufacturing Association (NEMA) and all applicable codes, all for the most
current editions as of the Schematic Design Submittal. Methods of construction and
material application shall comply with installation requirements of the National Fire
Protection Association (NFPA). All materials and equipment shall be listed and labeled
by the Underwriters Laboratories, Inc. (UL) or other approved testing agency as
conforming to their standards where such standards have been established for the
particular materials or equipment. The following codes and standards will be followed;
1.
NFPA - National Fire Protection Association, NFPA 101, 72, 110, and 780
2.
IBC - International Building Code
3.
UFC - Uniform Fire Code
4.
NEC - National Electrical Code
5.
UFAS - Uniform Federal Accessibility Standard
6.
IES - Illuminating Engineers Society - Lighting Levels Standards
7.
ASHRAE 90.1 - American Society of Heating, Refrigerating and Air Conditioning
Engineers, Inc.
8.
ANSI - American National Standards Institute
9.
NEMA - National Electrical Manufacturer's Association
10.
EIA/TIA - Electronic Industry Association/Telecommunications Industry
Association
11.
BICSI - Building Industry Consulting Service International
12.
Minnesota State Colleges and Universities (MNSCU) Facilities Design and
Construction Standards – 6th Addition (with 12/2010 revisions).
13.
All work will be performed by licensed contractors in the State of Minnesota.
V. DEMOLITION
A.
Remove accessible wiring including conduit, junction boxes, hangers, and supports for
main feeders to panel boards, from panel boards to light fixtures, and from panel
Electrical 90% Pre-Design
June 1, 2012
Page 3
Comm. #0412068
3.0 Project Description
B.
Where conduits are stubbed out of a surface not being removed for new construction,
such as a floor slab or poured concrete column or wall, these conduits shall be cut back
to a point where patching can adequately be performed.
C.
Demolition work shall be coordinated with the Owner. Should questions arise regarding
the removal of a conduit and/or wiring, (i.e. Is it energized? Does it serve a load in an
area not be remodeled?), confer with the Owner before such wiring or conduit is
actually demolished.
D.
Reused and Reinstalled equipment and devices: Carefully disconnect and remove items
to be reused or reinstalled. Items shall be properly stored in a manner causing no
additional damage to the item. Prior to reinstalling, clean and test item. Upon
completion, the item shall be in equivalent condition as prior to its removal. Items
damaged due to improper handling and storage by the Contractor shall be replaced
with new items of the same type and quality as the original item. Reinstalled light
fixtures shall be cleaned and re-lamped with new lamps. Non-functioning ballasts shall
be replaced with new ballasts. Lamps and ballasts shall be guaranteed as new items.
E.
Demolition equipment and devices: Existing equipment, devices, and light fixtures not
indicated for reuse (as indicated in other portions of this document) shall become the
property of the Contractor and disposed of properly.
F.
Light fixtures scheduled for removal on this Project may contain PCB impregnated
ballasts. Remove PCB ballasts from light fixtures and place ballasts in hazardous waste
disposal containers. Properly dispose of the ballasts with a registered hazardous
materials disposal contractor. Provide copies of the disposal certificate(s) to the Owner
and Engineer at the completion of the Project.
G.
Fluorescent and HID lamps removed from light fixtures shall be placed in containers,
and properly disposed of with a registered disposal contractor.
H.
Disconnect and remove wiring devices and replace with new devices and cover plates.
I.
Rework the existing conduit and junction box system such that upon completion of the
remodeling, no junction boxes are located in inaccessible locations. This includes
existing junction boxes that may be rendered inaccessible due to new piping or
ductwork installation. Coordinate with other trades in this effort. Provide additional
conduit and connections as required.
VI. SITE UTILITIES
A.
Electrical Utility Service: The campus has an existing 12,470 kV underground distribution
system, utilizing exterior medium voltage switches and transformers to feed buildings.
Electrical 90% Pre-Design
June 1, 2012
Page 4
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
boards to wiring devices such as receptacles, switches, floor outlets, special electrical
devices, etc., indicated to be removed in other portions of this document. Existing
conduit, boxes, cable, etc. that remain which are presently being supported from
existing ceiling or ceiling supports, which are to be removed, shall be re-supported to
building structure.
3.45
3.46
3.0 Project Description
The building is currently tied into redundant loop feeders, with the connections to pad
mounted equipment on the northeast side of the building. Initial design anticipates
being able to reuse the existing medium voltage switches, but will need to upgrade the
transformer for the building due to the increase in anticipated capacity needs.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
VII. DIVISION 26 – ELECTRICAL SYSTEMS
A.
Design Load Calculations: Refer to Appendix A thru C for estimated design loads based
on the architectural Tier Level square footages. The following information will be based
on the Tier 3 electrical loads.
B.
The existing 225kVA - 12,470V to 208/120V Medium Voltage pad mounted transformer
shall be remaining as is to continue serving Riverview. A new medium voltage switch
and 500kVA - 12,470V to 208/120V Medium Voltage pad mounted transformer to be
provided, located in the same general location as the existing switch and transformer,
with new connections into the medium voltage loops provided.
C.
The existing 208/120V, 600A main switchboard shall be removed in its entirety.
D.
Provide a new suitable for use as service entrance, 208/120 volt, 3-phase, 4-wire power
switchboard, locating in the basement level of the building. The electrical room
requirements for the building will be:
1.
Main Electrical Room (Basement)
a.
Switchboard distribution sections to feed secondary electrical rooms and
large mechanical equipment.
1)
Rated at 1600 amps, 208V/3PH/4W with a 1600 amp main circuit
breaker.
2)
UL 891 compliant
3)
Full capacity non-tapered main bus, 100% neutral bus and 50%
ground bus.
4)
Integral Transient Voltage Surge Suppression (TVSS).
5)
100,000 AIC Rating
6)
Customer metering shall be provided.
7)
100 amp, 208/120 volt, 3-phase, 4-wire lighting panel board(s) for
interior/exterior lighting.
8)
100 amp, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for
HVAC package units, pumps, fans, general purpose power
requirements, etc. and general purpose power requirements.
9)
Life Safety and Optional Standby Automatic Transfer Switches (260
amp) and associated 225 amp, 208/120 volt, 3-phase, 4-wire panel
boards for emergency loads.
10)
Lighting Control System Panel.
2.
Mechanical Room (Basement)
a.
Switchboard construction distribution board to feed large mechanical
equipment.
1)
Rated at 1600 amps, 208V/3PH/4W with a 1600 amp main circuit
breaker.
2)
UL 891 compliant
Electrical 90% Pre-Design
June 1, 2012
Page 5
Comm. #0412068
3.0 Project Description
3.
4.
5.
6.
Full capacity non-tapered main bus, 100% neutral bus and 50%
ground bus.
4)
Integral Transient Voltage Surge Suppression (TVSS).
5)
100,000 AIC Rating
6)
Customer metering shall be provided.
b.
225 amp, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC
package units, pumps, fans, general purpose power requirements, etc. and
general purpose power requirements.
st
Secondary Electrical Room (1 Level)
a.
100A, 208/120 volt, 3-phase, 4-wire lighting panel board(s) for
interior/exterior lighting.
b.
225A, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC
package units, pumps, fans, etc. and general purpose power requirements.
c.
400A, 208/120 volt, 3-phase, 4-wire health care equipment and general
purpose power requirements.
d.
Lighting Control System Panel(s).
nd
Secondary Electrical Room (2 Level)
a.
208/120 volt, 3-phase, 4-wire lighting panel board(s) for interior and
exterior lighting.
b.
225A, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC
package units, pumps, fans, etc. and general purpose power requirements.
c.
400A, 208/120 volt, 3-phase, 4-wire health care equipment and general
purpose power requirements. TVSS shall be provided with this panel
board.
d.
200A, 208V, 3-phase, 4-wire imaging equipment feeder and disconnect.
TVSS shall be provided with this feeder/disconnect.
e.
Lighting Control System Panel(s).
rd
Secondary Electrical Room (3 Level)
a.
208/120 volt, 3-phase, 4-wire lighting panel board(s) for interior/exterior
lighting.
b.
225A, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC
package units, pumps, fans, etc. and general purpose power requirements.
c.
400A, 208/120 volt, 3-phase, 4-wire lab equipment and general purpose
power requirements. TVSS shall be provided with this panel board.
d.
Lighting Control System Panel(s).
Emergency (Central Plant Generator Feeder)
a.
A new 75kVA K-4 rated transformer will be provided to utilize the central
plant emergency system (480V to 120/208V). This transformer shall feed
the following:
b.
Life Safety Branch: Loads include egress lighting, telephone,
communications, fire alarm, and other essential equipment for the
evacuation of personnel from the facility.
c.
Optional Standby Branch: Loads include the elevator, network electronics,
servers, and other owner designated equipment.
d.
Automatic Transfer Switches (ATS): Transfer switches transfer loads to the
emergency feed upon loss of normal power. Transfer switch shall be open
transition. The Life Safety transfer switch must be re-energized within a
maximum of 10 seconds from the loss of normal power.
Electrical 90% Pre-Design
June 1, 2012
Page 6
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3)
3.47
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
3.48
3.0 Project Description
E.
All branch circuit panels will include bolt-on circuit breakers, door in door covers, UL 67
compliant, 200% neutrals, and will be designed with 50% spare/space circuit capacity.
Panel board withstand rating (SCCR) shall be a minimum of 10,000 Amps for 208/120V
panels. The distribution design shall be a fully rated system, SCCR and AIC ratings for
panels shall be as noted on the panel schedules.
F.
All transformers shall be dry-type, 480V-3PH-3W Delta to 208/120V-3PH-4W Wye, K-4
rated.
G.
Transient Voltage Surge Suppression: Transient Voltage Surge Suppression (TVSS)
design shall be compliant with UL 1449 and IEEE C62.41 standards. The design shall
take a two tier approach with surge suppression provided at the main service and at key
branch panels where sensitive electronic equipment is fed from.
H.
Grounding Systems: A complete grounding electrode system will be provided which
will include connection to building steel, underground metal water piping systems,
building Ufer ground (if available), and building ground ring (new). All electrodes shall
comply with NEC article 250. A continuous equipment grounding conductor will be
installed in all power/lighting conduit systems and all distribution equipment will have
ground buses. New grounding components shall tie back into the existing grounding
system.
I.
Motor Starters and Disconnect Switches: Starters and control equipment will be
provided for all electrically operated motors and equipment.
Motor electrical
connection will be as follows:
1.
½ HP or less – 120V single phase. Manual motor starters (MMS) shall be snap
action toggle switch type. Manual motor starters shall be surface or flush
mounted. For single phase 120V motor loads, switches shall be horsepower
rated, manual, non-reversing switches without overload protection.
2.
¾ HP or greater – 208V three phase. Magnetic starters shall be full voltage,
combination type, except where otherwise specified. Required starter sizes and
types are indicated on the drawings. Safety switches shall be NEMA type "HD",
heavy duty, horsepower rated (note that HP rating of switch must be equal to or
greater than HP rating of motor or equivalent equipment loads).
3.
Motors rated 10 Hp or higher. Solid-state sensing circuit with isolated output
contacts for hard-wired connection; arranged to operate on phase failure, phase
reversal, current unbalance from 30 to 40 percent, or loss of supply voltage.
Provide adjustable response delay.
4.
Fuses protecting motors shall be protected by dual-element type fuses able to
carry 500% of rating for 10 seconds and sized at least 125% of motor nameplate
rating (100 amps and less - Fusetron FRN-R or FRS-R; larger than 100 amps Low-Peak LPN-RK or LPS-RK).
J.
Wires and Cables: Wires and Cables: Conductors shall be copper (minimum 98%) and
shall be insulated for 600 volts. Aluminum conductors will not be acceptable. Unless
shown otherwise, minimum wire size shall be #12. 120V branch circuits with lengths
greater than 75 feet (150 feet for 277 volt) measured from center of load shall not be
smaller than No. 10. Conductors larger than 10 shall be stranded. Feeder and branch
circuit wiring shall be color coded by line or phase in accordance with the National
Electrical 90% Pre-Design
June 1, 2012
Page 7
Comm. #0412068
3.0 Project Description
K.
Wiring Devices:
1.
Local light switches shall be low voltage control switches with minimum four
buttons.
2.
Wiring Devices: Includes receptacles and device cover plates. Receptacles shall
be specification grade, grounding type, 20 ampere, mounted with ground lug
down. Isolated ground, surge suppression and ground fault outlets on branch
circuits where required. Device cover plates shall be stainless steel type 302 with
beveled edges. Normal devices shall be gray and emergency devices shall be
red.
3.
Special purpose receptacles will be provided for miscellaneous loads.
L.
Surface Raceway (Non-Lab areas):
1.
Basis-of-Design Product: Subject to compliance with requirements, provide the
following product (or a comparable product):
a.
Walker Systems, Inc.; Wiremold DS4000 Series (power and data)
M.
Surface Raceway (Lab areas):
1.
Basis-of-Design Product: Subject to compliance with requirements, provide the
following product (or a comparable product):
a.
Walker Systems, Inc.; Wiremold ALDS4000 Series (power and data)
N.
Multiservice Floorboxes (Slab on grade).
1.
Basis-of-Design Product: Subject to compliance with requirements, provide the
following product (or a comparable product):
a.
Walker Systems, Inc.; Wiremold RFB4-CI Recessed Floor Box
b.
Hubbell Wiring Devices Floorbox
O.
Multiservice Floorboxes (Non-slab on grade).
1.
Basis-of-Design Product: Subject to compliance with requirements, provide the
following product (or a comparable product):
a.
Wiremold RFB4-SS Recessed Floor Box
b.
Hubbell Wiring Devices Floorbox
P.
Multiservice PokeThru (Non-slab on grade).
1.
Basis-of-Design Product: Subject to compliance with requirements, provide the
following product (or a comparable product):
a.
Wiremold Evolution 8AT Series
Electrical 90% Pre-Design
June 1, 2012
Page 8
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Electrical Code. All conductors shall be installed inside metallic conduit. Metal Clad
cable shall only be allowed for connection to light fixtures. Conductors with type THWN
or XHHW code grade insulation rated at 75 degrees C for wet and dry locations shall be
used throughout the project except as follows:
1.
Type THHN/THWN and XHHW-2 600 volt, rated 90 degrees C, under dry
conditions shall be used for feed-through wiring in channel of continuous rows of
fluorescent fixture, and between recessed type lighting fixtures and adjacent
outlet boxes.
2.
Type AVA 600 volt, rated 110 degrees C, under dry conditions shall be used for
wiring adjacent to hot water heaters, to steam lines, to boilers, and to heat
producing equipment hoods.
3.49
3.50
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
b.
Hubbell Wiring Devices PokeThru
Q.
Multiservice Raised Floor Floorboxes (Raised Flooring).
1.
Basis-of-Design Product: Subject to compliance with requirements, provide the
following product (or a comparable product):
a.
Walker Systems, Inc.; Wiremold SAF Floor Box
b.
Hubbell Wiring Devices Floorbox
R.
Electrical Circuits:
1.
Lighting Homeruns: Provide 3/4"C. - (branch circuits shall have dedicated
neutrals). Load each 120 Volt, 20 Amp lighting circuit to a maximum of 1200
Watts.
2.
General Purpose Homeruns: Provide 3/4"C. - (branch circuits shall have
dedicated neutrals). Load each 120 Volt, 20 Amp receptacle circuit to a maximum
of 1400 Watts, approximately eight (8) receptacles. These receptacles include
general purpose and maintenance receptacles.
3.
Computer Circuit Homeruns: Provide 3/4"C. - (branch circuits shall have
dedicated neutrals). Load each 120 Volt, 20 Amp receptacle circuit to a maximum
of 1200 Watts, approximately Six (6) receptacles.
4.
Branch Circuit Conductor Size: Provide #12 AWG branch circuit conductors for all
20 amp, 120 volt circuits less than 100’. Provide #10 branch circuit conductors for
all 20 amp, 120 volt circuits over 100’.
5.
Each circuit shall have a dedicated neutral. The use of multi-wire branch circuits
with a common neutral is not permitted.
S.
Lightning Protection System for Structures:
1.
A new UL and LPI Certified Lightning protection system, which shall comply with
UL 96 and NFPA 780 requirements, will be installed on Eastman Hall.
T.
Lighting Systems:
1.
The lighting systems for the building will include a combination of direct and
indirect LED lighting fixtures. The fixtures shall be designed such that they
provide maximum efficiency and lowest expended watts. The selection of the
light fixtures will be based on size and use of each space.
2.
Lighting controls shall include day light sensors (DL), occupancy sensors (OS), and
time of day (TD) control utilizing a network lighting control system with individual
fixture control (Lithonia nLight product or equal). Daylight sensors shall be placed
in spaces that have exterior windows to provide daylight harvesting
opportunities.
3.
Exterior Lighting: IESNA “full cutoff” LED Luminaries will be provided. Controls for
exterior lighting shall consist of a relay panel with photocell and time of day
schedule. Exterior lighting will comply with MNSCU standards on lighting levels
and max/min ratios for public walkways associated with the project.
4.
Lighting Design: The lighting layout will be designed as per Illuminating
Engineering Society (IES) and ASHRAE 90.1 recommendations. Occupancy Sensor
and Time of Day control measures will be provided as noted. LED fixtures shall be
based on 3500K color temperatures at 325mA. Fluorescent fixtures shall utilize
Super T8, 3250 initial lumens, 35K lamps shall be used throughout. Low Ballast
Factor (0.71-0.78) program start, < 10% THD, electronic ballasts; dimmable
Electrical 90% Pre-Design
June 1, 2012
Page 9
Comm. #0412068
3.0 Project Description
Area Type
Avg.
Footcandles
Offices Areas
30-50
Common Spaces
Laboratories
30-50
75-100
Classrooms
Administration Areas
Exam Rooms
30-50
30-50
50-75
Human Performance
Lab
50-75
Corridors
Storage
10-20
20-30
Mechanical Rooms
Electrical Rooms
Toilets
Exterior
30
30
10-20
1-5
Control Intent
OS
TD with local
override
No automatic
control, Multiple
Levels
OS
OS, Photocell
No automatic
control, Multiple
Levels
No automatic
control, Multiple
Levels
TD
OS
No automatic
control
No automatic
control
TD, OS
Photocell, TD
Table 1: Lighting Levels and Controls (TD = Time of Day; OS=Occupancy Sensor)
U.
Identification: Electrical equipment identification for the following equipment will be
provided (utilizing permanent marker, printed labels, laminated paper).
1.
Raceways
2.
Boxes
3.
Outlet devices, where indicated on plans.
4.
Motor starters and Disconnect Switches
5.
Panel boards
6.
Switchboards
7.
Transformers
8.
Lighting Controllers
9.
Equipment Cabinets (i.e. FACP, Security Panel, etc.)
10.
Emergency Equipment
V.
Raceways: All electrical wiring (120V AC and greater) will be installed in conduit. All
raceway shall include a green grounding conductor. Conduit installation will be as
follows;
Electrical 90% Pre-Design
June 1, 2012
Page 10
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
ballasts will be provided in areas requiring aesthetic lighting effects with-in the
space.
3.51
3.52
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.
2.
3.
4.
5.
6.
Electric Metallic Tubing (EMT): Concealed Indoor
Intermediate Metal Conduit (IMC): Exposed Indoor and Outdoor
Rigid Nonmetallic Conduit (Plastic): Exterior Underground and Below Slab
Flexible Conduit: Where permitted for fixture connections (less than 6 ft.)
Liquid Tight Flexible Conduit: Motor and Transformer Connections.
Inner duct: Textile, 3-cell type installed in Telecommunications backbone and
riser conduit.
W.
Electrical Testing and Commissioning
1.
Performance testing of the equipment and system installation/operation by an
accredited testing firm in conformance with criteria by the International Electrical
Testing Association. Compliance with the standards and associations of the
industry including UL, IEEE, NEMA, NFPA, NBFU, ICEA, ASTM, OSHA, NESC, ANSI,
ETL, NETA, where applicable. The testing firm will be a qualified independent
testing agency.
2.
Electrical Equipment and Systems Tested: Perform test on equipment and
systems listed, tabulate data and submit with equipment submittal (factory) or
acceptance checkout (contractor).
a.
Electrical switchboards: Factory certification.
b.
Electrical equipment including panels, transformers, motor control centers:
Factory certification.
c.
Service and Feeder Cables (600V): Insulation, continuity, short circuits,
grounds, other faults.
d.
Branch circuit wires: Short circuits, grounds, other faults.
e.
Panelboards: Voltage tests after completion of all work.
f.
Grounding: Resistance Fall of potential testing.
g.
Fire Alarm System: Per NFPA.
3.
Electrical Start-up and Commissioning: Electrical system and components shall
be fully functional, operational, and verified by the contractor prior to final
acceptance by Owner
X.
Motor tests shall be recorded and submitted to the Architect/Engineer. Test record shall
include:
1.
Motor Number, Location, HP Rating
2.
Motor circuit protector setting and size
3.
Fuse size
4.
Heater Size
5.
Full load amperes
6.
Running amperes
7.
Rated voltage
8.
Terminal operating voltage
Y.
Training: Owners facility personnel shall be trained in the proper operation of the
electrical systems, minimum of 8 hours.
Z.
Divisions 27 and 28 Raceway and Box Rough-in Requirements: Electrical rough-in shall
be provided for the following systems (cabling/terminations to be provided by the
Division 27 and Division 28 contractors as required below) -
Electrical 90% Pre-Design
June 1, 2012
Page 11
Comm. #0412068
3.0 Project Description
2.
3.
4.
5.
6.
7.
8.
9.
10.
Data, Voice, Video and Security system - A complete empty conduit / rough-in
system and support requirements will be provided for each system.
Raceways for the following systems that are in accessible locations shall have a
manufacturer applied color coding as follows:
a.
Fire Alarm: Red
b.
Telecommunications: Blue
c.
Audio/Visual: Yellow
d.
Security Systems: Green
3/4" minimum conduit will be stubbed into accessible ceiling space for each
voice, video, and security system outlet device. Non-metallic thread-less
insulating bushing on the end of all conduits will be provided.
1” minimum conduit will be stubbed into accessible ceiling space for each data
information outlet device. Non-metallic thread-less insulating bushing on the
end of all conduits will be provided.
Cable Tray: 8”Wx2”D Basket Tray will be provided throughout the building for
routing of special system cabling. Cable tray systems will be provided for all data,
voice, and video cabling. Ladder type cable tray will be provided in the main
telecommunication equipment room.
Raceways 2-inch and smaller inside the buildings will not exceed 150 feet in
length. All raceways installed will not contain more than two 90 degree bends or
the equivalent. Pull boxes or junction boxes will be provided as necessary to
comply with these requirements.
Bends in conduits will be long sweep radius bends and in no instance will the
inside radius of bends be less than ten times the internal diameter for all conduit
sizes.
Plywood mounting boards will be provided in all Telecommunication Closets,
minimum 3/4" thick AC plywood. Paint all mounting boards on the smooth side
with two coats gray alkyd enamel.
A complete telecommunication grounding system complying with ANSI/EIA/TIA
607 will be provided. Equipment grounding connections will be provided at all
equipment terminal systems and mounting boards.
All device outlet boxes will be minimum 4" square x 2-1/2" deep, with single or
two gang plaster ring and blank cover plate.
VIII. BUILDING COMMISSIONING:
A.
Commissioning of building electrical system will be implemented at the design
development phase, and continued through construction completion.
IX. B3 MINNESOTA SUSTAINABLE BUILDING GUIDELINES:
B.
The design will comply with State of Minnesota B3 Requirements and will utilize
sustainable concepts where applicable. Some of the sustainable concepts for electrical
include:
1.
Lighting control systems (occupancy sensors, daylight harvesting, time sweep
control)
2.
Energy efficient lamp/ballast combinations
3.
A renewable energy study will be done as follows:
Electrical 90% Pre-Design
June 1, 2012
Page 12
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.
3.53
3.54
3.0 Project Description
4.
a.
Photovoltaic – Building Integrated, Roof Mounted, Ground Mounted
b.
Wind Turbine
Recycling of demolished electrical equipment, devices, and cabling.
X. ELECTRICAL, COMMUNICATION, AND ELECTRONIC SAFETY AND SECURITY SPACE
DESIGN CRITERIA:
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.
2.
3.
Commons /Administration area will be designed to have recessed and/or
suspended linear LED fixtures (dimming drivers) for general lighting, along with
task and decorative lighting fixtures for select areas utilizing LED or low voltage
incandescent lamp sources. Lighting will be controlled on an individual fixture
basis utilizing addressable ballast controllers or drivers. General power
receptacles will be provided in the space for cleaning equipment, and workstation
power receptacles will be provided for designated locations throughout the
space. In conjunction with the workstation power, SCSU LAN network receptacles
and wireless access points will be located to provide network connections.
Accommodations will be provided for a wall mounted LCD monitor(s) which will
show the Campus digital signage channel, and also provide the capability of
showing building local information. Life safety devices will consist of ceiling
mounted smoke detectors and speaker/strobes.
Gathering/Entry area will be designed to have recessed and/or suspended linear
LED fixtures (dimming drivers) for general lighting, along with task and decorative
lighting fixtures for select areas utilizing LED or low voltage incandescent lamp
sources. Lighting will be controlled on an individual fixture basis utilizing
addressable ballast controllers or drivers. General power receptacles will be
provided in the space for cleaning equipment, and workstation power receptacles
will be provided for designated locations throughout the space. In conjunction
with the workstation power, SCSU LAN network receptacles and wireless access
points will be located to provide network connections. Accommodations will be
provided for a wall mounted LCD monitor(s) which will show the Campus digital
signage channel, and also provide the capability of showing building local
information. There will also be designated self-care health kiosks which will
incorporate touchscreen capabilities, access to local health service information
and connection to web services, and the ability to tie into the Campus Digital
Signage and Scheduling System. The reception area will also be the building’s
security check point, with access control on the vestibule doors and video
surveillance cameras watching entry points and SCSU designated locations. Life
safety devices will consist of ceiling mounted smoke detectors and
speaker/strobes, and a wall mounted Fire Alarm Annunciator that should be
located near the entry door.
Student Health Services will be designed to have linear LED light fixture(s) with
dimmable driver, controlled by a wall mounted occupancy sensor with manual
override/dimming control. Each room will receive new electrical and
communication outlets to accommodate a computer/monitor, phone, and
miscellaneous equipment as directed by Health Services. A basic electronic Nurse
Call system will be designed for notification and scheduling of exam rooms to
help efficiency of the space. Life safety will be accomplished with a ceiling
mounted system connected smoke detector for smoke detection within the space
and ceiling mounted speaker/strobe for annunciation of fire alarm.
Electrical 90% Pre-Design
June 1, 2012
Page 13
Comm. #0412068
3.0 Project Description
5.
6.
7.
8.
Counseling Services area will be designed to have recessed and/or suspended
linear LED fixtures (dimming drivers) for general lighting, along with task lighting
fixtures for select areas utilizing LED or low voltage incandescent lamp sources.
Lighting will be controlled on an individual fixture basis utilizing dimmable
drivers. General power receptacles will be provided in the space for cleaning
equipment, and workstation power receptacles will be provided for designated
locations throughout the space. In conjunction with the workstation power, SCSU
LAN network receptacles and wireless access points will be located to provide
network connections. Life safety devices will consist of ceiling mounted smoke
detectors and speaker/strobes.
The U-Choose, Health Education, and Human Performance will be designed to
have recessed and/or suspended linear LED fixtures (dimming drivers) for general
lighting. Lighting will be controlled with ceiling mounted occupancy sensors,
manual push buttons, daylight harvest sensors, and Audio Visual touchscreen
interfaces. Power and communication cabling will be provided to accommodate
designated locations and for flexibility of the space. The rooms will be set up for
audio visual accommodations including large format screens, touchscreen
interfaces, sound reinforcement, and future interactive white boards. The entry
door will be designed with access control to safeguard the equipment that will be
located in the space. To meet life safety codes, a system connected ceiling
mounted smoke detector and speaker strobe for smoke detection and
annunciation within the space.
Conference Rooms will be designed to have recessed and/or suspended linear
LED fixtures (dimming drivers) for general lighting. Lighting will be controlled
with ceiling mounted occupancy sensors, manual push buttons, daylight harvest
sensors, and Audio Visual touchscreen interfaces. Power and communication
cabling will be a combination of wall mounted receptacles and floor mounted
poke-thru. The rooms will be set up for audio visual accommodations including
large format screens, touchscreen interfaces, sound reinforcement, and future
interactive white boards. To meet life safety codes, a system connected ceiling
mounted smoke detector and speaker strobe for smoke detection and
annunciation within the space.
Corridors will be designed to have recessed mounted linear LED light fixtures
that will be 12’-0” on center the length of the corridor. Each fixture will have
dimmable drivers, controlled by time of day schedule with ceiling mounted
occupancy sensors for automatic overrides. Lighting will be dimmed to 20%
levels during scheduled night hours for energy conservation. Power circuiting will
be routed in conduits above the new accessible ceiling that will be installed,
along with a new basket cabletray for communication cabling and the fire alarm
system conduit. Each corridor will be designed to have general receptacles
spaced no more than 50’-0” on center to accommodate 25’-0” equipment cords
(i.e. vacuums) and wireless access points for students access to the SCSU LAN
network (with devices spaced approximately 50’-0” on center). To meet life safety
codes, system connected smoke detectors will be ceiling mounted in conjunction
with ceiling mounted speaker/strobes.
Restrooms will be designed to have surface mounted linear LED fixtures with
dimmable drivers controlled by time of day schedule with ceiling mounted
occupancy sensors for automatic overrides. Lighting will be dimmed to 20%
Electrical 90% Pre-Design
June 1, 2012
Page 14
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
4.
3.55
3.56
3.0 Project Description
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
9.
10.
11.
12.
levels during scheduled night hours for energy conservation and be conducive to
sleeping accommodations. General power receptacles will be provided near the
sink/mirror locations for student use, and power will be provided to automatic
faucet and urinal sensors for water conservation. To meet life safety codes, a
system connected heat detector and strobe unit ceiling mounted for fire
detection and annunciation within the space.
Electrical Service Entrance rooms will be designed to accommodate a floor
mounted Suitable for Use as Service Entrance switchboard with main circuit
breaker/metering section and circuit breaker distribution sections, wall mounted
branch circuit panelboards, floor mounted automatic transfer switches (life safety
and option standby), and floor mounted transformer. Lighting in the space will
be industrial linear fluorescent strip fixtures with symmetric reflectors and two T8
lamps, controlled by a wall mounted toggle switch. Communication cabling will
be provided to selected pieces of equipment for remote monitoring of
information. Life safety will be accomplished with a ceiling mounted system
connected smoke detector and wall mounted speaker/strobe unit for smoke
detection and annunciation within the space.
Electrical Secondary rooms will be designed to accommodate wall mounted
branch circuit panelboards. Lighting in the space will be industrial linear
fluorescent strip fixtures reflectors and two T8 lamps, controlled by a wall
mounted toggle switch. Communication cabling will be provided to selected
pieces of equipment for remote monitoring of information.
Communication Equipment room will be designed to have industrial linear
fluorescent strip fixtures with symmetric reflectors and two T8 lamps, controlled
by a wall mounted toggle switch. The space will be designed to accommodate
two rows of equipment racks and/or cabinets, interconnected with cabletray
mounted overhead. An in-row UPS cabinet will be provided for powering all
equipment, with the Campus LAN/WAN terminating in the space. Life safety will
be accomplished with a ceiling mounted system connected smoke detector and
wall mounted speaker/strobe unit for smoke detection and annunciation within
the space.
Communication Secondary rooms will be designed to accommodate a floor
mounted two post rack for communication equipment and cabling. Lighting in
the space will be industrial linear fluorescent strip fixtures reflectors and two T8
lamps, controlled by a wall mounted toggle switch. Dedicated power receptacles
will be mounted on the ceiling hung cable tray in the room, with general
receptacles wall mounted on the back wall of the space. Life safety will be
accomplished with a ceiling mounted system connected smoke detector for
smoke detection within the space.
Appendix A: Tier 1Electrical Load Estimate
Area
Connected Power
Total Power
2
2
Load Type
(ft )
Density (w/ft )
(w)
Common Area/Administration
Lighting - General
Emergency -
Electrical 90% Pre-Design
June 1, 2012
9,705
9,705
1.0
0.1
Page 15
9,705
970
Comm. #0412068
3.0 Project Description
9,705
9,705
9,705
1.5
0.5
2.0
14,557
4,852
19,409
11,245
1.2
13,494
11,245
11,245
11,245
11,245
0.1
2.0
1.0
2.0
1,125
22,490
11,245
22,490
5,164
1.0
5,164
5,164
5,164
5,164
5,164
0.1
1.5
0.5
2.0
516
7,746
2,582
10,328
3,406
1.2
4,087
3,406
3,406
3,406
3,406
0.1
1.5
1.0
2.0
341
5,109
3,406
6,812
0
1.2
0
0
0
0
0
0.1
1.5
1.0
2.0
0
0
0
0
12,066
0.8
9,653
12,066
12,066
12,066
12,066
0.1
0.5
0.5
2.0
1,207
6,033
6,033
24,132
Air Handling
Equip
Pumps
29,519
29,519
5.0
2.0
147,596
59,039
Service Entrance
420,118
Service Entrance Total:
420,118
Student Health Services
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Counseling Services
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
U-Choose and Health Education
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Human Performance Center
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Existing Building and Support Spaces
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Lighting
Receptacles
Electronic Equip.
Miscellaneous
3.57
Mechanical
Electrical 90% Pre-Design
June 1, 2012
Page 16
Comm. #0412068
3.58
3.0 Project Description
Total:
Service Entrance
Amps (@480V):
Service Entrance Amps
(@208V):
505
1,166
Appendix B: Tier 2 Electrical Load Estimate
Area
Connected Power
Total Power
2
2
Load Type
(ft )
Density (w/ft )
(w)
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Common Area/Administration
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
11,369
1.0
11,369
11,369
11,369
11,369
11,369
0.1
1.5
0.5
2.0
1,137
17,053
5,684
22,737
14,384
1.2
17,261
14,384
14,384
14,384
14,384
0.1
2.0
1.0
2.0
1,438
28,768
14,384
28,768
6,467
1.0
6,467
6,467
6,467
6,467
6,467
0.1
1.5
0.5
2.0
647
9,700
3,233
12,933
4,732
1.2
5,678
4,732
4,732
4,732
4,732
0.1
1.5
1.0
2.0
473
7,098
4,732
9,464
4,128
1.2
4,954
4,128
4,128
4,128
4,128
0.1
1.5
1.0
2.0
413
6,192
4,128
8,256
Student Health Services
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Counseling Services
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
U-Choose and Health Education
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Human Performance Center
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Electrical 90% Pre-Design
June 1, 2012
Page 17
Comm. #0412068
3.0 Project Description
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
0.8
0
0.1
0.5
0.5
2.0
0
0
0
0
5.0
2.0
205,398
82,159
Mechanical
Air Handling
Equip
Pumps
41,080
41,080
Service Entrance
Total:
Service Entrance
Amps (@480V):
520,525
626
Service Entrance
Total:
Service Entrance
Amps (@208V):
520,525
1,445
Appendix C: Tier 3 Electrical Load Estimate
Area
Connected Power
Total Power
2
2
Load Type
(ft )
Density (w/ft )
(w)
Common Area/Administration
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
12,058
1.0
12,058
12,058
12,058
12,058
12,058
0.1
1.5
0.5
2.0
1,206
18,086
6,029
24,115
17,183
1.2
20,620
17,183
17,183
17,183
17,183
0.1
2.0
1.0
2.0
1,718
34,366
17,183
34,366
8,026
1.0
8,026
8,026
8,026
8,026
8,026
0.1
1.5
0.5
2.0
803
12,039
4,013
16,052
1.2
6,302
Student Health Services
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Existing Building and Support Spaces
3.59
Counseling Services
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
U-Choose and Health Education
Lighting - General
Electrical 90% Pre-Design
June 1, 2012
5,252
Page 18
Comm. #0412068
3.60
3.0 Project Description
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
5,252
5,252
5,252
5,252
0.1
1.5
1.0
2.0
525
7,878
5,252
10,504
4,128
1.2
4,954
4,128
4,128
4,128
4,128
0.1
1.5
1.0
2.0
413
6,192
4,128
8,256
0.8
0
0.1
0.5
0.5
2.0
0
0
0
0
5.0
2.0
233,231
93,293
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Human Performance Center
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Existing Building and Support Spaces
Lighting - General
Emergency Lighting
Receptacles
Electronic Equip.
Miscellaneous
Mechanical
Air Handling
Equip
Pumps
Service Entrance
Total:
Service Entrance
Amps (@480V):
46,646
46,646
591,605
712
Service Entrance
Total:
Service Entrance
Amps (@208V):
591,605
1,642
THIS PAGE LEFT INTENTIONALLY BLANK
Electrical 90% Pre-Design
June 1, 2012
Page 19
Comm. #0412068
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
4.0
Sustainability
4.2
4.0 Sustainability
Renovation of Eastman Hall for Student Health Related Services
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
St. Cloud State University
St. Cloud, MN
Pre-Design Energy Report
October 5, 2012
Commission Number
0412067-000-00
4.0 Sustainability
St. Cloud State University is renovating and infilling Eastman Hall on its campus in St. Cloud, MN. The project is
currently in the Pre-Design stage and its programing will include Student Health Services, Counseling &
Psychological Services, U Choose / Health Education, Human Performance Lab, and a Pharmacy.
The project will tie into the campus chilled water and steam systems for cooling and heating needs. The project
will be served by Xcel Energy for electric service. The specific rates will be researched in schematic design.
Project Objectives
This project will need to adhere to the MN commercial energy code and since the renovation scope includes
replacement of the air side mechanical systems, the project is considered a “Major Renovation” and will need to
adhere to the MN Sustainable Building Design Guidelines (MSBG) including Sustainable Buildings 2030
(SB2030). The State of Minnesota design guidelines require that where practicable, designers consider the use
of geothermal and solar heating and cooling systems. This project currently connects to campus steam and
geothermal is not practicable for this site. The most recent state bonding bill requires bonded projects consider
Minnesota made photovoltaic panels.
SCSU Eastman Hall Renovation
Pre-Design Energy Report
DUNHAM
October 5, 2012
Page 1
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Project Background
4.3
4.4
4.0 Sustainability
Energy Use
Energy Use Objectives
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
The state of MN commercial energy code (an amended version of ASHRAE 90.1-2004) has primarily
prescriptive requirements for certain components, such as roof conductance or lighting power density. These
prescriptive criteria are generally readily achievable for both new construction and renovation.
SB 2030 is an entirely different approach as its sets an energy use intensity target for each building using one of
two tools: an interim target spreadsheet or a web tool available through the MSBG tracking website. The
building is perhaps most akin to a medical office building but that building type is not available in either tool.
The web tool was utilized by entering a typical 56,000 gsf office with 4 floors, remodeled construction, and
district heating and cooling. Then 2,800 gsf of the lab space type was added to represent the Health Services
lab & radiology and the lab, workshop, and testing areas of the Human Performance Lab. The office and lab
areas combine for 58,800 total gsf. The following screen capture shows the resulting energy standard of 185
kBtu/ft2/yr and 45 lbs CO2e/ft2/yr.
SCSU Eastman Hall Renovation
Pre-Design Energy Report
DUNHAM
October 5, 2012
Page 2
4.0 Sustainability
To satisfy both the process and outcome criteria, detailed energy modeling will be performed starting at the
schematic design phase and continued through the remaining phases of the design. A simple pre-design
energy model was simulated in eQUEST to gauge anticipated annual energy consumption, energy costs and
related greenhouse for the pre-design and to confirm a trajectory of achieving the SB2030 energy and
greenhouse gas emission targets. The TMY3 (typical meteorological year) weather file from St. Cloud Regional
Airport was used for this analysis. Mechanically, the modeling included the use of multiple variable air volume
(VAV) air handling units with terminal VAV reheat boxes and perimeter baseboard radiators. Heating water
will be from a heat exchanger with the campus steam and cooling will be by campus chilled water. Additional
energy conservation measures such as daylighting, reduced power lighting design, and outdoor air load
reduction strategies were represented as broad schematic inputs to the model.
The following three charts show the modeled annual energy costs, site energy consumption and greenhouse
gas emissions for the pre-design model. Regarding the SB2030 targets, the pre-design model shows the
potential to meet both the site energy use intensity target and the greenhouse gas (CO2e) emissions target.
The completion of design, construction and the operation of the building will determine the ultimate building
performance.
SCSU Eastman Hall Renovation
Pre-Design Energy Report
DUNHAM
October 5, 2012
Page 3
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Energy Modeling
4.5
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
4.6
4.0 Sustainability
CO2e is an abbreviation of 'carbon dioxide equivalent' and is the internationally recognized measure of
greenhouse emissions.
SCSU Eastman Hall Renovation
Pre-Design Energy Report
DUNHAM
October 5, 2012
Page 4
4.0 Sustainability
Renewable Energy Objectives
The Minnesota Sustainable Building Guidelines require the evaluation of the two renewable (wind or solar)
scenarios to provide 2% of the building’s anticipated total energy usage. The State of Minnesota design
guidelines require inclusion of an alternative energy source to provide 2% of the project’s energy use.
Based upon on the modeled energy use target of 137 kBtu/sf that equates to about 3 kBtu/sf. At 58,800 gross
square foot, this equates to 176 million Btus of energy or 52,000 kWh of electricity. Solar domestic hot water
and photovoltaic panel alternatives to meet this renewable energy target are evaluated in the following sections.
Solar Domestic Hot Water Analysis
At the schematic phase, the anticipated domestic hot water load is approximately 400 gallons per day,
resulting in an annual thermal load of about 90 million Btus. Assuming the heating is done by campus steam
with a total system efficiency of 50%, the resulting natural gas consumption of 1824 therms at a cost of roughly
$1368 annually.
Based on RETscreen analysis, a schematic solar DHW system consisting of (4) 80 sf panels and a 600 gallon
storage tank would reduce the annual natural gas consumption to about 572 therms at an annual cost of $429.
At an estimated initial cost of $45,000 and $938 savings per year the simple payback is about 48 years. This
payback exceeds the anticipated life of the system components (panels, pump, and controller).
Since the anticipated annual domestic hot water consumption is relatively small, another renewable energy
technology may also need to be implemented to satisfy the 2% renewable energy objective.
Photovoltaic Panels Analysis
Based on the PV Watts screening tool a 40 kW photovoltaic array mounted at a 40 degree angle in St. Cloud,
MN would produce approximately 51,000 kWh annually. This generation would very nearly satisfy the 2%
renewable target. This generation would save approximately $4,000 annually in utility costs. The cost to
install PV typically starts at $5,000 per kW and increases with site specific mounting and structural concerns.
Assuming no complexities, this system would cost $200,000 and have a payback of 50 years which exceeds
the anticipated life of the system components. This schematic analysis of PV is appropriate for panels made in
MN or elsewhere.
Renewable energy systems rarely directly pay for themselves. To see a positive return, renewable projects need
to identify value in other benefits and/or access some of the ever changing financial incentives. The most
common types of incentives are utility rebates and preferential tax treatment. However, per Minnesota Statute
16B.323 this project is ineligible to receive a utility rebate for PV and no preferential tax treatment would apply
to renewable energy systems owned by a government entity.
Other government and non-profit entities have explored agreements to lease roof area to a private party. The
private party purchases the photovoltaic panels, receives the advantageous tax treatment, and the sells the
generated electricity back to the building owner under a power purchasing agreement. Such an arrangement
would be outside the scope of the project design with exception of some electrical infrastructure to
accommodate future onsite renewable energy generation.
SCSU Eastman Hall Renovation
Pre-Design Energy Report
DUNHAM
October 5, 2012
Page 5
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
Renewable Energy
4.7
This page was left blank intentionally.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
5.0
financial information – capital expenditures
0
101
0
9,666
29
300
967
11,063
98
98
1,281
98
98
1,477
Feb-2016
0.20
2,803
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
38
GRAND TOTAL (rounded up to next $1000)
Revised 10/29/2012
PROJECT COST
16,889
0
0
0
0
132
330
55
98
615
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
SUBTOTAL
4. Project Management (6-8% constr. costs)
4a) State Staff Project Management (.8% total project cost)
4b) Nonstate Construction Management (2-3% total project)
4c) Commissioning (.5% of construction cost)
4d) Testing/Quality Assurance (1% construction cost)
SUBTOTAL
5. Construction Costs
5a) Site and Building Preparation
5b) Demolition/Decommissioning
5c) Construction (consistent with project construction total)
5d) Infrastructure/Roads/Utilities
5e) Hazardous Materials Abatement
5f) Construction Contingency (6-10% of construction 5c)
SUBTOTAL
6. Art (1% of construction or a maximum of $100 k)
SUBTOTAL
7. Occupancy (4-10% of construction 5c)
7a) Furniture, Fixtures and Equipment (4-8% of construction)
7b) Telecommunications - Voice & Data (1% of construction)
7c) Security Equipment (1% of construction)
SUBTOTAL
8. Inflation
8a) Mid Point of Construction (mo/yr)
8b) Multipler (2012 CPMI Building Projects Inflation Schedule)
8c) Inflation Cost
9. Other (explain)
SUBTOTAL
167
208
250
208
833
SUBTOTAL
0
0
0
0
0
3. Design Fees (7-10% of construction costs)
3a) Schematics (20% of design fee)
3b) Design Development (25% of design fee)
3c) Contract Documents (30% of design fee)
3d) Construction Administration (25% of design fee)
2. Pre Design (.5% of total project cost)
0
0
0
0
0
0
0
0
0
0
Project Cost Project Cost Project Cost
All Prior Years FY 2014-15 FY 2016-17
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Project Cost
FY 2018-19
AGENCY CAPITAL BUDGET REQUEST
Fiscal Years 2014-19
Dollars in thousands (e.g. $137,500 = $138 thousand)
0
0
0
38
38
TOTAL PROJECT COSTS
All Years and All Funding Sources
1. Property Acquisition
1a) Land, Land and Easements Options
1b) Buildings and Land
Project Name: Renovation of Eastman Hall
for Student Health Related Services
1
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
16,927
0
1,281
98
98
1,477
101
0
9,666
29
300
967
11,063
98
98
132
330
55
98
615
167
208
250
208
833
0
0
0
38
38
Project Cost
All years
Aug-2016
Aug-2016
Aug-2016
Aug-2016
Sep-2015
Jan-2016
Jan-2016
Jan-2016
Aug-2016
Aug-2016
Oct-2014
Mar-2015
Aug-2015
Aug-2016
Sep-2012
Project Finish
Finish (mo/yr)
Sep-2015
Aug-2014
Aug-2014
Jan-2015
May-2015
Sep-2015
Aug-2011
Project Start
Start (mo/yr)
5.2
5.0 Financial Information
0
0
0
9,982
5,580
0
0
0
0
0
0
0
0
0
0
0
0
0
Clinic
Lab
Radiology
Counseling
Health Education/U Choose
Human Poerformance lab
Mechanical/Electrical
Revised 10/29/2012
0
0
Building support
15,562
0
0
Pharmacy
0
0
0
Gathering/café/retail
0
0
0
0
150
175
0
0
0
0
0
0
0
43,291
0
0
5,931
5,159
985
-
2,151
2,499
15,247
2,389
1,901
2,438
4,591
PROJECT CONSTRUCTION
$2,584
0
0
0
0
$837
$1,747
0
0
0
0
0
0
0
RENEWAL
$7,082
0
0
$9,666
0
0
0
0
0
$474
$800
$970
$1,747
$581
$575
$2,744
$275
$303
$463
$735
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
TOTAL
COST
(in $000)
0
0
0
80
155
135
-
270
230
180
115
160
190
160
Cost Per
Sq. Foot
(in $)
0
0
0
$474
$800
$133
0
$581
$575
$2,744
$275
$303
$463
$735
Cost Per
Gross
Cost
Cost
Gross
Sq. Foot
Sq. Feet (in $000)
Sq. Feet (in $000)
(in $)
RENOVATION
PROJECT CONSTRUCTION
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
TOTAL
0
0
Cost Per
Sq. Foot
(in $)
NEW CONSTRUCTION
Gross Sq. Gross Sq.
Cost
Feet
Feet
(in $000)
EXISTING
AGENCY CAPITAL BUDGET REQUEST
Fiscal Years 2014-19
Dollars in thousands (e.g. $137,500 = $138 thousand)
Common area
List Major Type of Space
(class, office, Lab, mech., etc.)
CONSTRUCTION TYPE OF SPACE
Project Name: Renovation of Eastman Hall
for Student Health Related Services
3
5.0 Financial Information
5.3
TOTAL
Revised 10/29/2012
Other: specify
Financial Services
Mining and Natural
Resources
Agriculture
Transportation and
Trades
Energy
Healthcare/Allied Health
Engineering/advanced
technology
Manufacturing
Information Technology
TYPE OF SPACE Workforce Alignment
15,562
15,562
New
Construction
43,291
43,291
Renovation
0
0
Renewal
$
2,584
2,584 $
7,082
7,082
Renovated
WORKFORCE ALIGNMENT
58,853
58,853
TOTAL
Gross
Square Feet
New
Impacted Construction
$
0
-
Renewal
PROJECT CONSTRUCTION COST
($000)
AGENCY CAPITAL BUDGET REQUEST
Fiscal Years 2014-19
Dollars in thousands (e.g. $137,500 = $138 thousand)
GROSS SQUARE FEET IMPACTED
Project Name: Renovation of Eastman Hall
for Student Health Related Services
4
$
7,261
7,261
(Costs for everything on
"Project Cost" spreadsheet
except 5a-5e)
$
16,927
TOTAL COST
0
0
0
0
0
0
0
0
0
16,927
WORKFORCE ALIGNMENT
OTHER PROJECT
COST
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
5.4
5.0 Financial Information
5.0 Financial Information
St. Cloud State University Eastman Hall
Pre-Design Estimate
St. Cloud, MN
90% Pre-Design Cost Estimate
INTRODUCTION
Project Description
In brief, the project consists of renovations to the St. Cloud State University Eastman Hall in St. Cloud, MN. Scope of work includes creating a new
interstitial level at Level 3 of the Upper Gymnasium, raising +/-4,000sf of floor elevation on Level 1 at the pool area and complete demo and
renovation to 4-Levels of the existing structure.
This document is based on the measurement and pricing of quantities wherever information is provided and/or reasonable assumptions for other
work not covered in the drawings and programs as stated in this document.
Basis of Pricing
Pricing shown reflects probable construction costs obtainable in the St. Cloud, MN, area on the date of this statement of probable costs. This
estimate is a determination of fair market value for the construction of this project. It is not a predication of low bid. Pricing assumes competitive
bidding for every portion of the construction work for all subcontractors, that is to mean 4 to 5 bids. If fewer bids are received, bid results can be
expected to be higher.
Subcontractor’s markups have been included in each line item unit price. These markups cover the cost of field overhead, home office overhead,
and profit. These markups can range from 5% to 15% of the cost for that particular item of work. The rates that have been established are for
budgetary purposes only and are not to be used to establish the cost of additions or deletions to the scope of work that may arise during the actual
construction process.
General Contractors General Conditions, Overhead and Profit are calculated at 15%
Documentations
Faithful+Gould received the following documents for the this cost estimate:
Pre-design package- dated October 2011
As-built drawings- dated September 1929
Various site photos taken by BWBR
Soil Solidification Grouting- lump sum budget provided by Veit & Company, Inc. Dated- March 8th, 2012
Design Contingency
A 15% conceptual/estimating contingency has been included in the estimate. This contingency should reduce to zero at bid stage, but the monies
identified are likely to be absorbed in the detail "above-the-line".
Escalation
Escalation has been calculated based upon the mid-point of construction being January 2017. From the date of estimate, May 2012, until the midpoint of construction we have added 16.3% based upon the MN DOF 2011-2012 Escalation factors
Items excluded from the Cost Estimate
Legal and accounting fees
Design, engineering and consultant fees
Testing and inspection
Fire and all risk insurance
Owner's contingency
Hazardous material mitigation
Loose furniture, fittings and equipment (FF&E)
Moving costs
Medical equipment
Head IT equipment
Audio/visual equipment
Any additional structural modifications to existing structure to support new floor levels.
6/12/2012
Intro Notes
2
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
12-Jun-12
5.5
5.6
5.0 Financial Information
12-Jun-12
St. Cloud State University Eastman Hall
Pre-Design Estimate
St. Cloud, MN
90% Pre-Design Cost Estimate
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
INTRODUCTION
Items that may affect the cost estimate
Modifications to the scope of work included in this estimate.
Unforeseen sub-surface conditions.
Special phasing requirements.
Restrictive technical specifications or excessive contract conditions.
Any other non-competitive bid situations.
Bids delayed beyond the projected schedule.
Statements of Probable Cost
Faithful+Gould has no control over the cost of labor and materials, general contractor’s or any subcontractor’s method of determining prices, or
competitive bidding and market conditions. This opinion of probable cost of construction is made on the basis of the experience, qualifications, and
best judgment of the professional consultant familiar with the construction industry. Faithful+Gould cannot and does not guarantee that proposals,
bids, or actual construction costs will not vary from this or subsequent cost estimates.
Faithful+Gould has prepared this estimate in accordance with generally accepted principles and practices. This staff is available to discuss its
contents with interested personnel.
Recommendation for Cost Control
Faithful+Gould. recommends that the Owner carefully review this document, including line item descriptions, unit prices, clarifications, exclusions,
inclusions and assumptions,
assumptions contingencies,
contingencies escalation and markups.
markups If the project is over budget
budget, or if there are unresolved budgeting issues
issues,
alternate systems schemes should be evaluated before proceeding into the design phase.
Requests for modifications of any apparent errors or omissions to this document must be made to Faithful+Gould within ten (10) days of receipt of
this estimate. Otherwise, it will be understood that the contents have been concurred with and accepted.
6/12/2012
Intro Notes
3
5.0 Financial Information
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
GFA
CONSTRUCTION COST SUMMARY
SYSTEM DESCRIPTION
54,315
TOTAL
A10
A20
FOUNDATIONS
BASEMENT CONSTRUCTION
$228,390
$0
B10
B20
B30
SUPERSTRUCTURE
EXTERIOR CLOSURE
ROOFING
$516,582
$428,840
$0
C10
C20
C30
INTERIOR CONSTRUCTION
STAIRCASES
INTERIOR FINISHES
$1,030,325
$85,000
$814,725
D10
D20
D30
D40
D50
CONVEYING SYSTEMS
PLUMBING
HVAC
FIRE PROTECTION
ELECTRICAL
$300,000
$488,835
$2,206,934
$217,260
$1
$1,569,704
569 704
E10
E20
EQUIPMENT
FURNISHINGS
F10
F20
SPECIAL CONSTRUCTION
SELECTIVE BUILDING DEMOLITION
G10
G20
G30
SITE PREPARATION
SITE IMPROVEMENT
SITE UTILITIES
TOTAL DIRECT COST (Trade Costs)
MARK UP
GENERAL CONDITIONS
$0
$65,000
$40,000
$398,680
$2,500
$85,000
$25,000
$8,502,774
$1,275,416
SUBTOTAL CONSTRUCTION
$9,778,190
CONTINGENCIES/ESCALATION
DESIGN & PRICING CONTINGENCY
ESCALATION
$1,466,728
$1,832,922
TOTAL CONSTRUCTION COST
$13,077,840
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
12-Jun-12
5.7
5.8
5.0 Financial Information
12-Jun-12
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
CONSTRUCTION COST SUMMARY
SYSTEMS DESCRIPTION
GFA
54,315
SUB-TOTAL
TOTAL
$/SF
%
A10
FOUNDATIONS
A1030
Lowest Floor Construction
$146,600
$228,390
$4.20
1.7%
B10
SUPERSTRUCTURE
B1010
Upper Floor Construction
$516,582
$516,582
$9.51
4.0%
B20
EXTERIOR CLOSURE
B2010
Exterior Walls
B2020
Windows
B2030
Exterior Doors
$15,000
$392,840
$21,000
$428,840
$7.90
3.3%
C10
INTERIOR CONSTRUCTION
C1010
Interior Construction
$1,030,325
$1,030,325
$18.97
7.9%
C20
STAIRCASES
C1020
Stair Construction
C2020
Stair Finishes
$45,000
$40,000
$85,000
$1.56
0.6%
C30
INTERIOR FINISHES
C3010
Interior Finishes
$814,725
$814,725
$15.00
6.2%
D10
CONVEYING SYSTEMS
D1010
Elevator
$300,000
$300,000
$5.52
2.3%
D20
PLUMBING
D20
Plumbing
$488,835
$488,835
$9.00
3.7%
D30
HVAC
D30
$2,206,934
$2,206,934
$40.63
16.9%
D40
FIRE PROTECTION
D40
Fire Protection
$217,260
$217,260
$4.00
1.7%
D50
ELECTRICAL
D5010
Service & Distribution
D5020
Lighting & Power
D5030
Communication & Security Systems
D5040
Other Electrical Systems
$551,297
$515,993
$339,469
$162,945
$1,569,704
$28.90
12.0%
HVAC
E10
EQUIPMENT
E10
Equipment, generally
$0
$0
$0.00
0.0%
E20
FURNISHINGS
E2010
Fixed Furnishings
E2020
Movable Furnishings
$65,000
NIC
$65,000
$1.20
0.5%
F10
SPECIAL CONSTRUCTION
F10
Special Construction
$40,000
$40,000
$0.74
0.3%
F20
SELECTIVE BUILDING DEMOLITION
F2010
Building Elements Demolition
$398,680
$398,680
$7.34
3.0%
G10
SITE PREPARATION
G1010
Site Preparation
$2,500
$2,500
$0.05
0.0%
G20
SITE IMPROVEMENT
G2030
Site Improvements
$85,000
$85,000
$1.56
0.6%
G30
SITE MECHANICAL UTILITIES
G3050
Cooling Distribution
$25,000
$25,000
$0.46
0.2%
$8,502,774
$156.55
65.0%
TOTAL DIRECT COST (Trade Costs)
5.0 Financial Information
90% Pre-Design Cost Estimate
GFA
CONSTRUCTION COST SUMMARY
SYSTEMS DESCRIPTION
MARK UP
GCs/OH&P/Permits
SUB-TOTAL
15%
$1,275,416
SUBTOTAL CONSTRUCTION
CONTINGENCIES/ESCALATION
15.0%
Design & Pricing Contingency
Escalation (to mid-point of construction 16.3%
TOTAL PROJECT COST
$1,466,728
$1,832,922
54,315
TOTAL
$/SF
%
$1,275,416
$23.48
9.8%
$9,778,190
$180.03
74.8%
$3,299,650
$13,077,840
25.2%
$240.78
100.0%
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
12-Jun-12
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
5.9
5.10
5.0 Financial Information
12-Jun-12
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
DESCRIPTION
A10
A1010
GFA
QTY
UNIT
UNIT
EST'D
SUB
TOTAL
COST
COST
TOTAL
COST
FOUNDATIONS
STANDARD FOUNDATIONS
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
SUBTOTAL
A1020
$
-
$
81,790
$
146,600
SPECIAL FOUNDATIONS
Soil solidification grouting- (lump sum by Veit & Co.)
1
ls
$
81,790.00 $
81,790
SUBTOTAL
A1030
54,315
LOWEST FLOOR CONSTRUCTION
Infill at Pool and viewing deck area at Level 1; steel structure and
composite floor system.
Structural steel; assumes existing columns can support new structure
24
ton
$
4,500.00 $
Metal deck
4,000
sf
$
3.65 $
108,000
14,600
CIP floor slab
4,000
sf
$
6.00 $
24,000
SUBTOTAL
TOTAL - FOUNDATIONS
A20
A2010
$228,390
BASEMENT CONSTRUCTION
BASEMENT EXCAVATION
SUBTOTAL
A2020
$
-
$
-
BASEMENT WALLS
SUBTOTAL
TOTAL - BASEMENT CONSTRUCTION
B10
B1010
$0
SUPERSTRUCTURE
UPPER FLOOR CONSTRUCTION
Create new interstitial level at Upper Gymnasium
Structural steel; assumes existing columns can support new structure
$
76
$
4,500.00 $
343,737
Metal deck
12,730
sf
$
3.65 $
46,465
CIP floor slab
12,730
sf
$
6.00 $
76,380
1
allow
$
50,000.00 $
50,000
Allowance to reinforce existing columns
SUBTOTAL
B1020
ton
$
516,582
ROOF CONSTRUCTION
SUBTOTAL
$
-
TOTAL - SUPERSTRUCTURE
B20
$516,582
EXTERIOR CLOSURE
6/12/2012
backup
7
5.0 Financial Information
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
DESCRIPTION
B2010
GFA
QTY
UNIT
1
allow
UNIT
EST'D
SUB
TOTAL
COST
COST
TOTAL
COST
EXTERIOR WALLS & SOFFITS
Allowance for misc
$
15,000.00 $
15,000
SUBTOTAL
B2020
$
15,000
$
392,840
$
21,000
WINDOWS, STOREFRONT, TRANSLUCENT PANELS
New exterior glazing to all existing openings
5,612
sf
$
70.00 $
392,840
SUBTOTAL
B2030
EXTERIOR DOORS
New double glazed entry doors
2
pr
$
5,000.00 $
New single glazed entry doors
2
ea
$
3,500.00 $
10,000
7,000
New single metal doors
2
ea
$
2,000.00 $
4,000
SUBTOTAL
TOTAL - EXTERIOR CLOSURE
B30
B3010
$
428,840
ROOFING
ROOF COVERINGS
SUBTOTAL
B3020
54,315
$
-
$
-
ROOF OPENINGS
SUBTOTAL
TOTAL - ROOFING
C10
INTERIOR CONSTRUCTION
C1010
INTERIOR CONSTRUCTION
Partitions, doors, specialties and millwork
$0
54,315
gfa
$
15.00 $
814,725
Elevator shafts - assumes 8" cmu
2
allow
$
52,800.00 $
105,600
"Z" furring rigid insulation w/ gyp at inside face of exterior wall
1
allow
$
85,000.00 $
85,000
Allowance for decorative railing at 2" flr opening
100
lf
$
150.00 $
15,000
Aluminum vestibule doors at entrances; double
2
pr
$
2,300.00 $
4,600
Aluminum vestibule doors at entrances; single
3
ea
$
1,800.00 $
5,400
SUBTOTAL
$
1,030,325
TOTAL - INTERIOR CONSTRUCTION
C20
C2010
$1,030,325
STAIRCASES
STAIR CONSTRUCTION
Remove and replace handrail & guardrail at existing stairways allowance
1
SUBTOTAL
6/12/2012
allow
$
45,000.00 $
45,000
$
backup
45,000
8
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
12-Jun-12
5.11
5.12
5.0 Financial Information
12-Jun-12
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
DESCRIPTION
C2020
GFA
QTY
UNIT
1
allow
UNIT
EST'D
SUB
TOTAL
COST
COST
TOTAL
COST
STAIR FINISHES
New stair finishes in all stairways
$
40,000.00 $
40,000
SUBTOTAL
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
54,315
$
40,000
TOTAL - STAIRCASES
C30
INTERIOR FINISHES
C3010
INTERIOR FINISHES
Wall, floor and ceiling finishes and treatments
$85,000
54,315
gfa
$
15.00 $
814,725
SUBTOTAL
$
814,725
TOTAL - INTERIOR FINISHES
D10
D1010
$814,725
CONVEYING SYSTEMS
ELEVATOR
Passenger elevator
4
stop
$
30,000.00 $
120,000
Freight elevator
4
stop
$
45,000.00 $
180,000
SUBTOTAL
$
300,000
TOTAL - CONVEYING SYSTEMS
D20
PLUMBING
D20
Plumbing Piping & Accessories
Plumbing piping & accessories
$300,000
54,315
gfa
$
9.00 $
488,835
SUBTOTAL
$
488,835
TOTAL - PLUMBING
D30
HVAC
D30
HVAC, GENERALLY
$488,835
AHUs (3) and associated motors, pumps, fans etc
1
allow
$ 780,000.00 $
HVAC distribution; duct, vavs, dampers etc
1
allow
$ 490,000.00 $
780,000
490,000
Chilled water and hydronic piping distribution
54,315
gfa
$
9.75 $
529,571
Controls and Instrumentation
54,315
gfa
$
7.50 $
407,363
SUBTOTAL
$
TOTAL - HVAC
D40
FIRE PROTECTION
D40
FIRE PROTECTION, GENERALLY
Fire protection (currently none)
6/12/2012
2,206,934
$2,206,934
54,315
backup
gfa
$
4.00 $
217,260
9
5.0 Financial Information
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
DESCRIPTION
GFA
QTY
UNIT
54,315
UNIT
EST'D
SUB
TOTAL
COST
COST
TOTAL
COST
SUBTOTAL
$
217,260
TOTAL - FIRE PROTECTION
D50
D5010
$217,260
ELECTRICAL
SERVICE & DISTRIBUTION
Service & distribution
54,315
gfa
$
10.15 $
551,297
SUBTOTAL
D5020
54,315
gfa
$
9.50 $
$
515,993
$
339,469
$
162,945
515,993
SUBTOTAL
COMMUNICATION & SECURITY SYSTEMS
Communication & security systems rough-in
54,315
gfa
$
6.25 $
339,469
SUBTOTAL
D5040
551,297
LIGHTING & POWER
Lighting & power
D5030
$
OTHER ELECTRICAL SYSTEMS
Fire Alarm
54,315
gfa
$
3.00 $
162,945
SUBTOTAL
TOTAL - ELECTRICAL
E10
EQUIPMENT
E10
EQUIPMENT, GENERALLY
$
SUBTOTAL
$
1,569,704
-
TOTAL - EQUIPMENT
E20
E2010
$0
FURNISHINGS
FIXED FURNISHINGS
Allowance for audio/visual equip mounting brackets and other misc
Locker room allowance
1
allow
$
25,000.00 $
25,000
100
ea
$
400.00 $
40,000
SUBTOTAL
E2020
$
65,000
MOVABLE FURNISHINGS
SUBTOTAL
NIC
TOTAL - FURNISHINGS
F10
SPECIAL CONSTRUCTION
F10
SPECIAL CONSTRUCTION
6/12/2012
$65,000
backup
10
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
12-Jun-12
5.13
5.14
5.0 Financial Information
12-Jun-12
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
DESCRIPTION
Shielding allowance
GFA
QTY
UNIT
1
allow
$
54,315
UNIT
EST'D
SUB
TOTAL
COST
COST
TOTAL
COST
40,000.00 $
40,000
SUBTOTAL
$
40,000
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
TOTAL - SPECIAL CONSTRUCTION
F20
SELECTIVE BUILDING DEMOLITION
F2010
BUILDING ELEMENTS DEMOLITION
$40,000
Building demolition; scope to include architectural elements and MEP
systems
41,585
gfa
Removal of existing steel, ceiling hung mezzanine at gymnasium
1,840
sf
incl above
$
885
sf
incl above
$
-
4,727
sf
incl above
$
-
Remove existing exterior window concrete infill to front façade
Remove existing exterior windows
$
8.00 $
332,680
-
Remove existing exterior doors
6
ea
Cut opening in existing floor slab at level 2
1
allow
$
incl above
16,000.00 $
16,000
Cut new elevator shafts
1
allow
$
50,000.00 $
50,000
SUBTOTAL
F2020
$
398,680
HAZARDOUS COMPONENTS ABATEMENT
excluded
$
-
$
-
SUBTOTAL
$
-
TOTAL - SELECTIVE BUILDING DEMOLITION
G10
SITE PREPARATION
G1010
SITE PREPARATIONS
Remove existing sidewalk/paving
$398,680
1
allow
$
2,500.00 $
2,500
SUBTOTAL
$
2,500
TOTAL - SITE PREPARATION
G20
SITE IMPROVEMENT
G2030
SITE IMPROVEMENT
Create new patio areas to east and west elevations, new retaining wall at
west elevation
$2,500
1
allow
$
85,000.00 $
85,000
SUBTOTAL
$
85,000
TOTAL - SITE IMPROVEMENT
G30
G3050
$85,000
SITE MECHANICAL UTILITIES
COOLING DISTRIBUTION
Tie into existing central plant chilled water loop- allowance
1
SUBTOTAL
6/12/2012
allow
$
25,000.00 $
25,000
$
backup
25,000
11
5.0 Financial Information
St. Cloud State University Eastman Hall
BWBR Architects
St. Cloud, MN
90% Pre-Design Cost Estimate
DESCRIPTION
GFA
QTY
UNIT
54,315
UNIT
EST'D
SUB
TOTAL
COST
COST
TOTAL
COST
TOTAL - SITE MECHANICAL UTILITIES
$25,000
SUBTOTAL - BUILDING TRADES
6/12/2012
$8,502,774
backup
12
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
12-Jun-12
5.15
5.16
5.0 Financial Information
CPMI 10/5/2010
BUILDING PROJECTS INFLATION SCHEDULE
EXHIBIT 3
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
(Projected Rates For FY 2011 - 2012)
Midpoint of
Construction
Dept. of Finance
MULTIPLIER
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Nov-12
Dec-12
Jan-13
Feb-13
Mar-13
Apr-13
May-13
Jun-13
Jul-13
Aug-13
Sep-13
Oct-13
Nov-13
Dec-13
Jan-14
Feb-14
Mar-14
Apr-14
May-14
Jun-14
Jul-14
Aug-14
Sep-14
Oct-14
Nov-14
Dec-14
0.00%
0.21%
0.42%
0.63%
0.84%
1.05%
1.34%
1.64%
1.94%
2.24%
2.54%
2.84%
3.14%
3.44%
3.74%
4.04%
4.34%
4.64%
4.99%
5.34%
5.69%
6.04%
6.39%
6.74%
7.10%
7.46%
7.82%
8.18%
8.54%
8.90%
9.31%
9.72%
10.13%
10.54%
10.95%
11.37%
11.79%
12.21%
12.63%
13.05%
13.47%
13.90%
MN DOF ESCALATION 2011- 2012 - 10_05_10 %.xls
Midpoint of
Construction
Dept. of Finance
MULTIPLIER
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15
Jul-15
Aug-15
Sep-15
Oct-15
Nov-15
Dec-15
Jan-16
Feb-16
Mar-16
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
Jan-17
Feb-17
Mar-17
Apr-17
May-17
Jun-17
Jul-17
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17
Jan-18
Feb-18
Mar-18
Apr-18
May-18
14.33%
14.76%
15.19%
15.62%
16.05%
16.49%
16.93%
17.37%
17.81%
18.25%
18.69%
19.14%
19.59%
20.04%
20.49%
20.94%
21.39%
21.85%
22.31%
22.77%
23.23%
23.69%
24.15%
24.62%
25.09%
25.56%
26.03%
26.50%
26.97%
27.45%
27.93%
28.41%
28.89%
29.37%
29.86%
30.35%
30.89%
31.44%
31.99%
32.54%
33.09%
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
6.0
Ongoing operating expenditures
This page was left blank intentionally.
Revised 10/29/2012
0
0
FY 2016-17
0
0
0
0
0
0
0
0
FY 2018-19
0
0
0
0
0
0
0
0
2
2
0
2,926
3,122
0
3,122
0
2,931
3,127
0
475
475
98
0
0
0
98
0
3,127
98
0
0
0
0
475
0
0
98
0
0
0
PROJECT DETAIL
Amount
0
2,787
0
2,787
2,787
0
0
0
0
0
0
16,889
38
0
0
0
0
16,927
TOTAL
Projected Costs (Without Inflation)
FY 2014-15
FY 2016-17
FY 2018-19 FY2020-21
16,889
16,889
0
0
0
0
0
16,889
FY 2014-15
PREVIOUS STATE CAPITAL APPROPRIATIONS FOR THIS PROJECT (Legal Citations)
Laws of Minnesota (year), Chapter, Section, Subdivision
Revenue Offsets; attach explanation
TOTAL
Change from Current FY 2012-13
Change in F.T.E. Personnel
IMPACT ON STATE
FY2012-13
OPERATING COSTS
Compensation - Program and Building
Operation
0
Other Program Related Expenses
0
Building Operating Expenses
0
Building Repair and Replacement
Expenses (1%)
0
State Owned Lease Expenses
0
Non State Owned Lease
Expenses/(Savings)
0
Projected Debt Service Expenses
0
Expenditure Subtotal
0
CAPITAL FUNDING SOURCES
Prior Years
State Funds:
G.O. Bonds/State Bldgs
0
State Funds Subtotal
0
Agency Operating Budget Funds
38
Federal Funds
0
Local Government Funds
0
Private Funds
0
Other
0
TOTAL
38
for Student Health Related Services
Project Name:Renovation of Eastman Hall
AGENCY CAPITAL BUDGET REQUEST
Fiscal Years 2014-19
Dollars in thousands (e.g. $137,500 = $138 thousand)
2,584
1,292
Amount
67%
33%
Percent of
Total
MS 16A.695: Program Funding Review Required
(Agency)
MS 16A.695: Use Agreement Required (MMB)
MS 16A.641 (Subd. 9): Special accounts; appropriation
MS 16A.633 (Subd. 4):Report on Jobs Created or
Retained.
MS 16B.35: Percent for Art
MS 16B.335 (Subd. 5): Information Technology Review
(MN.IT Services-formerly OET)
MS 16B.335 (Subd. 4): Energy Conservation Standards
MS 16B.335 (Subd. 2): Other Projects (Legislative
Notification)
MS
16B.335 (Subd. 3): Predesign Requirement
(Administration Dept)
MS 16B.335 (Subd. 1b): Project Exempt From this
Review (Legislature)
MS 16B.335 (Subd. 1a): Construction/Major Remodeling
Review (Legislature)
MS 16B.33: State Designer Selection Board
MS 16B.325, Sustainable Building Guidelines, (B3)
MS 16B.326 and 16B.32 : Energy Conservation
Requirements (Agency)
MS 16B.323: Solar Energy in State Buildings.
STATUTORY AND OTHER REQUIREMENTS
Project applicants should be aware that the following
requirements will apply to their projects after adoption of the
bonding bill
SOURCE OF FUNDS
FOR DEBT SERVICE
PAYMENT
General Fund
User Financing
PROJECT DETAIL
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
2
6.0 Ongoing Operating Expenditures
6.3
This page was left blank intentionally.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
7.0
Project schedule
This page was left blank intentionally.
7.0 Project Schedule
PROJECT SCHEDULE
2012
OCT
2013
NOV
DEC
JAN
2014
FEB
MAR
APR
MAY
JUN
JUN
2015
JUL
AUG
SEP
OCT
NOV
DEC
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
PREDESIGN SUBMITTAL
BOARD OF TRUSTEES
DESIGNER SELECTION
SCHEMATIC DESIGN
MNSCU REVIEW
SD REVIEW MTG.
SD REVISIONS
SD FINAL SUBMISSION
DESIGN DEVELOPMENT
DD PRICING
MNSCU REVIEW
CONSTRUCTION DOCUMENTS
MNSCU REVIEW
CD REVISIONS
FINAL MNSCU APPROVAL
BIDDING & CONTRACT AWARD
Construction (12 months)
Mid-Point of Construction (Feb. 2016)
Punch List/Final (July 2016)
Occupancy (August 2016)
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
7.1 pROJECT SCHEDULE
7.3
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
8.0
TECHNOLOGY PLAN
8.2
8.0 Technology Plan
8.1 Technology plan
“SCSU will provide appropriate technologies and resources
that support teaching, learning, service and access. This
goal is in alignment with the SCSU Technology Master
Plan.”
1. The University will provide students and faculty with
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
classrooms and laboratories containing up-to-date,
discipline-specific equipment and software.
Rationale: Technology is a means to offer students
a high quality education with the skills needed
to compete in the marketplace and to make that
education accessible. Skills in most fields, from fine
arts to technical professional fields, use some form
of technology, which may range from microscopes,
musical instruments, and kilns, to computers and
software.
2. The University will utilize information technology
and distributed learning to support classroom learning and to provide access for outreach.
Rationale: With demographics changing (Date
Source: Minnesota Higher Education Services
Offices), and job requirements requiring ongoing
education (Date Source: MDES), many of our new
students may have time and location constraints.
Distributed learning is one way to make education
accessible for them and allow the institution to
access new markets.
3. The University will apply appropriate technolo-
gies and resources to support teaching, learning,
research, creativity, scholarship, and service.
Rationale: Technology should support the pedagogy,
learning goals, research, creativity, scholarship, and
service that remain at the core of professional needs
and development.
4. The University will provide appropriate technolo-
gies and resources to enhance access to support
services.
Rationale: The University needs an infrastructure to
support services for its students, faculty and staff,
including human resource functions, e-services, and
integrated business functions.
SCSU willl:
• Create an exceptional e-learning environment
• Develop excellent classroom resources that effec-
tively support SCSU’s teaching and learning missions
• Ensure that technology matches pedagogy
• Assess how student learning is being affected by
classrooms technology use
• Provide a robust and stable IMS platform to support
teaching and learning.
PRE-DESIGN NARRATIVE
COMMUNICATION, LIFE SAFETY & SECURITY
DIVISIONS 27 & 28
I.
Technology Systems Assessment
A.
Dunham Engineering prepared an assessment of the electrical system serving Eastman Hall
on the St Cloud State University Campus. The purpose of this study is to identify
modifications to the existing mechanical and electrical systems to accommodate planned
remodeling. The assessment includes non-intrusive observations, review of existing plans,
and discussions with building maintenance staff of the power, lighting, communication
security, life safety (fire alarm devices), heating, ventilation, air conditioning and plumbing
systems.
B.
Interviews with SCSU facility management staff with knowledge of the systems indicate that
the general conditions of the systems are they are the end of life (with some exceptions which
are noted within this document). Their preference would be for a complete replacement of
the all the existing systems to current standards and code compliance.
C.
Fire Alarm System:
1.
The existing Simplex 2001 fire alarm control panel and associated annunciation
devices are nearing end of useful life and does not meet new campus standards.
security, life safety (fire alarm devices), heating, ventilation, air conditioning and plumbing
systems.
8.0 Technology Plan
Interviews with SCSU facility management staff with knowledge of the systems indicate that
the general conditions of the systems are they are the end of life (with some exceptions which
are noted within this document). Their preference would be for a complete replacement of
the all the existing systems to current standards and code compliance.
C.
Fire Alarm System:
1.
The existing Simplex 2001 fire alarm control panel and associated annunciation
devices are nearing end of useful life and does not meet new campus standards.
a.
Recommendation: The existing fire alarm system shall be removed in its
entirety and replaced with a new voice style fire alarm system to meet current
SCSU campus standards.
D.
Communication System:
1.
The existing building is served by a 2-post rack located in the west side of the
basement. The rack currently holds (3) data patch panels, (1) rack mounted 110-block,
48 port switch, and UPS. Adjacent to the rack is a wall mounted fiber patch panel,
connecting building to campus LAN.
a.
Recommendation: Provide a new main communication room in the basement
(approximately 150 square feet) which will house the building network
electronics. The space should be provided with a cabinet style UPS, dedicated
cooling, cabling racks, network cabinets, and cable tray for proper cabling
routing. This room would then serve a secondary communication closet
(approximately 80 square feet) located on each floor via backbone fiber and
UTP. Replace all existing communication cabling (phone, data, television, etc.)
and provide new category 6 cabling corresponding to the building’s new space
programming.
E.
Audio Visual Systems:
1.
The only observed audio visual system was in recently renovated classrooms that
included a new projector, speakers, and projection screen.
a.
Recommendation: Provide building wide audio systems for paging (via the new
voice style fire alarm system), and select areas for dedicated Audio Visual
Systems with Crestron Controls.
F.
Security System:
1.
Dunham did not observe any existing electronic security system or devices.
a.
Recommendation: Provide building wide security systems that will include
intrusion detection, access control, and video surveillance.
II. NEW TECHNOLOGY GENERAL REQUIREMENTS
A.
The work described in this document includes all materials, labor, equipment and services to
construct and install a complete operating low voltage system for the renovation of Eastman
Hall at St. Cloud State University in St. Cloud Minnesota.
III. DESIGN CONDITIONS
A.
Exterior Environmental Conditions: Electrical systems shall withstand the following
environmental conditions without mechanical or electrical damage or degradation of
performance capability:
1.
Ambient Temperature: -20 to 104 deg F
2.
Relative Humidity: 0 to 95 percent.
3.
Altitude: 1031 feet
B.
Interior Environmental Conditions: Electrical systems shall withstand the following
environmental conditions without mechanical or electrical damage or degradation of
performance capability:
1.
Ambient Temperature: 65 to 75 deg F
2.
Relative Humidity: 0 to 95 percent.
3.
Altitude: 1031 feet
8.3
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
B.
A.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
8.4
8.0
Exterior Environmental Conditions: Electrical systems shall withstand the following
environmental conditions without mechanical or electrical damage or degradation of
performance
Technology
Plancapability:
1.
Ambient Temperature: -20 to 104 deg F
2.
Relative Humidity: 0 to 95 percent.
3.
Altitude: 1031 feet
B.
Interior Environmental Conditions: Electrical systems shall withstand the following
environmental conditions without mechanical or electrical damage or degradation of
performance capability:
1.
Ambient Temperature: 65 to 75 deg F
2.
Relative Humidity: 0 to 95 percent.
3.
Altitude: 1031 feet
C.
Interruption of Existing Electric or Communication Services: Do not interrupt services to
facilities occupied by Owner or others unless permitted under the following conditions and
then only after arranging to provide temporary electric service according to requirements
indicated:
1.
Notify Owner/Owner's Representative no fewer than 5 working days in advance of
proposed interruption of electric service.
2.
Do not proceed with interruption of electric service without Owner's/Owner's
Representative's written permission.
IV. CODES AND STANDARDS
A.
Codes and Standards: Materials, products, devices, fixtures, and forms shall meet or exceed
the requirements of National Electrical Code (NEC), American National Standards Institute
(ANSI), Institute of Electrical and Electronics Engineers (IEEE), National Manufacturing
Association (NEMA) and all applicable codes, all for the most current editions as of the
Schematic Design Submittal. Methods of construction and material application shall comply
with installation requirements of the National Fire Protection Association (NFPA). All
materials and equipment shall be listed and labeled by the Underwriters Laboratories, Inc.
(UL) or other approved testing agency as conforming to their standards where such standards
have been established for the particular materials or equipment. The following codes and
standards will be followed;
1.
NFPA - National Fire Protection Association, NFPA 101, 72, 110, and 780
2.
IBC - International Building Code
3.
UFC - Uniform Fire Code
4.
NEC - National Electrical Code
5.
UFAS - Uniform Federal Accessibility Standard
6.
IES - Illuminating Engineers Society - Lighting Levels Standards
7.
ASHRAE 90.1 - American Society of Heating, Refrigerating and Air Conditioning
Engineers, Inc.
8.
ANSI - American National Standards Institute
9.
NEMA - National Electrical Manufacturer's Association
10.
EIA/TIA - Electronic Industry Association/Telecommunications Industry Association
11.
BICSI - Building Industry Consulting Service International
12.
Minnesota State Colleges and Universities (MNSCU) Facilities Design and
Construction Standards – 6th Addition (with 12/2010 revisions).
13.
All work will be performed by licensed contractors in the State of Minnesota.
V. DEMOLITION
A.
Remove accessible wiring including conduit, junction boxes, hangers, and supports for main
feeders to panel boards, from panel boards to light fixtures, and from panel boards to wiring
devices such as receptacles, switches, floor outlets, special electrical devices, etc., indicated
to be removed in other portions of this document. Existing conduit, boxes, cable, etc. that
remain which are presently being supported from existing ceiling or ceiling supports, which
are to be removed, shall be re-supported to building structure.
B.
Where conduits are stubbed out of a surface not being removed for new construction, such as
a floor slab or poured concrete column or wall, these conduits shall be cut back to a point
where patching can adequately be performed.
C.
Demolition work shall be coordinated with the Owner. Should questions arise regarding the
removal of a conduit and/or wiring, (i.e. Is it energized? Does it serve a load in an area not be
11.
12.
V. DEMOLITION
A.
Remove accessible wiring including conduit, junction boxes, hangers, and supports for main
feeders to panel boards, from panel boards to light fixtures, and from panel boards to wiring
devices such as receptacles, switches, floor outlets, special electrical devices, etc., indicated
to be removed in other portions of this document. Existing conduit, boxes, cable, etc. that
remain which are presently being supported from existing ceiling or ceiling supports, which
are to be removed, shall be re-supported to building structure.
B.
Where conduits are stubbed out of a surface not being removed for new construction, such as
a floor slab or poured concrete column or wall, these conduits shall be cut back to a point
where patching can adequately be performed.
C.
Demolition work shall be coordinated with the Owner. Should questions arise regarding the
removal of a conduit and/or wiring, (i.e. Is it energized? Does it serve a load in an area not be
remodeled?), confer with the Owner before such wiring or conduit is actually demolished.
D.
Reused and Reinstalled equipment and devices: Carefully disconnect and remove items to be
reused or reinstalled. Items shall be properly stored in a manner causing no additional
damage to the item. Prior to reinstalling, clean and test item. Upon completion, the item shall
be in equivalent condition as prior to its removal. Items damaged due to improper handling
and storage by the Contractor shall be replaced with new items of the same type and quality
as the original item. Reinstalled light fixtures shall be cleaned and re-lamped with new lamps.
Non-functioning ballasts shall be replaced with new ballasts. Lamps and ballasts shall be
guaranteed as new items.
E.
Demolition equipment and devices: Existing equipment, devices, and light fixtures not
indicated for reuse (as indicated in other portions of this document) shall become the
property of the Contractor and disposed of properly.
F.
Light fixtures scheduled for removal on this Project may contain PCB impregnated ballasts.
Remove PCB ballasts from light fixtures and place ballasts in hazardous waste disposal
containers. Properly dispose of the ballasts with a registered hazardous materials disposal
contractor. Provide copies of the disposal certificate(s) to the Owner and Engineer at the
completion of the Project.
G.
Fluorescent and HID lamps removed from light fixtures shall be placed in containers, and
properly disposed of with a registered disposal contractor.
H.
Disconnect and remove wiring devices and replace with new devices and cover plates.
I.
Rework the existing conduit and junction box system such that upon completion of the
remodeling, no junction boxes are located in inaccessible locations. This includes existing
junction boxes that may be rendered inaccessible due to new piping or ductwork installation.
Coordinate with other trades in this effort. Provide additional conduit and connections as
required.
Plan
8.5
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
13.
BICSI - Building Industry Consulting Service International
8.0 Technology
Minnesota State Colleges and Universities (MNSCU) Facilities Design and
Construction Standards – 6th Addition (with 12/2010 revisions).
All work will be performed by licensed contractors in the State of Minnesota.
8.6
8.0 Technology Plan
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
VI. SITE UTILITIES
A.
Communication Utility Service: The building shall be served by the campus LAN which is
currently being brought via fiber optic and copper cables. All design/installation work will be
coordinated with the Office of Information Technology at SCSU.
1.
Campus Intercommunications –Not Applicable (via Phone in future)
2.
Campus Paging – Not Applicable (via new Fire Alarm in future)
B.
Health Services: The building shall tie into the following existing head end systems 1.
Nurse Call – Not existing (new system to be provided based on building’s new space
programming)
C.
Life Safety/Security Service: The building shall tie into the following existing head end
systems
1.
Campus Fire Alarm System – Simplex (Voice Evacuation Style)
2.
Campus Security Intrusion System – Blackboard
3.
Campus Access Control System – Blackboard
4.
Area of Rescue – (Talk A Phone)
VII. DIVISION 26 – ELECTRICAL SYSTEMS
A.
Divisions 27 and 28 Raceway and Box Rough-in Requirements: Electrical rough-in shall be
provided for the following systems (cabling/terminations to be provided by the Division 27
and Division 28 contractors as required below) 1.
Data, Voice, Video and Security system - A complete empty conduit / rough-in system
and support requirements will be provided for each system.
2.
Raceways for the following systems that are in accessible locations shall have a
manufacturer applied color coding as follows:
a.
Fire Alarm: Red
b.
Telecommunications: Blue
c.
Audio/Visual: Yellow
d.
Security Systems: Green
3.
3/4" minimum conduit will be stubbed into accessible ceiling space for each voice,
video, and security system outlet device. Non-metallic thread-less insulating bushing
on the end of all conduits will be provided.
4.
1” minimum conduit will be stubbed into accessible ceiling space for each data
information outlet device. Non-metallic thread-less insulating bushing on the end of all
conduits will be provided.
5.
Cable Tray: 8”Wx2”D Basket Tray will be provided throughout the building for routing
of special system cabling. Cable tray systems will be provided for all data, voice, and
video cabling. Ladder type cable tray will be provided in the main telecommunication
equipment room.
6.
Raceways 2-inch and smaller inside the buildings will not exceed 150 feet in length. All
raceways installed will not contain more than two 90 degree bends or the equivalent.
Pull boxes or junction boxes will be provided as necessary to comply with these
requirements.
7.
Bends in conduits will be long sweep radius bends and in no instance will the inside
radius of bends be less than ten times the internal diameter for all conduit sizes.
8.
Plywood mounting boards will be provided in all Telecommunication Closets,
minimum 3/4" thick AC plywood. Paint all mounting boards on the smooth side with
two coats gray alkyd enamel.
9.
A complete telecommunication grounding system complying with ANSI/EIA/TIA 607
will be provided. Equipment grounding connections will be provided at all equipment
terminal systems and mounting boards.
10.
All device outlet boxes will be minimum 4" square x 2-1/2" deep, with single or two
gang plaster ring and blank cover plate.
VIII. DIVISION 27 – COMMUNICATION SYSTEMS
10.
8.0 Technology Plan
All device outlet boxes will be minimum 4" square x 2-1/2" deep, with single or two
gang plaster ring and blank cover plate.
A.
Communication Systems: All offices, community common areas, classrooms, exam rooms,
laboratories, and student use areas shall consist of hard wired and wireless communication
systems.
B.
Installation Requirements:
1.
Performance testing of the equipment and system installation/operation by an
accredited testing firm in conformance with criteria by the International Electrical
Testing Association. Compliance with the standards and associations of the industry
including UL, IEEE, NEMA, NFPA, NBFU, ICEA, ASTM, OSHA, NESC, ANSI, ETL, NETA,
where applicable. The testing firm will be a qualified independent testing agency.
2.
ANSI/TIA/EIA Standard 568-B: Commercial Building Telecommunications Cabling
Standards
3.
ANSI/TIA/EIA Standard 569-A: Pathways and Spaces
4.
ANSI/TIA/EIA Standard 606: Administration
5.
ANSI/TIA/EIA Standard 607: Grounding and Bonding
6.
NFPA 70 National Electric Code (NEC).
C.
Communication Rooms:
1.
Main Point of Presence (MPOP): Room shall be located in basement level in a
dedicated Equipment Room (ER) and shall be a minimum of 12’-0” x 10’-0”. This room
shall accommodate the building's communication(s) distribution frames (data and
voice) and shall connect the building with the Campus's system networks via fiber and
copper cables provided as part of this work.
2.
Floor Telecommunication Rooms (TR): Rooms shall be located on each level of the
building, and shall be a minimum 8’-0” x 10’-0”. This room shall accommodate the
floors communication(s) distribution frames (data and voice) and shall connect back
to the ER via the communication’s backbone risers.
3.
Telecommunication Racks and Cabinets: TE Connectivity frames with
horizontal/vertical cabling management.
4.
Basket Cable Tray: Basket Rack Cable Tray will be provided above all
telecommunication racks in each ER/TR.
5.
Grounding: Grounding will be provided in compliance with EIA/TIA 607, IEEE 1100,
and NEC.
6.
UPS Power Distribution: Rack Mounted UPS equipment will be provided for each
Telecommunication Rack. (1) 1500 VA UPS per room is anticipated at this time.
Backbone Communication Cabling:
1.
2.
3.
4.
5.
E.
Backbone cabling system shall provide interconnections between communications
equipment rooms (TR), main terminal space, entrance facilities, and equipment rooms
(ER) in the telecommunications cabling system structure. Cabling system consists of
backbone cables, intermediate and main cross-connects, mechanical terminations, and
patch cords or jumpers used for backbone-to-backbone cross-connection.
Backbone cabling cross-connects may be located in communications equipment
rooms or at entrance facilities. Bridged taps and splitters shall not be used as part of
backbone cabling.
Analog Voice Backbone Cable requirements: Minimum compliant Category 5e cabling
from TE Connectivity, in 25-pair binder groups connecting each secondary TR to the
ER.
Network Backbone Cable requirements: Combination 50 micron, laser optimized
multimode fiber optic cables and single mode fiber optic cables connecting each
secondary TR to the ER.
Video Backbone Cable: Utilize fiber optic single mode cabling plant for distribution.
Horizontal Communication Cabling:
1.
Horizontal cable and its connecting hardware provide the means of transporting
signals between the telecommunications outlet/connector and the horizontal crossconnect located in the communications equipment room (TR). This cabling and its
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
VIII. DIVISION 27 – COMMUNICATION SYSTEMS
D.
8.7
8.8
8.0 Technology
Plan Backbone Cable requirements: Combination 50 micron, laser optimized
4.
Network
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
5.
multimode fiber optic cables and single mode fiber optic cables connecting each
secondary TR to the ER.
Video Backbone Cable: Utilize fiber optic single mode cabling plant for distribution.
E.
Horizontal Communication Cabling:
1.
Horizontal cable and its connecting hardware provide the means of transporting
signals between the telecommunications outlet/connector and the horizontal crossconnect located in the communications equipment room (TR). This cabling and its
connecting hardware are called "permanent link," a term that is used in the testing
protocols.
a.
TIA/EIA-568-B.1 requires that a minimum of two telecommunications
outlet/connectors be installed for each work area.
b.
Horizontal cabling shall contain no more than one transition point or
consolidation point/zone box between the horizontal cross-connect and the
telecommunications outlet/connector.
c.
Bridged taps and splices shall not be installed in the horizontal cabling.
2.
A work area is approximately 100 sq. ft., and includes the components that extend
from the telecommunications outlet/connectors to the station equipment.
3.
The maximum allowable horizontal cable length is 295 feet. This maximum allowable
length does include the 10 feet of service loop required by this specification. This
maximum allowable length does not include an allowance for the length of 16 feet to
the workstation equipment. The maximum allowable length does not include an
allowance for the length of 16 feet in the horizontal cross-connect.
4.
Horizontal Network Cable requirements: Mid-tier Category 6 cabling from TE
Connectivity.
5.
Horizontal Video Distribution Cable requirements: Video over UTP, with associated
electronics and baluns to accomplish interface.
F.
Work Area Devices: All device locations and quantities will be provided in accordance to
SCSU and MNSCU technology standards and user/design team input.
G.
Campus Digital Signage System – Video backbone and horizontal cabling to be provided to
Owner provided/designated digital signage monitors.
H.
Local Audio Visual Systems for dedicated spaces to be provided by Owner, coordinated with
cabling/power infrastructure.
I.
Master Clock System: Provide 120V power to Owner designated locations for Owner
provided wireless clocks.
J.
Local Audio/Visual (A/V) Reinforcement Systems: Owner provided systems.
K.
Network Electronics: Owner provided systems
L.
Wireless Access Points: Owner provided systems, utilizing network cabling provided as part
of the project..
M.
Nurse Call Notification System: Hardwired system to provide notification services between
the various areas of the facility including, but not limited to: Exam Rooms, Laboratories,
Radiology, and Administration. Basis of Design system will be a Rauland 4000 Series.
N.
EMR System cabling will be provided based on the selected system.
8.0 Technology Plan
A.
Electronic Safety and Security Systems: The new facility will utilize access control, video
surveillance, intrusion detection, and digital/addressable fire alarm system to promote a safe
and secure environment for employees and students. The systems shall be integrated to
minimize failure points and promote ease of use for a single point of control.
B.
Installation Requirements:
1.
Performance testing of the equipment and system installation/operation by an
accredited testing firm in conformance with criteria by the International Electrical
Testing Association. Compliance with the standards and associations of the industry
including UL, IEEE, NEMA, NFPA, NBFU, ICEA, ASTM, OSHA, NESC, ANSI, ETL, NETA,
where applicable. The testing firm will be a qualified independent testing agency.
2.
NFPA 70 National Electric Code (NEC).
C.
Equipment Rooms:
1.
Equipment shall be housed in Communication Equipment and Telecommunication
Rooms, and shall adhere to those requirements.
D.
Electronic Safety and Security (ESS) Cabling:
1.
Cabling as required to meet the requirements of the existing Access Control and Video
Surveillance Systems.
E.
Security / Surveillance System: The renovation will provide a new Blackboard control panel
for Owner designated access control locations and intrusion detection, and adhere to campus
security standards. Video Surveillance will be an IP based system that will be designed as a
standalone system that will be capable of integrating into the existing ONSSI security video
surveillance system located at the campus security office.
F.
Fire Alarm System: The renovation of the building will provide a new addressable fire alarm
control panel (Simplex to meet campus standards) with voice evacuation capabilities. The
new system will be provided with ( but not be limited to), remote control panel(s),
annunciator panel, smoke detectors, heat detectors, manual pull stations, and combination
audible speaker / strobes. The system will be non-coded, supervised and in accordance with
local fire codes.
1.
Carbon monoxide detection will be provided at all gas burning equipment.
2.
Smoke detectors will be provided on each side of magnetically held fire rated doors, in
all mechanical/electrical rooms, and janitor/storage rooms.
3.
Duct smoke detectors will be in all air handling equipment on the supply and return
side, 2000CFM or greater. Detectors will also be provided within 5’ of all fire smoke
dampers. Optional design will allow for full area coverage of the building and
eliminating the duct smoke detectors from the air handling units.
4.
Manual pull stations will be provided at the Fire Alarm Control Panel location and a
designated reception area.
5.
Speakers or Speaker/Strobe units will be provided throughout the building.
6.
Magnetic door holders will be provided at appropriate door locations.
7.
Monitor Modules will be provided for sprinkler flow and tamper switches, and an
additional monitor module will be provided at each flow to connect directly to the
campus EMS.
8.
Control Modules will be provided to interface with elevator recall and power off (shunt
trip) equipment if required.
9.
The system will be UL listed to be operated as a digital paging system, with
connections into the facility phone system and future Mass Notification System.
10.
The system will be provided with BACNet IP card to connect with the campus EMS
system.
X. ELECTRICAL, COMMUNICATION, AND ELECTRONIC SAFETY AND SECURITY SPACE DESIGN
CRITERIA:
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
IX. DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
8.9
8.10
8.0 Technology Plan
10.
The system will be provided with BACNet IP card to connect with the campus EMS
system.
X. ELECTRICAL, COMMUNICATION, AND ELECTRONIC SAFETY AND SECURITY SPACE DESIGN
CRITERIA:
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
1.
2.
3.
4.
5.
Commons /Administration area will be designed to have recessed and/or suspended
linear LED fixtures (dimming drivers) for general lighting, along with task and
decorative lighting fixtures for select areas utilizing LED or low voltage incandescent
lamp sources. Lighting will be controlled on an individual fixture basis utilizing
addressable ballast controllers or drivers. General power receptacles will be provided
in the space for cleaning equipment, and workstation power receptacles will be
provided for designated locations throughout the space. In conjunction with the
workstation power, SCSU LAN network receptacles and wireless access points will be
located to provide network connections. Accommodations will be provided for a wall
mounted LCD monitor(s) which will show the Campus digital signage channel, and
also provide the capability of showing building local information. Life safety devices
will consist of ceiling mounted smoke detectors and speaker/strobes.
Gathering/Entry area will be designed to have recessed and/or suspended linear LED
fixtures (dimming drivers) for general lighting, along with task and decorative lighting
fixtures for select areas utilizing LED or low voltage incandescent lamp sources.
Lighting will be controlled on an individual fixture basis utilizing addressable ballast
controllers or drivers. General power receptacles will be provided in the space for
cleaning equipment, and workstation power receptacles will be provided for
designated locations throughout the space. In conjunction with the workstation power,
SCSU LAN network receptacles and wireless access points will be located to provide
network connections. Accommodations will be provided for a wall mounted LCD
monitor(s) which will show the Campus digital signage channel, and also provide the
capability of showing building local information. There will also be designated self-care
health kiosks which will incorporate touchscreen capabilities, access to local health
service information and connection to web services, and the ability to tie into the
Campus Digital Signage and Scheduling System. The reception area will also be the
building’s security check point, with access control on the vestibule doors and video
surveillance cameras watching entry points and SCSU designated locations. Life safety
devices will consist of ceiling mounted smoke detectors and speaker/strobes, and a
wall mounted Fire Alarm Annunciator that should be located near the entry door.
Student Health Services will be designed to have linear LED light fixture(s) with
dimmable driver, controlled by a wall mounted occupancy sensor with manual
override/dimming control. Each room will receive new electrical and communication
outlets to accommodate a computer/monitor, phone, and miscellaneous equipment as
directed by Health Services. A basic electronic Nurse Call system will be designed for
notification and scheduling of exam rooms to help efficiency of the space. Life safety
will be accomplished with a ceiling mounted system connected smoke detector for
smoke detection within the space and ceiling mounted speaker/strobe for
annunciation of fire alarm.
Counseling Services area will be designed to have recessed and/or suspended linear
LED fixtures (dimming drivers) for general lighting, along with task lighting fixtures for
select areas utilizing LED or low voltage incandescent lamp sources. Lighting will be
controlled on an individual fixture basis utilizing dimmable drivers. General power
receptacles will be provided in the space for cleaning equipment, and workstation
power receptacles will be provided for designated locations throughout the space. In
conjunction with the workstation power, SCSU LAN network receptacles and wireless
access points will be located to provide network connections. Life safety devices will
consist of ceiling mounted smoke detectors and speaker/strobes.
The U-Choose, Health Education, and Human Performance will be designed to have
recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting.
Lighting will be controlled with ceiling mounted occupancy sensors, manual push
buttons, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and
communication cabling will be provided to accommodate designated locations and for
flexibility of the space. The rooms will be set up for audio visual accommodations
including large format screens, touchscreen interfaces, sound reinforcement, and
future interactive white boards. The entry door will be designed with access control to
8.0 Technology Plan
6.
7.
8.
9.
10.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
5.
access points will be located to provide network connections. Life safety devices will
consist of ceiling mounted smoke detectors and speaker/strobes.
The U-Choose, Health Education, and Human Performance will be designed to have
recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting.
Lighting will be controlled with ceiling mounted occupancy sensors, manual push
buttons, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and
communication cabling will be provided to accommodate designated locations and for
flexibility of the space. The rooms will be set up for audio visual accommodations
including large format screens, touchscreen interfaces, sound reinforcement, and
future interactive white boards. The entry door will be designed with access control to
safeguard the equipment that will be located in the space. To meet life safety codes, a
system connected ceiling mounted smoke detector and speaker strobe for smoke
detection and annunciation within the space.
The Smart Classroom/Multipurpose Space(s) will be designed to have recessed
linear LED fixtures (dimming drivers) for general lighting and work in conjunction with
specialty LED fixtures (spots, down lights, gimbal, linear wash) for selected locations
for scene setup capabilities. Lighting will be controlled with ceiling mounted occupancy
sensors, manual push buttons with individual zone level control, daylight harvest
sensors, and Audio Visual touchscreen interfaces. Power and communication cabling
will be provided to accommodate designated locations and for flexibility of the space.
The rooms will be set up for audio visual accommodations including multiple large
format screens, touchscreen interfaces, sound reinforcement, interactive white boards,
and distance learning equipment (video conferencing capabilities). The entry door will
be designed with access control to safeguard the equipment that will be located in the
space. To meet life safety codes, a system connected ceiling mounted smoke detector
and speaker strobe for smoke detection and annunciation within the space.
Conference Rooms will be designed to have recessed and/or suspended linear LED
fixtures (dimming drivers) for general lighting. Lighting will be controlled with ceiling
mounted occupancy sensors, manual push buttons, daylight harvest sensors, and
Audio Visual touchscreen interfaces. Power and communication cabling will be a
combination of wall mounted receptacles and floor mounted poke-thru. The rooms will
be set up for audio visual accommodations including large format screens,
touchscreen interfaces, sound reinforcement, and future interactive white boards. To
meet life safety codes, a system connected ceiling mounted smoke detector and
speaker strobe for smoke detection and annunciation within the space.
Corridors will be designed to have recessed mounted linear LED light fixtures that will
be 12’-0” on center the length of the corridor. Each fixture will have dimmable drivers,
controlled by time of day schedule with ceiling mounted occupancy sensors for
automatic overrides. Lighting will be dimmed to 20% levels during scheduled night
hours for energy conservation. Power circuiting will be routed in conduits above the
new accessible ceiling that will be installed, along with a new basket cabletray for
communication cabling and the fire alarm system conduit. Each corridor will be
designed to have general receptacles spaced no more than 50’-0” on center to
accommodate 25’-0” equipment cords (i.e. vacuums) and wireless access points for
students access to the SCSU LAN network (with devices spaced approximately 50’-0”
on center). To meet life safety codes, system connected smoke detectors will be
ceiling mounted in conjunction with ceiling mounted speaker/strobes.
Restrooms will be designed to have surface mounted linear LED fixtures with
dimmable drivers controlled by time of day schedule with ceiling mounted occupancy
sensors for automatic overrides. Lighting will be dimmed to 20% levels during
scheduled night hours for energy conservation and be conducive to sleeping
accommodations. General power receptacles will be provided near the sink/mirror
locations for student use, and power will be provided to automatic faucet and urinal
sensors for water conservation. To meet life safety codes, a system connected heat
detector and strobe unit ceiling mounted for fire detection and annunciation within the
space.
Electrical Service Entrance rooms will be designed to accommodate a floor mounted
Suitable for Use as Service Entrance switchboard with main circuit breaker/metering
section and circuit breaker distribution sections, wall mounted branch circuit
panelboards, floor mounted automatic transfer switches (life safety and option
standby), and floor mounted transformer. Lighting in the space will be industrial linear
8.11
8.12
8.0 Technology Plan
10.
St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012
11.
12.
13.
detector and strobe unit ceiling mounted for fire detection and annunciation within the
space.
Electrical Service Entrance rooms will be designed to accommodate a floor mounted
Suitable for Use as Service Entrance switchboard with main circuit breaker/metering
section and circuit breaker distribution sections, wall mounted branch circuit
panelboards, floor mounted automatic transfer switches (life safety and option
standby), and floor mounted transformer. Lighting in the space will be industrial linear
fluorescent strip fixtures with symmetric reflectors and two T8 lamps, controlled by a
wall mounted toggle switch. Communication cabling will be provided to selected
pieces of equipment for remote monitoring of information. Life safety will be
accomplished with a ceiling mounted system connected smoke detector and wall
mounted speaker/strobe unit for smoke detection and annunciation within the space.
Electrical Secondary rooms will be designed to accommodate wall mounted branch
circuit panelboards. Lighting in the space will be industrial linear fluorescent strip
fixtures reflectors and two T8 lamps, controlled by a wall mounted toggle switch.
Communication cabling will be provided to selected pieces of equipment for remote
monitoring of information.
Communication Equipment room will be designed to have industrial linear
fluorescent strip fixtures with symmetric reflectors and two T8 lamps, controlled by a
wall mounted toggle switch. The space will be designed to accommodate two rows of
equipment racks and/or cabinets, interconnected with cabletray mounted overhead.
An in-row UPS cabinet will be provided for powering all equipment, with the Campus
LAN/WAN terminating in the space. Life safety will be accomplished with a ceiling
mounted system connected smoke detector and wall mounted speaker/strobe unit for
smoke detection and annunciation within the space.
Communication Secondary rooms will be designed to accommodate a floor mounted
two post rack for communication equipment and cabling. Lighting in the space will be
industrial linear fluorescent strip fixtures reflectors and two T8 lamps, controlled by a
wall mounted toggle switch. Dedicated power receptacles will be mounted on the
ceiling hung cable tray in the room, with general receptacles wall mounted on the back
wall of the space. Life safety will be accomplished with a ceiling mounted system
connected smoke detector for smoke detection within the space.
Download