October 2012 ST. CLOUD STATE UNIVERSITY Predesign Submittal RENOVATION OF EASTMAN HALL FOR STUDENT HEALTH RELATED SERVICES OCTOBER 2011 Table of Contents section 1.0: Predesign Summary Statement . . . . . . . . . . . . . . . . . 1.1 1.1 Project Participants. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2 Project Information. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.3 Project Budget. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4 Project Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5 Alternative Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.6 Campus Plan. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . section 2.0: Project Background Narrative. . . . . . . . . . . . . . . . . . 2.1 2.1 Statutory and Other Requirements. . . . . . . . . . . . . . . 2.2 2.2 Project Rationale/Summary of Needs. . . . . . . . . . . . 2.2 2.3 Relationship to 2010 Comprehensive Plan. . . . . . . . 2.5 2.4 Space Utilization. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6 2.5 Facilities Systems Summary . . . . . . . . . . . . . . . . . . . . 2.6 2.6 Code Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.17 2.7 Sustainability Highlights. . . . . . . . . . . . . . . . . . . . . . . . 2.17 section 3.0: Project Description. . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1 3.1 Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2 3.2 Existing Floor Plans. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.5 3.3 Project Scope and Program . . . . . . . . . . . . . . . . . . . . 3.10 3.4Design Concepts. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.17 3.5 Systems Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.27 Sustainability. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.1 section 4.0: 1.2 1.3 1.5 1.5 1.6 1.6 4.1 Energy Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.2 section 5.0: Financial Information-Capital Expenditures. . . . . . 5.1 5.1 Project Budget. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2 section 6.0: Ongoing Operating Expenditures. . . . . . . . . . . . . . . 6.1 section 7.0: Project Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7.1 7.1 Project Schedule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7.3 section 8.0: Technology Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8.1 section 9.0: Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.1 9.1 Multi-tiered Program. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.1 9.2 Student Health Services-Org. Charts. . . . . . . . . . . . . 9.2 9.3 Meeting Minutes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.3 9.4 Planning Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.4 9.5 Room Data Sheets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.5 9.6 Existing Building Plans. . . . . . . . . . . . . . . . . . . . . . . . . . 9.6 9.7 Soils Report (Existing Footings). . . . . . . . . . . . . . . . . . 9.7 9.8 Structural Testing (Existing Structure). . . . . . . . . . . . 9.8 9.9 Furniture, Fixtures & Equipment . . . . . . . . . . . . . . . . . 9.9 9.10 Asbestos Survey . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.10 9.11 Lead Paint Testing Report. . . . . . . . . . . . . . . . . . . . . . . 9.11 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 This page was left blank intentionally. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1.0 Predesign summary statement 1.2 1.0 Predesign Summary Statement 1.1 PROJECT PARTICIPANTS This Predesign Report describes the proposed renovation of Eastman Hall at St. Cloud State University for the purpose of co-locating Student Health Services, Counseling and Psychological Services and related services. Developing the strategy for this project was a collaborative effort of dedicated faculty, leadership, staff, students and consultants. Key contributors to the Predesign effort include: St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 St. Cloud State University Planning Participants Earl H. Potter III, PhD President Steve Ludwig Former Vice President for Administrative Affairs Wanda Overland, PhD Vice President for Student Life and Development Monica Devers, PhD Interim Dean – School of Health and Human Services Corie Beckermann Director – Student Health Services Brent Nielsen, MD Medical Director - Student Health Services John Eggers, PhD Director – Counseling & Psychological Services Rob Reff, PhD Former Assistant Dean of Students for Outreach Programs Jennifer Johnson Coordinator of Alcohol Prevention and Community Programs Troy Shafer Health Educator David Bacharach, PhD Human Performance Lab Glenn Street, PhD Human Performance Lab Student Health Services Staff Counseling and Psychological Services Staff Daryl Scholz Information Technology Tim Norton Director - Facilities Management John Frischmann Facilities Construction Coordinator Architect - BWBR Rick Dahl Jason Nordling Mike Gordan Connie Cook Principal Project Manager Project Designer Medical Planner Structural Engineering – Ericksen Roed & Associates Steve Clark Structural Engineer Mechanical/Electrical Engineering – Dunham Associates Nic Igl Nathan Wriedt Mechanical Engineer Electrical Engineer Cost Estimating – Faithful + Gould John Pidgeon Jeremy Soukup Chief Estimator Senior Estimator 1.0 Predesign Summary Statement SCSU VISION STATEMENT Through active discovery, applied knowledge and creative interaction, we positively transform our students and the communities where they live and work. SCSU VISION DEFINED St. Cloud State University makes a positive, long-term impact on the lives of our students. We provide rigorous and relevant academic experiences with engaged, active learning opportunities in an intellectually vibrant, inclusive and diverse campus community. Our graduates are well-prepared to act as responsible global citizens and professionals who remain actively connected with our university. SCSU MISSION STATEMENT We prepare our students for life, work and citizenship in the twenty-first century. PREDESIGN SUMMARY This predesign is for the renovation of Eastman Hall, colocating Student Health Services (SHS), Counseling and Psychological Services (CAPS), the Human Performance Lab (HPL) and U-Choose in Eastman Hall. The project aligns with the University’s mission of preparing students for life, work, and citizenship. Specifically, our strategic focus of an Integrated Student Experience frames the OCTOBER 2011 ST. CLOUD STATE UNIVERSITY l EASTMAN HALL PREDESIGN – DESIGN REVIEW Existing St. Cloud State University – Eastman Hall design through linkages between learning in and outside of the classroom, linkages between career choices and experiential learning, work force development through partnerships and community outreach and accessible service delivery. From the inception of this work our commitment is to align the project design to support sustainability and stewardship of place by repurposing a historic facility, currently not in use, that highlights its location by the Mississippi River. This project increases square footage but not cubic footage with the use of air space in the gymnasium, resulting in increased energy efficiency and facility productivity. The co-location of these programs will address the fractured and insufficient spaces that limit our ability to serve students. In addition to creating efficiencies by co-locating SHS and CAPS, the renovation will provide students with easier access to U Choose (the campus alcohol and drug education program), health education services and HPL, in the School of Health and Human Services. It will provide an improved pharmacy, the addition of diagnostic imaging and enhanced laboratory space to support clinic functions. Improving these professional spaces will allow academic programs, such as radiologic technology, to offer more real world, collaborative experiences to students. When the renovation is completed, it is anticipated that the existing SHS location in Hill Hall will return to its original use as a residence hall and the existing CAPS clinic space in Stewart Hall and HPL program in Halenbeck Hall will be re-purposed for academic space. This work is not included in the predesign, and will be determined in more detail in the future. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1.2 PROJECT information 1.3 1.4 1.0 Predesign Summary Statement PROJECT RATIONALE AND RELATIONSHIP TO AGENCY STRATEGIC FRAMEWORK: MnSCU Strategic Framework: Ensure access to an extraordinary education for all Minnesotans: St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 • Supports redesign of the classroom experience in needed health related areas such as radiologic technology, medical laboratory science, nursing, community health, counseling and kinesiology. This includes multi-purpose spaces that are flexible and utilize technology to enhance learning. • Expansion of program space in the medical clinic, pharmacy, counseling, human performance lab, health promotion and alcohol and drug programs along with the addition of on-site radiologic imaging provides opportunities for St. Cloud Technical and Community College (SCTCC) and SCSU students to have clinical experiences, job shadowing, research opportunities, internship and practicum experiences. Because CAPS is an accredited counseling center, SCSU serves as a location for students to obtain clinical experiences to complete their academic degrees from state higher education institutions and due to space limitations, we are limited in our ability to provide this experience to more students. • Supports employer expectations that students will have applied learning experiences to better prepare them for the work force. • Supports our commitment to development of the whole student. Given the changing demographics and needs of the student body, greater integration and collaboration of programs is required. For example, we have seen an increase of 398% from 2001 to 2011 in our students with mental/emotional disabilities requesting support services. Our studentveteran population has increased from 521 students in 2011 to over 600 today. These changes require us to build partnerships and linkages throughout campus to help these students succeed. Be the partner of choice to meet Minnesota’s workforce and community needs: • Enhance collaboration with SCTCC for student services. We have seen an increase in SCTCC visits to our clinic from 18 visits in 2002 to 312 visits in 2012. • The completed project will encourage more experiential learning opportunities, preparing students for the workforce, For instance, the remodeled space will provide greater opportunities to engage students in Medical Lab Science program via shared use of our clinic labs, designed large enough to serve as a working/ teaching space. • Accommodate anticipated demand for university graduates in health sciences – projected to increase 23.27% (3,033 total new hires needed) from 2009 to 2019 for medical/radiological/ nuclear med technicians (Source: DEED analysis & DEED Labor Market Info Office, MN Employment Projections. • Strengthen ties with the local professional and medical communities including CentraCare, Central MN Heart Center, St Cloud Hospital and the St Cloud Police Department, and city of St. Cloud. • Health care remains among the top areas for job opportunities for 2010 and beyond. Registered nurses are among the top occupations in demand for all regions of Minnesota. Deliver to students, employers, communities and taxpayers the highest value/most affordable option: • The entire amount of Eastman hall’s deferred maintenance will be eliminated ($3.836 million), decreasing need for future R & R expenditures • Existing systems will be replaced with more energy-efficient systems • The building’s Facility Condition Index (FCI) will be decreased from .31 to 0.00, reducing the need to use campus R & R funds • Renovating an existing structure is more cost effective • Multi-purpose rooms will provide increased opportunity for academic collaboration • Backfilling current CAPS space in Stewart hall and HPL program in Halenbeck Hall with co-located Academic programs will aid SCSU re-organization efforts & return spaces back to academic use. • Although not on the Historic register, renovating and re-purposing this structure by adding a floor within the building has important local and regional significance. 1.0 Predesign Summary Statement Existing Building New 3rd Floor Total = 45,997 GSF (totally renovated) Program area = 58,853 GSF = 810,000 Gross Cubic Feet = 15,562 GSF = 61,559 GSF = 810,000 Gross Cubic Feet $ 9.796M Construction Cost $ 978 K Contingency $ 2.829M Escalation (to Feb. 2016) $ 3.476M Soft Costs $ 17.079M Total Project Costs 3rd Quarter 2016 Occupancy 1.3 Project Budget This capital budget request is for the renovation of Eastman Hall, co-locating Student Health Services (SHS), Counseling and Psychological Services (CAPS), Human Performance Lab (HPL) and U-Choose in Eastman Hall. The project aligns with the University’s mission of preparing students for life, work, and citizenship. Specifically, our strategic focus of an Integrated Student Experience frames the design through linkages between learning in and outside of the classroom, linkages between career choices and experiential learning, work force development through partnerships and community outreach and accessible service delivery. From the inception of this work, our commitment is to align the project design to support sustainability and stewardship of place by repurposing a historic facility, currently not in use, that highlights its location by the Mississippi River. This project increases square footage but not cubic footage with the use of air space in the gymnasium, resulting in increased energy efficiency and facility productivity. The co-location of these programs will address the fractured and insufficient spaces that limit our ability to serve students. In addition to creating efficiencies by co-locating SHS and CAPS, the renovation will provide students with easier access to U Choose (the campus alcohol and drug education program), health education services and HPL, in the School of Health and Human Service. It will provide an improved retail pharmacy, the addition of diagnostic imaging and enhanced laboratory space to support clinic functions. Improving these professional spaces will allow existing academic programs, such as radiologic technology, to offer more real world, collaborative experiences to students. When the renovation is completed, it is anticipated that the existing SHS space in Hill Hall will return to its original use as a residence hall and the existing CAPS clinic in Stewart Hall and HPL program in Halenbeck Hall will be re-purposed for academic space. The costs for any such re-purposing are not included in this project. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Project Data 1.5 O Lot 7th St. 1st Ave. 2nd Ave. 3rd Ave. Miller Pay Lot Performing Arts Center Whitney Atwood Memorial Center Sk yw ay Admissions Parking James W. Miller Learning Resources Center L Lot shs Hill Hall Public Safety Center X Lot Garvey Commons I Lot 525 Building MTC Bus Stop Administrative Services Building Kiehl Visual Arts Center D Lot Stewart Hall Centennial Hall Ritshe Auditorium 51 Barden City Park 4 Building caps Skyway Lewis House 8th St. P Lot Headley Hall Brown Hall H Lot Wick Addition American Indian Center 6 E Lot Skalicky Plaza E Lot Eastman Hall J Lot Engineering and Computing Center N Lot South Pay Lot Child Care Center Shoemaker Hall University Drive Walkway M Lot R Lot 11th St. Facilities Management G Heating Lot Plant J Lot TO S ELKE FIELD Univ ersity Bridg e G Lot Hydroelectric Plant Student Rec. Ctr. 8 eastman hall Chiller Plant hpl Halenbeck Hall Riverview IPP Richard Green House Robert H. Wick Science Building SISS V Lot 9th St. F Lane Education Building DAM Husky Stadium National Hockey Center MISSISSIPPI RIVER 12th St. Husky Pay Lot 13th St. Herb Brooks Way 10 14th St. K Lot U Lo t 9 K Lot Husky Hub 11 Beaver Islands Trail Head St. Cloud City Utilities 16th St. Q Lot Bike Path nd sT rai l Husky Challenge Course Q Lot I ver Bea sla Beaver Islands 15th St. 12 ER ISELF 5 MIS South Office Center I RIV Skyway Mis siss H Lo ipp t i Riv er W alk Skyway 4th Ave. S The adjacent map highlights the location of Eastman Hall as well as the existing Student Health Services (SHS) location in Hill Hall, the existing Counseling and Psychological Services (CAPS) location in Stewart Hall, and the existing Human Performance Lab (HPL) in Halenbeck Hall. Mitchell Hall Women's Center 6th St. B Lot Lawrence Hall 2 Ervin House Sherburne Hall A-2 Lot Case Hall N Benton Hall Stearns Hall 4th Avenue Parking Ramp (public) A-A Lot A S Lot Stateview South C Lot 5th St. B North Benton Hall A-1 Lot Holes Hall A-3 Lot Stateview Lot G Lot Eastman Hall is centrally located on campus for ease of access, and offers great views of the Mississippi River and access to the riverside biking/walking path. It is also located near a mass transit line, a critical mass of student housing, and health-related academic departments. C Stateview North 1 7 1.6 CAMPUS PLAN D 3rd Ave. S With the space needs identified in this predesign, there is currently no other existing space on campus (other than Eastman Hall) that could accommodate the required space to achieve the goal of consolidation of healthcare services as outlined in this document. Compared to the cost of building a new building for approximately $25.03 million, the investment in renovating this well sited and structurally sound building will provide great value, and many more years of use to an 83 year old building that is currently highly underutilized. 4th Ave. C XX Lot Lot 3 1.5 ALTERNATIVE OPTIONS 4th St. P Lane St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 E O Lane It is anticipated that the funding for the remainder of the design phases and construction would be pursued with the Minnesota Legislative bonding bill in 2014, with construction beginning in the third quarter of 2015. A 12 month construction period is expected, so the midpoint of construction would be about February 2016, with completion scheduled for the third quarter of 2016. Coborn Plaza Apartments and Welcome Center Downtown V Lot 1.4 Project SCHEDULE 5th Ave. 1.0 Predesign Summary Statement C ommunity G arden 1.6 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2.0 Project background narrative 2.2 2.0 Project Background Narrative 2.1 statutory and other requirements Since there have been no prior funding requests for this project, there are no previous statutory requirements tied to this project. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 The following requirements will apply to the project after funding approval: • MS 16B.32 Energy Use • MS 16B.325 Sustainable Building Guidelines • MS 16B.326 Heating and Cooling Systems; State Funded Buildings • MS 16B.335 (1a) Construction/Major Remodeling Review (Legislature) • MS 16B.335 (1b) Project Exempt From this Review (Legislature) • MS 16B.335 (2) Other Projects (Legislative Notification) • MS 16B.335 (3) Predesign Requirement (Administration) • MS 16B.335 (4) Energy Conservation Requirements (Agency) • MS 16B.335 (5) Information Technology Review (Office of Technology). visits. Eastman’s location in relationship to healthrelated academic programs not only addresses the space needs for the provision of quality student health care services, but also provides for rich integrated academic partnerships for students. 2. An extraordinary education is one that prepares students for life, work, and citizenship. This includes the development of the whole person who is able to manage their health and well-being. Mental and 2.2 project RATIONALE There are three basic elements in the project rationale: 1. The framework which informs strategic plans for the university is the Integrated Student Experience facilitated by rethinking of our programs and activities across the institution with embedded needs for spatial reconfiguration. Eastman Hall is in close proximity to academic buildings housing health-related programs such as nursing, radiologic and medical technology, counseling and community health. Opportunities for increased experiential training and outside the classroom learning will provide a richer academic experience and better prepare our students for employment in the future. For example, the addition of an x-ray unit in Eastman would provide radiologic technology students with on-campus job shadowing opportunities, access to x-ray equipment to practice imaging of test objects, the ability to coordinate outside the classroom learning about x-ray equipment installation, maintenance, and repairs. Additionally, students could participate in quality assurance testing and regulatory agency SHS Pharmacy Window 2.0 Project Background Narrative Stewart Hall Corridor Map of Off Campus Services Connections 1. St. Cloud State University 10 11 12 2. Psychology Associates 1.0 miles 16 17 7 5 9 3. CentraCare Clinic 13 15 4 3 1.8 miles 4. St. Cloud Hospital 2.0 miles 5. CentraCare Clinic 2.5 miles 6. Solutions Behavioral Healthcare 3.0 miles 6 2 7. Center for Family Counseling 3.2 miles 14 8. St. Cloud Medical Group South Campus 1 3.3 miles 9. VA Medical Center 4.7 miles 10. St. Cloud Medical Group North Campus 5.5 miles 11. Center for Diagnostic Imaging 5.5 miles 12. CentraCare Surgery Center 5.6 miles 13. St. Cloud Tech. Community College 14. City of St. Cloud 15. Central Minnesota Heart Center 8 16. Whitney Senior Center 17. St. Cloud YMCA St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 physical health issues can have a profound impact on students’ ability to engage fully in the opportunities presented to them while in college. These issues affect their physical, emotional and cognitive wellbeing and can lead to poor academic performance and lower graduation rates. Our integrated care approach in assisting students in the form of a case worker and Behavioral Intervention Team has resulted in saving of student lives. However, our progress is impeded because our fractured and insufficient spaces no longer can meet student needs and influences our delivery of quality service. The co-location of SHS, CAPS, HPL and U Choose will lead to better coordination of patient care, reduced stigma for mental health, increased access to support services and better space utilization for both SCSU and SCTCC students. 2.3 2.4 2.0 Project Background Narrative According to the 2011 American College Health Association (ACHA) - National College Health Assessment report, nearly 30% of college students have experienced stress and/or depression during the school year that made it difficult for them to function, and ultimately negatively affected their academic performance. Nearly 20% of students have experienced anxiety that negatively affected their academic performance, with 50% of those experiencing “overwhelming anxiety”. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 CAPS is currently located in Stewart Hall, which is primarily used for academic purposes. The high student traffic and loitering in the corridors between classes by students in this busy facility decrease the likelihood of students feeling comfortable accessing help because of perceived stigmas The renovation of Eastman would provide adequate space for the co-location of these programs to increase access of care by decreasing stigma. The March 2010 ACHA White Paper, Considerations for Integration of Counseling and Health Services on College and University Campuses, suggests taking a more integrated approach may provide the best foundation for providing holistic care to students, allowing better alignment of support services. 73% of survey respondents with integrated health and counseling services reported they were better able to meet student needs and their utilization of services increased by 71%. Additionally, improvements were also noted in comprehensiveness of services and programs, quality of clinical services, client satisfaction, efficiency of administrative processes and staff communication. 3. Better and more effective space is required for SHS to retain national accreditation status with the Accreditation Association for Ambulatory Health Care (AAAHC). The possibility of losing national accreditation status is a real and pending threat. In the most recent (2010) AAAHC site visit report, the surveyors included multiple comments regarding the SHS facility only partially meeting compliance standards relative to patient privacy, accessibility, inadequate heating and cooling systems and staffing ratios. “Results of the current study suggest that these centers have found integration to result in an improvement in many aspects of clinical service. Centers reported that they were more easily able to meet the demands of their students and had a more efficient utilization of their services. Most reported that their services were more comprehensive and reflected a more seamless approach to health and mental health care. While staff morale was initially sometimes negatively affected, as the model persisted, turf concerns and other related issues were subsumed by the perceived improvements in service to students. Overall, satisfaction by the consumers was reported as very high” – ACHA 2.0 Project Background Narrative In the past three years SHS has averaged a little more than 10,000 patient visits per year and CAPS has provided almost 3,600 visits per year, a 30% increase in the past five years. Of the visits listed above, SCTCC students visit SHS approximately 300 times per year. The utilization of all of these services is expected to grow based on our increasing need, an uptick in use due to the upgrade in facilities, less stigma for users and a more cohesive “one stop shop”. With Eastman Hall being located near a campus edge, it will support the master plan to push services and programs that have community connections closer to the perimeter of the campus. There will be parking stalls near the building that will be designated “visitor parking”, which will provide improved parking access It will also make access to the services offered more convenient to students who are living off-campus. By incorporating a ground floor gathering space, café, and exterior patio area overlooking the river, it will provide interior and exterior spaces that “allow and encourage lingering/gathering/incidental social interactions.” • An integrated health service facility is identified as a need in the master plan to compete with St. Cloud State’s peer institutions. • Support our commitment to sustainability by incorporating high end building systems. (see following data for more sustainability detail) • Expand links to the river emphasizing the existing river walk, will take advantage of river views and expand river oriented uses and activities. AGENDA In a 2010 comparison to peer institutions, SCSU SHS’s “student to provider” ratio based on head count was 5,309 to 1, compared to 4,334 to 1 at MN State University Mankato, 4,124 to 1 at Western Kentucky University, and 894 to 1 at Towson University. With appropriate space, additional providers could be added allowing better access to care and improved “student to provider” ratios. Introductions Goals & Objectives Predesign An accreditation visit was made was 2010. The Understanding resulting report pointed out several deficiencies, such as inadequate “student/provider” ratio, poor provisionsof for privacy and improper accessibility. Recap previous When the accreditation team returns in July, 2013, it will be important to demonstrate progress meeting comments toward addressing these concerns. Technology 2.3 RELATIONSHIP TO 2010 AGENCY COMPREHENSIVE PLAN Sustainability This project supports many of the items discussed in the Concept Plans 2010 campus master plan. OCTOBER 2011 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 SHS is currently housed on the ground floor of Hill Hall in space that was formerly a student residence hall, a space not originally designed to deliver these services. Among the issues with the existing space: a “hidden” clinic entrance on the back side of the building, inadequately-sized spaces, an inefficient layout, lack of storage space, ambulance access issues and a lack of space for growth such as imaging and specialist provider exam space. Recently, as many as 250 x-ray studies and 800 specialist consultations were sent off-campus. This required students to find transportation to off campus sites that many times are not conveniently served by public transportation. 2.5 2.6 2.0 Project Background Narrative 2.4 SPACE UTILIZATION St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 The Eastman Hall building was originally designed and used as an athletic facility for the campus. Currently, the building is closed and is not being utilized at all. The building is not being utilized based on a number of factors including: lack of accessibility (toilet rooms, no elevator, etc.), lack of appropriate classroom spaces, poor heating and cooling systems, and poor technology infrastructure. The renovated space will dramatically increase the quality of the spaces, and also the utilization of the building.In future projects, Hill Hall space vacated by Student Health will be returned to use as a residence hall, Stewart Hall space vacated by Counseling and Psychological Services will be returned to academic use, and the space in Halenback Hall vacated by the Human Performance Lab will be returned to academic use. 2.5 FACILITY SYSTEMS SUMMARY The existing Eastman Hall building was originally constructed in 1929 to serve as the primary athletic facility on the St. Cloud State campus and has a current FCI score of .31. It is a three story steel and concrete framed structure with uninsulated brick exterior walls, and non-structural brick walls separating the gymnasium spaces. According to the existing drawings, the floor to floor height from first to second is 13’-0”, between second and third is 12’-7”, and third floor clearance is 8’-6”. Eastman Hall currently houses a pool (closed to use in 2009), locker rooms, and office space on the first floor, a large central gymnasium with smaller flanking gyms on the second floor, and a bleacher mezzanine in the large gymnasium and some small office suites on the third floor. There are some hazardous materials that will need to abated before any of the interior selective demolition takes place. The hazardous materials testing reports are included in the appendix for reference. PCB containing transformers were replaced in 1986, and some asbestos was abated in the building in 1993. The building exterior was refurbished most recently in 1989, and appears to be in good condition. The roof was partially replaced in 1999 and 2006, so should not need replacement until 2039 at the earliest. As indicated in the Comprehensive Campus Plan, the existing building is marginally suitable for use in its current state, and will need to undergo significant renovation to be reused. Renovations will include replacement of all exterior window and door systems, and added insulation. As noted 2.0 Project Background Narrative South façade showing the extent of window replacement required. Close up of the southernmost east entrance. Light fixtures and aluminum entrances will be replaced. The grade will be altered to make this entrance accessible via a new east plaza. OCTOBER 2011 Hall HALL West facade/entrance. New windows will be ST. CLOUD STATE UNIVERSITY l Eastman EASTMAN PREDESIGN – DESIGN REVIEW installed where the tall arch topped windows previously existed. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 in the included mechanical and electrical narratives the entire heating and cooling system, controls, plumbing, electrical service and distribution, lighting, and fire alarm system will be replaced with new systems that are compliant with current building codes and sustainability requirements. 2.7 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2.8 2.0 Project Background Narrative Existing “cellar” doors to the basement level. These should be replaced if this entrance will be maintained. Existing area well grates on the south side. East façade showing the extent of window replacement required. 2.0 Project Background Narrative Entrance door on the south end of the east side of Eastman Hall that will exit onto the new plaza. North façade of the building showing the extent of window replacement required. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Entrance door on the east side of Eastman Hall that will be used for staff and ambulance access. This area will be regraded and sidewalk will be added. 2.9 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2.10 2.0 Project Background Narrative Partial north façade. Close up of typical window openings on the north side of Eastman Hall. The existing windows and glass block will all be replaced with new thermally broken aluminum windows. 2.0 Project Background Narrative Existing north-south corridor in the office area on the west side of the 1st floor. Existing unused classroom on the 2nd floor. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Existing primary north-south corridor on the 1st floor with terrazzo flooring. 2.11 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2.12 2.0 Project Background Narrative Existing classroom on the 1st floor. This is the only functioning room in the building. Existing classroom on the 1st floor. 2.0 Project Background Narrative Existing locker room space on the south end of the 1st floor. Existing pool on the 1st floor – looking south. The existing pool deck is several feet below the 1st floor, and will be built up to support a new floor at the same elevation as the existing 1st floor. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Existing locker room space on the south end of the 1st floor. 2.13 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2.14 2.0 Project Background Narrative Existing pool on the 1st floor – looking north. Existing secondary gym space (fitness center) on the 2nd floor – looking east. These smaller gyms are located north and south of the main gym space on the 2nd floor. 2.0 Project Background Narrative Existing primary gym space on the 2nd floor – looking east. The mezzanine seating will be removed and replaced with a new floor which will divide the existing two story space into two floors. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Existing main gymnasium space on the 2nd floor – looking west. Windows will be re-installed in the existing openings of the west wall. 2.15 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2.16 2.0 Project Background Narrative Existing basement area. The concrete floor slab was added in place of the original dirt floor. Note the partially exposed column footings, which will be stabilized to support the loads of the new 3rd floor. Existing stairway from the 1st floor to the basement mechanical space. Existing basement area. 2.0 Project Background Narrative This predesign is based upon conformance with the following current building codes and standards. A complete code review will be required during the design phase of the project. Current codes and standards include: • International Building Code (IBC), 2006 Edition • MN Amendments to the IBC, 2007 Edition • MN Accessibility Code, MN Rules Chapter 1341 • MN Energy Code, MN Rules Chapter 1323 • International Fire Code (IFC), 2006 Edition • MN Amendments to the IFC, 2007 Edition • International Mechanical Code (IMC), 2006 Edition • MN Amendments to the IMC, 2009 Edition • MN State Plumbing Code, 2009 Edition • National Electrical Code, 2008 Edition • Americans with Disabilities Act (ADA) • Guidelines for the Rehabilitation of Existing Buildings (GREB), 2000 • B3 MN State Sustainable Building Guidelines • MnSCU Design Standards Accessibility for the building will be vastly improved by this project. These improvements include making all of the existing first floor building entrances accessible, the addition of elevators, and new accessible toilet rooms, locker rooms, and showers. 2.7 Sustainability highlights The most important sustainability concept for this project is that it involves the reuse of an existing building and site. Because this project is a renovation of an existing building, it will most likely not comply with State of Minnesota B3 requirements, but will utilize sustainable measures where possible. These measures include: • Replacement of existing single pane windows with high performance thermally broken windows. • The addition of insulation to the interior of all exterior walls to improve energy efficiency and thermal comfort. • Low flow plumbing fixtures. • Variable air volume air handling systems to minimize air transport energy. • Energy recovery of exhaust air. • High efficiency, variable flow heating hot water systems. • New lighting systems which will include high efficiency fixtures, occupancy sensors, and time sweep controls. • Daylight harvesting, especially the areas on the east and west side of the building with the largest window areas. • Building commissioning. Geothermal systems were discussed, but will not be viable because the building footprint covers a majority of the available site area. Photovoltaics could be explored, but will involve further study into the existing roof structure capacity to determine feasibility. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2.6 Code Summary 2.17 This page was left blank intentionally. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.0 Project description 3.2 3.0 Project Description 3.1 site Eastman Hall is located in the east central zone of the campus along the Mississippi River, and is bounded by 1st Avenue on the west and University Drive on the south. Its central location makes it accessible equally from all points of campus, and its adjacency to University Drive makes it a very visible building. The site is identified in the Comprehensive Campus Plan as a “secondary gateway” to the campus. After renovation, the building occupants will have great views of the river, and access to the adjacent river walk. If possible, space should be provided in the existing “J” lot south of the building for staff and short term parking for patient and facility use. Ambulance access will be provided from the parking area that currently exists on the east side of the building. M is s is s ip 1st Ave p i R ive r St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 The building is across the street from the Wick Science Building and a bus stop, which will allow easy access by students in the Health Sciences programs, and it is also close to Shoemaker Hall, which is home to about 325 students. The new location of the Student Health and Related Services will also make it more convenient to students who may be injured while involved in activities in nearby Halenbeck Hall. Eastman Hall U n i ve r s i t y D r i ve St. Cloud State University Campus Map 3.0 Project Description Riverview Wick Science Building Bus Stop 1st Ave Ambulance Access Eastman Hall VIEWS Mi ss iss ipp iR i ve r Repurposed existing parking for Student Health Shoemaker Hall Eastman Hall Site St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Brown Hall 3.3 This page was left blank intentionally. 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.2 existing floor planS Basement Level SWIMMING POOL MECHANICAL ROOM B2 STORAGE B1 UP UP UP Area to be completely renovated 0 St. Cloud State University Eastman Hall (EH) Floor : Basement Date : October 20, 2011 E N S W 1”=20’ 3.5 10 20 30 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.2 existing floor planS Level 1 UP UP DOWN DOWN SHOWER 102C TOILET 107D SHOWER 107E SWIMMING POOL 105 TOILET 102B MENS LOCKER ROOM 107 CUST. STOR. 107C SAUNA 102A RAMP DOWN WOMENS LOCKER ROOM 102 OFFICE 103 TOILET TOILET SAUNA 107B OFFICE 106 JAN. DOWN STORAGE 125 TOILET 107A CORRIDOR 16B UP UP STORAGE 104 OFFICE 116 OFFICE 114 OFFICE 112 OFFICE 115 OFFICE 113 OFFICE 111 OFFICE 110 OFFICE 118 TOIL. CLASS ROOM 101 OFFICE 117 OFFICE 109 Area to be completely renovated VEST VEST OFFICE 121 OFFICE 119 TOIL. OFFICE 120 0 St. Cloud State University Eastman Hall (EH) Floor : First Date : October 20, 2011 E N S W 1”=20’ 3.6 10 20 30 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.2 existing floor planS Level 2 DN DN UP UP GYMNASIUM 201 FITNESS CENTER 204 MAIN GYMNASIUM 203 UP UP DN DN CLASS ROOM 202 CLASS ROOM 205 Area to be completely renovated 0 St. Cloud State University Eastman Hall (EH) Floor : Second Date : October 20, 2011 E N S W 1”=20’ 3.7 10 20 30 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.2 existing floor planS Level 3 DN DN C D UPPER FITNESS CENTER UPPER GYMNASIUM BALCONY 42A UPPER MAIN GYMNASIUM BALCONY 42B DOWN DOWN 303 304 OFFICE 301 Area to be completely renovated OFFICE 302 OFFICE 305 OFFICE 306 TOILET TOILET 0 St. Cloud State University Eastman Hall (EH) Floor : Third Date : October 20, 2011 E N S W 1”=20’ 3.8 10 20 30 This page was left blank intentionally. 3.10 3.0 Project Description 3.3 PROJECT SCOPE and Program The planning process for this predesign involved many rounds of meetings with all of the groups included in the space program in order to determine the extent of their space needs and optimal location and adjacencies. The concept planning options in this section reflect the culmination of those discussions. Many other options that were studied are included in the appendix at the end of this document, as well as the minutes from the planning meetings. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 The proposed building program consists of 58,853 s.f. which includes: • Student Health Services: 19,897 s.f. • Counseling and Psychological Services: 9,982 s.f. • Building support, storage, mechanical, and electrical spaces: 8,320 s.f. • U Choose and Health Education spaces: 6,565 s.f. • Common areas such as gathering space, café, retail, check-in and reception, multipurpose room, and restrooms: 7,029 s.f. • Human Performance Lab: 5,159 s.f. • Pharmacy space: 1,901 s.f. The first floor of the building will house a large gathering/ social space near the building entrance that will include seating and interactive digital health kiosks, a classroom for 30-40 people, and a multi-purpose room that can be used as a classroom or conference space as well as for activities and student services. It will also include a pharmacy, and a café/retail space for serving healthy food and beverages that will have views to the river to the east and access to an exterior patio space. A digital radiography room will also be located on the first floor, and it will be large enough to allow small classes to engage in various learning activities within the space. The Student Health Services area is anticipated to be located on the second floor of the building in what is currently the gymnasium spaces, and includes space for 15 exam rooms, 4 consultation rooms (can be used as future exam rooms), 4 nurse station areas, a shared office for up to 3 physicians, a shared office for up to 3 nurse practitioners, a shared office for up to 2 physician assistants, waiting space for up to 25 people, administrative offices, and all needed support spaces. In addition, at least one of the consultation rooms will be set up as an “E-exam” space that can be used for video consultation with off-campus specialists, and students traveling abroad. Ambulance access will be from the first floor, and utilize the new service elevator. A lab to support the clinic will be located adjacent to the clinic on the second floor. The Counseling and Psychological Services (CAPS) area will be located on the newly constructed third floor of the building along with the U Choose and Health Education areas. Because a variety of uses are located on the third floor and the use of the adjacent spaces is less intensive than Stewart Hall where Counseling and Psychological Services is currently located, patients accessing this area will have greater anonymity than if it had its own isolated area in the building. This will, in turn, help to de-stigmatize the counseling area, and make the use of these services more appealing to the student body. The CAPS area includes space for 10 clinical therapy offices, two alcohol and other drug counselors, two graduate assistants, 4 practicum interns, a psychiatrist office, two mid-level practitioners, two case managers, two case manager interns, a large group therapy room, and all needed support spaces. It is anticipated that the psychiatrist will utilize the Student Health Services clinic for exams. The final space program is included on the following pages. For clarity, spaces used for academic purposes are highlighted and account for approximately 6% of the overall program space. Total Program: 58,853 BGSF 34% Student Health Services 17% Counseling & Psychological Services 14% Building Support 12% Common Areas 11% U Choose/Health Education 9% Human Performance Lab 3% Pharmacy 3.0 Project Description SUMMARY SCSUPROGRAM STudent health Related services Program Summary Component/Area Total NASF Bldg Grossup Total GSF 1 Common Area/Building Support 13,800 1.25 17,249 2 Student Health Services 15,919 1.25 19,898 3 Counseling & Psychological Services 7,985 1.25 9,982 4 U Choose & Health Education 5,252 1.25 6,565 5 Human Performance Lab 4,128 1.25 5,159 Program Total 47,083 NASF 58,853 GSF Basement 10,347 * 14,541 1st Floor 13,818 14,822 2nd Floor 13,807 14,597 3rd Floor 1,212 2,038 Existing Eastman Hall Existing Total 39,184 NASF * Minus crawl spaces and pool 2012-10-02 SCSU Program.xlsx Page 1 45,997 GSF St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 SCSU STUDENT HEALTH RELATED SERVICES 3.11 3.12 3.0 Project Description Section 1 SCSU Student Health Related Services Summary Information Section 1 Room/Area Unit Total NSF NSF Comments St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1.1 Common Areas Check-In/Reception Self Check-in Kiosk Multipurpose Room Commons Area/Intro Waiting Area Public Restrooms Lactation Room Locker/Shower Rooms Triage Room Treatment Room Gathering Space/Café/Retail 1 7 1 1 2 1 2 0 3 1 300 20 650 200 200 75 350 100 120 1500 Subtotal 300 140 650 200 400 75 700 0 360 1,500 4,325 Building general Health and Counseling Services combined Conferences, classes, large meetings, dividable. NSF 1.2 Pharmacy Waiting OTC Retail Sales Prescription Pick-up/Drop-off Dispensing/Computer Work Stations Drug Storage Pharmacist Office Consultation Room Record Storage 1 1 3 3 1 1 1 1 180 120 60 60 180 90 90 150 Subtotal 180 120 180 180 180 90 90 150 1,170 Room/Area Unit NSF Total NSF Waiting for 10-12 Integrate with waiting Semi-private 1 Pharmacist and 2 Techs. 3'-4' of counter space each. Need storage for vials, bottles. etc. Adjacent to pick up/drop-off. Adjacent to pick up/drop-off. NSF Comments 1.3 Info Technology I.T. Office Data Closets 1 3 80 80 80 240 320 Subtotal NSF 1.4 Building Support Storage Mechanical Electrical Data Clean Holding Soiled Holding 2012-10-02 SCSU Program.xlsx Receiving Custodial Trash Recycling 1 1 1 1 1 1 1 1 1 1 80 3150 500 150 150 150 300 120 100 100 80 3,150 500 150 150 150 Page 300 2 120 100 100 4,800 NSF Subtotal 10,615 NSF Total 13,800 NASF Subtotal END OF SPACE PROGRAM 1.30 i 1 Section 3.0 Project Description Section 2 3.13 SCSU Student Health Related Services Section 2 Room/Area Unit NSF Total NSF Comments 2.1 Patient Reception / Business Office/Administration SHS Director's Office SHS Associate Director Office SHS Administrative Assistant Work Room Cashier Insurance Billing / Coder Insurance Advocate 1 1 1 1 3 2 1 150 120 100 120 60 120 120 150 120 100 120 180 240 120 1,030 Subtotal Includes space for conferencing. NSF 2.2 Medical Records Inactive Storage Supply Storage 1 1 50 100 50 100 150 Subtotal NSF 2.3 Student Health Services Waiting Room Appointment Desk Conference Room MD Office NP Office PA Office Medical Directors Office Nursing Manager (RN) Referrals/Manager's Office Work Room Exam Rooms Consult Rooms Nursing Station Triage Nurse Observation (IV's) Procedure Room Injection Room 2012-10-02 SCSU Program.xlsx 1 2 1 1 1 1 1 1 450 60 300 150 180 120 150 90 450 120 300 150 180 120 150 90 1 1 18 4 4 2 1 1 1 150 120 110 110 150 110 110 200 110 150 120 1,980 440 600 220 110 200 110 Page 4 Seating for 25 people. 20 people. Shared office for 2 MD Open area for 3 NP Open area for 2 PA 2-3 per provider 1 E-Exam Window preferred Near Lab & Nurse Station St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Summary Information 3.14 3.0 Project Section 2 Description Room/Area Supply Storage SCSU Student Health Clean Utility Soiled Holding Patient Toilets Summary Information Staff Break room Section (cont’d) Building2Services Subtotal Unit NSF 1 150 1 4 1 1 100 65 500 40 Related Services 1 150 Room/Area Unit NSF Total NSF 150 150 100 260 500 40 Total NSF 6,690 Comments Autoclave Share with counseling Comments NSF 2.1 Patient Reception / Business Office/Administration 2.4 Laboratory St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Lab Subwait SHS Director's Office Reception SHS Associate Director Office Phlebotomy Work Space SHS Administrative Assistant Phlebotomy Stations Work PatientRoom Toilet Staff Toilet Cashier Lab Insurance Billing / Coder Office Insurance Advocate Storage 1 1 1 1 1 1 2 1 1 3 1 2 1 1 1 150 150 60 120 120 100 110 120 65 65 60 400 120 90 120 120 1,030 Subtotal Subtotal 1,290 2.2 Records 2.5 Medical Radiology Inactive Storage Supply SubwaitStorage Radiography Exam Room Dressing Room Subtotal Toilet Technician Work Room Control Area 2.3 Student Health Viewing/Consultation Storage Waiting Room Wheelchair Storage Appointment Desk Conference Subtotal Room MD Office NP Office PASubtotal Office Medical Directors Office Nursing Manager (RN) 150 150 60 120 120 100 220 120 65 65 180 400 240 90 120 120 Services Total Referrals/Manager's Office Work Room Exam ENDRooms OF SPACE PROGRAM Consult Rooms Nursing Station Triage Nurse Observation (IV's) Procedure Room Injection Room 2012-10-02 2012-10-02 SCSU SCSU Program.xlsx Program.xlsx 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 50 50 100 100 120 120 450 450 75 75 150 65 65 100 100 100 100 75 75 100 100 450 450 25 25 60 120 300 300 1,110 150 150 180 180 120 10,270 120 150 150 1.55 90 90 1 150 1 120 18 110 Section 2 4 110 4 150 2 110 1 110 1 200 1 110 15,919 150 120 1,980 440 600 220 110 200 110 Page Page 4 5 For 8 people Includes space for conferencing. 2 Technicians Semi-private Unisex, connected to Lab, with exhaust fans. Unisex, connected to Lab, with exhaust fans. NSF NSF For 6 people Sized for academic use - student observation NSF Alcove. No PACS Seating for 25 people. 20 people. NSF Shared office for 2 MD Open area for 3 NP Open NSF area for 2 PA NASF 2-3 per provider 1 E-Exam Window preferred Near Lab & Nurse Station 3.0 Project Description Section 3 3.15 SCSU Student Health Related Services Section 3 Room/Area Unit NSF Total NSF Comments 3.1 Counseling Waiting Room Work Room Administration Support File & Archive Storage Storage/AV Storage Directors Office Associate Directors Office Clinical Therapy Offices AOD Counselor Grad Assistant Practicum Intern Psychiatrist Mid Level Psychiatric Practitioner Case Manager Case Manager Intern Conference Room Group Room Testing/Biofeedback/SAD/ Relax. Staff Toilet Patient Toilet 1 1 1 1 1 1 1 10 2 2 4 1 2 2 2 1 1 3 2 2 550 200 160 200 75 150 120 150 150 120 120 150 120 150 120 200 250 100 65 65 550 200 160 200 75 150 120 1,500 300 240 480 150 240 300 240 200 250 300 130 130 25-30 People 8 File Cabinets + 1 or 2 more Includes space for conferencing. 3 currently, grow to 4 Near Health Services. Share exam with Health Services. 12 People Need space for 8-12. More square in plan than rectangular Comfortable/Blackout window shades/noise control Subtotal 5,915 NSF Total 7,985 NASF END OF SPACE PROGRAM 2012-10-02 SCSU Program.xlsx 1.35 Section 3 Page 6 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Summary Information 3.16 3.0 Project Description Section 4 SCSU Student Health Related Services Summary Information Section 4 Room/Area Unit NSF Total NSF Comments St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 4.1 Health Education/ U Choose Student Services Health Educator Offices U Choose Administrator Office Coordinator Office Offices 2 1 2 3 120 120 100 100 240 120 200 300 Health Promotion Marketing Peer Ed. Area Resource Area/Husky Neighbors Storage Space Classroom Graduate Assistant/Student Workspace 1 1 1 1 1 1 120 350 500 400 700 850 120 350 500 400 700 850 Staff Toilet Student Toilet 2 2 65 65 130 130 Dietician, Grad Assistant Suicide Prevention, Community Outreach. 8-10 Peer Ed. (Coop with Husky Neighbors) TV, 12-15 people per group, Relaxed feel. 40 Students (22 hrs./wk) Tables & Chairs 16-20 workers. "War Room", Kitchenette Subtotal 4,040 NSF Total 5,252 NASF 1.30 END OF SPACE PROGRAM Section 5 Section 4 SCSU Student Health Related Services Summary Information Section 5 Room/Area Unit NSF Total NSF Comments 5.1 Human Performance Lab Reception/Waiting Offices Conference/Resource Room Underwater weigh room 1 3 1 1 150 120 200 150 150 360 200 150 Locker/Shower Exam Room Lab Metal/Wood Workshop Electronics Workshop 0 2 1 1 1 150 120 250 385 60 0 240 250 385 60 Physiology Testing Room Graduate Student 2012-10-02 SCSU Program.xlsx Storage Toilet 1 1 1 2 350 750 150 65 350 750 Page 7 10 Graduate Students 150 10 Graduate Students 130 Used for academic conferences and resources Connected to Locker/Shower Under counter refrigerator, vented hood, storage. Subtotal 3,175 NSF Total 4,128 NASF END OF SPACE PROGRAM 1.30 Section 5 3.0 Project Description Final DESIGN CONCEPT Proposed build out of Existing Basement Level NOTES: -MECHANICAL, STRUCTURAL & EXISTING BUILDING CONSTRAINTS GENERAL BUILDING STORAGE NEED TO BE FIELD BUILDING SERVICE VERIFIED IN ORDER TO DETERMINE THE AHU - 2 AHU - 1 MECHANICAL (2) AHUs IMPACT ON THE TOTAL PROGRAM HUMAN PERFORMANCE LAB WORKSHOP MEDICAL STAFF LOCKERS / TOILETS / SHOWERS RECORD S DATA FUNCTIONAL LEGEND COMMON AREA PHARMACY LABORATORY ELECTR ICAL MEDICAL RECORDS INFORMATION TECHNOLOGY HUMAN PERFORMANCE LAB MECHANICAL SUPPORT SHS RADIOLOGY CAPS HEALTH ED. / U CHOOSE STUDENT SERVICES HUMAN PERFORMANCE LAB LEVEL B UNUSABLE SPACE TO BE VERIFIED NON-BUSINESS HOURS ACCESS Level B St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.4 DESIGN CONCEPTS 3.17 3.0 Project Description EXTENT OF FLOOR INFILL CONSTRUCTION FOR LEVEL 1 SERVICE ENTRY / AMBULANCE ACCESS PLAZA ENTRY NOTES: -EXISTING POOL & SURROUNDING AREA TO BE FILLED IN. TWO STORY SPACE ABOVE RECEIVING / CLEAN/ SOILED / CUSTODIAL / TRASH / RECYCLING / BIOHAZARD STORAGE GATHERING SPACE CAFÉ, RETAIL RADIOLOGY PHARMACY BLDG SERV CMFRT CLASSROOM DATA ELEC PUBLIC TOILETS INFO RECEPT PUBLIC TOILETS SHS ADMIN OFFICES RETAIL FUNCTIONAL LEGEND COMMON AREA PHARMACY LABORATORY GATHERING SPACE/ INTERACTIVE KIOSKS MEDICAL RECORDS INFORMATION TECHNOLOGY SUPPORT SHS MULTI-PURPOSE ROOM BUSINESS OFFICE INS ADVOC CASHIER RADIOLOGY CAPS HEALTH ED. / U CHOOSE STUDENT SERVICES LEVEL 1 HUMAN PERFORMANCE LAB UNUSABLE SPACE TO BE VERIFIED NON-BUSINESS HOURS ACCESS MAIN ENTRY MAIN ENTRY Level 1 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Final DESIGN CONCEPT Proposed build out of Existing Level 1 3.18 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Final DESIGN CONCEPT Proposed build out of Existing Level 2 TWO STORY SPACE STUDENT HEALTH SERVICES LABORATORY DATA ELEC BLDG SERV FUNCTIONAL LEGEND CHECK-IN/ RECEPTION CHECKIN KIOSKS COMMON AREA PHARMACY LABORATORY MEDICAL RECORDS INFORMATION TECHNOLOGY SUPPORT SHS RADIOLOGY CAPS EXAM TRIAGE #3 STUDENT HEALTH SERVICES 580 DGSF EXAM EXAM #2 #1 HEALTH ED. / U CHOOSE STUDENT SERVICES HUMAN PERFORMANCE LAB 3.19 STUDENT HEALTH SERVICES STUDENT HEALTH SERVICES LEVEL 2 UNUSABLE SPACE TO BE VERIFIED NON-BUSINESS HOURS ACCESS Level 2 3.0 Project Description EXTENT OF NEW FLOOR CONSTRUCTION FOR LEVEL 3 EXISTING STAIR TO LEVEL 3 EXISTING STAIR TO LEVEL 3 NOTES: -EXISTING 2 STORY HEIGHT SPACE ON LEVEL 2 WILL BE SPLIT TO ACCOMMODATE COUNSELING FLOOR IN-FILL FOR LEVEL 3. COUNSELING MECHANICAL (1) AHU DATA ELEC AHU - 3 U CHOOSE & HEALTH EDUCATION APPT DESK CAPS WAITING (15-20 PPL) BLDG SERV FUNCTIONAL LEGEND EXISTING STAIR TO LEVEL 3 COMMON AREA PHARMACY LABORATORY MEDICAL RECORDS INFORMATION TECHNOLOGY SUPPORT SHS U CHOOSE & HEALTH EDUCATION U CHOOSE & HEALTH EDUCATION RADIOLOGY BUILD OUT OF EXISTING LEVEL 3 CAPS HEALTH ED. / U CHOOSE STUDENT SERVICES HUMAN PERFORMANCE LAB UNUSABLE SPACE TO BE VERIFIED CLASSROOM EXISTING STAIR TO LEVEL 3 DASHED LINE INDICATES EXTENT LEVEL 3 BUILD OUT OF EXISTING LEVEL 3 OF FLOOR IN-FILL IN FILL FOR LEVEL 3. 3 NON-BUSINESS HOURS ACCESS Level 3 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Final DESIGN CONCEPT Proposed build out of Existing/New Level 3 3.20 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Clinic Options Option 1 – Traditional Clinic Model SCALE: 1/16”=1’-0” 3.21 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Clinic Options Option 2 – Core Clinic Model (Preferred Model) SCALE: 1/16”=1’-0” 3.22 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Clinic Options Option 3 – Core Clinic Model SCALE: 1/16”=1’-0” 3.23 3.0 Project Description 3.0 Project Description NEW FLOOR 3RD LEVEL 2ND LEVEL 1ST LEVEL EXISTING FLOOR SLAB NEW FLOOR SLAB INFILL NEW PLAZA BASEMENT EXISTING POOL TO BE INFILLED | EASTMAN HALL RENOVATION 3.2011111.00 08.01.2012 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 proposed section Addition of Levels 3.24 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Concept Images 3.25 Plaza St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.26 3.0 Project Description East Plaza Image East Plaza Image 3.0 Project Description Overview Eastman Hall was built in 1929 as a physical education building. It contains three gymnasiums, a pool, locker rooms, and classrooms. SCSU Health and Counseling Services proposes to renovate this building for use in health care and counseling. The renovations include adding a new floor between the roof and the gymnasium floors, creating new openings for elevators, mechanical shafts and open spaces, and removing substantial portions of the masonry walls that surround the main gymnasium to improve circulation. Existing Structure The existing building was designed by C. H. Johnson in 1929 and consists of three structural floors and roof framing. The Basement Level, at EL 83'-0" and 85'-0", consists of a slab on grade. At some time in the past, the original dirt floor at the western portion of the building at EL 91'-6" was replaced by a concrete slab on grade at EL 85'-0". Thus, the new slab was located at approximately the bottom of footing elevation of the adjacent columns. A retaining wall structure was constructed near the western exterior wall to retain soil around the wall footing since it is located at EL 91'-6", well above the new floor level. The dirt floor at the northeastern section of the basement was also replaced with slab on grade, and the sloping areas of the floor were replaced with CMU walls. Level 1, at EL 96'-6", consists of concrete joists and beams with a 2 1/2" top slab. Level 2, at EL 109'-6", consist of a similar concrete joist beam system, and includes steel beams encased in concrete over the pool area. Level 3, at EL 121'-8", consists of a relatively small area of the concrete joist and beam system. The new structural floor will be constructed at this elevation. The roofs over the small gymnasiums, at EL 131'-2"and 130'-8", consist of concrete joist and beam system, with steel beams encased in concrete for the major spans. The roof over Main Gymnasium consists of steel trusses that span approximately 80' supporting purlins spanning between trusses. The purlins support metal deck. The truss depth varies from approx 7' to 9'. New Structural Floor At Level 3 in both the Main and adjacent gymnasiums, a new floor will be constructed between the existing gymnasium floors and the roof. The structure will consist of composite steel beams supporting 2" composite metal deck and 2.5" light weight concrete. Beams will be supported by steel columns located over existing concrete columns. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Schematic Structural Narrative Renovation of Eastman Hall for SCSU Health and Counseling Services St. Cloud State University 3.5 Systems Narrative – Structural St. Cloud, Minnesota 3.27 3.28 3.0 Project Description Modifications to Existing Structure St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 In order to create the desired open space above the Level 1 Gathering Space/Café/Retail area, five individual openings approximately 9' square will be cut through the existing concrete joists. The openings will be located in front of the large windows, and will allow the existing concrete encased steel beams to continue through to the east wall. At the existing pool, the area within the pool walls will be filled with sand or flowable fill, and a new slab on grade will be constructed. The pool walls will be extended up to the Level 1 elevation with CMU. The area surrounding the pool will be framed at the Level 1 elevation with steel beams and composite deck similar to the new floor at Level 3. The existing pool walls with the CMU extension will act as bearing walls for this framing. Depending on the capacity of the existing concrete columns, it may be necessary to demolish the existing concrete slabs that form the bleachers along the west side of the pool to help offset some of the new loads . The repurposing requires new elevator shafts and mechanical shafts. Elevators will be located in an effort to minimize the interaction between the existing footings and the new elevator pits to avoid underpinning. However, the proposed location for the service elevator adjacent to the northeast stairs will require underpinning for the existing footings. Openings through the existing framing will be located in an effort to minimize the impact on the existing framing. Where this is not feasible, a new CMU wall will be constructed around the shaft to support the existing framing. This CMU shaft will extend down to the Basement Level and include new footings. Investigation and Reinforcing of the Existing Structure To ensure that all of the elements of the existing structure are capable of supporting the new loads associated with the proposed modifications, we recommend budgeting for the following testing. Investigate the bearing capacity of the soil at each column footing, and reinforce the soil with chemical grouting or other appropriate method as required. As more data on the existing soil conditions is obtained, patterns may emerge that make it unnecessary to investigate each footing. However, because the current data shows large variations in properties, we recommend budgeting for testing at each footing. Investigate the reinforcing contained in all footings. The existing drawings provide only a limited amount of information on selected footings. We recommend using GPR to identify thickness and reinforcement in all footings. If footings need to be reinforced, reinforcing will likely consist of pouring 8" to 12" of additional concrete over the existing footing and providing dowels into the existing footing to ensure that the two act compositely. If punching shear is a problem, dowels into the column will also be required. Investigate all existing concrete columns using GPR or radiographic methods. The existing drawings provide no information on the amount of steel rebar contained within the existing concrete columns. If an existing column cannot support the new load, one method to reinforce the existing columns is to add new steel tube column adjacent to the existing concrete column to share load. Where needed, the new steel column would likely extend from below Level 3 to the top of the existing column footing. The footing may need to be modified to support the load from the new steel tube column. 3.0 Project Description Building Code: International Building Code as adopted by the State of Minnesota Design Live Loads: The preferred design live load for the Lab, Office, and Exam spaces is 60 psf. This allows for better flexibility in the future. However, the existing structure's capacity may dictate that code minimums are used. Slabs on Grade 125 psf Level 1 100 psf Corridors above Level 1 80 psf Lab 60 psf Office 60 psf (Code minimum 50 psf) Exam 60 psf (Code minimum 40 psf) Mechanical AHU 80 psf (Approximate equipment weight) Roofs 35 psf + drifting Partitions 15 psf Wind Loads: 90 MPH Exposure 'B' Material Strengths Concrete: Composite Slab All Other Concrete f'c = 3000 psi, light weight f'c = 4000 psi Reinforcement: Fy = 60,000 psi Structural Steel: Fy = 50,000 psi – wide flange sections Fy = 46,000 psi – tubes Fy = 36,000 psi – misc. steel, angles, plates Masonry: f'm = 1500 psi Masonry Grout: f'c = 3000 psi St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Design Criteria 3.29 3.30 3.0 Project Description Systems Narrative – mechanical PRE-DESIGN NARRATIVE MECHANICAL DIVISIONS 21, 22, & 23 I. MECHANICAL SYSTEMS ASSESSMENT St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Dunham Engineering prepared an assessment of the mechanical system serving Eastman Hall at St. Cloud State University in St. Cloud Minnesota. The purpose of this study is to identify modifications to the existing mechanical systems to accommodate planned remodeling. The assessment includes non-intrusive observations, review of existing plans, and discussions with building maintenance staff regarding the state of the heating, ventilation, air conditioning and plumbing systems. Interviews with St. Cloud State facility management staff with knowledge of the systems indicate that the system is currently not functioning. In general, the HVAC system has exceeded its service life, and it is not anticipated that the systems will adequately serve the building once remodeled and renovated. The systems are outdated vintage 1929, inefficient and do not meet current ASHRAE codes and ventilation requirements as described below. Replacement and modifications are recommended. Division 23 HVAC Systems: The existing HVAC systems consist of three air handling systems and numerous toilet exhaust fans. The perimeter rooms are heated with steam fin-tube radiation. Steam is provided from the Campus central plant. 1. Existing Air Handling Units (AHU): The existing AHU’s were installed as part of the 1929 building construction. They serve the pool and gymnasium and provide make up air for the toilet room exhaust. The AHU’s are in poor condition with failing insulation promoting mold growth, failing motor bearings and leaking casings. Recommendation is to replace as part of a system overhaul. 2. Exhaust Fans: The exhaust fans have exceeded their service life as defined by ASHRAE. The dampers do not function and require replacement. Recommendation is to replace as part of a system overhaul. 3. Steam System: The steam supplied to the building is from the campus central plant and is provided at 115 PSI. The steam pressure is reduced to 10 psi at a pressure reducing station. The owner indicated that the pressure reducing station is original and is past its service life. The steam piping, condensate piping and traps are original to the building. The steam and condensate piping is showing wear due to age. The steam piping, condensate piping and traps are beyond their service life as described by ASHRAE. Recommendation is to replace the pressure reducing station with one that is sized to allow for the new heating of the remolded building. Steam and condensate piping and traps should be replaced as part of a system overhaul. a. Radiation: The existing radiation is cast iron radiator type. The equipment is original to the building. Recommendation is to replace as part of a system overhaul. b. Unit Heaters and Convectors: The unit heaters are beyond their service life. Maintenance staff stated that they are unreliable. Recommendation is to replace as part of a system overhaul. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 1 Comm. #0412068 3.0 Project Description Cooling System: No hydronic cooling systems currently exists. Recommendation is to add hydronic chilled water cooling as part of a system overhaul. 5. Controls: The heating system, AHU’s, control valves and dampers are controlled via pneumatic control system. Due to the age of the system, there are a number of leaks. This system is inefficient and outdated. Recommendation is to replace with a direct digital control (DDC) control system as part of a system overhaul. 6. Miscellaneous Code Concerns: a. Ventilation: The current system does not meet current codes as described in ASHRAE Standards 62, 55 and 90. Modifications to the system are required to update to current standards. b. Fire and Fire/Smoke Dampers: New fire and fire/smoke dampers will be required as required by code and any modified Architectural plan layouts. Division 22 Plumbing Systems: 1. Domestic Water System: The domestic water supply system is original to the building. Maintenance staff noted various pin-hole leaks in the system. The system has exceeded the service life and is need of replacement. Pipe insulation was observed to be removed or missing from distribution piping in the Lower Level. Recommendation is to replace as part of a system overhaul. 2. Sanitary Waste System: The above ground and underground sanitary waste system is original to the 1929 building. The piping system observed in the lower level appeared in good condition for its age, although the piping may have reduced capacity due to corrosion and sediment on the inside of the piping. The sanitary waste system has exceeded its service life and is need of replacement. Recommendation is to replace as part of a system overhaul. 3. Storm Water System: The above ground and underground storm water system is original to the 1929 building. The piping system observed in the lower level appeared in good condition for its age, although the piping may have reduced capacity due to corrosion and sediment on the inside of the piping. The storm water system connects to the sanitarily system, in violation of current code requirements. Pipe sizes appear to be smaller in size than is required by current code for the roof area served. The storm water system has exceeded its service life and is need of replacement and does not meet code. Recommendation is to replace as part of a system overhaul. 4. Plumbing Accessories: a. Water Heaters: There is one steam-to-water domestic water heater installed in the lower level to serve the building hot water needs. The building water heaters are over 80 years old. Current code requires that domestic water heaters be double wall. It is unlikely that the heaters are double wall. Recommendation is to replacement of the water heaters due to their age. b. Circulation Pump: The circulation pump is in poor condition and is in need of replacement. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 2 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 4. 3.31 3.32 3.0 Project Description Recommendation is to replace as part of a system overhaul. c. Fixtures and Trim: The building fixture and trim are in some cases original to the 1929 building. The fixtures and trim are at the end of their service life and are no longer serviceable due to the lack of available parts. Recommendation is to replace as part of a system overhaul. Division 21 Fire Protection Sprinkler System: St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1. II. There is no fire protection system installed in the building. . Recommendation is for a new fire protection system to be installed as part of the renovations. DESIGN CONDITIONS 1. Outdoor: o a. Winter = -20 F DB o o b. Summer = 91 F DB / 73 F WB 2. Indoor: o a. Winter = 72 F o b. Summer = 75 F /50%RH 3. “U” Values: a. Walls = To be determined b. Roof = To be determined c. Windows = To be determined 4. Occupancy Levels for load and ventilation rate calculations: a. Designed to meet ASHRAE design conditions unless noted as follows: 1) Conference, Waiting, Commons = Number of Chairs +1. 2) Private Office = 2. 3) Exam = 2 5. Ventilation Air Quantities: a. Designed to meet AIA and ASHRAE guide lines for Health Care Occupancies. b. Designed to meet ASHRAE 62-2004 requirements per space usage. c. Toilet Room Ventilation = 75 CFM per toilet/urinal or 2 CFM/SF, whichever is larger. III. CODES AND STANDARDS 1. Codes and Standards: The following codes and standards will be used in the building design: a. 2007 Minnesota Building Code (which adopts the 2006 International Building Code with State Amendments) b. 2009 Minnesota State Mechanical Code (which adopts the 2006 IMC with State Amendments) c. State of Minnesota Plumbing Code d. 2007 State Fire Code (which adopts the 2006 IFC with State Amendments, and NFPA) e. Federal ADA Guidelines. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 3 Comm. #0412068 3.0 Project Description IV. DEMOLITION 1. V. Demolish all abandoned piping and equipment noted to be removed in subsequent sections. SITE UTILITIES 1. Domestic Water Service: The existing 3” domestic water service is located in the Lower Level of the building. A new service is recommended to be provided with a new city water meter will be installed. 2. Fire Protection Water Service: A new 8” fire protection water service will be provide in the Lower Level. 3. Sanitary Sewer: a. 4. Storm Sewer: a. 5. VI. The existing sanitary sewer for the building shall be removed and replaced with a new service. The estimated size of the new service is 6”. A new 10” storm sewer is required to serve the building. Natural Gas: There is no natural gas required to serve the building. DIVISION 21 – FIRE PROTECTION SYSTEM 1. General: Provide a new wet pipe fire protection system to serve the building. The floors of the building will be served via zone valves located from the wet pipe riser for each floor. The wet pipe riser shall be located either at the stair riser or in accessible location adjacent to a vertical riser location. Each stair well shall have a stand pipe connection complying with Minnesota Code and NFPA 14. Provide hydraulic calculation showing compliance with Minnesota State Fire Code (NFPA 13 and 14 by reference), including Minnesota amendments. Note that the incoming water pressure is approximately 65 PSI, per the MN amendments and fire pump is not required. 2. Sprinkler Heads: Concealed type in all spaces with ceilings. Upright in rooms without ceilings and in plenum spaces, including mechanical equipment rooms. 3. Sprinkler Piping: a. VII. Sprinkler piping shall be: i. Schedule 40 black steel with threaded joints and malleable fittings. ii. No schedule 10 or CPVC piping is allowed. DIVISION 22 – PLUMBING SYSTEMS 1. General: Demolish the existing domestic water hot, cold and circulating system. Demolish the existing waste and vent piping located above and below grade. 2. Domestic Water Systems: Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 4 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 f. ASHRAE 62-2004, Standard for Acceptable Indoor Air Quality. g. State of Minnesota Energy Code. h. Applicable NFPA Standards. i. SMACNA Duct Construction Standards. j. MNSCU Standards Revision Date 2010. k. SCSU Standards. 3.33 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.34 3.0 Project Description 3. 4. a. Domestic Water: Provide new domestic water piping from the main water service to the water heater and provide hot and cold water to each plumbing fixture. A 120 degree domestic hot water loop with circulating pump will be installed to serve all fixtures. b. Sanitary Waste and Vent System: Sanitary waste and vent piping will be provided to each plumbing fixture. Provide a clean out above the spill line for each fixture. Provide new underground waste piping to the exterior of the building. c. Booster Pump: No booster pump is anticipated. Inlet pressure is 65psi. d. Water Softener: No water softener to be installed as hardness level of incoming water is below MNSCU requirements. e. Water Heaters: Provide two (2) steam to water double wall instantaneous water heaters. Water heaters to be set at 120 degrees. These water heaters will be located in the lower level mechanical room. Roof Drainage System: a. Primary Roof Drains: Provide new primary roof drains and primary roof drainage system for the building. Route to 5 feet from the building. Proposed size is 10”. b. Overflow Roof Drains: Provide new overflow roof drains and overflow roof drainage system for the building. Route to 5 feet from the building. Proposed size is 10”. Plumbing Fixtures (no alternate manufacturers are allowed): a. Water closets: Wall hung, flush valve with infrared sensor, hardwired , 1.28 gallons per flush. i. Sloan royal flush valve with American Standard china. b. Urinals: Wall hung, flush valve with infrared sensor, hardwired, 0.13 gallons per flush. i. Sloan model WEUS-1000. c. Public Lavatories : Vitreous china, wall hung with infrared sensor mixing faucet, hardwired. i. Sloan Faucet model EAF-200 with Chicago 1025-CP stops and American Standard China. d. Sinks: Stainless steel counter mounted sinks of scheduled sizes with wrist blade faucets. i. Chicago faucet model 1100-GN2AE3-317CP with Chicago 1025 stops. e. Showers: Shower stall specified by architect. i. Trim: Simmons Pressure balance anti scald mixing valve Chicago 600 CP shower head. One Josam floor drain per shower. f. Floor Drains: Provide one floor drain per toilet group and one floor drain per shower group (outside of shower). g. Floor Sinks: Provide one floor sink per AHU and adjacent to water heaters and pumps. h. Electric Water Coolers: Wall hung high/low ADA compliant with bottle filler. i. Service Sinks: Floor-mounted 24”x 24” receptors in custodial closets and wall mounted sinks in Mechanical Rooms with mixing faucets. j. Wall hydrants: Recessed, non-freeze type with keyed operator. Assume 6 hydrants for pricing. 5. Emergency Plumbing Fixtures: Domestic hot and cold water will be connected to point-of-use mixing valves to provide tepid water at all emergency fixtures. Provide in Mechanical Rooms, Main Janitorial Room, and Laundry Room. a. Combination units, ADA compliant combination shower with eye/face wash, six aerated sprays and rectangular stainless steel bowl. Painted galvanized steel stanchion with a deluge shower head activated by a high visibility yellow pull rod, Speakman SE-603-ADA or equal. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 5 Comm. #0412068 3.0 Project Description 6. Plumbing Materials: a. Domestic water piping: Type L copper with 95/5 soldered joints. b. Sanitary waste and vent: Service weight cast iron with no-hub couplings above grade and hub-and-spigot joints below grade. c. Rain water piping: Service weight cast iron with no-hub couplings above grade and hub-andspigot joints below grade. 7. Plumbing Insulation: a. b. 8. VIII. Type: Rigid preformed fiberglass type with vapor proof all service jacket. Application: Domestic cold, hot, and circulated hot water piping, and all rainwater piping. Estimated Quantity: a. 64 sinks, 6 showers, 1 café (3 sinks 5 floor drains), 7 floor sinks. DIVISION 23 – HEATING SYSTEM 1. General: The building is supplied from the campus central plant with high pressure steam. All new piping and equipment will be provided with in the building. 2. Steam and Condensate Systems: 3. a. Pressure Reducing Station: Provide a new pressure reducing station. This station shall consist of a 1/3 and 2/3 pressure reducing valve. This unit will be located in the Lower Level mechanical room. Provide a steam flash tank. Pipe new steam piping to the equipment served. b. Condensate Return System: Provide a new condensate return system consisting of pressure assisted steam powered condensate pumps. Pipe condensate piping to the tunnel for connection to existing piping. Hydronic Systems: a. 180 degree heating water will be created in two (2) 100% redundant steam to water convertors, located in the Lower Level Mechanical room. b. Hydronic heating water will be pumped to air handling unit heating coils, radiation and building terminal units. Two (2) circulating pumps sized for 100% of the load (primary/standby) will pump heating water to the system. c. 4. The primary/standby pumping system will use base-mounted, end-suction pumps mounted on concrete isolation bases for acoustical isolation. Basis of design: B&G 1500 series. Terminal Units: a. b. c. Provide new finned tube radiation in each perimeter room. Provide a DDC temperature sensor and control valve for each zone. Provide duct mounted heating coils for zone temperature control, 1 or 2 rows as required, on the discharge of the VAV boxes. Provide “quick recovery” cabinet unit heaters in vestibules and exit stairwells. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 6 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 b. Water Tempering Equipment, thermostatic mixing valve designed to produce 85-degree potable water for a 15-minute test. In case of failure, unit will continue a cold-water flow, mixing valve to be by Symmons. System will be a non-recirculating type. 3.35 3.36 3.0 Project Description d. e. 2. Piping Materials: a. b. c. d. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Provide horizontal unit heaters in mechanical equipment and storage rooms. Provide radiant ceiling panels in the toilet rooms adjacent to the showers. High Pressure Steam: Schedule 40 seamless steel pipe with flanged, or welded fittings for pipe sizes 2-1/2” and larger. Schedule 40 seamless steel pipe with butt-welded fittings for pipe sizes 2” and below. Low Pressure Steam: Schedule 40 seamless steel pipe with flanged, or welded fittings for pipe sizes 2-1/2” and larger. Schedule 40 seamless steel pipe with screwed or butt-welded fittings for pipe sizes 2” and below. Condensate: Schedule 80 seamless steel with flanged, or welded fittings for pipe sizes 2-1/2” and larger. Schedule 80 black steel with screwed fittings for pipe sizes 2” and below. Hydronic Heating Water: Schedule 40 black steel with flanged, welded, or cut grooved mechanical couplings for pipe sizes 2-1/2” and larger. Schedule 40 black steel with screwed fittings or Type ‘L’ copper with soldered fittings for pipe sizes 2” and below. 3. Piping Installation: Pump piping connections will be made with flexible connectors. 4. Piping Insulation: a. b. 5. Type: Rigid preformed fiberglass type with vapor proof all service jacket. Application: All steam, condensate and hydronic water piping. Estimated Size: 1) 4500 MBH steam reducing station 2) Two 370 GPM, 90 ft HD pumps 3) 68 VAV zones. IX. DIVISION 23 – COOLING SYSTEM 1. General: Provide a new cooling system for this building by extending piping from the central plant piping located in the tunnel adjacent to the building. 2. Chilled Water System: The building will be served from the central chilled water plant. Campus chilled water piping to the new building will be provided via a separate contract. Campus chilled water will be provided to the new building through a pair of 8” supply and return mains. The chilled water pumping system will be via the secondary pumps located in the central plant. The design chilled systems will be a 12 degF dT (42 degF EWT and 54 degF LWT). 3. BTU Meters: BTU Meters will be provided for monitoring of the chilled water system. 4. Piping Materials: a. Exposed in Mechanical Room spaces: 4) Schedule 40 black steel with flanged, welded, or cut grooved mechanical couplings for pipe sizes 3-1/2" and larger. 5) Schedule 40 black steel with screwed fittings or Type 'L' copper with soldered fittings for pipe sizes 3" and below. b. Concealed in chases, or above ceilings: 1) Schedule 40 black steel with flanged or welded for pipe sizes 3-1/2" and larger. 2) Schedule 40 black steel with screwed fittings or Type 'L' copper with soldered fittings for pipe sizes 3" and below. Chilled Water Piping Insulation: 5. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 7 Comm. #0412068 3.0 Project Description Type: Rigid preformed fiberglass type with vapor proof all service jacket. Exterior Insulation Type: Rigid preformed fiberglass with all service jacket. Application: All chilled water piping. Control valve bodies, fittings, and pump volutes will be insulated to prevent condensation. 6. Elevator Equipment Room Cooling: The elevator equipment room will be cooled with nominal 1ton split system cooling units. The units will be connected to grade-mounted air cooled condensing units. 7. Refrigerant Piping Materials: a. 8. Refrigerant Piping Insulation: a. b. 9. X. Refrigerant: Type ACR copper. Type: Flexible elastomeric insulation for irregular shapes. Application: All refrigerant piping. Control valve bodies and fittings will be insulated to prevent condensation. Estimated Size: 1) 190 Ton Capacity DIVISION 23 - AIR HANDLING SYSTEMS 1. General: Demolish all existing ductwork, air handling units and exhaust fans and provide new systems as described here-in. 2. AHU-1: The system serving the Basement and First Floor (Human Performance Lab, Receiving, Café, Radiology etc.) will be an variable volume, constant temperature air handling unit ducted to VAV boxes that supply air via a mixing system (i.e. overhead diffusers). The unit will consist of a indoor modular air handling unit with a plate type energy recovery core. This unit will be located in the basement mechanical room. Basis of design is McQuay. Cabinet construction will be 2” thick insulated double wall with solid internal liner unless noted as perforated liner. This unit will be a variable volume, constant temperature, air handling unit. The estimated capacity is: a. 22,500 CFM with 72 tons cooling. AHU-1 will have the following components: a. Inlet plenum section. (Back inlet). Cabinet liner shall be perforated b. Return / Relief Fan: Single inlet plenum centrifugal return/relief fan with Variable Speed Drive mounted on spring vibration isolators. c. Side access filter section with 35% (MERV 7) efficient pre-filters. d. Pumped water coil preheat section with coil discharge air temperature controls, and circulation pump e. Aluminum Plate energy recovery section f. Access/Inspection Section for control sensor installation g. Pumped water coil heating section with coil discharge air temperature controls, and circulation pump h. Access/Inspection Section for control sensor installation i. Chilled water cooling and dehumidification coils with discharge control j. Access/Inspection Section for control sensor installation k. Single inlet centrifugal plenum supply fan with Variable Speed Drive, low discharge sound Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 8 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 a. b. c. 3.37 3.38 3.0 Project Description l. m. n. o. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3. characteristics, and mounted on spring vibration isolators. Access/Inspection Section to allow for in swing door. Side access final filter section with 95% (MERV 14) efficient cartridge filters. Discharge plenum section. Exhaust air energy recovery (plate or wheel type) AHU-2: The system serving the Second Floor (Health Services.) will be an variable volume, constant temperature air handling unit ducted to VAV boxes that supply air via a mixing system (i.e. overhead diffusers). The unit will consist of a indoor modular air handling unit with a plate type energy recovery core. This unit will be located in the basement mechanical room. Basis of design is McQuay. Cabinet construction will be 2” thick insulated double wall with solid internal liner unless noted as perforated liner. This unit will be a variable volume, constant temperature, air handling unit. The estimated capacity is: a. 24,000 CFM with 65 tons cooling. AHU-2 will have the following components: a. b. Inlet plenum section. (Back inlet). Cabinet liner shall be perforated Return / Relief Fan: Single inlet plenum centrifugal return/relief fan with Variable Speed Drive mounted on spring vibration isolators. c. Side access filter section with 35% (MERV 7) efficient pre-filters. d. Pumped water coil preheat section with coil discharge air temperature controls, and circulation pump e. Aluminum Plate energy recovery section f. Access/Inspection Section for control sensor installation g. Pumped water coil heating section with coil discharge air temperature controls, and circulation pump h. Access/Inspection Section for control sensor installation i. Chilled water cooling and dehumidification coils with discharge control j. Access/Inspection Section for control sensor installation k. Single inlet centrifugal plenum supply fan with Variable Speed Drive, low discharge sound characteristics, and mounted on spring vibration isolators. . l. Access/Inspection Section to allow for in swing door. m. Side access final filter section with 95% (MERV 14) efficient cartridge filters. n. Discharge plenum section. o. Exhaust air energy recovery (plate or wheel type) 4. AHU-3: The system serving the Third Floor (Counseling and U Choose) will be an variable volume, constant temperature air handling unit ducted to VAV boxes that supply air via a mixing system (i.e. overhead diffusers). The unit will consist of a indoor modular air handling unit with a plate type energy recovery core. This unit will be located in the basement mechanical room. Basis of design is McQuay. Cabinet construction will be 2” thick insulated double wall with solid internal liner unless noted as perforated liner. This unit will be a variable volume, constant temperature, air handling unit. The estimated capacity is: a. 18,500 CFM with 50 tons cooling. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 9 Comm. #0412068 3.0 Project Description a. Inlet plenum section. (Back inlet). Cabinet liner shall be perforated b. Return / Relief Fan: Single inlet plenum centrifugal return/relief fan with Variable Speed Drive mounted on spring vibration isolators. c. Side access filter section with 35% (MERV 7) efficient pre-filters. d. Pumped water coil preheat section with coil discharge air temperature controls, and circulation pump e. Aluminum Plate energy recovery section f. Access/Inspection Section for control sensor installation g. Pumped water coil heating section with coil discharge air temperature controls, and circulation pump h. Access/Inspection Section for control sensor installation i. Chilled water cooling and dehumidification coils with discharge control j. Access/Inspection Section for control sensor installation k. Single inlet centrifugal plenum supply fan with Variable Speed Drive, low discharge sound characteristics, and mounted on spring vibration isolators. . l. Access/Inspection Section to allow for in swing door. m. Side access final filter section with 95% (MERV 14) efficient cartridge filters. n. Discharge plenum section. o. Exhaust air energy recovery (plate or wheel type) 5. Exhaust Ventilation: Utility set exhaust fans will provide the exhaust needs for the building. Fans will be equipped with motorized isolation dampers in the ductwork for isolation. Located fans in the mezzanine mechanical room. Provide fans for services as follows: a. b. c. d. e. 6. Toilet room exhaust (Assume 4 fans) Laboratory fume hood exhaust (Assume 1 fan) Kitchenette exhaust (Assume 1 Fan) Work room exhaust (Assume 1 Fan) Trash room exhaust (Assume 1 Fan) Distribution Systems: a. b. Ductwork Systems (All): Low-pressure ductwork systems shall be G90 galvanized steel, rectangular or round. Exposed ductwork shall have a mill phosphatized finish to accept field painting. Supply ductwork upstream of VAV terminal units will be constructed to SMACNA 4” pressure class with seal class ‘A’ All supply ductwork downstream of VAV terminal units, all return/relief, and general exhaust will be constructed to SMACNA 2” pressure class (positive/negative) with seal class ‘A’. Duct Insulation: Two-inch thick fiberglass board with foil face in mechanical equipment rooms for supply, and outside air ductwork. One-and-one-half-inch thick fiberglass board with foil face in mechanical equipment rooms for return, and relief air ductwork. One-andone-half-inch thick flexible fiberglass with foil face for supply, return, and exhaust air in unconditioned spaces (i.e. shafts and above ceilings). Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 10 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 AHU-3 will have the following components: 3.39 3.40 3.0 Project Description 7. Air Inlets and Outlets: Supply air will be distributed using wall or ceiling registers with double deflection adjustable vanes, round ceiling diffusers in areas with exposed ductwork, and square louvered-face ceiling diffusers in rooms with ceilings. Return and exhaust air inlets will be wall o registers and grilles with fixed 45 degree vanes or grates with 1” cube openings, and ceiling egg crate registers and grilles. 8. Sound Control: Specified sound criteria for spaces will be as follows: Offices, Conference, Lobby (RC-35N), Toilet Room (RC-40N). a. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 b. c. XI. Noise generated at the air handling units will be attenuated using manufactured duct mounted sound attenuators with perforated internal liners covering faced fiberglass insulation. Noise generated by air movement in ductwork will be controlled through established design criteria, including low air velocity, and radius elbows. Flow splitters, and terminal duct mounted attenuators will not be used. Spring vibration isolators will be used on fans, pump isolation bases, ductwork, and piping located in the Mechanical Equipment Rooms. BUILDING AUTOMATION SYSTEM (BAS): 1. XII. General: The building automation system will include automatic controls for monitoring and control of building temperature, humidity, outside air, and pressure. System components will include microprocessor based stand-alone field panels, electronic sensors, electric operators, and wiring. All controls for this building will be connected to the existing Central Operators personnel computer workstation at the facilities building. The new controls will be by Trane to integrate with the current automation system. BUILDING COMMISSIONING: 1. XIII. Commissioning of building mechanical systems (HVAC, Plumbing, Controls) will be implemented at the design development phase, and continued through construction completion. Commissioning will be independent via the owner. B3 MINNESOTA SUSTAINABLE BUILDING GUIDELINES: 1. The design will comply with State of Minnesota B3 Requirements, and will utilize sustainable concepts where applicable: a. Variable air volume air handling system to minimize air transport energy b. Energy recovery of exhaust air c. Modulate the minimum outdoor air air via space CO2 Sensors for demand control ventilation. d. Variable flow heating hot water systems to match heating energy to required building loads e. Low flow plumbing fixtures XIV. ENERGY EFFICIENCY OPTIONS: 1. In lieu of providing a mixing system and three air handling units as stated above, for a chilled beam system could be provided as follows: a. b. Provide 3 eight foot active chilled beams per 1000 ft. space. Provide 1 four foot active chilled beam for each office and exam space. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 11 Comm. #0412068 3.0 Project Description Provide a 100% outside air, air handling unit sized at 22000 CFM. Provide air handling unit similar to AHU-1 described above with the addition a of a desiccant dehumidification wheel. d. Provide minimum outside air ductwork to each chilled beam. e. Provide ducted return to each space. f. Heating system is unchanged from description above. In addition, pipe hydronic heating water to each chilled beam. g. Cooling system: 1) In addition to the chilled water system described above, provide a plate heat exchanger and two chilled water pumps. Pipe chilled water to each active chilled beam. 2) Provide a dry cooler for economizer operation. Estimate size 125 tons. Eastman Hall Mechanical 50% Pre-Design March 27, 2012 Page 12 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 c. 3.41 3.42 3.0 Project Description Systems Narrative – Electrical PRE-DESIGN NARRATIVE ELECTRICAL DIVISION 26 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 I. Electrical Systems Assessment A. Dunham Engineering prepared an assessment of the electrical system serving Eastman Hall on the St Cloud State University Campus. The purpose of this study is to identify modifications to the existing mechanical and electrical systems to accommodate planned remodeling. The assessment includes non-intrusive observations, review of existing plans, and discussions with building maintenance staff of the power, lighting, communication security, life safety (fire alarm devices), heating, ventilation, air conditioning and plumbing systems. B. Interviews with SCSU facility management staff with knowledge of the systems indicate that the general conditions of the systems are they are the end of life (with some exceptions which are noted within this document). Their preference would be for a complete replacement of the all the existing systems to current standards and code compliance. C. Medium Voltage: 1. The existing building medium voltage components are relatively new (less than 10 years old) and are in good condition. The equipment is located on the north side of the building, at grade, and feeds down into an underground vault off the existing tunnel. Within the vault, there is a 600A service disconnect for Eastman Hall and also an 800A service disconnect that feeds Riverview from the Eastman Hall transformer. The existing medium voltage transformer is currently adequate for the existing space program and the Riverview feed, but will not accommodate the proposed change in space program to Eastman Hall. a. Proposed: Disconnect Eastman Hall from the existing medium voltage transformer (leave in place for continued feeding of Riverview), and a new appropriately sized transformer for the proposed space programming will be provided. D. Power Distribution: 1. The existing building electrical distribution system equipment varies from relatively new fusible disconnect switches (a 600A Siemens distribution board located in the basement in the northwest corner; a two section 400A Siemens board in the boiler room on the south side basement) to panel boards that are greater than 40 years old. The existing electrical distribution system is currently adequate for the existing space program, but will not accommodate the proposed change in space program. a. Recommendation: Replace entire existing electrical distribution system with a new building service infrastructure. The existing Siemens switchboards will be provided to the Owner for spare parts. E. Power Receptacles: Electrical 90% Pre-Design June 1, 2012 Page 1 Comm. #0412068 3.0 Project Description The existing power receptacle installation is a mix of old and newer devices connected to the existing electrical installation. a. Recommendation: Replace all existing power receptacles to new style receptacles that correspond to the building’s new space programming. F. Lighting: 1. Lighting throughout the building is mostly older, low-efficiency fluorescent, HID (high intensity discharge), and incandescent fixtures. The fluorescents are mostly T12 lamps with low-efficiency magnetic ballasts. Lighting in the Gymnasium and the Pool areas provided by HID light fixtures with large magnetic ballasts. a. Recommendation: Replace all existing lighting with new energy efficient fluorescent (T8, T5, T5HO) and LED fixtures, corresponding to the building’s new space programming. G. Life Safety Egress Lighting: 1. The existing Egress Lighting is achieved from self contained battery units in scattered areas. a. Recommendation: Egress lighting will be achieved via a new emergency power feed to designated light fixtures, which will be new and accommodate the building’s new space programming. Replace all existing exit signs with new high efficiency, longer lasting LED illuminated exit lights. H. Emergency Electrical Power: 1. Dunham did not observe an existing connection to the campus emergency system radial feed derived from the campus central plant, and does not believe there is currently emergency electrical power in the facility other than selected battery operated lighting. a. Recommendation: Provide a new transformer and Automatic Transfer Switch to connect to the SCSU Campus Emergency Radial Distribution System. II. NEW ELECTRICAL GENERAL REQUIREMENTS A. The work described in this document includes all materials, labor, equipment and services to construct and install a complete operating electrical and low voltage roughin system for the renovation of Eastman Hall at St. Cloud State University in St. Cloud Minnesota. III. DESIGN CONDITIONS A. Exterior Environmental Conditions: Electrical systems shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance capability: 1. Ambient Temperature: -20 to 104 deg F 2. Relative Humidity: 0 to 95 percent. 3. Altitude: 1031 feet Electrical 90% Pre-Design June 1, 2012 Page 2 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1. 3.43 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.44 3.0 Project Description B. Interior Environmental Conditions: Electrical systems shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance capability: 1. Ambient Temperature: 65 to 75 deg F 2. Relative Humidity: 0 to 95 percent. 3. Altitude: 1031 feet C. Interruption of Existing Electric or Communication Services: Do not interrupt services to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary electric service according to requirements indicated: 1. Notify Owner/Owner's Representative no fewer than 5 working days in advance of proposed interruption of electric service. 2. Do not proceed with interruption of electric service without Owner's/Owner's Representative's written permission. IV. CODES AND STANDARDS A. Codes and Standards: Materials, products, devices, fixtures, and forms shall meet or exceed the requirements of National Electrical Code (NEC), American National Standards Institute (ANSI), Institute of Electrical and Electronics Engineers (IEEE), National Manufacturing Association (NEMA) and all applicable codes, all for the most current editions as of the Schematic Design Submittal. Methods of construction and material application shall comply with installation requirements of the National Fire Protection Association (NFPA). All materials and equipment shall be listed and labeled by the Underwriters Laboratories, Inc. (UL) or other approved testing agency as conforming to their standards where such standards have been established for the particular materials or equipment. The following codes and standards will be followed; 1. NFPA - National Fire Protection Association, NFPA 101, 72, 110, and 780 2. IBC - International Building Code 3. UFC - Uniform Fire Code 4. NEC - National Electrical Code 5. UFAS - Uniform Federal Accessibility Standard 6. IES - Illuminating Engineers Society - Lighting Levels Standards 7. ASHRAE 90.1 - American Society of Heating, Refrigerating and Air Conditioning Engineers, Inc. 8. ANSI - American National Standards Institute 9. NEMA - National Electrical Manufacturer's Association 10. EIA/TIA - Electronic Industry Association/Telecommunications Industry Association 11. BICSI - Building Industry Consulting Service International 12. Minnesota State Colleges and Universities (MNSCU) Facilities Design and Construction Standards – 6th Addition (with 12/2010 revisions). 13. All work will be performed by licensed contractors in the State of Minnesota. V. DEMOLITION A. Remove accessible wiring including conduit, junction boxes, hangers, and supports for main feeders to panel boards, from panel boards to light fixtures, and from panel Electrical 90% Pre-Design June 1, 2012 Page 3 Comm. #0412068 3.0 Project Description B. Where conduits are stubbed out of a surface not being removed for new construction, such as a floor slab or poured concrete column or wall, these conduits shall be cut back to a point where patching can adequately be performed. C. Demolition work shall be coordinated with the Owner. Should questions arise regarding the removal of a conduit and/or wiring, (i.e. Is it energized? Does it serve a load in an area not be remodeled?), confer with the Owner before such wiring or conduit is actually demolished. D. Reused and Reinstalled equipment and devices: Carefully disconnect and remove items to be reused or reinstalled. Items shall be properly stored in a manner causing no additional damage to the item. Prior to reinstalling, clean and test item. Upon completion, the item shall be in equivalent condition as prior to its removal. Items damaged due to improper handling and storage by the Contractor shall be replaced with new items of the same type and quality as the original item. Reinstalled light fixtures shall be cleaned and re-lamped with new lamps. Non-functioning ballasts shall be replaced with new ballasts. Lamps and ballasts shall be guaranteed as new items. E. Demolition equipment and devices: Existing equipment, devices, and light fixtures not indicated for reuse (as indicated in other portions of this document) shall become the property of the Contractor and disposed of properly. F. Light fixtures scheduled for removal on this Project may contain PCB impregnated ballasts. Remove PCB ballasts from light fixtures and place ballasts in hazardous waste disposal containers. Properly dispose of the ballasts with a registered hazardous materials disposal contractor. Provide copies of the disposal certificate(s) to the Owner and Engineer at the completion of the Project. G. Fluorescent and HID lamps removed from light fixtures shall be placed in containers, and properly disposed of with a registered disposal contractor. H. Disconnect and remove wiring devices and replace with new devices and cover plates. I. Rework the existing conduit and junction box system such that upon completion of the remodeling, no junction boxes are located in inaccessible locations. This includes existing junction boxes that may be rendered inaccessible due to new piping or ductwork installation. Coordinate with other trades in this effort. Provide additional conduit and connections as required. VI. SITE UTILITIES A. Electrical Utility Service: The campus has an existing 12,470 kV underground distribution system, utilizing exterior medium voltage switches and transformers to feed buildings. Electrical 90% Pre-Design June 1, 2012 Page 4 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 boards to wiring devices such as receptacles, switches, floor outlets, special electrical devices, etc., indicated to be removed in other portions of this document. Existing conduit, boxes, cable, etc. that remain which are presently being supported from existing ceiling or ceiling supports, which are to be removed, shall be re-supported to building structure. 3.45 3.46 3.0 Project Description The building is currently tied into redundant loop feeders, with the connections to pad mounted equipment on the northeast side of the building. Initial design anticipates being able to reuse the existing medium voltage switches, but will need to upgrade the transformer for the building due to the increase in anticipated capacity needs. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 VII. DIVISION 26 – ELECTRICAL SYSTEMS A. Design Load Calculations: Refer to Appendix A thru C for estimated design loads based on the architectural Tier Level square footages. The following information will be based on the Tier 3 electrical loads. B. The existing 225kVA - 12,470V to 208/120V Medium Voltage pad mounted transformer shall be remaining as is to continue serving Riverview. A new medium voltage switch and 500kVA - 12,470V to 208/120V Medium Voltage pad mounted transformer to be provided, located in the same general location as the existing switch and transformer, with new connections into the medium voltage loops provided. C. The existing 208/120V, 600A main switchboard shall be removed in its entirety. D. Provide a new suitable for use as service entrance, 208/120 volt, 3-phase, 4-wire power switchboard, locating in the basement level of the building. The electrical room requirements for the building will be: 1. Main Electrical Room (Basement) a. Switchboard distribution sections to feed secondary electrical rooms and large mechanical equipment. 1) Rated at 1600 amps, 208V/3PH/4W with a 1600 amp main circuit breaker. 2) UL 891 compliant 3) Full capacity non-tapered main bus, 100% neutral bus and 50% ground bus. 4) Integral Transient Voltage Surge Suppression (TVSS). 5) 100,000 AIC Rating 6) Customer metering shall be provided. 7) 100 amp, 208/120 volt, 3-phase, 4-wire lighting panel board(s) for interior/exterior lighting. 8) 100 amp, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC package units, pumps, fans, general purpose power requirements, etc. and general purpose power requirements. 9) Life Safety and Optional Standby Automatic Transfer Switches (260 amp) and associated 225 amp, 208/120 volt, 3-phase, 4-wire panel boards for emergency loads. 10) Lighting Control System Panel. 2. Mechanical Room (Basement) a. Switchboard construction distribution board to feed large mechanical equipment. 1) Rated at 1600 amps, 208V/3PH/4W with a 1600 amp main circuit breaker. 2) UL 891 compliant Electrical 90% Pre-Design June 1, 2012 Page 5 Comm. #0412068 3.0 Project Description 3. 4. 5. 6. Full capacity non-tapered main bus, 100% neutral bus and 50% ground bus. 4) Integral Transient Voltage Surge Suppression (TVSS). 5) 100,000 AIC Rating 6) Customer metering shall be provided. b. 225 amp, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC package units, pumps, fans, general purpose power requirements, etc. and general purpose power requirements. st Secondary Electrical Room (1 Level) a. 100A, 208/120 volt, 3-phase, 4-wire lighting panel board(s) for interior/exterior lighting. b. 225A, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC package units, pumps, fans, etc. and general purpose power requirements. c. 400A, 208/120 volt, 3-phase, 4-wire health care equipment and general purpose power requirements. d. Lighting Control System Panel(s). nd Secondary Electrical Room (2 Level) a. 208/120 volt, 3-phase, 4-wire lighting panel board(s) for interior and exterior lighting. b. 225A, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC package units, pumps, fans, etc. and general purpose power requirements. c. 400A, 208/120 volt, 3-phase, 4-wire health care equipment and general purpose power requirements. TVSS shall be provided with this panel board. d. 200A, 208V, 3-phase, 4-wire imaging equipment feeder and disconnect. TVSS shall be provided with this feeder/disconnect. e. Lighting Control System Panel(s). rd Secondary Electrical Room (3 Level) a. 208/120 volt, 3-phase, 4-wire lighting panel board(s) for interior/exterior lighting. b. 225A, 208/120 volt, 3-phase, 4-wire HVAC panel board(s) for HVAC package units, pumps, fans, etc. and general purpose power requirements. c. 400A, 208/120 volt, 3-phase, 4-wire lab equipment and general purpose power requirements. TVSS shall be provided with this panel board. d. Lighting Control System Panel(s). Emergency (Central Plant Generator Feeder) a. A new 75kVA K-4 rated transformer will be provided to utilize the central plant emergency system (480V to 120/208V). This transformer shall feed the following: b. Life Safety Branch: Loads include egress lighting, telephone, communications, fire alarm, and other essential equipment for the evacuation of personnel from the facility. c. Optional Standby Branch: Loads include the elevator, network electronics, servers, and other owner designated equipment. d. Automatic Transfer Switches (ATS): Transfer switches transfer loads to the emergency feed upon loss of normal power. Transfer switch shall be open transition. The Life Safety transfer switch must be re-energized within a maximum of 10 seconds from the loss of normal power. Electrical 90% Pre-Design June 1, 2012 Page 6 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3) 3.47 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 3.48 3.0 Project Description E. All branch circuit panels will include bolt-on circuit breakers, door in door covers, UL 67 compliant, 200% neutrals, and will be designed with 50% spare/space circuit capacity. Panel board withstand rating (SCCR) shall be a minimum of 10,000 Amps for 208/120V panels. The distribution design shall be a fully rated system, SCCR and AIC ratings for panels shall be as noted on the panel schedules. F. All transformers shall be dry-type, 480V-3PH-3W Delta to 208/120V-3PH-4W Wye, K-4 rated. G. Transient Voltage Surge Suppression: Transient Voltage Surge Suppression (TVSS) design shall be compliant with UL 1449 and IEEE C62.41 standards. The design shall take a two tier approach with surge suppression provided at the main service and at key branch panels where sensitive electronic equipment is fed from. H. Grounding Systems: A complete grounding electrode system will be provided which will include connection to building steel, underground metal water piping systems, building Ufer ground (if available), and building ground ring (new). All electrodes shall comply with NEC article 250. A continuous equipment grounding conductor will be installed in all power/lighting conduit systems and all distribution equipment will have ground buses. New grounding components shall tie back into the existing grounding system. I. Motor Starters and Disconnect Switches: Starters and control equipment will be provided for all electrically operated motors and equipment. Motor electrical connection will be as follows: 1. ½ HP or less – 120V single phase. Manual motor starters (MMS) shall be snap action toggle switch type. Manual motor starters shall be surface or flush mounted. For single phase 120V motor loads, switches shall be horsepower rated, manual, non-reversing switches without overload protection. 2. ¾ HP or greater – 208V three phase. Magnetic starters shall be full voltage, combination type, except where otherwise specified. Required starter sizes and types are indicated on the drawings. Safety switches shall be NEMA type "HD", heavy duty, horsepower rated (note that HP rating of switch must be equal to or greater than HP rating of motor or equivalent equipment loads). 3. Motors rated 10 Hp or higher. Solid-state sensing circuit with isolated output contacts for hard-wired connection; arranged to operate on phase failure, phase reversal, current unbalance from 30 to 40 percent, or loss of supply voltage. Provide adjustable response delay. 4. Fuses protecting motors shall be protected by dual-element type fuses able to carry 500% of rating for 10 seconds and sized at least 125% of motor nameplate rating (100 amps and less - Fusetron FRN-R or FRS-R; larger than 100 amps Low-Peak LPN-RK or LPS-RK). J. Wires and Cables: Wires and Cables: Conductors shall be copper (minimum 98%) and shall be insulated for 600 volts. Aluminum conductors will not be acceptable. Unless shown otherwise, minimum wire size shall be #12. 120V branch circuits with lengths greater than 75 feet (150 feet for 277 volt) measured from center of load shall not be smaller than No. 10. Conductors larger than 10 shall be stranded. Feeder and branch circuit wiring shall be color coded by line or phase in accordance with the National Electrical 90% Pre-Design June 1, 2012 Page 7 Comm. #0412068 3.0 Project Description K. Wiring Devices: 1. Local light switches shall be low voltage control switches with minimum four buttons. 2. Wiring Devices: Includes receptacles and device cover plates. Receptacles shall be specification grade, grounding type, 20 ampere, mounted with ground lug down. Isolated ground, surge suppression and ground fault outlets on branch circuits where required. Device cover plates shall be stainless steel type 302 with beveled edges. Normal devices shall be gray and emergency devices shall be red. 3. Special purpose receptacles will be provided for miscellaneous loads. L. Surface Raceway (Non-Lab areas): 1. Basis-of-Design Product: Subject to compliance with requirements, provide the following product (or a comparable product): a. Walker Systems, Inc.; Wiremold DS4000 Series (power and data) M. Surface Raceway (Lab areas): 1. Basis-of-Design Product: Subject to compliance with requirements, provide the following product (or a comparable product): a. Walker Systems, Inc.; Wiremold ALDS4000 Series (power and data) N. Multiservice Floorboxes (Slab on grade). 1. Basis-of-Design Product: Subject to compliance with requirements, provide the following product (or a comparable product): a. Walker Systems, Inc.; Wiremold RFB4-CI Recessed Floor Box b. Hubbell Wiring Devices Floorbox O. Multiservice Floorboxes (Non-slab on grade). 1. Basis-of-Design Product: Subject to compliance with requirements, provide the following product (or a comparable product): a. Wiremold RFB4-SS Recessed Floor Box b. Hubbell Wiring Devices Floorbox P. Multiservice PokeThru (Non-slab on grade). 1. Basis-of-Design Product: Subject to compliance with requirements, provide the following product (or a comparable product): a. Wiremold Evolution 8AT Series Electrical 90% Pre-Design June 1, 2012 Page 8 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Electrical Code. All conductors shall be installed inside metallic conduit. Metal Clad cable shall only be allowed for connection to light fixtures. Conductors with type THWN or XHHW code grade insulation rated at 75 degrees C for wet and dry locations shall be used throughout the project except as follows: 1. Type THHN/THWN and XHHW-2 600 volt, rated 90 degrees C, under dry conditions shall be used for feed-through wiring in channel of continuous rows of fluorescent fixture, and between recessed type lighting fixtures and adjacent outlet boxes. 2. Type AVA 600 volt, rated 110 degrees C, under dry conditions shall be used for wiring adjacent to hot water heaters, to steam lines, to boilers, and to heat producing equipment hoods. 3.49 3.50 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 b. Hubbell Wiring Devices PokeThru Q. Multiservice Raised Floor Floorboxes (Raised Flooring). 1. Basis-of-Design Product: Subject to compliance with requirements, provide the following product (or a comparable product): a. Walker Systems, Inc.; Wiremold SAF Floor Box b. Hubbell Wiring Devices Floorbox R. Electrical Circuits: 1. Lighting Homeruns: Provide 3/4"C. - (branch circuits shall have dedicated neutrals). Load each 120 Volt, 20 Amp lighting circuit to a maximum of 1200 Watts. 2. General Purpose Homeruns: Provide 3/4"C. - (branch circuits shall have dedicated neutrals). Load each 120 Volt, 20 Amp receptacle circuit to a maximum of 1400 Watts, approximately eight (8) receptacles. These receptacles include general purpose and maintenance receptacles. 3. Computer Circuit Homeruns: Provide 3/4"C. - (branch circuits shall have dedicated neutrals). Load each 120 Volt, 20 Amp receptacle circuit to a maximum of 1200 Watts, approximately Six (6) receptacles. 4. Branch Circuit Conductor Size: Provide #12 AWG branch circuit conductors for all 20 amp, 120 volt circuits less than 100’. Provide #10 branch circuit conductors for all 20 amp, 120 volt circuits over 100’. 5. Each circuit shall have a dedicated neutral. The use of multi-wire branch circuits with a common neutral is not permitted. S. Lightning Protection System for Structures: 1. A new UL and LPI Certified Lightning protection system, which shall comply with UL 96 and NFPA 780 requirements, will be installed on Eastman Hall. T. Lighting Systems: 1. The lighting systems for the building will include a combination of direct and indirect LED lighting fixtures. The fixtures shall be designed such that they provide maximum efficiency and lowest expended watts. The selection of the light fixtures will be based on size and use of each space. 2. Lighting controls shall include day light sensors (DL), occupancy sensors (OS), and time of day (TD) control utilizing a network lighting control system with individual fixture control (Lithonia nLight product or equal). Daylight sensors shall be placed in spaces that have exterior windows to provide daylight harvesting opportunities. 3. Exterior Lighting: IESNA “full cutoff” LED Luminaries will be provided. Controls for exterior lighting shall consist of a relay panel with photocell and time of day schedule. Exterior lighting will comply with MNSCU standards on lighting levels and max/min ratios for public walkways associated with the project. 4. Lighting Design: The lighting layout will be designed as per Illuminating Engineering Society (IES) and ASHRAE 90.1 recommendations. Occupancy Sensor and Time of Day control measures will be provided as noted. LED fixtures shall be based on 3500K color temperatures at 325mA. Fluorescent fixtures shall utilize Super T8, 3250 initial lumens, 35K lamps shall be used throughout. Low Ballast Factor (0.71-0.78) program start, < 10% THD, electronic ballasts; dimmable Electrical 90% Pre-Design June 1, 2012 Page 9 Comm. #0412068 3.0 Project Description Area Type Avg. Footcandles Offices Areas 30-50 Common Spaces Laboratories 30-50 75-100 Classrooms Administration Areas Exam Rooms 30-50 30-50 50-75 Human Performance Lab 50-75 Corridors Storage 10-20 20-30 Mechanical Rooms Electrical Rooms Toilets Exterior 30 30 10-20 1-5 Control Intent OS TD with local override No automatic control, Multiple Levels OS OS, Photocell No automatic control, Multiple Levels No automatic control, Multiple Levels TD OS No automatic control No automatic control TD, OS Photocell, TD Table 1: Lighting Levels and Controls (TD = Time of Day; OS=Occupancy Sensor) U. Identification: Electrical equipment identification for the following equipment will be provided (utilizing permanent marker, printed labels, laminated paper). 1. Raceways 2. Boxes 3. Outlet devices, where indicated on plans. 4. Motor starters and Disconnect Switches 5. Panel boards 6. Switchboards 7. Transformers 8. Lighting Controllers 9. Equipment Cabinets (i.e. FACP, Security Panel, etc.) 10. Emergency Equipment V. Raceways: All electrical wiring (120V AC and greater) will be installed in conduit. All raceway shall include a green grounding conductor. Conduit installation will be as follows; Electrical 90% Pre-Design June 1, 2012 Page 10 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 ballasts will be provided in areas requiring aesthetic lighting effects with-in the space. 3.51 3.52 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1. 2. 3. 4. 5. 6. Electric Metallic Tubing (EMT): Concealed Indoor Intermediate Metal Conduit (IMC): Exposed Indoor and Outdoor Rigid Nonmetallic Conduit (Plastic): Exterior Underground and Below Slab Flexible Conduit: Where permitted for fixture connections (less than 6 ft.) Liquid Tight Flexible Conduit: Motor and Transformer Connections. Inner duct: Textile, 3-cell type installed in Telecommunications backbone and riser conduit. W. Electrical Testing and Commissioning 1. Performance testing of the equipment and system installation/operation by an accredited testing firm in conformance with criteria by the International Electrical Testing Association. Compliance with the standards and associations of the industry including UL, IEEE, NEMA, NFPA, NBFU, ICEA, ASTM, OSHA, NESC, ANSI, ETL, NETA, where applicable. The testing firm will be a qualified independent testing agency. 2. Electrical Equipment and Systems Tested: Perform test on equipment and systems listed, tabulate data and submit with equipment submittal (factory) or acceptance checkout (contractor). a. Electrical switchboards: Factory certification. b. Electrical equipment including panels, transformers, motor control centers: Factory certification. c. Service and Feeder Cables (600V): Insulation, continuity, short circuits, grounds, other faults. d. Branch circuit wires: Short circuits, grounds, other faults. e. Panelboards: Voltage tests after completion of all work. f. Grounding: Resistance Fall of potential testing. g. Fire Alarm System: Per NFPA. 3. Electrical Start-up and Commissioning: Electrical system and components shall be fully functional, operational, and verified by the contractor prior to final acceptance by Owner X. Motor tests shall be recorded and submitted to the Architect/Engineer. Test record shall include: 1. Motor Number, Location, HP Rating 2. Motor circuit protector setting and size 3. Fuse size 4. Heater Size 5. Full load amperes 6. Running amperes 7. Rated voltage 8. Terminal operating voltage Y. Training: Owners facility personnel shall be trained in the proper operation of the electrical systems, minimum of 8 hours. Z. Divisions 27 and 28 Raceway and Box Rough-in Requirements: Electrical rough-in shall be provided for the following systems (cabling/terminations to be provided by the Division 27 and Division 28 contractors as required below) - Electrical 90% Pre-Design June 1, 2012 Page 11 Comm. #0412068 3.0 Project Description 2. 3. 4. 5. 6. 7. 8. 9. 10. Data, Voice, Video and Security system - A complete empty conduit / rough-in system and support requirements will be provided for each system. Raceways for the following systems that are in accessible locations shall have a manufacturer applied color coding as follows: a. Fire Alarm: Red b. Telecommunications: Blue c. Audio/Visual: Yellow d. Security Systems: Green 3/4" minimum conduit will be stubbed into accessible ceiling space for each voice, video, and security system outlet device. Non-metallic thread-less insulating bushing on the end of all conduits will be provided. 1” minimum conduit will be stubbed into accessible ceiling space for each data information outlet device. Non-metallic thread-less insulating bushing on the end of all conduits will be provided. Cable Tray: 8”Wx2”D Basket Tray will be provided throughout the building for routing of special system cabling. Cable tray systems will be provided for all data, voice, and video cabling. Ladder type cable tray will be provided in the main telecommunication equipment room. Raceways 2-inch and smaller inside the buildings will not exceed 150 feet in length. All raceways installed will not contain more than two 90 degree bends or the equivalent. Pull boxes or junction boxes will be provided as necessary to comply with these requirements. Bends in conduits will be long sweep radius bends and in no instance will the inside radius of bends be less than ten times the internal diameter for all conduit sizes. Plywood mounting boards will be provided in all Telecommunication Closets, minimum 3/4" thick AC plywood. Paint all mounting boards on the smooth side with two coats gray alkyd enamel. A complete telecommunication grounding system complying with ANSI/EIA/TIA 607 will be provided. Equipment grounding connections will be provided at all equipment terminal systems and mounting boards. All device outlet boxes will be minimum 4" square x 2-1/2" deep, with single or two gang plaster ring and blank cover plate. VIII. BUILDING COMMISSIONING: A. Commissioning of building electrical system will be implemented at the design development phase, and continued through construction completion. IX. B3 MINNESOTA SUSTAINABLE BUILDING GUIDELINES: B. The design will comply with State of Minnesota B3 Requirements and will utilize sustainable concepts where applicable. Some of the sustainable concepts for electrical include: 1. Lighting control systems (occupancy sensors, daylight harvesting, time sweep control) 2. Energy efficient lamp/ballast combinations 3. A renewable energy study will be done as follows: Electrical 90% Pre-Design June 1, 2012 Page 12 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1. 3.53 3.54 3.0 Project Description 4. a. Photovoltaic – Building Integrated, Roof Mounted, Ground Mounted b. Wind Turbine Recycling of demolished electrical equipment, devices, and cabling. X. ELECTRICAL, COMMUNICATION, AND ELECTRONIC SAFETY AND SECURITY SPACE DESIGN CRITERIA: St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1. 2. 3. Commons /Administration area will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting, along with task and decorative lighting fixtures for select areas utilizing LED or low voltage incandescent lamp sources. Lighting will be controlled on an individual fixture basis utilizing addressable ballast controllers or drivers. General power receptacles will be provided in the space for cleaning equipment, and workstation power receptacles will be provided for designated locations throughout the space. In conjunction with the workstation power, SCSU LAN network receptacles and wireless access points will be located to provide network connections. Accommodations will be provided for a wall mounted LCD monitor(s) which will show the Campus digital signage channel, and also provide the capability of showing building local information. Life safety devices will consist of ceiling mounted smoke detectors and speaker/strobes. Gathering/Entry area will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting, along with task and decorative lighting fixtures for select areas utilizing LED or low voltage incandescent lamp sources. Lighting will be controlled on an individual fixture basis utilizing addressable ballast controllers or drivers. General power receptacles will be provided in the space for cleaning equipment, and workstation power receptacles will be provided for designated locations throughout the space. In conjunction with the workstation power, SCSU LAN network receptacles and wireless access points will be located to provide network connections. Accommodations will be provided for a wall mounted LCD monitor(s) which will show the Campus digital signage channel, and also provide the capability of showing building local information. There will also be designated self-care health kiosks which will incorporate touchscreen capabilities, access to local health service information and connection to web services, and the ability to tie into the Campus Digital Signage and Scheduling System. The reception area will also be the building’s security check point, with access control on the vestibule doors and video surveillance cameras watching entry points and SCSU designated locations. Life safety devices will consist of ceiling mounted smoke detectors and speaker/strobes, and a wall mounted Fire Alarm Annunciator that should be located near the entry door. Student Health Services will be designed to have linear LED light fixture(s) with dimmable driver, controlled by a wall mounted occupancy sensor with manual override/dimming control. Each room will receive new electrical and communication outlets to accommodate a computer/monitor, phone, and miscellaneous equipment as directed by Health Services. A basic electronic Nurse Call system will be designed for notification and scheduling of exam rooms to help efficiency of the space. Life safety will be accomplished with a ceiling mounted system connected smoke detector for smoke detection within the space and ceiling mounted speaker/strobe for annunciation of fire alarm. Electrical 90% Pre-Design June 1, 2012 Page 13 Comm. #0412068 3.0 Project Description 5. 6. 7. 8. Counseling Services area will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting, along with task lighting fixtures for select areas utilizing LED or low voltage incandescent lamp sources. Lighting will be controlled on an individual fixture basis utilizing dimmable drivers. General power receptacles will be provided in the space for cleaning equipment, and workstation power receptacles will be provided for designated locations throughout the space. In conjunction with the workstation power, SCSU LAN network receptacles and wireless access points will be located to provide network connections. Life safety devices will consist of ceiling mounted smoke detectors and speaker/strobes. The U-Choose, Health Education, and Human Performance will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting. Lighting will be controlled with ceiling mounted occupancy sensors, manual push buttons, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and communication cabling will be provided to accommodate designated locations and for flexibility of the space. The rooms will be set up for audio visual accommodations including large format screens, touchscreen interfaces, sound reinforcement, and future interactive white boards. The entry door will be designed with access control to safeguard the equipment that will be located in the space. To meet life safety codes, a system connected ceiling mounted smoke detector and speaker strobe for smoke detection and annunciation within the space. Conference Rooms will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting. Lighting will be controlled with ceiling mounted occupancy sensors, manual push buttons, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and communication cabling will be a combination of wall mounted receptacles and floor mounted poke-thru. The rooms will be set up for audio visual accommodations including large format screens, touchscreen interfaces, sound reinforcement, and future interactive white boards. To meet life safety codes, a system connected ceiling mounted smoke detector and speaker strobe for smoke detection and annunciation within the space. Corridors will be designed to have recessed mounted linear LED light fixtures that will be 12’-0” on center the length of the corridor. Each fixture will have dimmable drivers, controlled by time of day schedule with ceiling mounted occupancy sensors for automatic overrides. Lighting will be dimmed to 20% levels during scheduled night hours for energy conservation. Power circuiting will be routed in conduits above the new accessible ceiling that will be installed, along with a new basket cabletray for communication cabling and the fire alarm system conduit. Each corridor will be designed to have general receptacles spaced no more than 50’-0” on center to accommodate 25’-0” equipment cords (i.e. vacuums) and wireless access points for students access to the SCSU LAN network (with devices spaced approximately 50’-0” on center). To meet life safety codes, system connected smoke detectors will be ceiling mounted in conjunction with ceiling mounted speaker/strobes. Restrooms will be designed to have surface mounted linear LED fixtures with dimmable drivers controlled by time of day schedule with ceiling mounted occupancy sensors for automatic overrides. Lighting will be dimmed to 20% Electrical 90% Pre-Design June 1, 2012 Page 14 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 4. 3.55 3.56 3.0 Project Description St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 9. 10. 11. 12. levels during scheduled night hours for energy conservation and be conducive to sleeping accommodations. General power receptacles will be provided near the sink/mirror locations for student use, and power will be provided to automatic faucet and urinal sensors for water conservation. To meet life safety codes, a system connected heat detector and strobe unit ceiling mounted for fire detection and annunciation within the space. Electrical Service Entrance rooms will be designed to accommodate a floor mounted Suitable for Use as Service Entrance switchboard with main circuit breaker/metering section and circuit breaker distribution sections, wall mounted branch circuit panelboards, floor mounted automatic transfer switches (life safety and option standby), and floor mounted transformer. Lighting in the space will be industrial linear fluorescent strip fixtures with symmetric reflectors and two T8 lamps, controlled by a wall mounted toggle switch. Communication cabling will be provided to selected pieces of equipment for remote monitoring of information. Life safety will be accomplished with a ceiling mounted system connected smoke detector and wall mounted speaker/strobe unit for smoke detection and annunciation within the space. Electrical Secondary rooms will be designed to accommodate wall mounted branch circuit panelboards. Lighting in the space will be industrial linear fluorescent strip fixtures reflectors and two T8 lamps, controlled by a wall mounted toggle switch. Communication cabling will be provided to selected pieces of equipment for remote monitoring of information. Communication Equipment room will be designed to have industrial linear fluorescent strip fixtures with symmetric reflectors and two T8 lamps, controlled by a wall mounted toggle switch. The space will be designed to accommodate two rows of equipment racks and/or cabinets, interconnected with cabletray mounted overhead. An in-row UPS cabinet will be provided for powering all equipment, with the Campus LAN/WAN terminating in the space. Life safety will be accomplished with a ceiling mounted system connected smoke detector and wall mounted speaker/strobe unit for smoke detection and annunciation within the space. Communication Secondary rooms will be designed to accommodate a floor mounted two post rack for communication equipment and cabling. Lighting in the space will be industrial linear fluorescent strip fixtures reflectors and two T8 lamps, controlled by a wall mounted toggle switch. Dedicated power receptacles will be mounted on the ceiling hung cable tray in the room, with general receptacles wall mounted on the back wall of the space. Life safety will be accomplished with a ceiling mounted system connected smoke detector for smoke detection within the space. Appendix A: Tier 1Electrical Load Estimate Area Connected Power Total Power 2 2 Load Type (ft ) Density (w/ft ) (w) Common Area/Administration Lighting - General Emergency - Electrical 90% Pre-Design June 1, 2012 9,705 9,705 1.0 0.1 Page 15 9,705 970 Comm. #0412068 3.0 Project Description 9,705 9,705 9,705 1.5 0.5 2.0 14,557 4,852 19,409 11,245 1.2 13,494 11,245 11,245 11,245 11,245 0.1 2.0 1.0 2.0 1,125 22,490 11,245 22,490 5,164 1.0 5,164 5,164 5,164 5,164 5,164 0.1 1.5 0.5 2.0 516 7,746 2,582 10,328 3,406 1.2 4,087 3,406 3,406 3,406 3,406 0.1 1.5 1.0 2.0 341 5,109 3,406 6,812 0 1.2 0 0 0 0 0 0.1 1.5 1.0 2.0 0 0 0 0 12,066 0.8 9,653 12,066 12,066 12,066 12,066 0.1 0.5 0.5 2.0 1,207 6,033 6,033 24,132 Air Handling Equip Pumps 29,519 29,519 5.0 2.0 147,596 59,039 Service Entrance 420,118 Service Entrance Total: 420,118 Student Health Services Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Counseling Services Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous U-Choose and Health Education Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Human Performance Center Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Existing Building and Support Spaces Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Lighting Receptacles Electronic Equip. Miscellaneous 3.57 Mechanical Electrical 90% Pre-Design June 1, 2012 Page 16 Comm. #0412068 3.58 3.0 Project Description Total: Service Entrance Amps (@480V): Service Entrance Amps (@208V): 505 1,166 Appendix B: Tier 2 Electrical Load Estimate Area Connected Power Total Power 2 2 Load Type (ft ) Density (w/ft ) (w) St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Common Area/Administration Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous 11,369 1.0 11,369 11,369 11,369 11,369 11,369 0.1 1.5 0.5 2.0 1,137 17,053 5,684 22,737 14,384 1.2 17,261 14,384 14,384 14,384 14,384 0.1 2.0 1.0 2.0 1,438 28,768 14,384 28,768 6,467 1.0 6,467 6,467 6,467 6,467 6,467 0.1 1.5 0.5 2.0 647 9,700 3,233 12,933 4,732 1.2 5,678 4,732 4,732 4,732 4,732 0.1 1.5 1.0 2.0 473 7,098 4,732 9,464 4,128 1.2 4,954 4,128 4,128 4,128 4,128 0.1 1.5 1.0 2.0 413 6,192 4,128 8,256 Student Health Services Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Counseling Services Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous U-Choose and Health Education Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Human Performance Center Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Electrical 90% Pre-Design June 1, 2012 Page 17 Comm. #0412068 3.0 Project Description Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous 0.8 0 0.1 0.5 0.5 2.0 0 0 0 0 5.0 2.0 205,398 82,159 Mechanical Air Handling Equip Pumps 41,080 41,080 Service Entrance Total: Service Entrance Amps (@480V): 520,525 626 Service Entrance Total: Service Entrance Amps (@208V): 520,525 1,445 Appendix C: Tier 3 Electrical Load Estimate Area Connected Power Total Power 2 2 Load Type (ft ) Density (w/ft ) (w) Common Area/Administration Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous 12,058 1.0 12,058 12,058 12,058 12,058 12,058 0.1 1.5 0.5 2.0 1,206 18,086 6,029 24,115 17,183 1.2 20,620 17,183 17,183 17,183 17,183 0.1 2.0 1.0 2.0 1,718 34,366 17,183 34,366 8,026 1.0 8,026 8,026 8,026 8,026 8,026 0.1 1.5 0.5 2.0 803 12,039 4,013 16,052 1.2 6,302 Student Health Services Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Existing Building and Support Spaces 3.59 Counseling Services Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous U-Choose and Health Education Lighting - General Electrical 90% Pre-Design June 1, 2012 5,252 Page 18 Comm. #0412068 3.60 3.0 Project Description Emergency Lighting Receptacles Electronic Equip. Miscellaneous 5,252 5,252 5,252 5,252 0.1 1.5 1.0 2.0 525 7,878 5,252 10,504 4,128 1.2 4,954 4,128 4,128 4,128 4,128 0.1 1.5 1.0 2.0 413 6,192 4,128 8,256 0.8 0 0.1 0.5 0.5 2.0 0 0 0 0 5.0 2.0 233,231 93,293 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Human Performance Center Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Existing Building and Support Spaces Lighting - General Emergency Lighting Receptacles Electronic Equip. Miscellaneous Mechanical Air Handling Equip Pumps Service Entrance Total: Service Entrance Amps (@480V): 46,646 46,646 591,605 712 Service Entrance Total: Service Entrance Amps (@208V): 591,605 1,642 THIS PAGE LEFT INTENTIONALLY BLANK Electrical 90% Pre-Design June 1, 2012 Page 19 Comm. #0412068 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 4.0 Sustainability 4.2 4.0 Sustainability Renovation of Eastman Hall for Student Health Related Services St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 St. Cloud State University St. Cloud, MN Pre-Design Energy Report October 5, 2012 Commission Number 0412067-000-00 4.0 Sustainability St. Cloud State University is renovating and infilling Eastman Hall on its campus in St. Cloud, MN. The project is currently in the Pre-Design stage and its programing will include Student Health Services, Counseling & Psychological Services, U Choose / Health Education, Human Performance Lab, and a Pharmacy. The project will tie into the campus chilled water and steam systems for cooling and heating needs. The project will be served by Xcel Energy for electric service. The specific rates will be researched in schematic design. Project Objectives This project will need to adhere to the MN commercial energy code and since the renovation scope includes replacement of the air side mechanical systems, the project is considered a “Major Renovation” and will need to adhere to the MN Sustainable Building Design Guidelines (MSBG) including Sustainable Buildings 2030 (SB2030). The State of Minnesota design guidelines require that where practicable, designers consider the use of geothermal and solar heating and cooling systems. This project currently connects to campus steam and geothermal is not practicable for this site. The most recent state bonding bill requires bonded projects consider Minnesota made photovoltaic panels. SCSU Eastman Hall Renovation Pre-Design Energy Report DUNHAM October 5, 2012 Page 1 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Project Background 4.3 4.4 4.0 Sustainability Energy Use Energy Use Objectives St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 The state of MN commercial energy code (an amended version of ASHRAE 90.1-2004) has primarily prescriptive requirements for certain components, such as roof conductance or lighting power density. These prescriptive criteria are generally readily achievable for both new construction and renovation. SB 2030 is an entirely different approach as its sets an energy use intensity target for each building using one of two tools: an interim target spreadsheet or a web tool available through the MSBG tracking website. The building is perhaps most akin to a medical office building but that building type is not available in either tool. The web tool was utilized by entering a typical 56,000 gsf office with 4 floors, remodeled construction, and district heating and cooling. Then 2,800 gsf of the lab space type was added to represent the Health Services lab & radiology and the lab, workshop, and testing areas of the Human Performance Lab. The office and lab areas combine for 58,800 total gsf. The following screen capture shows the resulting energy standard of 185 kBtu/ft2/yr and 45 lbs CO2e/ft2/yr. SCSU Eastman Hall Renovation Pre-Design Energy Report DUNHAM October 5, 2012 Page 2 4.0 Sustainability To satisfy both the process and outcome criteria, detailed energy modeling will be performed starting at the schematic design phase and continued through the remaining phases of the design. A simple pre-design energy model was simulated in eQUEST to gauge anticipated annual energy consumption, energy costs and related greenhouse for the pre-design and to confirm a trajectory of achieving the SB2030 energy and greenhouse gas emission targets. The TMY3 (typical meteorological year) weather file from St. Cloud Regional Airport was used for this analysis. Mechanically, the modeling included the use of multiple variable air volume (VAV) air handling units with terminal VAV reheat boxes and perimeter baseboard radiators. Heating water will be from a heat exchanger with the campus steam and cooling will be by campus chilled water. Additional energy conservation measures such as daylighting, reduced power lighting design, and outdoor air load reduction strategies were represented as broad schematic inputs to the model. The following three charts show the modeled annual energy costs, site energy consumption and greenhouse gas emissions for the pre-design model. Regarding the SB2030 targets, the pre-design model shows the potential to meet both the site energy use intensity target and the greenhouse gas (CO2e) emissions target. The completion of design, construction and the operation of the building will determine the ultimate building performance. SCSU Eastman Hall Renovation Pre-Design Energy Report DUNHAM October 5, 2012 Page 3 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Energy Modeling 4.5 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 4.6 4.0 Sustainability CO2e is an abbreviation of 'carbon dioxide equivalent' and is the internationally recognized measure of greenhouse emissions. SCSU Eastman Hall Renovation Pre-Design Energy Report DUNHAM October 5, 2012 Page 4 4.0 Sustainability Renewable Energy Objectives The Minnesota Sustainable Building Guidelines require the evaluation of the two renewable (wind or solar) scenarios to provide 2% of the building’s anticipated total energy usage. The State of Minnesota design guidelines require inclusion of an alternative energy source to provide 2% of the project’s energy use. Based upon on the modeled energy use target of 137 kBtu/sf that equates to about 3 kBtu/sf. At 58,800 gross square foot, this equates to 176 million Btus of energy or 52,000 kWh of electricity. Solar domestic hot water and photovoltaic panel alternatives to meet this renewable energy target are evaluated in the following sections. Solar Domestic Hot Water Analysis At the schematic phase, the anticipated domestic hot water load is approximately 400 gallons per day, resulting in an annual thermal load of about 90 million Btus. Assuming the heating is done by campus steam with a total system efficiency of 50%, the resulting natural gas consumption of 1824 therms at a cost of roughly $1368 annually. Based on RETscreen analysis, a schematic solar DHW system consisting of (4) 80 sf panels and a 600 gallon storage tank would reduce the annual natural gas consumption to about 572 therms at an annual cost of $429. At an estimated initial cost of $45,000 and $938 savings per year the simple payback is about 48 years. This payback exceeds the anticipated life of the system components (panels, pump, and controller). Since the anticipated annual domestic hot water consumption is relatively small, another renewable energy technology may also need to be implemented to satisfy the 2% renewable energy objective. Photovoltaic Panels Analysis Based on the PV Watts screening tool a 40 kW photovoltaic array mounted at a 40 degree angle in St. Cloud, MN would produce approximately 51,000 kWh annually. This generation would very nearly satisfy the 2% renewable target. This generation would save approximately $4,000 annually in utility costs. The cost to install PV typically starts at $5,000 per kW and increases with site specific mounting and structural concerns. Assuming no complexities, this system would cost $200,000 and have a payback of 50 years which exceeds the anticipated life of the system components. This schematic analysis of PV is appropriate for panels made in MN or elsewhere. Renewable energy systems rarely directly pay for themselves. To see a positive return, renewable projects need to identify value in other benefits and/or access some of the ever changing financial incentives. The most common types of incentives are utility rebates and preferential tax treatment. However, per Minnesota Statute 16B.323 this project is ineligible to receive a utility rebate for PV and no preferential tax treatment would apply to renewable energy systems owned by a government entity. Other government and non-profit entities have explored agreements to lease roof area to a private party. The private party purchases the photovoltaic panels, receives the advantageous tax treatment, and the sells the generated electricity back to the building owner under a power purchasing agreement. Such an arrangement would be outside the scope of the project design with exception of some electrical infrastructure to accommodate future onsite renewable energy generation. SCSU Eastman Hall Renovation Pre-Design Energy Report DUNHAM October 5, 2012 Page 5 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 Renewable Energy 4.7 This page was left blank intentionally. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 5.0 financial information – capital expenditures 0 101 0 9,666 29 300 967 11,063 98 98 1,281 98 98 1,477 Feb-2016 0.20 2,803 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 38 GRAND TOTAL (rounded up to next $1000) Revised 10/29/2012 PROJECT COST 16,889 0 0 0 0 132 330 55 98 615 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 SUBTOTAL 4. Project Management (6-8% constr. costs) 4a) State Staff Project Management (.8% total project cost) 4b) Nonstate Construction Management (2-3% total project) 4c) Commissioning (.5% of construction cost) 4d) Testing/Quality Assurance (1% construction cost) SUBTOTAL 5. Construction Costs 5a) Site and Building Preparation 5b) Demolition/Decommissioning 5c) Construction (consistent with project construction total) 5d) Infrastructure/Roads/Utilities 5e) Hazardous Materials Abatement 5f) Construction Contingency (6-10% of construction 5c) SUBTOTAL 6. Art (1% of construction or a maximum of $100 k) SUBTOTAL 7. Occupancy (4-10% of construction 5c) 7a) Furniture, Fixtures and Equipment (4-8% of construction) 7b) Telecommunications - Voice & Data (1% of construction) 7c) Security Equipment (1% of construction) SUBTOTAL 8. Inflation 8a) Mid Point of Construction (mo/yr) 8b) Multipler (2012 CPMI Building Projects Inflation Schedule) 8c) Inflation Cost 9. Other (explain) SUBTOTAL 167 208 250 208 833 SUBTOTAL 0 0 0 0 0 3. Design Fees (7-10% of construction costs) 3a) Schematics (20% of design fee) 3b) Design Development (25% of design fee) 3c) Contract Documents (30% of design fee) 3d) Construction Administration (25% of design fee) 2. Pre Design (.5% of total project cost) 0 0 0 0 0 0 0 0 0 0 Project Cost Project Cost Project Cost All Prior Years FY 2014-15 FY 2016-17 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Project Cost FY 2018-19 AGENCY CAPITAL BUDGET REQUEST Fiscal Years 2014-19 Dollars in thousands (e.g. $137,500 = $138 thousand) 0 0 0 38 38 TOTAL PROJECT COSTS All Years and All Funding Sources 1. Property Acquisition 1a) Land, Land and Easements Options 1b) Buildings and Land Project Name: Renovation of Eastman Hall for Student Health Related Services 1 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 16,927 0 1,281 98 98 1,477 101 0 9,666 29 300 967 11,063 98 98 132 330 55 98 615 167 208 250 208 833 0 0 0 38 38 Project Cost All years Aug-2016 Aug-2016 Aug-2016 Aug-2016 Sep-2015 Jan-2016 Jan-2016 Jan-2016 Aug-2016 Aug-2016 Oct-2014 Mar-2015 Aug-2015 Aug-2016 Sep-2012 Project Finish Finish (mo/yr) Sep-2015 Aug-2014 Aug-2014 Jan-2015 May-2015 Sep-2015 Aug-2011 Project Start Start (mo/yr) 5.2 5.0 Financial Information 0 0 0 9,982 5,580 0 0 0 0 0 0 0 0 0 0 0 0 0 Clinic Lab Radiology Counseling Health Education/U Choose Human Poerformance lab Mechanical/Electrical Revised 10/29/2012 0 0 Building support 15,562 0 0 Pharmacy 0 0 0 Gathering/café/retail 0 0 0 0 150 175 0 0 0 0 0 0 0 43,291 0 0 5,931 5,159 985 - 2,151 2,499 15,247 2,389 1,901 2,438 4,591 PROJECT CONSTRUCTION $2,584 0 0 0 0 $837 $1,747 0 0 0 0 0 0 0 RENEWAL $7,082 0 0 $9,666 0 0 0 0 0 $474 $800 $970 $1,747 $581 $575 $2,744 $275 $303 $463 $735 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL COST (in $000) 0 0 0 80 155 135 - 270 230 180 115 160 190 160 Cost Per Sq. Foot (in $) 0 0 0 $474 $800 $133 0 $581 $575 $2,744 $275 $303 $463 $735 Cost Per Gross Cost Cost Gross Sq. Foot Sq. Feet (in $000) Sq. Feet (in $000) (in $) RENOVATION PROJECT CONSTRUCTION St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 TOTAL 0 0 Cost Per Sq. Foot (in $) NEW CONSTRUCTION Gross Sq. Gross Sq. Cost Feet Feet (in $000) EXISTING AGENCY CAPITAL BUDGET REQUEST Fiscal Years 2014-19 Dollars in thousands (e.g. $137,500 = $138 thousand) Common area List Major Type of Space (class, office, Lab, mech., etc.) CONSTRUCTION TYPE OF SPACE Project Name: Renovation of Eastman Hall for Student Health Related Services 3 5.0 Financial Information 5.3 TOTAL Revised 10/29/2012 Other: specify Financial Services Mining and Natural Resources Agriculture Transportation and Trades Energy Healthcare/Allied Health Engineering/advanced technology Manufacturing Information Technology TYPE OF SPACE Workforce Alignment 15,562 15,562 New Construction 43,291 43,291 Renovation 0 0 Renewal $ 2,584 2,584 $ 7,082 7,082 Renovated WORKFORCE ALIGNMENT 58,853 58,853 TOTAL Gross Square Feet New Impacted Construction $ 0 - Renewal PROJECT CONSTRUCTION COST ($000) AGENCY CAPITAL BUDGET REQUEST Fiscal Years 2014-19 Dollars in thousands (e.g. $137,500 = $138 thousand) GROSS SQUARE FEET IMPACTED Project Name: Renovation of Eastman Hall for Student Health Related Services 4 $ 7,261 7,261 (Costs for everything on "Project Cost" spreadsheet except 5a-5e) $ 16,927 TOTAL COST 0 0 0 0 0 0 0 0 0 16,927 WORKFORCE ALIGNMENT OTHER PROJECT COST St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 5.4 5.0 Financial Information 5.0 Financial Information St. Cloud State University Eastman Hall Pre-Design Estimate St. Cloud, MN 90% Pre-Design Cost Estimate INTRODUCTION Project Description In brief, the project consists of renovations to the St. Cloud State University Eastman Hall in St. Cloud, MN. Scope of work includes creating a new interstitial level at Level 3 of the Upper Gymnasium, raising +/-4,000sf of floor elevation on Level 1 at the pool area and complete demo and renovation to 4-Levels of the existing structure. This document is based on the measurement and pricing of quantities wherever information is provided and/or reasonable assumptions for other work not covered in the drawings and programs as stated in this document. Basis of Pricing Pricing shown reflects probable construction costs obtainable in the St. Cloud, MN, area on the date of this statement of probable costs. This estimate is a determination of fair market value for the construction of this project. It is not a predication of low bid. Pricing assumes competitive bidding for every portion of the construction work for all subcontractors, that is to mean 4 to 5 bids. If fewer bids are received, bid results can be expected to be higher. Subcontractor’s markups have been included in each line item unit price. These markups cover the cost of field overhead, home office overhead, and profit. These markups can range from 5% to 15% of the cost for that particular item of work. The rates that have been established are for budgetary purposes only and are not to be used to establish the cost of additions or deletions to the scope of work that may arise during the actual construction process. General Contractors General Conditions, Overhead and Profit are calculated at 15% Documentations Faithful+Gould received the following documents for the this cost estimate: Pre-design package- dated October 2011 As-built drawings- dated September 1929 Various site photos taken by BWBR Soil Solidification Grouting- lump sum budget provided by Veit & Company, Inc. Dated- March 8th, 2012 Design Contingency A 15% conceptual/estimating contingency has been included in the estimate. This contingency should reduce to zero at bid stage, but the monies identified are likely to be absorbed in the detail "above-the-line". Escalation Escalation has been calculated based upon the mid-point of construction being January 2017. From the date of estimate, May 2012, until the midpoint of construction we have added 16.3% based upon the MN DOF 2011-2012 Escalation factors Items excluded from the Cost Estimate Legal and accounting fees Design, engineering and consultant fees Testing and inspection Fire and all risk insurance Owner's contingency Hazardous material mitigation Loose furniture, fittings and equipment (FF&E) Moving costs Medical equipment Head IT equipment Audio/visual equipment Any additional structural modifications to existing structure to support new floor levels. 6/12/2012 Intro Notes 2 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 12-Jun-12 5.5 5.6 5.0 Financial Information 12-Jun-12 St. Cloud State University Eastman Hall Pre-Design Estimate St. Cloud, MN 90% Pre-Design Cost Estimate St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 INTRODUCTION Items that may affect the cost estimate Modifications to the scope of work included in this estimate. Unforeseen sub-surface conditions. Special phasing requirements. Restrictive technical specifications or excessive contract conditions. Any other non-competitive bid situations. Bids delayed beyond the projected schedule. Statements of Probable Cost Faithful+Gould has no control over the cost of labor and materials, general contractor’s or any subcontractor’s method of determining prices, or competitive bidding and market conditions. This opinion of probable cost of construction is made on the basis of the experience, qualifications, and best judgment of the professional consultant familiar with the construction industry. Faithful+Gould cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from this or subsequent cost estimates. Faithful+Gould has prepared this estimate in accordance with generally accepted principles and practices. This staff is available to discuss its contents with interested personnel. Recommendation for Cost Control Faithful+Gould. recommends that the Owner carefully review this document, including line item descriptions, unit prices, clarifications, exclusions, inclusions and assumptions, assumptions contingencies, contingencies escalation and markups. markups If the project is over budget budget, or if there are unresolved budgeting issues issues, alternate systems schemes should be evaluated before proceeding into the design phase. Requests for modifications of any apparent errors or omissions to this document must be made to Faithful+Gould within ten (10) days of receipt of this estimate. Otherwise, it will be understood that the contents have been concurred with and accepted. 6/12/2012 Intro Notes 3 5.0 Financial Information St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate GFA CONSTRUCTION COST SUMMARY SYSTEM DESCRIPTION 54,315 TOTAL A10 A20 FOUNDATIONS BASEMENT CONSTRUCTION $228,390 $0 B10 B20 B30 SUPERSTRUCTURE EXTERIOR CLOSURE ROOFING $516,582 $428,840 $0 C10 C20 C30 INTERIOR CONSTRUCTION STAIRCASES INTERIOR FINISHES $1,030,325 $85,000 $814,725 D10 D20 D30 D40 D50 CONVEYING SYSTEMS PLUMBING HVAC FIRE PROTECTION ELECTRICAL $300,000 $488,835 $2,206,934 $217,260 $1 $1,569,704 569 704 E10 E20 EQUIPMENT FURNISHINGS F10 F20 SPECIAL CONSTRUCTION SELECTIVE BUILDING DEMOLITION G10 G20 G30 SITE PREPARATION SITE IMPROVEMENT SITE UTILITIES TOTAL DIRECT COST (Trade Costs) MARK UP GENERAL CONDITIONS $0 $65,000 $40,000 $398,680 $2,500 $85,000 $25,000 $8,502,774 $1,275,416 SUBTOTAL CONSTRUCTION $9,778,190 CONTINGENCIES/ESCALATION DESIGN & PRICING CONTINGENCY ESCALATION $1,466,728 $1,832,922 TOTAL CONSTRUCTION COST $13,077,840 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 12-Jun-12 5.7 5.8 5.0 Financial Information 12-Jun-12 St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 CONSTRUCTION COST SUMMARY SYSTEMS DESCRIPTION GFA 54,315 SUB-TOTAL TOTAL $/SF % A10 FOUNDATIONS A1030 Lowest Floor Construction $146,600 $228,390 $4.20 1.7% B10 SUPERSTRUCTURE B1010 Upper Floor Construction $516,582 $516,582 $9.51 4.0% B20 EXTERIOR CLOSURE B2010 Exterior Walls B2020 Windows B2030 Exterior Doors $15,000 $392,840 $21,000 $428,840 $7.90 3.3% C10 INTERIOR CONSTRUCTION C1010 Interior Construction $1,030,325 $1,030,325 $18.97 7.9% C20 STAIRCASES C1020 Stair Construction C2020 Stair Finishes $45,000 $40,000 $85,000 $1.56 0.6% C30 INTERIOR FINISHES C3010 Interior Finishes $814,725 $814,725 $15.00 6.2% D10 CONVEYING SYSTEMS D1010 Elevator $300,000 $300,000 $5.52 2.3% D20 PLUMBING D20 Plumbing $488,835 $488,835 $9.00 3.7% D30 HVAC D30 $2,206,934 $2,206,934 $40.63 16.9% D40 FIRE PROTECTION D40 Fire Protection $217,260 $217,260 $4.00 1.7% D50 ELECTRICAL D5010 Service & Distribution D5020 Lighting & Power D5030 Communication & Security Systems D5040 Other Electrical Systems $551,297 $515,993 $339,469 $162,945 $1,569,704 $28.90 12.0% HVAC E10 EQUIPMENT E10 Equipment, generally $0 $0 $0.00 0.0% E20 FURNISHINGS E2010 Fixed Furnishings E2020 Movable Furnishings $65,000 NIC $65,000 $1.20 0.5% F10 SPECIAL CONSTRUCTION F10 Special Construction $40,000 $40,000 $0.74 0.3% F20 SELECTIVE BUILDING DEMOLITION F2010 Building Elements Demolition $398,680 $398,680 $7.34 3.0% G10 SITE PREPARATION G1010 Site Preparation $2,500 $2,500 $0.05 0.0% G20 SITE IMPROVEMENT G2030 Site Improvements $85,000 $85,000 $1.56 0.6% G30 SITE MECHANICAL UTILITIES G3050 Cooling Distribution $25,000 $25,000 $0.46 0.2% $8,502,774 $156.55 65.0% TOTAL DIRECT COST (Trade Costs) 5.0 Financial Information 90% Pre-Design Cost Estimate GFA CONSTRUCTION COST SUMMARY SYSTEMS DESCRIPTION MARK UP GCs/OH&P/Permits SUB-TOTAL 15% $1,275,416 SUBTOTAL CONSTRUCTION CONTINGENCIES/ESCALATION 15.0% Design & Pricing Contingency Escalation (to mid-point of construction 16.3% TOTAL PROJECT COST $1,466,728 $1,832,922 54,315 TOTAL $/SF % $1,275,416 $23.48 9.8% $9,778,190 $180.03 74.8% $3,299,650 $13,077,840 25.2% $240.78 100.0% St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 12-Jun-12 St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 5.9 5.10 5.0 Financial Information 12-Jun-12 St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate DESCRIPTION A10 A1010 GFA QTY UNIT UNIT EST'D SUB TOTAL COST COST TOTAL COST FOUNDATIONS STANDARD FOUNDATIONS St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 SUBTOTAL A1020 $ - $ 81,790 $ 146,600 SPECIAL FOUNDATIONS Soil solidification grouting- (lump sum by Veit & Co.) 1 ls $ 81,790.00 $ 81,790 SUBTOTAL A1030 54,315 LOWEST FLOOR CONSTRUCTION Infill at Pool and viewing deck area at Level 1; steel structure and composite floor system. Structural steel; assumes existing columns can support new structure 24 ton $ 4,500.00 $ Metal deck 4,000 sf $ 3.65 $ 108,000 14,600 CIP floor slab 4,000 sf $ 6.00 $ 24,000 SUBTOTAL TOTAL - FOUNDATIONS A20 A2010 $228,390 BASEMENT CONSTRUCTION BASEMENT EXCAVATION SUBTOTAL A2020 $ - $ - BASEMENT WALLS SUBTOTAL TOTAL - BASEMENT CONSTRUCTION B10 B1010 $0 SUPERSTRUCTURE UPPER FLOOR CONSTRUCTION Create new interstitial level at Upper Gymnasium Structural steel; assumes existing columns can support new structure $ 76 $ 4,500.00 $ 343,737 Metal deck 12,730 sf $ 3.65 $ 46,465 CIP floor slab 12,730 sf $ 6.00 $ 76,380 1 allow $ 50,000.00 $ 50,000 Allowance to reinforce existing columns SUBTOTAL B1020 ton $ 516,582 ROOF CONSTRUCTION SUBTOTAL $ - TOTAL - SUPERSTRUCTURE B20 $516,582 EXTERIOR CLOSURE 6/12/2012 backup 7 5.0 Financial Information St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate DESCRIPTION B2010 GFA QTY UNIT 1 allow UNIT EST'D SUB TOTAL COST COST TOTAL COST EXTERIOR WALLS & SOFFITS Allowance for misc $ 15,000.00 $ 15,000 SUBTOTAL B2020 $ 15,000 $ 392,840 $ 21,000 WINDOWS, STOREFRONT, TRANSLUCENT PANELS New exterior glazing to all existing openings 5,612 sf $ 70.00 $ 392,840 SUBTOTAL B2030 EXTERIOR DOORS New double glazed entry doors 2 pr $ 5,000.00 $ New single glazed entry doors 2 ea $ 3,500.00 $ 10,000 7,000 New single metal doors 2 ea $ 2,000.00 $ 4,000 SUBTOTAL TOTAL - EXTERIOR CLOSURE B30 B3010 $ 428,840 ROOFING ROOF COVERINGS SUBTOTAL B3020 54,315 $ - $ - ROOF OPENINGS SUBTOTAL TOTAL - ROOFING C10 INTERIOR CONSTRUCTION C1010 INTERIOR CONSTRUCTION Partitions, doors, specialties and millwork $0 54,315 gfa $ 15.00 $ 814,725 Elevator shafts - assumes 8" cmu 2 allow $ 52,800.00 $ 105,600 "Z" furring rigid insulation w/ gyp at inside face of exterior wall 1 allow $ 85,000.00 $ 85,000 Allowance for decorative railing at 2" flr opening 100 lf $ 150.00 $ 15,000 Aluminum vestibule doors at entrances; double 2 pr $ 2,300.00 $ 4,600 Aluminum vestibule doors at entrances; single 3 ea $ 1,800.00 $ 5,400 SUBTOTAL $ 1,030,325 TOTAL - INTERIOR CONSTRUCTION C20 C2010 $1,030,325 STAIRCASES STAIR CONSTRUCTION Remove and replace handrail & guardrail at existing stairways allowance 1 SUBTOTAL 6/12/2012 allow $ 45,000.00 $ 45,000 $ backup 45,000 8 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 12-Jun-12 5.11 5.12 5.0 Financial Information 12-Jun-12 St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate DESCRIPTION C2020 GFA QTY UNIT 1 allow UNIT EST'D SUB TOTAL COST COST TOTAL COST STAIR FINISHES New stair finishes in all stairways $ 40,000.00 $ 40,000 SUBTOTAL St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 54,315 $ 40,000 TOTAL - STAIRCASES C30 INTERIOR FINISHES C3010 INTERIOR FINISHES Wall, floor and ceiling finishes and treatments $85,000 54,315 gfa $ 15.00 $ 814,725 SUBTOTAL $ 814,725 TOTAL - INTERIOR FINISHES D10 D1010 $814,725 CONVEYING SYSTEMS ELEVATOR Passenger elevator 4 stop $ 30,000.00 $ 120,000 Freight elevator 4 stop $ 45,000.00 $ 180,000 SUBTOTAL $ 300,000 TOTAL - CONVEYING SYSTEMS D20 PLUMBING D20 Plumbing Piping & Accessories Plumbing piping & accessories $300,000 54,315 gfa $ 9.00 $ 488,835 SUBTOTAL $ 488,835 TOTAL - PLUMBING D30 HVAC D30 HVAC, GENERALLY $488,835 AHUs (3) and associated motors, pumps, fans etc 1 allow $ 780,000.00 $ HVAC distribution; duct, vavs, dampers etc 1 allow $ 490,000.00 $ 780,000 490,000 Chilled water and hydronic piping distribution 54,315 gfa $ 9.75 $ 529,571 Controls and Instrumentation 54,315 gfa $ 7.50 $ 407,363 SUBTOTAL $ TOTAL - HVAC D40 FIRE PROTECTION D40 FIRE PROTECTION, GENERALLY Fire protection (currently none) 6/12/2012 2,206,934 $2,206,934 54,315 backup gfa $ 4.00 $ 217,260 9 5.0 Financial Information St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate DESCRIPTION GFA QTY UNIT 54,315 UNIT EST'D SUB TOTAL COST COST TOTAL COST SUBTOTAL $ 217,260 TOTAL - FIRE PROTECTION D50 D5010 $217,260 ELECTRICAL SERVICE & DISTRIBUTION Service & distribution 54,315 gfa $ 10.15 $ 551,297 SUBTOTAL D5020 54,315 gfa $ 9.50 $ $ 515,993 $ 339,469 $ 162,945 515,993 SUBTOTAL COMMUNICATION & SECURITY SYSTEMS Communication & security systems rough-in 54,315 gfa $ 6.25 $ 339,469 SUBTOTAL D5040 551,297 LIGHTING & POWER Lighting & power D5030 $ OTHER ELECTRICAL SYSTEMS Fire Alarm 54,315 gfa $ 3.00 $ 162,945 SUBTOTAL TOTAL - ELECTRICAL E10 EQUIPMENT E10 EQUIPMENT, GENERALLY $ SUBTOTAL $ 1,569,704 - TOTAL - EQUIPMENT E20 E2010 $0 FURNISHINGS FIXED FURNISHINGS Allowance for audio/visual equip mounting brackets and other misc Locker room allowance 1 allow $ 25,000.00 $ 25,000 100 ea $ 400.00 $ 40,000 SUBTOTAL E2020 $ 65,000 MOVABLE FURNISHINGS SUBTOTAL NIC TOTAL - FURNISHINGS F10 SPECIAL CONSTRUCTION F10 SPECIAL CONSTRUCTION 6/12/2012 $65,000 backup 10 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 12-Jun-12 5.13 5.14 5.0 Financial Information 12-Jun-12 St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate DESCRIPTION Shielding allowance GFA QTY UNIT 1 allow $ 54,315 UNIT EST'D SUB TOTAL COST COST TOTAL COST 40,000.00 $ 40,000 SUBTOTAL $ 40,000 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 TOTAL - SPECIAL CONSTRUCTION F20 SELECTIVE BUILDING DEMOLITION F2010 BUILDING ELEMENTS DEMOLITION $40,000 Building demolition; scope to include architectural elements and MEP systems 41,585 gfa Removal of existing steel, ceiling hung mezzanine at gymnasium 1,840 sf incl above $ 885 sf incl above $ - 4,727 sf incl above $ - Remove existing exterior window concrete infill to front façade Remove existing exterior windows $ 8.00 $ 332,680 - Remove existing exterior doors 6 ea Cut opening in existing floor slab at level 2 1 allow $ incl above 16,000.00 $ 16,000 Cut new elevator shafts 1 allow $ 50,000.00 $ 50,000 SUBTOTAL F2020 $ 398,680 HAZARDOUS COMPONENTS ABATEMENT excluded $ - $ - SUBTOTAL $ - TOTAL - SELECTIVE BUILDING DEMOLITION G10 SITE PREPARATION G1010 SITE PREPARATIONS Remove existing sidewalk/paving $398,680 1 allow $ 2,500.00 $ 2,500 SUBTOTAL $ 2,500 TOTAL - SITE PREPARATION G20 SITE IMPROVEMENT G2030 SITE IMPROVEMENT Create new patio areas to east and west elevations, new retaining wall at west elevation $2,500 1 allow $ 85,000.00 $ 85,000 SUBTOTAL $ 85,000 TOTAL - SITE IMPROVEMENT G30 G3050 $85,000 SITE MECHANICAL UTILITIES COOLING DISTRIBUTION Tie into existing central plant chilled water loop- allowance 1 SUBTOTAL 6/12/2012 allow $ 25,000.00 $ 25,000 $ backup 25,000 11 5.0 Financial Information St. Cloud State University Eastman Hall BWBR Architects St. Cloud, MN 90% Pre-Design Cost Estimate DESCRIPTION GFA QTY UNIT 54,315 UNIT EST'D SUB TOTAL COST COST TOTAL COST TOTAL - SITE MECHANICAL UTILITIES $25,000 SUBTOTAL - BUILDING TRADES 6/12/2012 $8,502,774 backup 12 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 12-Jun-12 5.15 5.16 5.0 Financial Information CPMI 10/5/2010 BUILDING PROJECTS INFLATION SCHEDULE EXHIBIT 3 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 (Projected Rates For FY 2011 - 2012) Midpoint of Construction Dept. of Finance MULTIPLIER Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 0.00% 0.21% 0.42% 0.63% 0.84% 1.05% 1.34% 1.64% 1.94% 2.24% 2.54% 2.84% 3.14% 3.44% 3.74% 4.04% 4.34% 4.64% 4.99% 5.34% 5.69% 6.04% 6.39% 6.74% 7.10% 7.46% 7.82% 8.18% 8.54% 8.90% 9.31% 9.72% 10.13% 10.54% 10.95% 11.37% 11.79% 12.21% 12.63% 13.05% 13.47% 13.90% MN DOF ESCALATION 2011- 2012 - 10_05_10 %.xls Midpoint of Construction Dept. of Finance MULTIPLIER Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 14.33% 14.76% 15.19% 15.62% 16.05% 16.49% 16.93% 17.37% 17.81% 18.25% 18.69% 19.14% 19.59% 20.04% 20.49% 20.94% 21.39% 21.85% 22.31% 22.77% 23.23% 23.69% 24.15% 24.62% 25.09% 25.56% 26.03% 26.50% 26.97% 27.45% 27.93% 28.41% 28.89% 29.37% 29.86% 30.35% 30.89% 31.44% 31.99% 32.54% 33.09% St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 6.0 Ongoing operating expenditures This page was left blank intentionally. Revised 10/29/2012 0 0 FY 2016-17 0 0 0 0 0 0 0 0 FY 2018-19 0 0 0 0 0 0 0 0 2 2 0 2,926 3,122 0 3,122 0 2,931 3,127 0 475 475 98 0 0 0 98 0 3,127 98 0 0 0 0 475 0 0 98 0 0 0 PROJECT DETAIL Amount 0 2,787 0 2,787 2,787 0 0 0 0 0 0 16,889 38 0 0 0 0 16,927 TOTAL Projected Costs (Without Inflation) FY 2014-15 FY 2016-17 FY 2018-19 FY2020-21 16,889 16,889 0 0 0 0 0 16,889 FY 2014-15 PREVIOUS STATE CAPITAL APPROPRIATIONS FOR THIS PROJECT (Legal Citations) Laws of Minnesota (year), Chapter, Section, Subdivision Revenue Offsets; attach explanation TOTAL Change from Current FY 2012-13 Change in F.T.E. Personnel IMPACT ON STATE FY2012-13 OPERATING COSTS Compensation - Program and Building Operation 0 Other Program Related Expenses 0 Building Operating Expenses 0 Building Repair and Replacement Expenses (1%) 0 State Owned Lease Expenses 0 Non State Owned Lease Expenses/(Savings) 0 Projected Debt Service Expenses 0 Expenditure Subtotal 0 CAPITAL FUNDING SOURCES Prior Years State Funds: G.O. Bonds/State Bldgs 0 State Funds Subtotal 0 Agency Operating Budget Funds 38 Federal Funds 0 Local Government Funds 0 Private Funds 0 Other 0 TOTAL 38 for Student Health Related Services Project Name:Renovation of Eastman Hall AGENCY CAPITAL BUDGET REQUEST Fiscal Years 2014-19 Dollars in thousands (e.g. $137,500 = $138 thousand) 2,584 1,292 Amount 67% 33% Percent of Total MS 16A.695: Program Funding Review Required (Agency) MS 16A.695: Use Agreement Required (MMB) MS 16A.641 (Subd. 9): Special accounts; appropriation MS 16A.633 (Subd. 4):Report on Jobs Created or Retained. MS 16B.35: Percent for Art MS 16B.335 (Subd. 5): Information Technology Review (MN.IT Services-formerly OET) MS 16B.335 (Subd. 4): Energy Conservation Standards MS 16B.335 (Subd. 2): Other Projects (Legislative Notification) MS 16B.335 (Subd. 3): Predesign Requirement (Administration Dept) MS 16B.335 (Subd. 1b): Project Exempt From this Review (Legislature) MS 16B.335 (Subd. 1a): Construction/Major Remodeling Review (Legislature) MS 16B.33: State Designer Selection Board MS 16B.325, Sustainable Building Guidelines, (B3) MS 16B.326 and 16B.32 : Energy Conservation Requirements (Agency) MS 16B.323: Solar Energy in State Buildings. STATUTORY AND OTHER REQUIREMENTS Project applicants should be aware that the following requirements will apply to their projects after adoption of the bonding bill SOURCE OF FUNDS FOR DEBT SERVICE PAYMENT General Fund User Financing PROJECT DETAIL St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 2 6.0 Ongoing Operating Expenditures 6.3 This page was left blank intentionally. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 7.0 Project schedule This page was left blank intentionally. 7.0 Project Schedule PROJECT SCHEDULE 2012 OCT 2013 NOV DEC JAN 2014 FEB MAR APR MAY JUN JUN 2015 JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC PREDESIGN SUBMITTAL BOARD OF TRUSTEES DESIGNER SELECTION SCHEMATIC DESIGN MNSCU REVIEW SD REVIEW MTG. SD REVISIONS SD FINAL SUBMISSION DESIGN DEVELOPMENT DD PRICING MNSCU REVIEW CONSTRUCTION DOCUMENTS MNSCU REVIEW CD REVISIONS FINAL MNSCU APPROVAL BIDDING & CONTRACT AWARD Construction (12 months) Mid-Point of Construction (Feb. 2016) Punch List/Final (July 2016) Occupancy (August 2016) St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 7.1 pROJECT SCHEDULE 7.3 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 8.0 TECHNOLOGY PLAN 8.2 8.0 Technology Plan 8.1 Technology plan “SCSU will provide appropriate technologies and resources that support teaching, learning, service and access. This goal is in alignment with the SCSU Technology Master Plan.” 1. The University will provide students and faculty with St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 classrooms and laboratories containing up-to-date, discipline-specific equipment and software. Rationale: Technology is a means to offer students a high quality education with the skills needed to compete in the marketplace and to make that education accessible. Skills in most fields, from fine arts to technical professional fields, use some form of technology, which may range from microscopes, musical instruments, and kilns, to computers and software. 2. The University will utilize information technology and distributed learning to support classroom learning and to provide access for outreach. Rationale: With demographics changing (Date Source: Minnesota Higher Education Services Offices), and job requirements requiring ongoing education (Date Source: MDES), many of our new students may have time and location constraints. Distributed learning is one way to make education accessible for them and allow the institution to access new markets. 3. The University will apply appropriate technolo- gies and resources to support teaching, learning, research, creativity, scholarship, and service. Rationale: Technology should support the pedagogy, learning goals, research, creativity, scholarship, and service that remain at the core of professional needs and development. 4. The University will provide appropriate technolo- gies and resources to enhance access to support services. Rationale: The University needs an infrastructure to support services for its students, faculty and staff, including human resource functions, e-services, and integrated business functions. SCSU willl: • Create an exceptional e-learning environment • Develop excellent classroom resources that effec- tively support SCSU’s teaching and learning missions • Ensure that technology matches pedagogy • Assess how student learning is being affected by classrooms technology use • Provide a robust and stable IMS platform to support teaching and learning. PRE-DESIGN NARRATIVE COMMUNICATION, LIFE SAFETY & SECURITY DIVISIONS 27 & 28 I. Technology Systems Assessment A. Dunham Engineering prepared an assessment of the electrical system serving Eastman Hall on the St Cloud State University Campus. The purpose of this study is to identify modifications to the existing mechanical and electrical systems to accommodate planned remodeling. The assessment includes non-intrusive observations, review of existing plans, and discussions with building maintenance staff of the power, lighting, communication security, life safety (fire alarm devices), heating, ventilation, air conditioning and plumbing systems. B. Interviews with SCSU facility management staff with knowledge of the systems indicate that the general conditions of the systems are they are the end of life (with some exceptions which are noted within this document). Their preference would be for a complete replacement of the all the existing systems to current standards and code compliance. C. Fire Alarm System: 1. The existing Simplex 2001 fire alarm control panel and associated annunciation devices are nearing end of useful life and does not meet new campus standards. security, life safety (fire alarm devices), heating, ventilation, air conditioning and plumbing systems. 8.0 Technology Plan Interviews with SCSU facility management staff with knowledge of the systems indicate that the general conditions of the systems are they are the end of life (with some exceptions which are noted within this document). Their preference would be for a complete replacement of the all the existing systems to current standards and code compliance. C. Fire Alarm System: 1. The existing Simplex 2001 fire alarm control panel and associated annunciation devices are nearing end of useful life and does not meet new campus standards. a. Recommendation: The existing fire alarm system shall be removed in its entirety and replaced with a new voice style fire alarm system to meet current SCSU campus standards. D. Communication System: 1. The existing building is served by a 2-post rack located in the west side of the basement. The rack currently holds (3) data patch panels, (1) rack mounted 110-block, 48 port switch, and UPS. Adjacent to the rack is a wall mounted fiber patch panel, connecting building to campus LAN. a. Recommendation: Provide a new main communication room in the basement (approximately 150 square feet) which will house the building network electronics. The space should be provided with a cabinet style UPS, dedicated cooling, cabling racks, network cabinets, and cable tray for proper cabling routing. This room would then serve a secondary communication closet (approximately 80 square feet) located on each floor via backbone fiber and UTP. Replace all existing communication cabling (phone, data, television, etc.) and provide new category 6 cabling corresponding to the building’s new space programming. E. Audio Visual Systems: 1. The only observed audio visual system was in recently renovated classrooms that included a new projector, speakers, and projection screen. a. Recommendation: Provide building wide audio systems for paging (via the new voice style fire alarm system), and select areas for dedicated Audio Visual Systems with Crestron Controls. F. Security System: 1. Dunham did not observe any existing electronic security system or devices. a. Recommendation: Provide building wide security systems that will include intrusion detection, access control, and video surveillance. II. NEW TECHNOLOGY GENERAL REQUIREMENTS A. The work described in this document includes all materials, labor, equipment and services to construct and install a complete operating low voltage system for the renovation of Eastman Hall at St. Cloud State University in St. Cloud Minnesota. III. DESIGN CONDITIONS A. Exterior Environmental Conditions: Electrical systems shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance capability: 1. Ambient Temperature: -20 to 104 deg F 2. Relative Humidity: 0 to 95 percent. 3. Altitude: 1031 feet B. Interior Environmental Conditions: Electrical systems shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance capability: 1. Ambient Temperature: 65 to 75 deg F 2. Relative Humidity: 0 to 95 percent. 3. Altitude: 1031 feet 8.3 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 B. A. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 8.4 8.0 Exterior Environmental Conditions: Electrical systems shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance Technology Plancapability: 1. Ambient Temperature: -20 to 104 deg F 2. Relative Humidity: 0 to 95 percent. 3. Altitude: 1031 feet B. Interior Environmental Conditions: Electrical systems shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance capability: 1. Ambient Temperature: 65 to 75 deg F 2. Relative Humidity: 0 to 95 percent. 3. Altitude: 1031 feet C. Interruption of Existing Electric or Communication Services: Do not interrupt services to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary electric service according to requirements indicated: 1. Notify Owner/Owner's Representative no fewer than 5 working days in advance of proposed interruption of electric service. 2. Do not proceed with interruption of electric service without Owner's/Owner's Representative's written permission. IV. CODES AND STANDARDS A. Codes and Standards: Materials, products, devices, fixtures, and forms shall meet or exceed the requirements of National Electrical Code (NEC), American National Standards Institute (ANSI), Institute of Electrical and Electronics Engineers (IEEE), National Manufacturing Association (NEMA) and all applicable codes, all for the most current editions as of the Schematic Design Submittal. Methods of construction and material application shall comply with installation requirements of the National Fire Protection Association (NFPA). All materials and equipment shall be listed and labeled by the Underwriters Laboratories, Inc. (UL) or other approved testing agency as conforming to their standards where such standards have been established for the particular materials or equipment. The following codes and standards will be followed; 1. NFPA - National Fire Protection Association, NFPA 101, 72, 110, and 780 2. IBC - International Building Code 3. UFC - Uniform Fire Code 4. NEC - National Electrical Code 5. UFAS - Uniform Federal Accessibility Standard 6. IES - Illuminating Engineers Society - Lighting Levels Standards 7. ASHRAE 90.1 - American Society of Heating, Refrigerating and Air Conditioning Engineers, Inc. 8. ANSI - American National Standards Institute 9. NEMA - National Electrical Manufacturer's Association 10. EIA/TIA - Electronic Industry Association/Telecommunications Industry Association 11. BICSI - Building Industry Consulting Service International 12. Minnesota State Colleges and Universities (MNSCU) Facilities Design and Construction Standards – 6th Addition (with 12/2010 revisions). 13. All work will be performed by licensed contractors in the State of Minnesota. V. DEMOLITION A. Remove accessible wiring including conduit, junction boxes, hangers, and supports for main feeders to panel boards, from panel boards to light fixtures, and from panel boards to wiring devices such as receptacles, switches, floor outlets, special electrical devices, etc., indicated to be removed in other portions of this document. Existing conduit, boxes, cable, etc. that remain which are presently being supported from existing ceiling or ceiling supports, which are to be removed, shall be re-supported to building structure. B. Where conduits are stubbed out of a surface not being removed for new construction, such as a floor slab or poured concrete column or wall, these conduits shall be cut back to a point where patching can adequately be performed. C. Demolition work shall be coordinated with the Owner. Should questions arise regarding the removal of a conduit and/or wiring, (i.e. Is it energized? Does it serve a load in an area not be 11. 12. V. DEMOLITION A. Remove accessible wiring including conduit, junction boxes, hangers, and supports for main feeders to panel boards, from panel boards to light fixtures, and from panel boards to wiring devices such as receptacles, switches, floor outlets, special electrical devices, etc., indicated to be removed in other portions of this document. Existing conduit, boxes, cable, etc. that remain which are presently being supported from existing ceiling or ceiling supports, which are to be removed, shall be re-supported to building structure. B. Where conduits are stubbed out of a surface not being removed for new construction, such as a floor slab or poured concrete column or wall, these conduits shall be cut back to a point where patching can adequately be performed. C. Demolition work shall be coordinated with the Owner. Should questions arise regarding the removal of a conduit and/or wiring, (i.e. Is it energized? Does it serve a load in an area not be remodeled?), confer with the Owner before such wiring or conduit is actually demolished. D. Reused and Reinstalled equipment and devices: Carefully disconnect and remove items to be reused or reinstalled. Items shall be properly stored in a manner causing no additional damage to the item. Prior to reinstalling, clean and test item. Upon completion, the item shall be in equivalent condition as prior to its removal. Items damaged due to improper handling and storage by the Contractor shall be replaced with new items of the same type and quality as the original item. Reinstalled light fixtures shall be cleaned and re-lamped with new lamps. Non-functioning ballasts shall be replaced with new ballasts. Lamps and ballasts shall be guaranteed as new items. E. Demolition equipment and devices: Existing equipment, devices, and light fixtures not indicated for reuse (as indicated in other portions of this document) shall become the property of the Contractor and disposed of properly. F. Light fixtures scheduled for removal on this Project may contain PCB impregnated ballasts. Remove PCB ballasts from light fixtures and place ballasts in hazardous waste disposal containers. Properly dispose of the ballasts with a registered hazardous materials disposal contractor. Provide copies of the disposal certificate(s) to the Owner and Engineer at the completion of the Project. G. Fluorescent and HID lamps removed from light fixtures shall be placed in containers, and properly disposed of with a registered disposal contractor. H. Disconnect and remove wiring devices and replace with new devices and cover plates. I. Rework the existing conduit and junction box system such that upon completion of the remodeling, no junction boxes are located in inaccessible locations. This includes existing junction boxes that may be rendered inaccessible due to new piping or ductwork installation. Coordinate with other trades in this effort. Provide additional conduit and connections as required. Plan 8.5 St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 13. BICSI - Building Industry Consulting Service International 8.0 Technology Minnesota State Colleges and Universities (MNSCU) Facilities Design and Construction Standards – 6th Addition (with 12/2010 revisions). All work will be performed by licensed contractors in the State of Minnesota. 8.6 8.0 Technology Plan St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 VI. SITE UTILITIES A. Communication Utility Service: The building shall be served by the campus LAN which is currently being brought via fiber optic and copper cables. All design/installation work will be coordinated with the Office of Information Technology at SCSU. 1. Campus Intercommunications –Not Applicable (via Phone in future) 2. Campus Paging – Not Applicable (via new Fire Alarm in future) B. Health Services: The building shall tie into the following existing head end systems 1. Nurse Call – Not existing (new system to be provided based on building’s new space programming) C. Life Safety/Security Service: The building shall tie into the following existing head end systems 1. Campus Fire Alarm System – Simplex (Voice Evacuation Style) 2. Campus Security Intrusion System – Blackboard 3. Campus Access Control System – Blackboard 4. Area of Rescue – (Talk A Phone) VII. DIVISION 26 – ELECTRICAL SYSTEMS A. Divisions 27 and 28 Raceway and Box Rough-in Requirements: Electrical rough-in shall be provided for the following systems (cabling/terminations to be provided by the Division 27 and Division 28 contractors as required below) 1. Data, Voice, Video and Security system - A complete empty conduit / rough-in system and support requirements will be provided for each system. 2. Raceways for the following systems that are in accessible locations shall have a manufacturer applied color coding as follows: a. Fire Alarm: Red b. Telecommunications: Blue c. Audio/Visual: Yellow d. Security Systems: Green 3. 3/4" minimum conduit will be stubbed into accessible ceiling space for each voice, video, and security system outlet device. Non-metallic thread-less insulating bushing on the end of all conduits will be provided. 4. 1” minimum conduit will be stubbed into accessible ceiling space for each data information outlet device. Non-metallic thread-less insulating bushing on the end of all conduits will be provided. 5. Cable Tray: 8”Wx2”D Basket Tray will be provided throughout the building for routing of special system cabling. Cable tray systems will be provided for all data, voice, and video cabling. Ladder type cable tray will be provided in the main telecommunication equipment room. 6. Raceways 2-inch and smaller inside the buildings will not exceed 150 feet in length. All raceways installed will not contain more than two 90 degree bends or the equivalent. Pull boxes or junction boxes will be provided as necessary to comply with these requirements. 7. Bends in conduits will be long sweep radius bends and in no instance will the inside radius of bends be less than ten times the internal diameter for all conduit sizes. 8. Plywood mounting boards will be provided in all Telecommunication Closets, minimum 3/4" thick AC plywood. Paint all mounting boards on the smooth side with two coats gray alkyd enamel. 9. A complete telecommunication grounding system complying with ANSI/EIA/TIA 607 will be provided. Equipment grounding connections will be provided at all equipment terminal systems and mounting boards. 10. All device outlet boxes will be minimum 4" square x 2-1/2" deep, with single or two gang plaster ring and blank cover plate. VIII. DIVISION 27 – COMMUNICATION SYSTEMS 10. 8.0 Technology Plan All device outlet boxes will be minimum 4" square x 2-1/2" deep, with single or two gang plaster ring and blank cover plate. A. Communication Systems: All offices, community common areas, classrooms, exam rooms, laboratories, and student use areas shall consist of hard wired and wireless communication systems. B. Installation Requirements: 1. Performance testing of the equipment and system installation/operation by an accredited testing firm in conformance with criteria by the International Electrical Testing Association. Compliance with the standards and associations of the industry including UL, IEEE, NEMA, NFPA, NBFU, ICEA, ASTM, OSHA, NESC, ANSI, ETL, NETA, where applicable. The testing firm will be a qualified independent testing agency. 2. ANSI/TIA/EIA Standard 568-B: Commercial Building Telecommunications Cabling Standards 3. ANSI/TIA/EIA Standard 569-A: Pathways and Spaces 4. ANSI/TIA/EIA Standard 606: Administration 5. ANSI/TIA/EIA Standard 607: Grounding and Bonding 6. NFPA 70 National Electric Code (NEC). C. Communication Rooms: 1. Main Point of Presence (MPOP): Room shall be located in basement level in a dedicated Equipment Room (ER) and shall be a minimum of 12’-0” x 10’-0”. This room shall accommodate the building's communication(s) distribution frames (data and voice) and shall connect the building with the Campus's system networks via fiber and copper cables provided as part of this work. 2. Floor Telecommunication Rooms (TR): Rooms shall be located on each level of the building, and shall be a minimum 8’-0” x 10’-0”. This room shall accommodate the floors communication(s) distribution frames (data and voice) and shall connect back to the ER via the communication’s backbone risers. 3. Telecommunication Racks and Cabinets: TE Connectivity frames with horizontal/vertical cabling management. 4. Basket Cable Tray: Basket Rack Cable Tray will be provided above all telecommunication racks in each ER/TR. 5. Grounding: Grounding will be provided in compliance with EIA/TIA 607, IEEE 1100, and NEC. 6. UPS Power Distribution: Rack Mounted UPS equipment will be provided for each Telecommunication Rack. (1) 1500 VA UPS per room is anticipated at this time. Backbone Communication Cabling: 1. 2. 3. 4. 5. E. Backbone cabling system shall provide interconnections between communications equipment rooms (TR), main terminal space, entrance facilities, and equipment rooms (ER) in the telecommunications cabling system structure. Cabling system consists of backbone cables, intermediate and main cross-connects, mechanical terminations, and patch cords or jumpers used for backbone-to-backbone cross-connection. Backbone cabling cross-connects may be located in communications equipment rooms or at entrance facilities. Bridged taps and splitters shall not be used as part of backbone cabling. Analog Voice Backbone Cable requirements: Minimum compliant Category 5e cabling from TE Connectivity, in 25-pair binder groups connecting each secondary TR to the ER. Network Backbone Cable requirements: Combination 50 micron, laser optimized multimode fiber optic cables and single mode fiber optic cables connecting each secondary TR to the ER. Video Backbone Cable: Utilize fiber optic single mode cabling plant for distribution. Horizontal Communication Cabling: 1. Horizontal cable and its connecting hardware provide the means of transporting signals between the telecommunications outlet/connector and the horizontal crossconnect located in the communications equipment room (TR). This cabling and its St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 VIII. DIVISION 27 – COMMUNICATION SYSTEMS D. 8.7 8.8 8.0 Technology Plan Backbone Cable requirements: Combination 50 micron, laser optimized 4. Network St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 5. multimode fiber optic cables and single mode fiber optic cables connecting each secondary TR to the ER. Video Backbone Cable: Utilize fiber optic single mode cabling plant for distribution. E. Horizontal Communication Cabling: 1. Horizontal cable and its connecting hardware provide the means of transporting signals between the telecommunications outlet/connector and the horizontal crossconnect located in the communications equipment room (TR). This cabling and its connecting hardware are called "permanent link," a term that is used in the testing protocols. a. TIA/EIA-568-B.1 requires that a minimum of two telecommunications outlet/connectors be installed for each work area. b. Horizontal cabling shall contain no more than one transition point or consolidation point/zone box between the horizontal cross-connect and the telecommunications outlet/connector. c. Bridged taps and splices shall not be installed in the horizontal cabling. 2. A work area is approximately 100 sq. ft., and includes the components that extend from the telecommunications outlet/connectors to the station equipment. 3. The maximum allowable horizontal cable length is 295 feet. This maximum allowable length does include the 10 feet of service loop required by this specification. This maximum allowable length does not include an allowance for the length of 16 feet to the workstation equipment. The maximum allowable length does not include an allowance for the length of 16 feet in the horizontal cross-connect. 4. Horizontal Network Cable requirements: Mid-tier Category 6 cabling from TE Connectivity. 5. Horizontal Video Distribution Cable requirements: Video over UTP, with associated electronics and baluns to accomplish interface. F. Work Area Devices: All device locations and quantities will be provided in accordance to SCSU and MNSCU technology standards and user/design team input. G. Campus Digital Signage System – Video backbone and horizontal cabling to be provided to Owner provided/designated digital signage monitors. H. Local Audio Visual Systems for dedicated spaces to be provided by Owner, coordinated with cabling/power infrastructure. I. Master Clock System: Provide 120V power to Owner designated locations for Owner provided wireless clocks. J. Local Audio/Visual (A/V) Reinforcement Systems: Owner provided systems. K. Network Electronics: Owner provided systems L. Wireless Access Points: Owner provided systems, utilizing network cabling provided as part of the project.. M. Nurse Call Notification System: Hardwired system to provide notification services between the various areas of the facility including, but not limited to: Exam Rooms, Laboratories, Radiology, and Administration. Basis of Design system will be a Rauland 4000 Series. N. EMR System cabling will be provided based on the selected system. 8.0 Technology Plan A. Electronic Safety and Security Systems: The new facility will utilize access control, video surveillance, intrusion detection, and digital/addressable fire alarm system to promote a safe and secure environment for employees and students. The systems shall be integrated to minimize failure points and promote ease of use for a single point of control. B. Installation Requirements: 1. Performance testing of the equipment and system installation/operation by an accredited testing firm in conformance with criteria by the International Electrical Testing Association. Compliance with the standards and associations of the industry including UL, IEEE, NEMA, NFPA, NBFU, ICEA, ASTM, OSHA, NESC, ANSI, ETL, NETA, where applicable. The testing firm will be a qualified independent testing agency. 2. NFPA 70 National Electric Code (NEC). C. Equipment Rooms: 1. Equipment shall be housed in Communication Equipment and Telecommunication Rooms, and shall adhere to those requirements. D. Electronic Safety and Security (ESS) Cabling: 1. Cabling as required to meet the requirements of the existing Access Control and Video Surveillance Systems. E. Security / Surveillance System: The renovation will provide a new Blackboard control panel for Owner designated access control locations and intrusion detection, and adhere to campus security standards. Video Surveillance will be an IP based system that will be designed as a standalone system that will be capable of integrating into the existing ONSSI security video surveillance system located at the campus security office. F. Fire Alarm System: The renovation of the building will provide a new addressable fire alarm control panel (Simplex to meet campus standards) with voice evacuation capabilities. The new system will be provided with ( but not be limited to), remote control panel(s), annunciator panel, smoke detectors, heat detectors, manual pull stations, and combination audible speaker / strobes. The system will be non-coded, supervised and in accordance with local fire codes. 1. Carbon monoxide detection will be provided at all gas burning equipment. 2. Smoke detectors will be provided on each side of magnetically held fire rated doors, in all mechanical/electrical rooms, and janitor/storage rooms. 3. Duct smoke detectors will be in all air handling equipment on the supply and return side, 2000CFM or greater. Detectors will also be provided within 5’ of all fire smoke dampers. Optional design will allow for full area coverage of the building and eliminating the duct smoke detectors from the air handling units. 4. Manual pull stations will be provided at the Fire Alarm Control Panel location and a designated reception area. 5. Speakers or Speaker/Strobe units will be provided throughout the building. 6. Magnetic door holders will be provided at appropriate door locations. 7. Monitor Modules will be provided for sprinkler flow and tamper switches, and an additional monitor module will be provided at each flow to connect directly to the campus EMS. 8. Control Modules will be provided to interface with elevator recall and power off (shunt trip) equipment if required. 9. The system will be UL listed to be operated as a digital paging system, with connections into the facility phone system and future Mass Notification System. 10. The system will be provided with BACNet IP card to connect with the campus EMS system. X. ELECTRICAL, COMMUNICATION, AND ELECTRONIC SAFETY AND SECURITY SPACE DESIGN CRITERIA: St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 IX. DIVISION 28 – ELECTRONIC SAFETY AND SECURITY 8.9 8.10 8.0 Technology Plan 10. The system will be provided with BACNet IP card to connect with the campus EMS system. X. ELECTRICAL, COMMUNICATION, AND ELECTRONIC SAFETY AND SECURITY SPACE DESIGN CRITERIA: St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 1. 2. 3. 4. 5. Commons /Administration area will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting, along with task and decorative lighting fixtures for select areas utilizing LED or low voltage incandescent lamp sources. Lighting will be controlled on an individual fixture basis utilizing addressable ballast controllers or drivers. General power receptacles will be provided in the space for cleaning equipment, and workstation power receptacles will be provided for designated locations throughout the space. In conjunction with the workstation power, SCSU LAN network receptacles and wireless access points will be located to provide network connections. Accommodations will be provided for a wall mounted LCD monitor(s) which will show the Campus digital signage channel, and also provide the capability of showing building local information. Life safety devices will consist of ceiling mounted smoke detectors and speaker/strobes. Gathering/Entry area will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting, along with task and decorative lighting fixtures for select areas utilizing LED or low voltage incandescent lamp sources. Lighting will be controlled on an individual fixture basis utilizing addressable ballast controllers or drivers. General power receptacles will be provided in the space for cleaning equipment, and workstation power receptacles will be provided for designated locations throughout the space. In conjunction with the workstation power, SCSU LAN network receptacles and wireless access points will be located to provide network connections. Accommodations will be provided for a wall mounted LCD monitor(s) which will show the Campus digital signage channel, and also provide the capability of showing building local information. There will also be designated self-care health kiosks which will incorporate touchscreen capabilities, access to local health service information and connection to web services, and the ability to tie into the Campus Digital Signage and Scheduling System. The reception area will also be the building’s security check point, with access control on the vestibule doors and video surveillance cameras watching entry points and SCSU designated locations. Life safety devices will consist of ceiling mounted smoke detectors and speaker/strobes, and a wall mounted Fire Alarm Annunciator that should be located near the entry door. Student Health Services will be designed to have linear LED light fixture(s) with dimmable driver, controlled by a wall mounted occupancy sensor with manual override/dimming control. Each room will receive new electrical and communication outlets to accommodate a computer/monitor, phone, and miscellaneous equipment as directed by Health Services. A basic electronic Nurse Call system will be designed for notification and scheduling of exam rooms to help efficiency of the space. Life safety will be accomplished with a ceiling mounted system connected smoke detector for smoke detection within the space and ceiling mounted speaker/strobe for annunciation of fire alarm. Counseling Services area will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting, along with task lighting fixtures for select areas utilizing LED or low voltage incandescent lamp sources. Lighting will be controlled on an individual fixture basis utilizing dimmable drivers. General power receptacles will be provided in the space for cleaning equipment, and workstation power receptacles will be provided for designated locations throughout the space. In conjunction with the workstation power, SCSU LAN network receptacles and wireless access points will be located to provide network connections. Life safety devices will consist of ceiling mounted smoke detectors and speaker/strobes. The U-Choose, Health Education, and Human Performance will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting. Lighting will be controlled with ceiling mounted occupancy sensors, manual push buttons, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and communication cabling will be provided to accommodate designated locations and for flexibility of the space. The rooms will be set up for audio visual accommodations including large format screens, touchscreen interfaces, sound reinforcement, and future interactive white boards. The entry door will be designed with access control to 8.0 Technology Plan 6. 7. 8. 9. 10. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 5. access points will be located to provide network connections. Life safety devices will consist of ceiling mounted smoke detectors and speaker/strobes. The U-Choose, Health Education, and Human Performance will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting. Lighting will be controlled with ceiling mounted occupancy sensors, manual push buttons, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and communication cabling will be provided to accommodate designated locations and for flexibility of the space. The rooms will be set up for audio visual accommodations including large format screens, touchscreen interfaces, sound reinforcement, and future interactive white boards. The entry door will be designed with access control to safeguard the equipment that will be located in the space. To meet life safety codes, a system connected ceiling mounted smoke detector and speaker strobe for smoke detection and annunciation within the space. The Smart Classroom/Multipurpose Space(s) will be designed to have recessed linear LED fixtures (dimming drivers) for general lighting and work in conjunction with specialty LED fixtures (spots, down lights, gimbal, linear wash) for selected locations for scene setup capabilities. Lighting will be controlled with ceiling mounted occupancy sensors, manual push buttons with individual zone level control, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and communication cabling will be provided to accommodate designated locations and for flexibility of the space. The rooms will be set up for audio visual accommodations including multiple large format screens, touchscreen interfaces, sound reinforcement, interactive white boards, and distance learning equipment (video conferencing capabilities). The entry door will be designed with access control to safeguard the equipment that will be located in the space. To meet life safety codes, a system connected ceiling mounted smoke detector and speaker strobe for smoke detection and annunciation within the space. Conference Rooms will be designed to have recessed and/or suspended linear LED fixtures (dimming drivers) for general lighting. Lighting will be controlled with ceiling mounted occupancy sensors, manual push buttons, daylight harvest sensors, and Audio Visual touchscreen interfaces. Power and communication cabling will be a combination of wall mounted receptacles and floor mounted poke-thru. The rooms will be set up for audio visual accommodations including large format screens, touchscreen interfaces, sound reinforcement, and future interactive white boards. To meet life safety codes, a system connected ceiling mounted smoke detector and speaker strobe for smoke detection and annunciation within the space. Corridors will be designed to have recessed mounted linear LED light fixtures that will be 12’-0” on center the length of the corridor. Each fixture will have dimmable drivers, controlled by time of day schedule with ceiling mounted occupancy sensors for automatic overrides. Lighting will be dimmed to 20% levels during scheduled night hours for energy conservation. Power circuiting will be routed in conduits above the new accessible ceiling that will be installed, along with a new basket cabletray for communication cabling and the fire alarm system conduit. Each corridor will be designed to have general receptacles spaced no more than 50’-0” on center to accommodate 25’-0” equipment cords (i.e. vacuums) and wireless access points for students access to the SCSU LAN network (with devices spaced approximately 50’-0” on center). To meet life safety codes, system connected smoke detectors will be ceiling mounted in conjunction with ceiling mounted speaker/strobes. Restrooms will be designed to have surface mounted linear LED fixtures with dimmable drivers controlled by time of day schedule with ceiling mounted occupancy sensors for automatic overrides. Lighting will be dimmed to 20% levels during scheduled night hours for energy conservation and be conducive to sleeping accommodations. General power receptacles will be provided near the sink/mirror locations for student use, and power will be provided to automatic faucet and urinal sensors for water conservation. To meet life safety codes, a system connected heat detector and strobe unit ceiling mounted for fire detection and annunciation within the space. Electrical Service Entrance rooms will be designed to accommodate a floor mounted Suitable for Use as Service Entrance switchboard with main circuit breaker/metering section and circuit breaker distribution sections, wall mounted branch circuit panelboards, floor mounted automatic transfer switches (life safety and option standby), and floor mounted transformer. Lighting in the space will be industrial linear 8.11 8.12 8.0 Technology Plan 10. St. Cloud State University Renovation of Eastman Hall for Student Health Related Services | BWBR | October 2012 11. 12. 13. detector and strobe unit ceiling mounted for fire detection and annunciation within the space. Electrical Service Entrance rooms will be designed to accommodate a floor mounted Suitable for Use as Service Entrance switchboard with main circuit breaker/metering section and circuit breaker distribution sections, wall mounted branch circuit panelboards, floor mounted automatic transfer switches (life safety and option standby), and floor mounted transformer. Lighting in the space will be industrial linear fluorescent strip fixtures with symmetric reflectors and two T8 lamps, controlled by a wall mounted toggle switch. Communication cabling will be provided to selected pieces of equipment for remote monitoring of information. Life safety will be accomplished with a ceiling mounted system connected smoke detector and wall mounted speaker/strobe unit for smoke detection and annunciation within the space. Electrical Secondary rooms will be designed to accommodate wall mounted branch circuit panelboards. Lighting in the space will be industrial linear fluorescent strip fixtures reflectors and two T8 lamps, controlled by a wall mounted toggle switch. Communication cabling will be provided to selected pieces of equipment for remote monitoring of information. Communication Equipment room will be designed to have industrial linear fluorescent strip fixtures with symmetric reflectors and two T8 lamps, controlled by a wall mounted toggle switch. The space will be designed to accommodate two rows of equipment racks and/or cabinets, interconnected with cabletray mounted overhead. An in-row UPS cabinet will be provided for powering all equipment, with the Campus LAN/WAN terminating in the space. Life safety will be accomplished with a ceiling mounted system connected smoke detector and wall mounted speaker/strobe unit for smoke detection and annunciation within the space. Communication Secondary rooms will be designed to accommodate a floor mounted two post rack for communication equipment and cabling. Lighting in the space will be industrial linear fluorescent strip fixtures reflectors and two T8 lamps, controlled by a wall mounted toggle switch. Dedicated power receptacles will be mounted on the ceiling hung cable tray in the room, with general receptacles wall mounted on the back wall of the space. Life safety will be accomplished with a ceiling mounted system connected smoke detector for smoke detection within the space.