64 CHAPTER – 3 Three Phase Distribution Transformer Modeling for Power Flow Calculation 3.1 Introduction Choosing a proper feeder model for analysis of a distribution system is a challenging task; one often has to make a compromise between the detail of system representation and the amount of data available for analysis. It is usually the amount of load data that limits the level of detail of system representation at distribution level. The approach to such problem is limited to the primary feeder analysis. Secondaries and customer loads are lumped as loads as seen from the primaries of the distribution transformers (DTs). The impact of the numerous transformers in a distribution system is significant. Transformers affect system loss, zero sequence current, grounding method, and protection strategy. Although transformer is one of the most important components of modem electric power systems, highly developed transformer models are not employed in system studies. Hence it is intended to introduce a transformer model and its implementation method so that large-scale unbalanced distribution system problems such as power flow, short circuit, system loss, and contingency studies, can be solved. 65 Recognizing the fact that the system is unbalanced, the conventional transformer models, based on a balanced three phase assumption, can no longer be considered suitable. This is done with justifiable reason. For example in the widely used, delta-grounded wye connection of distribution step-down transformers, the positive and negative sequence voltages are shifted in opposite directions, this phase shift must be included in the model to properly simulate the effects of the system imbalance. The purpose of this chapter is to demonstrate how the exact models for three-phase transformer connections can be developed for use in power-flow studies. Too many times, approximations are made in the modelings that result in erroneous results. The exact model of a threephase connection must satisfy Kirchhoff’s voltage and current laws and the ideal relationship between the voltages and currents on the two sides of the transformer windings. When this approach is followed, the correct phase shift, if any, will come out naturally. This transformer connection is employed in small- to mediumsized commercial loads that have three-phase motors as well as singlephase lighting and appliance load. It is an economical way to provide both 3-phase and single-phase service with one transformer bank. The authors of [19, 21, 23, 24] employed different approaches to model distribution transformers in a branch current based feeder analysis. In study [19], voltage and current equations were developed for 66 three of the most commonly used transformer connections based on their equivalent circuits. In studies [21, 23, 24], voltage/current equations were derived in the matrix form for transformers of the ungrounded wye-delta connections. However, these methods are mainly based on circuit analysis with Kirchhoff’s voltage and current laws. They are in need of deriving the individual formulae for different winding connections from scratch. In this chapter, symmetrical components modeling of 3 phase distribution transformers unbalanced power symmetrical flow components is used method. model and is General of incorporated information three-phase into the about the transformers is presented. A detailed description of the power flow algorithms used and the proposed modeling procedure is explained in detail. Extensive computation and comparisons have been made to verify the approach, and the results obtained are presented. 3.2 Symmetrical Components Model of Three Phase Transformers The method of symmetrical components, first applied to power system by C. L. Fortescue [29] in 1918, is a powerful technique for analyzing unbalanced three-phase systems. Fortescue defined a linear transformation from phase components to a new set of sequence components. The advantage of this transformation is that for balanced 67 three phase networks the equivalent circuits obtained for the symmetrical components, called sequence networks, are separated into three uncoupled networks. As a result, sequence networks for many cases of unbalanced three phase systems are relatively easy to analyze. The transformation between the phases and sequence components is defined by; 1 1 1 A 1 a 2 a 1 a a 2 (3.1) U AU And I AI (3.2) 2 Where A exp j , U and I denotes sequence voltages and currents, 3 respectively. Load injected current can be calculated as follows: S I i i Vi (3.3) The voltages of the receiving end line segment are calculated by using Kirchhoff’s voltage law as given in eqn. (3.4) ab ac V qa V pa z aa I apq pq z pq z pq b b ba bb bc b V q V p z pq z pq z pq I pq c c ca cb cc c V q V p z pq z pq z pq I pq (3.4) Where, V p And Vq stand for the sending end and receiving end voltages of the line segment pq respectively; 68 Z is the line impedance matrix I is the line current Voltage mismatches can be calculated at each bus as V (k ) V (k ) V (k 1) (3.5) Zero sequence current I P0 flowing through the primary side of transformer is defined by I 0 P V P0 0 Z (3.6) Where, Z 0 denotes the zero-sequence impedance of transformer. The new sequence-voltages of transformer secondary and primary bus voltages can be calculated by using Kirchhoff’s Voltage Law as given in eqns. (3.7) and (3.8) respectively. VS0 V P0 0 0 0 I S0 VS0 VS V P 0 Z 0 I S 0 V V 0 0 Z I 0 S S P (3.7) VS0 V P0 0 0 0 I S0 I 0 Z 0 VS V P 0 Z 0 I S 0 V V 0 0 Z I 0 S S P (3.8) The voltages of the sending end line segment pq are calculated by using Kirchhoff’s Voltage Law as follows: ab ac V pa V qa z aa I apq pq z pq z pq b b ba bb bc b V p V q z pq z pq z pq I pq c c ca cb cc c V p V q z pq z pq z pq I pq (3.9) 69 The sequence voltages of transformer primary side can be calculated for delta-grounded wye and grounded wye-delta as follows: V P0 VS0 0 0 0 I P0 V P0 V P VS 0 Z 0 I P 0 V V 0 0 Z I 0 P P S (3.10) Where VS0 and V P0 show sequence voltages of transformer secondary and primary side, respectively. I P0 Shows the sequence current of transformer primary side and V P0 Shows the zero-sequence voltage of transformer primary side. The transformation between the phases and sequence components are defined by a transformation matrix and the transformation is applied to both voltages and currents of phase-components (U and I, respectively) as given in eqns. (3.1) and (3.2). Normally, the three-phase transformer is modeled in terms of its symmetrical components under the assumption that the power system is sufficiently balanced. The typical symmetrical component models of the transformers for the most common three-phase connections were given in [30]. 3.3 Three Phase Power Flow Although the proposed algorithm can be extended to solve systems with loops and distributed generation buses, a radial network with only one voltage source is used here to depict the principles of the algorithm. 70 Such a system can be modeled as a tree, in which the root is the voltage source and the branches can be a segment of a feeder, a transformer, a shunt capacitor or other components between two buses. With the given voltage magnitude and phase angle at the root and known system load information, the power flow algorithm needs to determine the voltages at all other buses and currents in each branch. The proposed algorithm employs an iterative method to update bus voltages and branch currents. Several common connections of three-phase transformers are modeled using the nodal admittance matrices or different approaches employed in a branch current based feeder analysis for distribution system load flow calculation. The grounded Wye-grounded Wye (GY-GY), grounded WyeDelta (GY-D), and Delta-grounded Wye (D-GY) connection type transformers are most commonly used in the distribution systems. In the proposed method there is no need to use the nodal admittance matrices when the GY-GY connection is used for distribution transformers. The phase impedance matrices of transformer can be used directly in the algorithm. The other type of transformer connections needs to be modeled and adapted to the power flow algorithm. In this section, symmetrical components modeling for distribution transformers of GY-D and D-GY winding configurations are implemented into power flow algorithm. The flow chart of the proposed method is shown in Appendix F as Fig. F.1. 71 3.3.1 Algorithm for 3-Phase Power Flow with Transformer Symmetrical Component Modelling Step 1: Read the line data and identify the nodes beyond a particular node of the system. Step 2: Read load data and Initialize the bus voltages. Step 3: Calculate each bus current using eqn. (3.3). Step 4: Calculate each branch current starting from the far end branch and moving towards transformer secondary side. Step 5: Calculate the sequence currents (Is’) of transformer secondary current (Is) using eqn. (3.2). Step 6: If Gy-D connection (a) Apply the phase shift Is’ = Is’ *ejπ/6 and set Is0= 0 (b) Calculate the sequence voltages (Vp’) of transformer primary bus using eq. (2), and zero-sequence current (Ip0) using eqn. (3.6) (c) Calculate phase current Ip using Is+ and Is- instead of Ip+ and Iprespectively. (d) Continue to calculate branch current calculation moving towards a certain swing bus. (e) Calculate each line receiving end voltages starting from swing bus and moving using eqn. (3.4). towards the transformer primary bus 72 (f) Calculate the sequence voltages (Vs’) of transformer secondary bus using eqn. (3.2). (g) Calculate the sequence voltages (Vp’) of transformer primary bus using eqn. (3.2) and set Vp0=0. (h) Calculate the new sequence voltages of transformer secondary bus using eqn. (3.7). (i) Apply the phase shift Vs’ =Vs’ *ejπ/6 and calculate the phase voltages of transformer secondary bus Vs using eqn. (3.2). (j) Continue the bus voltages calculation moving towards the far end using eqn. (3.4). (k) Go to step 8 Step 7: If D-Gy connection (a) Save the zero-sequence current (Is0= I0 ) and apply the phase shift Is’ = Is’ *ejπ/6 and set Is0= 0. (b) Calculate phase-current Ip using Is+ and Is- instead of Ip+ and Ip- respectively. (c) Continue to calculate branch current calculation moving towards a swing bus. (d) Calculate each line receiving end voltage starting from swing bus and moving towards the transformer primary bus using eqn. (3.4). (e) Calculate the sequence-voltages (Vp’) of transformer primary bus using eqn. (3.2) and set Vp0=0. 73 (f) Calculate the new sequence voltages of transformer secondary bus using eq. (3.8). (g) Apply phase shift Vs’=Vs’*ejπ/6 and calculate the phase voltages of transformer secondary bus Vs using eq. (3.2). (h) Continue the busses voltage calculation moving towards the far end using eq. (3.4). Step 8: Calculate voltage mismatches ∆V(k)=||V(k)|-|V(k-1)|| Step 9: Test for convergence, if no, go to step 3 Step 10: Compute branch losses, total losses, quantity of unbalance etc. Step 11: Stop. 3.4 Simulation Results and Analysis 3.4.1 Case Study 1: 2-bus URDS To verify the proposed approach for the transformer modeling, two transformer configurations were included in both the proposed threephase distribution system power flow program and the forward/backward substitution power flow method [28] and the results obtained were compared. A two-bus three-phase standard test system, given in fig. 3.1, is used, and for simplification, the transformer in the sample system is assumed to be at nominal rating, therefore, the taps on the primary and secondary sides are equal to 1.0. In addition, the voltage of the swing bus (bus p) is assumed to be 1.0 pu and load is balanced. The magnitudes and phase angles of bus‘s’ are given in Table 3.1 for 74 each iteration. Secondly the connection of transformer is changed to delta- grounded wye, and the load is unbalanced, 50% load on phase a, 30% load on phase b, and 20% load on phase c, the results are given in Table 3.2. It is observed that results obtained match very well with those listed in the study [28] and the proposed algorithm can reach the tolerance of 0.00001 at fourth iteration. On the other hand, in the results of the study [28], the voltages do not reach this tolerance value for these two connection types. p Source bus q Three-Phase transformer 13.8 kV – 208 V, 1000 kVA, Z = 6% Load 400+j300 kVA Fig. 3.1 Two Bus Sample System 75 Table 3.1 Voltage magnitudes and Phase angles for Grounded wye-delta of 2-Bus Sample System Three phase Power Flow Method proposed Phase a Phase b Phase c |Va| |Vb| |Vc| Va Vb Vc p.u. p.u. p.u. deg. deg. deg. 0 1.0000 0.00 1.0000 -120.00 1.0000 120.00 1 0.9778 -31.18 0.9778 -151.18 0.9778 88.82 2 0.9769 -31.18 0.9769 -151.18 0.9769 88.82 3 0.9768 -31.18 0.9768 -151.18 0.9768 88.82 4 0.9768 -31.18 0.9768 -151.18 0.9768 88.82 5 0.9768 -13.18 0.9768 -151.18 0.9768 88.82 Comments: 1. Iteration No. ‘0’ means initial guess Iter. No Forward/Backward Power Flow Phase a Phase b |Va| |Vb| Va Vb p.u. p.u. deg. deg. 1.0000 0.00 1.0000 -120.00 0.9967 -32.84 0.9967 -152.84 0.9759 -32.05 0.9759 -151.04 0.9769 -31.18 0.9768 -151.19 0.9769 -31.18 0.9769 -151.17 0.9768 -31.18 0.9768 -151.18 Method [28] Phase c |Vc| Vc p.u. deg. 1.0000 120.00 0.9967 87.16 0.9760 88.96 0.9769 88.82 0.9768 88.83 0.9768 88.82 Table 3.2 Voltage magnitudes and Phase angles for delta-Grounded wye of 2-Bus Sample System Three phase Power Flow Method proposed Phase a Phase b Phase c Iter. No |Va| |Vb| |Vc| Va Vb Vc p.u. p.u. p.u. deg. deg. deg. 0 1.0000 0.00 1.0000 -120.00 1.0000 120.00 1 0.9668 28.22 0.9800 -91.06 0.9866 146.30 2 0.9647 28.22 0.9792 -91.06 0.9863 146.30 3 0.9647 28.21 0.9792 -91.06 0.9863 146.30 4 0.9647 28.21 0.9792 -91.06 0.9863 146.30 5 0.9647 28.21 0.9792 -91.06 0.9863 146.30 Comments: 1. Iteration No. ‘0’ means initial guess Forward/Backward Power Flow Method [28] Phase a Phase b Phase c |Va| |Vb| |Vc| Va Vb Vc p.u. p.u. p.u. deg. deg. deg. 1.0000 0.00 1.0000 -120.00 1.0000 120.00 0.9595 30.60 0.9778 -89.19 0.9870 150.91 0.9661 28.03 0.9800 -91.17 0.9866 149.21 0.9646 28.24 0.9792 -91.05 0.9862 149.30 0.9648 28.21 0.9792 -91.06 0.9863 149.30 0.9648 28.21 0.9792 -91.06 0.9860 149.30 76 3.4.2 Case Study II: 37-bus IEEE URDS 799 724 722 707 712 701 742 713 704 720 705 702 714 706 729 744 727 703 718 725 728 730 732 708 709 731 736 733 710 775 734 740 735 737 738 711 741 Fig. 3.2 Single line diagram of 37-bus IEEE URDS [128] The proposed algorithm is tested on IEEE 37 node unbalanced radial distribution system [128] illustrated in Fig. 3.2. This feeder is an actual feeder located in California. The characteristics of the feeder are, three-wire delta operating at a nominal voltage of 4.8 kV, all line segments are underground, Substation voltage regulator consisting of two single phase units connected in open delta, all loads are “spot” loads and consist of constant PQ, constant current and constant impedance and the loading is very unbalanced. The line and load, impedance, shunt admittance; transformer and regulator data are given in [31] and also 77 given in Appendix B Tables B1, B2, B3, B4 and B5 respectively. For the load flow, base voltage and base MVA are chosen as 4.8 kV and 30 MVA respectively. Table 3.3 Voltage magnitudes and Phase angles for IEEE 37 bus URDS Node No. Phase a Phase b Phase c |Va| Va |Vb| Vb |Vc| Vc p.u. deg. p.u. deg. p.u. deg. 799 1.0000 0.00 1.0000 -120.00 1.0000 120.00 Reg 1.0435 0.00 1.0200 -120.00 1.0340 120.90 701 1.0308 -0.08 1.0141 -120.39 1.0180 120.61 702 1.0248 -0.14 1.0088 -120.58 1.0098 120.43 703 1.0176 -0.17 1.0049 -120.70 1.0034 120.20 730 1.0125 -0.12 1.0018 -120.73 0.9979 120.10 709 1.0111 -0.11 1.0012 -120.73 0.9967 120.07 708 1.0087 -0.08 1.0002 -120.73 0.9945 120.02 733 1.0063 -0.05 0.9993 -120.73 0.9925 119.96 734 1.0027 -0.01 0.9978 -120.74 0.9893 119.88 737 0.9996 0.02 0.9969 -120.71 0.9871 119.79 738 0.9985 0.04 0.9965 -120.71 0.9859 119.76 711 0.9982 0.06 0.9963 -120.74 0.9852 119.76 741 0.9979 0.07 0.9962 -120.75 0.9849 119.76 713 1.0234 -0.15 1.0070 -120.60 1.0083 120.44 704 1.0217 -0.17 1.0044 -120.61 1.0065 120.46 720 1.0205 -0.21 1.0008 -120.66 1.0041 120.53 706 1.0204 -0.22 1.0007 -120.66 1.0037 120.54 725 1.0202 -0.23 1.0003 -120.65 1.0037 120.55 705 1.0240 -0.13 1.0072 -120.59 1.0088 120.46 742 1.0236 -0.15 1.0064 -120.59 1.0086 120.48 727 1.0167 -0.16 1.0044 -120.69 1.0025 120.19 744 1.0157 -0.16 1.0038 -120.68 1.0019 120.17 729 1.0155 -0.15 1.0037 -120.67 1.0018 120.17 775 1.0111 -0.11 1.0012 -120.73 0.9967 120.07 731 1.0109 -0.13 1.0004 -120.74 0.9964 120.10 Contd . . . 78 732 1.0086 -0.07 1.0001 -120.74 0.9941 120.02 710 1.0024 0.01 0.9968 -120.77 0.9878 119.91 735 1.0023 0.03 0.9966 -120.78 0.9873 119.91 740 0.9981 0.07 0.9963 -120.75 0.9851 119.76 714 1.0214 -0.17 1.0043 -120.60 1.0064 120.46 718 1.0199 -0.16 1.0040 -120.57 1.0058 120.42 707 1.0185 -0.30 0.9959 -120.62 1.0025 120.67 722 1.0183 -0.30 0.9952 -120.62 1.0023 120.68 724 1.0184 -0.32 0.9950 -120.61 1.0023 120.69 728 1.0156 -0.15 1.0037 -120.68 1.0015 120.18 736 1.0019 -0.02 0.9949 -120.75 0.9872 119.95 712 1.0238 -0.11 1.0072 -120.61 1.0081 120.46 The obtained voltage profile of IEEE 37 bus URDS is given Table 3.3. From Table 3.3, it is observed that the minimum voltage in phases a, b, and c are 0.9979, 0.9962, and 0.9849 respectively. Voltage regulator tap positions for the convergence of the power flow in phases a, b and c are 8, 0 and 5. Table 3.4 shows the power flows for 37 bus URDS. The active power loss in phases a, b and c are 29.67 kW, 17.80 kW and 24.09 kW respectively and the total reactive power loss in phases a, b and c are 21.77 kVAr, 13.95 kVAr and 20.73 kVAr respectively. Table 3.4 Power flow for the IEEE 37 bus unbalanced radial distribution system Bus Bus From To 799 701 701 702 Phase a Phase b Phase c P Q P Q P Q (kW) (kVAr) (kW) (kVAr) (kW) (kVAr) 964.09 1129.30 1554.00 1130.80 1198.90 1552.50 702 791.90 645.61 1392.40 895.51 826.79 1216.80 703 521.25 410.87 690.46 531.81 471.17 581.96 Contd . . . 79 703 730 387.58 349.82 549.54 419.96 382.77 494.64 730 709 378.12 255.53 543.44 421.86 296.22 453.90 709 708 377.84 280.68 436.18 394.45 288.92 365.52 702 705 101.52 85.601 228.71 153.77 99.351 216.64 702 713 166.34 147.75 467.57 204.76 251.04 412.55 703 727 132.08 60.64 138.74 110.48 86.51 85.81 709 731 0 25.21 106.67 27.17 6.91 88.19 709 775 0 0 0 0 0 0 708 733 375.24 323.38 196.06 337.27 257.32 164.43 708 707 2.11 42.73 239.43 57.03 31.14 200.98 733 734 289.73 291.41 180.53 247.69 257.12 164.57 734 737 277.78 216.75 74.89 264.67 127.22 60.19 734 710 8.35 34.11 97.50 12.24 87.54 83.45 737 738 137.26 156.84 55.90 113.16 127.14 60.46 738 711 11.14 106.06 36.43 21.65 127.09 60.68 711 741 2.91 36.38 11.27 6.72 42.00 20.87 711 740 8.19 69.86 25.15 14.72 85.02 39.95 713 704 157.87 63.06 454.87 211.86 165.48 372.5 704 714 102.06 13.31 83.75 91.38 1.60 21.60 704 720 10.66 21.25 312.29 60.19 118.91 285.73 720 707 2.10 42.97 240.42 56.98 31.07 201.93 720 706 0 18.39 57.56 11.54 2.311 43.95 706 725 0 18.08 57.54 11.84 2.30 44.21 705 742 8.00 16.09 102.94 38.76 6.99 88.35 705 712 93.42 101.86 125.41 115.08 92.06 128.36 727 744 129.04 32.24 120.46 121.24 44.46 64.95 744 725 44.99 35.49 75.36 50.24 44.45 65.18 744 729 42.00 2.08 22.95 35.28 0 0.07 710 735 8.32 70.99 24.23 14.21 85.02 39.95 710 736 0.01 36.36 73.20 2.48 2.41 43.93 714 718 85.04 8.86 35.13 77.95 0 0.13 707 724 0.00 34.22 71.29 3.705 2.19 44.18 707 722 2.08 8.45 168.44 53.38 28.35 157.86 80 3.5 Conclusion The symmetrical components model of distribution transformers are incorporated into the three phase power flow algorithm. A simple and efficient method to include three-phase transformers into the three phase distribution load flow is presented. Grounded wye-delta and deltagrounded wye connections are modeled by using their sequencecomponents and adapted to three phase power flow algorithm. The proposed method is tested on the IEEE 37 bus unbalanced radial distribution system. The 2 bus sample system results are compared with that of other existing method and it is concluded that the proposed technique is valid, reliable and effective. Most importantly it is easy to implement.